Alberta Electric System Operator | |
System Co-ordination Plan | |
2024-04-25 to 2024-05-03 | |
Approved Outages |
Previous Version | |
Download CSV |
From | To | Owner | Type | Element | Scheduled Activity | Date/Time Comments | Interconnection |
---|---|---|---|---|---|---|---|
05-Oct-18 08:00 | 31-Dec-24 16:00 | EPCOR | IO | C2 (Rossdale) | forced outage | 2,279.38 Days
Continuous |
|
24-Oct-18 01:13 | 31-Dec-24 16:00 | EPCOR | IO | C1 (Rossdale) | forced outage | 2,260.66 Days
Continuous |
|
04-Sep-22 16:50 | 30-Sep-24 18:00 | ATCO | Outage | 848s 401R (848s Ruth Lake) | forced outage | 757.05 Days
Continuous |
|
15-Mar-23 18:01 | 01-May-24 18:00 | SUNCOR | Outage | 29EDD-71 752-4651 (29EDD-71) | breaker will remain offline for undetermined period of time | 413 Days
Continuous |
|
31-Jul-23 14:56 | 27-Sep-24 16:00 | ENMAX | Outage | 38B138-38.1CAP (SS-38), 38.1C (SS-38) | motor run time fail | 424.04 Days
Continuous |
|
27-Nov-23 08:00 | 07-Mar-25 16:00 | ENMAX | Outage | 32.2TR (SS-32) | 32 sub 32.2TR 8 kV bus switchgear demolition | 466.33 Days
Continuous |
|
08-Jan-24 07:00 | 20-May-24 17:00 | EPCOR | Outage | T2 (Rossdale), R721 (Rossdale), R723 (Rossdale), RAB2 (Rossdale) | rossdale transformer assembly and scaffold build | 133.38 Days
Continuous |
|
19-Feb-24 10:00 | 17-Jun-24 17:00 | ATCO | TE | 863s RTU/SCADA (863s Paintearth) | modifications to existing RTU and new SCADA equipment | 119.25 Days
Continuous |
|
19-Feb-24 11:00 | 10-Jun-24 17:30 | ATCO | TE | 863S 240kV Breaker Relays, 863S 25kV Breaker Relays | disable all breaker fail protection for the duration of the project | 112.23 Days
Continuous |
|
19-Feb-24 11:00 | 06-Jun-24 17:30 | ATCO | TE | 863S 240kV Bus Relays | install new 900BS1 protection panel | 108.23 Days
Continuous |
|
26-Feb-24 07:00 | 10-May-24 17:00 | EPCOR | TE | EP 803s Protection & Control (EP 803s Lambton) | protection blocking for annual relay maintenance | 74.38 Days
Continuous |
|
01-Mar-24 11:00 | 01-May-24 13:00 | CNRL, ATCO | Outage | 859s 52G (859s Primrose), 859s 501TD (859s Primrose) | transfer all load from 25kV Bus A to 25kV Bus B | 61.04 Days
Continuous |
|
04-Mar-24 08:00 | 30-Apr-24 16:00 | ALTALINK | TE | 746s RTU/SCADA (746s Sherwood Park) | configuration updates for A-B/87/T1, L1, L8, L2 feeder protection and cutovers of controls for 746s3, s5, s34N, s40,s173W, s474X | 57.29 Days
Daily |
|
07-Mar-24 06:30 | 29-Aug-24 16:00 | ALTALINK | Outage | 477s T1 (477s Amoco West Pembina) | disconnect T1 and VR1 permanently, draining oil, release 477s T1, VR1, & 4.16kV equipment for salvage and RSLD2 then RSLD3 to be implemented at end of outage | 175.35 Days
Continuous |
|
11-Mar-24 07:00 | 30-Apr-24 17:00 | EPCOR | TE | 665s Protection & Control (665s Dome) | protection blocking for annual relay maintenance | 50.42 Days
Continuous |
|
18-Mar-24 14:30 | 29-Apr-24 14:00 | ATCO | Outage | 863s 902T (863s Paintearth) | protection upgrade, commission new wiring/trransformer protection, and new transformer protection panel | 41.98 Days
Continuous |
|
25-Mar-24 13:50 | 30-Apr-24 17:00 | BCH | Outage | 5CB1 (BCH Selkirk) | repair damaged equipment, BC maintenance does not affect the Alberta ATC | 36.13 Days
Continuous |
AB-BC |
01-Apr-24 00:00 | 01-May-24 00:00 | SUNCOR | Outage | 29EDD-71 29PT-235 (29EDD-71), 29EDD-71 752-4642 (29EDD-71), 29EDD-71 752-4641 (29EDD-71) | FB-maintenance and testing | 30 Days
Continuous |
|
01-Apr-24 08:00 | 10-May-24 17:00 | ALTALINK | TE | 244s RTU/SCADA (244s Bowmanton) | updating RTU configuration | 39.38 Days
Daily |
|
02-Apr-24 07:00 | 07-May-24 17:00 | EPCOR | Outage | T1 (Garneau), GT1 (Garneau) | Garneau S/S Tx1 bay outage | 35.42 Days
Continuous |
|
08-Apr-24 08:00 | 28-Apr-24 18:00 | ENMAX | Outage | 1.82L (SS-1 - SS-5), 5.1TR (SS-5), 5.6TR (SS-5), 5.8TR (SS-5), 5B138-5BT12 (SS-5), 5B138-5BT7 (SS-5), 5MD138-5.6TR (SS-5), 5MD138-5.8TR (SS-5), 5B138-1.82 (SS-5) | switches maintenance and substation washing | 20.42 Days
Continuous |
|
08-Apr-24 08:00 | 10-May-24 17:00 | ALTALINK | TE | 523s RTU/SCADA (523s Bullshead) | updating RTU configuration for the Dunmore project | 32.38 Days
Daily |
|
08-Apr-24 09:00 | 26-Apr-24 17:00 | ATCO | TE | 728s Protection & Control (728s Mercer Hill), 728s RTU/SCADA (728s Mercer Hill) | protection and RTU updates | 18.33 Days
Continuous |
|
08-Apr-24 10:55 | 02-Jun-24 17:00 | ATCO | Outage | 716s 701T (716s Lloydminster), 716s 703 (716s Lloydminster) | 716s rebuild | 55.25 Days
Continuous |
|
08-Apr-24 11:00 | 02-Jun-24 17:00 | ATCO | Outage | 716s 701 (716s Lloydminster) | 716s rebuild: 7L749 new line relay install & commission |
55.25 Days
Continuous |
|
08-Apr-24 11:00 | 02-Jun-24 17:00 | ATCO | Outage | 716s 701C (716s Lloydminster) | 716s rebuild: 701C new relay install & commission |
55.25 Days
Continuous |
|
09-Apr-24 10:00 | 02-Jun-24 18:00 | ATCO | TE | 716s Protection & Control (716s Lloydminster) | settings changes on 7L42 protection for 716S Sub Rebuild closing 700D1 at 716s | 54.33 Days
Continuous |
|
09-Apr-24 10:00 | 02-Jun-24 18:00 | ATCO | TE | 751s Protection & Control (751s Hill) | settings changes on 7L42 protection for 716S Sub Rebuild closing 700D1 at 716s | 54.33 Days
Continuous |
|
09-Apr-24 15:00 | 18-Jun-24 16:00 | ALTALINK | Outage | 151s C1 (151s Strathmore) | broken | 70.04 Days
Continuous |
|
12-Apr-24 17:00 | 10-May-24 17:00 | EPCOR | Outage | 987s CDS45 (987s Cloverbar) | repair of damage 240 kV CVT in order to properly energize 1191L bay | 28 Days
Continuous |
|
13-Apr-24 08:00 | 26-Apr-24 16:00 | SUNCOR | Outage | 29PL9-6 (29EDD-1 Millennium - 29EDD-34), 29EDD-1 952-105 (29EDD-1 Millennium), 29EDD-1 952-106 (29EDD-1 Millennium), 29EDD-34 29-952-111 (29EDD-34), 29EDD-34 29-952-112 (29EDD-34) | breakers, CTs & disconnect switches maintenance | 13.33 Days
Continuous |
|
15-Apr-24 07:00 | 17-May-24 17:00 | EPCOR | Outage | 816s P2402 (816s Petrolia), 816s P2401 (816s Petrolia), 816s T1 (816s Petrolia) | P2401 Breaker LCR | 32.42 Days
Continuous |
|
15-Apr-24 08:00 | 28-Apr-24 16:00 | ENMAX | Outage | 16.63L (SS-16 - SS-36), 36.5TR (SS-36), 36B69-16.63/36.5TR (SS-36), 16B69-16.63 (SS-16) | line protection upgrade | 13.33 Days
Continuous |
|
15-Apr-24 08:00 | 28-Apr-24 18:00 | SUNCOR | TE | 29EDD-94 RTU/SCADA (29EDD-94 Voyageur), 29EDD-94 406T (29EDD-94 Voyageur), 29EDD-94 407T (29EDD-94 Voyageur), 29PL9-16 (29EDD-1 Millennium - 29EDD-94 Voyageur), 29PL9-17 (29EDD-1 Millennium - 29EDD-94 Voyageur), 29EDD-94 29PP-98 260kV Bus (29EDD-94 Voyageur) | perform firmware upgrades and relay testing | 13.42 Days
Continuous |
|
15-Apr-24 08:00 | 28-Apr-24 16:00 | ENMAX | TE | Protection & Control (SS-36) | 36 sub autoswitching and Z32 bus differential protection disabled for 16.63 line protection upgrade | 13.33 Days
Daily |
|
15-Apr-24 10:00 | 02-May-24 18:00 | ALTALINK | Outage | 48s T1 (48s Pocaterra), 48s T2 (48s Pocaterra) | adding new equipment | 17.33 Days
Continuous |
|
16-Apr-24 07:00 | 30-Apr-24 18:00 | ALTALINK | Outage | 701L (223s Strome - 7LA701 tap) | 701L CRU and WMP component replacement (str 320D - 422) | 14.46 Days
Continuous |
|
16-Apr-24 07:00 | 30-Apr-24 18:00 | ATCO | Outage | 7L701 (757s Battle River - 7LA701 tap) | AltaLink scope - 701L CRU and WMP component replacement (str 320D - 422) | 14.46 Days
Continuous |
|
16-Apr-24 07:00 | 27-Apr-24 17:00 | EPCOR | Outage | 330p 1214 (330p Genesee), 330p 1215 (330p Genesee), 330p 1215A (330p Genesee), 330p 1214B (330p Genesee) | carona ball replacement | 11.42 Days
Continuous |
|
16-Apr-24 09:00 | 26-Apr-24 17:30 | ALTALINK | Outage | 575s T1 (575s Sundre) | corrosive sulphur, doble, oil gauge | 10.35 Days
Continuous |
|
17-Apr-24 09:00 | 26-Apr-24 15:00 | ATCO | Outage | 7L132 (767s Oyen - 959s Lanfine), 767s 701 (767s Oyen) | restring OPGW from structures 10-32 | 9.25 Days
Continuous |
|
17-Apr-24 09:30 | 26-Apr-24 14:30 | ATCO | Outage | 6L09 (767s Oyen - 6L21 tap), 767s 601 (767s Oyen) | GOI for stringing 7L132 overtop of 6L09 | 9.21 Days
Continuous |
|
18-Apr-24 09:00 | 14-Jun-24 16:00 | ATCO | TE | 716s RTU/SCADA (716s Lloydminster) | lloyd sub rebuild is completed in stages and therefore SCADA verifications performed at varying times | 57.29 Days
Continuous |
|
21-Apr-24 08:00 | 25-Apr-24 18:00 | SUNCOR | Outage | 29EDD-71 752-4624 (29EDD-71) | maintenance and test | 4.42 Days
Continuous |
|
22-Apr-24 02:00 | 26-Apr-24 16:00 | ATCO | Outage | 2075s 900SST2 (2075s Newell) | single phase 25kV regulator failure | 4.58 Days
Continuous |
|
22-Apr-24 07:00 | 27-Apr-24 17:00 | ALTALINK, EPCOR | Outage | 909L (310p Sundance - 665s Dome), 665s T2 (665s Dome), 665s D2402 (665s Dome), 665s D2403 (665s Dome), 665s DDS14 (665s Dome), 665s DAB2 (665s Dome) | breaker maintenance, P&C maintenance | 5.42 Days
Continuous |
|
22-Apr-24 07:00 | 27-Apr-24 17:00 | EPCOR | Outage | 52s T2 (52s East Industrial), 52s E2402 (52s East Industrial) | breaker maintenance E2402 (SF6) and TX2 doble | 5.42 Days
Continuous |
|
22-Apr-24 07:00 | 25-Apr-24 17:30 | ALTALINK | Outage | 310p 1852 (310p Sundance) | urgent replace failed 310p1852 CT | 3.44 Days
Continuous |
|
22-Apr-24 07:00 | 25-Apr-24 18:00 | ENMAX | Outage | 14.3TR (SS-14) | grounding deficiency iImprovements | 3.46 Days
Continuous |
|
22-Apr-24 07:00 | 26-Apr-24 17:00 | EPCOR | Outage | 330P SST1 (330P Genesee) | move from temporary bypass lines to permanent structures | 4.42 Days
Continuous |
|
22-Apr-24 07:00 | 26-Apr-24 17:00 | EPCOR | Outage | 330P SST3 (330P Genesee) | move from temporary bypass to permanent structures | 4.42 Days
Continuous |
|
22-Apr-24 08:00 | 26-Apr-24 17:00 | ALTALINK | TE | 535s RTU/SCADA (535s Joffre) | download new configurations and migrating and commissioning of T5 (TX18528) protection, tap changer and NE alarms, 535s52 controls, metering, alarms etc | 4.38 Days
Continuous |
|
22-Apr-24 08:00 | 26-Apr-24 17:00 | ALTALINK | TE | 283s RTU/SCADA (283s Violet Grove) | update RTU settings | 4.38 Days
Daily |
|
22-Apr-24 08:00 | 25-Apr-24 16:30 | ALTALINK | Outage | 508L (67s Stirling - 344s Warner), 344s T1 (344s Warner), 344s T2 (344s Warner) | replacing insulators at 508L306 and replacing structures at 508L286 and 508L40 | 3.35 Days
Continuous |
|
22-Apr-24 09:00 | 05-May-24 16:00 | ATCO | Outage | 7L32 (813s Little Smoky - 862s South Bezanson) | pole change from test and treat / X arm change | 13.29 Days
Continuous |
|
22-Apr-24 09:00 | 04-Jun-24 17:00 | ATCO | TE | 755s Protection & Control (755s Cordel) | removal of old protection relays | 43.33 Days
Continuous |
|
22-Apr-24 09:00 | 10-Jun-24 17:00 | ATCO | TE | 972s Protection & Control (972s Tinchebray), 972s RTU/SCADA (972s Tinchebray) | PT work for relay upgrade | 49.33 Days
Continuous |
|
22-Apr-24 09:00 | 04-Jun-24 17:00 | ATCO | TE | 972s Protection & Control (972s Tinchebray) | removal of old protection relays | 43.33 Days
Continuous |
|
22-Apr-24 10:00 | 10-May-24 17:30 | ATCO | Outage | 869s 702T (869s Seal Lake), 869s 702 (869s Seal Lake) | qualitrol ITM replacement, class2 major testing | 18.31 Days
Continuous |
|
22-Apr-24 10:00 | 10-May-24 17:30 | ATCO | TE | 869s RTU/SCADA (869s Seal Lake), 869s Protection & Control (869s Seal Lake) | qualitrol ITM replacement, update RTU/702T protection |
18.31 Days
Continuous |
|
22-Apr-24 10:00 | 03-May-24 16:00 | ATCO | TE | 951s Protection & Control (951s Thickwood Hills) | PRC-005 - relay testing |
11.25 Days
Continuous |
|
22-Apr-24 10:00 | 25-Apr-24 16:00 | ATCO | TE | 780s Protection & Control (780s Lubicon) | 7L60 RTXP test switch replacements, perform work with breakers in service to keep 7L60 line on | 3.25 Days
Continuous |
|
22-Apr-24 10:00 | 25-Apr-24 16:00 | ATCO | Outage | 780s 704 (780s Lubicon) | breaker maintenance in conjunction with 7L60 RTXP replacement | 3.25 Days
Continuous |
|
22-Apr-24 10:00 | 25-Apr-24 18:00 | ALTALINK | TE | 310p Protection & Control (310p Sundance) | change CT ratios and complete element testing for the urgent outage to replace failed 310p1852 CT | 3.33 Days
Daily |
|
22-Apr-24 11:00 | 10-Jun-24 17:00 | ATCO | TE | 755s Protection & Control (755s Cordel), 755s RTU/SCADA (755s Cordel) | relay upgrade, adding new SCADA points and protection upgrade. | 49.25 Days
Continuous |
|
22-Apr-24 13:30 | 02-May-24 17:30 | ALTALINK | Outage | 58s T1 (58s Edson) | replace 25 KV/138 KV bushings, doble and LR, re-gasket, repair leaks and CT blocks on T1, main tank/LTC gasket rebuild | 10.17 Days
Continuous |
|
22-Apr-24 13:30 | 25-Apr-24 17:30 | ALTALINK | Outage | 522s T1 (522s Cooking Lake), 522s 1252 (522s Cooking Lake) | 25 kV breaker replacement (522s259X), 138 kV/25 kV LAs and strain insulators, L4 feeder protection replacement | 3.17 Days
Continuous |
|
22-Apr-24 14:00 | 25-Apr-24 17:00 | ALTALINK | TE | 522s RTU/SCADA (522s Cooking Lake) | RTU database update | 3.13 Days
Daily |
|
22-Apr-24 20:25 | 25-Apr-24 18:00 | ALTALINK | Outage | 708L (71s Lamoureux - 708AL tap) | forced outage due to burnt structure | 2.9 Days
Daily |
|
23-Apr-24 07:00 | 27-Apr-24 17:00 | EPCOR | Outage | 330p 500kV Bus 2 (330p Genesee), 330p 12TC2 (330p Genesee), 330p 1203A (330p Genesee), 330p 1211 (330p Genesee), 330p 1215 (330p Genesee), 330p 1203 (330p Genesee), 330p 1206 (330p Genesee), 330p 1209 (330p Genesee) | Genesee bus 2 corona ball replacement | 4.42 Days
Continuous |
|
23-Apr-24 07:00 | 25-Apr-24 17:00 | ATCO | TE | 951s Protection & Control (951s Thickwood Hills) | test armed, runback, DTT signals to Suncor from RAS-A, RAS-B | 2.42 Days
Continuous |
|
23-Apr-24 07:00 | 25-Apr-24 18:00 | ALTALINK | TE | 310p Protection & Control (310p Sundance) | urgent protection outage on A87/ST5/6 & B87/ST5/6 to facilitate the urgent outage to replace failed 310p1852 CT | 2.46 Days
Daily |
|
23-Apr-24 08:00 | 30-Apr-24 16:00 | Syncrude | Outage | Syncrude Plant 30-2 72kV A Bus (UE-1 Syncrude Plant 30-2), Syncrude Plant 30-2 30-2PTR72-A1 (UE-1 Syncrude Plant 30-2), Syncrude Plant 30-2 30-2PTR72-A2 (UE-1 Syncrude Plant 30-2), UE-1 7201 (UE-1 Syncrude Plant 30-2), UE-1 7202 (UE-1 Syncrude Plant 30-2), UE-1 7203 (UE-1 Syncrude Plant 30-2), UE-1 7204 (UE-1 Syncrude Plant 30-2), UE-1 1509 (UE-1 Syncrude Plant 30-2), UE-1 72-11 (UE-1 Syncrude Plant 30-2), UE-1 72-01 (UE-1 Syncrude Plant 30-2), UE-1 72-02 (UE-1 Syncrude Plant 30-2), UE-1 72-03 (UE-1 Syncrude Plant 30-2), UE-1 72-04 (UE-1 Syncrude Plant 30-2), UE-1 72-14 (UE-1 Syncrude Plant 30-2), UE-1 72-15 (UE-1 Syncrude Plant 30-2), UE-1 72-09 (UE-1 Syncrude Plant 30-2), 1016 (Syncrude Mildred Lake) | SCL - Isolate 72kV bus in UE-1 Substation | 7.33 Days
Continuous |
|
23-Apr-24 08:00 | 25-Apr-24 17:00 | ATCO | RB | 7L65 (709s Vegreville - 7LA65 tap), 7L65 (710s Vermilion - 7LA65 tap), 7LA65 (708s Grizzly Bear - 7L65 tap) | marker cone replacement | 2.38 Days
Daily |
|
23-Apr-24 08:00 | 05-May-24 16:00 | ENMAX | Outage | 41.2TR (SS-41) | forced outage - differential protection trip | 12.33 Days
Continuous |
|
23-Apr-24 11:00 | 02-May-24 17:00 | ATCO | Outage | 755s 904 (755s Cordel) | 9L16 protection upgrade |
9.25 Days
Continuous |
|
23-Apr-24 17:00 | 27-Apr-24 07:59 | ALTALINK | Outage | 746s T1 (746s Sherwood Park) | T1 replacement continuation | 3.62 Days
Continuous |
|
24-Apr-24 07:30 | 25-Apr-24 16:30 | ENMAX, ALTALINK | Outage | 50L (44s Bearspaw Plant - SS-21), 60s50 (SS-21), 44s 50X (44s Bearspaw Plant) | replace leaking east phase CT at 60s50 | 1.38 Days
Continuous |
|
24-Apr-24 07:30 | 25-Apr-24 18:00 | ALTALINK | Outage | 993s T2 (993s Abee) | T2 doble, SFRA and tapchanger maintenance | 1.44 Days
Continuous |
|
24-Apr-24 07:30 | 25-Apr-24 16:30 | ENMAX, ALTALINK | IO | 50L (44s Bearspaw Plant - SS-21) | Altalink outage, replace the leaking East Phase CT 60s50. Reclose block on 50L required | 1.38 Days
Continuous |
|
24-Apr-24 07:30 | 25-Apr-24 16:30 | ENMAX, ALTALINK | TE | 60s50 (SS-21) | isolation of the 60s 21/L50 A and B protections - demolition, reconnect and commissioning of CT circuits from 60s50 outage | 1.38 Days
Continuous |
|
24-Apr-24 08:00 | 26-Apr-24 17:00 | ALTALINK | Outage | 700L (422s Westwood - 746L tap), 700L (746s Sherwood Park - 746L tap), 746L (700L tap - 746AL tap), 422s 700 (422s Westwood), 746s 700N (746s Sherwood Park) | urgent insulator washing 746L STR 30-45 | 2.38 Days
Continuous |
|
24-Apr-24 08:30 | 25-Apr-24 16:00 | ATCO | TE | 802s Protection & Control (802s Michichi Creek), 802s RTU/SCADA (802s Michichi Creek) | update 802S_703T_87TB_51HV-51LV_SEL487E relay | 31.5 Hours
Continuous |
|
24-Apr-24 23:00 | 25-Apr-24 03:00 | ALTALINK | Outage | 62s 11 (62s Brazeau Plant) | maintenance | 4 Hours
Daily |
|
25-Apr-24 03:00 | 25-Apr-24 07:00 | ALTALINK | Outage | 62s 12 (62s Brazeau Plant) | maintenance | 4 Hours
Daily |
|
25-Apr-24 07:00 | 25-Apr-24 17:00 | ENMAX | RB | 11.81L (SS-11 - SS-13) | tree trimming | 10 Hours
Daily |
|
25-Apr-24 07:00 | 25-Apr-24 17:00 | ENMAX | IO | Protection & Control (SS-21) | 21 sub 138 kV Zone 31 bus differential outage to facilitate 60s50 breaker CTs | 10 Hours
Continuous |
|
25-Apr-24 07:15 | 25-Apr-24 17:45 | ALTALINK | Outage | 522s 138kV Bus 1 (522s Cooking Lake), 874L (45s Bretona - 522s Cooking Lake), 522s T1 (522s Cooking Lake), 522s 874 (522s Cooking Lake), 522s 1252 (522s Cooking Lake), 45s 874 (45s Bretona) | strain glass insulator replacement | 10.5 Hours
Daily |
|
25-Apr-24 08:00 | 06-May-24 16:00 | SUNCOR | Outage | 29PL6-6 (29EDD-1 Millennium - 29EDD-2 Tar Island), 29EDD-1 29EDD1s1152 (29EDD-1 Millennium), 29EDD-2 29PT-2 (29EDD-2 Tar Island) | breaker test, relay upgrades | 11.33 Days
Continuous |
|
25-Apr-24 08:00 | 25-Apr-24 17:00 | ALTALINK | Outage | 162L (229s Glenwood - 415s Drywood), 415s 146E (415s Drywood) | replace insulators and repair OHSW bond | 9 Hours
Daily |
|
25-Apr-24 08:00 | 25-Apr-24 17:00 | ALTALINK | Outage | 759L (87s Gaetz - 276s Prentiss), 276s 759W (276s Prentiss) | upgrade bonding on entire pole at structure 4 | 9 Hours
Daily |
|
25-Apr-24 08:00 | 25-Apr-24 17:00 | ALTALINK | RB | 793L (87s Gaetz - 535s Joffre) | upgrade bonding on entire pole at structure 4 on 759L, shared tower | 9 Hours
Daily |
|
25-Apr-24 08:00 | 25-Apr-24 16:00 | ENMAX | TE | Protection & Control (SS-16) | 16sub 69 kV bus differential protection -16.63L line protection upgrade | 8 Hours
Daily |
|
25-Apr-24 08:00 | 25-Apr-24 12:00 | ALTALINK | TE | AltaLink Telecom Equipment, 56s RTU/SCADA (56s Boyle) | upgrade 9056R MPLS node | 4 Hours
Daily |
|
25-Apr-24 08:30 | 25-Apr-24 13:30 | ALTALINK | Outage | 186s C1 (186s Dry Creek) | urgent remove weeds and sticks from cap bank | 5 Hours
Daily |
|
25-Apr-24 10:00 | 25-Apr-24 16:00 | ATCO | Outage | 951s 903 (951s Thickwood Hills) | PRC-005 trip coil testing | 6 Hours
Continuous |
|
25-Apr-24 10:00 | 26-Apr-24 17:00 | ATCO, CNRL | TE | 838s RTU/SCADA (838s Horizon Mining), 838s Protection & Control (838s Horizon Mining) | annual PM - RTU, HMI, relays | 31 Hours
Continuous |
|
25-Apr-24 11:00 | 25-Apr-24 12:00 | ATCO | TE | ATCO Telecom Equipment | move RASEE022 to RASCP052 Ap |
60 Mins
Continuous |
|
25-Apr-24 12:00 | 26-Apr-24 17:00 | ALTALINK | Outage | 746s 700N (746s Sherwood Park), 700L (746s Sherwood Park - 746L tap) | test trip 746s700N from new protection, cutover CTs to new protection | 29 Hours
Continuous |
|
25-Apr-24 12:00 | 25-Apr-24 17:00 | ALTALINK | TE | AltaLink Telecom Equipment, 353s RTU/SCADA (353s Plamondon) | upgrade 9353R MPLS node | 5 Hours
Daily |
|
26-Apr-24 07:00 | 10-May-24 17:00 | EPCOR | Outage | 805s T4 (805s Jasper), EP 805s J2405 (EP 805s Jasper), EP 805s J2406 (EP 805s Jasper) | tap changer rebuild, doble, disconnect maintenance | 14.42 Days
Continuous |
|
26-Apr-24 07:00 | 26-Apr-24 18:00 | ALTALINK | Outage | 890L (58s Edson - 207s Pinedale), 58s 890 (58s Edson), 207s 890 (207s Pinedale) | replace structure 101 | 11 Hours
Daily |
|
26-Apr-24 07:00 | 26-Apr-24 17:00 | EPCOR | Outage | EP 803s L2405 (EP 803s Lambton) | L2405 P&C maintenance | 10 Hours
Continuous |
|
26-Apr-24 07:00 | 26-Apr-24 17:00 | ENMAX | RB | 40.81L (SS-40 - SS-41) | tree trimming | 10 Hours
Daily |
|
26-Apr-24 07:00 | 26-Apr-24 17:00 | ENMAX, ALTALINK | RB | 936L (5s East Calgary - 102s Langdon) | spring transmission line washing | 10 Hours
Continuous |
|
26-Apr-24 07:00 | 26-Apr-24 17:00 | ENMAX, ALTALINK | RB | 937L (5s East Calgary - 102s Langdon) | spring transmission line washing | 10 Hours
Continuous |
|
26-Apr-24 07:00 | 26-Apr-24 17:00 | ENMAX | RB | 11.82L (SS-11 - SS-14) | spring transmission line washing | 10 Hours
Continuous |
|
26-Apr-24 07:00 | 26-Apr-24 17:00 | ENMAX | RB | 24.81L (SS-24 - SS-31) | spring transmission line washing | 10 Hours
Continuous |
|
26-Apr-24 08:00 | 06-May-24 16:00 | SUNCOR | Outage | 29PL9-5 (29EDD-1 Millennium - 29EDD-34), 29EDD-34 29-952-122 (29EDD-34), 29EDD-34 29-952-121 (29EDD-34), 29EDD-34 29PS-62 (29EDD-34), 29EDD-1 29PS-71 (29EDD-1 Millennium), 29EDD-1 952-103 (29EDD-1 Millennium), 29EDD-1 952-102 (29EDD-1 Millennium) | BP - maintenance | 10.33 Days
Continuous |
|
26-Apr-24 08:00 | 26-Apr-24 16:00 | ENMAX | Outage | 13B138-3.84 (SS-13), 3.84L (SS-3 - SS-13), 3B138-3.84 (SS-3) | HV breaker maintenance | 8 Hours
Continuous |
|
26-Apr-24 08:00 | 26-Apr-24 12:00 | ENMAX | Outage | 33.83L (SS-33 - SS-41), 33.1TR (SS-33), 33MD138-33.1TR (SS-33), 33B138-33.83 (SS-33) | spring substation washing | 4 Hours
Continuous |
|
26-Apr-24 08:00 | 05-May-24 16:00 | Syncrude | Outage | Syncrude Plant 30-2 30-2PTR72-3 (UE-1 Syncrude Plant 30-2), UE-1 1509 (UE-1 Syncrude Plant 30-2), UE-1 72-09 (UE-1 Syncrude Plant 30-2) | SCL- perform maintenance and repairs | 9.33 Days
Continuous |
|
26-Apr-24 08:00 | 05-May-24 16:00 | Syncrude | Outage | UE-1 1502 (UE-1 Syncrude Plant 30-2), UE-1 1521 (UE-1 Syncrude Plant 30-2), UE-1 1522 (UE-1 Syncrude Plant 30-2) | maintenance | 9.33 Days
Continuous |
|
26-Apr-24 12:00 | 26-Apr-24 16:00 | ENMAX | Outage | 33.84L (SS-33 - SS-43), 33.2TR (SS-33), 33MD138-33.2TR (SS-33), 33B138-33.84 (SS-33) | spring substation washing, check reversing switch | 4 Hours
Continuous |
|
27-Apr-24 08:00 | 27-Apr-24 12:00 | ALTALINK | Outage | 746s 138kV East Bus (746s Sherwood Park), 636L (420s Broadmoor - 746s Sherwood Park), 746s T1 (746s Sherwood Park), 420s 636 (420s Broadmoor), 746s 3 (746s Sherwood Park) | de-energize partial 138 kV bus and 636L to energize new 746s T1 | 4 Hours
Daily |
|
27-Apr-24 08:00 | 27-Apr-24 12:00 | ENMAX | Outage | 2.80L (SS-2 - SS-23), 23.3TR (SS-23), 23B138-2.80 (SS-23), SW83 (SS-23), 23MD138-23.3TR (SS-23), 2MD138-2.80 (SS-2) | spring substation washing | 4 Hours
Continuous |
|
27-Apr-24 08:00 | 27-Apr-24 12:00 | ALTALINK | TE | 746s Protection & Control (746s Sherwood Park) | disable trips from T1 to protect T2 load during energization of new transformer | 4 Hours
Daily |
|
27-Apr-24 12:00 | 27-Apr-24 18:00 | ENMAX | Outage | 23.80L (74s Janet - SS-23), 23.4TR (SS-23), 23B138-23.80 (SS-23), SW84 (SS-23), 23MD138-23.4TR (SS-23) | spring substation washing, check reversing switch | 6 Hours
Continuous |
|
27-Apr-24 12:00 | 27-Apr-24 18:00 | ENMAX | Outage | 23.80L (74s Janet - SS-23) | spring substation washing, check reversing switch | 6 Hours
Daily |
|
28-Apr-24 08:00 | 28-Apr-24 12:00 | ENMAX | Outage | 1.81L (SS-1 - SS-20), 20.1TR (SS-20), 20B138-1.81 (SS-20), SW83 (SS-20), 20MD138-20.1TR (SS-20) | spring substation washing, check reversing switch | 4 Hours
Continuous |
|
28-Apr-24 12:00 | 28-Apr-24 18:00 | ENMAX | Outage | 20.82L (SS-20 - SS-21), 20.3TR (SS-20), 20B138-20.82 (SS-20), SW84 (SS-20), 20MD138-20.3TR (SS-20) | spring substation washing, check reversing switch | 6 Hours
Continuous |
|
28-Apr-24 22:00 | 23-May-24 22:00 | BCH | Outage | 5L72 (BCH Mica G.S. - BCH Nicola) | MCA PM on 5B7 and 5RX3 | 25 Days
Continuous |
AB-BC |
29-Apr-24 07:00 | 02-Aug-24 17:00 | EPCOR | TE | 557s Protection & Control (557s Castle Downs) | protection blocking for annual relay maintenance | 95.42 Days
Continuous |
|
29-Apr-24 07:00 | 29-Apr-24 17:00 | ENMAX | RB | 31.84L (SS-31 - SS-32) | tree trimming | 10 Hours
Daily |
|
29-Apr-24 07:00 | 29-Apr-24 17:00 | ENMAX | RB | 14.83L (SS-14 - SS-36) | tree trimming | 10 Hours
Daily |
|
29-Apr-24 07:00 | 02-May-24 17:00 | EPCOR | Outage | 330p 500kV Bus 1 (330p Genesee), 330P 12TC1 (330p Genesee), 330p 1201 (330p Genesee), 330p 1204 (330p Genesee), 330p 1207 (330p Genesee), 330p 1214 (330p Genesee), 330p 1210 (330p Genesee), 330p 1201A (330p Genesee) | Carona Ball replacement Genesee 12BU1 | 3.42 Days
Continuous |
|
29-Apr-24 07:00 | 02-May-24 18:00 | ENMAX | Outage | 14.4TR (SS-14) | grounding deficiency improvements | 3.46 Days
Continuous |
|
29-Apr-24 07:30 | 03-May-24 16:30 | ALTALINK | Outage | AML 511s FB Bus 1 (AML 511s Crossings), AML 511s ACF11 (AML 511s Crossings), AML 511s ACF12 (AML 511s Crossings), AML 511s ACF13 (AML 511s Crossings), AML 511s T30 (AML 511s Crossings), AML 511s SVC Plus (AML 511s Crossings), AML 511s 5352 (AML 511s Crossings), AML 511s 5252 (AML 511s Crossings), AML 511s 82 (AML 511s Crossings), AML 511s 81 (AML 511s Crossings) | annual inspections, bird mitigation | 4.38 Days
Continuous |
|
29-Apr-24 08:00 | 19-May-24 18:00 | ENMAX | Outage | 2.82L (SS-2 - SS-5), 1.84L (SS-1 - SS-5), 5.7TR (SS-5), 5.5TR (SS-5), 5B138-5BT7 (SS-5), 5B138-1.84 (SS-5), 5B138-2.82 (SS-5), 5MD138-5.5TR (SS-5), 5MD138-5.7TR (SS-5), 2MD138-2.82 (SS-2) | 138kV disconnect switch replacement and substation washing | 20.42 Days
Continuous |
|
29-Apr-24 08:00 | 10-May-24 16:00 | ENMAX | Outage | 1.83L (SS-1 - SS-8), 8B138-3A0 (SS-8), 8B138-4A0 (SS-8) | SS-8 protection work | 11.33 Days
Continuous |
|
29-Apr-24 08:00 | 02-May-24 17:00 | ALTALINK | TE | 535s RTU/SCADA (535s Joffre) | download new configurations and make LAN modifications | 3.38 Days
Continuous |
|
29-Apr-24 08:00 | 02-May-24 17:00 | ALTALINK | TE | 244s Protection & Control (244s Bowmanton) | removing protections one at a time to install and commission new circuits and protections | 3.38 Days
Daily |
|
29-Apr-24 08:00 | 02-May-24 17:00 | ALTALINK | TE | 244s Protection & Control (244s Bowmanton) | removing protections one at a time to install and commission new circuits and protections | 3.38 Days
Daily |
|
29-Apr-24 08:00 | 05-May-24 16:00 | ALTALINK, TRANSALTA | Outage | 33s T1 (33s Spray) | preventive maintenance | 6.33 Days
Continuous |
|
29-Apr-24 08:00 | 30-Apr-24 17:00 | ALTALINK | TE | 39s RTU/SCADA (39s Bickerdike) | RTU database update | 1.38 Days
Daily |
|
29-Apr-24 08:00 | 29-Apr-24 16:00 | ATCO | RB | 7L82 (788s Hotchkiss - 855s Hamburg), 7L82 (853s Ring Creek - 855s Hamburg) | inspect 7L51D2 and reinstall the guy wire | 8 Hours
Continuous |
|
29-Apr-24 08:00 | 29-Apr-24 16:00 | ATCO | RB | 7L51 (788s Hotchkiss - 927s Buchanan Creek) | inspect 7L51D2 and reinstall the guy wire | 8 Hours
Continuous |
|
29-Apr-24 08:00 | 09-May-24 17:00 | ALTALINK | TE | 55s RTU/SCADA (55s Olds) | download new configurations for breaker replacement work | 10.38 Days
Continuous |
|
29-Apr-24 08:00 | 30-Apr-24 17:00 | ALTALINK | TE | 62s RTU/SCADA (62s Brazeau Plant) | investigate a solution for the inaccurate 240 kV bus voltage and fix DNP comm fail for revenue meters T1/T2 | 1.38 Days
Daily |
|
29-Apr-24 08:00 | 10-Jun-24 17:00 | ATCO | IO | 755s Protection & Control (755s Cordel) | change relay settings at 755s on 9L16 protection | 42.38 Days
Continuous |
|
29-Apr-24 09:00 | 02-May-24 12:00 | ATCO | RB | 7L54 (794s Valleyview - 813s Little Smoky) | walk up and climbing inspection | 3.13 Days
Continuous |
|
29-Apr-24 09:00 | 05-May-24 17:00 | ATCO | TE | 728s Protection & Control (728s Mercer Hill), 728s RTU/SCADA (728s Mercer Hill) | protection and RTU updates | 6.33 Days
Continuous |
|
29-Apr-24 09:00 | 02-May-24 15:00 | ALTALINK | Outage | 122s T3 (122s Alberta Newsprint) | repair oil leaks and oil leak mitigation | 3.25 Days
Continuous |
|
29-Apr-24 09:30 | 29-Apr-24 16:30 | ALTALINK | Outage | 58s C1 (58s Edson) | replace 3 capacitors and weed spraying | 7 Hours
Daily |
|
29-Apr-24 10:00 | 06-May-24 17:30 | ATCO | Outage | 813s SVC (813s Little Smoky), 813s 719 (813s Little Smoky) | SVC valve cooling improvements | 7.31 Days
Continuous |
|
29-Apr-24 10:00 | 03-May-24 16:00 | ATCO | Outage | 951s SVC (951s Thickwood), 951s 901T (951s Thickwood Hills), 951s 902T (951s Thickwood Hills), 951s 919 (951s Thickwood Hills) | breakers trip coil testing and transformers SPR testing | 4.25 Days
Continuous |
|
29-Apr-24 11:00 | 02-May-24 17:00 | ALTALINK | TE | 320p RTU/SCADA (320P Keephills) | investigate failed SMP | 3.25 Days
Daily |
|
29-Apr-24 11:00 | 30-Apr-24 17:00 | ALTALINK | TE | 275s Protection & Control (275s Jenner) | replace redundant bus protection relays | 30 Hours
Daily |
|
29-Apr-24 11:00 | 02-May-24 17:00 | ALTALINK | TE | 297s Protection & Control (297s Rimbey) | isolating relays during the T1 outage | 3.25 Days
Daily |
|
29-Apr-24 13:00 | 02-May-24 17:30 | ALTALINK | Outage | 297s T1 (297s Rimbey) | transformer maintenance | 3.19 Days
Continuous |
|
29-Apr-24 14:00 | 09-May-24 17:00 | ALTALINK | Outage | 55s T1 (55s Olds) | breaker and switches replacements | 10.13 Days
Continuous |
|
29-Apr-24 14:01 | 10-Jun-24 14:00 | ATCO | Outage | 863s 901T (863s Paintearth) | protection upgrade | 42 Days
Continuous |
|
30-Apr-24 07:00 | 30-Apr-24 17:00 | ENMAX | RB | 16.60L (SS-16 - SS-34) | tree trimming | 10 Hours
Daily |
|
30-Apr-24 07:00 | 02-May-24 17:00 | ALTALINK | TE | 199s Protection & Control (199s East Airdrie) | 688L and RAS51 relays settings update | 2.42 Days
Continuous |
|
30-Apr-24 07:00 | 02-May-24 17:00 | ENMAX, ALTALINK | TE | 653s Protection & Control (653s Summit) | 688L, RAS49, RAS50 relays settings update | 2.42 Days
Continuous |
|
30-Apr-24 07:00 | 02-May-24 17:00 | ALTALINK, GLPC | TE | 1055s Protection & Control (1055s Sollair) | 688L, RAS49, RAS50, RAS51 relays settings update | 2.42 Days
Continuous |
|
30-Apr-24 08:00 | 02-May-24 17:00 | ALTALINK | Outage | 853L (504s Queenstown - 853AL tap) | Hardware tighten structures 232, 233, 243, 251, 260, 261, 273, 276, 282, 284, 288, 290, 291, 295, 316, 321 & 325. | 2.38 Days
Continuous |
|
30-Apr-24 08:00 | 30-Apr-24 15:00 | ALTALINK | Outage | 865L (38s East Edmonton - 216s Knightsbridge) | replace VSR on 865L at 216s and site checks at 216s | 7 Hours
Daily |
|
30-Apr-24 08:00 | 01-May-24 17:00 | ALTALINK | TE | 225s RTU/SCADA (225s Magrath) | updating RTU configuration for implementation of 863L & 225L fault reporting to SCADA | 1.38 Days
Daily |
|
30-Apr-24 08:00 | 30-Apr-24 16:00 | ALTALINK, CascadeP | TE | AltaLink Telecom Equipment, 39s RTU/SCADA (39s Bickerdike), 346s RTU/SCADA (346s Kaybob), 355s RTU/SCADA (355s Chevron Knight), 122s RTU/SCADA (122s Alberta Newsprint), 602s RTU/SCADA (602s Cold Creek), 338s RTU/SCADA (338s Cherhill), 1012s RTU/SCADA (1012s Deer Hill), 1047s RTU/SCADA (1047s Whisky Jack) | upgrade 338s - 9356R MW Radio | 8 Hours
Daily |
|
30-Apr-24 08:00 | 30-Apr-24 17:00 | ALTALINK | TE | 498s RTU/SCADA (498s Tilley), AltaLink Telecom Equipment | This is for access and outage to 9466R to complete a raw socket conversion on 7705A, as well as install 2 LAN Switches. 498s Visibility will be lost for 2 hrs. | 9 Hours
Daily |
|
30-Apr-24 08:00 | 30-Apr-24 18:00 | ALTALINK | TE | AltaLink Telecom Equipment, 256s RTU/SCADA (256s Harmattan), 238s RTU/SCADA (238s Shell Harmattan), 373s RTU/SCADA (373s Madden), 531s RTU/SCADA (531s Shell Schrader Creek) | 9433R and 9433R-7705A&B will be out of service one at a time for 4 hours for the upgrade. Will impact supervisory at 256s, 238s, 373s, 531s & 634s for 4hrs. Also 9004R Ops Lan will be OOS for 4hrs. 62p (Caution AGC will be impacted) & all other circuits will be re-routed in 50ms. | 10 Hours
Daily |
|
30-Apr-24 08:00 | 02-May-24 16:00 | ATCO | RB | 7L80 (740s H.R. Milner - 857s Kakwa Ridge), 7L80 (733s Simonette - 857s Kakwa Ridge) | reinforcing shield wire between str# 236 and 237 | 2.33 Days
Continuous |
|
30-Apr-24 08:00 | 11-May-24 16:00 | BCH | Outage | 5L72 (BCH Mica G.S. - BCH Nicola) | replace end of life spacer dampers BC Hydro maintenance does not affect the Alberta ATC | 11.33 Days
Continuous |
AB-BC |
30-Apr-24 08:30 | 30-Apr-24 15:30 | ALTALINK | TE | 225s Protection & Control (225s Magrath) | 225L B protection outage | 7 Hours
Daily |
|
30-Apr-24 08:30 | 30-Apr-24 17:30 | ALTALINK | Outage | 320p 2952 (320p Keephills) | urgent repair | 9 Hours
Daily |
|
30-Apr-24 09:00 | 30-Apr-24 10:00 | ATCO | TE | ATCO Telecom Equipment | Friedenstal_S-Telecom - move service to correct SDP | 60 Mins
Continuous |
|
30-Apr-24 09:00 | 01-May-24 16:00 | ATCO, PWLP | TE | 973s Protection & Control (973s Lanes Lake) | update relays settings pick up timer | 31 Hours
Continuous |
|
30-Apr-24 09:00 | 30-Apr-24 16:30 | ATCO | TE | ATCO RTU/SCADA | update A RTAC controller configuration | 7.5 Hours
Continuous |
|
30-Apr-24 09:00 | 01-May-24 17:00 | ALTALINK | TE | 48s Protection & Control (48s Pocaterra) | end to end testing NERC RAS AOP - CPC | 1.33 Days
Daily |
|
30-Apr-24 10:00 | 02-May-24 16:00 | ATCO | IO | 939s 1213R (939s Livock) | testing spare reactor only | 2.25 Days
Continuous |
|
30-Apr-24 10:00 | 30-Apr-24 17:00 | ENMAX, ALTALINK | RB | 50L (44s Bearspaw Plant - SS-21) | facilitate climbing an energized structure to inspect woodpecker holes | 7 Hours
Daily |
|
30-Apr-24 10:00 | 30-Apr-24 16:00 | ALTALINK | RB | 804L (40s 803L tap - 86s 803L tap), 804L (40s Wetaskiwin - 40s 803L tap), 804L (86s Bigstone - 86s 803L tap) | urgent repair - damaged downlead and burnt structure at 804L12 | 6 Hours
Daily |
|
01-May-24 00:00 | 03-May-24 00:00 | SUNCOR | TE | 29EDD-18 29PT-101 (29EDD-18 Firebag) | FB - 29EDD-18 29PT-101 Beckwith Relay Fail. Replace adapter panel for Beckwith relay with a new adapter panel. | 2 Days
Continuous |
|
01-May-24 00:00 | 02-May-24 00:00 | ALTALINK | TE | 618s RTU/SCADA (618s Riverbend) | updating RTU for 2021 fault reporting data on L1/L2/L4 | 24 Hours
Daily |
|
01-May-24 07:00 | 04-Jun-24 17:30 | ALTALINK | Outage | 326s 240kV Bus 1 (326s Murray lake), 326s 152 (326s Murray Lake), 326s 352 (326s Murray Lake), 961L (326s Murray lake - 516s Forty Mile) | closing 326s open point 'C' connecting 961L to 326s | 34.44 Days
Continuous |
|
01-May-24 07:00 | 02-May-24 18:00 | ALTALINK | Outage | 408L (51s Wainwright - 252s Jarrow) | Replace crossarms and insulators at structure 273, 276, 278 & 282. | 1.46 Days
Continuous |
|
01-May-24 07:00 | 01-May-24 17:00 | ENMAX | RB | 6.82L (SS-6 - SS-41) | tree trimming | 10 Hours
Daily |
|
01-May-24 07:00 | 04-May-24 16:00 | CMH | Outage | MH-16L (MHS-2 North Industrial - MHS-16 Cousins), MHS-16 16-69KV-BKR001 (MHS-16 Cousins), MHS-16 662-DS-8001 (MHS-16 Cousins), MHS-2 MH69-224 (MHS-2 North Industrial), MHS-2 MH69-223 (MHS-2 North Industrial), MHS-2 MH69-225 (MHS-2 North Industrial), MHS-2 West Bus (MHS-2 North Industrial), MHS-2 MH69-206 (MHS-2 North Industrial), MHS-2 MH69-205 (MHS-2 North Industrial), MHS-2 MH69-204 (MHS-2 North Industrial), MHS-2 MH69-207 (MHS-2 North Industrial), MHS-2 MH69-208 (MHS-2 North Industrial), MHS-2 MH69-210 (MHS-2 North Industrial), CS21 (MHS-2 North Industrial), MH69s2 T21 (MH69s2 North Industrial), MHS-2 2S1-M (MHS-2 North Industrial), MHS-2 2S2-TB (MHS-2 North Industrial), MHS-2 MH69-217 (MHS-2 North Industrial), MHS-2 MH69-216 (MHS-2 North Industrial) | Maintenance and repair activities on overhead 69kV switches in the MHS-2 N. Industrial substation West bus. Replacement of jumper connection conductors between MH69-16L transmission line termination and the MHS-2 N. Industrial substation West bus. | 3.38 Days
Continuous |
|
01-May-24 08:00 | 01-May-24 18:00 | Syncrude | TE | Syncrude ICCP Outage | SCADA - Server Update Whole Syncrude Visibility Loss |
10 Hours
Daily |
|
01-May-24 08:00 | 07-May-24 15:00 | ALTALINK | Outage | 753L (65s High River - 253s Blackie), 65s 753E (65s High River), 253s 753W (253s Blackie) | replace structures arms and insulators and hardware tighten structures | 6.29 Days
Continuous |
|
01-May-24 08:00 | 01-May-24 18:00 | ENMAX, ALTALINK | IO | 24.81L (SS-24 - SS-31), 24.83L (74s Janet - SS-24), 24.1TR (SS-24), 24B138-24BT3 (SS-24) | Power Factor Test - 24B138-24.83-CT, 24PT138-Z31 | 10 Hours
Continuous |
|
01-May-24 08:00 | 04-Jun-24 17:00 | ALTALINK | TE | 326s RTU/SCADA (326s Murray Lake) | update configurations | 34.38 Days
Continuous |
|
01-May-24 08:00 | 01-May-24 13:00 | ALTALINK | TE | 618s Protection & Control (618s Riverbend) | B87/863L (L2) ‘B’ protection outage | 5 Hours
Daily |
|
01-May-24 08:00 | 01-May-24 13:00 | ALTALINK | TE | 225s Protection & Control (225s Magrath) | B87/863L (L1) ‘B’ protection outage | 5 Hours
Daily |
|
01-May-24 08:00 | 01-May-24 18:00 | ENMAX, ALTALINK | Outage | 24.83L (74s Janet - SS-24), 74s 24.83X (74s Janet), 74s 32 (74s Janet), 24B138-24.83 (SS-24) | power factor test | 10 Hours
Daily |
|
01-May-24 08:00 | 01-May-24 17:00 | ALTALINK | TE | AltaLink Telecom Equipment | outage to 9273R | 9 Hours
Daily |
|
01-May-24 08:00 | 02-May-24 16:00 | ENMAX | Outage | 24.1TR (SS-24) | tap changer inspection | 1.33 Days
Continuous |
|
01-May-24 08:30 | 01-May-24 17:30 | ALTALINK | Outage | 320p 3052 (320p Keephills) | urgent repair; flash over protection enabled on 500kV breaker failure relays | 9 Hours
Daily |
|
01-May-24 09:00 | 01-May-24 10:00 | ATCO | TE | ATCO Telecom Equipment, ATCO TPR Outage | move multiple protection to new services | 60 Mins
Continuous |
|
01-May-24 09:00 | 02-May-24 17:00 | BCH | Outage | 5L52 (BPA Custer - BCH Ingledow) | perform transmission line insulator maintenance & conductor testing | 1.33 Days
Continuous |
AB-BC |
01-May-24 09:00 | 01-May-24 13:00 | ALTALINK | Outage | 338s 552 (338s Cherhill) | urgent - oil sample required for investigation of high oil levels in CT5 | 4 Hours
Daily |
|
01-May-24 09:30 | 01-May-24 15:30 | ATCO | Outage | 6L03 (757s Battle River - 6L17 tap), 6L17 (759s Castor - 6L03 tap), 6L03 (775s Sullivan Lake - 6L17 tap), 757s 603 (757s Battle River) | Inspect / test / repair 6L03D2 as it has been reported that vacuum bottles not working, and is now considered DLO 759S Castor Substation off-loaded to adjacent subs |
6 Hours
Continuous |
|
01-May-24 13:00 | 01-May-24 17:00 | ALTALINK | TE | 618s Protection & Control (618s Riverbend) | A87/863L (L2) ‘A’ protection outage | 4 Hours
Daily |
|
01-May-24 13:00 | 01-May-24 17:00 | ALTALINK | TE | 225s Protection & Control (225s Magrath) | A87/863L (L1) ‘A’ protection outage | 4 Hours
Daily |
|
01-May-24 13:00 | 01-May-24 15:00 | ALTALINK | TE | AltaLink Telecom Equipment, 54s Protection & Control (54s Fort Saskatchewan) | replace failed card in 54s MPLS shelf | 2 Hours
Daily |
|
02-May-24 07:00 | 02-May-24 17:00 | ENMAX | RB | 6.82L (SS-6 - SS-41) | tree trimming | 10 Hours
Daily |
|
02-May-24 08:00 | 02-May-24 18:00 | ENMAX, ALTALINK | Outage | 20.82L (SS-20 - SS-21), 21.80L (42s Sarcee - SS-21), 21.1TR (SS-21), 21.4TR (SS-21), 21B138-20.82 (SS-21), 21B138-21.80 (SS-21), 21B69-21.4TR (SS-21), SW64 (SS-21), 21MD138-21.1TR (SS-21), 21MD138-21.4TR (SS-21) | Fall Substation Washing. Altalink required to remove AML VT4 60S100 fuses | 10 Hours
Continuous |
|
02-May-24 08:00 | 02-May-24 13:00 | ALTALINK | TE | 618s Protection & Control (618s Riverbend) | A87/725AL (L1) ‘A’ protection outage | 5 Hours
Daily |
|
02-May-24 08:00 | 02-May-24 16:00 | ENMAX | Outage | 24.82L (SS-24 - SS-65), 24B138-24.82 (SS-24), 65B138-D81 (SS-65), 65B138-D82 (SS-65) | power factor test - 65PT138-24.82 | 8 Hours
Continuous |
|
02-May-24 08:00 | 02-May-24 18:00 | ENMAX, ALTALINK | Outage | 21.80L (42s Sarcee - SS-21), 20.82L (SS-20 - SS-21), 21.1TR (SS-21), 21.4TR (SS-21), 21B138-21.80 (SS-21), 21B138-20.82 (SS-21), 21MD138-21.4TR (SS-21), 21MD138-21.1TR (SS-21) | fall substation washing | 10 Hours
Continuous |
|
02-May-24 08:00 | 02-May-24 12:00 | ATCO | RB | 7L23 (796s Nipisi - 7L23 tap), 7L23 (732s Mitsue - 7L23 tap) | lift 1 phase on 144 kV line for a high load move | 4 Hours
Continuous |
|
02-May-24 08:00 | 02-May-24 12:00 | ATCO | RB | 7L63 (780s Lubicon - 812s Norcen), 7L63 (788s Hotchkiss - 7LA63 tap), 7L63 (812s Norcen - 7LA63 tap) | lift 1 phase on 144 kV line for a high load move | 4 Hours
Continuous |
|
02-May-24 08:00 | 02-May-24 17:00 | ALTALINK | TE | 237s RTU/SCADA (237s Foothills), AltaLink Telecom Equipment | raw socket conversion on 7705A and 2 LAN switches installation | 9 Hours
Daily |
|
02-May-24 08:00 | 02-May-24 17:00 | SUNCOR | TE | 29EDD-22 RTU/SCADA (29EDD-22) | BP- updates to 29EDD-22 for line protection upgrades 29PL6-5, transformer protection upgrade | 9 Hours
Continuous |
|
02-May-24 08:00 | 02-May-24 17:00 | ALTALINK | TE | 648s Protection & Control (648s Metiskow) | standard relay maintenance | 9 Hours
Daily |
|
02-May-24 08:30 | 02-May-24 17:30 | ALTALINK | Outage | 320p 3152 (320p Keephills) | urgent repair - flash over protection enabled on 500kV breaker failure relays | 9 Hours
Daily |
|
02-May-24 09:00 | 27-May-24 17:30 | ATCO | TE | 883s RTU/SCADA (883s Gregoire) | protection upgrade and PLC replacement | 25.35 Days
Continuous |
|
02-May-24 13:00 | 02-May-24 17:00 | ALTALINK | TE | 618s Protection & Control (618s Riverbend) | A87/824L (L4) ‘A’ protection outage | 4 Hours
Daily |
|
03-May-24 07:00 | 03-May-24 17:00 | ENMAX | RB | 6.82L (SS-6 - SS-41) | tree trimming | 10 Hours
Daily |
|
03-May-24 07:00 | 03-May-24 17:00 | EPCOR | Outage | 330p 430LD1 (330p Genesee), 330p 8L10D (330p Genesee) | Functional timing tests on 430LD1 and 8L10D motorized disconnects. No planned outage to any customers as testing can be completed with disconnect live and 430LD2 bypass closed. | 10 Hours
Continuous |
|
03-May-24 08:00 | 03-May-24 12:00 | ENMAX | Outage | 1.80L (SS-1 - SS-28), 28.1TR (SS-28), 28B138-1.80 (SS-28), SW83 (SS-28), 28MD138-28.1TR (SS-28) | spring substation washing | 4 Hours
Continuous |
|
03-May-24 08:00 | 03-May-24 17:00 | ALTALINK | Outage | 821L (158s Vauxhall - 421s Hays) | Retie OHSW at structure 23. | 9 Hours
Daily |
|
03-May-24 08:00 | 03-May-24 17:00 | SUNCOR | TE | 29EDD-1 RTU/SCADA (29EDD-1 Millennium) | BP-Updates to 29EDD-1 for Line Protection upgrades 29PL6-5 | 9 Hours
Continuous |
|
03-May-24 08:00 | 03-May-24 12:00 | ALTALINK | TE | AltaLink Telecom Equipment, 197s RTU/SCADA (197s Bardo), 299s RTU/SCADA (299s Kingman), 542s RTU/SCADA (542s Ervick) | upgrade MPLS node | 4 Hours
Daily |
|
03-May-24 09:00 | 03-May-24 17:00 | BCH | Outage | 1L274 (BCH Natal - BCH Line Creek tap) | 1L274 (NTL-LCC) replace structure BC maintenance does not affect the Alberta ATC | 8 Hours
Continuous |
AB-BC |
03-May-24 09:00 | 03-May-24 17:00 | ALTALINK | IO | 887L (48s Pocaterra - 978s BCH Britt Creek) | 1L274 (NTL-LCC) Replace structure | 8 Hours
Daily |
|
03-May-24 11:00 | 03-May-24 17:00 | ATCO | RB | 7L76 (786s High Level - 832s Blumenort) | hot lift bottom phase 7L76-4 | 6 Hours
Continuous |
|
03-May-24 12:00 | 03-May-24 18:00 | ENMAX, ALTALINK | Outage | 28.80L (42s Sarcee - SS-28), 28.2TR (SS-28), 28B138-28.80 (SS-28), SW82 (SS-28), 28MD138-28.2TR (SS-28) | spring substation washing | 6 Hours
Continuous |
|
03-May-24 12:00 | 03-May-24 18:00 | ENMAX, ALTALINK | IO | 28.80L (42s Sarcee - SS-28) | spring substation washing | 6 Hours
Continuous |
|
03-May-24 12:00 | 03-May-24 18:00 | ENMAX, ALTALINK | Outage | 28.80L (42s Sarcee - SS-28) | Spring Substation Washing. | 6 Hours
Daily |
This document and the information contained herein are based upon information and data which by their nature contain a degree of uncertainty and are subject to change. In addition, this document may contain information and data from public sources and/or third parties, which have been assumed to be accurate and complete and have not been verified. Accordingly, the Independent System Operator, operating as the Alberta Electric System Operator (the "AESO") makes no warranty, representation or guarantee, express or implied, with respect to this document or the information contained herein, including, but not limited to, any warranty, representation or guarantee of accuracy, completeness, timeliness, reliability, availability, absence of computer virus, non- infringement, merchantability or suitability for any purpose. Under no circumstances will the AESO, its members, officers, employees, contractors or agents, or any of their respective affiliates, be liable for any errors or omissions in, or any losses, damages or claims whatsoever, whether in contract, tort or otherwise, arising from use of or reliance upon, this document or any information contained herein. © 2009 Alberta Electric System Operator. All rights reserved |