| Alberta Electric System Operator | |
| System Co-ordination Plan | |
| 2026-11-26 to 2026-12-04 | |
| Approved Outages |
| Previous Version | |
| Download CSV |
| From | To | Owner | Type | Element | Scheduled Activity | Date/Time Comments | Interconnection |
|---|---|---|---|---|---|---|---|
| 26-Jul-24 10:00 | 30-Jun-27 16:00 | ATCO | Outage | 826s 504R (826s Marguerite Lake) | emergency removal to replace failed 502R @834S | 25,662 Hours
Continuous |
|
| 27-Nov-25 08:30 | 27-Nov-27 17:30 | ALTALINK | TE | 89s Protection & Control (89s Ellerslie) | DSP card replacements on1057L B87/L3 and B240B1 B87/240B1 | 17,528 Hours
Daily |
|
| 10-Mar-26 10:00 | 30-Nov-26 18:00 | ATCO | TE | 743s RTU/SCADA (743s Sarah Lake) | throughout the course of the project, different apparatus are being replaced, RTU will be blocked prior to download | 6,368 Hours
Continuous |
|
| 01-May-26 17:00 | 19-Feb-27 18:00 | EPCOR | Outage | T1 (Meadowlark) | T1 LCR civil work | 4,993 Hours
Continuous |
|
| 04-Jun-26 07:01 | 10-Feb-27 18:00 | EPCOR | Outage | T1 (Rossdale) | rossdale: TX1 lcr civil | 6,034.98 Hours
Continuous |
|
| 07-Jun-26 17:05 | 31-Mar-27 18:00 | ACCIONA, ENBRIDGE, ICPCL | Outage | 139s C1 (139s Hillridge) | forced outage | 7,128.92 Hours
Continuous |
|
| 08-Jun-26 07:00 | 15-Jan-27 18:00 | EPCOR | TE | EP 511s Protection & Control (EP 511s Victoria) | 72kV breaker fail protection blocking | 2,626 Hours
Continuous |
|
| 15-Jun-26 07:00 | 19-Mar-27 17:00 | EPCOR | TE | 805s Protection & Control (805s Jasper) | protection blocking, breaker replacement project | 1,954 Hours
Continuous |
|
| 19-Jun-26 17:00 | 01-May-27 17:00 | EPCOR | Outage | EP 511s Victoria T3 (EP 511s Victoria) | emergency outage due to degraded asset condition | 12,769 Hours
Continuous |
|
| 20-Jul-26 07:00 | 31-Dec-26 18:00 | EPCOR | TE | Protection & Control (Woodcroft) | woodcroft: protection blocking for TX1 LCR, line protection testing, and repairs | 3,947 Hours
Continuous |
|
| 08-Sep-26 07:00 | 18-Dec-26 18:00 | EPCOR | TE | EP 803s Protection & Control (EP 803s Lambton) | protection blocking, DFR upgrade cutovers and commissioning | 2,435 Hours
Continuous |
|
| 12-Sep-26 08:00 | 08-Dec-26 17:00 | SUNCOR | Outage | 29EDD-18 29PT-100 (29EDD-18 Firebag) | replace secondary cables on 29PT-100 | 1,833 Hours
Continuous |
|
| 14-Sep-26 08:00 | 17-Dec-26 18:00 | ATCO | TE | 738s RTU/SCADA (738s Virginia Hills), 738s Protection & Control (738s Virginia Hills) | SCADA/protection upgrade at 738s Virginia Hills, cut over to the new SCADA system and tested | 2,266 Hours
Continuous |
|
| 14-Sep-26 21:53 | 31-Dec-26 23:59 | NWE | Outage | 2375 (NWE Marias) | breaker hydraulic oil pump repeatedly | 2,595.1 Hours
Continuous |
AB-MATL |
| 21-Sep-26 10:00 | 27-Nov-26 14:00 | ATCO | Outage | 706s 701T (706s Irish Creek), 706s 701 (706s Irish Creek) | breaker, transformer and voltage regulator maintenance | 268 Hours
Continuous |
|
| 28-Sep-26 07:00 | 31-Dec-26 18:00 | EPCOR | Outage | 816s T1 (816s Petrolia) | emergency outage - tap changer gassing | 2,267 Hours
Continuous |
|
| 30-Sep-26 08:00 | 02-Feb-27 16:00 | SUNCOR | TE | 29EDD-1 Protection & Control (29EDD-1 Millennium) | 29EDD-1 - 29PL9-17 - Line protection Relay A87L ABB RED-670 is being isolated due to the "A PROT TRBL" Alarm | 3,008 Hours
Continuous |
|
| 05-Oct-26 08:00 | 28-Nov-26 20:00 | ALTALINK | Outage | 62s T2 (62s Brazeau Plant), 62s 2 (62s Brazeau Plant) | maintenance | 1,295 Hours
Continuous |
|
| 06-Oct-26 08:00 | 27-Nov-26 17:00 | ALTALINK | Outage | 431s C1 (431s Hussar) | urgent 431sC1 trouble investigation and repair | 1,257 Hours
Continuous |
|
| 13-Oct-26 09:00 | 18-Dec-26 19:00 | ALTALINK | Outage | 799L (235s Entwistle - 443s South Mayerthorpe), 235s 799N (235s Entwistle) | rebuild structure and restring OPGW | 1,594 Hours
Continuous |
|
| 21-Oct-26 12:00 | 30-Nov-26 17:00 | ALTALINK, Lethbridge | RB | 725LW (674s Bowron - 725BL tap), 725LE (674s Bowron - 725AL tap) | ongoing CVT issue and the transient voltages observed at the relays (forced) | 965 Hours
Continuous |
|
| 22-Oct-26 13:00 | 31-Dec-27 18:00 | ALTALINK, Keyera Cynthia | Outage | 359s T2 (359s Esso West Pembina), 359s 14 (359s Esso West Pembina) | T2 maintenance | 10,445 Hours
Continuous |
|
| 26-Oct-26 04:00 | 11-Dec-26 18:00 | EPCOR | Outage | 814s T2 (814s Bellamy), BR722 (Rossdale), 814s B2402 (814s Bellamy), 814s B2406 (814s Bellamy), R721 (Rossdale), RR723 (Rossdale), 814s BAB2 (814s Bellamy) | Bellamy: TX2 emergency bushing replacement and rossdale TX1 installation | 1,283 Hours
Continuous |
|
| 26-Oct-26 07:00 | 27-Nov-26 17:00 | EPCOR | Outage | 805s T3 (805s Jasper), EP 805s J2404 (EP 805s Jasper), EP 805s J2405 (EP 805s Jasper), EP 805s JAB3 (EP 805s Jasper) | Jasper: J2404/JAB3/JDS9 replacement LCR | 1,283 Hours
Continuous |
|
| 29-Oct-26 00:00 | 19-Dec-26 15:00 | ALTALINK | Outage | 1182s C1 (1182s Berland River) | 1182s Berland River capacitor C1 forced outage | 1,239 Hours
Continuous |
|
| 02-Nov-26 09:00 | 27-Nov-26 17:00 | ALTALINK | TE | 163s Protection & Control (163s Amoco Empress) | ACC visibility upgrade | 608 Hours
Daily |
|
| 02-Nov-26 09:00 | 27-Nov-26 17:00 | ALTALINK | TE | 562s Protection & Control (562s Cypress) | 669L and 1011L protection outages required for ACC visibility upgrades and alarm splitting | 608 Hours
Daily |
|
| 02-Nov-26 09:00 | 27-Nov-26 17:00 | ALTALINK | TE | 163s Protection & Control (163s Amoco Empress) | ACC visibility upgrade | 608 Hours
Daily |
|
| 02-Nov-26 09:00 | 27-Nov-26 17:00 | ALTALINK | TE | 394s Protection & Control (394s Empress) | 760LN L2 protection outages required for ACC visibility upgrades and alarm splitting at 163s | 608 Hours
Daily |
|
| 02-Nov-26 11:00 | 18-Dec-26 19:00 | ATCO | TE | 948s RTU/SCADA (948s Heatburg), 948s Protection & Control (948s Heatburg) | automation upgrade/relay firmware to at 948S Heatburg, | 1,112 Hours
Continuous |
|
| 04-Nov-26 08:00 | 04-Dec-26 18:00 | EPCOR | Outage | 72JM18 (EP 805s Jasper - Meadowlark), M721 (Meadowlark), M722 (Meadowlark), EP 805s J722 (EP 805s Jasper), MAB1 (Meadowlark) | JM18/meadowlark: meadowlark TX1 Zone, TX delivery and build | 730 Hours
Continuous |
|
| 08-Nov-26 13:00 | 04-Dec-26 19:00 | ENMAX | Outage | 8.5TR (SS-8) | fire alarm system upgrade | 630 Hours
Continuous |
|
| 09-Nov-26 08:00 | 11-Dec-26 18:00 | EPCOR | Outage | PM2405 (Poundmaker) | replace: P2405 breaker | 778 Hours
Continuous |
|
| 09-Nov-26 09:00 | 04-Dec-26 17:00 | ALTALINK | TE | 199s Protection & Control (199s East Airdrie) | protection outages - circuit cutovers and testing associated with Balzac RAS upgrades project | 608 Hours
Daily |
|
| 09-Nov-26 09:00 | 04-Dec-26 17:00 | ALTALINK | TE | 391s RTU/SCADA (391s Balzac) | SCADA configuration updates for Balzac RAS upgrades | 608 Hours
Daily |
|
| 09-Nov-26 09:00 | 04-Dec-26 17:00 | ALTALINK | TE | 64s Protection & Control (64s East Crossfield) | Balzac RAS upgrades project - 752L protection outages for circuit cutovers and testing | 608 Hours
Daily |
|
| 10-Nov-26 00:01 | 29-Jan-27 11:59 | ENMAX | TE | SS-162 PMU (SS-162 Beddington) | PMU outage for replacement | 1,931.97 Hours
Continuous |
|
| 10-Nov-26 20:00 | 31-Mar-27 20:00 | SUNCOR | IO | Unmodeled Transmission Facility (Suncor) | station service transformer is un-modeled | 3,384 Hours
Continuous |
|
| 16-Nov-26 07:00 | 18-Dec-26 17:00 | EPCOR | TE | Protection & Control (EPCOR Riverview) | relay maintenance | 778 Hours
Continuous |
|
| 16-Nov-26 08:00 | 06-Aug-27 17:00 | EPCOR | Outage | T2 (Woodcroft) | Woodcroft - TX2 LCR civil construction | 6,321 Hours
Continuous |
|
| 16-Nov-26 08:00 | 11-Dec-26 18:00 | EPCOR | Outage | 72NW15 (Namao - Woodcroft), T2 (Woodcroft), W725 (Woodcroft), W723 (Woodcroft), N726 (Namao) | Woodcroft TX2 Zone TX LCR demolition | 610 Hours
Continuous |
|
| 16-Nov-26 09:00 | 04-Dec-26 17:00 | ALTALINK | TE | 64s RTU/SCADA (64s East Crossfield) | SCADA configuration updates for Balzac RAS upgrades project | 440 Hours
Daily |
|
| 16-Nov-26 09:00 | 04-Dec-26 17:00 | ALTALINK | TE | 199s RTU/SCADA (199s East Airdrie) | SCADA updates for Balzac RAS upgrades project | 440 Hours
Daily |
|
| 16-Nov-26 10:00 | 27-Nov-26 18:00 | ATCO | TE | 2029s Protection & Control (2029s Heathfield) | complete the EN100 firmware update on ACF back up and aux SST protection relays | 272 Hours
Continuous |
|
| 19-Nov-26 08:00 | 27-Nov-26 18:00 | ALTALINK, ATCO | Outage | 234s Fort Assiniboine, 234s T1 (234s Fort Assiniboine), 234s T2 (234s Fort Assiniboine), 7L230 (743s Sarah Lake - 888AL tap), 7L230 (69s North Barrhead - 888AL tap), 888AL (234s Fort Assiniboine - 7L230 tap), 743s 703 (743s Sarah Lake), 69s 230W (69s North Barrhead), 234s 888 (234s Fort Assiniboine), 743s 7L230D1 (743s Sarah Lake) | replace 7L230D1 disconnect switch | 202 Hours
Continuous |
|
| 19-Nov-26 08:00 | 27-Nov-26 18:00 | ALTALINK, ATCO | IO | 7L230 (69s North Barrhead - 888AL tap), 888AL (234s Fort Assiniboine - 7L230 tap), 7L230 (743s Sarah Lake - 888AL tap) | replace 7L230D1 disconnect switch | 202 Hours
Continuous |
|
| 19-Nov-26 08:00 | 26-Nov-26 16:00 | ENMAX, ALTALINK | Outage | 24.83L (74s Janet - SS-24), 74s 24.83X (74s Janet) | steel pole installation | 176 Hours
Continuous |
|
| 19-Nov-26 08:00 | 26-Nov-26 16:00 | ENMAX, ALTALINK | IO | 24.83L (74s Janet - SS-24), 74s 24.83X (74s Janet) | Enmax steel pole installation | 176 Hours
Continuous |
|
| 21-Nov-26 08:00 | 31-Dec-30 17:00 | ATCO | Outage | 848s 402R (848s Ruth Lake) | forced - reactor failed and will be replaced during substation rebuild | 36,033 Hours
Continuous |
|
| 21-Nov-26 17:00 | 28-Nov-26 17:00 | ALTALINK, EPCOR | RB | 921L (71s Lamoureux - 987s Clover Bar) | Altalink work - recloser block 921L | 168 Hours
Continuous |
|
| 21-Nov-26 18:00 | 28-Nov-26 19:00 | ALTALINK, EPCOR | Outage | 71s 240kV West Bus (71s Lamoureux), 920L (71s Lamoureux - 557s Castle Downs), 71s T1 (71s Lamoureux), 71s 1252 (71s Lamoureux), 71s 1552 (71s Lamoureux), 71s 1652 (71s Lamoureux) | installing new foundation | 169 Hours
Continuous |
|
| 21-Nov-26 18:00 | 28-Nov-26 19:00 | ALTALINK, EPCOR | IO | 920L (71s Lamoureux - 557s Castle Downs) | Altalink request 26-14117 - isolate 920L (71s Lamoureux - 557s Castle Downs) | 169 Hours
Continuous |
|
| 22-Nov-26 08:30 | 28-Nov-26 18:00 | ALTALINK, EPCOR | RB | 921L (71s Lamoureux - 987s Clover Bar) | building new foundations | 153.5 Hours
Continuous |
|
| 23-Nov-26 07:00 | 27-Nov-26 17:00 | EPCOR | TE | 330p Protection & Control (330p Genesee) | protection blocking, transformer (12TC2) protection configuration changes | 106 Hours
Continuous |
|
| 23-Nov-26 08:00 | 07-Dec-26 16:00 | ATCO | TE | 738s Protection & Control (738s Virginia Hills) | block existing TX A and B protection, demo old 1K TX panel | 344 Hours
Continuous |
|
| 23-Nov-26 08:00 | 27-Nov-26 18:00 | ALTALINK, EPCOR | Outage | 1058L (657s Summerside - EP 803s Lambton), EP 803s L2403 (EP 803s Lambton), EP 803s L2404 (EP 803s Lambton) | 1058L: Lambton, DFR cutovers and commissioning | 106 Hours
Continuous |
|
| 23-Nov-26 08:00 | 26-Nov-26 16:00 | ALTALINK | TE | 89s Protection & Control (89s Ellerslie) | PRC maintenance | 80 Hours
Daily |
|
| 23-Nov-26 08:00 | 27-Nov-26 16:00 | ALTALINK | TE | 71s RTU/SCADA (71s Lamoureux) | RTU database update | 104 Hours
Daily |
|
| 23-Nov-26 08:00 | 18-Dec-26 16:00 | ENMAX | Outage | 38.3TR (SS-38) | B protection relay replacement, NGR install | 608 Hours
Continuous |
|
| 23-Nov-26 08:00 | 26-Nov-26 16:00 | ALTALINK | TE | 500s RTU/SCADA (500s Flatbush) | RTU configuration updates required for demo of T2 and associated P&C equipment | 80 Hours
Daily |
|
| 23-Nov-26 09:00 | 02-Dec-26 20:00 | ATCO | Outage | 7L16 (766s Nevis - 948s Heatburg), 766s 702 (766s Nevis), 948s 703 (948s Heatburg) | install interphase spacers
|
227 Hours
Continuous |
|
| 23-Nov-26 09:00 | 26-Nov-26 17:00 | ALTALINK | TE | 650s RTU/SCADA (650s Hansman Lake) | RTU database update | 80 Hours
Daily |
|
| 23-Nov-26 09:00 | 26-Nov-26 17:00 | ALTALINK | TE | 28s RTU/SCADA (28s West Brooks) | RTU outage for DDR1 replacement | 80 Hours
Daily |
|
| 23-Nov-26 09:00 | 27-Nov-26 17:00 | ALTALINK | TE | 237s RTU/SCADA (237s Foothills) | RTU outage to add SCADA points for fault reporting and test new SCADA points | 104 Hours
Daily |
|
| 23-Nov-26 09:00 | 04-Dec-26 15:00 | CMH | TE | MH-50L (MHS-2 North Industrial - MHS-5 NE Crescent Heights) | maintenance on the relay LDR-50L-A | 270 Hours
Continuous |
|
| 23-Nov-26 09:00 | 27-Nov-26 19:00 | ATCO | TE | 2075s Protection & Control (2075s Newell) | complete the EN100 firmware upgrade for the converter transformer protection, 900SST1, 900SST2, and aux station service transformer protection relays | 106 Hours
Continuous |
|
| 23-Nov-26 09:00 | 04-Dec-26 17:00 | ENMAX, ALTALINK | TE | 653s RTU/SCADA (653s Summit) | SCADA configuration updates for Balzac RAS upgrades project | 272 Hours
Daily |
|
| 23-Nov-26 09:00 | 27-Nov-26 17:00 | ALTALINK | TE | 163s RTU/SCADA (163s Amoco Empress) | SCADA configuration updates for ACC visibility scope | 104 Hours
Daily |
|
| 23-Nov-26 09:00 | 04-Dec-26 17:00 | ENMAX, ALTALINK | TE | 653s Protection & Control (653s Summit) | 688L protection outages for circuit cutovers and testing associated with Balzac RAS upgrades project | 272 Hours
Daily |
|
| 23-Nov-26 09:00 | 04-Dec-26 17:00 | ALTALINK | TE | 391s Protection & Control (391s Balzac) | protection outages for circuit cutovers and testing associated with Balzac RAS upgrades project | 272 Hours
Daily |
|
| 23-Nov-26 10:00 | 30-Nov-26 16:00 | ATCO | Outage | 7L56 (738s Virginia Hills - 809s Louise Creek), 738s 7L56D6 (738s Virginia Hills), 809s 707 (809s Louise Creek) | protection cutover to new building | 174 Hours
Continuous |
|
| 23-Nov-26 10:00 | 27-Nov-26 18:00 | ALTALINK | TE | 237s Protection & Control (237s Foothills) | implement fault reporting on 434L (L1), 646L (L4) 138 kV, 1037L (L16), 1037L (L16), 1038L (L18), 1038L (L18), 1107L (L17) , 1106L (L15) | 104 Hours
Daily |
|
| 23-Nov-26 10:00 | 27-Nov-26 17:00 | ATCO | TE | ATCO Telecom Equipment | remove existing link from 1888A Dover to 1848 Ruth lake | 103 Hours
Continuous |
|
| 23-Nov-26 11:00 | 28-Nov-26 10:00 | ATCO | Outage | 7L38 (875s Algar - 917s Horse River), 875s 701 (875s Algar), 917s 704 (917s Horse River) | line to ground clearance mitigation | 119 Hours
Continuous |
|
| 23-Nov-26 11:00 | 04-Dec-26 17:00 | ATCO | Outage | 7L48 (794s Valleyview - 7LA48 tap), 794s 703 (794s Valleyview) | changing rotten poles and crossarms | 270 Hours
Continuous |
|
| 23-Nov-26 13:00 | 26-Nov-26 19:00 | ALTALINK | RB | 801L (294s Brazeau Outlet Works - 801AL tap), 801L (358s Amoco Brazeau - 801AL tap), 801AL (445s Elk River - 801L tap), 801L (62s Brazeau Plant - 294s Brazeau Plant Outlet Works) | live line maintenance | 78 Hours
Daily |
|
| 23-Nov-26 14:00 | 11-Dec-26 14:00 | ATCO | Outage | 930s SVC (930s Arcenciel) | Arcenciel SVC upgrade
|
432 Hours
Continuous |
|
| 23-Nov-26 14:00 | 11-Dec-26 14:00 | ATCO | TE | 930s RTU/SCADA (930s Arcenciel) | in conjunction with 930s SVC outage, DFR upgrade will be implementing streaming to AESO | 432 Hours
Continuous |
|
| 24-Nov-26 08:00 | 27-Nov-26 18:00 | ALTALINK | RB | 726L (37s North Calder - 71s Lamoureux) | installing new foundations | 82 Hours
Daily |
|
| 24-Nov-26 09:00 | 07-Dec-26 17:00 | Syncrude | Outage | AL-2 (Aurora - D05 Syncrude), D05 511 (D05), D05 512 (D05), 222 (Aurora), 223 (Aurora), D05 514 (D05), 223A (Aurora), 222B (Aurora), 89-225 (Aurora), D05 511A (D05), D05 512B (D05) | substation - zone 4 (AL-2) PM | 296 Hours
Continuous |
|
| 25-Nov-26 08:00 | 07-Dec-26 16:00 | ENMAX | Outage | 6.80L (SS-6 - SS-35), 6B138-6.80 (SS-6) | 6.80L relocation project | 296 Hours
Continuous |
|
| 25-Nov-26 08:00 | 26-Nov-26 16:00 | ENMAX | Outage | 32.2TR (SS-32) | 32 sub construction - repair a broken wire on the voltage indicator | 32 Hours
Continuous |
|
| 25-Nov-26 08:00 | 26-Nov-26 16:00 | ALTALINK | TE | APS# 178 172L (370S-181S) Overload Mitigation, 15s Protection & Control (15s Fort Macleod) | PRC maintenance on 180L (L5) A and B, L5 B77 and 463L ( L10) RAS relay | 32 Hours
Daily |
|
| 25-Nov-26 11:00 | 26-Nov-26 18:00 | ALTALINK | Outage | 405s C1 (405s Waupisoo) | test cap bank and investigate multiple cap bank trips reported by ACC | 31 Hours
Continuous |
|
| 26-Nov-26 08:00 | 26-Nov-26 16:00 | ALTALINK | TE | AltaLink Telecom Equipment | radio maintenance | 8 Hours
Daily |
|
| 26-Nov-26 08:00 | 26-Nov-26 16:00 | ALTALINK | TE | 255s Protection & Control (255s Vulcan) | PRC maintenance on 180L A and B protections | 8 Hours
Daily |
|
| 26-Nov-26 08:00 | 26-Nov-26 16:00 | ALTALINK | TE | 255s RTU/SCADA (255s Vulcan) | RTU outage to remove nuisance motion detector and update SCADA configuration | 8 Hours
Daily |
|
| 26-Nov-26 08:00 | 26-Nov-26 16:00 | ALTALINK | TE | AltaLink Telecom Equipment | radio repair | 8 Hours
Daily |
|
| 26-Nov-26 08:00 | 27-Nov-26 15:00 | CMH | TE | MHS-6 MH69-602 (MHS-6 CMH Riverview), MHS-6 MH69-604 (MHS-6 CMH Riverview), MHS-6 MH69-607 (MHS-6 CMH Riverview), MHS-6 MH69-608 (MHS-6 CMH Riverview), MHS-6 MH69-611 (MHS-6 CMH Riverview), MHS-6 MH69-614 (MHS-6 CMH Riverview), MHS-6 MH69-616 (MHS-6 CMH Riverview), MHS-6 MH138-620 (MHS-6 CMH Riverview) | commissioning of new 69 kV breaker remote control | 31 Hours
Continuous |
|
| 26-Nov-26 08:00 | 27-Nov-26 17:00 | ALTALINK | Outage | 1182s C1 (1182s Berland River), 1182s 252 (1182s Berland River) | urgent request from Altalink to test capacitance on each capacitor | 33 Hours
Continuous |
|
| 26-Nov-26 09:00 | 27-Nov-26 17:00 | ALTALINK | TE | 320p RTU/SCADA (320P Keephills), AltaLink Telecom Equipment | telecom equipment maintenance | 32 Hours
Daily |
|
| 26-Nov-26 09:00 | 26-Nov-26 18:30 | ALTALINK, BPWF | RB | 1097L (356s Milo – 611s Amber) | required for 1005L outage - 1097L proximity | 9.5 Hours
Continuous |
|
| 26-Nov-26 09:00 | 26-Nov-26 10:00 | ATCO | Outage | 9L28 (937s AMR02 - 960s Birchwood Creek), 960s 9L28D1 (960s Birchwood Creek), 937s 06-DS-89T2 (937s Amr02), 937s 9L28 (937s Amr02) | switch status verification | 1 Hour
Continuous |
|
| 26-Nov-26 09:00 | 26-Nov-26 19:00 | ALTALINK, BCH | Outage | 1L274 (BCH Elkford - BCH Elkford tap), 1L274 (BCH Elkford Tap - BCH Greenhills Tap), 1L274 (BCH Elkford tap - BCH Line Creek tap) | replace structures |
10 Hours
Continuous |
AB-BC |
| 26-Nov-26 14:00 | 26-Nov-26 18:00 | ALTALINK, Travers2SolarLP | Outage | 1005L (120s Picture Butte - 1005AL tap), 1005L (356s Milo - 1005AL tap), 1005AL (991s Little Bow - 1005L tap), 356s 152 (356s Milo), 356s 252 (356s Milo), 991s 240-1 (991s Little Bow), 356s 1005 (356s Milo), 991s 1005BL (991s Little Bow) | remove ferruginous hawk nest and relocate to a stand alone platform outside the yard | 4 Hours
Continuous |
|
| 26-Nov-26 23:00 | 27-Nov-26 05:00 | EPCOR | Outage | EP 511s Victoria T4 (EP 511s Victoria) | install fence | 6 Hours
Continuous |
|
| 27-Nov-26 08:00 | 27-Nov-26 16:00 | ALTALINK | TE | APS# 178 172L (370S-181S) Overload Mitigation | testing of fiber optics | 8 Hours
Daily |
|
| 27-Nov-26 09:00 | 27-Nov-26 17:00 | ALTALINK | Outage | 431s C1 (431s Hussar) | 431sC1 cap bank testing to re energize. energize if testing passes review from engineering
|
8 Hours
Continuous |
|
| 27-Nov-26 09:30 | 27-Nov-26 15:30 | ATCO | Outage | 775s 604C (775s Sullivan Lake) | top up SF6 gas for the breaker 604 | 6 Hours
Continuous |
|
| 28-Nov-26 08:00 | 28-Nov-26 16:00 | ENMAX | TE | RTU/SCADA (SS-43) | RTU upgrade | 8 Hours
Continuous |
|
| 28-Nov-26 09:00 | 28-Nov-26 20:00 | SUNCOR | TE | Suncor RTU/SCADA (Suncor) | Baseplant - SDC Failover Test 2026 | 11 Hours
Continuous |
|
| 28-Nov-26 10:15 | 30-Nov-26 17:00 | ATCO | Outage | 7L121 (860s Crow - 7LA121 tap) | pole replacement, deficiency repair | 54.75 Hours
Continuous |
|
| 30-Nov-26 07:00 | 31-Dec-26 17:00 | EPCOR | TE | EP 511s Protection & Control (EP 511s Victoria) | protection blocking - relay maintenance | 754 Hours
Continuous |
|
| 30-Nov-26 08:00 | 02-Dec-26 18:00 | EPCOR | Outage | EP 511s V722 (EP 511s Victoria) | breaker fail upgrade cutovers and commissioning | 58 Hours
Continuous |
|
| 30-Nov-26 08:00 | 03-Dec-26 17:00 | ALTALINK | Outage | 71s 452 (71s Lamoureux), 71s 852 (71s Lamoureux), 71s 708N (71s Lamoureux), 71s 31 (71s Lamoureux), 71s T2 (71s Lamoureux), 71s 138kV East Bus (71s Lamoureux) | 138kV switch repairs (71s8, 71s42, 71s708N). Installation of the two new diameters being added to 71s (240kV side) | 81 Hours
Continuous |
|
| 30-Nov-26 08:00 | 03-Dec-26 16:00 | ALTALINK | TE | 103s Protection & Control (103s Goose Lake) | 893L RAS scheme is being salvaged, protection outages on A50P_RAS/L12, B50P_RAS/L12, A50/L12, B50/L12, and 616L A, B required to finish salvage on scheme | 80 Hours
Daily |
|
| 30-Nov-26 08:00 | 04-Dec-26 18:00 | EPCOR, ALTALINK | Outage | EP 803s T3 (EP 803s Lambton), 72LH8 (EP 803s Lambton - EP Hardisty), 72LS24 (EP 803s Lambton - Strathcona), EP 803s L2403 (EP 803s Lambton), EP 803s L2405 (EP 803s Lambton), EP 803s L721 (EP 803s Lambton), EP 803s LAB3 (EP 803s Lambton), H724 (EP Hardisty), S724 (Strathcona) | Lambton: TX3 zone, DFR cutovers and commissioning | 106 Hours
Continuous |
|
| 30-Nov-26 08:00 | 01-Dec-26 16:00 | ALTALINK | TE | 83s RTU/SCADA (83s Taber) | add new feeder breaker alarms for 83s263E | 32 Hours
Daily |
|
| 30-Nov-26 08:00 | 30-Nov-26 16:00 | ALTALINK, TRANSALTA | TE | 179s Protection & Control (179s Gleichen) | relay maintenance | 8 Hours
Daily |
|
| 30-Nov-26 08:00 | 03-Dec-26 16:00 | ALTALINK | TE | AltaLink Telecom Equipment | commissioning and integration of second backbone fiber node at 510s Sunnybrook | 80 Hours
Continuous |
|
| 30-Nov-26 08:00 | 30-Nov-26 16:00 | ENMAX, ALTALINK | Outage | 47.1TR (SS-47), 47B138-BT3 (SS-47), 47B138-771/1 (SS-47) | 47.1TR MD - center phase not down in the jaw - adjustment needed | 8 Hours
Continuous |
|
| 30-Nov-26 08:00 | 03-Dec-26 16:00 | ALTALINK | TE | 38s Protection & Control (38s East Edmonton) | maintenance on 1059L, 737L, 738L, 822L, 908L, 915L, 946L and B87/STUB2 | 80 Hours
Daily |
|
| 30-Nov-26 08:00 | 30-Nov-26 16:00 | ALTALINK | TE | 17s Protection & Control (17s Benalto) | maintenance and settings change on T2B, T1A and T1B | 8 Hours
Daily |
|
| 30-Nov-26 08:00 | 30-Nov-26 22:00 | ATCO | IO | ATCO Telecom Equipment | Vegreville_T(SCC)-Telecom- Vegreville tower upgrading dynamic load rating server for bug fixes | 14 Hours
Continuous |
|
| 30-Nov-26 08:00 | 04-Dec-26 16:00 | ALTALINK | TE | AltaLink Telecom Equipment | telecom equipment maintenance | 104 Hours
Continuous |
|
| 30-Nov-26 08:00 | 03-Dec-26 15:00 | CMH | Outage | MH-10L (MHS-10 Box Springs - MHS-8 Burnside), MH-12L (MHS-8 Burnside - MHS-6 CMH Riverview), MHS-8 MH138-T81 (MHS-8 Burnside), MHS-10 MH138-1008 (MHS-10 Box Springs), MHS-8 MH138-803 (MHS-8 Burnside), MHS-8 MH69-802 (MHS-8 Burnside), MHS-6 MH69-602 (MHS-6 CMH Riverview) | remove potential from MH-10L and MH-12L, operate and test SCADA initiating device at MHS-8, analog points for MH138-T81 LTC position indicator, and indoor building temperature | 79 Hours
Continuous |
|
| 30-Nov-26 08:00 | 16-Dec-26 16:00 | ENMAX | Outage | 21.1C (SS-21) | relocate the cap bank breaker 130V DC disconnect switch | 392 Hours
Continuous |
|
| 30-Nov-26 08:30 | 11-Dec-26 14:00 | ENMAX | Outage | 31.2TR (SS-31) | surge capacitor installation, surge arrestor installation, Dev 90 replacement | 269.5 Hours
Continuous |
|
| 30-Nov-26 09:00 | 03-Dec-26 17:00 | ALTALINK | TE | 103s Protection & Control (103s Goose Lake) | protection outages to perform settings changes in relation to 893L RAS removal | 80 Hours
Daily |
|
| 30-Nov-26 09:00 | 03-Dec-26 17:00 | ALTALINK | TE | AltaLink Telecom Equipment | commissiong and integration of DWDM circuit at 17s for DWDM node additions -9008R | 80 Hours
Continuous |
|
| 30-Nov-26 09:00 | 11-Dec-26 17:00 | ALTALINK | TE | 163s RTU/SCADA (163s Amoco Empress) | SCADA configuration updates for ACC visibility scope | 272 Hours
Daily |
|
| 30-Nov-26 09:00 | 04-Dec-26 16:00 | ATCO | TE | ATCO Telecom Equipment | CO latency testing | 103 Hours
Continuous |
|
| 30-Nov-26 09:00 | 11-Dec-26 13:00 | ATCO | TE | 813s Protection & Control (813s Little Smoky), 813s RTU/SCADA (813s Little Smoky) | installing new SVC DFR, adding alarms to RTU, installing new Sat clock for substation SEL-2032 and connecting to telecom network | 268 Hours
Continuous |
|
| 30-Nov-26 09:00 | 01-Dec-26 17:00 | ATCO | Outage | 749s 701T (749s Flyingshot Lake), 749s 701 (749s Flyingshot Lake), 749s 706 (749s Flyingshot Lake), 749s 701TD (749s Flyingshot Lake) | two hot spots were identified that require immediate repair, 701T X side arrestor and 701A hinge side connection, make repairs to 501TD | 32 Hours
Continuous |
|
| 30-Nov-26 09:00 | 04-Dec-26 17:00 | ALTALINK, BCH | Outage | 1L275 (799s Coleman - BCH Natal), 799s 786W (799s Coleman) | replace failed T&T 3PDE structure | 104 Hours
Continuous |
AB-BC |
| 30-Nov-26 09:00 | 01-Dec-26 17:00 | BCH | Outage | 5L98 (BCH Nicola - BCH Vaseux Lake) | replace 5B25 conductor at 5CVT25, BC maintenance does not affect the Alberta ATC | 32 Hours
Continuous |
AB-BC |
| 30-Nov-26 09:30 | 03-Dec-26 18:30 | ALTALINK, BCH | Outage | 786L (799s Coleman - BCH Natal) | BC hydro to replace failed T&T 3PDE structure | 80.5 Hours
Continuous |
|
| 30-Nov-26 10:00 | 30-Nov-26 10:20 | CMH | TE | MH-30L (MHS-3 Southridge - MHS-5 NE Crescent Heights) | facilitate fiber optic integrity testing on 5S_LDR-3040L-B line protection at MHS-5 Northeast Crescent Heights substation | 0.33 Hours
Continuous |
|
| 30-Nov-26 10:21 | 30-Nov-26 10:40 | CMH | TE | MH-50L (MHS-2 North Industrial - MHS-5 NE Crescent Heights) | facilitate fiber optic integrity testing on 5S_LDR-50L-A line protection at MHS-5 Northeast Crescent Heights substation | 0.32 Hours
Continuous |
|
| 30-Nov-26 10:41 | 30-Nov-26 11:00 | CMH | TE | MH-50L (MHS-2 North Industrial - MHS-5 NE Crescent Heights) | carry out maintenance on the relay 5S_LDR-50L-B at Northeast Crescent Heights substation | 0.32 Hours
Continuous |
|
| 30-Nov-26 11:01 | 30-Nov-26 11:20 | CMH | TE | MH-60L (MHS-5 NE Crescent Heights - MHS-7 Brier Park) | facilitate fiber optic integrity testing on 5S_LDR-60L-A line protection at MHS-5 Northeast Crescent Heights substation | 0.32 Hours
Continuous |
|
| 30-Nov-26 11:21 | 30-Nov-26 11:40 | CMH | TE | MH-60L (MHS-5 NE Crescent Heights - MHS-7 Brier Park) | facilitate fiber optic integrity testing on 5S_LDR-60L-B line protection at MHS-5 Northeast Crescent Heights substation | 0.32 Hours
Continuous |
|
| 30-Nov-26 12:00 | 03-Dec-26 18:00 | ATCO | RB | 7L159 (770s Three Hills - 7L159 tap) | pole change at structure 144 and arm change structure 350 | 78 Hours
Continuous |
|
| 30-Nov-26 12:00 | 03-Dec-26 17:00 | ALTALINK | TE | 103s RTU/SCADA (103s Goose Lake) | 103s RTU outage - correct SCADA deficiency associated with 103s HMI replacement | 77 Hours
Daily |
|
| 30-Nov-26 13:00 | 11-Dec-26 13:00 | ATCO | Outage | 813s SVC (813s Little Smoky) | 813S Little Smoky SVC DFR upgrade | 264 Hours
Continuous |
|
| 30-Nov-26 13:00 | 03-Dec-26 18:30 | ALTALINK | RB | 723L (438s Westlock - 724L tap), 723L (69s North Barrhead - 724L tap), 724L (500s Flatbush - 724L tap), 724L (723L tap - 724AL tap) | replace structure, arms and insulation | 77.5 Hours
Daily |
|
| 30-Nov-26 13:00 | 03-Dec-26 16:00 | ALTALINK | Outage | 310p T30 (310p Sundance), 310P 69 (310p Sundance) | drain oil from 310p T30, cut in 310p open point A and B | 75 Hours
Continuous |
|
| 01-Dec-26 07:00 | 01-Dec-26 17:00 | ALTALINK | Outage | AML 511s 5252 (AML 511s Crossings) | PRC relay maintenance on 5252 Siemens 6MD | 10 Hours
Continuous |
|
| 01-Dec-26 08:00 | 01-Dec-26 16:00 | ALTALINK | TE | 216s Protection & Control (216s Knightsbridge) | maintenance
|
8 Hours
Daily |
|
| 01-Dec-26 08:00 | 01-Dec-26 16:00 | ALTALINK | TE | 59s Protection & Control (59s Peigan) | maintenance on BAT1 27/BAT1, battery charger alarms will be brought in while testing | 8 Hours
Daily |
|
| 01-Dec-26 08:00 | 01-Dec-26 16:00 | ALTALINK | TE | 575s Protection & Control (575s Sundre) | relay maintenance | 8 Hours
Daily |
|
| 01-Dec-26 09:00 | 01-Dec-26 18:00 | ALTALINK | Outage | 103s 138kV Bus 2 (103s Goose Lake), 893L (103s Goose Lake - 893BL tap), 103s 1652 (103s Goose Lake), 103s 1752 (103s Goose Lake) | remove RAS scheme from breakers 103s1652 and 103s1752, wiring changes within the brakers | 9 Hours
Continuous |
|
| 01-Dec-26 09:00 | 03-Dec-26 20:00 | SUNCOR | TE | 29EDD-34 RTU/SCADA (29EDD-34) | 29EDD-34 - test low voltage 225A breakers, isolations affecting chargers DFR, HVAC, lighting, breaker heaters and firewall | 59 Hours
Continuous |
|
| 01-Dec-26 09:00 | 01-Dec-26 10:00 | ATCO | TE | ATCO Telecom Equipment | upgrading the SAR OS at Virginia Hills
|
1 Hour
Continuous |
|
| 01-Dec-26 09:00 | 01-Dec-26 18:00 | ALTALINK | TE | 172s RTU/SCADA (172s Sherritt Gordon), AltaLink Telecom Equipment | maintenance | 9 Hours
Daily |
|
| 01-Dec-26 09:00 | 02-Dec-26 17:00 | ATCO | TE | ATCO Telecom Equipment | MPLS Life Cycle upgrades to SAR A, Node 102.129, removal of DJF, replacement of SAR A SDI Card 1.3/1.4
|
32 Hours
Continuous |
|
| 01-Dec-26 10:00 | 01-Dec-26 17:00 | ATCO | TE | 875s RTU/SCADA (875s Algar) | HMI update required due to an incorrect local alarm displaying | 7 Hours
Continuous |
|
| 01-Dec-26 10:00 | 09-Dec-26 18:00 | ATCO | TE | 939s RTU/SCADA (939s Livock), 939s Protection & Control (939s Livock) | 951S-APL firmware upgrades | 200 Hours
Continuous |
|
| 01-Dec-26 11:00 | 08-Dec-26 17:00 | ATCO | Outage | 7L104 (856s Kinosis - 989s Quigley) | changing out L-G clearance mitigation poles and insulator change out | 174 Hours
Continuous |
|
| 02-Dec-26 06:30 | 02-Dec-26 17:00 | ALTALINK | IO | AltaLink AECC Back-up Activation | AltaLink will activate its Emergency Control Centre (AECC) and conduct operations from that location from 07:30 to approximately 16:00 | 10.5 Hours
Continuous |
|
| 02-Dec-26 07:00 | 02-Dec-26 17:00 | ALTALINK | Outage | AML 511s 5352 (AML 511s Crossings) | PRC relay maintenance on 5352 Siemens 6MD | 8 Hours
Continuous |
|
| 02-Dec-26 07:00 | 02-Dec-26 19:00 | ALTALINK | Outage | 194s 138kV Bus (194s South Red Deer), 425L (194s South Red Deer - 217s North Red Deer), 194s 425 (194s South Red deer), 217s 425 (217s North Red Deer) | urgent repair to replace center phase PT1 on 138kV bus | 12 Hours
Continuous |
|
| 02-Dec-26 08:00 | 04-Dec-26 18:30 | ALTALINK, CHDI | RB | 514L (396s Pincher Creek - 514BL tap), 514L (513s Lundbreck - 514BL tap), 514BL (322s Cowley Ridge Windplant - 514L tap) | 514L proximity R/B
|
58.5 Hours
Daily |
|
| 02-Dec-26 08:00 | 03-Dec-26 16:00 | ATCO | TE | 804s Protection & Control (804s Wintering Hills), 804s RTU/SCADA (804s Wintering Hills) | update the settings to the 21B relay as per engineering request | 32 Hours
Continuous |
|
| 02-Dec-26 08:00 | 02-Dec-26 17:00 | ALTALINK, TRANSALTA | TE | 218s RTU/SCADA (218s Fort Saskatchewan Co-Gen) | telecom upgrade | 9 Hours
Daily |
|
| 02-Dec-26 08:00 | 02-Dec-26 17:00 | ALTALINK | TE | 55s RTU/SCADA (55s Olds), AltaLink Telecom Equipment | investigating air link on 55S Olds end waveguide. may require to turn radio down if the waveguide needs to be disconnected. possible Feedhorn leak | 9 Hours
Daily |
|
| 02-Dec-26 09:00 | 02-Dec-26 19:00 | Syncrude | TE | Syncrude ICCP Outage | SCADA - server update | 10 Hours
Daily |
|
| 02-Dec-26 09:00 | 03-Dec-26 17:00 | ALTALINK | TE | 895s RTU/SCADA (895s Suffield) | 895s2272 meter module deficiency clean up | 32 Hours
Daily |
|
| 02-Dec-26 09:00 | 02-Dec-26 17:00 | ATCO, ALTALINK, SHELL | TE | 402s RTU/SCADA (402s Scotford Expansion 1) | RTU battery fail at 402S Scotford. techs to isolate the RTU, pull an AF RTU config, and change the battery
|
8 Hours
Continuous |
|
| 02-Dec-26 09:00 | 03-Dec-26 17:00 | ATCO | TE | ATCO Telecom Equipment | Oakland_S-Telecom- MPLS life cycle upgrades to SAR A, Node 167.1 | 32 Hours
Continuous |
|
| 02-Dec-26 09:00 | 02-Dec-26 17:00 | ATCO | TE | 807s RTU/SCADA (807s Sheerness), ATCO Telecom Equipment | both firewalls at the SHEERNESS_S substation will undergo a scheduled upgrade to maintain system security and to remove any bugs on the system | 8 Hours
Continuous |
|
| 02-Dec-26 09:30 | 02-Dec-26 16:00 | ALTALINK | TE | 39s RTU/SCADA (39s Bickerdike) | RTU database update | 6.5 Hours
Daily |
|
| 02-Dec-26 10:00 | 03-Dec-26 17:00 | ATCO | TE | ATCO Telecom Equipment | McNeill_S-Telecom-moving communication and Scada traffic onto new star link device.
There will be a Scada outage for the full day (10am-5pm). It will be put back in service for the evenings. |
31 Hours
Continuous |
|
| 02-Dec-26 10:00 | 02-Dec-26 16:00 | ALTALINK | TE | 137s Protection & Control (137s Sedgewick) | standard relay maintenance | 6 Hours
Daily |
|
| 02-Dec-26 11:00 | 06-Dec-26 19:00 | ATCO | TE | 2075s Protection & Control (2075s Newell) | complete the EN100 firmware upgrade for the AC Filter protection, Converter Transformer, 923L B protection, and 1035L B protection relays
|
104 Hours
Continuous |
|
| 03-Dec-26 07:00 | 03-Dec-26 17:00 | ALTALINK | Outage | AML 511s 5052 (AML 511s Crossings) | PRC maintenance | 10 Hours
Continuous |
|
| 03-Dec-26 08:00 | 03-Dec-26 17:00 | ALTALINK | TE | 258s RTU/SCADA (258s Dow Hydrocarbons), AltaLink Telecom Equipment | SCADA update. | 9 Hours
Daily |
|
| 03-Dec-26 08:00 | 05-Dec-26 16:00 | ALTALINK | TE | 38s RTU/SCADA (38s East Edmonton) | RTU update. | 56 Hours
Daily |
|
| 03-Dec-26 08:00 | 03-Dec-26 20:00 | ATCO | TE | 951s RTU/SCADA (951s Thickwood Hills), ATCO Telecom Equipment | adding additional bandwidth to the Livock substation | 12 Hours
Continuous |
|
| 03-Dec-26 10:00 | 03-Dec-26 17:00 | ATCO | TE | 2029s RTU/SCADA (2029s Heathfield), ATCO Telecom Equipment | 7750-2 integration, swapping site networking to VPLS 11 | 7 Hours
Continuous |
|
| 03-Dec-26 10:00 | 03-Dec-26 17:00 | ATCO | TE | 886s RTU/SCADA (886s Updike), ATCO Telecom Equipment | 7750-2 integration, swapping site networking to VPLS 11 | 7 Hours
Continuous |
|
| 03-Dec-26 10:00 | 13-Dec-26 18:30 | ATCO | TE | 801s RTU/SCADA (801s Anderson), 801s Protection & Control (801s Anderson) | replacement of failed 9L59D1 at 801s Anderson | 248.5 Hours
Continuous |
|
| 03-Dec-26 10:00 | 03-Dec-26 17:00 | ATCO, TRANSALTA | Outage | 9L59 (801s Anderson - 9LA59 tap), 9LA59 (1045s Garden Plain - 9LA59 tap), 9L59 (972s Tinchebray - 9LA59 tap), 801s 903 (801s Anderson), 801s 902 (801s Anderson) | cut in jumper J1 at T tap to Garden Plain | 7 Hours
Continuous |
|
| 03-Dec-26 11:00 | 03-Dec-26 13:00 | ALTALINK | TE | AltaLink Telecom Equipment, 250p RTU/SCADA (250P Bighorn Plant), 304s RTU/SCADA (304s Shell Limestone), 21s RTU/SCADA (21s Marion), 68s RTU/SCADA (68s Willesden Green), 115s RTU/SCADA (115s Mount Allan), 165s RTU/SCADA (165s Gainford), 180s RTU/SCADA (180s Cope Creek), 271s RTU/SCADA (271s Shell Jumping Pound), 406s RTU/SCADA (406s Fickle Lake), 411s RTU/SCADA (411s Obed), 512s RTU/SCADA (512s Hartell), 515s RTU/SCADA (515s Fedpipe Judy Creek), 527s RTU/SCADA (527s Coal Valley), 638s RTU/SCADA (638s Esso Judy Creek), 887s RTU/SCADA (887s Carson Creek), 975s RTU/SCADA (975s Dalehurst), 996s RTU/SCADA (996s Imperial Oil Carson Lake) | update configuration | 2 Hours
Continuous |
|
| 03-Dec-26 11:00 | 03-Dec-26 16:00 | ALTALINK | TE | 368s Protection & Control (368s Burdett) | T2 protections to be removed from service one at a time | 5 Hours
Daily |
|
| 03-Dec-26 17:01 | 13-Dec-26 08:59 | ATCO | Outage | 9L59 (801s Anderson - 9LA59 tap), 801s 902 (801s Anderson), 801s 903 (801s Anderson) | replacement of failed 9L59D1 at 801s Anderson | 248.5 Hours
Continuous |
|
| 03-Dec-26 17:01 | 11-Dec-26 18:00 | ALTALINK | Outage | 71s 240kV East Bus (71s Lamoureux), 71s T2 (71s Lamoureux), 71s 1752 (71s Lamoureux), 71s 1452 (71s Lamoureux), 71s 32 (71s Lamoureux) | prep work for the installation of the two new diameters being added to 71s | 192.98 Hours
Continuous |
|
| 04-Dec-26 08:00 | 04-Dec-26 18:00 | EPCOR | Outage | 557s T1 (557s Castle Downs), 557s CD2401 (557s Castle Downs), 557s CD2406 (557s Castle Downs), 557s CDAB1 (557s Castle Downs) | Castledowns TX1 wiring changes | 10 Hours
Continuous |
|
| 04-Dec-26 08:00 | 04-Dec-26 17:00 | ALTALINK | TE | AltaLink Telecom Equipment | telecom equipment maintenance | 9 Hours
Daily |
| This document and the information contained herein are based upon information and data which by their nature contain a degree of uncertainty and are subject to change. In addition, this document may contain information and data from public sources and/or third parties, which have been assumed to be accurate and complete and have not been verified. Accordingly, the Independent System Operator, operating as the Alberta Electric System Operator (the "AESO") makes no warranty, representation or guarantee, express or implied, with respect to this document or the information contained herein, including, but not limited to, any warranty, representation or guarantee of accuracy, completeness, timeliness, reliability, availability, absence of computer virus, non- infringement, merchantability or suitability for any purpose. Under no circumstances will the AESO, its members, officers, employees, contractors or agents, or any of their respective affiliates, be liable for any errors or omissions in, or any losses, damages or claims whatsoever, whether in contract, tort or otherwise, arising from use of or reliance upon, this document or any information contained herein. © 2009 Alberta Electric System Operator. All rights reserved |