Alberta Electric System Operator | |
System Co-ordination Plan | |
2025-02-27 to 2025-03-07 | |
Approved Outages |
Previous Version | |
Download CSV |
From | To | Owner | Type | Element | Scheduled Activity | Date/Time Comments | Interconnection |
---|---|---|---|---|---|---|---|
05-Oct-18 08:00 | 30-Jun-26 16:00 | EPCOR | IO | C2 (Rossdale) | forced outage | 2,825.33 Days
Continuous |
|
24-Oct-18 01:13 | 30-Jun-26 16:00 | EPCOR | IO | C1 (Rossdale) | forced outage | 2,806.62 Days
Continuous |
|
27-Nov-23 08:00 | 20-Jun-25 16:00 | ENMAX | Outage | 32.2TR (SS-32) | 32 sub 32.2TR 8 kV bus switchgear demolition | 571.29 Days
Continuous |
|
26-Jul-24 10:00 | 31-Mar-25 16:00 | ATCO | Outage | 826s 504R (826s Marguerite Lake) | emergency removal to replace failed 502R @834S | 248.25 Days
Continuous |
|
23-Aug-24 13:45 | 30-Apr-25 14:29 | ALTALINK | Outage | 157s C1 (157s Lac La Biche) | forced outage | 250.03 Days
Continuous |
|
23-Sep-24 10:00 | 15-May-25 12:00 | ATCO | TE | 741s RTU/SCADA (741s Fox Creek) | RTU configuration on new and old RTU's onsite | 234.08 Days
Continuous |
|
05-Oct-24 00:00 | 30-Apr-25 17:00 | BHE Canada | Outage | 120s C1 (120s Picture Butte) | forced outage | 207.71 Days
Continuous |
|
21-Oct-24 12:00 | 12-May-25 17:30 | ATCO | TE | 741s Protection & Control (741s Fox Creek) | block 144kv and 25 kv bus protection and breaker fail protection for the duration of 741s project | 203.23 Days
Continuous |
|
26-Dec-24 17:07 | 31-Mar-25 18:00 | ALTALINK | Outage | 256s C1 (256s Harmattan) | forced outage | 95 Days
Continuous |
|
03-Jan-25 07:00 | 07-Mar-25 17:00 | EPCOR | TE | 805s Protection & Control (805s Jasper), 805s RTU/SCADA (805s Jasper) | protection blocking for P&C maintenance at Jasper | 63.42 Days
Continuous |
|
06-Jan-25 09:30 | 21-Jun-25 18:00 | ALTALINK | Outage | 150L (42s Sarcee - 150AL tap), 42s 150W (42s Sarcee) | arctic arrow will require a GOI on 150L to rebuild the section of line from structure 47-198. | 166.31 Days
Continuous |
|
13-Jan-25 07:00 | 03-Mar-25 17:00 | EPCOR | Outage | 987s T2 (987s Clover Bar), 987s C2406 (987s Clover Bar), 987s C2410 (987s Clover Bar), 987s C2409 (987s Clover Bar), 987s CC721 (987s Clover Bar), 987s CDS45 (987s Cloverbar), 987s CDS31 (987s Clover Bar) | Cloverbar TX2 and 1191L bay outage | 49.42 Days
Continuous |
|
13-Jan-25 07:00 | 04-Apr-25 17:00 | EPCOR | TE | 330p Protection & Control (330p Genesee), 330p RTU/SCADA (330p Genesee) | Genessee - 138/500 kV protection blocking for relay maintenance and configuration changes | 81.38 Days
Continuous |
|
03-Feb-25 07:00 | 04-Apr-25 17:30 | ATCO | TE | 769s Protection & Control (769s Stettler), 769s RTU/SCADA (769s Stettler) | new RTU installation at 769S | 60.4 Days
Continuous |
|
03-Feb-25 09:00 | 28-Mar-25 17:00 | ATCO | TE | 730s RTU/SCADA (730s Rycroft) | change RTU configuration | 53.29 Days
Continuous |
|
10-Feb-25 00:00 | 30-Jun-25 23:59 | ATCO, ALTALINK | IO | 840s McNeill Station, 830L (562s Cypress - 840s McNeill Station), 840s 701T (840s McNeill Station), 840s 901T (840s McNeill Station) | available for emergency use only | 140.96 Days
Continuous |
AB-SK |
10-Feb-25 09:00 | 14-Mar-25 17:00 | BCH | Outage | T3 (BCH Natal) | station rebuild | 32.29 Days
Continuous |
AB-BC |
10-Feb-25 09:00 | 28-Feb-25 17:00 | BCH | TE | 2L113 (BCH Cranbrook - BCH Natal), T3 (BCH Natal) | protection work | 18.33 Days
Continuous |
AB-BC |
10-Feb-25 09:00 | 28-Feb-25 17:00 | BCH | Outage | 2CB1 (BCH Natal) | NTL station rebuild | 18.33 Days
Continuous |
AB-BC |
11-Feb-25 10:00 | 28-Mar-25 16:00 | ATCO | TE | 940s Protection & Control (940s Beartrap) | relay testing | 45.21 Days
Continuous |
|
17-Feb-25 07:00 | 06-Mar-25 17:00 | ALTALINK | TE | 498s RTU/SCADA (498s Tilley) | update RTU for line protection upgrades for alderson project | 17.42 Days
Daily |
|
17-Feb-25 07:00 | 28-Feb-25 17:00 | EPCOR | TE | Protection & Control (EPCOR Hardisty) | hardisty: 72kV Protection blocking for relay maintenance | 11.42 Days
Continuous |
|
17-Feb-25 07:00 | 06-Mar-25 17:00 | ALTALINK | TE | 28s RTU/SCADA (28s West Brooks) | update RTU for Line protection upgrades | 17.42 Days
Daily |
|
17-Feb-25 07:00 | 06-Mar-25 17:00 | ALTALINK | TE | 244s RTU/SCADA (244s Bowmanton) | update RTU for line protection upgrades | 17.42 Days
Daily |
|
17-Feb-25 07:00 | 06-Mar-25 17:00 | ALTALINK | TE | 895s RTU/SCADA (895s Suffield) | update RTU for line protection upgrades for alderson project | 17.42 Days
Daily |
|
18-Feb-25 07:00 | 28-Feb-25 17:30 | ATCO | TE | 769s Protection & Control (769s Stettler), 769s RTU/SCADA (769s Stettler) | RTU, transformer tap position indication and control, metering | 10.44 Days
Continuous |
|
18-Feb-25 07:00 | 07-Mar-25 17:00 | EPCOR | Outage | 72RG7 (Garneau - Rossdale), T1 (Garneau), G722 (Garneau), G723 (Garneau), G721 (Garneau), GDS4 (Garneau), GAB1 (Garneau) | TX1/RG7 zone- 72kV switchgear SF6 overhaul with GE | 17.42 Days
Continuous |
|
18-Feb-25 08:00 | 03-Mar-25 12:00 | ATCO | Outage | 9L10 (876s Brintnell - 939s Livock), 939s 911 (939s Livock), 939s 910 (939s Livock), 939s 903T (939s Livock) | line to ground mitigation | 13.17 Days
Continuous |
|
18-Feb-25 10:00 | 03-Mar-25 11:00 | ATCO | Outage | 741s 705C (741s Fox Creek) | Fox Creek substation upgrade project, demo old cabling, install new cabling and cut over to new protection | 13.04 Days
Continuous |
|
20-Feb-25 10:00 | 28-Feb-25 17:00 | ATCO | Outage | 6L44 (769s Stettler - 778s Big Valley), 6L02 (769s Stettler - 873s Marion Lake), 769s 703T (769s Stettler), 778s 601T (778s Big Valley), 769s 703 (769s Stettler), 769s 603 (769s Stettler), 769s 602 (769s Stettler), 769s 601 (769s Stettler), 778s 601TD (778s Big Valley), 769s 503TD1 (769s Stettler) | install new 6L02/6L44 panels, cutover 6L44 A&B protections | 8.29 Days
Continuous |
|
21-Feb-25 09:00 | 27-Feb-25 17:00 | ATCO | RB | 7L15 (841s Long Lake - 856s Kinosis) | 13 structures to be replaced plus one add-in structure |
6.33 Days
Continuous |
|
21-Feb-25 14:31 | 13-Mar-25 17:00 | ATCO | TE | 730s Protection & Control (730s Rycroft) | bus protection relay blocking for mobile installation | 20.06 Days
Continuous |
|
24-Feb-25 07:00 | 13-Mar-25 17:00 | ATCO | Outage | 730s 701T (730s Rycroft) | install new relays | 17.38 Days
Continuous |
|
24-Feb-25 07:00 | 28-Feb-25 17:00 | ATCO | TE | 2075s Protection & Control (2075s Newell) | Isolate and replace SEL AC bus bar protection 2 differential relay | 4.42 Days
Continuous |
|
24-Feb-25 07:00 | 06-Mar-25 17:00 | ALTALINK | TE | 895s Protection & Control (895s Suffield) | remove 96/752 (895s100) relay from service to test trip associated breakers | 10.42 Days
Daily |
|
24-Feb-25 07:00 | 28-Feb-25 17:00 | EPCOR | Outage | T1 (EP Riverview), RW2401 (EP Riverview), RW2405 (EP Riverview), RWAB1 (EP Riverview) | riverview: TX1 zone relay maintenance and temp gauge calibration | 4.42 Days
Continuous |
|
24-Feb-25 07:00 | 03-Mar-25 19:00 | ATCO | RB | 9L20 (755s Cordel - 766s Nevis) | facilitate various construction activities on CETO | 7.5 Days
Continuous |
|
24-Feb-25 07:00 | 21-Mar-25 17:00 | EPCOR | TE | 72RV6 (EP 511s Victoria - Rossdale) | RV6 - protection blocking, MPLS cutovers | 25.38 Days
Continuous |
|
24-Feb-25 07:00 | 27-Feb-25 17:00 | ALTALINK | TE | 945s RTU/SCADA (945s Sunshine Village) | RTU configuration for subnet and IP address update to all IEDs of this station | 3.42 Days
Daily |
|
24-Feb-25 07:00 | 27-Feb-25 17:00 | ALTALINK | TE | 945s Protection & Control (945s Sunshine Village) | protection outage to update IP address for sublan upgrade project. | 3.42 Days
Daily |
|
24-Feb-25 07:00 | 04-Apr-25 17:00 | EPCOR | TE | Protection & Control (EPCOR Riverview) | protection blocking, P&C maintenance. | 39.38 Days
Continuous |
|
24-Feb-25 07:15 | 28-Feb-25 17:45 | ALTALINK | Outage | 234L (310p Sundance - 505L tap), 234L1 (234L tap), 505L (234L tap - 505L tap), 505L1 (505L-521L tap), 310p 693 (310p Sundance) | component replacement 234L str 13-99 | 4.44 Days
Continuous |
|
24-Feb-25 08:00 | 02-Mar-25 17:00 | ALTALINK | RB | 610L (83s Taber - 336s Fincastle) | setting structures adjacent to existing 610L (str 1-102) (proximity) for VATD project | 6.38 Days
Daily |
|
24-Feb-25 08:00 | 28-Feb-25 16:00 | ENMAX | TE | 23.80L (74s Janet - SS-23) | relay testing | 4.33 Days
Continuous |
|
24-Feb-25 08:00 | 27-Feb-25 20:00 | SUNCOR | TE | 29EDD-34 29PT-340 (29EDD-34), 29EDD-34 29PT-341 (29EDD-34) | complete annual CIP Relay password changes & power cycle | 3.5 Days
Continuous |
|
24-Feb-25 08:00 | 15-Mar-25 16:00 | ALTALINK, EPCOR | RB | 1203L (320p Keephills - 510s Sunnybrook) | expose tower foundations to complete repair to corrosion damage by installation of stiffeners | 19.29 Days
Continuous |
|
24-Feb-25 09:00 | 28-Feb-25 17:00 | BCH | Outage | 5L51 (BPA Custer - BCH Ingledow) | ING 5CB3 Insp and doble | 4.33 Days
Continuous |
AB-BC |
24-Feb-25 09:00 | 28-Feb-25 17:00 | ATCO | RB | 890s 701 (890s Melito) | voltage reg bank addition - to perform hot line work just downstream of the substation 890S Melito | 4.33 Days
Continuous |
|
24-Feb-25 09:30 | 28-Feb-25 17:30 | ATCO | TE | 946s Protection & Control (946s Oakland) | relay testing | 4.33 Days
Continuous |
|
24-Feb-25 09:30 | 28-Feb-25 17:30 | ATCO | TE | 757s Protection & Control (757s Battle River) | relay testing- isolate relays as required on site. | 4.33 Days
Continuous |
|
24-Feb-25 10:00 | 27-Feb-25 16:00 | ATCO | TE | 700s Protection & Control (700s Bonnyville) | relay testing | 3.25 Days
Continuous |
|
24-Feb-25 10:00 | 27-Feb-25 17:30 | ATCO | TE | 810s Protection & Control (810s Dome Cutbank) | relay testing | 3.31 Days
Continuous |
|
24-Feb-25 10:00 | 28-Feb-25 16:30 | ATCO, ALTALINK | RB | 7L129 (526s Buffalo Creek - 7LA129 tap), 7L129 (710s Vermilion - 7LA129 tap) | replace structures and cross arms on 7L129 , live line work | 4.27 Days
Continuous |
|
24-Feb-25 10:00 | 28-Feb-25 16:30 | ATCO, ALTALINK | RB | 7L129 (526s Buffalo Creek - 7LA129 tap) | replace structures and cross arms on 7L129 , live line work | 4.27 Days
Daily |
|
24-Feb-25 10:00 | 27-Feb-25 17:00 | ALTALINK | TE | 77s Protection & Control (77s Sagitawah) | standard relay maintenance | 3.29 Days
Daily |
|
24-Feb-25 10:00 | 27-Feb-25 17:00 | ALTALINK | TE | 89s Protection & Control (89s Ellerslie) | relay maintenance | 3.29 Days
Daily |
|
24-Feb-25 12:00 | 03-Mar-25 12:00 | ATCO | TE | 800s Protection & Control (800s Friedenstal), 800s RTU/SCADA (800s Friedenstal) | change settings on the 25 kV bus relay [51-51N-81], remove 25 kV bus relay PT inputs, tie in 503 backup protection, re-Wire 500PT1 (new cable), change settings on 712BF & Add Trip to 503 | 7 Days
Continuous |
|
25-Feb-25 07:00 | 28-Feb-25 17:30 | ALTALINK | Outage | 430s 652 (430s Ursus) | urgent repair - replacement of leaking CT(A-phase) | 3.44 Days
Continuous |
|
25-Feb-25 08:30 | 12-Mar-25 17:30 | ATCO | TE | 730s Protection & Control (730s Rycroft) | 50BF/701TCS requires blocking for settings update and testing associated with the 701T transformer protection upgrade | 15.33 Days
Continuous |
|
25-Feb-25 08:30 | 12-Mar-25 17:30 | ATCO | TE | 730s Protection & Control (730s Rycroft) | replace 701T with new protection panel 7T1. | 15.33 Days
Continuous |
|
26-Feb-25 06:00 | 27-Feb-25 18:00 | ALTALINK | Outage | 895s T3 (895s Suffield), 895s 952 (895s Suffield) | test new 'B' bus protection and 752 BF relays | 1.5 Days
Continuous |
|
26-Feb-25 07:15 | 03-Mar-25 17:45 | ALTALINK | Outage | 890L (58s Edson - 207s Pinedale), 58s 890 (58s Edson), 207s 890 (207s Pinedale) | system upgrade on structures | 5.44 Days
Continuous |
|
26-Feb-25 08:00 | 17-Mar-25 16:00 | Syncrude | Outage | 1735 (Syncrude Mildred Lake), Mildred T17 (Syncrude Mildred Lake) | replace leaking pothead | 19.29 Days
Continuous |
|
26-Feb-25 08:00 | 27-Feb-25 16:00 | Syncrude | Outage | 1435 (Syncrude Mildred Lake), Mildred T14 (Syncrude Mildred Lake) | urgent maintenance | 1.33 Days
Continuous |
|
26-Feb-25 09:00 | 27-Feb-25 16:00 | ATCO | TE | 729s Protection & Control (729s Otauwau) | PRC005 relay testing | 31 Hours
Continuous |
|
26-Feb-25 09:00 | 08-Mar-25 17:00 | ATCO | RB | 7L65 (709s Vegreville - 7LA65 tap), 7L65 (710s Vermilion - 7LA65 tap) | stinging parallel along existing 7L65 for the new 7L65 phase three project | 10.33 Days
Continuous |
|
26-Feb-25 10:00 | 27-Feb-25 17:00 | ATCO, SUNCOR | Outage | 9L162 (29EDD-94 Voyageur - 951s Thickwood Hills), 29EDD-94 29PS-643 (29EDD-94 Voyageur) | weld new guy wire vangs and re-anchor structure 9L162/44 | 31 Hours
Continuous |
|
26-Feb-25 10:00 | 27-Feb-25 17:00 | ATCO | TE | 970s Protection & Control (970s Bourque), 970s RTU/SCADA (970s Bourque) | RTU configuration update to enable SOC/HMI alarms for 7L574 in alternate settings | 31 Hours
Continuous |
|
26-Feb-25 10:00 | 27-Feb-25 16:00 | ATCO | TE | 743s Protection & Control (743s Sarah Lake) | relay testing | 30 Hours
Continuous |
|
26-Feb-25 11:00 | 28-Feb-25 16:00 | ATCO | TE | 907s RTU/SCADA (907s Waddell) | feeder settings updates due to large D project |
2.21 Days
Continuous |
|
27-Feb-25 07:00 | 27-Feb-25 17:00 | EPCOR | TE | 987s RTU/SCADA (987s Clover Bar) | RTU communications outage for firmware upgrades | 10 Hours
Continuous |
|
27-Feb-25 07:30 | 27-Feb-25 18:00 | ATCO | TE | 2075s RTU/SCADA (2075s Newell), 2029s RTU/SCADA (2029s Heathfield) | Newell/Heathfield - patching | 10.5 Hours
Continuous |
|
27-Feb-25 07:30 | 27-Feb-25 18:00 | ATCO | TE | 939s RTU/SCADA (939s Livock), 951s RTU/SCADA (951s Thickwood Hills) | Livock/Thickwood - patching | 10.5 Hours
Continuous |
|
27-Feb-25 07:30 | 27-Feb-25 18:00 | ATCO, CNRL | TE | 838s RTU/SCADA (838s Horizon Mining) | Horizon - patching | 10.5 Hours
Continuous |
|
27-Feb-25 08:00 | 27-Feb-25 18:00 | ATCO | TE | ATCO Telecom Equipment, APS# 158 Ksituan 754S Voltage Stability Mitigation | Clairmont Lake telecom |
10 Hours
Continuous |
|
27-Feb-25 08:00 | 28-Feb-25 17:00 | ALTALINK | Outage | 58s 890 (58s Edson) | CT ratio change and relay settings change | 1.38 Days
Continuous |
|
27-Feb-25 08:00 | 27-Feb-25 17:00 | ALTALINK | TE | 212s Protection & Control (212s Lacombe) | PRC protection maintenance | 9 Hours
Daily |
|
27-Feb-25 08:00 | 27-Feb-25 17:00 | ALTALINK | TE | 199s RTU/SCADA (199s East Airdrie) | troubleshooting remote connection to 688L 'A' protection relay | 9 Hours
Daily |
|
27-Feb-25 08:00 | 27-Feb-25 17:00 | ALTALINK | TE | 199s Protection & Control (199s East Airdrie) | removing A21/79/L2 from service to troubleshoot issue with disturbance analysis being able to remote into the relay | 9 Hours
Daily |
|
27-Feb-25 09:30 | 27-Feb-25 17:30 | ATCO | Outage | 946s 908 (946s Oakland) | trip coil testing | 8 Hours
Continuous |
|
27-Feb-25 11:30 | 27-Feb-25 15:30 | ALTALINK | Outage | 700L (746s Sherwood Park - 746L tap), 746s 700N (746s Sherwood Park) | cutover CT connection to new B87/138B | 4 Hours
Daily |
|
27-Feb-25 12:00 | 27-Feb-25 16:00 | ATCO | Outage | 7L146 (700s Bonnyville - 970s Bourque), 700s 704 (700s Bonnyville), 970s 7L146D2 (970s Bourque) | trip coil testing | 4 Hours
Continuous |
|
27-Feb-25 12:00 | 27-Feb-25 13:00 | CENOVUS | TE | 1200s RTU/SCADA (1200s Foster Creek Station) | software upgrade | 60 Mins
Continuous |
|
27-Feb-25 17:00 | 11-Mar-25 17:00 | ATCO | Outage | 6L02 (769s Stettler - 873s Marion Lake), 769s 601 (769s Stettler) | commission 6L02 relays, end-to-end testing | 11.96 Days
Continuous |
|
28-Feb-25 07:00 | 28-Feb-25 17:00 | EPCOR | TE | RTU/SCADA (Garneau) | RTU communications outage for firmware upgrades | 10 Hours
Continuous |
|
28-Feb-25 09:00 | 28-Mar-25 16:00 | ALTALINK | TE | 344s Protection & Control (344s Warner) | protection changes to prevent future mis-operation, outages on A87/50/51/51NN/T1, B87/50/51/51NN/T1 | 28.25 Days
Daily |
|
28-Feb-25 10:00 | 01-Mar-25 17:00 | ATCO, SUNCOR | Outage | 9L193 (29EDD-94 Voyageur - 951s Thickwood Hills) | weld new guy wire vangs and re-anchor structure 9L193/44 | 31 Hours
Continuous |
|
28-Feb-25 19:00 | 07-Mar-25 19:00 | ALTALINK | Outage | 320p 2089 (320p Keephills) | repair work | 7 Days
Continuous |
|
02-Mar-25 08:00 | 06-Mar-25 14:00 | ENMAX | Outage | 32.83L (SS-32 - SS-40), 40.1TR (SS-40), 32B138-32.83 (SS-32), 40B138-32.83 (SS-40), 40MD138-40.1TR (SS-40) | grounding improvements | 4.25 Days
Continuous |
|
03-Mar-25 07:00 | 03-Mar-25 17:30 | ALTALINK | Outage | 666L (28s West Brooks - 498s Tilley), 28s 60 (28s West Brooks), 28s 81 (28s West Brooks), 28s 666 (28s West Brooks), 498s 666 (498s Tilley) | cutover and test LTO circuits at 28s and 498s install maintenance switch | 10.5 Hours
Daily |
|
03-Mar-25 07:00 | 07-Mar-25 17:00 | EPCOR | Outage | 816s P2401 (816s Petrolia) | gauge/valve repair | 4.42 Days
Continuous |
|
03-Mar-25 07:00 | 05-Mar-25 17:00 | EPCOR | Outage | T3 (Meadowlark), M723 (Meadowlark), M724 (Meadowlark), MAB3 (Meadowlark) | meadowlark: TX3 zone relay maintenance and apparatus counter repair | 2.42 Days
Continuous |
|
03-Mar-25 07:00 | 07-Mar-25 17:00 | EPCOR | Outage | 1098L (EP 805s Jasper - Poundmaker), EP 805s J2401 (EP 805s Jasper), EP 805s J2407 (EP 805s Jasper), PM2401 (Poundmaker), PM2402 (Poundmaker) | relay maintenance | 4.42 Days
Continuous |
|
03-Mar-25 07:00 | 29-Mar-25 17:00 | ALTALINK, EPCOR | RB | 1044L (EP 805s Jasper - 816s Petrolia) | detailed aerial patrol, shield wire bonding repair and contractor working in vicinity | 26.38 Days
Continuous |
|
03-Mar-25 07:00 | 29-Mar-25 17:00 | ALTALINK, EPCOR | RB | 1045L (EP 805s Jasper - 1045AL tap) | detailed aerial patrol, shield wire bonding repair and contractor working in vicinity | 26.38 Days
Continuous |
|
03-Mar-25 07:00 | 14-Mar-25 17:00 | ALTALINK, EPCOR | RB | 1045AL (320p Keephills - 1045L tap), 1045L (310p Sundance - 1045AL tap), 1045L (EP 805s Jasper - 1045AL tap) | perform detailed aerial patrol and shield wire bonding repair | 11.38 Days
Continuous |
|
03-Mar-25 07:00 | 06-Mar-25 17:30 | ALTALINK | RB | 508L (67s Stirling - 344s Warner) | replacing arms and insulation (str 289,290) - live line work | 3.44 Days
Daily |
|
03-Mar-25 07:30 | 03-Mar-25 17:30 | ALTALINK | RB | 700L (422s Westwood - 746L tap), 700L (746s Sherwood Park - 746L tap) | prep work for upcoming GOI to rebuild structure 22-37 | 10 Hours
Daily |
|
03-Mar-25 08:00 | 09-Mar-25 17:00 | ALTALINK | RB | 610L (83s Taber - 336s Fincastle) | setting structures adjacent to existing 610L (str 1-102) | 6.33 Days
Daily |
|
03-Mar-25 08:00 | 21-Mar-25 17:00 | ALTALINK | TE | 746s RTU/SCADA (746s Sherwood Park) | configuration updates to implement protections and cutover controls | 18.33 Days
Daily |
|
03-Mar-25 08:00 | 09-Mar-25 16:00 | ENMAX | Outage | 162.2TR (SS-162), 138kV South Bus (SS-162), 240kV South Bus (SS-162) | HV SW Maint. 162SW88, 162SW89, 162SW105, 162SW136, 162SW146, MD138-162.2TR, MD240-162.2TR. Oil Sampling MT, TC. Check reversing switch. 162.2TR H1 GE tap sensor replacement MS 3000 | 6.29 Days
Continuous |
|
03-Mar-25 08:00 | 07-Mar-25 17:00 | ALTALINK | TE | 419s Protection & Control (419s Chestermere) | settings and functional scheme changes | 4.38 Days
Daily |
|
03-Mar-25 08:00 | 07-Mar-25 17:00 | ALTALINK | TE | 419s RTU/SCADA (419s Chestermere) | update RTU with new alarms | 4.38 Days
Daily |
|
03-Mar-25 08:00 | 04-Mar-25 20:00 | SUNCOR | TE | 29EDD-94 406T (29EDD-94 Voyageur), 29EDD-94 407T (29EDD-94 Voyageur), 29EDD-94 29PP-97 260kV Bus (29EDD-94 Voyageur), 29EDD-94 29PP-98 260kV Bus (29EDD-94 Voyageur), 29PL9-17 (29EDD-1 Millennium - 29EDD-94 Voyageur), 29PL9-16 (29EDD-1 Millennium - 29EDD-94 Voyageur) | complete annual CIP relay password changes and power cycle | 1.5 Days
Continuous |
|
03-Mar-25 08:00 | 04-Mar-25 16:00 | ENMAX | TE | RTU/SCADA (SS-28) | SCADA RTU test | 1.33 Days
Daily |
|
03-Mar-25 08:00 | 07-Mar-25 16:00 | ENMAX | TE | 3.82L (SS-3 - SS-8) | relays end to end test | 4.33 Days
Continuous |
|
03-Mar-25 08:00 | 03-Mar-25 16:00 | ENMAX | TE | RTU/SCADA (SS-15) | SDN upgrade | 8 Hours
Continuous |
|
03-Mar-25 08:00 | 07-Mar-25 16:00 | ENMAX | TE | Protection & Control (SS-32) | 32.2TR slip over CT installation | 4.33 Days
Continuous |
|
03-Mar-25 08:30 | 07-Mar-25 15:30 | ALTALINK, DOW | Outage | 899L (166s Dow Chemical Fort Saskatchewan - 218s Fort Saskatchewan Co-Gen), 166s 899N (166s Dow Chemical Fort Saskatchewan) | urgent replacement of 138 kV Koncar CTs associated with 166s 899N | 4.29 Days
Continuous |
|
03-Mar-25 09:00 | 10-Mar-25 17:00 | ATCO | Outage | 7L23 (796s Nipisi - 7L23 tap), 7L23 (732s Mitsue - 7L23 tap), 796s 702 (796s Nipisi), 858S 701TD (858s Narrows Creek) | complete CAR cross arm replacements & TCM wood pole replacements | 7.29 Days
Continuous |
|
03-Mar-25 09:00 | 20-Mar-25 14:00 | ALTALINK | Outage | 746s T2 (746s Sherwood Park) | replace T2, 51L, 222L, & 2239L protections, add ground controls, upgrade 746s35 control module, replace 746s20 and 746s50 | 17.17 Days
Continuous |
|
03-Mar-25 09:30 | 07-Mar-25 17:30 | ATCO | TE | 946s Protection & Control (946s Oakland) | relay testing | 4.33 Days
Continuous |
|
03-Mar-25 09:30 | 03-Mar-25 17:30 | ATCO | Outage | 946s 902 (946s Oakland) | trip coil testing | 8 Hours
Continuous |
|
03-Mar-25 09:30 | 03-Mar-25 17:30 | ATCO | Outage | 734s 701T (734s Sturgeon), 734s 701 (734s Sturgeon) | 734s 701 heater repairs | 8 Hours
Continuous |
|
03-Mar-25 10:00 | 07-Mar-25 16:30 | ATCO, ALTALINK | Outage | 7L129 (526s Buffalo Creek - 7LA129 tap) | Replace structures, cross arms and insulators on 7L129 | 4.27 Days
Continuous |
|
03-Mar-25 10:00 | 03-Mar-25 15:00 | ATCO | RB | 7L90 (813s Little Smoky - 7LA90 tap), 7L90 (741s ATC Fox Creek - 7LA90 tap) | tap down mobile Sub 902S from 7L90 for 741S Fox Creek substation rebuild | 5 Hours
Continuous |
|
03-Mar-25 10:00 | 03-Mar-25 17:30 | ATCO | IO | 741s 705C (741s Fox Creek) | 705C protection requires bus voltage to verify closing on zero crossing | 7.5 Hours
Continuous |
|
03-Mar-25 10:00 | 07-Mar-25 16:30 | ATCO, ALTALINK | Outage | 7L129 (526s Buffalo Creek - 7LA129 tap) | Replace structures, cross arms and insulators on 7L129 | 4.27 Days
Continuous |
|
03-Mar-25 10:00 | 07-Mar-25 16:00 | ATCO | Outage | 700s 705C (700s Bonnyville), 700s 705 (700s Bonnyville) | prc-005 relay & trip coil testing, rtxp test switch replacement | 4.25 Days
Continuous |
|
03-Mar-25 10:00 | 06-Mar-25 16:00 | ATCO | TE | 956s Protection & Control (956s Watt Lake) | protection relay testing on 51-51N/702T | 3.25 Days
Continuous |
|
03-Mar-25 10:00 | 05-Mar-25 17:00 | ALTALINK | TE | 77s Protection & Control (77s Sagitawah) | standard relay maintenance | 2.29 Days
Daily |
|
03-Mar-25 11:00 | 06-Mar-25 17:00 | ALTALINK | TE | 157s Protection & Control (157s Lac La Biche) | standard relay maintenance | 3.25 Days
Daily |
|
03-Mar-25 12:00 | 05-Mar-25 16:00 | ATCO | TE | 951s Protection & Control (951s Thickwood Hills), 951s RTU/SCADA (951s Thickwood Hills) | updates to the 240 kV transformer protection relays for both 901T & 902T | 2.17 Days
Continuous |
|
03-Mar-25 12:00 | 04-Mar-25 16:00 | ATCO | TE | 718s Protection & Control (718s Parsons Creek) | PRC relay testing | 28 Hours
Continuous |
|
03-Mar-25 12:00 | 21-Mar-25 16:00 | ATCO | TE | 939s Protection & Control (939s Livock) | PRC relay testing on 7L125, 901T, 903T, 9L10 and 9L57 | 18.13 Days
Continuous |
|
03-Mar-25 12:01 | 31-Mar-25 12:00 | ATCO | Outage | 741s 701T (741s Fox Creek), 741s 703 (741s ATC Fox Creek) | substation upgrade project. | 27.96 Days
Continuous |
|
03-Mar-25 12:01 | 12-Mar-25 17:00 | ATCO | Outage | 7L56 (725s Goose River - 738s Virginia Hills) | replacing cross arms and poles | 9.17 Days
Continuous |
|
03-Mar-25 14:00 | 06-Mar-25 12:00 | ATCO | TE | 832s Protection & Control (832s Blumenort) | ITM/ETM wiring and settings updates to 701T protection | 2.92 Days
Continuous |
|
04-Mar-25 07:00 | 05-Mar-25 18:00 | ALTALINK | Outage | 892L (244s Bowmanton - 895s Suffield) | Cutover, test LTO, CT circuits at 244s and 895s to new RAS209 relays. Trip test 895s892 from new ‘B’ Bus protection and Breaker Fail relay. New maintenance switch being installed for breaker 244s2952 and 244s3052. | 1.46 Days
Continuous |
|
04-Mar-25 07:00 | 06-Mar-25 17:00 | ALTALINK | TE | 895s Protection & Control (895s Suffield) | PRC maintenance | 2.42 Days
Continuous |
|
04-Mar-25 07:00 | 05-Mar-25 16:00 | ALTALINK | Outage | 646L (237s Foothills - 678s Okotoks), 237s 552 (237s Foothills), 237s 652 (237s Foothills), 237s 646 (237s Foothills), 678s 646 (678s Okotoks) | urgent replacement of C phase PT 237s14 | 1.38 Days
Continuous |
|
04-Mar-25 07:00 | 09-Mar-25 19:00 | ATCO | RB | 9L20 (755s Cordel - 766s Nevis) | facilitate various construction activities on CETO | 5.46 Days
Continuous |
|
04-Mar-25 07:00 | 28-Mar-25 18:00 | ATCO | TE | 800s RTU/SCADA (800s Friedenstal) | additional PLC and new SCADA RTU changes | 24.42 Days
Continuous |
|
04-Mar-25 07:15 | 13-Mar-25 17:45 | ALTALINK | Outage | 700L (422s Westwood - 746L tap), 700L (746s Sherwood Park - 746L tap) | rebuild structure 22-37 | 9.4 Days
Continuous |
|
04-Mar-25 07:30 | 04-Mar-25 18:30 | ALTALINK | Outage | 283s C1 (283s Violet Grove), 283s T1 (283s Violet Grove), 283s 138kV Bus (283s Violet Grove), 836L (61s Lodgepole - 283s Violet Grove), 673L (131s Moon Lake - 283s Violet Grove), 283s 30 (283s Violet Grove), 283s 31 (283s Violet Grove), 283s 836 (283s Violet Grove), 283s 673 (283s Violet Grove), 131s 673 (131s Moon Lake), 61s 836N (61s Lodgepole) | replace leaking capacitor and 283s30 maintenance | 11 Hours
Daily |
|
04-Mar-25 08:00 | 14-Mar-25 16:00 | ENMAX, ALTALINK | Outage | 20.82L (SS-20 - SS-21), 21.80L (42s Sarcee - SS-21), 21.1TR (SS-21), 21.4TR (SS-21), 21B69-21.4TR (SS-21), 21MD138-21.1TR (SS-21), 21B138-20.82 (SS-21), 21B138-21.80 (SS-21), 21MD138-21.4TR (SS-21), 42s 21 (42s Sarcee), 20B138-20.82 (SS-20) | HV switch replacement | 10.29 Days
Continuous |
|
04-Mar-25 08:00 | 14-Mar-25 16:00 | ENMAX, ALTALINK | IO | 21.80L (42s Sarcee - SS-21) | HV switch replacement | 10.29 Days
Continuous |
|
04-Mar-25 08:00 | 07-Mar-25 17:00 | ALTALINK | Outage | 744L (228s T.M.P.L. Niton - 744AL tap) | Frame and replace structures 124 & 126. | 3.38 Days
Continuous |
|
04-Mar-25 08:00 | 06-Mar-25 16:00 | ALTALINK | TE | 336s Protection & Control (336s Fincastle) | RAS 180 cutover communication to B MPLS node | 2.33 Days
Daily |
|
04-Mar-25 08:00 | 06-Mar-25 16:00 | ALTALINK | TE | 244s Protection & Control (244s Bowmanton) | RAS 180 cutover communication to B MPLS node | 2.33 Days
Daily |
|
04-Mar-25 08:00 | 06-Mar-25 16:00 | ALTALINK, BHE | TE | 719s Protection & Control (719s Rattlesnake Ridge) | RAS 180 cutover communication to B MPLS node | 2.33 Days
Daily |
|
04-Mar-25 08:00 | 04-Mar-25 18:00 | ALTALINK | TE | 283s Protection & Control (283s Violet Grove) | maintenance on protections | 10 Hours
Daily |
|
04-Mar-25 08:00 | 12-Mar-25 16:00 | ATCO | TE | 730s Protection & Control (730s Rycroft) | block 21A/7L73 relay for new transformer protection upgrade | 8.29 Days
Continuous |
|
04-Mar-25 08:00 | 05-Mar-25 17:00 | ALTALINK | TE | 103s Protection & Control (103s Goose Lake) | relay maintenance | 1.38 Days
Daily |
|
04-Mar-25 08:30 | 04-Mar-25 17:30 | ALTALINK | Outage | 332s C1 (332s Ellis) | 138 kV breaker maintenance | 9 Hours
Daily |
|
04-Mar-25 09:00 | 04-Mar-25 17:00 | BCH, ALTALINK | Outage | 1L275 (799s Coleman - BCH Natal), 1CB2 (BCH Natal) | NTL 1CB2 Ras testing | 8 Hours
Continuous |
AB-BC |
04-Mar-25 09:00 | 04-Mar-25 15:00 | ATCO | TE | ATCO Telecom Equipment | Telecom OPGW Splice enclosure Repair on Structure 128 North of Sedalia Sub. Full Outage to OPGW Telecom Fiber Carrier and Circuits | 6 Hours
Continuous |
|
04-Mar-25 09:00 | 06-Mar-25 16:00 | ATCO | TE | 826s Protection & Control (826s Marguerite Lake) | repair leak on 901T DGA device | 2.29 Days
Continuous |
|
04-Mar-25 09:00 | 04-Mar-25 17:00 | ALTALINK | TE | 304s RTU/SCADA (304s Shell Limestone) | factory reset on LAN-ES1 and replace HMI | 8 Hours
Daily |
|
04-Mar-25 09:30 | 04-Mar-25 17:30 | ATCO | Outage | 946s 903 (946s Oakland), 946s 903B (946s Oakland) | trip coil testing | 8 Hours
Continuous |
|
04-Mar-25 10:00 | 04-Mar-25 18:00 | BCH | Outage | 2L113 (BCH Cranbrook - BCH Natal) | Placeholder NTL 2D21 & 2L113 OOS for 2D21 control cutover and testing. For Natal Substation rebuild project. BC maintenance does not affect the Alberta ATC | 8 Hours
Continuous |
AB-BC |
04-Mar-25 10:00 | 14-Mar-25 16:00 | ATCO | TE | 939s RTU/SCADA (939s Livock) | install new BMS | 10.21 Days
Continuous |
|
05-Mar-25 08:00 | 05-Mar-25 16:00 | ALTALINK | Outage | 126L1 (6L126 tap) | Install MOD on 126L1, test operate, adjust switch as necessary. | 8 Hours
Daily |
|
05-Mar-25 08:00 | 05-Mar-25 18:00 | ATCO | TE | ATCO Telecom Equipment, 740s RTU/SCADA (740s H.R.Milner), 810s RTU/SCADA (810s Dome Cutbank) | Smokey River Telecom. Work on Battery Banks. | 10 Hours
Continuous |
|
05-Mar-25 08:00 | 05-Mar-25 18:00 | Syncrude | TE | Syncrude ICCP Outage | SCL (Jing) - SCADA - Server Update Whole Syncrude Visibility loss |
10 Hours
Daily |
|
05-Mar-25 08:00 | 05-Mar-25 15:00 | ATCO | Outage | 6L126 (743s Sarah Lake - 515L tap) | AltaLink Work: Install MOD on 126L1, test operate, adjust switch as necessary. | 7 Hours
Continuous |
|
05-Mar-25 08:00 | 05-Mar-25 16:00 | ENMAX | TE | RTU/SCADA (SS-15) | SCADA RTU Test - RTU-15. SCADA Alarm Test - RTU-15 ANN | 8 Hours
Continuous |
|
05-Mar-25 08:00 | 05-Mar-25 17:00 | ALTALINK | TE | 358s Protection & Control (358s Amoco Brazeau) | Standard relay maintenance, cap protection is redundant. Meter Reseal on the following 358S 287L and 358S 5955T Temporary loss of analogs on the listed meters while being replaced . | 9 Hours
Daily |
|
05-Mar-25 08:00 | 05-Mar-25 17:00 | ALTALINK | TE | 542s Protection & Control (542s Ervick) | standard relay maintenance, redundant protection in place at all times | 9 Hours
Daily |
|
05-Mar-25 08:30 | 05-Mar-25 17:30 | ALTALINK | Outage | 216s 29 (216s Knightsbridge) | First trip & breaker maintenance | 9 Hours
Daily |
|
05-Mar-25 08:30 | 05-Mar-25 17:30 | ALTALINK | Outage | 331s 422 (331s Ponoka), 422L (288s Wolf Creek - 331s Ponoka) | Replace failing tank heaters | 9 Hours
Daily |
|
05-Mar-25 09:00 | 05-Mar-25 17:00 | ALTALINK | IO | 887L (48s Pocaterra - 978s BCH Britt Creek) | NTL 1CB1 Ras testing | 8 Hours
Continuous |
|
05-Mar-25 09:00 | 05-Mar-25 17:00 | ALTALINK, BCH | Outage | 1L274 (BCH Natal - BCH Line Creek tap), 1CB1 (BCH Natal) | NTL 1CB1 Ras testing | 8 Hours
Continuous |
AB-BC |
05-Mar-25 09:00 | 07-Mar-25 16:00 | ATCO | TE | 718s Protection & Control (718s Parsons Creek) | PRC Relay testing. Redundant protection in service at all times. |
2.29 Days
Continuous |
|
05-Mar-25 09:00 | 06-Mar-25 18:00 | Saskpower | Outage | SASK POWER P2C | maintenance | 1.38 Days
Continuous |
AB-SK |
05-Mar-25 09:00 | 05-Mar-25 17:00 | ATCO | TE | ATCO Telecom Equipment, 957s RTU/SCADA (957s McClelland) | Loss of visibility and control for 90min during this work. | 8 Hours
Continuous |
|
05-Mar-25 09:30 | 05-Mar-25 17:30 | ATCO | Outage | 946s 905 (946s Oakland) | trip coil testing | 8 Hours
Continuous |
|
06-Mar-25 07:00 | 06-Mar-25 18:00 | ALTALINK | Outage | 100L (498s Tilley - 895s Suffield), 498s 100X (498s Tilley), 895s 100 (895s Suffield) | replace bus protection CT circuit | 11 Hours
Daily |
|
06-Mar-25 07:00 | 06-Mar-25 17:00 | ALTALINK | TE | 895s Protection & Control (895s Suffield) | update T3 A protection settings | 10 Hours
Daily |
|
06-Mar-25 07:00 | 15-Mar-25 18:00 | ALTALINK | TE | 347s Protection & Control (347s Fox Creek) | disable trips on 77/85/L2 | 9.42 Days
Continuous |
|
06-Mar-25 08:00 | 06-Mar-25 16:00 | ALTALINK | Outage | 45s Bretona, 874L (45s Bretona - 522s Cooking Lake), 897L (38s East Edmonton - 45s Bretona), 45s T1 (45s Bretona), 45s 138kV Bus (45s Bretona), 45s 897 (45s Bretona), 45s 874 (45s Bretona), 45s 9 (45s Bretona), 522s 874 (522s Cooking Lake), 38s 897 (38s East Edmonton) | replace 45s16 failing cooper cutout, replace 45s874 tank heaters, replace 45s14 vt fuse | 8 Hours
Daily |
|
06-Mar-25 08:00 | 06-Mar-25 16:00 | ENMAX | TE | RTU/SCADA (SS-27) | SCADA RTU test - RTU-27, SCADA alarm test | 8 Hours
Continuous |
|
06-Mar-25 08:00 | 06-Mar-25 17:00 | ALTALINK | TE | 54s RTU/SCADA (54s Fort Saskatchewan) | RTU database update | 9 Hours
Daily |
|
06-Mar-25 08:00 | 06-Mar-25 17:00 | ALTALINK | TE | 178s Protection & Control (178s Cynthia) | standard relay maintenance | 9 Hours
Daily |
|
06-Mar-25 08:00 | 06-Mar-25 17:00 | ALTALINK | TE | 212s Protection & Control (212s Lacombe) | PRC maintenance | 9 Hours
Daily |
|
06-Mar-25 08:30 | 06-Mar-25 11:30 | ALTALINK | Outage | 185L (379s Shell Canada Waterton - 396s Pincher Creek), 396s 185 (396s Pincher Creek), 379s 185N (379s Shell Canada Waterton) | techs to remove pistol handle from breaker control module switch due to reliability hazard | 3 Hours
Daily |
|
06-Mar-25 08:30 | 06-Mar-25 12:30 | ALTALINK | Outage | 865L (38s East Edmonton - 216s Knightsbridge), 216s 865X (216s Knightsbridge), 38s 865N (38s East Edmonton) | first trip & breaker maintenance | 4 Hours
Daily |
|
06-Mar-25 09:30 | 06-Mar-25 17:30 | ATCO | Outage | 946s 909 (946s Oakland) | Trip coil testing | 8 Hours
Continuous |
|
06-Mar-25 12:30 | 06-Mar-25 17:30 | ALTALINK | Outage | 705L (184s Petro-Canada Edmonton - 216s Knightsbridge), 216s 32 (216s Knightsbridge), 184s 705W (184s Petro-Canada Edmonton) | first trip & breaker maintenance | 5 Hours
Daily |
|
07-Mar-25 09:00 | 07-Mar-25 16:00 | ATCO | RB | 7L46 (813s Little Smoky - 845s Big Mountain) | High load move at structure 7L46-23 | 7 Hours
Continuous |
|
07-Mar-25 09:00 | 07-Mar-25 16:00 | ATCO | RB | 7L228 (845s Big Mountain - 7L20 tap) | Lift will be needed @ structure 774 to accommodate the height of the load. | 7 Hours
Continuous |
|
07-Mar-25 10:00 | 07-Mar-25 17:00 | ATCO | TE | ATCO Telecom Equipment, 706s RTU/SCADA (706s Irish Creek) | Elk Point Telecom maintenance |
7 Hours
Continuous |
This document and the information contained herein are based upon information and data which by their nature contain a degree of uncertainty and are subject to change. In addition, this document may contain information and data from public sources and/or third parties, which have been assumed to be accurate and complete and have not been verified. Accordingly, the Independent System Operator, operating as the Alberta Electric System Operator (the "AESO") makes no warranty, representation or guarantee, express or implied, with respect to this document or the information contained herein, including, but not limited to, any warranty, representation or guarantee of accuracy, completeness, timeliness, reliability, availability, absence of computer virus, non- infringement, merchantability or suitability for any purpose. Under no circumstances will the AESO, its members, officers, employees, contractors or agents, or any of their respective affiliates, be liable for any errors or omissions in, or any losses, damages or claims whatsoever, whether in contract, tort or otherwise, arising from use of or reliance upon, this document or any information contained herein. © 2009 Alberta Electric System Operator. All rights reserved |