| Alberta Electric System Operator | |
| System Co-ordination Plan | |
| 2026-02-19 to 2026-02-27 | |
| Approved Outages |
| Previous Version | |
| Download CSV |
| From | To | Owner | Type | Element | Scheduled Activity | Date/Time Comments | Interconnection |
|---|---|---|---|---|---|---|---|
| 26-Jul-24 10:00 | 31-Jul-26 16:00 | ATCO | Outage | 826s 504R (826s Marguerite Lake) | emergency removal to replace failed 502R @834S | 735.25 Days
Continuous |
|
| 23-Aug-24 13:45 | 30-Jun-26 14:29 | ALTALINK | Outage | 157s C1 (157s Lac La Biche) | forced outage | 676.03 Days
Continuous |
|
| 20-Mar-25 08:00 | 20-Mar-26 17:00 | ALTALINK | Outage | 256s C1 (256s Harmattan) | forced outage | 365.38 Days
Continuous |
|
| 31-Mar-25 07:00 | 27-Feb-26 17:00 | EPCOR | TE | Protection & Control (Woodcroft) | Woodcroft: protection blocking for merging unit and protection upgrade. | 333.46 Days
Continuous |
|
| 14-May-25 08:00 | 13-Mar-26 16:00 | ENMAX | TE | Protection & Control (SS-32) | 32sub 138kV autoswitching protection outage | 303.33 Days
Continuous |
|
| 22-Jul-25 08:30 | 31-Mar-26 16:30 | ALTALINK | Outage | 263s C1 (263s Strachan) | forced outage | 252.33 Days
Continuous |
|
| 25-Jul-25 17:01 | 17-Apr-26 17:00 | EPCOR | Outage | T2 (EP Riverview) | bushing test failure (found during OE110184) | 266 Days
Continuous |
|
| 25-Aug-25 08:00 | 24-Feb-26 16:00 | ENMAX | Outage | 32.1TR (SS-32) | slip over CT and new power cables installation and P&C works | 183.38 Days
Continuous |
|
| 12-Sep-25 08:00 | 19-Jun-26 16:00 | ENMAX | Outage | 33.1TR (SS-33) | tap changer refurbishments. soak test required | 280.33 Days
Continuous |
|
| 27-Nov-25 08:30 | 27-Nov-27 16:30 | ALTALINK | TE | 89s Protection & Control (89s Ellerslie) | DSP card replacements on1057L B87/L3 and B240B1 B87/240B1 | 730.33 Days
Daily |
|
| 04-Jan-26 08:00 | 02-Sep-26 16:00 | SUNCOR | Outage | 29EDD-34 260kV Bus 29PP-45 (29EDD-34), 29EDD-34 29-952-113 (29EDD-34) | urgent repairs on 29PT-224 at 29EDD34 on 29PP-45 bus | 241.29 Days
Continuous |
|
| 05-Jan-26 08:00 | 22-Mar-26 16:00 | ENMAX | Outage | 1.80L (SS-1 - SS-28), 28B138-1.80 (SS-28) | 1 sub transmission line cut over | 76.29 Days
Continuous |
|
| 05-Jan-26 08:00 | 22-Mar-26 16:00 | ENMAX | Outage | 1.81L (SS-1 - SS-20), 20B138-1.81 (SS-20) | 1 sub transmission line cut over | 76.29 Days
Continuous |
|
| 08-Jan-26 15:00 | 28-Feb-26 17:00 | ALTALINK | Outage | 42s C2 (42s Sarcee) | forced outage | 51.08 Days
Daily |
|
| 12-Jan-26 07:00 | 03-Apr-26 17:00 | EPCOR | TE | 330p Protection & Control (330p Genesee) | protect blocking, annual relay maintenance and password changes | 81.38 Days
Continuous |
|
| 12-Jan-26 07:00 | 01-May-26 17:00 | EPCOR | TE | Protection & Control (Rossdale) | protection blocking, relay maintenance | 109.38 Days
Continuous |
|
| 12-Jan-26 07:00 | 03-Apr-26 17:00 | EPCOR | TE | 987s Protection & Control (987s Clover Bar) | protection blocking, relay maintenance | 81.38 Days
Continuous |
|
| 17-Jan-26 11:00 | 28-Feb-26 17:00 | BHE Canada | Outage | 120s C2 (120s Picture Butte) | forced outage | 42.25 Days
Continuous |
|
| 21-Jan-26 08:00 | 30-Oct-26 16:00 | ENMAX | Outage | 5.7TR (SS-5) | 25kV switchgear replacement | 282.29 Days
Continuous |
|
| 26-Jan-26 07:01 | 19-Feb-26 17:00 | EPCOR | Outage | T3 (Rossdale), R723 (Rossdale), R724 (Rossdale), RAB3 (Rossdale) | Rossdale: TX3 Zone, P&C Commissioning and Initial Energization | 24.42 Days
Continuous |
|
| 03-Feb-26 09:00 | 30-Jun-26 17:00 | ATCO | TE | 972s RTU/SCADA (972s Tinchebray) | config changes needed throughout the CETO project | 147.29 Days
Continuous |
|
| 06-Feb-26 07:00 | 27-Feb-26 17:30 | ALTALINK | RB | 793L (87s Gaetz - 535s Joffre) | crews will be setting structures on 986L/962L STR’s 41-56 & 24-41 and will require a Reclosure Block on 793L |
21.44 Days
Daily |
|
| 08-Feb-26 07:00 | 06-Apr-26 18:00 | ALTALINK | Outage | 799L (235s Entwistle - 443s South Mayerthorpe), 235s 799N (235s Entwistle) | 799L rebuild between Str 721B-758 (Section B) | 57.42 Days
Continuous |
|
| 09-Feb-26 08:00 | 13-Mar-26 16:00 | ENMAX | TE | Protection & Control (SS-32) | 32sub zone 31 and zone 32 bus differential protection outage | 32.29 Days
Continuous |
|
| 09-Feb-26 08:00 | 19-Feb-26 18:00 | ATCO | RB | 7L81 (791s Rainbow Lake - BCH Harvest Energy FNC Tap) | BC Hydro tree trimming | 10.42 Days
Continuous |
|
| 09-Feb-26 09:00 | 26-Jun-26 17:00 | ATCO | TE | 972s Protection & Control (972s Tinchebray) | block all 50BF protection until cutovers and associated commissioning are complete | 137.29 Days
Continuous |
|
| 14-Feb-26 08:00 | 26-Feb-26 16:00 | Syncrude | Outage | 18215 (Syncrude Mildred Lake), 1834 (Syncrude Mildred Lake), 1835 (Syncrude Mildred Lake) | perform 6-Year PM on bus 18 in Plant 31 at Mildred Lake | 12.33 Days
Continuous |
|
| 15-Feb-26 07:00 | 25-Feb-26 17:30 | ALTALINK | RB | 759L (87s Gaetz - 276s Prentiss) | stringing new lines under construction | 10.44 Days
Continuous |
|
| 16-Feb-26 07:00 | 19-Feb-26 17:00 | ALTALINK | TE | 87s RTU/SCADA (87s Gaetz) | SCADA change for CETO: adding new status, alarms, controls for new breaker 1352 & 1752 | 3.42 Days
Daily |
|
| 16-Feb-26 07:00 | 21-Feb-26 19:00 | ATCO | RB | 9L16 (755s Cordel - 972s Tinchebray) | a hold-off is required to facilitate the erection of 3 new towers and stringing for the CETO project near Tynchebray Sub | 5.5 Days
Daily |
|
| 16-Feb-26 08:00 | 22-Feb-26 20:00 | SUNCOR | TE | 29EDD-94 Protection & Control (29EDD-94 Voyageur) | updates | 6.5 Days
Continuous |
|
| 16-Feb-26 08:00 | 28-Feb-26 16:00 | ENMAX | TE | Protection & Control (SS-28) | transmission line cut over, 1.80L reconfiguration to new 1 sub- settings changes for new protection | 12.33 Days
Daily |
|
| 16-Feb-26 08:00 | 28-Feb-26 16:00 | ENMAX | TE | Protection & Control (SS-28) | transmission line cut over, 1.80L reconfiguration to new 1 sub- settings changes for new protection | 12.33 Days
Daily |
|
| 16-Feb-26 08:00 | 28-Feb-26 16:00 | ENMAX | TE | Protection & Control (SS-28) | bus differential protection outage, transmission line cut over for 1.80L reconfiguration to new 1 sub- settings changes for new protection | 12.33 Days
Daily |
|
| 17-Feb-26 06:30 | 19-Feb-26 17:30 | ALTALINK | RB | 944L (132s Ware Junction - 275s Jenner) | dress and install the 944AL1 structure within 15m of 944L | 2.46 Days
Daily |
|
| 17-Feb-26 06:30 | 19-Feb-26 17:30 | ALTALINK | RB | 951L (132s Ware Junction - 275s Jenner) | required due to proximity | 2.46 Days
Daily |
|
| 17-Feb-26 07:00 | 20-Feb-26 17:00 | EPCOR | Outage | 72CH9 (987s Clover Bar - EP Hardisty), T3 (EP Hardisty), H723 (EP Hardisty), H724 (EP Hardisty), HAB3 (EP Hardisty) | relay maintenance on TX3 | 3.42 Days
Continuous |
|
| 17-Feb-26 07:00 | 06-Mar-26 17:00 | EPCOR | Outage | T1 (Woodcroft), W721 (Woodcroft), W722 (Woodcroft), 72JW19 (EP 805s Jasper - Woodcroft) | Woodcroft TX1 LCR demo | 17.42 Days
Continuous |
|
| 17-Feb-26 07:00 | 03-Mar-26 17:00 | EPCOR | TE | EP 511s RTU/SCADA (EP 511s Victoria) | upgrade RTU | 14.42 Days
Continuous |
|
| 17-Feb-26 07:30 | 21-Feb-26 17:30 | ALTALINK | RB | 443L (55s Olds - 214s Innisfail) | structure replacements from 443L63 – 443L137 | 4.42 Days
Daily |
|
| 17-Feb-26 07:30 | 27-Feb-26 17:30 | ALTALINK | RB | 974L (39s Bickerdike - 310p Sundance) | fixing piles str 165 | 10.42 Days
Daily |
|
| 17-Feb-26 07:30 | 27-Feb-26 17:30 | ALTALINK | RB | 973L (39s Bickerdike - 310p Sundance) | fixing piles str 165 | 10.42 Days
Daily |
|
| 17-Feb-26 08:00 | 26-Feb-26 16:00 | ATCO | Outage | 7L48 (794s Valleyview - 7LA48 tap), 794s 703 (794s Valleyview) | pole and cross arm replacement | 9.33 Days
Continuous |
|
| 17-Feb-26 08:00 | 24-Feb-26 16:00 | BCH | Outage | T3 (BCH Natal) | install ETM BC Hydro maintenance does not affect Alberta ATC | 7.33 Days
Continuous |
AB-BC |
| 17-Feb-26 08:00 | 19-Feb-26 17:00 | ALTALINK | TE | AltaLink Telecom Equipment, 108s RTU/SCADA (108s Amelia) | firewall upgrade and LAN switch upgrade | 2.38 Days
Daily |
|
| 17-Feb-26 08:00 | 19-Feb-26 17:00 | ALTALINK | TE | 132s RTU/SCADA (132s Ware Junction), AltaLink Telecom Equipment | firewall upgrades | 2.38 Days
Daily |
|
| 17-Feb-26 08:00 | 20-Feb-26 16:00 | ENMAX | Outage | 832L (SS-10 - SS-12), 12.1TR (SS-12), 10B138-832 (SS-10), 12B138-832L (SS-12), 12MD138-12.1TR (SS-12) | maintenance on SW84, SW85, SW86, MD-12.1TR and reversing switch check 12.1-TC | 3.33 Days
Continuous |
|
| 17-Feb-26 08:00 | 19-Feb-26 17:00 | ALTALINK | TE | 38s Protection & Control (38s East Edmonton) | standard relay maintenance | 2.38 Days
Daily |
|
| 17-Feb-26 09:00 | 03-Mar-26 17:00 | ATCO | Outage | 972s 240kV Bus 900BS1 (972s Tinchebray) | install breaker 904 and 904CT | 14.33 Days
Continuous |
|
| 17-Feb-26 09:00 | 20-Feb-26 17:30 | ATCO | TE | 2075s Protection & Control (2075s Newell) | PRC-005 relay testing | 3.35 Days
Continuous |
|
| 17-Feb-26 09:00 | 20-Feb-26 17:30 | ATCO | TE | 2029s Protection & Control (2029s Heathfield) | PRC-005 relay testing | 3.35 Days
Continuous |
|
| 17-Feb-26 10:00 | 25-Feb-26 18:00 | ATCO | RB | 7L08 (830s Carmon - 834s Wesley Creek) | maintenance program for 32 pole changes, 21 crossarm changes and other structure deficiencies | 8.33 Days
Continuous |
|
| 17-Feb-26 10:00 | 20-Feb-26 15:00 | ATCO | TE | 749s Flyingshot Lake RTU/SCADA | RTU updates | 3.21 Days
Continuous |
|
| 17-Feb-26 10:00 | 03-Mar-26 17:00 | ATCO | TE | 972s Protection & Control (972s Tinchebray) | 9L59 and 9L16 protections need to have 901 breaker status simulated “open” over the course of 1-00484273 | 14.29 Days
Continuous |
|
| 17-Feb-26 11:00 | 19-Feb-26 17:00 | ALTALINK | TE | 428s Protection & Control (428s Namaka) | PRC maintenance | 2.25 Days
Daily |
|
| 17-Feb-26 11:30 | 19-Feb-26 17:00 | ALTALINK | TE | 681s Protection & Control (681s Bannerman) | card replacement | 2.23 Days
Daily |
|
| 17-Feb-26 12:00 | 09-Apr-26 13:31 | ATCO | TE | 882s RTU/SCADA (882s Triangle) | updating RTU/station controller configuration during SCADA upgrade project | 51.02 Days
Continuous |
|
| 17-Feb-26 13:00 | 12-Mar-26 13:00 | ATCO | TE | 733s Protection & Control (733s Simonette), 733s RTU/SCADA (733s Simonette) | tying in RAS circuits to relays, updating RTU | 22.96 Days
Continuous |
|
| 17-Feb-26 17:30 | 05-Mar-26 17:30 | ALTALINK | RB | 202L (178s Cynthia - 202AL tap), 202L (61s Lodgepole - 202AL tap) | safety requirement; create/close 202L open point 'B' | 16 Days
Continuous |
|
| 18-Feb-26 08:00 | 19-Feb-26 17:00 | ALTALINK | TE | 28s Protection & Control (28s West Brooks) | PRC maint on the following redundant line protections:853L A21/L6, 853L B21/79/L6 one at a time.Also be performing meter reseals on: 28S 2057L, 28S 2056L, 28S 2255L | 1.38 Days
Daily |
|
| 18-Feb-26 09:00 | 20-Feb-26 16:00 | ATCO | TE | 784s Protection & Control (784s Donnelly), 784s RTU/SCADA (784s Donnelly) | 25 kV feeder relay and station controller update to repair broken enable/disable reclosing | 2.29 Days
Continuous |
|
| 19-Feb-26 07:30 | 20-Feb-26 17:30 | ALTALINK | RB | 199L (268s Whitecourt - 199AL tap), 199L (347s AML Fox Creek - 199AL tap) | anchor installation near 199L structure 175 | 1.42 Days
Daily |
|
| 19-Feb-26 08:00 | 22-Feb-26 16:00 | ATCO | Outage | 9L40 (732s Mitsue - 809s Louise Creek) | changing rotten poles from our inspection | 3.33 Days
Continuous |
|
| 19-Feb-26 08:00 | 19-Feb-26 16:00 | ALTALINK | TE | AML 793s RTU/SCADA (AML 793s Horse Creek), AltaLink Telecom Equipment | split the existing SCADA VLAN from 1 to 1 and 2 | 8 Hours
Daily |
|
| 19-Feb-26 08:00 | 20-Feb-26 16:00 | ENMAX | IO | 833L (SS-2 - SS-12) | hw sw maintenance SW81, SW82, SW83, MD-12.2TR, reversing Switch Check - 12.2-TC | 1.33 Days
Continuous |
|
| 19-Feb-26 08:00 | 19-Feb-26 16:00 | ENMAX | TE | Protection & Control (SS-37) | 37 sub 138kV Z31 87 (bus differential) and 86 (lockout relay) protection scheme outage, relay protection test - 37RLY138 - 86 lockouts 37RLY138-37.Z31 | 8 Hours
Continuous |
|
| 19-Feb-26 08:00 | 19-Feb-26 16:00 | ENMAX, ALTALINK | TE | 771L (SS-47 - SS-162) | 47sub 771L A protection outage, troubleshoot channel asymmetry alarm | 8 Hours
Continuous |
|
| 19-Feb-26 08:00 | 19-Feb-26 23:00 | ATCO, ALTALINK | RB | 7L696 (508s Lakesend - 892s Ribstone Creek) | AltaLink requested reclosing blocked due to emergency outage at 508S (1-00516679) | 15 Hours
Continuous |
|
| 19-Feb-26 09:00 | 19-Feb-26 18:00 | ALTALINK | Outage | 706L (54s Fort Saskatchewan - 706AL tap), 54s 706N (54s Fort Saskatchewan) | arctic arrow requires a GOI on 706L for a planned high load move between structures 34-35, see also 862L | 9 Hours
Daily |
|
| 19-Feb-26 09:00 | 19-Feb-26 18:00 | ALTALINK, DOW | Outage | 862L (166s Dow Chemical Fort Saskatchewan - 258s Dow Hydrocarbons), 166s 862N (166s Dow Chemical Fort Saskatchewan) | arctic arrow requires a GOI on 862L for a planned high load move between structures 26-27, see also 706L | 9 Hours
Daily |
|
| 19-Feb-26 09:00 | 19-Feb-26 16:00 | ATCO | TE | 2009s Protection & Control (2009s Willow Lake) | PRC-005 relay testing on 50BF/706, 50BF/708 | 7 Hours
Continuous |
|
| 19-Feb-26 09:00 | 19-Feb-26 16:00 | ATCO | TE | 715s Protection & Control (715s Leming Lake) | PRC-005 relay testing on 87TA/702T. | 7 Hours
Continuous |
|
| 19-Feb-26 09:00 | 19-Feb-26 16:00 | ATCO | TE | 751s RTU/SCADA (751s Hill) | smp config update |
7 Hours
Continuous |
|
| 19-Feb-26 09:00 | 19-Feb-26 10:00 | PEL | TE | 318s RTU/SCADA (318s Scoria) | communication outage | 60 Mins
Continuous |
|
| 19-Feb-26 10:00 | 19-Feb-26 13:00 | ALTALINK | Outage | 508s T1 (508s Lakesend), 508s 696 (508s Lakesend) | urgent repair of T1 bushing site glass and oil samples on bushings | 3 Hours
Daily |
|
| 19-Feb-26 12:00 | 20-Feb-26 17:00 | ALTALINK | Outage | 202L (178s Cynthia - 202AL tap), 178s 202X (178s Cynthia) | create 202L open point 'B' | 29 Hours
Continuous |
|
| 19-Feb-26 12:00 | 19-Feb-26 17:00 | ALTALINK | TE | 120s RTU/SCADA (120s Picture Butte) | rtu outage | 5 Hours
Continuous |
|
| 20-Feb-26 08:00 | 20-Feb-26 16:00 | ENMAX | TE | Protection & Control (SS-7) | relay protection test | 8 Hours
Continuous |
|
| 20-Feb-26 08:00 | 20-Feb-26 16:00 | ALTALINK | TE | 370s RTU/SCADA (370s North Lethbridge) | split the existing SCADA VLAN | 8 Hours
Daily |
|
| 20-Feb-26 08:00 | 20-Feb-26 16:00 | ENMAX | Outage | 39.2TR (SS-39) | tag 39.2TR secondary cables | 8 Hours
Continuous |
|
| 20-Feb-26 09:00 | 20-Feb-26 16:00 | ATCO | TE | 2009s Protection & Control (2009s Willow Lake) | PRC-005 relay testing on 21A/7L36, 21B/7L36. | 7 Hours
Continuous |
|
| 20-Feb-26 09:00 | 20-Feb-26 16:00 | ATCO | TE | 715s Protection & Control (715s Leming Lake) | PRC-005 relay testing | 7 Hours
Continuous |
|
| 20-Feb-26 17:01 | 05-Mar-26 14:00 | ALTALINK | Outage | 202L (178s Cynthia - 202AL tap), 178s 202X (178s Cynthia) | installing a new deadend and air break (202L336B) | 12.87 Days
Continuous |
|
| 21-Feb-26 07:00 | 21-Feb-26 17:00 | EPCOR | TE | RTU/SCADA (Meadowlark) | firewall replacement on Meadowlark substation | 10 Hours
Continuous |
|
| 21-Feb-26 13:00 | 21-Feb-26 15:00 | EPCOR | TE | APS# 172 Garneau - Meadowlark Reconfiguration Scheme | Meadowlark MPLS repair | 2 Hours
Continuous |
|
| 22-Feb-26 10:00 | 27-Feb-26 18:00 | ALTALINK | Outage | 443L (55s Olds - 214s Innisfail), 55s 443 (55S Olds), 214s 443 (214s Innisfail) | structure replacements from 443L63 – 443L137 and 55s83 switch repairs | 5.33 Days
Continuous |
|
| 23-Feb-26 07:00 | 27-Feb-26 17:00 | EPCOR | Outage | EP 511s Victoria T4 (EP 511s Victoria), EP 511s V725 (EP 511s Victoria), EP 511s V726 (EP 511s Victoria) | Victoria: TX4 Zone, Relay Maintenance and SCADA RTU Upgrade | 4.42 Days
Continuous |
|
| 23-Feb-26 07:00 | 20-Mar-26 17:00 | EPCOR | Outage | 805s T3 (805s Jasper) | bushing change | 25.38 Days
Continuous |
|
| 23-Feb-26 07:00 | 27-Feb-26 17:00 | EPCOR | Outage | 805s T3 (805s Jasper), EP 805s J2404 (EP 805s Jasper), EP 805s J2405 (EP 805s Jasper) | emergency outage for scaffold build for bushing change (PCB) | 4.42 Days
Continuous |
|
| 23-Feb-26 07:00 | 06-Mar-26 17:00 | EPCOR | TE | Protection & Control (EPCOR Hardisty) | relay maintenance | 11.42 Days
Continuous |
|
| 23-Feb-26 08:00 | 25-Feb-26 16:00 | ENMAX | Outage | 40.81L (SS-40 - SS-41), 41.84L (SS-41 - SS-54), 41.1TR (SS-41), 41B138-41BT3 (SS-41), 41B138-40.81 (SS-41), 41B138-41.84 (SS-41), 40B138-40.81 (SS-40), 54B138-41.84 (SS-54) | HV SW maintenance, reversing switch check | 2.33 Days
Continuous |
|
| 23-Feb-26 08:00 | 27-Nov-26 18:00 | ENMAX | Outage | 20.1TR (SS-20) | 20 SUB switchgear replacement. 1 sub transmission line cut over | 277.42 Days
Continuous |
|
| 23-Feb-26 08:00 | 25-Feb-26 17:00 | ALTALINK | TE | 254s RTU/SCADA (254s Coaldale) | add T2 tap position sensor and tap position visibility | 2.38 Days
Daily |
|
| 23-Feb-26 08:00 | 25-Feb-26 16:00 | ALTALINK | TE | AltaLink Telecom Equipment, 122s RTU/SCADA (122s Alberta Newsprint), 122s Protection & Control (122s Alberta Newsprint) | firewall upgrades and TPR outages | 2.33 Days
Daily |
|
| 23-Feb-26 08:00 | 26-Feb-26 17:00 | ALTALINK | TE | AltaLink Telecom Equipment, 263s RTU/SCADA (263s Strachan) | firewall upgrade and LAN switch upgrade | 3.38 Days
Daily |
|
| 23-Feb-26 08:00 | 26-Feb-26 18:00 | ENMAX | TE | Protection & Control (SS-20) | 20 sub 94-1 tripping relay outage, BMR 20 SUB switchgear replacement | 3.42 Days
Daily |
|
| 23-Feb-26 08:00 | 26-Feb-26 18:00 | ENMAX | TE | Protection & Control (SS-20) | 20 sub BMR-82 protection outage, 20 SUB switchgear replacement | 3.42 Days
Daily |
|
| 23-Feb-26 08:00 | 26-Feb-26 18:00 | ENMAX | TE | Protection & Control (SS-20) | 20 sub BMR-81 protection outage, switchgear replacement | 3.42 Days
Daily |
|
| 23-Feb-26 08:00 | 23-Feb-26 16:00 | ALTALINK | TE | 87s Protection & Control (87s Gaetz) | L9 B protection needs to move locations in rack 28 | 8 Hours
Continuous |
|
| 23-Feb-26 08:00 | 23-Feb-26 16:00 | ALTALINK | TE | 338s RTU/SCADA (338s Cherhill) | split VLAN | 8 Hours
Daily |
|
| 23-Feb-26 08:00 | 23-Feb-26 16:00 | ENMAX | Outage | 47B138-BT3 (SS-47) | I&R BT3 Heater Fail | 8 Hours
Continuous |
|
| 23-Feb-26 08:00 | 23-Feb-26 16:00 | ENMAX | TE | RTU/SCADA (SS-2) | SDN upgrade | 8 Hours
Continuous |
|
| 23-Feb-26 09:00 | 23-Feb-26 16:00 | ATCO | TE | 2009s Protection & Control (2009s Willow Lake) | PRC-005 relay testing | 7 Hours
Continuous |
|
| 23-Feb-26 10:00 | 24-Feb-26 16:00 | ATCO | Outage | 7L91 (715s Leming Lake - 826s Marguerite Lake) | Install aerial nest platform pole and transfer osprey nest from 7L91-158 | 30 Hours
Continuous |
|
| 23-Feb-26 10:00 | 26-Feb-26 17:30 | ALTALINK | TE | 237s Protection & Control (237s Foothills) | PRC maintennace | 3.31 Days
Daily |
|
| 23-Feb-26 10:00 | 26-Feb-26 15:00 | ATCO | TE | 749s Flyingshot Lake RTU/SCADA | RTU updates | 3.21 Days
Continuous |
|
| 23-Feb-26 10:00 | 26-Feb-26 17:00 | ALTALINK | TE | 237s Protection & Control (237s Foothills) | PRC maintenance | 3.29 Days
Daily |
|
| 23-Feb-26 10:00 | 27-Feb-26 17:30 | ATCO | TE | 768s Protection & Control (768s Rowley) | PRC-005 relay testing | 4.31 Days
Continuous |
|
| 23-Feb-26 10:00 | 26-Feb-26 17:00 | ALTALINK | TE | 266s Protection & Control (266s SC1) | PRC maintenance | 3.29 Days
Daily |
|
| 23-Feb-26 11:00 | 26-Feb-26 17:00 | ALTALINK | TE | 288s Protection & Control (288s Wolf Creek) | card replacement and standard relay maintenance | 3.25 Days
Daily |
|
| 23-Feb-26 11:00 | 24-Feb-26 17:00 | ALTALINK | TE | 89s Protection & Control (89s Ellerslie) | relay maintenance | 30 Hours
Daily |
|
| 23-Feb-26 11:00 | 26-Feb-26 17:00 | ALTALINK | TE | 38s Protection & Control (38s East Edmonton) | relay maintenance | 3.25 Days
Daily |
|
| 24-Feb-26 07:00 | 25-Feb-26 17:30 | ATCO, ALTALINK | RB | 807AL (402s Scotford Expansion One - 807L tap) | disable reclosing for ALtaLink work | 1.44 Days
Continuous |
|
| 24-Feb-26 07:00 | 24-Feb-26 17:00 | EPCOR | Outage | 330p 1209 (330p Genesee) | Genesee: 1209 breaker status indicator investigation | 10 Hours
Continuous |
|
| 24-Feb-26 07:00 | 25-Feb-26 17:30 | ALTALINK, ATCO | RB | 807L (410s Josephburg - 807AL tap), 807L (233s Beamer - 807AL tap), 807AL (402s Scotford Expansion One - 807L tap) | crews will be working under and near 807L 67A-72 delivering poles and materials. | 1.44 Days
Daily |
|
| 24-Feb-26 07:00 | 24-Feb-26 17:00 | ENMAX, ALTALINK | RB | 21.80L (42s Sarcee - SS-21) | spring transmission line washing near 1.80, 1.81L. | 10 Hours
Daily |
|
| 24-Feb-26 07:00 | 24-Feb-26 17:00 | ENMAX, ALTALINK | RB | 21.80L (42s Sarcee - SS-21) | spring pothead washing near 1.80, 1.81L | 10 Hours
Daily |
|
| 24-Feb-26 08:00 | 24-Feb-26 17:00 | ALTALINK | TE | 244s Protection & Control (244s Bowmanton) | PRC maint on the following redundant line prot. 892L A21/79/L15 | 9 Hours
Daily |
|
| 24-Feb-26 08:00 | 04-Mar-26 16:00 | Syncrude | Outage | 11 (Aurora), 12 (Aurora), 13 (Aurora), T3 (Aurora), UT1 (Aurora) | zone 6, 6 year PM | 8.33 Days
Continuous |
|
| 24-Feb-26 08:00 | 25-Feb-26 16:00 | ALTALINK | TE | 122s RTU/SCADA (122s Alberta Newsprint) | split VLAN | 1.33 Days
Daily |
|
| 24-Feb-26 08:00 | 25-Feb-26 16:00 | ENMAX | Outage | 39.1TR (SS-39) | relay protection test | 1.33 Days
Continuous |
|
| 24-Feb-26 08:00 | 02-Mar-26 16:00 | ATCO, USPCE | RB | 7L15 (841s Long Lake - 856s Kinosis) | hop required on 7L15 for pole changes | 6.33 Days
Continuous |
|
| 24-Feb-26 08:00 | 27-Feb-26 17:30 | ATCO | TE | 2075s Protection & Control (2075s Newell) | PRC-005 relay testing on AC filter 1 protection & AC filter | 3.4 Days
Continuous |
|
| 24-Feb-26 08:00 | 24-Feb-26 16:00 | ENMAX | Outage | 27.1TR (SS-27) | 27B8-27.1TR trip free while racking out | 8 Hours
Continuous |
|
| 24-Feb-26 09:00 | 24-Feb-26 16:00 | ATCO | TE | 2009s Protection & Control (2009s Willow Lake) | PRC-005 relay testing on 21A/ 7L182, 21B/ 7L182 | 7 Hours
Continuous |
|
| 25-Feb-26 07:00 | 25-Feb-26 18:00 | ALTALINK | Outage | 254s T2 (254s Coaldale), 254s 35 (254s Coaldale) | add T2 tap position sensor and tap position visibility | 11 Hours
Daily |
|
| 25-Feb-26 07:30 | 26-Feb-26 16:00 | ENMAX | Outage | B138-83 (SS-1), B138-84 (SS-1) | 1 sub transmission line cut over, 87LA-1.80L and 87LB-1.80L end to end | 1.35 Days
Continuous |
|
| 25-Feb-26 08:00 | 25-Feb-26 17:00 | ALTALINK | TE | 178s RTU/SCADA (178s Cynthia) | update RTU config for BMI project | 9 Hours
Daily |
|
| 25-Feb-26 08:00 | 25-Feb-26 17:30 | ALTALINK | Outage | 523s C1 (523s Bullshead) | cap bank outage to perform PRC functional testing on the following prot's: A50/51/60/59/C1, B50/51/2760/59/C1 | 9.5 Hours
Daily |
|
| 25-Feb-26 08:00 | 27-Feb-26 17:00 | ALTALINK | TE | 347s RTU/SCADA (347s Fox Creek) | config update for 347s199W breaker replacement | 2.38 Days
Daily |
|
| 25-Feb-26 08:00 | 25-Feb-26 17:00 | ALTALINK | TE | AltaLink Telecom Equipment | replace damaged RF cable connectors | 9 Hours
Daily |
|
| 25-Feb-26 08:30 | 25-Feb-26 17:00 | ALTALINK | TE | 62s RTU/SCADA (62s Brazeau Plant) | RTU database updates, several ~15min supervisory outages required | 8.5 Hours
Daily |
|
| 25-Feb-26 09:00 | 26-Feb-26 17:00 | ATCO | TE | 851s RTU/SCADA (851s Morse River), 809s RTU/SCADA (809s Louise Creek), ATCO Telecom Equipment | replace existing battery charger | 1.33 Days
Continuous |
|
| 25-Feb-26 09:00 | 25-Feb-26 16:00 | ATCO | TE | 2009s Protection & Control (2009s Willow Lake) | PRC-005 relay testing | 7 Hours
Continuous |
|
| 25-Feb-26 10:00 | 25-Feb-26 17:30 | ATCO | Outage | 7L137 (768s Rowley - 770s Three Hills), 770s 702 (770s Three Hills), 768s 703 (768s Rowley) | PRC-005 trip coil testing, breaker 702 @ 770S | 7.5 Hours
Continuous |
|
| 25-Feb-26 10:00 | 25-Feb-26 17:00 | ALTALINK | TE | 62s Protection & Control (62s Brazeau Plant) | protection troubleshooting | 7 Hours
Daily |
|
| 26-Feb-26 07:00 | 06-Mar-26 18:00 | ATCO, ALTALINK | IO | 807AL (402s Scotford Expansion One - 807L tap) | isolate line for Altalink scope: replace 807L structures 67B-71 and reconductor 67A-72. | 8.46 Days
Continuous |
|
| 26-Feb-26 07:00 | 06-Mar-26 18:00 | ALTALINK, ATCO | Outage | 807L (410s Josephburg - 807AL tap), 807L (233s Beamer - 807AL tap), 807AL (402s Scotford Expansion One - 807L tap), 233s 807X (233s Beamer) | replace 807L structures 67B-71 and reconductor 67A-72 | 8.46 Days
Continuous |
|
| 26-Feb-26 07:30 | 26-Feb-26 17:30 | ALTALINK | RB | 924L (102s Langdon - 356s Milo) | arctic arrow crew will require a reclosure block on 924L to complete geo-tech near 924L Span 96-97 | 10 Hours
Daily |
|
| 26-Feb-26 08:00 | 26-Feb-26 17:00 | ALTALINK | TE | 199s RTU/SCADA (199s East Airdrie), AltaLink Telecom Equipment | firewall upgrades and firmware upgrades at 199s. loss of 199s visibility for ~ 1hrs. some TPR channels will be rerouted in 50ms, TPR 261 AISm77/85 PCESO2L will be OOS for 1hr. | 9 Hours
Daily |
|
| 26-Feb-26 08:00 | 26-Feb-26 16:00 | ENMAX | Outage | 15.62L (SS-15 - SS-16), 15.2TR (SS-15) | Replace Centre Phase Braid Strap - 15MD69-15.2TR. I&R 15B69-15.62L Recloser not working | 8 Hours
Continuous |
|
| 26-Feb-26 08:00 | 27-Feb-26 16:00 | ALTALINK | TE | 58s RTU/SCADA (58s Edson) | split VLAN | 1.33 Days
Daily |
|
| 26-Feb-26 09:00 | 26-Feb-26 18:00 | ALTALINK, DOW | Outage | 862L (166s Dow Chemical Fort Saskatchewan - 258s Dow Hydrocarbons), 166s 862N (166s Dow Chemical Fort Saskatchewan) | arctic arrow requires a GOI on 862L for a planned high load move between structures 26-27, see also 706L record | 9 Hours
Daily |
|
| 26-Feb-26 09:00 | 26-Feb-26 18:00 | ALTALINK | Outage | 706L (54s Fort Saskatchewan - 706AL tap), 54s 706N (54s Fort Saskatchewan) | arctic arrow requires a GOI on 706L for a planned high load move between structures 34-35, see also 862L record | 9 Hours
Daily |
|
| 26-Feb-26 09:00 | 26-Feb-26 16:00 | ATCO | TE | 2009s Protection & Control (2009s Willow Lake) | PRC-005 relay testing on 21A/ 7L155, 21B/ 7L155 | 7 Hours
Continuous |
|
| 26-Feb-26 09:00 | 26-Feb-26 17:00 | ALTALINK | TE | 331s Protection & Control (331s Ponoka) | standard relay maintenance | 8 Hours
Daily |
|
| 26-Feb-26 10:00 | 27-Feb-26 17:30 | ATCO | Outage | 770s 703T (770s Three Hills) | PRC-005 - TRIP COIL TESTING - BREAKER 703 @ 770S RELAY MICROPROCESSOR BASED COMPLETE - 87T/703T @ 770S RELAY MICROPROCESSOR BASED COMPLETE - 50-51-51N/703T @ 770S |
31.5 Hours
Continuous |
|
| 26-Feb-26 12:00 | 02-Mar-26 12:00 | ATCO | Outage | 7L121 (917s Horse River - 7LA121 tap) | Changing structure 99, 100, 101 due to L-G violations. | 4 Days
Continuous |
|
| 26-Feb-26 12:00 | 26-Feb-26 17:00 | ALTALINK | TE | 120s RTU/SCADA (120s Picture Butte) | RTU outage | 5 Hours
Continuous |
|
| 27-Feb-26 08:00 | 27-Feb-26 17:00 | ATCO | RB | 7L48 (787s High Prairie - 7L48 tap), 7L48 (794s Valleyview - 7LA48 tap) | connect mobile substation 835S to 7LA48 | 9 Hours
Continuous |
|
| 27-Feb-26 08:00 | 28-Feb-26 16:00 | ALTALINK | TE | 207s RTU/SCADA (207s Pinedale) | split VLAN | 1.33 Days
Daily |
|
| 27-Feb-26 08:00 | 27-Feb-26 16:00 | ENMAX | Outage | 35.1TR (SS-35), 35B138-81 (SS-35), 35B138-82 (SS-35), 35MD138-84 (SS-35), 35MD138-86 (SS-35) | HV breaker maintenance 35B138-81 | 8 Hours
Continuous |
| This document and the information contained herein are based upon information and data which by their nature contain a degree of uncertainty and are subject to change. In addition, this document may contain information and data from public sources and/or third parties, which have been assumed to be accurate and complete and have not been verified. Accordingly, the Independent System Operator, operating as the Alberta Electric System Operator (the "AESO") makes no warranty, representation or guarantee, express or implied, with respect to this document or the information contained herein, including, but not limited to, any warranty, representation or guarantee of accuracy, completeness, timeliness, reliability, availability, absence of computer virus, non- infringement, merchantability or suitability for any purpose. Under no circumstances will the AESO, its members, officers, employees, contractors or agents, or any of their respective affiliates, be liable for any errors or omissions in, or any losses, damages or claims whatsoever, whether in contract, tort or otherwise, arising from use of or reliance upon, this document or any information contained herein. © 2009 Alberta Electric System Operator. All rights reserved |