| Alberta Electric System Operator | |
| System Co-ordination Plan | |
| 2026-04-23 to 2026-05-01 | |
| Approved Outages |
| Previous Version | |
| Download CSV |
| From | To | Owner | Type | Element | Scheduled Activity | Date/Time Comments | Interconnection |
|---|---|---|---|---|---|---|---|
| 26-Jul-24 10:00 | 31-Jul-26 16:00 | ATCO | Outage | 826s 504R (826s Marguerite Lake) | emergency removal to replace failed 502R @834S | 735.25 Days
Continuous |
|
| 23-Aug-24 13:45 | 21-May-26 14:29 | ALTALINK | Outage | 157s C1 (157s Lac La Biche) | forced outage | 636.03 Days
Continuous |
|
| 20-Mar-25 08:00 | 29-May-26 17:00 | ALTALINK | Outage | 256s C1 (256s Harmattan) | forced outage | 435.38 Days
Continuous |
|
| 31-Mar-25 07:00 | 01-May-26 17:00 | EPCOR | TE | Protection & Control (Woodcroft) | Woodcroft: protection blocking for merging unit and protection upgrade. | 396.42 Days
Continuous |
|
| 12-Sep-25 08:00 | 19-Jun-26 16:00 | ENMAX | Outage | 33.1TR (SS-33) | tap changer refurbishments. soak test required | 280.33 Days
Continuous |
|
| 25-Nov-25 17:46 | 18-Sep-26 18:00 | ATCO | Outage | 876s 901T (876s Brintnell) | forced outage oil leaking | 296.97 Days
Continuous |
|
| 27-Nov-25 08:30 | 27-Nov-27 16:30 | ALTALINK | TE | 89s Protection & Control (89s Ellerslie) | DSP card replacements on1057L B87/L3 and B240B1 B87/240B1 | 730.33 Days
Daily |
|
| 04-Jan-26 08:00 | 02-Sep-26 16:00 | SUNCOR | Outage | 29EDD-34 260kV Bus 29PP-45 (29EDD-34), 29EDD-34 29-952-113 (29EDD-34), 29EDD-34 29PS-216 (29EDD-34) | urgent repairs on 29PT-224 at 29EDD34 on 29PP-45 bus | 241.29 Days
Continuous |
|
| 12-Jan-26 07:00 | 03-Jul-26 17:00 | EPCOR | TE | 330p Protection & Control (330p Genesee) | protect blocking, annual relay maintenance and password changes | 172.38 Days
Continuous |
|
| 12-Jan-26 07:00 | 01-May-26 17:00 | EPCOR | TE | Protection & Control (Rossdale) | protection blocking, relay maintenance | 109.38 Days
Continuous |
|
| 17-Jan-26 11:00 | 30-Apr-26 17:00 | BHE Canada | Outage | 120s C2 (120s Picture Butte) | forced outage | 103.21 Days
Continuous |
|
| 21-Jan-26 08:00 | 30-Oct-26 16:00 | ENMAX | Outage | 5.7TR (SS-5) | 25kV switchgear replacement | 282.29 Days
Continuous |
|
| 03-Feb-26 09:00 | 30-Jun-26 17:00 | ATCO | TE | 972s RTU/SCADA (972s Tinchebray) | config changes needed throughout the CETO project | 147.29 Days
Continuous |
|
| 09-Feb-26 09:00 | 26-Jun-26 17:00 | ATCO | TE | 972s Protection & Control (972s Tinchebray) | block all 50BF protection until cutovers and associated commissioning are complete | 137.29 Days
Continuous |
|
| 06-Mar-26 17:00 | 13-Nov-26 17:00 | EPCOR | Outage | T1 (Woodcroft) | woodcroft: TX1 LCR civil | 252 Days
Continuous |
|
| 10-Mar-26 10:00 | 30-Nov-26 17:00 | ATCO | TE | 743s RTU/SCADA (743s Sarah Lake) | throughout the course of the project, different apparatus are being replaced, RTU will be blocked prior to download | 265.33 Days
Continuous |
|
| 11-Mar-26 13:45 | 26-Apr-26 16:00 | ALTALINK | Outage | 535s C1 (535s Joffre) | breaker maintenance | 46.09 Days
Continuous |
|
| 13-Mar-26 16:00 | 24-Apr-26 17:00 | ATCO | Outage | 7L122 (791s Rainbow Lake - 930s Arcenciel), 791s 701 (791s Rainbow Lake) | phase replacement | 42.04 Days
Continuous |
|
| 22-Mar-26 13:00 | 30-Jun-26 17:00 | BHE Canada | Outage | 120s C1 (120s Picture Butte), 120s C2 (120s Picture Butte) | forced outage | 100.17 Days
Continuous |
|
| 28-Mar-26 12:00 | 14-May-26 17:00 | ATCO | TE | 833s RTU/SCADA (833s Mariana) | updating RTU/station controller configuration during SCADA upgrade project | 47.21 Days
Continuous |
|
| 30-Mar-26 08:30 | 04-May-26 16:30 | ALTALINK | Outage | 62s T1 (62s Brazeau Plant), 62s 1 (62s Brazeau Plant) | maintenance | 35.33 Days
Continuous |
|
| 06-Apr-26 07:00 | 01-May-26 17:00 | EPCOR | Outage | 72JM18 (EP 805s Jasper - Meadowlark), T1 (Meadowlark), M721 (Meadowlark), M722 (Meadowlark), EP 805s J722 (EP 805s Jasper), EP 805s JDS29 (EP 805s Jasper), MAB1 (Meadowlark) | Meadowlark - T1 LCR demo | 25.42 Days
Continuous |
|
| 06-Apr-26 08:00 | 19-Jun-26 16:00 | ALTALINK | TE | 37s RTU/SCADA (37s North Calder) | RTU database updates | 74.33 Days
Continuous |
|
| 08-Apr-26 07:00 | 10-May-26 17:00 | ALTALINK, ALPAC | IO | 796L (282s Grassland - 796AL tap) | note for area assessments | 32.42 Days
Continuous |
|
| 09-Apr-26 17:01 | 13-May-26 07:00 | EPCOR | Outage | 72RW3 (Rossdale - Woodcroft), RW727 (Rossdale) | termination rebuild at the Woodcroft end | 33.58 Days
Continuous |
|
| 13-Apr-26 07:00 | 29-May-26 17:00 | EPCOR | Outage | 805s T4 (805s Jasper) | bushing replacement and fan repair | 46.42 Days
Continuous |
|
| 13-Apr-26 08:00 | 24-Apr-26 15:00 | CMH | TE | MHS-7 Protection & Control (MHS-7 Brier Park) | preventative maintenance | 11.29 Days
Continuous |
|
| 13-Apr-26 09:00 | 23-Apr-26 17:00 | BCH | RB | 2L294 (BCH A. A. Lambert - BCH Cranbrook), 2L294 (BCH A. A. Lambert - BCH Nelway) | ANRP for tree removal | 10.33 Days
Daily |
AB-BC |
| 13-Apr-26 09:00 | 21-May-26 10:00 | ALTALINK | Outage | 157s C1 (157s Lac La Biche) | replace breaker and disconnect switch | 38.04 Days
Continuous |
|
| 14-Apr-26 07:00 | 27-Apr-26 17:00 | EPCOR | Outage | 330p 500kV Bus 2 (330p Genesee), 330p 12TC2 (330p Genesee), 330p 1209 (330p Genesee), 330p 1206 (330p Genesee), 330p 1203 (330p Genesee), 330p 1211 (330p Genesee), 330p 1215 (330p Genesee), 330p 12TC2D (330p Genesee), 330p 809 (330p Genesee) | Genesee 500 kV bus 2, POW project installation | 13.42 Days
Continuous |
|
| 16-Apr-26 07:00 | 29-Apr-26 17:00 | EPCOR | Outage | 330P GT7 (330p Genesee), 330p 1215 (330p Genesee), 330p 1214 (330p Genesee) | POW project installation | 13.42 Days
Continuous |
|
| 16-Apr-26 07:00 | 29-Apr-26 17:00 | EPCOR | Outage | 330P GT7 (330p Genesee) | POW project installation | 13.42 Days
Continuous |
|
| 17-Apr-26 08:00 | 28-Apr-26 16:00 | ENMAX | Outage | 3.82L (SS-3 - SS-8), 3B138-3.82 (SS-3) | City of Calgary traffic light rebuild | 11.33 Days
Continuous |
|
| 17-Apr-26 08:00 | 26-Apr-26 16:00 | Syncrude | Outage | 1834 (Syncrude Mildred Lake), 1835 (Syncrude Mildred Lake), Mildred T18 (Syncrude Mildred Lake) | T18 6-year maintenance | 9.33 Days
Continuous |
|
| 20-Apr-26 07:00 | 24-Apr-26 17:00 | EPCOR | Outage | T2 (Kennedale), K723 (Kennedale), K722 (Kennedale), KAB2 (Kennedale) | transformer T2 relay maintenance | 4.42 Days
Continuous |
|
| 20-Apr-26 07:00 | 26-Apr-26 17:00 | EPCOR | Outage | T2 (Strathcona), S722 (Strathcona), S723 (Strathcona), SAB2 (Strathcona) | transformer T2 doble and disconnect maintenance | 6.42 Days
Continuous |
|
| 20-Apr-26 07:00 | 01-May-26 17:00 | EPCOR | Outage | T4 (Rossdale), R724 (Rossdale), RR729 (Rossdale), RAB4 (Rossdale) | transformer T4 zone doble, repairs | 11.42 Days
Continuous |
|
| 20-Apr-26 07:00 | 23-Apr-26 17:00 | ALTALINK | TE | 87s RTU/SCADA (87s Gaetz) | SCADA RTU configuration update for CETO project | 3.42 Days
Continuous |
|
| 20-Apr-26 07:00 | 30-Apr-26 18:00 | ALTALINK | RB | 974L (39s Bickerdike - 310p Sundance) | transmission line maintenance | 10.46 Days
Continuous |
|
| 20-Apr-26 07:00 | 30-Apr-26 18:00 | ALTALINK | RB | 973L (39s Bickerdike - 310p Sundance) | transmission line maintenance | 10.46 Days
Continuous |
|
| 20-Apr-26 07:00 | 23-Apr-26 17:00 | ALTALINK | TE | 275s RTU/SCADA (275s Jenner) | update RTU configuration for 944L line protections | 3.42 Days
Continuous |
|
| 20-Apr-26 07:00 | 23-Apr-26 17:00 | ALTALINK | TE | 132s RTU/SCADA (132s Ware Junction) | update RTU configuration 944L line protection | 3.42 Days
Continuous |
|
| 20-Apr-26 07:00 | 23-Apr-26 17:00 | ALTALINK | TE | 1080s RTU/SCADA (1080s Raptor) | RTU configuration update for 944L protection | 3.42 Days
Continuous |
|
| 20-Apr-26 07:00 | 08-May-26 17:00 | EPCOR | TE | Protection & Control (Kennedale) | protection blocking - relay maintenance | 18.42 Days
Continuous |
|
| 20-Apr-26 07:00 | 08-May-26 17:00 | EPCOR | TE | 72CN10 (987s Clover Bar - Namao) | protection blocking - MPLS upgrade | 18.42 Days
Continuous |
|
| 20-Apr-26 07:00 | 08-May-26 17:00 | EPCOR | TE | 72CH11 (987s Clover Bar - EP Hardisty) | protection blocking - MPLS upgrade | 18.42 Days
Continuous |
|
| 20-Apr-26 07:00 | 08-May-26 17:00 | EPCOR | TE | 72CH9 (987s Clover Bar - EP Hardisty) | protection blocking - MPLS upgrade | 18.42 Days
Continuous |
|
| 20-Apr-26 07:00 | 08-May-26 17:00 | EPCOR | TE | 72KN23 (Kennedale - Namao) | protection blocking - MPLS upgrade | 18.42 Days
Continuous |
|
| 20-Apr-26 07:15 | 23-Apr-26 16:45 | ALTALINK | Outage | 898L (37s North Calder - 92s Viscount), 37s 898 (37s North Calder), 92s 898 (92s Viscount) | protection upgrade (37s898) | 3.4 Days
Continuous |
|
| 20-Apr-26 08:00 | 30-Apr-26 16:00 | ALTALINK | TE | 87s Protection & Control (87s Gaetz) | setting and wiring change | 10.33 Days
Continuous |
|
| 20-Apr-26 08:00 | 23-Apr-26 16:00 | ATCO | RB | 7L60 (780s Lubicon - 827s Cranberry Lake) | walk up and climbing inspection | 3.33 Days
Continuous |
|
| 20-Apr-26 08:00 | 23-Apr-26 16:00 | ALTALINK | TE | 1080s Protection & Control (1080s Raptor) | protection outages on 944AL A and B protection relays to test new SCN point for differential protection fail | 3.33 Days
Continuous |
|
| 20-Apr-26 08:00 | 23-Apr-26 16:00 | ALTALINK | TE | 132s Protection & Control (132s Ware Junction) | protection outage on 944L A and B line protection relays to test new differential protection fail SCN points | 3.33 Days
Continuous |
|
| 20-Apr-26 08:00 | 23-Apr-26 16:00 | ALTALINK | TE | 275s Protection & Control (275s Jenner) | 944L A and B line protection outages, testing of new differential protection fail SCN point | 3.33 Days
Continuous |
|
| 20-Apr-26 08:00 | 24-Apr-26 16:00 | ENMAX | Outage | 8.1TR (SS-8) | transformer power factor test, secondary cable test , transformer maintenance, relay fault pressure test, reversing switch check - 8.1-TC | 4.33 Days
Continuous |
|
| 20-Apr-26 08:00 | 23-Apr-26 16:00 | ALTALINK | TE | 37s Protection & Control (37s North Calder) | relay settings change | 3.33 Days
Continuous |
|
| 20-Apr-26 08:00 | 23-Apr-26 16:00 | ALTALINK | TE | 92s Protection & Control (92s Viscount) | relay settings change | 3.33 Days
Continuous |
|
| 20-Apr-26 08:00 | 23-Apr-26 16:00 | ALTALINK | TE | 92s RTU/SCADA (92s Viscount) | RTU database update | 3.33 Days
Continuous |
|
| 20-Apr-26 09:00 | 27-Apr-26 17:00 | ATCO, PWLP | TE | 973s Protection & Control (973s Lanes Lake), 973s RTU/SCADA (973s Lanes Lake) | 9LA93 protection updates and testing | 7.33 Days
Continuous |
|
| 20-Apr-26 09:00 | 27-Apr-26 17:00 | ATCO | TE | 972s Protection & Control (972s Tinchebray) | 9L93 protection setting changes including updates at 973s and 615s | 7.33 Days
Continuous |
|
| 20-Apr-26 09:00 | 24-Apr-26 17:00 | BCH | Outage | 5L98 (BCH Nicola - BCH Vaseux Lake) | replace emergent broken insulators | 4.33 Days
Continuous |
AB-BC |
| 20-Apr-26 09:00 | 08-May-26 17:00 | BCH | Outage | 5L98 (BCH Nicola - BCH Vaseux Lake) | replace spacer damper and insulator, BC maintenance does not affect the Alberta ATC | 18.33 Days
Continuous |
AB-BC |
| 20-Apr-26 09:00 | 23-Apr-26 17:00 | BCH | TE | Protection & Control (BCH Natal) | installing new cards in the NTLDCS002 SY DACS | 3.33 Days
Continuous |
AB-BC |
| 20-Apr-26 10:00 | 24-Apr-26 16:00 | ATCO | TE | 951s RTU/SCADA (951s Thickwood Hills) | configuration changes, computer patching | 4.25 Days
Continuous |
|
| 20-Apr-26 11:00 | 23-Apr-26 15:00 | ATCO | Outage | 6L02 (765s Mannix Mine - 873s Marion Lake) | climbing inspection on 6L02 | 3.17 Days
Continuous |
|
| 20-Apr-26 11:30 | 23-Apr-26 17:00 | ALTALINK | TE | 379s Protection & Control (379s Shell Canada Waterton) | DSP card replacement and firmware upgrades on GE relays | 3.23 Days
Continuous |
|
| 20-Apr-26 12:00 | 24-Apr-26 17:00 | ATCO | Outage | 813s SVC (813s Little Smoky), 813s 719 (813s Little Smoky) | SVC maintenance | 4.21 Days
Continuous |
|
| 20-Apr-26 14:31 | 23-Apr-26 17:00 | ATCO | Outage | 951s 920C (951s Thickwood) | 920C cap at 951s Thickwood unavailable, forced outage | 3.1 Days
Continuous |
|
| 21-Apr-26 08:00 | 23-Apr-26 08:00 | ALTALINK | Outage | 244s C1 (244s Bowmanton) | replace secondary control fuses in breaker control cabinet
|
2 Days
Continuous |
|
| 21-Apr-26 08:00 | 23-Apr-26 08:00 | ALTALINK | Outage | 244s C2 (244s Bowmanton) | replace control fuses within breaker secondary cabinet
|
2 Days
Continuous |
|
| 21-Apr-26 08:00 | 23-Apr-26 08:00 | ALTALINK | Outage | 244s C3 (244s Bowmanton) | replace secondary control fuses in breaker control cabinet
|
2 Days
Continuous |
|
| 21-Apr-26 08:00 | 24-Apr-26 16:00 | ALTALINK | TE | 618s Protection & Control (618s Riverbend) | move relay to new city of Lethbridge communication system | 3.33 Days
Continuous |
|
| 21-Apr-26 08:00 | 24-Apr-26 17:00 | Lethbridge | TE | 111s Protection & Control (111s Coalbanks), 674s Protection & Control (674s Bowron) | protection outages on 111s and 674s 725LE 'A' & 'B' protections to transfer TPR (teleprotection) circuits from existing JMUX to new SEL ICON | 3.38 Days
Continuous |
|
| 21-Apr-26 08:00 | 23-Apr-26 14:00 | ATCO | RB | 7L137 (768s Rowley - 770s Three Hills) | climbing inspection on 7L137 | 2.25 Days
Continuous |
|
| 21-Apr-26 08:00 | 24-Apr-26 17:00 | SUNCOR | Outage | 635EDD-1001 635PT-1037 (635EDD-1001) | transformer's second side equipment maintenance | 3.38 Days
Continuous |
|
| 21-Apr-26 08:30 | 23-Apr-26 16:00 | ALTALINK | TE | 394s RTU/SCADA (394s Empress) | replace T3 metering equipment | 2.31 Days
Continuous |
|
| 21-Apr-26 09:00 | 26-Apr-26 17:00 | ATCO, CapitalPower, PWLP | Outage | 9L93 (972s Tinchebray - 9L93 tap), 9LA93 (973s Lanes Lake - 9L93 tap), 972s 904 (972s Tinchebray), 972s 905 (972s Tinchebray), 615s 52T1 (615s Halkirk), 973s 52-240 (973s Lanes Lake), 615s 9L93D2 (615s Halkirk), 972s 9L93D1 (972s Tinchebray), 973s 89-L1 (973s Lanes Lake) | cutover and commission 9L93 protection | 5.33 Days
Continuous |
|
| 21-Apr-26 09:00 | 23-Apr-26 16:00 | ALTALINK | Outage | 394s T3 (394s Empress), 394s 36 (394s Empress) | 394sT3 CT7 replacement, cable repair | 2.29 Days
Continuous |
|
| 21-Apr-26 13:00 | 23-Apr-26 12:00 | REDDEER | Outage | 217s T2 (217s North Red Deer) | transformer protection relay replacement | 1.96 Days
Continuous |
|
| 21-Apr-26 15:00 | 06-May-26 09:00 | ALTALINK | Outage | 1182s 138kV Bus 1 (1182s Berland River), 620L (1182s Berland River - 328s Pine Creek), 1182s T1 (1182s Berland River), 1182s C1 (1182s Berland River), 1182s C2 (1182s Berland River), 328s 620 (328s Pine Creek), 1182s 152 (1182s Berland River) | complete 620L and energize new 1182s, close 620L ope point 'A', 1182s cap bank testing, soak 1182s T1 for 24 hours, load pickup | 14.75 Days
Continuous |
|
| 21-Apr-26 15:00 | 03-May-26 18:00 | ALTALINK | IO | 1182s 4 (1182s Berland River) | complete commissioning on 1182s8 | 12.13 Days
Continuous |
|
| 22-Apr-26 08:00 | 08-May-26 16:00 | ALTALINK | TE | 328s RTU/SCADA (328s Pine Creek) | RTU updates for changes involving 620L P&C equipment | 16.33 Days
Continuous |
|
| 22-Apr-26 08:00 | 08-May-26 16:00 | ALTALINK | TE | 328s Protection & Control (328s Pine Creek) | circuit modification and testing involving 620L P&C equipment | 16.33 Days
Continuous |
|
| 22-Apr-26 08:00 | 23-Apr-26 16:00 | ENMAX | Outage | 40.2TR (SS-40) | tap changer inspection, reversing switch check, tap changer oil filtration maintenance, oil sampling MT, TC | 1.33 Days
Continuous |
|
| 22-Apr-26 09:30 | 05-May-26 16:30 | ATCO, ALTALINK | IO | 6L126 (743s Sarah Lake - 515L tap), 126L1 (6L126 tap) | 743S Sarah Lake rebuild and replace H-Frame structure and 72 kV switches | 13.29 Days
Continuous |
|
| 22-Apr-26 10:00 | 05-May-26 16:00 | ATCO, ALTALINK | Outage | 743s 72kV Bus 600BS1 (743s Sarah Lake), 6L126 (743s Sarah Lake - 515L tap), 6L96 (735s Swan River - 743s Sarah Lake), 6L11 (743s Sarah Lake - 854s Swan Dive), 743s 705 (743s Sarah Lake), 743s 601 (743s Sarah Lake), 743s 603 (743s Sarah Lake), 743s 604 (743s Sarah Lake), 743s 605 (743s Sarah Lake), 743s 501 (743s Sarah Lake), 735s 604 (735s Swan River) | 743S Sarah Lake rebuild, 72 kV bus outage and replace wood H-Frame structure and 72 kV switches | 13.25 Days
Continuous |
|
| 23-Apr-26 03:30 | 23-Apr-26 06:30 | ALTALINK | Outage | 62s T2 (62s Brazeau Plant) | maintenance | 3 Hours
Continuous |
|
| 23-Apr-26 07:00 | 23-Apr-26 19:00 | ALTALINK | Outage | 404s T1 (404s Peace Butte) | 404s T1 maintenance | 12 Hours
Continuous |
|
| 23-Apr-26 07:00 | 23-Apr-26 17:00 | EPCOR | TE | RTU/SCADA (Rossdale) | emergency RTU outage, repair label issue and re-commission | 10 Hours
Continuous |
|
| 23-Apr-26 07:30 | 23-Apr-26 12:30 | ALTALINK | Outage | 87s 952 (87s Gaetz) | demo 1652 and 2352 breaker fail trips from the 87s952 trip chain | 5 Hours
Continuous |
|
| 23-Apr-26 08:00 | 23-Apr-26 17:00 | ALTALINK | TE | 331s RTU/SCADA (331s Ponoka), AltaLink Telecom Equipment | firmware upgrade on MPLS node A, firewall upgrade
|
9 Hours
Continuous |
|
| 23-Apr-26 08:00 | 23-Apr-26 16:00 | ENMAX, ALTALINK | Outage | 5s C3 (5s East Calgary), 5s C4 (5s East Calgary) | HV switch Maintenance 2-5S7E | 8 Hours
Continuous |
|
| 23-Apr-26 08:00 | 24-Apr-26 16:00 | ENMAX | Outage | 16.63L (SS-16 - SS-36), 36.5TR (SS-36), 16B69-16.63 (SS-16), 36B69-16.63/36.5TR (SS-36) | HV breaker maintenance | 1.33 Days
Continuous |
|
| 23-Apr-26 08:00 | 23-Apr-26 16:00 | ENMAX, ALTALINK | IO | 5s C3 (5s East Calgary), 5s C4 (5s East Calgary) | ENMAX HV switch maintenance 2-5S7E | 8 Hours
Continuous |
|
| 23-Apr-26 08:00 | 24-Apr-26 16:00 | ENMAX | Outage | 3.82L (SS-3 - SS-8), 3.3TR (SS-3), 3MD138-3.3TR (SS-3), SW83 (SS-3) | power factor test - 3PT138-Z31, 3.3TR MD needs adjustments | 1.33 Days
Continuous |
|
| 23-Apr-26 08:00 | 23-Apr-26 18:00 | ATCO | IO | ATCO Telecom Equipment | non redundant firewall replacement | 10 Hours
Continuous |
|
| 23-Apr-26 08:00 | 23-Apr-26 17:00 | ATCO | IO | ATCO Telecom Equipment | Vegreville_T(SCC)-Telecom- Vegreville tower upgrading dynamic load rating server | 9 Hours
Continuous |
|
| 23-Apr-26 08:01 | 23-Apr-26 16:00 | ALTALINK | Trans Test | 244s C2 (244s Bowmanton) | energize C2 to update SEL protective relay KSET value with real world data | 7.98 Hours
Continuous |
|
| 23-Apr-26 09:00 | 23-Apr-26 16:00 | ATCO | TE | ATCO Telecom Equipment | flashcard failure replacement, link facing Whitecourt |
7 Hours
Continuous |
|
| 23-Apr-26 09:00 | 24-Apr-26 17:00 | BCH | Outage | 5L98 (BCH Nicola - BCH Vaseux Lake) | 5CB51 rebuild | 1.33 Days
Continuous |
AB-BC |
| 23-Apr-26 09:00 | 23-Apr-26 16:30 | ATCO | TE | 832s RTU/SCADA (832s Blumenort) | SCADA updates for EPSS alarm and control | 7.5 Hours
Continuous |
|
| 23-Apr-26 09:00 | 23-Apr-26 10:00 | ATCO | TE | ATCO Telecom Equipment, 796s RTU/SCADA (796s Nipisi) | Nipisi_T-Telecom - upgrading NIPISI sub SAR OS to V21, then V22 | 60 Mins
Continuous |
|
| 23-Apr-26 09:30 | 23-Apr-26 16:00 | ALTALINK | Outage | 54s T3 (54s Fort Saskatchewan) | 25 kV breaker maintenance | 6.5 Hours
Continuous |
|
| 23-Apr-26 10:00 | 23-Apr-26 14:00 | ATCO | Outage | 789s 705R (789s Keg River) | PRC trip coil testing | 4 Hours
Continuous |
|
| 23-Apr-26 10:00 | 23-Apr-26 16:00 | ATCO | Outage | 7L56 (725s Goose River - 813s Little Smoky) | splicing bird cage conductor causing outage on 7L56 | 6 Hours
Continuous |
|
| 23-Apr-26 12:00 | 23-Apr-26 17:00 | ATCO | TE | 972s Protection & Control (972s Tinchebray) | 9L93 relays require new PT connections to accommodate CETO upgrade | 5 Hours
Continuous |
|
| 23-Apr-26 12:30 | 23-Apr-26 17:30 | ALTALINK | Outage | 87s 1052 (87s Gaetz) | demo 1252 and 2352 breaker fail trips from the 87s1052 trip chain | 5 Hours
Continuous |
|
| 23-Apr-26 13:00 | 24-Apr-26 13:00 | ATCO | TE | 832s RTU/SCADA (832s Blumenort) | investigate 832S Blumenort SCADA configuration issues |
24 Hours
Continuous |
|
| 23-Apr-26 14:01 | 24-Apr-26 16:00 | ATCO | Outage | 789s 706C (789s Keg River) | PRC trip coil testing | 25.98 Hours
Continuous |
|
| 24-Apr-26 07:00 | 24-Apr-26 17:00 | ALTALINK, REDDEER | Outage | 464L (87s Gaetz - 209s Timberlands), 209s 464E (209s Timberlands) | replace damaged/broken insulator for 1 structure 13 | 10 Hours
Continuous |
|
| 24-Apr-26 07:00 | 04-May-26 17:00 | ALTALINK | Outage | 238s T1 (238s Shell Harmattan) | maintenance | 10.42 Days
Continuous |
|
| 24-Apr-26 07:00 | 25-Apr-26 17:00 | ALTALINK | Outage | 113L (20s Ghost - 33s Spray), 20s 113 (20s Ghost), 33s 113 (33s Spray) | urgent outage to replace structure 113L154 | 1.42 Days
Continuous |
|
| 24-Apr-26 07:30 | 24-Apr-26 16:30 | ALTALINK | RB | 778L (87s Gaetz - 217s North Red Deer) | working within close proximity on 464L | 9 Hours
Continuous |
|
| 24-Apr-26 07:30 | 25-Apr-26 16:30 | ALTALINK | RB | 3L (245s Seebe - 3AL tap), 3AL (43s Jumping Pound Junction - 3L tap), 3L (272s Springbank - 3AL tap), 3L (42s Sarcee - 272s Springbank) | 3L recloser block required for work on 113L154 | 1.38 Days
Continuous |
|
| 24-Apr-26 08:00 | 11-May-26 16:00 | Syncrude | Outage | C1 (Aurora), 31 (Aurora), 32 (Aurora), 33 (Aurora), 31B (Aurora), 32A (Aurora), 32B (Aurora) | zone 12 6 year maintenance | 17.33 Days
Continuous |
|
| 24-Apr-26 08:00 | 24-Apr-26 17:00 | ALTALINK | TE | AltaLink Telecom Equipment | firmware upgrade on MPLS node A, firewall upgrade | 9 Hours
Continuous |
|
| 24-Apr-26 08:00 | 27-Apr-26 17:00 | SUNCOR | Outage | 635EDD-1001 635PT-1036 (635EDD-1001) | 635PT-1036 outage for transformer's second side equipment maintenance | 3.38 Days
Continuous |
|
| 25-Apr-26 08:00 | 27-Jun-26 16:00 | ENMAX | Outage | 1.82L (SS-1 - SS-5) | 1 sub Transmission line cut over | 63.33 Days
Continuous |
|
| 25-Apr-26 08:00 | 27-Jun-26 16:00 | ENMAX | Outage | 1.84L (SS-1 - SS-5) | 1 sub Transmission line cut over | 63.33 Days
Continuous |
|
| 25-Apr-26 08:00 | 26-Apr-26 18:00 | ENMAX, ALTALINK | Outage | 20.82L (SS-20 - SS-21), 21.80L (42s Sarcee - SS-21), 21.4TR (SS-21), 21.1TR (SS-21), 21B69-21.4TR (SS-21), 21MD138-21.4TR (SS-21), 21B138-20.82 (SS-21), 21B138-21.80 (SS-21), 20B138-20.82 (SS-20) | HV SW Maintenance, spring substation washing, corona on string bus insulator-on plate, Altalink required to remove AML VT4 60S100 fuses | 1.42 Days
Continuous |
|
| 25-Apr-26 08:00 | 26-Apr-26 18:00 | ALTALINK, ENMAX | Outage | 42s 21 (42s Sarcee), 21.80L (42s Sarcee - SS-21) | Enmax request for maintenance and washing | 1.42 Days
Continuous |
|
| 25-Apr-26 08:00 | 25-Apr-26 16:00 | ENMAX | TE | RTU/SCADA (SS-25) | 25 sub SDN / RTU upgrade - disconnecting / reconnecting cables, relabel DPAC inputs | 8 Hours
Daily |
|
| 25-Apr-26 08:00 | 25-Apr-26 16:00 | ENMAX | TE | Protection & Control (SS-25), APS# 145 Shepard RAS - Mitigation of 138 kV Thermal Constraints on ENMAX System | 25 sub RAS A and B protection scheme outage - 25 sub SDN / RTU upgrade | 8 Hours
Daily |
|
| 26-Apr-26 09:00 | 30-Apr-26 17:00 | BCH, BPA | Outage | 5L52 (BPA Custer - BCH Ingledow) | doble and inspection | 4.33 Days
Continuous |
AB-BC |
| 27-Apr-26 07:00 | 30-Apr-26 17:00 | EPCOR | Outage | 1055L (629s Argyll Transfer Station - 816s Petrolia), 240BA3 (629s Argyll Transfer Station - 814s Bellamy), 816s P2402 (816s Petrolia), 816s P2403 (816s Petrolia) | 1055L/Petrolia: SA/CT/CVT Doble and PDS4/PDS5 Disconnect Maintenance and Aerial Washing Program | 3.42 Days
Continuous |
|
| 27-Apr-26 07:00 | 27-Apr-26 17:00 | EPCOR | Outage | RW2401 (EP Riverview) | Riverview: RW2401 (SF6) Breaker Maintenance | 10 Hours
Continuous |
|
| 27-Apr-26 07:00 | 30-Apr-26 17:30 | ALTALINK, EPCOR | RB | 1056L (89s Ellerslie - 629s Argyll Transfer Station) | aerial structure refurbishment and washing program | 3.44 Days
Continuous |
|
| 27-Apr-26 07:00 | 01-May-26 16:00 | ALTALINK | Outage | AML 511s T30 (AML 511s Crossings), AML 511s 1152 (AML 511s Crossings), AML 511s SVC Plus (AML 511s Crossings) | firmware upgrades on protections that are out of service | 4.38 Days
Continuous |
|
| 27-Apr-26 07:00 | 27-Apr-26 18:00 | ALTALINK | Outage | 285s T2 (285s East Camrose), 285s 3202 (285s East Camrose), 285s 1152 (285s East Camrose), 285s 1252 (285s East Camrose), 285s 389 (285s East Camrose) | terminator replacement at 2038L0U1 Y & 2038L0U2 X, VLF cables. | 11 Hours
Continuous |
|
| 27-Apr-26 07:00 | 01-May-26 17:00 | ALTALINK | Outage | 174L (197s Bardo - 289s Saunders Lake), 197s 174W (197s Bardo) | 174L replace structure 123 and install new structure 122A for customer line move project | 4.42 Days
Continuous |
|
| 27-Apr-26 07:00 | 01-May-26 15:00 | CMH | Outage | MH-30L (MHS-3 Southridge - MHS-5 NE Crescent Heights), MHS-3 MH69-308 (MHS-3 Southridge), MHS-5 MH69-502 (MHS-5 NE Crescent Heights), MHS-3 MH69-307 (MHS-3 Southridge), MHS-5 MH69-501 (MHS-5 NE Crescent Heights) | breaker maintenance | 4.33 Days
Continuous |
|
| 27-Apr-26 07:00 | 30-Apr-26 18:00 | ALTALINK, DOW | RB | 787L (166s Dow Chemical Fort Saskatchewan - 787AL tap), 787L (71s Lamoureux - 787AL tap), 787AL (906s Ross Creek - 787L tap) | install a concrete foundation for future structure 31 monopole | 3.46 Days
Continuous |
|
| 27-Apr-26 08:00 | 11-May-26 18:00 | ALTALINK, ATCO | Outage | 87s T2 (87s Gaetz), 87s 240kV East Bus (87s Gaetz), 87s 1552 (87s Gaetz), 87s 1652 (87s Gaetz), 87s 1952 (87s Gaetz), 87s 1252 (87s Gaetz), 962L (87s Gaetz - 972s Tinchebray), 986L (87s Gaetz - 972s Tinchebray) | Closing Open points 'A' & 'C' and commissioning 87s962 & 87s986 MODs | 14.42 Days
Continuous |
|
| 27-Apr-26 08:00 | 28-Apr-26 16:00 | ALTALINK | TE | 15s Protection & Control (15s Fort Macleod) | move relay to new city of Lethbridge communication system | 1.33 Days
Continuous |
|
| 27-Apr-26 08:00 | 27-Apr-26 17:00 | Lethbridge | TE | 146s Protection & Control (146s Macdonald), 593s Protection & Control (593s Lakeview) | protection outages on 593s and 146s 823L 'B' protection to transfer TPR (teleprotection) circuit from existing JMUX to new SEL ICON | 9 Hours
Continuous |
|
| 27-Apr-26 08:00 | 28-Apr-26 17:00 | Lethbridge | TE | 674s Protection & Control (674s Bowron) | protection outages on 674s 725LW 'A' & 'B' protections to transfer TPR (teleprotection) circuits from existing JMUX to new SEL ICON | 1.38 Days
Continuous |
|
| 27-Apr-26 08:00 | 27-Apr-26 16:00 | ENMAX | Outage | 25B240-D139 (SS-25) | hv breaker maintenance, SF6 gas sample | 8 Hours
Continuous |
|
| 27-Apr-26 08:00 | 27-Apr-26 16:00 | ALTALINK | TE | 38s RTU/SCADA (38s East Edmonton) | split the existing SCADA VLAN from 1 to 1 and 2
|
8 Hours
Continuous |
|
| 27-Apr-26 08:00 | 01-May-26 14:00 | ALTALINK | Outage | 37s 4 (37s North Calder), 37s 88 (37s North Calder), 37s 81 (37s North Calder), 37s 82 (37s North Calder), 37s T6 (37s North Calder) | P&C upgrades (37s4, 37s88, 37s82, 37s81, T6, PT20, PT21) | 4.25 Days
Continuous |
|
| 27-Apr-26 08:00 | 01-May-26 14:00 | ALTALINK, EPCOR | RB | 920L (37s North Calder - 557s Castle Downs) | Altalink working on 37s North Calder | 4.25 Days
Continuous |
|
| 27-Apr-26 08:00 | 01-May-26 14:00 | EPCOR, ALTALINK | Outage | 557s CDDS13 (557s Castle Downs), 920L (37s North Calder - 557s Castle Downs) | 920LW/Castledowns: Altalink working on 37s North Calder | 4.25 Days
Continuous |
|
| 27-Apr-26 08:00 | 27-Apr-26 16:00 | ALTALINK, DOW | TE | 166s RTU/SCADA (166s Dow Chemical Fort Saskatchewan) | SCADA VLAN split | 8 Hours
Continuous |
|
| 27-Apr-26 08:00 | 08-May-26 16:00 | CMH | TE | MHS-7 Protection & Control (MHS-7 Brier Park) | perform preventative maintenance on BPR-138-B | 11.33 Days
Continuous |
|
| 27-Apr-26 08:00 | 30-Apr-26 16:00 | ENMAX | Outage | 22.2TR (SS-22) | tap changer inspection - 22.2-X-TC, 22.2-Y-TC, oil sampling MT, TC(X), TC(Y) | 3.33 Days
Continuous |
|
| 27-Apr-26 08:00 | 29-Apr-26 16:00 | ENMAX | Outage | 21.4TR (SS-21), 21B69-21.4TR (SS-21) | transformer power factor test, transformer maintenance, relay fault pressure test, oil sampling | 2.33 Days
Continuous |
|
| 27-Apr-26 08:00 | 30-Apr-26 16:00 | ENMAX | Outage | 12.2TR (SS-12) | transformer power factor test, secondary cable test, transformer maintenance, relay fault pressure test, oil sampling MT, TC | 3.33 Days
Continuous |
|
| 27-Apr-26 08:00 | 30-Apr-26 16:00 | ENMAX | Outage | 21.1C (SS-21) | relays, lockout testing 21RLY138-21.Z31, 21RLYCS138-21CAP, relay protection test - 21RLY138-21CAP | 3.33 Days
Continuous |
|
| 27-Apr-26 08:00 | 27-Apr-26 16:00 | ENMAX | TE | Protection & Control (SS-21) | 21sub 138kV Bus Differential Z31 Protection outage. Relays, Lockout Testing 21RLY138-21.Z31. Outage in conjunction with 21.4TR and 21B138-21.CAP outages. Back-up fault clearing time 26.5 cycles. | 8 Hours
Daily |
|
| 27-Apr-26 08:00 | 28-Apr-26 16:00 | ENMAX | TE | RTU/SCADA (SS-31) | SCADA RTU Test - RTU-31, SCADA Alarm Test - RTU-31 ANN | 1.33 Days
Daily |
|
| 27-Apr-26 08:00 | 15-May-26 16:00 | ALTALINK | TE | 37s Protection & Control (37s North Calder) | P&C upgrades (37s4, 37s82, 37s88, 37s81) | 18.33 Days
Continuous |
|
| 27-Apr-26 09:00 | 01-May-26 18:00 | ATCO, ALTALINK | Outage | 953L (574s Nilrem - 755s Cordel) | switch and breaker maintenance | 4.38 Days
Continuous |
|
| 27-Apr-26 09:00 | 30-Apr-26 17:30 | ALTALINK, EPCOR | Outage | 89s 352 (89s Ellerslie), 89s 452 (89s Ellerslie), 1057L (89s Ellerslie - 657s Summerside) | 1057L/Summerside: CVT/Arrestor Doble, SUDS1/SUDS3/SUDS9 Disconnect Maintenance | 3.35 Days
Continuous |
|
| 27-Apr-26 09:30 | 01-May-26 17:30 | ATCO, ALTALINK | Outage | 9L953 (574s Nilrem - 755s Cordel), 755s 905 (755s Cordel), 755s 906 (755s Cordel) | trip coil test | 4.33 Days
Continuous |
|
| 27-Apr-26 09:30 | 30-Apr-26 17:00 | ALTALINK, EPCOR | Outage | 1057L (89s Ellerslie - 657s Summerside), 657s SU2401 (657s Summerside), 657s SU2402 (657s Summerside) | 1057L/Summerside: CVT/Arrestor Doble, SUDS1/SUDS3/SUDS9 Disconnect Maintenance | 3.31 Days
Continuous |
|
| 27-Apr-26 09:30 | 30-Apr-26 17:00 | ALTALINK, EPCOR | RB | 1056L (89s Ellerslie - 629s Argyll Transfer Station) | aerial structure refurbishment and washing program | 3.31 Days
Continuous |
|
| 27-Apr-26 09:30 | 01-May-26 17:30 | ATCO | TE | 755s Protection & Control (755s Cordel) | TCM Program. RTXP Test Switch Mitigation and Replacement: 87A/9L953, 21B/9L953, 50BF/906BF. In conjunction with 1-00513803 | 4.33 Days
Continuous |
|
| 27-Apr-26 11:00 | 05-May-26 16:00 | ATCO | TE | ATCO Telecom Equipment, 875s RTU/SCADA (875s Algar), 917s RTU/SCADA (917s Horse River), 907s RTU/SCADA (907s Waddell) | Horse River_S_Telecom/Algar_T-Telecom- EOL Radio Replacement. Impact to the following for the outage duration: 7L38 A & B, 9L89A&B All other circuits will have redundant protection in place |
8.21 Days
Continuous |
|
| 27-Apr-26 11:00 | 30-Apr-26 16:30 | ALTALINK | Outage | 198s T2 (198s Blackfalds) | PRC5 transformer maintenance and oil leaks repair | 3.23 Days
Continuous |
|
| 27-Apr-26 11:00 | 27-Apr-26 16:00 | ALTALINK, TRANSALTA | TE | 179s RTU/SCADA (179s Gleichen) | investigate IED trouble alarm and potentially replace LAN-ES1 | 5 Hours
Continuous |
|
| 27-Apr-26 11:00 | 27-Apr-26 16:00 | ALTALINK | TE | 310p Protection & Control (310p Sundance) | ACC reported breaker would not close remotely. Techs to replace CX relay associated with 1852 breaker prot | 5 Hours
Continuous |
|
| 27-Apr-26 11:30 | 27-Apr-26 16:00 | ALTALINK, CSCL | Outage | 385s 112 (385s Spring Coulee), 385s T3 (385s Spring Coulee), 385s 52-2 (385s Spring Coulee), 385s 589 (385s Spring Coulee), 385s 89-L2 (385s Spring Coulee) | urgent bird nest removal on 385s112 | 4.5 Hours
Continuous |
|
| 27-Apr-26 12:00 | 04-May-26 12:00 | ATCO | Outage | 730s STATCOM (730s Rycroft), 730s 705 (730s Rycroft), 730s 702T (730s Rycroft) | svc fire system and annual inspection @ Rycroft 730s | 7 Days
Continuous |
|
| 27-Apr-26 12:00 | 27-Apr-26 18:00 | ENMAX, ALTALINK | IO | 36.81L (44s Bearspaw Plant - SS-36) | PRC5 maintenance - AML outage - 44s36.81E, first trip | 6 Hours
Continuous |
|
| 27-Apr-26 13:00 | 27-Apr-26 17:00 | ENMAX, ALTALINK | Outage | 36.81L (44s Bearspaw Plant - SS-36), 44s 36.81E (44s Bearspaw Plant) | 44s36.81E PRC5 maintenance, first trip | 4 Hours
Continuous |
|
| 27-Apr-26 13:00 | 28-Apr-26 17:00 | ALTALINK | Outage | 410s 952 (410s Josephburg) | PRC5 breaker maintenance, tank heater replacement & first trip | 28 Hours
Continuous |
|
| 27-Apr-26 13:30 | 30-Apr-26 16:00 | ALTALINK | Outage | 310p T36 (310p Sundance) | T36 transformer maintenance | 3.1 Days
Continuous |
|
| 27-Apr-26 13:30 | 27-Apr-26 16:30 | ALTALINK | Outage | 14s T1 (14s Devon) | 25 kV bus maintenance | 3 Hours
Continuous |
|
| 28-Apr-26 07:00 | 29-Apr-26 17:00 | EPCOR | Outage | T3 (Poundmaker) | Poundmaker T3 conservator tank investigation | 1.42 Days
Continuous |
|
| 28-Apr-26 07:00 | 04-May-26 17:30 | ATCO | TE | 743s Protection & Control (743s Sarah Lake) | 50BF/704 relay settings change and testing | 6.44 Days
Continuous |
|
| 28-Apr-26 08:00 | 28-Apr-26 17:00 | ALTALINK | TE | 133s RTU/SCADA (133s Stelco Edmonton), 38s RTU/SCADA (38s East Edmonton), AltaLink Telecom Equipment | firmware upgrade on MPLS nodes A and B and C, firewall upgrade | 9 Hours
Continuous |
|
| 28-Apr-26 08:00 | 30-Apr-26 16:00 | ALTALINK | TE | APS# 217 180L- Fort Macleod 15S Overload Mitigation | move relay to new city of Lethbridge communication system | 2.33 Days
Continuous |
|
| 28-Apr-26 08:00 | 30-Apr-26 17:00 | Lethbridge | TE | APS# 169 725LW-674S Overload Mitigation | protection outages on 674s 725LW RAS 169 'A' & 'B' protections to transfer TPR (teleprotection) circuits from existing JMUX to new SEL ICON | 2.38 Days
Continuous |
|
| 28-Apr-26 08:00 | 28-Apr-26 16:00 | ENMAX | Outage | 25B240-D142 (SS-25) | breaker maintenance | 8 Hours
Continuous |
|
| 28-Apr-26 08:00 | 28-Apr-26 13:00 | ENMAX, ALTALINK | IO | 50L (44s Bearspaw Plant - SS-21), 60s50 (SS-21) | Altalink outage. 44s50X maintenance, PRC5 and first trip | 5 Hours
Continuous |
|
| 28-Apr-26 08:00 | 28-Apr-26 16:00 | ALTALINK | TE | 62s Protection & Control (62s Brazeau Plant), APS# 25 Brazeau 62s Generation Tripping Scheme | standard relay maintenance | 8 Hours
Continuous |
|
| 28-Apr-26 08:00 | 28-Apr-26 16:30 | ALTALINK | Outage | 453L (305s Acheson - 367s Harry Smith), 305s 453 (305s Acheson), 367s 453 (367s Harry Smith) | breaker maintenance | 8.5 Hours
Continuous |
|
| 28-Apr-26 08:00 | 22-May-26 16:00 | ENMAX | TE | Protection & Control (SS-32) | 32 sub 138 kV autoswitching protection outage - HV switch replacement. MD-32.2TR, 32SW84, 32SW85, 32SW86, 32SW87, 32SW88 | 24.33 Days
Daily |
|
| 28-Apr-26 08:30 | 22-May-26 14:00 | ENMAX | Outage | 32.83L (SS-32 - SS-40), 32.2TR (SS-32), 32.1TR (SS-32), 26.81L (SS-26 - SS-32) | HV SW Replacement. MD-32.2TR, 32SW84, 32SW85, 32SW86, 32SW87, 32SW88 | 24.23 Days
Continuous |
|
| 28-Apr-26 09:00 | 28-Apr-26 16:00 | ATCO | TE | ATCO Telecom Equipment | radio firmware update | 7 Hours
Continuous |
|
| 28-Apr-26 09:00 | 01-May-26 12:00 | ATCO | Outage | 930s SVC (930s Arcenciel), 930s 701T (930s Arcenciel) | SVC air cooled maintenance | 3.13 Days
Continuous |
|
| 28-Apr-26 09:00 | 28-Apr-26 12:00 | ENMAX, ALTALINK | Outage | 50L (44s Bearspaw Plant - SS-21), 44s 50X (44s Bearspaw Plant), 60s50 (SS-21) | 44s50X maintenance, PRC5 and first trip | 3 Hours
Continuous |
|
| 28-Apr-26 10:00 | 28-Apr-26 14:00 | ATCO | TE | 827s RTU/SCADA (827s Cranberry Lake), ATCO Telecom Equipment | Lubicon Telecom replace existing battery chargers & distribution panel with new Eltek rectifier and distribution panel | 4 Hours
Continuous |
|
| 28-Apr-26 13:00 | 28-Apr-26 17:00 | ALTALINK | Outage | 237s 152 (237s Foothills) | 237s152 first trip, maintenance and PRC 5 checks | 4 Hours
Continuous |
|
| 29-Apr-26 07:00 | 29-Apr-26 18:00 | ALTALINK | Outage | 38s 731E (38s East Edmonton), 420s 731 (420s Broadmoor), 731L (38s East Edmonton - 746L tap) | Replace structure 731L17
Install dampers at structures 731L16 & 731L18 |
11 Hours
Continuous |
|
| 29-Apr-26 07:00 | 07-May-26 17:00 | ALTALINK | TE | 275s RTU/SCADA (275s Jenner) | 275s Jenner RTU update for switch replacement | 8.42 Days
Continuous |
|
| 29-Apr-26 08:00 | 29-Apr-26 17:00 | ALTALINK | TE | 293s RTU/SCADA (293s Bernese) | replace firewall | 9 Hours
Continuous |
|
| 29-Apr-26 08:00 | 30-Apr-26 17:00 | ALTALINK | RB | 1071L (205s Castle Rock Ridge - 312s Fidler), 205s 352 (205s Castle Rock Ridge), 205s 452 (205s Castle Rock Ridge), 312s 852 (312s Fidler), 312s 952 (312s Fidler) | replace Both OH support hardware assembly's structures 2 and 37, aligned with 26-10472 1072L RB and 26-10481 994L RB | 1.38 Days
Continuous |
|
| 29-Apr-26 08:00 | 30-Apr-26 17:00 | ALTALINK | RB | 1072L (103s Goose Lake - 205s Castle Rock Ridge), 103s 252 (103s Goose Lake), 103s 352 (103s Goose Lake), 205s 152 (205s Castle Rock Ridge), 205s 252 (205s Castle Rock Ridge) | replace Both OH support hardware assembly's structure 2, Required for 26-10467 1071L RB , See also 26-10481 994L RB that goes with these | 1.38 Days
Continuous |
|
| 29-Apr-26 08:00 | 30-Apr-26 16:00 | ALTALINK | RB | 994L (103s Goose Lake - 312s Fidler), 103s 552 (103s Goose Lake), 103s 652 (103s Goose Lake), 312s 552 (312s Fidler), 312s 952 (312s Fidler) | replace Both OH support hardware assembly's structure 37, aligned with 26-10472 1072L RB and 26-10467 1071L RB | 1.33 Days
Continuous |
|
| 29-Apr-26 08:00 | 07-May-26 18:00 | ALTALINK | Outage | 275s T1 (275s Jenner) | 275sT1 oil reclaim, maintenance, plugged radiator, replace switch 275s37 and 275s39. replace 25kV post insulators.275s2269, 275s2036N, & 275s81 | 8.42 Days
Continuous |
|
| 29-Apr-26 08:00 | 29-Apr-26 16:00 | ENMAX | Outage | 25B240-D138 (SS-25) | HV Breaker Maintenance. SF6 Gas Sample | 8 Hours
Continuous |
|
| 29-Apr-26 08:00 | 29-Apr-26 16:30 | ALTALINK | Outage | 14s 739N (14s Devon), 739L (14s Devon - 305s Acheson), 305s 739 (305s Acheson) | 138kV breaker maintenance | 8.5 Hours
Continuous |
|
| 29-Apr-26 08:30 | 29-Apr-26 12:30 | ALTALINK | Outage | 237s 252 (237s Foothills) | 237s252 First Trip, PRC5 and maintenance. | 4 Hours
Continuous |
|
| 29-Apr-26 08:30 | 30-Apr-26 16:30 | ENMAX, ALTALINK | Outage | 5s 752 (5s East Calgary) | 5s752 Maint. and PRC5 checks no first trip required.
5sC3 and C4 weed spraying |
1.33 Days
Continuous |
|
| 29-Apr-26 09:00 | 29-Apr-26 12:00 | ATCO | TE | ATCO Telecom Equipment | Saskatoon Mtn_T-Telecom/Flying Shot Lake_S-Telecom- RADIO DIGITAL AVIAT IRU 600 7GHZ PM. IMPACT TO THE FOLLOWING TRAFFIC DURING PM AND SOFTWARE UPGRADE: 7LA33 A&B, 7L33 A&B | 3 Hours
Continuous |
|
| 29-Apr-26 09:00 | 30-Apr-26 17:00 | ALTALINK | Outage | 410s 1052 (410s Josephburg) | PRC5 Breaker Maintenance, Tank heater replacement & First Trip | 1.33 Days
Continuous |
|
| 29-Apr-26 09:00 | 29-Apr-26 17:00 | BCH | Outage | 2L294 (BCH A. A. Lambert - BCH Nelway) | replace severely cracked cross arm | 8 Hours
Continuous |
AB-BC |
| 29-Apr-26 12:30 | 29-Apr-26 16:30 | ALTALINK | Outage | 237s 2352 (237s Foothills) | 237s2352 First Trip, PRC5 checks Investigate trip coil 1. | 4 Hours
Continuous |
|
| 29-Apr-26 13:00 | 29-Apr-26 16:00 | ATCO | TE | ATCO Telecom Equipment | Saskatoon Mtn_T-Telecom/Goodfare_S-Telecom- RADIO DIGITAL MDR 8502 PM. Impact to the following During PM: 7L33 A&B BIG MOUNTAIN / FLYINGSHOT, 7LA33 A&B FLYINGSHOT / CANADIAN HYDRO | 3 Hours
Continuous |
|
| 29-Apr-26 17:00 | 19-May-26 07:00 | ALTALINK | Outage | 320p 2089 (320p Keephills) | Urgent customer work on G3 | 19.58 Days
Continuous |
|
| 30-Apr-26 07:30 | 30-Apr-26 07:45 | CMH | TE | Medicine Hat ICCP Outage | plugging in ICCP router to a new UPS system | 15 Mins
Continuous |
|
| 30-Apr-26 08:00 | 30-Apr-26 16:00 | ALTALINK | Outage | 332s T1 (332s Ellis), 332s 111 (332s Ellis) | work on the NGR | 8 Hours
Continuous |
|
| 30-Apr-26 08:00 | 30-Apr-26 16:00 | ALTALINK | TE | 197s RTU/SCADA (197s Bardo) | split the existing SCADA VLAN from 1 to 1 and 2
|
8 Hours
Continuous |
|
| 30-Apr-26 08:00 | 30-Apr-26 16:30 | ALTALINK | Outage | 14s 739E (14s Devon) | 138 kV breaker maintenance | 8.5 Hours
Continuous |
|
| 30-Apr-26 08:00 | 30-Apr-26 16:00 | ENMAX | TE | RTU/SCADA (SS-10) | SCADA RTU test - RTU-10, SCADA alarm test - RTU-10 ANN | 8 Hours
Daily |
|
| 30-Apr-26 08:00 | 30-Apr-26 17:00 | ATCO | TE | ATCO Telecom Equipment, ATCO EMS/ICCP Outage | replace the old HP and mobile firewalls at Vegreville and install some new networking cards on the LowBES VPN firewalls | 9 Hours
Continuous |
|
| 30-Apr-26 09:00 | 30-Apr-26 16:00 | ATCO | TE | 917s RTU/SCADA (917s Horse River), ATCO Telecom Equipment | updates to the firewall and LAN configuration on Horse River telecom during the EOL radio upgrade | 7 Hours
Continuous |
|
| 01-May-26 08:00 | 01-May-26 16:00 | ALTALINK | Outage | 332s T2 (332s Ellis), 332s 122 (332s Ellis) | work on the NGR | 8 Hours
Continuous |
|
| 01-May-26 08:00 | 01-May-26 17:00 | ALTALINK | TE | 410s RTU/SCADA (410s Josephburg), 452s RTU/SCADA (452s B.F. Goodrich Fort Saskatchewan), AltaLink Telecom Equipment | upgrading VLAN, MPLS, and firewall | 9 Hours
Continuous |
|
| 01-May-26 08:00 | 01-May-26 16:00 | ENMAX | TE | Protection & Control (SS-2) | 2 sub 86 BF-D94 protection outage - relays, lockout testing | 8 Hours
Continuous |
|
| 01-May-26 08:00 | 01-May-26 16:00 | ENMAX | TE | RTU/SCADA (SS-40) | SCADA RTU test - RTU-40, SCADA alarm test - RTU-40 ANN | 8 Hours
Daily |
|
| 01-May-26 09:00 | 03-May-26 17:00 | ALTALINK | Outage | 719L (378s Shell Caroline - 575s Sundre), 575s 719N (575s Sundre), 378s 719X (378s Shell Caroline) | replace 575s719N breaker CT`s | 2.33 Days
Continuous |
|
| 01-May-26 09:30 | 01-May-26 17:30 | ATCO, BSRW | TE | 363s RTU/SCADA (363s Sedalia), 363s Protection & Control (363s Sedalia) | 87L-21B/9LA46 relay settings update at 363s Sedalia |
8 Hours
Continuous |
|
| 01-May-26 14:00 | 07-May-26 16:00 | ALTALINK | Outage | 37s Protection & Control (37s North Calder), 37s T6 (37s North Calder) | P&C upgrades (37s4, 37s88, 37s81, T6, PT20) | 6.08 Days
Continuous |
|
| 01-May-26 14:00 | 07-May-26 16:00 | ALTALINK, EPCOR | RB | 920L (37s North Calder - 557s Castle Downs) | reclose block for Altalink working on 37s North Calder | 6.08 Days
Continuous |
|
| 01-May-26 14:00 | 07-May-26 16:00 | ALTALINK, EPCOR | RB | 930L (37s North Calder - Poundmaker) | reclose block for Altalink working on 37s North Calder | 6.08 Days
Continuous |
|
| 01-May-26 17:00 | 25-Nov-26 17:00 | EPCOR | Outage | T1 (Meadowlark) | T1 LCR civil work | 208.04 Days
Continuous |
| This document and the information contained herein are based upon information and data which by their nature contain a degree of uncertainty and are subject to change. In addition, this document may contain information and data from public sources and/or third parties, which have been assumed to be accurate and complete and have not been verified. Accordingly, the Independent System Operator, operating as the Alberta Electric System Operator (the "AESO") makes no warranty, representation or guarantee, express or implied, with respect to this document or the information contained herein, including, but not limited to, any warranty, representation or guarantee of accuracy, completeness, timeliness, reliability, availability, absence of computer virus, non- infringement, merchantability or suitability for any purpose. Under no circumstances will the AESO, its members, officers, employees, contractors or agents, or any of their respective affiliates, be liable for any errors or omissions in, or any losses, damages or claims whatsoever, whether in contract, tort or otherwise, arising from use of or reliance upon, this document or any information contained herein. © 2009 Alberta Electric System Operator. All rights reserved |