| Alberta Electric System Operator | |
| System Co-ordination Plan | |
| 2026-06-11 to 2026-06-19 | |
| Approved Outages |
| Previous Version | |
| Download CSV |
| From | To | Owner | Type | Element | Scheduled Activity | Date/Time Comments | Interconnection |
|---|---|---|---|---|---|---|---|
| 26-Jul-24 10:00 | 31-Jul-26 16:00 | ATCO | Outage | 826s 504R (826s Marguerite Lake) | emergency removal to replace failed 502R @834S | 17,646 Hours
Continuous |
|
| 20-Mar-25 08:00 | 30-Jun-26 17:00 | ALTALINK | Outage | 256s C1 (256s Harmattan) | forced outage | 11,217 Hours
Continuous |
|
| 25-Nov-25 17:46 | 18-Sep-26 18:00 | ATCO | Outage | 876s 901T (876s Brintnell) | forced outage oil leaking | 7,127.23 Hours
Continuous |
|
| 27-Nov-25 08:30 | 27-Nov-27 16:30 | ALTALINK | TE | 89s Protection & Control (89s Ellerslie) | DSP card replacements on1057L B87/L3 and B240B1 B87/240B1 | 17,528 Hours
Daily |
|
| 04-Jan-26 08:00 | 02-Sep-26 16:00 | SUNCOR | Outage | 29EDD-34 260kV Bus 29PP-45 (29EDD-34), 29EDD-34 29-952-113 (29EDD-34), 29EDD-34 29PS-216 (29EDD-34) | urgent repairs on 29PT-224 at 29EDD34 on 29PP-45 bus | 5,791 Hours
Continuous |
|
| 12-Jan-26 07:00 | 03-Jul-26 17:00 | EPCOR | TE | 330p Protection & Control (330p Genesee) | protect blocking, annual relay maintenance and password changes | 4,137 Hours
Continuous |
|
| 21-Jan-26 08:00 | 30-Oct-26 16:00 | ENMAX | Outage | 5.7TR (SS-5) | 25kV switchgear replacement | 6,775 Hours
Continuous |
|
| 03-Feb-26 09:00 | 09-Jul-26 17:00 | ATCO | TE | 972s RTU/SCADA (972s Tinchebray) | config changes needed throughout the CETO project | 3,751 Hours
Continuous |
|
| 09-Feb-26 09:00 | 09-Jul-26 17:00 | ATCO | TE | 972s Protection & Control (972s Tinchebray) | block all 50BF protection until cutovers and associated commissioning are complete | 3,607 Hours
Continuous |
|
| 06-Mar-26 17:00 | 13-Nov-26 17:00 | EPCOR | Outage | T1 (Woodcroft) | woodcroft: TX1 LCR civil | 6,048 Hours
Continuous |
|
| 10-Mar-26 10:00 | 30-Nov-26 17:00 | ATCO | TE | 743s RTU/SCADA (743s Sarah Lake) | throughout the course of the project, different apparatus are being replaced, RTU will be blocked prior to download | 6,368 Hours
Continuous |
|
| 11-Mar-26 13:45 | 19-Jun-26 16:00 | ALTALINK | Outage | 535s C1 (535s Joffre) | breaker maintenance | 2,402.25 Hours
Continuous |
|
| 22-Mar-26 13:00 | 30-Jun-26 17:00 | BHE Canada | Outage | 120s C1 (120s Picture Butte), 120s C2 (120s Picture Butte) | forced outage | 2,404 Hours
Continuous |
|
| 28-Mar-26 12:00 | 26-Jun-26 17:00 | ATCO | TE | 833s RTU/SCADA (833s Mariana) | updating RTU/station controller configuration during SCADA upgrade project | 1,661 Hours
Continuous |
|
| 06-Apr-26 08:00 | 19-Jun-26 16:00 | ALTALINK | TE | 37s RTU/SCADA (37s North Calder) | RTU database updates | 1,784 Hours
Continuous |
|
| 25-Apr-26 08:00 | 01-Jul-26 16:00 | ENMAX | Outage | 1.82L (SS-1 - SS-5), 5B138-1.82 (SS-5) | 1 sub Transmission line cut over | 1,520 Hours
Continuous |
|
| 25-Apr-26 08:00 | 01-Jul-26 16:00 | ENMAX | Outage | 1.84L (SS-1 - SS-5), 5B138-1.84 (SS-5) | 1 sub Transmission line cut over | 1,520 Hours
Continuous |
|
| 01-May-26 17:00 | 25-Nov-26 17:00 | EPCOR | Outage | T1 (Meadowlark) | T1 LCR civil work | 4,993 Hours
Continuous |
|
| 19-May-26 07:00 | 28-Aug-26 17:00 | EPCOR | TE | 987s Protection & Control (987s Clover Bar) | protection blocking - relay maintenance and bus differential upgrade project | 2,434 Hours
Continuous |
|
| 20-May-26 09:00 | 16-Jun-26 17:00 | ALTALINK | Outage | 275s T2 (275s Jenner), 275s 46 (275s Jenner), 275s 2252 (275s Jenner) | maintenance | 656 Hours
Continuous |
|
| 25-May-26 08:00 | 11-Jun-26 16:00 | ALTALINK, Travers2SolarLP | TE | 102s Protection & Control (102s Langdon), 991s Protection & Control (991s Little Bow) | settings changes, circuit cutovers and testing associated with the DLR project | 416 Hours
Continuous |
|
| 25-May-26 08:00 | 11-Jun-26 16:00 | ALTALINK | TE | 102s RTU/SCADA (102s Langdon) | configuration changes and testing associated with the DLR project | 416 Hours
Daily |
|
| 26-May-26 09:30 | 15-Jul-26 16:30 | ALTALINK | Outage | 157s C1 (157s Lac La Biche) | trip test (157s852) | 1,207 Hours
Continuous |
|
| 27-May-26 18:00 | 19-Jun-26 17:00 | ALTALINK | Outage | 526s C1 (526s Buffalo Creek) | forced outage | 551 Hours
Daily |
|
| 30-May-26 09:00 | 13-Jun-26 17:00 | ATCO, ALTALINK | Outage | 972s 906 (972s Tinchebray), 972s 905 (972s Tinchebray), 9L62 (87s Gaetz - 972s Tinchebray) | connect new 9L62 to 972S and prepare to energize, string conductors 9L62 from str #3 to substation to 9L62D1, coordinate with AML conductor jumpers and termination at 9L86 Str 409 | 344 Hours
Continuous |
|
| 01-Jun-26 07:30 | 11-Jun-26 09:30 | ALTALINK, EPCOR | Outage | 930L (37s North Calder - Poundmaker), 37s 76 (37s North Calder), 37s Protection & Control (37s North Calder), 37s 81 (37s North Calder), PMDS10 (Poundmaker) | protection upgrade (37s76, 37s72, 37s81, 37s86) | 242 Hours
Continuous |
|
| 01-Jun-26 08:00 | 11-Jun-26 13:00 | ALTALINK, EPCOR | RB | 920L (37s North Calder - 557s Castle Downs) | 920LW - reclose block for Altalink working on 37s North Calder | 245 Hours
Continuous |
|
| 01-Jun-26 08:00 | 11-Jun-26 09:00 | ALTALINK, EPCOR | RB | 930L (37s North Calder - Poundmaker) | 930L - reclose block for Altalink working on 37s North Calder | 241 Hours
Continuous |
|
| 01-Jun-26 08:00 | 11-Jun-26 09:00 | ALTALINK, EPCOR | IO | 930L (37s North Calder - Poundmaker) | 930L outage: Altalink working on 37s North Calder | 241 Hours
Continuous |
|
| 01-Jun-26 08:00 | 11-Jun-26 16:00 | ALTALINK | TE | 102s Protection & Control (102s Langdon) | protection outages required for 'B' DC distribution cutover | 248 Hours
Continuous |
|
| 01-Jun-26 08:00 | 25-Jun-26 16:00 | ALTALINK | TE | 37s Protection & Control (37s North Calder) | trip test 37s76, 37s81 | 584 Hours
Continuous |
|
| 01-Jun-26 09:00 | 16-Jul-26 17:30 | ATCO | TE | 865s RTU/SCADA (865s Saddlehills) | updating RTU/station controller configuration during SCADA upgrade project | 1,088.5 Hours
Continuous |
|
| 02-Jun-26 10:00 | 13-Jul-26 16:00 | ATCO | Outage | 743s 701T (743s Sarah Lake), 743s 705 (743s Sarah Lake), 743s 605 (743s Sarah Lake), 743s 501 (743s Sarah Lake) | 743S Sarah lake rebuild | 990 Hours
Continuous |
|
| 04-Jun-26 07:01 | 10-Feb-27 17:00 | EPCOR | Outage | T1 (Rossdale) | rossdale: TX1 lcr civil | 6,034.98 Hours
Continuous |
|
| 04-Jun-26 08:00 | 13-Jun-26 16:00 | Syncrude | Outage | TL-1 (Aurora - Aurora), 14 (Aurora), 13 (Aurora) | CT-14 in G01 Substation at Aurora needs to be replaced | 224 Hours
Continuous |
|
| 08-Jun-26 00:00 | 29-Jun-26 23:59 | ATCO | Outage | 9L45 (856s Kinosis - 2049s Kettle River) | forced outage | 527.98 Hours
Continuous |
|
| 08-Jun-26 07:00 | 14-Jun-26 17:00 | EPCOR, ALTALINK | Outage | 657s T3 (657s Summerside), 657s SU2405 (657s Summerside), 657s SU2401 (657s Summerside), 657s SUAB3 (657s Summerside) | Summerside: T3 Doble and disconnect maintenance | 154 Hours
Continuous |
|
| 08-Jun-26 07:00 | 12-Jun-26 17:30 | ALTALINK | RB | 747L (37s North Calder - 711L tap), 747L (99s North St. Albert - 711L tap) | reclose block for aerial washing program | 106.5 Hours
Continuous |
|
| 08-Jun-26 07:00 | 11-Jun-26 17:00 | ALTALINK | TE | 87s RTU/SCADA (87s Gaetz) | RTU/HMI change for line 962L CETO project | 82 Hours
Continuous |
|
| 08-Jun-26 07:00 | 30-Oct-26 17:00 | EPCOR | TE | EP 511s Protection & Control (EP 511s Victoria) | 72kV breaker fail protection blocking | 2,626 Hours
Continuous |
|
| 08-Jun-26 07:15 | 11-Jun-26 17:45 | ALTALINK | Outage | 704L (51s Wainwright - 478s Tucuman), 478s 152 (478s Tucuman), 51s 704 (51s Wainwright) | transmission line maintenance | 82.5 Hours
Continuous |
|
| 08-Jun-26 07:30 | 11-Jun-26 16:30 | ALTALINK | RB | 757L (17s Benalto - 758L tap), 757L (297s Rimbey - 758L tap), 758L (534s Eckville - 757L tap) | 758L4-21 crossarm/structure replacement | 81 Hours
Daily |
|
| 08-Jun-26 08:00 | 12-Jun-26 20:00 | SUNCOR | Outage | 29EDD-94 29PP-97 260kV Bus (29EDD-94 Voyageur), 29EDD-94 29-952-9701 (29EDD-94 Voyageur), 29EDD-94 29-952-9712 (29EDD-94 Voyageur), 29EDD-94 29-952-9706 (29EDD-94 Voyageur), 29EDD-94 29-952-9707 (29EDD-94 Voyageur), 29EDD-94 29PS-386 (29EDD-94 Voyageur), 29EDD-94 29PS-638 (29EDD-94 Voyageur), 29EDD-94 29PS-395 (29EDD-94 Voyageur), 29EDD-94 29PS-629 (29EDD-94 Voyageur) | leak repair and top up | 108 Hours
Continuous |
|
| 08-Jun-26 08:00 | 26-Jun-26 16:00 | ENMAX | Outage | 37.2TR (SS-37) | maintenance | 440 Hours
Continuous |
|
| 08-Jun-26 08:00 | 11-Jun-26 16:00 | ATCO | RB | 7L10 (754s Ksituan River - 7LA10 tap), 7L10 (730s Rycroft - 7LA10 tap) | 7L10 TCM pole replacement | 80 Hours
Continuous |
|
| 08-Jun-26 08:00 | 19-Jun-26 14:30 | CMH, TCPL | TE | MH-65L (MHS-7 Brier Park - Cancarb Energy Medicine Hat) | maintenance on the LDR-65L-B | 270.5 Hours
Continuous |
|
| 08-Jun-26 08:00 | 25-Jun-26 10:00 | ALTALINK, ATCO | Outage | 87s 240kV East Bus (87s Gaetz), 9L62 (87s Gaetz - 972s Tinchebray), 962L (87s Gaetz - 972s Tinchebray), 986L (87s Gaetz - 972s Tinchebray), 9L86 (87s Gaetz - 972s Tinchebray), 87s T2 (87s Gaetz), 87s 1252 (87s Gaetz), 87s 1652 (87s Gaetz), 87s 1552 (87s Gaetz), 87s 1952 (87s Gaetz), 87s 34 (87s Gaetz) | completing all telecom work & protection testing with ATCO | 514 Hours
Continuous |
|
| 08-Jun-26 08:00 | 11-Jun-26 16:00 | ALTALINK | TE | 698s RTU/SCADA (698s Jackfish), AltaLink Telecom Equipment | MPLS 7705 A&B Node upgrade, raw socket upgrade, LAN switch replacement | 80 Hours
Daily |
|
| 08-Jun-26 08:00 | 11-Jun-26 16:00 | ALTALINK | TE | 818s Winefred RTU/SCADA, AltaLink Telecom Equipment | MPLS 7705 A node upgrade, raw socket upgrade, LAN switch replacement | 80 Hours
Continuous |
|
| 08-Jun-26 08:00 | 12-Jun-26 16:00 | ALTALINK | TE | 74s Protection & Control (74s Janet) | Enmax work | 104 Hours
Daily |
|
| 08-Jun-26 08:00 | 12-Jun-26 16:00 | ENMAX, ALTALINK | TE | 24.83L (74s Janet - SS-24) | 24.83L A and B protection outage | 104 Hours
Continuous |
|
| 08-Jun-26 08:00 | 11-Jun-26 16:00 | ENMAX | Outage | 32.1TR (SS-32) | transformer power factor test | 80 Hours
Continuous |
|
| 08-Jun-26 08:00 | 11-Jun-26 16:00 | ENMAX | Outage | 38.1TR (SS-38) | transformer power factor test | 80 Hours
Continuous |
|
| 08-Jun-26 08:00 | 12-Jun-26 16:00 | ATCO | RB | 7L68 (730s Rycroft - 811s Clairmont Lake) | emergency pole change on 7L03 and 7L69 str 437 from our line inspecting | 104 Hours
Continuous |
|
| 08-Jun-26 09:00 | 21-Jun-26 20:00 | SUNCOR | Outage | 29EDD-34 29PT-341 (29EDD-34), 29EDD-34 29-952-142 (29EDD-34), 29EDD-34 29-952-143 (29EDD-34), 29EDD-34 29-652-10200T (29EDD-34), 29EDD-34 29-652-10301 (29EDD-34), 29EDD-34 29-652-10302 (29EDD-34), 29EDD-34 29-652-10303 (29EDD-34), 29EDD-34 29PS-0375 (29EDD-34), 29EDD-34 29PS-0380 (29EDD-34), 29EDD-34 29PS-0381 (29EDD-34), 29EDD-34 29PS-0383 (29EDD-34), 29EDD-34 29PS-609 (29EDD-34) | 10 year PM on 29EDD34;29PT-341 system and 5 year, 10 year PM on 29EDD34;29PP-103 system |
323 Hours
Continuous |
|
| 08-Jun-26 09:00 | 22-Jun-26 17:00 | ATCO | Outage | 7L88 (865s Saddle Hills - 7L22 tap), 865s 701T (865s Saddlehills), 865s 701 (865s Saddle Hills) | protection and scada upgrade on 865S | 344 Hours
Continuous |
|
| 08-Jun-26 09:00 | 12-Jun-26 16:00 | ATCO | Outage | 7L03 (731s Elmworth - 7L09 tap) | TCM pole changes from test and treat | 103 Hours
Continuous |
|
| 08-Jun-26 13:00 | 11-Jun-26 17:00 | ALTALINK | TE | 283s Protection & Control (283s Violet Grove) | CT3 (283s853E) replacement
|
76 Hours
Continuous |
|
| 09-Jun-26 07:00 | 13-Jul-26 17:30 | ATCO | TE | 743s Protection & Control (743s Sarah Lake) | relay testing | 826.5 Hours
Continuous |
|
| 09-Jun-26 07:00 | 16-Jun-26 17:30 | ATCO | TE | 743s Protection & Control (743s Sarah Lake) | isolating 50BF/705 for relay testing | 178.5 Hours
Continuous |
|
| 09-Jun-26 07:00 | 16-Jun-26 17:30 | ATCO | TE | 743s Protection & Control (743s Sarah Lake) | isolating 50BF/605 for relay testing | 178.5 Hours
Continuous |
|
| 09-Jun-26 07:00 | 16-Jun-26 17:30 | ATCO | TE | 743s Protection & Control (743s Sarah Lake) | minor setting changes on 21B/6L11 relay | 178.5 Hours
Continuous |
|
| 09-Jun-26 07:00 | 16-Jun-26 17:30 | ATCO | TE | 743s Protection & Control (743s Sarah Lake) | minor setting changes on 21B/6L11 relay | 178.5 Hours
Continuous |
|
| 09-Jun-26 07:00 | 16-Jun-26 17:30 | ATCO | TE | 743s Protection & Control (743s Sarah Lake) | minor setting changes on 21B/6L11 relay | 178.5 Hours
Continuous |
|
| 09-Jun-26 07:00 | 16-Jun-26 17:30 | ATCO | TE | 743s Protection & Control (743s Sarah Lake) | minor settings changes on 21B/6L126 | 178.5 Hours
Continuous |
|
| 09-Jun-26 07:00 | 12-Jun-26 17:00 | ALTALINK | TE | 296s RTU/SCADA (296s Rosyth) | SCADA change for T3 revenue meter replacement | 82 Hours
Daily |
|
| 09-Jun-26 09:30 | 11-Jun-26 17:00 | ALTALINK, TRANSALTA | Outage | 164L (103s Goose Lake - 415s Drywood), 415s T1 (415s Drywood), 415s 21 (415s Drywood), 415s 164 (415s Drywood), 415s 352 (415s Drywood), 415s 15 (415s Drywood), 415s 146E (415s Drywood), 162L (229s Glenwood - 415s Drywood) | switch and breaker maintenance | 55.5 Hours
Continuous |
|
| 10-Jun-26 08:00 | 11-Jun-26 16:00 | ENMAX | Outage | 1.80L (SS-1 - SS-28), 28B138-1.80 (SS-28), 1MD138-1.80 (SS-1) | hv breaker maintenance 28B138-1.80 | 32 Hours
Continuous |
|
| 10-Jun-26 08:00 | 13-Jun-26 16:00 | SUNCOR | TE | 29EDD-34 RTU/SCADA (29EDD-34) | add duplicate power sources | 80 Hours
Continuous |
|
| 10-Jun-26 09:00 | 19-Jun-26 17:00 | BCH | Outage | 2L294 (BCH A. A. Lambert - BCH Cranbrook), T3 (BCH Cranbrook), T7 (BCH Cranbrook) | insulator replacement | 224 Hours
Continuous |
AB-BC |
| 10-Jun-26 10:00 | 11-Jun-26 16:00 | ATCO | Outage | 849s 904 (849s Joslyn Creek) | breaker maintenance, PRC-005 trip coil testing | 30 Hours
Continuous |
|
| 10-Jun-26 23:00 | 11-Jun-26 03:00 | ALTALINK | Outage | 62s T1 (62s Brazeau Plant), 62s 1 (62s Brazeau Plant) | maintenance | 3 Hours
Continuous |
|
| 11-Jun-26 03:00 | 11-Jun-26 07:00 | ALTALINK | Outage | 62s T2 (62s Brazeau Plant), 62s 2 (62s Brazeau Plant) | maintenance | 3 Hours
Continuous |
|
| 11-Jun-26 07:00 | 12-Jun-26 18:00 | ALTALINK | TE | 944L (132s Ware Junction - 275s Jenner), AltaLink Telecom Equipment | Tower re-alignment at 1080S Raptor, requires 944L outage | 35 Hours
Continuous |
|
| 11-Jun-26 07:00 | 12-Jun-26 17:00 | ALTALINK | Outage | 944L (132s Ware Junction - 275s Jenner), 944AL (1080s Raptor - 944AL tap), 1080s 240CB1 (1080s Raptor), 1080s 240MDS1 (1080s Raptor), 1080s 240MDS3(1080s Raptor) | dish realignment | 34 Hours
Continuous |
|
| 11-Jun-26 08:00 | 11-Jun-26 16:00 | ENMAX | Outage | 15.62L (SS-15 - SS-16), 15B69-15.62 (SS-15), 16B69-15.62 (SS-16) | shield wire replacement | 8 Hours
Continuous |
|
| 11-Jun-26 08:00 | 11-Jun-26 16:00 | ENMAX | Outage | 16.60L (SS-16 - SS-34) | shield wire replacement | 8 Hours
Continuous |
|
| 11-Jun-26 08:00 | 11-Jun-26 17:00 | ATCO, ALTALINK | TE | ATCO Telecom Equipment, APS# 134 Central East Transfer Out Overload Mitigation Scheme | radio maintenance | 9 Hours
Continuous |
|
| 11-Jun-26 08:00 | 11-Jun-26 12:00 | ENMAX | Outage | 33.84L (SS-33 - SS-43) | cable testing | 4 Hours
Continuous |
|
| 11-Jun-26 08:00 | 11-Jun-26 16:00 | ALTALINK | TE | 520s RTU/SCADA (520s Bennett), AltaLink Telecom Equipment | firewall replacement
|
8 Hours
Continuous |
|
| 11-Jun-26 09:00 | 11-Jun-26 16:00 | ATCO | TE | ATCO Telecom Equipment, 843s RTU/SCADA (843s Bigknife Creek) | telecom installation | 7 Hours
Continuous |
|
| 11-Jun-26 09:30 | 12-Jun-26 17:30 | ATCO | Outage | 772s 601C (772s Youngstown) | breaker SF6 GL312 testing | 32 Hours
Continuous |
|
| 11-Jun-26 10:30 | 11-Jun-26 13:30 | ALTALINK | Outage | 37s 88 (37s North Calder) | breaker fail trip testing | 3 Hours
Continuous |
|
| 11-Jun-26 23:00 | 12-Jun-26 05:00 | ALTALINK | Outage | 534s 138kV Bus 1 (534s Eckville), 297s 138kV Bus 1 (297s Rimbey), 297s 138kV Bus 2 (297s Rimbey), 757L (17s Benalto - 758L tap), 757L (297s Rimbey - 758L tap), 758L (534s Eckville - 757L tap), 297s T1 (297s Rimbey), 297s T2 (297s Rimbey), 534s T1 (534s Eckville), 297s 757 (297s Rimbey), 534s 758 (534s Eckville), 17s 757N (17s Benalto), 534s 40 (534s Eckville), 297s 189 (297s Rimbey), 297s 389 (297s Rimbey) | 757L199 replace cross-arm and insulators,17s dead end insulator replacement | 6 Hours
Continuous |
|
| 12-Jun-26 07:00 | 12-Jun-26 17:00 | EPCOR | TE | 330p RTU/SCADA (330p Genesee) | SCADA repair | 10 Hours
Continuous |
|
| 12-Jun-26 08:00 | 12-Jun-26 16:00 | ENMAX | Outage | 15.60L (SS-15 - SS-21), 15B69-15.60 (SS-15), 21B69-15.60 (SS-21) | shield wire replacement. 21.61L (oos) | 8 Hours
Continuous |
|
| 12-Jun-26 08:00 | 12-Jun-26 16:00 | ENMAX | Outage | 21.61L (SS-21 - SS-34), 21B69-21.61 (SS-21), 34B69-21.61 (SS-34) | shield wire replacement | 8 Hours
Continuous |
|
| 12-Jun-26 08:00 | 12-Jun-26 12:00 | ENMAX | Outage | 32.83L (SS-32 - SS-40), 40.1TR (SS-40), 40B138-32.83 (SS-40), 32B138-32.83 (SS-32) | summer substation washing | 4 Hours
Continuous |
|
| 12-Jun-26 08:00 | 14-Jun-26 16:00 | ALTALINK | TE | 72s RTU/SCADA (72s Leismer) | updating SCADA LAN switch settings
|
56 Hours
Continuous |
|
| 12-Jun-26 08:00 | 13-Jun-26 16:00 | ENMAX | TE | RTU/SCADA (SS-162) | communications outages | 32 Hours
Daily |
|
| 12-Jun-26 08:00 | 12-Jun-26 16:00 | ALTALINK | TE | AltaLink RTU/SCADA (AltaLink) | updating RTU config | 8 Hours
Continuous |
|
| 12-Jun-26 08:00 | 12-Jun-26 16:00 | ALTALINK | TE | AltaLink Telecom Equipment, AltaLink RTU/SCADA (AltaLink) | install power supply | 8 Hours
Continuous |
|
| 12-Jun-26 12:00 | 12-Jun-26 18:00 | ENMAX | Outage | 40B138-40.81 (SS-40), 40.81L (SS-40 - SS-41), 40.2TR (SS-40) | summer substation washing | 6 Hours
Continuous |
|
| 13-Jun-26 07:00 | 13-Jun-26 17:00 | EPCOR | TE | 987s RTU/SCADA (987s Clover Bar) | Cloverbar: RTU outage, substation firewall replacement – full communications outage | 10 Hours
Continuous |
|
| 13-Jun-26 08:00 | 13-Jun-26 16:00 | ENMAX | Outage | 11.83L (SS-162 - SS-11), 11B138-11.83 (SS-11), 162B138-RB85 (SS-162), 162B138-RB84 (SS-162) | power factor test - 162PT138-11.83 | 8 Hours
Continuous |
|
| 13-Jun-26 08:00 | 14-Jun-26 16:00 | ALTALINK | TE | 993s RTU/SCADA (993s Abee) | split the existing SCADA VLAN
|
32 Hours
Continuous |
|
| 13-Jun-26 08:00 | 13-Jun-26 18:00 | ENMAX | Outage | 32.83L (SS-32 - SS-40), 40.1TR (SS-40), 32B138-32.83 (SS-32), 40B138-32.83 (SS-40) | substation structure painting | 10 Hours
Continuous |
|
| 13-Jun-26 08:00 | 13-Jun-26 16:00 | ALTALINK | Outage | 133s T1 (133s Stelco Edmonton), 133s T2 (133s Stelco Edmonton) | measurements for 133s7 replacement | 8 Hours
Continuous |
|
| 13-Jun-26 17:01 | 25-Jun-26 17:00 | ATCO, ALTALINK | Outage | 9L62 (87s Gaetz - 972s Tinchebray) | Work on parallel line 9L86 | 272 Hours
Continuous |
|
| 14-Jun-26 07:00 | 14-Jun-26 17:00 | EPCOR | TE | 814s RTU/SCADA (814s Bellamy) | Bellamy: RTU Outage. Substation firewall replacement – Full communications outage, loss of visibility and control to all relays, RTU, DA or oil pressure, OLMS, and FOC related to station. Possible momentary loss of visibility to substation within first 5 minutes of work commencing. All protection | 10 Hours
Continuous |
|
| 14-Jun-26 08:00 | 14-Jun-26 12:00 | ENMAX | Outage | 1.80L (SS-1 - SS-28), 28.1TR (SS-28) | Spring Substation Washing. Reversing Switch Check - 28.1-TC | 4 Hours
Continuous |
|
| 14-Jun-26 08:00 | 14-Jun-26 18:00 | ENMAX | Outage | 40.81L (SS-40 - SS-41), 40.2TR (SS-40) | Substation Structure Painting | 10 Hours
Continuous |
|
| 14-Jun-26 08:30 | 19-Jun-26 14:00 | ENMAX | Outage | 13.82L (SS-13 - SS-22) | 13-Sub Disconnect Switch Replacement, SCO/QMF work | 125.5 Hours
Continuous |
|
| 14-Jun-26 09:00 | 14-Jun-26 16:00 | ENMAX | TE | Protection & Control (SS-162) | 162sub C60-1, C60-2, C30-3, C60-4, C60-5, C60-6, C60-7, C60-8, C60-13, C60-15, C60-16 Breaker fail communication outages (one at a time). Cutover Breaker Management relays to new SDN switches. | 7 Hours
Continuous |
|
| 14-Jun-26 09:00 | 15-Jun-26 16:00 | ENMAX | TE | RTU/SCADA (SS-162) | Communications outages for DNP communication only. Cutting over to new firewall and SDN switches. All protection remains in service except breaker fail protection (submitted on separate outage) | 31 Hours
Daily |
|
| 14-Jun-26 11:55 | 14-Jun-26 18:10 | ALTALINK, ENMAX | Outage | 42s 28 (42s Sarcee), 28.80L (42s Sarcee - SS-28) | Spring Substation Washing. Reversing Switch Check - 28.2-TC | 6.25 Hours
Continuous |
|
| 14-Jun-26 12:00 | 14-Jun-26 18:00 | ENMAX, ALTALINK | Outage | 28.80L (42s Sarcee - SS-28), 28.2TR (SS-28) | Spring Substation Washing. Reversing Switch Check - 28.2-TC | 6 Hours
Continuous |
|
| 15-Jun-26 07:00 | 24-Jul-26 17:00 | EPCOR | Outage | EP 805s J2403 (EP 805s Jasper) | Jasper: J2403 Replacement LCR | 946 Hours
Continuous |
|
| 15-Jun-26 07:00 | 19-Jun-26 17:00 | EPCOR | Outage | EP 511s Victoria T3 (EP 511s Victoria), EP 511s V724 (EP 511s Victoria), EP 511s V725 (EP 511s Victoria), EP 511s V722 (EP 511s Victoria) | Victoria: TX3 Relay Maintenance and V724/V725 (SF6) Breaker Maintenance | 106 Hours
Continuous |
|
| 15-Jun-26 07:00 | 19-Jun-26 17:00 | EPCOR | Outage | 987s GT2 (987s Clover Bar), 987s CGB2 (987s Clover Bar) | Cloverbar: Customer maintenance | 106 Hours
Continuous |
|
| 15-Jun-26 07:00 | 19-Jun-26 17:00 | EPCOR, ALTALINK | Outage | 1058L (657s Summerside - EP 803s Lambton), EP 803s L2404 (EP 803s Lambton), EP 803s L2403 (EP 803s Lambton) | 1058L: Aerial Washing Program | 106 Hours
Continuous |
|
| 15-Jun-26 07:00 | 26-Jun-26 17:00 | ALTALINK, EPCOR | TE | 1056L (89s Ellerslie - 629s Argyll Transfer Station) | MPLS upgrade cutover and commissioning | 274 Hours
Continuous |
|
| 15-Jun-26 07:00 | 16-Jun-26 16:00 | ENMAX | Outage | 1.82L (SS-1 - SS-5), B138-87 (SS-1), B138-88 (SS-1) | 1 sub transmission line cut over and commissioning | 33 Hours
Continuous |
|
| 15-Jun-26 07:00 | 18-Jun-26 17:00 | ALTALINK | TE | 87s RTU/SCADA (87s Gaetz) | RTU/HMI change: testing and commissioning SCADA points for line 986L CETO project | 82 Hours
Daily |
|
| 15-Jun-26 07:00 | 04-Sep-26 17:00 | EPCOR | TE | 805s Protection & Control (805s Jasper) | protection blocking, breaker replacement project | 1,954 Hours
Continuous |
|
| 15-Jun-26 07:00 | 19-Jun-26 17:00 | EPCOR | Outage | 72CK12 (987s Clover Bar - Kennedale), 987s CC13 (987s Clover Bar), 987s CCP7213 (987s Clover Bar), 987s CGB2 (987s Clover Bar), 987s CK725 (987s Clover Bar), 987s 72kV Bus 3 (987s Clover Bar) | Cloverbar: 72kV BUS 3 outage, CVT Doble and disconnect maintenance | 106 Hours
Continuous |
|
| 15-Jun-26 07:00 | 23-Jun-26 17:00 | ALTALINK, EPCOR | TE | 909L (310p Sundance - 665s Dome) | Altalink is relocating 2012F fiber for road move | 202 Hours
Continuous |
|
| 15-Jun-26 07:00 | 23-Jun-26 17:00 | ALTALINK, EPCOR | TE | 1139L (367s Harry Smith - EP Riverview) | Altalink is relocating 2012F fiber for road move | 202 Hours
Continuous |
|
| 15-Jun-26 07:00 | 23-Jun-26 17:00 | ALTALINK, EPCOR | TE | 1209L (89s Ellerslie - 330p Genesee) | Altalink is relocating 2012F fiber for road move | 202 Hours
Continuous |
|
| 15-Jun-26 07:00 | 23-Jun-26 17:00 | ALTALINK, EPCOR | TE | 1045L (EP 805s Jasper - 1045AL tap) | Altalink is relocating 2012F fiber for road move | 202 Hours
Continuous |
|
| 15-Jun-26 07:00 | 26-Jun-26 17:00 | EPCOR | Outage | 72JM18 (EP 805s Jasper - Meadowlark), M721 (Meadowlark), M722 (Meadowlark), T1 (Meadowlark) | Meadowlark: TX1 Zone, LCR Civil Work | 274 Hours
Continuous |
|
| 15-Jun-26 07:30 | 18-Jun-26 18:00 | ALTALINK | Outage | 510s 2652 (510s Sunnybrook), 510s 2752 (510s Sunnybrook), AML 511s 4852 (AML 511s Crossings), AML 511s 4952 (AML 511s Crossings), 1325L (510s Sunnybrook - AML 511s Crossings) | South Lines Crew will be doing component replacement on 1325L (STR 501-542) HVDC Maint. | 82.5 Hours
Continuous |
|
| 15-Jun-26 07:30 | 25-Jun-26 09:30 | ALTALINK | Outage | 19s 905 (19s Wabamun), 37s Protection & Control (37s North Calder), 37s 82 (37s North Calder), 37s 76 (37s North Calder), 905L (19s Wabamun - 37s North Calder) | P&C Upgrade (37s76, 37s82) | 242 Hours
Continuous |
|
| 15-Jun-26 07:30 | 15-Jun-26 16:30 | ALTALINK | RB | 757L (297s Rimbey - 758L tap), 758L (534s Eckville - 757L tap), 757L (17s Benalto - 758L tap) | 758L4-21 crossarm/structure replacements | 9 Hours
Daily |
|
| 15-Jun-26 08:00 | 15-Jun-26 16:00 | ENMAX | Outage | 9.80L (SS-9 - SS-31) | Shield Wire Replacement. HV Breaker SF6 Gas Sample - 9B138-9.80 | 8 Hours
Continuous |
|
| 15-Jun-26 08:00 | 18-Jun-26 16:00 | ALTALINK | TE | AltaLink Telecom Equipment, 332s RTU/SCADA (332s Ellis) | 2026 firewall program - 1 firewall, 1 MPLS node | 80 Hours
Continuous |
|
| 15-Jun-26 08:00 | 18-Jun-26 16:00 | ATCO | RB | 7L10 (754s Ksituan River - 7LA10 tap), 7L10 (730s Rycroft - 7LA10 tap) | 7L10 TCM pole replacement (live line ) | 80 Hours
Continuous |
|
| 15-Jun-26 08:00 | 18-Jun-26 16:00 | ATCO | Outage | 7L48 (794s Valleyview - 7LA48 tap) | Pole replacement from Test and treat | 80 Hours
Continuous |
|
| 15-Jun-26 08:00 | 26-Jun-26 16:00 | ALTALINK | TE | 89s Protection & Control (89s Ellerslie) | MPLS TPR re-arrangements project: relay testing and cutover | 272 Hours
Continuous |
|
| 15-Jun-26 08:00 | 18-Jun-26 16:00 | ALTALINK | TE | AltaLink Telecom Equipment, 364s RTU/SCADA (364s Whitecourt Industrial) | firewall replacement + MPLS 705 A&B node upgrade | 80 Hours
Continuous |
|
| 15-Jun-26 08:00 | 25-Jun-26 09:00 | ALTALINK, EPCOR | RB | 930L (37s North Calder - Poundmaker) | reclose block for Altalink working on 37s North Calder | 241 Hours
Continuous |
|
| 15-Jun-26 08:00 | 25-Jun-26 09:00 | ALTALINK, EPCOR | RB | 920L (37s North Calder - 557s Castle Downs) | reclose block for Altalink working on 37s North Calder | 241 Hours
Continuous |
|
| 15-Jun-26 08:00 | 18-Jun-26 16:00 | ATCO | RB | 7L03 (749s Flyingshot Lake - 7L09 tap), 7L03 (731s Elmworth - 7L09 tap) | changing red tag poles on 7L03 structures 19, 131 and 132 | 80 Hours
Continuous |
|
| 15-Jun-26 08:00 | 17-Jun-26 16:00 | ENMAX | Outage | 31.2TR (SS-31) | relay protection test | 56 Hours
Continuous |
|
| 15-Jun-26 08:00 | 03-Jul-26 16:00 | ALTALINK | TE | 254s RTU/SCADA (254s Coaldale) | replace the GE D20 RTU with a new EATON SMP SG-4260 RTU/HMI | 440 Hours
Daily |
|
| 15-Jun-26 08:00 | 21-Jun-26 14:00 | ATCO | Outage | 6L15 (763s Hanna - 775s Sullivan Lake), 763s 602 (763s Hanna), 775s 601 (775s Sullivan Lake) | 10-year climbing inspection on 6L15 | 150 Hours
Continuous |
|
| 15-Jun-26 08:00 | 18-Jun-26 16:00 | ENMAX | Outage | 41.1TR (SS-41) | transformer power factor test, secondary cable test, transformer maintenance relay fault pressure test | 80 Hours
Continuous |
|
| 15-Jun-26 08:00 | 18-Jun-26 16:00 | ALTALINK | TE | 397s RTU/SCADA (397s Benbow) | RTU outage required to add and test AIS1159 alarms | 80 Hours
Continuous |
|
| 15-Jun-26 08:00 | 18-Jun-26 16:00 | ALTALINK | TE | 328s RTU/SCADA (328s Pine Creek) | RTU outage required for HMI password update | 80 Hours
Continuous |
|
| 15-Jun-26 08:00 | 18-Jun-26 16:00 | ALTALINK | TE | 1182s RTU/SCADA (1182s Berland River) | RTU outage required to add 138kV bus volts metering | 80 Hours
Continuous |
|
| 15-Jun-26 08:00 | 18-Jun-26 16:00 | ALTALINK | TE | 397s Protection & Control (397s Benbow) | protection outages required to add AIS trip 3 alarm from A77/AIS1159 & B77/AIS1159 protections | 80 Hours
Continuous |
|
| 15-Jun-26 08:00 | 18-Jun-26 16:00 | ALTALINK | TE | 1182s Protection & Control (1182s Berland River) | protection outages required to add bus volts from T1 protections (redundant), and test 43/152 input to 96/152 protection (non-redundant) | 80 Hours
Continuous |
|
| 15-Jun-26 08:00 | 15-Jun-26 16:00 | ALTALINK | TE | AML 511s RTU/SCADA (AML 511s Crossings) | update the RTU/HMI configuration for the new intrusion alarms to meet the ARS target zero compliance | 8 Hours
Continuous |
|
| 15-Jun-26 09:00 | 29-Jun-26 10:00 | ATCO, CNRL | Outage | 859s 701T (859s Primrose), 859s 701 (859s Primrose), 859s 701TD (859s Primrose), 859s 704 (859s Primrose) | maintenance | 337 Hours
Continuous |
|
| 15-Jun-26 09:00 | 19-Jun-26 17:30 | ALTALINK, EPCOR | Outage | 915L (38s East Edmonton - 987s Clover Bar) | 915L/Cloverbar: CT/CVT/SA Doble and CDS35/CDS36/CDS7 Disconnect Maintenance and Relay Maintenance | 103.5 Hours
Continuous |
|
| 15-Jun-26 09:00 | 20-Jun-26 17:30 | ALTALINK, EPCOR | Outage | 1139L (367s Harry Smith - EP Riverview) | Riverview: 1139L Zone Doble and RWDS6/RWDS9/RWSA12 Disconnect Maintenance and RW2403/RW2405 (SF6) Breaker Maintenance | 127.5 Hours
Continuous |
|
| 15-Jun-26 09:30 | 19-Jun-26 17:00 | ALTALINK, EPCOR | Outage | 915L (38s East Edmonton - 987s Clover Bar), 987s C2403 (987s Clover Bar), 987s C2405 (987s Clover Bar) | 915L/Cloverbar: CT/CVT/SA Doble and CDS35/CDS36/CDS7 Disconnect Maintenance and Relay Maintenance | 103.5 Hours
Continuous |
|
| 15-Jun-26 09:30 | 20-Jun-26 17:00 | ALTALINK, EPCOR | Outage | 1139L (367s Harry Smith - EP Riverview), RW2405 (EP Riverview), RW2403 (EP Riverview) | Riverview: 1139L Zone Doble and RWDS6/RWDS9/RWSA12 Disconnect Maintenance and RW2403/RW2405 (SF6) Breaker Maintenance | 127.5 Hours
Continuous |
|
| 15-Jun-26 10:00 | 16-Jun-26 16:00 | ATCO | Outage | 970s 708 (970s Bourque) | breaker maintenance | 30 Hours
Continuous |
|
| 15-Jun-26 10:00 | 17-Jun-26 12:00 | ATCO | Outage | 2029s ACF12 (2029s Heathfield), 2029s 1219 (2029s Heathfield) | FILTER BANK AC MAINTENANCE @ HEATHFIELD 2029S ACF12 PRC-005 - TRIP COIL TESTING - BREAKER 1219 @ 2029S |
50 Hours
Continuous |
|
| 15-Jun-26 10:00 | 15-Jun-26 11:59 | ATCO | Outage | 849s 902 (849s Joslyn Creek) | PRC-005 trip coil testing | 1.98 Hours
Continuous |
|
| 15-Jun-26 10:30 | 18-Jun-26 16:30 | ALTALINK | Outage | 704L (51s Wainwright - 478s Tucuman), 51s 704 (51s Wainwright), 478s 152 (478s Tucuman) | transmission line maintenance | 78 Hours
Continuous |
|
| 15-Jun-26 11:00 | 19-Jun-26 17:00 | ALTALINK | Outage | 1002L (163s Amoco Empress - 275s Jenner), 163s 1752 (163s Amoco Empress), 163s 1552 (163s Amoco Empress), 163s Protection & Control (163s Amoco Empress) | replace 163s1752 breaker CT at 163s Amoco | 102 Hours
Continuous |
|
| 15-Jun-26 12:00 | 18-Jun-26 17:00 | ALTALINK | Outage | 245s 10 (245s Seebe) | 245s10 138kV CT replacement | 77 Hours
Continuous |
|
| 15-Jun-26 12:00 | 15-Jun-26 13:59 | ATCO | Outage | 849s 903 (849s Joslyn Creek) | PRC-005 trip coil testing | 1.98 Hours
Continuous |
|
| 15-Jun-26 12:30 | 18-Jun-26 17:00 | ALTALINK | Outage | 198s T1 (198s Blackfalds) | transformer maintenance, doble, IDD wiring repair & tap changer major maintenance | 76.5 Hours
Continuous |
|
| 15-Jun-26 12:30 | 18-Jun-26 17:00 | ALTALINK | Outage | 310p 952 (310p Sundance) | PRC5 breaker/major maintenance & grading capacitor replacement | 76.5 Hours
Continuous |
|
| 15-Jun-26 13:00 | 16-Jun-26 13:00 | ATCO | Outage | 780s 703 (780s Lubicon) | replace two densimeters | 24 Hours
Continuous |
|
| 15-Jun-26 13:00 | 17-Jun-26 16:30 | ALTALINK | Outage | 71s 252 (71s Lamoureux) | 138kV breaker maintenance | 51.5 Hours
Continuous |
|
| 15-Jun-26 13:00 | 18-Jun-26 16:30 | ALTALINK | TE | 245s Protection & Control (245s Seebe) | 245s10 CT replacement |
75.5 Hours
Continuous |
|
| 15-Jun-26 14:00 | 15-Jun-26 15:59 | ATCO | Outage | 849s 905 (849s Joslyn Creek) | PRC-005 trip coil testing | 1.98 Hours
Continuous |
|
| 16-Jun-26 06:00 | 16-Jun-26 11:00 | ALTALINK | Outage | 77s 29 (77s Sagitawah) | trip test (77s29) | 5 Hours
Continuous |
|
| 16-Jun-26 07:00 | 17-Jun-26 17:00 | EPCOR | Outage | 4R T1 (A.T. Plastics 4R), ATP1381 (A.T. Plastics 4Rs), 5R T3 (A.T. Plastics 5Rs), ATP1382 (A.T. Plastics 5Rs), ATPAB3 (A.T. Plastics 5Rs), ATPAB1 (A.T. Plastics 4Rs) | AT Plastic: ATPAB2/ATPAB3 disconnect repairs (site outage) | 34 Hours
Continuous |
|
| 16-Jun-26 07:00 | 17-Jun-26 13:00 | ALTALINK | Outage | 38s 736E (38s East Edmonton), 736L (38s East Edmonton - 293s Bernese), 293s 152 (293s Bernese), 293s 252 (293s Bernese), 293s T1 (293s Bernese), 293s T2 (293s Bernese) | CT replacement on 38s736E breaker | 30 Hours
Continuous |
|
| 16-Jun-26 07:30 | 19-Jun-26 18:00 | ALTALINK | Outage | 534s 758 (534s Eckville), 534s T1 (534s Eckville), 534s 138kV Bus 1 (534s Eckville), 758L (534s Eckville - 757L tap), 534s 40 (534s Eckville) | Str 4: replace arms insulators
Str 13 replace str Str 21 replace str single pole tangent Str 40: change single pole tangent. Str 38,39 arm changes |
82.5 Hours
Continuous |
|
| 16-Jun-26 07:30 | 16-Jun-26 17:30 | ALTALINK | RB | 760L (163s Amoco Empress - 760AL tap) | HOP to remove slack span from 7LA760-3 at the 7LA760 end of the 7L760/7LA760 junction temporary bypass | 10 Hours
Daily |
|
| 16-Jun-26 08:00 | 16-Jun-26 16:00 | ENMAX | Outage | 24.81L (SS-24 - SS-31), 31B138-24.81 (SS-31) | shield wire replacement | 8 Hours
Continuous |
|
| 16-Jun-26 08:00 | 16-Jun-26 16:00 | ENMAX | Outage | 13.82L (SS-13 - SS-22), 22.1TR (SS-22), 22B138-13.82 (SS-22) | maintenance on SW 82 @ 22 Sub | 8 Hours
Continuous |
|
| 16-Jun-26 08:00 | 16-Jun-26 20:00 | SUNCOR | TE | 29PL9-15 (29EDD-34 - 29EDD-56) | 29PL9-15 (PML7550) comm failure require meter replacement | 12 Hours
Continuous |
|
| 16-Jun-26 08:00 | 18-Jun-26 15:00 | ATCO | RB | 7L85 (801s Anderson - ATC 803s Bullpound), 7L85 (803s ATC Bullpound - 7LA85 tap), 7L85 (804s Wintering Hills - 7LA85 tap) | HOP required for installing interphase spacers on 7L85 live line | 55 Hours
Continuous |
|
| 16-Jun-26 08:00 | 16-Jun-26 16:00 | ALTALINK | TE | AltaLink Telecom Equipment | faulty RFU on radio requires troubleshooting and possible replacement to correct., end-to-end testing of radio required after repairs to ensure radio functionality is in place | 8 Hours
Continuous |
|
| 16-Jun-26 08:00 | 16-Jun-26 16:00 | ALTALINK | TE | 275s RTU/SCADA (275s Jenner) | techs to complete work on IRIG clock to fix a cycling alarms | 8 Hours
Continuous |
|
| 16-Jun-26 08:00 | 18-Jun-26 16:00 | ENMAX | Outage | 39.4TR (SS-39) | relay protection test | 56 Hours
Continuous |
|
| 16-Jun-26 08:00 | 16-Jun-26 16:00 | ENMAX | Outage | 9.3TR (SS-9) | take measurements in the secondary cabinet | 8 Hours
Continuous |
|
| 16-Jun-26 09:00 | 25-Jun-26 17:00 | ATCO | Outage | 972s 902 (972s Tinchebray), 972s 903 (972s Tinchebray) | connect new 9L86 to 972S and prepare to energize, complete protection commissioning | 224 Hours
Continuous |
|
| 16-Jun-26 09:00 | 19-Jun-26 15:00 | ATCO | Outage | 800s 702T (800s Friedenstal) | transformer class2 major testing | 78 Hours
Continuous |
|
| 16-Jun-26 09:00 | 16-Jun-26 14:00 | ALTALINK | Outage | 77s 40 (77s Sagitawah) | trip test (77s40) | 5 Hours
Continuous |
|
| 16-Jun-26 09:00 | 25-Jun-26 17:00 | ATCO | TE | 972s Protection & Control (972s Tinchebray) | commission both 21A and 21B relays for 9L86 during the line outage | 224 Hours
Continuous |
|
| 16-Jun-26 09:00 | 16-Jun-26 13:30 | ALTALINK, BCH | TE | 5L94 (BCH Cranbrook - 520s Bennett) | CBK 5L94 Protection/NIC RAS controller | 4.5 Hours
Continuous |
AB-BC |
| 16-Jun-26 10:00 | 16-Jun-26 11:59 | ATCO | Outage | 849s 906 (849s Joslyn Creek) | PRC-005 trip coil testing | 1.98 Hours
Continuous |
|
| 16-Jun-26 12:00 | 16-Jun-26 13:59 | ATCO | IO | 849s 907 (849s Joslyn Creek) | PRC-005 trip coil testing | 1.98 Hours
Continuous |
|
| 16-Jun-26 12:00 | 16-Jun-26 18:00 | ALTALINK | Outage | 77s 57 (77s Sagitawah) | trip test (77s57) | 6 Hours
Continuous |
|
| 16-Jun-26 13:01 | 18-Jun-26 13:00 | ATCO | Outage | 780s 705 (780s Lubicon) | breaker SF6 LTB145D1/B complete testing | 47.98 Hours
Continuous |
|
| 16-Jun-26 13:31 | 16-Jun-26 17:00 | ALTALINK, BCH | TE | 5L94 (BCH Cranbrook - 520s Bennett) | CBK 5L94 Protection/NIC RAS controller
|
3.48 Hours
Continuous |
AB-BC |
| 17-Jun-26 07:00 | 24-Jun-26 17:00 | EPCOR | Outage | 987s GT3 (987s Clover Bar), 987s CGB3 (987s Clover Bar) | maintenance | 178 Hours
Continuous |
|
| 17-Jun-26 07:00 | 18-Jun-26 16:00 | ENMAX | Outage | B138-94 (SS-1), B138-95 (SS-1), MD138_107 (SS-1), MD138_108 (SS-1) | 1 sub transmission line cut over. commissioning | 33 Hours
Continuous |
|
| 17-Jun-26 08:00 | 18-Jun-26 17:00 | ALTALINK | Outage | 262s 870W (262s Rocky Mountain House), 263s 870E (263s Strachan), 870L (262s Rocky Mountain House - 263s Strachan) | Replacing structure 12
Replacing cross arms and insulators on structure 13 |
33 Hours
Continuous |
|
| 17-Jun-26 08:00 | 17-Jun-26 16:00 | ALTALINK | TE | AltaLink Telecom Equipment | 28s West Brooks MPLS 7705A 1/1/8 Low Rx, test fiber, patch panel ports and MPLS SFP's and note any issues with fiber between 28s - 324s | 8 Hours
Continuous |
|
| 17-Jun-26 08:00 | 18-Jun-26 16:00 | ENMAX | Outage | 38.3TR (SS-38) | take measurements in secondary cabinet, test secondary CT | 32 Hours
Continuous |
|
| 17-Jun-26 08:00 | 18-Jun-26 16:00 | ENMAX | Outage | 22B138-13.82 (SS-22) | breaker maintenance | 32 Hours
Continuous |
|
| 17-Jun-26 08:00 | 17-Jun-26 16:00 | ALTALINK | TE | 48s Protection & Control (48s Pocaterra) | 887L B21/67N/L2 URD60, techs to complete settings change on the listed protection
|
8 Hours
Continuous |
|
| 17-Jun-26 08:30 | 18-Jun-26 16:00 | ALTALINK | TE | 895s Protection & Control (895s Suffield) | relay PRC005 maintenance (6yr compliance) and prep work for 2272L metering equipment upgrade | 31.5 Hours
Daily |
|
| 17-Jun-26 09:00 | 17-Jun-26 10:00 | ATCO | TE | ATCO Telecom Equipment, 768s RTU/SCADA (768s Rowley) | Rowley_S-Telecom-upgrade Rowley substation SAR OS TO V21, then N V22 | 1 Hour
Continuous |
|
| 17-Jun-26 09:00 | 17-Jun-26 13:30 | ALTALINK, BCH | TE | 1L275 (799s Coleman - BCH Natal), 1L274 (BCH Natal - BCH Line Creek tap) | NIC RAS PLC PY OOS | 4.5 Hours
Continuous |
AB-BC |
| 17-Jun-26 09:30 | 20-Jun-26 17:30 | ATCO | Outage | 6L21 tap | xfmr testing | 80 Hours
Continuous |
|
| 17-Jun-26 09:30 | 17-Jun-26 10:59 | ATCO | Outage | 856s 701 (856s Kinosis) | PRC-005 trip coil testing | 1.48 Hours
Continuous |
|
| 17-Jun-26 10:00 | 18-Jun-26 16:00 | ATCO | Outage | 700s 706C (700s Bonnyville), 700s 706 (700s Bonnyville) | test ASEA IMBD CT | 30 Hours
Continuous |
|
| 17-Jun-26 11:00 | 17-Jun-26 12:29 | ATCO | Outage | 856s 703 (856s Kinosis) | PRC-005 trip coil testing | 1.48 Hours
Continuous |
|
| 17-Jun-26 12:30 | 17-Jun-26 13:59 | ATCO | Outage | 856s 704 (856s Kinosis) | PRC-005 trip coil testing | 1.48 Hours
Continuous |
|
| 17-Jun-26 13:00 | 19-Jun-26 17:30 | ATCO | Outage | 2029s ACF14 (2029s Heathfield), 2029s 1221 (2029s Heathfield) | filter bank maintenance | 52.5 Hours
Continuous |
|
| 17-Jun-26 13:31 | 17-Jun-26 17:00 | ALTALINK, BCH | TE | 1L275 (799s Coleman - BCH Natal), 1L274 (BCH Natal - BCH Line Creek tap) | NIC RAS PLC SY OOS | 3.48 Hours
Continuous |
AB-BC |
| 17-Jun-26 14:00 | 17-Jun-26 15:29 | ATCO | Outage | 856s 705 (856s Kinosis) | PRC-005 trip coil testing | 1.48 Hours
Continuous |
|
| 18-Jun-26 08:00 | 18-Jun-26 16:00 | ALTALINK | TE | AltaLink Telecom Equipment | troubleshoot and replace defective radio components, end-to-end testing required after radio is repaired | 8 Hours
Continuous |
|
| 18-Jun-26 08:00 | 18-Jun-26 16:00 | ENMAX | TE | Protection & Control (SS-2) | 2 sub 86 BF-D87 protection outage, relays, lockout testing | 8 Hours
Continuous |
|
| 18-Jun-26 08:00 | 18-Jun-26 16:00 | ALTALINK | TE | 281s RTU/SCADA (281s Johnson) | configure push on the RTU to add more SCADA points | 8 Hours
Continuous |
|
| 18-Jun-26 08:00 | 18-Jun-26 16:00 | ALTALINK | TE | AML 511s RTU/SCADA (AML 511s Crossings) | update the RTU/HMI configuration for the new intrusion alarms to meet the compliance | 8 Hours
Continuous |
|
| 18-Jun-26 08:00 | 18-Jun-26 16:00 | ENMAX | Outage | 36.2TR (SS-36) | center & east 138KV LA hot spot - change LA's | 8 Hours
Continuous |
|
| 18-Jun-26 08:30 | 18-Jun-26 17:00 | ALTALINK | TE | 895s RTU/SCADA (895s Suffield) | Techs require supervisory outage to upgrade 2272L Meter module.~15min loss of visibility while updating RTU configs.. restored at the end of each day. | 8.5 Hours
Daily |
|
| 18-Jun-26 09:00 | 18-Jun-26 16:00 | ATCO | TE | ATCO Telecom Equipment | Salt Creek_S-Telecom/Thickwood Hills_S-Telecom- Radio Major IRU link Salt Creek to Thickwood. Link will be down for 4 hours 10am-2pm. MPACT TO THE FOLLOWING TRAFFIC DURING PM AND UPGRADE: TPRCP211 / 7L71 A - DOG ROB / PARSONS CREEK TPRCP212 / 7L71 B - DOG ROB / PARSONS CREEK TPRCP209 / 7L71 A - RUT |
7 Hours
Continuous |
|
| 18-Jun-26 09:00 | 18-Jun-26 15:00 | ALTALINK | TE | 42s RTU/SCADA (42s Sarcee), AltaLink Telecom Equipment | firewall replacement, MPLS 7705 A&B upgrade, raw socket upgrade, LAN switch replacement | 80 Hours
Continuous |
|
| 19-Jun-26 07:00 | 20-Jun-26 18:00 | ALTALINK | Outage | 379s 185N (379s Shell Canada Waterton), 396s 185 (396s Pincher Creek), 185L (379s Shell Canada Waterton - 396s Pincher Creek) | replacing cross arms and insulators | 35 Hours
Continuous |
|
| 19-Jun-26 08:00 | 19-Jun-26 16:00 | ENMAX, ALTALINK | Outage | 693L (42s Sarcee - SS-10), 10B138-693 (SS-10), 42s 693 (42s Sarcee) | 10B138-693 breaker SF6 gas sample and adjust SW 86 at 10 sub | 8 Hours
Continuous |
|
| 19-Jun-26 08:00 | 19-Jun-26 10:00 | ENMAX | Outage | 2.2TR (SS-2) | summer substation washing. reversing switch check - 2.2-TC | 2 Hours
Continuous |
|
| 19-Jun-26 08:00 | 19-Jun-26 16:00 | ENMAX, ALTALINK | IO | 693L (42s Sarcee - SS-10) | breaker SF6 gas sample - 10B138-693 | 8 Hours
Continuous |
|
| 19-Jun-26 09:00 | 25-Jun-26 17:00 | BCH | Outage | 2L294 (BCH A. A. Lambert - BCH Cranbrook) | maintenance | 152 Hours
Continuous |
AB-BC |
| 19-Jun-26 10:00 | 19-Jun-26 12:00 | ENMAX | Outage | 2.3TR (SS-2) | summer substation washing, reversing switch check - 2.3-TC | 2 Hours
Continuous |
|
| 19-Jun-26 12:00 | 19-Jun-26 16:00 | ENMAX | Outage | 2.4TR (SS-2) | summer substation washing, reversing switch check, bushing oil sampling | 4 Hours
Continuous |
| This document and the information contained herein are based upon information and data which by their nature contain a degree of uncertainty and are subject to change. In addition, this document may contain information and data from public sources and/or third parties, which have been assumed to be accurate and complete and have not been verified. Accordingly, the Independent System Operator, operating as the Alberta Electric System Operator (the "AESO") makes no warranty, representation or guarantee, express or implied, with respect to this document or the information contained herein, including, but not limited to, any warranty, representation or guarantee of accuracy, completeness, timeliness, reliability, availability, absence of computer virus, non- infringement, merchantability or suitability for any purpose. Under no circumstances will the AESO, its members, officers, employees, contractors or agents, or any of their respective affiliates, be liable for any errors or omissions in, or any losses, damages or claims whatsoever, whether in contract, tort or otherwise, arising from use of or reliance upon, this document or any information contained herein. © 2009 Alberta Electric System Operator. All rights reserved |