Alberta Electric System Operator | |
System Co-ordination Plan | |
2025-02-06 to 2025-02-14 | |
Approved Outages |
Previous Version | |
Download CSV |
From | To | Owner | Type | Element | Scheduled Activity | Date/Time Comments | Interconnection |
---|---|---|---|---|---|---|---|
05-Oct-18 08:00 | 30-Jun-26 16:00 | EPCOR | IO | C2 (Rossdale) | forced outage | Continuous |
2,825.33 Days
|
24-Oct-18 01:13 | 30-Jun-26 16:00 | EPCOR | IO | C1 (Rossdale) | forced outage | 2,806.62 Days
Continuous |
|
27-Nov-23 08:00 | 07-Mar-25 16:00 | ENMAX | Outage | 32.2TR (SS-32) | 32 sub 32.2TR 8 kV bus switchgear demolition | 466.33 Days
Continuous |
|
06-May-24 07:00 | 21-Feb-25 17:00 | EPCOR | Outage | EP 511s Victoria T1 (EP 511s Victoria) | Victoria: TX1 LCR, civil, demo, and construction | 291.46 Days
Continuous |
|
26-Jul-24 10:00 | 31-Mar-25 16:00 | ATCO | Outage | 826s 504R (826s Marguerite Lake) | emergency removal to replace failed 502R @834S | 248.25 Days
Continuous |
|
12-Aug-24 08:00 | 26-Feb-25 16:00 | ENMAX | Outage | 28.1TR (SS-28) | 28.1TR transformer replacement | 198.38 Days
Continuous |
|
23-Aug-24 13:45 | 30-Apr-25 14:29 | ALTALINK | Outage | 157s C1 (157s Lac La Biche) | forced outage | 250.03 Days
Continuous |
|
23-Sep-24 10:00 | 15-May-25 12:00 | ATCO | TE | 741s RTU/SCADA (741s Fox Creek) | RTU configuration on new and old RTU's onsite | 234.08 Days
Continuous |
|
04-Oct-24 01:05 | 05-May-25 12:00 | ATCO, ALTALINK | Outage | 840s McNeill Station, 830L (562s Cypress - 840s McNeill Station), 840s 701T (840s McNeill Station), 840s 901T (840s McNeill Station), 840s 702C (840s McNeill Station), 840s 703C (840s McNeill Station) | forced outage | 213.45 Days
Continuous |
AB-SK |
05-Oct-24 00:00 | 30-Apr-25 17:00 | BHE Canada | Outage | 120s C1 (120s Picture Butte) | forced outage | 207.71 Days
Continuous |
|
21-Oct-24 12:00 | 12-May-25 17:30 | ATCO | TE | 741s Protection & Control (741s Fox Creek) | block 144kv and 25 kv bus protection and breaker fail protection for the duration of 741s project | 203.23 Days
Continuous |
|
28-Oct-24 07:00 | 14-Feb-25 17:00 | EPCOR | TE | EP 511s Protection & Control (EP 511s Victoria) | protection blocking for protection upgrade and annual maintenance | 109.46 Days
Continuous |
|
08-Nov-24 16:00 | 07-Feb-25 17:00 | EPCOR | Outage | 816s P2404 (816s Petrolia) | P2404 vendor gas mixture repair | 91.04 Days
Continuous |
|
26-Dec-24 17:07 | 13-Feb-25 07:59 | ALTALINK | Outage | 38s C1 (38s East Edmonton) | forced outage | 48.62 Days
Continuous |
|
26-Dec-24 17:07 | 07-Feb-25 18:00 | ALTALINK | Outage | 256s C1 (256s Harmattan) | forced outage | 43.04 Days
Continuous |
|
03-Jan-25 07:00 | 07-Mar-25 17:00 | EPCOR | TE | 805s Protection & Control (805s Jasper), 805s RTU/SCADA (805s Jasper) | protection blocking for P&C maintenance at Jasper | 63.42 Days
Continuous |
|
06-Jan-25 09:30 | 21-Jun-25 18:00 | ALTALINK | Outage | 150L (42s Sarcee - 150AL tap), 42s 150W (42s Sarcee) | arctic arrow will require a GOI on 150L to rebuild the section of line from structure 47-198. | 166.31 Days
Continuous |
|
13-Jan-25 07:00 | 07-Feb-25 17:00 | EPCOR | Outage | T1 (Meadowlark) | meadowlark tx1 bay outage | 25.42 Days
Continuous |
|
13-Jan-25 07:00 | 14-Mar-25 17:00 | EPCOR | Outage | 987s T2 (987s Clover Bar), 987s C2406 (987s Clover Bar), 987s C2410 (987s Clover Bar), 987s C2409 (987s Clover Bar), 987s CC721 (987s Clover Bar), 987s CDS45 (987s Cloverbar), 987s CDS31 (987s Clover Bar) | Cloverbar TX2 and 1191L bay outage | 60.38 Days
Continuous |
|
13-Jan-25 07:00 | 04-Apr-25 17:00 | EPCOR | TE | 330p Protection & Control (330p Genesee), 330p RTU/SCADA (330p Genesee) | Genessee - 138/500 kV protection blocking for relay maintenance and configuration changes | 81.38 Days
Continuous |
|
13-Jan-25 12:00 | 07-Feb-25 16:00 | ATCO | TE | 905s Protection & Control (905s Meikle) | testing breaker fail relays, | 25.17 Days
Continuous |
|
20-Jan-25 08:00 | 10-Feb-25 17:00 | ATCO | IO | 809s RTU/SCADA (809s Louise Creek) | station controller (RTU) requires a firmware upgrade for CIP compliance | 21.38 Days
Continuous |
|
24-Jan-25 00:00 | 14-Feb-25 00:00 | ALTALINK | Outage | 74s C3 (74s Janet) | forced outage | 21 Days
Continuous |
|
25-Jan-25 08:00 | 21-Feb-25 16:00 | ENMAX | TE | Protection & Control (SS-28) | 28 sub Z31 138 kV bus differential protection outage - commission 28.1TR protection | 27.33 Days
Daily |
|
25-Jan-25 08:00 | 21-Feb-25 16:00 | ENMAX | TE | Protection & Control (SS-28) | 28 sub 138 kV autoswitching scheme outage - commission 28.1TR protection | 27.33 Days
Daily |
|
25-Jan-25 08:00 | 21-Feb-25 16:00 | ENMAX | TE | Protection & Control (SS-28) | 28 sub BMR-81 outage -commission 28.1TR protection | 27.33 Days
Daily |
|
25-Jan-25 08:00 | 21-Feb-25 16:00 | ENMAX | TE | Protection & Control (SS-28) | 28PT138-Z31 sec. outage - commission 28.1TR protection | 27.33 Days
Daily |
|
27-Jan-25 07:00 | 14-Feb-25 17:00 | EPCOR | Outage | 72RG1 (Garneau - Rossdale), T2 (Garneau), G724 (Garneau), G725 (Garneau), G726 (Garneau), RG7210 (Rossdale), GAB2 (Garneau), GDS18 (Garneau) | TX2/RG1 zone- 72 kV switchgear SF6 overhaul with GE | 18.42 Days
Continuous |
|
27-Jan-25 08:00 | 06-Feb-25 17:00 | ALTALINK | RB | 610L (83s Taber - 336s Fincastle) | setting structures adjacent to existing 610L (str 1-102) - proximity for VATD project | 10.38 Days
Daily |
|
27-Jan-25 08:00 | 07-Feb-25 16:00 | ENMAX, ALTALINK | TE | 21.80L (42s Sarcee - SS-21) | 21.80L A and B line protection outage - relay protection end to end test | 11.33 Days
Continuous |
|
28-Jan-25 09:00 | 06-Feb-25 09:00 | CUB, ALTALINK | Outage | 672s 901T (672s Fengate Co-Generation), 430s 589 (430s Ursus) | AESO compliance testing | 9 Days
Daily |
|
03-Feb-25 07:00 | 07-Feb-25 17:00 | EPCOR | Outage | T2 (Poundmaker), PM2405 (Poundmaker), PM2401 (Poundmaker) | Poundmaker: TX2 zone relay maintenance | 4.42 Days
Continuous |
|
03-Feb-25 07:00 | 04-Apr-25 17:30 | ATCO | TE | 769s Protection & Control (769s Stettler), 769s RTU/SCADA (769s Stettler) | new RTU installation at 769S | 60.4 Days
Continuous |
|
03-Feb-25 07:00 | 07-Feb-25 17:00 | EPCOR | Outage | 72RV2 (EP 511s Victoria - Rossdale), EP 511s Victoria T1 (EP 511s Victoria), EP 511s V729 (EP 511s Victoria), EP 511s V721 (EP 511s Victoria), EP 511s V722 (EP 511s Victoria), RV728 (Rossdale) | Victoria: TX1 LCR commissioning and scaffold removal and V729 relay maintenance | 4.42 Days
Continuous |
|
03-Feb-25 07:00 | 06-Feb-25 17:00 | ALTALINK | TE | AltaLink RTU/SCADA (AltaLink) | new RTU installation and commissioning for ACC connection via MPLS digital | 3.42 Days
Daily |
|
03-Feb-25 08:00 | 07-Feb-25 16:00 | ENMAX | Outage | 16.63L (SS-16 - SS-36), 36.5TR (SS-36), 36B69-16.63/36.5TR (SS-36), 16B69-16.63 (SS-16) | HV SW Replacement 36SW61 | 4.33 Days
Continuous |
|
03-Feb-25 09:00 | 28-Mar-25 17:00 | ATCO | TE | 730s RTU/SCADA (730s Rycroft) | change RTU configuration | 53.29 Days
Continuous |
|
03-Feb-25 09:00 | 06-Feb-25 16:00 | ALTALINK | Outage | 133s T1 (133s Stelco Edmonton), 133s T2 (133s Stelco Edmonton) | install grounds to provide working clearance for maintenance downstream | 3.29 Days
Daily |
|
03-Feb-25 10:00 | 07-Feb-25 16:30 | ATCO | Outage | 7L129 (710s Vermilion - 7LA129 tap) | replace structures, cross arms and insulators on 7L129 | 4.27 Days
Continuous |
|
03-Feb-25 10:00 | 17-Feb-25 17:00 | ATCO | Outage | 800s 601 (800s Friedenstal) | upgrade 6L37 21A/21B protections, new protection panel | 14.29 Days
Continuous |
|
03-Feb-25 10:00 | 06-Feb-25 16:00 | ATCO | TE | 709s Protection & Control (709s Vegreville) | relay testing PRC-005 | 3.25 Days
Continuous |
|
03-Feb-25 12:00 | 07-Feb-25 18:00 | ALTALINK | RB | 903L (17s Benalto - 320p Keephills) | proximity RB for line component replacement on 190L (STR24-417) | 4.25 Days
Daily |
|
03-Feb-25 12:00 | 07-Feb-25 18:00 | ALTALINK | Outage | 190L (17s Benalto - 320p Keephills) | component replacement on 190L (STR24-417) | 4.25 Days
Continuous |
|
03-Feb-25 12:00 | 14-Feb-25 16:00 | ATCO | TE | 934s Protection & Control (934s Black Fly) | relay testing |
11.17 Days
Continuous |
|
04-Feb-25 06:00 | 06-Feb-25 18:00 | EPCOR | Outage | 113s T1 (113s Inland Cement) | customer request | 2.5 Days
Continuous |
|
04-Feb-25 07:00 | 09-Feb-25 19:00 | ATCO | RB | 9L20 (755s Cordel - 766s Nevis) | facilitate various construction activities on CETO | 5.5 Days
Continuous |
|
04-Feb-25 07:00 | 06-Feb-25 17:00 | ALTALINK | TE | 320p RTU/SCADA (320P Keephills) | replace failed RTU | 2.42 Days
Daily |
|
04-Feb-25 08:00 | 14-Feb-25 15:00 | ATCO | TE | 800s Protection & Control (800s Friedenstal), 800s RTU/SCADA (800s Friedenstal) | CSP for upcoming scheduled outage on breaker 601 | 10.29 Days
Continuous |
|
04-Feb-25 09:00 | 11-Feb-25 17:00 | ATCO | Outage | 7L23 (796s Nipisi - 7L23 tap), 7L23 (732s Mitsue - 7L23 tap), 796s 702 (796s Nipisi) | complete CAR cross arm replacements & TCM wood pole replacements | 7.33 Days
Continuous |
|
04-Feb-25 09:00 | 16-Feb-25 17:00 | ATCO | Outage | 7L56 (725s Goose River - 738s Virginia Hills) | replacing cross arms and poles at various structures from 809S Louise Creek substation to 813S Little Smoky substation | 12.33 Days
Continuous |
|
04-Feb-25 10:00 | 07-Feb-25 16:00 | ATCO | TE | 745s Protection & Control (745s Slave Lake), 745s RTU/SCADA (745s Slave Lake) | updates to 601T relay settings or configs, relay complete testing on 6L73 and 6L99, and wiring updates to non electrical circuits | 3.25 Days
Continuous |
|
05-Feb-25 08:00 | 06-Feb-25 17:00 | ATCO | TE | 809s Protection & Control (809s Louise Creek) | 21B-50BF/7L56 firmware upgrade for CIP compliance | 1.38 Days
Continuous |
|
05-Feb-25 08:00 | 06-Feb-25 17:00 | ATCO | TE | 809s Protection & Control (809s Louise Creek) | 87TB/901T firmware upgrade for CIP compliance | 1.38 Days
Continuous |
|
05-Feb-25 08:00 | 06-Feb-25 17:30 | BHE Canada | Outage | MATL (120s Picture Butte - Montana), 120s 1052 (120s Picture Butte), 120s 1352 (120s Picture Butte) | emergency maintenance outage | 1.4 Days
Continuous |
AB-MATL |
05-Feb-25 09:00 | 06-Feb-25 16:00 | ATCO | TE | 934s Protection & Control (934s Black Fly) | PRC 240kV relay testing |
31 Hours
Continuous |
|
05-Feb-25 09:00 | 06-Feb-25 16:00 | ATCO | TE | 905s Protection & Control (905s Meikle) | PRC 21A/7L62, 21B/7L62 relay testing | 31 Hours
Continuous |
|
05-Feb-25 09:00 | 06-Feb-25 16:05 | ATCO | TE | ATCO Telecom Equipment | 1045s Garden Plain-9LA59_87L-21B_SEL-411L relay firmware upgrade and settings update | 31.08 Hours
Continuous |
|
05-Feb-25 09:00 | 06-Feb-25 16:30 | ATCO | TE | 801s Protection & Control (801s Anderson) | 87L-21B/9L59 relay firmware upgrade and settings update | 31.5 Hours
Continuous |
|
05-Feb-25 09:00 | 06-Feb-25 16:30 | ATCO | TE | 972s Protection & Control (972s Tinchebray) | 87L-21B/9L59 relay firmware upgrade and settings update | 31.5 Hours
Continuous |
|
05-Feb-25 09:00 | 06-Feb-25 17:00 | ALTALINK | TE | 67s Protection & Control (67s Stirling) | change settings for the re-build @ 344s | 1.33 Days
Daily |
|
05-Feb-25 13:00 | 14-Feb-25 15:30 | ATCO | TE | 848s Protection & Control (848s Ruth Lake), 848s RTU/SCADA (848s Ruth Lake) | commissioning new 401 breaker, may need to block protection on 901T RTU updates for new breaker alarming | 9.1 Days
Continuous |
|
05-Feb-25 13:00 | 14-Feb-25 15:30 | ATCO | Outage | 848s 401R (848s Ruth Lake), 848s 401 (848s Ruth Lake) | replace breaker 401 | 9.1 Days
Continuous |
|
06-Feb-25 00:00 | 06-Feb-25 16:30 | ALTALINK | TE | 562s Protection & Control (562s Cypress) | block trip outputs of the GE L90 relays on 658L | 16.5 Hours
Daily |
|
06-Feb-25 08:00 | 07-Feb-25 16:00 | ENMAX | Outage | 162.3TR (SS-162), 162B138-RB85 (SS-162), 162B138-RB86 (SS-162), 162MD138-162.3TR (SS-162) | maintenance on 162SW92, 162SW93, and 162.3TR | 1.33 Days
Continuous |
|
06-Feb-25 08:00 | 09-Feb-25 16:00 | Syncrude | Outage | 89-17 (Aurora), TL-1 (Aurora - Aurora) | to allow projects to tie into line to provide power to a new project | 3.33 Days
Continuous |
|
06-Feb-25 08:00 | 06-Feb-25 17:00 | ALTALINK | TE | AltaLink Telecom Equipment | repair radio | 9 Hours
Daily |
|
06-Feb-25 08:00 | 06-Feb-25 16:00 | ALTALINK | TE | 649s Protection & Control (649s Chappice Lake) | block trip outputs of the GE L90 relays on 658L | 8 Hours
Daily |
|
06-Feb-25 08:00 | 06-Feb-25 16:30 | ALTALINK | TE | 662s Protection & Control (662s Hilda) | block trip outputs of the GE L90 relays on 658L | 8.5 Hours
Daily |
|
06-Feb-25 08:30 | 06-Feb-25 17:30 | ALTALINK | Outage | 87s 1052 (87s Gaetz) | first trip and PRC005 breaker maintenance | 9 Hours
Daily |
|
06-Feb-25 09:00 | 06-Feb-25 17:00 | ATCO | TE | 717s RTU/SCADA (717S Ethel Lake), ATCO Telecom Equipment | add RS232 card | 8 Hours
Continuous |
|
06-Feb-25 10:00 | 06-Feb-25 14:00 | ALTALINK, TRANSALTA | Outage | 250p T2 (250p Bighorn Plant) | maintenance | 4 Hours
Continuous |
|
06-Feb-25 10:00 | 06-Feb-25 16:00 | ATCO | Outage | 6L05 (764s Heisler - 843s Bigknife Creek) | Replace a damaged pole. | 6 Hours
Continuous |
|
07-Feb-25 07:00 | 07-Feb-25 17:00 | EPCOR | Outage | 52s T2 (52s East Industrial), 52s E2402 (52s East Industrial) | emergency LV bushing investigation | 10 Hours
Continuous |
|
07-Feb-25 08:00 | 08-Feb-25 17:00 | ATCO | TE | 809s Protection & Control (809s Louise Creek) | 87B/700BS firmware upgrade for CIP compliance. | 1.38 Days
Continuous |
|
07-Feb-25 08:00 | 08-Feb-25 17:00 | ATCO | TE | 809s Protection & Control (809s Louise Creek) | 87TB/902T firmware upgrade for CIP compliance. | 1.38 Days
Continuous |
|
07-Feb-25 08:00 | 08-Feb-25 17:00 | ATCO | TE | 809s Protection & Control (809s Louise Creek) | 51B-27-50BF/701C firmware upgrade for CIP compliance. | 1.38 Days
Continuous |
|
07-Feb-25 08:00 | 07-Feb-25 17:00 | SUNCOR | TE | 635EDD-1001 Protection & Control (635EDD-1001) | 635PP-1006 Bus Protection A Relay B95 outage to replace its CPU, | 9 Hours
Continuous |
|
07-Feb-25 17:00 | 14-Feb-25 17:00 | EPCOR | Outage | EP 511s Victoria T1 (EP 511s Victoria), EP 511s V721 (EP 511s Victoria), EP 511s V722 (EP 511s Victoria), EP 511s VAB1 (EP 511s Victoria) | commissioning and V721 relay maintenance | 7 Days
Continuous |
|
08-Feb-25 07:00 | 08-Feb-25 18:00 | ALTALINK | Outage | 749L (648s Metiskow - 749AL tap) | Install clamp stars at structures 18, 54, 56 and 57. | 11 Hours
Daily |
|
08-Feb-25 08:00 | 13-Feb-25 16:00 | ENMAX | Outage | 39.82L (SS-39 - SS-162) | Install interphase spacers on 39.82L | 5.33 Days
Continuous |
|
08-Feb-25 10:00 | 08-Feb-25 14:00 | ENMAX | Outage | 31.1TR (SS-31) | 31.1TC - low oil alarm - top up needed | 4 Hours
Continuous |
|
08-Feb-25 14:00 | 08-Feb-25 18:00 | ENMAX | Outage | 14.4TR (SS-14) | 14.4TR -LTC low oil | 4 Hours
Continuous |
|
09-Feb-25 07:00 | 09-Feb-25 18:00 | ALTALINK | Outage | 749L (899s Edgerton - 7LB749 tap) | Urgent outage to install clamp stars at structures 345, 347 and 367. | 11 Hours
Daily |
|
09-Feb-25 08:00 | 10-Feb-25 17:00 | ATCO | TE | 809s Protection & Control (809s Louise Creek) | 21B/9L02 firmware upgrade for CIP compliance. Redundant protection will remain in service at all times. | 1.38 Days
Continuous |
|
09-Feb-25 08:00 | 10-Feb-25 17:00 | ATCO | TE | 809s Protection & Control (809s Louise Creek) | 51NGR/901T firmware upgrade for CIP compliance. Redundant protection will remain in service at all times. | 1.38 Days
Continuous |
|
10-Feb-25 07:00 | 10-Feb-25 17:00 | EPCOR | Outage | RW727 (Rossdale) | Rossdale: RW727 Breaker Maintenance | 10 Hours
Continuous |
|
10-Feb-25 07:00 | 14-Feb-25 17:00 | EPCOR | Outage | T3 (Poundmaker), PM2405 (Poundmaker), PM2404 (Poundmaker) | Poundmaker: TX3 Zone Relay Maintenance | 4.42 Days
Continuous |
|
10-Feb-25 07:00 | 16-Feb-25 19:00 | ATCO | RB | 9L20 (755s Cordel - 766s Nevis) | HOP on 9l20 to facilitate various construction activities on CETO | 6.5 Days
Continuous |
|
10-Feb-25 07:30 | 10-Feb-25 11:30 | ENMAX, ALTALINK | IO | 50L (44s Bearspaw Plant - SS-21) | Enmax to remove switch blade at SW88. Required due to SW88 not opening to 90 degrees, This allow Enmax to be able to issue SW88 To Altalink for 60s50 outage | 4 Hours
Daily |
|
10-Feb-25 08:00 | 14-Feb-25 17:00 | ALTALINK | RB | 610L (83s Taber - 336s Fincastle) | setting structures adjacent to existing 610L (STR 1-102) (Proximity) for VATD project | 4.38 Days
Daily |
|
10-Feb-25 08:00 | 13-Feb-25 17:30 | ATCO | RB | 7L09 tap | HOP on 7L09 to change rotten cross arms and poles using live line techniques | 3.4 Days
Continuous |
|
10-Feb-25 08:00 | 11-Feb-25 16:00 | ENMAX | Outage | 162B138-RB92 (SS-162), 162.4TR (SS-162), 162B138-RB94 (SS-162) | HV SW Maint. 162SW106, 162SW107, 162SW109, MD-162.4TR. Check reversing switch 162.4TR | 1.33 Days
Continuous |
|
10-Feb-25 08:00 | 11-Feb-25 16:30 | ENMAX, ALTALINK | Outage | 162.81L (391s Balzac - SS-162), 391s 162.81 (391s Balzac), 162B138-RB80 (SS-162), 162B138-RB81 (SS-162), 162MD138-162.81 (SS-162) | HV switch maintenance | 1.35 Days
Continuous |
|
10-Feb-25 08:00 | 14-Feb-25 17:00 | ATCO | TE | 749s Flyingshot Lake Protection & Control | relay settings changes to decrease the zone 2 tripping time to 15 cycles on 7L33 | 4.38 Days
Continuous |
|
10-Feb-25 08:00 | 14-Feb-25 17:00 | ATCO | TE | 845s Protection & Control (845s Big Mountain) | relay settings changes to decrease the zone 2 tripping time to 15 cycles on 7L33 | 4.38 Days
Continuous |
|
10-Feb-25 08:00 | 14-Feb-25 16:00 | ENMAX | TE | 3.82L (SS-3 - SS-8) | 3.82L A and B line protection outage. relays end to end test -138-3.82L-GE,-SEL. relay protection test 3RLY138-3.82-GE, 3RLY138-3.82-SEL. 8RLY138-3.82L-GE, 8RLY138-3.82L-SEL | 4.33 Days
Continuous |
|
10-Feb-25 08:00 | 10-Feb-25 17:00 | ALTALINK | TE | 67s Protection & Control (67s Stirling) | Online setting change. Redundant protection in service at all times. Momentary alarm as settings are changed on relay. | 9 Hours
Daily |
|
10-Feb-25 08:00 | 10-Feb-25 12:00 | ENMAX, ALTALINK | Outage | 50L (44s Bearspaw Plant - SS-21), 21.2TR (SS-21), 21.1C (SS-21), 44s 50X (44s Bearspaw Plant), 60s50 (SS-21), 21B138-21.CAP (SS-21) | urgent outage to remove 138kV bus risers from the top of SW88 (SS-21) to 21sub 138kV bus in order to provide adequate isolation for 60s50 CT replacement | 4 Hours
Continuous |
|
10-Feb-25 08:30 | 13-Feb-25 16:30 | ATCO | TE | 801s Protection & Control (801s Anderson) | working on 9L100 A and B protection relays | 3.33 Days
Continuous |
|
10-Feb-25 08:30 | 13-Feb-25 16:30 | ATCO | TE | 807s Protection & Control (807s Sheerness) | working on 9L100 A and B protection relays. | 3.33 Days
Continuous |
|
10-Feb-25 09:00 | 14-Mar-25 17:00 | BCH | Outage | T3 (BCH Natal) | NTL Station Rebuild. T3 OOS for PN replacement | 32.29 Days
Continuous |
AB-BC |
10-Feb-25 09:00 | 10-Feb-25 14:00 | ATCO | Outage | 7L92 (709s Vegreville - 7LA92 tap) | GOI required to develop work method changing a wishbone structure with the line wise live line jib. | 5 Hours
Continuous |
|
10-Feb-25 09:00 | 14-Feb-25 13:00 | ALTALINK, EPCOR | Outage | 1043L (320p Keephills - 367s Harry Smith) | Replace CVT1 and 1043L strain insulators. | 4.17 Days
Continuous |
|
10-Feb-25 09:00 | 28-Feb-25 17:00 | BCH | TE | 2L113 (BCH Cranbrook - BCH Natal), T3 (BCH Natal) | protection work | 18.33 Days
Continuous |
AB-BC |
10-Feb-25 09:00 | 10-Feb-25 17:00 | CMH | Outage | MHS-1 69kV South Bus (MHS-1 Power P Switchyard), MH-8L (MHS-1 CMH Power Plant - MHS-6 CMH Riverview) | isolation to provide clearance for a transformer being offloaded at the switchyard. | 8 Hours
Continuous |
|
10-Feb-25 09:00 | 28-Feb-25 17:00 | BCH | Outage | 2CB1 (BCH Natal) | NTL station rebuild | 18.33 Days
Continuous |
AB-BC |
10-Feb-25 09:30 | 10-Feb-25 17:30 | ATCO | TE | 790s Protection & Control (790s Poplar Hill) | microprocessor relay testing. | 8 Hours
Continuous |
|
10-Feb-25 09:30 | 10-Feb-25 14:30 | ALTALINK | RB | 860L (44s Bearspaw Plant - 291s Cochrane) | removing raptor nest from STR 56 | 5 Hours
Daily |
|
10-Feb-25 10:00 | 17-Feb-25 08:00 | ATCO | Outage | 7L32 (811s Clairmont Lake - 862s South Bezanson) | changing rotten X arms and rotten poles | 6.92 Days
Continuous |
|
10-Feb-25 10:00 | 14-Feb-25 16:30 | ATCO, ALTALINK | RB | 7L129 (526s Buffalo Creek - 7LA129 tap), 7L129 (710s Vermilion - 7LA129 tap) | replace structures and cross arms on 7L129 , live line. | 4.27 Days
Continuous |
|
10-Feb-25 10:00 | 13-Feb-25 15:30 | ATCO | Outage | 848s 604 (848s Ruth Lake), 848s 606 (848s Ruth Lake) | replace breaker 401, clearance under/around the 72KV bus is required for 401 placement | 3.23 Days
Continuous |
|
10-Feb-25 10:00 | 14-Feb-25 16:30 | ATCO, ALTALINK | RB | 7L129 (526s Buffalo Creek - 7LA129 tap) | replace structures and cross arms on 7L129 , live line | 4.27 Days
Daily |
|
10-Feb-25 10:00 | 12-Feb-25 17:00 | ALTALINK | TE | 69s Protection & Control (69s North Barrhead) | Techs will be performing redundant relay mtce. on 723L. Non-redundant mtce. will be performed on 69s 240kV BUS protection. | 2.29 Days
Daily |
|
10-Feb-25 11:00 | 12-Feb-25 17:00 | ALTALINK | TE | 954L (648s Metiskow - 650s Hansman Lake), 648s Protection & Control (648s Metiskow) | Protection repair/testing "A" out of service during protection replacement. Line prot is redundant, "B" will remain in service at all times | 2.25 Days
Continuous |
|
10-Feb-25 11:00 | 12-Feb-25 17:00 | ALTALINK | TE | 954L (648s Metiskow - 650s Hansman Lake), 650s Protection & Control (650s Hansman Lake) | Protection repair/testing "A" out of service during protection replacement. Line prot is redundant, "B" will remain in service at all times | 2.25 Days
Continuous |
|
10-Feb-25 11:00 | 13-Feb-25 17:00 | ALTALINK | TE | 648s Protection & Control (648s Metiskow) | Maintainence on A87/T3, 472L A21-P1/L8, A21-P2/L8, S51G/L8, A67G/L8, S21-P3/L8 protections. Redundant protection always in service. Maintainence on 96/552, 27-C/L8, UF 81 protections. No redundancy. | 3.25 Days
Daily |
|
10-Feb-25 12:00 | 14-Feb-25 18:00 | ALTALINK | RB | 190L (17s Benalto - 320p Keephills) | proximity 190L RB for structure replacement at 903L24 | 4.25 Days
Daily |
|
10-Feb-25 12:00 | 14-Feb-25 18:00 | ALTALINK | Outage | 903L (17s Benalto - 320p Keephills) | Structure replacement at 903L24 | 4.25 Days
Continuous |
|
10-Feb-25 12:00 | 14-Feb-25 16:00 | ATCO | TE | 939s Protection & Control (939s Livock) | PRC relay testing | 4.17 Days
Continuous |
|
10-Feb-25 12:00 | 14-Feb-25 16:00 | ATCO | TE | 934s Protection & Control (934s Black Fly) | 240kV relay testing | 4.17 Days
Continuous |
|
10-Feb-25 12:00 | 13-Feb-25 15:00 | ENMAX | Outage | 21.4TR (SS-21) | Outage required to remove 21sub bus differential relay from service. Altalink 60s50 CT replacement | 3.13 Days
Continuous |
|
10-Feb-25 12:00 | 13-Feb-25 15:00 | ENMAX | Outage | 21.1C (SS-21) | Outage required to remove 21sub bus differential relay from service. Altalink 60s50 CT replacement | 3.13 Days
Continuous |
|
10-Feb-25 12:00 | 13-Feb-25 15:00 | ENMAX | TE | Protection & Control (SS-21) | 21sub 138kV bus differential protection outage | 3.13 Days
Continuous |
|
10-Feb-25 12:01 | 13-Feb-25 15:00 | ENMAX, ALTALINK | Outage | 50L (44s Bearspaw Plant - SS-21), 60s50 (SS-21) | urgent replace CTs at breaker C60s50 | 3.12 Days
Daily |
|
11-Feb-25 07:00 | 11-Feb-25 17:30 | ALTALINK | RB | 729L (40s Wetaskiwin - 729AL tap), 729L (542s Ervick - 729AL tap), 729L (285s East Camrose - 542s Ervick) | REA to install new tap on 729L | 10.5 Hours
Daily |
|
11-Feb-25 07:30 | 12-Feb-25 17:30 | ALTALINK | RB | 719L (263s Strachan - 719AL tap), 719L (378s Shell Caroline - 719BL tap), 719L (719AL tap - 719BL tap), 719AL (581s Amoco Ricinus - 719L tap), 719BL (634s Shell Raven River - 719L tap) | inspecting woodpecker damage on STRs 253, 254, 310, 319 & 334 | 1.42 Days
Daily |
|
11-Feb-25 08:00 | 11-Feb-25 16:00 | ALTALINK | TE | 489s RTU/SCADA (489s Petro Canada Brazeau River) | fuse change required on radio | 8 Hours
Daily |
|
11-Feb-25 08:00 | 13-Feb-25 20:00 | SUNCOR | TE | 29EDD-1 952-104 (29EDD-1 Millennium) | 29EDD-1 29-952-104 PRC5 checks | 2.5 Days
Continuous |
|
11-Feb-25 08:00 | 14-Feb-25 16:00 | Syncrude | Outage | 89-26 (Aurora) | SCL - Isolate TL-2 Transmission line to allow for Projects to tie in a new Project. | 3.33 Days
Continuous |
|
11-Feb-25 08:00 | 11-Feb-25 17:00 | ALTALINK, Travers2SolarLP | TE | 991s RTU/SCADA (991s Little Bow) | fix SCADA/OT connection issues on the following relay: B87/27/L1 | 9 Hours
Daily |
|
11-Feb-25 08:00 | 11-Feb-25 17:00 | ALTALINK, Travers2SolarLP | TE | 991s Protection & Control (991s Little Bow) | relay outage to fix SCADA/OT connection issues 1005L B87/27/L1 | 9 Hours
Daily |
|
11-Feb-25 08:00 | 11-Feb-25 17:00 | ALTALINK | TE | 356s Protection & Control (356s Milo) | relay outage to isolate 1005L B87/21/79/L1 required to fix SCADA/OT connection issues at 991s | 9 Hours
Daily |
|
11-Feb-25 08:00 | 11-Feb-25 17:00 | ALTALINK | TE | 120s Protection & Control (120s Picture Butte) | relay outage to isolate 1005L B87/21/79/L1 required to fix SCADA/OT connection issues at 991s | 9 Hours
Daily |
|
11-Feb-25 08:00 | 11-Feb-25 12:00 | ENMAX | Outage | 35.1TR (SS-35) | investigate transformer protection | 4 Hours
Continuous |
|
11-Feb-25 09:00 | 21-Feb-25 17:00 | ENMAX, ALTALINK | Outage | 1109L (SS-25 - SS-65), 240kV West Bus (SS-25), 25B240-D133 (SS-25), 25B240-D136 (SS-25), 25B240-D142 (SS-25), 25B240-D141 (SS-25), 25B240-D139 (SS-25), 65MD240-1109 (SS-65) | 25s 240kV West Bus and 1109L outage required due to clearances while placing new cables onto strs (1109L STR1 and C25s). | 10.33 Days
Continuous |
|
11-Feb-25 09:00 | 21-Feb-25 17:00 | ENMAX, ALTALINK | Outage | 240kV West Bus (SS-25), 1109L (SS-25 - SS-65) | Altalink outage. 25s 240kV West Bus and 1109L outage required due to clearances while placing new cables onto strs (1109L STR1 and C25s). Enmax to install grounds at 25s. | 10.33 Days
Continuous |
|
11-Feb-25 09:30 | 11-Feb-25 17:30 | ATCO | TE | 790s Protection & Control (790s Poplar Hill) | relay testing | 8 Hours
Continuous |
|
11-Feb-25 10:00 | 13-Feb-25 16:00 | ATCO | TE | 940s Protection & Control (940s Beartrap) | relay testing | 2.25 Days
Continuous |
|
11-Feb-25 12:00 | 14-Feb-25 16:00 | ATCO | TE | 797s Protection & Control (797s Kemp River) | Addition of 86 lockout protection, commissioning/wiring on transformer protection circuits | 3.17 Days
Continuous |
|
11-Feb-25 12:00 | 11-Feb-25 16:00 | ENMAX | Outage | 3.3TR (SS-3) | investigate transformer protection | 4 Hours
Continuous |
|
12-Feb-25 06:00 | 12-Feb-25 17:00 | ATCO | IO | ATCO RTU/SCADA | SOC2 backup control centre activation system operation will perform the failover to SOC2 Edmonton. |
11 Hours
Continuous |
|
12-Feb-25 07:00 | 14-Feb-25 18:00 | ALTALINK | Outage | 702L (137s Sedgewick - 377s AML Hardisty), 137s 169X (137s Sedgewick) | Replace structures 269, 270, 329 & 330. Install bird diverters on OHSW from structure 328 to 335. | 2.46 Days
Continuous |
|
12-Feb-25 07:00 | 14-Feb-25 18:00 | ATCO | RB | 7L702 (137s Sedgewick - 757s Battle River) | AltaLink scope: replace structures 269, 270, 329 & 330. install bird diverters on OHSW from structure 328 to 335. block reclosing for AltaLink |
2.46 Days
Continuous |
|
12-Feb-25 07:00 | 12-Feb-25 17:00 | EPCOR | Outage | T1 (Woodcroft) | Woodcroft: TX1 temperature probe repair | 10 Hours
Continuous |
|
12-Feb-25 07:00 | 14-Feb-25 18:00 | ALTALINK | RB | 702L (137s Sedgewick - 377s AML Hardisty), 702L (137s Sedgewick - 757s Battle River) | installing bucket pile at structure 84 | 2.46 Days
Daily |
|
12-Feb-25 08:00 | 13-Feb-25 16:00 | ENMAX, ALTALINK | IO | 162B240-RB133 (SS-162), 918L (281s Johnson - SS-162), 162B240-RB132 (SS-162), 162MD240-918L (SS-162) | high voltage switching maintenance. 162SW135, 162SW134. MD-918L | 1.33 Days
Continuous |
|
12-Feb-25 08:00 | 13-Feb-25 16:30 | ENMAX, ALTALINK | Outage | 918L (281s Johnson - SS-162), 162B240-RB133 (SS-162), 162B240-RB132 (SS-162), 162MD240-918L (SS-162) | high voltage switching maintenance. 162SW135, 162SW134. MD-918L | 1.35 Days
Continuous |
|
12-Feb-25 08:00 | 12-Feb-25 10:00 | ATCO | TE | ATCO Telecom Equipment, 728s RTU/SCADA (728s Mercer Hill) | Transfer the Battery Bank from the DC Distribution to the Unity Rectifier. Impact to the following traffic: 845s 7L33 A&B, 811s 7L68 A&B, 845s 7L228 A&B, 845s 7L45 21B, 845s 7L46 21B, 7LA33 A&B, 728s Mercer hill RTU. | 2 Hours
Continuous |
|
12-Feb-25 08:00 | 13-Feb-25 17:00 | ALTALINK | TE | 103s Protection & Control (103s Goose Lake) | techs will be removing 103s 613L RAS 129A & B one at a time for trip logic changes. redundant protection to remain in service at all times. | 1.38 Days
Daily |
|
12-Feb-25 08:00 | 13-Feb-25 17:00 | ALTALINK | TE | 205s Protection & Control (205s Castle Rock Ridge) | techs will be removing 103s 613L RAS 129A & B one at a time for trip logic changes. redundant protection to remain in service at all times. | 1.38 Days
Daily |
|
12-Feb-25 08:00 | 14-Feb-25 16:00 | Syncrude | Outage | 1435 (Syncrude Mildred Lake), Mildred T14 (Syncrude Mildred Lake) | SCL - isolate transformer T14 for inspection and to add oil, | 2.33 Days
Continuous |
|
12-Feb-25 09:00 | 18-Feb-25 09:00 | CUB, ALTALINK | Outage | 672s 902T (672s Fengate Co-Generation), 430s 689 (430s Ursus) | AESO compliance testing | 6 Days
Daily |
|
13-Feb-25 08:00 | 13-Feb-25 17:30 | ALTALINK | Outage | 38s C1 (38s East Edmonton) | techs to troubleshoot, repair contactors and perform PRC005 maintenance on C1 cap bank breaker | 9.5 Hours
Daily |
|
13-Feb-25 08:00 | 13-Feb-25 17:00 | ALTALINK | TE | 198s Protection & Control (198s Blackfalds) | PRC maintenance | 9 Hours
Daily |
|
13-Feb-25 08:00 | 13-Feb-25 17:00 | ALTALINK | TE | 899s Protection & Control (899s Edgerton) | PRC maintenance | 9 Hours
Daily |
|
13-Feb-25 09:00 | 13-Feb-25 16:00 | ATCO | Outage | 7L50 (757s Battle River - 491L tap), 757s 709 (757s Battle River) | 7L50 pole replacement structure 214 | 7 Hours
Continuous |
|
13-Feb-25 09:00 | 13-Feb-25 16:00 | ALTALINK | TE | 244s Protection & Control (244s Bowmanton) | update RAS164 A relay setting to correct an issue | 7 Hours
Daily |
|
14-Feb-25 07:30 | 14-Feb-25 11:30 | ENMAX, ALTALINK | IO | 50L (44s Bearspaw Plant - SS-21) | enmax to add switch blade back to SW88 switch, enmax will have bus outage at 21sub to remove blade (21.2TR, 50L out of service) | 4 Hours
Daily |
|
14-Feb-25 08:00 | 16-Feb-25 20:00 | SUNCOR | TE | 29EDD-1 29EDD1s752 (29EDD-1 Millennium) | 29EDD-1 - 29EDD1s752 PRC5 checks | 2.5 Days
Continuous |
|
14-Feb-25 08:00 | 14-Feb-25 12:00 | ENMAX, ALTALINK | Outage | 50L (44s Bearspaw Plant - SS-21), 21.2TR (SS-21), 21.1C (SS-21), 44s 50X (44s Bearspaw Plant), 60s50 (SS-21) | urgent outage to restore 138kV bus risers from the top of SW88 (SS-21) to 21sub 138kV bus for 60s50 CT replacement | 4 Hours
Continuous |
|
14-Feb-25 09:00 | 14-Feb-25 16:00 | ATCO | RB | 7L696 (508s Lakesend - 892s Ribstone Creek) | HOP required to install interphase spacer on 7L696 span 191 | 7 Hours
Continuous |
|
14-Feb-25 09:00 | 14-Feb-25 16:00 | ALTALINK | RB | 696L (508s Lakesend - 892s Ribstone Creek) | install interphase spacer on 7L696 span 191 | 7 Hours
Daily |
This document and the information contained herein are based upon information and data which by their nature contain a degree of uncertainty and are subject to change. In addition, this document may contain information and data from public sources and/or third parties, which have been assumed to be accurate and complete and have not been verified. Accordingly, the Independent System Operator, operating as the Alberta Electric System Operator (the "AESO") makes no warranty, representation or guarantee, express or implied, with respect to this document or the information contained herein, including, but not limited to, any warranty, representation or guarantee of accuracy, completeness, timeliness, reliability, availability, absence of computer virus, non- infringement, merchantability or suitability for any purpose. Under no circumstances will the AESO, its members, officers, employees, contractors or agents, or any of their respective affiliates, be liable for any errors or omissions in, or any losses, damages or claims whatsoever, whether in contract, tort or otherwise, arising from use of or reliance upon, this document or any information contained herein. © 2009 Alberta Electric System Operator. All rights reserved |