Alberta Electric System Operator | |
System Co-ordination Plan | |
2025-05-15 to 2025-05-23 | |
Approved Outages |
Previous Version | |
Download CSV |
From | To | Owner | Type | Element | Scheduled Activity | Date/Time Comments | Interconnection |
---|---|---|---|---|---|---|---|
05-Oct-18 08:00 | 30-Jun-26 16:00 | EPCOR | IO | C2 (Rossdale) | forced outage | 2,825.33 Days
Continuous |
|
24-Oct-18 01:13 | 30-Jun-26 16:00 | EPCOR | IO | C1 (Rossdale) | forced outage | 2,806.62 Days
Continuous |
|
27-Nov-23 08:00 | 20-Jun-25 16:00 | ENMAX | Outage | 32.2TR (SS-32) | 32 sub 32.2TR 8 kV bus switchgear demolition | 571.29 Days
Continuous |
|
26-Jul-24 10:00 | 31-Jul-26 16:00 | ATCO | Outage | 826s 504R (826s Marguerite Lake) | emergency removal to replace failed 502R @834S | 735.25 Days
Continuous |
|
23-Aug-24 13:45 | 31-May-25 14:29 | ALTALINK | Outage | 157s C1 (157s Lac La Biche) | forced outage | 281.03 Days
Continuous |
|
23-Sep-24 10:00 | 29-May-25 12:00 | ATCO | TE | 741s RTU/SCADA (741s Fox Creek) | RTU configuration on new and old RTU's onsite | 248.08 Days
Continuous |
|
05-Oct-24 00:00 | 30-Jun-25 17:00 | BHE Canada | Outage | 120s C1 (120s Picture Butte) | forced outage | 268.71 Days
Continuous |
|
21-Oct-24 12:00 | 29-May-25 17:30 | ATCO | TE | 741s Protection & Control (741s Fox Creek) | block 144kv and 25 kv bus protection and breaker fail protection for the duration of 741s project | 220.23 Days
Continuous |
|
03-Jan-25 07:00 | 27-Jun-25 17:00 | EPCOR | TE | 805s Protection & Control (805s Jasper), 805s RTU/SCADA (805s Jasper) | protection blocking for P&C maintenance at Jasper | 175.38 Days
Continuous |
|
06-Jan-25 09:30 | 23-May-25 17:00 | ALTALINK | Outage | 150L (42s Sarcee - 150AL tap), 42s 150W (42s Sarcee) | arctic arrow will require a GOI on 150L to rebuild the section of line from structure 47-198. | 137.27 Days
Continuous |
|
24-Jan-25 00:00 | 31-Dec-25 16:00 | ALTALINK | Outage | 74s C3 (74s Janet) | forced outage | 341.67 Days
Continuous |
|
10-Feb-25 00:00 | 23-Dec-25 23:00 | ATCO, ALTALINK | IO | 840s McNeill Station, 830L (562s Cypress - 840s McNeill Station), 840s 701T (840s McNeill Station), 840s 901T (840s McNeill Station) | available for emergency use only | 316.96 Days
Continuous |
AB-SK |
11-Feb-25 10:00 | 30-May-25 16:00 | ATCO | TE | 940s Protection & Control (940s Beartrap) | relay testing | 108.21 Days
Continuous |
|
11-Mar-25 00:00 | 31-Dec-25 16:00 | ALTALINK | Outage | 377s C1 (377s AML Hardisty) | forced outage | 295.71 Days
Continuous |
|
18-Mar-25 14:00 | 17-Mar-26 17:30 | ALTALINK | Outage | 217s C1 (217s North Red Deer) | cap. bank unavailable and cannot be energized due to Koncar CTs being present | 364.15 Days
Daily |
|
20-Mar-25 08:00 | 20-Mar-26 17:00 | ALTALINK | Outage | 263s C1 (263s Strachan) | forced outage | 365.38 Days
Continuous |
|
20-Mar-25 08:00 | 20-Mar-26 17:00 | ALTALINK | Outage | 256s C1 (256s Harmattan) | forced outage | 365.38 Days
Continuous |
|
28-Mar-25 17:31 | 02-Jun-25 16:00 | ATCO | TE | APS# 203 7L128-963S Overload Mitigation | DLR integration checks | 65.94 Days
Continuous |
|
31-Mar-25 07:00 | 07-Aug-25 17:00 | EPCOR | Outage | 987s T1 (987s Clover Bar), 987s CCP7213 (987s Clover Bar), 987s CCP7214 (987s Clover Bar) | Cloverbar - TX1 LCR | 129.42 Days
Continuous |
|
31-Mar-25 07:00 | 29-Aug-25 17:00 | EPCOR | TE | 987s Protection & Control (987s Clover Bar) | Cloverbar: protection blocking, 240 kV bus 3 differential for TX1 LCR duration | 151.42 Days
Continuous |
|
31-Mar-25 07:00 | 04-Jul-25 17:00 | EPCOR | TE | Protection & Control (Woodcroft) | Woodcroft: protection blocking for merging unit and protection upgrade. | 95.42 Days
Continuous |
|
14-Apr-25 07:00 | 23-May-25 17:00 | EPCOR | Outage | 52s E2402 (52s East Industrial), 52s T2 (52s East Industrial) | east industrial: emergency investigation and possible replacement of secondary cable and followed by TX2 protection upgrade cutovers | 39.42 Days
Continuous |
|
28-Apr-25 07:00 | 19-May-25 17:00 | ALTALINK, EPCOR | RB | 1044L (EP 805s Jasper - 816s Petrolia) | broken insulator replacement/insulator washing and City of Edmonton proximity request | 21.42 Days
Continuous |
|
28-Apr-25 07:00 | 19-May-25 17:00 | ALTALINK, EPCOR | RB | 1045L (EP 805s Jasper - 1045AL tap) | City of Edmonton proximity request | 21.42 Days
Continuous |
|
30-Apr-25 09:30 | 23-May-25 17:30 | ATCO | TE | 790s Protection & Control (790s Poplar Hill), 790s RTU/SCADA (790s Poplar Hill) | replace 5L999 protection |
23.33 Days
Continuous |
|
30-Apr-25 14:00 | 23-May-25 14:00 | ENMAX, ALTALINK | Outage | 1109L (SS-25 - SS-65) | complete termination of new cables on 1109L str 1 | 23 Days
Continuous |
|
30-Apr-25 14:00 | 23-May-25 14:00 | ENMAX, ALTALINK | Outage | 1109L (SS-25 - SS-65) | complete termination of new cables on 1109L str 1 | 23 Days
Continuous |
|
04-May-25 04:00 | 16-May-25 18:00 | SUNCOR | TE | SUNCOR ICCP Outage, Suncor RTU/SCADA (Suncor) | temporary power tie in | 12.58 Days
Continuous |
|
05-May-25 07:00 | 23-May-25 17:00 | EPCOR | Outage | 72NW15 (Namao - Woodcroft), T2 (Woodcroft), W725 (Woodcroft), W723 (Woodcroft), N726 (Namao), WAB2 (Woodcroft) | TX2 zone protection upgrade cutovers and W725 breaker maintenance | 18.42 Days
Continuous |
|
05-May-25 07:00 | 17-May-25 17:00 | EPCOR | Outage | CV5 (EP 511s Victoria - 557s Castle Downs), EP 511s Victoria T5 (EP 511s Victoria), 557s CD2405 (557s Castle Downs), 557s CD2406 (557s Castle Downs), EP 511s V2401 (EP 511s Victoria), EP 511s V727 (EP 511s Victoria), EP 511s V728 (EP 511s Victoria), EP 511s VDS25 (EP 511s Victoria) | CV5 zone doble and disconnect maintenance and Victoria TX5 doble and UGT manhole inspections | 12.42 Days
Continuous |
|
05-May-25 09:30 | 16-May-25 17:30 | ATCO | Outage | 2029s 500kV Bus 1200BS21 (2029s Heathfield), 2029s 1203 (2029s Heathfield), 2029s 1206 (2029s Heathfield), 2029s 1209 (2029s Heathfield), 2029s 1215 (2029s Heathfield), 2029s 1203B (2029s Heathfield), 2029s 1206B (2029s Heathfield), 2029s 1209B (2029s Heathfield), 2029s 1215B (2029s Heathfield) | PRC-005 - trip coil testing - breaker 1215 @ 2029s - relays & aux relays for 1200BS2 and bus breakers return on weekends |
11.33 Days
Continuous |
|
05-May-25 11:00 | 15-May-25 17:01 | ATCO | Outage | 7L90 (741s ATC Fox Creek - 7LA90 tap), 741s 701 (741s ATC Fox Creek) | 741s Fox Creek substation rebuild project - demo old cables, install and terminate new cables, cut over to new protection | 10.25 Days
Continuous |
|
06-May-25 07:00 | 15-May-25 17:30 | ALTALINK | Outage | 776L (308s Albchem Beaverhill Creek - 410s Josephburg), 308s 776W (308s Albchem Beaverhill Creek) | replace structures 39-41 in new alignment with new structures for line move project | 9.44 Days
Continuous |
|
06-May-25 08:00 | 22-May-25 16:00 | ATCO, CNRL | TE | 838s Protection & Control (838s Horizon Mining) | block relay, update firmware for latest security vulnerabilities | 16.33 Days
Continuous |
|
06-May-25 08:00 | 16-May-25 20:00 | SUNCOR | Outage | 29PL6-7 (30EDD-1 - 29EDD-5), 29PL6-4 (29EDD-1 Millennium - 30EDD-1), 30EDD-1 623T (30EDD-1), 30EDD-1 626T (30EDD-1), 30EDD-1 621T (30EDD-1), 30EDD-1 PSD-621-LOAD (30EDD-1), 30EDD-1 621 (30EDD-1), 30EDD-1 622 (30EDD-1), 30EDD-1 623 (30EDD-1), 30EDD-1 624 (30EDD-1), 30EDD-1 629 (30EDD-1), 30EDD-1 630 (30EDD-1), SPL6-7 (29EDD-5), 30EDD-1 622TD (30EDD-1), 30EDD-1 29PL6-4D1 (30EDD-1) | 29PP-116 G/H/I/E/F Bus pm | 10.5 Days
Continuous |
|
06-May-25 08:00 | 16-May-25 16:00 | ATCO, CNRL | TE | 838s RTU/SCADA (838s Horizon Mining) | block SMP/2440, update firmware for latest security vulnerabilities | 10.33 Days
Continuous |
|
07-May-25 08:30 | 16-May-25 17:00 | ATCO | Outage | 879s 702T (879s Scotford Upgrader), 879s 52-1B (879s Upgrader) | 702T maintenance, 502FCL maintenance | 9.35 Days
Continuous |
|
09-May-25 08:00 | 15-May-25 17:00 | PANC, ALTALINK, NEXENI | Outage | PCES02L (391s Balzac - Balzac Power Station), 391s 25 (391s Balzac), 52-211 (Balzac Power Station), 89-213BP (Balzac Power Station) | maintenance
|
6.38 Days
Continuous |
|
12-May-25 07:00 | 16-May-25 11:00 | EPCOR | Outage | 72NW15 (Namao - Woodcroft), N726 (Namao), W723 (Woodcroft) | doble and disconnect maintenance | 4.17 Days
Continuous |
|
12-May-25 07:00 | 17-May-25 17:00 | EPCOR | Outage | 805s T4 (805s Jasper), EP 805s J2405 (EP 805s Jasper), EP 805s J2406 (EP 805s Jasper), EP 805s JAB4 (EP 805s Jasper) | t4 zone relay maintenance | 5.42 Days
Continuous |
|
12-May-25 07:00 | 16-May-25 17:00 | EPCOR | RB | 711L (113s Inland Cement - 747L tap) | washing program | 4.42 Days
Continuous |
|
12-May-25 07:00 | 16-May-25 17:00 | ALTALINK | RB | 747L (99s North St. Albert - 711L tap), 747L (37s North Calder - 711L tap) | 711L / 747L: reclose block for EPCOR aerial washing program | 4.42 Days
Daily |
|
12-May-25 07:00 | 15-May-25 17:00 | ALTALINK | TE | 89s RTU/SCADA (89s Ellerslie) | testing and commissioning new fence gate status/alarms to ACC/EMS | 3.42 Days
Daily |
|
12-May-25 07:00 | 16-May-25 11:00 | EPCOR | Outage | 330p 500kV Bus 1 (330p Genesee), 330P 12TC1 (330p Genesee), 330p 1207 (330p Genesee), 330p 1204 (330p Genesee), 330p 1201 (330p Genesee), 330p 1210 (330p Genesee), 330p 1214 (330p Genesee), 330p 805 (330p Genesee), 330p 12TC1D (330p Genesee) | 500kV bus 1 yard lighting upgrade. | 4.17 Days
Continuous |
|
12-May-25 07:00 | 16-May-25 17:00 | EPCOR | Outage | 330p 12GT7D (330p Genesee), 330p 1214 (330p Genesee), 330p 1215 (330p Genesee) | MOD wiring and logic changes | 4.42 Days
Continuous |
|
12-May-25 07:30 | 15-May-25 17:30 | ALTALINK | RB | 1201L (520s Bennett - BCH Cranbrook) | south crew will be replacing anchors at structure #1201L400 | 3.42 Days
Daily |
|
12-May-25 08:00 | 29-Jun-25 16:00 | ENMAX | Outage | 3.84L (SS-3 - SS-13), 3B138-3.84 (SS-3), 13B138-3.84 (SS-13) | complete reconductoring of 3.84 line | 48.33 Days
Continuous |
|
12-May-25 08:00 | 22-May-25 16:00 | Syncrude | Outage | 12 (Aurora) | SCL - replace 72kV breaker in G01 substation | 10.33 Days
Continuous |
|
12-May-25 08:00 | 15-May-25 16:00 | ATCO | RB | 7L51 (788s Hotchkiss - 927s Buchanan Creek) | 7L51 climbing inspection | 3.33 Days
Continuous |
|
12-May-25 08:00 | 18-May-25 07:00 | CMH | Outage | MH-6L (MHS-1 CMH Power Plant - MHS-9 South Saskatchewan), MHS-9 MH138-T11 (MHS9 Power Plant), MHS-9 MH138-902 (MHS-9 South Saskatchewan) | replacement of bushings on MH138-T11 and perform breaker maintenance on MH138-902 | 5.96 Days
Continuous |
|
12-May-25 08:00 | 15-May-25 17:00 | ALTALINK | RB | 113L (20s Ghost - 33s Spray) | prepping for component replacement str 114-193 | 3.38 Days
Daily |
|
12-May-25 08:00 | 15-May-25 16:00 | ENMAX | Outage | 9.1TR (SS-9) | relay protection test | 3.33 Days
Continuous |
|
12-May-25 09:00 | 17-Jun-25 20:00 | SUNCOR | TE | 29EDD-94 Protection & Control (29EDD-94 Voyageur) | block 7 relays CWP16 | 36.46 Days
Continuous |
|
12-May-25 09:00 | 15-May-25 18:00 | ALTALINK | Outage | 799L (235s Entwistle - 443s South Mayerthorpe), 235s 799N (235s Entwistle) | 799L rebuild (Str 858-889) | 3.38 Days
Continuous |
|
12-May-25 09:30 | 16-May-25 17:30 | ATCO | Outage | 757s 701T (757s Battle River), 757s 606 (757s Battle River), 757s 701 (757s Battle River) | transformer class1 major testing | 4.33 Days
Continuous |
|
12-May-25 10:00 | 15-May-25 16:00 | ATCO | Outage | 7L89 (700s Bonnyville - 721s La Corey), 700s 703 (700s Bonnyville) | PRC-005 relay testing | 3.25 Days
Continuous |
|
12-May-25 10:00 | 16-May-25 16:00 | ATCO | TE | 732s Protection & Control (732s Mitsue) | microprocessor relay testing | 4.25 Days
Continuous |
|
12-May-25 11:00 | 15-May-25 17:00 | ATCO, ALTALINK | RB | 9L960 (13s Deerland - 825s Whitefish Lake) | climbing inspection | 3.25 Days
Continuous |
|
12-May-25 11:00 | 15-May-25 17:00 | ATCO, ALTALINK | RB | 9L961 (13s Deerland - 825s Whitefish Lake) | climbing inspection | 3.25 Days
Continuous |
|
12-May-25 11:00 | 15-May-25 17:00 | ATCO, ALTALINK | RB | 9L960 (13s Deerland - 825s Whitefish Lake) | climbing inspection | 3.25 Days
Continuous |
|
12-May-25 11:00 | 15-May-25 17:00 | ATCO, ALTALINK | RB | 9L961 (13s Deerland - 825s Whitefish Lake) | climbing inspection | 3.25 Days
Continuous |
|
12-May-25 12:00 | 22-May-25 16:00 | ATCO | TE | 849s Protection & Control (849s Joslyn Creek) | once firmware upgrade completed at Horizon, line differential testing required, block relay and test | 10.17 Days
Continuous |
|
13-May-25 07:00 | 23-May-25 17:00 | EPCOR | Outage | 987s T3 (987s Clover Bar), 987s T1 (987s Clover Bar), 987s CCP7213 (987s Clover Bar), 987s CCP7214 (987s Clover Bar), 987s C2402 (987s Clover Bar), 987s C2401 (987s Clover Bar), 987s C2403 (987s Clover Bar), 987s C2407 (987s Clover Bar), 987s CDS25 (987s Cloverbar) | clearance and induction hazards for TX1 construction | 10.42 Days
Continuous |
|
13-May-25 07:00 | 15-May-25 17:00 | ALTALINK, EPCOR | Outage | 809L (320p Keephills - 510s Sunnybrook), 834L (320p Keephills - 384s Keystone), 400L (320p Keephills - 320p Keephills), 401L (320p Keephills - 320p Keephills), 767L (320p Keephills - 767CL tap), 320p T1 (320p Keephills), 320p T4 (320p Keephills), 320p 138kV Bus (320p Keephills), 320p 809X (320p Keephills), 320p 834X (320p Keephills), 320p 767N (320p Keephills), 320p 400 (320p Keephills), 320p 401 (320p Keephills), 320p 91 (320p Keephills), 320p 105 (320p Keephills) | replace 320p92 and perform maintenance on 320p400 and 320p401 | 2.42 Days
Continuous |
|
13-May-25 08:00 | 22-May-25 17:00 | ALTALINK | Outage | 163s T2 (163s Amoco Empress) | 163sT2 oil reclaim and maintenance | 9.38 Days
Continuous |
|
13-May-25 08:00 | 30-May-25 09:00 | BCH | Outage | T3 (BCH Natal) | disconnect T3 | 17.04 Days
Continuous |
AB-BC |
13-May-25 08:30 | 16-May-25 16:00 | ATCO, FMGW | Outage | 1024s PT-6001 (1024s Granlea), 1024s PT-6002 (1024s Granlea), 1024s 952-600001 (1024s Granlea), 1024s PS-6005 (1024s Granlea), 1024s PS-6006 (1024s Granlea), 1024s PS-6007 (1024s Granlea), 1024s PS-6008 (1024s Granlea) | transformer leak repairs and inspections and 34kv bus bird proofing installation | 3.31 Days
Continuous |
|
13-May-25 08:30 | 15-May-25 18:00 | ATCO, ALTALINK, FMGW | TE | 1024s RTU/SCADA (1024s Granlea) | networking cutover | 2.4 Days
Continuous |
|
13-May-25 09:00 | 16-May-25 17:00 | ATCO | TE | 879s Scotford Upgrader RTU/SCADA | 702T ITM wiring/settings update | 3.33 Days
Continuous |
|
13-May-25 12:17 | 15-May-25 15:00 | ALTALINK, BCH | Outage | 786L (799s Coleman - BCH Natal), 1D24 (BCH Natal), 799s 786W (799s Coleman) | out-of-service on BCH request | 2.11 Days
Continuous |
AB-BC |
14-May-25 04:01 | 14-Jul-25 07:30 | ALTALINK | Outage | 799s T3 (799s Coleman) | replace T3 | 61.15 Days
Continuous |
|
14-May-25 07:00 | 15-May-25 15:00 | ALTALINK | TE | 267s RTU/SCADA (267s Killarney Lake) | changing default settings from VLAN1 to VLAN2 | 1.33 Days
Daily |
|
14-May-25 07:00 | 16-May-25 17:00 | ALTALINK | TE | 184s RTU/SCADA (184s Petro-Canada Edmonton) | replace failing RTU | 2.42 Days
Daily |
|
14-May-25 08:00 | 10-Feb-26 16:00 | ENMAX | TE | Protection & Control (SS-32) | 32sub 138kV autoswitching protection outage | 272.38 Days
Continuous |
|
14-May-25 08:00 | 15-May-25 17:30 | ALTALINK | Outage | 425L (194s South Red Deer - 217s North Red Deer), 217s 425 (217s North Red Deer), 194s 425 (194s South Red deer) | breaker maintenance | 1.4 Days
Continuous |
|
14-May-25 08:00 | 15-May-25 16:00 | ENMAX | Outage | 41.84L (SS-41 - SS-54), 41B138-41.84 (SS-41), 54B138-41.84 (SS-54) | HV breaker maintenance | 1.33 Days
Continuous |
|
14-May-25 09:30 | 16-May-25 17:30 | ATCO | Outage | 790s 703T (790s Poplar Hill), 790s 704 (790s Poplar Hill) | trip coil testing | 2.33 Days
Continuous |
|
14-May-25 23:00 | 15-May-25 03:00 | ALTALINK | Outage | 62s T1 (62s Brazeau Plant), 62s 1 (62s Brazeau Plant) | maintenance | 4 Hours
Continuous |
|
15-May-25 03:00 | 15-May-25 07:00 | ALTALINK | Outage | 62s T2 (62s Brazeau Plant), 62s 2 (62s Brazeau Plant) | maintenance | 4 Hours
Daily |
|
15-May-25 07:00 | 15-May-25 17:00 | ALTALINK | TE | AltaLink Telecom Equipment, 373s RTU/SCADA (373s Madden), 238s RTU/SCADA (238s Shell Harmattan) | 238S and 373S supervisories are unstable, MDS master super has issue and needs attention | 10 Hours
Daily |
|
15-May-25 08:00 | 15-May-25 16:00 | ENMAX | Outage | 1.81L (SS-1 - SS-20), 20.1TR (SS-20), 20B138-1.81 (SS-20), 20MD138-20.1TR (SS-20) | spring substation washing. check reversing switch. | 8 Hours
Continuous |
|
15-May-25 08:00 | 15-May-25 17:00 | ALTALINK | TE | 35s Protection & Control (35s Rundle), AltaLink RTU/SCADA (AltaLink) | MDA card replacement | 9 Hours
Daily |
|
15-May-25 08:00 | 16-May-25 20:00 | SUNCOR | TE | 29EDD-60 Protection & Control (29EDD-60 Inglis Island), 29EDD-61 Protection & Control (29EDD-61 Stony Island) | 29EDD-60/61 OLRAS time sync alarm - update IRIG B settings | 1.5 Days
Continuous |
|
15-May-25 08:00 | 15-May-25 16:00 | ENMAX | Outage | 16.1TR (SS-16) | 16 sub 69kV PT outage. power factor test - 16PT69-1 | 8 Hours
Continuous |
|
15-May-25 08:00 | 15-May-25 17:00 | ALTALINK | TE | 17s Protection & Control (17s Benalto) | techs to replace DPS module and complete firmware update/testing | 9 Hours
Daily |
|
16-May-25 08:00 | 16-May-25 12:00 | ENMAX, ALTALINK | Outage | 28.80L (42s Sarcee - SS-28), 28.2TR (SS-28), 28B138-28.80 (SS-28), 28MD138-28.2TR (SS-28) | spring substation washing and check reversing switch | 4 Hours
Continuous |
|
16-May-25 08:00 | 18-May-25 15:00 | ATCO | Outage | 6L03 (757s Battle River - 6L17 tap), 757s 603 (757s Battle River) | installing ADSS/ADFO communication cables from 7L701-1 & 6L03-1830 to 6L03 A frame & placing cables in cable tray into control building | 2.29 Days
Continuous |
|
16-May-25 08:00 | 16-May-25 12:00 | ENMAX, ALTALINK | IO | 28.80L (42s Sarcee - SS-28), 28.2TR (SS-28), 28B138-28.80 (SS-28), 28MD138-28.2TR (SS-28), SW82 (SS-28) | spring substation washing and check reversing switch | 4 Hours
Daily |
|
16-May-25 08:00 | 16-May-25 16:00 | ENMAX | Outage | 54.81L (SS-54 - SS-65), 54B138-54.81 (SS-54) | hv breaker maintenance - 54B138-54.81 | 8 Hours
Continuous |
|
16-May-25 09:00 | 16-May-25 17:00 | ATCO | Outage | 7L51 (ATC 793s West Peace River - 927s Buchanan Creek), ATC 793s 701 (ATC 793s West Peace River) | emergency outage needed to replace broken structure | 8 Hours
Continuous |
|
16-May-25 11:00 | 16-May-25 16:00 | ATCO | Outage | 9L101 (957s McClelland - 2005s Secord), 957s 901 (957s McClelland), 957s 902 (957s McClelland) | repair - 957S 900SST1 leak severity | 5 Hours
Continuous |
|
16-May-25 12:01 | 16-May-25 18:00 | ENMAX | Outage | 1.80L (SS-1 - SS-28), 28.1TR (SS-28), 28B138-1.80 (SS-28), 28MD138-28.1TR (SS-28) | spring substation washing | 5.98 Hours
Continuous |
|
16-May-25 17:00 | 16-May-25 19:00 | ALTALINK, BCH | Outage | 786L (799s Coleman - BCH Natal), 1D24 (BCH Natal), 799s 786W (799s Coleman) | BCH request | 2 Hours
Continuous |
AB-BC |
16-May-25 20:01 | 28-May-25 20:00 | SUNCOR | Outage | 29PL6-7 (30EDD-1 - 29EDD-5), 29PL6-1 (30EDD-1 - 29EDD-55), 30EDD-1 621T (30EDD-1), 30EDD-1 626T (30EDD-1), 30EDD-1 622 (30EDD-1), 30EDD-1 621 (30EDD-1), 30EDD-1 628 (30EDD-1), 30EDD-1 629 (30EDD-1), 30EDD-1 630 (30EDD-1), SPL6-7 (29EDD-5), 30EDD-1 621TD (30EDD-1), 30EDD-1 626TD (30EDD-1), 30EDD-1 625TD (30EDD-1), 30EDD-1 29PL6-1CS (30EDD-1) | 29PP-116 d/e/f/g 5 year pm | 12 Days
Continuous |
|
17-May-25 08:00 | 17-May-25 12:00 | ENMAX, ALTALINK | Outage | 833L (SS-2 - SS-12), 12B138-833L (SS-12), 12.2TR (SS-12), SW83 (SS-12), 12MD138-12.2TR (SS-12) | summer substation washing | 4 Hours
Continuous |
|
17-May-25 08:00 | 17-May-25 12:00 | ENMAX, ALTALINK | IO | 833L (SS-2 - SS-12) | summer substation washing | 4 Hours
Daily |
|
17-May-25 09:30 | 17-May-25 17:30 | ATCO | TE | 731s Protection & Control (731s Elmworth) | 7L69 sync check settings update on A and B relays at 731s Elmworth | 8 Hours
Continuous |
|
17-May-25 12:01 | 17-May-25 18:00 | ENMAX, ALTALINK | Outage | 832L (SS-10 - SS-12), 12.1TR (SS-12), 12B138-832L (SS-12), SW84 (SS-12), 12MD138-12.1TR (SS-12) | summer substation washing | 5.98 Hours
Continuous |
|
17-May-25 12:01 | 17-May-25 18:00 | ENMAX, ALTALINK | IO | 832L (SS-10 - SS-12) | 12.2TR CT replacement | 5.98 Hours
Continuous |
|
18-May-25 07:00 | 25-May-25 17:00 | ALTALINK, EPCOR | Outage | 1055L (629s Argyll Transfer Station - 816s Petrolia), 240BA3 (629s Argyll Transfer Station - 814s Bellamy), 816s P2402 (816s Petrolia), 816s P2403 (816s Petrolia), 816s PDS11 (816s Petrolia) | pole refurbishment, doble and disconnect maintenance | 7.42 Days
Continuous |
|
18-May-25 07:00 | 25-May-25 17:00 | ALTALINK, EPCOR | RB | 1056L (89s Ellerslie - 629s Argyll Transfer Station) | pole refurbishment | 7.42 Days
Continuous |
|
18-May-25 08:00 | 18-May-25 12:00 | ENMAX, ALTALINK | Outage | 693L (42s Sarcee - SS-10), 10.2TR (SS-10), 10B138-693 (SS-10), SW84 (SS-10), 10MD138-10.2TR (SS-10), 42s 693 (42s Sarcee) | summer substation washing | 4 Hours
Continuous |
|
18-May-25 08:00 | 18-May-25 12:00 | ENMAX, ALTALINK | IO | 693L (42s Sarcee - SS-10) | summer substation washing | 4 Hours
Daily |
|
18-May-25 12:01 | 18-May-25 18:00 | ENMAX, ALTALINK | Outage | 832L (SS-10 - SS-12), 10.1TR (SS-10), 10B138-832 (SS-10), SW83 (SS-10), 10MD138-10.1TR (SS-10) | summer substation washing | 5.98 Hours
Continuous |
|
18-May-25 12:01 | 18-May-25 18:00 | ENMAX, ALTALINK | IO | 832L (SS-10 - SS-12) | summer substation washing | 5.98 Hours
Continuous |
|
19-May-25 08:00 | 19-May-25 12:00 | ENMAX | Outage | 6.80L (SS-6 - SS-35), 6B138-6.80 (SS-6), 6.4TR (SS-6), 6MD138-6.4TR (SS-6) | summer substation washing. | 4 Hours
Continuous |
|
19-May-25 08:00 | 20-May-25 20:00 | SUNCOR | TE | 29EDD-94 Protection & Control (29EDD-94 Voyageur) | 29EDD-94H PMU data validation | 1.5 Days
Continuous |
|
19-May-25 09:30 | 20-May-25 17:30 | ATCO | Outage | 749s 706 (749s Flyingshot Lake) | trip coil testing. | 1.33 Days
Continuous |
|
19-May-25 12:00 | 19-May-25 18:00 | ENMAX | Outage | 6.82L (SS-6 - SS-41), 6B138-6.82 (SS-6), 6.1TR (SS-6) | summer substation washing. | 6 Hours
Continuous |
|
20-May-25 07:00 | 30-May-25 17:00 | EPCOR | Outage | T3 (Rossdale), R723 (Rossdale), R724 (Rossdale) | Rossdale: TX3 zone LCR demo outage | 10.42 Days
Continuous |
|
20-May-25 07:00 | 21-May-25 17:00 | ALTALINK, EPCOR | RB | 430L (330P Genesee - 510S Sunnybrook) | washing program | 1.42 Days
Continuous |
|
20-May-25 07:00 | 21-May-25 17:00 | ALTALINK, EPCOR | RB | 430L (330P Genesee - 510S Sunnybrook) | washing program | 1.42 Days
Daily |
|
20-May-25 07:00 | 21-May-25 17:00 | EPCOR | Outage | 72CK12 (987s Clover Bar - Kennedale), 987s CK725 (987s Clover Bar), K724 (Kennedale) | metering upgrade cutovers | 1.42 Days
Continuous |
|
20-May-25 07:00 | 22-May-25 16:00 | ALTALINK | TE | 83s Protection & Control (83s Taber), 336s Protection & Control (336s Fincastle) | troubleshoot communication issues with 610L ‘B’ protection relays between 83s and 336s. | 2.38 Days
Daily |
|
20-May-25 07:00 | 20-May-25 17:00 | EPCOR | Outage | 330p 1202 (330p Genesee) | 1202 bay yard lighting upgrade (pole #7) | 10 Hours
Continuous |
|
20-May-25 07:00 | 20-May-25 17:00 | ALTALINK | TE | 421s Protection & Control (421s Hays) | A87/50/51/T1 remote setting change being performed | 10 Hours
Daily |
|
20-May-25 07:00 | 20-May-25 17:00 | ALTALINK | TE | 428s Protection & Control (428s Namaka) | A87/50/51/T1, A87/50/51/T2 remote setting change being performed | 10 Hours
Daily |
|
20-May-25 07:00 | 20-May-25 17:00 | ALTALINK | TE | 431s Protection & Control (431s Hussar) | A87/50/51NN/T1, A87/50/51NN/T2 remote setting change being performed | 10 Hours
Daily |
|
20-May-25 07:00 | 20-May-25 17:00 | ALTALINK | TE | 435s Protection & Control (435s Bassano) | A87/50/51/51N/T1 Remote setting change being performed | 10 Hours
Daily |
|
20-May-25 07:00 | 20-May-25 17:00 | ALTALINK | TE | 437s Protection & Control (437s Baymag) | A87/50/51/T1, A87/50/51/T2 remote setting change being performed | 10 Hours
Daily |
|
20-May-25 07:00 | 20-May-25 17:00 | ALTALINK | TE | 422s Protection & Control (422s Westwood) | settings change | 10 Hours
Daily |
|
20-May-25 07:00 | 20-May-25 17:00 | ALTALINK | TE | 429s Protection & Control (429s Nelson Lake) | settings change | 10 Hours
Daily |
|
20-May-25 07:00 | 20-May-25 17:00 | ALTALINK | TE | 432s Protection & Control (432s Carvel) | settings change | 10 Hours
Daily |
|
20-May-25 07:00 | 20-May-25 17:00 | ALTALINK | TE | 438s Protection & Control (438s Westlock) | settings change | 10 Hours
Daily |
|
20-May-25 07:00 | 20-May-25 17:00 | ALTALINK | TE | 445s Protection & Control (445s Elk River) | settings change | 10 Hours
Daily |
|
20-May-25 07:30 | 22-May-25 16:30 | ALTALINK, ENEL | Outage | 205s T1 (205s Castle Rock Ridge), 205s 52M1 (205s Castle Rock Ridge), 205s 89T1 (205s Castle Rock Ridge) | maintenance | 2.38 Days
Continuous |
|
20-May-25 07:30 | 23-May-25 17:30 | ALTALINK | RB | 113L (20s Ghost - 33s Spray) | component replacement str 114-193 | 3.42 Days
Daily |
|
20-May-25 08:00 | 22-May-25 16:00 | ATCO | RB | 7L51 (788s Hotchkiss - 927s Buchanan Creek) | climbing inspection | 2.33 Days
Continuous |
|
20-May-25 08:00 | 21-May-25 16:00 | ENMAX | Outage | 6.82L (SS-6 - SS-41), 41B138-6.82 (SS-41), 6B138-6.82 (SS-6) | HV breaker maintenance - 41B138-6.82 | 1.33 Days
Continuous |
|
20-May-25 08:00 | 24-May-25 16:00 | CMH | Outage | MHS2 MH69-T22 (MHS-2 North Industrial), MHS-2 MH69-215 (MHS-2 North Industrial) | replacement of transformer bushings | 4.33 Days
Continuous |
|
20-May-25 08:00 | 21-May-25 16:00 | ENMAX | Outage | 40.2TR (SS-40) | tap changer inspection, reversing switch check, oil sampling, oil filtration maintenance | 1.33 Days
Continuous |
|
20-May-25 08:00 | 20-May-25 16:00 | ENMAX | Outage | 162.4TR (SS-162), 162B138-RB92 (SS-162), 162B138-RB94 (SS-162), 162MD138-162.4TR (SS-162) | power factor test - 162PT138-T4 | 8 Hours
Continuous |
|
20-May-25 08:00 | 20-May-25 16:00 | ENMAX | RB | 11.82L (SS-11 - SS-14) | tree trimming | 8 Hours
Continuous |
|
20-May-25 09:00 | 22-May-25 17:00 | BCH | Outage | 2L113 (BCH Cranbrook - BCH Natal), 2D23 (BCH Cranbrook) | replace end-of-life timbers, BC maintenance does not affect the Alberta ATC | 2.33 Days
Continuous |
AB-BC |
20-May-25 09:00 | 30-May-25 17:00 | BCH | Outage | T3 (BCH Natal), 2CB1 (BCH A. A. Lambert) | reconfigure NTL T3 bus connection and cut over to new station equipment | 10.33 Days
Continuous |
AB-BC |
20-May-25 09:00 | 22-May-25 18:00 | ALTALINK | Outage | 799L (235s Entwistle - 443s South Mayerthorpe) | 799L rebuild | 2.38 Days
Continuous |
|
20-May-25 09:00 | 21-May-25 15:00 | ALTALINK | TE | AltaLink Telecom Equipment | update GE D25 RTU configuration | 30 Hours
Daily |
|
20-May-25 09:00 | 20-May-25 17:00 | ALTALINK | TE | 92s Protection & Control (92s Viscount) | remote settings change on 898L B87/21/67N/25SC/L2 & 792L B21/L1 protections | 8 Hours
Daily |
|
20-May-25 09:30 | 20-May-25 19:00 | ALTALINK | TE | 191s Protection & Control (191s N.W. Cardiff) | remote settings change on 792LS B21/25SC/L2 protection | 9.5 Hours
Daily |
|
20-May-25 09:30 | 20-May-25 17:00 | ALTALINK | TE | 37s Protection & Control (37s North Calder) | remote settings change on 898L B87/21/79/L10 protection | 7.5 Hours
Daily |
|
20-May-25 11:00 | 26-May-25 17:00 | ATCO | Outage | 7L199 (347s AML Fox Creek - 741s ATC Fox Creek), 741s 702 (741s ATC Fox Creek) | Fox Creek substation upgrade project |
6.25 Days
Continuous |
|
20-May-25 11:00 | 29-May-25 17:00 | ALTALINK | Outage | 199L (347s AML Fox Creek - 741s ATC Fox Creek) | demo old cables, install and terminate new cables, cut over to new protection | 9.25 Days
Continuous |
|
20-May-25 11:00 | 22-May-25 17:00 | ATCO, ALTALINK | RB | 9L960 (13s Deerland - 825s Whitefish Lake) | climbing inspection | 2.25 Days
Continuous |
|
20-May-25 11:00 | 22-May-25 17:00 | ATCO, ALTALINK | RB | 9L961 (13s Deerland - 825s Whitefish Lake) | climbing inspection | 2.25 Days
Continuous |
|
20-May-25 11:00 | 22-May-25 17:00 | ATCO, ALTALINK | RB | 9L960 (13s Deerland - 825s Whitefish Lake) | climbing inspection | 2.25 Days
Continuous |
|
20-May-25 11:00 | 22-May-25 17:00 | ATCO, ALTALINK | RB | 9L961 (13s Deerland - 825s Whitefish Lake) | climbing inspection | 2.25 Days
Continuous |
|
21-May-25 07:00 | 21-May-25 16:00 | ALTALINK | TE | 510s Protection & Control (510s Sunnybrook) | PRC relay maintenance | 9 Hours
Daily |
|
21-May-25 07:00 | 22-May-25 17:00 | EPCOR | Outage | 330p 1205 (330p Genesee) | 1205 bay yard lighting upgrade (pole #8) | 1.42 Days
Continuous |
|
21-May-25 07:00 | 21-May-25 17:00 | ALTALINK | TE | 447s Protection & Control (447s Enchant) | A87/50/51/T2 remote setting change being performed | 10 Hours
Daily |
|
21-May-25 07:00 | 21-May-25 17:00 | ALTALINK | TE | 454s Protection & Control (454s Buck Lake) | settings change | 10 Hours
Daily |
|
21-May-25 07:00 | 21-May-25 17:00 | ALTALINK | TE | 478s Protection & Control (478s Tucuman) | settings change | 10 Hours
Daily |
|
21-May-25 07:00 | 21-May-25 17:00 | ALTALINK | TE | 508s Protection & Control (508s Lakesend) | settings change | 10 Hours
Daily |
|
21-May-25 07:00 | 21-May-25 17:00 | ALTALINK | TE | 522s Protection & Control (522s Cooking Lake) | settings change | 10 Hours
Daily |
|
21-May-25 07:00 | 21-May-25 17:00 | ALTALINK | TE | 526s Protection & Control (526s Buffalo Creek) | settings change | 10 Hours
Daily |
|
21-May-25 07:00 | 21-May-25 17:00 | ALTALINK | TE | 538s Protection & Control (538s Buford) | settings change | 10 Hours
Daily |
|
21-May-25 07:00 | 21-May-25 17:00 | ALTALINK | TE | 545s Protection & Control (545s Provost) | settings change | 10 Hours
Daily |
|
21-May-25 07:00 | 21-May-25 17:00 | ALTALINK | TE | 498s Protection & Control (498s Tilley) | remote setting change to enable through fault protection on A87/50/51/T2 | 10 Hours
Daily |
|
21-May-25 07:00 | 21-May-25 17:00 | ALTALINK | TE | 523s Protection & Control (523s Bullshead) | remote setting change to enable through fault protection on A87/50/51N/T2 | 10 Hours
Daily |
|
21-May-25 07:00 | 21-May-25 17:00 | ALTALINK | TE | 525s Protection & Control (525s Carseland) | remote setting change to enable through fault protection on A87/50/51/T1 | 10 Hours
Daily |
|
21-May-25 07:00 | 21-May-25 17:00 | ALTALINK | TE | 534s Protection & Control (534s Eckville) | remote setting change to enable through fault protection on A87/50/51/T1 | 10 Hours
Daily |
|
21-May-25 08:00 | 21-May-25 17:00 | ALTALINK | TE | AltaLink Telecom Equipment | replace defective MDA 1 card due to trace error 953L | 9 Hours
Daily |
|
21-May-25 08:00 | 21-May-25 17:00 | ALTALINK | TE | AltaLink Telecom Equipment, AltaLink RTU/SCADA (AltaLink) | replace damaged cables on radio and upgrade software of the radio hop | 9 Hours
Daily |
|
21-May-25 08:00 | 21-May-25 17:00 | ALTALINK | Outage | 65s T2 (65s High River) | first trip and major maintenance on 65s2213, replace counter, 65s14X first trip and minor maintenance, replace cooper cutouts on 65s2 | 9 Hours
Daily |
|
21-May-25 08:00 | 22-May-25 17:00 | CENOVUS | Outage | 539s PCB-9203 (539s Sunday Creek) | PRC maintenance | 1.38 Days
Continuous |
|
21-May-25 08:00 | 21-May-25 16:00 | ENMAX | TE | Protection & Control (SS-32) | power factor test - 32PT138-Z31 | 8 Hours
Continuous |
|
21-May-25 08:00 | 21-May-25 16:00 | ENMAX | RB | 16.63L (SS-16 - SS-36) | tree trimming | 8 Hours
Continuous |
|
21-May-25 08:00 | 21-May-25 17:00 | ALTALINK | TE | 118s RTU/SCADA (118s Canmore) | RTU outage for the fast trip setting change implementation/point clean up | 9 Hours
Daily |
|
21-May-25 09:00 | 29-May-25 20:00 | SUNCOR | Outage | 29EDD-1 T2 (29EDD-1 Millennium) | OLTC maintenance and testing, 29EDD-1 T2 72LV arrester replacement | 8.46 Days
Continuous |
|
21-May-25 09:00 | 21-May-25 12:30 | ATCO, CNRL | Outage | 847s 902 (847s Muskeg River) | PRC-005 - trip coil testing | 3.5 Hours
Continuous |
|
21-May-25 09:00 | 21-May-25 12:30 | ATCO, CNRL | TE | 847s Protection & Control (847s Muskeg River) | PRC-005 - trip coil testing | 3.5 Hours
Continuous |
|
21-May-25 09:00 | 23-May-25 14:00 | ENMAX | Outage | 31.1TR (SS-31) | grounding improvements, install new surge arrestor insulator supports | 2.21 Days
Continuous |
|
21-May-25 09:30 | 21-May-25 16:00 | ATCO | TE | ATCO Telecom Equipment | cutting over traffic from EOL MDR radios to new IRU radios between Chard Substation and Chard Tower | 6.5 Hours
Continuous |
|
21-May-25 09:30 | 21-May-25 12:00 | ALTALINK | TE | 746s RTU/SCADA (746s Sherwood Park) | updating the supervisory circuit to a VPRN circuit | 2.5 Hours
Daily |
|
21-May-25 10:00 | 21-May-25 12:00 | SUNCOR | TE | 29EDD-65 Protection & Control (29EDD-65) | replacing module due to 29-952-4812 50BF card failure UR-8LH | 2 Hours
Continuous |
|
21-May-25 10:00 | 21-May-25 14:00 | ATCO | TE | ATCO Telecom Equipment, 741s RTU/SCADA (741s Fox Creek) | Fox Creek_S-Telecom- adding in a second switch for more comm ports | 4 Hours
Continuous |
|
21-May-25 11:00 | 23-May-25 16:00 | ATCO | Outage | 789s 706C (789s Keg River) | breaker SF6 HPL complete testing | 2.21 Days
Continuous |
|
21-May-25 13:00 | 21-May-25 17:00 | ATCO, CNRL | Outage | 847s 903 (847s Muskeg River) | PRC-005 - trip coil testing | 4 Hours
Continuous |
|
21-May-25 13:00 | 21-May-25 17:00 | ATCO, CNRL | TE | 847s Protection & Control (847s Muskeg River) | PRC-005 - trip coil testing | 4 Hours
Continuous |
|
22-May-25 07:00 | 23-May-25 17:00 | EPCOR | RB | 746AL (524s Owens Corning - 746L tap) | washing program | 1.42 Days
Continuous |
|
22-May-25 07:00 | 23-May-25 17:00 | ALTALINK | RB | 731L (420s Broadmoor - 746L tap), 746L (731L tap - 746BL tap), 731L (38s East Edmonton - 746L tap) | washing program | 1.42 Days
Daily |
|
22-May-25 07:00 | 22-May-25 19:00 | ALTALINK | Outage | 736L (38s East Edmonton - 293s Bernese), 293s T1 (293s Bernese), 293s T2 (293s Bernese), 38s 736E (38s East Edmonton), 293s 152 (293s Bernese), 293s 252 (293s Bernese) | urgent outage to replace leaking CT | 12 Hours
Daily |
|
22-May-25 07:00 | 23-May-25 17:00 | EPCOR | Outage | 72CK13 (987s Clover Bar - Kennedale), 987s CK726 (987s Clover Bar), K721 (Kennedale), KDS1 (Kennedale) | CK13: metering upgrade cutovers | 1.42 Days
Continuous |
|
22-May-25 07:00 | 22-May-25 17:00 | ALTALINK | TE | 574s Protection & Control (574s Nilrem) | settings change | 10 Hours
Daily |
|
22-May-25 07:00 | 22-May-25 17:00 | ALTALINK | TE | 595s Protection & Control (595s Spruce Grove) | settings change | 10 Hours
Daily |
|
22-May-25 07:00 | 22-May-25 17:00 | ALTALINK | TE | 602s Protection & Control (602s Cold Creek) | settings change | 10 Hours
Daily |
|
22-May-25 07:00 | 22-May-25 17:00 | ALTALINK | TE | 635s Protection & Control (635s Rose Valley) | settings change | 10 Hours
Daily |
|
22-May-25 07:00 | 22-May-25 17:00 | ALTALINK | TE | 651s Protection & Control (651s Kirby) | settings change | 10 Hours
Daily |
|
22-May-25 07:00 | 22-May-25 17:00 | ALTALINK | TE | 818s Protection & Control (818s Winefred) | settings change | 10 Hours
Daily |
|
22-May-25 07:00 | 22-May-25 17:00 | ALTALINK | TE | 899s Protection & Control (899s Edgerton) | settings change | 10 Hours
Daily |
|
22-May-25 07:00 | 22-May-25 17:00 | ALTALINK | TE | 993s Protection & Control (993s Abee) | settings change | 10 Hours
Daily |
|
22-May-25 07:00 | 22-May-25 17:00 | ALTALINK | TE | 1012s Protection & Control (1012s Deer Hill) | settings change | 10 Hours
Daily |
|
22-May-25 07:00 | 22-May-25 17:00 | ALTALINK | TE | 678s Protection & Control (678s Okotoks) | remote setting change to enable through fault protection on A87/50/51/T1 & B87/50/51/T3. momentary alarm as settings are changed on relay. | 10 Hours
Daily |
|
22-May-25 07:00 | 22-May-25 17:00 | ALTALINK | TE | 580s Protection & Control (580s Sylvan Lake) | remote setting change to enable through fault protection on A87/50/51/51N/T1 & A87/50/51/51N/T2. momentary alarm as settings are changed on relay. | 10 Hours
Daily |
|
22-May-25 07:00 | 25-May-25 19:00 | ATCO | RB | 9L20 (755s Cordel - 766s Nevis) | stringing activities on CETO project adjacent to 9L20 | 3.5 Days
Daily |
|
22-May-25 07:30 | 22-May-25 17:30 | ALTALINK | TE | 899s RTU/SCADA (899s Edgerton) | update configuration to implement controls | 10 Hours
Daily |
|
22-May-25 08:00 | 22-May-25 16:00 | ENMAX | Outage | 26B138-26BT3 (SS-26) | high voltage breaker maintenance - 26B138-26BT3 | 8 Hours
Continuous |
|
22-May-25 08:00 | 22-May-25 17:30 | ALTALINK | Outage | 331s 422 (331s Ponoka), 422L (288s Wolf Creek - 331s Ponoka) | test "B" phase CT's, update firmware on "B" prot and upgrade DSP card from 8F to 8L | 9.5 Hours
Daily |
|
22-May-25 08:00 | 22-May-25 16:00 | ENMAX | Outage | 38.3TR (SS-38) | investigate TR secondary cables in secondary cabinet and cell. | 8 Hours
Continuous |
|
22-May-25 08:00 | 22-May-25 17:00 | ALTALINK | TE | 115s RTU/SCADA (115s Mount Allan) | RTU outage for the FORTIS fast trip setting change implementation and point on the SCN sign off. | 9 Hours
Daily |
|
22-May-25 08:00 | 22-May-25 16:00 | ENMAX | RB | 21.61L (SS-21 - SS-34) | tree trimming | 8 Hours
Continuous |
|
22-May-25 08:30 | 22-May-25 17:00 | ALTALINK | TE | 288s Protection & Control (288s Wolf Creek) | update F/W and replace DSP card from 8F to 8L | 8.5 Hours
Daily |
|
22-May-25 09:00 | 22-May-25 12:30 | ATCO, CNRL | Outage | 847s 904 (847s Muskeg River) | PRC-005 - trip coil testing | 3.5 Hours
Continuous |
|
22-May-25 09:00 | 22-May-25 12:30 | ATCO, CNRL | TE | 847s Protection & Control (847s Muskeg River) | PRC-005 - trip coil testing. | 3.5 Hours
Continuous |
|
22-May-25 11:00 | 22-May-25 16:30 | ALTALINK | Outage | 899s T3 (899s Edgerton) | implement controls for 899s24 and alarm separation for both 25 kV Breakers 899s373W and 899s95E | 5.5 Hours
Daily |
|
22-May-25 13:00 | 22-May-25 17:00 | ATCO, CNRL | Outage | 847s 901 (847s Muskeg River) | PRC-005 - trip coil testing | 4 Hours
Continuous |
|
22-May-25 13:00 | 22-May-25 17:00 | ATCO, CNRL | TE | 847s Protection & Control (847s Muskeg River) | PRC-005 - trip coil testing. | 4 Hours
Continuous |
|
23-May-25 07:00 | 24-May-25 17:00 | EPCOR | Outage | 330p 1208 (330p Genesee) | Genesee: 1208 bay yard lighting upgrade (Pole #9) | 1.42 Days
Continuous |
|
23-May-25 08:00 | 24-May-25 16:00 | ENMAX | Outage | 33.84L (SS-33 - SS-43), 33B138-33.84 (SS-33), 43B138-33.84 (SS-43) | sheath & oil testing | 1.33 Days
Continuous |
|
23-May-25 08:00 | 23-May-25 16:00 | ENMAX | RB | 16.60L (SS-16 - SS-34) | tree trimming | 8 Hours
Continuous |
|
23-May-25 10:00 | 23-May-25 17:00 | ATCO | RB | 7L90 (813s Little Smoky - 7LA90 tap), 7L90 (741s ATC Fox Creek - 7LA90 tap) | permanently disconnect 700PT2 from 144kV bus | 7 Hours
Continuous |
|
23-May-25 11:00 | 23-May-25 17:00 | ALTALINK | Outage | 33s 138kV Bus (33s Spray), 113L (20s Ghost - 33s Spray), 76L (33s Spray - 115s Mount Allan), 84L (33s Spray - 35s Rundle Plant), 33s 113 (33s Spray), 33s 76 (33s Spray), 33s 84 (33s Spray), 20s 113 (20s Ghost), 115s 76LX (115s Mount Allan), 35s 84 (35s Rundle Plant) | 33s hot bus LA's. | 6 Hours
Daily |
|
23-May-25 14:00 | 02-Jun-25 10:00 | ENMAX, ALTALINK | Outage | 1109L (SS-25 - SS-65), 25B240-D136 (SS-25), 25B240-D139 (SS-25), 25B240-D133 (SS-25), 25B240-D141 (SS-25), 25B240-D142 (SS-25), 25MD240-1109 (SS-25) | cable testing, close cable open points on 1109L and salvage temp O/H 1109L. expanding zone to include 1109L C25s bus. Enmax grounding required, and Enmax to close 1109L risers removed from bus to potthead. soak test June 2nd 10:00 | 9.83 Days
Continuous |
|
23-May-25 14:00 | 03-Jun-25 12:00 | ENMAX, ALTALINK | IO | 240kV West Bus (SS-25), 1109L (SS-25 - SS-65) | Altalink outage. Cable testing, close cable open points on 1109L and salvage Temp O/H 1109L. Expanding zone to include 1109L C25s Bus. Enmax grounding required, and Enmax to close 1109L risers removed from bus to potthead. Soak test June 2nd 10:00 | 10.92 Days
Continuous |
This document and the information contained herein are based upon information and data which by their nature contain a degree of uncertainty and are subject to change. In addition, this document may contain information and data from public sources and/or third parties, which have been assumed to be accurate and complete and have not been verified. Accordingly, the Independent System Operator, operating as the Alberta Electric System Operator (the "AESO") makes no warranty, representation or guarantee, express or implied, with respect to this document or the information contained herein, including, but not limited to, any warranty, representation or guarantee of accuracy, completeness, timeliness, reliability, availability, absence of computer virus, non- infringement, merchantability or suitability for any purpose. Under no circumstances will the AESO, its members, officers, employees, contractors or agents, or any of their respective affiliates, be liable for any errors or omissions in, or any losses, damages or claims whatsoever, whether in contract, tort or otherwise, arising from use of or reliance upon, this document or any information contained herein. © 2009 Alberta Electric System Operator. All rights reserved |