Alberta Electric System Operator
System Co-ordination Plan
2020-12-03 to 2020-12-11
Approved Outages

Previous Version
Download CSV

From To Owner Type Element Scheduled Activity Date/Time Comments Interconnection
05-Oct-18 08:00 31-Dec-20 16:00 EPCOR IO Rossdale C2 (Rossdale) forced outage 818.38 Days
Continuous
 
24-Oct-18 01:13 31-Dec-20 16:00 EPCOR IO Rossdale C1 (Rossdale) forced outage 799.66 Days
Continuous
 
19-Sep-19 08:00 31-Mar-21 16:00 ATCO Outage 826s 504R (826s Marguerite Lake) emergency: move reactor from 826s to 732s 559.33 Days
Continuous
 
01-Jan-20 08:00 31-Dec-20 18:00 SUNCOR Outage Unmodeled Transmission Facility (Suncor) 29L3-167, 29L3-141 , 29PL3-63, 29PL3-183, 29PT-241 & 29PL7-4, 29PP-47 & 29PT-576, 29PP-46 & 29PT-575, 144KV NODE,29PT-246, 144KV NODE,29PT-238, 29PT-257 & 29PL7-4,29PT-260 & 29PL7-4, 29PT-250&29PL7-3,29PT-236 & 29PL7-3,29PL3-153/152/196, 29PT-128 & 29PL7-10 365.42 Days
Daily
 
24-Jan-20 08:00 31-Mar-21 16:00 ATCO Outage 2029s ACF13 (2029s Heathfield) forced outage repairs 432.29 Days
Continuous
 
05-Aug-20 08:00 15-Dec-20 16:00 ATCO TE 794S Valleyview remove failed breaker 702 BF relay and install when it is returned from repair 132.38 Days
Continuous
 
18-Aug-20 08:00 01-Feb-21 17:00 ATCO TE 811s Clairmont Lake RTU/SCADA RTU download and test 167.42 Days
Continuous
 
22-Aug-20 08:00 01-Feb-21 16:00 ATCO TE 811S Clairmont Lake block 144 kV bus current differential protection for duration of project: changes to all CT circuits, and doing primary injections which could trip the bus relay 163.38 Days
Continuous
 
31-Aug-20 07:00 31-Dec-20 23:59 EPCOR Outage 805s C1 (805s Jasper) forced 122.75 Days
Continuous
 
31-Aug-20 08:30 22-Jan-21 18:00 ALTALINK Outage 74s C1 (74s Janet), 74s C2 (74s Janet) replace 138kV C1 cap bank 144.44 Days
Continuous
 
19-Oct-20 07:00 31-Dec-20 17:00 EPCOR Outage 814s T1 (814s Bellamy), 814s B2401 (814s Bellamy), 814s B2407 (814s Bellamy) regasketing work 73.46 Days
Continuous
 
27-Oct-20 13:00 16-Feb-21 13:00 ALTALINK Outage 293s T2 (293s Bernese) install grounds to facilitate high bus installation 112.04 Days
Continuous
 
02-Nov-20 09:30 04-Dec-20 16:00 ENMAX Outage 162s 138-RB80 (162s Beddington), 162s 138-RB81 (162s Beddington), 162.81L (162s Beddington - 391S Balzac) line protection upgrade 32.27 Days
Continuous
 
02-Nov-20 09:30 04-Dec-20 16:00 ALTALINK IO 162.81L GOI & Advice for ENMAX line protection upgrade 32.27 Days
Continuous
 
02-Nov-20 12:00 05-Dec-20 16:00 ENMAX TE 162s Beddington RTU & line protection upgrade - settings changes 33.17 Days
Daily
 
03-Nov-20 07:00 31-Dec-20 17:00 EPCOR TE Garneau RTU/SCADA station SA system being upgraded and tested to accommodate future upgrade to ADMS system 58.42 Days
Daily
 
03-Nov-20 07:00 31-Dec-20 17:00 EPCOR TE 816s Petrolia RTU/SCADA station SA system being upgraded and tested to accommodate future upgrade to ADMS system 58.42 Days
Daily
 
03-Nov-20 07:00 31-Dec-20 17:00 EPCOR TE 52s East Industrial RTU/SCADA station SA system being upgraded and tested to accommodate future upgrade to ADMS system 58.42 Days
Daily
 
03-Nov-20 07:00 31-Dec-20 17:00 EPCOR IO Strathcona S/S SA upgrade and commissioning for ADMS project Station SA system being upgraded and tested to accommodate future upgrade to ADMS system. 58.42 Days
Daily
 
05-Nov-20 08:00 07-Dec-20 16:00 CMH Outage MH-10L (MH69s2 North Industrial - MHS8 Burnside) cut the 10L into the new MHS-10 substation (P2151 CMH Central Area Upgrade) 32.33 Days
Continuous
 
07-Nov-20 08:00 05-Dec-20 16:00 ENMAX TE 162.1TR (162s Beddington) 162.81 line protection upgrade - differential protection update 28.33 Days
Daily
 
07-Nov-20 08:00 05-Dec-20 16:00 ENMAX TE 162s Beddington 162.81 line protection upgrade - settings changes 28.33 Days
Daily
 
07-Nov-20 08:00 05-Dec-20 16:00 ENMAX TE 162s Beddington 162.81 line protection upgrade - 138 kV and 240 kV bus differential protection settings changes, testing, modifications 28.33 Days
Daily
 
07-Nov-20 08:00 05-Dec-20 16:00 ENMAX, ALTALINK TE 771L (162s Beddington - ENMAX 47) 162.81 line protection upgrade- settings changes 28.33 Days
Daily
 
07-Nov-20 08:00 05-Dec-20 16:00 ENMAX TE 11.83L (162s Beddington - ENMAX 11) 162.81 line protection upgrade - settings changes 28.33 Days
Daily
 
21-Nov-20 07:00 04-Dec-20 16:00 ENMAX Outage 7.84L (ENMAX 7 - ENMAX 36) Broadcast Hill project, relocating structures 11 to 16, phasing required 13.38 Days
Continuous
 
23-Nov-20 07:00 04-Dec-20 17:18 ATCO TE 2075S Newell replace the in-service PMUs at Newell 11.43 Days
Continuous
 
23-Nov-20 07:30 11-Dec-20 17:30 ALTALINK TE 993s Abee RTU/SCADA update RTU configuration for new transformer alarms 18.42 Days
Daily
 
23-Nov-20 07:30 05-Dec-20 17:30 ALTALINK RB 113L (20s Ghost - 33s Spray) bore hole testing 12.42 Days
Daily
 
23-Nov-20 09:00 04-Dec-20 17:00 ALTALINK TE 247s Piper Creek RTU/SCADA cut over alarm and update, RTU for 247s Piper Creek – 427L A & B line protections replacements 11.33 Days
Continuous
 
23-Nov-20 09:00 04-Dec-20 17:00 ALTALINK TE 63s Red Deer RTU/SCADA cut over alarm and update, RTU for 63s Red Deer – 427L A & B line protections replacements 11.33 Days
Continuous
 
23-Nov-20 11:15 04-Dec-20 17:45 ALTALINK Outage 55s T2 (55s Olds) oil reclamation 11.27 Days
Continuous
 
23-Nov-20 12:30 04-Dec-20 17:30 ALTALINK Outage 427L (63s Red Deer - 247s Piper Creek) replace A and B line protections at 247s 11.21 Days
Continuous
 
26-Nov-20 08:00 07-Dec-20 20:00 Syncrude Outage 11 (Aurora), T1 (Aurora), 21 (Aurora), 31 (Aurora), 211 (Aurora), 221 (Aurora) transformer maintenance 11.5 Days
Continuous
 
27-Nov-20 08:00 09-Dec-20 20:00 Syncrude Outage Mildred T15 (Syncrude Mildred Lake), Mildred Lake 1535 (Syncrude Mildred Lake) maintenance 12.5 Days
Continuous
 
28-Nov-20 08:00 04-Dec-20 18:00 SUNCOR Outage Unmodeled Transmission Facility (Suncor) 452-9001, 652-9102, 652-9003T, 30PP-91, 29PP-70B, 30PP-90, 29PT280, 29PT281 6.42 Days
Daily
 
28-Nov-20 08:00 07-Dec-20 18:00 SUNCOR Outage Unmodeled Transmission Facility (Suncor) 29-652-7010, 29-652-7020, 29-652-7030, 29-652-7040, 29-652-7050, 29-652-7060 9.42 Days
Daily
 
28-Nov-20 08:00 08-Dec-20 18:00 SUNCOR Outage Unmodeled Transmission Facility (Suncor) 29PP-37C, 29PP-37B, 29PP-37A, 652-3701, 652-3702, 652-3703, 652-3704 10.42 Days
Daily
 
30-Nov-20 07:00 11-Dec-20 17:00 EPCOR Outage 72LH8 (803s Lambton - Hardisty), 72LS24 (803s Lambton - Strathcona) Line protection cutover 11.42 Days
Continuous
 
30-Nov-20 07:00 04-Dec-20 17:00 EPCOR Outage 1164L (816s Petrolia - EPCOR Riverview) switch repair/P&C wiring 4.42 Days
Continuous
 
30-Nov-20 07:00 04-Dec-20 18:00 ALTALINK Outage 545s T1 (545s Provost), 715L (545s Provost - 650s Hansman Lake), 715L (648s Metiskow - 650s Hansman Lake) removing mobile substation and energizing new 138kV bus and associated equipment 4.46 Days
Continuous
 
30-Nov-20 07:00 04-Dec-20 17:00 ALTALINK IO 1164L OOS for EPCOR switch repair/P&C wiring 4.42 Days
Continuous
 
30-Nov-20 07:30 04-Dec-20 17:30 ALTALINK Outage 89s 252 (89s Ellerslie) replace CT252 4.42 Days
Continuous
 
30-Nov-20 08:00 03-Dec-20 16:00 ENMAX Outage 8B138-3A0 (ENMAX 8), 8B138-4A0 (ENMAX 8), 1.83L (ENMAX 1 - ENMAX 8) maintenance GIS switches 3.33 Days
Continuous
 
30-Nov-20 08:00 03-Dec-20 18:00 ALTALINK TE 277s Hayter RTU/SCADA updating for the addition of the new 277s852 bus tie breaker associated protections 3.42 Days
Daily
 
30-Nov-20 08:00 03-Dec-20 17:00 ALTALINK TE 391s Balzac RTU/SCADA update configuration for 162.81L protection replacement 3.38 Days
Daily
 
30-Nov-20 09:00 07-Dec-20 17:00 BCH Outage 1L274 (48s Pocaterra - Britt Creek) structure refurbishment 7.33 Days
Continuous
AB-BC
30-Nov-20 09:00 19-Dec-20 17:00 ALTALINK IO 48s38 (887L) Advice for BCH structure refurbishment - BC Hydro 19.33 Days
Continuous
 
30-Nov-20 09:00 04-Dec-20 17:00 BCH TE 5L94 (Cranbrook - 102s Langdon) protection work 4.33 Days
Continuous
 
30-Nov-20 09:00 04-Dec-20 17:00 ALTALINK IO 1201L (520s Bennett - BCH Cranbrook) 1201 Protection Outage for BCH 4.33 Days
Continuous
 
30-Nov-20 09:30 16-Dec-20 14:00 EPCOR Outage 72NW15 (Namao - Woodcroft) line maintenance and upgrades 16.19 Days
Continuous
 
30-Nov-20 09:55 03-Dec-20 17:05 ALTALINK RB 185AL (415s Drywood - 995s Yarrow), 185L (379s Shell Canada Waterton - 415s Drywood) structure replacements 185AL, str's range 8-39 3.3 Days
Daily
 
30-Nov-20 10:00 04-Dec-20 17:00 ATCO TE 951S Thickwood Hills replace faulty motor/pump on SVS cooling system 4.29 Days
Continuous
 
30-Nov-20 12:15 03-Dec-20 17:45 ALTALINK Outage 730L (285s East Camrose - 732L) component replacements complete remaining work structures range 64-196 - south section of 730L 3.23 Days
Continuous
 
01-Dec-20 07:15 03-Dec-20 16:45 ALTALINK Outage 245s T1 (245s Horseshoe) 138kV CT replacement (245s T1) 2.4 Days
Continuous
 
01-Dec-20 07:15 03-Dec-20 17:45 ALTALINK Outage 5s 1152 (5s East Calgary), 5s 1252 (5s East Calgary), 936L (5s East Calgary - 102s Langdon) urgent replace C-phase (CT43572) on 5s1152 due to leaking SF6 2.44 Days
Continuous
 
01-Dec-20 08:00 03-Dec-20 16:00 ENMAX Outage 162.1TR (162s Beddington), 162s 138-RB86 (162s Beddington), 162s 138_RB94 (162s Beddington), 162s 240-RB131 (162s Beddington), 162s 240-RB134 (162s Beddington) RTU & line protection upgrade & settings changes 2.33 Days
Continuous
 
01-Dec-20 08:00 03-Dec-20 16:00 ENMAX TE 162s Beddington 162s C60-1: RTU & line protection upgrade and settings changes 2.33 Days
Continuous
 
01-Dec-20 08:00 14-Dec-20 16:00 ALTALINK Outage 180L (15s Fort Macleod - 928s East Stavely) install new tap for new substation 604s Granum & OPGW repairs between structures 515-520 (P1879) 13.33 Days
Continuous
 
01-Dec-20 09:30 11-Dec-20 16:30 ALTALINK Outage 15s 180N (15s Fort Macleod) implement and test new RAS scheme 10.29 Days
Continuous
 
01-Dec-20 10:00 11-Dec-20 16:00 ALTALINK TE 15s Fort Macleod RTU/SCADA ability to do daily visibility outages during the outage for the downloading of required SCADA, additions, changes, corrections related to the modifications / upgrade of 180L line and RAS relays 10.25 Days
Daily
 
01-Dec-20 13:00 04-Dec-20 17:00 ATCO TE 875S Algar relay preventative maintenance 3.17 Days
Continuous
 
02-Dec-20 07:00 03-Dec-20 18:00 ALTALINK Outage 519L (996s Imperial Oil Carson Lake - 519AL), 519AL (661s Laura Lake - 519L tap), 519L (519AL - 526L) fire mitigation 1.46 Days
Continuous
 
02-Dec-20 07:15 03-Dec-20 17:45 ALTALINK Outage 85L (35s Rundle - 54L tap) maintenance on structure 1 1.44 Days
Continuous
 
02-Dec-20 07:15 03-Dec-20 17:45 ALTALINK Outage 1082L (63s Red Deer - 287s Hazelwood) maintenance on strs 27, 29, 37 38 1.44 Days
Continuous
 
02-Dec-20 07:15 03-Dec-20 17:45 ALTALINK Outage 925L (63s Red Deer - 74s Janet) maintenance on strs 27, 29, 37, 38 1.44 Days
Continuous
 
02-Dec-20 08:00 03-Dec-20 17:00 ATCO Outage 6L09 (772s Youngstown - 776s Richdale) crossarm and insulator replacements 1.38 Days
Continuous
 
02-Dec-20 08:00 03-Dec-20 16:00 ALTALINK TE 48s Pocaterra RTU/SCADA upgrade RTUs 1.33 Days
Daily
 
02-Dec-20 08:00 03-Dec-20 16:00 ATCO TE 722S Crystal Lake maintenance 1.33 Days
Continuous
 
02-Dec-20 08:30 03-Dec-20 15:30 ALTALINK TE 225S Magrath settings change 31 Hours
Daily
 
02-Dec-20 08:30 03-Dec-20 15:30 ALTALINK TE 618S Riverbend settings change 31 Hours
Daily
 
02-Dec-20 09:00 03-Dec-20 09:00 ATCO Outage 7L95 (715s Leming Lake - 889s Mahkeses) urgent breaker maintenance and tie in bus lockout logic 24 Hours
Continuous
 
03-Dec-20 07:55 03-Dec-20 17:05 ALTALINK RB 893L (103s Goose Lake - 806s Oldman River), 893L (312s Fidler - 806s Oldman River) P5 893L8 install links in guy wire 9.17 Hours
Daily
 
03-Dec-20 08:00 05-Dec-20 16:00 ENMAX Outage 27.2TR (ENMAX 27) NGR installation 2.33 Days
Continuous
 
03-Dec-20 08:00 03-Dec-20 16:00 ENMAX TE 20.82L (ENMAX 20 - ENMAX 21) ENMAX 20 Sub 20.82 L90 settings change 8 Hours
Continuous
 
03-Dec-20 08:00 03-Dec-20 16:00 ENMAX Outage 41.2TR (ENMAX 41) replacement of external control wiring 8 Hours
Continuous
 
03-Dec-20 12:00 03-Dec-20 18:00 MONTANA Outage MATL (120s Picture Butte - Montana) emergency PST outage to investigate & repair oil leak 6 Hours
Continuous
AB-MATL
04-Dec-20 07:00 04-Dec-20 18:00 ALTALINK Outage 776L (308s Albchem Beaverhill Creek - 410s Josephburg) maintenance on structures 84, 89 and 95 11 Hours
Daily
 
04-Dec-20 08:00 04-Dec-20 17:00 ALTALINK RB 503L (268s Whitecourt - 323s Whitecourt Power) require a reclose block for maintenance work on structures 1, 2 and 9 9 Hours
Daily
 
04-Dec-20 08:00 04-Dec-20 16:00 ENMAX Outage 8B138-1A0 (ENMAX 8), 8B138-7A0 (ENMAX 8), 2.84L (ENMAX 2 - ENMAX 8) maintenance on GIS switches 8 Hours
Continuous
 
04-Dec-20 08:00 04-Dec-20 16:00 ENMAX Outage 3.82L (ENMAX 3 - ENMAX 8) crew setting streetlight near line and routine maintenance on line 8 Hours
Continuous
 
04-Dec-20 08:00 04-Dec-20 16:00 ATCO TE 710s Vermilion RTU/SCADA, ATCO Radio Tower perform radio maintenance on the radio carrier facing 710s Vermillion at Mannville tower 8 Hours
Continuous
 
04-Dec-20 08:00 04-Dec-20 18:00 ALTALINK Outage 417L (55s Olds - 281s Johnson) urgent fix broken conductor strands 55s79 10 Hours
Daily
 
04-Dec-20 17:00 04-Dec-20 19:00 ALTALINK TE 89S Ellerslie isolate 240B1 protections for load readings 2 Hours
Daily
 
05-Dec-20 08:00 05-Dec-20 16:00 ENMAX Outage 9.80L (ENMAX 9 - ENMAX 31) SF6 gas sample retest 8 Hours
Continuous
 
05-Dec-20 08:00 05-Dec-20 17:00 ATCO IO 9L938 AltaLink request - require a reclose block for maintenance work on structure 15 9 Hours
Continuous
 
05-Dec-20 08:00 05-Dec-20 17:00 ALTALINK RB 938L (77s Sagitawah - 809s Louise Creek) maintenance work on structure 15 9 Hours
Daily
 
05-Dec-20 08:00 09-Dec-20 20:00 Syncrude Outage Syncrude Mildred Lake operation of circuit breaker 18215 4.5 Days
Continuous
 
05-Dec-20 08:00 05-Dec-20 18:00 ENMAX Outage 2.82L (ENMAX 2 - ENMAX 5) cable sheath test 10 Hours
Continuous
 
05-Dec-20 08:00 05-Dec-20 18:00 ALTALINK IO 2.82L OOS for Enmax cable sheath test 10 Hours
Daily
 
05-Dec-20 08:00 05-Dec-20 16:00 ALTALINK IO 9.80L OOS for Enmax 9B138-9.80 SF6 gas sample retest (Dec 2020) 8 Hours
Daily
 
06-Dec-20 07:00 06-Dec-20 18:00 ALTALINK Outage 452L (367s Harry Smith - 434s Stony Plain) maintenance on structure 7 11 Hours
Daily
 
06-Dec-20 07:15 07-Dec-20 17:45 ALTALINK Outage 1083L (63s Red Deer - 288s Wolf Creek) maintenance on strs 133, 135, 154 1.44 Days
Continuous
 
06-Dec-20 07:30 07-Dec-20 17:30 ALTALINK RB 914L (86s Bigstone - 87s Gaetz) safety requirement; re: 1083L GOI 1.42 Days
Daily
 
06-Dec-20 08:00 06-Dec-20 18:00 ENMAX Outage 2.83L (ENMAX 2 - ENMAX 5 - ENMAX 13) GIS switch maintenance 10 Hours
Continuous
 
06-Dec-20 08:00 06-Dec-20 18:00 ALTALINK IO 2.83(c2s - c13s) OOS for Enmax GIS switch maintenance 2MD138-2.83_2.83G, 2SW2.83G 10 Hours
Daily
 
07-Dec-20 07:00 07-Dec-20 18:00 ALTALINK Outage 780L (38s - 522s) - GOI Maintenance on structures 83, 86 and 87 11 Hours
Daily
 
07-Dec-20 07:00 08-Dec-20 17:00 ALTALINK TE 59s Peigan RTU/SCADA updating configuration to split alarms 1.42 Days
Daily
 
07-Dec-20 07:00 11-Dec-20 17:00 ALTALINK TE 602s Cold Creek RTU/SCADA update RTU configuration for the addition of new alarms 4.42 Days
Daily
 
07-Dec-20 07:00 07-Dec-20 17:00 ALTALINK TE 133s T2 (133s Stelco Edmonton) deficiency cleanup on T2 protections 10 Hours
Daily
 
07-Dec-20 07:00 07-Dec-20 17:00 ALTALINK TE 133s Stelco Edmonton RTU/SCADA update configuration for transformer replacement 10 Hours
Daily
 
07-Dec-20 07:00 10-Dec-20 18:00 ALTALINK TE 56s Boyle RTU/SCADA required for 56s27 circuit switcher replacement to 56s1252 new breaker 3.46 Days
Daily
 
07-Dec-20 07:00 11-Dec-20 17:00 ALTALINK TE 17s Benalto RTU/SCADA update RTU for 17S637 breaker fail/ctrl and move new alarms and controls 4.42 Days
Daily
 
07-Dec-20 07:00 11-Dec-20 17:00 ALTALINK TE 17S Benalto commissioning checks for 17s11 breaker fail replacement 4.42 Days
Daily
 
07-Dec-20 07:00 11-Dec-20 17:00 ALTALINK TE 17s Benalto 138 kV Bus 3 isolate 138kV B3 CT contribution for 17s637 breaker fail upgrade 4.42 Days
Daily
 
07-Dec-20 07:55 07-Dec-20 17:05 ALTALINK RB 631L (186s Dry Creek - 199s East Airdrie) maintenance on str 611L8 9.17 Hours
Daily
 
07-Dec-20 08:00 18-Dec-20 16:00 ENMAX Outage 2.80L (ENMAX 2 - ENMAX 23) breaker overhaul 11.33 Days
Continuous
 
07-Dec-20 08:00 09-Dec-20 16:00 ENMAX Outage 11.83L (162s Beddington - ENMAX 11) RTU & line protection upgrade 2.33 Days
Continuous
 
07-Dec-20 08:00 09-Dec-20 16:00 ENMAX TE 162s 138-RB84 (162s Beddington), 162s 138-RB85 (162s Beddington) upgrade RTU and line protection 2.33 Days
Continuous
 
07-Dec-20 08:00 09-Dec-20 16:00 ENMAX Outage 12.1TR (ENMAX 12) installation NGR 2.33 Days
Continuous
 
07-Dec-20 08:00 10-Dec-20 17:00 ATCO Outage 6L09 (772s Youngstown - 776s Richdale) crossarm and insulator replacements 3.38 Days
Continuous
 
07-Dec-20 08:00 10-Dec-20 16:00 ENMAX Outage 3.82L (ENMAX 3 - ENMAX 8) GIS switch maintenance 3.33 Days
Continuous
 
07-Dec-20 08:00 09-Dec-20 16:00 ALTALINK IO 11.83L OOS Enmax RTU & Line Protection Upgrade. Settings changes. 2.33 Days
Continuous
 
07-Dec-20 08:00 18-Dec-20 17:00 ATCO TE 801S Anderson annual relay maintenance 11.38 Days
Continuous
 
07-Dec-20 08:00 18-Dec-20 17:00 ALTALINK IO 9L933/9L934/9L950 (A801s) ATCO Relays - annual relay maintenance at 801s 11.38 Days
Daily
 
07-Dec-20 08:00 18-Dec-20 16:00 ENMAX Outage 6.82L (ENMAX 6 - ENMAX 41) maintenance 11.33 Days
Continuous
 
07-Dec-20 08:00 08-Dec-20 16:00 ENMAX Outage 14.1TR (ENMAX 14) 14B8-14.1TR breaker racking adjustment 1.33 Days
Continuous
 
07-Dec-20 08:00 07-Dec-20 16:00 ATCO TE 863S Paintearth testing 240kv breaker fail relays 8 Hours
Continuous
 
07-Dec-20 08:00 08-Dec-20 17:00 ATCO TE 767s Oyen RTU/SCADA update RTU and add new alarms 1.38 Days
Continuous
 
07-Dec-20 09:00 11-Dec-20 12:30 ALTALINK Outage 17s637 (637L-Open) - GOI Replace 17s637 breaker fail and control module 4.15 Days
Continuous
 
07-Dec-20 09:00 07-Dec-20 18:00 ALTALINK Outage 611L(186s - 391s) GOI work includes maintenance on structures 8 and 79. 9 Hours
Daily
 
07-Dec-20 09:00 11-Dec-20 17:00 ATCO TE 907S Waddell perform relay preventative maintenance 4.33 Days
Continuous
 
07-Dec-20 09:00 07-Dec-20 18:00 ALTALINK Outage 863L (618s - 863L162A) GOI Asset Management as requested Insulator Bells Resistance testing on 863L Root Cause Investigation Structures Range 79-159 9 Hours
Daily
 
07-Dec-20 09:00 07-Dec-20 18:00 ALTALINK Outage 777L (48s Pocaterra - 245s Seebe) *P5 777L136 Uplift Concerns-Will install Hold Down Arm 9 Hours
Daily
AB-BC
07-Dec-20 09:15 08-Dec-20 16:30 ALTALINK Outage 310p T30 (310p Sundance) move T30 tapchanger indication from old RTU to new RTU 31.25 Hours
Continuous
 
07-Dec-20 09:30 11-Dec-20 17:30 ALTALINK Outage 378s552 Advice Emergency Work; replace breaker fail relay and breaker control module 4.33 Days
Continuous
 
07-Dec-20 09:55 10-Dec-20 17:05 ALTALINK RB 185AL (415s Drywood - 995s Yarrow), 185L (379s Shell Canada Waterton - 415s Drywood) structure replacements 185AL str's range 8-39 3.3 Days
Daily
 
07-Dec-20 10:00 14-Dec-20 15:00 ATCO Outage 7L20 Replacement of under rated and rotten crossarms 7.21 Days
Continuous
 
07-Dec-20 10:00 14-Dec-20 15:00 ATCO RB 7L80 (740s H.R.Milner - 857s Kakwa Ridge), 7L80 (733s Simonette - 857s Kakwaridge) conduct mitigation work on 7L80 7.21 Days
Continuous
 
07-Dec-20 10:00 07-Dec-20 11:00 ATCO TE 2014s Halfway RTU/SCADA, 933s Tower Road RTU/SCADA, ATCO Radio Tower, 718s Parsons Creek RTU/SCADA upgrade SAR firmware to 8.0.R13 60 Mins
Continuous
 
07-Dec-20 10:00 07-Dec-20 11:00 ALTALINK IO Stoney Mtn. Telecom ATCO - Info upgrade SAR firmware to 8.0.R13 60 Mins
Daily
 
07-Dec-20 10:00 11-Dec-20 17:00 ALTALINK TE 378S Shell Caroline standard relay maintenance 4.29 Days
Daily
 
07-Dec-20 10:00 11-Dec-20 17:00 ALTALINK TE 378s Shell Caroline RTU/SCADA update RTU database 4.29 Days
Daily
 
07-Dec-20 10:30 07-Dec-20 16:30 ALTALINK TE 528S Blue Trail Wind Farm relay setting changes at 528s 6 Hours
Daily
 
07-Dec-20 10:30 07-Dec-20 16:30 ALTALINK TE 138S Windy Flats relay setting changes 6 Hours
Daily
 
07-Dec-20 12:00 11-Dec-20 18:00 ALTALINK Outage 730L (285s-730L62)- GOI Component Replacements Complete remaining work Structures Range 64-196 4.25 Days
Continuous
 
07-Dec-20 12:00 07-Dec-20 16:30 ALTALINK TE 612L (336s Fincastle - 368s Burdett), 722L (107s Westfield - 368s Burdett) perform PRC005 maintenance on A21 protection at 368s 4.5 Hours
Daily
 
07-Dec-20 12:30 07-Dec-20 16:30 ALTALINK TE 510s Sunnybrook RTU/SCADA investigate loss of communication issue 4 Hours
Daily
 
07-Dec-20 12:30 07-Dec-20 16:30 ALTALINK TE 1012s Deer Hill perform PRC005 relay maintenance on B138B1 87/138B1 MFAC34 4 Hours
Daily
 
08-Dec-20 07:00 09-Dec-20 18:00 ALTALINK Outage 901L (63s Red Deer - 901AL), 901L (74s Janet - 901AL), 901AL (64s East Crossfield - 901L) maintenance on strs 26, 28, 36 and 37 1.46 Days
Continuous
 
08-Dec-20 07:00 09-Dec-20 17:00 ALTALINK TE 799s Coleman RTU/SCADA update configuration to split alarms 1.42 Days
Daily
 
08-Dec-20 07:00 08-Dec-20 16:00 ALTALINK Outage 993s T1 (993s Abee) connecting new 993s T2 9 Hours
Daily
 
08-Dec-20 07:00 08-Dec-20 17:00 ALTALINK TE 602s T1 (602s Cold Creek) A & B protections will be coming out of service to update settings and install maintenance switch 10 Hours
Daily
 
08-Dec-20 07:00 09-Dec-20 18:00 ALTALINK Outage 56s Boyle 138 kV Bus 2, 710L (56s Boyle - 159s Colinton), 56s 652 (56s Boyle), 56s C1 (56s Boyle), 56s T2 (56s Boyle) replace 56s27 Circuit Switcher - with new 56s1252 SF6 Breaker & 56s28 Switch 1.46 Days
Continuous
 
08-Dec-20 07:00 08-Dec-20 16:00 ATCO RB 7L437 (947s Weasel Creek - 993s Abee) AltaLink requested - reclosing off on 7L437 @ 947S Weasel Creek to connect the new 993s T2 9 Hours
Continuous
 
08-Dec-20 08:00 08-Dec-20 17:00 ALTALINK TE 337s Canada Liquidair RTU/SCADA radio troubleshooting 9 Hours
Daily
 
08-Dec-20 08:00 10-Dec-20 16:30 ALTALINK TE 310P Sundance maintenance on PMU and relays 2.35 Days
Daily
 
08-Dec-20 08:00 09-Dec-20 17:30 ATCO IO AltaLink AltaLink General Communication Work, 898S 9L930 Protection Relay, 2049S 9L990 Protection Relay AltaLink Comm work affects 9L930 & 9L990 A&B Teleprotection and potentially a number of AltaLink substation SCADA Sites.

9932R ATCO Chard - 72s Radio - TPR/RTU
Ref #: 272525
Dates: Dec 9 @ 08:00 – Dec 10 @ 17:30
Scope: Radio replacement. Loss of visibility of a number of sites
for the duration. Clean up 72s RTU configuration on Oct 5.

Comments/Scope Clarification:
On Oct 5 @ 08:00 – 17:00 = 72s RTU configuration update – needs to be done prior to radio outage. 2 or 3 short (15 minute) outages in the timeframe listed.
On Oct 6 @ 08:00 – Oct 7 @ 17:30 – Radio replacement.
Loss of 9L930 & 9L990 A&B TPR for the duration. Stability study completed.
AltaLink is looking at re-routing the affected sites, but if the re-route is not successful (bandwidth issue) there is a possibility that the following sites will lose visibility for the duration.
72s Leismer, 762s Conklin, 539s Sunday Creek, 167s Ipiatik, 183s Underwood, 170s Pike, 154s Black Spruce, 698s Jackfish, 651s Kirby, 818s Winefred, 723s Christina Lake, 852s Roundhill.
Priority will be given to 762s, 539s, 72s if the bandwidth issue arises.
Arrangements made with 539s and 762s to go to manual reporting if the bandwidth issue arises.
There is also a setting change on 7L114 required.

72s Relays
Ref #: 272529
Dates: Dec 9 @ 08:00 – Dec 10 @ 17:30
Scope: Radio replacement on 9932R – 72s. Setting change on 7L114. Redundant protections one at a time.
1.4 Days
Continuous
 
08-Dec-20 08:00 09-Dec-20 17:00 ALTALINK TE 9932R ATCO Chard - 72s Radio - TPR/RTU Radio replacement. Loss of visibility of a number of sites for the duration. Loss of TPR on 9L930 & 9L990 1.38 Days
Continuous
 
08-Dec-20 08:00 13-Dec-20 16:00 ENMAX Outage 21.61L (ENMAX 21 - ENMAX 34) 34.2TR & 34.3TR replacement-grounding study 5.33 Days
Continuous
 
08-Dec-20 08:30 08-Dec-20 16:30 ALTALINK TE 759L (87s Gaetz - 276s Prentiss) TPR maintenance 8 Hours
Daily
 
08-Dec-20 08:30 08-Dec-20 16:00 ALTALINK TE 447s Enchant RTU/SCADA SCADA updates for Qualitrol & winding temperature trips being removed, correct the HMI,RTU & ACC for the non electrical trip alarm changes 7.5 Hours
Daily
 
08-Dec-20 09:00 18-Dec-20 17:00 BCH Outage 1L274 (48s Pocaterra - Britt Creek) structure refurbishment 10.33 Days
Continuous
AB-BC
08-Dec-20 09:00 19-Dec-20 17:00 ALTALINK IO 48s38 (887L) Advice for BCH Structure refurbishment - BC Hydro 11.33 Days
Continuous
 
08-Dec-20 09:00 08-Dec-20 17:00 ALTALINK RB 1046L (310p Sundance - 338s Cherhill) tighten guy wire on 1046L108 8 Hours
Daily
 
08-Dec-20 09:30 08-Dec-20 16:30 ALTALINK Outage 58s 35 (58s Edson), 58s C1 (58s Edson) SPRC5 test breaker 7 Hours
Daily
 
08-Dec-20 10:00 08-Dec-20 11:00 ATCO TE 732S Mitsue, 809S Louise Creek, 738s Virginia Hills RTU/SCADA, ATCO Radio Tower Telecom SAR Firmware upgrade to 8.0.R13 60 Mins
Continuous
 
08-Dec-20 10:00 08-Dec-20 11:00 ALTALINK IO Virginia Hills Telecom ATCO - Info Telecom SAR firmware upgrade to 8.0.R13 60 Mins
Daily
 
08-Dec-20 11:00 09-Dec-20 18:00 ENMAX Outage 2.80L (ENMAX 2 - ENMAX 23), 23.3TR (ENMAX 23) fall substation washing 31 Hours
Continuous
 
08-Dec-20 12:30 08-Dec-20 14:30 ALTALINK IO 634S Shell Raven River site inspection & IR scan 2 Hours
Daily
 
09-Dec-20 07:00 09-Dec-20 18:00 ATCO IO 789L AltaLink Request - They will be working on 789L and require ATCO to Open 704A @898S and block reclosing 788L and 789L as well 11 Hours
Continuous
 
09-Dec-20 07:00 09-Dec-20 17:00 ALTALINK TE 602s T2 (602s Cold Creek) update settings 10 Hours
Daily
 
09-Dec-20 07:00 09-Dec-20 18:00 ALTALINK Outage 789L (898s Heart Lake - 1034s Margie) maintenance work on Str 185 11 Hours
Daily
 
09-Dec-20 07:15 09-Dec-20 16:45 ALTALINK Outage 58L (32s Barrier - 245s Seebe) fix PLC cabinet safety issue 9.5 Hours
Daily
 
09-Dec-20 08:00 09-Dec-20 16:00 ALTALINK Outage 69s T2 (69s North Barrhead) T2 tap change and testing 8 Hours
Daily
 
09-Dec-20 08:00 10-Dec-20 17:00 ALTALINK TE 72S Leismer radio replacement 9932R 1.38 Days
Continuous
 
09-Dec-20 08:00 09-Dec-20 20:00 ALTALINK TE AltaLink Radio Tower, 245s Seebe RTU/SCADA 9286R - cutover to new radios 12 Hours
Daily
 
09-Dec-20 08:00 09-Dec-20 11:00 ALTALINK TE AltaLink Radio Tower 9286R - 9273R troubleshoot low RSL levels for 9286R to 9273R radio 3 Hours
Daily
 
09-Dec-20 08:00 09-Dec-20 11:00 ALTALINK TE T793s Horse Creek RTU/SCADA, AltaLink Radio Tower troubleshoot low RSL levels 3 Hours
Daily
 
09-Dec-20 08:00 09-Dec-20 16:30 ALTALINK TE 191s N.W.Cardiff RTU/SCADA SCADA updates for qualitrol & winding temp trips being removed 8.5 Hours
Daily
 
09-Dec-20 08:00 10-Dec-20 16:00 ENMAX Outage 14.2TR (ENMAX 14) 14B8-14.2TR breaker racking adjustment and oil sampling TC 1.33 Days
Continuous
 
09-Dec-20 09:15 10-Dec-20 16:30 ALTALINK Outage 310p T36 (310p Sundance) move T36 tapchanger indication from old RTU to new RTU 31.25 Hours
Continuous
 
09-Dec-20 10:00 09-Dec-20 11:00 ATCO, ALTALINK TE ATCO Radio Tower, 7L760 (767s Oyen - 7L760D2), 772s Youngstown RTU/SCADA, 914s Bindloss RTU/SCADA telecom SAR firmware upgrade to 8.0.R13 60 Mins
Continuous
 
09-Dec-20 10:00 09-Dec-20 11:00 ALTALINK IO Pollockville Telecom ATCO - Info Telecom SAR firmware upgrade to 8.0.R13 60 Mins
Daily
 
09-Dec-20 11:00 09-Dec-20 15:00 ALTALINK Outage 250p 11 (250p Bighorn Plant) maintenance 4 Hours
Continuous
 
09-Dec-20 11:00 09-Dec-20 13:00 ALTALINK TE 56S Boyle perform functional trip testing to 56s1252 2 Hours
Daily
 
09-Dec-20 12:30 09-Dec-20 16:00 ALTALINK TE 163S Amoco Empress test the relay 760LN B21/L1 URD60 3.5 Hours
Daily
 
10-Dec-20 07:00 10-Dec-20 18:00 ALTALINK Outage 897L (38s East Edmonton - 45s Bretona) fire mitigation on structures #57, 83 & 96 11 Hours
Daily
 
10-Dec-20 07:00 11-Dec-20 17:00 ALTALINK TE 525s Carseland RTU/SCADA update config for new alarms 1.42 Days
Daily
 
10-Dec-20 07:15 10-Dec-20 17:45 ALTALINK Outage 180L (15s Fort Macleod - 928s East Stavely) maintenance on Str 540 10.5 Hours
Daily
 
10-Dec-20 07:30 10-Dec-20 17:30 ATCO Outage 2075s ACF22 (2075s Newell) repair structural towers supporting ACF22 capacitor banks 10 Hours
Continuous
 
10-Dec-20 07:30 10-Dec-20 17:30 ALTALINK RB 780L (38s East Edmonton - 522s Cooking Lake) crews working on common structure #897L57/780L57 10 Hours
Daily
 
10-Dec-20 08:00 10-Dec-20 16:00 ENMAX Outage 1.80L (ENMAX 1 - ENMAX 28) conductor scanning on circuit 8 Hours
Continuous
 
10-Dec-20 08:00 10-Dec-20 17:00 ALTALINK IO 993S Abee telecom site inspection 9 Hours
Daily
 
10-Dec-20 08:00 10-Dec-20 17:00 ALTALINK TE 337s Canada Liquidair RTU/SCADA repair radio 9 Hours
Daily
 
10-Dec-20 08:30 10-Dec-20 16:00 EPCOR Outage K722 (Kennedale) substation switching school isolation 7.5 Hours
Continuous
 
10-Dec-20 08:30 10-Dec-20 16:30 ALTALINK TE 197S Bardo UR card replacement 8 Hours
Daily
 
10-Dec-20 09:00 10-Dec-20 13:00 ALTALINK Outage 250p 22 (250p Bighorn Plant) maintenance 4 Hours
Continuous
 
10-Dec-20 10:00 10-Dec-20 12:00 ALTALINK Outage 17s 91 (17s Benalto) trip test 17s92 from new s637 breaker fail 2 Hours
Daily
 
10-Dec-20 10:00 10-Dec-20 11:00 ATCO, SHELL TE 9L57 (939s Livock - 960s Birchwood Creek), 7L71 (848s Ruth Lake - 2082s Dog Rib), 847s Muskeg River RTU/SCADA, 920s Jackpine RTU/SCADA, 919s Hartley RTU/SCADA, 2082s Dog Rib RTU/SCADA, 888s Dover RTU/SCADA, 960s Birchwood Creek RTU/SCADA, 2015s YEO RTU/SCADA Dover Telecom firmware upgrade 60 Mins
Continuous
 
10-Dec-20 10:00 10-Dec-20 11:00 ALTALINK IO Dover Telecom ATCO - Info telecom SAR firmware upgrade to 8.0.R13 60 Mins
Daily
 
10-Dec-20 14:00 10-Dec-20 15:00 ENMAX IO ENMAX 8 transfer station service load to preferred source 60 Mins
Continuous
 
10-Dec-20 14:00 10-Dec-20 17:00 ALTALINK IO 412S Shell Eagle Creek site inspection & IR scan 3 Hours
Daily
 
11-Dec-20 07:30 11-Dec-20 17:30 ATCO Outage 2075s ACF12 (2075s Newell) repair structural towers supporting ACF12 capacitor banks 10 Hours
Continuous
 
11-Dec-20 08:00 11-Dec-20 16:00 TRANSCANADAP TE 903S Loyalist test 87T/701T & 50BF/701 protection relays 8 Hours
Continuous
 
11-Dec-20 08:00 11-Dec-20 16:00 ENMAX, ALTALINK Outage 21.80L (42s Sarcee - ENMAX 21) conductor scanning on circuit 8 Hours
Continuous
 
11-Dec-20 08:00 11-Dec-20 16:00 ALTALINK Outage 42s21 (21.80L) Advice for Enmax conductor scanning on circuit 8 Hours
Daily
 
11-Dec-20 08:00 11-Dec-20 17:00 ALTALINK TE 71S Lamoureux 71s 452 -settings changes of sync check and testing of GE C60 relay 9 Hours
Daily
 
11-Dec-20 08:00 18-Dec-20 18:00 ATCO IO AltaLink SE AltaLink outage AltaLink emergency outages that may affect EATL dispatch on next contingency 7.42 Days
Continuous
 
11-Dec-20 08:00 13-Dec-20 18:00 ALTALINK RB 1206L (12s Heartland - 89s Ellerslie) safety concern - common tower with 1212L 2.42 Days
Continuous
 
11-Dec-20 08:00 13-Dec-20 18:00 ALTALINK Outage 1212L (12s Heartland - 89s Ellerslie) urgent repair - reposition dampers 2.42 Days
Continuous
 
11-Dec-20 08:00 11-Dec-20 16:00 ENMAX Outage 34.2TR (ENMAX 34) rack in new ground buggy 8 Hours
Continuous
 

Prepared On:   2020-12-02   2:44:26 PM

This document and the information contained herein are based upon information and data which by their nature contain a degree of uncertainty and are subject to change. In addition, this document may contain information and data from public sources and/or third parties, which have been assumed to be accurate and complete and have not been verified. Accordingly, the Independent System Operator, operating as the Alberta Electric System Operator (the "AESO") makes no warranty, representation or guarantee, express or implied, with respect to this document or the information contained herein, including, but not limited to, any warranty, representation or guarantee of accuracy, completeness, timeliness, reliability, availability, absence of computer virus, non- infringement, merchantability or suitability for any purpose. Under no circumstances will the AESO, its members, officers, employees, contractors or agents, or any of their respective affiliates, be liable for any errors or omissions in, or any losses, damages or claims whatsoever, whether in contract, tort or otherwise, arising from use of or reliance upon, this document or any information contained herein.

© 2009 Alberta Electric System Operator. All rights reserved