| Alberta Electric System Operator | |
| System Co-ordination Plan | |
| 2026-07-16 to 2026-07-24 | |
| Approved Outages |
| Previous Version | |
| Download CSV |
| From | To | Owner | Type | Element | Scheduled Activity | Date/Time Comments | Interconnection |
|---|---|---|---|---|---|---|---|
| 26-Jul-24 10:00 | 31-Jul-26 16:00 | ATCO | Outage | 826s 504R (826s Marguerite Lake) | emergency removal to replace failed 502R @834S | 17,646 Hours
Continuous |
|
| 20-Mar-25 08:00 | 31-Jul-26 17:00 | ALTALINK | Outage | 256s C1 (256s Harmattan) | forced outage | 11,961 Hours
Continuous |
|
| 25-Nov-25 17:46 | 18-Sep-26 18:00 | ATCO | Outage | 876s 901T (876s Brintnell) | forced outage oil leaking | 7,127.23 Hours
Continuous |
|
| 27-Nov-25 08:30 | 27-Nov-27 16:30 | ALTALINK | TE | 89s Protection & Control (89s Ellerslie) | DSP card replacements on1057L B87/L3 and B240B1 B87/240B1 | 17,528 Hours
Daily |
|
| 04-Jan-26 08:00 | 02-Sep-26 16:00 | SUNCOR | Outage | 29EDD-34 260kV Bus 29PP-45 (29EDD-34), 29EDD-34 29-952-113 (29EDD-34), 29EDD-34 29PS-216 (29EDD-34) | urgent repairs on 29PT-224 at 29EDD34 on 29PP-45 bus | 5,791 Hours
Continuous |
|
| 21-Jan-26 08:00 | 30-Oct-26 16:00 | ENMAX | Outage | 5.7TR (SS-5) | 25kV switchgear replacement | 6,775 Hours
Continuous |
|
| 09-Feb-26 09:00 | 16-Jul-26 17:00 | ATCO | TE | 972s Protection & Control (972s Tinchebray) | block all 50BF protection until cutovers and associated commissioning are complete | 3,607 Hours
Continuous |
|
| 06-Mar-26 17:00 | 13-Nov-26 17:00 | EPCOR | Outage | T1 (Woodcroft) | woodcroft: TX1 LCR civil | 6,048 Hours
Continuous |
|
| 10-Mar-26 10:00 | 30-Nov-26 17:00 | ATCO | TE | 743s RTU/SCADA (743s Sarah Lake) | throughout the course of the project, different apparatus are being replaced, RTU will be blocked prior to download | 6,368 Hours
Continuous |
|
| 11-Mar-26 13:45 | 31-Jul-26 16:00 | ALTALINK | Outage | 535s C1 (535s Joffre) | breaker maintenance | 3,410.25 Hours
Continuous |
|
| 01-May-26 17:00 | 25-Nov-26 17:00 | EPCOR | Outage | T1 (Meadowlark) | T1 LCR civil work | 4,993 Hours
Continuous |
|
| 19-May-26 07:00 | 02-Oct-26 17:00 | EPCOR | TE | 987s Protection & Control (987s Clover Bar) | protection blocking - relay maintenance and bus differential upgrade project | 2,434 Hours
Continuous |
|
| 27-May-26 18:00 | 17-Jul-26 10:59 | ALTALINK | Outage | 526s C1 (526s Buffalo Creek) | forced outage | 1,216.98 Hours
Daily |
|
| 01-Jun-26 09:00 | 16-Jul-26 17:30 | ATCO | TE | 865s RTU/SCADA (865s Saddlehills) | updating RTU/station controller configuration during SCADA upgrade project | 1,088.5 Hours
Continuous |
|
| 02-Jun-26 10:00 | 16-Jul-26 16:00 | ATCO | Outage | 743s 701T (743s Sarah Lake), 743s 705 (743s Sarah Lake), 743s 605 (743s Sarah Lake), 743s 501 (743s Sarah Lake) | 743S Sarah lake rebuild | 990 Hours
Continuous |
|
| 04-Jun-26 07:01 | 10-Feb-27 17:00 | EPCOR | Outage | T1 (Rossdale) | rossdale: TX1 lcr civil | 6,034.98 Hours
Continuous |
|
| 07-Jun-26 17:05 | 01-Oct-26 00:00 | ACCIONA, ENBRIDGE, ICPCL | Outage | 139s C1 (139s Hillridge) | forced outage | 2,766.92 Hours
Continuous |
|
| 08-Jun-26 07:00 | 04-Dec-26 17:00 | EPCOR | TE | EP 511s Protection & Control (EP 511s Victoria) | 72kV breaker fail protection blocking | 2,626 Hours
Continuous |
|
| 09-Jun-26 07:00 | 16-Jul-26 17:30 | ATCO | TE | 743s Protection & Control (743s Sarah Lake) | relay testing | 826.5 Hours
Continuous |
|
| 09-Jun-26 07:00 | 16-Jul-26 17:30 | ATCO | TE | 743s Protection & Control (743s Sarah Lake) | isolating 50BF/705 for relay testing | 178.5 Hours
Continuous |
|
| 09-Jun-26 07:00 | 16-Jul-26 17:30 | ATCO | TE | 743s Protection & Control (743s Sarah Lake) | isolating 50BF/605 for relay testing | 178.5 Hours
Continuous |
|
| 15-Jun-26 07:00 | 24-Jul-26 17:00 | EPCOR | Outage | EP 805s J2403 (EP 805s Jasper) | J2403 replacement LCR | 946 Hours
Continuous |
|
| 15-Jun-26 07:00 | 04-Sep-26 17:00 | EPCOR | TE | 805s Protection & Control (805s Jasper) | protection blocking, breaker replacement project | 1,954 Hours
Continuous |
|
| 15-Jun-26 07:00 | 17-Jul-26 17:00 | EPCOR | Outage | 72JM18 (EP 805s Jasper - Meadowlark), M721 (Meadowlark), M722 (Meadowlark), EP 805s J722 (EP 805s Jasper), T1 (Meadowlark), MAB1 (Meadowlark) | Meadowlark: TX1 Zone, LCR Civil Work | 274 Hours
Continuous |
|
| 19-Jun-26 17:00 | 03-Dec-27 17:00 | EPCOR | Outage | EP 511s Victoria T3 (EP 511s Victoria) | emergency outage due to degraded asset condition | 12,769 Hours
Continuous |
|
| 29-Jun-26 10:00 | 24-Jul-26 17:30 | ATCO | TE | 763s RTU/SCADA (763s Hanna) | 602T ITM replacement , SCADA updates required as part of ITM replacement project |
439.5 Hours
Continuous |
|
| 05-Jul-26 08:00 | 23-Jul-26 16:00 | Syncrude | TE | Syncrude RTU/SCADA (Syncrude Plant 30-2) | replacing an obsolete UPS in 30-2PEB15-2 | 440 Hours
Continuous |
|
| 06-Jul-26 07:00 | 16-Jul-26 17:00 | ALTALINK | TE | 368s RTU/SCADA (368s Burdett) | 368s RTU configuration update | 250 Hours
Daily |
|
| 06-Jul-26 08:00 | 17-Jul-26 16:00 | ALTALINK | TE | 214s Protection & Control (214s Innisfail), 287s Protection & Control (287s Hazelwood), 55s Protection & Control (55s Olds) | LTO and transfer tripping settings changes for RAS scheme updates due to the implementation of 475s mobile sub at 55s | 272 Hours
Daily |
|
| 06-Jul-26 08:00 | 17-Jul-26 16:00 | ALTALINK | TE | 214s RTU/SCADA (214s Innisfail) | RAS updates due to 55s mobile sub installation | 272 Hours
Daily |
|
| 06-Jul-26 08:00 | 17-Jul-26 16:00 | ALTALINK | TE | 287s RTU/SCADA (287s Hazelwood) | changes to RAS scheme due to addition of 55s mobile sub | 272 Hours
Daily |
|
| 06-Jul-26 09:00 | 17-Jul-26 17:00 | BCH | RB | 2L113 (BCH Cranbrook - BCH Natal) | hazard tree removals | 272 Hours
Continuous |
AB-BC |
| 06-Jul-26 10:00 | 24-Jul-26 17:30 | ATCO | Outage | 763s 602T (763s Hanna), 763s 507C (763s Hanna), 763s 604 (763s Hanna) | 500D1 repair - 602T ITM replacement |
271.5 Hours
Continuous |
|
| 06-Jul-26 13:00 | 16-Jul-26 17:00 | ALTALINK | Outage | 761L (38s East Edmonton - 71s Lamoureux), 38s 761N (38s East Edmonton), 71s 552 (71s Lamoureux), 71s 652 (71s Lamoureux), 71s 761W (71s Lamoureux) | 38s761N breaker replacement, replace 71s39, maintenance on 71s761W | 244 Hours
Continuous |
|
| 06-Jul-26 14:00 | 16-Jul-26 17:00 | ALTALINK | TE | 38s Protection & Control (38s East Edmonton) | 38s761N 138 kV breaker replacement, isolations, protection testing
|
243 Hours
Continuous |
|
| 09-Jul-26 07:00 | 16-Jul-26 17:00 | ALTALINK | TE | 77s RTU/SCADA (77s Sagitawah) | RTU database update | 178 Hours
Daily |
|
| 10-Jul-26 08:00 | 18-Nov-26 16:00 | Syncrude | Outage | 815 (Syncrude Mildred Lake), 816 (Syncrude Mildred Lake) | replace 72 kV underground feeder cables on west mine feeder | 2,696 Hours
Continuous |
|
| 13-Jul-26 07:00 | 19-Jul-26 17:00 | EPCOR | Outage | 72CH11 (987s Clover Bar - EP Hardisty), T1 (EP Hardisty), H722 (EP Hardisty), H725 (EP Hardisty), 987s CH724 (987s Clover Bar), S724 (Strathcona), H723 (EP Hardisty) | t1 maintenance and bus diff | 154 Hours
Continuous |
|
| 13-Jul-26 07:00 | 19-Jul-26 17:00 | EPCOR | Outage | EP 803s L2401 (EP 803s Lambton) | breaker maintenance | 154 Hours
Continuous |
|
| 13-Jul-26 07:00 | 17-Jul-26 17:00 | ALTALINK | TE | AltaLink Telecom Equipment | 2012F fiber relocation for road move | 106 Hours
Continuous |
|
| 13-Jul-26 07:00 | 17-Jul-26 17:00 | ALTALINK, EPCOR | TE | 909L (310p Sundance - 665s Dome) | Altalink is relocating 2012F fiber for road move | 106 Hours
Continuous |
|
| 13-Jul-26 07:00 | 17-Jul-26 17:00 | ALTALINK, EPCOR | TE | 1139L (367s Harry Smith - EP Riverview) | Altalink is relocating 2012F fiber for road move | 106 Hours
Continuous |
|
| 13-Jul-26 07:00 | 17-Jul-26 17:00 | ALTALINK, EPCOR | TE | 1209L (89s Ellerslie - 330p Genesee) | Altalink is relocating 2012F fiber for road move | 106 Hours
Continuous |
|
| 13-Jul-26 07:00 | 17-Jul-26 17:00 | ALTALINK, EPCOR | TE | 1045L (EP 805s Jasper - 1045AL tap) | Altalink is relocating 2012F fiber for road move | 106 Hours
Continuous |
|
| 13-Jul-26 07:00 | 24-Jul-26 17:00 | ALTALINK, EPCOR | TE | 909L (310p Sundance - 665s Dome) | protection blocking for MPLS cutovers and commissioning | 274 Hours
Continuous |
|
| 13-Jul-26 07:00 | 24-Jul-26 17:00 | ALTALINK, EPCOR | TE | 909L (89s Ellerslie - 665s Dome) | protection blocking for MPLS cutovers and commissionin | 274 Hours
Continuous |
|
| 13-Jul-26 07:30 | 16-Jul-26 16:30 | ALTALINK, DOW | RB | 787AL (906s Ross Creek - 787L tap), 787L (166s Dow Chemical Fort Saskatchewan - 787AL tap), 787L (71s Lamoureux - 787AL tap) | safety requirement - crew working in vicinity | 81 Hours
Continuous |
|
| 13-Jul-26 08:00 | 24-Jul-26 16:00 | ALTALINK | TE | 310p Protection & Control (310p Sundance) | EPCOR MPLS upgrade
|
272 Hours
Continuous |
|
| 13-Jul-26 08:00 | 24-Jul-26 16:00 | ALTALINK | TE | 89s Protection & Control (89s Ellerslie) | EPCOR MPLS upgrade | 272 Hours
Continuous |
|
| 13-Jul-26 08:00 | 16-Jul-26 16:00 | ENMAX | Outage | 13.3TR (SS-13) | transformer testing | 80 Hours
Continuous |
|
| 13-Jul-26 08:00 | 16-Jul-26 16:00 | ENMAX | Outage | 3.82L (SS-3 - SS-8), 3.3TR (SS-3), 3B138-3.82 (SS-3), SW83 (SS-3), 3MD138-3.3TR (SS-3) | tap changer inspection | 80 Hours
Continuous |
|
| 13-Jul-26 09:00 | 24-Jul-26 17:30 | ATCO | Outage | 2075s 901T (2075s Newell), 2075s 917 (2075s Newell), 2075s 918 (2075s Newell), 2075s ACF11 (2075s Newell), 2075s ACF12 (2075s Newell), 2075s ACF13 (2075s Newell), 2075s ACF14 (2075s Newell), 2075s ACF1D1 (2075s Newell) | SVC Newell maintenance | 272.5 Hours
Continuous |
|
| 13-Jul-26 10:00 | 16-Jul-26 16:00 | ATCO | Outage | 918s 702T (918s Bauer), 918s 702 (918s Bauer) | transformer and breaker maintenance | 78 Hours
Continuous |
|
| 13-Jul-26 10:00 | 17-Jul-26 17:30 | ALTALINK | RB | 472AL (221s Sunken Lake - 472L tap), 472L (213s Hughenden - 472AL tap), 472L (648s Metiskow - 472AL tap) | 472L 204, 208, 241, 245, 343, 358, 367, replace arms and glass, replace structure 241 | 103.5 Hours
Continuous |
|
| 13-Jul-26 10:00 | 16-Jul-26 16:00 | ATCO | TE | 918s RTU/SCADA (918s Bauer) | In conjunction with 1-00519538. 918s RTU outage 10-20 min to push new config file. | 78 Hours
Continuous |
|
| 13-Jul-26 12:00 | 17-Jul-26 16:00 | ATCO | Outage | 6L12 (774s Monitor - 6L25 tap), 774s 601 (774s Monitor), 774s 6L12D5 (774s Monitor), 774s 601A (774s Monitor) | road rebuild structure replacements | 100 Hours
Continuous |
|
| 13-Jul-26 13:00 | 16-Jul-26 15:00 | ATCO | RB | 7L85 (801s Anderson - ATC 803s Bullpound), 7L85 (803s ATC Bullpound - 7LA85 tap), 7L85 (804s Wintering Hills - 7LA85 tap) | installing interphase spacers on 7L85 - live line work | 74 Hours
Continuous |
|
| 14-Jul-26 08:00 | 01-Oct-26 17:00 | ALTALINK | IO | 287s 552 (287s Hazelwood) | 287s552 must be open during 443L and 417L outage for the 214s AIS to work properly | 1,905 Hours
Continuous |
|
| 14-Jul-26 09:30 | 23-Jul-26 11:00 | ALTALINK | Outage | 163s T5 (163s Amoco Empress) | 163sT5 maintenance and oil leaks | 217.5 Hours
Continuous |
|
| 14-Jul-26 12:00 | 20-Jul-26 10:00 | ATCO | Outage | 886s 701T (886s Updike) | transformer and breaker testing, mobile sub will be carrying all the load | 166 Hours
Continuous |
|
| 14-Jul-26 13:00 | 17-Jul-26 13:00 | ATCO | Outage | 783s 701T (783s Cadotte River), 783s 701TD (783s Cadotte River) | 783S 144kV fuse replacement , 783s 701T transformer class 2 major testing |
72 Hours
Continuous |
|
| 15-Jul-26 07:00 | 16-Jul-26 17:00 | ALTALINK, TRANSALTA | RB | 179s 733 (179s Gleichen), 428s 733X (428s Namaka), 733L (179s Gleichen - 428s Namaka) | 733L str. 161-211 prep. Live line work. | 34 Hours
Daily |
|
| 15-Jul-26 07:00 | 16-Jul-26 17:00 | ALTALINK | RB | 151s 733E (151s Strathmore), 428s 733N (428s Namaka), 733L (151s Strathmore - 428S Namaka) | 733L 131 Top Phase Keeper Key. Live Line. | 34 Hours
Daily |
|
| 15-Jul-26 07:30 | 16-Jul-26 16:00 | ALTALINK, ENEL | Outage | 205s T1 (205s Castle Rock Ridge), 205s 89T1 (205s Castle Rock Ridge) | two day outage required for 205s planned maintenance | 32.5 Hours
Continuous |
|
| 15-Jul-26 08:00 | 21-Jul-26 10:59 | SUNCOR | Outage | 29EDD-1 29EDD1s452 (29EDD-1 Millennium) | maintenance and test | 156 Hours
Continuous |
|
| 15-Jul-26 08:00 | 16-Jul-26 16:00 | ENMAX | Outage | 21.61L (SS-21 - SS-34), 34B69-21.61 (SS-34), 21B69-21.61 (SS-21) | hv breaker maintenance | 32 Hours
Continuous |
|
| 15-Jul-26 08:00 | 16-Jul-26 16:00 | ENMAX | Outage | 40.1TR (SS-40) | secondary cabinet measurements and CT testing | 32 Hours
Continuous |
|
| 15-Jul-26 08:00 | 16-Jul-26 14:30 | ALTALINK | Outage | 62s T1 (62s Brazeau Plant), 62s 1 (62s Brazeau Plant) | customer to balance BR1 motor | 30.5 Hours
Daily |
|
| 15-Jul-26 09:00 | 21-Jul-26 17:00 | ATCO, SUNCOR | TE | 29PL9-1 (29EDD-1 Millennium - 848s Ruth Lake) | pm 5y,10y protection only | 104 Hours
Continuous |
|
| 15-Jul-26 10:00 | 16-Jul-26 16:00 | ATCO | Outage | 825s 904 (825s Whitefish Lake) | breaker maintenance | 30 Hours
Continuous |
|
| 15-Jul-26 10:00 | 16-Jul-26 16:00 | ATCO | Outage | 856s 904 (856s Kinosis) | trip coil testing, breaker maintenance | 30 Hours
Continuous |
|
| 15-Jul-26 11:00 | 27-Jul-26 16:00 | ATCO, ALTALINK | Outage | 6L126 (743s Sarah Lake - 515L tap), 743s 601 (743s Sarah Lake) | 743S Sarah lake rebuild. Replace breaker 601 | 317 Hours
Continuous |
|
| 15-Jul-26 14:01 | 05-Oct-26 09:00 | ALTALINK | Outage | 417L (55s Olds - 281s Johnson), 55s T1 (55s Olds), 55s T2 (55s Olds), 55s 417 (55S Olds), 287s 552 (287s Hazelwood), 55s 2 (55s Olds) | mobile install at 55s for P_C major upgrade, repair/replace s80, s83, s84. salvage s51. | 1,962.98 Hours
Continuous |
|
| 16-Jul-26 07:00 | 16-Jul-26 17:00 | ALTALINK | RB | 600L (404s Peace Butte - 523s Bullshead) | 600L str 30, 102, 131, re-install keeper key top right phase - live line work | 9 Hours
Continuous |
|
| 16-Jul-26 07:00 | 21-Jul-26 17:00 | SUNCOR | Outage | 635EDD-1000 635PK-1000 (635EDD-1000), 635EDD-1000 635-752-132 (635EDD-1000), 635EDD-1000 635-752-131 (635EDD-1000), 635EDD-1000 635PS-1017 (635EDD-1000), 635EDD-1000 635PS-1018 (635EDD-1000), 635EDD-1000 635PS-1040 (635EDD-1000), 635EDD-1000 635PS-1016 (635EDD-1000) | 6 year planned maintenance on 144kV equipment | 130 Hours
Continuous |
|
| 16-Jul-26 08:00 | 16-Jul-26 16:00 | ENMAX | TE | Protection & Control (SS-23) | 23sub zone 31 138kV bus differential, 86-Z31 lockout relay protection outage | 8 Hours
Continuous |
|
| 16-Jul-26 08:30 | 16-Jul-26 16:00 | ALTALINK | Outage | 256s C1 (256s Harmattan) | PRC maintenance on the cap bank protection | 7.5 Hours
Continuous |
|
| 16-Jul-26 08:30 | 16-Jul-26 16:00 | ALTALINK | TE | 256s Protection & Control (256s Harmattan) | PRC maintenance | 7.5 Hours
Continuous |
|
| 16-Jul-26 09:00 | 16-Jul-26 16:00 | ATCO | TE | ATCO Telecom Equipment, 2091s RTU/SCADA (2091s Thornton) | Smoky River_T-Telecom-MDR Radio | 7 Hours
Continuous |
|
| 16-Jul-26 09:30 | 16-Jul-26 12:30 | ALTALINK | Outage | 38s C1 (38s East Edmonton), 38s C2 (38s East Edmonton) | cap bank weed spraying | 3 Hours
Continuous |
|
| 16-Jul-26 10:00 | 16-Jul-26 14:00 | ALTALINK | TE | 178s RTU/SCADA (178s Cynthia), 359s RTU/SCADA (359s Esso West Pembina), AltaLink Telecom Equipment | Firewall upgrade with a switch changeout. MPLS Node Firmware upgrade as well, SCADA VLAN Config.
|
4 Hours
Daily |
|
| 16-Jul-26 15:00 | 16-Jul-26 17:00 | ALTALINK | Trans Test | 157s 852 (157s Lac La Biche) | multiple breaker operations required to sync POW controller | 2 Hours
Continuous |
|
| 17-Jul-26 06:00 | 18-Jul-26 18:00 | ALTALINK | Outage | 42s 3W (42s Sarcee), 3L (42s Sarcee - 272s Springbank) | replacing cross arms and insulators on structures 373, 387, & 390
|
36 Hours
Continuous |
|
| 17-Jul-26 08:00 | 17-Jul-26 16:00 | ALTALINK | TE | 86s RTU/SCADA (86s Bigstone) | split the existing SCADA VLAN from 1 to 1 and 2
|
8 Hours
Continuous |
|
| 17-Jul-26 08:00 | 17-Jul-26 18:00 | ENMAX | Outage | 14.1C (SS-14), 14.2C (SS-14), 14.83L (SS-14 - SS-36), 14.4TR (SS-14), 14.2TR (SS-14), SW84 (SS-14), 14B138-14.83 (SS-14), 14MD138-14.4TR (SS-14), 14MD138-14.2TR (SS-14), 36B138-14.83 (SS-36) | power factor test, reversing switch check and oil sampling | 10 Hours
Continuous |
|
| 17-Jul-26 09:00 | 17-Jul-26 11:00 | BCH | Outage | 2L293 (BCH Nelway - BCH Selkirk) | 2CT2 energization | 2 Hours
Continuous |
AB-BC |
| 17-Jul-26 10:00 | 20-Jul-26 14:00 | ATCO | RB | 6L56 (763s Hanna - 802s Michichi Creek) | climbing inspection on 6L56 between Hanna and Michichi | 76 Hours
Continuous |
|
| 17-Jul-26 10:00 | 17-Jul-26 14:00 | ALTALINK | Outage | 252s T2 (252s Jarrow) | install T2 transformer grounding | 4 Hours
Continuous |
|
| 17-Jul-26 11:00 | 25-Jul-26 15:30 | ALTALINK | Outage | 526s 652 (526s Buffalo Creek) | replace 526s652 breaker | 196.5 Hours
Continuous |
|
| 18-Jul-26 08:00 | 18-Jul-26 18:00 | ENMAX | Outage | 33.84L (SS-33 - SS-43), 43.2TR (SS-43), 43B138-33.84 (SS-43), 33B138-33.84 (SS-33), 43MD138-43.2TR (SS-43) | substation structure painting | 10 Hours
Continuous |
|
| 18-Jul-26 08:00 | 18-Jul-26 16:00 | ENMAX | Outage | 32.2TR (SS-32) | 32.2TR transformer repair | 8 Hours
Continuous |
|
| 18-Jul-26 11:00 | 18-Jul-26 12:00 | ATCO | Outage | 914s Bindloss, 893s Cavendish, 7L760 (7LA760 tap - 7LC760 tap) | Outage Required to put 7L760D4 into service. Open D3, Open D5, Open D1 ??Obtain GOI (1-hour) To put D4 in service Remove temp D4 bypass jumpers Install risers to D4 |
1 Hour
Continuous |
|
| 18-Jul-26 11:00 | 18-Jul-26 16:00 | ATCO | RB | 6L09 (763s Hanna - 776s Richdale) | reclosing blocked for 7L760 outages 1-528265 and 1-528266 | 5 Hours
Continuous |
|
| 18-Jul-26 12:15 | 18-Jul-26 16:00 | ATCO | Outage | 7L760 (7LA760 tap - 7LC760 tap) | Outage Required to put 7L760D4 into service. Remove standoff insulators from structure 495 that were installed for the temporary bypass Splice out temporary jumpers J1, permanently removing J1 |
3.75 Hours
Continuous |
|
| 19-Jul-26 08:00 | 19-Jul-26 18:00 | ENMAX | Outage | 24.81L (SS-24 - SS-31), 31.84L (SS-31 - SS-32), 31.3TR (SS-31), 31.2TR (SS-31), 31B138-31.84 (SS-31), 31B138-24.81 (SS-31), 32B138-31.84 (SS-32), 24B138-24.81 (SS-24), 31MD138-31.2TR (SS-31), 31MD138-31.3TR (SS-31) | spring substation washing and 31 sub maintenance | 10 Hours
Continuous |
|
| 19-Jul-26 08:00 | 19-Jul-26 18:00 | ENMAX | Outage | 31.1C (SS-31) | 31sub spring substation washing, cap bank outage required while 138kV PTs offline | 10 Hours
Continuous |
|
| 19-Jul-26 09:00 | 20-Jul-26 09:00 | ATCO | Outage | 6L12 (774s Monitor - 6L25 tap), 774s 601 (774s Monitor) | outage required on 6L12 between Sullivan and 6L25 Tap for structure replacements and deficiency repair
|
24 Hours
Continuous |
|
| 20-Jul-26 07:00 | 02-Aug-26 17:00 | EPCOR | Outage | 987s T1 (987s Clover Bar), 987s CCP7213 (987s Clover Bar), 987s CCP7214 (987s Clover Bar), 987s C2401 (987s Clover Bar), 987s C2403 (987s Clover Bar) | cloverbar: C2401/C2403 breaker maintenance and CT doble and CDS19 LCR and C2401 relay maintenance | 322 Hours
Continuous |
|
| 20-Jul-26 07:00 | 23-Jul-26 18:00 | ALTALINK, TRANSALTA | Outage | 179s 733 (179s Gleichen), 428s 733X (428s Namaka), 733L (179s Gleichen - 428s Namaka) | interphase spacers str: 181, 193, 195, 196
repair conductor with sleeve or preform splice: 181,193, 195, 196 str change: 211 (foundation in concrete) arm/insulator change str: 161, 163, 165 " |
81 Hours
Continuous |
|
| 20-Jul-26 07:00 | 23-Jul-26 17:00 | ALTALINK, EPCOR | Outage | 1057L (89s Ellerslie - 657s Summerside), 657s SU2401 (657s Summerside), 657s SU2402 (657s Summerside), 89s 352 (89s Ellerslie), 89s 452 (89s Ellerslie), 657s SUDS9 (657s Summerside), 89s 1057 (89s Ellerslie) | 1057L/Summerside: CVT/arrestor doble, SUDS1/SUDS3/SUDS9 disconnect maintenance | 82 Hours
Continuous |
|
| 20-Jul-26 07:00 | 23-Jul-26 17:00 | EPCOR | Outage | 805s T3 (805s Jasper) | jasper: transformer3 tap changer investigation w/vendor | 82 Hours
Continuous |
|
| 20-Jul-26 07:00 | 31-Jul-26 17:00 | ALTALINK, EPCOR | TE | 908AL (52S East Industrial - 908L tap) | 908LW: protection blocking for MPLS cutovers and commissioning | 274 Hours
Continuous |
|
| 20-Jul-26 07:00 | 31-Jul-26 17:00 | ALTALINK, EPCOR | TE | 1059AL (52s East Industrial - 1059L tap), 1059L (EP 803s Lambton - 1059AL tap) | 1059L: protection blocking for MPLS cutovers and commissioning | 274 Hours
Continuous |
|
| 20-Jul-26 07:00 | 29-Jul-26 09:00 | ALTALINK | Outage | 77s 40 (77s Sagitawah) | protection upgrade | 218 Hours
Continuous |
|
| 20-Jul-26 07:00 | 30-Jul-26 17:00 | ALTALINK | TE | 238s RTU/SCADA (238s Shell Harmattan) | RTU configuration update | 250 Hours
Daily |
|
| 20-Jul-26 07:00 | 31-Dec-26 17:00 | EPCOR | TE | Protection & Control (Woodcroft) | woodcroft: protection blocking for TX1 LCR, line protection testing, and repairs | 3,947 Hours
Continuous |
|
| 20-Jul-26 07:00 | 04-Sep-26 17:00 | EPCOR | TE | 330p Protection & Control (330p Genesee) | genesee: protection blocking, firmware updates | 1,114 Hours
Continuous |
|
| 20-Jul-26 07:00 | 20-Jul-26 17:00 | ALTALINK, TRANSALTA | Outage | 33s 2 (33s Spray), 33s T2 (33s Spray) | brushgear maintenance | 10 Hours
Continuous |
|
| 20-Jul-26 07:00 | 21-Jul-26 17:00 | ALTALINK | TE | 310p Protection & Control (310p Sundance) | isolating protections for CT1252 testing, protections restored daily. | 34 Hours
Daily |
|
| 20-Jul-26 07:30 | 29-Jul-26 08:30 | ATCO, ALTALINK | RB | 9L938 (77s Sagitawah - 809s Louise Creek) | reclosing blocked for AltaLink | 217 Hours
Continuous |
|
| 20-Jul-26 08:00 | 21-Jul-26 17:00 | ALTALINK | RB | 151s 733E (151s Strathmore), 428s 733N (428s Namaka), 733L (151s Strathmore - 428S Namaka) | replace install keeper key str: 131
|
33 Hours
Continuous |
|
| 20-Jul-26 08:00 | 27-Jul-26 16:00 | ATCO | Outage | 7L48 (794s Valleyview - 7LA48 tap), 794s 703 (794s Valleyview) | pole replacement from test and treat | 176 Hours
Continuous |
|
| 20-Jul-26 08:00 | 20-Jul-26 16:00 | ENMAX, ALTALINK | Outage | 28.80L (42s Sarcee - SS-28), 28B138-28.80 (SS-28), 42s 28 (42s Sarcee) | hv breaker maintenance | 8 Hours
Continuous |
|
| 20-Jul-26 08:00 | 20-Jul-26 16:00 | ENMAX, ALTALINK | IO | 28.80L (42s Sarcee - SS-28) | enmax hv breaker maintenance | 8 Hours
Continuous |
|
| 20-Jul-26 08:00 | 21-Jul-26 17:00 | ALTALINK | Outage | 310p 1252 (310p Sundance) | test 310p1252 CTs | 33 Hours
Continuous |
|
| 20-Jul-26 08:00 | 20-Jul-26 16:00 | ALTALINK | TE | 95s RTU/SCADA (95s Imperial Oil Edmonton) | split the existing SCADA vlan from 1 to 1 and 2, no impact on production | 8 Hours
Continuous |
|
| 20-Jul-26 08:00 | 31-Jul-26 16:00 | ALTALINK, EPCOR | TE | 38s Protection & Control (38s East Edmonton), 1059AL (52s East Industrial - 1059L tap), 1059L (38s East Edmonton - 1059AL tap), 1059L (EP 803s Lambton - 1059AL tap) | 1059L, relay testing and cutover, protection blocking, EPCOR MPLS Upgrade, TPR cutover, commissioning, EPCOR Ref. #: OE114341 | 272 Hours
Continuous |
|
| 20-Jul-26 08:00 | 31-Jul-26 16:00 | ALTALINK, EPCOR | TE | 38s Protection & Control (38s East Edmonton), 89s Protection & Control (89s Ellerslie), 908L (38s East Edmonton - 908AL tap), 908AL (52S East Industrial - 908L tap), 908L (89s Ellerslie - 816s Petrolia), 908L (89s Ellerslie - 908AL tap) | relay testing and cutover, protection blocking, MPLS Upgrade, TPR Cutover, Commissioning, OE114342
|
272 Hours
Continuous |
|
| 20-Jul-26 08:00 | 23-Jul-26 16:00 | ALTALINK | TE | 1080s RTU/SCADA (1080s Raptor) | RTU config updates to remove RAS alarms from HMI. Visibility will be lost for approx. 5 min. during re-boots. | 80 Hours
Daily |
|
| 20-Jul-26 08:00 | 20-Jul-26 16:00 | ENMAX | TE | Protection & Control (SS-2) | 2 sub 86 breaker fail-D84 protection outage. relays, lockout testing. back up fault clearing time 5.5 cycles | 8 Hours
Continuous |
|
| 20-Jul-26 08:00 | 21-Jul-26 16:00 | ENMAX | Outage | 38.1TR (SS-38) | tap changer inspection - 38.1-TC. tap changer reversing switch check | 32 Hours
Continuous |
|
| 20-Jul-26 08:00 | 23-Jul-26 16:00 | ENMAX | Outage | 31.1TR (SS-31) | transformer power factor test, secondary cable test. transformer maintenance. relay fault pressure test. oil sampling | 80 Hours
Continuous |
|
| 20-Jul-26 08:00 | 21-Jul-26 16:00 | ENMAX | Outage | 9.1TR (SS-9) | secondary cabinet measurements and CT testing | 32 Hours
Continuous |
|
| 20-Jul-26 08:00 | 21-Jul-26 16:00 | ENMAX | Outage | 13.82L (SS-13 - SS-22), 13B138-13.82 (SS-13), 22B138-13.82 (SS-22) | 13-sub disconnect switch replacement, sco/qmf work | 32 Hours
Continuous |
|
| 20-Jul-26 08:00 | 24-Jul-26 16:00 | ALTALINK | TE | 254s RTU/SCADA (254s Coaldale) | update the RTU/HMI configuration. the supervisory outage will be returned by EOD everyday. | 104 Hours
Daily |
|
| 20-Jul-26 08:00 | 24-Jul-26 16:00 | ALTALINK | TE | 254s Protection & Control (254s Coaldale) | need to take the protection outage for A protection (SEL-311C) to update relay settings, this outage will be returned EOD, every day | 104 Hours
Daily |
|
| 20-Jul-26 08:00 | 30-Jul-26 15:00 | CMH | TE | MH-60L (MHS-5 NE Crescent Heights - MHS-7 Brier Park) | perform preventative maintenance on LDR-60L-A. | 247 Hours
Continuous |
|
| 20-Jul-26 08:00 | 21-Jul-26 16:00 | ATCO | RB | 7L03 (731s Elmworth - 7L09 tap), 7L03 (749s Flyingshot Lake - 7L09 tap) | complete the remaining 1 structure | 32 Hours
Continuous |
|
| 20-Jul-26 08:00 | 21-Jul-26 16:00 | ENMAX | TE | Protection & Control (SS-8) | 8 sub 138kV bus differential zone 43 "A" protection outage. relay protection test - 8RLY138-8.ZE4-E3 A GE. back-up clearing time 5.5 cycles | 32 Hours
Continuous |
|
| 20-Jul-26 09:00 | 21-Jul-26 18:00 | ALTALINK, GWPCORP | Outage | 138s 2552 (138s Windy Flats), 603L (138s Windy Flats - 243s Soderglen), 243s Soderglen | maintenance on 243s138DS1 | 33 Hours
Continuous |
|
| 20-Jul-26 09:00 | 23-Jul-26 17:30 | ALTALINK, EPCOR | IO | 1057L (89s Ellerslie - 657s Summerside) | 1057L/Summerside: CVT/Arrestor Doble, SUDS1/SUDS3/SUDS9 disconnect maintenance | 80.5 Hours
Continuous |
|
| 20-Jul-26 09:00 | 24-Jul-26 17:00 | BCH | RB | 5L92 (BCH Cranbrook - BCH Selkirk) | 5L92 LLP/ANR - barehand insulator replacement | 104 Hours
Continuous |
AB-BC |
| 20-Jul-26 09:00 | 24-Jul-26 17:00 | BCH | RB | 2L113 (BCH Cranbrook - BCH Natal) | LLP work - hazard tree removals between 10-01 to 44-01 | 104 Hours
Daily |
AB-BC |
| 20-Jul-26 09:30 | 20-Jul-26 13:30 | Lethbridge | TE | 146s RTU/SCADA (146s Macdonald) | replace rx1500, commission new rx1524, cc will lose comms to 146s, substation tech on site | 4 Hours
Continuous |
|
| 20-Jul-26 10:00 | 21-Jul-26 16:00 | ATCO | Outage | 825s 905 (825s Whitefish Lake) | breaker maintenance | 30 Hours
Continuous |
|
| 20-Jul-26 10:00 | 21-Jul-26 15:00 | ATCO | Outage | 7L85 (804s Wintering Hills - 7LA85 tap), 804s 702 (804s Wintering Hills) | breaker SF6 GL312 TESTING - 702 @ 804S | 29 Hours
Continuous |
|
| 20-Jul-26 10:00 | 24-Jul-26 16:00 | ATCO | Outage | 7L135 (820s Hangingstone - 977s Salt Creek), 977s 901T (977s Salt Creek) | transformer and tap changer maintenance | 102 Hours
Continuous |
|
| 20-Jul-26 10:00 | 20-Jul-26 11:00 | ATCO | RB | 7L34 (815s Goodfare - 886s Updike) | HOP to disconnect 902S mobile 3 - opening Jumper J1 | 1 Hour
Continuous |
|
| 20-Jul-26 10:00 | 23-Jul-26 17:30 | ALTALINK | RB | 472AL (221s Sunken Lake - 472L tap), 472L (213s Hughenden - 472AL tap), 472L (648s Metiskow - 472AL tap) | 472L 204, 208, 241, 245, 343, 358, 367.replace arms, glass, structure 241. | 79.5 Hours
Continuous |
|
| 20-Jul-26 10:00 | 20-Jul-26 16:00 | ALTALINK | TE | 255s Protection & Control (255s Vulcan) | techs to complete PRC maintenance on the following redundant relays: 161L (L1) line prot, 161L (L1) line prot, one at a time | 6 Hours
Continuous |
|
| 20-Jul-26 10:00 | 20-Jul-26 20:00 | ALTALINK, EPCOR | Outage | 700L (422s Westwood - 746L tap), 700L (746s Sherwood Park - 746L tap), 746L (700L tap - 746AL tap), 422s 700 (422s Westwood), 746s 700N (746s Sherwood Park) | urgent high load move on 700L/746L due to a road washout, causing the delivery of equipment to take an alternate route | 10 Hours
Daily |
|
| 20-Jul-26 11:30 | 27-Jul-26 14:30 | ATCO, ALTALINK | RB | 199L (347s AML Fox Creek - 741s ATC Fox Creek) | 14 Red tag pole change program | 171 Hours
Continuous |
|
| 20-Jul-26 12:00 | 27-Jul-26 14:00 | ATCO, ALTALINK | RB | 7L199 (347s AML Fox Creek - 741s ATC Fox Creek) | 14 Red tag pole change program | 170 Hours
Continuous |
|
| 20-Jul-26 13:00 | 23-Jul-26 15:00 | ATCO | RB | 7L85 (801s Anderson - ATC 803s Bullpound), 7L85 (803s ATC Bullpound - 7LA85 tap), 7L85 (804s Wintering Hills - 7LA85 tap) | HOP required for installing interphase spacers on 7L85 live line. | 74 Hours
Continuous |
|
| 20-Jul-26 13:00 | 23-Jul-26 17:00 | ALTALINK | Outage | 767L (310p Sundance - 767AL tap), 310p 767X (310p Sundance) | breaker maintenance on 310p767X | 76 Hours
Continuous |
|
| 20-Jul-26 14:30 | 07-Aug-26 17:00 | ALTALINK | Outage | 1083L (63s Red Deer - 288s Wolf Creek), 63s 452 (63s Red Deer), 63s 552 (63s Red Deer), 288s 352 (288s Wolf Creek), 288s 152 (288s Wolf Creek), 288s 1083 (288s Wolf Creek), 63s 1083 (63s Red Deer) | 63s452 breaker replacement | 434.5 Hours
Continuous |
|
| 20-Jul-26 14:30 | 23-Jul-26 16:30 | ALTALINK | Outage | 157s 788N (157s Lac La Biche), 788L (157s Lac La Biche - 788AL tap) | 157s788N breaker maintenance | 74 Hours
Continuous |
|
| 20-Jul-26 14:30 | 23-Jul-26 16:30 | ATCO, ALTALINK | RB | 788L (898s Heart Lake - 788AL tap) | reclosing blocked 0n 788L for AltaLink | 74 Hours
Continuous |
|
| 21-Jul-26 06:00 | 21-Jul-26 18:00 | SUNCOR | Outage | 635EDD-1000 635-752-113 (635EDD-1000) | 144kV Breaker outage required to replace merging unit with faulty core | 12 Hours
Continuous |
|
| 21-Jul-26 07:00 | 27-Jul-26 17:30 | ATCO | TE | 743s Protection & Control (743s Sarah Lake) | isolating 21A/6L126 for relay testing | 154.5 Hours
Continuous |
|
| 21-Jul-26 07:00 | 27-Jul-26 17:30 | ATCO | TE | 743s Protection & Control (743s Sarah Lake) | isolating 21B/6L126 for relay testing | 154.5 Hours
Continuous |
|
| 21-Jul-26 07:00 | 27-Jul-26 17:30 | ATCO | TE | 743s Protection & Control (743s Sarah Lake) | isolating 86-50BF-1/600BS1 and 94-50BF-1/600BS1 (50BF-600BS1) | 154.5 Hours
Continuous |
|
| 21-Jul-26 07:00 | 27-Jul-26 17:30 | ATCO | TE | 743s Protection & Control (743s Sarah Lake) | 50BF/601 for relay testing | 154.5 Hours
Continuous |
|
| 21-Jul-26 07:30 | 21-Jul-26 15:30 | ALTALINK | Outage | 993s T2 (993s Abee) | replace the cabinet cover on the T2 NGR | 8 Hours
Daily |
|
| 21-Jul-26 08:00 | 22-Jul-26 17:00 | ATCO | Outage | 7L65 (709s Vegreville - 7LA65 tap), 7L65 (710s Vermilion - 7LA65 tap), 7LA65 (708s Grizzly Bear - 7L65 tap) | Switch Repairs, 7LA65D1 | 33 Hours
Continuous |
|
| 21-Jul-26 08:00 | 21-Jul-26 16:00 | ALTALINK, CHDI | TE | AltaLink Telecom Equipment, 322s RTU/SCADA (322s Cowley Ridge) | fix issues | 8 Hours
Continuous |
|
| 21-Jul-26 08:00 | 21-Jul-26 17:00 | ALTALINK | TE | 171s RTU/SCADA (171s Redwater) | split the existing SCADA VLAN from 1 to 1 and 2 and firewall upgrade | 9 Hours
Continuous |
|
| 21-Jul-26 08:00 | 22-Jul-26 16:00 | ENMAX | Outage | 2.80L (SS-2 - SS-23), 23B138-2.80 (SS-23) | 23B138-2.80 Rebuild dash pot, low oil. HV Breaker SF6 Gas Sample | 32 Hours
Continuous |
|
| 21-Jul-26 08:00 | 21-Jul-26 16:00 | ALTALINK | TE | 237s RTU/SCADA (237s Foothills) | to push new configuration to add points for future SCADA fault reporting project | 8 Hours
Continuous |
|
| 21-Jul-26 08:00 | 22-Jul-26 16:00 | ENMAX | Outage | 2.80L (SS-2 - SS-23), 2B138-D93 (SS-2), 2B138-D94 (SS-2) | Install ITBs - 2RLY138-D93-D94 (BMR7). Relay maint. | 32 Hours
Continuous |
|
| 21-Jul-26 08:00 | 29-Jul-26 16:00 | ENMAX | Outage | 1.80L (SS-1 - SS-28), 28B138-1.80 (SS-28) | transmission tower climbing inspection | 200 Hours
Continuous |
|
| 21-Jul-26 08:00 | 25-Jul-26 12:00 | ENMAX | Outage | 20.82L (SS-20 - SS-21) | Transmission tower climbing inspection | 100 Hours
Continuous |
|
| 21-Jul-26 08:00 | 21-Jul-26 17:00 | ATCO | TE | ATCO Telecom Equipment, 2009s RTU/SCADA (2009s Willow Lake) | both firewalls at the Willow Lake substation will undergo a scheduled upgrade to maintain system security and to remove any bugs on the system | 9 Hours
Continuous |
|
| 21-Jul-26 08:00 | 21-Jul-26 17:00 | ATCO | TE | 718s RTU/SCADA (718s Parsons Creek), ATCO Telecom Equipment | both firewalls at the Parsons Creek substation will undergo a scheduled upgrade to maintain system security and to remove any bugs on the system | 9 Hours
Continuous |
|
| 21-Jul-26 10:00 | 21-Jul-26 14:00 | ALTALINK | TE | AltaLink Telecom Equipment | MPLS firmware upgrade | 4 Hours
Daily |
|
| 21-Jul-26 11:01 | 21-Jul-26 20:00 | SUNCOR | Outage | 29EDD-1 29EDD1s552 (29EDD-1 Millennium) | maintenance | 6.98 Hours
Continuous |
|
| 22-Jul-26 07:00 | 23-Jul-26 16:00 | ALTALINK | Outage | 310p 1352 (310p Sundance) | Test 310p1352 CTs | 33 Hours
Continuous |
|
| 22-Jul-26 07:00 | 23-Jul-26 16:00 | ALTALINK, EPCOR | RB | 909L (310p Sundance - 665s Dome) | 909LW recloser blocked at Dome e665S | 33 Hours
Continuous |
|
| 22-Jul-26 07:00 | 23-Jul-26 17:00 | ALTALINK | TE | 310p Protection & Control (310p Sundance) | isolate protections for CT1352 testing | 34 Hours
Daily |
|
| 22-Jul-26 08:00 | 10-Aug-26 16:00 | Syncrude | Outage | Mildred T6 (Syncrude Mildred Lake), 635 (Syncrude Mildred Lake) | repair tap changer in T6 transformer | 464 Hours
Continuous |
|
| 22-Jul-26 08:00 | 23-Jul-26 16:00 | ALTALINK | Outage | 745A1L (975s Dalehurst - 745AL tap), 975s T1 (975s Dalehurst), 975s 745 (975s Dalehurst) | salvage underground feeder cables and install new slack span and new riser pole outside of fence
|
32 Hours
Continuous |
|
| 22-Jul-26 08:00 | 22-Jul-26 17:00 | ALTALINK | TE | AltaLink Telecom Equipment, 681s RTU/SCADA (681s Bannerman) | 681s Firewall Upgrade. Mpls Node A and B upgrade, SCADA SUB LAN Work. Loss of 681s visibility for 2 hours in the timeframe indicated. 776L TPR OOS 50ms during reroute. All other TPR redundant. | 9 Hours
Daily |
|
| 22-Jul-26 08:00 | 23-Jul-26 16:00 | ENMAX | TE | Protection & Control (SS-41) | relay protection test - 41RLY138-41.ASW | 32 Hours
Continuous |
|
| 22-Jul-26 08:00 | 22-Jul-26 16:00 | ENMAX | TE | Protection & Control (SS-21) | 21PT69-1 outage and power factor test | 8 Hours
Continuous |
|
| 22-Jul-26 08:00 | 23-Jul-26 16:00 | ALTALINK | TE | 281s RTU/SCADA (281s Johnson) | Intermittent RTU outages for Techs to complete firmware upgrade and configuration changes on the RTU for Fault reporting implementation. Temporary loss of analogs while firmware and configuration are updated. | 32 Hours
Daily |
|
| 22-Jul-26 08:00 | 22-Jul-26 17:00 | ATCO | TE | 757s RTU/SCADA (757s Battle River), ATCO Telecom Equipment | upgrade to maintain system security and to remove any bugs on the system | 9 Hours
Continuous |
|
| 22-Jul-26 08:00 | 23-Jul-26 16:00 | ENMAX | TE | Protection & Control (SS-8) | relay protection test - 8RLY138-8.ZE3-E2 A GE | 32 Hours
Continuous |
|
| 22-Jul-26 09:00 | 23-Jul-26 16:00 | ALTALINK | TE | 281s Protection & Control (281s Johnson) | implement fault reporting | 31 Hours
Daily |
|
| 22-Jul-26 10:00 | 22-Jul-26 14:00 | ALTALINK, TRANSALTA | Outage | 250p T1 (250p Bighorn Plant), 250p 1 (250p Bighorn Plant) | maintenance | 4 Hours
Continuous |
|
| 22-Jul-26 10:00 | 23-Jul-26 17:30 | ATCO, OWF2 | Outage | 804s 703 (804s Wintering Hills), 7L153 (609s Wheatland - 804s Wintering Hills) | BREAKER SF6 GL312 TESTING - 703 @ 804S | 31.5 Hours
Continuous |
|
| 22-Jul-26 12:31 | 22-Jul-26 18:00 | ATCO, ALTALINK | IO | 9L939 (77s Sagitawah - 809s Louise Creek) | Reclosing Blocked for AltaLink's work on 77s57 | 5.48 Hours
Continuous |
|
| 22-Jul-26 15:30 | 22-Jul-26 17:30 | ATCO | TE | ATCO Telecom Equipment, 804s RTU/SCADA (804s Wintering Hills), 963s RTU/SCADA (963s Coyote Lake) | UPGRADING COYOTE NET 2, NET 11 AND HIGHLAND SUB SAR OS TO V21, THEN V22 Please see the email that was sent on May 7, 2026 about all the circuits impacted TRAFFIC interuppted FOR UP TO 90 MINS |
2 Hours
Continuous |
|
| 22-Jul-26 15:30 | 22-Jul-26 17:30 | ATCO | RB | 7L128 (802s Michichi Creek - 7LA128 tap), 7L128 (963s Coyote Lake - 7LA128 tap) | disable reclosing for telecom work 1-00524894 | 2 Hours
Continuous |
|
| 22-Jul-26 15:30 | 22-Jul-26 17:30 | ATCO | RB | 7L85 (801s Anderson - ATC 803s Bullpound), 7L85 (803s ATC Bullpound - 7LA85 tap), 7L85 (804s Wintering Hills - 7LA85 tap) | disable reclosing for telecom work 1-00524894 | 2 Hours
Continuous |
|
| 23-Jul-26 07:00 | 24-Jul-26 17:00 | EPCOR | Outage | RR729 (Rossdale) | RR729, DFR upgrade project | 34 Hours
Continuous |
|
| 23-Jul-26 08:00 | 04-Aug-26 16:00 | Syncrude | Outage | 23 (Aurora), 22B (Aurora), 23A (Aurora), 89-26 (Aurora) | Zone 10 6yr PM | 224 Hours
Continuous |
|
| 23-Jul-26 08:00 | 23-Jul-26 17:00 | ALTALINK | TE | 308s RTU/SCADA (308s Albchem Beaverhill Creek) | split the existing SCADA VLAN from 1 to 1 and 2 | 9 Hours
Continuous |
|
| 23-Jul-26 08:00 | 23-Jul-26 12:00 | ENMAX | Outage | 65B240-D134 (SS-65) | HV breaker SF6 gas sample - 65B240-D134 | 4 Hours
Continuous |
|
| 23-Jul-26 08:00 | 29-Jul-26 16:00 | ALTALINK | TE | 77s RTU/SCADA (77s Sagitawah) | RTU database update | 152 Hours
Daily |
|
| 23-Jul-26 08:00 | 25-Jul-26 16:00 | Syncrude | Outage | 211 (Aurora) | replace failed interposing relay | 56 Hours
Continuous |
|
| 23-Jul-26 08:00 | 23-Jul-26 16:00 | ENMAX | TE | Protection & Control (SS-2) | 2 sub 86 BF-D83 protection outage | 8 Hours
Continuous |
|
| 23-Jul-26 08:00 | 23-Jul-26 16:00 | ENMAX | Outage | 15.62L (SS-15 - SS-16), 16B69-15.62 (SS-16), 15B69-15.62 (SS-15) | breaker power factor test - 16B69-15.62 | 8 Hours
Continuous |
|
| 23-Jul-26 09:00 | 23-Jul-26 16:00 | ATCO | TE | ATCO Telecom Equipment | radio major | 7 Hours
Continuous |
|
| 23-Jul-26 10:00 | 23-Jul-26 14:00 | ALTALINK | Outage | 250p 2 (250p Bighorn Plant) | maintenance | 4 Hours
Continuous |
|
| 23-Jul-26 10:00 | 23-Jul-26 16:00 | ATCO | TE | ATCO Telecom Equipment, 861s RTU/SCADA (861s Eureka River) | Aprisa radio major Clear Hills to Eureka |
6 Hours
Continuous |
|
| 23-Jul-26 12:00 | 23-Jul-26 16:00 | ENMAX | Outage | 65B240-D135 (SS-65) | HV breaker SF6 gas sample | 4 Hours
Continuous |
|
| 24-Jul-26 07:00 | 24-Jul-26 17:00 | EPCOR | RB | 1055L (629s Argyll Transfer Station - 816s Petrolia) | 1055L: Reclose Blocking for Insulator Testing Demo | 10 Hours
Continuous |
|
| 24-Jul-26 07:30 | 29-Jul-26 16:30 | ALTALINK | Outage | 304s 352 (304s Shell Limestone), 304s T2 (304s Shell Limestone) | customer maintenance.
|
129 Hours
Continuous |
|
| 24-Jul-26 08:00 | 24-Jul-26 17:00 | ALTALINK | TE | 293s RTU/SCADA (293s Bernese) | Upgrade Firewall , Telecom Switch, and SCADA VLAN config. Loss of 293s visibility for 2 hours in the timeframe indicated. | 9 Hours
Daily |
|
| 24-Jul-26 08:00 | 24-Jul-26 16:00 | ENMAX | Outage | 40.81L (SS-40 - SS-41), 40.2TR (SS-40), 40B138-40.81 (SS-40), 41B138-40.81 (SS-41), SW83 (SS-40) | power factor test | 8 Hours
Continuous |
|
| 24-Jul-26 08:00 | 24-Jul-26 17:30 | ALTALINK | Outage | 719AL (581s Amoco Ricinus - 719L tap), 581s T1 (581s Amoco Ricinus) | urgent repair | 9.5 Hours
Continuous |
|
| 24-Jul-26 10:00 | 24-Jul-26 14:00 | ATCO | RB | 705s 144kV Bus (705s Kitscoty) | connect 144kV risers for 2000S, energize and let soak over the weekend | 4 Hours
Continuous |
| This document and the information contained herein are based upon information and data which by their nature contain a degree of uncertainty and are subject to change. In addition, this document may contain information and data from public sources and/or third parties, which have been assumed to be accurate and complete and have not been verified. Accordingly, the Independent System Operator, operating as the Alberta Electric System Operator (the "AESO") makes no warranty, representation or guarantee, express or implied, with respect to this document or the information contained herein, including, but not limited to, any warranty, representation or guarantee of accuracy, completeness, timeliness, reliability, availability, absence of computer virus, non- infringement, merchantability or suitability for any purpose. Under no circumstances will the AESO, its members, officers, employees, contractors or agents, or any of their respective affiliates, be liable for any errors or omissions in, or any losses, damages or claims whatsoever, whether in contract, tort or otherwise, arising from use of or reliance upon, this document or any information contained herein. © 2009 Alberta Electric System Operator. All rights reserved |