| Alberta Electric System Operator | |
| System Co-ordination Plan | |
| 2026-08-13 to 2026-08-21 | |
| Approved Outages |
| Previous Version | |
| Download CSV |
| From | To | Owner | Type | Element | Scheduled Activity | Date/Time Comments | Interconnection |
|---|---|---|---|---|---|---|---|
| 26-Jul-24 10:00 | 30-Jun-27 16:00 | ATCO | Outage | 826s 504R (826s Marguerite Lake) | emergency removal to replace failed 502R @834S | 25,662 Hours
Continuous |
|
| 20-Mar-25 08:00 | 30-Sep-26 17:00 | ALTALINK | Outage | 256s C1 (256s Harmattan) | forced outage | 13,425 Hours
Continuous |
|
| 25-Nov-25 17:46 | 18-Sep-26 18:00 | ATCO | Outage | 876s 901T (876s Brintnell) | forced outage oil leaking | 7,127.23 Hours
Continuous |
|
| 27-Nov-25 08:30 | 27-Nov-27 16:30 | ALTALINK | TE | 89s Protection & Control (89s Ellerslie) | DSP card replacements on1057L B87/L3 and B240B1 B87/240B1 | 17,528 Hours
Daily |
|
| 04-Jan-26 08:00 | 02-Sep-26 16:00 | SUNCOR | Outage | 29EDD-34 260kV Bus 29PP-45 (29EDD-34), 29EDD-34 29-952-113 (29EDD-34), 29EDD-34 29PS-216 (29EDD-34) | urgent repairs on 29PT-224 at 29EDD34 on 29PP-45 bus | 5,791 Hours
Continuous |
|
| 21-Jan-26 08:00 | 30-Oct-26 16:00 | ENMAX | Outage | 5.7TR (SS-5) | 25kV switchgear replacement | 6,775 Hours
Continuous |
|
| 06-Mar-26 17:00 | 13-Nov-26 17:00 | EPCOR | Outage | T1 (Woodcroft) | woodcroft: TX1 LCR civil | 6,048 Hours
Continuous |
|
| 10-Mar-26 10:00 | 30-Nov-26 17:00 | ATCO | TE | 743s RTU/SCADA (743s Sarah Lake) | throughout the course of the project, different apparatus are being replaced, RTU will be blocked prior to download | 6,368 Hours
Continuous |
|
| 11-Mar-26 13:45 | 15-Sep-26 08:59 | ALTALINK | Outage | 535s C1 (535s Joffre) | breaker maintenance | 4,507.23 Hours
Continuous |
|
| 01-May-26 17:00 | 25-Nov-26 17:00 | EPCOR | Outage | T1 (Meadowlark) | T1 LCR civil work | 4,993 Hours
Continuous |
|
| 19-May-26 07:00 | 02-Oct-26 17:00 | EPCOR | TE | 987s Protection & Control (987s Clover Bar) | protection blocking - relay maintenance and bus differential upgrade project | 2,434 Hours
Continuous |
|
| 27-May-26 18:00 | 18-Aug-26 17:00 | ALTALINK | Outage | 526s C1 (526s Buffalo Creek) | forced outage | 1,991 Hours
Daily |
|
| 04-Jun-26 07:01 | 10-Feb-27 17:00 | EPCOR | Outage | T1 (Rossdale) | rossdale: TX1 lcr civil | 6,034.98 Hours
Continuous |
|
| 07-Jun-26 17:05 | 01-Oct-26 00:00 | ACCIONA, ENBRIDGE, ICPCL | Outage | 139s C1 (139s Hillridge) | forced outage | 2,766.92 Hours
Continuous |
|
| 08-Jun-26 07:00 | 04-Dec-26 17:00 | EPCOR | TE | EP 511s Protection & Control (EP 511s Victoria) | 72kV breaker fail protection blocking | 2,626 Hours
Continuous |
|
| 15-Jun-26 07:00 | 18-Dec-26 17:00 | EPCOR | TE | 805s Protection & Control (805s Jasper) | protection blocking, breaker replacement project | 1,954 Hours
Continuous |
|
| 19-Jun-26 17:00 | 03-Dec-27 17:00 | EPCOR | Outage | EP 511s Victoria T3 (EP 511s Victoria) | emergency outage due to degraded asset condition | 12,769 Hours
Continuous |
|
| 10-Jul-26 08:00 | 18-Nov-26 16:00 | Syncrude | Outage | 815 (Syncrude Mildred Lake), 816 (Syncrude Mildred Lake) | replace 72 kV underground feeder cables on west mine feeder | 2,696 Hours
Continuous |
|
| 14-Jul-26 00:00 | 31-Aug-26 00:00 | ALTALINK | Outage | 151s C1 (151s Strathmore) | forced outage | 1,152 Hours
Continuous |
|
| 14-Jul-26 08:00 | 01-Oct-26 17:00 | ALTALINK | IO | 287s 552 (287s Hazelwood) | 287s552 must be open during 443L and 417L outage for the 214s AIS to work properly | 1,905 Hours
Continuous |
|
| 15-Jul-26 14:01 | 28-Sep-26 09:00 | ALTALINK | Outage | 417L (55s Olds - 281s Johnson), 55s T1 (55s Olds), 55s T2 (55s Olds), 55s 417 (55S Olds), 287s 552 (287s Hazelwood), 55s 2 (55s Olds) | mobile install at 55s for P_C major upgrade, repair/replace s80, s83, s84. salvage s51. | 1,962.98 Hours
Continuous |
|
| 20-Jul-26 07:00 | 31-Dec-26 17:00 | EPCOR | TE | Protection & Control (Woodcroft) | woodcroft: protection blocking for TX1 LCR, line protection testing, and repairs | 3,947 Hours
Continuous |
|
| 20-Jul-26 07:00 | 04-Sep-26 17:00 | EPCOR | TE | 330p Protection & Control (330p Genesee) | genesee: protection blocking, firmware updates | 1,114 Hours
Continuous |
|
| 27-Jul-26 07:00 | 04-Sep-26 17:00 | EPCOR | Outage | EP 805s J2401 (EP 805s Jasper) | Jasper: J2401 replacement LCR | 946 Hours
Continuous |
|
| 27-Jul-26 10:00 | 31-Aug-26 17:00 | ATCO | Outage | 827s 701T (827s Cranberry Lake) | class2 major testing |
76 Hours
Continuous |
|
| 01-Aug-26 08:00 | 31-Aug-26 20:00 | SUNCOR | Outage | 29EDD-60 29PT-702 (29EDD-60 Inglis Island) | IBP pressure low | 732 Hours
Continuous |
|
| 03-Aug-26 08:00 | 28-Aug-26 16:00 | ENMAX | Outage | 2.82L (SS-2 - SS-5), 5B138-2.82 (SS-5) | A phase replacement, 12 hr soak test | 608 Hours
Continuous |
|
| 03-Aug-26 08:00 | 04-Sep-26 16:00 | ENMAX | TE | Protection & Control (SS-5) | 5 sub zone 31 auto switching protection scheme outage, 25kV switchgear addition | 776 Hours
Daily |
|
| 03-Aug-26 08:00 | 14-Aug-26 15:00 | CMH | TE | MH-60L (MHS-5 NE Crescent Heights - MHS-7 Brier Park) | maintenance on the LDR-60L-B | 271 Hours
Continuous |
|
| 03-Aug-26 08:00 | 30-Oct-26 16:00 | ALTALINK | TE | 55s RTU/SCADA (55s Olds) | adding/testing new alarms & controls associated with the 55s P&C | 2,120 Hours
Daily |
|
| 04-Aug-26 07:03 | 17-Sep-26 17:00 | ALTALINK | Outage | 869L (163s Amoco Empress - 204s Sandy Point), 204s T1 (204s Sandypoint), 163s 869W (163s Amoco Empress) | customer maintenance work | 777.95 Hours
Continuous |
|
| 04-Aug-26 07:30 | 13-Aug-26 08:30 | ALTALINK | Outage | 77s 652 (77s Sagitawah) | protection upgrade 77s652 | 217 Hours
Continuous |
|
| 04-Aug-26 08:00 | 23-Aug-26 16:00 | ENMAX, ALTALINK | Outage | 24.83L (74s Janet - SS-24), 74s 24.83X (74s Janet) | wood pole installation | 416 Hours
Continuous |
|
| 04-Aug-26 08:00 | 24-Aug-26 16:00 | ALTALINK, ENMAX | IO | 74s 24.83X (74s Janet), 24.83L (74s Janet - SS-24) | Enmax wood pole installation | 488 Hours
Continuous |
|
| 04-Aug-26 08:00 | 13-Aug-26 16:00 | ALTALINK | TE | 62s RTU/SCADA (62s Brazeau Plant) | replace RTU | 224 Hours
Continuous |
|
| 04-Aug-26 19:01 | 17-Aug-26 11:00 | BCH | Outage | 5CB9 (BCH Selkirk), 5CB8 (BCH Selkirk) | replace 5PT9, 5L91 remains in service | 303.98 Hours
Continuous |
AB-BC |
| 04-Aug-26 19:01 | 17-Aug-26 11:00 | BCH | RB | 5L91 (BCH Ashton Creek - BCH Selkirk) | 5L91 AR turned off | 303.98 Hours
Continuous |
AB-BC |
| 05-Aug-26 07:00 | 21-Aug-26 17:00 | EPCOR | Outage | 72LH8 (EP 803s Lambton - EP Hardisty) | aerial pole LCR (3 poles) and surge arrestor repair and HDS13 repair | 394 Hours
Continuous |
|
| 05-Aug-26 13:00 | 05-Sep-26 13:00 | ATCO | TE | 2085s Protection & Control (2085s Sheridan) | power quality meter install at 2085s Sheridan |
744 Hours
Continuous |
|
| 07-Aug-26 07:00 | 13-Aug-26 16:00 | ALTALINK | TE | 77s RTU/SCADA (77s Sagitawah) | RTU database update | 153 Hours
Daily |
|
| 08-Aug-26 08:00 | 18-Aug-26 16:00 | Syncrude | Outage | MH1 (Aurora - Aurora), 24 (Aurora), 23 (Aurora) | zone 11 6yr preventative maintenance | 248 Hours
Continuous |
|
| 08-Aug-26 08:00 | 13-Aug-26 20:00 | SUNCOR | TE | 29EDD-1 29EDD1s1852 (29EDD-1 Millennium), 29EDD-1 29EDD1S1452 (29EDD-1 Millennium) | PRC-005 relay testing | 132 Hours
Continuous |
|
| 09-Aug-26 07:00 | 13-Aug-26 17:00 | ALTALINK | IO | 77s 38 (77s Sagitawah) | test protection functionality | 106 Hours
Continuous |
|
| 10-Aug-26 07:00 | 16-Aug-26 17:00 | EPCOR | Outage | 665s T3 (665s Dome), 665s D721 (665s Dome), 665s D2404 (665s Dome), S721 (Strathcona) | Dome TX3 and disconnect maintenance | 154 Hours
Continuous |
|
| 10-Aug-26 07:30 | 02-Oct-26 17:00 | ALTALINK | Outage | 434s T3 (434s East Stony Plain) | T3 transformer replacement | 1,281.5 Hours
Continuous |
|
| 10-Aug-26 08:00 | 13-Aug-26 16:00 | ALTALINK | TE | 95s RTU/SCADA (95s Imperial Oil Edmonton), AltaLink Telecom Equipment | MPLS 95S-7705B addition, and 95S-7705A upgrade | 80 Hours
Continuous |
|
| 10-Aug-26 08:00 | 13-Aug-26 16:00 | ALTALINK | TE | AltaLink Telecom Equipment | MPLS 9095R-7705B addition, 9095R-7705A upgrade | 80 Hours
Continuous |
|
| 10-Aug-26 08:00 | 17-Aug-26 16:00 | ENMAX | Outage | 37.81L (SS-37 - SS-38), 37B138-37.81 (SS-37), 38B138-37.81 (SS-38) | siding work near line | 176 Hours
Continuous |
|
| 10-Aug-26 08:00 | 13-Aug-26 16:00 | ATCO | TE | 969s Protection & Control (969s Lindbergh) | settings changes to 50BF/701, 67-67N-32-59/5L767, SPS/969 | 80 Hours
Continuous |
|
| 10-Aug-26 08:00 | 14-Aug-26 16:00 | ALTALINK | TE | 395s RTU/SCADA (395s North Holden) | update RTU/HMI configuration | 104 Hours
Daily |
|
| 10-Aug-26 09:00 | 13-Aug-26 16:00 | ATCO | Outage | 7LA53 (969s Lindbergh - 7L53 tap), 969s 701T (969s Lindbergh), 969s 501 (969s Lindbergh), 969s 701 (969s Lindbergh), 969s 301 (969s Lindbergh) | total station outage at 969s | 79 Hours
Continuous |
|
| 10-Aug-26 09:00 | 09-Oct-26 10:00 | ALTALINK | Outage | 58s T1 (58s Edson) | 58s T1 transformer replacement and containment install | 1,177 Hours
Continuous |
|
| 10-Aug-26 10:00 | 14-Aug-26 17:30 | ATCO | Outage | 959s SVC (959s Lanfine), 959s 921 (959s Lanfine) | SVC transformer maintenance
|
103.5 Hours
Continuous |
|
| 10-Aug-26 10:00 | 20-Aug-26 17:30 | ATCO | TE | 2029s Protection & Control (2029s Heathfield) | relay firmware upgrade | 247.5 Hours
Continuous |
|
| 10-Aug-26 10:00 | 13-Aug-26 16:00 | ALTALINK | TE | 245s Protection & Control (245s Seebe) | Techs to temporary disable A87/138BN and B87/138BN Bus protections for approx 1hr to block at the beginning & end of the outage for 245s754W CT replacement. Protections are redundant. 11(96/25SC)/652, 754L A21/79/L7 & 754L B21/L7 will be out of service for the duration of the outage. | 78 Hours
Continuous |
|
| 10-Aug-26 10:00 | 13-Aug-26 16:00 | ALTALINK | TE | 186s RTU/SCADA (186s Dry Creek) | supervisory outage to upgrade meter modules | 78 Hours
Continuous |
|
| 10-Aug-26 11:00 | 13-Aug-26 16:30 | ALTALINK | Outage | 71s 138kV West Bus (71s Lamoureux), 71s T1 (71s Lamoureux), 71s 152 (71s Lamoureux), 71s 552 (71s Lamoureux), 71s C1 (71s Lamoureux), 71s C2 (71s Lamoureux) | transformer maintenance, switch maintenance, breaker maintenance | 77.5 Hours
Continuous |
|
| 10-Aug-26 12:00 | 13-Aug-26 18:00 | ALTALINK | Outage | 754L (245s Seebe - 742L tap), 245s 754W (245s Seebe) | 245s754W CT replacement | 78 Hours
Continuous |
|
| 10-Aug-26 12:30 | 13-Aug-26 17:00 | ALTALINK | Outage | 17s 85 (17s Benalto), 17s T2 (17s Benalto) | 17s85 CT replacement | 76.5 Hours
Continuous |
|
| 10-Aug-26 13:00 | 13-Aug-26 13:00 | ATCO | TE | 939s Protection & Control (939s Livock), 939s RTU/SCADA (939s Livock) | CIP update password at 939S | 72 Hours
Continuous |
|
| 10-Aug-26 23:52 | 14-Aug-26 17:00 | ATCO | Outage | 7L171 (802s Michichi Creek - 804s Wintering Hills), 802s 706 (802s Michichi Creek), 804s 701 (804s Wintering Hills) | forced outage | 89.13 Hours
Continuous |
|
| 11-Aug-26 07:00 | 13-Aug-26 18:00 | ALTALINK | Outage | 310p 1852 (310p Sundance) | replace 310p1852 CT's | 59 Hours
Continuous |
|
| 11-Aug-26 07:00 | 13-Aug-26 18:00 | ALTALINK | TE | 310p Protection & Control (310p Sundance) | isolate protections for CT1852 testing, restore protections daily | 59 Hours
Daily |
|
| 11-Aug-26 07:15 | 16-Aug-26 16:45 | ALTALINK | Outage | 790L (434s Stony Plain - 790AL tap), 434s 790 (434s Stony Plain) | LOA for old 434s T3 transformer removal | 129.5 Hours
Continuous |
|
| 11-Aug-26 10:00 | 24-Aug-26 16:00 | ATCO | Outage | 6L96 (735s Swan River - 743s Sarah Lake), 743s 604 (743s Sarah Lake), 735s 604 (735s Swan River) | 743S sarah lake rebuild, replace breaker 604 | 318 Hours
Continuous |
|
| 12-Aug-26 07:00 | 16-Aug-26 17:00 | EPCOR | Outage | T1 (Meadowlark), 72JM18 (EP 805s Jasper - Meadowlark), M722 (Meadowlark), M721 (Meadowlark), MAB1 (Meadowlark), EP 805s J722 (EP 805s Jasper) | TX1zone, LCR civil work | 106 Hours
Continuous |
|
| 12-Aug-26 08:00 | 13-Aug-26 16:00 | ALTALINK | TE | AltaLink Telecom Equipment | MPLS maintenance | 32 Hours
Daily |
|
| 12-Aug-26 09:00 | 13-Aug-26 17:00 | ATCO | TE | 2075s Protection & Control (2075s Newell) | replace failed 900BS2 relay | 32 Hours
Continuous |
|
| 13-Aug-26 06:00 | 18-Aug-26 18:00 | SUNCOR | Outage | 635EDD-1000 635PK-1001 (635EDD-1000), 635EDD-1000 635-752-161 (635EDD-1000), 635EDD-1000 635-752-162 (635EDD-1000), 635EDD-1000 635PS-1044 (635EDD-1000) | planned maintenance of diameter | 132 Hours
Continuous |
|
| 13-Aug-26 07:00 | 13-Aug-26 11:30 | EPCOR | Outage | 987s CS2 (987s Clover Bar), 987s SST2 (987s Clover Bar) | bus diff upgrade cutovers | 4.5 Hours
Continuous |
|
| 13-Aug-26 07:00 | 13-Aug-26 17:00 | ALTALINK | TE | 77s Protection & Control (77s Sagitawah) | breaker fail protection outage (77s652) for trip testing, no redundancy | 10 Hours
Daily |
|
| 13-Aug-26 08:00 | 13-Aug-26 16:00 | ALTALINK | TE | 356s Protection & Control (356s Milo) | 927L settings changes for metering updates | 8 Hours
Daily |
|
| 13-Aug-26 08:00 | 13-Aug-26 16:00 | ALTALINK | TE | 356s RTU/SCADA (356s Milo) | configuration updates for L4 protection metering updates | 8 Hours
Daily |
|
| 13-Aug-26 08:00 | 13-Aug-26 16:00 | ENMAX | TE | Protection & Control (SS-3) | 138 kV bus differential protection, lockout relay protection outage, relay protection test | 8 Hours
Continuous |
|
| 13-Aug-26 08:31 | 13-Aug-26 17:30 | ALTALINK | Outage | 77s 552 (77s Sagitawah) | trip test 77s552 | 8.98 Hours
Continuous |
|
| 13-Aug-26 09:30 | 14-Aug-26 16:00 | ATCO | TE | ATCO Telecom Equipment, 840s RTU/SCADA (840s McNeill Station) | moving communication and Scada traffic onto new star link device
|
30.5 Hours
Continuous |
|
| 13-Aug-26 10:00 | 13-Aug-26 12:59 | SUNCOR | Outage | 29EDD-1 29EDD1s1852 (29EDD-1 Millennium) | PRC-00, relay testing | 2.98 Hours
Continuous |
|
| 13-Aug-26 10:00 | 13-Aug-26 16:00 | ATCO | TE | 977s Protection & Control (977s Salt Creek) | troubleshoot communication to 901T ground current monitoring device | 6 Hours
Continuous |
|
| 13-Aug-26 12:00 | 13-Aug-26 16:00 | ALTALINK | TE | 395s RTU/SCADA (395s North Holden), AltaLink Telecom Equipment | MPLS upgrade | 4 Hours
Continuous |
|
| 13-Aug-26 13:00 | 13-Aug-26 17:00 | SUNCOR | Outage | 29EDD-1 29EDD1S1452 (29EDD-1 Millennium) | PRC-005, relay testing | 4 Hours
Continuous |
|
| 14-Aug-26 07:00 | 15-Aug-26 18:00 | ALTALINK | Outage | 720L (347s AML Fox Creek - 397s Benbow), 347s 720X (347s AML Fox Creek), 397s 720N (397s Benbow) | urgent, 720L repair existing dead-ends on structure 99 & 99A | 35 Hours
Continuous |
|
| 14-Aug-26 08:00 | 14-Aug-26 12:00 | ENMAX | Outage | 162.3TR (SS-162), 162B138-RB85 (SS-162), 162B138-RB86 (SS-162) | summer substation washing | 4 Hours
Continuous |
|
| 14-Aug-26 08:00 | 18-Aug-26 20:00 | SUNCOR | TE | 29EDD-1 29EDD1s1052 (29EDD-1 Millennium), 29EDD-1 29EDD1s852 (29EDD-1 Millennium) | 29EDD1/ X260B2 south bus PRC-005 / relay test | 84 Hours
Continuous |
|
| 14-Aug-26 09:00 | 14-Aug-26 11:00 | ATCO | TE | ATCO Telecom Equipment | upgrading the Dino park SAR OS to V21, then V22 | 2 Hours
Continuous |
|
| 14-Aug-26 09:00 | 15-Aug-26 17:30 | ALTALINK | Outage | 1034L (244s Bowmanton - 324s Cassils) | urgent repair 1034L6 OPGW | 32.5 Hours
Continuous |
|
| 14-Aug-26 09:00 | 15-Aug-26 17:30 | ATCO, ALTALINK | RB | 1088L (324s Cassils - 2075s Newell) | 1088L proximity R/B For 1034L urgent repair | 32.5 Hours
Daily |
|
| 14-Aug-26 09:00 | 15-Aug-26 17:30 | ATCO, ALTALINK | RB | 9L1088 (324s Cassils - 2075s Newell) | AltaLink request: 1034L urgent repair. block reclosers on 1088L @ 2075s | 32.5 Hours
Continuous |
|
| 14-Aug-26 10:00 | 28-Aug-26 17:30 | ATCO | Outage | 7L65 (709s Vegreville - 7LA65 tap), 709s 703 (709s Vegreville) | 7L65 rebuild - phase 3 - protection upgrade at 709S, 708S and 710S
|
343.5 Hours
Continuous |
|
| 14-Aug-26 12:00 | 21-Aug-26 17:30 | ATCO | TE | 709s Protection & Control (709s Vegreville) | 7L65 rebuild - phase 3
|
173.5 Hours
Continuous |
|
| 14-Aug-26 12:00 | 14-Aug-26 18:00 | ENMAX | Outage | 162B138-RB92 (SS-162), 162B138-RB94 (SS-162), 162.4TR (SS-162) | summer substation washing | 6 Hours
Continuous |
|
| 14-Aug-26 17:00 | 14-Aug-26 19:00 | BCH | Outage | 2L293 (BCH Nelway - BCH Selkirk) | instrument transformer replacement project | 2 Hours
Continuous |
AB-BC |
| 15-Aug-26 08:00 | 15-Aug-26 18:00 | ENMAX | Outage | 36.5TR (SS-36), 16B69-16.63 (SS-16), 14.83L (SS-14 - SS-36), 36.2TR (SS-36), 36B138-36BT3 (SS-36) | Substation Structure Painting | 10 Hours
Continuous |
|
| 15-Aug-26 08:00 | 15-Aug-26 16:00 | ENMAX | Outage | 16.63L (SS-16 - SS-36), 16B69-16.63 (SS-16) | Breaker Power Factor Test - 16B69-16.63 | 8 Hours
Continuous |
|
| 15-Aug-26 09:00 | 16-Aug-26 20:00 | SUNCOR | TE | 29EDD-34 29PT-340 (29EDD-34), 29EDD-34 29PT-341 (29EDD-34) | 29PT-340 / 29PT-341 re-calibrate | 35 Hours
Continuous |
|
| 15-Aug-26 12:00 | 15-Aug-26 17:00 | EPCOR | Outage | 987s CK726 (987s Clover Bar), 72CK13 (987s Clover Bar - Kennedale) | Cloverbar: CK726, BUS Diff Upgrade Cutovers | 5 Hours
Continuous |
|
| 16-Aug-26 07:00 | 18-Aug-26 17:00 | ALTALINK | TE | 254s Protection & Control (254s Coaldale) | modify the communication settings | 58 Hours
Daily |
|
| 16-Aug-26 08:00 | 16-Aug-26 18:00 | ENMAX | Outage | 7.84L (SS-7 - SS-36), 36B138-36BT3 (SS-36), 36.1TR (SS-36), 36.3TR (SS-36), 36B138-36.81 (SS-36) | Substation Structure Painting | 10 Hours
Continuous |
|
| 16-Aug-26 08:00 | 16-Aug-26 18:00 | ENMAX, ALTALINK | IO | 36.81L (44s Bearspaw Plant - SS-36) | ENMAX - Substation Structure Painting | 10 Hours
Continuous |
|
| 16-Aug-26 08:00 | 18-Aug-26 16:00 | ALTALINK | TE | 254s Protection & Control (254s Coaldale), 254s RTU/SCADA (254s Coaldale) | Loss of ACC visibility for up to 5 minutes to fix remote access issue with 172LE, 172LW and 820L SEL-311C relays. Supervisory outage will be returned EOD, everyday | 56 Hours
Daily |
|
| 17-Aug-26 07:00 | 23-Aug-26 17:00 | EPCOR | Outage | T2 (EP Hardisty), H722 (EP Hardisty), H723 (EP Hardisty), H726 (EP Hardisty) | Hardisty: TX2/H722 Doble and HAB2/HDS6/HDS7/HDS12 Disconnect Maintenance and H722/H723/H726 (SF6) Breaker Maintenance | 154 Hours
Continuous |
|
| 17-Aug-26 07:00 | 21-Aug-26 18:00 | ALTALINK, BCH | RB | 1201L (520s Bennett - BCH Cranbrook) | conductor inspection on STR's 21-22, 50-51, 187-188, 279-280
|
107 Hours
Continuous |
|
| 17-Aug-26 07:00 | 23-Aug-26 17:00 | EPCOR | TE | RTU/SCADA (University of Alberta) | cutovers and commissioning | 154 Hours
Continuous |
|
| 17-Aug-26 07:00 | 18-Aug-26 17:00 | EPCOR | Outage | 987s T3 (987s Clover Bar), 987s C2407 (987s Clover Bar) | relay maintenance | 34 Hours
Continuous |
|
| 17-Aug-26 07:00 | 18-Aug-26 17:00 | ALTALINK, EPCOR | TE | 947L (89s Ellerslie - 987s Clover Bar) | protection blocking, MPLS troubleshooting | 34 Hours
Continuous |
|
| 17-Aug-26 07:30 | 21-Aug-26 17:30 | ALTALINK | RB | 760L (163s Amoco Empress - 760AL tap) | HOP required for installing interphase spacers on 7L760 live line | 106 Hours
Continuous |
|
| 17-Aug-26 08:00 | 27-Aug-26 16:00 | Syncrude | Outage | 34 (Aurora), 33B (Aurora), 34A (Aurora), 89-37 (Aurora) | Zone 13 6yr PM | 248 Hours
Continuous |
|
| 17-Aug-26 08:00 | 21-Aug-26 17:00 | ATCO | RB | 7L760 (767s Oyen - 7LC760 tap) | HOP required for installing interphase spacers on 7L760 live line and installing bird flight diverters on shield wire | 105 Hours
Continuous |
|
| 17-Aug-26 08:00 | 24-Aug-26 16:00 | ATCO | Outage | 7L48 (794s Valleyview - 7LA48 tap), 794s 703 (794s Valleyview) | pole replacement from test and treat | 176 Hours
Continuous |
|
| 17-Aug-26 08:00 | 21-Aug-26 16:00 | ALTALINK | TE | 237s Protection & Control (237s Foothills) | fault recording implementation | 104 Hours
Daily |
|
| 17-Aug-26 08:00 | 21-Aug-26 16:00 | ALTALINK | TE | 237s RTU/SCADA (237s Foothills) | firmware upgrade and configuration changes on the RTU for fault reporting implementation | 104 Hours
Daily |
|
| 17-Aug-26 08:00 | 18-Aug-26 16:00 | ENMAX | TE | Protection & Control (SS-3) | 3sub BMR 82 protection outage, relay protection test | 32 Hours
Daily |
|
| 17-Aug-26 08:00 | 27-Aug-26 15:00 | CMH | TE | MH-15L (MHS-7 Brier Park - MHS-9 South Saskatchewan) | carry out maintenance on the LDR-15L-A | 247 Hours
Continuous |
|
| 17-Aug-26 08:00 | 20-Aug-26 17:00 | ALTALINK | Outage | 310p 1252 (310p Sundance), 310p 1152 (310p Sundance), 310p 11A (310p Sundance), 310p 12B (310p Sundance) | replace 310p1152 BKR CT's and repair switch 310p11A | 81 Hours
Continuous |
|
| 17-Aug-26 08:00 | 20-Aug-26 17:00 | ALTALINK | TE | 310p Protection & Control (310p Sundance) | CT 1152 testing | 81 Hours
Daily |
|
| 17-Aug-26 08:00 | 20-Aug-26 16:00 | ENMAX | Outage | 3.3TR (SS-3) | tap changer inspection, oil leaks | 80 Hours
Continuous |
|
| 17-Aug-26 08:00 | 17-Aug-26 16:00 | ENMAX | Outage | 8.6TR (SS-8) | display replacement | 8 Hours
Continuous |
|
| 17-Aug-26 08:00 | 11-Sep-26 16:00 | ALTALINK | TE | 89s Protection & Control (89s Ellerslie) | MPLS TPR re-arrangements project: 908L (Ellerslie 89S -Petrolia E816s) relay testing and cutover | 608 Hours
Continuous |
|
| 17-Aug-26 08:00 | 11-Sep-26 16:00 | ALTALINK | TE | 37s Protection & Control (37s North Calder) | 930L (North Calder 37S -Poundmaker EPCOR) relay testing and cutover | 608 Hours
Continuous |
|
| 17-Aug-26 08:00 | 11-Sep-26 16:00 | ALTALINK | TE | 367s Protection & Control (367s Harry Smith) | 1139L (Harry Smith 367S -Riverview EPCOR) MPLS TPR re-arrangements project, EPCOR relay testing and cutover | 608 Hours
Continuous |
|
| 17-Aug-26 08:00 | 11-Sep-26 16:00 | ALTALINK | TE | 37s Protection & Control (37s North Calder) | 920LE (North Calder 37S -E557s Castle Downs EPCOR) EPCOR relay testing and cutover | 608 Hours
Continuous |
|
| 17-Aug-26 08:00 | 11-Sep-26 16:00 | ALTALINK | TE | 71s Protection & Control (71s Lamoureux) | 920LW (Lamoreux 71S -E557s Castle Downs EPCOR) MPLS TPR re-arrangements project, EPCOR relay testing and cutover | 608 Hours
Continuous |
|
| 17-Aug-26 08:00 | 18-Aug-26 16:00 | ENMAX | Outage | 5.5TR (SS-5) | make adjustments on the 5B13-5.5TR breaker due to an alignment/racking issue | 32 Hours
Continuous |
|
| 17-Aug-26 08:00 | 18-Aug-26 16:00 | ALTALINK | TE | 89s Protection & Control (89s Ellerslie) | EPCOR requested AML to support EPCOR with 947L B protection comm fail in EPCOR MPLS TPR re-arrangements project | 32 Hours
Continuous |
|
| 17-Aug-26 08:00 | 17-Aug-26 16:00 | ALTALINK | TE | 213s Protection & Control (213s Hughenden) | remote settings change on A21/L2 and B21/L2 | 8 Hours
Continuous |
|
| 17-Aug-26 08:00 | 19-Aug-26 16:00 | ENMAX | RB | 16.60L (SS-16 - SS-34) | tree trimming | 56 Hours
Continuous |
|
| 17-Aug-26 08:00 | 21-Aug-26 16:00 | ATCO | TE | 888s Protection & Control (888s Dover) | settings change on 9L43 for Telecom work 1-00524242
|
104 Hours
Continuous |
|
| 17-Aug-26 08:00 | 19-Aug-26 15:30 | CMH | Outage | MHS-3 MH69-T33 (MHS-3 South Ridge), MHS-3 MH69-314 (MHS-3 Southridge) | Transformer protection settings change and functional testing | 55.5 Hours
Continuous |
|
| 17-Aug-26 08:00 | 17-Aug-26 12:00 | ENMAX | Outage | 65B138-D81 (SS-65) | HV Breaker SF6 Gas Sample - 65B138-D81 | 4 Hours
Continuous |
|
| 17-Aug-26 09:00 | 17-Aug-26 10:00 | ATCO | TE | ATCO Telecom Equipment | upgrading the Nevis sub net 11 SAR TO V21, THEN V21 | 1 Hour
Continuous |
|
| 17-Aug-26 09:00 | 17-Aug-26 15:00 | ATCO | TE | 802s 702T (802s Michichi Creek), 802s 703T (802s Michichi Creek), 802s Protection & Control (802s Michichi Creek) | to mitigate against transformer loss of life, adjustments to the Fan 1 and Fan 2 factory TURN ON temps from 75°C and 85°C to 60 °C and 70 °C respectively for both 702T and 703T at 802S Michichi | 6 Hours
Continuous |
|
| 17-Aug-26 09:00 | 20-Aug-26 17:30 | ALTALINK | Outage | 761L (38s East Edmonton - 71s Lamoureux), 38s 761N (38s East Edmonton) | transmission line maintenance | 80.5 Hours
Continuous |
|
| 17-Aug-26 09:00 | 20-Aug-26 20:00 | SUNCOR | Outage | 29EDD-94 29PS-641 (29EDD-94 Voyageur), 29PL9-24 (29EDD-94 Voyageur - 29EDD-60 Inglis Island) | 29PS-641 Requires to be realigned as it is not seated correctly while closed. This should be completed in the current outage window of GTG-12 / along with Outage 1-00530435, WO# 300769279 | 83 Hours
Continuous |
|
| 17-Aug-26 09:30 | 22-Aug-26 17:00 | ALTALINK, EPCOR | Outage | 920L (71s Lamoureux - 557s Castle Downs), 557s CD2405 (557s Castle Downs), 557s CD2404 (557s Castle Downs), 557s CDDS14 (557s Castle Downs), 557s CDDS8 (557s Castle Downs) | CT/CVT doble and surge arrestor LCR | 127.5 Hours
Continuous |
|
| 17-Aug-26 09:30 | 22-Aug-26 17:00 | ALTALINK, EPCOR | IO | 920L (71s Lamoureux - 557s Castle Downs) | CT/CVT doble and surge arrestor LCR | 127.5 Hours
Continuous |
|
| 17-Aug-26 09:30 | 11-Sep-26 17:00 | ALTALINK, EPCOR | TE | 908L (89s Ellerslie - 816s Petrolia) | protection blocking for MPLS cutovers and commissioning | 607.5 Hours
Continuous |
|
| 17-Aug-26 09:30 | 11-Sep-26 17:00 | ALTALINK, EPCOR | TE | 1139L (367s Harry Smith - EP Riverview) | protection blocking for MPLS cutovers and commissioning | 607.5 Hours
Continuous |
|
| 17-Aug-26 09:30 | 11-Sep-26 17:00 | ALTALINK, EPCOR | TE | 930L (37s North Calder - Poundmaker) | protection blocking for MPLS cutovers and commissioning | 607.5 Hours
Continuous |
|
| 17-Aug-26 09:30 | 11-Sep-26 17:00 | ALTALINK, EPCOR | TE | 1045L (EP 805s Jasper - 1045AL tap) | protection blocking for MPLS cutovers and commissioning | 607.5 Hours
Continuous |
|
| 17-Aug-26 09:30 | 11-Sep-26 17:00 | ALTALINK, EPCOR | TE | 920L (71s Lamoureux - 557s Castle Downs) | protection blocking for MPLS cutovers and commissioning | 607.5 Hours
Continuous |
|
| 17-Aug-26 09:30 | 11-Sep-26 17:00 | ALTALINK, EPCOR | TE | 920L (37s North Calder - 557s Castle Downs) | protection blocking for MPLS cutovers and commissioning | 607.5 Hours
Continuous |
|
| 17-Aug-26 10:00 | 27-Aug-26 17:30 | ATCO | TE | 2075s Protection & Control (2075s Newell) | 20DL02.06+R1-F873 (9L1087) relay firmware upgrade | 271.5 Hours
Continuous |
|
| 17-Aug-26 10:00 | 18-Aug-26 16:00 | ATCO | Outage | 7L47 (718s Parsons Creek - 848s Ruth Lake), 848s 703T (848s Ruth Lake), 718s 701 (718s Parsons Creek), 848s 702 (848s Ruth Lake) | breaker maintenance | 30 Hours
Continuous |
|
| 17-Aug-26 10:00 | 18-Aug-26 15:00 | ATCO | TE | 741s RTU/SCADA (741s Fox Creek), 741s Protection & Control (741s Fox Creek) | 741S Fox Creek 21B/7L90 deficiency - fixing relay mis-coordination, BMS fail alarm, BMS DNP3 index mismatch - station controller update | 29 Hours
Continuous |
|
| 17-Aug-26 10:00 | 19-Aug-26 17:00 | ATCO | Outage | 813s 708 (813s Little Smoky) | breaker SF6 HGF complete testing | 55 Hours
Continuous |
|
| 17-Aug-26 11:00 | 20-Aug-26 16:00 | ALTALINK | TE | 320p Protection & Control (320P Keephills) | protection outages required to isolate for 320p652 CT replacement | 77 Hours
Continuous |
|
| 17-Aug-26 11:00 | 20-Aug-26 16:45 | ALTALINK | Outage | 997L (71s Lamoureux - 430s Ursus), 71s T2 (71s Lamoureux), 71s 240kV East Bus (71s Lamoureux), 71s 1752 (71s Lamoureux), 71s 1452 (71s Lamoureux), 71s 1352 (71s Lamoureux), 71s 32 (71s Lamoureux), 71s 997E (71s Lamoureux), 71s 37 (71s Lamoureux), 71s 36 (71s Lamoureux), 71s 47 (71s Lamoureux), 71s 46 (71s Lamoureux) | multiple switch repair/replacement and maintenance 71s36, 71s37, 71s46, 71s47 | 77.75 Hours
Continuous |
|
| 17-Aug-26 11:00 | 19-Aug-26 19:00 | ATCO | RB | 7L09 (823s Wapiti - 7L03 tap) | installing marker cones on span at str 70 | 56 Hours
Continuous |
|
| 17-Aug-26 11:00 | 20-Aug-26 16:00 | ATCO | RB | 7L85 (801s Anderson - ATC 803s Bullpound), 7L85 (804s Wintering Hills - 7LA85 tap) | installing interphase spacers on 7L85 live line | 77 Hours
Continuous |
|
| 17-Aug-26 11:00 | 20-Aug-26 16:00 | ALTALINK | TE | 245s Protection & Control (245s Seebe) | 245s777X CT replacement | 77 Hours
Continuous |
|
| 17-Aug-26 11:00 | 21-Aug-26 17:00 | BCH | Outage | 5L91 (BCH Ashton Creek - BCH Selkirk) | end of life insulator replacement | 102 Hours
Continuous |
AB-BC |
| 17-Aug-26 11:30 | 24-Aug-26 14:30 | ATCO, ALTALINK | RB | 199L (347s AML Fox Creek - 741s ATC Fox Creek) | 14 red tag pole change program | 171 Hours
Continuous |
|
| 17-Aug-26 12:00 | 20-Aug-26 17:00 | ALTALINK | Outage | 777L (48s Pocaterra - 245s Seebe), 245s 777X (245s Seebe) | 245s777X 138kV CT replacement | 77 Hours
Continuous |
AB-BC |
| 17-Aug-26 12:00 | 24-Aug-26 14:00 | ATCO, ALTALINK | RB | 7L199 (347s AML Fox Creek - 741s ATC Fox Creek) | 14 red tag pole change program | 170 Hours
Continuous |
|
| 17-Aug-26 12:00 | 20-Aug-26 14:00 | ATCO | Outage | 6L12 (774s Monitor - 6L25 tap), 774s 601 (774s Monitor) | structure replacements and deficiency repair | 74 Hours
Continuous |
|
| 17-Aug-26 12:00 | 17-Aug-26 16:00 | ENMAX | Outage | 65B138-D84 (SS-65) | HV breaker SF6 gas sample - 65B138-D84 | 4 Hours
Continuous |
|
| 17-Aug-26 12:30 | 20-Aug-26 17:00 | ALTALINK | Outage | 320p 652 (320p Keephills) | replace 320p652 external CT's | 76.5 Hours
Continuous |
|
| 17-Aug-26 13:00 | 20-Aug-26 13:00 | ATCO | Outage | 9L10 (876s Brintnell - 939s Livock), 939s 903T (939s Livock), 939s 911 (939s Livock), 939s 910 (939s Livock), 939s 904 (939s Livock), 939s 903 (939s Livock), 939s 912 (939s Livock), 939s 910A (939s Livock), 939s 900D1 (939s Livock) | PRC-005 - SPR TESTING - TRANSFORMER 903T @ 939S Repair and adjust 910A @ 939S APL Repalce OLTC Filters, 903T @ 939S Livock |
72 Hours
Continuous |
|
| 17-Aug-26 13:00 | 20-Aug-26 13:00 | ATCO | Outage | 828s 702 (828s Sulphur Point) | breaker SF6 LTB145D1/B complete testing
|
72 Hours
Continuous |
|
| 17-Aug-26 14:00 | 25-Aug-26 17:00 | ALTALINK, FORTIS | Outage | 275s T1 (275s Jenner), 275s 52F1 (275s Jenner), 275s 52F2 (275s Jenner) | replace LV bushings, TC Maintenance, copper cutouts | 195 Hours
Continuous |
|
| 17-Aug-26 14:00 | 20-Aug-26 16:30 | ALTALINK | Outage | 574s T1 (574s Nilrem) | transformer maintenance | 74.5 Hours
Continuous |
|
| 18-Aug-26 07:00 | 18-Aug-26 18:00 | ALTALINK | Outage | 1112L (89s Ellerslie - 289s Saunders Lake) | transmission line maintenance | 10.5 Hours
Daily |
|
| 18-Aug-26 07:00 | 18-Aug-26 18:00 | ALTALINK | RB | 1140L (89s Ellerslie - 289s Saunders Lake) | safety requirement for proximity to 1112L | 10 Hours
Daily |
|
| 18-Aug-26 07:00 | 19-Aug-26 20:00 | ALTALINK, PR | Outage | 949L (275s Jenner - 306s Halsbury), 275s 949 (275s Jenner), 306s 240CB1 (306s Halsbury), 306s 240MDS1 (306s Halsbury), 306s 240MDS2 (306s Halsbury), 306s 240MDS3 (306s Halsbury) | customer 949L work | 37 Hours
Continuous |
|
| 18-Aug-26 07:00 | 24-Aug-26 17:00 | ATCO | TE | 743s Protection & Control (743s Sarah Lake) | isolating 21A/6L96 | 154 Hours
Continuous |
|
| 18-Aug-26 07:30 | 27-Aug-26 08:30 | ALTALINK | Outage | 77s 752 (77s Sagitawah) | protection upgrade 77s752 | 217 Hours
Continuous |
|
| 18-Aug-26 07:30 | 18-Aug-26 15:30 | ALTALINK | Outage | 106s 744 (106s Paddle River), 106s T1 (106s Paddle River) | customer maintenance | 8 Hours
Continuous |
|
| 18-Aug-26 08:00 | 19-Aug-26 17:00 | ALTALINK, FMGW, ATCO | Outage | 964AL (1024s Granlea - 964L tap), 1024s PT-6001 (1024s Granlea), 1024s PT-6002 (1024s Granlea), 1024s 952-600001 (1024s Granlea), 1024s PS-6005 (1024s Granlea), 1024s PS-6006 (1024s Granlea), 1024s PS-6007 (1024s Granlea), 1024s PS-6008 (1024s Granlea), 1024s 489-600201 (1024s Granlea) | maintenance activities (testing and inspection) of electrical equipment | 33 Hours
Continuous |
|
| 18-Aug-26 08:00 | 18-Aug-26 16:00 | ENMAX | Outage | 13.82L (SS-13 - SS-22), 22.1TR (SS-22), 22B138-13.82 (SS-22), 13B138-13.82 (SS-13) | maintenance on SW 82 at 22 Sub | 8 Hours
Continuous |
|
| 18-Aug-26 08:00 | 20-Aug-26 16:00 | ALTALINK | TE | 138s Protection & Control (138s Windy Flats) | removing for maintenance, 603L, 608L, 1037L, 1038L A & B removed one at a time, redundant protection at all times | 56 Hours
Daily |
|
| 18-Aug-26 08:00 | 18-Aug-26 16:00 | ALTALINK | TE | 332s Protection & Control (332s Ellis) | techs to complete standard maintenance on the following redundant protections,784L, T1 A, B & S, T2 A, B & S. | 8 Hours
Daily |
|
| 18-Aug-26 08:00 | 19-Aug-26 19:00 | ATCO | RB | 7L44 (749s Flyingshot Lake - 845s Big Mountain) | installing marker cones on span at str 25 | 35 Hours
Continuous |
|
| 18-Aug-26 08:00 | 19-Aug-26 17:00 | ATCO | RB | 7L46 (813s Little Smoky - 845s Big Mountain) | installing marker cones on 7L45/46 at spans 352, 403, 92 | 33 Hours
Continuous |
|
| 18-Aug-26 08:00 | 19-Aug-26 19:00 | ATCO | RB | 7L33 (845s Big Mountain - 7LA33 tap), 7L33 (749s Flyingshot Lake - 7LA33 tap) | installing marker cones on span at str 97 | 35 Hours
Continuous |
|
| 18-Aug-26 08:00 | 19-Aug-26 19:00 | ATCO | RB | 7L45 (798s Bridge Creek - 813s Little Smoky), 7L45 (798s Bridge Creek - 845s Big Mountain) | installing marker cones on span at str 352, 403, 92 | 35 Hours
Continuous |
|
| 18-Aug-26 08:00 | 24-Aug-26 17:00 | ATCO | TE | 743s Protection & Control (743s Sarah Lake) | blocking 21B/6L96 for relay testing | 153 Hours
Continuous |
|
| 18-Aug-26 08:00 | 24-Aug-26 17:00 | ATCO | TE | 743s Protection & Control (743s Sarah Lake) | 50BF/604 for relay testing | 153 Hours
Continuous |
|
| 18-Aug-26 08:00 | 24-Aug-26 17:00 | ATCO | TE | 743s Protection & Control (743s Sarah Lake) | 86-50BF-1/600BS1 and 94-50BF-1/600BS1. | 153 Hours
Continuous |
|
| 18-Aug-26 08:00 | 18-Aug-26 16:00 | ALTALINK | TE | AltaLink Telecom Equipment | MPLS node A&B upgrade | 8 Hours
Daily |
|
| 18-Aug-26 09:00 | 18-Aug-26 16:00 | ATCO | TE | ATCO Telecom Equipment, 933s RTU/SCADA (933s Tower Road) | Tower Road Telecom outage | 7 Hours
Continuous |
|
| 18-Aug-26 09:00 | 19-Aug-26 16:00 | ATCO | TE | ATCO Telecom Equipment | Leak in the IRU radio to Nevis_T waveguide. Checked the inside lines and no leak found, will need a tower crew to check feedline going up the tower and connectors to the feedhorn. link will be down from 10am-2pm on August 19th Please see the Email sent of May 11 for impacts |
31 Hours
Continuous |
|
| 18-Aug-26 09:00 | 19-Aug-26 17:00 | ATCO | TE | ATCO Telecom Equipment, 757s RTU/SCADA (757s Battle River) | comm pls life cycle upgrades to SAR A , new SAR A, SDI cards 1.3/1.4 slots |
32 Hours
Continuous |
|
| 18-Aug-26 09:00 | 18-Aug-26 10:00 | ATCO, ALTALINK | TE | 951s Protection & Control (951s Thickwood Hills), 12L41 (510s Sunnybrook - 939s Livock), 12L44 (939s Livock - 951s Thickwood Hills), 9L01 (848s Ruth Lake - 951s Thickwood Hills), 9L30 (888s Dover - 951s Thickwood Hills), 9L112 (888s Dover - 951s Thickwood Hills), 9L07 (951s Thickwood Hills - 2011s Dawes), ATCO Telecom Equipment | Upgrade 951s net sar OS to v21, then v22 impact to following traffic up to 1 hr: 9L74 RAS B (951S / 888S), 12L41 LTO RAS A (951S / 510S), 12L44-21LB1 ALT B (951S / 939S), 9L07B (951S/ 2011S), 9L112 A (951S /888S), 9L30A (951S /888S)
9L01A 951S/ 848S |
1 Hour
Continuous |
|
| 18-Aug-26 09:00 | 18-Aug-26 14:00 | Saskpower | Outage | Sask Power AS905 | maintenance | 5 Hours
Continuous |
AB-SK |
| 18-Aug-26 09:30 | 19-Aug-26 17:30 | ATCO, ALTALINK | Outage | 702L (137s Sedgewick - 757s Battle River), 757s 708 (757s Battle River), 137s 702W (137s Sedgewick) | breaker sf6 ltb145D1/B and PRC-005 - trip coil testing, breaker 708 @ 757S | 32 Hours
Continuous |
|
| 18-Aug-26 09:30 | 18-Aug-26 17:30 | ALTALINK | TE | 48s Protection & Control (48s Pocaterra) | isolate and test DTT from BC hydro as per their request, protections are not redundant | 8 Hours
Continuous |
|
| 18-Aug-26 09:30 | 18-Aug-26 17:30 | ALTALINK, BCH | TE | 1L274 (BCH Natal - BCH Line Creek tap) | NIC RAS PLC PY/SY OOS | 8 Hours
Continuous |
AB-BC |
| 18-Aug-26 10:00 | 18-Aug-26 12:59 | SUNCOR | Outage | 29EDD-1 29EDD1s1052 (29EDD-1 Millennium) | 29EDD1 / X260B2 south PRC-005 / relay test -trip open 29EDD1s1052 (29EDD-1 Millennium) - 450338057 In conjunction with Outage 1-00529388 |
2.98 Hours
Continuous |
|
| 18-Aug-26 10:00 | 18-Aug-26 16:00 | ATCO | TE | ATCO Telecom Equipment | Green Stocking telecom switch update | 6 Hours
Continuous |
|
| 18-Aug-26 13:00 | 18-Aug-26 17:00 | SUNCOR | Outage | 29EDD-1 29EDD1s852 (29EDD-1 Millennium) | 29EDD1 / X260B2 south bus PRC-005 / relay test -trip open 29EDD1s852 (29EDD-1 Millennium) | 4 Hours
Continuous |
|
| 19-Aug-26 08:00 | 20-Aug-26 16:00 | ENMAX | Outage | 13.82L (SS-13 - SS-22), 22B138-13.82 (SS-22), 13B138-13.82 (SS-13) | HV Breaker Maintenance. | 32 Hours
Continuous |
|
| 19-Aug-26 08:00 | 22-Aug-26 16:00 | ALTALINK | TE | 38s RTU/SCADA (38s East Edmonton) | loss of ACC visibility for up to 10 minutes to replace the failing RTU/HMI-B | 80 Hours
Daily |
|
| 19-Aug-26 08:00 | 20-Aug-26 17:00 | ATCO | RB | 9L05 (809s Louise Creek - 813s Little Smoky) | installing marker cones on 9L02/05 at span 345 | 33 Hours
Continuous |
|
| 19-Aug-26 08:00 | 20-Aug-26 19:00 | ATCO | RB | 9L02 (809s Louise Creek - 813s Little Smoky) | installing marker cones on 9L02/06 span at str 345 | 35 Hours
Continuous |
|
| 19-Aug-26 08:00 | 19-Aug-26 16:00 | ENMAX | TE | Protection & Control (SS-33) | 33sub Z31 138kV bus differential protection, 86-Z31 lockout relay protection outage, testing 33RLY138-33.Z31 | 8 Hours
Continuous |
|
| 19-Aug-26 08:00 | 20-Aug-26 16:00 | ALTALINK | TE | AltaLink Telecom Equipment, 89s RTU/SCADA (89s Ellerslie) | upgrade MPLS and firewall | 32 Hours
Daily |
|
| 19-Aug-26 08:00 | 19-Aug-26 16:00 | ENMAX | TE | Protection & Control (SS-41) | 41sub BMR-BT3 protection outage, I&R broken ITB on 41BT3-BMR | 8 Hours
Continuous |
|
| 19-Aug-26 08:00 | 19-Aug-26 16:00 | ENMAX | Outage | 41.2TR (SS-41) | I&R broken ITB | 8 Hours
Continuous |
|
| 19-Aug-26 08:00 | 20-Aug-26 16:00 | ALTALINK | TE | 62s Protection & Control (62s Brazeau Plant) | replace failed protection | 32 Hours
Continuous |
|
| 19-Aug-26 09:00 | 19-Aug-26 16:00 | ATCO | TE | ATCO Telecom Equipment | Birchwood-S-Telecom/Dover_T-Telecom, radio major on IRU link Birchwood to Dover Tower, link will be down from 10am-2pm | 7 Hours
Continuous |
|
| 19-Aug-26 09:00 | 19-Aug-26 16:00 | ATCO | TE | ATCO Telecom Equipment | Flat Top_T-Telecom- radio major at Flat Top | 7 Hours
Continuous |
|
| 19-Aug-26 09:00 | 20-Aug-26 16:00 | ALTALINK | TE | 12s Protection & Control (12s Heartland) | Atco requested 12L85 line protection testing | 31 Hours
Continuous |
|
| 19-Aug-26 10:00 | 20-Aug-26 16:00 | ATCO | Outage | 7L71 (848s Ruth Lake - 2082s Dog Rib), 848s 701 (848s Ruth Lake) | breaker maintenance | 30 Hours
Continuous |
|
| 19-Aug-26 10:00 | 21-Aug-26 17:30 | ATCO, ENEL | TE | 7LA65 (708s Grizzly Bear - 7L65 tap) | 7L65 rebuild, 21A/7LA65 and 21B/7LA65 relay settings updates + end-to-end testing |
55.5 Hours
Continuous |
|
| 19-Aug-26 10:00 | 21-Aug-26 17:30 | ATCO | TE | 710s Protection & Control (710s Vermilion) | 7L65 rebuild, 21A/7L65 and 21B/7L65 relay settings updates + end-to-end testing between 708s Grizzly Bear, 709s Vegreville, and 710s Vermillion | 55.5 Hours
Continuous |
|
| 19-Aug-26 10:30 | 19-Aug-26 16:00 | ALTALINK | TE | 163s Protection & Control (163s Amoco Empress) | settings change and testing of new set points on T1 A & B protections | 5.5 Hours
Continuous |
|
| 19-Aug-26 11:00 | 20-Aug-26 16:00 | ALTALINK | TE | 650s RTU/SCADA (650s Hansman Lake) | RTU database update | 29 Hours
Daily |
|
| 20-Aug-26 08:00 | 24-Aug-26 20:00 | SUNCOR | TE | 29EDD-1 29EDD1s1152 (29EDD-1 Millennium), 29EDD-1 29EDD1s1552 (29EDD-1 Millennium) | 29EDD-1 / N72B1 north bus PRC-005 / relay test | 108 Hours
Continuous |
|
| 20-Aug-26 08:00 | 21-Aug-26 16:00 | ALTALINK | TE | 510s RTU/SCADA (510s Sunnybrook) | split the existing SCADA VLAN from 1 to 1 and 2 | 32 Hours
Daily |
|
| 20-Aug-26 08:00 | 20-Aug-26 16:00 | ENMAX | Outage | 33.2TR (SS-33) | relays, lockout testing | 8 Hours
Continuous |
|
| 20-Aug-26 08:00 | 20-Aug-26 12:00 | ENMAX | TE | 54.81L (SS-54 - SS-65) | SS54 54.81L 'A' protection outage, L90 internal battery fail | 4 Hours
Continuous |
|
| 20-Aug-26 08:00 | 20-Aug-26 16:00 | ENMAX | RB | 21.61L (SS-21 - SS-34) | tree trimming | 8 Hours
Continuous |
|
| 20-Aug-26 08:00 | 20-Aug-26 16:00 | ENMAX | RB | 15.62L (SS-15 - SS-16) | tree trimming | 8 Hours
Continuous |
|
| 20-Aug-26 09:00 | 20-Aug-26 16:00 | ATCO | TE | ATCO Telecom Equipment | Dover_T-Telecom/Mackay River_S-Telecom outage |
7 Hours
Continuous |
|
| 21-Aug-26 07:30 | 26-Aug-26 19:30 | ATCO, ALTALINK | RB | 939L (77s Sagitawah - 809s Louise Creek) | line inspection on 9L939/38 | 132 Hours
Continuous |
|
| 21-Aug-26 07:30 | 26-Aug-26 17:30 | ATCO, ALTALINK | RB | 938L (77s Sagitawah - 809s Louise Creek) | line inspection 9L939/38 | 130 Hours
Continuous |
|
| 21-Aug-26 08:00 | 21-Aug-26 16:00 | ENMAX | Outage | 16.61L (SS-16 - SS-27), 16B69-16.61 (SS-16) | breaker power factor test | 8 Hours
Continuous |
|
| 21-Aug-26 08:00 | 23-Aug-26 16:00 | ALTALINK | TE | 72s RTU/SCADA (72s Leismer) | split the existing SCADA VLAN from 1 to 1 and 2 | 56 Hours
Daily |
|
| 21-Aug-26 08:00 | 26-Aug-26 19:00 | ATCO, ALTALINK | RB | 9L939 (77s Sagitawah - 809s Louise Creek) | line inspection on 9L939/38 | 131 Hours
Continuous |
|
| 21-Aug-26 08:00 | 26-Aug-26 17:00 | ATCO, ALTALINK | RB | 9L938 (77s Sagitawah - 809s Louise Creek) | line inspection 9L939/38 | 129 Hours
Continuous |
|
| 21-Aug-26 08:00 | 21-Aug-26 16:00 | ENMAX | Outage | 41.1C (SS-41), 41B138-41.1CAP (SS-41) | internal battery fail alarm | 8 Hours
Continuous |
|
| 21-Aug-26 08:00 | 21-Aug-26 17:00 | ATCO, ALTALINK, SHELL | TE | 402s Protection & Control (402s Scotford Expansion 1) | urgent protection outage to troubleshoot air break status into protection and test B87/21/807L L90 relay to prevent mis-operation | 9 Hours
Continuous |
|
| 21-Aug-26 08:00 | 21-Aug-26 17:00 | ALTALINK | TE | 233s Protection & Control (233s Beamer) | urgent work to block protection on 807L B87/21/L1 URL90 for testing of protection logic to prevent mis-operation | 9 Hours
Continuous |
|
| 21-Aug-26 08:00 | 21-Aug-26 17:00 | ALTALINK | TE | 410s Protection & Control (410s Josephburg) | urgent work to block protection 807L B87/21/L7 URL90 for testing of protection logic to prevent mis-operation | 9 Hours
Continuous |
|
| 21-Aug-26 10:00 | 21-Aug-26 16:00 | ATCO | TE | ATCO Telecom Equipment, 720s RTU/SCADA (720s Wabasca) | swapping site networking to VPLS 11 | 6 Hours
Continuous |
| This document and the information contained herein are based upon information and data which by their nature contain a degree of uncertainty and are subject to change. In addition, this document may contain information and data from public sources and/or third parties, which have been assumed to be accurate and complete and have not been verified. Accordingly, the Independent System Operator, operating as the Alberta Electric System Operator (the "AESO") makes no warranty, representation or guarantee, express or implied, with respect to this document or the information contained herein, including, but not limited to, any warranty, representation or guarantee of accuracy, completeness, timeliness, reliability, availability, absence of computer virus, non- infringement, merchantability or suitability for any purpose. Under no circumstances will the AESO, its members, officers, employees, contractors or agents, or any of their respective affiliates, be liable for any errors or omissions in, or any losses, damages or claims whatsoever, whether in contract, tort or otherwise, arising from use of or reliance upon, this document or any information contained herein. © 2009 Alberta Electric System Operator. All rights reserved |