| Alberta Electric System Operator | |
| System Co-ordination Plan | |
| 2025-12-11 to 2026-01-09 | |
| Approved Outages |
| Previous Version | |
| Download CSV |
| From | To | Owner | Type | Element | Scheduled Activity | Date/Time Comments | Interconnection |
|---|---|---|---|---|---|---|---|
| 26-Jul-24 10:00 | 31-Jul-26 16:00 | ATCO | Outage | 826s 504R (826s Marguerite Lake) | emergency removal to replace failed 502R @834S | 735.25 Days
Continuous |
|
| 23-Aug-24 13:45 | 30-Jun-26 14:29 | ALTALINK | Outage | 157s C1 (157s Lac La Biche) | forced outage | 676.03 Days
Continuous |
|
| 11-Mar-25 00:00 | 12-Jan-26 16:00 | ALTALINK | Outage | 377s 473C (377s AML Hardisty) | forced outage | 307.71 Days
Continuous |
|
| 18-Mar-25 14:00 | 17-Mar-26 17:30 | ALTALINK | Outage | 217s C1 (217s North Red Deer) | cap. bank unavailable and cannot be energized due to Koncar CTs being present | 364.15 Days
Daily |
|
| 20-Mar-25 08:00 | 20-Mar-26 17:00 | ALTALINK | Outage | 256s C1 (256s Harmattan) | forced outage | 365.38 Days
Continuous |
|
| 31-Mar-25 07:00 | 19-Dec-25 17:00 | EPCOR | TE | Protection & Control (Woodcroft) | Woodcroft: protection blocking for merging unit and protection upgrade. | 263.46 Days
Continuous |
|
| 14-May-25 08:00 | 10-Feb-26 16:00 | ENMAX | TE | Protection & Control (SS-32) | 32sub 138kV autoswitching protection outage | 272.38 Days
Continuous |
|
| 13-Jun-25 17:00 | 11-Feb-26 17:00 | EPCOR | Outage | T3 (Rossdale) | Rossdale - TX3 LCR | 243.04 Days
Continuous |
|
| 21-Jul-25 09:00 | 19-Jan-26 17:00 | ATCO | TE | 732s Protection & Control (732s Mitsue) | the breaker fail protection will be disabled during the project, as we migrate from the existing to the new protection | 182.38 Days
Continuous |
|
| 21-Jul-25 09:00 | 23-Jan-26 16:30 | ATCO | TE | 732s RTU/SCADA (732s Mitsue) | existing RTU system being replaced with new SMP system | 186.35 Days
Continuous |
|
| 22-Jul-25 08:30 | 12-Jan-26 16:30 | ALTALINK | Outage | 263s C1 (263s Strachan) | forced outage | 174.38 Days
Continuous |
|
| 25-Jul-25 17:01 | 20-Feb-26 17:00 | EPCOR | Outage | T2 (EP Riverview) | bushing test failure (found during OE110184) | 210.04 Days
Continuous |
|
| 20-Aug-25 17:00 | 17-Dec-25 17:00 | ALTALINK | Outage | 1075L (28s West Brooks - 132s Ware Junction) | restoration from real time storm | 119.04 Days
Continuous |
|
| 25-Aug-25 08:00 | 03-Apr-26 16:00 | ENMAX | Outage | 32.1TR (SS-32) | slip over CT and new power cables installation and P&C works | 221.33 Days
Continuous |
|
| 25-Aug-25 09:00 | 11-Dec-25 17:00 | ATCO | TE | 710s Protection & Control (710s Vermilion) | protection and hardwired IO on-site will need to be cut-over to the new SCADA system and tested | 108.38 Days
Continuous |
|
| 02-Sep-25 08:00 | 28-Feb-26 16:00 | ENMAX | Outage | 38.1C (SS-38) | capacitor bank switcher replacement | 179.38 Days
Continuous |
|
| 12-Sep-25 08:00 | 06-Mar-26 16:00 | ENMAX | Outage | 33.1TR (SS-33) | tap changer refurbishments. soak test required | 175.38 Days
Continuous |
|
| 01-Nov-25 12:00 | 01-Feb-26 18:00 | ALTALINK | Outage | AML 511s ACF12 (AML 511s Crossings) | forced outage | 92.29 Days
Continuous |
|
| 03-Nov-25 07:00 | 19-Dec-25 17:00 | EPCOR | TE | 987s Protection & Control (987s Clover Bar) | protection blocking for P&C maintenance at Cloverbar | 46.42 Days
Continuous |
|
| 12-Nov-25 08:00 | 12-Dec-25 16:00 | ENMAX | Outage | 20.1TR (SS-20), 20BA8-20.1TR (SS-20), 20BB8-20.1TR (SS-20) | maintenance | 30.33 Days
Continuous |
|
| 17-Nov-25 07:00 | 11-Dec-25 17:00 | EPCOR | TE | 814s Protection & Control (814s Bellamy) | protection blocking, DFR commissioning | 24.42 Days
Continuous |
|
| 21-Nov-25 08:00 | 09-Jan-26 16:00 | ENMAX | Outage | 38.3TR (SS-38) | 38.3TR secondary cable replacement | 49.33 Days
Continuous |
|
| 24-Nov-25 07:00 | 11-Dec-25 17:00 | ENMAX | TE | Protection & Control (SS-10) | 10 sub 138KV bus diff protection outage, 10.1TR and 10.2TR 'S' protection replacement | 17.42 Days
Daily |
|
| 24-Nov-25 07:00 | 11-Dec-25 17:00 | ENMAX | TE | Protection & Control (SS-10) | 10PT138-Z31 secondary outage, 10.1TR and 10.2TR 'S' protection replacement | 17.42 Days
Daily |
|
| 24-Nov-25 07:00 | 11-Dec-25 17:00 | ENMAX | TE | Protection & Control (SS-10) | 10sub auto switching scheme outage, 10.1TR and 10.2TR 'S' protection replacement | 17.42 Days
Daily |
|
| 25-Nov-25 17:46 | 25-Jan-26 18:00 | ATCO | Outage | 876s 901T (876s Brintnell) | forced outage oil leaking | 61.01 Days
Continuous |
|
| 27-Nov-25 08:30 | 27-Nov-27 16:30 | ALTALINK | TE | 89s Protection & Control (89s Ellerslie) | DSP card replacements on1057L B87/L3 and B240B1 B87/240B1 | 730.33 Days
Daily |
|
| 01-Dec-25 07:00 | 18-Dec-25 18:00 | ENMAX | TE | Protection & Control (SS-39) | 39s auto-switching scheme protection outage, SS-39 HV SW replacement | 17.46 Days
Daily |
|
| 01-Dec-25 08:00 | 18-Dec-25 16:00 | ENMAX | Outage | 31.84L (SS-31 - SS-32), 31B138-31.84 (SS-31), 32B138-31.84 (SS-32) | 31.84L P&C cut over | 17.33 Days
Continuous |
|
| 01-Dec-25 08:00 | 12-Dec-25 16:00 | Syncrude | TE | Aurora RTU/SCADA (Aurora) | RTU replacement | 11.33 Days
Continuous |
|
| 01-Dec-25 08:00 | 19-Dec-25 12:30 | ENMAX | Outage | 39.82L (SS-39 - SS-162), 22.81L (SS-22 - SS-39), 39.2TR (SS-39), 39.4TR (SS-39), 22B138-22.81 (SS-22), 39B138-22.81 (SS-39), 39B138-39.82 (SS-39), SW83 (SS-39), 39MD138-39.2TR (SS-39), 39MD138-39.4TR (SS-39) | HV switch replacement | 18.19 Days
Continuous |
|
| 01-Dec-25 08:00 | 12-Dec-25 17:00 | ALTALINK | TE | 397s RTU/SCADA (397s Benbow) | update configuration for L2 protection upgrades, 43m, and AIS 1159, 96/252, 96/452, B87/138B1 additions | 11.38 Days
Daily |
|
| 01-Dec-25 08:00 | 12-Dec-25 17:00 | ALTALINK | TE | 397s Protection & Control (397s Benbow) | settings changes and testing | 11.38 Days
Daily |
|
| 01-Dec-25 09:00 | 16-Dec-25 17:00 | BCH | Outage | 1L274 (48s Pocaterra - 978s BCH Britt Creek) | for LLP work | 15.33 Days
Daily |
AB-BC |
| 01-Dec-25 09:00 | 16-Dec-25 17:00 | ALTALINK | IO | 887L (48s Pocaterra - 978s BCH Britt Creek) | hazard tree removal along various sections of circuit near Elk Lakes provincial park | 15.33 Days
Daily |
|
| 01-Dec-25 10:00 | 12-Dec-25 17:30 | ATCO | TE | 977s RTU/SCADA (977s Salt Creek) | RTU update | 11.31 Days
Continuous |
|
| 01-Dec-25 10:00 | 12-Dec-25 17:30 | ATCO | TE | 845s Protection & Control (845s Big Mountain), 845s RTU/SCADA (845s Big Mountain) | 7L33 protection upgrade - upgrade SCADA |
11.31 Days
Continuous |
|
| 01-Dec-25 10:00 | 12-Dec-25 16:00 | ATCO | TE | 977s Protection & Control (977s Salt Creek) | PRC-005 testing - troubleshoot S/C operations fail | 11.25 Days
Continuous |
|
| 01-Dec-25 10:00 | 12-Dec-25 16:00 | ATCO | TE | 745s RTU/SCADA (745s Slave Lake) | install new BMS controller and modules on battery bank | 11.25 Days
Continuous |
|
| 01-Dec-25 12:00 | 12-Dec-25 16:00 | ATCO | TE | 898s Heart Lake RTU/SCADA | install battery monitoring system, update station controller configuration for BMS connection, test new alarms | 11.17 Days
Continuous |
|
| 02-Dec-25 13:00 | 11-Dec-25 13:00 | ENMAX, ALTALINK | Outage | 10B138-693 (SS-10), 693L (42s Sarcee - SS-10), 10.2TR (SS-10), 10MD138-10.2TR (SS-10) | protection replacement., trip test, protection operation | 9 Days
Continuous |
|
| 02-Dec-25 13:00 | 11-Dec-25 09:00 | ENMAX, ALTALINK | IO | 693L (42s Sarcee - SS-10) | protection replacement., trip test, protection operation | 8.83 Days
Continuous |
|
| 04-Dec-25 07:00 | 19-Dec-25 18:00 | ALTALINK | RB | 1053L (132s Ware Junction - 324s Cassils) | due to proximity to 931L | 15.46 Days
Daily |
|
| 04-Dec-25 11:00 | 19-Dec-25 18:00 | ALTALINK | Outage | 931L (28s West Brooks - 132s Ware Junction) | install new structures as part of the 1075L storm restoration. | 15.29 Days
Continuous |
|
| 08-Dec-25 07:00 | 11-Dec-25 17:00 | EPCOR, ALTALINK | Outage | 240BA3 (629s Argyll Transfer Station - 814s Bellamy), 1055L (629s Argyll Transfer Station - 816s Petrolia), 814s B2406 (814s Bellamy), 814s B2407 (814s Bellamy), 814s BDS20 (814s Bellamy) | 240BA3 metering upgrade cutovers | 3.42 Days
Continuous |
|
| 08-Dec-25 07:00 | 12-Dec-25 17:00 | EPCOR | Outage | 557s T1 (557s Castle Downs) | surge arrestor LCR | 4.42 Days
Continuous |
|
| 08-Dec-25 07:00 | 11-Dec-25 17:00 | ALTALINK, EPCOR | IO | 1055L (629s Argyll Transfer Station - 816s Petrolia) | 240BA3 metering upgrade cutovers | 3.42 Days
Continuous |
|
| 08-Dec-25 07:00 | 14-Dec-25 19:00 | ATCO | RB | 7L143 (766s Nevis - 769s Stettler) | facilitate work adjacent to line for CETO project | 6.5 Days
Continuous |
|
| 08-Dec-25 07:00 | 15-Dec-25 18:00 | ATCO | RB | 7L16 (766s Nevis - 948s Heatburg) | HOP on 7L16 to facilitate work adjacent to line for CETO project, stringing activities over 7L16 | 7.46 Days
Continuous |
|
| 08-Dec-25 08:00 | 11-Dec-25 17:00 | ATCO | TE | 732s Protection & Control (732s Mitsue) | block 87TB/902T transformer protection to verify out of service upstream bus relay CT inputs, wiring changes may be required | 3.38 Days
Continuous |
|
| 08-Dec-25 08:00 | 12-Dec-25 17:00 | ATCO | RB | 7L86 (822s Wolf Lake - 1200s Foster Creek) | L-G clearance mitigation pole changes | 4.38 Days
Continuous |
|
| 08-Dec-25 08:00 | 12-Dec-25 17:00 | ALTALINK | TE | 39s RTU/SCADA (39s Bickerdike) | update config for AIS 1159 additions | 4.38 Days
Daily |
|
| 08-Dec-25 08:00 | 12-Dec-25 17:00 | ALTALINK | TE | 1012s RTU/SCADA (1012s Deer Hill) | update config for AIS 1159 additions, and 43M addition | 4.38 Days
Daily |
|
| 08-Dec-25 08:00 | 12-Dec-25 17:00 | ALTALINK | TE | 1012s Protection & Control (1012s Deer Hill) | settings changes & testing on A21/L2, B21/L2, A21/L1, & B21/L1 for 1159AIS scheme | 4.38 Days
Daily |
|
| 08-Dec-25 09:00 | 12-Dec-25 17:00 | ATCO | TE | ATCO Telecom Equipment, 727s RTU/SCADA (727s Kinuso) | Kinuso_S-Telecom- installing a new panel | 4.33 Days
Continuous |
|
| 08-Dec-25 10:00 | 12-Dec-25 17:30 | ATCO | TE | 749s Flyingshot Lake Protection & Control, 749s Flyingshot Lake RTU/SCADA | 7L33 protection upgrade , upgrade SCADA |
4.31 Days
Continuous |
|
| 08-Dec-25 10:00 | 12-Dec-25 17:00 | ALTALINK | TE | 39s Protection & Control (39s Bickerdike) | settings changes & testing on A21/L1 & B21/L1 for 1159AIS scheme | 4.29 Days
Daily |
|
| 08-Dec-25 11:00 | 12-Dec-25 17:00 | ALTALINK | TE | 205s RTU/SCADA (205s Castle Rock Ridge) | SCADA upgrade - alarm splitting, RTU config updates | 4.25 Days
Daily |
|
| 08-Dec-25 11:00 | 12-Dec-25 17:00 | ALTALINK | TE | 58s RTU/SCADA (58s Edson) | RTU database updates | 4.25 Days
Daily |
|
| 08-Dec-25 11:00 | 12-Dec-25 17:00 | ALTALINK | TE | 207s RTU/SCADA (207s Pinedale) | RTU database updates | 4.25 Days
Daily |
|
| 08-Dec-25 11:00 | 12-Dec-25 17:00 | ALTALINK, CascadeP | TE | 1047s RTU/SCADA (1047s Whisky Jack) | RTU database updates | 4.25 Days
Daily |
|
| 08-Dec-25 12:00 | 12-Dec-25 16:00 | ATCO | TE | 960s Protection & Control (960s Birchwood Creek) | complete relay testing | 4.17 Days
Continuous |
|
| 08-Dec-25 12:00 | 11-Dec-25 17:00 | ALTALINK | TE | 263s RTU/SCADA (263s Strachan) | update configurations on RTU | 3.21 Days
Daily |
|
| 08-Dec-25 13:00 | 12-Dec-25 17:00 | ATCO | Outage | 9L40 (732s Mitsue - 809s Louise Creek), 732s 901 (732s Mitsue), 732s 902 (732s Mitsue), 732s 9L40D2 (732s Mitsue), 732s 902B (732s MItsue), 732s 901B (732s MItsue) | 240kV bus and 144kV breaker fail protection upgrade and SCADA upgrade | 4.17 Days
Continuous |
|
| 09-Dec-25 07:00 | 12-Dec-25 17:30 | ALTALINK | Outage | 38s 7252 (38s East Edmonton) | replace CTs | 3.44 Days
Continuous |
|
| 09-Dec-25 07:00 | 12-Dec-25 17:30 | ALTALINK, EPCOR | RB | 915L (38s East Edmonton - 987s Clover Bar) | Altalink working on 38s7252 | 3.44 Days
Continuous |
|
| 09-Dec-25 08:00 | 11-Dec-25 17:00 | ALTALINK, EXPPIPE | TE | AltaLink Telecom Equipment, 329s RTU/SCADA (329s Hrt Express) | update MPLS Node | 2.38 Days
Daily |
|
| 09-Dec-25 08:00 | 11-Dec-25 17:00 | ALTALINK | TE | 429s RTU/SCADA (429s Nelson Lake), AltaLink Telecom Equipment | update MPLS node | 2.38 Days
Daily |
|
| 09-Dec-25 09:00 | 11-Dec-25 17:00 | ATCO | TE | ATCO Telecom Equipment | flat top telecom replacement of existing damaged elliptical wave guide, dish facing Mitsue | 2.33 Days
Continuous |
|
| 09-Dec-25 09:00 | 11-Dec-25 17:00 | ATCO | TE | ATCO Telecom Equipment, 766s RTU/SCADA (766s Nevis) | firewall install | 2.33 Days
Continuous |
|
| 09-Dec-25 09:00 | 19-Dec-25 17:00 | BCH | Outage | 5L52 (BPA Custer - BCH Ingledow) | make emergent glass replacement on the circuit | 10.33 Days
Continuous |
AB-BC |
| 09-Dec-25 17:00 | 02-Feb-26 11:00 | ALTALINK | IO | 714L (397s Benbow – 1117s South Kaybob), 397s 714 (397s Benbow) | complete work on breaker and energize 397s 714 | 54.75 Days
Continuous |
|
| 10-Dec-25 07:00 | 11-Dec-25 16:00 | ATCO | Outage | 7L130 (705s Kitscoty - 710s Vermilion), 710s 702 (710s Vermilion), 705s 704 (705s Kitscoty) | conductor inspection | 1.38 Days
Continuous |
|
| 10-Dec-25 08:00 | 11-Dec-25 17:00 | ALTALINK | TE | 852s RTU/SCADA (852s Round Hill), AltaLink Telecom Equipment | MPLS upgrade | 1.38 Days
Continuous |
|
| 10-Dec-25 08:00 | 11-Dec-25 17:00 | ALTALINK | TE | 77s Protection & Control (77s Sagitawah) | standard relay maintenance | 1.38 Days
Daily |
|
| 10-Dec-25 08:00 | 11-Dec-25 17:00 | ALTALINK | TE | 77s RTU/SCADA (77s Sagitawah) | firmware update | 1.38 Days
Daily |
|
| 11-Dec-25 07:00 | 11-Dec-25 18:00 | ENMAX | TE | Protection & Control (SS-10), 10.2TR (SS-10) | 10.2TR 'A' & 'B' protection outage, trip testing | 11 Hours
Continuous |
|
| 11-Dec-25 07:00 | 12-Dec-25 17:00 | EPCOR | Outage | T1 (Woodcroft), W721 (Woodcroft), W722 (Woodcroft), WDS3 (Woodcroft) | woodcroft: tx1 zone, wab1 repair | 1.42 Days
Continuous |
|
| 11-Dec-25 07:30 | 11-Dec-25 12:30 | ALTALINK | Outage | 205s 352 (205s Castle Rock Ridge) | acc visibility scada upgrade - alarm splitting + wiring modifications | 5 Hours
Daily |
|
| 11-Dec-25 08:00 | 11-Dec-25 17:00 | ALTALINK | TE | 445s RTU/SCADA (445s Elk River) | investigate issues with low receive levels | 9 Hours
Daily |
|
| 11-Dec-25 08:00 | 11-Dec-25 10:30 | ALTALINK | Outage | 63s T3 (63s Red Deer), 63s 26 (63s Red Deer) | 63s26 Gas top up to eliminate nuisance alarming | 2.5 Hours
Daily |
|
| 11-Dec-25 08:00 | 11-Dec-25 17:00 | ALTALINK | TE | 378s Protection & Control (378s Shell Caroline) | dps card replacement/minor, firmware update on the following line protection: 848L B21/L1 | 9 Hours
Daily |
|
| 11-Dec-25 08:00 | 11-Dec-25 17:00 | ALTALINK | TE | 356s RTU/SCADA (356s Milo) | maintenance | 9 Hours
Daily |
|
| 11-Dec-25 08:00 | 14-Dec-25 16:00 | ATCO | RB | 7L46 (813s Little Smoky - 845s Big Mountain) | high load move 7L46 | 3.33 Days
Continuous |
|
| 11-Dec-25 08:00 | 14-Dec-25 16:00 | ATCO | RB | 7L45 (798s Bridge Creek - 845s Big Mountain), 7L45 (798s Bridge Creek - 813s Little Smoky) | high load move 7L45 | 3.33 Days
Continuous |
|
| 11-Dec-25 08:00 | 11-Dec-25 17:00 | ALTALINK | TE | 395s Protection & Control (395s North Holden) | standard relay maintenance | 9 Hours
Daily |
|
| 11-Dec-25 08:00 | 11-Dec-25 17:00 | ALTALINK | TE | AltaLink Telecom Equipment | 946s MPLS node update | 9 Hours
Daily |
|
| 11-Dec-25 08:00 | 11-Dec-25 17:00 | ALTALINK | TE | AltaLink Telecom Equipment | complete MPLS upgrade | 9 Hours
Daily |
|
| 11-Dec-25 09:00 | 11-Dec-25 16:00 | ENMAX, ALTALINK | IO | 832L (SS-10 - SS-12) | trip testing 10BA8-10.1TR, 10BB8-10.1TR, 10B138-832 | 7 Hours
Daily |
|
| 11-Dec-25 09:00 | 11-Dec-25 16:00 | ATCO | Outage | 700s 706C (700s Bonnyville) | replace rtxp test switch for 87V/705C @ 700S | 7 Hours
Continuous |
|
| 11-Dec-25 09:00 | 12-Dec-25 17:00 | BCH | TE | 5L92 (BCH Cranbrook - BCH Selkirk), 2L294 (BCH A. A. Lambert - BCH Cranbrook), 5L94 (BCH Cranbrook - 102s Langdon) | maintenance | 1.33 Days
Continuous |
|
| 11-Dec-25 09:00 | 12-Dec-25 17:00 | ALTALINK | IO | 1201L (520s Bennett - BCH Cranbrook) | CBK 5L94 PYPN & SYPN OOS one at a time | 1.33 Days
Continuous |
|
| 11-Dec-25 10:00 | 11-Dec-25 17:30 | ATCO | TE | 813s RTU/SCADA (813s Little Smoky) | replace HMI DVI KVM switch | 7.5 Hours
Continuous |
|
| 11-Dec-25 10:00 | 11-Dec-25 16:00 | ALTALINK | Outage | 1325L (510s Sunnybrook - AML 511s Crossings), 510s T11 (510s Sunnybrook), AML 511s T11 (AML 511s Crossings), 510s 2652 (510s Sunnybrook), 510s 2752 (510s Sunnybrook), 510s 41 (510s Sunnybrook), 510s 40 (510s Sunnybrook), 510s 43 (510s Sunnybrook), 510s 44 (510s Sunnybrook), 510s 4289 (510s Sunnybrook), AML 511s 1489 (AML 511s Crossings), 510s Protection & Control (510s Sunnybrook) | take the HVDC link to stopped state | 6 Hours
Daily |
|
| 11-Dec-25 12:31 | 11-Dec-25 17:30 | ALTALINK | Outage | 205s 452 (205s Castle Rock Ridge) | acc visibility scada upgrade - alarm splitting + wiring modifications | 4.98 Hours
Continuous |
|
| 11-Dec-25 14:00 | 11-Dec-25 18:00 | ENMAX, ALTALINK | Outage | 832L (SS-10 - SS-12), 10.1TR (SS-10), 10B138-832 (SS-10), 10MD138-10.1TR (SS-10), Protection & Control (SS-10) | trip testing 10BA8-10.1TR, 10BB8-10.1TR, 10B138-832 | 4 Hours
Continuous |
|
| 12-Dec-25 07:00 | 12-Dec-25 17:00 | EPCOR | Outage | EP 511s V724 (EP 511s Victoria) | switching school training | 10 Hours
Continuous |
|
| 12-Dec-25 07:30 | 12-Dec-25 12:30 | ALTALINK | Outage | 205s 152 (205s Castle Rock Ridge) | SCADA upgrade - alarm splitting + wiring modifications | 5 Hours
Daily |
|
| 12-Dec-25 08:00 | 12-Dec-25 16:00 | ENMAX | Outage | 15.60L (SS-15 - SS-21) | 15.60L SEL-311L ASW logic correction | 8 Hours
Continuous |
|
| 13-Dec-25 07:00 | 13-Dec-25 17:00 | EPCOR | TE | EP 511s Protection & Control (EP 511s Victoria) | protection blocking, relay maintenance | 10 Hours
Continuous |
|
| 13-Dec-25 08:00 | 14-Dec-25 16:00 | ENMAX, ALTALINK | Outage | 20.82L (SS-20 - SS-21), 21.80L (42s Sarcee - SS-21), 21.1TR (SS-21), 21.4TR (SS-21), 21B138-20.82 (SS-21), 21B138-21.80 (SS-21), 21B69-21.4TR (SS-21), 20B138-20.82 (SS-20), 42s 21 (42s Sarcee), 21MD138-21.1TR (SS-21), 21MD138-21.4TR (SS-21), SW64 (SS-21) | 21.1TR replacement, punch bolts into plate | 1.33 Days
Continuous |
|
| 13-Dec-25 08:00 | 14-Dec-25 16:00 | ENMAX, ALTALINK | IO | 21.80L (42s Sarcee - SS-21) | 21.1TR replacement, punch bolts into plate | 1.33 Days
Continuous |
|
| 13-Dec-25 08:00 | 14-Dec-25 17:00 | ENMAX, ALTALINK | TE | 50L (44s Bearspaw Plant - SS-21) | ENMAX request for techs to disable line protections to de-energize 60s100, 60s50L, line protection, A21/50L and B21/50L | 1.38 Days
Daily |
|
| 13-Dec-25 08:00 | 13-Dec-25 16:00 | ENMAX | Outage | 9.83L (SS-9 - SS-43) | oil sampling cable | 8 Hours
Continuous |
|
| 13-Dec-25 09:00 | 13-Dec-25 11:00 | EPCOR | Outage | EP 511s V721 (EP 511s Victoria), EP 511s V724 (EP 511s Victoria) | relay maintenance | 2 Hours
Continuous |
|
| 13-Dec-25 12:00 | 13-Dec-25 14:00 | EPCOR | Outage | EP 511s V729 (EP 511s Victoria) | relay maintenance | 2 Hours
Continuous |
|
| 14-Dec-25 07:30 | 20-Dec-25 17:30 | ALTALINK | RB | 793L (87s Gaetz - 535s Joffre) | setting structures on 986L/962L str’s 25-55, working near str’s 31-65 on 793L | 6.42 Days
Daily |
|
| 15-Dec-25 07:00 | 19-Dec-25 17:00 | EPCOR | Outage | 557s T2 (557s Castle Downs) | surge arrestor LCR | 4.42 Days
Continuous |
|
| 15-Dec-25 07:00 | 18-Dec-25 17:00 | EPCOR | Outage | 72 kV Bus 2 (Rossdale), RW727 (Rossdale), VHBB1 (Rossdale), VHBB2 (Rossdale), RG725 (Rossdale), RV726 (Rossdale) | Rossdale: BUS 2 Surge Arrestor Replacement | 3.42 Days
Continuous |
|
| 15-Dec-25 07:00 | 21-Dec-25 19:00 | ATCO | RB | 7L143 (766s Nevis - 769s Stettler) | facilitate work adjacent to line for CETO project | 6.5 Days
Continuous |
|
| 15-Dec-25 07:00 | 19-Dec-25 17:00 | ALTALINK, EPCOR | TE | 1139L (367s Harry Smith - EP Riverview) | protection blocking, relay maintenance | 4.42 Days
Continuous |
|
| 15-Dec-25 07:00 | 19-Dec-25 17:00 | EPCOR | TE | 72NW15 (Namao - Woodcroft) | protection blocking for 72NW15 line, CVT cutover | 4.42 Days
Continuous |
|
| 15-Dec-25 07:00 | 19-Dec-25 17:00 | EPCOR | TE | 72KN23 (Kennedale - Namao) | protection blocking for 72KN23 line, CVT cutover | 4.42 Days
Continuous |
|
| 15-Dec-25 07:00 | 19-Dec-25 17:00 | EPCOR | TE | 72VN21 (EP 511s Victoria - Namao) | protection blocking for 72VN21 line, CVT cutover | 4.42 Days
Continuous |
|
| 15-Dec-25 07:00 | 16-Dec-25 17:00 | EPCOR | Outage | RW2405 (EP Riverview) | emergency tank heater repair | 1.42 Days
Continuous |
|
| 15-Dec-25 08:00 | 16-Dec-25 17:00 | ALTALINK | TE | 67s RTU/SCADA (67s Stirling) | implement supervisory controls and indication to RAS-43 | 1.38 Days
Daily |
|
| 15-Dec-25 08:00 | 16-Dec-25 17:00 | ALTALINK | TE | 67s Protection & Control (67s Stirling) | implement supervisory controls and indication to RAS 43 and investigate or configure remote access issues | 1.38 Days
Daily |
|
| 15-Dec-25 08:00 | 15-Dec-25 16:00 | ENMAX, ALTALINK | Outage | 833L (SS-2 - SS-12), 12.2TR (SS-12), 12B138-833L (SS-12), 12MD138-12.2TR (SS-12), SW83 (SS-12), 2MD138-833L (SS-2) | west phase not fully down on stops | 8 Hours
Continuous |
|
| 15-Dec-25 08:00 | 19-Dec-25 17:00 | ALTALINK | TE | 267s RTU/SCADA (267s Killarney Lake) | RTU database update | 4.38 Days
Daily |
|
| 15-Dec-25 08:00 | 15-Dec-25 16:00 | ENMAX | Outage | 16.60L (SS-16 - SS-34) | logic correction | 8 Hours
Continuous |
|
| 15-Dec-25 08:00 | 15-Dec-25 12:00 | PEL | TE | 318s RTU/SCADA (318s Scoria) | communication outage | 4 Hours
Continuous |
|
| 15-Dec-25 08:00 | 15-Dec-25 16:00 | ENMAX | TE | RTU/SCADA (SS-31) | SDN upgrade | 8 Hours
Continuous |
|
| 15-Dec-25 08:00 | 15-Dec-25 12:00 | ALTALINK | TE | 356s Protection & Control (356s Milo) | remote setting change - 356s 1097L_B87/21/L7 L90 | 4 Hours
Daily |
|
| 15-Dec-25 08:00 | 15-Dec-25 17:00 | ALTALINK | TE | 428s RTU/SCADA (428s Namaka) | remove T2 Beckwith controls | 9 Hours
Daily |
|
| 15-Dec-25 08:00 | 19-Dec-25 17:00 | ATCO | RB | 7L86 (822s Wolf Lake - 1200s Foster Creek) | structure changes for line to ground clearance mitigation, live line work | 4.38 Days
Continuous |
|
| 15-Dec-25 08:00 | 15-Dec-25 16:00 | ENMAX | Outage | 5.5TR (SS-5) | I&R 5B13-5.5TR cell red light | 8 Hours
Continuous |
|
| 15-Dec-25 09:00 | 15-Dec-25 16:00 | ENMAX, ALTALINK | Outage | 833L (SS-2 - SS-12) | transfer from JMUX to JPAX circuits | 7 Hours
Continuous |
|
| 15-Dec-25 09:00 | 15-Dec-25 16:00 | ENMAX, ALTALINK | IO | 833L (SS-2 - SS-12) | transfer from JMUX to JPAX circuits | 7 Hours
Continuous |
|
| 15-Dec-25 09:00 | 19-Dec-25 16:00 | ATCO | RB | 7L171 (802s Michichi Creek - 804s Wintering Hills) | installing marker cones at critical crossing span 7L171-622 to 7L171-623 | 4.29 Days
Continuous |
|
| 15-Dec-25 09:00 | 16-Dec-25 18:00 | ALTALINK | Outage | 744L (235s Entwistle - 744AL tap), 235s 744W (235s Entwistle) | install dampers at structures 97A, 96A, 94A, 7 | 1.38 Days
Continuous |
|
| 15-Dec-25 09:00 | 16-Dec-25 17:00 | ENMAX | Outage | 31.1C (SS-31) | 31 sub capacitor bank CT wiring change / deficiency | 1.33 Days
Continuous |
|
| 15-Dec-25 10:00 | 16-Dec-25 17:30 | ATCO | Outage | 959s SVC (959s Lanfine), 959s 921 (959s Lanfine) | troubleshoot cause of recent SVC tripping event | 31.5 Hours
Continuous |
|
| 15-Dec-25 10:00 | 19-Dec-25 16:00 | ATCO | TE | 716s RTU/SCADA (716s Lloydminster) | transfer station DC to temporary battery bank, replace battery bank, install battery monitoring system, update station controller configuration for BMS connection, test new alarms | 4.25 Days
Continuous |
|
| 15-Dec-25 10:00 | 16-Dec-25 17:00 | ALTALINK | TE | 108s RTU/SCADA (108s Amelia) | RTU database update | 31 Hours
Daily |
|
| 15-Dec-25 10:00 | 18-Dec-25 17:30 | ATCO | TE | 749s Flyingshot Lake Protection & Control | PPRC-005 auxiliary trip relay testing | 3.31 Days
Continuous |
|
| 15-Dec-25 10:00 | 16-Dec-25 17:00 | ATCO | TE | ATCO Telecom Equipment, 784s RTU/SCADA (784s Donnelly) | cutover of the site to new switch will take place Dec 16 | 31 Hours
Continuous |
|
| 15-Dec-25 11:00 | 19-Dec-25 17:30 | ALTALINK | TE | 272s RTU/SCADA (272s Springbank) | implement supervisory controls and indication for sectionalizer | 4.27 Days
Daily |
|
| 15-Dec-25 11:30 | 15-Dec-25 17:30 | ALTALINK | Outage | 535s 6452 (535s Joffre) | urgent replace failing tank heaters | 6 Hours
Continuous |
|
| 15-Dec-25 11:30 | 16-Dec-25 17:00 | ALTALINK | TE | 140s Protection & Control (140s Thompson) | replace DSP cards and maintenance | 29.5 Hours
Continuous |
|
| 15-Dec-25 12:00 | 16-Dec-25 16:00 | ATCO | TE | 2005s Protection & Control (2005s Secord) | complete relay testing | 28 Hours
Continuous |
|
| 15-Dec-25 13:00 | 16-Dec-25 17:00 | ALTALINK | TE | 17s Protection & Control (17s Benalto) | card replacement affecting 240B2 - B87 relays | 28 Hours
Continuous |
|
| 16-Dec-25 08:00 | 16-Dec-25 16:00 | ALTALINK | Outage | 225L (67s Stirling - 225AL tap), 67s 225 (67s Stirling) | breaker 352 (s225) alarm splitting | 8 Hours
Daily |
|
| 16-Dec-25 08:00 | 16-Dec-25 17:00 | ALTALINK | TE | 358s RTU/SCADA (358s Amoco Brazeau) | investigate IED trouble on L3 MET | 9 Hours
Daily |
|
| 16-Dec-25 08:00 | 16-Dec-25 17:00 | ALTALINK | TE | 358s Protection & Control (358s Amoco Brazeau) | protection outage on U/F relay 2-1/81 to investigate VR1 voltage imbalance | 9 Hours
Daily |
|
| 16-Dec-25 08:00 | 16-Dec-25 12:00 | ENMAX | Outage | 33.83L (SS-33 - SS-41), 41B138-33.83 (SS-41), 33B138-33.83 (SS-33) | breaker trip circuit test - 41B138-33.83 | 4 Hours
Continuous |
|
| 16-Dec-25 08:00 | 16-Dec-25 12:00 | ENMAX | TE | Protection & Control (SS-24) | 24 sub auto-switching protection scheme outage, I&R 24 Sub GE C30 internal battery fail | 4 Hours
Continuous |
|
| 16-Dec-25 08:00 | 18-Dec-25 18:00 | ALTALINK | TE | 520s RTU/SCADA (520s Bennett) | update RTU to add supervisory control and indication for RAS-11 | 2.42 Days
Daily |
|
| 16-Dec-25 08:00 | 16-Dec-25 12:00 | ENMAX | Outage | 14.2TR (SS-14) | LV breaker maintenance | 4 Hours
Continuous |
|
| 16-Dec-25 08:00 | 18-Dec-25 16:00 | ALTALINK | TE | 520s Protection & Control (520s Bennett) | add E/D control to RAS 11 and RAS 12 | 2.33 Days
Daily |
|
| 16-Dec-25 08:30 | 16-Dec-25 12:30 | ATCO | TE | ATCO Telecom Equipment, 845s Protection & Control (845s Big Mountain), 749s Flyingshot Lake Protection & Control | replace RF cables on the IRU and troubleshoot alarms | 4 Hours
Continuous |
|
| 16-Dec-25 09:00 | 16-Dec-25 12:00 | ENMAX | Outage | 1.82L (SS-1 - SS-5) | transfer from JMUX to JPAX circuits | 3 Hours
Continuous |
|
| 16-Dec-25 09:00 | 16-Dec-25 17:00 | ALTALINK | TE | 108s Protection & Control (108s Amelia) | card replacement | 8 Hours
Daily |
|
| 16-Dec-25 09:00 | 19-Dec-25 20:00 | SUNCOR | IO | 29EDD-1 Protection & Control (29EDD-1 Millennium), 29EDD-94 Protection & Control (29EDD-94 Voyageur), 29EDD-34 Protection & Control (29EDD-34) | DFR firmware upgrade | 3.46 Days
Continuous |
|
| 16-Dec-25 10:00 | 16-Dec-25 17:30 | ATCO | TE | 809s Protection & Control (809s Louise Creek), 809s RTU/SCADA (809s Louise Creek) | configuration update | 7.5 Hours
Continuous |
|
| 16-Dec-25 11:00 | 18-Dec-25 13:30 | ALTALINK | Outage | 267s T1 (267s Killarney Lake) | Install wildlife cover on 267s3 and VT3, Install tap changer position sensor and current loop interface, complete I- bridge install, establish supervisory controls and tap status to Beckwith and function test, complete T1 'S' protection demo | 2.1 Days
Continuous |
|
| 16-Dec-25 12:01 | 16-Dec-25 16:00 | ENMAX | Outage | 1.84L (SS-1 - SS-5) | Transfer from JMUX to JPAX circuits | 3.98 Hours
Continuous |
|
| 16-Dec-25 12:01 | 16-Dec-25 16:00 | ENMAX | Outage | 54.81L (SS-54 - SS-65), 54B138-54.81 (SS-54) | breaker trip circuit test | 3.98 Hours
Continuous |
|
| 17-Dec-25 07:00 | 17-Dec-25 17:00 | ALTALINK, DOW | TE | 166s Protection & Control (166s Dow Chemical Fort Saskatchewan) | card replacement | 10 Hours
Daily |
|
| 17-Dec-25 07:00 | 18-Dec-25 17:30 | ALTALINK | RB | 759L (87s Gaetz - 276s Prentiss) | install bird diverters on span 28-29 | 1.44 Days
Daily |
|
| 17-Dec-25 08:00 | 17-Dec-25 17:00 | ALTALINK | TE | 272s Protection & Control (272s Springbank) | ACC visibility project wire and commission 272s 3L auto sectionalizer indication, alarms and remote controls | 9 Hours
Daily |
|
| 17-Dec-25 08:00 | 17-Dec-25 17:00 | ALTALINK | TE | 63s Protection & Control (63s Red Deer) | card replacement | 9 Hours
Daily |
|
| 17-Dec-25 08:00 | 17-Dec-25 11:00 | ENMAX | Outage | 2B138-D91 (SS-2) | breaker trip coil test - 2B138-D91 | 3 Hours
Continuous |
|
| 17-Dec-25 08:00 | 17-Dec-25 17:30 | ATCO | TE | 2075s Protection & Control (2075s Newell) | download settings files and event reports from all POW relays | 9.5 Hours
Continuous |
|
| 17-Dec-25 08:00 | 17-Dec-25 20:00 | SUNCOR | TE | Suncor RTU/SCADA (Suncor) | replace main network routers for MCC and BCC | 12 Hours
Continuous |
|
| 17-Dec-25 08:30 | 18-Dec-25 17:00 | ALTALINK | TE | 993s Protection & Control (993s Abee) | replace DSP cards and maintenance | 1.35 Days
Daily |
|
| 17-Dec-25 08:30 | 18-Dec-25 17:00 | ALTALINK | TE | 385s RTU/SCADA (385s Spring Coulee) | configuration update to RTU, replace failing voltage resistor in station service AC cabinet | 1.35 Days
Daily |
|
| 17-Dec-25 08:30 | 17-Dec-25 12:00 | ENMAX | TE | RTU/SCADA (SS-9) | transfer of SCADA from JMUX to JPAX at substations in ring 2 | 3.5 Hours
Continuous |
|
| 17-Dec-25 09:00 | 17-Dec-25 17:00 | ATCO | TE | ATCO Telecom Equipment, 2029s RTU/SCADA (2029s Heathfield) | Heathfield_S-Telecom- MED BES firewall install - outage to local network and SCADA communications | 8 Hours
Continuous |
|
| 17-Dec-25 09:00 | 17-Dec-25 16:00 | ALTALINK | Outage | 744L (228s T.M.P.L. Niton - 744AL tap), 228s 744 (228s T.M.P.L. Niton) | replace the gear box on 744L89B | 7 Hours
Daily |
|
| 17-Dec-25 09:30 | 18-Dec-25 16:00 | ATCO | TE | 848s Protection & Control (848s Ruth Lake) | complete relay testing | 30.5 Hours
Continuous |
|
| 17-Dec-25 09:30 | 18-Dec-25 17:30 | ATCO | Outage | 813s SVC (813s Little Smoky), 813s 719 (813s Little Smoky) | replace failed valve cooling pump | 1.33 Days
Continuous |
|
| 17-Dec-25 10:00 | 17-Dec-25 14:00 | ALTALINK, TRANSALTA | Outage | 250p T1 (250p Bighorn Plant) | maintenance | 4 Hours
Daily |
|
| 17-Dec-25 10:00 | 17-Dec-25 17:00 | ALTALINK | TE | 89s RTU/SCADA (89s Ellerslie) | firmware update | 7 Hours
Daily |
|
| 17-Dec-25 11:01 | 17-Dec-25 13:00 | ENMAX | Outage | 2B138-D93 (SS-2) | breaker trip coil test - 2B138-D93 | 119 Mins
Continuous |
|
| 17-Dec-25 13:01 | 17-Dec-25 16:00 | ENMAX | Outage | 2B138-D94 (SS-2) | breaker trip coil test - 2B138-D94 | 2.98 Hours
Continuous |
|
| 17-Dec-25 21:00 | 17-Dec-25 22:00 | BCH | IO | 1L274 (BCH Elkford - BCH Elkford tap) | PON submitted (PON #48393) to connect MO6, open EFT 1D23 |
60 Mins
Continuous |
|
| 17-Dec-25 21:00 | 17-Dec-25 22:00 | BCH | Outage | 1L274 (BCH Elkford - BCH Elkford tap) | PON submitted (PON #48393) to connect MO6, open EFT 1D23 |
60 Mins
Continuous |
AB-BC |
| 18-Dec-25 04:00 | 18-Dec-25 05:00 | BCH | IO | 1L274 (BCH Elkford - BCH Elkford tap) | PON submitted (PON #48393) to connect MO6. EFD station isolation will require a brief outage on 1L274 to open EFT 1D23 |
60 Mins
Continuous |
|
| 18-Dec-25 04:00 | 18-Dec-25 05:00 | BCH | Outage | 1L274 (BCH Elkford - BCH Elkford tap) | PON submitted (PON #48393) to connect MO6 |
60 Mins
Continuous |
AB-BC |
| 18-Dec-25 08:00 | 18-Dec-25 17:00 | ALTALINK | TE | 484s RTU/SCADA (484s Millar Western) | update configuration | 9 Hours
Daily |
|
| 18-Dec-25 08:00 | 18-Dec-25 13:00 | ALTALINK | TE | 332s Protection & Control (332s Ellis) | card replacements | 5 Hours
Daily |
|
| 18-Dec-25 08:00 | 18-Dec-25 11:00 | ENMAX | Outage | 2B138-D95 (SS-2) | breaker trip coil test - 2B138-D95 | 3 Hours
Continuous |
|
| 18-Dec-25 10:00 | 18-Dec-25 14:00 | ALTALINK, TRANSALTA | Outage | 250p T2 (250p Bighorn Plant) | maintenance | 4 Hours
Daily |
|
| 18-Dec-25 11:00 | 18-Dec-25 16:00 | ENMAX | Outage | 2B138-D96 (SS-2) | breaker trip coil test - 2B138-D96 | 5 Hours
Continuous |
|
| 18-Dec-25 11:00 | 22-Dec-25 13:00 | ALTALINK | Outage | 347s 199W (347s AML Fox Creek), 199L (347s AML Fox Creek - 741s ATC Fox Creek) | Gas top up on 347s199W | 4.08 Days
Daily |
|
| 19-Dec-25 08:00 | 21-Dec-25 16:00 | ATCO | RB | 7L45 (798s Bridge Creek - 813s Little Smoky) | high load move 7L45 str 158 | 2.33 Days
Continuous |
|
| 19-Dec-25 08:00 | 21-Dec-25 16:00 | ATCO | RB | 7L46 (813s Little Smoky - 845s Big Mountain) | high load move 7L46 str 158 | 2.33 Days
Continuous |
|
| 19-Dec-25 08:00 | 20-Dec-25 16:00 | ENMAX | Outage | 2.82L (SS-2 - SS-5) | Investigate sagging cables in MH2299. Xray and jacket test. | 1.33 Days
Continuous |
|
| 05-Jan-26 08:00 | 08-Mar-26 16:00 | ENMAX | Outage | 1.80L (SS-1 - SS-28) | 1 sub Transmission line cut over. Line will terminate at new 1 sub upon return to service. | 62.29 Days
Continuous |
|
| 05-Jan-26 08:00 | 08-Mar-26 16:00 | ENMAX | Outage | 1.81L (SS-1 - SS-20) | 1 sub Transmission line cut over. Line will terminate at new 1 sub upon return to service. | 62.29 Days
Continuous |
|
| 05-Jan-26 08:00 | 08-Jan-26 16:00 | ATCO | Outage | 7L48 (794s Valleyview - 7LA48 tap), 794s 703 (794s Valleyview) | pole and cross arm replacement from T&T | 3.33 Days
Continuous |
|
| 05-Jan-26 08:00 | 06-Jan-26 16:00 | ALTALINK | TE | AML 793s RTU/SCADA (AML 793s Horse Creek) | split the existing SCADA VLAN from 1 to 1 and 2 | 1.33 Days
Daily |
|
| 05-Jan-26 08:00 | 09-Jan-26 17:00 | ALTALINK | TE | 356s Protection & Control (356s Milo) | DLR project - protection outages required to make metering configuration changes | 4.38 Days
Daily |
|
| 05-Jan-26 08:00 | 09-Jan-26 17:00 | ALTALINK | TE | 356s RTU/SCADA (356s Milo) | DLR project - update RTU for RAS175 protection changes | 4.38 Days
Daily |
|
| 05-Jan-26 10:00 | 12-Jan-26 12:00 | ATCO | Outage | 9L40 (732s Mitsue - 809s Louise Creek) | replace 4 damaged poles | 7.08 Days
Continuous |
|
| 05-Jan-26 11:00 | 09-Jan-26 17:30 | ATCO | TE | 735s Protection & Control (735s Swan River) | relay testing on 50BF/601, 87TA/601T, 87B/600BS3, 21B/6L97, 21B/6L96, 50BF/602, 50BF/604, 50BF/603 | 4.27 Days
Continuous |
|
| 06-Jan-26 07:15 | 11-Jan-26 18:30 | ALTALINK | Outage | 890L (58s Edson - 207s Pinedale) | Replace structures 95, 96, 102, 103, 109, 113, 114, 116, 117 and 118. | 5.47 Days
Continuous |
|
| 06-Jan-26 08:00 | 09-Jan-26 17:00 | ATCO | Outage | 732s 902T (732s Mitsue), 732s 503R (732s Mitsue) | Protection upgrade. Remove old protection, cut over to new protection and cut over equipment status, control and alarms to new station controller. | 3.38 Days
Continuous |
|
| 06-Jan-26 08:00 | 08-Jan-26 17:00 | ALTALINK | TE | 38s Protection & Control (38s East Edmonton) | standard relay maintenance | 2.38 Days
Daily |
|
| 06-Jan-26 08:00 | 08-Jan-26 17:00 | ALTALINK | TE | 89s Protection & Control (89s Ellerslie) | standard relay maintenance | 2.38 Days
Daily |
|
| 06-Jan-26 08:00 | 06-Jan-26 17:00 | ALTALINK | TE | 316s Protection & Control (316s West Crossfield) | standard relay maintenance | 9 Hours
Daily |
|
| 06-Jan-26 08:00 | 07-Jan-26 16:00 | ALTALINK | TE | 5s RTU/SCADA (5s East Calgary) | split the existing SCADA VLAN from 1 to 1 and 2 | 1.33 Days
Daily |
|
| 06-Jan-26 08:00 | 06-Jan-26 17:00 | ALTALINK | TE | 99s RTU/SCADA (99s North St. Albert), AltaLink Telecom Equipment | replace firewall, split VLAN | 9 Hours
Daily |
|
| 06-Jan-26 08:30 | 07-Jan-26 17:00 | ALTALINK | TE | 378s Protection & Control (378s Shell Caroline) | Removing 138kV relays one at a time for maintenance. All protections impacted are non-redundant. | 1.35 Days
Daily |
|
| 06-Jan-26 08:30 | 08-Jan-26 17:00 | ALTALINK | TE | 15s Protection & Control (15s Fort Macleod) | relay maintenance | 2.35 Days
Daily |
|
| 06-Jan-26 09:00 | 06-Jan-26 11:00 | ATCO | TE | ATCO Telecom Equipment, 801s RTU/SCADA (801s Anderson), 807s RTU/SCADA (807s Sheerness) | Upgrading SAR from v9, to v21, then 22 IMPACT TO THE FOLLOWING TRAFFIC FOR UP TO 1 HOUR: Anderson Sub SCADA Anderson Sub PMU SCADA Anderson Sub GFO SCADA Thermal Prot RAS A 9L99 A 9L950 A 9L934 A 9L933 A 9L59 / 87L A 7L85 A&B 7LA85 A&B #200 RAS A 50BF / 705 |
2 Hours
Continuous |
|
| 07-Jan-26 07:00 | 13-Jan-26 17:30 | ALTALINK | RB | 799L (235s Entwistle - 443s South Mayerthorpe), 799L (77s Sagitawah - 443s South Mayerthorpe) | proximity for 799L rebuild str 888A–909 (section D) | 6.44 Days
Daily |
|
| 07-Jan-26 07:30 | 07-Jan-26 15:00 | ALTALINK | TE | 17s Protection & Control (17s Benalto) | commission fail alarms from new 297s3302L, possible setting changes required | 7.5 Hours
Daily |
|
| 07-Jan-26 08:00 | 07-Jan-26 17:00 | ATCO | Outage | 7L92 (709s Vegreville - 7LA92 tap), 709s 705 (709s Vegreville) | replace structure 7L92-37 | 9 Hours
Continuous |
|
| 07-Jan-26 08:00 | 07-Jan-26 18:00 | Syncrude | TE | Syncrude ICCP Outage | server update |
10 Hours
Daily |
|
| 07-Jan-26 08:00 | 20-Jan-26 18:00 | ALTALINK | Outage | 931L (28s West Brooks - 132s Ware Junction) | install steel self-supporting structure as part of the 1075L storm restoration | 13.42 Days
Continuous |
|
| 07-Jan-26 08:00 | 08-Jan-26 16:00 | ENMAX, ALTALINK | Outage | 35.81L (42s Sarcee - SS-35), 35B138-81 (SS-35), 42s 35 (42s Sarcee), 35MD138-81 (SS-35), 35MD138-83 (SS-35), 35MD138-35.81 (SS-35) | maintenance - 35MD138-35.81, 35MD138-83, 35MD138-81, SW81 | 1.33 Days
Continuous |
|
| 07-Jan-26 08:00 | 08-Jan-26 16:00 | ALTALINK | TE | 65s RTU/SCADA (65s High River) | split the existing SCADA VLAN from 1 to 1 and 2 | 1.33 Days
Daily |
|
| 07-Jan-26 08:00 | 08-Jan-26 16:00 | ALTALINK | IO | 42s 35 (42s Sarcee) | maintenance - 35MD138-35.81, 35MD138-83, 35MD138-81, SW81 | 1.33 Days
Daily |
|
| 07-Jan-26 08:00 | 07-Jan-26 17:00 | ALTALINK | TE | AltaLink Telecom Equipment, 305s RTU/SCADA (305s Acheson) | update MPLS nodes, split VLAN and update configuration | 9 Hours
Daily |
|
| 07-Jan-26 09:00 | 07-Jan-26 11:00 | ATCO | TE | ATCO Telecom Equipment | upgrading the Anderson NET 11 sar from v9 to v21, then v22 | 2 Hours
Continuous |
|
| 08-Jan-26 08:00 | 08-Jan-26 17:00 | ALTALINK | TE | 504s RTU/SCADA (504s Queenstown) | RTU outrage to replace Ronan annunciator | 9 Hours
Daily |
|
| 08-Jan-26 08:00 | 19-Jan-26 16:00 | Syncrude | Outage | 814 (Syncrude Mildred Lake), 815 (Syncrude Mildred Lake), 816 (Syncrude Mildred Lake) | SCL - Repair 72kV Pothead in Plant 31 Switchyard | 11.33 Days
Continuous |
|
| 08-Jan-26 08:00 | 08-Jan-26 17:00 | ALTALINK | TE | 42s Protection & Control (42s Sarcee) | PRC maintenance on T1 S59-T1/TERT, C3 B50/51N/27/59/60/60N/C3 , C2 B50/51N/27/59/60/60N/C2 | 9 Hours
Daily |
|
| 08-Jan-26 08:00 | 09-Jan-26 16:00 | ALTALINK | TE | 245s RTU/SCADA (245s Seebe) | split the existing SCADA VLAN from 1 to 1 and 2 | 1.33 Days
Daily |
|
| 08-Jan-26 08:00 | 08-Jan-26 16:00 | ENMAX | Outage | 5.1TR (SS-5) | relay protection test, lockouts, tap changer reversing switch check | 8 Hours
Continuous |
|
| 08-Jan-26 08:00 | 08-Jan-26 16:00 | ALTALINK | TE | 434s RTU/SCADA (434s Stony Plain) | split VLAN, replace firewall | 8 Hours
Daily |
|
| 08-Jan-26 08:30 | 08-Jan-26 12:00 | ALTALINK | TE | 412s Protection & Control (412s Shell Eagle Creek) | remove under frequency relays for maintenance | 3.5 Hours
Daily |
|
| 08-Jan-26 09:00 | 08-Jan-26 11:00 | ATCO | TE | ATCO Telecom Equipment, 930s RTU/SCADA (930s Arcenciel) | UPGRADING SAR OS TO V21, THEN TO V22 IMPACT TO THE FOLLOWING TRAFFIC FOR UP TO 1 HOUR: VPLS 10 - ARCENCIEL SCADA TPRNN128 / 7L64 A&B - ARCENCIEL / KEG RIVER TPRNN094 / 7L93 A &B- ARCENCIEL / SULPHUR POINT |
2 Hours
Continuous |
|
| 08-Jan-26 09:00 | 09-Jan-26 17:00 | ATCO | TE | ATCO Telecom Equipment, 718s Protection & Control (718s Parsons Creek) | telecom upgrade | 1.33 Days
Continuous |
|
| 08-Jan-26 09:00 | 08-Jan-26 09:30 | ALTALINK | Outage | 719L (263s Strachan - 719AL tap), 719L (719AL tap - 719BL tap), 304s T1 (304s Shell Limestone), 304s T2 (304s Shell Limestone), 581s T1 (581s Amoco Ricinus), 719AL (581s Amoco Ricinus - 719L tap), 764L (304s Shell Limestone - 581s Amoco Ricinus) | Outage required for switching to open 719L259C. | 30 Mins
Continuous |
|
| 08-Jan-26 09:30 | 25-Jan-26 18:00 | ALTALINK | Outage | 719L (263s Strachan - 719AL tap) | Component replacement/maintenance Str 260-287. | 17.35 Days
Continuous |
|
| 08-Jan-26 10:00 | 08-Jan-26 15:00 | ATCO | Outage | 7L53 (700s Bonnyville - 7LA53 tap), 700s 702 (700s Bonnyville) | 7L53 outage required to complete work on 7L53-620 | 5 Hours
Continuous |
|
| 08-Jan-26 12:30 | 08-Jan-26 17:00 | ALTALINK | TE | 531s Protection & Control (531s Shell Schrader Creek) | remove under frequency relays for maintenance | 4.5 Hours
Daily |
|
| 09-Jan-26 08:00 | 09-Jan-26 16:00 | ENMAX | Outage | 5.6TR (SS-5) | relay protection test lockouts, tap changer reversing switch check | 8 Hours
Continuous |
| This document and the information contained herein are based upon information and data which by their nature contain a degree of uncertainty and are subject to change. In addition, this document may contain information and data from public sources and/or third parties, which have been assumed to be accurate and complete and have not been verified. Accordingly, the Independent System Operator, operating as the Alberta Electric System Operator (the "AESO") makes no warranty, representation or guarantee, express or implied, with respect to this document or the information contained herein, including, but not limited to, any warranty, representation or guarantee of accuracy, completeness, timeliness, reliability, availability, absence of computer virus, non- infringement, merchantability or suitability for any purpose. Under no circumstances will the AESO, its members, officers, employees, contractors or agents, or any of their respective affiliates, be liable for any errors or omissions in, or any losses, damages or claims whatsoever, whether in contract, tort or otherwise, arising from use of or reliance upon, this document or any information contained herein. © 2009 Alberta Electric System Operator. All rights reserved |