| Alberta Electric System Operator | |
| System Co-ordination Plan | |
| 2026-04-16 to 2026-04-24 | |
| Approved Outages |
| Previous Version | |
| Download CSV |
| From | To | Owner | Type | Element | Scheduled Activity | Date/Time Comments | Interconnection |
|---|---|---|---|---|---|---|---|
| 26-Jul-24 10:00 | 31-Jul-26 16:00 | ATCO | Outage | 826s 504R (826s Marguerite Lake) | emergency removal to replace failed 502R @834S | 735.25 Days
Continuous |
|
| 23-Aug-24 13:45 | 21-May-26 14:29 | ALTALINK | Outage | 157s C1 (157s Lac La Biche) | forced outage | 636.03 Days
Continuous |
|
| 20-Mar-25 08:00 | 29-May-26 17:00 | ALTALINK | Outage | 256s C1 (256s Harmattan) | forced outage | 435.38 Days
Continuous |
|
| 31-Mar-25 07:00 | 01-May-26 17:00 | EPCOR | TE | Protection & Control (Woodcroft) | Woodcroft: protection blocking for merging unit and protection upgrade. | 396.42 Days
Continuous |
|
| 25-Jul-25 17:01 | 17-Apr-26 17:00 | EPCOR | Outage | T2 (EP Riverview) | bushing test failure (found during OE110184) | 266 Days
Continuous |
|
| 12-Sep-25 08:00 | 19-Jun-26 16:00 | ENMAX | Outage | 33.1TR (SS-33) | tap changer refurbishments. soak test required | 280.33 Days
Continuous |
|
| 25-Nov-25 17:46 | 18-Sep-26 18:00 | ATCO | Outage | 876s 901T (876s Brintnell) | forced outage oil leaking | 296.97 Days
Continuous |
|
| 27-Nov-25 08:30 | 27-Nov-27 16:30 | ALTALINK | TE | 89s Protection & Control (89s Ellerslie) | DSP card replacements on1057L B87/L3 and B240B1 B87/240B1 | 730.33 Days
Daily |
|
| 04-Jan-26 08:00 | 02-Sep-26 16:00 | SUNCOR | Outage | 29EDD-34 260kV Bus 29PP-45 (29EDD-34), 29EDD-34 29-952-113 (29EDD-34), 29EDD-34 29PS-216 (29EDD-34) | urgent repairs on 29PT-224 at 29EDD34 on 29PP-45 bus | 241.29 Days
Continuous |
|
| 12-Jan-26 07:00 | 03-Jul-26 17:00 | EPCOR | TE | 330p Protection & Control (330p Genesee) | protect blocking, annual relay maintenance and password changes | 172.38 Days
Continuous |
|
| 12-Jan-26 07:00 | 01-May-26 17:00 | EPCOR | TE | Protection & Control (Rossdale) | protection blocking, relay maintenance | 109.38 Days
Continuous |
|
| 17-Jan-26 11:00 | 30-Apr-26 17:00 | BHE Canada | Outage | 120s C2 (120s Picture Butte) | forced outage | 103.21 Days
Continuous |
|
| 21-Jan-26 08:00 | 30-Oct-26 16:00 | ENMAX | Outage | 5.7TR (SS-5) | 25kV switchgear replacement | 282.29 Days
Continuous |
|
| 03-Feb-26 09:00 | 30-Jun-26 17:00 | ATCO | TE | 972s RTU/SCADA (972s Tinchebray) | config changes needed throughout the CETO project | 147.29 Days
Continuous |
|
| 09-Feb-26 09:00 | 26-Jun-26 17:00 | ATCO | TE | 972s Protection & Control (972s Tinchebray) | block all 50BF protection until cutovers and associated commissioning are complete | 137.29 Days
Continuous |
|
| 06-Mar-26 17:00 | 13-Nov-26 17:00 | EPCOR | Outage | T1 (Woodcroft) | woodcroft: TX1 LCR civil | 252 Days
Continuous |
|
| 10-Mar-26 10:00 | 30-Nov-26 17:00 | ATCO | TE | 743s RTU/SCADA (743s Sarah Lake) | throughout the course of the project, different apparatus are being replaced, RTU will be blocked prior to download | 265.33 Days
Continuous |
|
| 11-Mar-26 13:45 | 19-Apr-26 16:00 | ALTALINK | Outage | 535s C1 (535s Joffre) | breaker maintenance | 39.09 Days
Continuous |
|
| 13-Mar-26 16:00 | 24-Apr-26 17:00 | ATCO | Outage | 7L122 (791s Rainbow Lake - 930s Arcenciel), 791s 701 (791s Rainbow Lake) | phase replacement | 42.04 Days
Continuous |
|
| 16-Mar-26 07:30 | 16-Apr-26 15:30 | CMH | TE | MHS-2 RTU/SCADA (MHS-2 North Industrial) | replacement of existing Axiom Scout RTAC with SEL 3350 RTAC. | 31.33 Days
Continuous |
|
| 22-Mar-26 13:00 | 30-Jun-26 17:00 | BHE Canada | Outage | 120s C1 (120s Picture Butte), 120s C2 (120s Picture Butte) | forced outage | 100.17 Days
Continuous |
|
| 28-Mar-26 12:00 | 14-May-26 17:00 | ATCO | TE | 833s RTU/SCADA (833s Mariana) | updating RTU/station controller configuration during SCADA upgrade project | 47.21 Days
Continuous |
|
| 30-Mar-26 08:30 | 04-May-26 16:30 | ALTALINK | Outage | 62s T1 (62s Brazeau Plant), 62s 1 (62s Brazeau Plant) | maintenance | 35.33 Days
Continuous |
|
| 06-Apr-26 07:00 | 01-May-26 17:00 | EPCOR | Outage | 72JM18 (EP 805s Jasper - Meadowlark), T1 (Meadowlark), M721 (Meadowlark), M722 (Meadowlark), EP 805s J722 (EP 805s Jasper), EP 805s JDS29 (EP 805s Jasper), MAB1 (Meadowlark) | Meadowlark - T1 LCR demo | 25.42 Days
Continuous |
|
| 06-Apr-26 08:00 | 16-Apr-26 16:00 | ALTALINK | Outage | 747L (37s North Calder - 711L tap), 37s 747W (37s North Calder) | P&C upgrades | 10.33 Days
Continuous |
|
| 06-Apr-26 08:00 | 16-Apr-26 16:00 | ALTALINK | TE | 37s Protection & Control (37s North Calder) | P&C protections upgrades to occur under the 37s747W GOI | 10.33 Days
Continuous |
|
| 06-Apr-26 08:00 | 19-Jun-26 16:00 | ALTALINK | TE | 37s RTU/SCADA (37s North Calder) | RTU database updates | 74.33 Days
Continuous |
|
| 07-Apr-26 07:00 | 21-Apr-26 17:00 | ALTALINK | TE | 1012s Protection & Control (1012s Deer Hill) | settings changes and testing associated with 685L line splitting | 14.42 Days
Continuous |
|
| 07-Apr-26 07:00 | 21-Apr-26 17:00 | ALTALINK | TE | 397s Protection & Control (397s Benbow) | settings changes and testing associated with L3 protection upgrades | 14.42 Days
Continuous |
|
| 07-Apr-26 07:00 | 21-Apr-26 17:00 | ALTALINK | TE | 39s Protection & Control (39s Bickerdike) | protection outages required on A21/L1 and B21/L1 (854L) protections for settings changes and testing associated with 685L line splitting | 14.42 Days
Continuous |
|
| 07-Apr-26 07:00 | 21-Apr-26 17:00 | ALTALINK | TE | 397s RTU/SCADA (397s Benbow) | alarm/control updates and testing of new L3 protections for the Berland River project | 14.42 Days
Continuous |
|
| 07-Apr-26 07:00 | 21-Apr-26 17:00 | ALTALINK | TE | 1012s RTU/SCADA (1012s Deer Hill) | alarm/control updates and testing for the Berland River project | 14.42 Days
Continuous |
|
| 07-Apr-26 09:00 | 21-Apr-26 15:00 | ALTALINK | Outage | 685L (397s Benbow - 1012s Deer Hill), 614L (397s Benbow - 328s Pine Creek), 1012s 685 (1012s Deer Hill), 397s 685 (397s Benbow), 328s 614 (328s Pine Creek), 328s 685 (328s Pine Creek) | split 685L into new 614L and 685L for in/out @ 328s, energize 328s614, 328s685, & 328s 138kV Bus 1, return temporary phase swap back to normal at flying tap location at 1012s
|
14.25 Days
Continuous |
|
| 07-Apr-26 10:00 | 20-Apr-26 16:00 | ATCO | Outage | 743s 702T (743s Sarah Lake), 743s 706 (743s Sarah Lake), 743s 502 (743s Sarah Lake) | 743S rebuild - replace breaker 502 | 13.25 Days
Continuous |
|
| 08-Apr-26 07:00 | 10-May-26 17:00 | ALTALINK, ALPAC | IO | 796L (282s Grassland - 796AL tap) | note for area assessments | 32.42 Days
Continuous |
|
| 08-Apr-26 09:00 | 22-Apr-26 17:00 | ATCO | Outage | 833s 701T (833s Mariana), 833s 701TCS (833s Mariana) | full protection and SCADA upgrades, replacement of battery bank, charger, and addition of BMS |
14.33 Days
Continuous |
|
| 09-Apr-26 17:01 | 13-May-26 07:00 | EPCOR | Outage | 72RW3 (Rossdale - Woodcroft), RW727 (Rossdale) | termination rebuild at the Woodcroft end | 33.58 Days
Continuous |
|
| 12-Apr-26 16:00 | 19-Apr-26 12:00 | ALTALINK | Outage | 525s T1 (525s Carseland) | 525sT1 doble test, maintenance, PT4 testing | 6.83 Days
Continuous |
|
| 13-Apr-26 07:00 | 17-Apr-26 17:00 | ALTALINK, EPCOR | Outage | 947L (89s Ellerslie - 987s Clover Bar), 987s C2402 (987s Clover Bar), 987s C2404 (987s Clover Bar), 89s 947 (89s Ellerslie) | Cloverbar: 947L relay maintenance | 4.42 Days
Continuous |
|
| 13-Apr-26 07:00 | 29-May-26 17:00 | EPCOR | Outage | 805s T4 (805s Jasper) | bushing replacement and fan repair | 46.42 Days
Continuous |
|
| 13-Apr-26 07:00 | 20-Apr-26 18:00 | ALTALINK | Outage | 87s 240kV West Bus (87s Gaetz), 914L (86s Bigstone - 87s Gaetz), 87s T1 (87s Gaetz), 87s 2352 (87s Gaetz), 87s 1252 (87s Gaetz), 87s 1352 (87s Gaetz), 87s 1552 (87s Gaetz), 87s 1752 (87s Gaetz) | closing open point 'I' and creating second permanent bus cut between 87s26 and 87s 240 kV west bus | 7.46 Days
Continuous |
|
| 13-Apr-26 07:00 | 17-Apr-26 17:00 | EPCOR | Outage | VHBB1 (Rossdale) | breaker fail upgrade | 4.42 Days
Continuous |
|
| 13-Apr-26 07:00 | 17-Apr-26 17:00 | EPCOR | Outage | T2 (EP Riverview), RW2402 (EP Riverview), RW2403 (EP Riverview) | T2 zone, scaffold removal | 4.42 Days
Continuous |
|
| 13-Apr-26 07:00 | 17-Apr-26 15:00 | CMH, TCPL | Outage | MH-65L (MHS-7 Brier Park - Cancarb Energy Medicine Hat), MHS-7 MH69-709 (MHS-7 Brier Park), BKR-900 (Cancarb Energy Medicine Hat) | maintenance on MH69-709 | 4.33 Days
Continuous |
|
| 13-Apr-26 07:00 | 16-Apr-26 17:00 | ALTALINK | TE | 87s RTU/SCADA (87s Gaetz) | SCADA change for CETO project | 3.42 Days
Continuous |
|
| 13-Apr-26 07:00 | 17-Apr-26 17:00 | EPCOR | TE | 72CK13 (987s Clover Bar - Kennedale) | protection blocking, relay maintenance | 4.42 Days
Continuous |
|
| 13-Apr-26 07:00 | 17-Apr-26 17:00 | EPCOR | TE | 72CK12 (987s Clover Bar - Kennedale) | protection blocking, relay maintenance | 4.42 Days
Continuous |
|
| 13-Apr-26 07:30 | 17-Apr-26 16:00 | ENMAX | IO | 2GSU-XF-001 (SS-25), 25B240-D135 (SS-25), 25B240-D134 (SS-25) | breaker maintenance | 4.35 Days
Continuous |
|
| 13-Apr-26 07:30 | 17-Apr-26 16:00 | ENMAX | Outage | 25B240-D135 (SS-25), 2GSU-XF-001 (SS-25), 25B240-D134 (SS-25) | degassing oil/oil processing | 4.35 Days
Continuous |
|
| 13-Apr-26 08:00 | 17-Apr-26 16:00 | ALTALINK, TRANSALTA, GLEI | Outage | 179s T1 (179s Gleichen), 179s 23N (179s Gleichen), 179s 52-M (179s Gleichen) | 179s t1 oil reclaim and tx maintenance | 4.33 Days
Continuous |
|
| 13-Apr-26 08:00 | 16-Apr-26 16:00 | ATCO | RB | 7L90 (741s ATC Fox Creek - 7LA90 tap), 7L90 (813s Little Smoky - 7LA90 tap) | walk up and climbing inspection | 3.33 Days
Continuous |
|
| 13-Apr-26 08:00 | 16-Apr-26 16:00 | ALTALINK | Outage | 851L (253s Blackie - 525s Carseland), 525s 851X (525s Carseland), 253s 851W (253s Blackie) | replace 525s851X breaker CTs | 3.33 Days
Continuous |
|
| 13-Apr-26 08:00 | 17-Apr-26 16:00 | ENMAX | Outage | 27.1TR (SS-27) | sub 27 PT Outage | 4.33 Days
Continuous |
|
| 13-Apr-26 08:00 | 16-Apr-26 16:00 | ATCO | RB | 7L73 (730s Rycroft - 829s Boucher Creek), 7L73 (800s Friedenstal - 829s Boucher Creek) | high load move on 7L73 str 336 | 3.33 Days
Continuous |
|
| 13-Apr-26 08:00 | 24-Apr-26 15:00 | CMH | TE | MHS-7 Protection & Control (MHS-7 Brier Park) | preventative maintenance | 11.29 Days
Continuous |
|
| 13-Apr-26 08:00 | 16-Apr-26 16:00 | ALTALINK | TE | 37s Protection & Control (37s North Calder) | trip testing | 3.33 Days
Continuous |
|
| 13-Apr-26 09:00 | 19-Apr-26 17:00 | ALTALINK, BHE, BHE Canada | Outage | MATL (120s Picture Butte - Montana), 120s 1052 (120s Picture Butte), PDB2401 (BHE Hay Lake), PDB2405 (BHE Hay Lake) | align with 1201L outage | 6.33 Days
Continuous |
AB-MATL |
| 13-Apr-26 09:00 | 23-Apr-26 17:00 | BCH | RB | 2L294 (BCH A. A. Lambert - BCH Cranbrook), 2L294 (BCH A. A. Lambert - BCH Nelway) | ANRP for tree removal | 10.33 Days
Daily |
AB-BC |
| 13-Apr-26 09:00 | 21-May-26 10:00 | ALTALINK | Outage | 157s C1 (157s Lac La Biche) | replace breaker and disconnect switch | 38.04 Days
Continuous |
|
| 13-Apr-26 10:00 | 17-Apr-26 16:00 | ATCO | Outage | 951s SVC (951s Thickwood), 951s 919 (951s Thickwood Hills), 951S 902 (951s Thickwood Hills), 951s 903 (951s Thickwood Hills), 951s 919A (951s Thickwood Hills) | maintenance/inspection of SVC | 4.25 Days
Continuous |
|
| 13-Apr-26 10:00 | 17-Apr-26 16:00 | ATCO | TE | 951s RTU/SCADA (951s Thickwood Hills) | password changes, computer patching | 4.25 Days
Continuous |
|
| 13-Apr-26 10:00 | 16-Apr-26 16:00 | ALTALINK | TE | 525s Protection & Control (525s Carseland) | protection maintenance | 3.25 Days
Continuous |
|
| 13-Apr-26 11:25 | 19-Apr-26 17:00 | ALTALINK, BCH | Outage | Path 1 (AIES Islanding), 1201L (520s Bennett - BCH Cranbrook), 5L94 (BCH Cranbrook - 520s Bennett), 520s 552 (520s Bennett), 520s 12 (520s Bennett), 5D25 (BCH Cranbrook) | BC hydro outage for insulator replacement program - 500 kV switchyard work | 6.23 Days
Continuous |
AB-BC |
| 13-Apr-26 11:25 | 19-Apr-26 17:00 | ALTALINK, BCH | Outage | 799s 786W (799s Coleman), 786L (799s Coleman - BCH Natal) | 1201L is out of service | 6.23 Days
Continuous |
AB-BC |
| 13-Apr-26 11:25 | 19-Apr-26 17:00 | ALTALINK, BCH | Outage | 48s 887X (48s Pocaterra), 887L (48s Pocaterra - 978s BCH Britt Creek) | 1201L is out of service | 6.23 Days
Continuous |
AB-BC |
| 13-Apr-26 11:30 | 16-Apr-26 16:30 | ALTALINK | Outage | 430s 352 (430s Ursus) | 430s352s CT replacement | 3.21 Days
Continuous |
|
| 13-Apr-26 13:00 | 16-Apr-26 16:00 | ALTALINK | TE | 525s RTU/SCADA (525s Carseland) | RTU maintenance | 3.13 Days
Continuous |
|
| 13-Apr-26 13:30 | 16-Apr-26 16:00 | ALTALINK | Outage | 905L (19s Wabamun - 37s North Calder), 19s 905 (19s Wabamun) | PRC5 breaker maintenance and first trip | 3.1 Days
Continuous |
|
| 14-Apr-26 07:00 | 17-Apr-26 13:00 | ATCO, CONS | Outage | 7L101 (790s Poplar Hill - 944s Lowe Lake), 790s 705 (790s Poplar Hill), 944s 7L101 (944s Lowe Lake) | maintenance | 3.25 Days
Continuous |
|
| 14-Apr-26 07:00 | 27-Apr-26 17:00 | EPCOR | Outage | 330p 500kV Bus 2 (330p Genesee), 330p 12TC2 (330p Genesee), 330p 1209 (330p Genesee), 330p 1206 (330p Genesee), 330p 1203 (330p Genesee), 330p 1211 (330p Genesee), 330p 1215 (330p Genesee), 330p 12TC2D (330p Genesee), 330p 809 (330p Genesee) | Genesee 500 kV bus 2, POW project installation | 13.42 Days
Continuous |
|
| 14-Apr-26 07:00 | 20-Apr-26 17:30 | ATCO | TE | 743s Protection & Control (743s Sarah Lake) | relay testing | 6.44 Days
Continuous |
|
| 14-Apr-26 07:00 | 20-Apr-26 17:30 | ATCO | TE | 743s Protection & Control (743s Sarah Lake) | relay testing | 6.44 Days
Continuous |
|
| 14-Apr-26 07:00 | 20-Apr-26 17:30 | ATCO | TE | 743s Protection & Control (743s Sarah Lake) | relay testing | 6.44 Days
Continuous |
|
| 14-Apr-26 08:00 | 16-Apr-26 17:00 | Lethbridge | TE | 181s Protection & Control (181s Chinook) | transfer TPR (Teleprotection) circuits from existing JMUX to new SEL ICON | 2.38 Days
Continuous |
|
| 14-Apr-26 08:00 | 17-Apr-26 17:00 | ATCO | RB | 7L137 (768s Rowley - 770s Three Hills) | climbing inspection on 7L137 | 3.38 Days
Daily |
|
| 14-Apr-26 08:00 | 16-Apr-26 16:00 | ALTALINK | TE | 370s Protection & Control (370s North Lethbridge) | move relay to new City of Lethbridge communication system | 2.33 Days
Continuous |
|
| 14-Apr-26 08:00 | 16-Apr-26 20:00 | ATCO | TE | ATCO Telecom Equipment, 939s RTU/SCADA (939s Livock), 951s RTU/SCADA (951s Thickwood Hills) | bandwidth upgrades done on site | 2.5 Days
Continuous |
|
| 14-Apr-26 09:30 | 16-Apr-26 16:00 | ALTALINK | Outage | 71s 752 (71s Lamoureux) | 138kV breaker maintenance | 2.27 Days
Continuous |
|
| 14-Apr-26 13:00 | 16-Apr-26 15:00 | ATCO | Outage | 6L02 (769s Stettler - 873s Marion Lake), 769s 601 (769s Stettler) | climbing inspection on 6L02 | 2.08 Days
Continuous |
|
| 15-Apr-26 07:00 | 16-Apr-26 17:00 | EPCOR | Outage | 72CH9 (987s Clover Bar - EP Hardisty), 987s CH722 (987s Clover Bar), H724 (EP Hardisty) | emergency valve leak repair | 1.42 Days
Continuous |
|
| 15-Apr-26 07:15 | 21-Apr-26 16:45 | ALTALINK | Outage | 790L (434s Stony Plain - 790AL tap), 434s 790 (434s Stony Plain) | transmission line maintenance | 6.4 Days
Continuous |
|
| 15-Apr-26 08:00 | 17-Apr-26 16:00 | ALTALINK | TE | 336s RTU/SCADA (336s Fincastle) | split the existing SCADA VLAN from 1 to 1 and 2, change IP address of relays | 2.33 Days
Continuous |
|
| 15-Apr-26 08:00 | 16-Apr-26 16:00 | ENMAX | Outage | 14.3TR (SS-14) | tap changer inspection - 14.3-TC, reversing switch check, oil sampling MT, TC | 1.33 Days
Continuous |
|
| 15-Apr-26 08:00 | 16-Apr-26 16:00 | ENMAX | TE | Protection & Control (SS-162) | relays, lockout testing | 1.33 Days
Daily |
|
| 15-Apr-26 12:00 | 17-Apr-26 12:00 | ATCO, Athabasca Oi | Outage | 7L182 (2009s Willow Lake - 279s AHS) | isolation for AOC to perform maintenance | 2 Days
Continuous |
|
| 16-Apr-26 08:00 | 16-Apr-26 17:00 | ALTALINK | TE | 251s RTU/SCADA (251s Whitla), AltaLink Telecom Equipment | firmware upgrade on MPLS, firewall upgrade and split the existing SCADA VLAN | 9 Hours
Continuous |
|
| 16-Apr-26 08:00 | 16-Apr-26 18:00 | ENMAX | Outage | 32.83L (SS-32 - SS-40), 26.81L (SS-26 - SS-32), 32.2TR (SS-32), 32.1TR (SS-32), 32B138-32BT5 (SS-32), 32B138-32.83 (SS-32), 32B138-26.81 (SS-32), 32MD138-32.1TR (SS-32), 32MD138-32.2TR (SS-32) | spring substation washing | 10 Hours
Continuous |
|
| 16-Apr-26 09:00 | 16-Apr-26 11:00 | ATCO | TE | ATCO Telecom Equipment, 885s RTU/SCADA (885s McMillan) | telecom upgrade | 2 Hours
Continuous |
|
| 16-Apr-26 09:00 | 16-Apr-26 17:00 | ALTALINK | Outage | 233s 6 (233s Beamer) | maintenance | 8 Hours
Continuous |
|
| 16-Apr-26 09:00 | 16-Apr-26 16:00 | ATCO | TE | 707s RTU/SCADA (707s St. Paul), ATCO Telecom Equipment | St Paul Telecom - maintenance, switching between A and B sides of the radio | 7 Hours
Continuous |
|
| 16-Apr-26 09:00 | 16-Apr-26 16:00 | ALTALINK, BCH | TE | 520s Protection & Control (520s Bennett), 1201L (520s Bennett - BCH Cranbrook) | test communication channels between 520s Bennett and Cranbrook | 7 Hours
Continuous |
|
| 16-Apr-26 11:00 | 18-Apr-26 16:00 | ALTALINK, TRANSCANADA | Outage | 782L (269s Wyndham - 525s Carseland), 525s 48 (525s Carseland), 269s 501 (269s Wyndham), 269s 502 (269s Wyndham), 269s 551 (269s Wyndham), 269s 552 (269s Wyndham) | prevent unintended trips | 2.21 Days
Continuous |
|
| 17-Apr-26 07:00 | 29-Apr-26 17:00 | EPCOR | Outage | 330P GT7 (330p Genesee), 330p 1215 (330p Genesee), 330p 1214 (330p Genesee) | POW project installation | 12.42 Days
Continuous |
|
| 17-Apr-26 07:00 | 29-Apr-26 17:00 | EPCOR | Outage | 330P GT7 (330p Genesee) | POW project installation | 12.42 Days
Continuous |
|
| 17-Apr-26 08:00 | 28-Apr-26 16:00 | ENMAX | Outage | 3.82L (SS-3 - SS-8), 3B138-3.82 (SS-3) | City of Calgary traffic light rebuild | 11.33 Days
Continuous |
|
| 17-Apr-26 08:00 | 17-Apr-26 16:00 | ALTALINK | TE | 244s RTU/SCADA (244s Bowmanton) | split the existing SCADA VLAN from 1 to 1 and 2
|
8 Hours
Continuous |
|
| 17-Apr-26 08:00 | 26-Apr-26 16:00 | Syncrude | Outage | 1834 (Syncrude Mildred Lake), 1835 (Syncrude Mildred Lake), Mildred T18 (Syncrude Mildred Lake) | T18 6-year maintenance | 9.33 Days
Continuous |
|
| 17-Apr-26 08:00 | 17-Apr-26 18:00 | ENMAX | Outage | 31.84L (SS-31 - SS-32), 32B138-32BT5 (SS-32), 32B138-31.84 (SS-32), 32.3TR (SS-32), 32MD138-32.3TR (SS-32) | spring substation washing, reversing switch check | 10 Hours
Continuous |
|
| 18-Apr-26 07:00 | 20-Apr-26 17:00 | EPCOR | RB | 1055L (629s Argyll Transfer Station - 816s Petrolia) | aerial washing program | 2.42 Days
Continuous |
|
| 18-Apr-26 07:00 | 19-Apr-26 16:00 | ATCO | Outage | 7L137 (768s Rowley - 770s Three Hills), 768s 703 (768s Rowley), 770s 702 (770s Three Hills) | sample climbing inspection, 160 poles to climb and inspect on 7L137 | 1.38 Days
Daily |
|
| 18-Apr-26 08:00 | 18-Apr-26 18:00 | ENMAX, ALTALINK | Outage | 50L (44s Bearspaw Plant - SS-21), 21.2TR (SS-21), 21.1C (SS-21), 60s50 (SS-21), 21MD138-21.2TR (SS-21) | HV switch maintenance 21SW90, spring substation washing, reversing switch check - 21.2-TC | 10 Hours
Continuous |
|
| 18-Apr-26 08:00 | 18-Apr-26 16:00 | ALTALINK | TE | 321s RTU/SCADA (321s Al Rothbauer) | split the existing SCADA VLAN from 1 to 1 and 2
|
8 Hours
Continuous |
|
| 18-Apr-26 09:00 | 18-Apr-26 17:00 | ENMAX, ALTALINK | IO | 50L (44s Bearspaw Plant - SS-21), 44s 50X (44s Bearspaw Plant) | HV switch maintenance 21SW90, spring substation washing, reversing switch check - 21.2-TC | 8 Hours
Continuous |
|
| 18-Apr-26 09:30 | 20-Apr-26 17:00 | ALTALINK, EPCOR | Outage | 1056L (89s Ellerslie - 629s Argyll Transfer Station), 240BA2 (629s Argyll Transfer Station - 814s Bellamy), 814s BDS19 (814s Bellamy) | aerial washing program | 2.31 Days
Continuous |
|
| 18-Apr-26 09:30 | 20-Apr-26 17:00 | ALTALINK, EPCOR | IO | 1056L (89s Ellerslie - 629s Argyll Transfer Station) | aerial washing program
|
2.31 Days
Continuous |
|
| 19-Apr-26 08:00 | 19-Apr-26 18:00 | ENMAX | Outage | 1.81L (SS-1 - SS-20), 20.1TR (SS-20), 20B138-1.81 (SS-20), 20BA8-20.1TR (SS-20), 20BB8-20.1TR (SS-20), SW83 (SS-20), 20MD138-20.1TR (SS-20) | spring substation washing, power factor test - 20PT138-Z31, breaker SF6 gas sample - 20B138-1.81 | 10 Hours
Continuous |
|
| 20-Apr-26 07:00 | 24-Apr-26 17:00 | EPCOR | Outage | T2 (Kennedale), K723 (Kennedale), K722 (Kennedale), KAB2 (Kennedale) | transformer T2 relay maintenance | 4.42 Days
Continuous |
|
| 20-Apr-26 07:00 | 26-Apr-26 17:00 | EPCOR | Outage | T2 (Strathcona), S722 (Strathcona), S723 (Strathcona), SAB2 (Strathcona) | transformer T2 doble and disconnect maintenance | 6.42 Days
Continuous |
|
| 20-Apr-26 07:00 | 01-May-26 17:00 | EPCOR | Outage | T4 (Rossdale), R724 (Rossdale), RR729 (Rossdale), RAB4 (Rossdale) | transformer T4 zone doble, repairs | 11.42 Days
Continuous |
|
| 20-Apr-26 07:00 | 23-Apr-26 17:00 | ALTALINK | TE | 87s RTU/SCADA (87s Gaetz) | SCADA RTU configuration update for CETO project | 3.42 Days
Continuous |
|
| 20-Apr-26 07:00 | 30-Apr-26 18:00 | ALTALINK | RB | 974L (39s Bickerdike - 310p Sundance) | transmission line maintenance | 10.46 Days
Continuous |
|
| 20-Apr-26 07:00 | 30-Apr-26 18:00 | ALTALINK | RB | 973L (39s Bickerdike - 310p Sundance) | transmission line maintenance | 10.46 Days
Continuous |
|
| 20-Apr-26 07:00 | 23-Apr-26 17:00 | ALTALINK | TE | 275s RTU/SCADA (275s Jenner) | update RTU configuration for 944L line protections | 3.42 Days
Continuous |
|
| 20-Apr-26 07:00 | 23-Apr-26 17:00 | ALTALINK | TE | 132s RTU/SCADA (132s Ware Junction) | update RTU configuration 944L line protection | 3.42 Days
Continuous |
|
| 20-Apr-26 07:00 | 23-Apr-26 17:00 | ALTALINK | TE | 1080s RTU/SCADA (1080s Raptor) | RTU configuration update for 944L protection | 3.42 Days
Continuous |
|
| 20-Apr-26 07:00 | 08-May-26 17:00 | EPCOR | TE | Protection & Control (Kennedale) | protection blocking - relay maintenance | 18.42 Days
Continuous |
|
| 20-Apr-26 07:00 | 08-May-26 17:00 | EPCOR | TE | 72CN10 (987s Clover Bar - Namao) | protection blocking - MPLS upgrade | 18.42 Days
Continuous |
|
| 20-Apr-26 07:00 | 08-May-26 17:00 | EPCOR | TE | 72CH11 (987s Clover Bar - EP Hardisty) | protection blocking - MPLS upgrade | 18.42 Days
Continuous |
|
| 20-Apr-26 07:00 | 08-May-26 17:00 | EPCOR | TE | 72CH9 (987s Clover Bar - EP Hardisty) | protection blocking - MPLS upgrade | 18.42 Days
Continuous |
|
| 20-Apr-26 07:00 | 08-May-26 17:00 | EPCOR | TE | 72KN23 (Kennedale - Namao) | protection blocking - MPLS upgrade | 18.42 Days
Continuous |
|
| 20-Apr-26 07:15 | 23-Apr-26 16:45 | ALTALINK | Outage | 37s Protection & Control (37s North Calder) | Protection upgrade (37s898) | 3.4 Days
Continuous |
|
| 20-Apr-26 08:00 | 30-Apr-26 16:00 | ALTALINK | TE | 87s Protection & Control (87s Gaetz) | setting and wiring change | 10.33 Days
Continuous |
|
| 20-Apr-26 08:00 | 30-Apr-26 16:00 | ALTALINK | IO | 87s Protection & Control (87s Gaetz) | setting and wiring change | 10.33 Days
Continuous |
|
| 20-Apr-26 08:00 | 30-Apr-26 16:00 | ALTALINK | IO | 87s Protection & Control (87s Gaetz) | setting and wiring change | 10.33 Days
Continuous |
|
| 20-Apr-26 08:00 | 23-Apr-26 16:00 | ATCO | RB | 7L60 (780s Lubicon - 827s Cranberry Lake) | walk up and climbing inspection | 3.33 Days
Continuous |
|
| 20-Apr-26 08:00 | 21-Apr-26 16:00 | ALTALINK | TE | 370s Protection & Control (370s North Lethbridge) | move relay to new city of Lethbridge communication system | 1.33 Days
Continuous |
|
| 20-Apr-26 08:00 | 21-Apr-26 17:00 | Lethbridge | TE | 181s Protection & Control (181s Chinook) | transfer TPR (teleprotection) circuits from existing JMUX to new SEL ICON | 1.38 Days
Continuous |
|
| 20-Apr-26 08:00 | 20-Apr-26 16:00 | ENMAX | Outage | 25B240-D133 (SS-25) | HV breaker maintenance, SF6 gas sample | 8 Hours
Continuous |
|
| 20-Apr-26 08:00 | 23-Apr-26 16:00 | ALTALINK | TE | 1080s Protection & Control (1080s Raptor) | protection outages on 944AL A and B protection relays to test new SCN point for differential protection fail | 3.33 Days
Continuous |
|
| 20-Apr-26 08:00 | 23-Apr-26 16:00 | ALTALINK | TE | 132s Protection & Control (132s Ware Junction) | protection outage on 944L A and B line protection relays to test new differential protection fail SCN points | 3.33 Days
Continuous |
|
| 20-Apr-26 08:00 | 23-Apr-26 16:00 | ALTALINK | TE | 275s Protection & Control (275s Jenner) | 944L A and B line protection outages, testing of new differential protection fail SCN point | 3.33 Days
Continuous |
|
| 20-Apr-26 08:00 | 21-Apr-26 17:30 | REDDEER | Outage | 217s T1 (217s North Red Deer) | transformer protection relay replacement | 1.4 Days
Continuous |
|
| 20-Apr-26 08:00 | 23-Apr-26 16:00 | ENMAX | Outage | 8.1TR (SS-8) | transformer power factor test, secondary cable test , transformer maintenance, relay fault pressure test, reversing switch check - 8.1-TC | 3.33 Days
Continuous |
|
| 20-Apr-26 08:00 | 20-Apr-26 12:00 | ENMAX | Outage | 22.81L (SS-22 - SS-39), 22.2TR (SS-22), 22B138-22.81 (SS-22), 22B138-22BT8 (SS-22), 22MD138-22.2TR (SS-22) | spring substation washing | 4 Hours
Continuous |
|
| 20-Apr-26 08:00 | 23-Apr-26 16:00 | ALTALINK | TE | 37s Protection & Control (37s North Calder) | settings change while 898L is under GOI | 3.33 Days
Continuous |
|
| 20-Apr-26 08:00 | 23-Apr-26 16:00 | ALTALINK | TE | 92s Protection & Control (92s Viscount) | settings change 92s | 3.33 Days
Continuous |
|
| 20-Apr-26 08:00 | 23-Apr-26 16:00 | ALTALINK | TE | 92s RTU/SCADA (92s Viscount) | RTU database update | 3.33 Days
Continuous |
|
| 20-Apr-26 08:00 | 23-Apr-26 17:00 | SUNCOR | Outage | 635EDD-1001 635PT-1037 (635EDD-1001) | transformer's second side equipment maintenance | 3.38 Days
Continuous |
|
| 20-Apr-26 09:00 | 27-Apr-26 17:00 | ATCO, PWLP | TE | 973s Protection & Control (973s Lanes Lake), 973s RTU/SCADA (973s Lanes Lake) | 9LA93 protection updates and testing | 7.33 Days
Continuous |
|
| 20-Apr-26 09:00 | 27-Apr-26 17:00 | ATCO | TE | 972s Protection & Control (972s Tinchebray) | 9L93 protection setting changes including updates at 973s and 615s | 7.33 Days
Continuous |
|
| 20-Apr-26 09:00 | 20-Apr-26 11:00 | ATCO | TE | ATCO Telecom Equipment, 2049s RTU/SCADA (2049s Kettle River) | Cheecham_T-Telecom/Kettle River_S-Telecom/Kinosis_S-Telecom - telecom upgrade | 2 Hours
Continuous |
|
| 20-Apr-26 09:00 | 24-Apr-26 17:00 | BCH | Outage | 5L98 (BCH Nicola - BCH Vaseux Lake) | replace emergent broken insulators | 4.33 Days
Continuous |
AB-BC |
| 20-Apr-26 09:00 | 08-May-26 17:00 | BCH | Outage | 5L98 (BCH Nicola - BCH Vaseux Lake) | replace spacer damper and insulator, BC maintenance does not affect the Alberta ATC | 18.33 Days
Continuous |
AB-BC |
| 20-Apr-26 10:00 | 24-Apr-26 16:00 | ATCO | TE | 951s RTU/SCADA (951s Thickwood Hills) | configuration changes, computer patching | 4.25 Days
Continuous |
|
| 20-Apr-26 11:00 | 23-Apr-26 15:00 | ATCO | Outage | 6L02 (765s Mannix Mine - 873s Marion Lake) | climbing inspection on 6L02 | 3.17 Days
Continuous |
|
| 20-Apr-26 11:30 | 23-Apr-26 17:00 | ALTALINK | TE | 379s Protection & Control (379s Shell Canada Waterton) | DSP card replacement and firmware upgrades on GE relays | 3.23 Days
Continuous |
|
| 20-Apr-26 12:00 | 24-Apr-26 17:00 | ATCO | Outage | 813s SVC (813s Little Smoky), 813s 719 (813s Little Smoky) | SVC maintenance | 4.21 Days
Continuous |
|
| 20-Apr-26 12:00 | 20-Apr-26 18:00 | ENMAX | Outage | 13.82L (SS-13 - SS-22), 22.3TR (SS-22), 22.1TR (SS-22), 22B138-22BT8 (SS-22), 22B138-13.82 (SS-22), 22MD138-22.1TR (SS-22), 22MD138-22.3TR (SS-22) | spring substation washing | 6 Hours
Continuous |
|
| 20-Apr-26 13:00 | 20-Apr-26 17:30 | ATCO | Trans Test | 755s 901 (755s Cordel) | PRC-005 - trip and close coil testing | 4.5 Hours
Continuous |
|
| 20-Apr-26 16:00 | 22-Apr-26 06:00 | ALTALINK | TE | AltaLink Telecom Equipment | AESO power outage will de-energize 9485R AESO Radio. 1201L, 786L & 887L BACKUP MW TELEMETRY, AESO to ACC PMU-DATA, COL ICCP to AESO PDC VLAN#1305, SYNCRUDE RTU to AESO, 218s DOW RTU AESO will be OOS for 3days. Redundant channels for swill remain available. All other channels will be rerouted in 50ms | 1.58 Days
Continuous |
|
| 21-Apr-26 07:00 | 21-Apr-26 17:00 | EPCOR | TE | APS# 172 Garneau - Meadowlark Reconfiguration Scheme | RAS - protection blocking, alarm repair | 10 Hours
Continuous |
|
| 21-Apr-26 07:30 | 21-Apr-26 12:30 | ALTALINK | Outage | 87s 152 (87s Gaetz) | demo 1652 and 2352 breaker fail trips to 87s 152 | 5 Hours
Continuous |
|
| 21-Apr-26 07:30 | 21-Apr-26 17:30 | ALTALINK | TE | 17s Protection & Control (17s Benalto) | setting changes in A77/1144AIS relay to split channel fail alarms | 10 Hours
Continuous |
|
| 21-Apr-26 08:00 | 21-Apr-26 16:00 | ALTALINK | Outage | 186s T1 (186s Dry Creek) | 186s27 and 186s12 cooper cutout replacement | 8 Hours
Continuous |
|
| 21-Apr-26 08:00 | 23-Apr-26 08:00 | ALTALINK | Outage | 244s C1 (244s Bowmanton) | replace secondary control fuses in breaker control cabinet
|
2 Days
Continuous |
|
| 21-Apr-26 08:00 | 23-Apr-26 08:00 | ALTALINK | Outage | 244s C2 (244s Bowmanton) | replace control fuses within breaker secondary cabinet
|
2 Days
Continuous |
|
| 21-Apr-26 08:00 | 23-Apr-26 08:00 | ALTALINK | Outage | 244s C3 (244s Bowmanton) | replace secondary control fuses in breaker control cabinet
|
2 Days
Continuous |
|
| 21-Apr-26 08:00 | 21-Apr-26 17:00 | ALTALINK | TE | 40s RTU/SCADA (40s Wetaskiwin), AltaLink Telecom Equipment | firmware upgrade on MPLS nodes A and B, firewall upgrade, telecom switch and firewall upgrade
|
9 Hours
Continuous |
|
| 21-Apr-26 08:00 | 24-Apr-26 16:00 | ALTALINK | TE | 618s Protection & Control (618s Riverbend) | move relay to new city of Lethbridge communication system | 3.33 Days
Continuous |
|
| 21-Apr-26 08:00 | 24-Apr-26 17:00 | Lethbridge | TE | 111s Protection & Control (111s Coalbanks), 674s Protection & Control (674s Bowron) | protection outages on 111s and 674s 725LE 'A' & 'B' protections to transfer TPR (teleprotection) circuits from existing JMUX to new SEL ICON | 3.38 Days
Continuous |
|
| 21-Apr-26 08:00 | 22-Apr-26 16:00 | ENMAX | Outage | 833L (SS-2 - SS-12), 12.2TR (SS-12), 12B138-833L (SS-12), SW83 (SS-12), 12MD138-12.2TR (SS-12) | hw sw maintenance SW81, SW82, SW83, MD-12.2TR,reversing switch check - 12.2-TC, 12B138-833L - gear box top up | 1.33 Days
Continuous |
|
| 21-Apr-26 08:00 | 21-Apr-26 16:00 | ENMAX | Outage | 25B240-D136 (SS-25) | HV breaker maintenance, SF6 gas sample | 8 Hours
Continuous |
|
| 21-Apr-26 08:00 | 21-Apr-26 16:00 | ALTALINK | TE | 40s RTU/SCADA (40s Wetaskiwin) | split the existing SCADA VLAN from 1 to 1 and 2 | 8 Hours
Continuous |
|
| 21-Apr-26 08:00 | 21-Apr-26 17:00 | ALTALINK | TE | 17s RTU/SCADA (17s Benalto) | RTU outage to upgrade RTU firmware and test new alarms from A77/1144AIS relay | 9 Hours
Continuous |
|
| 21-Apr-26 08:00 | 23-Apr-26 14:00 | ATCO | RB | 7L137 (768s Rowley - 770s Three Hills) | climbing inspection on 7L137 | 2.25 Days
Continuous |
|
| 21-Apr-26 08:00 | 21-Apr-26 17:00 | ALTALINK | Outage | 408L (51s Wainwright - 252s Jarrow), 51s 408N (51s Wainwright), 252s 408 (252s Jarrow) | 138 kV breaker maintenance | 9 Hours
Continuous |
|
| 21-Apr-26 08:00 | 22-Apr-26 16:00 | ENMAX | TE | Protection & Control (SS-162) | 162 sub 138 kV Z34 A and B (86) lockout relay and (87) bus differential protection outage - relays, lockout testing 86-Z34-A, 86-Z34-B | 1.33 Days
Daily |
|
| 21-Apr-26 08:00 | 21-Apr-26 17:00 | ALTALINK | RB | 202L (58s Edson - 178s Cynthia) | inspecting a woodpecker cavity on structure 799 | 9 Hours
Continuous |
|
| 21-Apr-26 08:30 | 23-Apr-26 16:00 | ALTALINK | TE | 394s RTU/SCADA (394s Empress) | replace T3 metering equipment | 2.31 Days
Continuous |
|
| 21-Apr-26 08:30 | 21-Apr-26 16:00 | ALTALINK | TE | 252s Protection & Control (252s Jarrow) | relay maintenance | 7.5 Hours
Continuous |
|
| 21-Apr-26 09:00 | 26-Apr-26 17:00 | ATCO, CapitalPower | Outage | 9L93 (972s Tinchebray - 9L93 tap), 9LA93 (973s Lanes Lake - 9L93 tap), 972s 904 (972s Tinchebray), 972s 905 (972s Tinchebray), 972s 9L93D1 (972s Tinchebray), 615s 9L93D2 (615s Halkirk), 615s 52T1 (615s Halkirk) | cutover and commission 9L93 protection | 5.33 Days
Continuous |
|
| 21-Apr-26 09:00 | 21-Apr-26 16:00 | ATCO | TE | ATCO Telecom Equipment, 886s RTU/SCADA (886s Updike) | Updike_S-telecom- investigate the Updike to Saskatoon radio link | 7 Hours
Continuous |
|
| 21-Apr-26 09:00 | 23-Apr-26 16:00 | ALTALINK | Outage | 394s T3 (394s Empress), 394s 36 (394s Empress) | 394sT3 CT7 replacement, cable repair | 2.29 Days
Continuous |
|
| 21-Apr-26 09:00 | 21-Apr-26 10:00 | ATCO | TE | ATCO Telecom Equipment, 780s RTU/SCADA (780s Lubicon), 869s RTU/SCADA (869s Seal Lake) | Otter Lakes NET 1 SAR OS upgrade to V21, then V22 |
60 Mins
Continuous |
|
| 21-Apr-26 09:30 | 21-Apr-26 12:00 | ATCO | Trans Test | 755s 902 (755s Cordel) | PRC-005 - trip and close coil testing | 2.5 Hours
Continuous |
|
| 21-Apr-26 09:30 | 21-Apr-26 13:30 | ALTALINK | Outage | 871L (163s Amoco Empress - 341s Sand Hills), 163s 871X (163s Amoco Empress) | PRC5 checks | 4 Hours
Continuous |
|
| 21-Apr-26 12:31 | 21-Apr-26 17:30 | ALTALINK | Outage | 87s 252 (87s Gaetz) | demo 1252 and 2352 breaker fail trips from the 87s 252 trip chain | 4.98 Hours
Continuous |
|
| 21-Apr-26 13:00 | 21-Apr-26 17:30 | ATCO | Trans Test | 755s 904 (755s Cordel) | PRC-005 - trip and close coil testing | 4.5 Hours
Continuous |
|
| 21-Apr-26 15:00 | 06-May-26 09:00 | ALTALINK | Outage | 328s 620 (328s Pine Creek), 1182s 152 (1182s Berland River), 1182s 138kV Bus 1 (1182s Berland River), 1182s C1 (1182s Berland River), 1182s C2 (1182s Berland River), 1182s T1 (1182s Berland River), 620L (1182s Berland River - 328s Pine Creek) | Complete 620L and energize new 1182s. Close 620L OPEN POINT 'A'. 1182s Cap bank testing. Soak 1182s T1 for 24 hours. Customer to take load. | 14.75 Days
Continuous |
|
| 21-Apr-26 15:00 | 03-May-26 18:00 | ALTALINK | IO | 1182s 4 (1182s Berland River) | customer advice to complete commissioning on 1182s8 | 12.13 Days
Continuous |
|
| 22-Apr-26 07:00 | 22-Apr-26 17:00 | ALTALINK | Outage | 432s 790 (432s Carvel), 790L (432s Carvel - 790AL tap) | transmission line maintenance | 10 Hours
Continuous |
|
| 22-Apr-26 07:30 | 22-Apr-26 12:30 | ALTALINK | Outage | 87s 552 (87s Gaetz) | 87s Gaetz, demo 1652 & 2352 breaker fail trips from the 87s552 trip chain | 5 Hours
Continuous |
|
| 22-Apr-26 08:00 | 22-Apr-26 17:00 | ALTALINK | TE | 288s RTU/SCADA (288s Wolf Creek), AltaLink Telecom Equipment | firmware upgrade on MPLS nodes A and B, firewall upgrade, split the existing SCADA VLAN from 1 to 1 and 2 | 9 Hours
Continuous |
|
| 22-Apr-26 08:00 | 22-Apr-26 17:00 | ALTALINK, WPLP, TRANSALTA | Outage | 503L (268s Whitecourt - 323s Whitecourt Power), 268s 503 (268s Whitecourt), 323s 52L (323s Whitecourt Power) | work on 323s3 | 9 Hours
Continuous |
|
| 22-Apr-26 08:00 | 22-Apr-26 16:00 | ALTALINK | TE | 341s Protection & Control (341s Sand Hills Sub) | PRC maintenance on 81/13B1 BE181 871L U/F line protection, perform routine site inspection | 8 Hours
Continuous |
|
| 22-Apr-26 08:00 | 23-Apr-26 17:30 | REDDEER | Outage | 217s T2 (217s North Red Deer) | transformer protection relay replacement | 1.4 Days
Continuous |
|
| 22-Apr-26 08:00 | 08-May-26 16:00 | ALTALINK | TE | 328s RTU/SCADA (328s Pine Creek) | RTU updates for changes involving 620L P&C equipment | 16.33 Days
Continuous |
|
| 22-Apr-26 08:00 | 08-May-26 16:00 | ALTALINK | TE | 328s Protection & Control (328s Pine Creek) | circuit modification and testing involving 620L P&C equipment | 16.33 Days
Continuous |
|
| 22-Apr-26 08:00 | 23-Apr-26 16:00 | ENMAX | Outage | 40.2TR (SS-40) | tap changer inspection, reversing switch check, tap changer oil filtration maintenance, oil sampling MT, TC | 1.33 Days
Continuous |
|
| 22-Apr-26 08:00 | 22-Apr-26 18:00 | ALTALINK | Outage | 127s 773W (127s Bruderheim), 127s 846X (127s Bruderheim), 127s T1 (127s Bruderheim), 127s 2 (127s Bruderheim), 127s 27 (127s Bruderheim), 127s 138kV Bus 1 (127s Bruderheim), 773L (127s Bruderheim - 308s Albchem Beaverhill Creek), 846L (127s Bruderheim - 365s Canadianoxy Astotin Creek) | 127s27 switch repair, 127s2 switch repair, 127s24,25,26,28 switch adjustment, 127s773W PRC5 maintenance & first trip | 10 Hours
Continuous |
|
| 22-Apr-26 08:15 | 22-Apr-26 17:00 | ALTALINK | Outage | 650s 952 (650s Hansman Lake) | 240kV breaker maintenance | 8.75 Hours
Continuous |
|
| 22-Apr-26 09:00 | 22-Apr-26 17:00 | ATCO | TE | 972s Protection & Control (972s Tinchebray) | cutover 901CT and 903CT cores U and V from 9L93 protection to 900BS1 protection and commission |
8 Hours
Continuous |
|
| 22-Apr-26 09:00 | 22-Apr-26 12:00 | ATCO | TE | ATCO Telecom Equipment, 815s RTU/SCADA (815s Goodfare) | Saskatoon Mtn_T-Telecom/Goodfare_S-Telecom- RADIO DIGITAL MDR 8502 PM. Impact to the following During PM: 815s RTU, 7L07 A& B, Advantage Oil & Gas Transfer Trip |
3 Hours
Continuous |
|
| 22-Apr-26 09:00 | 22-Apr-26 11:00 | ATCO, CNRL | TE | ATCO Telecom Equipment, 859s RTU/SCADA (859s Primrose), 822s Wolf Lake RTU/SCADA, 815s RTU/SCADA (815s Goodfare) | Leming Lake_S_Telecom/Wolf Lake_S-Telecom- Upgrading Leming 'A' SAR and WOLF LAKE 'A' SAR OS to v21, then v22. IMPACT TO THE FOLLOWING TRAFFIC FOR UP TO 90 MINS: 7L574 A&B, 7L35 A&B, 7L91 A&B, SPS 1161 - LEMING LAKE / ETHEL LAKE | 2 Hours
Continuous |
|
| 22-Apr-26 09:00 | 22-Apr-26 11:00 | ATCO | TE | 970s Protection & Control (970s Bourque) | Change relay settings on 7L574 to Alt settings at 970S (7L574 distance protection zone 2 delay to 0.25s for the duration of Telecom permit 2-106269/1-00516956) | 2 Hours
Continuous |
|
| 22-Apr-26 09:00 | 22-Apr-26 11:00 | ATCO | RB | 7L574 (822s Wolf Lake - 7L574 tap), 7L574 (970s Bourque - 7L574 tap), 7L35 (859s Primrose - 7L35 tap) | reclosing turned off on 7L574/7L35 for the duration of this work 1-00516956 | 2 Hours
Continuous |
|
| 22-Apr-26 09:00 | 22-Apr-26 11:00 | ATCO, CNRL | Outage | 859s RTU/SCADA (859s Primrose) | ATCO is performing radio work in 822/970S -Upgrading Leming 'A' SAR and WOLF LAKE 'A' SAR OS to v21, then v22. During this work, |
2 Hours
Continuous |
|
| 22-Apr-26 09:00 | 22-Apr-26 18:00 | ATCO, ALTALINK | RB | 9L948 (650s Hansman Lake - 863s Paintearth) | 240 kV breaker maintenance , block reclosing for AltaLink |
9 Hours
Continuous |
|
| 22-Apr-26 09:30 | 22-Apr-26 17:30 | ATCO | Outage | 755s 903 (755s Cordel) | PRC-005 - TRIP & CLOSE COIL TESTING. TCM Program. RTXP Test Switch Mitigation and Replacement: 50BF/903 @ 755S |
8 Hours
Continuous |
|
| 22-Apr-26 09:30 | 05-May-26 16:30 | ALTALINK | Outage | 126L1 (6L126 tap) | 743S Sarah lake rebuild. 72kV bus outage. Replace wood H-Frame structure and 72kV switches | 13.29 Days
Continuous |
|
| 22-Apr-26 10:00 | 05-May-26 16:00 | ATCO | Outage | 743s 72kV Bus 600BS1 (743s Sarah Lake) | 743S Sarah lake rebuild. 72kV bus outage. Replace wood H-Frame structure and 72kV switches | 13.25 Days
Continuous |
|
| 22-Apr-26 10:00 | 22-Apr-26 12:00 | ATCO | Outage | 789s 702 (789s Keg River), 7L62 (789s Keg River - 797s Kemp River) | PRC Trip Coil Testing | 2 Hours
Continuous |
|
| 22-Apr-26 12:01 | 22-Apr-26 14:00 | ATCO | Outage | 789s 704 (789s Keg River), 7L58 (789s Keg River - 905s Meikle) | PRC Trip Coil Testing | 119 Mins
Continuous |
|
| 22-Apr-26 12:30 | 22-Apr-26 17:30 | ALTALINK | Outage | 87s 852 (87s Gaetz) | 87s Gaetz, demo 1252 & 2352 breaker fail trips from the 87s852 trip chain | 5 Hours
Continuous |
|
| 23-Apr-26 03:30 | 23-Apr-26 06:30 | ALTALINK | Outage | 62s T2 (62s Brazeau Plant) | maintenance | 3 Hours
Continuous |
|
| 23-Apr-26 06:00 | 23-Apr-26 20:00 | ALTALINK | Outage | 600L (404s Peace Butte - 523s Bullshead), 404s T1 (404s Peace Butte), 404s T2 (404s Peace Butte), 523s 600 (523s Bullshead), 404s 12 (404s Peace Butte), 404s 600 (404s Peace Butte) | 404s T1 and T2 maintenance, 404sT1 bushing replacement, 600L (structure 30-131) component replacements | 14 Hours
Continuous |
|
| 23-Apr-26 07:30 | 23-Apr-26 12:30 | ALTALINK | Outage | 87s 952 (87s Gaetz) | 87s Gaetz, demo 1652 & 2352 breaker fail trips from the 87s952 trip chain | 5 Hours
Continuous |
|
| 23-Apr-26 08:00 | 23-Apr-26 17:00 | ALTALINK | TE | 331s RTU/SCADA (331s Ponoka), AltaLink Telecom Equipment | firmware upgrade on MPLS node A, firewall upgrade
|
9 Hours
Continuous |
|
| 23-Apr-26 08:00 | 23-Apr-26 16:00 | ENMAX, ALTALINK | Outage | 5s C3 (5s East Calgary), 5s C4 (5s East Calgary) | HV switch Maintenance 2-5S7E | 8 Hours
Continuous |
|
| 23-Apr-26 08:00 | 23-Apr-26 16:00 | ALTALINK | IO | 244s C2 (244s Bowmanton) | Energize C2 to update SEL protective relay KSET value with real world data | 8 Hours
Continuous |
|
| 23-Apr-26 08:00 | 24-Apr-26 16:00 | ENMAX | Outage | 16.63L (SS-16 - SS-36), 36.5TR (SS-36), 16B69-16.63 (SS-16), 36B69-16.63/36.5TR (SS-36) | HV Breaker Maintenance | 1.33 Days
Continuous |
|
| 23-Apr-26 08:00 | 23-Apr-26 16:00 | ENMAX, ALTALINK | IO | 5s C3 (5s East Calgary), 5s C4 (5s East Calgary) | ENMAX HV switch maintenance 2-5S7E | 8 Hours
Continuous |
|
| 23-Apr-26 08:00 | 24-Apr-26 16:00 | ENMAX | Outage | 3.82L (SS-3 - SS-8), 3.3TR (SS-3), 3B138-3.82 (SS-3), 5A01 (SS-8), 3MD138-3.3TR (SS-3) | Power Factor Test - 3PT138-Z31. 3.3TR MD -Mech does not open blades past 90Deg-need adjustments. (3.82L already oos) | 1.33 Days
Continuous |
|
| 23-Apr-26 08:00 | 26-Apr-26 17:00 | SUNCOR | Outage | 635EDD-1001 635PT-1036 (635EDD-1001) | 635PT-1036 outage for transformer's second side equipment maintenance | 3.38 Days
Continuous |
|
| 23-Apr-26 08:00 | 23-Apr-26 18:00 | ATCO | IO | ATCO Telecom Equipment | non redundant firewall replacement | 10 Hours
Continuous |
|
| 23-Apr-26 08:00 | 23-Apr-26 17:00 | ATCO | IO | ATCO Telecom Equipment | Vegreville_T(SCC)-Telecom- Vegreville tower upgrading dynamic load rating server | 9 Hours
Continuous |
|
| 23-Apr-26 09:00 | 23-Apr-26 16:00 | ATCO | TE | ATCO Telecom Equipment | Flashcard failure replacement. Link Facing Whitecourt |
7 Hours
Continuous |
|
| 23-Apr-26 09:00 | 24-Apr-26 17:00 | BCH | Outage | 5L98 (BCH Nicola - BCH Vaseux Lake) | 5CB51 rebuild | 1.33 Days
Continuous |
AB-BC |
| 23-Apr-26 09:00 | 23-Apr-26 16:30 | ATCO | TE | 832s RTU/SCADA (832s Blumenort) | SCADA updates for EPSS alarm and control | 7.5 Hours
Continuous |
|
| 23-Apr-26 09:00 | 23-Apr-26 10:00 | ATCO | TE | ATCO Telecom Equipment, 796s RTU/SCADA (796s Nipisi) | Nipisi_T-Telecom - upgrading NIPISI sub SAR OS to V21, then V22 | 60 Mins
Continuous |
|
| 23-Apr-26 09:30 | 23-Apr-26 16:00 | ALTALINK | Outage | 54s T3 (54s Fort Saskatchewan) | 25 kV breaker maintenance | 6.5 Hours
Continuous |
|
| 23-Apr-26 10:00 | 23-Apr-26 14:00 | ATCO | Outage | 789s 705R (789s Keg River) | PRC trip coil testing | 4 Hours
Continuous |
|
| 23-Apr-26 12:00 | 23-Apr-26 17:00 | ATCO | TE | 972s Protection & Control (972s Tinchebray) | 9L93 relays require new PT connections to accommodate CETO upgrade | 5 Hours
Continuous |
|
| 23-Apr-26 12:30 | 23-Apr-26 17:30 | ALTALINK | Outage | 87s 1052 (87s Gaetz) | 87s Gaetz, demo 1252 & 2352 breaker fail trips from the 87s1052 trip chain | 5 Hours
Continuous |
|
| 23-Apr-26 13:00 | 24-Apr-26 13:00 | ATCO | TE | 832s RTU/SCADA (832s Blumenort) | investigate 832S Blumenort SCADA configuration issues |
24 Hours
Continuous |
|
| 23-Apr-26 14:01 | 24-Apr-26 16:00 | ATCO | Outage | 789s 706C (789s Keg River) | PRC trip coil testing | 25.98 Hours
Continuous |
|
| 24-Apr-26 07:00 | 24-Apr-26 17:00 | ALTALINK, REDDEER | Outage | 464L (87s Gaetz - 209s Timberlands), 209s 464E (209s Timberlands) | replace damaged/broken insulator for 1 structure STR 13 | 10 Hours
Continuous |
|
| 24-Apr-26 07:00 | 04-May-26 17:00 | ALTALINK | Outage | 238s T1 (238s Shell Harmattan) | maintenance | 10.42 Days
Continuous |
|
| 24-Apr-26 07:00 | 25-Apr-26 17:00 | ALTALINK | Outage | 20s 113 (20s Ghost), 33s 113 (33s Spray), 113L (20s Ghost - 33s Spray) | Urgent outage to replace Structure 113L154 | 1.42 Days
Continuous |
|
| 24-Apr-26 07:30 | 24-Apr-26 16:30 | ALTALINK | RB | 778L (87s Gaetz - 217s North Red Deer) | working within close proximity on 464L | 9 Hours
Continuous |
|
| 24-Apr-26 07:30 | 25-Apr-26 16:30 | ALTALINK | RB | 3L (245s Seebe - 3AL tap), 3AL (43s Jumping Pound Junction - 3L tap), 3L (272s Springbank - 3AL tap), 3L (42s Sarcee - 272s Springbank) | 3L recloser block required for work on 113L154 | 1.38 Days
Continuous |
|
| 24-Apr-26 08:00 | 08-May-26 16:00 | Syncrude | Outage | C1 (Aurora), 31 (Aurora), 32 (Aurora), 33 (Aurora), 31B (Aurora), 32A (Aurora), 32B (Aurora) | zone 12 6 year maintenance | 14.33 Days
Continuous |
|
| 24-Apr-26 08:00 | 24-Apr-26 17:00 | ALTALINK | TE | AltaLink Telecom Equipment | firmware upgrade on MPLS node A, firewall upgrade | 9 Hours
Continuous |
| This document and the information contained herein are based upon information and data which by their nature contain a degree of uncertainty and are subject to change. In addition, this document may contain information and data from public sources and/or third parties, which have been assumed to be accurate and complete and have not been verified. Accordingly, the Independent System Operator, operating as the Alberta Electric System Operator (the "AESO") makes no warranty, representation or guarantee, express or implied, with respect to this document or the information contained herein, including, but not limited to, any warranty, representation or guarantee of accuracy, completeness, timeliness, reliability, availability, absence of computer virus, non- infringement, merchantability or suitability for any purpose. Under no circumstances will the AESO, its members, officers, employees, contractors or agents, or any of their respective affiliates, be liable for any errors or omissions in, or any losses, damages or claims whatsoever, whether in contract, tort or otherwise, arising from use of or reliance upon, this document or any information contained herein. © 2009 Alberta Electric System Operator. All rights reserved |