| Alberta Electric System Operator | |
| System Co-ordination Plan | |
| 2026-01-29 to 2026-02-06 | |
| Approved Outages |
| Previous Version | |
| Download CSV |
| From | To | Owner | Type | Element | Scheduled Activity | Date/Time Comments | Interconnection |
|---|---|---|---|---|---|---|---|
| 26-Jul-24 10:00 | 31-Jul-26 16:00 | ATCO | Outage | 826s 504R (826s Marguerite Lake) | emergency removal to replace failed 502R @834S | 735.25 Days
Continuous |
|
| 23-Aug-24 13:45 | 30-Jun-26 14:29 | ALTALINK | Outage | 157s C1 (157s Lac La Biche) | forced outage | 676.03 Days
Continuous |
|
| 18-Mar-25 14:00 | 17-Mar-26 17:30 | ALTALINK | Outage | 217s C1 (217s North Red Deer) | cap. bank unavailable and cannot be energized due to Koncar CTs being present | 364.15 Days
Daily |
|
| 20-Mar-25 08:00 | 20-Mar-26 17:00 | ALTALINK | Outage | 256s C1 (256s Harmattan) | forced outage | 365.38 Days
Continuous |
|
| 31-Mar-25 07:00 | 27-Feb-26 17:00 | EPCOR | TE | Protection & Control (Woodcroft) | Woodcroft: protection blocking for merging unit and protection upgrade. | 333.46 Days
Continuous |
|
| 14-May-25 08:00 | 13-Mar-26 16:00 | ENMAX | TE | Protection & Control (SS-32) | 32sub 138kV autoswitching protection outage | 303.33 Days
Continuous |
|
| 22-Jul-25 08:30 | 31-Mar-26 16:30 | ALTALINK | Outage | 263s C1 (263s Strachan) | forced outage | 252.33 Days
Continuous |
|
| 25-Jul-25 17:01 | 17-Apr-26 17:00 | EPCOR | Outage | T2 (EP Riverview) | bushing test failure (found during OE110184) | 266 Days
Continuous |
|
| 25-Aug-25 08:00 | 03-Apr-26 16:00 | ENMAX | Outage | 32.1TR (SS-32) | slip over CT and new power cables installation and P&C works | 221.33 Days
Continuous |
|
| 12-Sep-25 08:00 | 06-Mar-26 16:00 | ENMAX | Outage | 33.1TR (SS-33) | tap changer refurbishments. soak test required | 175.38 Days
Continuous |
|
| 01-Nov-25 12:00 | 01-Feb-26 18:00 | ALTALINK | Outage | AML 511s ACF12 (AML 511s Crossings) | forced outage | 92.29 Days
Continuous |
|
| 25-Nov-25 17:46 | 30-Jan-26 18:00 | ATCO | Outage | 876s 901T (876s Brintnell) | forced outage oil leaking | 66.01 Days
Continuous |
|
| 27-Nov-25 08:30 | 27-Nov-27 16:30 | ALTALINK | TE | 89s Protection & Control (89s Ellerslie) | DSP card replacements on1057L B87/L3 and B240B1 B87/240B1 | 730.33 Days
Daily |
|
| 09-Dec-25 17:00 | 02-Feb-26 11:00 | ALTALINK | IO | 714L (397s Benbow – 1117s South Kaybob), 397s 714 (397s Benbow) | complete work on breaker and energize 397s 714 | 54.75 Days
Continuous |
|
| 04-Jan-26 08:00 | 31-Mar-26 16:00 | SUNCOR | Outage | 29EDD-34 260kV Bus 29PP-45 (29EDD-34), 29EDD-34 29-952-113 (29EDD-34) | urgent repairs on 29PT-224 at 29EDD34 on 29PP-45 bus | 86.29 Days
Continuous |
|
| 05-Jan-26 08:00 | 08-Mar-26 16:00 | ENMAX | Outage | 1.80L (SS-1 - SS-28) | 1 sub transmission line cut over | 62.29 Days
Continuous |
|
| 05-Jan-26 08:00 | 08-Mar-26 16:00 | ENMAX | Outage | 1.81L (SS-1 - SS-20) | 1 sub transmission line cut over | 62.29 Days
Continuous |
|
| 05-Jan-26 08:00 | 30-Jan-26 16:00 | ATCO | Outage | 7L48 (794s Valleyview - 7LA48 tap), 794s 703 (794s Valleyview) | pole and cross arm replacement from T&T | 25.33 Days
Continuous |
|
| 08-Jan-26 15:00 | 31-Jan-26 17:00 | ALTALINK | Outage | 42s C2 (42s Sarcee) | forced outage | 23.08 Days
Daily |
|
| 12-Jan-26 07:00 | 03-Apr-26 17:00 | EPCOR | TE | 330p Protection & Control (330p Genesee) | protect blocking, annual relay maintenance and password changes | 81.38 Days
Continuous |
|
| 12-Jan-26 07:00 | 03-Apr-26 17:00 | EPCOR | TE | Protection & Control (Rossdale) | protection blocking, relay maintenance | 81.38 Days
Continuous |
|
| 12-Jan-26 07:00 | 03-Apr-26 17:00 | EPCOR | TE | 987s Protection & Control (987s Clover Bar) | protection blocking, relay maintenance | 81.38 Days
Continuous |
|
| 12-Jan-26 08:00 | 30-Jan-26 16:00 | ENMAX | Outage | 32.3TR (SS-32) | panel cut-over | 18.33 Days
Continuous |
|
| 14-Jan-26 07:00 | 31-Jan-26 18:00 | ALTALINK | Outage | 799L (235s Entwistle - 443s South Mayerthorpe), 235s 799N (235s Entwistle) | 799L rebuild between str 888A-909 (section d) | 17.46 Days
Continuous |
|
| 17-Jan-26 11:00 | 28-Feb-26 17:00 | BHE Canada | Outage | 120s C2 (120s Picture Butte) | forced outage | 42.25 Days
Continuous |
|
| 19-Jan-26 07:00 | 02-Feb-26 17:00 | EPCOR | Outage | 711L (113s Inland Cement - 747L tap), 113s T1 (113s Inland Cement), 113s T2 (113s Inland Cement), 113s 711N (113s Inland Cement), 113s 1 (113s Inland Cement), 113s 5 (113s Inland Cement) | aerial line repairs and apparatus emergency bushing replacement | 14.42 Days
Continuous |
|
| 19-Jan-26 08:00 | 30-Jan-26 18:00 | ENMAX | TE | Protection & Control (SS-20) | autoswitching scheme protection outage for 1.81L cutover protection circuit cutover and commissioning to new 1.81L protection | 11.42 Days
Daily |
|
| 19-Jan-26 08:00 | 30-Jan-26 18:00 | ENMAX | TE | Protection & Control (SS-20) | SS-20 BMR-82 protection outage. 1.81L cutover- protection circuit cutover and commissioning to new 1.81L protection | 11.42 Days
Daily |
|
| 19-Jan-26 08:00 | 30-Jan-26 18:00 | ENMAX | TE | Protection & Control (SS-20) | 1.81L cutover- protection circuit cutover and commissioning to new 1.81L protection | 11.42 Days
Daily |
|
| 19-Jan-26 08:00 | 30-Jan-26 18:00 | ENMAX | TE | Protection & Control (SS-20) | 1.81L cutover- protection circuit cutover and commissioning to new 1.81L protection | 11.42 Days
Daily |
|
| 21-Jan-26 08:00 | 30-Oct-26 16:00 | ENMAX | Outage | 5.7TR (SS-5) | 25kV switchgear replacement | 282.29 Days
Continuous |
|
| 21-Jan-26 15:53 | 06-Feb-26 15:53 | CMH | TE | MHS-3 Protection & Control (MHS-3 South Ridge) | urgent replace failed protection relay | 16 Days
Continuous |
|
| 22-Jan-26 07:30 | 29-Jan-26 17:30 | ALTALINK | RB | 931L (28s West Brooks - 132s Ware Junction) | salvage existing concrete foundations from previously removed structures 931L25 & 1075L25 | 7.42 Days
Daily |
|
| 24-Jan-26 07:00 | 03-Feb-26 19:00 | ALTALINK | RB | 922L (17s Benalto - 310p Sundance) | raising str 922/926L4, goes with sap: 401748 926L RB required due to proximity | 10.5 Days
Daily |
|
| 24-Jan-26 07:00 | 03-Feb-26 19:00 | ALTALINK | RB | 926L (17s Benalto - 310p Sundance) | raising str 922/926L4, goes with sap: 401747 922L RB required due to proximity | 10.5 Days
Daily |
|
| 25-Jan-26 07:00 | 31-Jan-26 18:00 | ATCO | RB | 7L16 (766s Nevis - 948s Heatburg) | HOP on 7L16 to facilitate work adjacent to line for CETO project, stringing activities over 7L16 | 6.46 Days
Continuous |
|
| 25-Jan-26 08:00 | 30-Jan-26 18:00 | ENMAX | Outage | 20.3TR (SS-20) | 20 SUB switchgear replacement | 5.42 Days
Continuous |
|
| 26-Jan-26 07:00 | 30-Jan-26 17:00 | ALTALINK, EPCOR | Outage | 920L (37s North Calder - 557s Castle Downs), 557s CD2403 (557s Castle Downs), 557s CD2401 (557s Castle Downs) | 920LW/castledowns: relay maintenance and op checks | 4.42 Days
Continuous |
|
| 26-Jan-26 07:00 | 30-Jan-26 16:30 | NWE | Outage | NWMT Highwood-Judith Gap Auto 230kV Line | pole replacement project on the 230 kV line between Highwood AND Spion Kop
|
4.4 Days
Daily |
AB-MATL |
| 26-Jan-26 07:01 | 19-Feb-26 17:00 | EPCOR | Outage | T3 (Rossdale), R723 (Rossdale), R724 (Rossdale), RAB3 (Rossdale) | Rossdale: TX3 Zone, P&C Commissioning and Initial Energization | 24.42 Days
Continuous |
|
| 26-Jan-26 07:15 | 29-Jan-26 17:45 | ALTALINK | Outage | 314L (207s Pinedale - 228s T.M.P.L. Niton), 207s 314 (207s Pinedale), 228s 314 (228s T.M.P.L. Niton) | component replacement str 8–97 | 3.44 Days
Continuous |
|
| 26-Jan-26 07:30 | 01-Feb-26 17:30 | ALTALINK | RB | 443L (55s Olds - 214s Innisfail) | south crew will be doing structure replacements from 443L63 – 443L137 | 6.42 Days
Daily |
|
| 26-Jan-26 08:00 | 31-Jan-26 20:00 | SUNCOR | TE | 29EDD-1 Protection & Control (29EDD-1 Millennium) | CIP relay password changes at 29EDD | 5.5 Days
Continuous |
|
| 26-Jan-26 08:00 | 29-Jan-26 16:00 | ENMAX, ALTALINK | TE | 932L (74s Janet - SS-162) | firmware upgrade | 3.33 Days
Continuous |
|
| 26-Jan-26 08:00 | 29-Jan-26 16:00 | ENMAX, ALTALINK | IO | 932L (74s Janet - SS-162) | firmware upgrade | 3.33 Days
Continuous |
|
| 26-Jan-26 08:00 | 30-Jan-26 16:00 | ALTALINK | TE | 397s Protection & Control (397s Benbow) | 397s714 addition requiring settings changes and testing on | 4.33 Days
Daily |
|
| 26-Jan-26 08:00 | 30-Jan-26 17:00 | ALTALINK | TE | 397s RTU/SCADA (397s Benbow) | supervisory outages required for alarm/control updates and testing of 397s714 breaker control | 4.38 Days
Daily |
|
| 26-Jan-26 09:00 | 04-Feb-26 15:00 | ATCO | Outage | 9L57 (939s Livock - 960s Birchwood Creek) | ground clearance mitigation | 9.25 Days
Continuous |
|
| 26-Jan-26 10:00 | 29-Jan-26 17:00 | ALTALINK | TE | 17s Protection & Control (17s Benalto) | upgrade protection relays | 3.29 Days
Daily |
|
| 26-Jan-26 10:00 | 29-Jan-26 17:00 | ALTALINK | TE | 310p Protection & Control (310p Sundance) | relay maintenance on 96/25SC/79/452 & 96/25SC/79/4052 no redundancy, relay maintenance on B87/240BC redundancy. | 3.29 Days
Daily |
|
| 26-Jan-26 13:00 | 30-Jan-26 13:00 | ATCO | TE | 789s Protection & Control (789s Keg River) | prc relay testing 7L64, 7L62, 7L59 and 701BF, 702BF, 703BF | 4 Days
Continuous |
|
| 26-Jan-26 13:00 | 29-Jan-26 13:00 | ATCO | TE | 2091s Protection & Control (2091s Thornton) | prc relay testing 7L20, 7L228, 87/700BS1, 5L703, 5L720 and 5L775 | 3 Days
Continuous |
|
| 27-Jan-26 10:00 | 30-Jan-26 16:30 | ATCO | Outage | 7L574 (822s Wolf Lake - 7L574 tap), 822s 702 (822s Wolf Lake) | isolate breaker 702 to find leaks and repair if possible, top up insulating gas, test gas mixture after 24hours |
3.27 Days
Continuous |
|
| 27-Jan-26 14:00 | 05-Feb-26 14:00 | ATCO | Outage | 740s 703T (740s H.R.Milner), 740s 507C (740s H.R.Milner), 740s 703 (740s H.R. Milner), 740s 503 (740s H.R. Milner) | isolate to investigate fault on underground cables or metering tank on T1 feeder at 740S HR Milner | 9 Days
Continuous |
|
| 27-Jan-26 17:00 | 29-Jan-26 19:00 | ALTALINK | Outage | 618s 863X (618s Riverbend), 863L (618s Riverbend - 891L tap) | forced outage | 2.08 Days
Daily |
|
| 28-Jan-26 06:00 | 11-Feb-26 18:00 | Lethbridge | IO | Lethbridge PCC | activating Backup Control Centre to allow for renovations to the Main Control Centre | 14.5 Days
Continuous |
|
| 28-Jan-26 07:30 | 29-Jan-26 16:00 | ENMAX | Outage | B138-85 (SS-1), B138-86 (SS-1) | line cut over | 1.35 Days
Continuous |
|
| 28-Jan-26 08:00 | 29-Jan-26 16:00 | ENMAX | Outage | 35.2TR (SS-35), 35B138-80 (SS-35), 35B138-83 (SS-35), 35MD138-80 (SS-35), 35MD138-90 (SS-35), 35MD138-92 (SS-35) | HV switch maintenance | 1.33 Days
Continuous |
|
| 29-Jan-26 07:00 | 29-Jan-26 17:00 | EPCOR | Outage | EP 511s V726 (EP 511s Victoria) | switching school recertification | 10 Hours
Continuous |
|
| 29-Jan-26 07:30 | 29-Jan-26 17:00 | ATCO | TE | ATCO Telecom Equipment, 888s RTU/SCADA (888s Dover) | CIP vulnerabilities are identified and then patched | 9.5 Hours
Continuous |
|
| 29-Jan-26 07:30 | 29-Jan-26 17:00 | ATCO | TE | ATCO Telecom Equipment, 849s RTU/SCADA (849s Joslyn Creek) | CIP vulnerabilities are identified and then patched | 9.5 Hours
Continuous |
|
| 29-Jan-26 07:30 | 29-Jan-26 20:00 | ATCO | TE | ATCO Telecom Equipment, 809s RTU/SCADA (809s Louise Creek) | as part of CIP patching vulnerabilities are identified and then patched |
12.5 Hours
Continuous |
|
| 29-Jan-26 07:30 | 29-Jan-26 20:00 | ATCO | TE | ATCO Telecom Equipment, 825s Whitefish Lake RTU/SCADA | CIP patching vulnerabilities are identified and then patched | 12.5 Hours
Continuous |
|
| 29-Jan-26 08:00 | 29-Jan-26 17:00 | ALTALINK | TE | 74s Protection & Control (74s Janet) | firmware upgrade on 932L | 9 Hours
Daily |
|
| 29-Jan-26 08:00 | 29-Jan-26 17:00 | ALTALINK | TE | 131s Protection & Control (131s Moon Lake) | standard relay maintenance | 9 Hours
Daily |
|
| 29-Jan-26 08:00 | 30-Jan-26 16:00 | ENMAX | Outage | 22.81L (SS-22 - SS-39), 22.2TR (SS-22), 22B138-22BT8 (SS-22), SW85 (SS-22), 22B138-22.81 (SS-22), 22MD138-22.2TR (SS-22), 39B138-22.81 (SS-39) | HV SW maintenance, reversing switch check | 1.33 Days
Continuous |
|
| 29-Jan-26 08:00 | 29-Jan-26 16:00 | ALTALINK | TE | AltaLink Telecom Equipment, 67s RTU/SCADA (67s Stirling) | split the existing SCADA VLAN | 8 Hours
Daily |
|
| 29-Jan-26 08:00 | 29-Jan-26 17:00 | ALTALINK | TE | 74s RTU/SCADA (74s Janet) | techs to resolve pass-through issues involved with RIO D10 | 9 Hours
Daily |
|
| 29-Jan-26 08:30 | 29-Jan-26 17:30 | ALTALINK | TE | 89s Protection & Control (89s Ellerslie) | DSP card replacements for 1057L | 9 Hours
Daily |
|
| 29-Jan-26 09:00 | 29-Jan-26 11:00 | ATCO, CNRL | TE | ATCO Telecom Equipment, 838s RTU/SCADA (838s Horizon Mining), 838s Protection & Control (838s Horizon Mining), 849s RTU/SCADA (849s Joslyn Creek) | CNRL Horizon Expansion_S-Telecom- Horizon sub A SAR and NET 11 SAR os upgrades | 2 Hours
Continuous |
|
| 29-Jan-26 09:00 | 29-Jan-26 16:00 | ATCO | TE | 917s Protection & Control (917s Horse River) | PRC-005 relay testing on 51-46/706C, 51-27-59/706C | 7 Hours
Continuous |
|
| 29-Jan-26 09:00 | 30-Jan-26 17:00 | ATCO, ALBIAN | TE | 919s RTU/SCADA (919s Hartley), 920s RTU/SCADA (920s Jackpine) | investigate CNRL communication signals, troubleshoot invalid data values, cycle power on 920S and 919S RTU | 1.33 Days
Continuous |
|
| 29-Jan-26 10:00 | 30-Jan-26 17:30 | ATCO | TE | 959s Protection & Control (959s Lanfine), 959s RTU/SCADA (959s Lanfine) | 87BA-B 700BS2 Siemens 7UT635 | 31.5 Hours
Continuous |
|
| 29-Jan-26 10:00 | 29-Jan-26 11:00 | ALTALINK, ATCO | Outage | 199L (347s AML Fox Creek - 741s ATC Fox Creek), 347s 199W (347s AML Fox Creek), 741s 702 (741s ATC Fox Creek) | gas top up on 347s199W | 60 Mins
Daily |
|
| 29-Jan-26 11:00 | 30-Jan-26 18:00 | ALTALINK | Outage | 854L (39s Bickerdike - 854AL tap) | urgent structure repair 854L str. 284, 285 | 31 Hours
Continuous |
|
| 30-Jan-26 07:30 | 30-Jan-26 20:00 | ATCO | TE | 898s Heart Lake RTU/SCADA, ATCO Telecom Equipment | Heart Lake_S-Telecom- CIP patching | 12.5 Hours
Continuous |
|
| 30-Jan-26 08:00 | 30-Jan-26 16:00 | ALTALINK | TE | 254s RTU/SCADA (254s Coaldale), AltaLink Telecom Equipment | split the existing SCADA VLAN | 8 Hours
Daily |
|
| 30-Jan-26 09:00 | 30-Jan-26 11:00 | ATCO | TE | 861s RTU/SCADA (861s Eureka River), ATCO Telecom Equipment | silver valley and clear hills SAR OS upgrades | 2 Hours
Continuous |
|
| 31-Jan-26 07:00 | 31-Jan-26 17:00 | EPCOR | TE | RTU/SCADA (Namao) | substation firewall replacement | 10 Hours
Continuous |
|
| 31-Jan-26 07:00 | 07-Feb-26 17:30 | ALTALINK | RB | 784L (535s Joffre - 784AL tap), 784L (332s Ellis - 784AL tap), 784AL (482s Haynes - 784L tap) | stringing (CETO) 962L/986L | 7.44 Days
Daily |
|
| 01-Feb-26 07:00 | 09-Feb-26 18:00 | ATCO | RB | 7L16 (766s Nevis - 948s Heatburg) | to facilitate work adjacent to line for CETO project | 8.46 Days
Continuous |
|
| 02-Feb-26 07:00 | 14-Feb-26 18:00 | ALTALINK | Outage | 719L (719AL tap - 719BL tap) | component replacement/maintenance structure 219-258 | 12.46 Days
Continuous |
|
| 02-Feb-26 07:00 | 06-Feb-26 17:00 | ALTALINK, EPCOR | Outage | 920L (71s Lamoureux - 557s Castle Downs), 557s CD2405 (557s Castle Downs), 557s CD2404 (557s Castle Downs) | relay maintenance and op checks on 920LE/Castledowns | 4.42 Days
Continuous |
|
| 02-Feb-26 07:00 | 06-Feb-26 17:00 | EPCOR | Outage | 72CH11 (987s Clover Bar - EP Hardisty), T1 (EP Hardisty), H725 (EP Hardisty), H722 (EP Hardisty), HAB1 (EP Hardisty) | relay maintenance on Hardisty TX1 | 4.42 Days
Continuous |
|
| 02-Feb-26 07:30 | 06-Feb-26 17:30 | ALTALINK | RB | 443L (55s Olds - 214s Innisfail) | South Crew will be doing structure replacements from 443L63 – 443L137 | 4.42 Days
Daily |
|
| 02-Feb-26 07:30 | 02-Feb-26 17:30 | ALTALINK | Outage | 202L (61s Lodgepole - 202AL tap) | create 202L open point 'A' | 10 Hours
Daily |
|
| 02-Feb-26 07:30 | 02-Feb-26 17:30 | ALTALINK | RB | 202L (61s Lodgepole - 202AL tap), 202L (178s Cynthia - 202AL tap) | Safety requirement; Create 202L Open Point 'A' | 10 Hours
Daily |
|
| 02-Feb-26 08:00 | 07-Feb-26 20:00 | SUNCOR | TE | 29EDD-34 Protection & Control (29EDD-34) | CIP relay password change | 5.5 Days
Continuous |
|
| 02-Feb-26 08:00 | 09-Feb-26 16:00 | ATCO | Outage | 7L48 (794s Valleyview - 7LA48 tap), 794s 703 (794s Valleyview) | pole and cross arm replacement | 7.33 Days
Continuous |
|
| 02-Feb-26 08:00 | 04-Feb-26 16:00 | ENMAX | Outage | 15.60L (SS-15 - SS-21), 21.61L (SS-21 - SS-34), 21.4TR (SS-21), 15B69-15.60 (SS-15), 21B69-15.60 (SS-21), 34B69-21.61 (SS-34), 21B69-21.61 (SS-21), 21B69-21.4TR (SS-21) | maintenance on 21SW61, 21SW62, 21SW63, 21SW64, 21SW65, 21SW66, 21SW67 and fix SW64 at 21 sub hot spot | 2.33 Days
Continuous |
|
| 02-Feb-26 08:00 | 05-Feb-26 17:00 | ALTALINK | TE | 17s RTU/SCADA (17s Benalto) | firewall upgrade | 3.38 Days
Daily |
|
| 02-Feb-26 08:00 | 03-Feb-26 17:00 | ALTALINK | TE | AltaLink Telecom Equipment, 13s RTU/SCADA (13s Deerland) | split the existing SCADA VLAN from 1 to 1 and 2 | 1.38 Days
Daily |
|
| 02-Feb-26 08:00 | 03-Feb-26 16:00 | ENMAX | Outage | 6.80L (SS-6 - SS-35), 35B138-82 (SS-35), 35B138-83 (SS-35), 6B138-6.80 (SS-6), 35MD138-6.80 (SS-35), 35MD138-86 (SS-35), 35MD138-87 (SS-35), 35MD138-89 (SS-35), 35MD138-90 (SS-35) | HV switch maintenance - 35MD138-6.80, 35MD138-87, 35MD138-89, SW83 | 1.33 Days
Continuous |
|
| 02-Feb-26 08:00 | 03-Feb-26 16:00 | ENMAX | TE | Protection & Control (SS-14) | 14sub Auto Switching Protection Scheme outage. Relay Protection Test - 14RLY138-14.ASW | 1.33 Days
Continuous |
|
| 02-Feb-26 08:00 | 03-Feb-26 16:00 | ENMAX | TE | Protection & Control (SS-41) | 41 sub BMR-81 outage. Relay Protection Test - 41RLY138-41.BMR81 | 1.33 Days
Continuous |
|
| 02-Feb-26 08:00 | 02-Feb-26 12:00 | ENMAX | Outage | 3.3TR (SS-3) | breaker maintenance. | 4 Hours
Continuous |
|
| 02-Feb-26 09:00 | 03-Feb-26 17:00 | ATCO | TE | ATCO Telecom Equipment | Cordel telecom equipment replacement | 1.33 Days
Continuous |
|
| 02-Feb-26 09:00 | 02-Feb-26 10:00 | ATCO | TE | ATCO Telecom Equipment | Sheerness_S-Telecom- SHEERNESS A AND NET 11 SAR OS UPGRADES.2 SEPARATE OUTAGES IMPACTING THE FOLLOWING TRAFFIC: OUTAGE 1 : 9L99 A,THERMAL PROTECTION RAS A, 9L100 A OUTAGE 2 : 9L99 B,THERMAL PROTECTION RAS B, 9L100 B |
60 Mins
Continuous |
|
| 02-Feb-26 09:00 | 02-Feb-26 16:00 | ATCO | TE | 849s Protection & Control (849s Joslyn Creek) | PRC-005 relay testing on 50BF/901& 50BF/902. | 7 Hours
Continuous |
|
| 02-Feb-26 09:00 | 02-Feb-26 18:00 | ALTALINK | Outage | 804L (40s Wetaskiwin - 40s 803L tap), 804L (40s 803L tap - 86s 803L tap), 804L (86s Bigstone - 86s 803L tap), 40s 804W (40s Wetaskiwin), 86s 852 (86s Bigstone), 804L-Pseudo (86s Bigstone) | Install grounds at 804L28 for county bridge construction | 9 Hours
Daily |
|
| 02-Feb-26 10:00 | 11-Feb-26 18:00 | ATCO | RB | 7L08 (830s Carmon - 834s Wesley Creek) | Maintenance Program, 32 Pole Changes, 21 Crossarm Changes, other structure deficiencies. | 9.33 Days
Continuous |
|
| 02-Feb-26 10:00 | 02-Feb-26 11:00 | ALTALINK | Outage | 397s 138kV Bus 1 (397s Benbow), 720L (347s AML Fox Creek - 397s Benbow), 714L (397s Benbow – 1117s South Kaybob), 397s T1 (397s Benbow), 347s 720X (347s AML Fox Creek) | de-energize 397s 138 kV bus B1 to facilitate the first energization of 397s714 | 60 Mins
Daily |
|
| 02-Feb-26 10:00 | 05-Feb-26 17:00 | ALTALINK | TE | 320p Protection & Control (320P Keephills) | relay maintenance | 3.29 Days
Daily |
|
| 02-Feb-26 10:00 | 06-Feb-26 17:30 | ATCO | Outage | 770s 705C (770s Three Hills) | trip coil testing PRC-005 | 4.31 Days
Continuous |
|
| 02-Feb-26 11:00 | 02-Feb-26 17:00 | ALTALINK | TE | 395s Protection & Control (395s North Holden) | Standard relay maintenance | 6 Hours
Daily |
|
| 02-Feb-26 11:00 | 05-Feb-26 17:00 | ALTALINK | TE | 320p RTU/SCADA (320P Keephills) | RTU "A" reboot | 3.25 Days
Daily |
|
| 02-Feb-26 11:00 | 05-Feb-26 17:00 | ALTALINK | TE | 320p RTU/SCADA (320P Keephills) | investigate IED trouble alarm. | 3.25 Days
Daily |
|
| 02-Feb-26 11:30 | 03-Feb-26 17:00 | ALTALINK | TE | 293s Protection & Control (293s Bernese) | Card replacements | 29.5 Hours
Daily |
|
| 02-Feb-26 11:30 | 06-Feb-26 16:30 | ALTALINK | Outage | 217s C1 (217s North Red Deer) | replacement of CT#5’s with RHM dry type, CTs are located between 217s652 and C1 | 4.21 Days
Continuous |
|
| 02-Feb-26 12:30 | 02-Feb-26 15:00 | ENMAX | TE | Protection & Control (SS-28) | 28PT138-Z31 -X core sec. voltage. 1 sub Transmission line cut over. Demo and reconnect. Fault clearing time 5.5 cycles | 2.5 Hours
Continuous |
|
| 02-Feb-26 13:00 | 06-Feb-26 13:00 | ATCO | TE | 739s Protection & Control (739s Edith Lake) | PRC Relay Testing 7L172, 7L43, 702BF, and 700BS1, including AUX tripping relays. One relay at a time. Loss of reclosing and channel teleprotection while line relay is out of service. Redundant A/B protection except for 700BS1. | 4 Days
Continuous |
|
| 02-Feb-26 13:00 | 06-Feb-26 13:00 | ATCO | TE | 789s Protection & Control (789s Keg River) | PRC relay testing | 4 Days
Continuous |
|
| 02-Feb-26 13:00 | 02-Feb-26 14:00 | ATCO | TE | ATCO Telecom Equipment, 931s RTU/SCADA (931s Bohn) | Telecom upgrading | 60 Mins
Continuous |
|
| 02-Feb-26 16:15 | 18-Feb-26 10:00 | ALTALINK | Outage | 202L (61s Lodgepole - 202AL tap), 61s 202X (61s Lodgepole) | replacing air break 202L335 | 15.74 Days
Continuous |
|
| 03-Feb-26 07:00 | 17-Feb-26 14:00 | ALTALINK | Outage | 685L (397s Benbow - 1012s Deer Hill), 714L1 (714L tap) | 685L OPGW tie into 328s and 397s, replace conductor inside 397s, Line crew to replace structure 685L1 and cut free 714L1, 685L temporary phase swap at 1012s flying tap location | 14.29 Days
Continuous |
|
| 03-Feb-26 07:00 | 03-Feb-26 17:00 | EPCOR | Outage | EP 511s V721 (EP 511s Victoria) | Victoria: V721, switching school recertification | 10 Hours
Continuous |
|
| 03-Feb-26 08:00 | 03-Feb-26 16:00 | SUNCOR | TE | 29EDD-2 29PT-3 (29EDD-2 Tar Island) | 300495274, 29PT-2 /3/84 AVR settings, implement settings | 8 Hours
Continuous |
|
| 03-Feb-26 08:00 | 04-Feb-26 17:00 | ALTALINK | TE | AltaLink Telecom Equipment, 108s RTU/SCADA (108s Amelia) | split the existing SCADA VLAN from 1 to 1 and 2 | 1.38 Days
Daily |
|
| 03-Feb-26 08:00 | 04-Feb-26 17:00 | ALTALINK | TE | 275s RTU/SCADA (275s Jenner) | settings changes/update to RTU and RSG2100 #3 to enable remote access to TESLA 4000 DDR2 | 1.38 Days
Daily |
|
| 03-Feb-26 08:00 | 03-Feb-26 16:00 | SUNCOR | TE | 29EDD-2 RTU/SCADA (29EDD-2 Tar Island) | 29EDD2 9PS-5/6 L/R switch DC fail alarms investigate and troubleshoot, DC fail simulate status change from the RTU |
8 Hours
Continuous |
|
| 03-Feb-26 09:00 | 03-Feb-26 11:00 | ATCO, ENEL, ALTALINK | TE | ATCO Telecom Equipment, 918s RTU/SCADA (918s Bauer), 708s RTU/SCADA (708s Grizzly Bear), 7L65 (709s Vegreville - 7LA65 tap), 7L65 (710s Vermilion - 7LA65 tap), APS# 134 Central East Transfer Out Overload Mitigation Scheme | Bauer_S-Telecom/Buffalo Creek_S_Telecom/Grizzly_S-Telecom- 'A' SAR OS upgrade | 2 Hours
Continuous |
|
| 03-Feb-26 09:00 | 03-Feb-26 17:00 | ATCO | TE | ATCO Telecom Equipment, 9L43 (874s McKay River - 888s Dover) | removal of DJF and install new Nokia RS232, new SAR A, SDI cards | 8 Hours
Continuous |
|
| 03-Feb-26 09:00 | 03-Feb-26 12:00 | ENMAX | TE | Protection & Control (SS-28) | 28PT138-Z31 -Y core sec. voltage, 1 sub transmission line cut over, demo and reconnect | 3 Hours
Continuous |
|
| 03-Feb-26 09:00 | 03-Feb-26 16:00 | ATCO | TE | 849s Protection & Control (849s Joslyn Creek) | PRC-005 relay testing on 50BF/903& 50BF/904 | 7 Hours
Continuous |
|
| 03-Feb-26 09:00 | 03-Feb-26 17:00 | ALTALINK | TE | 223s Protection & Control (223s Strome) | card replacements | 8 Hours
Daily |
|
| 03-Feb-26 09:00 | 30-Jun-26 17:00 | ATCO | TE | 972s RTU/SCADA (972s Tinchebray) | config changes needed throughout the CETO project | 147.29 Days
Continuous |
|
| 04-Feb-26 07:00 | 04-Feb-26 17:00 | EPCOR | Outage | EP 511s V722 (EP 511s Victoria) | Victoria: V722, switching school recertification | 10 Hours
Continuous |
|
| 04-Feb-26 07:00 | 04-Feb-26 18:30 | ALTALINK | Outage | 922L (17s Benalto - 310p Sundance) | Clipping in 922L OHSW between strs 922L1 and 922L7, after raising 922/926L4. See also SAP: 401749 926L RB required due to proximity | 11.5 Hours
Daily |
|
| 04-Feb-26 07:00 | 04-Feb-26 18:30 | ALTALINK | RB | 926L (17s Benalto - 310p Sundance) | required for SAP: 401742 922L GOI required due to proximity | 11.5 Hours
Daily |
|
| 04-Feb-26 08:00 | 04-Feb-26 18:00 | Syncrude | TE | Syncrude ICCP Outage | SCADA - server update whole Syncrude visibility loss | 10 Hours
Daily |
|
| 04-Feb-26 08:00 | 04-Feb-26 17:00 | ALTALINK | TE | AltaLink Telecom Equipment, 534s RTU/SCADA (534s Eckville) | radio maintenance. 534s Eckville supervisory will be lost for 2hrs | 9 Hours
Daily |
|
| 04-Feb-26 08:00 | 04-Feb-26 17:00 | ALTALINK | TE | 12s Protection & Control (12s Heartland) | standard relay maintenance, T1 A87/50/51/51N/T1, B240B1 B87/240B1, B500B2 B87/500B2, redundant protections in place at all times | 9 Hours
Daily |
|
| 04-Feb-26 08:00 | 05-Feb-26 17:00 | ALTALINK | TE | 127s RTU/SCADA (127s Bruderheim), AltaLink Telecom Equipment | split the existing SCADA VLAN from 1 to 1 and 2. loss of visibility of 127s for 15 minutes in the timeframe indicated. | 1.38 Days
Daily |
|
| 04-Feb-26 08:00 | 05-Feb-26 16:00 | ENMAX | Outage | 47B138-771/1 (SS-47) | Investigate the leak and possible repair | 1.33 Days
Continuous |
|
| 04-Feb-26 08:00 | 06-Feb-26 16:00 | ENMAX | Outage | 14.1TR (SS-14) | relay protection test | 2.33 Days
Continuous |
|
| 04-Feb-26 08:00 | 05-Feb-26 17:00 | SUNCOR | TE | 635EDD-1000 RTU/SCADA (635EDD-1000), 635EDD-1001 RTU/SCADA (635EDD-1001) | update the SCADA configurations at 635EDD-1000 and 635EDD-1001 to add in building temp and battery voltage metering points | 1.38 Days
Daily |
|
| 04-Feb-26 08:00 | 05-Feb-26 16:00 | ENMAX | TE | Protection & Control (SS-41) | 41 sub BMR BT3 protection outage. Relay Protection Test - 41RLY138-41BT3 (BMR) | 1.33 Days
Continuous |
|
| 04-Feb-26 08:30 | 04-Feb-26 17:00 | ALTALINK | TE | 221s Protection & Control (221s Sunken Lake) | relay card replacements | 8.5 Hours
Daily |
|
| 04-Feb-26 09:00 | 04-Feb-26 10:00 | ATCO | TE | ATCO Telecom Equipment, 804s RTU/SCADA (804s Wintering Hills) | Wintering Hills_S_Telecom- Upgrading the NET 2 SAR to V22. Impact to the following traffic: #202 RAS A & B 7L85 A&B 804s Winteirng Hills RTU |
60 Mins
Continuous |
|
| 04-Feb-26 09:00 | 04-Feb-26 16:00 | ATCO | TE | 849s Protection & Control (849s Joslyn Creek) | PRC-005 RELAY TESTING on 50BF/905& 50BF/906. Redundant protection in-service at all times. | 7 Hours
Continuous |
|
| 04-Feb-26 09:30 | 04-Feb-26 20:00 | SUNCOR | IO | Suncor RTU/SCADA (Suncor), 29EDD-34 Edd34Sub, 29EDD-1 Millennium, 29EDD-94 Voyageur | Rotating BLAN outages lasting 60 minutes or less each affecting security & cameras at the Top T&D Communication Room, SDC Server building / BCC1, SDC ( Control Room), 29EDD-34 P&C building, 29EDD-1X P&C Building, 29EDD-94 P&C Building. Guards will be posted during these outages |
10.5 Hours
Continuous |
|
| 04-Feb-26 13:00 | 04-Feb-26 14:00 | ATCO | TE | ATCO Telecom Equipment, 933s RTU/SCADA (933s Tower Road) | TowerRoad_S-Telecom- Upgrading the NET 2 SAR to V22. Impact to the following traffic: 7L165 A&B 7L98 A&B 933s Tower Road RTU |
60 Mins
Continuous |
|
| 04-Feb-26 19:00 | 05-Feb-26 18:30 | ALTALINK | Outage | 926L (17s Benalto - 310p Sundance) | Clipping in 926L OHSW between strs 926L1 and 926L7, after raising str 922/926L4 See also SAP: 401745 922L RB required due to proximity | 23.5 Hours
Continuous |
|
| 05-Feb-26 07:00 | 05-Feb-26 17:00 | EPCOR | Outage | EP 511s V723 (EP 511s Victoria) | Victoria: V723, Switching School Recertification | 10 Hours
Continuous |
|
| 05-Feb-26 07:00 | 05-Feb-26 19:00 | ALTALINK | RB | 922L (17s Benalto - 310p Sundance) | required due to proximity of 926L GOI | 12 Hours
Daily |
|
| 05-Feb-26 07:00 | 08-Feb-26 16:00 | ATCO | Outage | 9L913 (69s North Barrhead - 732s Mitsue) | Changing white tag poles from Test & Treat ( Str 16,69 and 503 ) | 3.38 Days
Continuous |
|
| 05-Feb-26 07:00 | 08-Feb-26 16:30 | ALTALINK | Outage | 913L (69s North Barrhead - 732s Mitsue) | changing white tag poles from test & treat | 3.4 Days
Continuous |
|
| 05-Feb-26 08:00 | 05-Feb-26 17:00 | ALTALINK | TE | 650s Protection & Control (650s Hansman Lake) | protection outages on the following to troubleshoot protection alarm cycling issues: 7L224, A21/L12, B21/79/L12 | 9 Hours
Daily |
|
| 05-Feb-26 08:00 | 05-Feb-26 16:00 | ENMAX | Outage | 65B138-D81 (SS-65), 24.82L (SS-24 - SS-65), 65B138-D82 (SS-65) | I&R red light very dim (LD) | 8 Hours
Continuous |
|
| 05-Feb-26 08:00 | 06-Feb-26 16:00 | ALTALINK | TE | 140s RTU/SCADA (140s Thompson) | split the existing SCADA VLAN from 1 to 1 and 2 | 1.33 Days
Daily |
|
| 05-Feb-26 09:00 | 05-Feb-26 12:00 | ATCO | TE | ATCO Telecom Equipment | upgrading the A SAR and NET 11 SAR to v21 then v22 | 3 Hours
Continuous |
|
| 05-Feb-26 09:00 | 05-Feb-26 11:00 | ATCO | TE | ATCO Telecom Equipment, 837s Mahihkan RTU/SCADA | upgrading the A SAR to v21 then v22 | 2 Hours
Continuous |
|
| 05-Feb-26 09:00 | 05-Feb-26 16:00 | ATCO | TE | 849s Protection & Control (849s Joslyn Creek) | PRC-005 relay testing on 21A/9L08, 21B/9L08. | 7 Hours
Continuous |
|
| 05-Feb-26 09:00 | 05-Feb-26 17:00 | ALTALINK | TE | 454s Protection & Control (454s Buck Lake) | card replacement | 8 Hours
Daily |
|
| 06-Feb-26 07:00 | 08-Feb-26 18:30 | ALTALINK | RB | 922L (17s Benalto - 310p Sundance) | removing tooling after raising str 922L4 Goes with SAP: 401756 926L RB required due to proximity | 2.48 Days
Daily |
|
| 06-Feb-26 07:00 | 08-Feb-26 18:30 | ALTALINK | RB | 926L (17s Benalto - 310p Sundance) | removing tooling after raising str 926L4 Goes with SAP: 401755 922L RB required due to proximity | 2.48 Days
Daily |
|
| 06-Feb-26 07:00 | 27-Feb-26 17:30 | ALTALINK | RB | 793L (87s Gaetz - 535s Joffre) | crews will be setting structures on 986L/962L STR’s 41-56 & 24-41 and will require a Reclosure Block on 793L |
21.44 Days
Daily |
|
| 06-Feb-26 09:00 | 06-Feb-26 16:00 | ATCO | TE | 849s Protection & Control (849s Joslyn Creek) | PRC-005 relay testing | 7 Hours
Continuous |
| This document and the information contained herein are based upon information and data which by their nature contain a degree of uncertainty and are subject to change. In addition, this document may contain information and data from public sources and/or third parties, which have been assumed to be accurate and complete and have not been verified. Accordingly, the Independent System Operator, operating as the Alberta Electric System Operator (the "AESO") makes no warranty, representation or guarantee, express or implied, with respect to this document or the information contained herein, including, but not limited to, any warranty, representation or guarantee of accuracy, completeness, timeliness, reliability, availability, absence of computer virus, non- infringement, merchantability or suitability for any purpose. Under no circumstances will the AESO, its members, officers, employees, contractors or agents, or any of their respective affiliates, be liable for any errors or omissions in, or any losses, damages or claims whatsoever, whether in contract, tort or otherwise, arising from use of or reliance upon, this document or any information contained herein. © 2009 Alberta Electric System Operator. All rights reserved |