| Alberta Electric System Operator | |
| System Co-ordination Plan | |
| 2025-11-15 to 2025-11-21 | |
| Approved Outages |
| Previous Version | |
| Download CSV |
| From | To | Owner | Type | Element | Scheduled Activity | Date/Time Comments | Interconnection |
|---|---|---|---|---|---|---|---|
| 26-Jul-24 10:00 | 31-Jul-26 16:00 | ATCO | Outage | 826s 504R (826s Marguerite Lake) | emergency removal to replace failed 502R @834S | 735.25 Days
Continuous |
|
| 23-Aug-24 13:45 | 30-Jun-26 14:29 | ALTALINK | Outage | 157s C1 (157s Lac La Biche) | forced outage | 676.03 Days
Continuous |
|
| 11-Mar-25 00:00 | 31-Dec-25 16:00 | ALTALINK | Outage | 377s 473C (377s AML Hardisty) | forced outage | 295.71 Days
Continuous |
|
| 18-Mar-25 14:00 | 17-Mar-26 17:30 | ALTALINK | Outage | 217s C1 (217s North Red Deer) | cap. bank unavailable and cannot be energized due to Koncar CTs being present | 364.15 Days
Daily |
|
| 20-Mar-25 08:00 | 20-Mar-26 17:00 | ALTALINK | Outage | 256s C1 (256s Harmattan) | forced outage | 365.38 Days
Continuous |
|
| 31-Mar-25 07:00 | 19-Dec-25 17:00 | EPCOR | TE | Protection & Control (Woodcroft) | Woodcroft: protection blocking for merging unit and protection upgrade. | 263.46 Days
Continuous |
|
| 14-May-25 08:00 | 10-Feb-26 16:00 | ENMAX | TE | Protection & Control (SS-32) | 32sub 138kV autoswitching protection outage | 272.38 Days
Continuous |
|
| 08-Jun-25 15:00 | 25-Nov-25 15:30 | ALTALINK | Outage | 397s 864W (397s Benbow) | new 864L line construction, new 397s48 (VT6) install | 170.06 Days
Continuous |
|
| 13-Jun-25 17:00 | 11-Feb-26 17:00 | EPCOR | Outage | T3 (Rossdale) | Rossdale - TX3 LCR | 243.04 Days
Continuous |
|
| 16-Jul-25 07:00 | 01-Dec-25 23:55 | NWE | Outage | 2366 (NWE Marias) | install new equipment at Marias | 138.75 Days
Continuous |
AB-MATL |
| 21-Jul-25 09:00 | 19-Jan-26 17:00 | ATCO | TE | 732s Protection & Control (732s Mitsue) | the breaker fail protection will be disabled during the project, as we migrate from the existing to the new protection | 182.38 Days
Continuous |
|
| 21-Jul-25 09:00 | 23-Jan-26 16:30 | ATCO | TE | 732s RTU/SCADA (732s Mitsue) | existing RTU system being replaced with new SMP system | 186.35 Days
Continuous |
|
| 22-Jul-25 08:30 | 31-Dec-25 16:30 | ALTALINK | Outage | 263s C1 (263s Strachan) | forced outage | 162.38 Days
Continuous |
|
| 25-Jul-25 17:01 | 20-Feb-26 17:00 | EPCOR | Outage | T2 (EP Riverview) | bushing test failure (found during OE110184) | 210.04 Days
Continuous |
|
| 02-Aug-25 23:30 | 10-Dec-25 18:00 | ATCO | Outage | 827s SVC (827s Cranberry Lake) | forced outage | 129.81 Days
Continuous |
|
| 18-Aug-25 07:00 | 21-Nov-25 17:00 | EPCOR | TE | 805s Protection & Control (805s Jasper) | protection blocking for P&C maintenance | 95.46 Days
Continuous |
|
| 20-Aug-25 17:00 | 17-Dec-25 17:00 | ALTALINK | Outage | 1075L (28s West Brooks - 132s Ware Junction) | restoration from real time storm | 119.04 Days
Continuous |
|
| 25-Aug-25 08:00 | 03-Apr-26 16:00 | ENMAX | Outage | 32.1TR (SS-32) | slip over CT and new power cables installation and P&C works | 221.33 Days
Continuous |
|
| 25-Aug-25 09:00 | 10-Dec-25 17:00 | ATCO | TE | 710s Protection & Control (710s Vermilion) | protection and hardwired IO on-site will need to be cut-over to the new SCADA system and tested | 107.38 Days
Continuous |
|
| 02-Sep-25 08:00 | 28-Feb-26 16:00 | ENMAX | Outage | 38.1C (SS-38) | capacitor bank switcher replacement | 179.38 Days
Continuous |
|
| 05-Sep-25 08:00 | 24-Nov-25 16:00 | ENMAX | Outage | 1.83L (SS-1 - SS-8) | 1 sub Transmission line cut over. Line will terminate at new 1 sub upon return to service. | 80.38 Days
Continuous |
|
| 05-Sep-25 08:00 | 24-Nov-25 16:00 | ENMAX | Outage | 1.85L (SS-1 - SS-8) | 1 sub transmission line cut over. line will terminate at new 1 sub upon return to service. | 80.38 Days
Continuous |
|
| 12-Sep-25 08:00 | 06-Mar-26 16:00 | ENMAX | Outage | 33.1TR (SS-33) | tap changer refurbishments. soak test required | 175.38 Days
Continuous |
|
| 26-Sep-25 07:00 | 23-Nov-25 11:00 | ALTALINK | Outage | 864L (397s Benbow - 864AL tap), 397s 864W (397s Benbow) | 864CL line construction | 58.21 Days
Continuous |
|
| 06-Oct-25 10:00 | 19-Nov-25 16:00 | ALTALINK | Outage | 102s SVC (102s Langdon), 102s T4 (102s Langdon), 102s 252 (102s Langdon), 102s 552 (102s Langdon) | the controls change | 44.29 Days
Continuous |
AB-BC |
| 15-Oct-25 12:00 | 01-Dec-25 17:00 | EPCOR | Outage | 330P 12TC1 (330p Genesee), 330p 805 (330p Genesee) | Genesee: 12TC1 emergency bushing investigation | 47.25 Days
Continuous |
|
| 16-Oct-25 08:00 | 24-Nov-25 20:00 | SUNCOR | Outage | 29EDD-61 29PT-653 (29EDD-61 Stony Island), 29EDD-61 30-252-500001 (29EDD-61 Stony Island) | 29PT-653 repair / replace burned bonding conductor (9000808061) | 39.54 Days
Continuous |
|
| 20-Oct-25 07:00 | 28-Nov-25 17:00 | ALTALINK, EPCOR | RB | 1044L (EP 805s Jasper - 816s Petrolia) | working in proximity (MN872 manhole replacement) | 39.46 Days
Continuous |
|
| 27-Oct-25 08:00 | 20-Nov-25 16:00 | ENMAX | Outage | 32.83L (SS-32 - SS-40), 32B138-32.83 (SS-32), 40B138-32.83 (SS-40) | 32.83L P&C cut over | 24.38 Days
Continuous |
|
| 01-Nov-25 12:00 | 01-Feb-26 18:00 | ALTALINK | Outage | AML 511s ACF12 (AML 511s Crossings) | forced outage | 92.29 Days
Continuous |
|
| 03-Nov-25 07:00 | 21-Nov-25 17:00 | EPCOR | TE | EP 511s Protection & Control (EP 511s Victoria) | protection block on “A” protections for VN21 at Victoria | 18.42 Days
Continuous |
|
| 03-Nov-25 07:00 | 19-Dec-25 17:00 | EPCOR | TE | 987s Protection & Control (987s Clover Bar) | protection blocking for P&C maintenance at Cloverbar | 46.42 Days
Continuous |
|
| 04-Nov-25 09:00 | 24-Nov-25 13:00 | ATCO | TE | 741s RTU/SCADA (741s Fox Creek) | SCADA SMP being updated with new points for 7L90 RAS addition | 20.17 Days
Continuous |
|
| 04-Nov-25 10:30 | 10-Dec-25 15:00 | ATCO | TE | 710s Protection & Control (710s Vermilion) | 86-50BF-1/700BS1 secondary protection block common lockout so we can tie in new BF trips from 7L117 A&B, 7L129 A&B, 7L130 A&B | 36.19 Days
Continuous |
|
| 04-Nov-25 10:30 | 10-Dec-25 15:00 | ATCO | TE | 710s Protection & Control (710s Vermilion) | 87BA/700BS1, secondary protection, blocked for 7L129 primary injection as well as 7L117 primary injection as well as local SCADA cutover testing | 36.19 Days
Continuous |
|
| 06-Nov-25 13:00 | 18-Nov-25 17:00 | BCH | Outage | 2L113 (BCH Cranbrook - BCH Natal), T3 (BCH Natal), T4 (BCH Natal), 12CB23 (BCH Natal) | NTL substation replacement + ETM install | 12.17 Days
Continuous |
AB-BC |
| 07-Nov-25 08:00 | 18-Nov-25 16:00 | ATCO | Outage | 7L117 (706s Irish Creek - 710s Vermilion), 710s 701 (710s Vermilion), 706s 703 (706s Irish Creek) | 7L117 - A and B line protection upgrade | 11.33 Days
Continuous |
|
| 07-Nov-25 08:00 | 18-Nov-25 15:30 | ATCO | TE | 710s Protection & Control (710s Vermilion) | protection upgrade | 11.31 Days
Continuous |
|
| 07-Nov-25 10:30 | 18-Nov-25 15:00 | ATCO | TE | 710s Protection & Control (710s Vermilion) | blocking A and B of each relay for 7L117 secondary injection | 11.19 Days
Continuous |
|
| 08-Nov-25 08:00 | 16-Nov-25 15:00 | ENMAX, ALTALINK | Outage | 28.80L (42s Sarcee - SS-28), 28.2TR (SS-28), 28B138-28.80 (SS-28), 42s 28 (42s Sarcee), 28MD138-28.2TR (SS-28), SW82 (SS-28) | 28.2TR protection upgrade and SW80 replacement | 8.29 Days
Continuous |
|
| 08-Nov-25 08:00 | 16-Nov-25 15:00 | ENMAX | TE | Protection & Control (SS-28) | 28.2TR protection upgrade | 8.29 Days
Daily |
|
| 08-Nov-25 08:00 | 16-Nov-25 15:00 | ENMAX | TE | Protection & Control (SS-28) | 28 sub auto switching protection scheme outage | 8.29 Days
Daily |
|
| 08-Nov-25 08:00 | 16-Nov-25 15:00 | ENMAX, ALTALINK | IO | 28.80L (42s Sarcee - SS-28) | 28.2TR protection upgrade and SW80 replacement | 8.29 Days
Continuous |
|
| 09-Nov-25 09:00 | 15-Nov-25 14:00 | ENMAX | Outage | 41.84L (SS-41 - SS-54), 41B138-41.84 (SS-41), 54B138-41.84 (SS-54) | install three new line surge arrestors at Sub 41 and replace SW86 at Sub 41 | 6.21 Days
Continuous |
|
| 10-Nov-25 07:00 | 15-Nov-25 17:00 | EPCOR | Outage | M724 (Meadowlark) | meadowlark: m724 breaker maintenance (min oil) | 5.42 Days
Continuous |
|
| 10-Nov-25 07:00 | 19-Nov-25 17:00 | EPCOR | Outage | T3 (Rossdale), R723 (Rossdale), R724 (Rossdale), RAB3 (Rossdale) | rossdale: tx3 zone for scaffold/hoarding install | 9.42 Days
Continuous |
|
| 10-Nov-25 07:00 | 17-Nov-25 17:00 | EPCOR | TE | APS# 172 Garneau - Meadowlark Reconfiguration Scheme | blocking A RAS for MPLS upgrade | 7.42 Days
Continuous |
|
| 11-Nov-25 07:00 | 16-Nov-25 18:00 | ATCO, ALTALINK | Outage | 923L (356s Milo - 2075s Newell) | performing maintenance between structures #74 - 162 | 5.46 Days
Continuous |
|
| 11-Nov-25 07:30 | 16-Nov-25 17:30 | ALTALINK | RB | 935L (324s Cassils - 356s Milo) | crews working within close proximity on 923L | 5.42 Days
Daily |
|
| 12-Nov-25 07:30 | 21-Nov-25 17:30 | ATCO, ALTALINK | RB | 1036L (356s Milo - 554s Travers) | crews will be within close proximity on 1005L (STR 3-75) | 9.42 Days
Daily |
|
| 12-Nov-25 08:00 | 19-Nov-25 20:00 | SUNCOR | TE | 29PL6-22 (29EDD-1 Millennium - 29EDD-2 Tar Island) | 29PL6-22 A87L GE L90 firmware upgrade - 300477551 | 7.5 Days
Continuous |
|
| 12-Nov-25 08:00 | 18-Nov-25 18:00 | ALTALINK | Trans Test | 102s SVC (102s Langdon) | live commissioning | 6.42 Days
Daily |
|
| 12-Nov-25 08:00 | 17-Nov-25 16:00 | ENMAX | Outage | 20.1TR (SS-20) | maintenance | 5.33 Days
Continuous |
|
| 12-Nov-25 14:00 | 15-Nov-25 16:00 | ATCO | Outage | 7L85 (803s ATC Bullpound - 7LA85 tap) | install conductor weights 7L85 between structures 401 to 457 | 3.08 Days
Continuous |
|
| 13-Nov-25 18:00 | 24-Nov-25 12:00 | ALTALINK | Outage | 1005L (356s Milo - 1005AL tap) | repairing the inner between STR 3-75 on 1005L | 10.75 Days
Continuous |
|
| 14-Nov-25 07:00 | 19-Nov-25 18:00 | ALTALINK | Outage | 612L (336s Fincastle - 368s Burdett), 336s 612 (336s Fincastle), 368s 612 (368s Burdett) | reroute Str 153-157 for road widening | 5.46 Days
Continuous |
|
| 14-Nov-25 07:00 | 03-Dec-25 18:00 | ALTALINK | RB | 931L (28s West Brooks - 132s Ware Junction) | required for 1053L GOI due to proximity | 19.46 Days
Daily |
|
| 14-Nov-25 07:00 | 24-Nov-25 17:30 | ALTALINK | RB | 759L (87s Gaetz - 276s Prentiss) | prep structure 27-30 for the upcoming GOI and setting structures on 986L/962L near 10-21 | 10.44 Days
Daily |
|
| 14-Nov-25 08:00 | 15-Nov-25 17:00 | ATCO | RB | 6L96 (735s Swan River - 743s Sarah Lake) | add a D'back to distribution under strung | 1.38 Days
Daily |
|
| 14-Nov-25 09:30 | 03-Dec-25 18:00 | ALTALINK | Outage | 1053L (132s Ware Junction - 324s Cassils) | install ~6.8 km of new conductor for new 1075L on open side of tower opposite to 1053L on structures | 19.35 Days
Continuous |
|
| 14-Nov-25 16:00 | 23-Nov-25 11:00 | ALTALINK | IO | 714L (397s Benbow – 1117s South Kaybob) | complete work inside of 714L breaker bay | 8.79 Days
Continuous |
|
| 15-Nov-25 07:00 | 15-Nov-25 17:00 | EPCOR | TE | RTU/SCADA (Rossdale) | substation firewall replacement | 10 Hours
Continuous |
|
| 15-Nov-25 07:00 | 17-Nov-25 18:00 | ENMAX | Outage | 1.83L (SS-1 - SS-8), 8B138-3A0 (SS-8), 8B138-4A0 (SS-8) | 1 sub transmission line cut over | 2.46 Days
Continuous |
|
| 15-Nov-25 08:00 | 16-Nov-25 14:00 | ENMAX | Outage | 162B240-RB131 (SS-162), 162B240-RB132 (SS-162), 1-GSU-XF-0001 (SS-162) | HV SW Maint. 162SW133, 162SW132. | 30 Hours
Continuous |
|
| 16-Nov-25 08:00 | 16-Nov-25 16:00 | ATCO | Outage | 7L85 (804s Wintering Hills - 7LA85 tap), 804s 702 (804s Wintering Hills) | pole change for L-G clearance mitigation, install conductor weights 7L85 between structures 401 to 457 | 8 Hours
Continuous |
|
| 16-Nov-25 08:00 | 17-Nov-25 17:00 | ATCO | RB | 6L96 (735s Swan River - 743s Sarah Lake) | salvage GS S31636 A#568876 close to 6L96-133 using live line techniques | 1.38 Days
Daily |
|
| 17-Nov-25 07:00 | 25-Nov-25 17:00 | EPCOR | TE | Protection & Control (Namao) | protection blocking for NW15 line protection upgrade | 8.42 Days
Continuous |
|
| 17-Nov-25 07:00 | 23-Nov-25 17:00 | EPCOR | Outage | 814s T2 (814s Bellamy), 814s B2402 (814s Bellamy), 814s B2406 (814s Bellamy), BR722 (Rossdale) | TX2 bushing replacement and 240kv SF6 gas tests and leak checks | 6.42 Days
Continuous |
|
| 17-Nov-25 07:00 | 21-Nov-25 08:00 | ALTALINK | Outage | 409s T2 (409s Shell Scotford) | replace T2 NGR | 4.04 Days
Continuous |
|
| 17-Nov-25 07:00 | 11-Dec-25 17:00 | EPCOR | TE | 814s Protection & Control (814s Bellamy) | protection blocking, DFR commissioning | 24.42 Days
Continuous |
|
| 17-Nov-25 07:00 | 21-Nov-25 17:00 | EPCOR | TE | 72DS26 (665s Dome - Strathcona) | protection blocking for 72DS26 line protection A upgrade | 4.42 Days
Continuous |
|
| 17-Nov-25 07:30 | 24-Nov-25 16:30 | ALTALINK | RB | 913L (69s North Barrhead - 732s Mitsue) | walk up and climbing inspection | 7.38 Days
Continuous |
|
| 17-Nov-25 07:30 | 17-Nov-25 15:30 | ALTALINK | RB | 825L (77s Sagitawah - 484s Millar Western) | insulator washing on 825L | 8 Hours
Daily |
|
| 17-Nov-25 08:00 | 18-Nov-25 14:00 | ENMAX | Outage | 162B240-RB135 (SS-162), 162B240-RB134 (SS-162), 2-GSU-XF-0002 (SS-162) | HV switch maintenance 162SW143, 162SW142 | 30 Hours
Continuous |
|
| 17-Nov-25 08:00 | 20-Nov-25 17:00 | ATCO | IO | ATCO Telecom Equipment | Lanfine_S-Telecom upgrade | 3.38 Days
Continuous |
|
| 17-Nov-25 08:00 | 17-Nov-25 17:00 | SUNCOR | TE | SUNCOR DNP Outage | updating AESO Gateway and DCS gateway RTU's as per CIP requirements for live data | 9 Hours
Continuous |
|
| 17-Nov-25 08:00 | 17-Nov-25 18:00 | ENMAX | Outage | 24.82L (SS-24 - SS-65), 24.2TR (SS-24), 24B138-24.82 (SS-24), 65B138-D81 (SS-65), 65B138-D82 (SS-65), 24B138-24BT3 (SS-24) | investigate 24.82L, check reversing switch 24.2TR, surge arrestor power factor test - 65MD138-24.82, 24B138-24.82 breaker racking support install | 10 Hours
Continuous |
|
| 17-Nov-25 08:00 | 24-Nov-25 16:00 | ATCO | RB | 7L61 (780s Lubicon - 796s Nipisi) | walk up and climbing inspection | 7.33 Days
Continuous |
|
| 17-Nov-25 08:00 | 24-Nov-25 16:00 | ATCO | RB | 9L913 (69s North Barrhead - 732s Mitsue) | walk up and climbing inspection | 7.33 Days
Continuous |
|
| 17-Nov-25 08:00 | 18-Nov-25 16:00 | ENMAX | TE | Protection & Control (SS-11) | 11sub 138kV bus differential protection outage, CT terminal replacement | 1.33 Days
Daily |
|
| 17-Nov-25 08:00 | 27-Nov-25 17:00 | ALTALINK | TE | 397s RTU/SCADA (397s Benbow) | update configuration for L2 protection upgrade, AIS 1159 additions, and 43M addition | 10.38 Days
Daily |
|
| 17-Nov-25 08:00 | 21-Nov-25 17:00 | ALTALINK | TE | 312s RTU/SCADA (312s Fidler) | split breaker alarms | 4.38 Days
Daily |
|
| 17-Nov-25 08:00 | 18-Nov-25 16:00 | Syncrude | Outage | C1 (Aurora) | complete cap bank maintenance in G01 substation | 1.33 Days
Continuous |
|
| 17-Nov-25 08:00 | 17-Nov-25 17:00 | ALTALINK | TE | AltaLink Telecom Equipment, 131s RTU/SCADA (131s Moon Lake), 283s RTU/SCADA (283s Violet Grove), 235s RTU/SCADA (235s Entwistle) | 131s - 9516R radio maintenance | 9 Hours
Daily |
|
| 17-Nov-25 08:00 | 17-Nov-25 17:00 | ALTALINK | TE | AltaLink Telecom Equipment, 498s RTU/SCADA (498s Tilley) | MPLS firmware upgrade | 9 Hours
Daily |
|
| 17-Nov-25 08:00 | 20-Nov-25 17:00 | ALTALINK | TE | AltaLink Telecom Equipment, 262s RTU/SCADA (262s Rocky Mountain House) | MPLS firmware upgrade | 3.38 Days
Daily |
|
| 17-Nov-25 08:00 | 20-Nov-25 17:00 | ALTALINK | TE | 250p RTU/SCADA (250P Bighorn Plant), AltaLink Telecom Equipment | MPLS firmware upgrade | 3.38 Days
Daily |
|
| 17-Nov-25 08:00 | 20-Nov-25 17:00 | ALTALINK | TE | 482s RTU/SCADA (482s Haynes), AltaLink Telecom Equipment | MPLS firmware upgrade | 3.38 Days
Daily |
|
| 17-Nov-25 08:00 | 20-Nov-25 17:00 | ALTALINK | TE | 297s RTU/SCADA (297s Rimbey), AltaLink Telecom Equipment | MPLS firmware upgrade | 3.38 Days
Daily |
|
| 17-Nov-25 08:00 | 20-Nov-25 17:00 | ALTALINK | TE | 581s RTU/SCADA (581s Amoco Ricinus), AltaLink Telecom Equipment | MPLS firmware upgrade | 3.38 Days
Daily |
|
| 17-Nov-25 08:00 | 20-Nov-25 17:00 | ALTALINK | TE | AltaLink Telecom Equipment, 142s RTU/SCADA (142s Magcan) | MPLS firmware upgrade | 3.38 Days
Daily |
|
| 17-Nov-25 08:00 | 17-Nov-25 12:00 | ENMAX | TE | RTU/SCADA (SS-47) | 47 sub SDN project | 4 Hours
Continuous |
|
| 17-Nov-25 08:30 | 20-Nov-25 16:30 | ALTALINK | IO | 913L (69s North Barrhead - 732s Mitsue) | protection upgrade | 3.33 Days
Continuous |
|
| 17-Nov-25 08:30 | 20-Nov-25 17:00 | ALTALINK | TE | 409s Protection & Control (409s Shell Scotford) | protection outages for SCADA upgrades | 3.35 Days
Daily |
|
| 17-Nov-25 08:30 | 20-Nov-25 17:00 | ALTALINK | TE | 409s RTU/SCADA (409s Shell Scotford) | update config for new functionality on existing RTU | 3.35 Days
Daily |
|
| 17-Nov-25 09:00 | 27-Nov-25 18:00 | ALTALINK | Outage | 799L (235s Entwistle - 443s South Mayerthorpe), 235s 799N (235s Entwistle) | 799L rebuild (Str 830-858) | 10.38 Days
Continuous |
|
| 17-Nov-25 09:00 | 20-Nov-25 16:00 | ATCO, ALTALINK | Outage | 9L913 (69s North Barrhead - 732s Mitsue), 732s 903 (732s Mitsue), 732s 904 (732s Mitsue), 69s 913N (69s North Barrhead) | protection upgrade | 3.29 Days
Continuous |
|
| 17-Nov-25 09:00 | 28-Nov-25 17:30 | ALTALINK | TE | 177s RTU/SCADA (177s West Cascade) | SCADA cutover | 11.35 Days
Daily |
|
| 17-Nov-25 09:00 | 18-Nov-25 17:00 | BCH | Outage | T3 (BCH Natal), 2CB1 (BCH Natal) | NTL 2CB1 BFPN | 1.33 Days
Continuous |
AB-BC |
| 17-Nov-25 10:00 | 26-Nov-25 16:00 | ATCO | Outage | 7L106 (834s Wesley Creek - 905s Meikle) | soil around the tower footings has eroded ( tower replacement ) | 9.25 Days
Continuous |
|
| 17-Nov-25 10:00 | 26-Nov-25 16:00 | ATCO | Outage | 7L131 (834s Wesley Creek - 905s Meikle), 834s 708 (834s Wesley Creek), 834s 710 (834s Wesley Creek), 834s 7L131D2 (834s Wesley Creek) | soil around the tower footings has eroded ( Tower Replacement ) | 9.25 Days
Continuous |
|
| 17-Nov-25 10:00 | 24-Nov-25 16:00 | ATCO | Outage | 7L90 (741s ATC Fox Creek - 7LA90 tap), 741s 701 (741s ATC Fox Creek) | RAS installation and commissioning | 7.25 Days
Continuous |
|
| 17-Nov-25 10:00 | 18-Nov-25 17:00 | ALTALINK | TE | 320p Protection & Control (320P Keephills) | standard relay maintenance | 31 Hours
Daily |
|
| 17-Nov-25 10:00 | 25-Nov-25 17:00 | ALTALINK | TE | 397s Protection & Control (397s Benbow) | settings changes & testing | 8.29 Days
Daily |
|
| 17-Nov-25 10:00 | 20-Nov-25 17:00 | ATCO | RB | 7L86 (822s Wolf Lake - 1200s Foster Creek) | L-G clearance mitigation pole changes | 3.29 Days
Continuous |
|
| 17-Nov-25 11:30 | 21-Nov-25 10:30 | ALTALINK | Outage | 184s 34 (184s Petro-Canada Edmonton) | replace koncar CTs associated with 184s34 | 3.96 Days
Continuous |
|
| 17-Nov-25 11:30 | 20-Nov-25 17:00 | ALTALINK | TE | 42s Protection & Control (42s Sarcee) | protections required to isolate CTs associated with 42s7 | 3.23 Days
Daily |
|
| 17-Nov-25 11:30 | 18-Nov-25 16:30 | ALTALINK | Outage | 225s T1 (225s Magrath), 863L (225s Magrath - 891L tap), 225s 4 (225s Magrath), 225s 863 (225s Magrath) | urgent replacement of the qualitrol device for T1 | 29 Hours
Continuous |
|
| 17-Nov-25 12:00 | 28-Nov-25 18:30 | ALTALINK | Outage | 29s T2 (29s Cascade) | SCADA cutovers from T29s RTU to 177s RTU | 11.27 Days
Continuous |
|
| 17-Nov-25 12:00 | 24-Nov-25 17:00 | ATCO | TE | 951s RTU/SCADA (951s Thickwood Hills) | firmware upgrades of line protection relays and breaker fail relays for that week RTU Config changes may be required |
7.21 Days
Continuous |
|
| 17-Nov-25 12:30 | 27-Nov-25 17:30 | ALTALINK | TE | 62s RTU/SCADA (62s Brazeau Plant) | RTU database updates | 10.21 Days
Daily |
|
| 17-Nov-25 13:00 | 28-Nov-25 17:30 | ALTALINK | TE | 562s RTU/SCADA (562s Cypress) | ACC Visbility project | 11.19 Days
Daily |
|
| 17-Nov-25 13:00 | 17-Nov-25 17:00 | ALTALINK | TE | AltaLink Telecom Equipment, 498s RTU/SCADA (498s Tilley) | non-intrusive radio maintenance | 4 Hours
Daily |
|
| 17-Nov-25 14:00 | 20-Nov-25 17:00 | ENMAX, ALTALINK | Outage | 7.82L (42s Sarcee - SS-7), 42s 7 (42s Sarcee) | 42s7 CT replacement | 3.13 Days
Continuous |
|
| 17-Nov-25 14:00 | 20-Nov-25 17:00 | ENMAX, ALTALINK | RB | 7.82L (42s Sarcee - SS-7) | 42s7 CT replacement | 3.13 Days
Continuous |
|
| 18-Nov-25 07:00 | 19-Nov-25 17:00 | ATCO | TE | 951s Protection & Control (951s Thickwood Hills) | CSP needed for 900SST1 B relay for firmware upgrade and local testing | 1.42 Days
Continuous |
|
| 18-Nov-25 07:00 | 24-Nov-25 17:00 | ATCO | TE | 951s Protection & Control (951s Thickwood Hills) | breaker fail relays for firmware upgrade and local testing, 50bf/911 2. 50bf/910 3. 9L07-906 |
6.42 Days
Continuous |
|
| 18-Nov-25 08:00 | 20-Nov-25 16:00 | ENMAX | Outage | 16.61L (SS-16 - SS-27), 27B69-16.61 (SS-27), 16B69-16.61 (SS-16) | 27 sub security upgrade - security post proximity to line | 2.33 Days
Continuous |
|
| 18-Nov-25 08:00 | 18-Nov-25 17:30 | ALTALINK | TE | APS# 33 Cypress (T562s) Reverse Power and Undervoltage Scheme, 562s Protection & Control (562s Cypress) | acc visbility project, adding supervisory controls to RAS33 scheme | 9.5 Hours
Daily |
|
| 18-Nov-25 08:00 | 18-Nov-25 15:00 | ALTALINK | Outage | 312s 852 (312s Fidler) | splitting alarm contact and wiring each alarm point from breaker control cabinet to d25 in control building | 7 Hours
Daily |
|
| 18-Nov-25 08:00 | 18-Nov-25 17:00 | ATCO | TE | 732s Protection & Control (732s Mitsue) | Block 87BA/900BS1 to change alarm logic | 9 Hours
Continuous |
|
| 18-Nov-25 08:00 | 19-Nov-25 17:00 | ALTALINK | TE | 294s RTU/SCADA (294s Brazeau Outletworks), AltaLink Telecom Equipment | upgrade MPLS node | 1.38 Days
Daily |
|
| 18-Nov-25 08:00 | 19-Nov-25 17:00 | ALTALINK | TE | 207s RTU/SCADA (207s Pinedale) | RTU database updates | 1.38 Days
Daily |
|
| 18-Nov-25 08:00 | 18-Nov-25 17:00 | ALTALINK | TE | AltaLink Telecom Equipment, 562s RTU/SCADA (562s Cypress) | MPLS firmware upgrade | 9 Hours
Daily |
|
| 18-Nov-25 08:30 | 18-Nov-25 12:30 | ALTALINK, BPWF | Outage | 1097L (356s Milo – 611s Amber), 356s 1097 (356s Milo), 611s T1 (611s Amber), 611s T2 (611s Amber), 611s 52-240-1 (611s Amber), 611s 52-240-2 (611s Amber), 611s 89-B1 (611s Amber), 611s 89-T1 (611s Amber), 611s 89-T2 (611s Amber) | urgent outage for arctic arrow to make a damper repair for the customer on 1097L | 4 Hours
Continuous |
|
| 18-Nov-25 09:00 | 19-Nov-25 17:30 | ALTALINK | TE | 177s Protection & Control (177s West Cascade), 29s Protection & Control (29s Cascade) | cutover of 54L and T2 protection alarms to new 177s RTU from T29s RTU | 1.35 Days
Daily |
|
| 18-Nov-25 09:00 | 20-Nov-25 17:00 | ATCO | TE | ATCO Telecom Equipment, 2075s RTU/SCADA (2075s Newell) | med bes firewall install - outage to local network & scada communications | 2.33 Days
Continuous |
|
| 18-Nov-25 09:00 | 18-Nov-25 18:00 | ATCO | TE | ATCO Telecom Equipment, 779s RTU/SCADA (779s Chinchaga River) | chinchaga river_s-telecom- removing old vsat equipment, installing new firewall/checkpoint | 9 Hours
Continuous |
|
| 18-Nov-25 13:00 | 28-Nov-25 17:00 | BCH | Outage | T4 (BCH Natal) | natal substation replacement and etm install | 10.17 Days
Continuous |
AB-BC |
| 19-Nov-25 07:00 | 19-Nov-25 17:00 | ATCO | Outage | 7L749 (716s Lloydminster - 7LB749 tap), 716s 701 (716s Lloydminster) | 7L749 line raise span 57 | 10 Hours
Continuous |
|
| 19-Nov-25 07:00 | 20-Nov-25 17:00 | ATCO | TE | 951s Protection & Control (951s Thickwood Hills) | firmware upgrades on 94BA/900-1200BS1 (SEL-2440) and 94BA/900-1200BS1 (SEL-2440), including post upgrade commissioning | 1.42 Days
Continuous |
|
| 19-Nov-25 07:00 | 20-Nov-25 18:00 | ALTALINK | TE | AltaLink Telecom Equipment | addition of secondary MPLS node - MPLS 7705B, to provide diversity to the existing circuits | 1.46 Days
Continuous |
|
| 19-Nov-25 07:00 | 23-Nov-25 10:49 | ATCO | RB | 7L16 (766s Nevis - 948s Heatburg) | facilitate work adjacent to line for CETO project | 4.16 Days
Continuous |
|
| 19-Nov-25 07:00 | 19-Nov-25 09:00 | ALTALINK | TE | 83s Protection & Control (83s Taber) | 83s172L remote settings change | 2 Hours
Daily |
|
| 19-Nov-25 07:00 | 19-Nov-25 09:00 | ALTALINK | TE | 254s Protection & Control (254s Coaldale) | 254s172L remote settings change | 2 Hours
Daily |
|
| 19-Nov-25 08:00 | 19-Nov-25 17:00 | ATCO, ENEL | TE | ATCO Telecom Equipment, 708s RTU/SCADA (708s Grizzly Bear) | low BES firewall install - outage to Local Network & SCADA Communications |
9 Hours
Continuous |
|
| 19-Nov-25 08:00 | 19-Nov-25 17:30 | ATCO, ALTALINK | TE | APS# 27 562S Cypress McNeil Power and Undervoltage Scheme, 562s Protection & Control (562s Cypress) | ACC visibility project | 9.5 Hours
Daily |
|
| 19-Nov-25 08:00 | 21-Nov-25 20:00 | SUNCOR | TE | 29PL6-3 (29EDD-1 Millennium - 30EDD-1), 30EDD-1 627 (30EDD-1) | 29PL6-3 A87L GE L90 firmware 8.6 - 300477554 | 2.5 Days
Continuous |
|
| 19-Nov-25 08:00 | 19-Nov-25 15:00 | ALTALINK | Outage | 312s 952 (312s Fidler) | splitting alarm contact and wiring each alarm point from breaker control cabinet to D25 in control building | 7 Hours
Daily |
|
| 19-Nov-25 08:00 | 19-Nov-25 17:00 | ATCO | TE | 741s Protection & Control (741s Fox Creek) | new 7L90 RAS relays need to be connected to existing 700PT1 | 9 Hours
Continuous |
|
| 19-Nov-25 08:00 | 19-Nov-25 17:00 | ALTALINK | TE | AltaLink Telecom Equipment, 477s RTU/SCADA (477s Amoco West Pembina), 489s RTU/SCADA (489s Petro Canada Brazeau River) | upgrade MPLS node | 9 Hours
Daily |
|
| 19-Nov-25 08:00 | 19-Nov-25 17:00 | ALTALINK | TE | AltaLink Telecom Equipment, 378s RTU/SCADA (378s Shell Caroline) | 2025 MPLS firmware upgrade | 9 Hours
Daily |
|
| 19-Nov-25 09:00 | 20-Nov-25 16:00 | ATCO | TE | 939s Protection & Control (939s Livock) | relay work |
31 Hours
Continuous |
|
| 19-Nov-25 09:00 | 20-Nov-25 20:00 | SUNCOR | TE | 29EDD-2 29PT-3 (29EDD-2 Tar Island), 29EDD-2 Protection & Control (29EDD-2 Tar Island) | 29EDD-2, 29PT-3 94T-A - replacement | 1.46 Days
Continuous |
|
| 19-Nov-25 10:00 | 20-Nov-25 17:00 | ALTALINK | TE | 353s Protection & Control (353s Plamondon) | standard relay maintenance | 31 Hours
Daily |
|
| 19-Nov-25 10:00 | 21-Nov-25 17:30 | ATCO | TE | 834s Protection & Control (834s Wesley Creek), 834s RTU/SCADA (834s Wesley Creek) | 834S 7L131 21A protection communication card replacement |
2.31 Days
Continuous |
|
| 20-Nov-25 07:00 | 20-Nov-25 17:00 | ATCO | Outage | 7L42 (716s Lloydminster - 751s Hill), 751s 702 (751s Hill) | structure alterations to accommodate new development 75th Ave and 19th Street in the City of Lloydminster | 10 Hours
Continuous |
|
| 20-Nov-25 07:00 | 20-Nov-25 16:30 | ALTALINK | Outage | AML 511s T30 (AML 511s Crossings), AML 511s SVC Plus (AML 511s Crossings), AML 511s 1152 (AML 511s Crossings) | annual fire system maintenance on the SVC+ | 9.5 Hours
Daily |
|
| 20-Nov-25 07:00 | 21-Nov-25 17:00 | ATCO | TE | 951s Protection & Control (951s Thickwood Hills) | firmware upgrades on 94BA/SVS (SEL-2440) and 94BA/SVS (SEL-2440), including post upgrade commissioning | 1.42 Days
Continuous |
|
| 20-Nov-25 08:00 | 20-Nov-25 17:00 | ALTALINK | TE | APS# 112 Cypress 562s - Power/Under & Over Frequency Scheme, 562s Protection & Control (562s Cypress) | adding supervisory controls to RAS112 scheme | 9 Hours
Daily |
|
| 20-Nov-25 08:00 | 20-Nov-25 15:00 | ALTALINK | Outage | 312s 552 (312s Fidler) | splitting alarm contact and wiring each alarm point from breaker control cabinet to D25 in control building | 7 Hours
Daily |
|
| 20-Nov-25 08:00 | 24-Nov-25 16:00 | ENMAX | IO | Protection & Control (SS-1) | initial energization 1.1TR | 4.33 Days
Continuous |
|
| 20-Nov-25 08:00 | 20-Nov-25 16:00 | SUNCOR | TE | 29EDD-5 Protection & Control (29EDD-5), 30EDD-1 Protection & Control (30EDD-1) | urgent communication cabling and card swap out to correct communications issue | 8 Hours
Continuous |
|
| 20-Nov-25 08:00 | 20-Nov-25 17:00 | ALTALINK | TE | AltaLink Telecom Equipment, 242s RTU/SCADA (242s Flat Lake) | upgrade MPLS node | 9 Hours
Daily |
|
| 20-Nov-25 08:00 | 20-Nov-25 17:00 | ALTALINK | TE | AltaLink Telecom Equipment, 28s RTU/SCADA (28s West Brooks) | 2025 MPLS firmware upgrade | 9 Hours
Daily |
|
| 20-Nov-25 09:00 | 21-Nov-25 17:00 | ATCO | TE | ATCO Telecom Equipment, 767s RTU/SCADA (767s Oyen) | low BES firewall install - outage to local network & SCADA communications | 1.33 Days
Continuous |
|
| 20-Nov-25 09:00 | 20-Nov-25 17:00 | ATCO | TE | ATCO Telecom Equipment, 825s Whitefish Lake RTU/SCADA | Whitefish Lake_S_Telecom - firewall install - outage to local network & SCADA communications | 8 Hours
Continuous |
|
| 20-Nov-25 09:00 | 21-Nov-25 17:00 | BCH | IO | T4 (BCH Natal) | NTL 2CB2 BFPN, 2CT2 inspection | 1.33 Days
Continuous |
AB-BC |
| 21-Nov-25 07:00 | 22-Nov-25 17:00 | ATCO | TE | 951s Protection & Control (951s Thickwood Hills) | firmware upgrades on 87VB-51B-27B-59B/920C (SEL-487V) and 51-27-59/920C (SEL-351S) including post upgrade commissioning | 1.42 Days
Continuous |
|
| 21-Nov-25 07:00 | 25-Nov-25 18:00 | NWE, BHE Canada, BHE | Outage | Hay Lake (NorthWestern Energy) - Marias (MATL), North Series Capacitor (BHE Hay Lake), Marias Shunt Capacitor, 2302 (NWE Marias), 2305 (NWE Marias) | string wire into Marias from new Glacier sub and install new airbreaks | 4.46 Days
Continuous |
AB-MATL |
| 21-Nov-25 08:00 | 02-Dec-25 21:00 | SUNCOR | TE | 29EDD-94 29-952-9707 (29EDD-94 Voyageur), 29EDD-94 29-952-9708 (29EDD-94 Voyageur), 29EDD-94 29-952-9709 (29EDD-94 Voyageur), 29EDD-94 29-952-9710 (29EDD-94 Voyageur), 29EDD-94 29-952-9711 (29EDD-94 Voyageur), 29EDD-94 29-952-9712 (29EDD-94 Voyageur) | perform rolling regulatory GE C60 firmware 8.6 updates on the following breakers at 29EDD-94 - 952-9707/9708/9709/9712/9711/9710 | 11.54 Days
Continuous |
|
| 21-Nov-25 08:00 | 21-Nov-25 17:30 | ALTALINK | TE | 678s RTU/SCADA (678s Okotoks) | major SCADA upgrade project.-replacement of D20 RTU with new SG-4260 data concentrator, deficiency cleanup and complete points check | 9.5 Hours
Daily |
|
| 21-Nov-25 08:00 | 24-Nov-25 16:00 | ENMAX | IO | Protection & Control (SS-1) | Initial energization 1.2TR | 3.33 Days
Continuous |
|
| 21-Nov-25 08:00 | 24-Nov-25 16:00 | ENMAX | IO | Protection & Control (SS-1) | initial energization 1.3TR | 3.33 Days
Continuous |
|
| 21-Nov-25 08:00 | 24-Nov-25 16:00 | ENMAX | IO | Protection & Control (SS-1) | initial energization 1.4TR | 3.33 Days
Continuous |
|
| 21-Nov-25 08:00 | 24-Nov-25 16:00 | ENMAX | IO | Protection & Control (SS-1) | initial energization new 1 sub diameter Q01, Q02, Q03, Q04 Z32 Bus 138kV, Z31 Bus 138kV | 3.33 Days
Continuous |
|
| 21-Nov-25 08:00 | 21-Nov-25 17:30 | ALTALINK | TE | 678s Protection & Control (678s Okotoks) | major SCADA upgrade project-replacement of D20 RTU with new SG-4260 data concentrator and deficiency cleanup | 9.5 Hours
Daily |
|
| 21-Nov-25 08:00 | 21-Nov-25 12:00 | ENMAX | Outage | 3.3TR (SS-3) | oil sampling - 3.3-TC, MT snd Silica Gel Canister upgrade - 3.3 TR - MT | 4 Hours
Continuous |
|
| 21-Nov-25 08:00 | 20-Dec-25 16:00 | ENMAX | Outage | 38.3TR (SS-38) | 38.3TR secondary cable replacement | 29.33 Days
Continuous |
|
| 21-Nov-25 08:30 | 21-Nov-25 17:30 | ALTALINK | Outage | 678s T2 (678s Okotoks), 678s 452 (678s Okotoks) | completing deficiencies on T2 OLTC SCADA controls | 9 Hours
Daily |
|
| 21-Nov-25 09:00 | 24-Nov-25 16:00 | ATCO | Outage | 9L56 (720s Wabasca - 732s Mitsue), 732s 904 (732s Mitsue), 732s 906 (732s Mitsue) | protection upgrade | 3.29 Days
Continuous |
|
| 21-Nov-25 09:00 | 21-Nov-25 13:00 | ATCO | RB | 7L63 (780s Lubicon - 812s Norcen), 7L63 (788s Hotchkiss - 7LA63 tap) | high load move lift bottom phase | 4 Hours
Continuous |
|
| 21-Nov-25 09:00 | 21-Nov-25 15:06 | BCH | Outage | 2CB2 (BCH Nelway) | 5CB13 CN PM BC maintenance does not affect the Alberta ATC | 6.1 Hours
Continuous |
AB-BC |
| 21-Nov-25 09:30 | 21-Nov-25 18:00 | ATCO | Outage | 7L65 (710s Vermilion - 7LA65 tap), 710s 703 (710s Vermilion) | relocate breaker 703 controls to a new smaller mounting plate | 8.5 Hours
Continuous |
|
| 21-Nov-25 11:00 | 21-Nov-25 15:00 | ATCO | RB | 7L23 (732s Mitsue - 7L23 tap), 7L23 (796s Nipisi - 7L23 tap) | high load move lift bottom phase 2 locations - 7L23-212 & 7L23-440 | 4 Hours
Continuous |
|
| 21-Nov-25 18:00 | 23-Nov-25 08:00 | ENMAX, ALTALINK | IO | 936L (5s East Calgary - 102s Langdon) | crew working in vicinity of 937L | 1.58 Days
Continuous |
|
| 21-Nov-25 18:00 | 23-Nov-25 08:00 | ENMAX, ALTALINK | Outage | 937L (5s East Calgary - 102s Langdon) | re-conductor between str 15 to 18 on both circuits for line clearance mitigation | 1.58 Days
Continuous |
|
| 21-Nov-25 18:00 | 23-Nov-25 08:00 | ENMAX, ALTALINK | Outage | 936L (5s East Calgary - 102s Langdon) | crew working in vicinity of 937L | 1.58 Days
Continuous |
|
| 21-Nov-25 18:00 | 23-Nov-25 08:00 | ENMAX, ALTALINK | IO | 937L (5s East Calgary - 102s Langdon) | re-conductor between str 15 to 18 on both circuits for line clearance mitigation | 1.58 Days
Continuous |
| This document and the information contained herein are based upon information and data which by their nature contain a degree of uncertainty and are subject to change. In addition, this document may contain information and data from public sources and/or third parties, which have been assumed to be accurate and complete and have not been verified. Accordingly, the Independent System Operator, operating as the Alberta Electric System Operator (the "AESO") makes no warranty, representation or guarantee, express or implied, with respect to this document or the information contained herein, including, but not limited to, any warranty, representation or guarantee of accuracy, completeness, timeliness, reliability, availability, absence of computer virus, non- infringement, merchantability or suitability for any purpose. Under no circumstances will the AESO, its members, officers, employees, contractors or agents, or any of their respective affiliates, be liable for any errors or omissions in, or any losses, damages or claims whatsoever, whether in contract, tort or otherwise, arising from use of or reliance upon, this document or any information contained herein. © 2009 Alberta Electric System Operator. All rights reserved |