Alberta Electric System Operator | |
System Co-ordination Plan | |
2021-10-28 to 2021-11-05 | |
Approved Outages |
Previous Version | |
Download CSV |
From | To | Owner | Type | Element | Scheduled Activity | Date/Time Comments | Interconnection |
---|---|---|---|---|---|---|---|
05-Oct-18 08:00 | 31-Dec-21 16:00 | EPCOR | IO | C2 (Rossdale) | forced outage | Continuous |
1,183.38 Days
|
24-Oct-18 01:13 | 31-Dec-21 16:00 | EPCOR | IO | C1 (Rossdale) | forced outage | 1,164.66 Days
Continuous |
|
01-Jan-21 08:00 | 31-Dec-21 18:00 | SUNCOR | Outage | Unmodeled Transmission Facility (Suncor) | 30EDD-200, 29EDD-106, 29EDD-141, 29EDD-192 | 364.42 Days
Daily |
|
01-Jan-21 08:00 | 01-Jan-22 18:00 | SUNCOR | Outage | Unmodeled Transmission Facility (Suncor) | 30EDD-200 | 365.42 Days
Daily |
|
01-Jan-21 08:00 | 11-Jan-22 18:00 | SUNCOR | Outage | Unmodeled Transmission Facility (Suncor) | 30EDD-200 | 375.42 Days
Continuous |
|
01-Jan-21 08:00 | 04-Jan-23 18:00 | SUNCOR | Outage | Unmodeled Transmission Facility (Suncor) | 30EDD-200 | 733.42 Days
Continuous |
|
02-Jan-21 08:00 | 05-Jan-23 18:00 | SUNCOR | Outage | Unmodeled Transmission Facility (Suncor) | 29EDD-181
|
733.42 Days
Continuous |
|
05-Jan-21 08:00 | 01-Jun-23 18:00 | SUNCOR | Outage | Unmodeled Transmission Facility (Suncor) | 29PT-69
|
877.38 Days
Continuous |
|
24-Jan-21 08:00 | 07-Jan-23 18:00 | SUNCOR | Outage | Unmodeled Transmission Facility (Suncor) | 29EDD-161
|
713.42 Days
Continuous |
|
02-Feb-21 08:00 | 10-Jan-23 18:00 | SUNCOR | Outage | Unmodeled Transmission Facility (Suncor) | 29EDD-221
|
707.42 Days
Continuous |
|
03-Feb-21 13:00 | 31-Dec-21 18:00 | ATCO | IO | 757s 703 (757s Battle River) | removing CT to replace damaged one on breaker 704 | 331.21 Days
Continuous |
|
24-Feb-21 08:00 | 11-Jan-23 18:00 | SUNCOR | Outage | Unmodeled Transmission Facility (Suncor) | 29EDD-211; substation ground test; PM 5y - 34.5kV | 686.42 Days
Continuous |
|
01-Mar-21 08:00 | 03-Feb-23 18:00 | SUNCOR | Outage | Unmodeled Transmission Facility (Suncor) | 29EDD-221 ;29PT-605 system | 704.42 Days
Continuous |
|
01-Mar-21 08:00 | 04-Feb-23 18:00 | SUNCOR | Outage | Unmodeled Transmission Facility (Suncor) | 29EDD-161; 29PT-582 system | 705.42 Days
Daily |
|
01-Mar-21 08:00 | 05-Feb-23 18:00 | SUNCOR | Outage | Unmodeled Transmission Facility (Suncor) | 29EDD-171; 29PT-600 system | 706.42 Days
Daily |
|
26-Apr-21 09:00 | 30-Nov-21 17:00 | ATCO | TE | 809s Louise Creek RTU/SCADA | RTU replacement | 218.38 Days
Continuous |
|
26-Apr-21 13:30 | 30-Nov-21 13:30 | ATCO | TE | 809s Louise Creek RTU/SCADA | RTU replacement | 218.04 Days
Continuous |
|
29-Apr-21 20:00 | 29-Oct-21 18:00 | ENBRIDGE | TE | 120s MATL PST (120s Picture Butte) | failed "B" protection relay | 182.92 Days
Continuous |
|
24-May-21 07:00 | 01-Nov-21 17:00 | EPCOR | TE | 805S Jasper | system being upgraded and tested to accommodate future upgrade to ADMS system | 161.42 Days
Daily |
|
12-Jul-21 08:00 | 13-Dec-21 16:00 | ATCO | TE | 809S Louise Creek | Louise Creek sub rebuild project -
installation, wiring and commissioning of new BF relays in subsequent outages |
154.38 Days
Continuous |
|
03-Aug-21 17:01 | 07-Dec-21 17:00 | EPCOR | Outage | T1 (EPCOR Hardisty) | Hardisty T1 replacement | 126.04 Days
Continuous |
|
13-Aug-21 09:00 | 31-Oct-21 17:00 | ATCO | TE | 7L101 (790s Poplar Hill - 944s Lowe Lake) | relay blocked after nuisance tripping was caused from a faulty CT wire | 79.33 Days
Continuous |
|
23-Aug-21 14:11 | 22-Nov-21 14:11 | ATCO | TE | 718s RTU/SCADA (718s Parsons Creek) | RTU config updates | 91.04 Days
Continuous |
|
30-Aug-21 14:00 | 30-Nov-21 17:00 | ATCO | Outage | 9L938 (77s Sagitawah - 809s Louise Creek), 809s 902T (809s Louise Creek), 809s 910 (809s Louise Creek), 809s 911 (809s Louise Creek), 809s 912 (809s Louise Creek), 809s 702 (809s Louise Creek) | Louise Creek Rebuild project upgrade 902T protection, replace 911 breaker | 92.17 Days
Continuous |
|
10-Sep-21 12:30 | 01-Nov-21 16:30 | ALTALINK | Outage | 320p 2089 (320p Keephills) | maintenance | 52.17 Days
Continuous |
|
13-Sep-21 07:00 | 15-Nov-21 17:00 | EPCOR | Outage | T3 (Poundmaker) | 240 kV ring re-configuration (P1649) | 63.46 Days
Continuous |
|
13-Sep-21 12:15 | 29-Oct-21 18:00 | ALTALINK | Outage | 437s T1 (437s Baymag) | T1 A & B protection replacement | 46.24 Days
Continuous |
|
14-Sep-21 08:00 | 08-Nov-21 17:00 | ATCO | TE | 6L03 (775s Sullivan Lake - 6L17 tap) | temp settings for line by pass for 775s Sullivan lake | 55.42 Days
Continuous |
|
14-Sep-21 08:00 | 08-Nov-21 17:00 | ATCO | TE | 6L12 (775s Sullivan Lake - 6L25 tap) | temp settings for line by pass for 775s Sullivan lake | 55.42 Days
Continuous |
|
16-Sep-21 08:00 | 08-Nov-21 16:00 | ATCO | Outage | 775S Sullivan Lake, 6L15 (763s Hanna - 775s Sullivan Lake) | 775S Sullivan Lake substation rebuild
complete breaker and disconnect switch replacement, 775S Sullivan Lake substation rebuild complete breaker and disconnect switch replacement |
53.38 Days
Continuous |
|
21-Sep-21 07:00 | 30-Nov-21 17:00 | EPCOR | TE | EP 511s VICTORIA, EP 511s RTU/SCADA (EP 511s Victoria) | station SA system being upgraded and tested to accommodate future upgrade to ADMS system | 70.46 Days
Daily |
|
21-Sep-21 07:15 | 23-Nov-21 17:45 | ALTALINK | Outage | 370s 2552 (370s North Lethbridge), 370s T4 (370s North Lethbridge) | isolate bus to provide clearance for new steel and equipment installation | 63.48 Days
Continuous |
|
27-Sep-21 07:00 | 12-Nov-21 17:00 | EPCOR | Outage | EP 511s Victoria T5 (EP 511s Victoria), CV5 (EP 511s Victoria - 557s Castle Downs) | regasketing Victoria T5 | 46.46 Days
Continuous |
|
27-Sep-21 08:00 | 29-Oct-21 16:00 | ENMAX | TE | RTU/SCADA (ENMAX 8) | RTU upgrade | 32.33 Days
Daily |
|
03-Oct-21 08:00 | 05-Nov-21 16:00 | ENMAX | Outage | 40.1TR (ENMAX 40) | install new Albarrie, plastibeton, duct banks and cables phasing required on return | 33.33 Days
Continuous |
|
04-Oct-21 08:01 | 02-Nov-21 17:00 | ATCO | Outage | 9L02 (809s Louise Creek - 813s Little Smoky), 809s 903 (809s Louise Creek), 809s 910 (809s Louise Creek) | Louise Creek rebuild project | 29.37 Days
Continuous |
|
07-Oct-21 08:00 | 30-Oct-21 16:00 | ALTALINK | IO | 1.82L OOS for Enmax | 5sub TRV Project. Replace circuit breaker | 23.33 Days
Continuous |
|
07-Oct-21 08:00 | 30-Oct-21 16:00 | ENMAX | Outage | 1.82L (ENMAX 1 - ENMAX 5), 5B138-1.82 (ENMAX 5) | 5sub TRV project: replace circuit breaker | 23.33 Days
Continuous |
|
12-Oct-21 08:00 | 21-Nov-21 16:00 | ENMAX | Outage | 2.83L (ENMAX 5 - 2.83L tap) | TRV project. replace circuit breaker | 40.38 Days
Continuous |
|
12-Oct-21 08:00 | 21-Nov-21 16:00 | ALTALINK | IO | 2.83L OOS for Enmax | 5sub TRV Project. Replace circuit breaker, Fall substation washing. | 40.38 Days
Continuous |
|
12-Oct-21 08:00 | 01-Nov-21 17:00 | ATCO | TE | 809s 701C (809s Louise Creek), 809s 901T (809s Louise Creek), 809s 902T (809s Louise Creek), 7L19 (809s Louise Creek - 851s Morse River), 7L43 (739s Edith Lake - 809s Louise Creek), 7L55 (743s Sarah Lake - 809s Louise Creek), 7L56 (738s Virginia Hills - 809s Louise Creek), 9L938 (77s Sagitawah - 809s Louise Creek) | firmware update | 20.38 Days
Continuous |
|
12-Oct-21 09:00 | 05-Nov-21 17:00 | BCH | Outage | 2L112 (Boundary - Nelway) | oil containment install, BC Maintenance does not affect the Alberta ATC | 24.33 Days
Continuous |
AB-BC |
12-Oct-21 09:00 | 05-Nov-21 17:00 | ALTALINK | IO | 2L112 BCH outage (Info Only) | oil containment install | 24.33 Days
Continuous |
|
18-Oct-21 08:00 | 29-Oct-21 17:00 | ATCO, ALTALINK | RB | 1035L (244s Bowmanton - 2075s Newell) | urgent - completion of damper replacement CRU scope between structures 300 & 367 | 11.38 Days
Daily |
|
18-Oct-21 08:00 | 29-Oct-21 17:00 | ATCO, ALTALINK | RB | 1035L (244s Bowmanton - 2075s Newell) | RB on 9L1035 @ 2075S for completion of damper replacement CRU scope between structures 300 & 367 | 11.38 Days
Daily |
|
18-Oct-21 08:00 | 29-Oct-21 18:00 | ALTALINK | Outage | 1034L (244s Bowmanton - 324s Cassils) | urgent repair damper | 11.42 Days
Continuous |
|
18-Oct-21 09:00 | 29-Oct-21 18:00 | ALTALINK | Outage | 1201L (520s Bennett - BCH Cranbrook) | components-structure range 383-464 | 11.38 Days
Continuous |
AB-BC |
18-Oct-21 09:00 | 29-Oct-21 18:00 | MONTANA | Outage | MATL (120s Picture Butte - Montana) | align with 1201L outage | 11.38 Days
Continuous |
AB-MATL |
18-Oct-21 09:30 | 08-Nov-21 16:00 | EPCOR | Outage | 72LS24 (EP 803s Lambton - Strathcona) | Line Maintenance | 21.31 Days
Continuous |
|
18-Oct-21 12:00 | 01-Nov-21 11:00 | ATCO | Outage | 7L59 (789s Keg River - 7L59 tap) | replace crossarms and replace poles | 13.96 Days
Continuous |
|
19-Oct-21 07:00 | 23-Nov-21 18:00 | ALTALINK | Outage | 39s 1052 (39s Bickerdike) | addition of new breaker 39s1152 and associated equipmen (P2032) | 35.5 Days
Continuous |
|
19-Oct-21 07:00 | 29-Oct-21 18:00 | ATCO | TE | ATCO RTU upgrades, ATCO's system operations centre | upgrading the EMS SCADA system | 10.46 Days
Continuous |
|
20-Oct-21 08:00 | 30-Oct-21 16:00 | CNRL | TE | 838s Horizon Mining RTU/SCADA | RTU replacement | 10.33 Days
Continuous |
|
21-Oct-21 08:00 | 04-Nov-21 18:00 | SUNCOR | Outage | 29PL6-3 (29EDD-1 Millennium - 836s Steepbank) | line protection upgrade | 14.42 Days
Continuous |
|
21-Oct-21 08:00 | 04-Nov-21 18:00 | SUNCOR | TE | 29EDD-1 Millennium RTU/SCADA, 30EDD-1 RTU/SCADA | updates to D20MX at 29EDD-1 & 30EDD1 substation to map values to DCS system for 29PL6-3 line upgrade project | 14.42 Days
Continuous |
|
21-Oct-21 08:15 | 16-Nov-21 17:45 | ALTALINK | Outage | 225L (225s Magrath - 385s Spring Coulee) | rebuilding a portion of 225L from structure 282 to structure 400 | 26.44 Days
Continuous |
|
21-Oct-21 14:53 | 29-Oct-21 18:00 | ATCO | Outage | 930s Syn Condenser (930s Arcenciel) | forced outage | 8.13 Days
Continuous |
|
22-Oct-21 08:00 | 05-Nov-21 16:00 | ENMAX | Outage | 5.8TR (ENMAX 5) | relay replacement. 5.8TR ground shield ground rerun | 14.33 Days
Continuous |
|
23-Oct-21 07:00 | 28-Oct-21 18:00 | ALTALINK | Outage | 795L (121s Brooks - 421s Hays) | bird fight diverter installation | 5.46 Days
Continuous |
|
23-Oct-21 17:25 | 29-Oct-21 18:30 | ALTALINK | IO | M120s Station GOI | annual maintenance routine - in conjunction with south bound and 1201L outage | 6.05 Days
Continuous |
|
23-Oct-21 18:00 | 29-Oct-21 18:00 | ENBRIDGE, MONTANA | Outage | 120s MATL PST (120s Picture Butte), 120s C1 (120s Picture Butte), 120s C2 (120s Picture Butte) | annual maintenance routine | 6 Days
Continuous |
AB-MATL |
25-Oct-21 07:00 | 29-Oct-21 15:00 | ALTALINK | TE | 167s RTU/SCADA (167s Ipiatik Lake) | HMI replacement | 4.33 Days
Daily |
|
25-Oct-21 07:00 | 05-Nov-21 17:00 | ALTALINK, EPCOR | Outage | 1238L (330p Genesee - 510s Sunnybrook) | spire #6 and # 7 repair | 11.42 Days
Continuous |
|
25-Oct-21 07:00 | 29-Oct-21 17:00 | EPCOR | Outage | 987s SST2 (987s Clover Bar) | clover Bar SDS2L LCR - SST2 work | 4.42 Days
Continuous |
|
25-Oct-21 07:30 | 03-Nov-21 17:30 | ALTALINK | RB | 1036L (356s Milo - 554s Travers) | safety requirement, re: 1005L GOI | 9.42 Days
Daily |
|
25-Oct-21 07:30 | 29-Oct-21 17:30 | ALTALINK, EPCOR | RB | 747L (37s North Calder - 99s North St Albert), 711L (Inland Cement - 747L tap) | urgent - line maintenance | 4.42 Days
Daily |
|
25-Oct-21 08:00 | 28-Oct-21 17:30 | ALTALINK | TE | 42s RTU/SCADA (42s Sarcee) | update RTU configuration | 3.4 Days
Daily |
|
25-Oct-21 08:00 | 30-Oct-21 17:00 | ATCO, ALTALINK | Outage | 7L77 (395s North Holden - 709s Vegreville) | change arms & insulators | 5.38 Days
Continuous |
|
25-Oct-21 08:00 | 29-Oct-21 17:00 | ALTALINK | TE | 199s RTU/SCADA (199s East Airdrie) | new configuration in RTUs | 4.38 Days
Continuous |
|
25-Oct-21 08:00 | 29-Oct-21 17:00 | ATCO | TE | 2005S Secord | PRC005 relays and line work | 4.38 Days
Continuous |
|
25-Oct-21 08:00 | 01-Nov-21 12:00 | ATCO | Outage | 7L12 (834s Wesley Creek - 7LA12 tap) | changing X Arms and installing stubs | 7.17 Days
Continuous |
|
25-Oct-21 08:00 | 28-Oct-21 18:00 | ALTALINK | TE | 17s RTU/SCADA (17s Benalto) | commission new Johnson node 2 into the network | 3.42 Days
Continuous |
|
25-Oct-21 08:00 | 28-Oct-21 18:00 | ATCO | IO | Benalto | Altalink work - working on the DWDM network | 3.42 Days
Continuous |
|
25-Oct-21 08:00 | 28-Oct-21 16:00 | ENMAX | Outage | 11.2TR (ENMAX 11) | cable trench replacement | 3.33 Days
Continuous |
|
25-Oct-21 08:00 | 29-Oct-21 18:00 | USPCE | TE | 841s Long Lake RTU/SCADA | firmware upgrade | 4.42 Days
Continuous |
|
25-Oct-21 08:30 | 28-Oct-21 17:00 | ENMAX | IO | Altalink outage. 5sT2 | change conservator bladder | 3.35 Days
Continuous |
|
25-Oct-21 08:30 | 29-Oct-21 17:00 | ATCO | TE | 856s Kinosis RTU/SCADA | firmware upgrade | 4.35 Days
Continuous |
|
25-Oct-21 08:30 | 01-Nov-21 16:30 | ATCO | TE | 802s Michichi Creek RTU/SCADA | complete 500PT2 wiring | 7.33 Days
Continuous |
|
25-Oct-21 09:00 | 30-Oct-21 17:30 | ALTALINK | IO | 7L77 (A709s - 395s) ATCO - Advice | change arms insulators | 5.35 Days
Continuous |
|
25-Oct-21 09:00 | 29-Oct-21 17:30 | ATCO | Outage | 2029s Heathfield | 2029S 500SST1/T2 - breaker thermal window install | 4.35 Days
Continuous |
|
25-Oct-21 09:00 | 28-Oct-21 16:00 | ATCO | RB | 7L10 (730s Rycroft - 754s Ksituan River) | maintenance | 3.29 Days
Continuous |
|
25-Oct-21 09:45 | 03-Nov-21 17:45 | ALTALINK | Outage | 1005L (120s Picture Butte - 356s Milo) | install/commission new line protections | 9.33 Days
Continuous |
|
25-Oct-21 11:00 | 29-Oct-21 15:00 | ALTALINK | Outage | 919L (77s Sagitawah - 310p Sundance) | replacement of 77s919x | 4.17 Days
Continuous |
|
25-Oct-21 12:00 | 28-Oct-21 18:00 | ALTALINK, EPCOR | Outage | 908L (89s Ellerslie - 816s Petrolia) | component replacements and fire mitigation | 3.25 Days
Continuous |
|
25-Oct-21 12:00 | 28-Oct-21 18:00 | ALTALINK, EPCOR | RB | 909L (89s Ellerslie - 665s Dome) | component replacements and fire mitigation on 908L Str's range 200-232 | 3.25 Days
Continuous |
|
25-Oct-21 12:00 | 28-Oct-21 18:00 | EPCOR | IO | ALTALINK - 908L - DE-ENERGIZE LINE | component replacements and fire mitigation on 908L Str's range 200-232 | 3.25 Days
Continuous |
|
25-Oct-21 12:00 | 28-Oct-21 18:00 | ALTALINK, EPCOR | RB | 909L (310p Sundance - 665s Dome) | component replacements and fire mitigation on 908L Str's range 200-232 | 3.25 Days
Continuous |
|
25-Oct-21 12:00 | 05-Nov-21 17:30 | ALTALINK | Outage | 89s 1252 (89s Ellerslie) | replace breaker fail relay | 11.23 Days
Continuous |
|
25-Oct-21 12:00 | 05-Nov-21 17:30 | ALTALINK | TE | 89S Ellerslie | breaker fail relay replacement | 11.23 Days
Daily |
|
25-Oct-21 12:00 | 05-Nov-21 17:30 | ALTALINK | TE | 89S Ellerslie | install of the new 96/1252 relay | 11.23 Days
Daily |
|
25-Oct-21 13:00 | 28-Oct-21 18:00 | ALTALINK | Outage | 89s 1352 (89s Ellerslie), 89s 1452 (89s Ellerslie) | replace 240 kV PTs 89s80 | 3.21 Days
Continuous |
|
26-Oct-21 07:30 | 28-Oct-21 17:30 | ALTALINK | Outage | 135s T2 (135s Conrad) | cable installation from T2 secondary CT’s to the new control building and change to feeder protection settings for the 135s4670 breaker | 2.42 Days
Daily |
|
26-Oct-21 08:00 | 28-Oct-21 18:00 | ALTALINK | Outage | 452L (367s Harry Smith - 434s Stony Plain), 434s T3 (434s East Stony Plain), 434s 452 (434s Stony Plain) | replace 434s2, replace 434s1 existing grounding mat, T3 pipe bus dampening repairs | 2.42 Days
Continuous |
|
26-Oct-21 08:00 | 28-Oct-21 17:00 | ALTALINK | TE | 89s RTU/SCADA (89s Ellerslie) | update configuration for replacement 89s1252 breaker fail relay | 2.38 Days
Daily |
|
26-Oct-21 08:00 | 01-Nov-21 09:00 | REDDEER | Outage | 194s T2 (194s South Red Deer) | relay testing and maintenance | 6.04 Days
Continuous |
|
26-Oct-21 08:00 | 09-Nov-21 09:00 | ATCO | Outage | 740s 144kV Main Bus (740s H.R.Milner), 740s 703T (740s H.R.Milner) | 740S 700BS1 outage | 14.08 Days
Continuous |
|
26-Oct-21 08:00 | 26-Nov-21 16:00 | ATCO | TE | 740S H.R.Milner | 144 kV bus - replace CT secondary cables | 31.38 Days
Continuous |
|
27-Oct-21 07:00 | 30-Oct-21 18:00 | ALTALINK | Outage | 853L (504s Queenstown - 853AL tap) | bird flight diverter installation on 853L structures 282-330 | 3.46 Days
Continuous |
|
27-Oct-21 08:00 | 11-Nov-21 18:00 | SUNCOR | Outage | 29EDD-71 Edd71Sub | breaker 10 year maintenance and test | 15.46 Days
Continuous |
|
27-Oct-21 08:30 | 28-Oct-21 16:30 | ALTALINK | Outage | 727L (65s High River - 727AL tap), 65s 727N (65s High River) | 65s High River grading cap (65s727N) | 1.33 Days
Continuous |
|
27-Oct-21 09:00 | 28-Oct-21 17:00 | ATCO | TE | 888S RTU Upgrades & Changes | configuration changes on RTU, station controller, SEL 2032
|
1.33 Days
Continuous |
|
27-Oct-21 09:00 | 28-Oct-21 17:00 | ATCO | Outage | 749s 701T (749s Flyingshot Lake) | 701T leak investigate and repair | 1.33 Days
Continuous |
|
27-Oct-21 09:15 | 28-Oct-21 15:45 | ALTALINK | Outage | 421s 795N (421s Hays), 795L (121s Brooks - 421s Hays) | 1st trip and maintenance - PRC5 | 30.5 Hours
Continuous |
|
28-Oct-21 08:00 | 29-Oct-21 17:00 | ALTALINK | TE | 199S East Airdrie | complete alarm splitting on T2 as part of ACC visibility upgrade program | 1.38 Days
Continuous |
|
28-Oct-21 08:00 | 28-Oct-21 16:00 | ENMAX | Outage | 1.7TR (ENMAX 1) | oil sampling, HV bushing, TC | 8 Hours
Continuous |
|
28-Oct-21 08:30 | 28-Oct-21 14:00 | ALTALINK | TE | 221s RTU/SCADA (221s Sunken Lake) | investigate ACC comms fail alarm coming from RTU and meter replacement | 5.5 Hours
Daily |
|
28-Oct-21 08:30 | 28-Oct-21 12:30 | ALTALINK | TE | 12S Heartland | minor setting change to enable local logging on the T1 B87/50/51/51N/T1 SEL387E | 4 Hours
Daily |
|
28-Oct-21 09:00 | 29-Oct-21 17:00 | ATCO | TE | 951s RTU/SCADA (951s Thickwood Hills) | configuration changes on SMP controller at 240 KV and SVS buildings | 1.33 Days
Continuous |
|
28-Oct-21 09:00 | 29-Oct-21 16:00 | ALTALINK | TE | 510s RTU/SCADA (510s Sunnybrook) | commissioning for geomagnetically induced current monitoring CTs and SCADA equipment | 31 Hours
Daily |
|
28-Oct-21 09:00 | 28-Oct-21 14:00 | ATCO | Outage | 826s 503R (826s Marguerite Lake), 826s 504R (826s Marguerite Lake) | emergency: repair hotspot found on 826S 504A during heat scanning | 5 Hours
Continuous |
|
28-Oct-21 09:30 | 01-Nov-21 17:30 | ALTALINK | Outage | 68s T2 (68s Willesden Green), 68s 552 (68s Amoco Willesden Green) | tie in new CT circuit for ne A87 protection, modify transformer protection relays setting and testing | 4.33 Days
Continuous |
|
28-Oct-21 10:00 | 01-Nov-21 17:00 | ALTALINK | TE | 68s RTU/SCADA (68s Willesden Green) | allow addition of new control/alarms | 4.29 Days
Daily |
|
28-Oct-21 10:00 | 28-Oct-21 17:00 | ALTALINK | TE | 422s RTU/SCADA (422s Westwood) | update RTU configuration | 7 Hours
Daily |
|
28-Oct-21 10:00 | 28-Oct-21 17:00 | ALTALINK | TE | 118S Canmore | standard relay maintenance | 7 Hours
Daily |
|
29-Oct-21 08:00 | 31-Oct-21 12:00 | ENMAX | Outage | 6.80L (ENMAX 6 - ENMAX 35), 6B138-6.80 (ENMAX 6) | 6 sub cable trench replacement | 2.17 Days
Continuous |
|
29-Oct-21 08:00 | 29-Oct-21 16:00 | ENMAX | TE | 5.8TR (ENMAX 5) | 5PT138-Z32 secondary circuit relay replacement and wiring new circuits | 8 Hours
Continuous |
|
29-Oct-21 08:00 | 30-Oct-21 17:00 | ATCO | IO | 2075S Newell | Notification of AltaLink work at 356s relay (Little Bow),13L50 - modify wiring and commissioning of new circuit | 1.38 Days
Continuous |
|
29-Oct-21 13:00 | 29-Oct-21 15:00 | SUNCOR | TE | SUNCOR ICCP Outage | SCADA failover test | 2 Hours
Continuous |
|
29-Oct-21 14:00 | 11-Nov-21 15:30 | ATCO | Outage | 757s 704 (757s Battle River) | 704T maintenance work and PRC005 work on 704 breaker | 13.1 Days
Continuous |
|
30-Oct-21 07:00 | 31-Oct-21 19:30 | ALTALINK | TE | 281s - Relay | Temporary setting change required for 275981 17s 138kV Bus outage 848L and Bus 4 at 17s. | 1.52 Days
Daily |
|
30-Oct-21 07:00 | 31-Oct-21 19:30 | ALTALINK | TE | 256S Harmattan | temporary setting change required for 275981 17s 138kV Bus outage 848L and Bus 4 at 17s | 1.52 Days
Daily |
|
30-Oct-21 07:00 | 31-Oct-21 19:30 | ALTALINK | TE | 575S Sundre | temporary setting change required for 275981 17s 138kV Bus outage 848L and Bus 4 at 17s | 1.52 Days
Daily |
|
30-Oct-21 08:00 | 30-Oct-21 18:00 | ENMAX | Outage | 11.82L (ENMAX 11 - ENMAX 14), 11.83L (ENMAX 162 - ENMAX 11), 11.3TR (ENMAX 11), 11.2TR (ENMAX 11) | fall substation washing. check reversing switch 11.2TR | 10 Hours
Continuous |
|
30-Oct-21 08:00 | 30-Oct-21 18:00 | ALTALINK | IO | 11.82L, 11.83L OOS - Enmax Info | fall substation washing. check reversing switch 11.2TR | 10 Hours
Daily |
|
30-Oct-21 10:00 | 15-Nov-21 16:00 | ENMAX | Outage | 14.1C (ENMAX 14), 14.2C (ENMAX 14) | 14 sub fencing replacement | 16.29 Days
Continuous |
|
31-Oct-21 07:15 | 31-Oct-21 16:45 | ALTALINK | IO | 937L (102s-5s) Urgent Enmax Advice | urgent outage to repair possible broken strands in splice | 9.5 Hours
Daily |
|
31-Oct-21 08:00 | 04-Nov-21 16:00 | ENMAX | TE | 6.80L (ENMAX 6 - ENMAX 35) | 6PT138-Z31 secondary circuit, 6 sub cable trench replacement | 4.33 Days
Continuous |
|
31-Oct-21 08:00 | 02-Nov-21 16:00 | ENMAX | Outage | 1.85L (ENMAX 1 - ENMAX 8) | 8sub RTU commissioning | 2.33 Days
Continuous |
|
31-Oct-21 08:00 | 31-Oct-21 16:00 | ENMAX, ALTALINK | Outage | 937L (5s East Calgary - 102s Langdon) | investigate high corona, possible internal broken strands on the conductor | 8 Hours
Continuous |
|
31-Oct-21 12:00 | 04-Nov-21 16:00 | ENMAX | Outage | 6.82L (ENMAX 6 - ENMAX 41) | 6 sub cable trench replacement | 4.17 Days
Continuous |
|
31-Oct-21 23:00 | 01-Nov-21 01:00 | ENMAX | Outage | 5B138-5BT7 (ENMAX 5) | relay replacement. 5.8TR, commissioning checks | 2 Hours
Continuous |
|
01-Nov-21 07:00 | 02-Nov-21 17:00 | EPCOR | Outage | 1164L (816s Petrolia - EPCOR Riverview), RW2401 (EPCOR Riverview), RW2402 (EPCOR Riverview) | RWDS2 / RWDS3 / RWDS11 adjustments | 1.42 Days
Continuous |
|
01-Nov-21 07:00 | 02-Nov-21 17:00 | ENMAX | RB | 1.80L (ENMAX 1 - ENMAX 28) | tree trimming | 1.42 Days
Daily |
|
01-Nov-21 07:00 | 04-Nov-21 17:00 | ALTALINK | TE | 285S East Camrose | T2 A protection outage to upgrade RS485 circuit to 4 wire RS485 | 3.42 Days
Daily |
|
01-Nov-21 07:00 | 04-Nov-21 17:00 | ALTALINK | Trans Test | 285s T2 (285s East Camrose) | troubleshoot T2 Tap changer control for Raise/Lower and Auto/Manual indication and control: functionally operate taps (+/-1) to prove control and indication | 3.42 Days
Daily |
|
01-Nov-21 07:00 | 02-Nov-21 17:00 | ALTALINK | IO | Riverview & 1164L Epcor - Info | Epcor 240kV Bus 1/2 and 1164L @ Riverview and Petrolia E816S, RWDS2 / RWDS3 / RWDS11 adjustments | 1.42 Days
Daily |
|
01-Nov-21 07:00 | 20-Nov-21 17:00 | ALTALINK | TE | 17S Benalto | required for 17s P&C upgrade project | 19.46 Days
Daily |
|
01-Nov-21 07:00 | 20-Nov-21 17:00 | ALTALINK | TE | 17s RTU/SCADA (17s Benalto) | RTU updates required for 17s P&C upgrade project | 19.46 Days
Daily |
|
01-Nov-21 07:00 | 23-Nov-21 17:30 | ALTALINK | TE | 39s RTU/SCADA (39s Bickerdike) | SCADA update for 39s 240KV Expansion Project for new 39s 1152, 1552, 1652, 1752 associated protections | 22.48 Days
Daily |
|
01-Nov-21 07:00 | 25-Nov-21 21:00 | EPCOR | Outage | VHBB2 (Rossdale) | breaker outage | 24.63 Days
Continuous |
|
01-Nov-21 07:30 | 02-Nov-21 17:30 | ALTALINK | TE | 138s Windy Flats RTU/SCADA | update RTU configuration to add new battery monitoring alarm | 1.42 Days
Continuous |
|
01-Nov-21 07:30 | 12-Nov-21 17:30 | ALTALINK | RB | 113L (20s Ghost - 33s Spray) | scope of work includes vegetation clearing between structures 1 and 91 | 11.46 Days
Daily |
|
01-Nov-21 07:30 | 09-Nov-21 17:30 | ALTALINK | TE | 151s RTU/SCADA (151s Strathmore) | SCADA RTU/HMI update | 8.46 Days
Continuous |
|
01-Nov-21 07:30 | 15-Nov-21 17:30 | ALTALINK | RB | 604L (149s Nisku - 155s Blackmud) | crews building new line beside 604L between structures 22 - 36 | 14.46 Days
Daily |
|
01-Nov-21 07:30 | 04-Nov-21 17:30 | ALTALINK | RB | 897L (38s East Edmonton - 45s Bretona) | RB for component replacements and fire mitigation on 908L Str's range 233-298 | 3.42 Days
Daily |
|
01-Nov-21 07:30 | 04-Nov-21 17:30 | ALTALINK | RB | 780L (38s East Edmonton - 522s Cooking Lake) | RB for component replacements and fire mitigation on 908L Str's range 233-298 | 3.42 Days
Daily |
|
01-Nov-21 08:00 | 05-Nov-21 17:30 | ALTALINK | TE | 42s RTU/SCADA (42s Sarcee) | Supervisory outage to update RTU configuration | 4.4 Days
Daily |
|
01-Nov-21 08:00 | 09-Nov-21 17:00 | ALTALINK | TE | 121s RTU/SCADA (121s Brooks) | add and commission new RTU/HMI alarms for P&C relay moves | 8.42 Days
Continuous |
|
01-Nov-21 08:00 | 07-Nov-21 16:00 | ENMAX | Outage | 38.83L (ENMAX 38 - ENMAX 39) | breaker refurbishments | 6.38 Days
Continuous |
|
01-Nov-21 08:00 | 07-Nov-21 16:00 | ALTALINK | IO | 38.83L (C38s-C39s) OOS - Enmax Info | HPL breaker refurbishments on 39B138-38.83 | 6.38 Days
Continuous |
|
01-Nov-21 08:00 | 13-Nov-21 18:00 | SUNCOR | Outage | 29EDD-1 260kV North Bus 1 (29EDD-1 Millennium), 29EDD-1 29EDD1s152 (29EDD-1 Millennium), 29EDD-1 29EDD1s452 (29EDD-1 Millennium) | preventative maintenance | 12.46 Days
Continuous |
|
01-Nov-21 08:00 | 08-Nov-21 12:00 | ATCO | RB | 7L60 (780s Lubicon - 827s Cranberry Lake), 7L94 (827s Cranberry Lake - 878s Kidney Lake) | climbing inspection on 7L94 | 7.21 Days
Continuous |
|
01-Nov-21 08:00 | 01-Nov-21 18:00 | ALTALINK | TE | AltaLink Radio Tower, 438s RTU/SCADA (438s Westlock) | upgrade 9374R MPLS node and upgrade radio | 10 Hours
Daily |
|
01-Nov-21 08:30 | 05-Nov-21 17:00 | ATCO | TE | 856S Kinosis, 856s Kinosis RTU/SCADA | replace 2032-3 with RTAC and test all soft alarms back to RTU | 4.35 Days
Continuous |
|
01-Nov-21 09:00 | 05-Nov-21 17:30 | ATCO | Outage | 2075S 500SST1, 2075S 500SST2 | Breaker thermal window installs in LV1 & LV2.
As Each Station service is removed-from and returned-to service the 240Kv breakers will be opened temporarily to allow for isolating the low voltage devices. (2075S 920 & 2075S 921 for 500SST1) & (2075S 904 & 2075S 905 for 500SST2) One LV will be performed at a time, then the other switched out. |
4.35 Days
Continuous |
|
01-Nov-21 09:00 | 08-Nov-21 18:00 | ALTALINK | Outage | 763L (158s Vauxhall - 257s Hull) | components 763L Str's Range (423-515) | 7.42 Days
Continuous |
|
01-Nov-21 09:00 | 05-Nov-21 15:30 | ATCO | Outage | 757s 702 (757s Battle River), 757s 702B (757s Battle River) | PRC005 work on 702 Breaker | 4.27 Days
Continuous |
|
01-Nov-21 09:00 | 12-Nov-21 16:00 | ATCO | Outage | 834s 501 (834s Wesley Creek), 834s 502 (834s Wesley Creek), 834s 503 (834s Wesley Creek), 834s 502R (834s Wesley Creek) | Install oil containment around 902T | 11.33 Days
Continuous |
|
01-Nov-21 09:30 | 20-Nov-21 18:00 | ALTALINK | Outage | 17s 138kV Bus 4 & T2 TX18477 - Advice, 17s 138kV Bus 4 (17s Benalto), 17s T2 (17s Benalto) | Replace 138kv Bus 4 bus prots, Replace breaker fails on s92, s85, s848X Replace s85 sync check, Replace line protections on 848L, Tie in new 138B3 'B' CT cont, and Tie in new 138B3 'B' CT cont | 19.4 Days
Continuous |
|
01-Nov-21 10:00 | 04-Nov-21 17:00 | ALTALINK | RB | 718L (250p Bighorn Plant - 263s Strachan) | component replacements 718L (Str's range 70-271) | 3.29 Days
Daily |
|
01-Nov-21 10:00 | 05-Nov-21 17:00 | ALTALINK | TE | 285s RTU/SCADA (285s East Camrose) | network switch upgrades | 4.29 Days
Daily |
|
01-Nov-21 10:00 | 08-Nov-21 09:00 | REDDEER | Outage | 194s T1 (194s South Red Deer) | relay testing and maintenance | 7 Days
Continuous |
|
01-Nov-21 11:00 | 10-Nov-21 17:30 | ALTALINK, EPCOR | RB | 920L (37s North Calder - 557s Castle Downs) | replace 37s77 & 37s79 switches, maintenance on 37s76 including first trip testing, replace grading caps on 37s76 | 9.31 Days
Continuous |
|
01-Nov-21 11:00 | 10-Nov-21 17:30 | ALTALINK, EPCOR | RB | 930L (37s North Calder - Poundmaker) | replace 37s77 & 37s79 switches, maintenance on 37s76 including first trip testing, replace grading caps on 37s76 | 9.31 Days
Continuous |
|
01-Nov-21 11:00 | 10-Nov-21 17:30 | ALTALINK | Outage | 905L (19s Wabamun - 37s North Calder), 37s 76 (37s North Calder), 37s 82 (37s North Calder) | replace 37s77 & 37s79 switches, salvage 37s74 and maintenance on 37s76 including first trip testing | 9.31 Days
Continuous |
|
01-Nov-21 11:00 | 04-Nov-21 18:00 | ALTALINK | Outage | 89s T2 (89s Ellerslie), 89s Ellerslie 240kV Bus 2, 89s 1652 (89s Ellerslie), 89s 852 (89s Ellerslie), 89s 452 (89s Ellerslie) | Replace 240kV PTs 89s91. Maintenance on 89s8, 89s16, 89s32. Trip testing from replacement 89s1252 breaker fail relay | 3.29 Days
Continuous |
|
01-Nov-21 11:00 | 04-Nov-21 18:00 | ALTALINK, EPCOR | RB | 947L (89s Ellerslie - 987s Clover Bar) | to replace 240kV PTs 89s91, maintenance on 89s8, 89s16, 89s32 | 3.29 Days
Continuous |
|
01-Nov-21 11:00 | 05-Nov-21 17:30 | ATCO | TE | 789S 7L59 Protection Relay | Settings change for work at 786S High Level (GOI 2-59684) | 4.27 Days
Continuous |
|
01-Nov-21 11:01 | 05-Nov-21 17:30 | ATCO | Outage | 786s 701T (786s High Level), 786s 701TCS (786s High Level) | CCT SW S&C complete test and maintenance, Transformer Major Testing | 4.27 Days
Continuous |
|
01-Nov-21 11:30 | 03-Nov-21 17:30 | ALTALINK | Outage | 447s T1 (447s Enchant) | bushing replacement | 2.25 Days
Continuous |
|
01-Nov-21 12:00 | 04-Nov-21 18:00 | ALTALINK, EPCOR | Outage | 908L (38s East Edmonton - 89s Ellerslie), 52s T2 (52s East Industrial) | component replacements and fire mitigation on Str's range 233-298 | 3.25 Days
Continuous |
|
01-Nov-21 12:00 | 04-Nov-21 18:00 | ALTALINK, EPCOR | RB | 1059L (38s East Edmonton - EP 803s Lambton), 1059AL (52s East Industrial - 1059L tap) | RB for component replacements and fire mitigation on 908L Str's range 233-298 | 3.25 Days
Continuous |
|
01-Nov-21 12:00 | 04-Nov-21 18:00 | EPCOR | RB | 1058L (657s Summerside - EP 803s Lambton) | RB for component replacements and fire mitigation on 908L Str's range 233-298 | 3.25 Days
Continuous |
|
01-Nov-21 12:00 | 04-Nov-21 18:00 | EPCOR, ALTALINK | IO | ALTALINK - 908L(89s-E52s-38s) - DE-ENERGIZE LINE, 908L (38s East Edmonton - 89s Ellerslie), 908AL (52S East Industrial - 908L tap) | Component replacements and fire mitigation on Str's Range 233-298 | 3.25 Days
Continuous |
|
01-Nov-21 12:00 | 04-Nov-21 18:00 | ALTALINK, EPCOR | RB | 1059L (EP 803s Lambton - 1059AL tap) | RB for component replacements and fire mitigation on 908L Str's range 233-298 | 3.25 Days
Continuous |
|
01-Nov-21 12:00 | 04-Nov-21 18:00 | EPCOR | IO | ALTALINK - 1058L - RB @E803s Lambton & E657s Summerside | RB for component replacements and fire mitigation on 908L Str's Range 233-298 | 3.25 Days
Continuous |
|
01-Nov-21 12:00 | 02-Nov-21 16:00 | ALTALINK | Outage | 434s T1 (434s East Stony Plain) | Install bird cover ups on T1 25 kV bushings and 36L feeder conductor terminations | 28 Hours
Continuous |
|
01-Nov-21 12:00 | 04-Nov-21 17:30 | ALTALINK | Outage | 316s T1 (316s West Crossfield) | doble and maintenance | 3.23 Days
Continuous |
|
01-Nov-21 12:00 | 01-Nov-21 18:00 | ALTALINK | TE | WAP1s MPLS - TPR/RTU | Upgrade MPLS node. Loss of visibility of WAP1s 2 hours in the timeframe indicated. Also affects 723L/724L TPR which causes slow fault clearing and removes the anti islanding scheme from service. WAP1s must be offline for this work, coordinated with their planned shutdown. | 6 Hours
Daily |
|
01-Nov-21 12:30 | 05-Nov-21 17:30 | ALTALINK | Outage | 245s T2 (245s Seebe) | TX protection replacements | 4.21 Days
Continuous |
|
01-Nov-21 13:00 | 04-Nov-21 17:00 | ALTALINK | TE | 245s RTU/SCADA (245s Seebe) | update RTU database | 3.17 Days
Daily |
|
01-Nov-21 13:30 | 01-Nov-21 14:30 | ALTALINK | TE | 245S Seebe | 138kV bus protection relays to isolate the CT contributions safely from the T2 high side CTs | 60 Mins
Daily |
|
01-Nov-21 14:30 | 03-Nov-21 17:00 | ALTALINK | TE | 163S Amoco Empress | troubleshoot/repair VT fuse fail issue | 2.1 Days
Daily |
|
01-Nov-21 14:30 | 03-Nov-21 17:00 | ALTALINK | TE | 394S Empress | troubleshoot/repair VT fuse fail issue | 2.1 Days
Daily |
|
02-Nov-21 06:00 | 02-Nov-21 18:00 | ALTALINK | TE | 5S East Calgary | relay replacement, wring changes, relay settings testing, commissioning checks | 12 Hours
Continuous |
|
02-Nov-21 06:45 | 02-Nov-21 17:15 | ALTALINK | IO | 23.80L (74s-C23s) RB - Enmax | tree trimming | 10.5 Hours
Daily |
|
02-Nov-21 07:00 | 02-Nov-21 17:00 | ENMAX, ALTALINK | RB | 23.80L (74s Janet - ENMAX 23) | tree trimming | 10 Hours
Daily |
|
02-Nov-21 07:00 | 18-Nov-21 17:00 | ALTALINK, EPCOR | RB | 1045L (310p Sundance - 320p Keephills - 805s Jasper) | Epcor work in proximity to 1045L | 16.46 Days
Daily |
|
02-Nov-21 08:00 | 04-Nov-21 17:00 | ATCO, SUNCOR | TE | 635PL9-1000 (2005s Secord - 635EDD-1000), 635PL9-1001 (2005s Secord - 635EDD-1000), 2005S Secord | raise line. move both A&B protections to the same fiber one at a time, complete PRC005 relays and line end to ends | 2.38 Days
Continuous |
|
02-Nov-21 08:00 | 11-Nov-21 17:00 | ATCO | IO | 9L1035 | AltaLink has scheduled 1035L(244s – A2075s) outage | 9.42 Days
Continuous |
|
02-Nov-21 08:00 | 11-Nov-21 17:00 | ALTALINK | RB | 1034L (244s Bowmanton - 324s Cassils) | required for completion of damper replacement CRU scope between structures 300 & 367 | 9.42 Days
Daily |
|
02-Nov-21 08:00 | 11-Nov-21 17:00 | ATCO, ALTALINK | Outage | 1035L (244s Bowmanton - 2075s Newell) | urgent damper replacement | 9.42 Days
Continuous |
|
02-Nov-21 08:00 | 16-Nov-21 17:00 | SUNCOR | Outage | 635EDD-1000 PT-1001 (635EDD-1000), 635PL9-1001 (2005s Secord - 635EDD-1000) | line structure change for line lift; line & transformer maintenance and protection work | 14.42 Days
Continuous |
|
02-Nov-21 08:00 | 04-Nov-21 17:00 | ALTALINK, TRANSALTAEM | RB | 723L (150s Clyde - 438s Westlock), 723L (69s North Barrhead - 724L tap), 724L (500s Flatbush - 723L tap), 724L (723L tap - 724AL tap), 724AL (WAP-7L1 - 724AL tap), 723L (438s Westlock - 724L tap) | urgent repair arms and insulator replacements 724L (Str's range 103-106) , live line work | 2.38 Days
Continuous |
|
02-Nov-21 08:00 | 03-Nov-21 16:00 | ENMAX | Outage | 13.1TR (ENMAX 13) | tripping hazard, oil sampling | 1.33 Days
Continuous |
|
02-Nov-21 08:00 | 02-Nov-21 16:00 | ENMAX | Outage | 37.2TR (ENMAX 37) | oil sampling, replace LTC mech heaters | 8 Hours
Continuous |
|
02-Nov-21 08:00 | 16-Nov-21 17:00 | ATCO | IO | 635PL9-1001 | Suncor Fort Hills raising 260kV lines to accommodate new mine site overpass installation, maintenance and PRC-5 activities and protection end to end testing | 14.42 Days
Continuous |
|
02-Nov-21 08:00 | 31-Dec-21 16:19 | ATCO | TE | 802s Michichi Creek RTU/SCADA | program changes to the RTU | 59.39 Days
Continuous |
|
02-Nov-21 08:00 | 09-Nov-21 18:00 | SUNCOR | TE | Suncor T&D SCADA hardware and software major upgrade | Suncor AESO ICCP intermittent, Suncor AESO DNP intermittent, SCADA visibility loss intermittent ( 20 -60 minutes every day) during cutover or failover. | 7.46 Days
Continuous |
|
02-Nov-21 09:00 | 04-Nov-21 15:00 | ALTALINK | TE | 385s RTU/SCADA (385s Spring Coulee) | RTU database update | 2.25 Days
Daily |
|
02-Nov-21 09:00 | 02-Nov-21 14:30 | ALTALINK | Outage | 142s 3 (142s Magcan), 142s C1 (142s Magcan) | replace dashpot, oil top up | 5.5 Hours
Daily |
|
02-Nov-21 09:00 | 02-Nov-21 16:30 | ATCO | Outage | 749S 702 | 749S 702 testing | 7.5 Hours
Continuous |
|
02-Nov-21 09:00 | 03-Nov-21 16:30 | ALTALINK | TE | 149S Nisku | relay settings change | 31.5 Hours
Daily |
|
02-Nov-21 09:00 | 03-Nov-21 17:00 | ALTALINK | TE | 510s RTU/SCADA (510s Sunnybrook) | update firmware | 1.33 Days
Daily |
|
02-Nov-21 10:30 | 09-Nov-21 17:00 | ALTALINK | TE | 370S North Lethbridge | relay setting changes and functional testing to trip the new 1552 breaker, one at a time with redundant protection | 7.31 Days
Continuous |
|
02-Nov-21 11:00 | 02-Nov-21 17:00 | ATCO | Outage | 7L23, 7L23 (732s Mitsue - 796s Nipisi) | High Load move | 6 Hours
Continuous |
|
02-Nov-21 12:00 | 04-Nov-21 17:00 | ALTALINK | TE | 254s RTU/SCADA (254s Coaldale) | install new config he RTU will require a reboot once the new config is in | 2.21 Days
Continuous |
|
02-Nov-21 12:00 | 04-Nov-21 17:00 | ALTALINK | TE | 254s T2 (254s Coaldale) | protection outages required to complete alarm splitting on T2 as part of ACC visibility upgrade program | 2.21 Days
Continuous |
|
02-Nov-21 14:00 | 02-Nov-21 16:00 | ALTALINK | TE | 385S Spring Coulee | setting modifications, redundant protections in place at all times | 2 Hours
Daily |
|
03-Nov-21 06:30 | 03-Nov-21 17:30 | ALTALINK | IO | 1139L (367s-Riverview) Epcor - Advice | Epcor RWDS12 adjustment | 11 Hours
Daily |
|
03-Nov-21 07:00 | 03-Nov-21 17:00 | ALTALINK | IO | 370S North Lethbridge | isolate breaker 370s10 (25 kV) to complete P&C cutovers, remove and add trips, modify block close | 10 Hours
Daily |
|
03-Nov-21 07:00 | 03-Nov-21 17:00 | EPCOR | Outage | 1139L (367s Harry Smith - EPCOR Riverview), RW2403 (EPCOR Riverview), RW2405 (EPCOR Riverview) | RWDS12 adjustment | 10 Hours
Continuous |
|
03-Nov-21 07:00 | 03-Nov-21 17:00 | ENMAX | RB | 3.84L (ENMAX 3 - ENMAX 13) | tree trimming | 10 Hours
Daily |
|
03-Nov-21 07:00 | 03-Nov-21 17:00 | ENMAX | RB | 24.82L (ENMAX 24 - ENMAX 65) | tree trimming | 10 Hours
Daily |
|
03-Nov-21 07:30 | 05-Nov-21 17:30 | ALTALINK | RB | 907L (77s Sagitawah - 122s Alberta Newsprint) | maintenance on structures 14, 83, 84, 96, 100, 101, 102, 106, 108, 110, 111, 112 and 122 | 2.42 Days
Daily |
|
03-Nov-21 07:30 | 04-Nov-21 17:30 | ALTALINK | TE | 336s RTU/SCADA (336s Fincastle) | update RTU configuration to add new battery monitoring alarm | 1.42 Days
Continuous |
|
03-Nov-21 07:30 | 04-Nov-21 17:30 | ALTALINK | RB | 428L (167s Ipiatik Lake - 818s Winefred) | required for installation of catch arm assembly on double circuit structure 428L5/457L7 | 1.42 Days
Continuous |
|
03-Nov-21 07:30 | 04-Nov-21 17:30 | ALTALINK | RB | 457L (167s Ipiatik Lake - 651s Kirby) | required for installation of catch arm assembly on double circuit structure 428L5/457L7 | 1.42 Days
Continuous |
|
03-Nov-21 07:30 | 03-Nov-21 17:30 | ATCO | RB | 9L939 (77s Sagitawah - 809s Louise Creek) | to facilitate 907L maintenance on structures 14, 83, 84, 96, 100, 101, 102, 106, 108, 110, 111, 112 and 122 | 10 Hours
Daily |
|
03-Nov-21 07:30 | 03-Nov-21 17:30 | ATCO | IO | 9L939 | Altalink requesting a reclose block on 9L939 from 809s | 10 Hours
Continuous |
|
03-Nov-21 07:45 | 03-Nov-21 12:15 | ALTALINK | IO | 9L933/933L (A801s-132s) Atco - R/B | HOP on 9L933 to install armor rod and weights @ structure 164 | 4.5 Hours
Daily |
|
03-Nov-21 08:00 | 03-Nov-21 18:00 | Syncrude | TE | Syncrude ICCP Outage | SCADA - server update
|
10 Hours
Daily |
|
03-Nov-21 08:00 | 03-Nov-21 20:00 | ATCO | TE | ATCO Radio Tower, ATCO TPR Outage | Wesley Creek_S-Telecom, Weberville_T-Telecom - carrier cutover from the Constellation to IRU 600 radio - antenna replacement | 12 Hours
Continuous |
|
03-Nov-21 08:00 | 03-Nov-21 16:00 | ENMAX | Outage | 1.84L (ENMAX 1 - ENMAX 5) | 5sub TRV Project - investigate control wiring in circuit breaker | 8 Hours
Continuous |
|
03-Nov-21 08:00 | 08-Nov-21 16:00 | ALTALINK | TE | 419s RTU/SCADA (419s Chestermere) | 419s loading RAS to be migrated to new realys, alarms will be moved incrementally aligning with protection outages | 5.38 Days
Continuous |
|
03-Nov-21 08:00 | 03-Nov-21 12:00 | ATCO | RB | 9L933 (132s Ware Junction - 801s Anderson) | we require HOP on 9L933 to install armor rod and weights @ structure 164 | 4 Hours
Continuous |
|
03-Nov-21 08:00 | 03-Nov-21 17:00 | ALTALINK | TE | 63s RTU/SCADA (63s Red Deer) | update RTU database | 9 Hours
Daily |
|
03-Nov-21 08:00 | 28-Nov-21 17:00 | ATCO | Outage | 9L40 (732s Mitsue - 809s Louise Creek) | wiring for 903/904BF relays | 25.42 Days
Continuous |
|
03-Nov-21 08:00 | 05-Nov-21 16:00 | ENMAX | Outage | 8.5TR (ENMAX 8) | 8sub RTU commissioning | 2.33 Days
Continuous |
|
03-Nov-21 08:30 | 03-Nov-21 17:30 | ALTALINK | Outage | 385s T1 (385s Spring Coulee), 385s T2 (385s Spring Coulee) | wire CT secondary contributions to new 69 kV U/V protections | 9 Hours
Daily |
|
03-Nov-21 09:00 | 04-Nov-21 16:00 | ALTALINK | TE | 419s Chestermere | install and commission relays for 419s Overload RAS on 691L remove RAS from existing ‘A’ line protection relay | 31 Hours
Continuous |
|
03-Nov-21 09:00 | 05-Nov-21 16:00 | ALTALINK | IO | 419s RAS 'A' Relay | Chestermere 419s overload RAS 'A' to be OOS during cutover to new relays | 2.29 Days
Continuous |
|
03-Nov-21 23:00 | 04-Nov-21 03:00 | ALTALINK | Outage | 62s 11 (62s Brazeau) | maintenance | 4 Hours
Continuous |
|
04-Nov-21 03:00 | 04-Nov-21 07:00 | ALTALINK | Outage | 62s12 Advice for TransAlta | brushgear | 4 Hours
Continuous |
|
04-Nov-21 07:00 | 04-Nov-21 17:00 | ENMAX | RB | 2.81L (ENMAX 2 - ENMAX 9) | tree trimming | 10 Hours
Daily |
|
04-Nov-21 07:00 | 05-Nov-21 17:00 | ENMAX | RB | 11.82L (ENMAX 11 - ENMAX 14) | tree trimming | 1.42 Days
Daily |
|
04-Nov-21 07:00 | 04-Nov-21 19:30 | ALTALINK | Outage | 993s489 Enbridge - Advice | Enbridge to service switches 410-BUS-2-IS and 70-SWGR-1-IS. Enbridge to hang grounds at 410-BUS-2-IS and 70-SWGR-1- IS. Enbridge request to hang their own tag as well. | 12.5 Hours
Daily |
|
04-Nov-21 07:00 | 05-Nov-21 23:00 | ALTALINK | Outage | 216s 317s, 705L & 865L GOI, 705L (184s Petro-Canada Edmonton - 216s Knightsbridge), 865L (38s East Edmonton - 216s Knightsbridge) | Insulator replacement, switch maintenance, SCADA upgrade. | 1.67 Days
Continuous |
|
04-Nov-21 08:00 | 04-Nov-21 20:00 | ATCO | TE | ATCO TPR Outage | Wesley Creek_S-Telecom, Simon Lake_T-Telecom -carrier cutover from the constellation to IRU 600 radio | 12 Hours
Continuous |
|
04-Nov-21 08:00 | 04-Nov-21 13:00 | ALTALINK | Outage | 89s1952 - GOI, 89s 1952 (89s Ellerslie) | Trip testing from replacement 89s1252 breaker fail relay. | 5 Hours
Daily |
|
04-Nov-21 08:00 | 04-Nov-21 17:00 | ATCO | RB | 7L171 (802s Michichi Creek - 804s Wintering Hills) | 802S Michichi substation TCM upgrades tap up mobile sub | 9 Hours
Continuous |
|
04-Nov-21 08:00 | 04-Nov-21 16:00 | ENMAX | Outage | 162.3TR | Replace Counter on 162.3TR Tap Changer. Oil Sampling MT, TC. Filmax LTC Oil Filtration Maintenance. LV load to transfer Nov 4th approx. 1:30 am, return Nov 5th 1:30am | 8 Hours
Continuous |
|
04-Nov-21 09:00 | 04-Nov-21 16:00 | ALTALINK | TE | 151S Strathmore | relay maintenance | 7 Hours
Daily |
|
04-Nov-21 09:00 | 05-Nov-21 17:00 | ALTALINK | TE | 216s RTU/SCADA (216s Knightsbridge), 317s RTU/SCADA (317s Baseline) | SCADA upgrade | 1.33 Days
Daily |
|
04-Nov-21 10:30 | 04-Nov-21 13:30 | ALTALINK | Outage | 151s T1(Tx 18431) GOI | Complete connections for the transformer protection to trip to 252 breaker and function test. | 3 Hours
Daily |
|
04-Nov-21 11:00 | 04-Nov-21 14:29 | ALTALINK | Outage | 245s10 Advice, 245s 10 (245s Seebe) | Functional Trip Test (245s3E); re T2 protection replacements | 3.48 Hours
Daily |
|
04-Nov-21 13:00 | 04-Nov-21 17:30 | ALTALINK | Outage | 89s2252 - GOI, 89s 2252 (89s Ellerslie) | Trip testing from replacement 89s1252 breaker fail relay. | 4.5 Hours
Daily |
|
04-Nov-21 14:30 | 04-Nov-21 17:00 | ALTALINK | Outage | 777L (48s Pocaterra - 245s Seebe), 245s 777X (245s Seebe) | functional trip test (245s3E); re T2 protection replacements | 2.5 Hours
Daily |
AB-BC |
04-Nov-21 14:30 | 04-Nov-21 17:00 | ALTALINK | TE | 48s - 245s PLC - TPR/RTU | reboot PLC | 2.5 Hours
Daily |
|
05-Nov-21 07:00 | 22-Nov-21 17:00 | EPCOR | Outage | Summerside S/S Tx2 Outage, 657s T2 (657s Summerside) | Tx2 isolation required for SUBT23 cell install as part of Southeast Expansion Project | 17.46 Days
Continuous |
|
05-Nov-21 08:00 | 06-Nov-21 16:00 | ENMAX | Outage | 6.80L, 6.80L (ENMAX 6 - ENMAX 35) | 6 sub cable trench replacement | 1.33 Days
Continuous |
|
05-Nov-21 08:00 | 05-Nov-21 10:29 | ALTALINK | Outage | 245s3E (3L) Advice, 3L (245s Seebe - 3AL Tap) | Functional Trip Test (245s3E); re T2 protection replacements | 2.48 Hours
Daily |
|
05-Nov-21 08:00 | 05-Nov-21 10:00 | ALTALINK | TE | 765L (151s Strathmore - 419s Chestermere) | install and commission relays for 419s overload RAS, A/21 RAS (765L) out-of-service during cutover | 2 Hours
Daily |
|
05-Nov-21 08:00 | 05-Nov-21 16:00 | ENMAX | Outage | 162.4TR. | 162.4TR Corrective -162MD138-162.4TR north phase not fully closed. LV load transfer Nov. 5th approximately 1:30am return to normal Nov 6th approx. 1:30am. | 8 Hours
Continuous |
|
05-Nov-21 08:00 | 05-Nov-21 16:00 | ENMAX | Outage | 3.4TR | LTC cabinet - heater fails | 8 Hours
Continuous |
|
05-Nov-21 10:30 | 05-Nov-21 13:00 | ALTALINK | Outage | 245s58X (58L) Advice, 58L (32s Barrier - 245s Seebe) | Functional Trip Test (245s3E); re T2 protection replacements | 2.5 Hours
Daily |
|
05-Nov-21 12:00 | 05-Nov-21 17:00 | ALTALINK | Outage | 89s1152 (946L) - GOI, 89s 1152 (89s Ellerslie) | Trip testing from replacement 89s1252 breaker fail relay. Outage coincides with 277255 89s1252 - GOI and will take 946L OOS. | 5 Hours
Daily |
|
05-Nov-21 12:30 | 05-Nov-21 15:30 | ALTALINK | TE | 245S Seebe | load readings to be taken on T2 with new protections | 3 Hours
Daily |
|
05-Nov-21 13:30 | 05-Nov-21 14:30 | ALTALINK | TE | 245S Seebe | 138kV bus protection relays to isolate the CT contributions safely from the T2 high side CTs | 60 Mins
Daily |
This document and the information contained herein are based upon information and data which by their nature contain a degree of uncertainty and are subject to change. In addition, this document may contain information and data from public sources and/or third parties, which have been assumed to be accurate and complete and have not been verified. Accordingly, the Independent System Operator, operating as the Alberta Electric System Operator (the "AESO") makes no warranty, representation or guarantee, express or implied, with respect to this document or the information contained herein, including, but not limited to, any warranty, representation or guarantee of accuracy, completeness, timeliness, reliability, availability, absence of computer virus, non- infringement, merchantability or suitability for any purpose. Under no circumstances will the AESO, its members, officers, employees, contractors or agents, or any of their respective affiliates, be liable for any errors or omissions in, or any losses, damages or claims whatsoever, whether in contract, tort or otherwise, arising from use of or reliance upon, this document or any information contained herein. © 2009 Alberta Electric System Operator. All rights reserved |