| Alberta Electric System Operator | |
| System Co-ordination Plan | |
| 2026-01-08 to 2026-01-16 | |
| Approved Outages |
| Previous Version | |
| Download CSV |
| From | To | Owner | Type | Element | Scheduled Activity | Date/Time Comments | Interconnection |
|---|---|---|---|---|---|---|---|
| 26-Jul-24 10:00 | 31-Jul-26 16:00 | ATCO | Outage | 826s 504R (826s Marguerite Lake) | emergency removal to replace failed 502R @834S | 735.25 Days
Continuous |
|
| 23-Aug-24 13:45 | 30-Jun-26 14:29 | ALTALINK | Outage | 157s C1 (157s Lac La Biche) | forced outage | 676.03 Days
Continuous |
|
| 11-Mar-25 00:00 | 13-Jan-26 08:29 | ALTALINK | Outage | 377s 473C (377s AML Hardisty) | forced outage | 308.4 Days
Continuous |
|
| 18-Mar-25 14:00 | 17-Mar-26 17:30 | ALTALINK | Outage | 217s C1 (217s North Red Deer) | cap. bank unavailable and cannot be energized due to Koncar CTs being present | 364.15 Days
Daily |
|
| 20-Mar-25 08:00 | 20-Mar-26 17:00 | ALTALINK | Outage | 256s C1 (256s Harmattan) | forced outage | 365.38 Days
Continuous |
|
| 31-Mar-25 07:00 | 27-Feb-26 17:00 | EPCOR | TE | Protection & Control (Woodcroft) | Woodcroft: protection blocking for merging unit and protection upgrade. | 333.46 Days
Continuous |
|
| 14-May-25 08:00 | 10-Feb-26 16:00 | ENMAX | TE | Protection & Control (SS-32) | 32sub 138kV autoswitching protection outage | 272.38 Days
Continuous |
|
| 13-Jun-25 17:00 | 11-Feb-26 17:00 | EPCOR | Outage | T3 (Rossdale) | Rossdale - TX3 LCR | 243.04 Days
Continuous |
|
| 21-Jul-25 09:00 | 19-Jan-26 17:00 | ATCO | TE | 732s Protection & Control (732s Mitsue) | the breaker fail protection will be disabled during the project, as we migrate from the existing to the new protection | 182.38 Days
Continuous |
|
| 21-Jul-25 09:00 | 23-Jan-26 16:30 | ATCO | TE | 732s RTU/SCADA (732s Mitsue) | existing RTU system being replaced with new SMP system | 186.35 Days
Continuous |
|
| 22-Jul-25 08:30 | 31-Mar-26 16:30 | ALTALINK | Outage | 263s C1 (263s Strachan) | forced outage | 252.33 Days
Continuous |
|
| 25-Jul-25 17:01 | 17-Apr-26 17:00 | EPCOR | Outage | T2 (EP Riverview) | bushing test failure (found during OE110184) | 266 Days
Continuous |
|
| 25-Aug-25 08:00 | 03-Apr-26 16:00 | ENMAX | Outage | 32.1TR (SS-32) | slip over CT and new power cables installation and P&C works | 221.33 Days
Continuous |
|
| 02-Sep-25 08:00 | 14-Jan-26 16:00 | ENMAX | Outage | 38.1C (SS-38) | capacitor bank switcher replacement | 134.38 Days
Continuous |
|
| 12-Sep-25 08:00 | 06-Mar-26 16:00 | ENMAX | Outage | 33.1TR (SS-33) | tap changer refurbishments. soak test required | 175.38 Days
Continuous |
|
| 01-Nov-25 12:00 | 01-Feb-26 18:00 | ALTALINK | Outage | AML 511s ACF12 (AML 511s Crossings) | forced outage | 92.29 Days
Continuous |
|
| 21-Nov-25 08:00 | 16-Jan-26 16:00 | ENMAX | Outage | 38.3TR (SS-38) | 38.3TR secondary cable replacement | 56.33 Days
Continuous |
|
| 25-Nov-25 17:46 | 30-Jan-26 18:00 | ATCO | Outage | 876s 901T (876s Brintnell) | forced outage oil leaking | 66.01 Days
Continuous |
|
| 27-Nov-25 08:30 | 27-Nov-27 16:30 | ALTALINK | TE | 89s Protection & Control (89s Ellerslie) | DSP card replacements on1057L B87/L3 and B240B1 B87/240B1 | 730.33 Days
Daily |
|
| 09-Dec-25 17:00 | 02-Feb-26 11:00 | ALTALINK | IO | 714L (397s Benbow – 1117s South Kaybob), 397s 714 (397s Benbow) | complete work on breaker and energize 397s 714 | 54.75 Days
Continuous |
|
| 12-Dec-25 01:30 | 09-Jan-26 18:00 | ALTALINK | Outage | 310p T30 (310p Sundance) | forced outage | 28.69 Days
Continuous |
|
| 17-Dec-25 07:30 | 16-Jan-26 17:30 | ALTALINK | Outage | 58s C1 (58s Edson) | urgent repair – replace failed cap, remove reactors until new reactor beams area available to reinstall | 30.42 Days
Continuous |
|
| 04-Jan-26 08:00 | 31-Mar-26 16:00 | SUNCOR | Outage | 29EDD-34 260kV Bus 29PP-45 (29EDD-34), 29EDD-34 29-952-113 (29EDD-34) | urgent repairs on 29PT-224 at 29EDD34 on 29PP-45 bus | 86.29 Days
Continuous |
|
| 05-Jan-26 07:00 | 08-Jan-26 17:00 | ATCO | TE | 710s Protection & Control (710s Vermilion) | change and test relay settings | 3.42 Days
Continuous |
|
| 05-Jan-26 08:00 | 08-Mar-26 16:00 | ENMAX | Outage | 1.80L (SS-1 - SS-28) | 1 sub transmission line cut over | 62.29 Days
Continuous |
|
| 05-Jan-26 08:00 | 08-Mar-26 16:00 | ENMAX | Outage | 1.81L (SS-1 - SS-20) | 1 sub transmission line cut over | 62.29 Days
Continuous |
|
| 05-Jan-26 08:00 | 15-Jan-26 16:00 | ATCO | Outage | 7L48 (794s Valleyview - 7LA48 tap), 794s 703 (794s Valleyview) | pole and cross arm replacement from T&T | 10.33 Days
Continuous |
|
| 05-Jan-26 08:00 | 09-Jan-26 17:00 | ALTALINK | TE | 356s Protection & Control (356s Milo) | DLR project - protection outages required to make metering configuration changes | 4.38 Days
Daily |
|
| 05-Jan-26 08:00 | 09-Jan-26 17:00 | ALTALINK | TE | 356s RTU/SCADA (356s Milo) | DLR project - update RTU for RAS175 protection changes | 4.38 Days
Daily |
|
| 05-Jan-26 10:00 | 12-Jan-26 12:00 | ATCO | Outage | 9L40 (732s Mitsue - 809s Louise Creek) | replace 4 damaged poles | 7.08 Days
Continuous |
|
| 05-Jan-26 11:00 | 09-Jan-26 17:30 | ATCO | TE | 735s Protection & Control (735s Swan River) | relay testing on 50BF/601, 87TA/601T, 87B/600BS3, 21B/6L97, 21B/6L96, 50BF/602, 50BF/604, 50BF/603 | 4.27 Days
Continuous |
|
| 06-Jan-26 08:00 | 09-Jan-26 17:00 | ATCO | Outage | 732s 902T (732s Mitsue), 732s 503R (732s Mitsue) | protection upgrade | 3.38 Days
Continuous |
|
| 06-Jan-26 08:00 | 08-Jan-26 17:00 | ALTALINK | TE | 38s Protection & Control (38s East Edmonton) | standard relay maintenance | 2.38 Days
Daily |
|
| 06-Jan-26 08:00 | 08-Jan-26 17:00 | ALTALINK | TE | 89s Protection & Control (89s Ellerslie) | standard relay maintenance | 2.38 Days
Daily |
|
| 06-Jan-26 08:30 | 08-Jan-26 17:00 | ALTALINK | TE | 15s Protection & Control (15s Fort Macleod) | relay maintenance | 2.35 Days
Daily |
|
| 06-Jan-26 19:46 | 09-Jan-26 18:00 | ATCO | Outage | 840s McNeill Station | forced outage | 2.93 Days
Continuous |
AB-SK |
| 07-Jan-26 07:00 | 13-Jan-26 17:30 | ALTALINK | RB | 799L (235s Entwistle - 443s South Mayerthorpe), 799L (77s Sagitawah - 443s South Mayerthorpe) | proximity for 799L rebuild str 888A–909 (section D) | 6.44 Days
Daily |
|
| 07-Jan-26 08:00 | 20-Jan-26 18:00 | ALTALINK | Outage | 931L (28s West Brooks - 132s Ware Junction) | install steel self-supporting structure as part of the 1075L storm restoration | 13.42 Days
Continuous |
|
| 07-Jan-26 08:00 | 08-Jan-26 16:00 | ENMAX, ALTALINK | Outage | 35.81L (42s Sarcee - SS-35), 35B138-81 (SS-35), 42s 35 (42s Sarcee), 35MD138-81 (SS-35), 35MD138-83 (SS-35), 35MD138-35.81 (SS-35) | maintenance - 35MD138-35.81, 35MD138-83, 35MD138-81, SW81 | 1.33 Days
Continuous |
|
| 07-Jan-26 08:00 | 08-Jan-26 16:00 | ALTALINK | TE | 65s RTU/SCADA (65s High River) | split the existing SCADA VLAN from 1 to 1 and 2 | 1.33 Days
Daily |
|
| 07-Jan-26 08:00 | 08-Jan-26 16:00 | ALTALINK | IO | 42s 35 (42s Sarcee) | maintenance - 35MD138-35.81, 35MD138-83, 35MD138-81, SW81 | 1.33 Days
Daily |
|
| 07-Jan-26 08:00 | 10-Jan-26 16:00 | ATCO | RB | 7L45 (798s Bridge Creek - 845s Big Mountain), 7L45 (798s Bridge Creek - 813s Little Smoky) | high load move on7L45 str 158 | 3.33 Days
Continuous |
|
| 07-Jan-26 08:00 | 10-Jan-26 16:00 | ATCO | RB | 7L46 (813s Little Smoky - 845s Big Mountain) | high load move on7L46 str 158 | 3.33 Days
Continuous |
|
| 08-Jan-26 07:00 | 08-Jan-26 17:00 | ALTALINK | TE | 648s RTU/SCADA (648s Metiskow) | RTU alarming update | 10 Hours
Daily |
|
| 08-Jan-26 08:00 | 08-Jan-26 17:00 | ALTALINK | TE | 504s RTU/SCADA (504s Queenstown) | RTU outrage to replace Ronan annunciator | 9 Hours
Daily |
|
| 08-Jan-26 08:00 | 19-Jan-26 16:00 | Syncrude | Outage | 815 (Syncrude Mildred Lake), 816 (Syncrude Mildred Lake) | repair 72 kV pothead in plant 31 switchyard | 11.33 Days
Continuous |
|
| 08-Jan-26 08:00 | 08-Jan-26 17:00 | ALTALINK | TE | 42s Protection & Control (42s Sarcee) | PRC maintenance on T1 S59-T1/TERT, C3 B50/51N/27/59/60/60N/C3 , C2 B50/51N/27/59/60/60N/C2 | 9 Hours
Daily |
|
| 08-Jan-26 08:00 | 09-Jan-26 16:00 | ALTALINK | TE | 245s RTU/SCADA (245s Seebe) | split the existing SCADA VLAN from 1 to 1 and 2 | 1.33 Days
Daily |
|
| 08-Jan-26 08:00 | 08-Jan-26 16:00 | ENMAX | Outage | 5.1TR (SS-5) | relay protection test, lockouts, tap changer reversing switch check | 8 Hours
Continuous |
|
| 08-Jan-26 08:00 | 08-Jan-26 16:00 | ALTALINK | TE | 434s RTU/SCADA (434s Stony Plain) | split VLAN, replace firewall | 8 Hours
Daily |
|
| 08-Jan-26 08:00 | 08-Jan-26 17:00 | ALTALINK | TE | 504s Protection & Control (504s Queenstown) | urgent -prot outages required on 853L(s853E) URD60, 853L(s853E) SEL311C relays to complete alarm path verifications to Ronan annunciator after replacement | 9 Hours
Daily |
|
| 08-Jan-26 08:30 | 08-Jan-26 12:00 | ALTALINK | TE | 412s Protection & Control (412s Shell Eagle Creek) | remove under frequency relays for maintenance | 3.5 Hours
Daily |
|
| 08-Jan-26 09:00 | 08-Jan-26 11:00 | ATCO | TE | ATCO Telecom Equipment, 930s RTU/SCADA (930s Arcenciel) | upgrading SAR OS TO V21 | 2 Hours
Continuous |
|
| 08-Jan-26 09:00 | 09-Jan-26 17:00 | ATCO | TE | ATCO Telecom Equipment, 718s Protection & Control (718s Parsons Creek) | telecom upgrade | 1.33 Days
Continuous |
|
| 08-Jan-26 09:00 | 08-Jan-26 09:30 | ALTALINK | Outage | 719L (263s Strachan - 719AL tap), 719L (719AL tap - 719BL tap), 764L (304s Shell Limestone - 581s Amoco Ricinus), 719AL (581s Amoco Ricinus - 719L tap), 719BL (634s Shell Raven River - 719L tap), 304s T1 (304s Shell Limestone), 304s T2 (304s Shell Limestone), 581s T1 (581s Amoco Ricinus), 634s T1 (634s Shell Raven River), 378s 719N (378s Shell Caroline) | switching to open 719L259C | 30 Mins
Continuous |
|
| 08-Jan-26 09:00 | 08-Jan-26 11:00 | ATCO | Outage | 7L93 (828s Sulphur Point - 930s Arcenciel) | 7L93 needs to be open ended during telecom outage | 2 Hours
Continuous |
|
| 08-Jan-26 09:31 | 25-Jan-26 18:00 | ALTALINK | Outage | 719L (263s Strachan - 719AL tap), 263s 719 (263s Strachan) | component replacement/maintenance str 260-287 | 17.35 Days
Continuous |
|
| 08-Jan-26 10:00 | 08-Jan-26 15:00 | ATCO | Outage | 7L53 (700s Bonnyville - 7LA53 tap), 700s 702 (700s Bonnyville) | complete work on 7L53-620 | 5 Hours
Continuous |
|
| 08-Jan-26 12:30 | 08-Jan-26 17:00 | ALTALINK | TE | 531s Protection & Control (531s Shell Schrader Creek) | remove under frequency relays for maintenance | 4.5 Hours
Daily |
|
| 09-Jan-26 08:00 | 09-Jan-26 16:00 | ENMAX | Outage | 5.6TR (SS-5) | relay protection test lockouts, tap changer reversing switch check | 8 Hours
Continuous |
|
| 12-Jan-26 07:00 | 15-Jan-26 17:00 | ALTALINK | TE | 74s Protection & Control (74s Janet) | PRC relay maintenance | 3.42 Days
Daily |
|
| 12-Jan-26 07:00 | 18-Jan-26 18:00 | ATCO | RB | 7L16 (766s Nevis - 948s Heatburg) | stringing activities over 7L16 for CETO project | 6.46 Days
Continuous |
|
| 12-Jan-26 07:00 | 03-Apr-26 17:00 | EPCOR | TE | 330p Protection & Control (330p Genesee) | protect blocking, annual relay maintenance and password changes | 81.38 Days
Continuous |
|
| 12-Jan-26 07:00 | 03-Apr-26 17:00 | EPCOR | TE | Protection & Control (Rossdale) | protection blocking, relay maintenance | 81.38 Days
Continuous |
|
| 12-Jan-26 07:00 | 03-Apr-26 17:00 | EPCOR | TE | 987s Protection & Control (987s Clover Bar) | protection blocking, relay maintenance | 81.38 Days
Continuous |
|
| 12-Jan-26 07:00 | 14-Jan-26 17:00 | EPCOR | Outage | T1 (Namao), N721 (Namao), N722 (Namao) | wiring changes for panel removal | 2.42 Days
Continuous |
|
| 12-Jan-26 07:15 | 15-Jan-26 17:45 | ALTALINK | Outage | 314L (207s Pinedale - 228s T.M.P.L. Niton) | component replacement str 8–97 | 3.44 Days
Continuous |
|
| 12-Jan-26 07:30 | 16-Jan-26 17:30 | ALTALINK | RB | 443L (55s Olds - 214s Innisfail) | structure replacements from 443L63 – 443L137 | 4.42 Days
Daily |
|
| 12-Jan-26 08:00 | 30-Jan-26 16:00 | ENMAX | Outage | 32.3TR (SS-32) | panel cut-over | 18.33 Days
Continuous |
|
| 12-Jan-26 08:00 | 13-Jan-26 16:00 | ENMAX | Outage | 33.84L (SS-33 - SS-43), 43.2TR (SS-43), 33B138-33.84 (SS-33), 43B138-33.84 (SS-43), 43MD138-43.2TR (SS-43) | maintenance | 1.33 Days
Continuous |
|
| 12-Jan-26 08:00 | 13-Jan-26 17:00 | ALTALINK | TE | 106s RTU/SCADA (106s Paddle River) | supervisory outages required for emergency HMI upgrade | 1.38 Days
Daily |
|
| 12-Jan-26 08:00 | 16-Jan-26 17:00 | ALTALINK | TE | 267s RTU/SCADA (267s Killarney Lake) | RTU database updates | 4.38 Days
Daily |
|
| 12-Jan-26 08:00 | 15-Jan-26 17:00 | ALTALINK | TE | 251s Protection & Control (251s Whitla) | 264s352 CT replacement requires relay outages at 251s | 3.38 Days
Daily |
|
| 12-Jan-26 08:30 | 16-Jan-26 17:00 | ATCO | TE | 732s Protection & Control (732s Mitsue) | troubleshoot and modify settings for Digsi remote access | 4.35 Days
Continuous |
|
| 12-Jan-26 09:00 | 21-Jan-26 15:00 | ATCO | Outage | 9L57 (939s Livock - 960s Birchwood Creek) | 9L57 Line to Ground Clearance Mitigation | 9.25 Days
Continuous |
|
| 12-Jan-26 09:00 | 12-Jan-26 11:00 | ATCO | TE | 844s RTU/SCADA (844s AEC Mill), ATCO Telecom Equipment | upgrade AEC mill SAR OS to V21, then rebuild TPRCP114 and TPRCP115 | 2 Hours
Continuous |
|
| 12-Jan-26 10:00 | 15-Jan-26 17:00 | ALTALINK | TE | 198s Protection & Control (198s Blackfalds) | PRC maintenance | 3.29 Days
Daily |
|
| 12-Jan-26 10:00 | 14-Jan-26 17:00 | ALTALINK | TE | 159s Protection & Control (159s Colinton) | standard relay maintenance | 2.29 Days
Daily |
|
| 12-Jan-26 10:00 | 15-Jan-26 17:00 | ALTALINK | TE | 39s Protection & Control (39s Bickerdike) | standard relay maintenance | 3.29 Days
Daily |
|
| 12-Jan-26 10:00 | 14-Jan-26 17:00 | ALTALINK | TE | 61s Protection & Control (61s Lodgepole) | standard relay maintenance | 2.29 Days
Daily |
|
| 12-Jan-26 10:00 | 15-Jan-26 17:00 | ALTALINK | TE | 121s Protection & Control (121s Brooks) | outage on 138kv bus protection to remove/restore CT contribution | 3.29 Days
Daily |
|
| 12-Jan-26 10:00 | 16-Jan-26 16:00 | ATCO | TE | 925s Protection & Control (925s Green Stocking) | relay testing | 4.25 Days
Continuous |
|
| 12-Jan-26 10:00 | 15-Jan-26 15:00 | ALTALINK | TE | 264s Protection & Control (264s Elkwater) | 264s352 CT replacement | 3.21 Days
Daily |
|
| 12-Jan-26 13:00 | 12-Jan-26 17:00 | ALTALINK | TE | AltaLink Telecom Equipment | software update to correct issues with radio hop | 4 Hours
Daily |
|
| 12-Jan-26 13:00 | 15-Jan-26 17:00 | ALTALINK | Outage | 827L (28s West Brooks - 121s Brooks), 121s 827W (121s Brooks) | replace leaking CT | 3.17 Days
Continuous |
|
| 12-Jan-26 13:00 | 15-Jan-26 17:00 | ALTALINK | Outage | 264s 240kV Bus 2 (264s Elkwater), 264s 352 (264s Elkwater) | urgent CT replacement | 3.17 Days
Continuous |
|
| 13-Jan-26 07:00 | 13-Jan-26 17:00 | EPCOR | Outage | EP 511s V724 (EP 511s Victoria) | Victoria: V724 | 10 Hours
Continuous |
|
| 13-Jan-26 07:00 | 13-Jan-26 18:00 | ALTALINK | Outage | 799L (77s Sagitawah - 443s South Mayerthorpe) | Urgent repair of broken strands on the conductor at 681 and a split cross-arm on 663. | 11 Hours
Daily |
|
| 13-Jan-26 08:00 | 13-Jan-26 17:00 | ALTALINK | TE | AltaLink Telecom Equipment | 9393R repair radio facing 9037R | 9 Hours
Daily |
|
| 13-Jan-26 08:00 | 14-Jan-26 16:00 | ALTALINK | TE | AltaLink RTU/SCADA (AltaLink) | split the existing SCADA VLAN from 1 to 1 and 2 | 1.33 Days
Daily |
|
| 13-Jan-26 08:00 | 13-Jan-26 17:00 | ALTALINK | TE | AltaLink Telecom Equipment | software update to correct issues with radio hop | 9 Hours
Daily |
|
| 13-Jan-26 08:00 | 13-Jan-26 17:00 | ALTALINK | TE | 62s RTU/SCADA (62s Brazeau Plant) | split the existing SCADA VLAN from 1 to 1 and 2 | 9 Hours
Daily |
|
| 13-Jan-26 08:30 | 13-Jan-26 17:00 | ALTALINK | TE | 370s Protection & Control (370s North Lethbridge) | removing 370s207X & 370s1552 relays one at a time for maintenance and removing 940L RAS Relays from service one at a time | 8.5 Hours
Continuous |
|
| 13-Jan-26 08:30 | 14-Jan-26 17:00 | ALTALINK | Outage | 377s 473C (377s AML Hardisty) | investigate and return mobile cap bank to service at 377s as per AESO/analyst request |
1.35 Days
Continuous |
|
| 13-Jan-26 09:00 | 13-Jan-26 11:00 | ATCO | TE | ATCO Telecom Equipment, 2015s RTU/SCADA (2015s Yeo), 960s RTU/SCADA (960s Birchwood Creek) | NET 1 and NET 11 SAR OS upgrade |
2 Hours
Continuous |
|
| 13-Jan-26 09:00 | 13-Jan-26 17:00 | ATCO | TE | ATCO Telecom Equipment, 898s Heart Lake RTU/SCADA | Heart Lake_S-Telecom- Med BES firewall install | 8 Hours
Continuous |
|
| 13-Jan-26 09:00 | 13-Jan-26 17:00 | ALTALINK | TE | AltaLink Telecom Equipment | NOC provision server issue with radio, resolve with access to the radio on site | 8 Hours
Daily |
|
| 13-Jan-26 09:00 | 14-Jan-26 17:30 | ATCO | TE | 7LA128 (572s Highland - 7L128 tap) | 21B/7LA128 protection settings updating for time sync issues | 1.35 Days
Continuous |
|
| 13-Jan-26 10:00 | 13-Jan-26 12:00 | ENMAX | Outage | 38.1TR (SS-38) | capacitor bank switcher replacement, commissioning and wiring changes | 2 Hours
Continuous |
|
| 13-Jan-26 12:30 | 13-Jan-26 14:30 | ENMAX | Outage | 38.2TR (SS-38) | capacitor bank switcher replacement, commissioning and wiring changes | 2 Hours
Continuous |
|
| 14-Jan-26 07:00 | 14-Jan-26 17:00 | EPCOR | Outage | EP 511s V722 (EP 511s Victoria) | victoria v722, switching school recertification | 10 Hours
Continuous |
|
| 14-Jan-26 07:00 | 31-Jan-26 18:00 | ALTALINK | Outage | 799L (235s Entwistle - 443s South Mayerthorpe), 235s 799N (235s Entwistle) | 799L rebuild between str 888A-909 (section d) | 17.46 Days
Continuous |
|
| 14-Jan-26 08:00 | 15-Jan-26 16:00 | ALTALINK | TE | 321s RTU/SCADA (321s Al Rothbauer) | split the existing SCADA VLAN from 1 to 1 and 2 | 1.33 Days
Daily |
|
| 14-Jan-26 08:00 | 14-Jan-26 17:00 | ALTALINK | TE | AltaLink Telecom Equipment, 431s RTU/SCADA (431s Hussar) | communication alarm | 9 Hours
Daily |
|
| 14-Jan-26 08:00 | 14-Jan-26 12:00 | ATCO | TE | 970s Protection & Control (970s Bourque) | adjust 7L574 line protection zone 2 delay to 0.15s for the duration of the telecom outages (1-00507478). | 4 Hours
Continuous |
|
| 14-Jan-26 08:00 | 15-Jan-26 16:00 | ENMAX | Outage | 9.83L (SS-9 - SS-43), 43.1TR (SS-43) | HV SW Maintenance 43SW81, 43SW82, 43SW83, MD-43.1TR. Tap Changer Reversing Switch Check - 43.1-X-TC, 43.1-Y-TC | 1.33 Days
Continuous |
|
| 14-Jan-26 08:00 | 15-Jan-26 16:00 | ATCO | RB | 7L45 (798s Bridge Creek - 845s Big Mountain), 7L45 (798s Bridge Creek - 813s Little Smoky) | high load move on7L45 str 158 | 1.33 Days
Continuous |
|
| 14-Jan-26 08:00 | 15-Jan-26 16:00 | ATCO | RB | 7L46 (813s Little Smoky - 845s Big Mountain) | high load move on7L46 str 158 | 1.33 Days
Continuous |
|
| 14-Jan-26 08:00 | 14-Jan-26 17:00 | ATCO | TE | 2075s Protection & Control (2075s Newell) | replace failed SEL-487B relay | 9 Hours
Continuous |
|
| 14-Jan-26 08:00 | 14-Jan-26 10:00 | ENMAX | Outage | 37.81L (SS-37 - SS-38), 38.2TR (SS-38), 38.3TR (SS-38), 38B138-37.81 (SS-38), 38.1C (SS-38), SW83 (SS-38) | capacitor bank switcher replacement sub 38, bus outage required for 38B138-38.1cap bank initial energization | 2 Hours
Continuous |
|
| 14-Jan-26 08:00 | 15-Jan-26 17:00 | ALTALINK | TE | 267s Protection & Control (267s Killarney Lake) | trip testing on 25kV breakers | 1.38 Days
Daily |
|
| 14-Jan-26 09:00 | 14-Jan-26 11:00 | ATCO | TE | 970s RTU/SCADA (970s Bourque), ATCO Telecom Equipment | impact to the following traffic for up to 1 hr: 970s SUB LOW BES SCADA 7L146 A&B - BOURQUE / BONNYVILLE 7L574, 7L35 A&B - BOURQUE / PRIMROSE 7L574. 7L35 B - BOURQUE / WOLF LAKE 7L574 A - BOURQUE / WOLF LAKE SPS1161 - LEMING LAKE / ETHEL LAKE 7L91 A&B - LEMING LAKE / MARGUERITE LAKE |
2 Hours
Continuous |
|
| 14-Jan-26 10:00 | 14-Jan-26 12:00 | ALTALINK, TRANSALTA | TE | 528s RTU/SCADA (528s Blue Trail Wind Farm), AltaLink Telecom Equipment | resolve with access to the radio on site | 2 Hours
Continuous |
|
| 14-Jan-26 10:00 | 15-Jan-26 17:30 | ATCO | TE | 959s Protection & Control (959s Lanfine), 959s RTU/SCADA (959s Lanfine) | 87BA-B 700BS2 SIEMENS 7UT635 | 31.5 Hours
Continuous |
|
| 14-Jan-26 23:00 | 15-Jan-26 03:00 | ALTALINK | Outage | 62s T1 (62s Brazeau Plant) | maintenance | 4 Hours
Continuous |
|
| 15-Jan-26 03:00 | 15-Jan-26 07:00 | ALTALINK | Outage | 62s T2 (62s Brazeau Plant) | maintenance | 4 Hours
Daily |
|
| 15-Jan-26 07:00 | 15-Jan-26 17:00 | EPCOR | Outage | EP 511s V723 (EP 511s Victoria) | V723 switching school recertification | 10 Hours
Continuous |
|
| 15-Jan-26 08:00 | 16-Jan-26 16:00 | ALTALINK | TE | 895s RTU/SCADA (895s Suffield) | split the existing SCADA VLAN from 1 to 1 and 2 | 1.33 Days
Daily |
|
| 15-Jan-26 08:00 | 15-Jan-26 15:00 | ALTALINK | TE | AltaLink Telecom Equipment | NCC card failure, replace card and upgrade software version to resolve errors | 7 Hours
Daily |
|
| 15-Jan-26 08:00 | 15-Jan-26 17:00 | ALTALINK | TE | 294s RTU/SCADA (294s Brazeau Outletworks) | replace firewall, split VLAN | 9 Hours
Daily |
|
| 15-Jan-26 08:30 | 15-Jan-26 17:00 | ALTALINK | TE | 409s RTU/SCADA (409s Shell Scotford) | update config for deficiency cleanup | 8.5 Hours
Daily |
|
| 15-Jan-26 12:00 | 15-Jan-26 15:00 | ALTALINK | Outage | 267s T1 (267s Killarney Lake) | replace line side risers on 267s2054X and energize new 267s2054X breaker from 267s3 | 3 Hours
Daily |
|
| 16-Jan-26 07:00 | 17-Jan-26 17:00 | EPCOR | Outage | 72VN21 (EP 511s Victoria - Namao), N725 (Namao) | wiring changes for mimic panel removal | 1.42 Days
Continuous |
|
| 16-Jan-26 08:00 | 16-Jan-26 16:00 | ALTALINK | TE | 454s RTU/SCADA (454s Buck Lake) | split VLAN, replace firewall | 8 Hours
Daily |
|
| 16-Jan-26 08:00 | 16-Jan-26 16:00 | ENMAX | Outage | 13.2TR (SS-13) | oil leaks, gas alarm - check/seal water leaks | 8 Hours
Continuous |
|
| 16-Jan-26 08:00 | 16-Jan-26 16:00 | ENMAX | Outage | 5.5TR (SS-5) | relay protection test, tap changer reversing switch check | 8 Hours
Continuous |
|
| 16-Jan-26 09:00 | 16-Jan-26 15:00 | ATCO | TE | 800s RTU/SCADA (800s Friedenstal), 800s Protection & Control (800s Friedenstal) | remove broken CT wire alarm and logic from the 21B/6L37 and station controller at 800S Friedenstal | 6 Hours
Continuous |
| This document and the information contained herein are based upon information and data which by their nature contain a degree of uncertainty and are subject to change. In addition, this document may contain information and data from public sources and/or third parties, which have been assumed to be accurate and complete and have not been verified. Accordingly, the Independent System Operator, operating as the Alberta Electric System Operator (the "AESO") makes no warranty, representation or guarantee, express or implied, with respect to this document or the information contained herein, including, but not limited to, any warranty, representation or guarantee of accuracy, completeness, timeliness, reliability, availability, absence of computer virus, non- infringement, merchantability or suitability for any purpose. Under no circumstances will the AESO, its members, officers, employees, contractors or agents, or any of their respective affiliates, be liable for any errors or omissions in, or any losses, damages or claims whatsoever, whether in contract, tort or otherwise, arising from use of or reliance upon, this document or any information contained herein. © 2009 Alberta Electric System Operator. All rights reserved |