Alberta Electric System Operator
System Co-ordination Plan
2022-05-05 to 2022-05-13
Approved Outages

Previous Version
Download CSV

From To Owner Type Element Scheduled Activity Date/Time Comments Interconnection
05-Oct-18 08:00 31-Dec-23 16:00 EPCOR IO C2 (Rossdale) forced outage 1,913.38 Days
Continuous
 
24-Oct-18 01:13 31-Dec-23 16:00 EPCOR IO C1 (Rossdale) forced outage 1,894.66 Days
Continuous
 
01-Jan-21 08:00 04-Jan-23 18:00 SUNCOR Outage Unmodeled Transmission Facility (Suncor) 30EDD-200 733.42 Days
Continuous
 
02-Jan-21 08:00 05-Jan-23 18:00 SUNCOR Outage Unmodeled Transmission Facility (Suncor) 29EDD-181
733.42 Days
Continuous
 
05-Jan-21 08:00 01-Jun-23 18:00 SUNCOR Outage Unmodeled Transmission Facility (Suncor) 29PT-69
877.38 Days
Continuous
 
24-Jan-21 08:00 07-Jan-23 18:00 SUNCOR Outage Unmodeled Transmission Facility (Suncor) 29EDD-161
713.42 Days
Continuous
 
02-Feb-21 08:00 10-Jan-23 18:00 SUNCOR Outage Unmodeled Transmission Facility (Suncor) 29EDD-221
707.42 Days
Continuous
 
24-Feb-21 08:00 11-Jan-23 18:00 SUNCOR Outage Unmodeled Transmission Facility (Suncor) 29EDD-211; substation ground test; PM 5y - 34.5kV 686.42 Days
Continuous
 
01-Mar-21 08:00 03-Feb-23 18:00 SUNCOR Outage Unmodeled Transmission Facility (Suncor) 29EDD-221 ;29PT-605 system 704.42 Days
Continuous
 
01-Mar-21 08:00 04-Feb-23 18:00 SUNCOR Outage Unmodeled Transmission Facility (Suncor) 29EDD-161; 29PT-582 system 705.42 Days
Daily
 
01-Mar-21 08:00 05-Feb-23 18:00 SUNCOR Outage Unmodeled Transmission Facility (Suncor) 29EDD-171; 29PT-600 system 706.42 Days
Daily
 
13-Sep-21 12:15 06-May-22 18:00 ALTALINK Outage 437s T1 (437s Baymag) T1 A & B protection replacement 235.24 Days
Continuous
 
03-Dec-21 08:00 30-Jun-22 17:00 ATCO TE 7L84 (722s Crystal Lake - 749s Flyingshot Lake) emergency - relay settings changes at 722s and 749s 209.33 Days
Continuous
 
09-Dec-21 13:00 31-Aug-22 17:00 ATCO Outage 863s 902T (863s Paintearth) forced outage and troubleshooting 265.13 Days
Continuous
 
01-Jan-22 08:00 06-Mar-23 18:00 SUNCOR Outage Unmodeled Transmission Facility (Suncor) 30EDD-200 429.42 Days
Daily
 
01-Jan-22 08:00 07-Mar-23 18:00 SUNCOR Outage Unmodeled Transmission Facility (Suncor) 30EDD-200 430.42 Days
Daily
 
01-Jan-22 08:00 19-Oct-22 18:00 SUNCOR Outage Unmodeled Transmission Facility (Suncor) 29EDD-9 291.38 Days
Daily
 
01-Jan-22 08:00 09-Nov-22 18:00 SUNCOR Outage Unmodeled Transmission Facility (Suncor) 29EDD-8 312.42 Days
Daily
 
24-Jan-22 07:00 14-Jun-22 17:00 EPCOR Outage T1 (Garneau) provide clearances for Tx1 replacement 141.38 Days
Continuous
 
25-Jan-22 07:00 03-Jun-22 17:00 EPCOR TE EP 511s Victoria relay blocking required on 'A' and 'B' protections for relay maintenance 129.38 Days
Daily
 
07-Feb-22 12:00 31-May-22 18:00 ATCO TE 951s 240kV 900BS2 (951s Thickwood Hills) wiring and CT changes for the 87BA/900BS2 and 87BB/900BS2 113.21 Days
Continuous
 
07-Feb-22 12:00 31-May-22 18:00 ATCO TE 951s 240kV 900BS1 (951s Thickwood Hills) addition of two new relays for 900BS1 113.21 Days
Continuous
 
14-Mar-22 14:00 30-Jun-22 18:00 ATCO TE 813s SVC (813s Little Smoky) emergency real time failed relay 108.17 Days
Continuous
 
18-Mar-22 16:30 20-May-22 12:00 NWE, BHE Canada, BHE Outage Marias South Series Capacitor, North Series Capacitor (BHE Hay Lake) repair series capacitor bypass breaker 62.81 Days
Continuous
AB-MATL
10-Apr-22 08:00 29-Nov-22 18:00 SUNCOR Outage Unmodeled Transmission Facility (Suncor) 29PL-3 233.46 Days
Daily
 
12-Apr-22 12:00 20-May-22 12:00 NWE, BHE Canada Outage Marias South Series Capacitor urgent- replace the Marias series capacitor bypass breaker 2385 Phase B 38 Days
Continuous
AB-MATL
13-Apr-22 09:30 18-May-22 17:00 ALTALINK Outage 115s T2 (115s Mount Allan) emergency work; hydrogen gas buildup needs to be removed from TX 35.31 Days
Continuous
 
18-Apr-22 08:00 29-May-23 17:00 ATCO TE 813s Little Smoky 144kV Bus 1, 813s Little Smoky 144kV Bus 2, 813s Little Smoky 240kV Bus 1, 813s Little Smoky 240kV Bus 2 813S Little Smoky rebuild: cutover wiring to the new relays as their corresponding apparatus are out of service 406.38 Days
Continuous
 
18-Apr-22 08:00 29-May-23 17:00 ATCO TE 813s Little Smoky 813S Little Smoky rebuild: cutover wiring to the new relays as their corresponding apparatus are out of service 406.38 Days
Continuous
 
19-Apr-22 08:00 15-May-22 12:00 ATCO Outage 9L11 (813s Little Smoky - 834s Wesley Creek), 813s 905 (813s Little Smoky), 813s 906 (813s Little Smoky) 813S Little Smoky rebuild 26.17 Days
Continuous
 
19-Apr-22 08:00 16-May-22 16:00 ATCO TE 813s Little Smoky protection relay work 27.33 Days
Continuous
 
20-Apr-22 08:30 07-May-22 17:30 ALTALINK Outage 38s C1 (38s East Edmonton), 38s 3052 (38s East Edmonton) breaker maintenance and testing 17.38 Days
Daily
 
21-Apr-22 14:30 17-May-22 13:30 ALTALINK Outage 538s T1 (538s Buford) bushing and oil replacement, leak repairs, maintenance 25.96 Days
Continuous
 
25-Apr-22 00:00 05-May-22 23:59 ALPAC TE 282s RTU/SCADA (282s Grassland (Alpac)) DCS upgrade 11 Days
Continuous
 
25-Apr-22 06:00 06-May-22 18:00 SUNCOR Outage 29EDD-94 407T (29EDD-94), 29EDD-94 29-952-9704 (29EDD-94 Voyageur), 29EDD-94 29-952-9705 (29EDD-94 Voyageur) maintenance and test 11.5 Days
Continuous
 
25-Apr-22 07:00 20-May-22 17:00 EPCOR TE RTU/SCADA (Poundmaker), RTU/SCADA (Strathcona), RTU/SCADA (Garneau), 816s RTU/SCADA (816s Petrolia), EP 803s RTU/SCADA (EP 803s Lambton), 665s RTU/SCADA (665s Dome), RTU/SCADA (EPCOR Hardisty) commissioning of RTU output for ADMS upgrade 25.42 Days
Daily
 
25-Apr-22 07:00 09-May-22 18:00 ATCO, ALTALINK RB 1035L (244s Bowmanton - 2075s Newell) AltaLink will require a continuous Reclose Block Advice on 1035L @ A2075S 14.46 Days
Continuous
 
25-Apr-22 07:00 09-May-22 18:00 ALTALINK Outage 964L (244s Bowmanton - 251s Whitla) removing and installing new protections for the future 1024s 14.46 Days
Continuous
 
25-Apr-22 07:00 09-May-22 17:00 ALTALINK TE 251s RTU/SCADA (251s Whitla) add new alarms and control points for 964L protections and RAS schemes 14.42 Days
Daily
 
25-Apr-22 07:00 09-May-22 17:00 ALTALINK TE 244s RTU/SCADA (244s Bowmanton) add new alarms and control points for 964L protections and RAS schemes 14.42 Days
Daily
 
25-Apr-22 08:00 03-Jun-22 16:00 ENMAX Outage 2.82L (ENMAX 2 - ENMAX 5) replace circuit breaker 39.33 Days
Continuous
 
25-Apr-22 08:00 03-Jun-22 16:00 ALTALINK IO 2.82L (C2s-C5s) Enmax - Info 5sub TRV Project. Replace circuit breaker 39.33 Days
Continuous
 
25-Apr-22 09:00 13-May-22 17:30 ATCO Outage 7L90 (813s Little Smoky - 7LA90 tap), 741s 701 (741s ATC Fox Creek) breaker 701 replacement 18.35 Days
Continuous
 
25-Apr-22 09:00 13-May-22 17:30 ALTALINK IO 7L90 (741s) Atco - Info Breaker 701 Replacement 18.35 Days
Continuous
 
26-Apr-22 07:00 05-May-22 17:00 ALTALINK TE 244s Bowmanton EATL RAS - change settings and to accommodate end- to-end testing, trip testing breaker @ 1024s 9.42 Days
Daily
 
27-Apr-22 17:00 27-Jun-22 07:00 ALTALINK Outage 165s T1 (165s Gainford) replacing T1 with a new transformer 60.58 Days
Continuous
 
28-Apr-22 17:30 07-Jul-22 17:30 ALTALINK Outage 370s T1 (370s North Lethbridge) Install breaker foundation and breaker between 370s3 and T1 70 Days
Continuous
 
01-May-22 06:10 06-May-22 20:00 SUNCOR Outage 29PL6-22 (29EDD-1 Millennium - 29EDD-2 Tar Island) disconnect switch arcing 5.58 Days
Continuous
 
01-May-22 07:30 13-May-22 17:30 ALTALINK TE 171s RTU/SCADA (171s Redwater) upgrade RTU/HMI and to cut-over SCADA to new RTU communication 12.42 Days
Daily
 
02-May-22 07:00 13-May-22 17:00 EPCOR Outage T1 (Meadowlark) secondary feeder recabling 11.42 Days
Continuous
 
02-May-22 07:00 06-May-22 17:00 EPCOR Outage 814s T2 (814s Bellamy), T1 (Rossdale), BR722 (Rossdale), R721 (Rossdale) P&C maintenance 4.42 Days
Continuous
 
02-May-22 07:00 06-May-22 17:00 EPCOR Outage 330p 1206 (330p Genesee) CT doble, breaker maintenance 4.42 Days
Continuous
 
02-May-22 07:00 06-May-22 17:00 EPCOR Outage 987s C2406 (987s Clover Bar) CT/breaker doble and breaker maintenance 4.42 Days
Continuous
 
02-May-22 07:00 10-May-22 17:00 EPCOR TE RTU/SCADA (Kennedale), RTU/SCADA (Namao), 557s RTU/SCADA (557s Castle Downs), RTU/SCADA (Meadowlark), 805s RTU/SCADA (805s Jasper), EP 511s Victoria, EP Riverview commissioning of all RTU outputs for ADMS upgrade 8.42 Days
Daily
 
02-May-22 07:00 13-May-22 17:00 EPCOR RB 72PM25 (Poundmaker - Meadowlark) pole refurbishment 11.42 Days
Continuous
 
02-May-22 07:30 06-May-22 17:30 ALTALINK TE 121s RTU/SCADA (121s Brooks) update the RTU and substation HMI to add new ACC alarms 4.42 Days
Daily
 
02-May-22 08:00 30-Sep-22 18:00 SUNCOR Outage Unmodeled Transmission Facility (Suncor) 29PP-901 151.42 Days
Daily
 
02-May-22 08:00 06-May-22 17:00 ATCO Outage 718s 701 (718s Parsons Creek), 848s 702 (848s Ruth Lake), 7L47 (718s Parsons Creek - 848s Ruth Lake) breaker maintenance 4.38 Days
Continuous
 
02-May-22 08:00 10-May-22 17:00 ALTALINK Outage 925L (63s Red Deer - 74s Janet) protection upgrade 8.38 Days
Continuous
 
02-May-22 08:00 05-May-22 16:00 ENMAX Outage 40.1TR (ENMAX 40) power factor test transformer, secondary cable testing, relays, gas testing, transformer maintenance, oil sampling MT, TC, replace PRD junction box 3.33 Days
Continuous
 
02-May-22 08:00 05-May-22 20:00 Syncrude Outage Syncrude Mildred Lake CB 1315 will be operated 3.5 Days
Continuous
 
02-May-22 08:00 05-May-22 16:00 ENMAX Outage 14.4TR (ENMAX 14) power factor test transformer, secondary cable testing, transformer maintenance, gas relay testing, oil sampling MT, TC. check reversing switch 3.33 Days
Continuous
 
02-May-22 08:00 06-May-22 15:00 Saskpower Outage SASK POWER P2C maintenance 4.29 Days
Continuous
AB-SK
02-May-22 09:00 05-May-22 16:00 ALTALINK TE 510s Sunnybrook relay maintenance on A878-A/ACF1B, A878-B/ACF1B and A878-C/ACF1B 3.29 Days
Daily
 
02-May-22 09:00 10-May-22 16:00 ALTALINK TE 925L (63s Red Deer - 74s Janet) 925L protection upgrade 8.29 Days
Continuous
 
02-May-22 09:00 27-May-22 17:00 ATCO TE 709s RTU/SCADA (709s Vegreville) downloading RTU controls 25.33 Days
Continuous
 
02-May-22 09:00 05-May-22 17:30 ALTALINK TE 121s Brooks tie in new CT on 795X & test B87/B138BX A87/B138BX 3.35 Days
Continuous
 
02-May-22 09:30 06-May-22 17:30 ATCO Outage 721s 701T (721s La Corey) maintenance 4.33 Days
Continuous
 
02-May-22 10:00 06-May-22 15:00 Saskpower Outage Sask Power P2P maintenance 4.21 Days
Continuous
AB-SK
02-May-22 11:00 25-May-22 17:30 ATCO TE 959s Lanfine install power quality monitor 23.27 Days
Continuous
 
02-May-22 12:00 06-May-22 12:00 BHE TE 719s RTU/SCADA (719s Rattlesnake Ridge) RTU database updates 4 Days
Daily
 
02-May-22 13:00 05-May-22 17:30 ATCO Outage 801s 705 (801s Anderson), 7L85 (801s Anderson - 803s Bullpound) Wheatland Wind Farm Project protection upgrades (P1718) 3.19 Days
Continuous
 
03-May-22 07:30 05-May-22 17:30 ALTALINK RB 1048L (59s Peigan - 138s Windy Flats) fire mitigation on structure #1048L10 - live line 2.42 Days
Daily
 
03-May-22 07:30 05-May-22 17:30 ALTALINK RB 1049L (59s Peigan - 138s Windy Flats) fire mitigation on structure #1049L20 - live line 2.42 Days
Daily
 
03-May-22 08:00 05-May-22 17:00 ALTALINK TE 394s Empress integrate anti islanding scheme 2.38 Days
Daily
 
03-May-22 08:00 05-May-22 16:00 ENMAX Outage 22.1TR (ENMAX 22) tapchanger maintenance (X), (Y), oil sampling MT TC(X), (Y) 2.33 Days
Continuous
 
03-May-22 08:15 05-May-22 15:45 ALTALINK Outage 437s Baymag, 754L (118s Canmore - 437s Baymag), 754L (437s Baymag - 742L tap) replace faulting switch 437s19 & 437s20 2.31 Days
Continuous
 
03-May-22 08:30 05-May-22 11:30 ATCO, ALTALINK IO 789L (898s Heart Lake - 1034s Margie) requesting ATCO to close N.O. 898s704A
for Altalink work at 167s
2.13 Days
Continuous
 
03-May-22 09:00 09-May-22 17:00 ALTALINK TE 74s RTU/SCADA (74s Janet), 63s RTU/SCADA (63s Red Deer) line protection upgrade on 925L 6.33 Days
Daily
 
03-May-22 09:00 06-May-22 17:00 BCH Outage 5L98 (BCH Nicola - Vaseux Lake) station work at NIC, BC maintenance does not affect the Alberta ATC 3.33 Days
Continuous
AB-BC
03-May-22 09:00 06-May-22 17:00 ALTALINK IO 5L98 (NIC-VAS) BCH - INFO station work at NIC (5L98) 3.33 Days
Continuous
 
03-May-22 09:30 05-May-22 17:30 ALTALINK Outage 138S R2 (138s Windy Flats), 138s 1752 (138s Windy Flats) maintenance, doble 2.33 Days
Continuous
 
03-May-22 17:00 06-May-22 15:00 ATCO Outage 876s 901T (876s Brintnell) transformer and regulator maintenance
901T Out of service 25Kv
2.92 Days
Continuous
 
03-May-22 17:00 20-May-22 17:00 EPCOR TE RTU/SCADA (Garneau), RTU/SCADA (Poundmaker) commissioning of all RTU outputs for ADMS upgrade 17 Days
Daily
 
03-May-22 23:00 05-May-22 07:00 ALTALINK Outage 250p 22 (250p Bighorn Plant) maintenance 1.33 Days
Continuous
 
04-May-22 06:00 12-May-22 18:00 SUNCOR Outage 29PL9-12 (29EDD-34 - 29EDD-65), 29EDD-34 29-952-122 (29EDD-34), 29EDD-34 29-952-123 (29EDD-34) PRC-023 settings update and maintenance 8.5 Days
Continuous
 
04-May-22 07:00 15-May-22 18:00 ALTALINK Outage 174L (197s Bardo - 395s North Holden) 174L phase 3 rebuild, structures 539 to 691 11.46 Days
Continuous
 
04-May-22 07:00 24-Jun-22 15:00 ALTALINK Outage 250p 11 (250p Bighorn Plant) maintenance 51.33 Days
Continuous
 
04-May-22 07:00 07-May-22 17:30 ALTALINK TE 39s Bickerdike settings changes to 973L and 974L protections - 39s Cascade project 3.44 Days
Daily
 
04-May-22 07:00 05-May-22 04:30 ALTALINK Outage 870L (262s Rocky Mountain House - 263s Strachan), 718L (250p Bighorn Plant - 263s Strachan), 263s C1 (263s Strachan), 263s 138kV Bus 1 (263s Strachan), 263s T1 (263s Strachan), 250p 718 (250P Bighorn Plant), 262s 870W (262s Rocky Mountain House) urgent - conductor repair, switch and insulator replacement 21.5 Hours
Continuous
 
04-May-22 08:00 12-May-22 18:00 SUNCOR Outage 29PL9-12 (29EDD-34 - 29EDD-65), 29EDD-65 29-952-4811 (29EDD-65), 29EDD-65 29-952-4812 (29EDD-65) maintenance 8.42 Days
Continuous
 
04-May-22 09:00 31-May-22 15:00 TRANSCANADAP TE 910s RTU/SCADA (910s Excel) test channels 27.25 Days
Continuous
 
04-May-22 09:15 05-May-22 16:45 ALTALINK Outage 433L (291s Cochrane - AML 793s Horse Creek), AML 793s 433 (AML 793s Horse Creek) replace 6 grading capacitor on 793s433 minimum oil breaker 31.5 Hours
Continuous
 
04-May-22 10:00 06-May-22 13:00 CMH Outage MH-10L (MHS10 - MHS8 Burnside), MHS8 T81 (MHS8 Burnside), MHS-8 MH69-802 (MHS-8 Burnside), MHS-8 MH138-803 (MHS-8 Burnside), MH-12L (MHS8 Burnside – MHS6 Riverview) PRC-005 - tapchanger maintenance 2.13 Days
Continuous
 
05-May-22 07:00 06-May-22 17:00 ENMAX RB 16.61L (ENMAX 16 - ENMAX 27) tree trimming 1.42 Days
Daily
 
05-May-22 07:30 05-May-22 12:30 ALTALINK Outage 914L (86s Bigstone - 87s Gaetz) fire risk mitigation; str 337 5 Hours
Daily
 
05-May-22 07:30 05-May-22 17:30 ALTALINK RB 1083L (63s Red Deer - 288s Wolf Creek) safety requirement for 914L 10 Hours
Daily
 
05-May-22 07:30 09-May-22 18:00 CNRL Outage 838s 75-TR-1801 (838s Horizon Mining) 5 year PM (breakers, PRC-005) 4.44 Days
Continuous
 
05-May-22 07:30 05-May-22 17:30 ALTALINK TE 410s RTU/SCADA (410s Josephburg) update RTU configuration to fix deficiencies for new SCADA system install 10 Hours
Daily
 
05-May-22 07:30 05-May-22 17:30 ALTALINK RB 426L (63s Red Deer - 194s South Red Deer) safety requirement for 914L 10 Hours
Daily
 
05-May-22 08:00 05-May-22 16:00 ENMAX Outage 65B240-D131 (ENMAX 65) breaker maintenance 8 Hours
Continuous
 
05-May-22 08:00 05-May-22 17:30 ALTALINK Outage 659s T1 (659s Pegasus Lake) perform tests on T1 9.5 Hours
Daily
 
05-May-22 08:00 10-May-22 20:00 Syncrude Outage Mildred T4 (Syncrude Mildred Lake) 4435 and 435 will be operated 5.5 Days
Continuous
 
05-May-22 08:30 06-May-22 17:30 ALTALINK IO 887L/1L274 (48s) BCH - Advice BCH live line work - replacing timbers 1.38 Days
Daily
 
05-May-22 10:00 05-May-22 16:00 ATCO RB 790s 144kV Bus 700BS2 (790s Poplar Hill) to tap up 902S 144kV risers to 790S 700BS2 6 Hours
Continuous
 
05-May-22 12:31 05-May-22 17:30 ALTALINK Outage 914L (63s Red Deer - 87s Gaetz) fire risk mitigation 4.98 Hours
Daily
 
06-May-22 08:00 06-May-22 16:00 ENMAX TE ENMAX 41 power factor test 41PT138-Z31 8 Hours
Continuous
 
06-May-22 08:00 15-May-22 17:00 SUNCOR Outage 635PL7-1001 (635EDD-1000 - 635EDD-1001) regulatory maintenance 9.38 Days
Continuous
 
06-May-22 10:00 17-May-22 14:00 ATCO Outage 790s 702T (790s Poplar Hill) transformer & circuit switcher PM 11.17 Days
Continuous
 
06-May-22 12:00 06-May-22 14:00 ATCO RB 790s 144kV Bus 700BS2 (790s Poplar Hill) HOP to open jumper J1 between 700BS2 and 702TCS 2 Hours
Continuous
 
06-May-22 14:00 16-May-22 10:00 ATCO Outage 790s 702T (790s Poplar Hill), 790s 702TCS (790s Poplar Hill) transformer & circuit switcher PM 9.83 Days
Continuous
 
07-May-22 06:00 16-May-22 18:00 SUNCOR Outage 29EDD-94 406T (29EDD-94), 29EDD-94 29-952-9702 (29EDD-94 Voyageur), 29EDD-94 29-952-9703 (29EDD-94 Voyageur) maintenance and test 9.5 Days
Continuous
 
07-May-22 07:00 08-May-22 16:00 Saskpower Outage Sask Power P2P maintenance 1.38 Days
Continuous
AB-SK
07-May-22 07:00 07-May-22 13:00 ALTALINK RB 955L (59s Peigan - 103s Goose Lake) crews working within close proximity on 956L 6 Hours
Daily
 
07-May-22 07:00 07-May-22 13:00 ALTALINK Outage 956L (59s - 103s) - GOI Maintenance on 956L80 6 Hours
Daily
 
07-May-22 07:30 14-May-22 18:00 CNRL Outage 838s 75-BC-1915 (838s Horizon Mining), 838s 75-BC-1916 (838s Horizon Mining), 838s 75-BC-1917 (838s Horizon Mining) testing of 260kV circuit breakers and PRC-005 trip coil testing. 7.44 Days
Continuous
 
07-May-22 08:00 07-May-22 16:00 ENMAX Outage 32B138-31.84 (ENMAX 32), 31.84L (ENMAX 31 - ENMAX 32) 32B138-31.84 breaker mech exposed to adverse weather 8 Hours
Continuous
 
07-May-22 13:00 07-May-22 18:00 ALTALINK Outage 955L (59s - 103s) - GOI Maintenance on 955L91 5 Hours
Daily
 
07-May-22 13:00 07-May-22 18:00 ALTALINK RB 956L (59s Peigan - 103s Goose Lake) crews working within close proximity on 955L 5 Hours
Daily
 
08-May-22 07:00 08-May-22 17:30 ALTALINK TE 740L (39s Bickerdike - 58s Edson) setting changes for 740L B Protection at 58s and 39s 10.5 Hours
Daily
 
08-May-22 07:00 12-May-22 18:00 ALTALINK Outage 39s 29 (39s Bickerdike), 39s 1052 (39s Bickerdike), 39s 1152 (39s Bickerdike), 39s T2 (39s Bickerdike), 39s 240kV Bus 2 (39s Bickerdike) iInstall new 973L, 974L and 1168L into A-frames at 39S as part of Cascade project 4.46 Days
Continuous
 
08-May-22 07:00 12-May-22 18:00 ALTALINK Outage 740L (39s Bickerdike - 58s Edson) modify 740L between Str 51D and 51E 4.46 Days
Continuous
 
08-May-22 08:00 08-May-22 17:30 Saskpower RB 9LS1M (840s McNeil - Swift Current) SaskPower has work planned in the Swift Current Switching Station that requires a standoff (HOP) on S1M to operate an isolator device. 9.5 Hours
Continuous
AB-SK
08-May-22 08:00 12-May-22 17:00 ATCO Outage 7L85 (803s Bullpound - 804s Wintering Hills) reroute line by adding 4-6 poles and moving the line out along its existing right away to allow the construction of the T-Tap portion down to 981s Badlands (P1718) 4.38 Days
Continuous
 
09-May-22 07:00 13-May-22 17:00 EPCOR Outage 805s T1 (805s Jasper), 72JM18 (805s Jasper - Meadowlark), 72JW19 (805s Jasper - Woodcroft) surge arrestor replacement 4.42 Days
Continuous
 
09-May-22 07:00 13-May-22 17:00 EPCOR Outage T2 (Rossdale), R721 (Rossdale), R723 (Rossdale) P&C maintenance 4.42 Days
Continuous
 
09-May-22 07:00 13-May-22 17:00 EPCOR Outage 805s T4 (805s Jasper) protection upgrade cutovers 4.42 Days
Continuous
 
09-May-22 07:00 09-May-22 17:00 ENMAX RB 16.60L (ENMAX 16 - ENMAX 34) tree trimming 10 Hours
Daily
 
09-May-22 07:00 09-May-22 17:00 ALTALINK TE 244s Bowmanton removing the A21 RAS Relay from service to change settings and to accommodate end-to-end testing 10 Hours
Daily
 
09-May-22 07:00 19-May-22 17:00 ALTALINK TE 244s Bowmanton removing relays from service to change settings and to accommodate end- to-end testing 10.42 Days
Daily
 
09-May-22 07:00 10-May-22 17:00 ALTALINK TE 304s RTU/SCADA (304s Shell Limestone) RTU database update 1.42 Days
Continuous
 
09-May-22 07:00 13-May-22 18:00 ALTALINK Outage 753L (65s High River - 253s Blackie) on Structures #14 - 38, 4.46 Days
Continuous
 
09-May-22 07:00 13-May-22 17:00 EPCOR Outage 330p 1207 (330p Genesee) breaker maintenance and CT doble 4.42 Days
Continuous
 
09-May-22 07:00 12-May-22 17:00 ALTALINK TE AltaLink Radio Tower repair antenna mounts 3.42 Days
Continuous
 
09-May-22 07:00 20-May-22 17:00 ALTALINK TE 121s Supervisory update the RTU and substation HMI to add new ACC alarms 11.42 Days
Continuous
 
09-May-22 07:00 20-May-22 17:00 EPCOR TE RTU/SCADA (Rossdale), 814s RTU/SCADA (814s Bellamy), 330p RTU/SCADA (330p Genesee), 657s RTU/SCADA (657s Summerside) commissioning of RTU output for ADMS upgrade 11.42 Days
Daily
 
09-May-22 07:15 09-May-22 17:45 ALTALINK Outage 100L (498s Tilley - 895s Suffield) maintenance (Str 177) 10.5 Hours
Daily
 
09-May-22 07:30 11-May-22 09:00 CMH Outage MHS2 T23 (MHS-2 North Industria), MH-9L (MH69s2 North Industrial - MHS10) PRC-005 - tapchanger maintenance 2.06 Days
Continuous
 
09-May-22 07:30 13-May-22 16:30 ALTALINK Outage AML 511s FB Bus 1 (AML 511s Crossings), AML 511s SVC Plus (AML 511s Crossings) breaker and AC filter maintenance 4.38 Days
Continuous
 
09-May-22 07:30 09-May-22 17:00 ENMAX RB 2.83L (ENMAX 2 - ENMAX 5 - ENMAX 13) spring transmission line washing 9.5 Hours
Continuous
 
09-May-22 07:30 09-May-22 17:00 ENMAX RB 2.82L (ENMAX 2 - ENMAX 5) spring transmission line washing 9.5 Hours
Continuous
 
09-May-22 08:00 09-May-22 16:00 ENMAX Outage 65B240-D132 (ENMAX 65) HV breaker maintenance 8 Hours
Continuous
 
09-May-22 08:00 16-May-22 12:00 ATCO Outage 951S 907 (951s Thickwood Hills), 951s 908 (951s Thickwood Hills), 9L01 (848s Ruth Lake - 951s Thickwood) construction on new breaker 909 and installation of gang switches relay settings change and testing on 908 (9L01) and operation of gang switch 9L01D2 7.17 Days
Continuous
 
09-May-22 08:00 09-May-22 12:00 SUNCOR TE 29EDD-2 Tar Island RTU/SCADA updates to D20MX at the 29EDD-2 4 Hours
Continuous
 
09-May-22 08:00 10-May-22 16:00 ENMAX Outage 24.2TR (ENMAX 24) tapchanger maintenance, oil sampling MT, TC 1.33 Days
Continuous
 
09-May-22 08:00 12-May-22 16:00 ALTALINK TE 99s RTU/SCADA (99s North St. Albert) program and test new alarms for battery monitors and battery charger 3.33 Days
Daily
 
09-May-22 08:00 13-May-22 16:00 ENMAX Outage 47.1TR (ENMAX 47) maintenance 4.33 Days
Continuous
 
09-May-22 08:00 11-May-22 16:00 ENMAX Outage 33.2TR (ENMAX 33) investigate dev. 90 PT 2.33 Days
Continuous
 
09-May-22 08:00 14-May-22 16:00 ATCO Outage 7L68 (730s Rycroft - 811s Clairmont Lake) walk up/ climbing inspection 5.33 Days
Continuous
 
09-May-22 09:00 12-May-22 16:00 ALTALINK TE 510s Sunnybrook relay maintenance 3.29 Days
Daily
 
09-May-22 09:00 13-May-22 17:00 ALTALINK IO 887L/1L274 (EFT-1D2L274) BCH - Info Install wood pole structures and bypass conductor underneath 1L274 & the tap to FRO on the POC side of BCK 4.33 Days
Continuous
 
09-May-22 09:00 10-May-22 17:00 ALTALINK TE 74s Janet restore the CT contributions for the 925L Protection upgrade 1.33 Days
Daily
 
09-May-22 09:00 13-May-22 17:00 BCH Outage 1L274 (48s Pocaterra - Britt Creek) install wood pole structures and bypass conductor underneath 1L274 & the tap to FRO on the POC side of BCK 4.33 Days
Continuous
AB-BC
09-May-22 09:00 10-May-22 17:00 ALTALINK TE 63s T2 (63s Red Deer) restore the CT contributions for the 925L protection upgrade 1.33 Days
Daily
 
09-May-22 09:00 10-May-22 17:00 ALTALINK TE 63s Red Deer, 900L (17s Benalto - 63s Red Deer) restore the CT contributions for the 925L protection upgrade 1.33 Days
Daily
 
09-May-22 09:00 10-May-22 17:00 ALTALINK TE 63s 240kV South Bus (63s Red Deer) restore the CT contributions for the 925L Protection upgrade 1.33 Days
Daily
 
09-May-22 09:00 09-May-22 10:00 ENMAX Outage 15.60L (ENMAX 15 - ENMAX 21) spring transmission line washing 60 Mins
Continuous
 
09-May-22 09:00 13-May-22 18:00 Saskpower Outage SaskPower C1S maintenance 4.38 Days
Continuous
AB-SK
09-May-22 09:00 20-May-22 17:00 ATCO TE 804s Wintering Hills RTU/SCADA upgrade to new HMI 11.33 Days
Continuous
 
09-May-22 09:00 12-May-22 17:00 ALTALINK TE 602s Cold Creek implement the new Irig signals to remote devices 3.33 Days
Daily
 
09-May-22 09:00 16-May-22 16:00 ATCO RB 7L82 (788s Hotchkiss - 855s Hamburg), 7L82 (853s Ring Creek - 855s Hamburg) walk up/ climbing inspection 7.29 Days
Daily
 
09-May-22 09:00 11-May-22 17:30 ATCO Outage 721s 702T (721s La Corey) 702T transformer maintenance & 25kv switch repair, load transferred to 701T 2.35 Days
Continuous
 
09-May-22 09:30 20-May-22 16:00 ATCO TE 706S 144kV Bus Protection PRC-005 relay testing 11.27 Days
Continuous
 
09-May-22 09:30 09-May-22 17:30 ATCO TE 972s RTU/SCADA (972s Tinchebray) RTU battery replacements 8 Hours
Continuous
 
09-May-22 10:00 12-May-22 17:30 ATCO Outage 843s 601T (843s Bigknife Creek) class 2 major testing 601T @ 843S 3.31 Days
Continuous
 
09-May-22 10:00 09-May-22 11:00 ENMAX Outage 21.61L (ENMAX 21 - ENMAX 34) spring transmission line washing 60 Mins
Continuous
 
09-May-22 10:15 13-May-22 17:45 ALTALINK Outage 336s T1 (336s Fincastle) replacement of 25kV & 138kV LA's 4.31 Days
Continuous
 
09-May-22 11:00 12-May-22 17:00 ALTALINK Outage 191s T1 (191s N.W. Cardiff) T1: fix leaks, maintain, doble, fix fan VR1: maintain, doble, 191s6 VT sweating, inspect 3.25 Days
Continuous
 
09-May-22 11:00 09-May-22 12:00 ENMAX Outage 15.62L (ENMAX 15 - ENMAX 16) spring transmission line washing 60 Mins
Continuous
 
09-May-22 12:00 09-May-22 17:00 ENMAX RB 14.83L (ENMAX 14 - ENMAX 36) spring transmission line washing 5 Hours
Continuous
 
09-May-22 12:00 09-May-22 13:00 ENMAX Outage 16.60L (ENMAX 16 - ENMAX 34) spring transmission line washing 60 Mins
Continuous
 
09-May-22 12:00 09-May-22 17:00 SUNCOR TE Suncor RTU/SCADA updates to D20MX at the 29EDD-22 5 Hours
Continuous
 
09-May-22 12:00 13-May-22 17:00 ATCO TE 951s RTU/SCADA (951s Thickwood Hills) update station controllers and HMI 4.21 Days
Continuous
 
09-May-22 12:00 13-May-22 17:00 ATCO TE 804s Wintering Hills updates and wiring for 702BF during the 7L85 protection upgrade 4.21 Days
Continuous
 
09-May-22 12:00 09-May-22 17:00 ALTALINK TE 510s Sunnybrook CIP compliance maintenance 5 Hours
Daily
 
09-May-22 12:30 13-May-22 14:30 ALTALINK Outage 437s T2 (437s Baymag) protection upgrade project for transformer T2; upgrading ‘A’ and ‘B’ protections 4.08 Days
Continuous
 
09-May-22 13:00 13-May-22 14:00 ALTALINK TE 437s Baymag RTU/SCADA protection upgrade project for transformer T2 4.04 Days
Continuous
 
10-May-22 07:00 10-May-22 17:00 ENMAX RB 13.60L (ENMAX 13 - ENMAX 27) tree trimming 10 Hours
Daily
 
10-May-22 07:00 10-May-22 17:00 ENMAX RB 21.61L (ENMAX 21 - ENMAX 34) tree trimming 10 Hours
Daily
 
10-May-22 07:00 11-May-22 18:00 ALTALINK Outage 983L (244s Bowmanton - 251s Whitla) re-wire trip circuits, add breaker status for RAS functions and tie in CT’s for SEL 451’s 1.46 Days
Continuous
 
10-May-22 07:00 10-May-22 18:00 ALTALINK Outage 234L (310p Sundance - 505L tap), 234L (133L tap - 505L tap), 505L (234L tap - 505L tap), 521AL (867s Sundance Blow-Down - 521L tap), 521L (505L tap - 521AL tap) P5 Urgent correct insufficient clearance from the bottom phase to the top strut guy off structure 234L82 / 521L33 11 Hours
Daily
 
10-May-22 07:30 10-May-22 16:30 ALTALINK Outage 38s 7152 (38s East Edmonton) replace 1 grading capacitor on 38s7152 9 Hours
Daily
 
10-May-22 07:30 10-May-22 16:30 ALTALINK, EPCOR RB 915L (38s East Edmonton - 987s Clover Bar) RB for replacing 1 grading capacitor on 38s7152 9 Hours
Continuous
 
10-May-22 07:30 10-May-22 17:30 ALTALINK Outage 668L (394s Empress - 562s Cypress), 394s 668 (394s Empress) integrate anti-island scheme 10 Hours
Daily
 
10-May-22 08:00 10-May-22 16:00 ENMAX Outage 65B240-D133 (ENMAX 65) HV breaker maintenance 8 Hours
Continuous
 
10-May-22 08:00 12-May-22 17:00 ATCO RB 9L01 (848s Ruth Lake - 951s Thickwood) climbing inspection 2.38 Days
Daily
 
10-May-22 08:00 10-May-22 12:00 SUNCOR TE 30EDD-1 RTU/SCADA updates to D20MX at the 30EDD-1 4 Hours
Continuous
 
10-May-22 08:00 12-May-22 17:00 ATCO RB 7L38 (875s Algar - 917s Horse River) climbing inspection 2.38 Days
Daily
 
10-May-22 08:00 10-May-22 09:00 Lethbridge TE 241s RTU/SCADA (241s Lethbridge Uplands) security patch upgrade to RX 1500 60 Mins
Continuous
 
10-May-22 08:30 12-May-22 18:00 ALTALINK Outage 489s T1 (489s Petro Canada Brazeau River) maintenance and doble testing 2.4 Days
Continuous
 
10-May-22 09:00 13-May-22 16:00 ATCO Outage 718s 702T (718s Parsons Creek) 702T maintenance 3.29 Days
Continuous
 
10-May-22 09:00 10-May-22 15:15 ENMAX IO Altalink outage. 5s C3 & C4 Cap urgent work to restore cap bank back into service from real time lockout, replace cap on cap bank and weed spraying 6.25 Hours
Continuous
 
10-May-22 09:00 11-May-22 16:00 ALTALINK Outage 5s C3 (5s East Calgary), 5s C4 (5s East Calgary) Urgent work to restore cap bank back into service from real time lockout, replace cap on cap bank and weed spraying 31 Hours
Continuous
 
10-May-22 09:00 10-May-22 10:00 Lethbridge TE 146s RTU/SCADA (146s Lethbridge Macdonald) security patch upgrade to RX 1500 60 Mins
Continuous
 
10-May-22 10:00 16-May-22 16:35 ATCO TE 9L02 (809s Louise Creek - 813s Little Smoky) isolate 906CT for primary injection for new 9L11 protection 6.27 Days
Continuous
 
10-May-22 10:00 10-May-22 11:00 ALTALINK TE 171s RTU/SCADA (171s Redwater) move the 171S Scada circuit to the new building #3 MPLS 60 Mins
Daily
 
10-May-22 10:00 10-May-22 11:00 Lethbridge TE 593s RTU/SCADA (593s Lethbridge Lakeview) security patch upgrade to RX 1500 60 Mins
Continuous
 
10-May-22 11:00 10-May-22 12:00 Lethbridge TE 111s RTU/SCADA (111s Coalbanks) security patch upgrade to RX 1500 60 Mins
Continuous
 
10-May-22 12:00 10-May-22 17:00 SUNCOR TE 29EDD-1 Millennium RTU/SCADA updates to D20MX at the 29EDD-1 5 Hours
Continuous
 
10-May-22 13:00 10-May-22 17:00 ALTALINK TE 12s T1 (12s Heartland) gather CIP SR08 data for AESO CIP 10 compliance 4 Hours
Daily
 
10-May-22 13:00 10-May-22 14:00 Lethbridge TE 674s RTU/SCADA (674s Lethbridge Bowron) security patch upgrade to RX 1500 60 Mins
Continuous
 
10-May-22 14:00 10-May-22 15:00 Lethbridge TE 181s RTU/SCADA (181s Chinook) security patch upgrade to RX 1500 60 Mins
Continuous
 
10-May-22 15:00 10-May-22 16:00 Lethbridge TE City of Lethbridge Control Centre security patch upgrade to RX 1500 60 Mins
Continuous
 
11-May-22 07:00 11-May-22 17:00 ENMAX RB 16.63L (ENMAX 16 - ENMAX 36) tree trimming 10 Hours
Daily
 
11-May-22 07:00 13-May-22 17:00 ALTALINK TE 356s RTU/SCADA (356s Milo) RTU database update 2.42 Days
Daily
 
11-May-22 07:00 13-May-22 17:00 ATCO RB 7L10 (730s Rycroft - 754s Ksituan River) SVC addition and 144kV bus rebuild
7L68D3 bypass to be moved to make way for sub expansion, install bypass switch between and jumper
2.42 Days
Continuous
 
11-May-22 07:30 11-May-22 16:30 ALTALINK Outage 89s352 - GOI, 89s 352 (89s Ellerslie) Replace 1 grading capacitor on 89s352 9 Hours
Daily
 
11-May-22 07:30 11-May-22 16:30 EPCOR RB ALTALINK - 1056L - RB @ (E814s - 89s) RB for replacing 1 grading capacitor on 89s352 9 Hours
Continuous
 
11-May-22 07:30 11-May-22 16:30 EPCOR RB ALTALINK - 1057L - RB @ (E657s - 89s) RB for replacing 1 grading capacitor on 89s352 9 Hours
Continuous
 
11-May-22 07:30 11-May-22 17:30 ALTALINK Outage 394s952 GOI, 394s 952 (394s Empress) integrate anti-island scheme 10 Hours
Daily
 
11-May-22 08:00 11-May-22 16:00 ENMAX Outage 65B240-D134 (ENMAX 65) breaker maintenance 8 Hours
Continuous
 
11-May-22 08:00 11-May-22 17:00 ALTALINK TE AltaLink Radio Tower 9495R to 9448R radio maintenance 9 Hours
Daily
 
11-May-22 08:00 11-May-22 18:00 ALTALINK TE AltaLink MPLS, 912L (63s Red Deer - 766s Nevis), 17s RTU/SCADA (17s Benalto), 534s RTU/SCADA (534s Eckville) upgrade MPLS node 10 Hours
Daily
 
11-May-22 08:00 11-May-22 12:00 ALTALINK Outage 33s 3 (33s Spray) maintenance 4 Hours
Daily
 
11-May-22 08:00 12-May-22 17:30 ALTALINK Outage 223s T3 (223s Strome) T3 maintenance and testing 1.4 Days
Continuous
 
11-May-22 08:00 11-May-22 12:00 SUNCOR TE 29EDD-3 29Edd-3 RTU/SCADA updates to SEL RTAC at the 29EDD-3 4 Hours
Continuous
 
11-May-22 08:00 12-May-22 16:00 ENMAX Outage 39.1TR (ENMAX 39) tapchanger maintenance, oil sampling MT, TC, bushing, check reversing switch 1.33 Days
Continuous
 
11-May-22 09:00 13-May-22 17:00 BCH Outage 5L98 (BCH Nicola - Vaseux Lake) flashed insulator replacements, BC maintenance does not affect the Alberta ATC 2.33 Days
Continuous
AB-BC
11-May-22 09:00 13-May-22 17:00 ALTALINK IO 5L98 (NIC-VAS) BCH - INFO flashed insulator replacements 2.33 Days
Continuous
 
11-May-22 10:00 13-May-22 13:00 CMH Outage MH69s2 T22 (MH69s2 North Industrial) PRC-005 - tapchanger maintenance 2.13 Days
Continuous
 
11-May-22 12:00 11-May-22 17:00 SUNCOR TE 29EDD-5 29Edd-5 RTU/SCADA updates to SEL RTAC at the 29EDD-5 5 Hours
Continuous
 
11-May-22 13:00 11-May-22 17:00 ALTALINK Outage 33s 6 (33s Spray) maintenance 4 Hours
Daily
 
11-May-22 13:00 12-May-22 17:30 ATCO TE ATC 803s Bullpound end to end testing with 801s 28.5 Hours
Continuous
 
11-May-22 23:00 12-May-22 03:00 ALTALINK Outage 62s 11 (62s Brazeau Plant) maintenance 4 Hours
Continuous
 
12-May-22 03:00 12-May-22 07:00 ALTALINK Outage 62s 12 (62s Brazeau Plant) maintenance 4 Hours
Daily
 
12-May-22 07:00 12-May-22 17:00 ALTALINK TE 244s Bowmanton 1035L - removing the B21/79 RAS relay from service to change settings and to accommodate end-to-end testing 10 Hours
Daily
 
12-May-22 07:00 12-May-22 17:00 ENMAX RB 11.82L (ENMAX 11 - ENMAX 14) tree trimming 10 Hours
Daily
 
12-May-22 07:30 12-May-22 17:30 ALTALINK Outage 760L (163s Amoco Empress - 394s Empress), 394s 760N (394s Empress) integrate anti-island scheme 10 Hours
Daily
 
12-May-22 08:00 12-May-22 16:00 ENMAX Outage 65B240-D135 (ENMAX 65) HV breaker maintenance 8 Hours
Continuous
 
12-May-22 08:00 12-May-22 18:00 ALTALINK TE 184s RTU/SCADA (184s Petro-Canada Edmonton), AltaLink TPR Outage upgrade MPLS node 10 Hours
Daily
 
12-May-22 08:00 15-May-22 17:00 ATCO RB 9L66 (847s Muskeg River - 849s Joslyn Creek) helicopter/ASTEP climbing inspections 3.38 Days
Daily
 
12-May-22 08:00 15-May-22 17:00 ATCO RB 9L32 (849s Joslyn Creek - 2005s Secord) helicpoter/ASTEP climbing inspection 3.38 Days
Daily
 
12-May-22 08:30 12-May-22 18:00 ATCO Outage 826s 902T (826s Marguerite Lake) inspection and maintenance 9.5 Hours
Continuous
 
12-May-22 08:30 12-May-22 17:00 ALTALINK TE 138s Windy Flats troubleshoot DNP/SCADA issue 8.5 Hours
Daily
 
12-May-22 08:30 12-May-22 17:00 ALTALINK TE 138s Windy Flats RTU/SCADA troubleshoot DNP/SCADA issue 8.5 Hours
Daily
 
12-May-22 09:00 12-May-22 15:00 ALTALINK TE 285s RTU/SCADA (285s East Camrose) revert RTU configuration settings back to original 6 Hours
Daily
 
12-May-22 18:00 14-May-22 17:00 ALTALINK IO 973L (39s Bickerdike - 310p Sundance) continued construction 1.96 Days
Continuous
 
12-May-22 18:00 13-Jun-22 06:00 ALTALINK IO 39s NEW 240kV Gear - GOI continued 240 kV breakers installation, continued 1168L/974L/973L construction 31.5 Days
Continuous
 
12-May-22 18:00 30-Oct-22 12:00 ALTALINK IO 1168L NEW (39s-Open Point 'F') - GOI 1135L continued construction 170.75 Days
Daily
 
12-May-22 18:00 29-Jun-22 17:00 ALTALINK IO 974L NEW (39s-Open Point 'Q') - GOI continued construction 47.96 Days
Continuous
 
13-May-22 07:00 19-Dec-22 17:00 ATCO Outage 730S 702, 730s 702 (730s Rycroft) SVC addition and 144 kv bus rebuild.
Electrical and commissioning Work including SVS (GC)
220.46 Days
Continuous
 
13-May-22 08:00 16-May-22 18:00 ALTALINK TE 9282R Fiber - TPR/RTU Relocate fiber due to county road move. Supervisory and TPR circuits rerouted to MPLS network in less than 50ms. 3.42 Days
Continuous
 
13-May-22 08:00 03-Jun-22 18:00 ENMAX Outage 3.82L., 3.82L (ENMAX 3 - ENMAX 8), 3B138-3.82 (ENMAX 3) LBCO contactors is working on behalf of the COC upgrading storm lines in the Sunnyside area 21.42 Days
Continuous
 

Prepared On:   2022-05-04   2:56:25 PM

This document and the information contained herein are based upon information and data which by their nature contain a degree of uncertainty and are subject to change. In addition, this document may contain information and data from public sources and/or third parties, which have been assumed to be accurate and complete and have not been verified. Accordingly, the Independent System Operator, operating as the Alberta Electric System Operator (the "AESO") makes no warranty, representation or guarantee, express or implied, with respect to this document or the information contained herein, including, but not limited to, any warranty, representation or guarantee of accuracy, completeness, timeliness, reliability, availability, absence of computer virus, non- infringement, merchantability or suitability for any purpose. Under no circumstances will the AESO, its members, officers, employees, contractors or agents, or any of their respective affiliates, be liable for any errors or omissions in, or any losses, damages or claims whatsoever, whether in contract, tort or otherwise, arising from use of or reliance upon, this document or any information contained herein.

© 2009 Alberta Electric System Operator. All rights reserved