| Alberta Electric System Operator | |
| System Co-ordination Plan | |
| 2024-03-29 to 2024-04-05 | |
| Approved Outages |
| Previous Version | |
| Download CSV |
| From | To | Owner | Type | Element | Scheduled Activity | Date/Time Comments | Interconnection |
|---|---|---|---|---|---|---|---|
| 05-Oct-18 08:00 | 31-Dec-24 16:00 | EPCOR | IO | C2 (Rossdale) | forced outage | 2,279.38 Days
Continuous |
|
| 24-Oct-18 01:13 | 31-Dec-24 16:00 | EPCOR | IO | C1 (Rossdale) | forced outage | 2,260.66 Days
Continuous |
|
| 04-Sep-22 16:50 | 30-Sep-24 18:00 | ATCO | Outage | 848s 401R (848s Ruth Lake) | forced outage | 757.05 Days
Continuous |
|
| 15-Mar-23 18:01 | 30-Apr-24 18:00 | SUNCOR | Outage | 29EDD-71 752-4651 (29EDD-71) | breaker will remain offline for undetermined period of time | 412 Days
Continuous |
|
| 04-Jul-23 13:00 | 29-Mar-24 17:30 | ATCO | IO | 840s McNeill Station | PQM at 840s McNeill to investigate voltage transients and harmonics | 269.19 Days
Continuous |
|
| 31-Jul-23 14:56 | 27-Sep-24 16:00 | ENMAX | Outage | 38B138-38.1CAP (SS-38), 38.1C (SS-38) | motor run time fail | 424.04 Days
Continuous |
|
| 10-Nov-23 17:00 | 09-Apr-24 17:00 | EPCOR | Outage | T2 (Rossdale) | TX2 LCR, civil demo and construction | 150.96 Days
Continuous |
|
| 27-Nov-23 08:00 | 07-Mar-25 16:00 | ENMAX | Outage | 32.2TR (SS-32) | 32 sub 32.2TR 8 kV bus switchgear demolition | 466.33 Days
Continuous |
|
| 05-Dec-23 08:30 | 29-Mar-24 17:00 | EPCOR | TE | 330p Protection & Control (330p Genesee) | Genesee - 138/500 kV protection blocking for repower project cut-overs | 115.31 Days
Continuous |
|
| 02-Jan-24 07:00 | 29-Mar-24 17:00 | EPCOR | TE | 814s Protection & Control (814s Bellamy) | annual relay maintenance | 87.38 Days
Continuous |
|
| 02-Jan-24 07:00 | 29-Mar-24 17:00 | EPCOR | TE | Protection & Control (EPCOR Hardisty) | Hardisty - protection blocking for annual relay maintenance | 87.38 Days
Continuous |
|
| 02-Jan-24 07:00 | 29-Mar-24 17:00 | EPCOR | TE | 987s Protection & Control (987s Clover Bar) | Cloverbar - protection blocking for annual relay maintenance | 87.38 Days
Continuous |
|
| 02-Jan-24 07:00 | 29-Mar-24 17:00 | EPCOR | TE | 657s Protection & Control (657s Summerside) | Summerside - protection blocking for annual relay maintenance | 87.38 Days
Continuous |
|
| 02-Jan-24 07:00 | 29-Mar-24 17:00 | EPCOR | TE | 330p RTU/SCADA (330p Genesee) | configuration changes and maintenance | 87.38 Days
Continuous |
|
| 02-Jan-24 07:00 | 29-Mar-24 17:00 | EPCOR | TE | 330p Protection & Control (330p Genesee) | Genesee - protection blocking for annual relay maintenance | 87.38 Days
Continuous |
|
| 08-Jan-24 07:00 | 30-Apr-24 17:00 | EPCOR | Outage | T2 (Rossdale), R721 (Rossdale), R723 (Rossdale), RAB2 (Rossdale) | rossdale transformer assembly and scaffold build | 113.38 Days
Continuous |
|
| 12-Jan-24 07:00 | 01-Apr-24 17:00 | EPCOR | Outage | 72CN10 (987s Clover Bar - Namao), N724 (Namao), 987s CN723 (987s Clover Bar) | forced outage: pothead/cable failure | 80.38 Days
Continuous |
|
| 15-Jan-24 07:00 | 20-Apr-24 17:00 | EPCOR | Outage | 113s T2 (113s Inland Cement) | emergency iInvestigation | 96.38 Days
Continuous |
|
| 19-Feb-24 08:00 | 29-Mar-24 17:00 | ALTALINK | TE | 15s Protection & Control (15s Fort Macleod) | update settings and commission new RAS circuits | 39.33 Days
Daily |
|
| 19-Feb-24 10:00 | 17-Jun-24 17:00 | ATCO | TE | 863s RTU/SCADA (863s Paintearth) | modifications to existing RTU and new SCADA equipment | 119.25 Days
Continuous |
|
| 19-Feb-24 11:00 | 10-Jun-24 17:30 | ATCO | TE | 863S 240kV Breaker Relays, 863S 25kV Breaker Relays | disable all breaker fail protection for the duration of the project | 112.23 Days
Continuous |
|
| 19-Feb-24 11:00 | 06-Jun-24 17:30 | ATCO | TE | 863S 240kV Bus Relays | install new 900BS1 protection panel | 108.23 Days
Continuous |
|
| 26-Feb-24 07:00 | 10-May-24 17:00 | EPCOR | TE | EP 803s Protection & Control (EP 803s Lambton) | protection blocking for annual relay maintenance | 74.38 Days
Continuous |
|
| 04-Mar-24 07:00 | 17-Apr-24 17:00 | EPCOR | Outage | 72CH11 (987s Clover Bar - EP Hardisty), H725 (EP Hardisty), 987s CH724 (987s Clover Bar) | 72CH11 pothead leak mitigation | 44.38 Days
Continuous |
|
| 04-Mar-24 08:00 | 22-Apr-24 08:00 | ALTALINK | Outage | 746s T1 (746s Sherwood Park) | replace T1 and NGR, cutover protection and controls of all devices in GOI zone to new control building | 48.96 Days
Continuous |
|
| 04-Mar-24 08:00 | 30-Apr-24 16:00 | ALTALINK | TE | 746s RTU/SCADA (746s Sherwood Park) | configuration updates for A-B/87/T1, L1, L8, L2 feeder protection and cutovers of controls for 746s3, s5, s34N, s40,s173W, s474X | 57.29 Days
Daily |
|
| 06-Mar-24 07:00 | 04-Apr-24 17:00 | EPCOR | Outage | 330p 500kV Bus 1 (330p Genesee), 330p 1201 (330p Genesee), 330p 1204 (330p Genesee), 330p 1207 (330p Genesee), 330p 1214 (330p Genesee), 330p 1210 (330p Genesee), 330p 12TC1D (330p Genesee), TLO1 (330p Genesee) | string 500KV BB1 and tie in new 500KV Bus 1 | 29.38 Days
Continuous |
|
| 07-Mar-24 06:30 | 29-Aug-24 16:00 | ALTALINK | Outage | 477s T1 (477s Amoco West Pembina) | disconnect T1 and VR1 permanently, draining oil, release 477s T1, VR1, & 4.16kV equipment for salvage and RSLD2 then RSLD3 to be implemented at end of outage | 175.35 Days
Continuous |
|
| 11-Mar-24 07:00 | 30-Apr-24 17:00 | EPCOR | TE | 665s Protection & Control (665s Dome) | protection blocking for annual relay maintenance | 50.42 Days
Continuous |
|
| 11-Mar-24 08:00 | 05-Apr-24 17:00 | ATCO | TE | 2075s Protection & Control (2075s Newell) | PRC-005 microprocessor and auxiliary protection relay testing |
25.38 Days
Continuous |
|
| 11-Mar-24 08:00 | 08-Apr-24 16:00 | ENMAX | Outage | 5.1TR (SS-5) | transformer protection upgrade | 28.33 Days
Continuous |
|
| 18-Mar-24 08:00 | 03-Apr-24 16:00 | ENMAX | Outage | 15.60L (SS-15 - SS-21), 15B69-15.60 (SS-15), 21B69-15.60 (SS-21) | line protection upgrade | 16.33 Days
Continuous |
|
| 18-Mar-24 08:00 | 01-Apr-24 18:00 | SUNCOR | Outage | 29EDD-94 29PP-97 260kV Bus (29EDD-94 Voyageur), 29PL9-162 (29EDD-94 Voyageur - 951s Thickwood Hills), 29PL9-193 (29EDD-94 Voyageur - 951s Thickwood Hills) | steel Inspection for 29PL9-162/193 A frame; 29PL9-24/25 A frame |
14.42 Days
Continuous |
|
| 18-Mar-24 08:00 | 29-Mar-24 17:00 | ALTALINK | TE | 244s RTU/SCADA (244s Bowmanton) | updating RTU configuration for the Dunmore project | 11.38 Days
Daily |
|
| 18-Mar-24 09:00 | 12-Apr-24 17:00 | BCH | Outage | 2L112 (BPA Boundary - BCH Nelway), T2 (BCH Natal) | repair NLY T2 oil leak BC maintenance does not affect the Alberta ATC, BPA replace structures | 25.33 Days
Continuous |
AB-BC |
| 18-Mar-24 09:00 | 07-Apr-24 17:00 | ATCO | TE | 728s RTU/SCADA (728s Mercer Hill) | 728S Mercer Hill scada upgrade | 20.33 Days
Continuous |
|
| 18-Mar-24 10:00 | 05-Apr-24 17:30 | ATCO | TE | 834s Protection & Control (834s Wesley Creek) | relay testing on. SEL 2506/2G, 904BF, 900BS2, 900BS1, 903BF, 9L11, 9L15, 7L08 |
18.31 Days
Continuous |
|
| 18-Mar-24 14:30 | 29-Apr-24 14:00 | ATCO | Outage | 863s 902T (863s Paintearth) | protection upgrade, commission new wiring/trransformer protection, and new transformer protection panel | 41.98 Days
Continuous |
|
| 22-Mar-24 09:00 | 29-Mar-24 12:00 | ATCO | RB | 9L10 (876s Brintnell - 939s Livock) | walk up and climbing inspection | 7.13 Days
Continuous |
|
| 22-Mar-24 09:00 | 29-Mar-24 12:00 | ATCO | RB | 7L49 (729s Otauwau - 732s Mitsue) | walk up and climbing inspection | 7.13 Days
Continuous |
|
| 22-Mar-24 12:22 | 04-Apr-24 17:00 | ALTALINK | Outage | 310p 1852 (310p Sundance) | emergency repair | 13.19 Days
Continuous |
|
| 25-Mar-24 06:00 | 29-Mar-24 18:00 | ALTALINK | Outage | 799L (77s Sagitawah - 443s South Mayerthorpe) | component and structure replacement | 4.5 Days
Continuous |
|
| 25-Mar-24 07:00 | 03-Apr-24 17:00 | EPCOR | Outage | 987s T2 (987s Clover Bar), 987s T4 (987s Clover Bar), 987s C2406 (987s Clover Bar), 987s C2405 (987s Clover Bar), 987s C2408 (987s Clover Bar), 987s CDS31 (987s Clover Bar), 987s CC721 (987s Clover Bar) | T2 and T4 bay outage for final tie in of 1191L bay | 9.42 Days
Continuous |
|
| 25-Mar-24 08:00 | 01-Apr-24 08:00 | ENMAX | Outage | 54.1TR (SS-54) | repair foundation leak | 7 Days
Continuous |
|
| 25-Mar-24 08:00 | 29-Mar-24 17:00 | ALTALINK | TE | 535s RTU/SCADA (535s Joffre) | download new configurations and make LAN modifications to add new SEL-2440s and LAN devices | 4.38 Days
Continuous |
|
| 25-Mar-24 10:00 | 03-Apr-24 15:00 | ATCO | TE | 932s Protection & Control (932s Pemukan) | relay work |
9.21 Days
Continuous |
|
| 26-Mar-24 12:00 | 04-Apr-24 16:00 | ALTALINK | Outage | 859L (20s Ghost - AML 793s Horse Creek), 20s 859E (20s Ghost), AML 793s 859W (AML 793s Horse Creek) | upgrade 859L line protections at 793s and test tpr circuits | 9.17 Days
Continuous |
|
| 26-Mar-24 12:00 | 04-Apr-24 16:00 | ALTALINK | TE | 20s RTU/SCADA (20s Ghost) | update SCADA configuration for line protection work on 859L | 9.17 Days
Continuous |
|
| 26-Mar-24 12:00 | 04-Apr-24 16:00 | ALTALINK | TE | AML 793s RTU/SCADA (AML 793s Horse Creek) | update SCADA configuration for line protection work on 859L | 9.17 Days
Continuous |
|
| 27-Mar-24 06:00 | 03-Apr-24 18:00 | ALTALINK | Outage | 792L (150s Clyde - 191s N.W. Cardiff), 150s 792X (150s Clyde), 191s 792N (191s N.W. Cardiff) | structure and component replacement | 7.5 Days
Continuous |
|
| 29-Mar-24 07:00 | 29-Mar-24 12:00 | ATCO, ALTALINK | Outage | 7L230 (69s North Barrhead - 888AL tap), 888AL (234s Fort Assiniboine - 7L230 tap), 69s 230W (69s North Barrhead), 234s 888 (234s Fort Assiniboine) | 1-2 poles on 7L230 that are leaning and could fall anytime | 5 Hours
Daily |
|
| 29-Mar-24 08:00 | 29-Mar-24 12:00 | ATCO, ALTALINK | Outage | 7L230 (743s Sarah Lake - 888AL tap), 7L230 (69s North Barrhead - 888AL tap), 743s 703 (743s Sarah Lake) | emergency pole change str#384 | 4 Hours
Continuous |
|
| 30-Mar-24 08:00 | 01-Apr-24 18:00 | ENMAX | Outage | 65.2TR (SS-65), 65B138-D85 (SS-65), 65B138-D82 (SS-65), 65B240-D132 (SS-65), 65B240-D135 (SS-65), 65MD138-65.2TR (SS-65), 65MD240-65.2TR (SS-65) | HV SW maintenance, check reversing switch, oil sampling, tapchanger, power factor test | 2.42 Days
Continuous |
|
| 31-Mar-24 08:00 | 05-Apr-24 15:00 | ENMAX | Outage | 3GSU-XF-001 (SS-25) | electrical testing | 5.29 Days
Continuous |
|
| 01-Apr-24 00:00 | 01-May-24 00:00 | SUNCOR | Outage | 29EDD-71 29PT-235 (29EDD-71), 29EDD-71 752-4642 (29EDD-71), 29EDD-71 752-4641 (29EDD-71) | FB-maintenance and testing | 30 Days
Continuous |
|
| 01-Apr-24 07:00 | 04-Apr-24 18:00 | ENMAX | Outage | 12.2TR (SS-12) | grounding deficiency improvements | 3.46 Days
Continuous |
|
| 01-Apr-24 08:00 | 05-Apr-24 17:00 | ALTALINK | TE | 5s RTU/SCADA (5s East Calgary) | SCADA upgrade | 4.38 Days
Daily |
|
| 01-Apr-24 08:00 | 12-Apr-24 17:00 | ALTALINK | TE | 321s RTU/SCADA (321s Al Rothbauer) | updating RTU configuration | 11.38 Days
Daily |
|
| 01-Apr-24 08:00 | 10-May-24 17:00 | ALTALINK | TE | 244s RTU/SCADA (244s Bowmanton) | updating RTU configuration | 39.38 Days
Daily |
|
| 01-Apr-24 08:00 | 19-Apr-24 16:00 | ENMAX | Outage | 8.5TR (SS-8), 8.6TR (SS-8), 8B138-2A0 (SS-8), 8B138-3A0 (SS-8), 2A10 (SS-8), 3A1 (SS-8) | 8 sub prot repl - Z32 | 18.33 Days
Continuous |
|
| 01-Apr-24 08:00 | 06-Apr-24 17:00 | ALTALINK | TE | 535s RTU/SCADA (535s Joffre) | download new configurations, migrating and commissioning of T4 SCADA | 5.38 Days
Continuous |
|
| 02-Apr-24 07:00 | 02-Apr-24 18:00 | ALTALINK | Outage | 244s 240kV Bus 1 (244s Bowmanton), 244s 138kV Bus 1 (244s Bowmanton), 244s T1 (244s Bowmanton), 244s 452 (244s Bowmanton), 244s 152 (244s Bowmanton), 244s 2552 (244s Bowmanton), 244s 2152 (244s Bowmanton), 244s 2589 (244s Bowmanton), 244s 2289 (244s Bowmanton), 244s 2189 (244s Bowmanton) | install and commission new circuits and protections pertaining to the Dunmore project | 11 Hours
Daily |
|
| 02-Apr-24 07:00 | 11-Apr-24 18:00 | ALTALINK | Outage | 925L (63s Red Deer - 74s Janet) | component replacement between structures | 9.46 Days
Continuous |
|
| 02-Apr-24 07:00 | 04-Apr-24 17:00 | ALTALINK, EPCOR | Outage | 1058L (657s Summerside - EP 803s Lambton), EP 803s L2403 (EP 803s Lambton), EP 803s L2404 (EP 803s Lambton), 657s SU2403 (657s Summerside), 657s SU2404 (657s Summerside), 657s SUDS10 (657s Summerside) | P&C maintenance | 2.42 Days
Continuous |
|
| 02-Apr-24 07:00 | 02-Apr-24 17:00 | ENMAX | RB | 9.83L (SS-9 - SS-43) | spring transmission line washing | 10 Hours
Continuous |
|
| 02-Apr-24 07:00 | 02-Apr-24 17:00 | ENMAX | RB | 20.82L (SS-20 - SS-21) | spring transmission line washing | 10 Hours
Continuous |
|
| 02-Apr-24 07:00 | 07-May-24 17:00 | EPCOR | Outage | T1 (Garneau), GT1 (Garneau) | Garneau S/S Tx1 bay outage | 35.42 Days
Continuous |
|
| 02-Apr-24 07:15 | 08-Apr-24 17:45 | ALTALINK, ATCO | Outage | 702L (137s Sedgewick - 757s Battle River), 757s 708 (757s Battle River) | component replacement (Str 11-197) | 6.44 Days
Continuous |
|
| 02-Apr-24 07:15 | 08-Apr-24 17:45 | ATCO | IO | 7L702 (137s Sedgewick - 757s Battle River) | AltaLink request, structure maintenance/replacement on 702L | 6.44 Days
Continuous |
|
| 02-Apr-24 07:30 | 03-Apr-24 18:00 | ALTALINK | Outage | 299s T1 (299s Kingman), 299s 732N (299s Kingman) | transformer maintenance and test | 1.44 Days
Continuous |
|
| 02-Apr-24 07:30 | 11-Apr-24 17:30 | ALTALINK | RB | 1082L (63s Red Deer - 287s Hazelwood) | crews working within close proximity on 925L | 9.42 Days
Daily |
|
| 02-Apr-24 07:30 | 11-Apr-24 17:30 | ALTALINK | RB | 929L (74S Janet - 287s Hazelwood) | crews working within close proximity on 925L | 9.42 Days
Daily |
|
| 02-Apr-24 07:30 | 11-Apr-24 17:30 | ALTALINK | RB | 901AL (64s East Crossfield - 901L tap), 901L (63s Red Deer - 901AL tap), 901L (74s Janet - 901AL tap) | working within close proximity on 925L | 9.42 Days
Daily |
|
| 02-Apr-24 07:30 | 02-Apr-24 15:30 | ALTALINK | RB | 551L (945s Sunshine Village - 551GL tap), 551L (953s Lake Louise - 551GL tap) | clean up osprey nest | 8 Hours
Daily |
|
| 02-Apr-24 07:30 | 03-Apr-24 18:00 | ALTALINK | TE | 299s RTU/SCADA (299s Kingman) | update configuration for T1 protection upgrade | 1.44 Days
Daily |
|
| 02-Apr-24 07:30 | 02-Apr-24 18:00 | ALTALINK | Outage | 221s T2 (221s Sunken Lake) | tap changer filter installation and metering replacement | 10.5 Hours
Daily |
|
| 02-Apr-24 08:00 | 04-Apr-24 18:00 | ENMAX | Outage | 65.1TR (SS-65), 65B138-D83 (SS-65), 65B138-D81 (SS-65), 65B240-D130 (SS-65), 65B240-D133 (SS-65), 65MD240-65.1TR (SS-65), 65MD138-65.1TR (SS-65) | maintenance and oil sampling | 2.42 Days
Continuous |
|
| 02-Apr-24 08:00 | 02-Apr-24 17:00 | ATCO | RB | 7L39 (722s Crystal Lake - 7LA39 tap), 7LA39 (728s Mercer Hill - 7L39 tap), 7L39 (811s Clairmont Lake - 7LA39 tap) | connection of 902s mobile substation to 7LA39 at 728s Mercer Hill | 9 Hours
Continuous |
|
| 02-Apr-24 08:00 | 12-Apr-24 08:00 | ATCO, CNRL, ALBIAN | Outage | 847s 902T (847s Muskeg River), 919s 908 (919s Hartley) | maintenance | 10 Days
Continuous |
|
| 02-Apr-24 08:00 | 24-Apr-24 16:00 | SUNCOR | Outage | 29PL6-5 (29EDD-1 Millennium - 29EDD-2 Tar Island), 29EDD-1 29EDD1s1652 (29EDD-1 Millennium), 29EDD-1 29EDD1s1752 (29EDD-1 Millennium), 29EDD-1 29PS-196 (29EDD-1 Millennium), 29PS-44 (29EDD-22) | maintenance and relay upgrades | 22.33 Days
Continuous |
|
| 02-Apr-24 08:00 | 02-Apr-24 18:00 | ALTALINK | Outage | 838L (14s Devon - 325s Leduc), 325s 838 (325s Leduc), 14s 838X (14s Devon) | high load move str 27-28 | 10 Hours
Daily |
|
| 02-Apr-24 08:00 | 02-Apr-24 17:00 | ALTALINK | TE | 632s RTU/SCADA (632s Russell) | raw socket conversion on 7705A and LAN switch upgrade | 9 Hours
Daily |
|
| 02-Apr-24 08:00 | 10-Apr-24 16:00 | ENMAX | Outage | 2.82L (SS-2 - SS-5), 5B138-2.82 (SS-5), 2MD138-2.82 (SS-2) | facilitate the duct break in for new tie in | 8.33 Days
Continuous |
|
| 02-Apr-24 09:00 | 08-Apr-24 16:00 | ATCO | IO | 710s Vermilion | training - hands on operation of spare NO system switches | 6.29 Days
Continuous |
|
| 02-Apr-24 09:00 | 04-Apr-24 16:00 | ATCO | TE | 826s Protection & Control (826s Marguerite Lake) | temporary isolation of transformer Non-electrical when bleeding air in piping to dissolved gas unit | 2.29 Days
Continuous |
|
| 02-Apr-24 09:30 | 02-Apr-24 17:30 | ATCO | TE | 823s Protection & Control (823s Wapiti) | 701T tap changer settings update | 8 Hours
Continuous |
|
| 02-Apr-24 10:00 | 02-Apr-24 15:00 | ATCO | Outage | 932s 722C (932s Pemukan) | PRC-005 trip coil testing | 5 Hours
Continuous |
|
| 02-Apr-24 10:00 | 02-Apr-24 10:30 | CMH | TE | Medicine Hat ICCP Outage | data center switches migration | 30 Mins
Continuous |
|
| 02-Apr-24 11:00 | 02-Apr-24 16:00 | ATCO | RB | 7L76 (786s High Level - 832s Blumenort) | HOP to lift bottom phase of 7L76-04 | 5 Hours
Continuous |
|
| 02-Apr-24 12:30 | 11-Apr-24 16:00 | ALTALINK | Outage | 158s T2 (158s Vauxhall) | 158sT2 oil reclaim or leak repair | 9.15 Days
Continuous |
|
| 02-Apr-24 12:30 | 04-Apr-24 17:30 | ALTALINK | Outage | 74s C1 (74s Janet), 74s C2 (74s Janet) | 74sC2 JB4 replacement | 2.21 Days
Continuous |
|
| 02-Apr-24 13:30 | 02-Apr-24 17:00 | ALTALINK | Outage | 103s 1752 (103s Goose Lake) | 1st trip only | 3.5 Hours
Daily |
|
| 02-Apr-24 17:00 | 04-Apr-24 18:00 | ALTALINK | Outage | 221s T2 (221s Sunken Lake) | tapchanger filter install, metering replacement | 2.04 Days
Continuous |
|
| 03-Apr-24 07:00 | 03-Apr-24 18:00 | ALTALINK | Outage | 244s 240kV Bus 2 (244s Bowmanton), 244s 138kV Bus 2 (244s Bowmanton), 244s T2 (244s Bowmanton), 244s 352 (244s Bowmanton), 244s 652 (244s Bowmanton), 244s 2652 (244s Bowmanton), 244s 2252 (244s Bowmanton), 244s 2389 (244s Bowmanton), 244s 2489 (244s Bowmanton) | install and commission new circuits and protections pertaining to the Dunmore Project | 11 Hours
Daily |
|
| 03-Apr-24 07:00 | 04-Apr-24 18:00 | ALTALINK | Outage | 453L (305s Acheson - 367s Harry Smith), 305s 453 (305s Acheson), 367s 453 (367s Harry Smith) | 305s453 grading cap replacement and 305s24 switch repair | 1.46 Days
Continuous |
|
| 03-Apr-24 08:00 | 03-Apr-24 18:00 | Syncrude | TE | Syncrude ICCP Outage | SCADA - server update | 10 Hours
Daily |
|
| 03-Apr-24 08:00 | 03-Apr-24 17:00 | ALTALINK | Outage | 631L (186s Dry Creek - 199s East Airdrie) | repair OHSW bond at str 86, replace dampers at str 90 | 9 Hours
Daily |
|
| 03-Apr-24 08:00 | 03-Apr-24 17:00 | ALTALINK | RB | 611L (186s Dry Creek - 391S Balzac) | repair OHSW bond on 631L86 (611L11), replace dampers on 631L90(611L7) | 9 Hours
Daily |
|
| 03-Apr-24 08:00 | 03-Apr-24 10:00 | ENMAX | Outage | 15.60L (SS-15 - SS-21) | spring transmission line washing | 2 Hours
Continuous |
|
| 03-Apr-24 08:00 | 03-Apr-24 18:00 | ALTALINK | TE | AltaLink Telecom Equipment | MPLS upgrade at 312s | 10 Hours
Daily |
|
| 03-Apr-24 08:00 | 03-Apr-24 17:00 | ALTALINK, Travers2SolarLP | TE | 991s Protection & Control (991s Little Bow) | settings change on 1005AL A87/27/L1 SEL411L | 9 Hours
Daily |
|
| 03-Apr-24 08:00 | 03-Apr-24 17:00 | ALTALINK, Travers2SolarLP | TE | 991s RTU/SCADA (991s Little Bow) | RTU SCADA outage | 9 Hours
Daily |
|
| 03-Apr-24 08:00 | 03-Apr-24 17:00 | ALTALINK | TE | 56s RTU/SCADA (56s Boyle) | troubleshoot comms issue and replace HMI | 9 Hours
Daily |
|
| 03-Apr-24 08:00 | 03-Apr-24 16:00 | ENMAX | Outage | 22.81L (SS-22 - SS-39), 22B138-22.81 (SS-22), 39B138-22.81 (SS-39) | power factor test | 8 Hours
Continuous |
|
| 03-Apr-24 08:00 | 13-Apr-24 16:00 | Syncrude | Outage | TL-2 (Aurora - Aurora) | TL-2 will be isolated to support project tie | 10.33 Days
Continuous |
|
| 03-Apr-24 08:00 | 03-Apr-24 12:00 | ATCO | RB | 7L23 (796s Nipisi - 7L23 tap), 7L23 (732s Mitsue - 7L23 tap) | require HOP on 7L23 str 7L23-305 to lift 1 phase on 144 line for a high load move | 4 Hours
Continuous |
|
| 03-Apr-24 08:00 | 03-Apr-24 12:00 | ATCO | RB | 7L63 (780s Lubicon - 812s Norcen), 7L63 (788s Hotchkiss - 7LA63 tap) | require HOP on 7L63 str 7L63-923 to lift 1 phase on 144 line for a high load move | 4 Hours
Continuous |
|
| 03-Apr-24 08:00 | 03-Apr-24 17:00 | ALTALINK | Outage | 256s T1 (256s Harmattan) | urgent - 256s4 like for like replacement and AMI associated cable re- attachment | 9 Hours
Daily |
|
| 03-Apr-24 08:30 | 03-Apr-24 17:30 | ALTALINK | Outage | 613L (103s Goose Lake - 396s Pincher Creek), 396s 20 (396s Pincher Creek) | clean/grease 103s21 and 103s1352,103s1452 first trips on return switching | 9 Hours
Daily |
AB-BC |
| 03-Apr-24 09:00 | 03-Apr-24 16:00 | ATCO | TE | ATCO Telecom Equipment | main microwave link cutover to new IRU AVIAT radios from constellations | 7 Hours
Continuous |
|
| 03-Apr-24 10:00 | 03-Apr-24 13:00 | ENMAX | Outage | 21.61L (SS-21 - SS-34) | spring transmission line washing | 3 Hours
Continuous |
|
| 03-Apr-24 10:00 | 03-Apr-24 15:00 | ATCO | Outage | 932s 723C (932s Pemukan) | PRC-005 - trip coil testing, microprocessor relay testing | 5 Hours
Continuous |
|
| 03-Apr-24 10:00 | 03-Apr-24 17:00 | ATCO | TE | ATCO Telecom Equipment, 827s RTU/SCADA (827s Cranberry Lake) | total outage to IP Network access traffic | 7 Hours
Continuous |
|
| 04-Apr-24 07:00 | 05-Apr-24 18:00 | ALTALINK | Outage | 792L (92s Viscount - 191s N.W. Cardiff), 92s 792 (92s Viscount), 191s 792X (191s N.W. Cardiff) | complete replacement of 792L structure 184. | 1.46 Days
Continuous |
|
| 04-Apr-24 07:00 | 04-Apr-24 17:00 | ENMAX | RB | 24.81L (SS-24 - SS-31) | spring transmission line washing | 10 Hours
Continuous |
|
| 04-Apr-24 08:00 | 05-Apr-24 12:00 | ALTALINK | TE | 244s Protection & Control (244s Bowmanton) | updates for the Dunmore project | 28 Hours
Daily |
|
| 04-Apr-24 08:00 | 05-Apr-24 12:00 | ALTALINK | TE | 321s Protection & Control (321s Al Rothbauer) | updates for the Dunmore project | 28 Hours
Daily |
|
| 04-Apr-24 08:00 | 05-Apr-24 17:00 | ALTALINK | Outage | 161L (255s Vulcan - 504s Queenstown), 504s 161 (504s Queenstown), 255s 161 (255s Vulcan) | replace damper on structure 239. hardware tighten structure 350. | 1.38 Days
Continuous |
|
| 04-Apr-24 08:00 | 05-Apr-24 17:00 | ALTALINK | RB | 876L (179s Gleichen - 253s Blackie) | repair conductor damage at structure 161L124 (876L54). | 1.38 Days
Daily |
|
| 04-Apr-24 08:00 | 04-Apr-24 17:00 | SUNCOR | TE | Suncor RTU/SCADA (Suncor) | update RTU program at 29EDD-4 | 9 Hours
Continuous |
|
| 04-Apr-24 08:00 | 10-Apr-24 16:00 | Syncrude | Outage | UT2 (Aurora) | complete maintenance on the 15kV switchgear fed from UT-2 | 6.33 Days
Continuous |
|
| 04-Apr-24 08:00 | 04-Apr-24 16:00 | ENMAX | Outage | 38B138-38.83 (SS-38), 38.83L (SS-38 - SS-39), 39B138-38.83 (SS-39) | power factor test 39B138-38.83 CT | 8 Hours
Continuous |
|
| 04-Apr-24 08:00 | 04-Apr-24 16:00 | REDDEER | Outage | 194s T1 (194s South Red Deer), 194s T2 (194s South Red Deer) | low voltage AC/DC panel replacement | 8 Hours
Continuous |
|
| 04-Apr-24 08:00 | 04-Apr-24 17:00 | ALTALINK, ENMAXEC | TE | 383s RTU/SCADA (383s Kettles Hill Windfarm) | complete a raw socket conversion on 7705A and a LAN switch upgrade | 9 Hours
Daily |
|
| 04-Apr-24 08:00 | 04-Apr-24 17:00 | ALTALINK | TE | 12s Protection & Control (12s Heartland) | factory reset on the 12L85 A87/L1 relay | 9 Hours
Daily |
|
| 04-Apr-24 08:00 | 04-Apr-24 17:30 | ATCO | TE | 2029s Protection & Control (2029s Heathfield) | end-to-end relay testing with AltaLink on 12L85 protection PRC-005 | 9.5 Hours
Continuous |
|
| 04-Apr-24 08:00 | 04-Apr-24 17:00 | ALTALINK | Outage | 256s T2 (256s Harmattan) | urgent 256s3 like for like replacement and cable re- attachment. | 9 Hours
Daily |
|
| 04-Apr-24 08:00 | 04-Apr-24 10:00 | Lethbridge | TE | APS# 169 725LW-674S Overload Mitigation | add time delay function to DNP (RS485) alarm for channel fail | 2 Hours
Continuous |
|
| 04-Apr-24 08:30 | 04-Apr-24 12:30 | ALTALINK | Outage | 103s 1552 (103s Goose Lake) | 1st trip test only | 4 Hours
Daily |
|
| 04-Apr-24 09:00 | 04-Apr-24 10:00 | ENMAX | Outage | 15.62L (SS-15 - SS-16) | spring transmission line washing | 60 Mins
Continuous |
|
| 04-Apr-24 10:00 | 04-Apr-24 17:00 | ATCO | TE | ATCO Telecom Equipment, 754s RTU/SCADA (754s Ksituan River) | outage to IP network access traffic | 7 Hours
Continuous |
|
| 04-Apr-24 10:01 | 04-Apr-24 11:00 | ENMAX | Outage | 16.60L (SS-16 - SS-34) | spring transmission line washing | 59 Mins
Continuous |
|
| 04-Apr-24 12:31 | 04-Apr-24 16:30 | ALTALINK | Outage | 103s 1652 (103s Goose Lake) | 1st trip test only | 3.98 Hours
Continuous |
|
| 05-Apr-24 08:00 | 07-Apr-24 16:00 | ENMAX | Outage | 13.82L (SS-13 - SS-22), 13B138-13.82 (SS-13), 22B138-13.82 (SS-22) | line clearance mitigation | 2.33 Days
Continuous |
|
| 05-Apr-24 08:00 | 06-Apr-24 16:00 | ENMAX, ALTALINK | Outage | 1109L (SS-25 - SS-65), 25B240-D141 (SS-25), 25B240-D142 (SS-25), 65B240-D135 (SS-65), 65B240-D134 (SS-65), 25MD240-1109 (SS-25), 65MD240-1109 (SS-65) | switch maintenance, power factor test, washing. replace harp | 1.33 Days
Continuous |
|
| 05-Apr-24 08:00 | 06-Apr-24 16:00 | ENMAX, ALTALINK | IO | 1109L (SS-25 - SS-65) | switch maintenance, power factor test | 1.33 Days
Continuous |
|
| 05-Apr-24 08:00 | 05-Apr-24 16:00 | ALTALINK | TE | 103s Protection & Control (103s Goose Lake) | finish implement fault reporting; 616L B21/79/L10 | 8 Hours
Daily |
|
| 05-Apr-24 08:00 | 05-Apr-24 16:00 | ALTALINK | TE | 103s RTU/SCADA (103s Goose Lake) | finish implement fault reporting | 8 Hours
Daily |
|
| 05-Apr-24 08:00 | 11-Apr-24 15:00 | ENMAX | Outage | 2GSU-XF-001 (SS-25) | electrical testing | 6.29 Days
Continuous |
|
| 05-Apr-24 08:00 | 05-Apr-24 17:00 | SUNCOR | TE | 29EDD-1 RTU/SCADA (29EDD-1 Millennium) | line protection upgrades | 9 Hours
Continuous |
| This document and the information contained herein are based upon information and data which by their nature contain a degree of uncertainty and are subject to change. In addition, this document may contain information and data from public sources and/or third parties, which have been assumed to be accurate and complete and have not been verified. Accordingly, the Independent System Operator, operating as the Alberta Electric System Operator (the "AESO") makes no warranty, representation or guarantee, express or implied, with respect to this document or the information contained herein, including, but not limited to, any warranty, representation or guarantee of accuracy, completeness, timeliness, reliability, availability, absence of computer virus, non- infringement, merchantability or suitability for any purpose. Under no circumstances will the AESO, its members, officers, employees, contractors or agents, or any of their respective affiliates, be liable for any errors or omissions in, or any losses, damages or claims whatsoever, whether in contract, tort or otherwise, arising from use of or reliance upon, this document or any information contained herein. © 2009 Alberta Electric System Operator. All rights reserved |