Alberta Electric System Operator | |
System Co-ordination Plan | |
2025-01-23 to 2025-01-31 | |
Approved Outages |
Previous Version | |
Download CSV |
From | To | Owner | Type | Element | Scheduled Activity | Date/Time Comments | Interconnection |
---|---|---|---|---|---|---|---|
05-Oct-18 08:00 | 30-Jun-26 16:00 | EPCOR | IO | C2 (Rossdale) | forced outage | 2,825.33 Days
Continuous |
|
24-Oct-18 01:13 | 30-Jun-26 16:00 | EPCOR | IO | C1 (Rossdale) | forced outage | 2,806.62 Days
Continuous |
|
27-Nov-23 08:00 | 07-Mar-25 16:00 | ENMAX | Outage | 32.2TR (SS-32) | 32 sub 32.2TR 8 kV bus switchgear demolition | 466.33 Days
Continuous |
|
26-Jul-24 10:00 | 31-Mar-25 16:00 | ATCO | Outage | 826s 504R (826s Marguerite Lake) | emergency removal to replace failed 502R @834S | 248.25 Days
Continuous |
|
12-Aug-24 08:00 | 14-Feb-25 16:00 | ENMAX | Outage | 28.1TR (SS-28) | 28.1TR transformer replacement | 186.38 Days
Continuous |
|
23-Aug-24 13:45 | 30-Apr-25 14:29 | ALTALINK | Outage | 157s C1 (157s Lac La Biche) | forced outage | 250.03 Days
Continuous |
|
23-Sep-24 10:00 | 15-May-25 12:00 | ATCO | TE | 741s RTU/SCADA (741s Fox Creek) | RTU configuration on new and old RTU's onsite | 234.08 Days
Continuous |
|
04-Oct-24 01:05 | 05-May-25 12:00 | ATCO, ALTALINK | Outage | 840s McNeill Station, 830L (562s Cypress - 840s McNeill Station), 840s 701T (840s McNeill Station), 840s 901T (840s McNeill Station), 840s 702C (840s McNeill Station), 840s 703C (840s McNeill Station) | forced outage | 213.45 Days
Continuous |
AB-SK |
05-Oct-24 00:00 | 30-Apr-25 17:00 | BHE Canada | Outage | 120s C1 (120s Picture Butte) | forced outage | 207.71 Days
Continuous |
|
21-Oct-24 10:00 | 03-Feb-25 14:00 | ATCO | Outage | 741s 504C (741s Fox Creek), 741S 504 (741s ATC Fox Creek) | oil sample required to verify PCB content, prior to completing breaker replacement | 105.21 Days
Continuous |
|
21-Oct-24 12:00 | 12-May-25 17:30 | ATCO | TE | 741s Protection & Control (741s Fox Creek) | block 144kv and 25 kv bus protection and breaker fail protection for the duration of 741s project | 203.23 Days
Continuous |
|
28-Oct-24 07:00 | 14-Feb-25 17:00 | EPCOR | TE | EP 511s Protection & Control (EP 511s Victoria) | protection blocking for protection upgrade and annual maintenance | 109.46 Days
Continuous |
|
08-Nov-24 16:00 | 07-Feb-25 17:00 | EPCOR | Outage | 816s P2404 (816s Petrolia) | P2404 vendor gas mixture repair | 91.04 Days
Continuous |
|
26-Dec-24 17:07 | 13-Feb-25 18:00 | ALTALINK | Outage | 38s C1 (38s East Edmonton) | forced outage | 49.04 Days
Continuous |
|
26-Dec-24 17:07 | 31-Jan-25 18:00 | ALTALINK | Outage | 256s C1 (256s Harmattan) | forced outage | 36.04 Days
Continuous |
|
03-Jan-25 07:00 | 07-Mar-25 17:00 | EPCOR | TE | 805s Protection & Control (805s Jasper), 805s RTU/SCADA (805s Jasper) | protection blocking for P&C maintenance at Jasper | 63.42 Days
Continuous |
|
06-Jan-25 07:00 | 24-Jan-25 17:00 | EPCOR | Outage | 72MG16 (Garneau - Meadowlark), T2 (Garneau), G721 (Garneau), G725 (Garneau), G726 (Garneau), GDS17 (Garneau), GAB2 (Garneau), M725 (Meadowlark) | garneau 72kv Switchgear SF6 overhaul | 18.42 Days
Continuous |
|
06-Jan-25 09:30 | 21-Jun-25 18:00 | ALTALINK | Outage | 150L (42s Sarcee - 150AL tap), 42s 150W (42s Sarcee) | arctic arrow will require a GOI on 150L to rebuild the section of line from structure 47-198. | 166.31 Days
Continuous |
|
07-Jan-25 07:00 | 23-Jan-25 19:00 | ATCO | RB | 6L02 (769s Stettler - 873s Marion Lake), 6L02 (765s Mannix Mine - 873s Marion Lake), 6L02 (757s Battle River - 765s Mannix Mine) | stringing of 9L68/9L86 for 1030230 CETO | 16.5 Days
Continuous |
|
13-Jan-25 07:00 | 07-Feb-25 17:00 | EPCOR | Outage | T1 (Meadowlark) | meadowlark tx1 bay outage | 25.42 Days
Continuous |
|
13-Jan-25 07:00 | 14-Mar-25 17:00 | EPCOR | Outage | 987s T2 (987s Clover Bar), 987s C2406 (987s Clover Bar), 987s C2410 (987s Clover Bar), 987s C2409 (987s Clover Bar), 987s CC721 (987s Clover Bar), 987s CDS45 (987s Cloverbar), 987s CDS31 (987s Clover Bar) | Cloverbar TX2 and 1191L bay outage | 60.38 Days
Continuous |
|
13-Jan-25 07:00 | 04-Apr-25 17:00 | EPCOR | TE | 330p Protection & Control (330p Genesee), 330p RTU/SCADA (330p Genesee) | Genessee - 138/500 kV protection blocking for relay maintenance and configuration changes | 81.38 Days
Continuous |
|
13-Jan-25 08:00 | 02-Feb-25 16:00 | ENMAX | Outage | 2.83L (SS-13 - 2.83L tap), 3.84L (SS-3 - SS-13), 13.1TR (SS-13), 13.3TR (SS-13), 13B138-3.84 (SS-13), 13B138-2.83 (SS-13), 3B138-3.84 (SS-3), 13MD138-13.1TR (SS-13), 13MD138-13.3TR (SS-13) | hv sw replacement | 20.33 Days
Continuous |
|
13-Jan-25 12:00 | 31-Jan-25 14:00 | ATCO | TE | 820s Protection & Control (820s Hangingstone) | PRC005 relay testing, all 144kV breaker fail relays | 18.08 Days
Continuous |
|
13-Jan-25 12:00 | 07-Feb-25 16:00 | ATCO | TE | 905s Protection & Control (905s Meikle) | testing breaker fail relays, | 25.17 Days
Continuous |
|
15-Jan-25 08:00 | 24-Jan-25 18:00 | SUNCOR | TE | SUNCOR ICCP Outage | (BP) Abin - SCADA site failover to switch between Suncor Main (SDC) and Backup control centers (BCC). this is to implement ICCP servers. (server migration from VM to Physical.) |
9.42 Days
Continuous |
|
20-Jan-25 07:00 | 26-Jan-25 18:00 | ATCO | RB | 9L20 (755s Cordel - 766s Nevis) | HOP on 9L20 for remainder of construction on CETO project | 6.46 Days
Continuous |
|
20-Jan-25 07:00 | 31-Jan-25 17:30 | ALTALINK | TE | 244s RTU/SCADA (244s Bowmanton) | update RTU for voltage support project | 11.44 Days
Daily |
|
20-Jan-25 07:30 | 23-Jan-25 17:30 | ATCO | RB | 9L1035 (244s Bowmanton - 2075s Newell) | perform splicing on 1034L97 structure in existing canister for new fibre cable to 498s | 3.42 Days
Continuous |
|
20-Jan-25 07:30 | 23-Jan-25 17:30 | ALTALINK | RB | 1034L (244s Bowmanton - 324s Cassils) | perform splicing on 1034L97 structure in existing canister for new fibre cable to 498s | 3.42 Days
Daily |
|
20-Jan-25 07:30 | 23-Jan-25 17:30 | ATCO, ALTALINK | RB | 1035L (244s Bowmanton - 2075s Newell) | perform splicing on 1034L97 structure in existing canister for new fibre cable to 498s | 3.42 Days
Daily |
|
20-Jan-25 07:30 | 23-Jan-25 16:30 | ENMAX, ALTALINK | Outage | 918L (281s Johnson - SS-162), 162B240-RB132 (SS-162), 162B240-RB133 (SS-162), 162MD240-918L (SS-162) | 162 substation -surge arrester addition | 3.38 Days
Continuous |
|
20-Jan-25 08:00 | 31-Jan-25 16:00 | ENMAX | Outage | 16.60L (SS-16 - SS-34), 16B69-16.60 (SS-16), 34B69-16.60 (SS-34) | 16 & 34 Sub 16.60 line protection replacement | 11.33 Days
Continuous |
|
20-Jan-25 08:00 | 10-Feb-25 17:00 | ATCO | IO | 809s RTU/SCADA (809s Louise Creek) | station controller (RTU) requires a firmware upgrade for CIP compliance | 21.38 Days
Continuous |
|
20-Jan-25 08:00 | 23-Jan-25 16:00 | ENMAX, ALTALINK | Outage | 918L (281s Johnson - SS-162), 162B240-RB132 (SS-162), 162B240-RB133 (SS-162), 162MD240-918L (SS-162) | 162 substation -surge arrester addition | 3.33 Days
Continuous |
|
20-Jan-25 08:00 | 23-Jan-25 16:00 | ENMAX | Outage | 9.2TR (SS-9) | relay protection test | 3.33 Days
Continuous |
|
20-Jan-25 09:00 | 24-Jan-25 17:30 | ATCO | TE | 963s Protection & Control (963s Coyote Lake), 963s RTU/SCADA (963s Coyote Lake) | 7L128 DLR project SCADA updates |
4.35 Days
Continuous |
|
20-Jan-25 09:30 | 24-Jan-25 17:30 | ATCO | TE | 774s Protection & Control (774s Monitor) | relay testing | 4.33 Days
Continuous |
|
20-Jan-25 09:30 | 24-Jan-25 17:30 | ATCO | TE | 813s Protection & Control (813s Little Smoky) | PRC-005 - aux trip relay testing | 4.33 Days
Continuous |
|
20-Jan-25 10:00 | 24-Jan-25 12:00 | ATCO | Outage | 741s 701T (741s Fox Creek), 741s 701 (741s ATC Fox Creek), 741s 702 (741s ATC Fox Creek), 741s 702T (741s Fox Creek), 741s 703 (741s ATC Fox Creek), 741s 704 (741s ATC Fox Creek), 741s 705C (741s Fox Creek), 741s 705 (741s ATC Fox Creek), 7L90 (741s ATC Fox Creek - 7LA90 tap), 7L199 (347s AML Fox Creek - 741s ATC Fox Creek) | install new 144kV PT to 144kV bus in a new location | 4.08 Days
Continuous |
|
20-Jan-25 10:00 | 23-Jan-25 16:30 | ATCO, ALTALINK | Outage | 7L129 (526s Buffalo Creek - 7LA129 tap) | replace structures, cross arms and insulators on 7L129 | 3.27 Days
Continuous |
|
20-Jan-25 10:00 | 23-Jan-25 16:30 | ATCO, ALTALINK | Outage | 7L129 (526s Buffalo Creek - 7LA129 tap), 526s 152 (526s Buffalo Creek) | replace structures, cross arms and insulators on 7L129 | 3.27 Days
Continuous |
|
20-Jan-25 10:00 | 23-Jan-25 16:00 | ATCO | TE | 751s Protection & Control (751s Hill) | 701T and 702T relay testing | 3.25 Days
Continuous |
|
20-Jan-25 12:00 | 24-Jan-25 16:00 | ATCO | TE | 2049s Protection & Control (2049s Kettle River), 2049s RTU/SCADA (2049s Kettle River) | update 240kv transformer protection relays | 4.17 Days
Continuous |
|
20-Jan-25 14:00 | 27-Jan-25 10:00 | ATCO | Outage | 7L23 (796s Nipisi - 7L23 tap), 7L23 (732s Mitsue - 7L23 tap), 796s 702 (796s Nipisi), 858S 701TD (858s Narrows Creek) | complete CAR cross arm replacements & TCM wood pole replacements | 6.83 Days
Continuous |
|
21-Jan-25 08:30 | 26-Jan-25 16:00 | ATCO | TE | 801s Protection & Control (801s Anderson), 801s RTU/SCADA (801s Anderson) | Relay Firmware upgrades and relay testing on relays 21B/7L85, 50BF/704, 50BF/705, 50BF/711, 87BA/700BS1 | 5.31 Days
Continuous |
|
21-Jan-25 09:00 | 26-Jan-25 16:00 | ATCO | Outage | 9L10 (876s Brintnell - 939s Livock) | line to ground mitigation | 5.29 Days
Continuous |
|
22-Jan-25 08:00 | 23-Jan-25 16:00 | ENMAX | Outage | 33.84L (SS-33 - SS-43), 33.2TR (SS-33), 33B138-33.84 (SS-33), 43B138-33.84 (SS-43), 33MD138-33.2TR (SS-33) | HV SW maintenance, oil sampling MT, TC, check reversing switch | 1.33 Days
Continuous |
|
22-Jan-25 08:00 | 23-Jan-25 17:00 | ATCO | TE | 809s Protection & Control (809s Louise Creek) | 21B/7L55 firmware upgrade | 1.38 Days
Continuous |
|
22-Jan-25 08:00 | 23-Jan-25 17:00 | ATCO | TE | 809s Protection & Control (809s Louise Creek) | 51NGR/902T firmware upgrade | 1.38 Days
Continuous |
|
22-Jan-25 08:00 | 23-Jan-25 16:00 | ENMAX | TE | Protection & Control (SS-7) | 7sub C30 138kV auto switching protection outage. relay protection test - 7RLY138-7.ASW | 1.33 Days
Continuous |
|
22-Jan-25 09:00 | 24-Jan-25 17:30 | ATCO | TE | 7LA128 (572s Highland - 7L128 tap) | SCADA updates- change internal RAS alarm logic in SCADA program | 2.35 Days
Continuous |
|
22-Jan-25 09:00 | 23-Jan-25 16:00 | ATCO | TE | 820s Protection & Control (820s Hangingstone) | PRC005 relay testing on 7L36 A&B | 31 Hours
Continuous |
|
23-Jan-25 07:00 | 23-Jan-25 17:00 | EPCOR | Outage | 72RV4 (EP 511s Victoria - Rossdale), RV726 (Rossdale) | breaker maintenance | 10 Hours
Continuous |
|
23-Jan-25 07:30 | 23-Jan-25 15:00 | ENMAX, ALTALINK | IO | 50L (44s Bearspaw Plant - SS-21) | adjust blade/jaw on west & east phase on SW89 at SS-21 | 7.5 Hours
Daily |
|
23-Jan-25 08:00 | 23-Jan-25 14:00 | Lethbridge | TE | 593s Protection & Control (593s Lakeview) | cutover SCADA points | 6 Hours
Continuous |
|
23-Jan-25 08:00 | 23-Jan-25 15:00 | ENMAX, ALTALINK | Outage | 50L (44s Bearspaw Plant - SS-21), 21.1C (SS-21), 21.2TR (SS-21), 44s 50X (44s Bearspaw Plant), 60s50 (SS-21) | adjust blade/jaw on west & east phase on SW89 at SS-21 | 7 Hours
Continuous |
|
23-Jan-25 09:00 | 23-Jan-25 19:00 | ATCO | TE | ATCO Telecom Equipment | Holden telecom full building equipment cutover |
10 Hours
Continuous |
|
23-Jan-25 09:00 | 24-Jan-25 16:00 | ATCO | TE | 905s Protection & Control (905s Meikle) | PRC 21A/7L131, 21B/7L131 relay testing |
31 Hours
Continuous |
|
23-Jan-25 09:00 | 23-Jan-25 16:00 | SUNCOR | TE | 635EDD-1000 RTU/SCADA (635EDD-1000), 635EDD-1001 RTU/SCADA (635EDD-1001), 635EDD-1002 RTU/SCADA (635EDD-1002), 635EDD-1003 RTU/SCADA (635EDD-1003) | update firewall rules and switch settings | 7 Hours
Continuous |
|
23-Jan-25 10:00 | 24-Jan-25 16:00 | ATCO | TE | 931s Protection & Control (931s Bohn), 931s RTU/SCADA (931s Bohn) | update 701T transformer protection relay wiring non electrical circuits | 30 Hours
Continuous |
|
23-Jan-25 14:00 | 23-Jan-25 18:00 | ALTALINK | Outage | 62s T1 (62s Brazeau Plant), 62s 1 (62s Brazeau Plant) | maintenance | 4 Hours
Daily |
|
24-Jan-25 07:00 | 24-Jan-25 17:00 | EPCOR | Outage | 987s GB1B (987s Clover Bar) | relay maintenance | 10 Hours
Continuous |
|
24-Jan-25 07:00 | 24-Jan-25 17:30 | ALTALINK | RB | 729L (40s Wetaskiwin - 729AL tap), 729L (542s Ervick - 729AL tap), 729L (285s East Camrose - 542s Ervick) | install new tap on 729L Structure 143 | 10.5 Hours
Daily |
|
24-Jan-25 08:00 | 25-Jan-25 17:00 | ATCO | TE | 809s Protection & Control (809s Louise Creek) | 21B/7L43, 21B/9L05, firmware upgrade firmware upgrade | 1.38 Days
Continuous |
|
24-Jan-25 08:00 | 24-Jan-25 18:00 | ATCO | TE | 813s Protection & Control (813s Little Smoky) | 21A_50BF/7L90 and 21B_50BF/7L90 protections at 813s to be isolated one a time to remove temporary settings for 741s mobile sub | 10 Hours
Continuous |
|
24-Jan-25 09:00 | 24-Jan-25 16:00 | ATCO | Outage | 7L50 (757s Battle River - 491L tap), 757s 709 (757s Battle River) | 7L50 pole replacement structure 214 | 7 Hours
Continuous |
|
24-Jan-25 09:00 | 24-Jan-25 15:00 | BCH | Outage | T1 (BCH Natal), 13CX1 (BCH Natal) | add oil to the conservater BC maintenance does not affect the Alberta ATC | 6 Hours
Continuous |
AB-BC |
24-Jan-25 12:01 | 29-Jan-25 17:00 | ATCO | Outage | 7L56 (725s Goose River - 738s Virginia Hills) | replacing cross arms and poles at various structures | 5.21 Days
Continuous |
|
24-Jan-25 12:01 | 03-Feb-25 12:00 | ATCO | Outage | 741s 701T (741s Fox Creek), 741s 702T (741s Fox Creek), 741s 703 (741s ATC Fox Creek), 741s 704 (741s ATC Fox Creek) | 25kV Bus outage to perform switch replacement | 10 Days
Continuous |
|
25-Jan-25 07:00 | 25-Jan-25 17:00 | EPCOR | Outage | T3 (Garneau) | low gas GT3 breaker | 10 Hours
Continuous |
|
25-Jan-25 08:00 | 09-Feb-25 16:00 | ENMAX | Outage | 7.84L (SS-7 - SS-36), 7B138-7.84 (SS-7), 36B138-7.84 (SS-36) | 36B138-7.84 H145A2752 breaker major overhaul | 15.33 Days
Continuous |
|
25-Jan-25 08:00 | 21-Feb-25 16:00 | ENMAX | TE | Protection & Control (SS-28) | 28 sub Z31 138 kV bus differential protection outage - commission 28.1TR protection | 27.33 Days
Daily |
|
25-Jan-25 08:00 | 21-Feb-25 16:00 | ENMAX | TE | Protection & Control (SS-28) | 28 sub 138 kV autoswitching scheme outage - commission 28.1TR protection | 27.33 Days
Daily |
|
25-Jan-25 08:00 | 21-Feb-25 16:00 | ENMAX | TE | Protection & Control (SS-28) | 28 sub BMR-81 outage -commission 28.1TR protection | 27.33 Days
Daily |
|
25-Jan-25 08:00 | 21-Feb-25 16:00 | ENMAX | TE | Protection & Control (SS-28) | 28PT138-Z31 sec. outage - commission 28.1TR protection | 27.33 Days
Daily |
|
26-Jan-25 06:00 | 26-Jan-25 18:00 | ENMAX | Outage | 38.83L (SS-38 - SS-39) | Iconic Power to change a street light pole beside the line | 12 Hours
Continuous |
|
26-Jan-25 08:00 | 27-Jan-25 17:00 | ATCO | TE | 809s Protection & Control (809s Louise Creek) | 87B/900BS1, 21B/9L938, firmware upgrade | 1.38 Days
Continuous |
|
26-Jan-25 08:00 | 29-Jan-25 14:00 | ENMAX | Outage | 33.2TR (SS-33) | grounding improvements | 3.25 Days
Continuous |
|
27-Jan-25 07:00 | 03-Feb-25 18:00 | ATCO | RB | 9L20 (755s Cordel - 766s Nevis) | facilitate various construction activities on CETO | 7.46 Days
Continuous |
|
27-Jan-25 07:00 | 14-Feb-25 17:00 | EPCOR | Outage | 72RG1 (Garneau - Rossdale), T2 (Garneau), G724 (Garneau), G725 (Garneau), G726 (Garneau), RG7210 (Rossdale) | TX2/RG1 zone- 72 kV switchgear SF6 overhaul with GE | 18.42 Days
Continuous |
|
27-Jan-25 07:00 | 27-Jan-25 17:00 | EPCOR | Outage | 72RV6 (EP 511s Victoria - Rossdale), RV722 (Rossdale) | breaker maintenance | 10 Hours
Continuous |
|
27-Jan-25 07:00 | 28-Jan-25 17:00 | EPCOR | Outage | 72CN10 (987s Clover Bar - Namao), 987s CN723 (987s Clover Bar), N724 (Namao) | disconnect and relay maintenance | 1.42 Days
Continuous |
|
27-Jan-25 07:00 | 29-Jan-25 17:00 | ALTALINK | TE | 77s Protection & Control (77s Sagitawah) | replace antenna/connector at 9269R Whitecourt radio facing 77s Sagitawah | 2.42 Days
Daily |
|
27-Jan-25 08:00 | 06-Feb-25 17:00 | ALTALINK | RB | 610L (83s Taber - 336s Fincastle) | setting structures adjacent to existing 610L (str 1-102) - proximity for VATD project | 10.38 Days
Daily |
|
27-Jan-25 08:00 | 30-Jan-25 17:30 | ATCO | RB | 7L09 tap | change rotten cross arms and poles using live line techniques | 3.4 Days
Continuous |
|
27-Jan-25 08:00 | 29-Jan-25 16:00 | ENMAX | Outage | 38.83L (SS-38 - SS-39), 38.3TR (SS-38), 38.1TR (SS-38), 38.1C (SS-38), 38MD138-38.3TR (SS-38), 39B138-38.83 (SS-39), 38B138-38.83 (SS-38) | HV switch maint. | 2.33 Days
Continuous |
|
27-Jan-25 08:00 | 30-Jan-25 17:00 | ALTALINK | Trans Test | 244s C1 (244s Bowmanton), 244s C2 (244s Bowmanton) | new C1, C2 energize for load testing, one at a time, and multiple operations required | 3.38 Days
Daily |
|
27-Jan-25 08:00 | 27-Jan-25 17:00 | ALTALINK | TE | 291s Protection & Control (291s Cochrane) | remote setting change for Fortis on 51/79/81/L8 | 9 Hours
Daily |
|
27-Jan-25 08:00 | 27-Jan-25 17:00 | ALTALINK | TE | 373s Protection & Control (373s Madden) | online setting change for Fortis on 191LE 51/51N/79/L1 & 191LW 50/51/79/81/L2 | 9 Hours
Daily |
|
27-Jan-25 08:00 | 31-Jan-25 16:00 | ENMAX, ALTALINK | TE | 21.80L (42s Sarcee - SS-21) | 21.80L A and B line protection outage - relay protection end to end test | 4.33 Days
Continuous |
|
27-Jan-25 08:00 | 30-Jan-25 17:00 | ALTALINK | Trans Test | 244s C3 (244s Bowmanton) | new C3 energize for load testing. Multiple operations required. | 3.38 Days
Daily |
|
27-Jan-25 08:00 | 31-Jan-25 16:00 | ENMAX, ALTALINK | TE | 21.80L (42s Sarcee - SS-21) | 21.80L A and B line protection outage. relay protection end to end test | 4.33 Days
Daily |
|
27-Jan-25 09:00 | 30-Jan-25 17:00 | ALTALINK | TE | 77s Protection & Control (77s Sagitawah) | standard relay maintenance | 3.33 Days
Daily |
|
27-Jan-25 09:30 | 27-Jan-25 17:30 | ATCO | TE | 892s Protection & Control (892s Ribstone Creek) | relay testing | 8 Hours
Continuous |
|
27-Jan-25 09:30 | 27-Jan-25 14:30 | ATCO | Outage | 7L137 (768s Rowley - 770s Three Hills), 770s 702 (770s Three Hills), 768s 703 (768s Rowley) | breaker motor circuit relay replacement and test | 5 Hours
Continuous |
|
27-Jan-25 10:00 | 31-Jan-25 16:30 | ATCO, ALTALINK | Outage | 7L129 (526s Buffalo Creek - 7LA129 tap), 526s 152 (526s Buffalo Creek) | replace structures, cross arms and insulators on 7L129 | 4.27 Days
Continuous |
|
27-Jan-25 10:00 | 03-Feb-25 08:00 | ATCO | Outage | 7L32 (813s Little Smoky - 862s South Bezanson) | changing rotten cross arms and poles | 6.92 Days
Continuous |
|
27-Jan-25 10:00 | 31-Jan-25 16:30 | ATCO, ALTALINK | Outage | 7L129 (526s Buffalo Creek - 7LA129 tap) | replace structures, cross arms and insulators on 7L129 | 4.27 Days
Continuous |
|
27-Jan-25 10:00 | 31-Jan-25 16:00 | ATCO | TE | 721s Protection & Control (721s La Corey) | relay testing, arc flash settings update | 4.25 Days
Continuous |
|
27-Jan-25 10:00 | 30-Jan-25 16:00 | ATCO | TE | 709s Protection & Control (709s Vegreville) | PRC-005 - relay testing | 3.25 Days
Continuous |
|
27-Jan-25 10:00 | 28-Jan-25 17:00 | ALTALINK | TE | 74s RTU/SCADA (74s Janet) | substation computer final commissioning and LAN configuration change | 31 Hours
Daily |
|
27-Jan-25 10:00 | 27-Jan-25 11:00 | ALTALINK | TE | 159s Protection & Control (159s Colinton) | settings change | 60 Mins
Daily |
|
27-Jan-25 11:00 | 29-Jan-25 17:00 | ALTALINK | TE | 285s Protection & Control (285s East Camrose) | implement fault reporting on 729L B21/L10 & 730L B21/67N/L9 | 2.25 Days
Daily |
|
27-Jan-25 11:00 | 29-Jan-25 17:00 | ALTALINK | TE | 285s RTU/SCADA (285s East Camrose) | configuration update to implement fault reporting on 729L B21/L10 & 730L B21/67N/L9 | 2.25 Days
Daily |
|
27-Jan-25 11:30 | 27-Jan-25 14:00 | ALTALINK | TE | 183s Protection & Control (183s Underwood) | remote settings change to enable through fault settings | 2.5 Hours
Daily |
|
27-Jan-25 12:00 | 28-Jan-25 16:00 | ATCO | TE | 977s Protection & Control (977s Salt Creek), 977s RTU/SCADA (977s Salt Creek) | updates to 901T transformer protection relay, wiring updates to non electrical circuits | 28 Hours
Continuous |
|
27-Jan-25 12:00 | 28-Jan-25 16:00 | ATCO | TE | 820s Protection & Control (820s Hangingstone) | PRC005 relay testing on 7L97 A&B | 28 Hours
Continuous |
|
27-Jan-25 12:00 | 31-Jan-25 16:00 | ATCO | TE | 951s Protection & Control (951s Thickwood Hills), 951s RTU/SCADA (951s Thickwood Hills) | New SVS OT laptop remote log-in testing/commissioning various functionalities remotely with field site support, non outage functional testing to take place | 4.17 Days
Continuous |
|
27-Jan-25 12:30 | 31-Jan-25 17:30 | ALTALINK | Outage | 190L (17s Benalto - 320p Keephills) | Component replacement on 190L (STR24-417) | 4.21 Days
Continuous |
|
28-Jan-25 08:00 | 28-Jan-25 17:00 | ALTALINK | TE | AltaLink Telecom Equipment | upgrade software on radio hop to resolve SNR performance issues | 9 Hours
Daily |
|
28-Jan-25 08:00 | 28-Jan-25 17:00 | ALTALINK | TE | AltaLink Telecom Equipment | MPLS card replacement to resolve failing condition | 9 Hours
Daily |
|
28-Jan-25 08:00 | 28-Jan-25 17:00 | ALTALINK | TE | 254s RTU/SCADA (254s Coaldale) | download new configurations for the Comm monitor installation project | 9 Hours
Daily |
|
28-Jan-25 08:00 | 28-Jan-25 09:00 | ALTALINK | TE | 191s Protection & Control (191s N.W. Cardiff) | remote settings change to enable through fault settings change on A87/50/51/51N/T2 protection | 60 Mins
Daily |
|
28-Jan-25 08:30 | 28-Jan-25 13:00 | ALTALINK | Outage | 551s T1 (551s Chevron Kaybob) | take PCB oil samples from bushings of 551sT1, 551sT2, SS1 and bus PTs | 4.5 Hours
Daily |
|
28-Jan-25 08:30 | 29-Jan-25 17:00 | ATCO | RB | 7L76 (786s High Level - 832s Blumenort) | high load coming under the line at 7L76 STR 4, hot lift work | 1.35 Days
Continuous |
|
28-Jan-25 09:00 | 30-Jan-25 14:00 | CUB, ALTALINK | Outage | 672s 901T (672s Fengate Co-Generation), 430s 589 (430s Ursus) | customer to complete AESO compliance testing | 2.21 Days
Daily |
|
28-Jan-25 10:00 | 28-Jan-25 11:00 | ALTALINK | TE | 207s Protection & Control (207s Pinedale) | settings change | 60 Mins
Daily |
|
28-Jan-25 12:30 | 28-Jan-25 13:30 | ALTALINK | TE | 234s Protection & Control (234s Fort Assiniboine) | remote settings change to enable through fault settings change A87/50/51/51N/T1 protection | 60 Mins
Daily |
|
28-Jan-25 14:30 | 28-Jan-25 15:30 | ALTALINK | TE | 127s Protection & Control (127s Bruderheim) | remote settings change to enable through fault settings change A87/50/51/51N/T2 protection | 60 Mins
Daily |
|
28-Jan-25 16:30 | 28-Jan-25 17:30 | ALTALINK | TE | 157s Protection & Control (157s Lac La Biche) | remote settings change to enable through fault settings change on A87/50/51/T2 protection | 60 Mins
Daily |
|
28-Jan-25 17:00 | 28-Jan-25 18:00 | ALTALINK | TE | AltaLink RTU/SCADA (AltaLink) | RigSat needs to remotely upgrade satellite equipment | 60 Mins
Daily |
|
29-Jan-25 07:00 | 29-Jan-25 17:00 | EPCOR | Outage | RR723 (Rossdale) | breaker maintenance | 10 Hours
Continuous |
|
29-Jan-25 08:00 | 29-Jan-25 16:00 | ALTALINK | TE | AltaLink Telecom Equipment | replace faulty RAC card and upgrade software on radio hop | 8 Hours
Daily |
|
29-Jan-25 08:00 | 29-Jan-25 18:00 | ATCO | TE | ATCO Telecom Equipment | transfer the battery bank from the DC distribution to the unity rectifier |
10 Hours
Continuous |
|
29-Jan-25 08:00 | 30-Jan-25 17:00 | ALTALINK | TE | 198s RTU/SCADA (198s Blackfalds) | RTU outage required for techs to replace the following device: LAN-ES2 Qualified switchman on site. A 1hour supervisory/visibility outage each day, during replacement of LAN-ES2 | 1.38 Days
Daily |
|
29-Jan-25 08:00 | 29-Jan-25 09:00 | ALTALINK | TE | 185s Protection & Control (185s Bretville) | remote settings change to enable through fault settings change on A87/50/51/51N/T2 protection | 60 Mins
Daily |
|
29-Jan-25 08:00 | 29-Jan-25 09:00 | ALTALINK | TE | 245s Protection & Control (245s Seebe) | remote setting change to enable through fault protection | 60 Mins
Daily |
|
29-Jan-25 09:00 | 29-Jan-25 17:00 | ATCO | TE | 933s Protection & Control (933s Tower Road), 933s RTU/SCADA (933s Tower Road) | updates to 701T transformer protection relay, wiring updates to non electrical circuits | 8 Hours
Continuous |
|
29-Jan-25 09:30 | 29-Jan-25 17:30 | ATCO | TE | 903s Protection & Control (903s Loyalist) | relay testing | 8 Hours
Continuous |
|
29-Jan-25 10:00 | 30-Jan-25 16:00 | ENMAX | Outage | 240kV West Bus (SS-25), 25B240-D136 (SS-25), 25B240-D133 (SS-25), 25B240-D142 (SS-25), 25B240-D139 (SS-25) | due to clearance under 240 kV lower west bus to deliver cables | 30 Hours
Continuous |
|
29-Jan-25 10:00 | 29-Jan-25 14:00 | ALTALINK, TRANSALTA | Outage | 250p T1 (250p Bighorn Plant) | maintenance | 4 Hours
Daily |
|
29-Jan-25 10:00 | 29-Jan-25 11:00 | ALTALINK | TE | 268s Protection & Control (268s Whitecourt) | settings change | 60 Mins
Daily |
|
29-Jan-25 10:00 | 29-Jan-25 13:30 | ALTALINK | TE | 254s Protection & Control (254s Coaldale) | remote setting change to enable through fault protection | 3.5 Hours
Daily |
|
29-Jan-25 10:00 | 29-Jan-25 13:30 | Lethbridge | TE | Lethbridge ICCP Outage | firmware upgrades to firewall at primary and backup control centre |
3.5 Hours
Continuous |
|
29-Jan-25 13:30 | 29-Jan-25 15:30 | ALTALINK | TE | 283s Protection & Control (283s Violet Grove) | settings change | 2 Hours
Daily |
|
29-Jan-25 14:30 | 29-Jan-25 17:30 | ALTALINK | TE | 256s Protection & Control (256s Harmattan) | remote setting change to enable through fault protection | 3 Hours
Daily |
|
29-Jan-25 16:30 | 29-Jan-25 17:30 | ALTALINK | TE | 92s Protection & Control (92s Viscount) | settings change | 60 Mins
Daily |
|
30-Jan-25 07:00 | 30-Jan-25 17:00 | EPCOR | Outage | RR729 (Rossdale) | Rossdale: RR729 Breaker | 10 Hours
Continuous |
|
30-Jan-25 08:00 | 31-Jan-25 16:00 | ENMAX | Outage | 37.81L (SS-37 - SS-38), 38.2TR (SS-38), 38.3TR (SS-38), 38B138-37.81 (SS-38), 37B138-37.81 (SS-37) | HV SW maintenance. 38SW81, 38SW82, 38SW83, MD-38.2TR. check reversing switch 38.2TR. | 1.33 Days
Continuous |
|
30-Jan-25 08:00 | 30-Jan-25 17:00 | ALTALINK | TE | 198s Protection & Control (198s Blackfalds) | perform relay maintenance | 9 Hours
Daily |
|
30-Jan-25 08:00 | 30-Jan-25 17:00 | ALTALINK | TE | AltaLink Telecom Equipment | flash card fail, requires replacement and software upgrade | 9 Hours
Daily |
|
30-Jan-25 08:00 | 30-Jan-25 17:00 | ALTALINK | TE | 135s RTU/SCADA (135s Conrad) | download new configurations for the comm monitor installation project | 9 Hours
Daily |
|
30-Jan-25 08:00 | 30-Jan-25 09:00 | ALTALINK | TE | 255s Protection & Control (255s Vulcan) | remote setting change to enable through fault protection | 60 Mins
Daily |
|
30-Jan-25 09:00 | 30-Jan-25 17:00 | ATCO | TE | 856s Protection & Control (856s Kinosis), 856s RTU/SCADA (856s Kinosis) | updates to 903T transformer protection relay, wiring updates to non electrical circuits | 8 Hours
Continuous |
|
30-Jan-25 09:00 | 30-Jan-25 12:00 | ATCO | Outage | 709s 701 (709s Vegreville), 709s 701Ta (709s Vegreville) | PRC-005 trip coil testing breaker 701, requires load transformer to 702T, | 3 Hours
Continuous |
|
30-Jan-25 09:00 | 30-Jan-25 15:00 | ALTALINK | Outage | 237s 2252 (237s Foothills) | urgent: 237s2252 gas top up. | 6 Hours
Daily |
|
30-Jan-25 09:00 | 30-Jan-25 15:00 | ENMAX, ALTALINK | RB | 1106L (237s Foothills - SS-65) | Altalink outage - 237s2252 gas top up | 6 Hours
Continuous |
|
30-Jan-25 09:30 | 04-Feb-25 17:30 | ATCO | TE | 948s Protection & Control (948s Heatburg) | relay testing- isolate relays as required on site | 5.33 Days
Continuous |
|
30-Jan-25 10:00 | 30-Jan-25 14:00 | ALTALINK, TRANSALTA | Outage | 250p T2 (250p Bighorn Plant) | maintenance | 4 Hours
Daily |
|
30-Jan-25 10:00 | 30-Jan-25 11:00 | ALTALINK | TE | 257s Protection & Control (257s Hull) | remote setting change to enable through fault protection | 60 Mins
Daily |
|
30-Jan-25 12:01 | 30-Jan-25 15:00 | ATCO | Outage | 709s 702 (709s Vegreville), 709s 702T (709s Vegreville) | PRC-005 trip coil testing breaker 702, requires load transformer to 701T | 2.98 Hours
Continuous |
|
30-Jan-25 12:30 | 30-Jan-25 15:30 | ALTALINK | TE | 263s Protection & Control (263s Strachan) | remote setting change to enable through fault protection | 3 Hours
Daily |
|
31-Jan-25 07:00 | 31-Jan-25 17:00 | EPCOR | TE | Protection & Control (Namao), RTU/SCADA (Namao) | protection blocking for SA upgrade | 10 Hours
Continuous |
|
31-Jan-25 09:00 | 31-Jan-25 16:00 | ATCO | TE | 2014s Protection & Control (2014s Halfway) | relay preventive maintenance | 7 Hours
Continuous |
|
31-Jan-25 09:00 | 31-Jan-25 17:00 | ATCO | TE | 2011s Protection & Control (2011s Dawes), 2011s RTU/SCADA (2011s Dawes) | updates to 901T transformer protection relay | 8 Hours
Continuous |
This document and the information contained herein are based upon information and data which by their nature contain a degree of uncertainty and are subject to change. In addition, this document may contain information and data from public sources and/or third parties, which have been assumed to be accurate and complete and have not been verified. Accordingly, the Independent System Operator, operating as the Alberta Electric System Operator (the "AESO") makes no warranty, representation or guarantee, express or implied, with respect to this document or the information contained herein, including, but not limited to, any warranty, representation or guarantee of accuracy, completeness, timeliness, reliability, availability, absence of computer virus, non- infringement, merchantability or suitability for any purpose. Under no circumstances will the AESO, its members, officers, employees, contractors or agents, or any of their respective affiliates, be liable for any errors or omissions in, or any losses, damages or claims whatsoever, whether in contract, tort or otherwise, arising from use of or reliance upon, this document or any information contained herein. © 2009 Alberta Electric System Operator. All rights reserved |