| Alberta Electric System Operator | |
| System Co-ordination Plan | |
| 2025-12-16 to 2026-01-09 | |
| Approved Outages |
| Previous Version | |
| Download CSV |
| From | To | Owner | Type | Element | Scheduled Activity | Date/Time Comments | Interconnection |
|---|---|---|---|---|---|---|---|
| 26-Jul-24 10:00 | 31-Jul-26 16:00 | ATCO | Outage | 826s 504R (826s Marguerite Lake) | emergency removal to replace failed 502R @834S | 735.25 Days
Continuous |
|
| 23-Aug-24 13:45 | 30-Jun-26 14:29 | ALTALINK | Outage | 157s C1 (157s Lac La Biche) | forced outage | 676.03 Days
Continuous |
|
| 11-Mar-25 00:00 | 31-Mar-26 16:00 | ALTALINK | Outage | 377s 473C (377s AML Hardisty) | forced outage | 385.67 Days
Continuous |
|
| 18-Mar-25 14:00 | 17-Mar-26 17:30 | ALTALINK | Outage | 217s C1 (217s North Red Deer) | cap. bank unavailable and cannot be energized due to Koncar CTs being present | 364.15 Days
Daily |
|
| 20-Mar-25 08:00 | 20-Mar-26 17:00 | ALTALINK | Outage | 256s C1 (256s Harmattan) | forced outage | 365.38 Days
Continuous |
|
| 31-Mar-25 07:00 | 19-Dec-25 17:00 | EPCOR | TE | Protection & Control (Woodcroft) | Woodcroft: protection blocking for merging unit and protection upgrade. | 263.46 Days
Continuous |
|
| 14-May-25 08:00 | 10-Feb-26 16:00 | ENMAX | TE | Protection & Control (SS-32) | 32sub 138kV autoswitching protection outage | 272.38 Days
Continuous |
|
| 13-Jun-25 17:00 | 11-Feb-26 17:00 | EPCOR | Outage | T3 (Rossdale) | Rossdale - TX3 LCR | 243.04 Days
Continuous |
|
| 21-Jul-25 09:00 | 19-Jan-26 17:00 | ATCO | TE | 732s Protection & Control (732s Mitsue) | the breaker fail protection will be disabled during the project, as we migrate from the existing to the new protection | 182.38 Days
Continuous |
|
| 21-Jul-25 09:00 | 23-Jan-26 16:30 | ATCO | TE | 732s RTU/SCADA (732s Mitsue) | existing RTU system being replaced with new SMP system | 186.35 Days
Continuous |
|
| 22-Jul-25 08:30 | 31-Mar-26 16:30 | ALTALINK | Outage | 263s C1 (263s Strachan) | forced outage | 252.33 Days
Continuous |
|
| 25-Jul-25 17:01 | 20-Feb-26 17:00 | EPCOR | Outage | T2 (EP Riverview) | bushing test failure (found during OE110184) | 210.04 Days
Continuous |
|
| 20-Aug-25 17:00 | 17-Dec-25 17:00 | ALTALINK | Outage | 1075L (28s West Brooks - 132s Ware Junction) | restoration from real time storm | 119.04 Days
Continuous |
|
| 25-Aug-25 08:00 | 03-Apr-26 16:00 | ENMAX | Outage | 32.1TR (SS-32) | slip over CT and new power cables installation and P&C works | 221.33 Days
Continuous |
|
| 02-Sep-25 08:00 | 28-Feb-26 16:00 | ENMAX | Outage | 38.1C (SS-38) | capacitor bank switcher replacement | 179.38 Days
Continuous |
|
| 12-Sep-25 08:00 | 06-Mar-26 16:00 | ENMAX | Outage | 33.1TR (SS-33) | tap changer refurbishments. soak test required | 175.38 Days
Continuous |
|
| 01-Nov-25 12:00 | 01-Feb-26 18:00 | ALTALINK | Outage | AML 511s ACF12 (AML 511s Crossings) | forced outage | 92.29 Days
Continuous |
|
| 03-Nov-25 07:00 | 19-Dec-25 17:00 | EPCOR | TE | 987s Protection & Control (987s Clover Bar) | protection blocking for P&C maintenance at Cloverbar | 46.42 Days
Continuous |
|
| 12-Nov-25 08:00 | 16-Jan-26 16:00 | ENMAX | Outage | 20.1TR (SS-20), 20BA8-20.1TR (SS-20), 20BB8-20.1TR (SS-20) | maintenance | 65.33 Days
Continuous |
|
| 21-Nov-25 08:00 | 09-Jan-26 16:00 | ENMAX | Outage | 38.3TR (SS-38) | 38.3TR secondary cable replacement | 49.33 Days
Continuous |
|
| 25-Nov-25 17:46 | 25-Jan-26 18:00 | ATCO | Outage | 876s 901T (876s Brintnell) | forced outage oil leaking | 61.01 Days
Continuous |
|
| 27-Nov-25 08:30 | 27-Nov-27 16:30 | ALTALINK | TE | 89s Protection & Control (89s Ellerslie) | DSP card replacements on1057L B87/L3 and B240B1 B87/240B1 | 730.33 Days
Daily |
|
| 01-Dec-25 07:00 | 18-Dec-25 18:00 | ENMAX | TE | Protection & Control (SS-39) | 39s auto-switching scheme protection outage, SS-39 HV SW replacement | 17.46 Days
Daily |
|
| 01-Dec-25 08:00 | 18-Dec-25 16:00 | ENMAX | Outage | 31.84L (SS-31 - SS-32), 31B138-31.84 (SS-31), 32B138-31.84 (SS-32) | 31.84L P&C cut over | 17.33 Days
Continuous |
|
| 01-Dec-25 08:00 | 19-Dec-25 12:30 | ENMAX | Outage | 39.82L (SS-39 - SS-162), 22.81L (SS-22 - SS-39), 39.2TR (SS-39), 39.4TR (SS-39), 22B138-22.81 (SS-22), 39B138-22.81 (SS-39), 39B138-39.82 (SS-39), SW83 (SS-39), 39MD138-39.2TR (SS-39), 39MD138-39.4TR (SS-39) | HV switch replacement | 18.19 Days
Continuous |
|
| 01-Dec-25 09:00 | 16-Dec-25 17:00 | BCH | Outage | 1L274 (48s Pocaterra - 978s BCH Britt Creek) | for LLP work | 15.33 Days
Daily |
AB-BC |
| 01-Dec-25 09:00 | 16-Dec-25 17:00 | ALTALINK | IO | 887L (48s Pocaterra - 978s BCH Britt Creek) | hazard tree removal along various sections of circuit near Elk Lakes provincial park | 15.33 Days
Daily |
|
| 04-Dec-25 07:00 | 19-Dec-25 18:00 | ALTALINK | RB | 1053L (132s Ware Junction - 324s Cassils) | due to proximity to 931L | 15.46 Days
Daily |
|
| 04-Dec-25 11:00 | 19-Dec-25 18:00 | ALTALINK | Outage | 931L (28s West Brooks - 132s Ware Junction) | install new structures as part of the 1075L storm restoration. | 15.29 Days
Continuous |
|
| 08-Dec-25 07:00 | 23-Dec-25 17:00 | EPCOR | Outage | 557s T1 (557s Castle Downs) | surge arrestor LCR | 15.42 Days
Continuous |
|
| 09-Dec-25 09:00 | 19-Dec-25 17:00 | BCH | Outage | 5L52 (BPA Custer - BCH Ingledow) | make emergent glass replacement on the circuit | 10.33 Days
Continuous |
AB-BC |
| 09-Dec-25 17:00 | 02-Feb-26 11:00 | ALTALINK | IO | 714L (397s Benbow – 1117s South Kaybob), 397s 714 (397s Benbow) | complete work on breaker and energize 397s 714 | 54.75 Days
Continuous |
|
| 11-Dec-25 00:00 | 17-Dec-25 18:00 | ATCO | Outage | 6L73 (729s Otauwau - 745s Slave Lake) | forced outage | 6.75 Days
Continuous |
|
| 12-Dec-25 01:30 | 17-Dec-25 18:00 | ALTALINK | Outage | 310p T30 (310p Sundance) | forced outage | 5.69 Days
Continuous |
|
| 13-Dec-25 08:00 | 16-Dec-25 16:00 | SUNCOR | Outage | 29EDD-34 260kV Bus 29PP-45 (29EDD-34), 29PL9-13 (29EDD-34 - 29EDD-65), 29EDD-34 29-952-112 (29EDD-34), 29EDD-34 29-952-113 (29EDD-34), 29EDD-34 29-952-123 (29EDD-34), 29EDD-34 29-952-133 (29EDD-34), 29EDD-34 29-952-143 (29EDD-34), 29EDD-65 29PS-0266 (29EDD-65 Edd65Sub) | inspection to bring 29PL9-13 back online and keep 29PP-45 offline for repairs | 3.33 Days
Continuous |
|
| 14-Dec-25 03:00 | 21-Dec-25 17:00 | ALTALINK | Outage | AML 511s SVC Plus (AML 511s Crossings) | forced | 7.58 Days
Continuous |
|
| 14-Dec-25 07:30 | 20-Dec-25 17:30 | ALTALINK | RB | 793L (87s Gaetz - 535s Joffre) | setting structures on 986L/962L str’s 25-55, working near str’s 31-65 on 793L | 6.42 Days
Daily |
|
| 15-Dec-25 07:00 | 18-Dec-25 17:00 | EPCOR | Outage | 72 kV Bus 2 (Rossdale), 72RW3 (Rossdale - Woodcroft), 72RV4 (EP 511s Victoria - Rossdale), 72RG7 (Garneau - Rossdale), RW727 (Rossdale), VHBB1 (Rossdale), VHBB2 (Rossdale), RG725 (Rossdale), RV726 (Rossdale), EP 511s VDS15 (EP 511s Victoria), GDS4 (Garneau), G725 (Garneau), G722 (Garneau), M723 (Meadowlark) | bus surge arrestor replacement | 3.42 Days
Continuous |
|
| 15-Dec-25 07:00 | 21-Dec-25 19:00 | ATCO | RB | 7L143 (766s Nevis - 769s Stettler) | facilitate work adjacent to line for CETO project | 6.5 Days
Continuous |
|
| 15-Dec-25 07:00 | 19-Dec-25 17:00 | ALTALINK, EPCOR | TE | 1139L (367s Harry Smith - EP Riverview) | protection blocking, relay maintenance | 4.42 Days
Continuous |
|
| 15-Dec-25 07:00 | 19-Dec-25 17:00 | EPCOR | TE | 72NW15 (Namao - Woodcroft) | protection blocking for 72NW15 line, CVT cutover | 4.42 Days
Continuous |
|
| 15-Dec-25 07:00 | 19-Dec-25 17:00 | EPCOR | TE | 72KN23 (Kennedale - Namao) | protection blocking for 72KN23 line, CVT cutover | 4.42 Days
Continuous |
|
| 15-Dec-25 07:00 | 19-Dec-25 17:00 | EPCOR | TE | 72VN21 (EP 511s Victoria - Namao) | protection blocking for 72VN21 line, CVT cutover | 4.42 Days
Continuous |
|
| 15-Dec-25 08:00 | 16-Dec-25 17:00 | ALTALINK | TE | 67s RTU/SCADA (67s Stirling) | implement supervisory controls and indication to RAS-43 | 1.38 Days
Daily |
|
| 15-Dec-25 08:00 | 16-Dec-25 17:00 | ALTALINK | TE | 67s Protection & Control (67s Stirling) | implement supervisory controls and indication to RAS 43 and investigate or configure remote access issues | 1.38 Days
Daily |
|
| 15-Dec-25 08:00 | 19-Dec-25 17:00 | ALTALINK | TE | 267s RTU/SCADA (267s Killarney Lake) | RTU database update | 4.38 Days
Daily |
|
| 15-Dec-25 08:00 | 19-Dec-25 17:00 | ATCO | RB | 7L86 (822s Wolf Lake - 1200s Foster Creek) | structure changes for line to ground clearance mitigation, live line work | 4.38 Days
Continuous |
|
| 15-Dec-25 09:00 | 19-Dec-25 16:00 | ATCO | RB | 7L171 (802s Michichi Creek - 804s Wintering Hills) | installing marker cones at critical crossing span 7L171-622 to 7L171-623 | 4.29 Days
Continuous |
|
| 15-Dec-25 09:00 | 16-Dec-25 18:00 | ALTALINK | Outage | 744L (235s Entwistle - 744AL tap), 235s 744W (235s Entwistle) | install dampers at structures 97A, 96A, 94A, 7 | 1.38 Days
Continuous |
|
| 15-Dec-25 09:00 | 16-Dec-25 18:00 | Saskpower | Outage | SASK POWER P2C | maintenance | 1.38 Days
Continuous |
AB-SK |
| 15-Dec-25 10:00 | 16-Dec-25 17:30 | ATCO | Outage | 959s SVC (959s Lanfine), 959s 921 (959s Lanfine) | troubleshoot cause of recent SVC tripping event | 31.5 Hours
Continuous |
|
| 15-Dec-25 10:00 | 19-Dec-25 16:00 | ATCO | TE | 716s RTU/SCADA (716s Lloydminster) | transfer station DC to temporary battery bank, replace battery bank, install battery monitoring system, update station controller configuration for BMS connection, test new alarms | 4.25 Days
Continuous |
|
| 15-Dec-25 10:00 | 16-Dec-25 17:00 | ALTALINK | TE | 108s RTU/SCADA (108s Amelia) | RTU database update | 31 Hours
Daily |
|
| 15-Dec-25 10:00 | 18-Dec-25 17:30 | ATCO | TE | 749s Flyingshot Lake Protection & Control | PPRC-005 auxiliary trip relay testing | 3.31 Days
Continuous |
|
| 15-Dec-25 10:00 | 16-Dec-25 17:00 | ATCO | TE | ATCO Telecom Equipment, 784s RTU/SCADA (784s Donnelly) | cutover of the site to new switch will take place Dec 16 | 31 Hours
Continuous |
|
| 15-Dec-25 11:00 | 19-Dec-25 17:30 | ALTALINK | TE | 272s RTU/SCADA (272s Springbank) | implement supervisory controls and indication for sectionalizer | 4.27 Days
Daily |
|
| 15-Dec-25 11:30 | 16-Dec-25 17:00 | ALTALINK | TE | 140s Protection & Control (140s Thompson) | replace DSP cards and maintenance | 29.5 Hours
Continuous |
|
| 15-Dec-25 12:00 | 16-Dec-25 16:00 | ATCO | TE | 2005s Protection & Control (2005s Secord) | complete relay testing | 28 Hours
Continuous |
|
| 15-Dec-25 13:00 | 16-Dec-25 17:00 | ALTALINK | TE | 17s Protection & Control (17s Benalto) | card replacement affecting 240B2 - B87 relays | 28 Hours
Continuous |
|
| 15-Dec-25 15:00 | 31-Jan-26 23:00 | ALTALINK | Outage | 58s C1 (58s Edson) | forced outage | 47.33 Days
Continuous |
|
| 16-Dec-25 08:00 | 16-Dec-25 16:00 | ALTALINK | Outage | 225L (67s Stirling - 225AL tap), 67s 225 (67s Stirling) | breaker 352 (225s) alarm splitting | 8 Hours
Daily |
|
| 16-Dec-25 08:00 | 16-Dec-25 17:00 | ALTALINK | TE | 358s RTU/SCADA (358s Amoco Brazeau) | investigate IED trouble on L3 MET | 9 Hours
Daily |
|
| 16-Dec-25 08:00 | 16-Dec-25 17:00 | ALTALINK | TE | 358s Protection & Control (358s Amoco Brazeau) | protection outage on U/F relay 2-1/81 to investigate VR1 voltage imbalance | 9 Hours
Daily |
|
| 16-Dec-25 08:00 | 16-Dec-25 12:00 | ENMAX | Outage | 33.83L (SS-33 - SS-41), 41B138-33.83 (SS-41), 33B138-33.83 (SS-33) | breaker trip circuit test - 41B138-33.83 | 4 Hours
Continuous |
|
| 16-Dec-25 08:00 | 16-Dec-25 12:00 | ENMAX | TE | Protection & Control (SS-24) | 24 sub auto-switching protection scheme outage, I&R 24 Sub GE C30 internal battery fail | 4 Hours
Continuous |
|
| 16-Dec-25 08:00 | 18-Dec-25 18:00 | ALTALINK | TE | 520s RTU/SCADA (520s Bennett) | update RTU to add supervisory control and indication for RAS-11 | 2.42 Days
Daily |
|
| 16-Dec-25 08:00 | 16-Dec-25 12:00 | ENMAX | Outage | 14.2TR (SS-14) | LV breaker maintenance | 4 Hours
Continuous |
|
| 16-Dec-25 08:00 | 18-Dec-25 16:00 | ALTALINK | TE | 520s Protection & Control (520s Bennett) | add E/D control to RAS 11 and RAS 12 | 2.33 Days
Daily |
|
| 16-Dec-25 08:30 | 16-Dec-25 12:30 | ATCO | TE | ATCO Telecom Equipment, 845s Protection & Control (845s Big Mountain), 749s Flyingshot Lake Protection & Control | replace RF cables on the IRU and troubleshoot alarms | 4 Hours
Continuous |
|
| 16-Dec-25 09:00 | 16-Dec-25 12:00 | ENMAX | Outage | 1.82L (SS-1 - SS-5) | transfer from JMUX to JPAX circuits | 3 Hours
Continuous |
|
| 16-Dec-25 09:00 | 16-Dec-25 17:00 | ALTALINK | TE | 108s Protection & Control (108s Amelia) | card replacement | 8 Hours
Daily |
|
| 16-Dec-25 09:00 | 19-Dec-25 20:00 | SUNCOR | IO | 29EDD-1 Protection & Control (29EDD-1 Millennium), 29EDD-94 Protection & Control (29EDD-94 Voyageur), 29EDD-34 Protection & Control (29EDD-34) | DFR firmware upgrade | 3.46 Days
Continuous |
|
| 16-Dec-25 10:00 | 16-Dec-25 17:30 | ATCO | TE | 809s Protection & Control (809s Louise Creek), 809s RTU/SCADA (809s Louise Creek) | configuration update | 7.5 Hours
Continuous |
|
| 16-Dec-25 11:00 | 18-Dec-25 13:30 | ALTALINK | Outage | 267s T1 (267s Killarney Lake), 267s 3 (267s Killarney Lake), 267s 2054X (267s Killarney Lake), 267s 2120W (267s Killarney Lake), 267s 14 (267s Killarney Lake) | install wildlife cover on 267s3 and VT3 | 2.1 Days
Continuous |
|
| 16-Dec-25 12:01 | 16-Dec-25 16:00 | ENMAX | Outage | 1.84L (SS-1 - SS-5) | transfer from JMUX to JPAX circuits | 3.98 Hours
Continuous |
|
| 16-Dec-25 12:01 | 16-Dec-25 16:00 | ENMAX | Outage | 54.81L (SS-54 - SS-65), 54B138-54.81 (SS-54) | breaker trip circuit test | 3.98 Hours
Continuous |
|
| 16-Dec-25 16:01 | 19-Dec-25 16:00 | SUNCOR | Outage | 29EDD-34 260kV Bus 29PP-45 (29EDD-34), 29EDD-34 29-952-113 (29EDD-34), 29EDD-34 29-952-123 (29EDD-34), 29EDD-34 29-952-133 (29EDD-34), 29EDD-34 29-952-143 (29EDD-34) | repairs at 29EDD34 on 29PP-45 bus after bringing 29PL9-13 back online | 3 Days
Continuous |
|
| 17-Dec-25 07:00 | 17-Dec-25 17:00 | ALTALINK, DOW | TE | 166s Protection & Control (166s Dow Chemical Fort Saskatchewan) | card replacement | 10 Hours
Daily |
|
| 17-Dec-25 07:00 | 18-Dec-25 17:30 | ALTALINK | RB | 759L (87s Gaetz - 276s Prentiss) | install bird diverters on span 28-29 | 1.44 Days
Daily |
|
| 17-Dec-25 08:00 | 17-Dec-25 17:00 | ALTALINK | TE | 272s Protection & Control (272s Springbank) | ACC visibility project wire and commission 272s 3L auto sectionalizer indication, alarms and remote controls | 9 Hours
Daily |
|
| 17-Dec-25 08:00 | 17-Dec-25 17:00 | ALTALINK | TE | 63s Protection & Control (63s Red Deer) | card replacement | 9 Hours
Daily |
|
| 17-Dec-25 08:00 | 17-Dec-25 11:00 | ENMAX | Outage | 2B138-D91 (SS-2) | breaker trip coil test - 2B138-D91 | 3 Hours
Continuous |
|
| 17-Dec-25 08:00 | 17-Dec-25 17:30 | ATCO | TE | 2075s Protection & Control (2075s Newell) | download settings files and event reports from all POW relays | 9.5 Hours
Continuous |
|
| 17-Dec-25 08:00 | 17-Dec-25 20:00 | SUNCOR | TE | Suncor RTU/SCADA (Suncor) | replace main network routers for MCC and BCC | 12 Hours
Continuous |
|
| 17-Dec-25 08:30 | 18-Dec-25 17:00 | ALTALINK | TE | 993s Protection & Control (993s Abee) | replace DSP cards and maintenance | 1.35 Days
Daily |
|
| 17-Dec-25 08:30 | 18-Dec-25 17:00 | ALTALINK | TE | 385s RTU/SCADA (385s Spring Coulee) | configuration update to RTU, replace failing voltage resistor in station service AC cabinet | 1.35 Days
Daily |
|
| 17-Dec-25 08:30 | 17-Dec-25 12:00 | ENMAX | TE | RTU/SCADA (SS-9) | transfer of SCADA from JMUX to JPAX at substations in ring 2 | 3.5 Hours
Continuous |
|
| 17-Dec-25 09:00 | 17-Dec-25 17:00 | ATCO | TE | ATCO Telecom Equipment, 2029s RTU/SCADA (2029s Heathfield) | Heathfield_S-Telecom- MED BES firewall install - outage to local network and SCADA communications | 8 Hours
Continuous |
|
| 17-Dec-25 09:00 | 17-Dec-25 16:00 | ALTALINK | Outage | 744L (228s T.M.P.L. Niton - 744AL tap), 228s 744 (228s T.M.P.L. Niton) | replace the gear box on 744L89B | 7 Hours
Daily |
|
| 17-Dec-25 09:30 | 18-Dec-25 16:00 | ATCO | TE | 848s Protection & Control (848s Ruth Lake) | complete relay testing | 30.5 Hours
Continuous |
|
| 17-Dec-25 09:30 | 18-Dec-25 17:30 | ATCO | Outage | 813s SVC (813s Little Smoky), 813s 719 (813s Little Smoky) | replace failed valve cooling pump | 1.33 Days
Continuous |
|
| 17-Dec-25 10:00 | 17-Dec-25 14:00 | ALTALINK, TRANSALTA | Outage | 250p T1 (250p Bighorn Plant) | maintenance | 4 Hours
Daily |
|
| 17-Dec-25 10:00 | 17-Dec-25 17:00 | ALTALINK | TE | 89s RTU/SCADA (89s Ellerslie) | firmware update | 7 Hours
Daily |
|
| 17-Dec-25 11:01 | 17-Dec-25 13:00 | ENMAX | Outage | 2B138-D93 (SS-2) | breaker trip coil test - 2B138-D93 | 119 Mins
Continuous |
|
| 17-Dec-25 13:01 | 17-Dec-25 16:00 | ENMAX | Outage | 2B138-D94 (SS-2) | breaker trip coil test - 2B138-D94 | 2.98 Hours
Continuous |
|
| 17-Dec-25 21:00 | 17-Dec-25 22:00 | BCH | IO | 1L274 (BCH Elkford - BCH Elkford tap) | PON submitted (PON #48393) to connect MO6, open EFT 1D23 |
60 Mins
Continuous |
|
| 17-Dec-25 21:00 | 17-Dec-25 22:00 | BCH | Outage | 1L274 (BCH Elkford - BCH Elkford tap) | PON submitted (PON #48393) to connect MO6, open EFT 1D23 |
60 Mins
Continuous |
AB-BC |
| 18-Dec-25 04:00 | 18-Dec-25 05:00 | BCH | IO | 1L274 (BCH Elkford - BCH Elkford tap) | PON submitted (PON #48393) to connect MO6, open EFT 1D23 |
60 Mins
Continuous |
|
| 18-Dec-25 04:00 | 18-Dec-25 05:00 | BCH | Outage | 1L274 (BCH Elkford - BCH Elkford tap) | PON submitted (PON #48393) to connect MO6 |
60 Mins
Continuous |
AB-BC |
| 18-Dec-25 07:00 | 18-Dec-25 17:00 | ALTALINK | TE | 120s RTU/SCADA (120s Picture Butte) | RTU outage | 10 Hours
Continuous |
|
| 18-Dec-25 08:00 | 18-Dec-25 17:00 | ALTALINK | TE | 484s RTU/SCADA (484s Millar Western) | update configuration | 9 Hours
Daily |
|
| 18-Dec-25 08:00 | 18-Dec-25 13:00 | ALTALINK | TE | 332s Protection & Control (332s Ellis) | card replacements | 5 Hours
Daily |
|
| 18-Dec-25 08:00 | 18-Dec-25 11:00 | ENMAX | Outage | 2B138-D95 (SS-2) | breaker trip coil test - 2B138-D95 | 3 Hours
Continuous |
|
| 18-Dec-25 08:00 | 18-Dec-25 17:00 | ALTALINK | TE | 74s RTU/SCADA (74s Janet) | techs need to trouble shoot the issue and possibly replace RIO-D10 | 9 Hours
Daily |
|
| 18-Dec-25 10:00 | 18-Dec-25 14:00 | ALTALINK, TRANSALTA | Outage | 250p T2 (250p Bighorn Plant) | maintenance | 4 Hours
Daily |
|
| 18-Dec-25 11:00 | 18-Dec-25 16:00 | ENMAX | Outage | 2B138-D96 (SS-2) | breaker trip coil test - 2B138-D96 | 5 Hours
Continuous |
|
| 18-Dec-25 11:00 | 22-Dec-25 13:00 | ALTALINK | Outage | 199L (347s AML Fox Creek - 741s ATC Fox Creek), 347s 199W (347s AML Fox Creek) | gas top up on 347s199W | 4.08 Days
Daily |
|
| 19-Dec-25 08:00 | 21-Dec-25 16:00 | ATCO | RB | 7L45 (798s Bridge Creek - 813s Little Smoky) | high load move 7L45 str 158 | 2.33 Days
Continuous |
|
| 19-Dec-25 08:00 | 21-Dec-25 16:00 | ATCO | RB | 7L46 (813s Little Smoky - 845s Big Mountain) | high load move 7L46 str 158 | 2.33 Days
Continuous |
|
| 19-Dec-25 08:00 | 20-Dec-25 16:00 | ENMAX | Outage | 2.82L (SS-2 - SS-5), 5B138-2.82 (SS-5) | investigate sagging cables in MH2299, xray and jacket test | 1.33 Days
Continuous |
|
| 22-Dec-25 08:00 | 22-Dec-25 12:00 | ENMAX | Outage | 7.84L (SS-7 - SS-36), 36B138-7.84 (SS-36), 7B138-7.84 (SS-7) | low SF6 gas in breaker, need to top up | 4 Hours
Continuous |
|
| 22-Dec-25 09:00 | 24-Dec-25 17:00 | ALTALINK | IO | 1201L (520s Bennett - BCH Cranbrook) | CBK 2L294, 5L94, 5L92, AutoVAR PLC, Overvoltage PLC OOS OAT for maintenance | 2.33 Days
Daily |
|
| 22-Dec-25 09:00 | 24-Dec-25 17:00 | BCH | TE | 5L94 (BCH Cranbrook - 102s Langdon), 2L294 (BCH A. A. Lambert - BCH Cranbrook), 5L92 (BCH Cranbrook - BCH Selkirk) | CBK 2L294, 5L94, 5L92, AutoVAR PLC, overvoltage PLC OOS OAT for NERC RAS PM | 2.33 Days
Daily |
|
| 29-Dec-25 09:00 | 31-Dec-25 17:00 | ALTALINK | IO | 1201L (520s Bennett - BCH Cranbrook) | CBK 2L294, 5L94, 5L92, AutoVAR PLC, Overvoltage PLC OOS OAT for maintenance | 2.33 Days
Daily |
|
| 29-Dec-25 09:00 | 31-Dec-25 17:00 | BCH | TE | 5L94 (BCH Cranbrook - 102s Langdon), 5L92 (BCH Cranbrook - BCH Selkirk), 2L294 (BCH A. A. Lambert - BCH Cranbrook) | maintenance | 2.33 Days
Daily |
|
| 05-Jan-26 07:00 | 08-Jan-26 17:00 | ATCO | TE | 710s Protection & Control (710s Vermilion) | change and test relay settings | 3.42 Days
Continuous |
|
| 05-Jan-26 08:00 | 08-Mar-26 16:00 | ENMAX | Outage | 1.80L (SS-1 - SS-28), 28B138-1.80 (SS-28) | 1 sub transmission line cut over | 62.29 Days
Continuous |
|
| 05-Jan-26 08:00 | 08-Mar-26 16:00 | ENMAX | Outage | 1.81L (SS-1 - SS-20), 20B138-1.81 (SS-20) | 1 sub transmission line cut over | 62.29 Days
Continuous |
|
| 05-Jan-26 08:00 | 08-Jan-26 16:00 | ATCO | Outage | 7L48 (794s Valleyview - 7LA48 tap), 794s 703 (794s Valleyview) | pole and cross arm replacement from T&T | 3.33 Days
Continuous |
|
| 05-Jan-26 08:00 | 06-Jan-26 16:00 | ALTALINK | TE | AML 793s RTU/SCADA (AML 793s Horse Creek) | split the existing SCADA VLAN from 1 to 1 and 2 | 1.33 Days
Daily |
|
| 05-Jan-26 08:00 | 09-Jan-26 17:00 | ALTALINK | TE | 356s Protection & Control (356s Milo) | DLR project - protection outages required to make metering configuration changes | 4.38 Days
Daily |
|
| 05-Jan-26 08:00 | 09-Jan-26 17:00 | ALTALINK | TE | 356s RTU/SCADA (356s Milo) | DLR project - update RTU for RAS175 protection changes | 4.38 Days
Daily |
|
| 05-Jan-26 10:00 | 12-Jan-26 12:00 | ATCO | Outage | 9L40 (732s Mitsue - 809s Louise Creek) | replace 4 damaged poles | 7.08 Days
Continuous |
|
| 05-Jan-26 11:00 | 09-Jan-26 17:30 | ATCO | TE | 735s Protection & Control (735s Swan River) | relay testing on 50BF/601, 87TA/601T, 87B/600BS3, 21B/6L97, 21B/6L96, 50BF/602, 50BF/604, 50BF/603 | 4.27 Days
Continuous |
|
| 05-Jan-26 12:30 | 05-Jan-26 15:00 | ENMAX | TE | Protection & Control (SS-20) | 1 sub transmission line cut over, relocate and reconnect | 2.5 Hours
Continuous |
|
| 06-Jan-26 07:15 | 11-Jan-26 18:30 | ALTALINK | Outage | 890L (58s Edson - 207s Pinedale), 207s 890 (207s Pinedale), 58s 890 (58s Edson) | replace structures | 5.47 Days
Continuous |
|
| 06-Jan-26 08:00 | 09-Jan-26 17:00 | ATCO | Outage | 732s 902T (732s Mitsue), 732s 503R (732s Mitsue) | protection upgrade | 3.38 Days
Continuous |
|
| 06-Jan-26 08:00 | 08-Jan-26 17:00 | ALTALINK | TE | 38s Protection & Control (38s East Edmonton) | standard relay maintenance | 2.38 Days
Daily |
|
| 06-Jan-26 08:00 | 08-Jan-26 17:00 | ALTALINK | TE | 89s Protection & Control (89s Ellerslie) | standard relay maintenance | 2.38 Days
Daily |
|
| 06-Jan-26 08:00 | 06-Jan-26 17:00 | ALTALINK | TE | 316s Protection & Control (316s West Crossfield) | standard relay maintenance | 9 Hours
Daily |
|
| 06-Jan-26 08:00 | 07-Jan-26 16:00 | ALTALINK | TE | 5s RTU/SCADA (5s East Calgary) | split the existing SCADA VLAN from 1 to 1 and 2 | 1.33 Days
Daily |
|
| 06-Jan-26 08:00 | 06-Jan-26 17:00 | ALTALINK | TE | 99s RTU/SCADA (99s North St. Albert), AltaLink Telecom Equipment | replace firewall, split VLAN | 9 Hours
Daily |
|
| 06-Jan-26 08:30 | 07-Jan-26 17:00 | ALTALINK | TE | 378s Protection & Control (378s Shell Caroline) | removing 138 kV relays for maintenance | 1.35 Days
Daily |
|
| 06-Jan-26 08:30 | 08-Jan-26 17:00 | ALTALINK | TE | 15s Protection & Control (15s Fort Macleod) | relay maintenance | 2.35 Days
Daily |
|
| 06-Jan-26 09:00 | 06-Jan-26 11:00 | ATCO | TE | ATCO Telecom Equipment, 801s RTU/SCADA (801s Anderson), 807s RTU/SCADA (807s Sheerness) | upgrading SAR | 2 Hours
Continuous |
|
| 06-Jan-26 09:00 | 06-Jan-26 12:00 | ENMAX | TE | Protection & Control (SS-20) | 1 sub transmission line cut over, relocate and reconnect | 3 Hours
Continuous |
|
| 07-Jan-26 07:00 | 13-Jan-26 17:30 | ALTALINK | RB | 799L (235s Entwistle - 443s South Mayerthorpe), 799L (77s Sagitawah - 443s South Mayerthorpe) | proximity for 799L rebuild str 888A–909 (section D) | 6.44 Days
Daily |
|
| 07-Jan-26 07:30 | 07-Jan-26 15:00 | ALTALINK | TE | 17s Protection & Control (17s Benalto) | commission fail alarms from new 297s3302L, possible setting changes required | 7.5 Hours
Daily |
|
| 07-Jan-26 08:00 | 07-Jan-26 17:00 | ATCO | Outage | 7L92 (709s Vegreville - 7LA92 tap), 709s 705 (709s Vegreville) | replace structure 7L92-37 | 9 Hours
Continuous |
|
| 07-Jan-26 08:00 | 07-Jan-26 18:00 | Syncrude | TE | Syncrude ICCP Outage | server update |
10 Hours
Daily |
|
| 07-Jan-26 08:00 | 20-Jan-26 18:00 | ALTALINK | Outage | 931L (28s West Brooks - 132s Ware Junction) | install steel self-supporting structure as part of the 1075L storm restoration | 13.42 Days
Continuous |
|
| 07-Jan-26 08:00 | 08-Jan-26 16:00 | ENMAX, ALTALINK | Outage | 35.81L (42s Sarcee - SS-35), 35B138-81 (SS-35), 42s 35 (42s Sarcee), 35MD138-81 (SS-35), 35MD138-83 (SS-35), 35MD138-35.81 (SS-35) | maintenance - 35MD138-35.81, 35MD138-83, 35MD138-81, SW81 | 1.33 Days
Continuous |
|
| 07-Jan-26 08:00 | 08-Jan-26 16:00 | ALTALINK | TE | 65s RTU/SCADA (65s High River) | split the existing SCADA VLAN from 1 to 1 and 2 | 1.33 Days
Daily |
|
| 07-Jan-26 08:00 | 08-Jan-26 16:00 | ALTALINK | IO | 42s 35 (42s Sarcee) | maintenance - 35MD138-35.81, 35MD138-83, 35MD138-81, SW81 | 1.33 Days
Daily |
|
| 07-Jan-26 08:00 | 07-Jan-26 17:00 | ALTALINK | TE | AltaLink Telecom Equipment, 305s RTU/SCADA (305s Acheson) | update MPLS nodes, split VLAN and update configuration | 9 Hours
Daily |
|
| 07-Jan-26 09:00 | 07-Jan-26 11:00 | ATCO | TE | ATCO Telecom Equipment, 9L59 (801s Anderson - 9LA59 tap) | upgrading the Anderson NET 11 sar from v9 to v21, then v22 | 2 Hours
Continuous |
|
| 07-Jan-26 09:00 | 07-Jan-26 11:00 | ATCO | Outage | 9L59 (801s Anderson - 9LA59 tap) | open 9L59 at 801S during telecom outage 1-00506750 | 2 Hours
Continuous |
|
| 08-Jan-26 08:00 | 08-Jan-26 17:00 | ALTALINK | TE | 504s RTU/SCADA (504s Queenstown) | RTU outrage to replace Ronan annunciator | 9 Hours
Daily |
|
| 08-Jan-26 08:00 | 19-Jan-26 16:00 | Syncrude | Outage | 815 (Syncrude Mildred Lake), 816 (Syncrude Mildred Lake) | repair 72 kV pothead in plant 31 switchyard | 11.33 Days
Continuous |
|
| 08-Jan-26 08:00 | 08-Jan-26 17:00 | ALTALINK | TE | 42s Protection & Control (42s Sarcee) | PRC maintenance on T1 S59-T1/TERT, C3 B50/51N/27/59/60/60N/C3 , C2 B50/51N/27/59/60/60N/C2 | 9 Hours
Daily |
|
| 08-Jan-26 08:00 | 09-Jan-26 16:00 | ALTALINK | TE | 245s RTU/SCADA (245s Seebe) | split the existing SCADA VLAN from 1 to 1 and 2 | 1.33 Days
Daily |
|
| 08-Jan-26 08:00 | 08-Jan-26 16:00 | ENMAX | Outage | 5.1TR (SS-5) | relay protection test, lockouts, tap changer reversing switch check | 8 Hours
Continuous |
|
| 08-Jan-26 08:00 | 08-Jan-26 16:00 | ALTALINK | TE | 434s RTU/SCADA (434s Stony Plain) | split VLAN, replace firewall | 8 Hours
Daily |
|
| 08-Jan-26 08:30 | 08-Jan-26 12:00 | ALTALINK | TE | 412s Protection & Control (412s Shell Eagle Creek) | remove under frequency relays for maintenance | 3.5 Hours
Daily |
|
| 08-Jan-26 09:00 | 08-Jan-26 11:00 | ATCO | TE | ATCO Telecom Equipment, 930s RTU/SCADA (930s Arcenciel) | upgrading SAR OS TO V21 | 2 Hours
Continuous |
|
| 08-Jan-26 09:00 | 09-Jan-26 17:00 | ATCO | TE | ATCO Telecom Equipment, 718s Protection & Control (718s Parsons Creek) | telecom upgrade | 1.33 Days
Continuous |
|
| 08-Jan-26 09:00 | 08-Jan-26 09:30 | ALTALINK | Outage | 719L (263s Strachan - 719AL tap), 719L (719AL tap - 719BL tap), 764L (304s Shell Limestone - 581s Amoco Ricinus), 719AL (581s Amoco Ricinus - 719L tap), 304s T1 (304s Shell Limestone), 304s T2 (304s Shell Limestone), 581s T1 (581s Amoco Ricinus) | switching to open 719L259C | 30 Mins
Continuous |
|
| 08-Jan-26 09:00 | 08-Jan-26 11:00 | ATCO | Outage | 7L93 (828s Sulphur Point - 930s Arcenciel) | 7L93 needs to be open ended during telecom outage | 2 Hours
Continuous |
|
| 08-Jan-26 09:30 | 25-Jan-26 18:00 | ALTALINK | Outage | 719L (263s Strachan - 719AL tap), 263s 719 (263s Strachan) | component replacement/maintenance str 260-287 | 17.35 Days
Continuous |
|
| 08-Jan-26 10:00 | 08-Jan-26 15:00 | ATCO | Outage | 7L53 (700s Bonnyville - 7LA53 tap), 700s 702 (700s Bonnyville) | complete work on 7L53-620 | 5 Hours
Continuous |
|
| 08-Jan-26 12:30 | 08-Jan-26 17:00 | ALTALINK | TE | 531s Protection & Control (531s Shell Schrader Creek) | remove under frequency relays for maintenance | 4.5 Hours
Daily |
|
| 09-Jan-26 08:00 | 09-Jan-26 16:00 | ENMAX | Outage | 5.6TR (SS-5) | relay protection test lockouts, tap changer reversing switch check | 8 Hours
Continuous |
| This document and the information contained herein are based upon information and data which by their nature contain a degree of uncertainty and are subject to change. In addition, this document may contain information and data from public sources and/or third parties, which have been assumed to be accurate and complete and have not been verified. Accordingly, the Independent System Operator, operating as the Alberta Electric System Operator (the "AESO") makes no warranty, representation or guarantee, express or implied, with respect to this document or the information contained herein, including, but not limited to, any warranty, representation or guarantee of accuracy, completeness, timeliness, reliability, availability, absence of computer virus, non- infringement, merchantability or suitability for any purpose. Under no circumstances will the AESO, its members, officers, employees, contractors or agents, or any of their respective affiliates, be liable for any errors or omissions in, or any losses, damages or claims whatsoever, whether in contract, tort or otherwise, arising from use of or reliance upon, this document or any information contained herein. © 2009 Alberta Electric System Operator. All rights reserved |