Alberta Electric System Operator | |
Long Range Significant Transmission Outages for the period of 24 months starting 2022-01-15 | |
The table below contains the significant transmission outages submitted as tentative to the AESO. These Outages have not yet necessarily been approved, but are listed for awareness and coordination purposes. An Outage has been considered significant for this table if it meets any one (1) or more of the following criteria: |
|
|
|
Note: Where a transmission outage requires generation curtailments, the adjustments to generation will typically happen in the hours before the scheduled transmission outage and in the hour after the element is returned to service. | |
Previous Version | |
Download CSV | |
Owner | From | To | Duration | Element | Scheduled Activity | Affected Intertie |
---|---|---|---|---|---|---|
ATCO | 09-Dec-21 13:00 | 28-Jan-22 17:00 | Continuous |
50.17 Days
863s 902T (863s Paintearth) | forced outage and troubleshooting | |
ATCO | 10-Jan-22 08:00 | 30-Jan-22 17:00 | 20.38 Days
Continuous |
9L05 (809s Louise Creek - 813s Little Smoky) | Louise Creek rebuild project
wiring for 904/905BF relays, CT ratio changes, relay programming and functionality, commission control, alarms and status, blocking procedures for BF and bus protections |
|
EPCOR | 17-Jan-22 07:00 | 04-Mar-22 17:00 | 46.42 Days
Continuous |
Summerside S/S Tx1 bay outage, 657s T1 (657s Summerside) | Continuation of 240 kV ring re-configuration for South East Expansion Project.
Tx1 bay to be isolated for 240 kV bus re-configuration and installation of SU2405, SUDS11 and CVT's. Upon restoration Tx1 to be energized from SU2404 and a new isolation point of SUDS11 disconnect to remain open. |
|
ATCO | 17-Jan-22 09:00 | 24-Jan-22 12:00 | 7.13 Days
Continuous |
7L46, 7L46 (813s Little Smoky - 845s Big Mountain) | Changing Poles under Mitigation and Test and Treat | |
ATCO | 17-Jan-22 09:00 | 24-Jan-22 16:00 | 7.29 Days
Continuous |
7L80, 7L80 (733s Simonette - 740s H.R.Milner) | Changing Arms and Pole Repairs | |
ATCO | 17-Jan-22 10:00 | 21-Jan-22 17:30 | 4.31 Days
Continuous |
951S SVC, 951s SVC (951s Thickwood) | Warranty Repairs, annual inspections | |
BCH | 18-Jan-22 09:00 | 25-Jan-22 17:00 | 7.33 Days
Continuous |
1L274 (48s Pocaterra - Britt Creek) | transmission refurbishment | AB-BC |
ALTALINK | 19-Jan-22 08:00 | 23-Jan-22 18:00 | 4.42 Days
Continuous |
924L(102s - 356s) GOI, 924L (102s Langdon - 356s Milo) | Component replacements for 924L (Str' 1-299). D/C 927L. | |
ALTALINK | 20-Jan-22 08:00 | 22-Jan-22 17:00 | 2.38 Days
Continuous |
973L (39s-310p) - GOI, 973L (39s Bickerdike - 310p Sundance) | Install new 973L Str 2 in the existing line. Install new 1135L3 in the existing 973L line. Install conductor between new Str 2 and 1C to connect 973L in the new alignment. Remove conductor between new 973L2 and 1135L3. (P2032) | |
ALTALINK, EPCOR | 22-Jan-22 07:00 | 22-Jan-22 18:00 | 11 Hours
Daily |
920L (71s - E557s) - GOI, 920L (71s Lamoureux - 557s Castle Downs) | Maintenance on structure 48 | |
ALTALINK | 23-Jan-22 08:00 | 25-Jan-22 17:00 | 2.38 Days
Continuous |
974L (39s-310p) - GOI, 974L (39s Bickerdike - 310p Sundance) | Install new 974L Str 2 in the existing line. Install new 1084L Str 3 in the existing 974L line. Install conductor between new 974L Str 2 and 1C to connect 974L in the new alignment. Remove conductor between new 974L2 and 1084L3. (P2032) | |
EPCOR | 24-Jan-22 07:00 | 28-Jan-22 17:00 | 4.42 Days
Continuous |
LDS5 @ Lambton E806S, EP 803s L2403 (EP 803s Lambton), EP 803s L2405 (EP 803s Lambton), EP 803s T3 (EP 803s Lambton) | Lambton LDS5 LCR | |
ATCO, ALTALINK | 24-Jan-22 08:00 | 27-Jan-22 17:00 | 3.38 Days
Continuous |
7L129, 7L129 (526s Buffalo Creek - 7LA129 tap) | GOI 7L129D3 to 526S Buffalo Creek Reroute Transmission Line around water | |
ALTALINK | 25-Jan-22 07:00 | 26-Jan-22 18:00 | 1.46 Days
Continuous |
789L (898s Heart Lake - 1034s Margie), 789L (789L192A-A898s-602L1) - GOI | Scope of work includes maintenance on structure 78 | |
ATCO | 25-Jan-22 08:00 | 26-Jan-22 14:00 | 30 Hours
Continuous |
930S 700 BUS 5, 930S SVC, 930s SVC (930s Arcenciel) | Replace recalled RXTP Test Switches on 700BS5 Protection Circuits - 930S SVC unavailable | |
ALTALINK | 26-Jan-22 07:00 | 29-Jan-22 18:00 | 3.46 Days
Continuous |
39s29 - GOI, 39s 29 (39s Bickerdike) | Install A frame for future 974L and 1168L | |
ALTALINK | 27-Jan-22 07:45 | 27-Jan-22 16:15 | 8.5 Hours
Daily |
777L (48s-245s) OOS, 777L (48s Pocaterra - 245s Seebe) | de-energize 777L due to the PLC being out of service | AB-BC |
ALTALINK | 29-Jan-22 07:15 | 30-Jan-22 17:45 | 1.44 Days
Daily |
33s 2 (33s Spray) | Scope of work includes stringing new conductor on 113L from 33s Spray to Structure 2. GOI required due to limits of approach violation & cannot be done under reclosing. | |
EPCOR | 31-Jan-22 07:00 | 31-Jan-22 17:00 | 10 Hours
Continuous |
J2401 @ Jasper Terminal E805S, 805s J2401 (805s Jasper) | Jasper: P&C RAS Scheme Cut Over and Op-Checks | |
EPCOR | 31-Jan-22 07:00 | 04-Feb-22 17:00 | 4.42 Days
Continuous |
TX1 Zone @ Bellamy E814S, 814s T1 (814s Bellamy) | Bellamy 240kV SF6 Maintenance | |
EPCOR | 31-Jan-22 07:00 | 04-Feb-22 17:00 | 4.42 Days
Continuous |
TX3 @ Jasper Terminal E805S, 805s T3 (805s Jasper) | Jasper protection upgrade cutovers | |
EPCOR | 31-Jan-22 07:00 | 18-Feb-22 17:00 | 18.42 Days
Continuous |
Poundmaker S/S Tx4 bay outage | Continuation of 240 kV ring re-configuration for WETUP project. (P1649)
Outage will provide isolation for tie in of new Tx4. |
|
ATCO | 31-Jan-22 09:00 | 04-Feb-22 17:30 | 4.35 Days
Continuous |
2029S 500SST2, 2029s 1200SST2 (2029s Heathfield) | Breaker 10NA02-Q03 Investigate & Repair in LV2.
Low voltage isolations will occur in the 480 V rooms (in addition to using 502VRA). Alarms will occur when switching out the LV room, as the circuits change over from 1 source to the other. 500 kV breakers on transformer primary will be opened for a few moments while opening 502VRA. |
|
ATCO | 31-Jan-22 09:00 | 07-Feb-22 12:00 | 7.13 Days
Continuous |
7L46, 7L46 (813s Little Smoky - 845s Big Mountain) | Changing Poles under Mitigation and Test and treat | |
ATCO | 31-Jan-22 09:00 | 07-Feb-22 16:00 | 7.29 Days
Continuous |
7L80, 7L80 (733s Simonette - 740s H.R.Milner) | hanging Arms and Pole Repairs | |
ATCO | 31-Jan-22 09:00 | 20-Feb-22 17:00 | 20.33 Days
Continuous |
9L939 (77s Sagitawah - 809s Louise Creek) | Louise Creek Rebuild project
Wiring for 905/906BF relays. CT ratio changes. Relay programming. Commission control, alarms and status. Blocking procedures for BF and Bus protections. |
|
ATCO | 31-Jan-22 12:00 | 31-Jan-22 17:00 | 5 Hours
Continuous |
7L66, 7L66 (715s Leming Lake - 717s Ethel Lake) | Tie in structure 32 on 7L66. HOP on 7L91 | |
ALTALINK | 31-Jan-22 12:30 | 31-Jan-22 15:30 | 3 Hours
Continuous |
1201L (520s Bennett - BCH Cranbrook), 520s 552 (520s Benett) | urgent 520s552 gas sampling | AB-BC |
BHE Canada | 31-Jan-22 12:30 | 31-Jan-22 15:30 | 3 Hours
Continuous |
MATL (120s Picture Butte - Montana) | align with 1201L urgent outage | AB-MATL |
EPCOR | 01-Feb-22 07:00 | 01-Feb-22 17:00 | 10 Hours
Continuous |
J2407 @ Jasper Terminal E805S, 805s J2407 (805s Jasper) | Jasper: P&C RAS Scheme Cut Over and Op-Checks | |
ALTALINK | 02-Feb-22 07:00 | 06-Feb-22 18:00 | 4.46 Days
Continuous |
39s 240kV Bus 2 - GOI, 39s 240kV Bus 2 (39s Bickerdike) | Install new 973L, 974L and 1168L into A-frames at 39S as part of Cascade Project. New spans to 973L, 974L and 1168L A-frames to cross over 39S 240 kV bus 2. | |
ENMAX, ALTALINK | 02-Feb-22 08:00 | 04-Feb-22 16:00 | 2.33 Days
Continuous |
23.80L. 23.4TR, 23.80L (74s Janet - ENMAX 23) | 23 Sub 138kV DFR Equipment Upgrade | |
EPCOR | 07-Feb-22 07:00 | 11-Feb-22 17:00 | 4.42 Days
Continuous |
TX4 @ Jasper Terminal E805S, 805s T4 (805s Jasper) | Jasper protection upgrade cutovers | |
EPCOR | 07-Feb-22 07:00 | 11-Feb-22 17:00 | 4.42 Days
Continuous |
240BA Zone @ Bellamy E814S and Argyll Transfer Station E629S, 240BA2 (629s Argyll Transfer Station - 814s Bellamy) | Bellamy 240kV SF6 Maintenance | |
ENMAX, ALTALINK | 07-Feb-22 08:00 | 08-Feb-22 18:00 | 1.42 Days
Continuous |
832L. 10.1TR., 832L (ENMAX 10 - ENMAX 12) | HV SW Maint. SW81, SW82, SW83, MD-10.1TR | |
ALTALINK | 07-Feb-22 08:30 | 07-Feb-22 13:30 | 5 Hours
Daily |
320p400 (SSTA & SSTB) - GOI, 400L (320p Keephills - 320p Keephills) | 1st trip and PRC5 maintenance; New C60 breaker fail trip testing on breaker 1552 (320p400) | |
ALTALINK, ENMAX | 08-Feb-22 07:15 | 09-Feb-22 17:45 | 1.44 Days
Continuous |
918L (281s - 162s) GOI, 918L (281s Johnson - ENMAX 162) | Fire Mitigation (Str 797, 810, 813, 818, 825, 835) | |
ALTALINK | 08-Feb-22 11:45 | 08-Feb-22 18:15 | 6.5 Hours
Daily |
887L (48s) OOS, 887L (48s Pocaterra - BCH Britt Creek) | Open 887L for 266s MPLS upgrade (coincides with 278560). Work is coordinated with BC 887L outage. | AB-BC |
ENMAX, ALTALINK | 09-Feb-22 08:00 | 10-Feb-22 18:00 | 1.42 Days
Continuous |
693L. 10.2TR., 693L (42s Sarcee - ENMAX 10) | HV SW Maint. SW84, SW85, SW86, MD-10.2TR | |
ALTALINK | 09-Feb-22 09:00 | 16-Feb-22 18:00 | 7.38 Days
Continuous |
927L(102s - 356) GOI, 927L (102s Langdon - 356s Milo) | Component replacements for 927L (Str' 1A-302). D/C 924L. | |
ALTALINK, TRANSALTA | 10-Feb-22 07:30 | 10-Feb-22 16:30 | 9 Hours
Continuous |
59s 138kV Bus (T1 & 616L) - GOI, 59s T1 (59s Peigan), 616L (59s Peigan - 616AL tap) | repair PT oil level glass | |
EPCOR | 14-Feb-22 07:00 | 18-Feb-22 17:00 | 4.42 Days
Continuous |
805s T3 (805s Jasper), TX3 @ Jasper Terminal E805S | 15kV BUS PT Replacement | |
EPCOR | 14-Feb-22 07:00 | 18-Feb-22 17:00 | 4.42 Days
Continuous |
TX2 Zone @ Bellamy E814S, 814s T2 (814s Bellamy) | Bellamy 240kV SF6 Maintenance | |
ALTALINK | 14-Feb-22 08:00 | 23-Feb-22 18:30 | 9.44 Days
Continuous |
39s 138kV B2, T2, 240B2, & 973L - GOI, 39s T2 (39s Bickerdike), 973L (39s Bickerdike - 310p Sundance) | Complete relocation of 973L, Complete connection of 1135L Close open point ‘K’,Complete breaker fail, T2 trip testing from/to 39s452, 39s852, 39s1152, 39s29, 39s1752 (P2032) | |
ATCO | 14-Feb-22 09:00 | 21-Feb-22 12:00 | 7.13 Days
Continuous |
7L46, 7L46 (813s Little Smoky - 845s Big Mountain) | Changing Poles under Mitigation and Test N treat | |
ATCO | 14-Feb-22 09:00 | 21-Feb-22 14:30 | 7.23 Days
Continuous |
7L80, 7L80 (733s Simonette - 740s H.R.Milner) | hanging Arms and Pole Repairs | |
ALTALINK | 22-Feb-22 12:00 | 22-Feb-22 18:00 | 6 Hours
Daily |
702L (A757s - 137s) - GOI, 702L (137s Sedgewick - 757s Battle River) | Fire mitigation on Structures #113, 116 & 117 | |
ALTALINK | 24-Feb-22 07:00 | 24-Feb-22 18:00 | 11 Hours
Continuous |
310p 240kV B Bus - GOI, 310p 240kV Bus B (310p Sundance) | Scope of work includes replacing insulators on structures 310P and 1 on 1046L, we require a GOI on the B bus in order to safely handle the conductor running over the bus work as well as safely set up the equipment inside the 310p Sundance Substation. Required due to proximity for 1046L GOI See also SAP: 277114 | |
ALTALINK | 24-Feb-22 07:00 | 27-Feb-22 18:00 | 3.46 Days
Continuous |
1046L (310p-338s) - GOI, 1046L (310p Sundance - 338s Cherhill) | Scope of work includes maintenance on structures 310p, 1 ,21, 22, 23, 24, 25, 26, 55, 57, 74, 75, 80, 89, 90, 91, 102, 110, 111, 120 and 121. See also 310p 240kV Bus SAP: 277113 Required due to proximity to 1046L and also SAP: 277115 902L R/B required due to proximity to 1046L | |
EPCOR | 28-Feb-22 07:00 | 04-Mar-22 17:00 | 4.42 Days
Continuous |
805s T1 (805s Jasper), TX1 @ Jasper Terminal E805S | Surge Arrestor Replacement | |
EPCOR | 28-Feb-22 07:00 | 04-Mar-22 17:00 | 4.42 Days
Continuous |
240BA2 Zone @ Bellamy E814S and Argyll Transfer Station E629S, 240BA2 (629s Argyll Transfer Station - 814s Bellamy) | Bellamy 240kV SF6 Maintenance | |
ALTALINK | 28-Feb-22 07:30 | 01-Mar-22 17:30 | 1.42 Days
Continuous |
902L (310p-19s) - GOI, 902L (19s Wabamun - 310p Sundance) | Scope of work includes installing bird divertors on the OHSW on structures 36, 37, 38, 39, 40 and 41. See also 1046L Recloser block SAP: 277117 required due to proximity to 902L | |
ATCO | 28-Feb-22 09:00 | 07-Mar-22 16:00 | 7.29 Days
Continuous |
7L80, 7L80 (733s Simonette - 740s H.R.Milner) | Changing Arms and Pole Repairs | |
ALTALINK, ENMAX | 28-Feb-22 12:30 | 28-Feb-22 17:30 | 5 Hours
Daily |
42s693 (693L) - GOI, 693L (42s Sarcee - ENMAX 10) | Techs require a breaker outage on 42s693 Breaker to add in wiring for trip coil monitoring on the following relay: 96/1452 (s693) | |
ALTALINK | 01-Mar-22 07:00 | 11-Mar-22 18:00 | 10.46 Days
Continuous |
927L(102s - 356) GOI, 927L (102s Langdon - 356s Milo) | Component replacements for 927L (Str' 1A-302). D/C 924L. | |
ALTALINK | 01-Mar-22 07:00 | 14-Mar-22 18:00 | 13.42 Days
Continuous |
39s 240B1, 974L, 1084L, 1168L - GOI | Complete relocation of 974L (P2032) | |
ATCO, ALTALINK | 01-Mar-22 08:00 | 03-Mar-22 18:00 | 2.42 Days
Continuous |
7L65, 7L77, 7L65 (709s Vegreville - 710s Vermilion), 7L77 (395s North Holden - 709s Vegreville) | String over 7L65 and 7L77 | |
ENMAX, ALTALINK | 02-Mar-22 08:00 | 04-Mar-22 18:00 | 2.42 Days
Continuous |
23.80L. 23.4TR, 23.80L (74s Janet - ENMAX 23) | HV SW Maint. SW84, SW88, SW87, MD-23.4TR | |
ATCO | 03-Mar-22 08:00 | 04-Mar-22 17:00 | 1.38 Days
Continuous |
7L03, 7L03 (749s Flyingshot Lake - 7L09 tap) | Relay work for the Northstone Project | |
EPCOR, ALTALINK | 07-Mar-22 07:00 | 01-Apr-22 17:00 | 25.38 Days
Continuous |
Summerside S/S Tx2 bay outage, 1057L bay outage and SU2405 bay outage, 657s T2 (657s Summerside), 1057L (89s Ellerslie - 657s Summerside) | Continuation of 240 kV ring re-configuration for South East Expansion Project.
Outage will provide isolation for HV bus re work and SUDS12 installation. |
|
ATCO | 07-Mar-22 08:00 | 07-Mar-22 17:00 | 9 Hours
Continuous |
7L69, 7L69 (731s Elmworth - 815s Goodfare) | 731s Elmworth project | |
ALTALINK | 07-Mar-22 09:30 | 10-Mar-22 18:00 | 3.35 Days
Continuous |
410s T1, 240kV Bus 1, 138kV Bus 1 – GOI, 410s 138kV Bus 1 (410s Josephburg), 410s 240kV Bus 1 (410s Josephburg), 410s T1 (410s Josephburg) | Migration of control and status of MODs 410s12 and 410s15. Functioning of these devices will be required. Migration of alarms, metering and controls to protections T1/A87/50/51, T1/B87/50/51, 240B1/A87, 240B1/B87, 138B1/A87, and 138B1/B87. Migration and function testing of CVT3 and VT5 Alarms | |
ATCO | 08-Mar-22 08:00 | 08-Mar-22 17:00 | 9 Hours
Continuous |
7L22, 7L22 (790s Poplar Hill - 7L88 tap), 7L22 (811s Clairmont Lake - 7L88 tap) | 731s Elmworth project | |
ENMAX, ALTALINK | 08-Mar-22 08:00 | 08-Mar-22 18:00 | 10 Hours
Continuous |
24.81L. 24.83L. 24.1TR, 24.81L (ENMAX 24 - ENMAX 31), 24.83L (74s Janet - ENMAX 24) | HV SW Maint. MD-24.1TR | |
ALTALINK, Lethbridge | 08-Mar-22 09:30 | 08-Mar-22 13:30 | 4 Hours
Daily |
370s667 (667L) - GOI, 667L (146s Lethbridge MacDonald - 370s North Lethbridge) | 1st trip and PRC5 maintenance | |
ALTALINK | 08-Mar-22 13:30 | 08-Mar-22 17:00 | 3.5 Hours
Daily |
370s2252 (T5) - GOI, 370s T5 (370s North Lethbridge) | 1st trip and PRC5 maintenance | |
ATCO, ALTALINK | 09-Mar-22 07:00 | 10-Mar-22 17:00 | 1.42 Days
Continuous |
7L77, 7L77 (395s North Holden - 709s Vegreville) | 7L65 Rebuild Project | |
ATCO | 09-Mar-22 08:00 | 09-Mar-22 17:00 | 9 Hours
Continuous |
7L07, 7L07 (790s Poplar Hill - 815s Goodfare) | 731s Elmworth project | |
ALTALINK | 12-Mar-22 07:00 | 12-Mar-22 18:00 | 11 Hours
Daily |
463L (15s - 463L46) - GOI, 463L (15s Fort Macleod - 463L46) | Fire mitigation on Structure #224 | |
ATCO | 14-Mar-22 08:00 | 15-Mar-22 17:00 | 1.38 Days
Continuous |
766S 901T, 766s 901T (766s Nevis) | Sharp Hills Project
Installation of new RAS panel at 766S Nevis |
|
ATCO, ALTALINK | 14-Mar-22 08:00 | 17-Mar-22 17:00 | 3.38 Days
Continuous |
7L129, 7L129 (526s Buffalo Creek - 7LA129 tap) | GOI 7L129D3 to 526S Buffalo Creek Reroute Transmission Line around water | |
ATCO | 14-Mar-22 08:00 | 03-Apr-22 16:00 | 20.33 Days
Continuous |
951S 900BS2, 951S 908, 951S 903, 951S 906, 951S 907 | 951S construction for 9L162 & 9L193 addition
AESO should be notified of any changes to below workplan: Isolation pts: 908B,909A Impact: BKR 908 OOS Scope of work: Demo bus & install 909A & 909B March 31, 2022 – April 01, 2022 Expand to isolation pts:903B, 906B,908B Impact: BKR 903,BKR 906, 900BS2 OOS Scope of work: Make connections to 909A & 912A |
|
ATCO | 14-Mar-22 09:00 | 21-Mar-22 16:00 | 7.29 Days
Continuous |
7L80, 7L80 (733s Simonette - 740s H.R.Milner) | Changing Arms and Pole Repairs | |
ALTALINK | 14-Mar-22 09:30 | 17-Mar-22 18:00 | 3.35 Days
Continuous |
410s T2, 240kV Bus 2, 138kV Bus 2 – GOI, 410s 138kV Bus 2 (410s Josephburg), 410s 240kV Bus 2 (410s Josephburg), 410s T2 (410s Josephburg) | Migration of control and status of MODs 410s14 and 410s16. Functioning of these devices will be required. Migration of alarms, metering and controls to protections T2/A87/50/51, T2/B87/50/51, 240B2/A87, 240B2/B87, 138B2/A87, and 138B2/B87. Migration and function testing of CVT4 and VT6 Alarms | |
ALTALINK | 14-Mar-22 12:00 | 15-Mar-22 18:00 | 30 Hours
Continuous |
28s 138kV Bus 2 (827L/853L & T2) - GOI, 28s T2 (28s West Brooks), 827L (28s West Brooks - 121s Brooks), 853L (28s West Brooks - 853AL tap) | 28s27 hot switch, 28s827L line polymer dead end damage, 28s827E motor mech. | |
ALTALINK | 14-Mar-22 12:00 | 17-Mar-22 18:00 | 3.25 Days
Continuous |
1206L (89s - 12s) - GOI, 1206L (12s Heartland - 89s Ellerslie) | Component Replacements on 1206L ( Structure Range 2-193) | |
ALTALINK, ATCO | 14-Mar-22 12:00 | 17-Mar-22 18:00 | 3.25 Days
Continuous |
7L230(A743s-234s-69s) and 234s888 GOI, 7L230 (69s North Barrhead - 7L230 tap), 7L230 (743s Sarah Lake - 7L230 tap), 888AL (234s Fort Assiniboine - 7L230 tap) | 1st trip & full maintenance, adjust 234s1. | |
ALTALINK | 15-Mar-22 07:00 | 20-Mar-22 18:30 | 5.48 Days
Continuous |
602s745N (745L) - GOI, 745L (602s Cold Creek - 745AL tap) | Breaker outage to replace the 745L line protections, and install a new breaker fail protection for 745L. | |
ATCO | 16-Mar-22 09:00 | 17-Mar-22 16:00 | 31 Hours
Continuous |
766S 901T, 766s 901T (766s Nevis) | Install new 9S4 Nevis RAS panel. Outage required on 901T for new CT input wiring. | |
ALTALINK | 21-Mar-22 09:30 | 22-Mar-22 18:00 | 1.35 Days
Continuous |
1027L (410s-430s) – GOI, 1027L (410s Josephburg - 430s Ursus) | Migration of alarms, status and control of breakers 410s152 and 410s252. Migration of control and status of MOD 410s1027. Functioning of these devices will be required. Migration of alarms, metering and controls to protections L1/A21/79 and L1/B21. Migration and function testing of CVT1 Alarms | |
ALTALINK | 21-Mar-22 12:00 | 21-Mar-22 15:30 | 3.5 Hours
Daily |
61s202X (202L) – GOI, 202L (61s Lodgepole - 62s Brazeau) | Breaker maintenance including 1st trip testing. | |
ALTALINK | 21-Mar-22 12:00 | 24-Mar-22 18:00 | 3.25 Days
Continuous |
1206L (89s - 12s) - GOI, 1206L (12s Heartland - 89s Ellerslie) | Component Replacements on 1206L ( Structure Range 2-193) | |
ALTALINK | 21-Mar-22 12:15 | 25-Mar-22 17:45 | 4.23 Days
Continuous |
225s15 (CHD-1) GOI, 225s 15 (225s Magrath) | Replacing A&B line protection during outage | |
ALTALINK | 21-Mar-22 14:00 | 21-Mar-22 17:00 | 3 Hours
Daily |
602s847 (847L) - Advice, 847L (602s Cold Creek - 847AL tap) | Isolated breaker, complete wiring of trips from new 602s745N breaker fail protection and complete functional trip test | |
ALTALINK | 22-Mar-22 08:30 | 22-Mar-22 11:30 | 3 Hours
Daily |
62s201 (801L) – GOI, 801L (62s Brazeau - 294s Brazeau Outlet Works) | Breaker maintenance including 1st trip testing. Replace tank heater | |
ALTALINK | 22-Mar-22 08:30 | 22-Mar-22 13:00 | 4.5 Hours
Daily |
17s10 - GOI, 17s 10 (17s Benalto) | 1st trip and PRC5 maintenance | |
ALTALINK | 22-Mar-22 08:30 | 22-Mar-22 17:30 | 9 Hours
Daily |
103s21 (613L) GOI, 613L (103s Goose Lake - 396s Pincher Creek) | 138kV Switch Maintenance | AB-BC |
ALTALINK | 22-Mar-22 12:30 | 22-Mar-22 15:30 | 3 Hours
Daily |
62s202 (202L) – GOI, 202L (61s Lodgepole - 62s Brazeau) | Breaker maintenance including 1st trip testing. | |
ALTALINK | 22-Mar-22 13:00 | 22-Mar-22 17:30 | 4.5 Hours
Daily |
17s8 - GOI, 17s 8 (17s Benalto) | 1st trip and PRC5 maintenance | |
ALTALINK | 23-Mar-22 07:00 | 24-Mar-22 18:00 | 1.46 Days
Continuous |
1120L (410s-108s) – GOI, 1120L (108s Amelia - 410s Josephburg) | Migration of alarms, status and control of breakers 410s352 and 410s452. Migration of control and status of MOD 410s1120. Functioning of these devices will be required. Migration of alarms, metering and controls to protections L1/A21 and L1/B21/79. Migration and function testing of CVT2 Alarms | |
ALTALINK | 23-Mar-22 08:30 | 23-Mar-22 17:30 | 9 Hours
Daily |
103s994 (994L) GOI, 994L (103s Goose Lake - 312s Fidler) | 240kV Switch Maintenance | |
ALTALINK | 24-Mar-22 08:30 | 24-Mar-22 17:30 | 9 Hours
Daily |
103s14 (955L) GOI, 955L (59s Peigan - 103s Goose Lake) | 240kV Switch Maintenance | |
EPCOR, ALTALINK | 28-Mar-22 07:00 | 01-Apr-22 17:00 | 4.42 Days
Continuous |
Castledowns 920LE Bay @ Castledowns E557S, 920L (71s Lamoureux - 557s Castle Downs) | Castledowns 920LE Bay Op-Checks, P&C Maintenance | |
ATCO | 28-Mar-22 09:00 | 04-Apr-22 16:00 | 7.29 Days
Continuous |
7L80, 7L80 (733s Simonette - 740s H.R.Milner) | Changing Arms and Pole Repairs | |
ALTALINK | 28-Mar-22 12:00 | 31-Mar-22 18:00 | 3.25 Days
Continuous |
1212L (89s - 12s) - GOI, 1212L (12s Heartland - 89s Ellerslie) | Component Replacements on 1212L ( Structure Range 20-194) | |
EPCOR, ALTALINK | 04-Apr-22 07:00 | 08-Apr-22 17:00 | 4.42 Days
Continuous |
Castledowns 920LW Bay @ Castlesdowns E557S, 920L (37s North Calder - 557s Castle Downs) | Castledowns 920LW Bay Op-Checks, P&C Maintenance | |
EPCOR | 04-Apr-22 07:00 | 08-Apr-22 17:00 | 4.42 Days
Continuous |
TX3 @ Jasper Terminal E805S, 805s T3 (805s Jasper) | Jasper protection upgrade cutovers and **15kV BUS 3 PT Replacement** | |
EPCOR | 04-Apr-22 07:00 | 09-Apr-22 17:00 | 5.42 Days
Continuous |
D2403 @ Dome E665S, 665s D2403 (665s Dome) | Dome D2403 Bay Doble and Breaker Maintenance | |
SUNCOR | 04-Apr-22 08:00 | 07-Apr-22 18:00 | 3.42 Days
Continuous |
29EDD-65 Edd65Sub | 29EDD65 ;29PT-259 SYSTEM;PM 5y line 29PL9-12 | |
SUNCOR | 04-Apr-22 08:00 | 07-Apr-22 18:00 | 3.42 Days
Continuous |
29EDD-65 Edd65Sub | 29PL9-13; 29PT-249;MTCE & TEST;(A)5Y | |
SUNCOR | 04-Apr-22 08:00 | 09-Apr-22 18:00 | 5.42 Days
Continuous |
29PL9-12, 29PL9-12 (29EDD-34 - 29EDD-65) | 29EDD65 ;29PT-259 SYSTEM;PM 5y line 29PL9-12 | |
ALTALINK | 04-Apr-22 11:00 | 08-Apr-22 19:00 | 4.33 Days
Continuous |
310P 240kV B&C Bus, T30, T36&974L - GOI, 310p 240kV Bus C (310p Sundance), 310p 240kV Bus B (310p Sundance), 310p T30 (310p Sundance), 310p T36 (310p Sundance), 974L (39s Bickerdike - 310p Sundance) | First trip on 310P2552, 310P2252, 310P1952, 310P1352, 310P1052, 310P752, 310P452, 310P152, & 310P2852. Replace 310P1A and 310P1B. Maintain 240kV bus switches. Replace T36 25kV bushing. Replace 310P252 grading caps & maintenance. | |
ALTALINK | 04-Apr-22 12:00 | 07-Apr-22 18:00 | 3.25 Days
Continuous |
1212L (89s - 12s) - GOI, 1212L (12s Heartland - 89s Ellerslie) | Component Replacements on 1212L ( Structure Range 20-194) | |
ALTALINK, Lethbridge | 05-Apr-22 07:30 | 06-Apr-22 16:00 | 1.35 Days
Continuous |
725L (674s Lethbridge Bowron - 725BL tap), 725L (15s Fort MacLeod - 725BL tap) | 725LW Line Maintenance, 674s Switch Maintenance | |
ALTALINK, Lethbridge | 05-Apr-22 07:30 | 06-Apr-22 16:00 | 1.35 Days
Continuous |
725L (111s Coalbanks - 725AL tap), 725L (674s Lethbridge Bowron - 725AL tap) | 725LE Line Maintenance, 674s Switch Maintenance | |
ATCO | 09-Apr-22 08:00 | 15-Apr-22 17:00 | 6.38 Days
Continuous |
9L46, 9L46 (932s Pemukan - 959s Lanfine) | Sharp Hills Project
Outage for Line termination to 363S Sedalia on 9L46 |
|
EPCOR | 11-Apr-22 07:00 | 11-Apr-22 17:00 | 10 Hours
Continuous |
CDDS7 @ Castledowns E557S, 557s T2 (557s Castle Downs) | Castledows CDDS7 Disconnect Maintenance | |
EPCOR | 11-Apr-22 07:00 | 15-Apr-22 17:00 | 4.42 Days
Continuous |
TX4 @ Jasper Terminal E805S, 805s T4 (805s Jasper) | Jasper protection upgrade cutovers | |
ATCO | 11-Apr-22 08:00 | 14-Apr-22 16:00 | 3.33 Days
Continuous |
951S 900BS1 | 951S construction for 240kv expansion - 9L162 & 9L193 addition
Connect 910A to 900BS1 Impact: 900BS1 OOS, BKR 901 OOS, BKR 904 OOS, BKR 907 OOS, 920C OOS |
|
ALTALINK | 11-Apr-22 11:00 | 13-Apr-22 17:00 | 2.25 Days
Continuous |
67s T1 (Tx18666) GOI, 67s T1 (67s Stirling) | Perform maintenance , doble, SFRA, AMP replacement | |
ALTALINK | 11-Apr-22 12:30 | 13-Apr-22 17:30 | 2.21 Days
Daily |
37s82 GOI, 37s 82 (37s North Calder) | First trip and PRC5 maintenance, replace AC receptacle in cabinet | |
ALTALINK | 12-Apr-22 07:00 | 19-Apr-22 16:00 | 7.38 Days
Continuous |
39s T1, 138kV B1, 240B1, 974L, 1084L, 1168L, 1, 39s T1 (39s Bickerdike), 974L (39s Bickerdike - 310p Sundance), 39s 138kV Bus 1 (39s Bickerdike), 39s 240kV Bus 1 (39s Bickerdike) | Complete relocation of 974L (close open point ‘L’) Terminate 1084L, Terminate 1168L (close open point ‘M’) Complete breaker fail, T1 trip testing from/to 39s1552, 39s26, 39s33, 39s38, 39s152, 39s1052 | |
ATCO | 12-Apr-22 08:00 | 15-Apr-22 17:00 | 3.38 Days
Continuous |
801S 901T, 801s 901T (801s Anderson) | WHEATLAND PROJECT
801S Anderson Sub Protection Upgrade |
|
SUNCOR | 13-Apr-22 08:00 | 19-Apr-22 18:00 | 6.42 Days
Continuous |
29EDD-71 | 29EDD71;29PT-430;PM 5y | |
EPCOR, ALTALINK | 19-Apr-22 09:30 | 23-Apr-22 17:00 | 4.31 Days
Continuous |
1059L and TX1 @ East Industrial E52S and East Edmonton 38S, 1059L (38s East Edmonton - EP 803s Lambton) | East Industrial 1059L CT/Arrestor/TX1 Doble, EDS1 Disconnect Maintenance | |
ALTALINK | 19-Apr-22 11:30 | 21-Apr-22 17:30 | 2.25 Days
Continuous |
138s1652 (R1) GOI, 138s 1652 (138s Windy Flats) | Maintenance, doble (R1). 138kV Breaker Maintenance (138s1652) | |
ATCO | 20-Apr-22 08:00 | 22-Apr-22 16:00 | 2.33 Days
Continuous |
9L74, 888S 905, 888S 906, 9L74 (888s Dover - 960s Birchwood Creek) | Cut in new CT and PT circuit extension to the new RAS relays, complete SCADA terminations. | |
ALTALINK, ENMAX | 21-Apr-22 08:00 | 21-Apr-22 17:30 | 9.5 Hours
Daily |
74s30 (23.80L) - GOI, 23.80L (74s Janet - ENMAX 23) | Repair switch | |
ATCO | 24-Apr-22 08:00 | 27-Apr-22 17:00 | 3.38 Days
Continuous |
766S 901T, 766s 901T (766s Nevis) | WHEATLAND PROJECT
766S Nevis Sub Protection Upgrade |
|
EPCOR | 25-Apr-22 07:00 | 26-Apr-22 17:00 | 1.42 Days
Continuous |
BDS18 and Bellamy TX2 @ Bellamy E814S and Rossdale, 814s T2 (814s Bellamy) | BDS18 Repair/Maintenance, Doble Bellamy TX2 PT | |
EPCOR | 25-Apr-22 07:00 | 29-Apr-22 17:00 | 4.42 Days
Continuous |
1098L, J2407, PM2401, PM2402 @ Jasper Terminal E805S and Poundmaker, 1098L (805s Jasper - Poundmaker) | Jasper 1098L CVT LCR and Poundmaker/Jasper 1098L Zone Doble and PMDS2/PMDS3/PMDS9 Disconnect Maintenance | |
ALTALINK | 25-Apr-22 11:30 | 28-Apr-22 17:00 | 3.23 Days
Continuous |
74s2452 GOI, 74s 2452 (74s Janet) | Perform maintenance on s2452 (PRC5) | |
ALTALINK | 25-Apr-22 12:00 | 28-Apr-22 18:00 | 3.25 Days
Continuous |
288s T2 TX18900 - GOI, 288s T2 (288s Wolf Creek) | First trip PRC5 maintenance, fix oil leaks, doble | |
EPCOR | 02-May-22 07:00 | 06-May-22 17:00 | 4.42 Days
Continuous |
1203 Bay @ Genesee 330P, 330p 1203 (330p Genesee) | Genesee 1203 Bay CT Doble, Breaker Maintenance | |
ATCO | 02-May-22 08:00 | 15-May-22 00:17 | 12.68 Days
Continuous |
7L01, 7L01 (813s Little Smoky - 881s Sturgeon) | 813S Little Smoky Rebuild
BKR 711 and 712 P&C wiring, remove old panel 8G, set up new panel 7P2, prep work Relay programming and functionality Commission control, alarms and status |
|
EPCOR, ALTALINK | 02-May-22 09:30 | 06-May-22 17:00 | 4.31 Days
Continuous |
908L and TX2 @ East Industrial E52S and Ellerslie 89S and East Edmonton 38S, 908L (38s East Edmonton - 89s Ellerslie) | East Industrial 908L CVT/Arrestor/TX2 Doble and EDS2/E2T2 Maintenance | |
ALTALINK | 03-May-22 09:30 | 05-May-22 17:30 | 2.33 Days
Continuous |
138s1752 (R2) GOI, 138s 1752 (138s Windy Flats) | Maintenance, doble (R1). 138kV Breaker Maintenance (138s1652) | |
SUNCOR | 04-May-22 06:00 | 17-May-22 18:00 | 13.5 Days
Continuous |
29EDD-5 29Edd-5 | 29EDD-5 / 29PL6-7 Phase A Repair
Install RFCT for 2PL6-7 at 30EDD-1 |
|
EPCOR | 09-May-22 07:00 | 13-May-22 17:00 | 4.42 Days
Continuous |
1206 Bay @ Genesee 330P, 330p 1206 (330p Genesee) | Genesee 1206 Bay CT Doble, Breaker Maintenance | |
EPCOR | 09-May-22 07:00 | 13-May-22 17:00 | 4.42 Days
Continuous |
TX1 @ Jasper Terminal E805S, 805s T1 (805s Jasper) | Surge Arrestor Replacement | |
ATCO | 11-May-22 07:00 | 11-May-22 17:00 | 10 Hours
Continuous |
7L68, 7L68 (730s Rycroft - 811s Clairmont Lake) | SVC addition and 144 kv bus rebuild.
Install new bypass switch 7L68D3 |
|
EPCOR | 16-May-22 07:00 | 20-May-22 17:00 | 4.42 Days
Continuous |
1207 Bay @ Genesee 330P, 330p 1207 (330p Genesee) | Genesee 1207 Bay CT Doble, Breaker Maintenance | |
EPCOR | 16-May-22 07:00 | 03-Jun-22 17:00 | 18.42 Days
Continuous |
240BA2 @ Bellamy E814S and Argyll Transfer Station E629S, 240BA2 (629s Argyll Transfer Station - 814s Bellamy) | BA2 Oil Degassing | |
ATCO | 16-May-22 08:00 | 29-May-22 17:00 | 13.38 Days
Continuous |
7L46, 7L46 (813s Little Smoky - 845s Big Mountain) | 813S Little Smoky Rebuild
Replace 705CT and 706CT junction boxes 705, 706 P&C wiring, prep work Relay programming and functionality Commission control, alarms and status |
|
ATCO | 16-May-22 09:00 | 23-May-22 17:30 | 7.35 Days
Continuous |
790S 704, 790S 703T | Replace 1 phase on 790S 704, 790S 703T maintenance | |
SUNCOR | 23-May-22 06:00 | 29-May-22 18:00 | 6.5 Days
Continuous |
29PL9-12, 29PL9-12 (29EDD-34 - 29EDD-65) | 29EDD34;29PL9-12 SYSTEM;PM 5y,10y | |
SUNCOR | 30-May-22 06:00 | 05-Jun-22 18:00 | 6.5 Days
Continuous |
29PL9-13, 29PL9-13 (29EDD-34 - 29EDD-65) | 29EDD34;29PL9-13 SYSTEM;PM 5y,10y | |
ATCO | 30-May-22 08:00 | 12-Jun-22 17:00 | 13.38 Days
Continuous |
7L45, 7L45 (813s Little Smoky - 845s Big Mountain) | 813S Little Smoky Rebuild813S Little Smoky Rebuild
BKR 703 and 704 P&C wiring, remove old panel 7G, set up new panel 7P4, prep work Relay programming and functionality Commission control, alarms and status |
|
EPCOR, ALTALINK | 30-May-22 09:30 | 03-Jun-22 17:00 | 4.31 Days
Continuous |
1209L, 1208/1209 Bay @ Genesee 330P and Ellerslie 89S, 1209L (89s Ellerslie - 330p Genesee) | Genesee 1209L Arrestor Doble, 1208/1209 Breaker Maintenance and Doble, 1208B/1209A/1209LLD Disconnect Maintenance | |
EPCOR | 06-Jun-22 07:00 | 10-Jun-22 17:00 | 4.42 Days
Continuous |
12TC1 Zone @ Genesee 330P, 330P 12TC1 (330p Genesee) | Genesee 12TC1 Zone Doble | |
EPCOR | 06-Jun-22 07:00 | 11-Jun-22 17:00 | 5.42 Days
Continuous |
J2404 Bay @ Jasper Terminal E805S, 805s J2404 (805s Jasper) | Jasper J2404 Bay Doble and Breaker Maintenance | |
EPCOR | 13-Jun-22 07:00 | 17-Jun-22 17:00 | 4.42 Days
Continuous |
12TC2 Zone @ Genesee 330P, 330P 12TC2 (330p Genesee) | Genesee 12TC2 Zone Doble | |
ATCO | 13-Jun-22 08:00 | 26-Jun-22 17:00 | 13.38 Days
Continuous |
7L54, 7L54 (794s Valleyview - 813s Little Smoky) | 813S Little Smoky Rebuild813S Little Smoky Rebuild
BKR 703 and 704 P&C wiring, remove old panel 7G, set up new panel 7P4, prep work Relay programming and functionality Commission control, alarms and status |
|
ATCO | 15-Jun-22 07:00 | 28-Jul-22 17:00 | 43.42 Days
Continuous |
972S 900BS2, 9L16, 9L16 (755s Cordel - 972s Tinchebray), 972s 240kV Bus 900BS2 (972s Tinchebray) | Outage on 907B and 908A for the installation and commissioning of 907 and 907CT | |
SUNCOR | 20-Jun-22 06:00 | 26-Jun-22 18:00 | 6.5 Days
Continuous |
30EDD-2 | 30EDD2;30PK-10 SYSTEM;PM 5y | |
EPCOR, ALTALINK | 20-Jun-22 07:00 | 20-Jun-22 17:00 | 10 Hours
Continuous |
1044L @ Jasper Terminal E805S and Petrolia E816S, 1044L (805s Jasper - 816s Petrolia) | Jasper 1044L Line Arrestor Doble | |
EPCOR | 27-Jun-22 07:00 | 29-Jun-22 17:00 | 2.42 Days
Continuous |
C2408 Bay @ Cloverbar E987S, 987s C2408 (987s Clover Bar), 987s T2 (987s Clover Bar) | Cloverbar C2408 Bay CVT Doble and Breaker Maintenance | |
EPCOR | 27-Jun-22 07:00 | 30-Jun-22 17:00 | 3.42 Days
Continuous |
500kV BUS1 @ Genesee 330P, 330p 500kV Bus 1 (330p Genesee) | Genesee 1201A/1204A/1207A/12TC1D/12TC1GS Disconnect Maintenance | |
ATCO | 29-Jun-22 07:00 | 01-Jul-22 17:00 | 2.42 Days
Continuous |
766S 701, 766S 901T, 766s 901T (766s Nevis), 766s 701 (766s Nevis) | RAS modifications for the Pattern Lanfine WAGF project | |
EPCOR | 04-Jul-22 07:00 | 08-Jul-22 17:00 | 4.42 Days
Continuous |
C2406 Bay @ Cloverbar E987S, 987s C2406 (987s Clover Bar) | Cloverbar C2406 CT/Breaker Doble and Breaker Maintenance | |
EPCOR | 04-Jul-22 07:00 | 08-Jul-22 17:00 | 4.42 Days
Continuous |
TX1 @ East Industrial E52S, 52s T1 (52s East Industrial) | East Industrial TX1 Zone Op-Checks, P&C Maintenance | |
SUNCOR | 11-Jul-22 06:00 | 17-Jul-22 18:00 | 6.5 Days
Continuous |
30EDD-2 | 46711253 30EDD2;30PK-11 SYSTEM;PM 5y,10y | |
EPCOR | 11-Jul-22 07:00 | 15-Jul-22 17:00 | 4.42 Days
Continuous |
TX1 Zone @ Cloverbar E987S, 987s T1 (987s Clover Bar) | Cloverbar TX1 Zone Doble and CDS19/CDS20/CDS24/CDS38 Disconnect Maintenance | |
EPCOR | 11-Jul-22 07:00 | 15-Jul-22 17:00 | 4.42 Days
Continuous |
TX2 @ East Industrial E52S, 52s T2 (52s East Industrial) | East Industrial TX2 Zone Op-Checks, P&C Maintenance | |
ALTALINK | 11-Jul-22 10:30 | 14-Jul-22 17:30 | 3.29 Days
Daily |
138s T2(TX18906), 138kV Bus2 (603L, 608L, 603L (138s Windy Flats - 243s Soderglen Wind Farm), 608L (138s Windy Flats - 418s Ardenville - 528s Blue Trail Wind Farm), 138s T2 (138s Windy Flats) | Maintenance, doble, leak repair, bushing and monitor repair (T2). 138kV Breaker Maintenance (138s2152, 138s2552) | |
ATCO | 12-Jul-22 07:00 | 16-Jul-22 17:00 | 4.42 Days
Continuous |
7L224, 774S 701, 7L224 (650s Hansman Lake - 774s Monitor), 774s 701 (774s Monitor) | RAS modifications for the Pattern Lanfine WAGF project | |
ALTALINK | 15-Jul-22 07:00 | 05-Aug-22 18:00 | 21.46 Days
Continuous |
20sT1 (Tx 18459) GOI, 20s T1 (20s Ghost) | Alignment with TAU Outage to replace Transformer | |
ATCO | 25-Jul-22 08:00 | 07-Aug-22 17:00 | 13.38 Days
Continuous |
7L40, 7L40 (733s Simonette - 813s Little Smoky) | 813S Little Smoky Rebuild
BKR 709 and 710 P&C wiring, remove old panels 3G and 4G, set up new panel 7P1, prep work Relay programming and functionality Commission control, alarms and status |
|
ALTALINK | 26-Jul-22 07:00 | 29-Jul-22 18:00 | 3.46 Days
Continuous |
20s 138kV BUS South GOI, 113L (20s Ghost - 33s Spray), 150L (20s Ghost - 150AL tap), 859L (20s Ghost - AML 793s Horse Creek), 20s 138kV South Bus (20s Ghost) | Replace CVT1 and connect to new distribution. Complete T1 CT contributions and trip testing new bus protection, Trip testing Cutover MOD 20s153 to new building and controls | |
ATCO | 27-Jul-22 07:00 | 28-Jul-22 17:00 | 1.42 Days
Continuous |
972S 900BS2, 9L16, 9L16 (755s Cordel - 972s Tinchebray), 972s 240kV Bus 900BS2 (972s Tinchebray) | Outage on 9L16 to cut the line over to the new bay | |
ATCO | 27-Jul-22 07:00 | 31-Jul-22 17:00 | 4.42 Days
Continuous |
7L760, 767S 702, 7L760 (767s Oyen - 7L760D2), 767s 702 (767s Oyen) | RAS modifications for the Pattern Lanfine WAGF project | |
ATCO | 29-Jul-22 07:00 | 03-Aug-22 17:00 | 5.42 Days
Continuous |
9L177, 9L177 (620s Goldeye - 972s Tinchebray) | Installing new 240Kv Bay (connect 907B to BUS 1) for 620S Goldeye substation connection | |
ALTALINK | 29-Jul-22 08:00 | 29-Jul-22 16:00 | 8 Hours
Daily |
20s 138kV BUS & Station GOI, 20S Ghost, 20s 138kV South Bus (20s Ghost), 20s 138kV North Bus (20s Ghost) | Complete Cutover of MOD 20s14 and functional testing | |
ATCO | 02-Aug-22 00:00 | 13-Aug-22 00:00 | 11 Days
Continuous |
720S 901T, 720s 901T (720s Wabasca) | 720S Wabasca 901T Replacement, Load transferred to 902T | |
ATCO | 02-Aug-22 08:00 | 15-Aug-22 16:00 | 13.33 Days
Continuous |
801S 903, 801S 902, 9L59, 9L59 (801s Anderson - 972s Tinchebray) | TransAlta GARDEN PLAIN PROJECT
Relay Settings changes |
|
ATCO | 02-Aug-22 08:00 | 15-Aug-22 16:00 | 13.33 Days
Continuous |
972S 901, 972S 902, 9L59, 9L59 (801s Anderson - 972s Tinchebray) | TransAlta GARDEN PLAIN PROJECT
Relay Settings Changes |
|
EPCOR | 03-Aug-22 07:00 | 05-Aug-22 17:00 | 2.42 Days
Continuous |
TX4 Zone @ Poundmaker, T4 (Poundmaker) | Poundmaker BUS 3 CVT Doble and PMDS4, PMDS5 Disconnect Maintenance | |
ATCO | 07-Aug-22 08:00 | 15-Aug-22 16:00 | 8.33 Days
Continuous |
9L59, 9L59 (801s Anderson - 972s Tinchebray) | TransAlta GARDEN PLAIN PROJECT
Line 9LA59 tie-in to Garden Plain Sub |
|
SUNCOR | 08-Aug-22 06:00 | 14-Aug-22 18:00 | 6.5 Days
Continuous |
29EDD-3 29Edd-3 | transforme Line protection upgrade and 29PT-5 replace PRD | |
ATCO | 08-Aug-22 08:00 | 11-Aug-22 17:00 | 3.38 Days
Continuous |
9L29, 9L29 (946s Oakland - 963s Coyote Lake) | BER Hand Hills Project
P & C circuit cutovers Commission LTO 908 & 909 52b open status and line MOD 9L29D2 89b open status @ 946S and LTO 901 open status and line MOD, 9L29D1 open status @ 963S, end-to-end testing |
|
ATCO | 08-Aug-22 08:00 | 21-Aug-22 17:00 | 13.38 Days
Continuous |
7L32, 7L32 (813s Little Smoky - 862s South Bezanson) | 813S Little Smoky Rebuild
BKR 701 and 702 P&C wiring, prep work Relay programming and functionality Commission control, alarms and status |
|
EPCOR, ALTALINK | 08-Aug-22 09:30 | 13-Aug-22 17:00 | 5.31 Days
Continuous |
D2403 and 909LW @ Dome E665S and Sundance310P, 909L (310p Sundance - 665s Dome) | Dome D2403 Bay Doble and Breaker Maintenance, 909LW CT/Arrestor Doble | |
EPCOR | 15-Aug-22 07:00 | 20-Aug-22 17:00 | 5.42 Days
Continuous |
D2401 @ Dome E665S, 665s D2401 (665s Dome) | Dome D2401 Bay Doble and Breaker Maintenance | |
ATCO | 22-Aug-22 08:00 | 29-Aug-22 16:00 | 7.33 Days
Continuous |
766S 901T, 766s 901T (766s Nevis) | Joss Jenner 2 Power Project Connection
Complete CT, PT, P&C cutover, commission relays and DTT to 770S Three Hills (option 1) or 1-114S Ghost Pine (option 2) |
|
ATCO | 22-Aug-22 08:00 | 04-Sep-22 17:00 | 13.38 Days
Continuous |
7L90, 7L90 (741s Fox Creek - 813s Little Smoky) | 813S Little Smoky Rebuild
BKR 702 and 703 P&C wiring, remove old panels 1G and 2G, prep work Relay programming and functionality Commission control, alarms and status |
|
EPCOR, ALTALINK | 22-Aug-22 09:30 | 26-Aug-22 17:00 | 4.31 Days
Continuous |
1045L Zone and J2407 @ Jasper Terminal E805S and Sundance 310P, 1045L (310p Sundance - 320p Keephills - 805s Jasper) | Jasper 1045L Zone Doble and J2407 Doble and Maintenance | |
EPCOR | 29-Aug-22 07:00 | 02-Sep-22 17:00 | 4.42 Days
Continuous |
TX3 Zone @ Lambton E803S, EP 803s T3 (EP 803s Lambton) | Lambton TX3 Zone Doble and LAB3/LDS10/LDS11 Disconnect Maintenance | |
ATCO | 05-Sep-22 08:00 | 24-Sep-22 17:00 | 19.38 Days
Continuous |
813S 901T, 813s 901T (813s Little Smoky) | 813S Little Smoky Rebuild
Remove panels 3K,4K - install new panel 9T1 - BKR 901, 701, 705, 718 P&C wiring, prep work Replace 500PT disconnect assembly Relay programming and functionality Commission control, alarms and status |
|
ATCO | 05-Sep-22 08:00 | 30-Sep-22 16:00 | 25.33 Days
Continuous |
972S 900BS2, 972s 240kV Bus 900BS2 (972s Tinchebray) | CETO project | |
EPCOR | 12-Sep-22 07:00 | 18-Sep-22 17:00 | 6.42 Days
Continuous |
TX5 and 240CV5 Zone @ Victoria E511S and Castledowns E557S, EP 511s Victoria T5 (EP 511s Victoria), CV5 (EP 511s Victoria - 557s Castle Downs) | Victoria TX5 and CV5 Zone Op-Checks, P&C Maintenance | |
SUNCOR | 14-Sep-22 08:00 | 19-Sep-22 18:00 | 5.42 Days
Continuous |
29PL9-13, 29PL9-13 (29EDD-34 - 29EDD-65) | 29PL9-13; 29PT-249;MTCE & TEST;(A)5Y | |
ATCO | 26-Sep-22 08:00 | 19-Oct-22 17:00 | 23.38 Days
Continuous |
813S 902T, 813s 902T (813s Little Smoky) | 813S Little Smoky Rebuild
Remove panels 1K,2K - install new panel 9T2 - BKR 904, 710, 711, 713, 717 P&C wiring, prep work Replace cap bank protection relays Replace 501PT disconnect assembly Relay settings update for capacitor banks 714C, 715C, 716C Relay programming and functionality Commission control, alarms and status |
|
ATCO | 22-Oct-22 07:00 | 02-Nov-22 17:00 | 11.42 Days
Continuous |
7L129, 7L129 (710s Vermilion - 918s Bauer) | Re stringing conductor | |
ATCO | 24-Oct-22 08:00 | 06-Nov-22 17:00 | 13.42 Days
Continuous |
9L11, 9L11 (813s Little Smoky - 834s Wesley Creek) | 813S Little Smoky Rebuild
Remove panels 5H,6H - install new panel 9P3 - BKR 905 and 906 P&C wiring, prep work Relay programming and functionality Commission control, alarms and status |
|
ATCO | 07-Nov-22 08:00 | 20-Nov-22 17:00 | 13.38 Days
Continuous |
9L05, 9L05 (809s Louise Creek - 813s Little Smoky) | 813S Little Smoky Rebuild
Remove panels 5H,6H - install new panel 9P3 - BKR 905 and 906 P&C wiring, prep work Relay programming and functionality Commission control, alarms and status |
|
ATCO | 08-Nov-22 08:00 | 08-Nov-22 17:00 | 9 Hours
Continuous |
7L32 (813s Little Smoky - 862s South Bezanson) | 862S S. Bezanson Substation Rebuild Project, Disconnect and remove 7L32PT2 | |
ATCO | 08-Nov-22 08:00 | 08-Nov-22 17:00 | 9 Hours
Continuous |
7L32 (813s Little Smoky - 862s South Bezanson) | 862S S. Bezanson Substation Rebuild Project, Disconnect and remove 7L32PT3 | |
ALTALINK | 16-Nov-22 07:15 | 16-Nov-22 12:45 | 5.5 Hours
Daily |
20sT1 (Tx 18459) GOI | Trip testing of 20s30, 20s2, 20s3, and 20s4 from relocated A87/138B Bus protection | |
ATCO | 21-Nov-22 08:00 | 04-Dec-22 17:00 | 13.38 Days
Continuous |
9L02, 9L02 (809s Louise Creek - 813s Little Smoky) | "Louise Creek Rebuild project - On Oct 24 - Breaker 903 will remain open overnight as this breaker will be part of the following GOI on 9L40 2-50614. Reason: Protection on this breaker is only partially upgraded at this point.
Wiring for 903/910BF relays. CT ratio changes. Relay programming and functionality. Commission control, alarms and status. Blocking procedures for BF protections." |
|
ATCO | 05-Dec-22 08:00 | 18-Dec-22 17:00 | 13.38 Days
Continuous |
813S SVC, 813s SVC (813s Little Smoky) | 813S Little Smoky Rebuild
Cutover new filter bank relays, P&C wiring Relay programming and functionality Commission control, alarms and status |
|
ATCO | 27-Jan-23 08:00 | 07-Feb-23 17:00 | 11.38 Days
Continuous |
75-PLH-902, 75-PHL-902 (838s Horizon Mining - 849s Joslyn Creek) | ATCO 9L32-9L66 CNRL- Horizon Project
Disconnect existing 75-PLH-902 from Horizon substation 75 Connect new bus Horizon substation 75 (former 75-PLH-902 bay)to new 838S-900BS1 Reroute and connect 9L137 (former 75-PLH-902) to new 838S and energize Commission 87L/900BS1 protection, end-to-end testing Upgrade 21B/9L137 line protection @ 849S Joslyn Commission line protection, SCADA and end-to-end testing, BF/DTT to 838S |
|
ATCO | 08-Feb-23 08:00 | 19-Feb-23 17:00 | 11.38 Days
Continuous |
75-PLH-901, 849s 907 (849s Joslyn Creek), 75-PLH-901 (838s Horizon Mining - 849s Joslyn Creek) | ATCO 9L32-9L66 CNRL- Horizon Project
Disconnect existing 75-PLH-901 from Horizon substation 75 Connect new bus Horizon substation 75 (former 75-PLH-901 bay) to new 838S-900BS2 Reroute and connect 9L155 (former 75-PLH-901) to new 838S and energize Commission 87L/900BS1 protection, end-to-end testing Upgrade 21B/9L155 line protection @ 849S Joslyn Commission line protection, SCADA and end-to-end testing, BF/DTT to 838S |
|
ATCO | 20-Feb-23 08:00 | 23-Feb-23 17:00 | 3.38 Days
Continuous |
9L66, 9L66 (847s Muskeg River - 849s Joslyn Creek) | ATCO 9L32-9L66 CNRL- Horizon Project
Disconnect existing line 9L66 at tap point and connect new line segment to 838S Horizon Expansion Disconnect existing 9L66 from Joslyn 849S Commissioning upgrade - relay settings @ 847S |
|
ATCO | 24-Feb-23 08:00 | 27-Feb-23 17:00 | 3.38 Days
Continuous |
9L32, 9L32 (849s Joslyn Creek - 2005s Secord) | ATCO 9L32-9L66 CNRL- Horizon Project
Disconnect existing line 9L32 at tap point and connect new line segment to 838S Horizon Expansion Disconnect existing 9L32 from Joslyn 849S Commissioning upgrade - relay settings @ 2005S |
|
ATCO | 21-Mar-23 08:00 | 22-Mar-23 17:00 | 1.38 Days
Continuous |
7L53, 7LA53, 7L53 (700s Bonnyville - 706s Irish Creek) | Cold Lake Area Energy Centre Project
7LA53 (New Line T-Tap) 1064S Garnier Lake Sub (Customer) Build 6km 7LA53 144kV from T-Tap to 1064S Garnier Lake Substation. Remote end protection upgrades |
|
ATCO | 27-Mar-23 08:00 | 30-Mar-23 17:00 | 3.38 Days
Continuous |
7L91, 7L91 (715s Leming Lake - 826s Marguerite Lake) | Cold Lake Area Energy Centre Project
Cutover CT/PT/P&C ccts for new Thermal RAS relays Complete commissioning 49A/49B/7L91 relays End-to-end testing to 1064S |
|
SUNCOR | 01-May-23 08:00 | 14-May-23 18:00 | 13.42 Days
Continuous |
29EDD-1, 29EDD-1 Millennium | N260B1 + Relays, 29CVT-11, 29PS-72/76.
29EDD-1S1/1S7/1S13/1S452/1S152 + Relays, 952-101/104 + Controller + Relays assets |
|
SUNCOR | 01-May-23 08:00 | 30-May-23 18:00 | 29.42 Days
Continuous |
29EDD-94, 29EDD-94 Voyageur | 29EDD94; Breaker MTCE & TEST, PM 10y on breakers 29-452-6704, 29-452-6703, 29-452-6702, 29-452-8302, 29-452-8303, 29-452-8304, 29-452-8407, 29-452-8406, 29-452-8405, 29-452-8404, 29-452-8403, 29-452-8402, 29-452-8502, 29-452-8503,29-452-8504, 29-452-8505, 29-452-8506, 29-452-8507 |
AB-BC, AB-SK & AB-MATL: refer to AESO web posting: | http://itc.aeso.ca/itc/public/atc |
Also, | |
AB-BC, AB-SK & AB-MATL: refer to ISO Rule 203.6: | http://www.aeso.ca/rulesprocedures/18592.html |
Prepared On: | 2022-01-05 2:28:46 PM |
This document and the information contained herein are based upon information and data which by their nature contain a degree of uncertainty and are subject to change. In addition, this document may contain information and data from public sources and/or third parties, which have been assumed to be accurate and complete and have not been verified. Accordingly, the Independent System Operator, operating as the Alberta Electric System Operator (the "AESO") makes no warranty, representation or guarantee, express or implied, with respect to this document or the information contained herein, including, but not limited to, any warranty, representation or guarantee of accuracy, completeness, timeliness, reliability, availability, absence of computer virus, non- infringement, merchantability or suitability for any purpose. Under no circumstances will the AESO, its members, officers, employees, contractors or agents, or any of their respective affiliates, be liable for any errors or omissions in, or any losses, damages or claims whatsoever, whether in contract, tort or otherwise, arising from use of or reliance upon, this document or any information contained herein. © 2009 Alberta Electric System Operator. All rights reserved |