| Alberta Electric System Operator | |
| System Co-ordination Plan | |
| 2025-11-01 to 2025-11-07 | |
| Approved Outages |
| Previous Version | |
| Download CSV |
| From | To | Owner | Type | Element | Scheduled Activity | Date/Time Comments | Interconnection |
|---|---|---|---|---|---|---|---|
| 26-Jul-24 10:00 | 31-Jul-26 16:00 | ATCO | Outage | 826s 504R (826s Marguerite Lake) | emergency removal to replace failed 502R @834S | 735.25 Days
Continuous |
|
| 23-Aug-24 13:45 | 30-Jun-26 14:29 | ALTALINK | Outage | 157s C1 (157s Lac La Biche) | forced outage | 676.03 Days
Continuous |
|
| 11-Mar-25 00:00 | 31-Dec-25 16:00 | ALTALINK | Outage | 377s 473C (377s AML Hardisty) | forced outage | 295.71 Days
Continuous |
|
| 18-Mar-25 14:00 | 17-Mar-26 17:30 | ALTALINK | Outage | 217s C1 (217s North Red Deer) | cap. bank unavailable and cannot be energized due to Koncar CTs being present | 364.15 Days
Daily |
|
| 20-Mar-25 08:00 | 20-Mar-26 17:00 | ALTALINK | Outage | 256s C1 (256s Harmattan) | forced outage | 365.38 Days
Continuous |
|
| 31-Mar-25 07:00 | 19-Dec-25 17:00 | EPCOR | TE | Protection & Control (Woodcroft) | Woodcroft: protection blocking for merging unit and protection upgrade. | 263.46 Days
Continuous |
|
| 14-May-25 08:00 | 10-Feb-26 16:00 | ENMAX | TE | Protection & Control (SS-32) | 32sub 138kV autoswitching protection outage | 272.38 Days
Continuous |
|
| 08-Jun-25 15:00 | 25-Nov-25 15:30 | ALTALINK | Outage | 397s 864W (397s Benbow) | new 864L line construction, new 397s48 (VT6) install | 170.06 Days
Continuous |
|
| 13-Jun-25 17:00 | 11-Feb-26 17:00 | EPCOR | Outage | T3 (Rossdale) | Rossdale - TX3 LCR | 243.04 Days
Continuous |
|
| 16-Jul-25 07:00 | 01-Dec-25 23:55 | NWE | Outage | 2366 (NWE Marias) | install new equipment at Marias | 138.75 Days
Continuous |
AB-MATL |
| 21-Jul-25 09:00 | 19-Jan-26 17:00 | ATCO | TE | 732s Protection & Control (732s Mitsue) | the breaker fail protection will be disabled during the project, as we migrate from the existing to the new protection | 182.38 Days
Continuous |
|
| 21-Jul-25 09:00 | 23-Jan-26 16:30 | ATCO | TE | 732s RTU/SCADA (732s Mitsue) | existing RTU system being replaced with new SMP system | 186.35 Days
Continuous |
|
| 22-Jul-25 08:30 | 31-Dec-25 16:30 | ALTALINK | Outage | 263s C1 (263s Strachan) | forced outage | 162.38 Days
Continuous |
|
| 25-Jul-25 17:01 | 20-Feb-26 17:00 | EPCOR | Outage | T2 (EP Riverview) | bushing test failure (found during OE110184) | 210.04 Days
Continuous |
|
| 02-Aug-25 23:30 | 07-Nov-25 18:00 | ATCO | Outage | 827s SVC (827s Cranberry Lake) | forced outage | 96.81 Days
Continuous |
|
| 18-Aug-25 07:00 | 21-Nov-25 17:00 | EPCOR | TE | 805s Protection & Control (805s Jasper) | protection blocking for P&C maintenance | 95.46 Days
Continuous |
|
| 20-Aug-25 17:00 | 17-Dec-25 17:00 | ALTALINK | Outage | 1075L (28s West Brooks - 132s Ware Junction) | restoration from real time storm | 119.04 Days
Continuous |
|
| 25-Aug-25 08:00 | 03-Apr-26 16:00 | ENMAX | Outage | 32.1TR (SS-32) | slip over CT and new power cables installation and P&C works | 221.33 Days
Continuous |
|
| 25-Aug-25 09:00 | 10-Dec-25 17:00 | ATCO | TE | 710s Protection & Control (710s Vermilion) | protection and hardwired IO on-site will need to be cut-over to the new SCADA system and tested | 107.38 Days
Continuous |
|
| 02-Sep-25 08:00 | 28-Nov-25 16:00 | ENMAX | Outage | 38.1C (SS-38) | capacitor bank switcher replacement | 87.38 Days
Continuous |
|
| 05-Sep-25 08:00 | 24-Nov-25 16:00 | ENMAX | Outage | 1.83L (SS-1 - SS-8) | 1 sub Transmission line cut over. Line will terminate at new 1 sub upon return to service. | 80.38 Days
Continuous |
|
| 05-Sep-25 08:00 | 24-Nov-25 16:00 | ENMAX | Outage | 1.85L (SS-1 - SS-8) | 1 sub transmission line cut over. line will terminate at new 1 sub upon return to service. | 80.38 Days
Continuous |
|
| 12-Sep-25 08:00 | 06-Mar-26 16:00 | ENMAX | Outage | 33.1TR (SS-33) | tap changer refurbishments. soak test required | 175.38 Days
Continuous |
|
| 26-Sep-25 07:00 | 23-Nov-25 11:00 | ALTALINK | Outage | 864L (397s Benbow - 864AL tap), 397s 864W (397s Benbow) | 864CL line construction | 58.21 Days
Continuous |
|
| 29-Sep-25 08:00 | 07-Nov-25 16:00 | ENMAX | Outage | 21.2TR (SS-21) | 21.2TR replacement | 39.38 Days
Continuous |
|
| 06-Oct-25 07:00 | 06-Nov-25 17:00 | ENMAX | Outage | 1.8TR (SS-1) | new 1 sub construction | 31.46 Days
Continuous |
|
| 06-Oct-25 10:00 | 19-Nov-25 16:00 | ALTALINK | Outage | 102s SVC (102s Langdon), 102s T4 (102s Langdon), 102s 252 (102s Langdon), 102s 552 (102s Langdon) | the controls change | 44.29 Days
Continuous |
AB-BC |
| 14-Oct-25 13:30 | 04-Nov-25 16:00 | ENMAX | Outage | 8B138-1A0 (SS-8), 8B138-2A0 (SS-8), 1A10 (SS-8), 2A1 (SS-8) | 1 sub transmission line cut over, BMR 2a0, and 1.85L protection upgrade related demo and re-connects, commissioning and functions | 21.15 Days
Continuous |
|
| 15-Oct-25 12:00 | 28-Nov-25 17:00 | EPCOR | Outage | 330P 12TC1 (330p Genesee), 330p 805 (330p Genesee) | Genesee: 12TC1 emergency bushing investigation | 44.25 Days
Continuous |
|
| 16-Oct-25 08:00 | 24-Nov-25 20:00 | SUNCOR | Outage | 29EDD-61 29PT-653 (29EDD-61 Stony Island), 29EDD-61 30-252-500001 (29EDD-61 Stony Island) | 29PT-653 repair / replace burned bonding conductor (9000808061) | 39.54 Days
Continuous |
|
| 20-Oct-25 07:00 | 28-Nov-25 17:00 | ALTALINK, EPCOR | RB | 1044L (EP 805s Jasper - 816s Petrolia) | working in proximity (MN872 manhole replacement) | 39.46 Days
Continuous |
|
| 20-Oct-25 07:00 | 14-Nov-25 17:00 | EPCOR | TE | Protection & Control (Rossdale) | block A protection for RG1, RG7, RV2 and RV4 | 25.46 Days
Continuous |
|
| 20-Oct-25 07:00 | 04-Nov-25 17:00 | ALTALINK, CENOVUS | TE | 539s Protection & Control (539s Sunday Creek) | PRC-5 - 5 year maintenance on PCB-9201 & CT-9205 and PCB-9202 & CT-9206 | 15.46 Days
Daily |
|
| 21-Oct-25 07:00 | 02-Nov-25 18:00 | ALTALINK, ATCO | Outage | 912L (63s Red Deer - 766s Nevis), 766s 902 (766s Nevis) | string overtop 912L STR 147-148 with the new CETO 962L/986L spans 165-166 | 12.5 Days
Continuous |
|
| 24-Oct-25 20:00 | 13-Nov-25 20:00 | EPCOR | Outage | 330P GT3 (330p Genesee), 330p 1208 (330p Genesee), 330p 1207 (330p Genesee), 330p 12GT3D (330p Genesee) | connection repair | 20.04 Days
Continuous |
|
| 26-Oct-25 09:00 | 02-Nov-25 17:00 | ALTALINK | IO | 887L (48s Pocaterra - 978s BCH Britt Creek) | Elk Lakes Beetle Hazard tree removals. 64-08 to 25-01 | 7.38 Days
Daily |
|
| 27-Oct-25 07:00 | 13-Nov-25 17:00 | ENMAX | TE | Protection & Control (SS-3) | 3 sub 138 kV Z31 bus differential protection outage | 17.46 Days
Daily |
|
| 27-Oct-25 07:00 | 03-Nov-25 07:00 | ENMAX | Outage | 3.3TR (SS-3) | 3.3TR transformer protection 'S' protection replacement with 'B' protection | 7.04 Days
Continuous |
|
| 27-Oct-25 07:00 | 03-Nov-25 17:00 | ENMAX | TE | Protection & Control (SS-3) | 3 sub BMR82 protection outage | 7.46 Days
Daily |
|
| 27-Oct-25 07:00 | 02-Nov-25 19:00 | ATCO | RB | 9L20 (755s Cordel - 766s Nevis) | complete construction activities on CETO project adjacent to 9L20 | 6.54 Days
Continuous |
|
| 27-Oct-25 07:00 | 02-Nov-25 16:00 | ALTALINK, EPCOR | IO | 1055L (629s Argyll Transfer Station - 816s Petrolia) | ADS2 LCR - Bellamy transducer and DFR cutovers, Bellamy 240 kV SF6 gas tests and leak checks | 6.42 Days
Continuous |
|
| 27-Oct-25 07:00 | 02-Nov-25 19:00 | ATCO | RB | 7L143 (766s Nevis - 769s Stettler) | facilitate work adjacent to line for CETO project | 6.54 Days
Continuous |
|
| 27-Oct-25 07:00 | 13-Nov-25 17:00 | ENMAX | TE | Protection & Control (SS-3) | 3PT138-Z31 secondary outage | 17.46 Days
Daily |
|
| 27-Oct-25 07:30 | 06-Nov-25 17:30 | ALTALINK | RB | 1097L (356s Milo – 611s Amber) | working within proximity on 1036L | 10.46 Days
Daily |
|
| 27-Oct-25 07:30 | 06-Nov-25 17:30 | ALTALINK | RB | 1005AL (991s Little Bow - 1005L tap), 1005L (120s Picture Butte - 1005AL tap), 1005L (356s Milo - 1005AL tap) | working within close proximity on 1036L (str 5-45) | 10.46 Days
Daily |
|
| 27-Oct-25 08:00 | 20-Nov-25 16:00 | ENMAX | Outage | 32.83L (SS-32 - SS-40), 32B138-32.83 (SS-32), 40B138-32.83 (SS-40) | 32.83L P&C cut over | 24.38 Days
Continuous |
|
| 27-Oct-25 08:00 | 03-Nov-25 17:00 | ATCO | RB | 7L128 (802s Michichi Creek - 7LA128 tap), 7L128 (963s Coyote Lake - 7LA128 tap) | hardware tightening on H-frame structures | 7.42 Days
Continuous |
|
| 27-Oct-25 09:00 | 05-Nov-25 17:00 | BCH | Outage | 2L112 (BPA Boundary - BCH Nelway), 2D24 (BCH Nelway), 2D2CB7 (BCH Nelway) | NLY 2SA2 2SA12 replacement, BC maintenance does not affect the Alberta ATC | 9.38 Days
Continuous |
AB-BC |
| 27-Oct-25 09:00 | 04-Nov-25 17:00 | BCH | Outage | 5L98 (BCH Nicola - BCH Vaseux Lake) | repair damaged conductor and install new mid-span structure in the 102 mile BC maintenance does not affect the Alberta ATC | 8.38 Days
Continuous |
AB-BC |
| 27-Oct-25 09:00 | 02-Nov-25 17:00 | BCH | Outage | 1L274 (48s Pocaterra - 978s BCH Britt Creek) | Elk Lakes Beetle hazard tree removals 64-08 to 25-01 BC maintenance does not affect the Alberta ATC | 6.38 Days
Daily |
AB-BC |
| 27-Oct-25 12:00 | 07-Nov-25 16:00 | ATCO | TE | 925s Protection & Control (925s Green Stocking) | complete relay testing | 11.21 Days
Continuous |
|
| 27-Oct-25 15:00 | 10-Nov-25 14:00 | ATCO | Outage | 7L49 (729s Otauwau - 732s Mitsue), 732s 702 (732s Mitsue), 732s 703 (732s Mitsue), 729s 705 (729s Otauwau), 732s 7L49D1 (732s Mitsue) | protection upgrade, remove old protection, cut over to new protection and cut over equipment status, control and alarms to new station controller | 14 Days
Continuous |
|
| 27-Oct-25 19:00 | 02-Nov-25 16:00 | EPCOR, ALTALINK | Outage | 240BA3 (629s Argyll Transfer Station - 814s Bellamy), 1055L (629s Argyll Transfer Station - 816s Petrolia), 814s B2406 (814s Bellamy), 814s B2407 (814s Bellamy), 814s BDS20 (814s Bellamy) | ADS2 LCR - Bellamy transducer and DFR cutovers, Bellamy 240 kV SF6 gas tests and leak checks | 5.92 Days
Continuous |
|
| 30-Oct-25 07:00 | 06-Nov-25 18:00 | ATCO, ALTALINK | Outage | 1036L (356s Milo - 554s Travers) | installing interphase spacers and repairing the inner of the conductor (str 5-45) | 7.5 Days
Continuous |
|
| 31-Oct-25 07:00 | 02-Nov-25 18:00 | ALTALINK | Outage | 944L (132s Ware Junction - 275s Jenner) | modifying existing structure 944L156 from a tangent assembly to a floating DE/phase raise configuration to tap onto a new adjacent substation | 2.5 Days
Continuous |
|
| 31-Oct-25 07:00 | 02-Nov-25 18:00 | ALTALINK | RB | 951L (132s Ware Junction - 275s Jenner) | due to proximity | 2.5 Days
Continuous |
|
| 01-Nov-25 08:00 | 02-Nov-25 18:00 | ENMAX | Outage | 11.82L (SS-11 - SS-14), 11.83L (SS-162 - SS-11), 11.3TR (SS-11), 11.2TR (SS-11), 11B138-11.82 (SS-11), 11B138-11.83 (SS-11), 11B138-BT5 (SS-11) | substation - insulator washing (fall). power factor test | 1.46 Days
Continuous |
|
| 02-Nov-25 07:00 | 09-Nov-25 19:00 | ATCO | RB | 7L16 (766s Nevis - 948s Heatburg) | HOP on 7L16 to facilitate work adjacent to line for CETO project | 7.5 Days
Continuous |
|
| 02-Nov-25 09:00 | 04-Nov-25 14:00 | ENMAX | Outage | 33.83L (SS-33 - SS-41), 33B138-33.83 (SS-33), 41B138-33.83 (SS-41) | install line surge arrestors at Sub 41 | 2.21 Days
Continuous |
|
| 03-Nov-25 06:00 | 10-Nov-25 18:00 | ATCO | Outage | 9L16 (755s Cordel - 972s Tinchebray) | install foundations for new 9L16 structures 73 and 74 in preparation of the future line bay re-termination into 972S tinchebray expansion, part2 | 7.5 Days
Continuous |
|
| 03-Nov-25 07:00 | 09-Nov-25 17:00 | EPCOR | Outage | 814s T1 (814s Bellamy), 814s B2401 (814s Bellamy), 814s B2407 (814s Bellamy), BR721 (Rossdale), 814s BAB1 (814s Bellamy) | bushing replacement and 240kv SF6 gas tests and leak checks | 6.42 Days
Continuous |
|
| 03-Nov-25 07:00 | 04-Nov-25 16:00 | ENMAX | Outage | 3.82L (SS-3 - SS-8), 3.3TR (SS-3), 3B138-3.82 (SS-3), 3MD138-3.3TR (SS-3) | 3.3TR transformer protection 'S' protection replacement with 'B' protection, 3MD138-3.3TR commissioning and trip test 3B138-3.82 | 1.38 Days
Continuous |
|
| 03-Nov-25 07:00 | 09-Nov-25 19:00 | ATCO | RB | 9L20 (755s Cordel - 766s Nevis) | complete construction activities on CETO project adjacent to 9L20 | 6.5 Days
Continuous |
|
| 03-Nov-25 07:00 | 21-Nov-25 17:00 | EPCOR | TE | EP 511s Protection & Control (EP 511s Victoria) | protection block on “A” protections for VN21 at Victoria | 18.42 Days
Continuous |
|
| 03-Nov-25 07:00 | 19-Dec-25 17:00 | EPCOR | TE | 987s Protection & Control (987s Clover Bar) | protection blocking for P&C maintenance at Cloverbar | 46.42 Days
Continuous |
|
| 03-Nov-25 07:00 | 07-Nov-25 17:00 | EPCOR | TE | Protection & Control (Poundmaker) | protection blocking for P&C maintenance. at Poundmaker | 4.42 Days
Continuous |
|
| 03-Nov-25 07:00 | 03-Nov-25 17:00 | ENMAX | RB | 2.83L (SS-5 - 2.83L tap), 2.83L (SS-2 - 2.83L tap), 2.83L (SS-13 - 2.83L tap) | tree trimming | 10 Hours
Daily |
|
| 03-Nov-25 07:00 | 04-Nov-25 18:00 | ALTALINK | TE | AltaLink Telecom Equipment | 947s MPLS node addition upgrade | 1.46 Days
Daily |
|
| 03-Nov-25 07:00 | 04-Nov-25 17:00 | EPCOR | Outage | T3 (EP Hardisty) | lighting upgrade (#8) on TX3 | 1.42 Days
Continuous |
|
| 03-Nov-25 08:00 | 05-Nov-25 15:30 | ALTALINK | TE | 523s RTU/SCADA (523s Bullshead) | upgrade the configuration regarding the card replacement project | 2.31 Days
Daily |
|
| 03-Nov-25 08:00 | 05-Nov-25 15:30 | ALTALINK | TE | 523s Protection & Control (523s Bullshead) | removing B21/L1 (600L) from service for card replacements project | 2.31 Days
Daily |
|
| 03-Nov-25 08:00 | 15-Nov-25 16:00 | Syncrude | Outage | AL-2 (Aurora - D05 Syncrude), 222 (Aurora), 223 (Aurora), D05 514 (D05), D05 511 (D05), D05 512 (D05) | complete D05 substation zone 3 260kV PM | 12.33 Days
Continuous |
|
| 03-Nov-25 08:00 | 03-Nov-25 17:00 | ALTALINK, Lethbridge | Outage | 667L (146s MacDonald - 370s North Lethbridge), 146s 667 (146s Macdonald) | 146s667L open end outage, add CT circuit into new sel ddr, recording and commission, protection outages on 667L "A" protection relay | 9 Hours
Continuous |
|
| 03-Nov-25 08:00 | 03-Nov-25 17:00 | ALTALINK, Lethbridge | IO | 667L (146s MacDonald - 370s North Lethbridge) | 146s667L open end outage required to add CT circuit into new SEL DDR and test DDR recording and commission | 9 Hours
Daily |
|
| 03-Nov-25 08:00 | 07-Nov-25 17:30 | ALTALINK | TE | 678s RTU/SCADA (678s Okotoks) | major SCADA upgrade project, replacement of D20 RTU with new SG-4260 data concentrator, deficiency cleanup and complete points check | 4.4 Days
Daily |
|
| 03-Nov-25 08:00 | 09-Nov-25 16:00 | ATCO | RB | 7L48 (787s High Prairie - 7L48 tap), 7L48 (794s Valleyview - 7LA48 tap) | walk up and climbing inspection | 6.33 Days
Continuous |
|
| 03-Nov-25 08:00 | 04-Nov-25 16:00 | ENMAX | Outage | 12.1TR (SS-12) | replace CT terminal | 1.33 Days
Continuous |
|
| 03-Nov-25 08:00 | 06-Nov-25 16:00 | ENMAX | TE | Protection & Control (SS-12) | 12sub 138kV bus differential protection CT terminal replacement | 3.33 Days
Daily |
|
| 03-Nov-25 08:00 | 07-Nov-25 17:00 | ALTALINK | TE | 397s RTU/SCADA (397s Benbow) | update configuration for L2 protection upgrade and AIS 1159 additions | 4.38 Days
Daily |
|
| 03-Nov-25 08:00 | 07-Nov-25 17:00 | ALTALINK | TE | 347s RTU/SCADA (347s Fox Creek) | update config to add and test new 1159AIS points | 4.38 Days
Daily |
|
| 03-Nov-25 08:00 | 04-Nov-25 18:00 | ENMAX | Outage | 2.3TR (SS-2) | tap changer Inspection - 2.3-tc. oil filtration maintenance - 2.3-tc | 1.42 Days
Continuous |
|
| 03-Nov-25 08:00 | 03-Nov-25 12:00 | ENMAX | TE | RTU/SCADA (SS-10) | transfer of SCADA from JMUX to JPAX at substations in ring 2 | 4 Hours
Continuous |
|
| 03-Nov-25 08:00 | 03-Nov-25 16:00 | ENMAX | TE | RTU/SCADA (SS-23) | upgrade SDN | 8 Hours
Continuous |
|
| 03-Nov-25 09:00 | 10-Nov-25 16:00 | ATCO | RB | 7L46 (813s Little Smoky - 845s Big Mountain) | pole replacement line to ground issue ( Line raise ) | 7.29 Days
Continuous |
|
| 03-Nov-25 09:00 | 10-Nov-25 16:00 | ATCO | Outage | 7L45 (798s Bridge Creek - 813s Little Smoky) | pole replacement line to ground issue ( Line raise ) | 7.29 Days
Continuous |
|
| 03-Nov-25 09:00 | 06-Nov-25 09:00 | BCH | Outage | T3 (BCH Natal), 12CB23 (BCH Natal) | natal substation replacement and ETM install BC Hydro maintenance does not affect Alberta ATC | 3 Days
Continuous |
AB-BC |
| 03-Nov-25 09:00 | 07-Nov-25 18:00 | ALTALINK | Outage | 477s 138kV Bus (477s Amoco West Pembina), 841L (477s Amoco West Pembina - 489s Petro-Canada Brazeau River), 844L (358s Amoco Brazeau - 477s Amoco West Pembina), 477s T1 (477s Amoco West Pembina), 477s 841X (477s Amoco West Pembina), 477s 844X (477s Amoco West Pembina), 477s 18 (477s Amoco West Pembina), 477s 19 (477s Amoco West Pembina) | replace CTs associated with 477s841X & 477s844X, remove PCB light on 358s 844L a-frame | 4.38 Days
Continuous |
|
| 03-Nov-25 09:00 | 05-Nov-25 17:00 | ATCO | TE | ATCO Telecom Equipment | Nevis_S-Telecom outage to install new Nokia RS232 & x.21 distribution panels & re cabling. install new SAR A, SDI cards 1.3/1.4 slots, ETH cards 1.1/1.2 | 2.33 Days
Continuous |
|
| 03-Nov-25 09:00 | 07-Nov-25 17:00 | ALTALINK | TE | 102s RTU/SCADA (102s Langdon) | add T4 ASMA points from the new qualitrol ITM delay | 4.33 Days
Daily |
|
| 03-Nov-25 10:00 | 07-Nov-25 17:00 | ALTALINK | TE | 397s Protection & Control (397s Benbow) | settings changes and testing associated with new 11/252, 11/452, & B87/138B protections | 4.29 Days
Daily |
|
| 03-Nov-25 10:30 | 06-Nov-25 17:30 | ALTALINK | Outage | 38s C1 (38s East Edmonton), 38s 3052 (38s East Edmonton) | replace CT | 3.29 Days
Continuous |
|
| 03-Nov-25 11:30 | 06-Nov-25 16:30 | ALTALINK | TE | 159s Protection & Control (159s Colinton) | protection upgrade | 3.21 Days
Daily |
|
| 03-Nov-25 11:30 | 06-Nov-25 16:30 | ALTALINK | TE | 159s RTU/SCADA (159s Colinton) | update RTU database | 3.21 Days
Daily |
|
| 03-Nov-25 12:00 | 06-Nov-25 18:00 | ALTALINK | Outage | 749L (899s Edgerton - 749AL tap), 899s 749X (899s Edgerton) | component replacement from 749L123 - 749L292 | 3.25 Days
Continuous |
|
| 03-Nov-25 12:00 | 10-Nov-25 17:00 | ATCO | TE | 951s RTU/SCADA (951s Thickwood Hills) | firmware upgrades of line protection relays and breaker fail relays | 7.21 Days
Continuous |
|
| 03-Nov-25 12:00 | 06-Nov-25 18:00 | ALTALINK | Outage | 744L (235s Entwistle - 744AL tap), 235s 744W (235s Entwistle) | urgent outage to replace rotting arms and fixing conductor at structures 97A, 96A, 94A, 7 | 3.25 Days
Continuous |
|
| 03-Nov-25 12:30 | 03-Nov-25 17:00 | ENMAX, ALTALINK | Outage | 50L (44s Bearspaw Plant - SS-21), 44s 50X (44s Bearspaw Plant) | 44s50X heater replacement / site inspection | 4.5 Hours
Continuous |
|
| 03-Nov-25 12:30 | 03-Nov-25 17:00 | ENMAX, ALTALINK | RB | 50L (44s Bearspaw Plant - SS-21) | 44s50X heater replacement / site inspection | 4.5 Hours
Continuous |
|
| 03-Nov-25 13:00 | 06-Nov-25 17:00 | ALTALINK | Outage | 83s T3 (83s Taber), 83s 64 (83s Taber) | leak repair | 3.17 Days
Continuous |
|
| 03-Nov-25 13:00 | 07-Nov-25 11:00 | ALTALINK | Outage | 798L (77s Sagitawah - 364s Whitecourt Industrial), 77s 552 (77s Sagitawah), 77s 352 (77s Sagitawah), 364s 798 (364s Whitecourt Industrial), 77s 798N (77s Sagitawah) | replace CTs associated with 77s352 | 3.92 Days
Continuous |
|
| 03-Nov-25 13:00 | 13-Nov-25 16:00 | Saskpower | Outage | SaskPower A1R | planned outage | 10.13 Days
Continuous |
AB-SK |
| 03-Nov-25 14:00 | 04-Nov-25 17:30 | ALTALINK | Outage | 39s 26 (39s Bickerdike) | first trip and breaker maintenance on 39s26 | 27.5 Hours
Continuous |
|
| 03-Nov-25 14:30 | 04-Nov-25 17:00 | ALTALINK | TE | 650s Protection & Control (650s Hansman Lake) | maintenance on 650s B87/21/67N/L10 (885L) | 26.5 Hours
Continuous |
|
| 03-Nov-25 14:30 | 04-Nov-25 17:00 | ALTALINK | TE | 648s Protection & Control (648s Metiskow) | maintenance 648s B87/21/67N/L3 (885L | 26.5 Hours
Continuous |
|
| 03-Nov-25 14:30 | 06-Nov-25 17:30 | ALTALINK | TE | 405s RTU/SCADA (405s Waupisoo) | update configuration for SCADA alarm splitting and ACC visibility upgrades | 3.13 Days
Daily |
|
| 04-Nov-25 06:00 | 04-Nov-25 18:00 | EPCOR | Outage | 330p 805 (330p Genesee), 330P 12TC1 (330p Genesee), 330p 1214 (330p Genesee), 330p 1210 (330p Genesee), 330p 1201 (330p Genesee), 330p 1204 (330p Genesee), 330p 1207 (330p Genesee), 330p 500kV Bus 1 (330p Genesee) | emergency 500kV BUS #1 outage for removing connection from 12TC1D to 500kV BUS. 12TC1D will be isolated/air gapped from 500kV BUS on restoration of BUS. | 12 Hours
Continuous |
|
| 04-Nov-25 07:00 | 13-Nov-25 17:00 | ENMAX | TE | Protection & Control (SS-3) | 3 sub BMR84 protection outage | 9.42 Days
Daily |
|
| 04-Nov-25 07:00 | 05-Nov-25 17:00 | ATCO | TE | 951s Protection & Control (951s Thickwood Hills) | 9L112 B relay will be out of service for firmware upgrade and local testing | 1.42 Days
Continuous |
|
| 04-Nov-25 07:00 | 10-Nov-25 17:00 | ATCO | TE | 951s Protection & Control (951s Thickwood Hills) | breaker fail relays for firmware upgrade and local testing | 6.42 Days
Continuous |
|
| 04-Nov-25 07:00 | 07-Nov-25 17:00 | ALTALINK | Outage | 409s T1 (409s Shell Scotford) | customer to replace T1 NGR | 3.42 Days
Continuous |
|
| 04-Nov-25 07:00 | 04-Nov-25 17:00 | ENMAX | RB | 24.81L (SS-24 - SS-31) | tree trimming | 10 Hours
Daily |
|
| 04-Nov-25 07:00 | 04-Nov-25 17:00 | ENMAX | RB | 11.81L (SS-11 - SS-13) | tree trimming | 10 Hours
Daily |
|
| 04-Nov-25 07:00 | 04-Nov-25 17:00 | ENMAX | RB | 24.82L (SS-24 - SS-65) | tree trimming | 10 Hours
Daily |
|
| 04-Nov-25 07:30 | 13-Nov-25 17:30 | ALTALINK | RB | 1053L (132s Ware Junction - 324s Cassils) | install insulators and travelers for new 1075L on open side of tower opposite to 1053L on structures | 9.42 Days
Daily |
|
| 04-Nov-25 08:00 | 04-Nov-25 17:00 | Lethbridge | Outage | 813L (146s MacDonald - 241s Uplands), 146s 813L (146s Macdonald), 241s 813L (241s Uplands) | 146s813L open end outage | 9 Hours
Continuous |
|
| 04-Nov-25 08:00 | 04-Nov-25 13:00 | ALTALINK | Outage | 633L (56s Boyle - 405s Waupisoo), 405s 633 (405s Waupisoo) | SCADA alarm splitting and ACC visibility upgrades | 5 Hours
Daily |
|
| 04-Nov-25 08:00 | 06-Nov-25 16:00 | SUNCOR | IO | 29EDD-94 Voyageur | 29EDD94;S23 meter- meter certification | 2.33 Days
Continuous |
|
| 04-Nov-25 08:00 | 06-Nov-25 16:00 | SUNCOR | IO | 30EDD-2 | 30EDD2;TG1 S23 meter reverification | 2.33 Days
Continuous |
|
| 04-Nov-25 08:00 | 04-Nov-25 20:00 | SUNCOR | TE | Suncor RTU/SCADA (Suncor) | SDC failover test 2025 | 12 Hours
Continuous |
|
| 04-Nov-25 08:00 | 04-Nov-25 17:00 | ALTALINK | TE | AltaLink Telecom Equipment | 9932R MPLS firmware upgrade | 9 Hours
Daily |
|
| 04-Nov-25 08:00 | 04-Nov-25 16:00 | ENMAX | IO | Protection & Control (SS-13) | 13sub sstr13-1, sstr13-2 outage. automatic transfer switch maintenance | 8 Hours
Continuous |
|
| 04-Nov-25 08:00 | 04-Nov-25 17:00 | ALTALINK | TE | 293s RTU/SCADA (293s Bernese), AltaLink Telecom Equipment | upgrade MPLS node | 9 Hours
Daily |
|
| 04-Nov-25 08:00 | 06-Nov-25 17:00 | ALTALINK | TE | 104s RTU/SCADA (104s Watson Creek), AltaLink Telecom Equipment | upgrade MPLS | 2.38 Days
Daily |
|
| 04-Nov-25 08:00 | 06-Nov-25 17:00 | ALTALINK | TE | 384s RTU/SCADA (384s Keystone), AltaLink Telecom Equipment | MPLS firmware upgrade | 2.38 Days
Daily |
|
| 04-Nov-25 08:00 | 06-Nov-25 17:00 | ALTALINK | TE | 61s RTU/SCADA (61s Lodgepole), AltaLink Telecom Equipment | MPLS firmware upgrade | 2.38 Days
Daily |
|
| 04-Nov-25 08:00 | 06-Nov-25 17:00 | ALTALINK | TE | 414s RTU/SCADA (414s Gulf Robb), AltaLink Telecom Equipment | MPLS firmware upgrade | 2.38 Days
Daily |
|
| 04-Nov-25 08:00 | 06-Nov-25 17:00 | ALTALINK | TE | 412s RTU/SCADA (412s Shell Eagle Creek), AltaLink Telecom Equipment | MPLS firmware upgrade | 2.38 Days
Daily |
|
| 04-Nov-25 08:00 | 06-Nov-25 17:00 | ALTALINK | TE | AltaLink Telecom Equipment, 426s RTU/SCADA (426s Coalspur) | MPLS firmware upgrade | 2.38 Days
Daily |
|
| 04-Nov-25 08:00 | 06-Nov-25 17:00 | ALTALINK | TE | AltaLink Telecom Equipment, 953s RTU/SCADA (953s Lake Louise), 945s RTU/SCADA (945s Sunshine Village), 115s RTU/SCADA (115s Mount Allan), 437s RTU/SCADA (437s Baymag), 43s RTU/SCADA (43s Shell Canada Jumping Pound Jct) | MPLS firmware upgrade | 2.38 Days
Daily |
|
| 04-Nov-25 08:00 | 06-Nov-25 17:00 | ALTALINK | TE | 438s RTU/SCADA (438s Westlock), AltaLink Telecom Equipment | MPLS firmware upgrade | 2.38 Days
Daily |
|
| 04-Nov-25 08:00 | 06-Nov-25 17:00 | ALTALINK | TE | 701s RTU/SCADA (701s Blue Ridge Lumber), AltaLink Telecom Equipment | MPLS firmware upgrade | 2.38 Days
Daily |
|
| 04-Nov-25 09:00 | 04-Nov-25 17:00 | ATCO | TE | ATCO Telecom Equipment | Linden_T-Telecom- commissioning a new DC power rectifier remove the old Haley rectifiers | 8 Hours
Continuous |
|
| 04-Nov-25 09:00 | 06-Nov-25 17:00 | ATCO | RB | 7L86 (822s Wolf Lake - 1200s Foster Creek) | L-G clearance mitigation pole changes. | 2.33 Days
Daily |
|
| 04-Nov-25 09:00 | 24-Nov-25 13:00 | ATCO | TE | 741s RTU/SCADA (741s Fox Creek) | SCADA SMP being updated with new points for 7L90 RAS addition | 20.17 Days
Continuous |
|
| 04-Nov-25 09:30 | 04-Nov-25 17:00 | ALTALINK | TE | 69s Protection & Control (69s North Barrhead) | settings update on 723L (L3) ‘A’ protection to facilitate the commissioning of the travelling wave relay | 7.5 Hours
Daily |
|
| 04-Nov-25 09:30 | 04-Nov-25 17:00 | ALTALINK | TE | 150s Protection & Control (150s Clyde) | settings update on 723L | 7.5 Hours
Daily |
|
| 04-Nov-25 10:00 | 04-Nov-25 18:00 | ALTALINK | Outage | 353s T1 (353s Plamondon), 353s 195 (353s Plamondon) | replace broken strain insulators in 25kV bus 1 | 8 Hours
Daily |
|
| 04-Nov-25 10:00 | 05-Nov-25 17:00 | ATCO | TE | 732s RTU/SCADA (732s Mitsue) | pre-commission new SCADA controls from STG to the Mitsue new RTU | 31 Hours
Continuous |
|
| 04-Nov-25 10:30 | 10-Dec-25 15:00 | ATCO | TE | 710s Protection & Control (710s Vermilion) | 86-50BF-1/700BS1 secondary protection block common lockout so we can tie in new BF trips from 7L117 A&B, 7L129 A&B, 7L130 A&B | 36.19 Days
Continuous |
|
| 04-Nov-25 10:30 | 01-Dec-25 15:00 | ATCO | TE | 710s Protection & Control (710s Vermilion) | 87BA/700BS1, secondary protection, blocked for 7L129 primary injection as well as 7L117 primary injection as well as local SCADA cutover testing | 27.19 Days
Continuous |
|
| 04-Nov-25 13:00 | 04-Nov-25 18:00 | ALTALINK | Outage | 728L (353s Plamondon - 405s Waupisoo), 405s 728 (405s Waupisoo), 353s 452 (353s Plamondon) | SCADA alarm splitting and ACC visibility upgrades | 5 Hours
Daily |
|
| 05-Nov-25 07:00 | 06-Nov-25 17:00 | ENMAX | TE | Protection & Control (SS-3) | 3.3TR A and B protection outage | 1.42 Days
Daily |
|
| 05-Nov-25 07:00 | 06-Nov-25 17:00 | ATCO | TE | 951s Protection & Control (951s Thickwood Hills) | 9L30 B relay will be out of service for firmware upgrade and local testing | 1.42 Days
Continuous |
|
| 05-Nov-25 07:00 | 05-Nov-25 17:00 | ENMAX | RB | 11.82L (SS-11 - SS-14) | tree trimming | 10 Hours
Daily |
|
| 05-Nov-25 07:00 | 07-Nov-25 17:00 | EPCOR | Outage | 72LH8 (EP 803s Lambton - EP Hardisty), T2 (EP Hardisty), H723 (EP Hardisty), H722 (EP Hardisty), HAB2 (EP Hardisty) | TX2 zone, lighting upgrade | 2.42 Days
Continuous |
|
| 05-Nov-25 08:00 | 05-Nov-25 18:00 | Syncrude | TE | Syncrude ICCP Outage | server update |
10 Hours
Daily |
|
| 05-Nov-25 08:00 | 05-Nov-25 15:00 | ALTALINK, ENMAX | Outage | 688L (653s Summit - 688AL tap), 688AL (284s Nose Creek - 688L tap), 284s T1 (284s Nose Creek), 653s 688 (653s Summit) | 284s strain insulator replacement on the structure inside the | 7 Hours
Daily |
|
| 05-Nov-25 08:00 | 06-Nov-25 17:00 | ALTALINK | TE | 650s Protection & Control (650s Hansman Lake) | card replacement on 650s B21/79/L12 (7L224) | 1.38 Days
Continuous |
|
| 05-Nov-25 08:00 | 05-Nov-25 18:00 | ALTALINK, CascadeP | Outage | 1135L (39s Bickerdike - 1047s Whisky Jack), 39s 26 (39s Bickerdike), 39s 29 (39s Bickerdike) | first trip & breaker maintenance on 39s29, and repair 39s28 | 10 Hours
Daily |
|
| 05-Nov-25 08:00 | 05-Nov-25 13:00 | ALTALINK | Outage | 796L (405s Waupisoo - 796AL tap), 796L (282s Grassland - 796AL tap), 796AL (242s Flat Lake - 796L tap), 405s 796 (405s Waupisoo) | SCADA alarm splitting and ACC visibility upgrades | 5 Hours
Daily |
|
| 05-Nov-25 08:00 | 06-Nov-25 16:00 | ENMAX | Outage | 12.2TR (SS-12) | CT terminal replacement | 1.33 Days
Continuous |
|
| 05-Nov-25 08:00 | 05-Nov-25 12:00 | ENMAX | TE | RTU/SCADA (SS-12) | transfer of SCADA from JMUX to JPAX | 4 Hours
Continuous |
|
| 05-Nov-25 08:00 | 05-Nov-25 16:00 | ENMAX | Outage | 39.4TR (SS-39) | oil sampling - 39.4-TC. silica gel canister upgrade - 39.4 TR - MT | 8 Hours
Continuous |
|
| 05-Nov-25 08:00 | 05-Nov-25 17:00 | ALTALINK, TRANSALTA | TE | AltaLink Telecom Equipment, 229s RTU/SCADA (229s Glenwood), 502s RTU/SCADA (502s Shell Waterton (#2)) | urgent troubleshooting required at 502S and 229S to fix supervisory intermittently failing at 229S that highly suspect caused by 9232R raw socket conversion | 9 Hours
Daily |
|
| 05-Nov-25 08:30 | 05-Nov-25 17:00 | ALTALINK | TE | 140s Protection & Control (140s Thompson) | card replacement | 8.5 Hours
Daily |
|
| 05-Nov-25 08:30 | 05-Nov-25 17:00 | ALTALINK | TE | 650s Protection & Control (650s Hansman Lake) | card replacement | 8.5 Hours
Daily |
|
| 05-Nov-25 09:00 | 05-Nov-25 16:00 | ATCO | Outage | 7L587 (822s Wolf Lake - 826s Marguerite Lake), 822s 701 (822s Wolf Lake) | inspect CT wiring at RTXP test switch and replace |
7 Hours
Continuous |
|
| 05-Nov-25 09:00 | 05-Nov-25 17:00 | ATCO | TE | ATCO Telecom Equipment, 846s Grand Centre RTU/SCADA | low BES firewall install | 8 Hours
Continuous |
|
| 05-Nov-25 09:00 | 06-Nov-25 17:00 | ATCO | TE | ATCO Telecom Equipment, 766s RTU/SCADA (766s Nevis) | low BES firewall install | 1.33 Days
Continuous |
|
| 05-Nov-25 09:30 | 05-Nov-25 16:30 | ALTALINK | Outage | 421s T1 (421s Hays) | 421sT1 H3 hot bushing | 7 Hours
Daily |
|
| 05-Nov-25 12:00 | 12-Nov-25 07:00 | ENMAX | Outage | 3.4TR (SS-3) | 3.4TR transformer protection 'S' protection replacement with 'B' protection | 6.79 Days
Continuous |
|
| 05-Nov-25 13:00 | 05-Nov-25 18:00 | ALTALINK | Outage | 405s C2 (405s Waupisoo), 405s 23 (405s Waupisoo) | SCADA alarm splitting and ACC visibility upgrades | 5 Hours
Daily |
|
| 05-Nov-25 13:00 | 05-Nov-25 14:00 | ALTALINK, CENOVUS | TE | 154s RTU/SCADA (154s Black Spruce), 539s RTU/SCADA (539s Sunday Creek), AltaLink Telecom Equipment | upgrade MPLS node | 60 Mins
Daily |
|
| 05-Nov-25 17:00 | 06-Nov-25 18:00 | ALTALINK | Outage | 39s 29 (39s Bickerdike) | breaker maintenance on 39s29 | 25 Hours
Continuous |
|
| 06-Nov-25 07:00 | 06-Nov-25 13:00 | ALTALINK | Outage | 729L (40s Wetaskiwin - 729AL tap), 729L (542s Ervick - 729AL tap), 6500s T1 (6500s Trueweld Grating), 40s 729E (40s Wetaskiwin) | remove PCB ballast fixture on structure 40s126 | 6 Hours
Daily |
|
| 06-Nov-25 07:00 | 06-Nov-25 13:00 | ALTALINK | Outage | 397s T2 (397s Benbow), 397s 31 (397s Benbow) | breaker trip circuit cutovers and testing | 6 Hours
Daily |
|
| 06-Nov-25 07:00 | 07-Nov-25 17:00 | ATCO | TE | 951s Protection & Control (951s Thickwood Hills) | 9L07 B relay will be out of service for firmware upgrade and local testing. | 1.42 Days
Continuous |
|
| 06-Nov-25 07:00 | 06-Nov-25 17:00 | ENMAX | RB | 11.82L (SS-11 - SS-14) | tree trimming | 10 Hours
Daily |
|
| 06-Nov-25 07:00 | 06-Nov-25 09:00 | ALTALINK | TE | 83s Protection & Control (83s Taber) | remote settings change redundant protection | 2 Hours
Daily |
|
| 06-Nov-25 07:00 | 06-Nov-25 09:00 | ALTALINK | TE | 254s Protection & Control (254s Coaldale) | remote settings change redundant protection | 2 Hours
Daily |
|
| 06-Nov-25 08:00 | 06-Nov-25 13:00 | ALTALINK | Outage | 405s C1 (405s Waupisoo), 405s 17 (405s Waupisoo) | SCADA alarm splitting and ACC visibility upgrades | 5 Hours
Daily |
|
| 06-Nov-25 08:00 | 06-Nov-25 12:00 | ENMAX | Outage | 40.1TR (SS-40) | oil sampling, reversing switch check | 4 Hours
Continuous |
|
| 06-Nov-25 08:00 | 06-Nov-25 17:00 | ALTALINK | TE | AltaLink Telecom Equipment | 898s MPLS chassis and firmware upgrade | 9 Hours
Daily |
|
| 06-Nov-25 08:00 | 06-Nov-25 17:00 | ALTALINK | TE | 45s RTU/SCADA (45s Bretona), 45s Protection & Control (45s Bretona), AltaLink Telecom Equipment | upgrade MPLS | 9 Hours
Daily |
|
| 06-Nov-25 08:30 | 06-Nov-25 15:00 | ALTALINK | TE | 993s Protection & Control (993s Abee) | card replacement | 6.5 Hours
Daily |
|
| 06-Nov-25 08:30 | 06-Nov-25 17:00 | ALTALINK | TE | 51s Protection & Control (51s Wainwright) | card replacement | 8.5 Hours
Daily |
|
| 06-Nov-25 09:00 | 06-Nov-25 17:00 | ATCO | TE | ATCO Telecom Equipment, 874s RTU/SCADA (874s McKay River) | removal of DJF | 8 Hours
Continuous |
|
| 06-Nov-25 09:00 | 06-Nov-25 17:00 | ATCO | TE | ATCO Telecom Equipment, 849s RTU/SCADA (849s Joslyn Creek) | firewall install, outage to local network & SCADA communications | 8 Hours
Continuous |
|
| 06-Nov-25 09:00 | 06-Nov-25 12:59 | BCH | Outage | 2L113 (BCH Cranbrook - BCH Natal) | F26 AOP | 3.98 Hours
Continuous |
AB-BC |
| 06-Nov-25 09:30 | 07-Nov-25 16:30 | ATCO | TE | 861s RTU/SCADA (861s Eureka River) | Scada/RTU upgrades | 31 Hours
Continuous |
|
| 06-Nov-25 12:00 | 06-Nov-25 16:00 | ENMAX | Outage | 6.1TR (SS-6) | oil sampling, silica gel canister upgrade | 4 Hours
Continuous |
|
| 06-Nov-25 13:00 | 06-Nov-25 18:00 | ALTALINK | Outage | 40s T2 (40s Wetaskiwin) | remove PCB ballast fixture on structure near T2 138 kV risers | 5 Hours
Daily |
|
| 06-Nov-25 13:00 | 18-Nov-25 17:00 | BCH | Outage | 2L113 (BCH Cranbrook - BCH Natal), T3 (BCH Natal), T4 (BCH Natal), 12CB23 (BCH Natal) | NTL substation replacement + ETM install | 12.17 Days
Continuous |
AB-BC |
| 07-Nov-25 07:00 | 08-Nov-25 17:00 | ATCO | TE | 951s Protection & Control (951s Thickwood Hills) | 9L193-909 B relay - firmware upgrade and local testing | 1.42 Days
Continuous |
|
| 07-Nov-25 07:00 | 07-Nov-25 17:00 | ENMAX | RB | 11.82L (SS-11 - SS-14) | tree trimming | 10 Hours
Daily |
|
| 07-Nov-25 08:00 | 18-Nov-25 16:00 | ATCO | Outage | 7L117 (706s Irish Creek - 710s Vermilion), 710s 701 (710s Vermilion), 706s 703 (706s Irish Creek) | 7L117 - A and B line protection upgrade | 11.33 Days
Continuous |
|
| 07-Nov-25 08:00 | 18-Nov-25 15:30 | ATCO | TE | 710s Protection & Control (710s Vermilion) | protection upgrade | 11.31 Days
Continuous |
|
| 07-Nov-25 08:00 | 07-Nov-25 17:00 | ATCO | TE | 732s Protection & Control (732s Mitsue) | block 21B/7L162 to update settings | 9 Hours
Continuous |
|
| 07-Nov-25 08:00 | 07-Nov-25 12:00 | ENMAX | Outage | 31.2TR (SS-31) | oil sampling - 31.2-TC | 4 Hours
Continuous |
|
| 07-Nov-25 10:30 | 18-Nov-25 15:00 | ATCO | TE | 710s Protection & Control (710s Vermilion) | blocking A and B of each relay for 7L117 secondary injection | 11.19 Days
Continuous |
|
| 07-Nov-25 12:01 | 07-Nov-25 14:00 | ENMAX | Outage | 31.3TR (SS-31) | oil sampling, tap changer, oil filtration maintenance | 119 Mins
Continuous |
|
| 07-Nov-25 14:01 | 07-Nov-25 16:00 | ENMAX | Outage | 31.1TR (SS-31) | oil sampling - 31.1-TC | 119 Mins
Continuous |
| This document and the information contained herein are based upon information and data which by their nature contain a degree of uncertainty and are subject to change. In addition, this document may contain information and data from public sources and/or third parties, which have been assumed to be accurate and complete and have not been verified. Accordingly, the Independent System Operator, operating as the Alberta Electric System Operator (the "AESO") makes no warranty, representation or guarantee, express or implied, with respect to this document or the information contained herein, including, but not limited to, any warranty, representation or guarantee of accuracy, completeness, timeliness, reliability, availability, absence of computer virus, non- infringement, merchantability or suitability for any purpose. Under no circumstances will the AESO, its members, officers, employees, contractors or agents, or any of their respective affiliates, be liable for any errors or omissions in, or any losses, damages or claims whatsoever, whether in contract, tort or otherwise, arising from use of or reliance upon, this document or any information contained herein. © 2009 Alberta Electric System Operator. All rights reserved |