| Alberta Electric System Operator | |
| System Co-ordination Plan | |
| 2026-07-09 to 2026-07-17 | |
| Approved Outages |
| Previous Version | |
| Download CSV |
| From | To | Owner | Type | Element | Scheduled Activity | Date/Time Comments | Interconnection |
|---|---|---|---|---|---|---|---|
| 26-Jul-24 10:00 | 31-Jul-26 16:00 | ATCO | Outage | 826s 504R (826s Marguerite Lake) | emergency removal to replace failed 502R @834S | 17,646 Hours
Continuous |
|
| 20-Mar-25 08:00 | 31-Jul-26 17:00 | ALTALINK | Outage | 256s C1 (256s Harmattan) | forced outage | 11,961 Hours
Continuous |
|
| 25-Nov-25 17:46 | 18-Sep-26 18:00 | ATCO | Outage | 876s 901T (876s Brintnell) | forced outage oil leaking | 7,127.23 Hours
Continuous |
|
| 27-Nov-25 08:30 | 27-Nov-27 16:30 | ALTALINK | TE | 89s Protection & Control (89s Ellerslie) | DSP card replacements on1057L B87/L3 and B240B1 B87/240B1 | 17,528 Hours
Daily |
|
| 04-Jan-26 08:00 | 02-Sep-26 16:00 | SUNCOR | Outage | 29EDD-34 260kV Bus 29PP-45 (29EDD-34), 29EDD-34 29-952-113 (29EDD-34), 29EDD-34 29PS-216 (29EDD-34) | urgent repairs on 29PT-224 at 29EDD34 on 29PP-45 bus | 5,791 Hours
Continuous |
|
| 21-Jan-26 08:00 | 30-Oct-26 16:00 | ENMAX | Outage | 5.7TR (SS-5) | 25kV switchgear replacement | 6,775 Hours
Continuous |
|
| 03-Feb-26 09:00 | 09-Jul-26 17:00 | ATCO | TE | 972s RTU/SCADA (972s Tinchebray) | config changes needed throughout the CETO project | 3,751 Hours
Continuous |
|
| 09-Feb-26 09:00 | 16-Jul-26 17:00 | ATCO | TE | 972s Protection & Control (972s Tinchebray) | block all 50BF protection until cutovers and associated commissioning are complete | 3,607 Hours
Continuous |
|
| 06-Mar-26 17:00 | 13-Nov-26 17:00 | EPCOR | Outage | T1 (Woodcroft) | woodcroft: TX1 LCR civil | 6,048 Hours
Continuous |
|
| 10-Mar-26 10:00 | 30-Nov-26 17:00 | ATCO | TE | 743s RTU/SCADA (743s Sarah Lake) | throughout the course of the project, different apparatus are being replaced, RTU will be blocked prior to download | 6,368 Hours
Continuous |
|
| 11-Mar-26 13:45 | 31-Jul-26 16:00 | ALTALINK | Outage | 535s C1 (535s Joffre) | breaker maintenance | 3,410.25 Hours
Continuous |
|
| 01-May-26 17:00 | 25-Nov-26 17:00 | EPCOR | Outage | T1 (Meadowlark) | T1 LCR civil work | 4,993 Hours
Continuous |
|
| 19-May-26 07:00 | 02-Oct-26 17:00 | EPCOR | TE | 987s Protection & Control (987s Clover Bar) | protection blocking - relay maintenance and bus differential upgrade project | 2,434 Hours
Continuous |
|
| 26-May-26 09:30 | 15-Jul-26 16:30 | ALTALINK | Outage | 157s C1 (157s Lac La Biche) | trip test (157s852) | 1,207 Hours
Continuous |
|
| 27-May-26 18:00 | 17-Jul-26 10:59 | ALTALINK | Outage | 526s C1 (526s Buffalo Creek) | forced outage | 1,216.98 Hours
Daily |
|
| 01-Jun-26 09:00 | 16-Jul-26 17:30 | ATCO | TE | 865s RTU/SCADA (865s Saddlehills) | updating RTU/station controller configuration during SCADA upgrade project | 1,088.5 Hours
Continuous |
|
| 02-Jun-26 10:00 | 15-Jul-26 16:00 | ATCO | Outage | 743s 701T (743s Sarah Lake), 743s 705 (743s Sarah Lake), 743s 605 (743s Sarah Lake), 743s 501 (743s Sarah Lake) | 743S Sarah lake rebuild | 990 Hours
Continuous |
|
| 04-Jun-26 07:01 | 10-Feb-27 17:00 | EPCOR | Outage | T1 (Rossdale) | rossdale: TX1 lcr civil | 6,034.98 Hours
Continuous |
|
| 07-Jun-26 17:05 | 01-Oct-26 00:00 | ACCIONA, ENBRIDGE, ICPCL | Outage | 139s C1 (139s Hillridge) | forced outage | 2,766.92 Hours
Continuous |
|
| 08-Jun-26 07:00 | 30-Oct-26 17:00 | EPCOR | TE | EP 511s Protection & Control (EP 511s Victoria) | 72kV breaker fail protection blocking | 2,626 Hours
Continuous |
|
| 09-Jun-26 07:00 | 15-Jul-26 17:30 | ATCO | TE | 743s Protection & Control (743s Sarah Lake) | relay testing | 826.5 Hours
Continuous |
|
| 09-Jun-26 07:00 | 15-Jul-26 17:30 | ATCO | TE | 743s Protection & Control (743s Sarah Lake) | isolating 50BF/705 for relay testing | 178.5 Hours
Continuous |
|
| 09-Jun-26 07:00 | 15-Jul-26 17:30 | ATCO | TE | 743s Protection & Control (743s Sarah Lake) | isolating 50BF/605 for relay testing | 178.5 Hours
Continuous |
|
| 15-Jun-26 07:00 | 24-Jul-26 17:00 | EPCOR | Outage | EP 805s J2403 (EP 805s Jasper) | J2403 replacement LCR | 946 Hours
Continuous |
|
| 15-Jun-26 07:00 | 04-Sep-26 17:00 | EPCOR | TE | 805s Protection & Control (805s Jasper) | protection blocking, breaker replacement project | 1,954 Hours
Continuous |
|
| 15-Jun-26 07:00 | 17-Jul-26 17:00 | EPCOR | Outage | 72JM18 (EP 805s Jasper - Meadowlark), M721 (Meadowlark), M722 (Meadowlark), EP 805s J722 (EP 805s Jasper), T1 (Meadowlark), MAB1 (Meadowlark) | Meadowlark: TX1 Zone, LCR Civil Work | 274 Hours
Continuous |
|
| 19-Jun-26 17:00 | 03-Dec-27 17:00 | EPCOR | Outage | EP 511s Victoria T3 (EP 511s Victoria) | emergency outage due to degraded asset condition | 12,769 Hours
Continuous |
|
| 22-Jun-26 12:00 | 10-Jul-26 12:00 | ATCO | TE | 791s RTU/SCADA (791s Rainbow Lake), 791s Protection & Control (791s Rainbow Lake) | 701CT testing for breaker repair | 432 Hours
Continuous |
|
| 23-Jun-26 10:00 | 13-Jul-26 17:00 | ATCO | Outage | 743s 701T (743s Sarah Lake) | 743S Sarah Lake rebuild - replace 501A solid blade switches, replace surge arrestors 507, 508 | 487 Hours
Continuous |
|
| 25-Jun-26 07:00 | 10-Jul-26 17:00 | ALTALINK, EPCOR | Outage | 1044L (EP 805s Jasper - 816s Petrolia), EP 805s J2404 (EP 805s Jasper), EP 805s J2408 (EP 805s Jasper), 805s C1 (805s Jasper), EP 805s J2403 (EP 805s Jasper) | J2403 replacement LCR | 370 Hours
Continuous |
|
| 29-Jun-26 07:00 | 10-Jul-26 17:00 | ALTALINK, EPCOR | TE | 921L (71s Lamoureux - 987s Clover Bar) | protection blocking for MPLS upgrade, cutover and commissioning | 274 Hours
Continuous |
|
| 29-Jun-26 08:00 | 10-Jul-26 16:00 | ALTALINK | IO | 71s Protection & Control (71s Lamoureux) | EPCOR MPLS TPR re-arrangements project | 272 Hours
Continuous |
|
| 29-Jun-26 10:00 | 24-Jul-26 17:30 | ATCO | TE | 763s RTU/SCADA (763s Hanna) | 602T ITM replacement , SCADA updates required as part of ITM replacement project |
439.5 Hours
Continuous |
|
| 02-Jul-26 07:00 | 15-Jul-26 17:00 | EPCOR | Outage | 72LS24 (EP 803s Lambton - Strathcona), S724 (Strathcona), SDS10 (Strathcona) | pole | 322 Hours
Continuous |
|
| 06-Jul-26 06:30 | 15-Jul-26 09:30 | ALTALINK | Outage | 77s 57 (77s Sagitawah) | protection upgrade 77s57 | 219 Hours
Continuous |
|
| 06-Jul-26 06:30 | 15-Jul-26 09:30 | ATCO, ALTALINK | RB | 9L939 (77s Sagitawah - 809s Louise Creek) | Altalink work | 219 Hours
Continuous |
|
| 06-Jul-26 07:00 | 12-Jul-26 17:00 | EPCOR | Outage | 987s T2 (987s Clover Bar), 987s CC721 (987s Clover Bar), 987s C2406 (987s Clover Bar), 987s C2410 (987s Clover Bar) | Cloverbar: TX2 doble and CDS1/CDS31/CDS33/CDS43 disconnect maintenance and measurements | 154 Hours
Continuous |
|
| 06-Jul-26 07:00 | 16-Jul-26 17:00 | ALTALINK | TE | 368s RTU/SCADA (368s Burdett) | 368s RTU configuration update | 250 Hours
Daily |
|
| 06-Jul-26 08:00 | 09-Jul-26 16:00 | ENMAX | Outage | 35.2TR (SS-35) | transformer power factor test, secondary cable test, maintenance, relay fault pressure test, reversing switch check, oil sampling MT, TC | 80 Hours
Continuous |
|
| 06-Jul-26 08:00 | 13-Jul-26 16:00 | ENMAX | Outage | 32.1TR (SS-32) | tap changer inspection | 32 Hours
Continuous |
|
| 06-Jul-26 08:00 | 09-Jul-26 16:00 | ENMAX | Outage | 38.1TR (SS-38) | 38.1TR 8 kV bus breaker alignment | 32 Hours
Continuous |
|
| 06-Jul-26 08:00 | 17-Jul-26 16:00 | ALTALINK | TE | 214s Protection & Control (214s Innisfail), 287s Protection & Control (287s Hazelwood), 55s Protection & Control (55s Olds) | LTO and transfer tripping settings changes for RAS scheme updates due to the implementation of 475s mobile sub at 55s | 272 Hours
Daily |
|
| 06-Jul-26 08:00 | 17-Jul-26 16:00 | ALTALINK | TE | 214s RTU/SCADA (214s Innisfail) | RAS updates due to 55s mobile sub installation | 272 Hours
Daily |
|
| 06-Jul-26 08:00 | 17-Jul-26 16:00 | ALTALINK | TE | 287s RTU/SCADA (287s Hazelwood) | changes to RAS scheme due to addition of 55s mobile sub | 272 Hours
Daily |
|
| 06-Jul-26 09:00 | 09-Jul-26 17:00 | TRANSALTA, ATCO, GREENGATEP | Outage | 1045s Garden Plain, 9L59 (801s Anderson - 9LA59 tap), 9L59 (972s Tinchebray - 9LA59 tap), 1045s T1 (1045s Garden Plain), 801s 902 (801s Anderson), 801s 903 (801s Anderson), 972s 901 (972s Tinchebray), 972s 902 (972s Tinchebray), 1045s 52-L (1045s Garden Plain), 801s 9L59D1 (801s Anderson), 801S 902A (801s Anderson), 801S 903A (801s Anderson), 972s 9L59D2 (972s Tinchebray), 1045s 89-L1 (1045s Garden Plain) | connect new 907B to 900BS1 |
80 Hours
Continuous |
|
| 06-Jul-26 09:00 | 10-Jul-26 17:30 | ATCO | Outage | 2075s 902T (2075s Newell), 2075s ACF21 (2075s Newell), 2075S 930 (2075s Newell) | PRC-005 - SVC Newell valve cooling maintenance, trip coil testing, breaker 2075s 930 VESDA replacement , annual fire system inspection |
104.5 Hours
Continuous |
|
| 06-Jul-26 09:00 | 09-Jul-26 17:00 | ATCO | TE | 801s Protection & Control (801s Anderson), 801s RTU/SCADA (801s Anderson) | adjust relay settings and SPS for final configuration after Gaetz energization and 801s RTU outages | 80 Hours
Continuous |
|
| 06-Jul-26 09:00 | 17-Jul-26 17:00 | BCH | RB | 2L113 (BCH Cranbrook - BCH Natal) | hazard tree removals | 272 Hours
Continuous |
AB-BC |
| 06-Jul-26 09:15 | 09-Jul-26 17:45 | ALTALINK | Outage | 726L (37s North Calder - 71s Lamoureux), 37s 726E (37s North Calder) | transmission line maintenance | 80.5 Hours
Continuous |
|
| 06-Jul-26 09:30 | 09-Jul-26 13:00 | ATCO | Outage | 856s 903T (856s Kinosis) | PRC-005 - transformer maintenance, trip coil testing on 903 and 906 during this switching |
75.5 Hours
Continuous |
|
| 06-Jul-26 10:00 | 17-Jul-26 17:30 | ATCO | Outage | 763s 602T (763s Hanna), 763s 507C (763s Hanna), 763s 604 (763s Hanna) | 500D1 repair - 602T ITM replacement |
271.5 Hours
Continuous |
|
| 06-Jul-26 12:01 | 09-Jul-26 18:00 | ENMAX | Outage | 33.1TR (SS-33) | 33 sub 33.1TR Dev 90 replacement | 77.98 Hours
Continuous |
|
| 06-Jul-26 13:00 | 09-Jul-26 16:00 | ALTALINK | Outage | 385s T3 (385s Spring Coulee), 385s 112 (385s Spring Coulee) | 385sT3 filter install and tap changer investigation | 75 Hours
Continuous |
|
| 06-Jul-26 13:00 | 16-Jul-26 17:00 | ALTALINK | Outage | 761L (38s East Edmonton - 71s Lamoureux), 38s 761N (38s East Edmonton), 71s 552 (71s Lamoureux), 71s 652 (71s Lamoureux), 71s 761W (71s Lamoureux) | 38s761N breaker replacement, replace 71s39, maintenance on 71s761W | 244 Hours
Continuous |
|
| 06-Jul-26 13:00 | 09-Jul-26 14:00 | ATCO | RB | 6L56 (763s Hanna - 802s Michichi Creek) | climbing inspection on 6L56 between Hanna and Michichi | 73 Hours
Continuous |
|
| 06-Jul-26 13:30 | 09-Jul-26 17:00 | ALTALINK | Outage | 104s T1 (104s Watson Creek), 104s 152 (104s Watson Creek) | transformer maintenance, doble and leak repairs | 75.5 Hours
Continuous |
|
| 06-Jul-26 13:30 | 09-Jul-26 17:00 | ALTALINK | Outage | 320p PS2 (320p Keephills), 320p 2652 (320p Keephills), 320p 2752 (320p Keephills) | 320sPS2 PRC5 maintenance and leak repairs | 75.5 Hours
Continuous |
|
| 06-Jul-26 14:00 | 16-Jul-26 17:00 | ALTALINK | TE | 38s Protection & Control (38s East Edmonton) | 38s761N 138 kV breaker replacement, isolations, protection testing
|
243 Hours
Continuous |
|
| 07-Jul-26 07:00 | 09-Jul-26 17:00 | ALTALINK | RB | 76L (33s Spray - 115s Mount Allan) | 76L structure 58,63 - prep/woodpecker inspection
|
58 Hours
Daily |
|
| 07-Jul-26 07:00 | 09-Jul-26 17:00 | ALTALINK | TE | 170s Protection & Control (170s Pike) | DSP module and firewall update | 58 Hours
Continuous |
|
| 07-Jul-26 07:00 | 10-Jul-26 17:00 | ALTALINK | Outage | 896L (19s Wabamun - 432s Carvel), 19s 896 (19s Wabamun), 432s 896 (432s Carvel) | urgent - cross arm and structure repair | 82 Hours
Continuous |
|
| 07-Jul-26 08:00 | 13-Jul-26 16:00 | ATCO | RB | 7L10 (754s Ksituan River - 7LA10 tap), 7L10 (730s Rycroft - 7LA10 tap) | 7L10 TCM pole replacement (live line ) | 152 Hours
Continuous |
|
| 07-Jul-26 08:00 | 13-Jul-26 16:00 | ATCO | RB | 7L03 (749s Flyingshot Lake - 7L09 tap), 7L03 (731s Elmworth - 7L09 tap) | changing red tag poles on 7L03 structures 19, 131 and 132 | 152 Hours
Continuous |
|
| 07-Jul-26 08:00 | 09-Jul-26 16:00 | ALTALINK | TE | 121s Protection & Control (121s Brooks) | standard maintenance | 56 Hours
Daily |
|
| 08-Jul-26 07:00 | 09-Jul-26 19:00 | BPWF | Outage | 611s T2 (611s Amber), 611s 52-240-2 (611s Amber), 611s 52-CAP2 (611s Amber), 611s 52-F5 (611s Amber), 611s 52-F6 (611s Amber), 611s 52-F7 (611s Amber), 611s 52-F8 (611s Amber) | substation maintenance | 36 Hours
Continuous |
|
| 08-Jul-26 08:00 | 09-Jul-26 17:00 | ATCO | RB | 7L24 (700s Bonnyville - 7LA24 tap), 7L24 (846s Grand Centre - 7LA24 tap) | straighten poles - 7L24-280, 7L24-281 | 33 Hours
Continuous |
|
| 08-Jul-26 08:00 | 09-Jul-26 16:00 | ENMAX | TE | Protection & Control (SS-3) | 3 sub BMR 84 protection outage - relay protection test - 3RLY138-3.BMR84 | 32 Hours
Daily |
|
| 08-Jul-26 08:00 | 09-Jul-26 16:00 | ALTALINK | TE | 996s RTU/SCADA (996s Imperial Oil Carson Lake) | satellite comms repairs
|
32 Hours
Continuous |
|
| 08-Jul-26 09:00 | 10-Jul-26 16:30 | ATCO | TE | 845s Protection & Control (845s Big Mountain) | settings update | 55.5 Hours
Continuous |
|
| 08-Jul-26 09:00 | 10-Jul-26 16:30 | ATCO | TE | 749s Flyingshot Lake Protection & Control | settings update | 55.5 Hours
Continuous |
|
| 08-Jul-26 10:00 | 09-Jul-26 16:00 | ATCO | Outage | 825s 902 (825s Whitefish Lake) | breaker maintenance | 30 Hours
Continuous |
|
| 09-Jul-26 06:00 | 15-Jul-26 18:00 | SUNCOR | Outage | 635EDD-1000 635PT-1002 (635EDD-1000), 635EDD-1000 635-752-133 (635EDD-1000), 635EDD-1000 635PS-1041 (635EDD-1000) | maintenance on 144 kV and 72 kV equipment | 156 Hours
Continuous |
|
| 09-Jul-26 07:00 | 09-Jul-26 15:00 | CMH | Outage | MHS-2 MH69-221 (MHS-2 North Industrial) | breaker maintenance | 8 Hours
Continuous |
|
| 09-Jul-26 07:00 | 09-Jul-26 18:00 | ALTALINK | Outage | 1140L (89s Ellerslie - 289s Saunders Lake), 89s 1140 (89s Ellerslie) | replacing insulators on structure 36 | 11 Hours
Continuous |
|
| 09-Jul-26 07:00 | 09-Jul-26 18:00 | ALTALINK | RB | 1112L (89s Ellerslie - 289s Saunders Lake) | close proximity work replacing insulators on 1140L | 11 Hours
Continuous |
|
| 09-Jul-26 07:00 | 16-Jul-26 17:00 | ALTALINK | TE | 77s RTU/SCADA (77s Sagitawah) | RTU database update | 178 Hours
Daily |
|
| 09-Jul-26 07:00 | 09-Jul-26 11:30 | EPCOR | Outage | 987s C1 (987s Clover Bar) | bus differential protection upgrade cutovers | 4.5 Hours
Continuous |
|
| 09-Jul-26 08:00 | 09-Jul-26 17:00 | ALTALINK | TE | 131s RTU/SCADA (131s Moon Lake), 235s RTU/SCADA (235s Entwistle), 283s RTU/SCADA (283s Violet Grove), AltaLink Telecom Equipment | firewall upgrade, MPLS node firmware update. SCADA SUB LAN work | 9 Hours
Continuous |
|
| 09-Jul-26 08:00 | 09-Jul-26 12:00 | ENMAX | Outage | 65B138-D82 (SS-65) | breaker SF6 gas sample - 65B138-D82 | 4 Hours
Continuous |
|
| 09-Jul-26 08:00 | 09-Jul-26 16:00 | ALTALINK | TE | AltaLink Telecom Equipment | urgent repair - 412s MPLS node cycling | 8 Hours
Daily |
|
| 09-Jul-26 09:00 | 09-Jul-26 16:00 | ATCO | TE | ATCO Telecom Equipment | capacity and reliability upgrades | 7 Hours
Continuous |
|
| 09-Jul-26 09:00 | 09-Jul-26 16:00 | ATCO | TE | ATCO Telecom Equipment, 2009s RTU/SCADA (2009s Willow Lake) | MDR link Salt Creek to Willow |
7 Hours
Continuous |
|
| 09-Jul-26 09:00 | 09-Jul-26 13:30 | BCH | TE | BCH Nicola | NIC primary RAS PLC PM | 4.5 Hours
Continuous |
AB-BC |
| 09-Jul-26 10:00 | 09-Jul-26 16:00 | ATCO | TE | ATCO Telecom Equipment | replacing telecom equipment at Saskatoon Mountain | 6 Hours
Continuous |
|
| 09-Jul-26 11:30 | 09-Jul-26 17:00 | EPCOR | Outage | 72CH9 (987s Clover Bar - EP Hardisty), 987s CH722 (987s Clover Bar), H724 (EP Hardisty) | bus differential protection upgrade cutovers | 5.5 Hours
Continuous |
|
| 09-Jul-26 12:00 | 09-Jul-26 16:00 | ENMAX | Outage | 65B138-D83 (SS-65) | breaker SF6 gas sample - 65B138-D83 | 4 Hours
Continuous |
|
| 09-Jul-26 13:01 | 09-Jul-26 15:00 | ATCO | Outage | 856s 901 (856s Kinosis) | PRC-005 trip coil testing | 1.98 Hours
Continuous |
|
| 09-Jul-26 13:31 | 09-Jul-26 17:00 | BCH | TE | BCH Nicola | NIC secondary RAS PLC PM | 3.48 Hours
Continuous |
AB-BC |
| 09-Jul-26 14:00 | 12-Jul-26 15:00 | ATCO | RB | 7L34 (815s Goodfare - 886s Updike) | connect 902S mobile 3 - closing jumper J1 | 1 Hour
Continuous |
|
| 10-Jul-26 07:00 | 10-Jul-26 17:00 | EPCOR | Outage | 987s CC24 (987s Clover Bar) | bus differential protection upgrade cutovers | 10 Hours
Continuous |
|
| 10-Jul-26 07:30 | 10-Jul-26 15:00 | CMH | Outage | CS21 (MHS-2 North Industrial) | PRC-005 maintenance - breaker maintenance on MH69-208 at MHS-2S North Industrial substation and associated relay | 7.5 Hours
Continuous |
|
| 10-Jul-26 08:00 | 10-Jul-26 16:00 | ALTALINK | TE | 286s RTU/SCADA (286s Yasa) | split the existing SCADA VLAN from 1 to 1 and 2 | 8 Hours
Continuous |
|
| 10-Jul-26 08:00 | 18-Nov-26 16:00 | Syncrude | Outage | 815 (Syncrude Mildred Lake), 816 (Syncrude Mildred Lake) | replace 72 kV underground feeder cables on west mine feeder | 2,696 Hours
Continuous |
|
| 10-Jul-26 09:00 | 13-Jul-26 20:00 | SUNCOR | TE | 29PL9-17 (29EDD-1 Millennium - 29EDD-94 Voyageur) | 29EDD1 - 29PT419/29PL9-17 system protection isolation only | 83 Hours
Continuous |
|
| 10-Jul-26 09:00 | 12-Jul-26 17:00 | BCH | RB | 5L92 (BCH Cranbrook - BCH Selkirk) | 5L92 LLP/ANR - logging beside power lines 134-01 to 136-01 | 56 Hours
Continuous |
AB-BC |
| 11-Jul-26 07:00 | 11-Jul-26 12:00 | ALTALINK | TE | 77s Protection & Control (77s Sagitawah) | trip test 77s57 | 5 Hours
Daily |
|
| 11-Jul-26 07:00 | 11-Jul-26 11:30 | EPCOR | Outage | 987s CK725 (987s Clover Bar), 72CK12 (987s Clover Bar - Kennedale), K724 (Kennedale) | BUS diff upgrade cutovers | 4.5 Hours
Continuous |
|
| 11-Jul-26 07:15 | 11-Jul-26 16:45 | ALTALINK | Outage | 235s 744W (235s Entwistle), 744L (235s Entwistle - 744AL tap) | transmission line maintenance | 9.5 Hours
Continuous |
|
| 11-Jul-26 12:00 | 11-Jul-26 17:00 | ALTALINK | TE | 77s Protection & Control (77s Sagitawah) | trip test 77s57 | 5 Hours
Continuous |
|
| 11-Jul-26 12:00 | 11-Jul-26 17:00 | EPCOR | Outage | 987s CK726 (987s Clover Bar), 72CK13 (987s Clover Bar - Kennedale), K721 (Kennedale) | BUS diff upgrade cutovers | 5 Hours
Continuous |
|
| 12-Jul-26 06:30 | 12-Jul-26 12:29 | ALTALINK | Outage | 77s 652 (77s Sagitawah) | trip test 77s652 | 5.98 Hours
Continuous |
|
| 12-Jul-26 07:00 | 12-Jul-26 11:30 | EPCOR | Outage | 987s GT2 (987s Clover Bar), 987s CGB2 (987s Clover Bar) | Cloverbar: GT2/CGB2, bus diff upgrade cutovers | 4.5 Hours
Continuous |
|
| 12-Jul-26 08:00 | 12-Jul-26 16:00 | ALTALINK | TE | 77s Protection & Control (77s Sagitawah) | trip test 77s57 | 8 Hours
Daily |
|
| 12-Jul-26 12:00 | 12-Jul-26 17:00 | EPCOR | Outage | 72CN10 (987s Clover Bar - Namao), 987s CN723 (987s Clover Bar) | Cloverbar: CN723, BUS Diff Upgrade Cutovers | 5 Hours
Continuous |
|
| 12-Jul-26 12:30 | 12-Jul-26 18:00 | ALTALINK | Outage | 77s 752 (77s Sagitawah) | trip test 77s752 | 5.5 Hours
Continuous |
|
| 13-Jul-26 06:30 | 13-Jul-26 12:29 | ALTALINK | Outage | 77s 29 (77s Sagitawah) | trip test 77s29 | 5.98 Hours
Continuous |
|
| 13-Jul-26 07:00 | 19-Jul-26 17:00 | EPCOR | Outage | 72CH11 (987s Clover Bar - EP Hardisty), T1 (EP Hardisty), H722 (EP Hardisty), H725 (EP Hardisty), 987s CH724 (987s Clover Bar), S724 (Strathcona), H723 (EP Hardisty) | t1 maintenance and bus diff | 154 Hours
Continuous |
|
| 13-Jul-26 07:00 | 19-Jul-26 17:00 | EPCOR | Outage | EP 803s L2401 (EP 803s Lambton) | breaker maintenance | 154 Hours
Continuous |
|
| 13-Jul-26 07:00 | 17-Jul-26 17:00 | ALTALINK | TE | AltaLink Telecom Equipment | 2012F fiber relocation for road move | 106 Hours
Continuous |
|
| 13-Jul-26 07:00 | 17-Jul-26 17:00 | ALTALINK, EPCOR | TE | 909L (310p Sundance - 665s Dome) | Altalink is relocating 2012F fiber for road move | 106 Hours
Continuous |
|
| 13-Jul-26 07:00 | 17-Jul-26 17:00 | ALTALINK, EPCOR | TE | 1139L (367s Harry Smith - EP Riverview) | Altalink is relocating 2012F fiber for road move | 106 Hours
Continuous |
|
| 13-Jul-26 07:00 | 17-Jul-26 17:00 | ALTALINK, EPCOR | TE | 1209L (89s Ellerslie - 330p Genesee) | Altalink is relocating 2012F fiber for road move | 106 Hours
Continuous |
|
| 13-Jul-26 07:00 | 17-Jul-26 17:00 | ALTALINK, EPCOR | TE | 1045L (EP 805s Jasper - 1045AL tap) | Altalink is relocating 2012F fiber for road move | 106 Hours
Continuous |
|
| 13-Jul-26 07:00 | 24-Jul-26 17:00 | ALTALINK, EPCOR | TE | 909L (310p Sundance - 665s Dome) | protection blocking for MPLS cutovers and commissioning | 274 Hours
Continuous |
|
| 13-Jul-26 07:00 | 24-Jul-26 17:00 | ALTALINK, EPCOR | TE | 909L (89s Ellerslie - 665s Dome) | protection blocking for MPLS cutovers and commissionin | 274 Hours
Continuous |
|
| 13-Jul-26 07:00 | 13-Jul-26 12:00 | ALTALINK | TE | 77s Protection & Control (77s Sagitawah) | trip test 77s29 (breaker fail), no redundancy | 5 Hours
Daily |
|
| 13-Jul-26 07:30 | 16-Jul-26 16:30 | ALTALINK, DOW | RB | 787AL (906s Ross Creek - 787L tap), 787L (166s Dow Chemical Fort Saskatchewan - 787AL tap), 787L (71s Lamoureux - 787AL tap) | safety requirement - crew working in vicinity | 81 Hours
Continuous |
|
| 13-Jul-26 07:30 | 17-Jul-26 15:00 | CMH | Outage | CS21 (MHS-2 North Industrial), MHS-2 MH69-208 (MHS-2 North Industrial) | Maintenance on MH69-208. Maintenance on CS-21 including replacement of leaking caps and electrical testing |
103.5 Hours
Continuous |
|
| 13-Jul-26 08:00 | 14-Jul-26 16:30 | ALTALINK, ENEL | Outage | 205s T2 (205s Castle Rock Ridge), 205s 52M2 (205s Castle Rock Ridge), 205s 89T2 (205s Castle Rock Ridge), 205s 89M2 (205s Castle Rock Ridge) | maintenance | 32.5 Hours
Continuous |
|
| 13-Jul-26 08:00 | 14-Jul-26 16:00 | ENMAX | Outage | 24B138-24.81 (SS-24), 31B138-24.81 (SS-31) | breaker maintenance | 32 Hours
Continuous |
|
| 13-Jul-26 08:00 | 14-Jul-26 16:00 | ALTALINK | TE | 157s RTU/SCADA (157s Lac La Biche) | Scada Outage to fix time stamp deficiency. RTU database updates. Daily ~15min 157s supervisory outages required. | 32 Hours
Daily |
|
| 13-Jul-26 08:00 | 24-Jul-26 16:00 | ALTALINK | TE | 310p Protection & Control (310p Sundance) | EPCOR MPLS TPR Re-Arrangements Project:
909LW (310P Sundance Plant -E665s Dome): Relay testing and cutover: Protection Blocking Supporting EPCOR MPLS Upgrade, TPR Cutover and Commissioning. EPCOR Ref. #: OE114340 Redundant Protection will remain in service at all times |
272 Hours
Continuous |
|
| 13-Jul-26 08:00 | 24-Jul-26 16:00 | ALTALINK | TE | 89s Protection & Control (89s Ellerslie) | EPCOR MPLS TPR Re-Arrangements Project:
909LE (89s Ellerslie-E665s Dome): Relay testing and cutover: Protection Blocking Supporting EPCOR MPLS Upgrade, TPR Cutover and Commissioning. EPCOR Ref. #: OE114339 Redundant Protection will remain in service at all times |
272 Hours
Continuous |
|
| 13-Jul-26 08:00 | 16-Jul-26 16:00 | ENMAX | Outage | 13.3TR (SS-13) | transformer testing | 80 Hours
Continuous |
|
| 13-Jul-26 08:00 | 15-Jul-26 16:00 | ENMAX | Outage | 31.3TR (SS-31) | relay protection test | 56 Hours
Continuous |
|
| 13-Jul-26 08:00 | 14-Jul-26 16:00 | ENMAX | Outage | 39.2TR (SS-39) | CT testing | 32 Hours
Continuous |
|
| 13-Jul-26 08:00 | 16-Jul-26 16:00 | ENMAX | Outage | 3.82L (SS-3 - SS-8), 3.3TR (SS-3), 3B138-3.82 (SS-3), SW83 (SS-3), 3MD138-3.3TR (SS-3) | tap changer inspection | 80 Hours
Continuous |
|
| 13-Jul-26 09:00 | 24-Jul-26 17:30 | ATCO | Outage | 2075s 901T (2075s Newell), 2075s 917 (2075s Newell), 2075s 918 (2075s Newell), 2075s ACF11 (2075s Newell), 2075s ACF12 (2075s Newell), 2075s ACF13 (2075s Newell), 2075s ACF14 (2075s Newell), 2075s ACF1D1 (2075s Newell) | SVC Newell maintenance | 272.5 Hours
Continuous |
|
| 13-Jul-26 09:00 | 14-Jul-26 18:00 | ALTALINK | Outage | 76L (33s Spray - 115s Mount Allan) | tower repair work and insulation change on 33s A frame | 33 Hours
Continuous |
|
| 13-Jul-26 10:00 | 13-Jul-26 13:00 | SUNCOR | Outage | 29EDD-1 952-104 (29EDD-1 Millennium) | prc testing |
156 Hours
Continuous |
|
| 13-Jul-26 10:00 | 14-Jul-26 16:00 | ATCO | Outage | 825s 903 (825s Whitefish Lake) | breaker maintenance | 30 Hours
Continuous |
|
| 13-Jul-26 10:00 | 16-Jul-26 16:00 | ATCO | Outage | 918s 702T (918s Bauer), 918s RTU/SCADA (918s Bauer) | transformer and breaker maintenance. RTU config may need to be pushed as well complete visibility will be lost for SOC for a duration of 10-20 min. | 78 Hours
Continuous |
|
| 13-Jul-26 10:00 | 14-Jul-26 16:00 | ATCO | Outage | 856s 902 (856s Kinosis) | PRC-005 test and breaker maintenance | 30 Hours
Continuous |
|
| 13-Jul-26 10:00 | 17-Jul-26 17:30 | ALTALINK | RB | 472AL (221s Sunken Lake - 472L tap), 472L (213s Hughenden - 472AL tap), 472L (648s Metiskow - 472AL tap) | 472L 204, 208, 241, 245, 343, 358, 367, replace arms and glass, replace structure 241 | 103.5 Hours
Continuous |
|
| 13-Jul-26 10:00 | 16-Jul-26 16:00 | ATCO | TE | 918s RTU/SCADA (918s Bauer) | In conjunction with 1-00519538. 918s RTU outage 10-20 min to push new config file. | 78 Hours
Continuous |
|
| 13-Jul-26 12:00 | 17-Jul-26 16:00 | ATCO | Outage | 6L12 (774s Monitor - 6L25 tap) | Outage required on 6L12A between 6L25 Tap and 6L12D4 (veteran) for road rebuild structure replacements. Structure replace 6L12A:441, 443, 446, 447, 452, 453, 454, 455, 456, 457, 459, 466, 468, 470, 472, 473, 476, 477, 478, 481, 486, 487, 488, 489 |
100 Hours
Continuous |
|
| 13-Jul-26 12:00 | 20-Jul-26 10:00 | ATCO | Outage | 886s 701T (886s Updike) | transformer and breaker testing, mobile sub will be carrying all the load | 166 Hours
Continuous |
|
| 13-Jul-26 12:00 | 14-Jul-26 16:00 | ALTALINK | TE | 723s RTU/SCADA (723s Christina Lake) | HMI replacement, daily ~15min supervisory outages required | 28 Hours
Daily |
|
| 13-Jul-26 12:30 | 13-Jul-26 18:00 | ALTALINK | Outage | 77s 40 (77s Sagitawah) | trip test 77s40 | 5.5 Hours
Continuous |
|
| 13-Jul-26 12:30 | 13-Jul-26 18:00 | ATCO, ALTALINK | RB | 9L938 (77s Sagitawah - 809s Louise Creek) | reclosing blocked for AltaLink | 5.5 Hours
Continuous |
|
| 13-Jul-26 13:00 | 16-Jul-26 15:00 | ATCO | RB | 7L85 (801s Anderson - ATC 803s Bullpound), 7L85 (803s ATC Bullpound - 7LA85 tap), 7L85 (804s Wintering Hills - 7LA85 tap) | installing interphase spacers on 7L85 - live line work | 74 Hours
Continuous |
|
| 13-Jul-26 13:01 | 13-Jul-26 16:00 | SUNCOR | Outage | 29EDD-1 952-105 (29EDD-1 Millennium) | prc testing | 2.98 Hours
Continuous |
|
| 14-Jul-26 07:00 | 14-Jul-26 13:00 | ALTALINK | Outage | 562s 1452 (562s Cypress), 562s 1652 (562s Cypress), 658L (562s Cypress - 658AL tap), 658L (649s Chappice Lake - 658AL tap) | replacing insulator on structure 306 | 6 Hours
Continuous |
|
| 14-Jul-26 07:00 | 14-Jul-26 17:00 | ALTALINK | TE | 77s 37 (77s Sagitawah) | test the functionality of clearing the 240kV East Bus | 10 Hours
Continuous |
|
| 14-Jul-26 07:00 | 14-Jul-26 08:30 | ALTALINK | TE | 77s Protection & Control (77s Sagitawah) | trip test 77s57 | 1.5 Hours
Continuous |
|
| 14-Jul-26 07:00 | 14-Jul-26 17:00 | ALTALINK | Outage | 723L (69s North Barrhead - 724L tap), 723L (438s Westlock - 724L tap), 724L (500s Flatbush - 724L tap), 724L (723L tap - 724AL tap) | Repair damaged cross-arms on structures 724L 47 & 64. 723L to come offline during switching to switch 724L0B. | 10 Hours
Continuous |
|
| 14-Jul-26 07:00 | 14-Jul-26 11:30 | EPCOR | Outage | 987s CCP7214 (987s Clover Bar) | Cloverbar: CCP7214, BUS Diff Upgrade Cutovers | 4.5 Hours
Continuous |
|
| 14-Jul-26 07:00 | 14-Jul-26 19:00 | ALTALINK, PR | Outage | 275s 949 (275s Jenner), 949L (275s Jenner - 306s Halsbury), 306s 240MDS4 (306s Halsbury), 306s 240CB1 (306s Halsbury) | customer work on 949L | 12 Hours
Continuous |
|
| 14-Jul-26 08:00 | 14-Jul-26 11:00 | ATCO | Outage | 7L172 (739s Edith Lake - 743s Sarah Lake), 739s 702 (739s Edith Lake), 743s 704 (743s Sarah Lake) | PRC-005 - TRIP COIL TESTING - BREAKER 704 @ 743S PRC-005 - TRIP COIL TESTING - BREAKER 702 @ 739S |
3 Hours
Continuous |
|
| 14-Jul-26 08:00 | 14-Jul-26 16:00 | ALTALINK | TE | 104s RTU/SCADA (104s Watson Creek) | split the existing SCADA VLAN from 1 to 1 and 2 | 8 Hours
Continuous |
|
| 14-Jul-26 08:00 | 01-Oct-26 17:00 | ALTALINK | IO | 287s 552 (287s Hazelwood) | 287s552 must be open during 443L and 417L outage for the 214s AIS to work properly | 1,905 Hours
Continuous |
|
| 14-Jul-26 08:00 | 14-Jul-26 12:00 | ALTALINK | TE | 394s Protection & Control (394s Empress) | protection outage A77/1134_AIS and B77/1134_AIS, required for 658L outage | 4 Hours
Continuous |
|
| 14-Jul-26 08:00 | 14-Jul-26 16:00 | ALTALINK | TE | AML 793s Protection & Control (AML 793s Horse Creek) | techs to complete standard maintenance T1 relays | 8 Hours
Continuous |
|
| 14-Jul-26 08:00 | 15-Jul-26 17:00 | ALTALINK | TE | AltaLink Telecom Equipment | 67s Stirling-225s Magrath MW upgrades | 33 Hours
Continuous |
|
| 14-Jul-26 08:31 | 14-Jul-26 10:00 | ALTALINK | TE | 77s Protection & Control (77s Sagitawah) | trip test 77s57 | 1.48 Hours
Continuous |
|
| 14-Jul-26 09:00 | 14-Jul-26 16:00 | ATCO | TE | ATCO Telecom Equipment | Weberville_T-Telecom/Wesley Creek_S-Telecom - IRU radio majors | 7 Hours
Continuous |
|
| 14-Jul-26 09:00 | 15-Jul-26 14:00 | ALTALINK | Outage | 214s 443 (214s Innisfail), 55s 443 (55S Olds), 443L (55s Olds - 214s Innisfail), 287s 552 (287s Hazelwood) | create open point 'D', connect 475s mobile | 29 Hours
Continuous |
|
| 14-Jul-26 09:00 | 14-Jul-26 16:00 | ATCO | TE | ATCO Telecom Equipment | Clairmont Lake_S_Telecom/Crystal Lake_S-Telecom- IUR radio major PM | 7 Hours
Continuous |
|
| 14-Jul-26 09:00 | 15-Jul-26 14:00 | ALTALINK | Outage | 55s T2 (55s Olds) | Connect 475s mobile | 29 Hours
Continuous |
|
| 14-Jul-26 09:30 | 23-Jul-26 11:00 | ALTALINK | Outage | 163s T5 (163s Amoco Empress) | 163sT5 maintenance and oil leaks | 217.5 Hours
Continuous |
|
| 14-Jul-26 10:00 | 14-Jul-26 12:00 | ATCO | TE | ATCO Telecom Equipment | strategic fiber project |
2 Hours
Continuous |
|
| 14-Jul-26 10:01 | 14-Jul-26 11:30 | ALTALINK | TE | 77s Protection & Control (77s Sagitawah) | trip test 77s57 | 1.48 Hours
Continuous |
|
| 14-Jul-26 11:01 | 14-Jul-26 15:00 | ATCO | Outage | 739s 701 (739s Edith Lake), 7L43 (739s Edith Lake - 809s Louise Creek) | PRC-005 - TRIP COIL TESTING - BREAKER 701 @ 739S Breaker operation only. open-close-open-close. |
3.98 Hours
Continuous |
|
| 14-Jul-26 11:31 | 14-Jul-26 13:00 | ALTALINK | TE | 77s Protection & Control (77s Sagitawah) | trip test 77s57 | 1.48 Hours
Continuous |
|
| 14-Jul-26 12:00 | 14-Jul-26 17:00 | EPCOR | Outage | 987s CS2 (987s Clover Bar) | Cloverbar: SST2/CS2, BUS Diff Upgrade Cutovers | 5 Hours
Continuous |
|
| 14-Jul-26 13:00 | 17-Jul-26 13:00 | ATCO | Outage | 783s 701T (783s Cadotte River), 783s 701TD (783s Cadotte River) | 783S 144kV fuse replacement , 783s 701T transformer class 2 major testing |
72 Hours
Continuous |
|
| 14-Jul-26 13:01 | 14-Jul-26 14:30 | ALTALINK | TE | 77s Protection & Control (77s Sagitawah) | trip test 77s57 | 1.48 Hours
Continuous |
|
| 14-Jul-26 14:31 | 14-Jul-26 16:00 | ALTALINK | TE | 77s Protection & Control (77s Sagitawah) | trip test 77s57 | 1.48 Hours
Continuous |
|
| 15-Jul-26 07:00 | 16-Jul-26 17:00 | ALTALINK, TRANSALTA | RB | 179s 733 (179s Gleichen), 428s 733X (428s Namaka), 733L (179s Gleichen - 428s Namaka) | 733L str. 161-211 prep. Live line work. | 34 Hours
Daily |
|
| 15-Jul-26 07:00 | 16-Jul-26 17:00 | ALTALINK | RB | 151s 733E (151s Strathmore), 428s 733N (428s Namaka), 733L (151s Strathmore - 428S Namaka) | 733L 131 Top Phase Keeper Key. Live Line. | 34 Hours
Daily |
|
| 15-Jul-26 07:00 | 15-Jul-26 11:30 | EPCOR | Outage | 987s GT1 (987s Clover Bar), 987s CGB1 (987s Clover Bar) | Cloverbar: GT1/CGB1, bus diff upgrade cutovers | 4.5 Hours
Continuous |
|
| 15-Jul-26 07:00 | 15-Jul-26 17:00 | ENMAX, ALTALINK | IO | 1064L (74s Janet - 102s Langdon) | ENMAX - Shield Wire replacement | 10 Hours
Continuous |
|
| 15-Jul-26 07:00 | 15-Jul-26 17:00 | ENMAX, ALTALINK | IO | 1065L (74s Janet - 102s Langdon) | ENMAX Shield Wire replacement | 10 Hours
Continuous |
|
| 15-Jul-26 07:30 | 16-Jul-26 16:00 | ALTALINK, ENEL | Outage | 205s T1 (205s Castle Rock Ridge), 205s 89T1 (205s Castle Rock Ridge) | two day outage required for 205s planned maintenance | 32.5 Hours
Continuous |
|
| 15-Jul-26 08:00 | 19-Jul-26 12:59 | SUNCOR | Outage | 29EDD-1 29EDD1s452 (29EDD-1 Millennium) | 29EDD1; 29EDD1;29EDD1S452 MAINT&TEST;PM 10Y - For PRC-005 Breakers 29EDD1S452 will be trip tested | 156 Hours
Continuous |
|
| 15-Jul-26 08:00 | 15-Jul-26 16:00 | ENMAX, ALTALINK | Outage | 1064L (74s Janet - 102s Langdon) | Shield Wire Replacement. | 8 Hours
Continuous |
|
| 15-Jul-26 08:00 | 15-Jul-26 16:00 | ENMAX, ALTALINK | Outage | 1065L (74s Janet - 102s Langdon) | Shield Wire Replacement. | 8 Hours
Continuous |
|
| 15-Jul-26 08:00 | 15-Jul-26 17:00 | ALTALINK | TE | 39s RTU/SCADA (39s Bickerdike), AltaLink Telecom Equipment | firmware upgrade an A&B Nodes. firewall upgrade. SCADA Upgrade | 9 Hours
Continuous |
|
| 15-Jul-26 08:00 | 16-Jul-26 16:00 | ENMAX | Outage | 21.61L (SS-21 - SS-34), 34B69-21.61 (SS-34) | HV Breaker Maintenance | 32 Hours
Continuous |
|
| 15-Jul-26 08:00 | 15-Jul-26 16:00 | ALTALINK | Outage | 20s 113 (20s Ghost), 33s 113 (33s Spray), 113L (20s Ghost - 33s Spray) | 113L Replacing insulator on structure 77 | 8 Hours
Continuous |
|
| 15-Jul-26 08:00 | 15-Jul-26 16:00 | ALTALINK, CapitalPower | TE | 1018s Protection & Control (1018s Shamrock) | temporary isolated the listed protections for customer request, 1148L A87/21/L1 SEL411L - FT 99-3,1148L B87/21/L1 URL90 - FT 99-5 | 8 Hours
Continuous |
|
| 15-Jul-26 08:00 | 16-Jul-26 16:00 | ENMAX | Outage | 40.1TR (SS-40) | secondary cabinet measurements and CT testing | 32 Hours
Continuous |
|
| 15-Jul-26 08:30 | 15-Jul-26 17:30 | ATCO, ALTALINK | RB | 9L939 (77s Sagitawah - 809s Louise Creek) | Reclosing blocked for AltaLink | 9 Hours
Continuous |
|
| 15-Jul-26 08:30 | 15-Jul-26 16:30 | ALTALINK | Outage | 77s 54 (77s Sagitawah) | trip test 77s54 | 8 Hours
Continuous |
|
| 15-Jul-26 09:00 | 15-Jul-26 16:00 | ATCO, ALTALINK | TE | ATCO Telecom Equipment, 9L960 (13s Deerland - 825s Whitefish Lake), 9L961 (13s Deerland - 825s Whitefish Lake), 825s Whitefish Lake | capacity & reliability upgrades. changing radio through put on link Whitefish to Harry Hill, link will be down for the duration of the outage , impacts TPRCP146 / 9L960A TPRCP147 / 9L961A |
7 Hours
Continuous |
|
| 15-Jul-26 09:00 | 15-Jul-26 16:00 | ATCO | TE | ATCO Telecom Equipment, 7L228 (845s Big Mountain - 7L20 tap) | debolt_t-telecom- IRU radio major pm impact to the following traffic during radio outage: TPRNN007 / 7L228 A - and TPRNN012 / 7L228 B - Thornton/ Big mountain |
7 Hours
Continuous |
|
| 15-Jul-26 09:00 | 19-Jul-26 17:00 | ATCO, SUNCOR | TE | 29PL9-1 (29EDD-1 Millennium - 848s Ruth Lake) | 29EDD1;29CVT-3 SYSTEM;PM 5y,10y Protection only - 450338053 | 104 Hours
Continuous |
|
| 15-Jul-26 09:00 | 15-Jul-26 17:00 | ALTALINK | TE | 77s Protection & Control (77s Sagitawah) | trip test 77s57. Breaker fail protection, no redundancy | 8 Hours
Continuous |
|
| 15-Jul-26 09:00 | 15-Jul-26 17:00 | ALTALINK | Outage | 198s T2 (198s Blackfalds) | replace failed qualitrol 930 boards | 8 Hours
Daily |
|
| 15-Jul-26 10:00 | 16-Jul-26 16:00 | ATCO | Outage | 825s 904 (825s Whitefish Lake) | BREAKER MAINTENANCE | 30 Hours
Continuous |
|
| 15-Jul-26 10:00 | 16-Jul-26 16:00 | ATCO | Outage | 856s 904 (856s Kinosis) | trip coil testing, breaker maintenance | 30 Hours
Continuous |
|
| 15-Jul-26 11:00 | 27-Jul-26 16:00 | ATCO | Outage | 743s 601 (743s Sarah Lake) | 743S Sarah lake rebuild. Replace breaker 601 | 317 Hours
Continuous |
|
| 15-Jul-26 14:00 | 05-Oct-26 09:00 | ALTALINK | Outage | 55s 417 (55S Olds), 55s T1 (55s Olds), 55s T2 (55s Olds), 417L (55s Olds - 281s Johnson), 287s 552 (287s Hazelwood) | Mobile install at 55s for P_C major upgrade. Repair/replace s80, s83, s84. Salvage s51. | 1,963 Hours
Continuous |
|
| 16-Jul-26 07:00 | 16-Jul-26 17:00 | ALTALINK | RB | 600L (404s Peace Butte - 523s Bullshead) | 600L str 30, 102, 131, re-install keeper key top right phase - live line work | 9 Hours
Continuous |
|
| 16-Jul-26 07:00 | 21-Jul-26 17:00 | SUNCOR | Outage | 635EDD-1000 635PK-1000 (635EDD-1000), 635EDD-1000 635-752-132 (635EDD-1000), 635EDD-1000 635-752-131 (635EDD-1000), 635EDD-1000 635PS-1017 (635EDD-1000), 635EDD-1000 635PS-1018 (635EDD-1000), 635EDD-1000 635PS-1040 (635EDD-1000), 635EDD-1000 635PS-1016 (635EDD-1000) | 6 year planned maintenance on 144kV equipment | 130 Hours
Continuous |
|
| 16-Jul-26 08:00 | 16-Jul-26 16:00 | ENMAX | TE | Protection & Control (SS-23) | 23sub zone 31 138kV bus differential, 86-Z31 lockout relay protection outage | 8 Hours
Continuous |
|
| 16-Jul-26 08:30 | 16-Jul-26 16:00 | ALTALINK | Outage | 256s C1 (256s Harmattan) | PRC maintenance on the cap bank protection | 7.5 Hours
Continuous |
|
| 16-Jul-26 08:30 | 16-Jul-26 16:00 | ALTALINK | TE | 256s Protection & Control (256s Harmattan) | PRC maintenance | 7.5 Hours
Continuous |
|
| 16-Jul-26 09:00 | 16-Jul-26 16:00 | ATCO | TE | ATCO Telecom Equipment, 2091s RTU/SCADA (2091s Thornton) | Smoky River_T-Telecom-MDR Radio | 7 Hours
Continuous |
|
| 16-Jul-26 09:30 | 16-Jul-26 12:30 | ALTALINK | Outage | 38s C1 (38s East Edmonton), 38s C2 (38s East Edmonton) | cap bank weed spraying | 3 Hours
Continuous |
|
| 16-Jul-26 10:00 | 16-Jul-26 14:00 | ALTALINK | TE | 178s RTU/SCADA (178s Cynthia), 359s RTU/SCADA (359s Esso West Pembina), AltaLink Telecom Equipment | Firewall upgrade with a switch changeout. MPLS Node Firmware upgrade as well, SCADA VLAN Config.
|
4 Hours
Daily |
|
| 16-Jul-26 15:00 | 16-Jul-26 17:00 | ALTALINK | IO | 157s 852 (157s Lac La Biche) | Multiple breaker operations required to sync POW controller | 2 Hours
Continuous |
|
| 17-Jul-26 06:00 | 18-Jul-26 18:00 | ALTALINK | Outage | 42s 3W (42s Sarcee), 3L (42s Sarcee - 272s Springbank) | Replacing cross arms and insulators on structures 373, 387, & 390
|
36 Hours
Continuous |
|
| 17-Jul-26 08:00 | 17-Jul-26 16:00 | ALTALINK | TE | 86s RTU/SCADA (86s Bigstone) | split the existing SCADA VLAN from 1 to 1 and 2
|
8 Hours
Continuous |
|
| 17-Jul-26 08:00 | 17-Jul-26 18:00 | ENMAX | Outage | 14.1C (SS-14), 14.2C (SS-14), 14.83L (SS-14 - SS-36), 14.4TR (SS-14), 14.2TR (SS-14), SW84 (SS-14), 14B138-14.83 (SS-14), 14MD138-14.4TR (SS-14), 14MD138-14.2TR (SS-14), 36B138-14.83 (SS-36) | power factor test, reversing switch check and oil sampling | 10 Hours
Continuous |
|
| 17-Jul-26 10:00 | 20-Jul-26 14:00 | ATCO | RB | 6L56 (763s Hanna - 802s Michichi Creek) | climbing inspection on 6L56 between Hanna and Michichi | 76 Hours
Continuous |
|
| 17-Jul-26 10:00 | 17-Jul-26 14:00 | ALTALINK | Outage | 252s T2 (252s Jarrow) | install T2 transformer grounding | 4 Hours
Continuous |
|
| 17-Jul-26 11:00 | 25-Jul-26 15:30 | ALTALINK | Outage | 526s 652 (526s Buffalo Creek), 526s C1 (526s Buffalo Creek) | replace 526s652 breaker | 196.5 Hours
Continuous |
| This document and the information contained herein are based upon information and data which by their nature contain a degree of uncertainty and are subject to change. In addition, this document may contain information and data from public sources and/or third parties, which have been assumed to be accurate and complete and have not been verified. Accordingly, the Independent System Operator, operating as the Alberta Electric System Operator (the "AESO") makes no warranty, representation or guarantee, express or implied, with respect to this document or the information contained herein, including, but not limited to, any warranty, representation or guarantee of accuracy, completeness, timeliness, reliability, availability, absence of computer virus, non- infringement, merchantability or suitability for any purpose. Under no circumstances will the AESO, its members, officers, employees, contractors or agents, or any of their respective affiliates, be liable for any errors or omissions in, or any losses, damages or claims whatsoever, whether in contract, tort or otherwise, arising from use of or reliance upon, this document or any information contained herein. © 2009 Alberta Electric System Operator. All rights reserved |