| Alberta Electric System Operator | |
| System Co-ordination Plan | |
| 2026-05-07 to 2026-05-15 | |
| Approved Outages |
| Previous Version | |
| Download CSV |
| From | To | Owner | Type | Element | Scheduled Activity | Date/Time Comments | Interconnection |
|---|---|---|---|---|---|---|---|
| 26-Jul-24 10:00 | 31-Jul-26 16:00 | ATCO | Outage | 826s 504R (826s Marguerite Lake) | emergency removal to replace failed 502R @834S | 735.25 Days
Continuous |
|
| 23-Aug-24 13:45 | 21-May-26 14:29 | ALTALINK | Outage | 157s C1 (157s Lac La Biche) | forced outage | 636.03 Days
Continuous |
|
| 20-Mar-25 08:00 | 29-May-26 17:00 | ALTALINK | Outage | 256s C1 (256s Harmattan) | forced outage | 435.38 Days
Continuous |
|
| 12-Sep-25 08:00 | 19-Jun-26 16:00 | ENMAX | Outage | 33.1TR (SS-33) | tap changer refurbishments. soak test required | 280.33 Days
Continuous |
|
| 25-Nov-25 17:46 | 18-Sep-26 18:00 | ATCO | Outage | 876s 901T (876s Brintnell) | forced outage oil leaking | 296.97 Days
Continuous |
|
| 27-Nov-25 08:30 | 27-Nov-27 16:30 | ALTALINK | TE | 89s Protection & Control (89s Ellerslie) | DSP card replacements on1057L B87/L3 and B240B1 B87/240B1 | 730.33 Days
Daily |
|
| 04-Jan-26 08:00 | 02-Sep-26 16:00 | SUNCOR | Outage | 29EDD-34 260kV Bus 29PP-45 (29EDD-34), 29EDD-34 29-952-113 (29EDD-34), 29EDD-34 29PS-216 (29EDD-34) | urgent repairs on 29PT-224 at 29EDD34 on 29PP-45 bus | 241.29 Days
Continuous |
|
| 12-Jan-26 07:00 | 03-Jul-26 17:00 | EPCOR | TE | 330p Protection & Control (330p Genesee) | protect blocking, annual relay maintenance and password changes | 172.38 Days
Continuous |
|
| 21-Jan-26 08:00 | 30-Oct-26 16:00 | ENMAX | Outage | 5.7TR (SS-5) | 25kV switchgear replacement | 282.29 Days
Continuous |
|
| 03-Feb-26 09:00 | 30-Jun-26 17:00 | ATCO | TE | 972s RTU/SCADA (972s Tinchebray) | config changes needed throughout the CETO project | 147.29 Days
Continuous |
|
| 09-Feb-26 09:00 | 26-Jun-26 17:00 | ATCO | TE | 972s Protection & Control (972s Tinchebray) | block all 50BF protection until cutovers and associated commissioning are complete | 137.29 Days
Continuous |
|
| 06-Mar-26 17:00 | 13-Nov-26 17:00 | EPCOR | Outage | T1 (Woodcroft) | woodcroft: TX1 LCR civil | 252 Days
Continuous |
|
| 10-Mar-26 10:00 | 30-Nov-26 17:00 | ATCO | TE | 743s RTU/SCADA (743s Sarah Lake) | throughout the course of the project, different apparatus are being replaced, RTU will be blocked prior to download | 265.33 Days
Continuous |
|
| 11-Mar-26 13:45 | 15-May-26 16:00 | ALTALINK | Outage | 535s C1 (535s Joffre) | breaker maintenance | 65.09 Days
Continuous |
|
| 22-Mar-26 13:00 | 30-Jun-26 17:00 | BHE Canada | Outage | 120s C1 (120s Picture Butte), 120s C2 (120s Picture Butte) | forced outage | 100.17 Days
Continuous |
|
| 28-Mar-26 12:00 | 14-May-26 17:00 | ATCO | TE | 833s RTU/SCADA (833s Mariana) | updating RTU/station controller configuration during SCADA upgrade project | 47.21 Days
Continuous |
|
| 06-Apr-26 08:00 | 19-Jun-26 16:00 | ALTALINK | TE | 37s RTU/SCADA (37s North Calder) | RTU database updates | 74.33 Days
Continuous |
|
| 08-Apr-26 07:00 | 10-May-26 17:00 | ALTALINK, ALPAC | IO | 796L (282s Grassland - 796AL tap) | note for area assessments | 32.42 Days
Continuous |
|
| 09-Apr-26 17:01 | 15-May-26 17:00 | EPCOR | Outage | 72RW3 (Rossdale - Woodcroft), RW727 (Rossdale) | termination rebuild at the Woodcroft end | 36 Days
Continuous |
|
| 13-Apr-26 07:00 | 29-May-26 17:00 | EPCOR | Outage | 805s T4 (805s Jasper) | bushing replacement and fan repair | 46.42 Days
Continuous |
|
| 13-Apr-26 09:00 | 21-May-26 10:00 | ALTALINK | Outage | 157s C1 (157s Lac La Biche) | replace breaker and disconnect switch | 38.04 Days
Continuous |
|
| 14-Apr-26 07:00 | 07-May-26 17:00 | EPCOR | Outage | 330p 500kV Bus 2 (330p Genesee), 330p 12TC2 (330p Genesee), 330p 1209 (330p Genesee), 330p 1206 (330p Genesee), 330p 1203 (330p Genesee), 330p 1211 (330p Genesee), 330p 1215 (330p Genesee), 330p 12TC2D (330p Genesee), 330p 809 (330p Genesee) | Genesee 500 kV bus 2, POW project installation | 23.42 Days
Continuous |
|
| 20-Apr-26 07:00 | 08-May-26 17:00 | EPCOR | TE | Protection & Control (Kennedale) | protection blocking - relay maintenance | 18.42 Days
Continuous |
|
| 20-Apr-26 07:00 | 08-May-26 17:00 | EPCOR | TE | 72CN10 (987s Clover Bar - Namao) | protection blocking - MPLS upgrade | 18.42 Days
Continuous |
|
| 20-Apr-26 07:00 | 08-May-26 17:00 | EPCOR | TE | 72CH11 (987s Clover Bar - EP Hardisty) | protection blocking - MPLS upgrade | 18.42 Days
Continuous |
|
| 20-Apr-26 07:00 | 08-May-26 17:00 | EPCOR | TE | 72CH9 (987s Clover Bar - EP Hardisty) | protection blocking - MPLS upgrade | 18.42 Days
Continuous |
|
| 20-Apr-26 07:00 | 08-May-26 17:00 | EPCOR | TE | 72KN23 (Kennedale - Namao) | protection blocking - MPLS upgrade | 18.42 Days
Continuous |
|
| 21-Apr-26 09:00 | 08-May-26 17:00 | ALTALINK | Outage | 394s T3 (394s Empress), 394s 36 (394s Empress) | 394sT3 CT7 replacement, cable repair | 17.33 Days
Continuous |
|
| 21-Apr-26 15:00 | 08-May-26 09:00 | ALTALINK | Outage | 1182s 138kV Bus 1 (1182s Berland River), 620L (1182s Berland River - 328s Pine Creek), 1182s T1 (1182s Berland River), 1182s C1 (1182s Berland River), 1182s C2 (1182s Berland River), 328s 620 (328s Pine Creek), 1182s 152 (1182s Berland River) | complete 620L and energize new 1182s, close 620L ope point 'A', 1182s cap bank testing, soak 1182s T1 for 24 hours, load pickup | 16.75 Days
Continuous |
|
| 22-Apr-26 08:00 | 08-May-26 16:00 | ALTALINK | TE | 328s RTU/SCADA (328s Pine Creek) | RTU updates for changes involving 620L P&C equipment | 16.33 Days
Continuous |
|
| 22-Apr-26 08:00 | 08-May-26 16:00 | ALTALINK | TE | 328s Protection & Control (328s Pine Creek) | circuit modification and testing involving 620L P&C equipment | 16.33 Days
Continuous |
|
| 24-Apr-26 08:00 | 11-May-26 16:00 | Syncrude | Outage | C1 (Aurora), 31 (Aurora), 32 (Aurora), 33 (Aurora), 31B (Aurora), 32A (Aurora), 32B (Aurora) | zone 12 6 year maintenance | 17.33 Days
Continuous |
|
| 25-Apr-26 08:00 | 27-Jun-26 16:00 | ENMAX | Outage | 1.82L (SS-1 - SS-5), 5B138-1.82 (SS-5) | 1 sub Transmission line cut over | 63.33 Days
Continuous |
|
| 25-Apr-26 08:00 | 27-Jun-26 16:00 | ENMAX | Outage | 1.84L (SS-1 - SS-5), 5B138-1.84 (SS-5) | 1 sub Transmission line cut over | 63.33 Days
Continuous |
|
| 27-Apr-26 08:00 | 11-May-26 18:00 | ALTALINK, ATCO | Outage | 87s 240kV East Bus (87s Gaetz), 87s T2 (87s Gaetz), 962L (87s Gaetz - 972s Tinchebray), 986L (87s Gaetz - 972s Tinchebray), 87s 1552 (87s Gaetz), 87s 1652 (87s Gaetz), 87s 1952 (87s Gaetz), 87s 1252 (87s Gaetz) | commissioning 87s962 & 87s986 MODs | 14.42 Days
Continuous |
|
| 27-Apr-26 08:00 | 08-May-26 16:00 | CMH | TE | MHS-7 Protection & Control (MHS-7 Brier Park) | perform preventative maintenance on BPR-138-B | 11.33 Days
Continuous |
|
| 27-Apr-26 08:00 | 15-May-26 16:00 | ALTALINK | TE | 37s Protection & Control (37s North Calder) | P&C upgrades (37s4, 37s82, 37s88, 37s81) | 18.33 Days
Continuous |
|
| 27-Apr-26 08:00 | 28-May-26 08:00 | Saskpower | Outage | Sask Power CC904T | maintenance | 31 Days
Continuous |
AB-SK |
| 27-Apr-26 11:00 | 07-May-26 16:00 | ALTALINK, EPCOR | RB | 930L (37s North Calder - Poundmaker) | reclose block for Altalink working on 37s North Calder | 10.21 Days
Continuous |
|
| 28-Apr-26 08:00 | 22-May-26 16:00 | ENMAX | TE | Protection & Control (SS-32) | 32 sub 138 kV autoswitching protection outage - HV switch replacement. MD-32.2TR, 32SW84, 32SW85, 32SW86, 32SW87, 32SW88 | 24.33 Days
Daily |
|
| 28-Apr-26 08:30 | 22-May-26 14:00 | ENMAX | Outage | 32.83L (SS-32 - SS-40), 26.81L (SS-26 - SS-32), 32.2TR (SS-32), 32.1TR (SS-32), 32B138-32BT5 (SS-32), 32B138-32.83 (SS-32), 32B138-26.81 (SS-32), 40B138-32.83 (SS-40), 26B138-26.81 (SS-26), 32MD138-32.1TR (SS-32), 32MD138-32.2TR (SS-32) | HV SW replacement. MD-32.2TR, 32SW84, 32SW85, 32SW86, 32SW87, 32SW88 | 24.23 Days
Continuous |
|
| 29-Apr-26 07:00 | 07-May-26 17:00 | ALTALINK | TE | 275s RTU/SCADA (275s Jenner) | 275s Jenner RTU update for switch replacement | 8.42 Days
Continuous |
|
| 29-Apr-26 08:00 | 07-May-26 18:00 | ALTALINK | Outage | 275s T1 (275s Jenner), 275s 38 (275s Jenner), 275s 39 (275s Jenner), 275s 2152 (275s Jenner), 275s 81 (275s Jenner), 275s 2269 (275s Jenner), 275s 2036N (275s Jenner) | 275sT1 oil reclaim, maintenance, plugged radiator, replace switch 275s37 and 275s39. replace 25kV post insulators.275s2269, 275s2036N, & 275s81 | 8.42 Days
Continuous |
|
| 29-Apr-26 17:00 | 19-May-26 07:00 | ALTALINK | Outage | 320p 2089 (320p Keephills) | urgent customer work | 19.58 Days
Continuous |
|
| 01-May-26 14:00 | 07-May-26 16:00 | ALTALINK, EPCOR | RB | 920L (37s North Calder - 557s Castle Downs) | reclose block for Altalink working on 37s North Calder | 6.08 Days
Continuous |
|
| 01-May-26 14:01 | 07-May-26 13:29 | ALTALINK | Outage | 37s T6 (37s North Calder), 37s 4 (37s North Calder), 37s 88 (37s North Calder), 37s 81 (37s North Calder), 37s 90 (37s North Calder) | P&C upgrades (37s4, 37s88, 37s81, T6, PT20) | 5.98 Days
Continuous |
|
| 01-May-26 17:00 | 25-Nov-26 17:00 | EPCOR | Outage | T1 (Meadowlark) | T1 LCR civil work | 208.04 Days
Continuous |
|
| 01-May-26 17:01 | 15-May-26 17:00 | ATCO | Outage | 951s 920C (951s Thickwood) | 920C cap at 951s Thickwood unavailable, forced outage | 14 Days
Continuous |
|
| 03-May-26 10:00 | 15-May-26 17:00 | ATCO, ALTALINK | Outage | 9L960 (13s Deerland - 825s Whitefish Lake), 9L961 (13s Deerland - 825s Whitefish Lake) | forced outage due to damaged structure |
12.29 Days
Continuous |
|
| 04-May-26 07:00 | 10-May-26 17:00 | EPCOR | Outage | 814s T1 (814s Bellamy), BR721 (Rossdale), 814s B2401 (814s Bellamy), 814s B2407 (814s Bellamy), 814s BAB1 (814s Bellamy) | Bellamy: TX1, breaker and disconnect switch maintenance | 6.42 Days
Continuous |
|
| 04-May-26 07:00 | 08-May-26 17:00 | EPCOR | Outage | 805s T4 (805s Jasper), EP 805s J2406 (EP 805s Jasper), EP 805s J2405 (EP 805s Jasper), EP 805s JAB4 (EP 805s Jasper) | Jasper: TX4 relay maintenance | 4.42 Days
Continuous |
|
| 04-May-26 07:00 | 08-May-26 15:00 | CMH | Outage | MHS-5 MH69-510 (MHS-5 NE Crescent Heights) | breaker maintenance and inspection | 4.33 Days
Continuous |
|
| 04-May-26 07:00 | 07-May-26 17:00 | ALTALINK | TE | 256s Protection & Control (256s Harmattan) | techs to isolate cap bank protection to assist with subs capacitor bank outage | 3.42 Days
Continuous |
|
| 04-May-26 08:00 | 15-May-26 17:00 | BCH, BPA | Outage | 2L112 (BPA Boundary - BCH Nelway) | emergency replacement of a boundary PCB, BC maintenance does not affect the Alberta ATC | 11.38 Days
Continuous |
AB-BC |
| 04-May-26 08:00 | 07-May-26 16:00 | ALTALINK | TE | AltaLink Telecom Equipment, 321s RTU/SCADA (321s Al Rothbauer) | firewall replacement, LAN switch replacement, firmware 7705A upgrade, raw socket conversion | 3.33 Days
Continuous |
|
| 04-May-26 08:00 | 07-May-26 16:00 | ENMAX | Outage | 11.1TR (SS-11) | transformer power factor test, secondary cable test, transformer maintenance, relay fault pressure test, reversing switch check and oil sampling | 3.33 Days
Continuous |
|
| 04-May-26 08:00 | 22-May-26 16:00 | ENMAX | TE | Protection & Control (SS-5) | 5PT138-Z31 secondary voltage outage, SS-1 transmission line cut over | 18.33 Days
Daily |
|
| 04-May-26 08:00 | 22-May-26 16:00 | ENMAX | TE | Protection & Control (SS-5) | 1 sub transmission line cut over | 18.33 Days
Daily |
|
| 04-May-26 09:00 | 18-May-26 17:30 | ATCO | Outage | 13L50 (2029s Heathfield - 2075s Newell) | annual EATL outage at 2075s and 2029s | 14.35 Days
Continuous |
|
| 04-May-26 09:00 | 18-May-26 17:30 | ATCO | Outage | 2029s T11 (2029s Heathfield), 2029s 1205 (2029s Heathfield), 2029s 1206 (2029s Heathfield) | annual EATL outage | 14.35 Days
Continuous |
|
| 04-May-26 09:00 | 18-May-26 17:30 | ATCO | Outage | 2075s T11 (2075s Newell), 2075s 916 (2075s Newell), 2075s 917 (2075s Newell) | annual EATL outage | 14.35 Days
Continuous |
|
| 04-May-26 09:00 | 08-May-26 17:00 | BCH | Outage | 5L98 (BCH Nicola - BCH Vaseux Lake) | replace spacer damper and insulator, BC maintenance does not affect the Alberta ATC | 4.33 Days
Continuous |
AB-BC |
| 04-May-26 09:30 | 07-May-26 17:30 | ATCO | Outage | 722s 702T (722s Crystal Lake) | repair damaged secondary cables on 702T |
3.33 Days
Continuous |
|
| 04-May-26 09:30 | 07-May-26 17:30 | ATCO | TE | 722s RTU/SCADA (722s Crystal Lake) | rewire breaker 510 status, RTXP test switch mitigation and replacement | 3.33 Days
Continuous |
|
| 04-May-26 10:00 | 08-May-26 16:00 | ATCO, CNRL | TE | 838s RTU/SCADA (838s Horizon Mining), 842s RTU/SCADA (842s Horizon Upgrading) | SCADA Outages while RTU updates are completed | 4.25 Days
Continuous |
|
| 04-May-26 10:00 | 25-May-26 16:00 | ATCO | TE | 825s Whitefish Lake RTU/SCADA | isolations and modifications to alarm/ SCADA points, wiring, and configurations, may require shot duration | 21.25 Days
Continuous |
|
| 04-May-26 12:00 | 07-May-26 18:00 | ALTALINK | Outage | 256s C1 (256s Harmattan) | 256sC1 replace capacitors, testing and trouble shooting | 3.25 Days
Continuous |
|
| 05-May-26 08:00 | 07-May-26 16:00 | ALTALINK | TE | 370s Protection & Control (370s North Lethbridge) | move relay to new City of Lethbridge communication system | 2.33 Days
Continuous |
|
| 05-May-26 08:00 | 07-May-26 17:00 | Lethbridge | TE | 241s Protection & Control (241s Uplands) | transfer TPR (Teleprotection) circuit from existing JMUX to new SEL ICON | 2.38 Days
Continuous |
|
| 05-May-26 08:00 | 07-May-26 16:00 | ALTALINK | TE | 177s RTU/SCADA (177s West Cascade) | testing analogs on 105L to clean up SCADA deficiencies, 177s 15min loss of visibility while RTU is updated | 2.33 Days
Continuous |
|
| 05-May-26 08:00 | 18-May-26 17:30 | ATCO | TE | 2029s Protection & Control (2029s Heathfield) | fire suppression inspection and recertification, install blocking switches, requires protection to be blocked, could case alarms to AML, valve cooling system maintenance and repairs. | 13.4 Days
Continuous |
|
| 05-May-26 08:00 | 18-May-26 17:30 | ATCO | TE | 2075s Protection & Control (2075s Newell) | fire suppression inspection and recertification, install blocking switches, requires protection to be blocked, could case alarms to AML, valve cooling system maintenance and repairs. | 13.4 Days
Continuous |
|
| 05-May-26 08:00 | 07-May-26 17:00 | ALTALINK | Outage | 33s 2 (33s Spray) | maintenance | 2.38 Days
Continuous |
|
| 05-May-26 08:00 | 08-May-26 16:00 | CMH | Outage | MHS-5 MH69-509 (MHS-5 NE Crescent Heights) | repair of damaged disconnect Switch MH69-509 that requires immediate attention | 3.33 Days
Continuous |
|
| 05-May-26 09:00 | 07-May-26 16:00 | ALTALINK | TE | 29s Protection & Control (29s Cascade) | cutover of 54L prot alarms | 2.29 Days
Continuous |
|
| 05-May-26 09:00 | 07-May-26 17:00 | ATCO | Outage | 972s 901 (972s Tinchebray) | connect 900BS1 to new 907B Cutover 900SST1 non elec trips to new 900BS1 protection cutover 901CT and 901 trips to new 900BS1 protection |
2.33 Days
Continuous |
|
| 05-May-26 09:00 | 07-May-26 17:00 | ALTALINK | Outage | 33s 1 (33s Spray) | maintenance | 2.33 Days
Continuous |
|
| 05-May-26 12:00 | 08-May-26 12:00 | ATCO | Outage | 786s 703T (786s High Level), 786s 703 (786s High Level), 786s SVC (786s High Level) | svc air cooled maintenance at 786s | 3 Days
Continuous |
|
| 06-May-26 07:00 | 07-May-26 18:00 | ALTALINK | Outage | 887s 520 (887s Carson Creek), 520L (887s Carson Creek - 526L tap) | component replacement on 520L (STR 5-6) | 1.46 Days
Continuous |
|
| 06-May-26 07:00 | 08-May-26 17:30 | ALTALINK | Outage | 268s 797 (268s Whitecourt), 364s 797 (364s Whitecourt Industrial), 797L (268s Whitecourt - 364s Whitecourt industrial) | transmission line maintenance | 2.44 Days
Continuous |
|
| 06-May-26 07:15 | 07-May-26 17:45 | ATCO | RB | 9L27 (755s Cordel - 863s Paintearth) | work on 9L948 | 1.44 Days
Continuous |
|
| 06-May-26 08:00 | 07-May-26 16:00 | ENMAX | Outage | 12B138-832L (SS-12), 832L (SS-10 - SS-12), 10B138-832 (SS-10) | breaker maintenance | 1.33 Days
Continuous |
|
| 06-May-26 08:00 | 07-May-26 17:00 | ATCO, ALTALINK | Outage | 948L (650s Hansman Lake - 863s Paintearth), 863s 902 (863s Paintearth), 863s 9L948D4 (863s Paintearth) | transmission line maintenance | 1.38 Days
Continuous |
|
| 06-May-26 08:00 | 01-Jun-26 17:30 | ATCO | TE | 743s Protection & Control (743s Sarah Lake) | relay testing 50BF/700BS1 | 26.4 Days
Continuous |
|
| 06-May-26 08:00 | 01-Jun-26 17:30 | ATCO | TE | 743s Protection & Control (743s Sarah Lake) | relay testing 87TA/701T | 26.4 Days
Continuous |
|
| 06-May-26 08:00 | 01-Jun-26 17:30 | ATCO | TE | 743s Protection & Control (743s Sarah Lake) | relay testing 51MV/701T | 26.4 Days
Continuous |
|
| 06-May-26 08:00 | 01-Jun-26 17:30 | ATCO | TE | 743s Protection & Control (743s Sarah Lake) | relay testing 51HV-51N/701T | 26.4 Days
Continuous |
|
| 06-May-26 09:00 | 08-May-26 16:00 | ATCO | Outage | 2032s 701T (2032s Sweetheart Lake) | transformer maintenance | 2.29 Days
Continuous |
|
| 07-May-26 07:00 | 07-May-26 18:00 | ATCO | TE | 970s Protection & Control (970s Bourque) | change relay settings on 7L574 to alt settings at 970S | 11 Hours
Continuous |
|
| 07-May-26 07:30 | 08-May-26 18:00 | ALTALINK | Outage | 262s 870W (262s Rocky Mountain House), 870L (262s Rocky Mountain House - 263s Strachan), 263s 870E (263s Strachan) | test CT7 to determine if Koncar type CT needs to be scheduled for replacement | 1.44 Days
Continuous |
|
| 07-May-26 07:30 | 07-May-26 10:30 | ALTALINK | Outage | 37s 747W (37s North Calder), 747L (37s North Calder - 711L tap) | trip testing | 3 Hours
Continuous |
|
| 07-May-26 08:00 | 07-May-26 17:00 | ATCO, CNRL | TE | ATCO Telecom Equipment, 859s RTU/SCADA (859s Primrose) | Wolf Lake_S-Telecom- testing and possibly replacing the B side or the switch gear | 9 Hours
Continuous |
|
| 07-May-26 08:00 | 07-May-26 16:00 | ALTALINK | TE | 698s RTU/SCADA (698s Jackfish) | split the existing SCADA VLAN from 1 to 1 and 2
|
8 Hours
Continuous |
|
| 07-May-26 08:00 | 07-May-26 16:00 | ENMAX | RB | 31.84L (SS-31 - SS-32) | tree trimming | 8 Hours
Continuous |
|
| 07-May-26 08:00 | 07-May-26 16:00 | ENMAX | RB | 16.63L (SS-16 - SS-36) | tree trimming | 8 Hours
Continuous |
|
| 07-May-26 08:00 | 07-May-26 17:00 | ATCO | RB | 7L574 (822s Wolf Lake - 7L574 tap), 7L574 (970s Bourque - 7L574 tap), 7L35 (859s Primrose - 7L35 tap) | reclosing turned off on 7L574/7L35 for the duration of this work 1-00517342 | 9 Hours
Continuous |
|
| 07-May-26 08:00 | 07-May-26 17:00 | ATCO, CNRL | TE | 859s RTU/SCADA (859s Primrose) | ATCO scope - aprisa radio between Wolf Lake and Primrose testing |
9 Hours
Continuous |
|
| 07-May-26 08:00 | 07-May-26 16:00 | ENMAX | TE | RTU/SCADA (SS-35) | SCADA RTU/Alarm test | 8 Hours
Daily |
|
| 07-May-26 08:00 | 07-May-26 15:00 | ENMAX | Outage | 6.82L (SS-6 - SS-41), 6B138-6.82 (SS-6), 41B138-6.82 (SS-41) | OH crew to install a pole under the line at the corner of 24 st and 162 av sw | 7 Hours
Continuous |
|
| 07-May-26 08:45 | 07-May-26 16:45 | ALTALINK | Outage | 14s 739E (14s Devon), 155s 739 (155s Blackmud), 739L (14s Devon - 155s Blackmud) | 138kV breaker maintenance | 8 Hours
Continuous |
|
| 07-May-26 09:00 | 19-May-26 17:00 | ATCO | Outage | 972s 908 (972s Tinchebray), 972s 909 (972s Tinchebray) | GOI is required on 907B to isolate 908/909 bay and new 9L16 | 12.33 Days
Continuous |
|
| 07-May-26 09:00 | 07-May-26 09:20 | CMH | TE | MH-15L (MHS-7 Brier Park - MHS-9 South Saskatchewan) | facilitate fiber optic integrity testing on MH138-15L A line protection | 20 Mins
Continuous |
|
| 07-May-26 09:20 | 07-May-26 09:40 | CMH | TE | MH-15L (MHS-7 Brier Park - MHS-9 South Saskatchewan) | facilitate fiber optic integrity testing on MH138-15L B line protection | 20 Mins
Continuous |
|
| 07-May-26 09:40 | 07-May-26 10:00 | CMH | TE | MH-60L (MHS-5 NE Crescent Heights - MHS-7 Brier Park) | facilitate fiber optic integrity testing on MH69-60L A line protection | 20 Mins
Continuous |
|
| 07-May-26 10:00 | 07-May-26 10:20 | CMH | TE | MH-60L (MHS-5 NE Crescent Heights - MHS-7 Brier Park) | facilitate fiber optic integrity testing on MH69-60L B line protection | 20 Mins
Continuous |
|
| 07-May-26 10:20 | 07-May-26 10:40 | CMH, TCPL | TE | MH-65L (MHS-7 Brier Park - Cancarb Energy Medicine Hat) | facilitate fiber optic integrity testing on MH69-65L A line protection | 20 Mins
Continuous |
|
| 07-May-26 10:31 | 07-May-26 13:30 | ALTALINK | Outage | 37s 898 (37s North Calder), 898L (37s North Calder - 92s Viscount), 92s 898 (92s Viscount) | trip testing | 2.98 Hours
Continuous |
|
| 07-May-26 10:40 | 07-May-26 11:00 | CMH, TCPL | TE | MH-65L (MHS-7 Brier Park - Cancarb Energy Medicine Hat) | facilitate fiber optic integrity testing on MH69-65L B line protection | 20 Mins
Continuous |
|
| 07-May-26 12:00 | 07-May-26 17:00 | ALTALINK | TE | 120s RTU/SCADA (120s Picture Butte) | RTU mitigations and reboot | 5 Hours
Continuous |
AB-MATL |
| 07-May-26 13:30 | 07-May-26 16:30 | ALTALINK | Outage | 37s 726E (37s North Calder) | trip testing | 3 Hours
Continuous |
|
| 07-May-26 14:00 | 14-May-26 17:00 | ALTALINK, EPCOR | Outage | 37s Protection & Control (37s North Calder), 37s 88 (37s North Calder), 37s 82 (37s North Calder), 920L (37s North Calder - 557s Castle Downs), 37s 87 (37s North Calder) | P&C upgrades (37s88, 37s82, PT21) | 7.13 Days
Continuous |
|
| 08-May-26 07:00 | 09-May-26 18:00 | ALTALINK | Outage | 228s 744 (228s T.M.P.L. Niton), 744L (228s T.M.P.L. Niton - 744AL tap) | replacing cross arms and insulators on structures | 1.46 Days
Continuous |
|
| 08-May-26 08:00 | 08-May-26 16:00 | ENMAX | Outage | 3.84L (SS-3 - SS-13), 3B138-3.84 (SS-3), 13B138-3.84 (SS-13) | shield wire corrosion, power factor test | 8 Hours
Continuous |
|
| 08-May-26 08:00 | 08-May-26 16:00 | ALTALINK | TE | 818s Winefred RTU/SCADA | split the existing SCADA VLAN
|
8 Hours
Continuous |
|
| 08-May-26 08:00 | 08-May-26 16:00 | ENMAX | RB | 21.61L (SS-21 - SS-34) | tree trimming | 8 Hours
Continuous |
|
| 08-May-26 08:00 | 08-May-26 16:00 | ENMAX | RB | 13.60L (SS-13 - SS-27) | tree trimming | 8 Hours
Continuous |
|
| 08-May-26 08:00 | 08-May-26 16:00 | ENMAX | RB | 16.60L (SS-16 - SS-34) | tree trimming | 8 Hours
Continuous |
|
| 08-May-26 08:00 | 08-May-26 16:00 | ALTALINK | TE | AltaLink Telecom Equipment | Wiring 3 intrusion alarms from the door contract device to the SCADA D25 in the ACC data room. 15min lost of visibility while updating RTU Config. | 8 Hours
Continuous |
|
| 08-May-26 09:00 | 09-May-26 17:00 | ATCO | Outage | 972s 240kV Bus 900BS2 (972s Tinchebray), 972s 903 (972s Tinchebray), 972s 906 (972s Tinchebray) | connect new 909A to 900BS2 | 1.33 Days
Continuous |
|
| 09-May-26 07:00 | 09-May-26 17:00 | EPCOR | TE | EP 803s RTU/SCADA (EP 803s Lambton) | RTU outage - station firewall replacement, communications outage | 10 Hours
Continuous |
|
| 09-May-26 07:00 | 13-May-26 18:00 | ALTALINK | Outage | 612L (336s Fincastle - 368s Burdett), 336s 612 (336s Fincastle), 368s 612 (368s Burdett) | replacing cross arms and insulators on structures 174, 196, 197, 198, 203, 205, 206, 207, 208, 209, 210, 211 and 212 | 4.46 Days
Continuous |
|
| 09-May-26 08:00 | 09-May-26 16:00 | ALTALINK | TE | 71s RTU/SCADA (71s Lamoureux) | split the existing SCADA VLAN | 8 Hours
Continuous |
|
| 09-May-26 09:00 | 10-May-26 17:00 | BCH | Outage | 5L91 (BCH Ashton Creek - BCH Selkirk) | urgent work to support a major project | 1.33 Days
Continuous |
AB-BC |
| 10-May-26 07:00 | 10-May-26 17:00 | EPCOR | TE | RTU/SCADA (EPCOR Hardisty) | RTU outage - substation firewall replacement, full communications outage | 10 Hours
Continuous |
|
| 10-May-26 08:00 | 10-May-26 17:00 | ALTALINK | Outage | 199L (268s Whitecourt - 199AL tap), 268s 199N (268s Whitecourt) | replace keeper keys at structure 375 | 9 Hours
Continuous |
|
| 10-May-26 08:00 | 11-May-26 16:00 | ENMAX, ALTALINK | TE | 653s RTU/SCADA (653s Summit) | updating the RTU configuration | 1.33 Days
Continuous |
|
| 11-May-26 07:00 | 14-May-26 18:00 | ATCO, ENBRIDGE, ALTALINK | IO | 7LA114 (658s Chard - 7L114 tap), 7L114 (72s Leismer - 7LA114 tap), 7L114 (907s Waddell - 7LA114 tap), 907s Waddell | AltaLink outage on 72sT2 causing an outage to 7L114 at 907S | 3.46 Days
Continuous |
|
| 11-May-26 07:00 | 13-May-26 17:00 | EPCOR | Outage | 72RW3 (Rossdale - Woodcroft), W724 (Woodcroft), W725 (Woodcroft), RW727 (Rossdale) | termination rebuild (Woodcroft end), scaffold removal | 2.42 Days
Continuous |
|
| 11-May-26 07:00 | 17-May-26 17:00 | EPCOR | Outage | 814s T2 (814s Bellamy), BR722 (Rossdale), 814s B2402 (814s Bellamy), 814s B2406 (814s Bellamy), 814s BAB2 (814s Bellamy) | TX2 zone doble, breaker maintenance/doble, and disconnect maintenance | 6.42 Days
Continuous |
|
| 11-May-26 07:00 | 22-May-26 17:00 | EPCOR | Outage | 52s T1 (52s East Industrial), 52s E2401 (52s East Industrial) | TX1 DGA monitor replacement | 11.42 Days
Continuous |
|
| 11-May-26 07:00 | 15-May-26 17:00 | ALTALINK, EPCOR | RB | 711L (113s Inland Cement - 747L tap) | 711L - aerial washing program | 4.42 Days
Continuous |
|
| 11-May-26 07:00 | 15-May-26 17:30 | ALTALINK | RB | 747L (37s North Calder - 711L tap), 747L (99s North St. Albert - 711L tap), 711L tap | 711L - aerial washing program | 4.44 Days
Continuous |
|
| 11-May-26 07:00 | 14-May-26 18:00 | ALTALINK | Outage | 72s T2 (72s Leismer), 72s 1052 (72s Leismer) | T2 - maintenance, doble testing, Coresense and Qualitrol installation
72s1052 - 1st trip and breaker maintenance |
3.46 Days
Continuous |
|
| 11-May-26 07:00 | 14-May-26 17:00 | ALTALINK, ATCO | Outage | 72s 1052 (72s Leismer), 7L114 (72s Leismer - 7LA114 tap) | customer maintenance | 3.42 Days
Continuous |
|
| 11-May-26 07:00 | 13-May-26 18:00 | ALTALINK, DOW | RB | 787L (166s Dow Chemical Fort Saskatchewan - 787AL tap), 787L (71s Lamoureux - 787AL tap), 787AL (906s Ross Creek - 787L tap) | install a concrete foundation for future structure 31 monopole | 2.46 Days
Continuous |
|
| 11-May-26 07:00 | 11-May-26 13:00 | EPCOR | Outage | 987s GT3 (987s Clover Bar), 987s CGB3 (987s Clover Bar) | maintenance | 6 Hours
Continuous |
|
| 11-May-26 07:00 | 11-May-26 17:00 | EPCOR | Outage | 987s C1 (987s Clover Bar), 987s C72C1 (987s Clover Bar) | bus diff upgrade project | 10 Hours
Continuous |
|
| 11-May-26 07:00 | 11-May-26 17:00 | EPCOR | Outage | 987s GB1B (987s Clover Bar) | bus diff upgrade project | 10 Hours
Continuous |
|
| 11-May-26 08:00 | 14-May-26 16:00 | ALTALINK | TE | 71s RTU/SCADA (71s Lamoureux), AltaLink Telecom Equipment | upgrade firewall, MPLS nodes, MPLS raw socket | 3.33 Days
Continuous |
|
| 11-May-26 08:00 | 14-May-26 16:00 | ATCO | RB | 7L75 (ATC 793s West Peace River - 800s Friedenstal) | walk up and climbing inspection | 3.33 Days
Continuous |
|
| 11-May-26 08:00 | 12-May-26 16:00 | ALTALINK | TE | APS# 178 172L (370S-181S) Overload Mitigation | move relay to new City of Lethbridge communication system | 1.33 Days
Continuous |
|
| 11-May-26 08:00 | 12-May-26 17:00 | Lethbridge | TE | 181s Protection & Control (181s Chinook) | protection outages on 181s RAS 178 'A' & 'B' protections to transfer TPR (teleprotection) circuits from existing JMUX to new SEL ICON | 1.38 Days
Continuous |
|
| 11-May-26 08:00 | 12-May-26 16:00 | ENMAX | Outage | 833L (SS-2 - SS-12), 12B138-833L (SS-12), 2MD138-833L (SS-2) | breaker maintenance | 1.33 Days
Continuous |
|
| 11-May-26 08:00 | 14-May-26 16:00 | ALTALINK | Outage | 74s 76 (74s Janet) | 74s76 major maintenance | 3.33 Days
Continuous |
|
| 11-May-26 08:00 | 14-May-26 16:00 | ALTALINK | TE | 127s RTU/SCADA (127s Bruderheim), AltaLink Telecom Equipment | firewall upgrade, raw socket conversion, MPLS 7705A and 7705B upgrade | 3.33 Days
Continuous |
|
| 11-May-26 08:00 | 13-May-26 16:00 | ALTALINK | TE | AltaLink Telecom Equipment, 275s RTU/SCADA (275s Jenner) | firewall replacement, MPLS 7705 A and 7705B upgrade | 2.33 Days
Continuous |
|
| 11-May-26 08:00 | 24-May-26 16:00 | Syncrude | Outage | 211 (Aurora), 213 (Aurora), 212B (Aurora), 213A (Aurora), 89-215 (Aurora), AL-1 (Aurora - D05), D05 520 (D05), D05 517 (D05), D05 519 (D05) | zone 5 6yr PM | 13.33 Days
Continuous |
|
| 11-May-26 08:00 | 11-May-26 16:00 | ENMAX | RB | 26.81L (SS-26 - SS-32) | tree trimming | 8 Hours
Continuous |
|
| 11-May-26 08:00 | 11-May-26 16:00 | ENMAX | RB | 37.81L (SS-37 - SS-38) | tree trimming | 8 Hours
Continuous |
|
| 11-May-26 08:00 | 15-May-26 16:00 | CMH | TE | MHS-7 Protection & Control (MHS-7 Brier Park) | Perform preventative maintenance on BPR-69-A | 4.33 Days
Continuous |
|
| 11-May-26 08:00 | 15-May-26 15:00 | CMH | Outage | MH-20L (MHS-3 Southridge - MHS-6 CMH Riverview), MHS-3 MH138-T34 (MHS-3 Southridge), MHS-6 MH138-T63 (MHS-6 Riverview), MHS-6 MH138-620 (MHS-6 CMH Riverview), MHS-3 MH138-317 (MHS-3 Southridge), MHS-3 MH69-302 (MHS-3 Southridge), MHS-6 MH69-611 (MHS-6 CMH Riverview) | installation of lightning protection at MHS-3S south ridge substation | 4.29 Days
Continuous |
|
| 11-May-26 08:00 | 12-May-26 16:00 | ENMAX | TE | RTU/SCADA (SS-43) | SCADA RTU test - RTU-43, SCADA alarm test - RTU-43 ANN | 1.33 Days
Daily |
|
| 11-May-26 08:00 | 11-May-26 16:00 | ENMAX | TE | Protection & Control (SS-65) | 65 sub 86BF D135 lockout relay protection outage - relays, lockout testing 65RLY240-D135 | 8 Hours
Continuous |
|
| 11-May-26 08:00 | 14-May-26 16:00 | ENMAX | Outage | 16.1TR (SS-16) | 16PT69-Z21 PT outage. Fault clearing time 6.5 cycles. Transformer Power Factor Test. Secondary Cable Test. Transformer Maintenance. Relay Fault Pressure Test. Reversing Switch Check. Oil Sampling MT, TC. | 3.33 Days
Continuous |
|
| 11-May-26 08:00 | 29-May-26 16:00 | ALTALINK | TE | 1182s RTU/SCADA (1182s Berland River) | RTU outage required for SCADA deficiency clean-up and SCN testing | 18.33 Days
Continuous |
|
| 11-May-26 08:00 | 14-May-26 16:00 | ENMAX | Outage | 8.5TR (SS-8) | Transformer Power Factor Test. Transformer Maintenance. Relay Fault Pressure Test. Oil Sampling MT, TC. | 3.33 Days
Continuous |
|
| 11-May-26 09:00 | 12-May-26 15:00 | ATCO, ALBIAN | Outage | 920s 901T (920s Jackpine), 920s A1 (920s Jackpine), 920s 901 (920s Jackpine), 920s 901TD (920s Jackpine) | 901T outage for CNRL to troubleshoot problems on their system | 30 Hours
Continuous |
|
| 11-May-26 09:00 | 15-May-26 16:00 | ATCO | TE | ATCO Telecom Equipment | EOL Radio Replacement Codesa to Jean Cote Removal of constellation radio, replace with IRU600 THE FOLLOWING TRAFFIC WILL BE IMPACTED FOR THE DURATION OF THE RADIO REPLACEMENT: 7L75 A&B - WEST PEACE / FRIEDENSTAL 7L75 RAS A&B - WEST PEACE / KSITUAN |
4.29 Days
Continuous |
|
| 11-May-26 09:00 | 11-May-26 17:00 | ALTALINK | Outage | 291s T1 (291s Cochrane), 291s 1 (291s Cochrane) | install full loops for LA grounds on high side and low side | 8 Hours
Daily |
|
| 11-May-26 09:00 | 11-May-26 18:00 | ALTALINK | Outage | 185s 252 (185s Bretville), 185s 152 (185s Bretville), 286s 605 (286s Yasa), 605L (185s Bretville - 286s Yasa) | transmission line maintenance | 9 Hours
Continuous |
|
| 11-May-26 09:45 | 12-May-26 17:45 | ALTALINK | Outage | 171s 735X (171s Redwater), 233s 735N (233s Beamer), 735L (171s Redwater - 233s Beamer) | transmission line maintenance | 1.33 Days
Continuous |
|
| 11-May-26 10:00 | 11-May-26 17:00 | ALTALINK | RB | 158s 763N (158s Vauxhall), 28s 47 (28s West Brooks), 28s 31 (28s West Brooks), 447s 763A (447s Enchant), 763AL (447s Enchant - 763A1L tap), 763L (158s Vauxhall - 763AL tap), 763L (28s West Brooks - 763AL tap) | damper change on 763AL123, damper wearing through conductor (live line work) | 7 Hours
Continuous |
|
| 11-May-26 13:00 | 14-May-26 09:00 | ATCO | Outage | 2033s 703C (2033s Mowat) | PRC trip coil testing and protection testing | 2.83 Days
Continuous |
|
| 11-May-26 13:00 | 14-May-26 13:00 | ATCO | Outage | 827s SVC (827s Cranberry Lake), 827s 703 (827s Cranberry Lake) | SVC maintenance | 3 Days
Continuous |
|
| 11-May-26 13:30 | 14-May-26 17:00 | ALTALINK | Outage | 38s 7452 (38s East Edmonton) | 240kV breaker maintenance | 3.15 Days
Continuous |
|
| 11-May-26 18:00 | 08-Jun-26 08:00 | ATCO, ALTALINK | Outage | 962L (87s Gaetz - 972s Tinchebray) | Switch needs to remain open until ATCO is ready @ 972s for energization | 27.58 Days
Continuous |
|
| 11-May-26 18:00 | 08-Jun-26 08:00 | ATCO, ALTALINK | Outage | 986L (87s Gaetz - 972s Tinchebray) | Switch needs to remain open until ATCO is ready @ 972s for energization | 27.58 Days
Continuous |
|
| 12-May-26 07:00 | 13-May-26 18:00 | ALTALINK, ICPCL | Outage | 225L (225s Magrath - 225AL tap), 225L (67s Stirling - 225AL tap), 225AL (313s Raymond Reservoir - 225L tap), 67s 225 (67s Stirling), 225s 225E (225s Magrath) | 93, 149 replace arms and insulators | 1.46 Days
Continuous |
|
| 12-May-26 07:00 | 19-May-26 17:30 | ATCO | TE | 743s Protection & Control (743s Sarah Lake) | relay isolation for 50BF/705 and 50BF/706 for settings update | 7.44 Days
Continuous |
|
| 12-May-26 07:30 | 13-May-26 16:30 | ALTALINK | Outage | 157s 788N (157s Lac La Biche), 157s 728W (157s Lac La Biche), 157s 652 (157s Lac La Biche), 157s 3 (157s Lac La Biche), 157s T1 (157s Lac La Biche), 157s 138kV Bus 1 (157s Lac La Biche) | Installing new screw piles | 1.38 Days
Continuous |
|
| 12-May-26 08:00 | 13-May-26 16:00 | ATCO | Outage | 6L05 (757s Battle River - 843s Bigknife Creek), 6LA05 (843s Bigknife Creek - 765s Mannix Mine), 757s 602 (757s Battle River) | line to ground clearance mitigation, structures 2A, 3A, 5A, 6A | 1.33 Days
Continuous |
|
| 12-May-26 08:00 | 14-May-26 16:00 | ALTALINK | TE | 349s Protection & Control (349s Stavely) | move relay to new City of Lethbridge communication system | 2.33 Days
Continuous |
|
| 12-May-26 08:00 | 14-May-26 17:00 | Lethbridge | TE | 181s Protection & Control (181s Chinook) | protection outages on 181s RAS AIS 1147 'A' & 'B' protections to transfer TPR (teleprotection) circuits from existing JMUX to new SEL ICON | 2.38 Days
Continuous |
|
| 12-May-26 08:00 | 12-May-26 17:00 | ALTALINK | Outage | 291s T2 (291s Cochrane) | install full loops for LA grounds on high side and low side of transformer | 9 Hours
Daily |
|
| 12-May-26 08:00 | 12-May-26 17:00 | ALTALINK | Outage | 422s 694 (422s Westwood), 54s 694 (54s Fort Saskatchewan), 694L (54s Fort Saskatchewan - 422s Westwood) | Replacing cross arms and insulators on structure 6
Replacing OHSW bayonet on structure 8 |
9 Hours
Continuous |
|
| 12-May-26 08:00 | 12-May-26 17:00 | ALTALINK | Outage | 77s 26 (77s Sagitawah) | 240kV breaker maintenance | 9 Hours
Continuous |
|
| 12-May-26 08:00 | 13-May-26 17:00 | ALTALINK | TE | AltaLink Telecom Equipment | microwave upgrade hop between 618s Riverbend to 225s Magrath | 1.38 Days
Continuous |
|
| 12-May-26 08:00 | 29-May-26 17:00 | ATCO | TE | ATCO RTU/SCADA | firewall firmware upgrades at the Primary Control Center and the Secondary Control Center potential activity due to firmware upgrades, firewall failovers, and site cutover activities |
17.38 Days
Continuous |
|
| 12-May-26 08:00 | 13-May-26 16:00 | ATCO, ALTALINK | RB | 788L (898s Heart Lake - 788AL tap) | reclosing blocked on 788L for AltaLink work | 1.33 Days
Continuous |
|
| 12-May-26 08:00 | 12-May-26 16:00 | ENMAX | TE | Protection & Control (SS-65) | 65 sub 86BF D134 lockout relay protection outage - relays, lockout testing 65RLY240-D134 | 8 Hours
Continuous |
|
| 12-May-26 09:00 | 12-May-26 16:00 | ATCO | TE | ATCO Telecom Equipment, 893s RTU/SCADA (893s Cavendish) | Cappon_T-Telecom/Cavendish_S-Telecom- radio major maintenance. | 7 Hours
Continuous |
|
| 12-May-26 12:00 | 15-May-26 14:00 | ATCO | TE | ATCO Telecom Equipment | Chard telecom replacing | 3.08 Days
Continuous |
|
| 13-May-26 06:00 | 13-May-26 17:00 | ATCO | TE | ATCO RTU/SCADA | SOC2 Backup Control Centre activation | 11 Hours
Continuous |
|
| 13-May-26 07:00 | 14-May-26 18:00 | ALTALINK | Outage | 761L (38s East Edmonton - 71s Lamoureux), 71s 652 (71s Lamoureux), 38s 761N (38s East Edmonton), 71s 552 (71s Lamoureux) | North Crew will be replacing arms and insulation | 1.46 Days
Continuous |
|
| 13-May-26 08:00 | 26-May-26 16:00 | ATCO, CNRL, ALBIAN | Outage | 847s 902T (847s Muskeg River), 919s 908 (919s Hartley) | open 908 breaker and 902TD in the Hartley 919S substation for maintenance | 13.33 Days
Continuous |
|
| 13-May-26 08:00 | 13-May-26 17:00 | ALTALINK | Outage | 77s 40 (77s Sagitawah) | breaker maintenance | 9 Hours
Continuous |
|
| 13-May-26 08:00 | 14-May-26 16:00 | ENMAX | Outage | 2.80L (SS-2 - SS-23), 23B138-2.80 (SS-23), 2MD138-2.80 (SS-2) | 23B138-2.80 rebuild dash pot, low oil, breaker SF6 gas sample | 1.33 Days
Continuous |
|
| 13-May-26 08:00 | 14-May-26 16:00 | ATCO | RB | 7L34 (815s Goodfare - 886s Updike) | walk up and climbing inspection | 1.33 Days
Continuous |
|
| 13-May-26 08:00 | 13-May-26 16:00 | ENMAX | TE | Protection & Control (SS-65) | 65 sub 86BF D133 lockout relay protection outage - relays, lockout testing 65RLY240-D133 | 8 Hours
Continuous |
|
| 13-May-26 08:00 | 13-May-26 16:30 | ATCO, ALTALINK | RB | 9L938 (77s Sagitawah - 809s Louise Creek) | reclosing blocked for AltaLink | 8.5 Hours
Continuous |
|
| 13-May-26 08:00 | 13-May-26 16:00 | ENMAX | Outage | 3.3TR (SS-3) | 3 sub - switchgear cleaning - 3.3TR secondary cable compartment | 8 Hours
Continuous |
|
| 13-May-26 08:30 | 14-May-26 16:00 | ALTALINK | TE | 562s Protection & Control (562s Cypress) | 562s RAS relay maintenance, Non redundant, RAS33, RAS112, RAS 27. One a time. | 31.5 Hours
Continuous |
|
| 13-May-26 08:30 | 13-May-26 17:30 | ALTALINK | IO | 67s 225 (67s Stirling) | CRU upgrade for ACC visibility | 9 Hours
Daily |
|
| 13-May-26 09:00 | 14-May-26 15:00 | ATCO, ALBIAN | Outage | 9LJH2 (919s Hartley - 920s Jackpine), 920s 902T (920s Jackpine), 920s 902 (920s Jackpine), 919s 907 (919s Hartley), 920s B1 (920s Jackpine), 920s 902TD (920s Jackpine) | isolation of 902T for CNRL to troubleshoot problems on their system | 30 Hours
Continuous |
|
| 13-May-26 09:00 | 13-May-26 16:00 | ATCO | TE | ATCO Telecom Equipment, 914s RTU/SCADA (914s Bindloss) | Cappon_T-Telecom/Bindloss_S-Telecom- RADIO Major DIGITAL PHOENIX G2 2GHZ PM(to Bindloss) Radio A, the Radio B..IMPACT TO THE FOLLOWING TRAFFIC: 7L760 / 7LA760 BF DTT, BINDLOSS SUB SCADA | 7 Hours
Continuous |
|
| 13-May-26 09:00 | 14-May-26 17:00 | ALTALINK | TE | 67s RTU/SCADA (67s Stirling) | CRU upgrade - supervisory outage to complete upgrades to RTU and alarm splitting | 1.33 Days
Daily |
|
| 13-May-26 09:00 | 14-May-26 17:00 | ALTALINK | TE | 67s Protection & Control (67s Stirling) | upgrade CRU - alarm splitting, protection outages on 508L A/B protections to complete scope | 1.33 Days
Daily |
|
| 14-May-26 05:30 | 14-May-26 07:00 | ATCO | TE | ATCO Telecom Equipment, ATCO EMS/ICCP Outage | replace the old HP and mobile firewalls at Vegreville and install some new networking cards on the Low BES VPN firewalls | 90 Mins
Continuous |
|
| 14-May-26 07:00 | 14-May-26 18:00 | ALTALINK | Outage | 880L (321s Al Rothbauer - 523s Bullshead), 321s 880 (321s Al Rothbauer), 523s 880 (523s Bullshead) | re-installing damper on structure 4, re-tying OHSW's on structure 8 | 11 Hours
Daily |
|
| 14-May-26 08:00 | 14-May-26 17:00 | ALTALINK | Outage | 77s 552 (77s Sagitawah) | 138kV breaker maintenance | 9 Hours
Continuous |
|
| 14-May-26 08:00 | 14-May-26 16:00 | ENMAX | TE | Protection & Control (SS-65) | 65 sub 86BF D132 lockout relay protection outage, relays, lockout testing 65RLY240-D132 | 8 Hours
Continuous |
|
| 14-May-26 08:00 | 14-May-26 16:00 | ALTALINK | TE | 42s Protection & Control (42s Sarcee) | urgent - complete card replacements and firmware upgrade on relay to correct communications failure, 3L B21/79/L8 URD60 out of service | 8 Hours
Continuous |
|
| 14-May-26 08:00 | 14-May-26 11:00 | Lethbridge | TE | 241s Protection & Control (241s Uplands) | 241s 138kv Bus Protection (SEL 487b) outage to add logic for DDR initiate and test output circuits, Will lose buss differential (87) while relay is OOS | 3 Hours
Continuous |
|
| 14-May-26 09:30 | 15-May-26 16:00 | ATCO | TE | 840s RTU/SCADA (840s McNeill Station) | moving communication and SCADA traffic onto new star link device | 30.5 Hours
Continuous |
|
| 14-May-26 12:00 | 14-May-26 17:00 | ALTALINK | TE | 120s RTU/SCADA (120s Picture Butte) | RTU mitigations and reboot | 5 Hours
Continuous |
AB-MATL |
| 15-May-26 07:00 | 15-May-26 17:30 | ATCO | TE | 743s Protection & Control (743s Sarah Lake) | blocking 21B/6L126 relay for some settings changes | 10.5 Hours
Continuous |
|
| 15-May-26 07:15 | 17-May-26 18:00 | ALTALINK | Outage | 305s 677 (305s Acheson), 595s 677 (595s Spruce Grove), 677L (305s Acheson - 595s Spruce Grove) | transmission line maintenance | 2.45 Days
Continuous |
|
| 15-May-26 08:00 | 18-May-26 16:00 | ALTALINK | TE | 275s RTU/SCADA (275s Jenner) | split the existing SCADA VLAN from 1 to 1 and 2
|
3.33 Days
Continuous |
|
| 15-May-26 08:00 | 15-May-26 12:00 | ENMAX | Outage | 22.81L (SS-22 - SS-39), 22.2TR (SS-22), 22B138-22.81 (SS-22), 22B138-22BT8 (SS-22), SW85 (SS-22), 39B138-22.81 (SS-39) | spring substation washing | 4 Hours
Continuous |
|
| 15-May-26 08:00 | 27-May-26 16:00 | ENMAX | Outage | 1.5TR (SS-1) | connect transformer secondary cables to 1B8-1.5TR | 12.33 Days
Continuous |
|
| 15-May-26 09:00 | 25-May-26 17:00 | BCH | Outage | 2L113 (BCH Cranbrook - BCH Natal), 2D23 (BCH Nelway), 2D21 (BCH Natal) | install marker balls | 10.33 Days
Continuous |
AB-BC |
| 15-May-26 12:00 | 15-May-26 18:00 | ENMAX | Outage | 13.82L (SS-13 - SS-22), 22.3TR (SS-22), 22.1TR (SS-22), 13B138-13.82 (SS-13), 22B138-13.82 (SS-22), 22B138-22BT8 (SS-22), SW83 (SS-22), SW84 (SS-22) | spring substation washing | 6 Hours
Continuous |
| This document and the information contained herein are based upon information and data which by their nature contain a degree of uncertainty and are subject to change. In addition, this document may contain information and data from public sources and/or third parties, which have been assumed to be accurate and complete and have not been verified. Accordingly, the Independent System Operator, operating as the Alberta Electric System Operator (the "AESO") makes no warranty, representation or guarantee, express or implied, with respect to this document or the information contained herein, including, but not limited to, any warranty, representation or guarantee of accuracy, completeness, timeliness, reliability, availability, absence of computer virus, non- infringement, merchantability or suitability for any purpose. Under no circumstances will the AESO, its members, officers, employees, contractors or agents, or any of their respective affiliates, be liable for any errors or omissions in, or any losses, damages or claims whatsoever, whether in contract, tort or otherwise, arising from use of or reliance upon, this document or any information contained herein. © 2009 Alberta Electric System Operator. All rights reserved |