Alberta Electric System Operator | |
Long Range Significant Transmission Outages for the period of 24 months starting 2021-10-16 | |
The table below contains the significant transmission outages submitted as tentative to the AESO. These Outages have not yet necessarily been approved, but are listed for awareness and coordination purposes. An Outage has been considered significant for this table if it meets any one (1) or more of the following criteria: |
|
|
|
Note: Where a transmission outage requires generation curtailments, the adjustments to generation will typically happen in the hours before the scheduled transmission outage and in the hour after the element is returned to service. | |
Previous Version | |
Download CSV | |
Owner | From | To | Duration | Element | Scheduled Activity | Affected Intertie |
---|---|---|---|---|---|---|
ALTALINK | 06-Sep-21 07:00 | 20-Oct-21 20:00 | Continuous |
44.54 Days
62s 11 (62s Brazeau) | maintenance | |
ALTALINK | 10-Sep-21 12:30 | 01-Nov-21 16:30 | 52.17 Days
Continuous |
320p 2089 (320p Keephills) | maintenance | |
EPCOR | 13-Sep-21 07:00 | 15-Nov-21 17:00 | 63.46 Days
Continuous |
T3 (Poundmaker) | 240 kV ring re-configuration (P1649) | |
EPCOR | 27-Sep-21 07:00 | 12-Nov-21 17:00 | 46.46 Days
Continuous |
EP 511s Victoria T5 (EP 511s Victoria), CV5 (EP 511s Victoria - 557s Castle Downs) | regasketing Victoria T5 | |
ENMAX, ALTALINK | 27-Sep-21 08:00 | 24-Oct-21 16:00 | 27.33 Days
Continuous |
7.82L (42s Sarcee - ENMAX 7) | line relocation at 101 street | |
ALTALINK | 28-Sep-21 09:30 | 17-Oct-21 18:00 | 19.35 Days
Continuous |
320p T6 (320p Keephills), 320p PS2 (320p Keephills), 320p 2652 (320p Keephills), 320p 2852 (320p Keephills) | maintenance, leaks, CT replacement, model 11 relay replacements | |
ATCO | 04-Oct-21 08:01 | 24-Oct-21 17:00 | 20.37 Days
Continuous |
9L02 (809s Louise Creek - 813s Little Smoky), 809s 903 (809s Louise Creek), 809s 910 (809s Louise Creek) | Louise Creek rebuild project | |
SUNCOR | 06-Oct-21 08:00 | 21-Oct-21 17:00 | 15.38 Days
Continuous |
635PL7-1004 (635EDD-1001 - 635EDD-1002), 635PT-1036 (635EDD-1001), 635EDD-1001 635-752-651 (635EDD-1001), 635EDD-1001 635-752-652 (635EDD-1001), 635EDD-1001 635-752-653 (635EDD-1001) | dia 5 equipment outage at 635EDD-1001 | |
BCH | 11-Oct-21 09:00 | 05-Nov-21 17:00 | 25.33 Days
Continuous |
2L112 (Boundary - Nelway) | oil containment install, BC Maintenance does not affect the Alberta ATC | AB-BC |
REDDEER, ALTALINK | 12-Oct-21 15:00 | 25-Oct-21 09:00 | 12.75 Days
Continuous |
209S Timberlands, 209s 768W (209s Timberlands), 464L (87s Gaetz - 209s Timberlands), 768L (209s Timberlands - 217s North Red Deer), 209s T1 (209s Timberlands) | City of Red Deer: P&C relay testing and maintenance | |
ALTALINK | 13-Oct-21 07:00 | 16-Oct-21 18:00 | 3.46 Days
Continuous |
927L (102s Langdon - 356s Milo) | structure maintenance | |
ALTALINK | 14-Oct-21 07:00 | 16-Oct-21 18:00 | 2.46 Days
Continuous |
1212L (89s-12s) - GOI, 1212L (12s Heartland - 89s Ellerslie) | Scope of work includes maintenance on structures 31, 42, 46, 71 and 76 | |
ALTALINK | 17-Oct-21 07:15 | 19-Oct-21 17:45 | 2.44 Days
Continuous |
820L (254s - 315s - 67s) GOI, 820L (254s Coaldale - 820AL tap), 820AL (315s Chin Chute - 820L tap), 820L (67s Stirling - 820AL tap) | Scope of work includes maintenance on structures 160, 161, 168, 175, 176, 177, 179, 187, 190, 197 and 198 | |
ALTALINK | 18-Oct-21 07:30 | 22-Oct-21 17:30 | 4.42 Days
Continuous |
510s ACF14 - GOI, 510s ACF14 (510s Sunnybrook) | Replace point on wave relay associated with 510s1452 and ACF14 TX 18882 | |
Syncrude | 18-Oct-21 08:00 | 18-Oct-21 20:00 | 12 Hours
Daily |
Significant Outage: T2 Transformer (260/72KV) in D05 Substation Following Circuit Breakers will be operated to isolate T2: 516, 513, 78 Following MOD's will be operated to isolate T1: 516A, 516B, 513A, 513B, 509, 78A, 78B | Significant Outage:
T2 Transformer (260/72KV) in D05 Substation Following Circuit Breakers will be operated to isolate T2: 516, 513, 78 Following MOD's will be operated to isolate T1: 516A, 516B, 513A, 513B, 509, 78A, 78B |
|
ALTALINK | 18-Oct-21 08:00 | 29-Oct-21 18:00 | 11.42 Days
Continuous |
1034L(324s - 244s) GOI (URGENT), 1034L (244s Bowmanton - 324s Cassils) | GOI required for P5 Urgent Repair damper scope between structures 82 and 262. *Completion of Damper Replacement CRU scope between Structures 300 & 367 will coincide with this outage. | |
ALTALINK | 18-Oct-21 08:55 | 18-Oct-21 18:30 | 9.58 Hours
Daily |
941L(M120 - Hay Lake) GOI | Annual maintenance routine - in conjunction with south bound and 1201L outage. The following maintenance items will be completed; K-Line Line maintenance | |
ALTALINK | 18-Oct-21 08:55 | 18-Oct-21 18:30 | 9.58 Hours
Continuous |
M120s Station GOI | Annual maintenance routine - in conjunction with south bound and 1201L outage. The following maintenance items will be completed; RTU outage as needed to complete ORION change out and complete alarm checks to ACC and timer modification as needed… station will be out, PS1; diverter, filters, exciter tank conservator bladder, switch maintenance, Relay PMs for site… operating lockouts and AC station service outage for testing ATS | |
MONTANA | 18-Oct-21 09:00 | 18-Oct-21 18:00 | 9 Hours
Continuous |
MATL (120s Picture Butte - Montana) | annual maintenance routine | AB-MATL |
MONTANA | 18-Oct-21 09:00 | 18-Oct-21 18:00 | 9 Hours
Continuous |
MATL (120s Picture Butte - Montana) | annual maintenance routine | AB-MATL |
ATCO | 18-Oct-21 09:00 | 20-Oct-21 16:15 | 2.3 Days
Continuous |
888S 906, 888S 906 Recloser, 888s 906 (888s Dover) | Breaker Maintenance 906 | |
BCH | 18-Oct-21 09:00 | 21-Oct-21 17:00 | 3.33 Days
Continuous |
5L94 (Cranbrook - 102s Langdon) | NERC PM | AB-BC |
ALTALINK | 18-Oct-21 09:00 | 29-Oct-21 18:00 | 11.38 Days
Continuous |
1201L (520s - B2s) GOI, 1201L (520s Bennett - BCH Cranbrook) | components-structure range 383-464 | AB-BC |
MONTANA | 18-Oct-21 09:00 | 29-Oct-21 18:00 | 11.38 Days
Continuous |
MATL (120s Picture Butte - Montana) | align with 1201L outage | AB-MATL |
ALTALINK | 18-Oct-21 09:30 | 19-Oct-21 16:30 | 31 Hours
Continuous |
42s70 GOI, 42s 70 (42s Sarcee) | Migrate and commission all 42s70 (1052) at 42s Sarcee associated protections, synch check, breakers, breaker fail alarms, status, controls, metering and remote access to new RTU and LAN. | |
ALTALINK | 18-Oct-21 10:00 | 18-Oct-21 17:30 | 7.5 Hours
Daily |
67s T2(TX18703) GOI, 67s T2 (67s Stirling) | investigate and replace failing LTC controller | |
ATCO | 18-Oct-21 10:00 | 20-Oct-21 12:00 | 2.08 Days
Continuous |
800S 701, 7L75, 7L75 (ATC 793s West Peace River - 800s Friedenstal) | 800S Friedenstal Breaker 701 Maintenance | |
ALTALINK | 18-Oct-21 10:05 | 25-Oct-21 17:30 | 7.31 Days
Continuous |
520s552 GOI, 520s 552 (520s Benett) | 520s552 Replace "A Phase" pole, & Corona Ring Bent Replacement | |
ALTALINK | 18-Oct-21 11:00 | 21-Oct-21 18:00 | 3.29 Days
Continuous |
89s T1 & 240kV West Bus 1 - GOI, 89s T1 (89s Ellerslie), 289s 240kV Bus 1 (289s Saunders Lake) | Replace 240kV PTs 89s80 & 89s90 | |
ATCO | 18-Oct-21 12:00 | 01-Nov-21 11:00 | 13.96 Days
Continuous |
7L59, 7L59 (789s Keg River - 7L59 tap) | Replace crossarms and replace poles | |
ALTALINK | 18-Oct-21 17:25 | 23-Oct-21 18:30 | 5.05 Days
Continuous |
M120s and 941L(M120 - Hay Lake) GOI | Annual maintenance routine - in conjunction with south bound and 1201L outage. The following maintenance items will be completed; Rising Edge -RTU outage as needed to complete ORION change out and complete alarm checks to ACC and timer modification as needed… station will be out -PS1; diverter, filters, exciter tank conservator bladder -switch maintenance -Relay PMs for site… operating lockouts… -AC station service outage for testing ATS KLINE -line maintenance | |
MONTANA | 18-Oct-21 18:00 | 23-Oct-21 18:00 | 5 Days
Continuous |
MATL (120s Picture Butte - Montana) | annual maintenance routine | AB-MATL |
ALTALINK | 19-Oct-21 07:00 | 23-Nov-21 18:00 | 35.5 Days
Continuous |
39s1052 - GOI, 39s 1052 (39s Bickerdike) | GOI to allow for the addition of new breaker 39s1152 and associated equipment. New 39s1152 is Being installed between 39s11A, and 39s31, Part of 240kV Expansion cascade project. and Add new 39s973 MOD which will remain normal open until the 973L is relocated to this diameter.Add New 39s56 switch (P2032) | |
ALTALINK, Lethbridge | 19-Oct-21 08:00 | 19-Oct-21 13:00 | 5 Hours
Continuous |
667L (146s Lethbridge MacDonald - 370s North Lethbridge), 146s 667 (146s Lethbridge McDonald) | test trip and breaker fail trip | |
ALTALINK | 19-Oct-21 09:15 | 20-Oct-21 17:00 | 31.75 Hours
Continuous |
42s C3 GOI, 42s C3 (42s Sarcee) | Techs will require 42sC3 Cap bank OOS to complete PRC005 compliant relay maintenance and trip path verifications. | |
ALTALINK | 19-Oct-21 09:15 | 20-Oct-21 17:00 | 31.75 Hours
Continuous |
42s C3 Advice | Techs will require 42sC3 Cap bank OOS to complete PRC005 compliant relay maintenance and trip path verifications. | |
EPCOR | 20-Oct-21 07:00 | 22-Oct-21 17:00 | 2.42 Days
Continuous |
C2404 and C2406 @ Cloverbar E987S, 987s C2404 (987s Clover Bar), 987s C2406 (987s Clover Bar) | 240CVT 85/86/87 and C2404 Bay CT's Doble | |
ALTALINK | 20-Oct-21 09:30 | 21-Oct-21 17:30 | 1.33 Days
Continuous |
77s26 - GOI Urgent | Replace failed grading capacitors and do an internal inspection on the phase's contacts that had the cap failure | |
ATCO | 20-Oct-21 12:00 | 22-Oct-21 17:00 | 2.21 Days
Continuous |
800S 702, 7L73, 7L73 (730s Rycroft - 800s Friedenstal) | 800S Friedenstal Breaker 702 Maintenance | |
ALTALINK | 21-Oct-21 07:00 | 21-Oct-21 18:00 | 11 Hours
Daily |
913L (338s - 69s) - GOI, 913L (69s North Barrhead - 338s Cherhill) | Crews performing mtce. on Structure #913L124 | |
SUNCOR | 22-Oct-21 08:00 | 23-Oct-21 18:00 | 1.42 Days
Continuous |
29EDD-71 | 29EDD71; BREAKER FUNCTIONAL TEST REG 5y_A
29-752-4613;29-752-4614;29-752-4621;29-752-4622;29-752-4623 29-752-4624; 29-752-4631; 29-752-4632; 29-752-4633; 29-752-4634 29-752-4641;29-752-4642;29-752-4644 29-752-4651;29-752-4652;29-752-4654 |
|
ALTALINK | 23-Oct-21 17:25 | 29-Oct-21 19:00 | 6.07 Days
Continuous |
M120s Station GOI | Annual maintenance routine - in conjunction with south bound and 1201L outage. The following maintenance items will be completed; RTU outage as needed to complete ORION change out and complete alarm checks to ACC and timer modification as needed… station will be out, PS1; diverter, filters, exciter tank conservator bladder, switch maintenance, Relay PMs for site… operating lockouts and AC station service outage for testing ATS. KLINE line maintenance | |
MONTANA | 23-Oct-21 18:00 | 29-Oct-21 18:00 | 6 Days
Continuous |
MATL (120s Picture Butte - Montana) | annual maintenance routine | AB-MATL |
ATCO | 24-Oct-21 17:01 | 25-Oct-21 07:59 | 14.97 Hours
Continuous |
809s 903 (809s Louise Creek) | Louise Creek rebuild project | |
EPCOR | 25-Oct-21 07:00 | 29-Oct-21 17:00 | 4.42 Days
Continuous |
LDS2 @ Lambton E803S | Lambton LDS2 LCR | |
EPCOR, ALTALINK | 25-Oct-21 07:00 | 05-Nov-21 17:00 | 11.42 Days
Continuous |
1201, 1202, 1238LD @ Genesee 330P, 1238L (330p Genesee - 510s Sunnybrook) | Spire #6 and # 7 repair | |
ENMAX, ALTALINK | 25-Oct-21 08:00 | 25-Oct-21 16:00 | 8 Hours
Continuous |
50L. 21.2TR. 138KV PT @ Bearspaw. 21 CAP. 21PT138-Z31, 50L (44s Bearspaw Plant - ENMAX 21) | Fall Substation Washing. Original date Sept 10th. | |
ENMAX, ALTALINK | 25-Oct-21 08:00 | 28-Oct-21 16:00 | 3.33 Days
Continuous |
832L, 832L (ENMAX 10 - ENMAX 12) | 12B138-832L CT Replacement | |
ATCO, ALTALINK | 25-Oct-21 08:00 | 30-Oct-21 17:00 | 5.38 Days
Continuous |
7L77, 7L77 (395s North Holden - 709s Vegreville) | change arms & insulators | |
ALTALINK | 25-Oct-21 09:00 | 28-Oct-21 17:00 | 3.33 Days
Continuous |
5s T2(TX18835) GOI, 5s T2 (5s East Calgary) | change conservator bladder | |
ATCO | 25-Oct-21 09:00 | 29-Oct-21 17:30 | 4.35 Days
Continuous |
2029S 500SST1, 2029S 500SST2 | Breaker thermal window installs in LV1 & LV2.
One LV will be performed at a time, then the other switched out. 500 kV breakers on transformer primary will be opened for a few moments while opening 501VRA & 502VRA. |
|
ALTALINK | 25-Oct-21 09:45 | 03-Nov-21 17:45 | 9.33 Days
Continuous |
1005L (120s - 356s) GOI, 1005L (120s Picture Butte - 356s Milo) | Build new T-tap into new 991s substation (Little Bow). Install/commission new line protections | |
ATCO | 25-Oct-21 10:00 | 27-Oct-21 16:00 | 2.25 Days
Continuous |
790S 702, 7L22, 7L22 (790s Poplar Hill - 7L88 tap), 790s 702 (790s Poplar Hill) | 790S 702 maintenance, 7L22 open ended | |
ALTALINK | 25-Oct-21 11:00 | 29-Oct-21 15:00 | 4.17 Days
Continuous |
77s919X (919L) - GOI, 919L (77s Sagitawah - 310p Sundance) | Replacement of 77s919x | |
ALTALINK, EPCOR | 25-Oct-21 12:00 | 28-Oct-21 18:00 | 3.25 Days
Continuous |
908L (89s-E816s) - GOI, 908L (89s Ellerslie - 816s Petrolia) | Component replacements and fire mitigation on 908L Str's Range 200-232 | |
EPCOR, ALTALINK | 25-Oct-21 12:00 | 28-Oct-21 18:00 | 3.25 Days
Continuous |
ALTALINK - 908L - DE-ENERGIZE LINE, 908L (89s Ellerslie - 816s Petrolia) | Component replacements and fire mitigation on 908L Str's Range 200-232 | |
ALTALINK | 25-Oct-21 12:00 | 05-Nov-21 17:30 | 11.23 Days
Continuous |
89s1252 - GOI, 89s 1252 (89s Ellerslie) | Replace 89s1252 breaker fail relay | |
ALTALINK | 26-Oct-21 07:30 | 26-Oct-21 12:30 | 5 Hours
Continuous |
151s765 (765L) GOI, 765L (151s Strathmore - 419s Chestermere) | Install and commission relays for RAS179 on 765L | |
ALTALINK | 26-Oct-21 08:30 | 26-Oct-21 17:30 | 9 Hours
Daily |
17s85 (T2)- GOI, 17s 85 (17s Benalto), 17s T2 (17s Benalto) | Replace 6 grading capacitors on 17s85 breaker like for like. Other maintenance work on the breaker as required, | |
ALTALINK | 27-Oct-21 07:00 | 30-Oct-21 18:00 | 3.46 Days
Continuous |
853L(504s - 853L76A) GOI, 853L (504s Queenstown - 853AL tap) | GOI required for Bird Flight Diverter Installation on 853L Structures 282-330 | |
ALTALINK, Lethbridge | 27-Oct-21 08:00 | 27-Oct-21 13:00 | 5 Hours
Daily |
667L (146s Lethbridge MacDonald - 370s North Lethbridge), 813L (146s Lethbridge MacDonald - 241s Lethbridge Uplands) | energize new distribution transformer | |
ATCO | 27-Oct-21 09:00 | 27-Oct-21 17:00 | 8 Hours
Continuous |
811S 709, 7L39, 7L39 (811s Clairmont Lake - 7L39 tap), 811s 709 (811s Clairmont Lake) | 811S 709 partial maintenance | |
ALTALINK | 28-Oct-21 09:30 | 01-Nov-21 17:30 | 4.33 Days
Continuous |
68s T2 and 68s552 GOI, 68s T2 (68s Willesden Green) | Tie in new CT circuit for ne A87 protection. Modify Transformer protection relays setting and Test trip to 68s3103 Modify 370s552 Breaker Fail Protection and Test trip to 68s3103 | |
EPCOR | 01-Nov-21 07:00 | 02-Nov-21 17:00 | 1.42 Days
Continuous |
240kV Bus 1/2 and 1164L @ Riverview and Petrolia E816S, 1164L (816s Petrolia - EPCOR Riverview) | RWDS2 / RWDS3 / RWDS11 adjustments | |
Lethbridge, ALTALINK | 01-Nov-21 08:00 | 04-Nov-21 16:00 | 3.33 Days
Continuous |
667L ( 146S), 667L (146s Lethbridge MacDonald - 370s North Lethbridge) | Air break and switch function test and maintance | |
SUNCOR | 01-Nov-21 08:00 | 13-Nov-21 18:00 | 12.46 Days
Continuous |
29EDD-1 260kV North Bus 1 (29EDD-1 Millennium), 29EDD-1 29EDD1s152 (29EDD-1 Millennium), 29EDD-1 29EDD1s452 (29EDD-1 Millennium) | preventative maintenance | |
ALTALINK | 01-Nov-21 08:30 | 01-Nov-21 13:30 | 5 Hours
Daily |
320p400 (SSTA & SSTB) - GOI, 320p 400 (320p Keephills) | 1st trip and PRC5 maintenance; New C60 breaker fail trip testing on breaker 1552 (320p400) | |
ATCO | 01-Nov-21 09:00 | 05-Nov-21 17:30 | 4.35 Days
Continuous |
2075S 500SST1, 2075S 500SST2 | Breaker thermal window installs in LV1 & LV2.
As Each Station service is removed-from and returned-to service the 240Kv breakers will be opened temporarily to allow for isolating the low voltage devices. (2075S 920 & 2075S 921 for 500SST1) & (2075S 904 & 2075S 905 for 500SST2) One LV will be performed at a time, then the other switched out. |
|
ATCO | 01-Nov-21 09:00 | 11-Nov-21 15:30 | 10.31 Days
Continuous |
757S 704, 757S 704B, 757S 704PT, 757s 704 (757s Battle River) | 704T maintenance work and PRC005 work on 704 Breaker | |
ALTALINK | 01-Nov-21 09:30 | 20-Nov-21 18:00 | 19.4 Days
Continuous |
17s 138kV Bus 4 & T2 TX18477 - Advice, 17s 138kV Bus 4 (17s Benalto), 17s T2 (17s Benalto) | Replace 138kv Bus 4 bus prots, Replace breaker fails on s92, s85, s848X Replace s85 sync check, Replace line protections on 848L, Tie in new 138B3 'B' CT cont, and Tie in new 138B3 'B' CT cont | |
ALTALINK | 01-Nov-21 11:00 | 04-Nov-21 18:00 | 3.29 Days
Continuous |
89s T2 & 240kV East Bus 2 - GOI, 89s T2 (89s Ellerslie), 89s Ellerslie 240kV Bus 2 | Replace 240kV PTs 89s91. Maintenance on 89s8, 89s16, 89s32. Trip testing from replacement 89s1252 breaker fail relay. | |
ALTALINK | 01-Nov-21 11:00 | 10-Nov-21 17:30 | 9.31 Days
Continuous |
905L (37s - 19s) - GOI, 905L (19s Wabamun - 37s North Calder) | Replace 37s77 & 37s79 Switches. Salvage 37s74. Maintenance on 37s76 including first trip testing. Replace grading caps on 37s76. RSLD1 to be implemented after outage is complete. | |
ALTALINK | 01-Nov-21 12:00 | 04-Nov-21 18:00 | 3.25 Days
Continuous |
908L (38s-E52s-89s) - GOI, 908L (38s East Edmonton - 89s Ellerslie) | Component replacements and fire mitigation on Str's Range 233-298 | |
ATCO, ALTALINK | 02-Nov-21 08:00 | 11-Nov-21 17:00 | 9.42 Days
Continuous |
1035L (244s Bowmanton - 2075s Newell), 1035L(244s - A2075s) GOI (URGENT) | GOI required for completion of Damper Replacement CRU scope between Structures 300 & 367 | |
SUNCOR | 02-Nov-21 08:00 | 16-Nov-21 17:00 | 14.42 Days
Continuous |
635PL9-1001 and 635PT-1001, 635PL9-1001 (2005s Secord - 635EDD-1000) | 260kV line structure change for line lift; maintenance of 260kV line, transformer, associated equipment and protection | |
ATCO | 02-Nov-21 13:00 | 02-Nov-21 15:00 | 2 Hours
Continuous |
7L63, 7L63 (780s Lubicon - 812s Norcen) | High load crossing | |
EPCOR | 03-Nov-21 07:00 | 03-Nov-21 17:00 | 10 Hours
Continuous |
RWDS12 and 1139L @ Riverview and Harry Smith 367S, 1139L (367s Harry Smith - EPCOR Riverview) | RWDS12 adjustment | |
ALTALINK | 04-Nov-21 08:00 | 04-Nov-21 13:00 | 5 Hours
Daily |
89s1952 - GOI, 89s 1952 (89s Ellerslie) | Trip testing from replacement 89s1252 breaker fail relay. | |
ALTALINK | 04-Nov-21 13:00 | 04-Nov-21 17:30 | 4.5 Hours
Daily |
89s2252 - GOI, 89s 2252 (89s Ellerslie) | Trip testing from replacement 89s1252 breaker fail relay. | |
ALTALINK | 04-Nov-21 14:30 | 04-Nov-21 17:00 | 2.5 Hours
Daily |
245s777X (777L) Advice, 777L (48s Pocaterra - 245s Seebe) | Functional Trip Test (245s3E); re T2 protection replacements | AB-BC |
EPCOR | 05-Nov-21 07:00 | 22-Nov-21 17:00 | 17.46 Days
Continuous |
Summerside S/S Tx2 Outage, 657s T2 (657s Summerside) | Tx2 isolation required for SUBT23 cell install as part of Southeast Expansion Project | |
ALTALINK | 05-Nov-21 12:00 | 05-Nov-21 17:00 | 5 Hours
Daily |
89s1152 (946L) - GOI, 89s 1152 (89s Ellerslie) | Trip testing from replacement 89s1252 breaker fail relay. Outage coincides with 277255 89s1252 - GOI and will take 946L OOS. | |
ALTALINK | 08-Nov-21 07:00 | 16-Nov-21 18:00 | 8.46 Days
Continuous |
749L (899s-7L749D3) - GOI, 749L (899s Edgerton - 7LB749 tap) | GOI required for Urgent Repair Installation of Clamp Star assemblies on 749L Str 295B - 472 | |
ENMAX, ALTALINK | 08-Nov-21 08:00 | 11-Nov-21 16:00 | 3.33 Days
Continuous |
833L, 833L (ENMAX 2 - ENMAX 12) | 12B138-833L CT Replacement | |
SUNCOR | 08-Nov-21 08:00 | 15-Nov-21 17:00 | 7.38 Days
Continuous |
635PP-1001, 635EDD-1000 635-952-635PT-1001 (635EDD-1000) | Bus-Side Disconnect Repairs Main Sub 635EDD-1000 | |
EPCOR, ALTALINK | 08-Nov-21 09:30 | 10-Nov-21 16:00 | 2.27 Days
Continuous |
930L, 930L (37s North Calder - Poundmaker) | Line Maintenance | |
ALTALINK, EPCOR | 08-Nov-21 12:00 | 10-Nov-21 18:00 | 2.25 Days
Continuous |
908L (38s-E52s-89s) - GOI, 908L (38s East Edmonton - 89s Ellerslie), 908AL (52S East Industrial - 908L tap) | Component replacements and fire mitigation on Str's Range 233-298 | |
ATCO | 09-Nov-21 08:00 | 11-Nov-21 17:00 | 2.38 Days
Continuous |
740S 701T, 740S 702T, 740S 703T, 740s 701T (740s H.R.Milner), 740s 702T (740s H.R.Milner), 740s 703T (740s H.R.Milner), 740s 701 (740s H.R. Milner) | HR Milner uprate Project | |
ALTALINK | 10-Nov-21 09:00 | 10-Nov-21 17:00 | 8 Hours
Daily |
245s1 (245sT1) GOI, 245s T1 (245s Horseshoe) | Functional Trip Test (245s3E); re T2 protection replacements | |
ATCO | 12-Nov-21 08:00 | 24-Nov-21 17:00 | 12.38 Days
Continuous |
740S 700BS2 | HR Milner Upgrade Project
740S 770BS2 outage |
|
ALTALINK, EPCOR | 13-Nov-21 07:00 | 14-Nov-21 18:00 | 1.46 Days
Continuous |
1209L (89s-E330p) - GOI, 1209L (89s Ellerslie - 330p Genesee) | Scope of work includes maintenance on structures 57, 59, 62, 67 and 68 | |
ENMAX, ALTALINK | 13-Nov-21 08:00 | 13-Nov-21 18:00 | 10 Hours
Continuous |
21.80L. 20.82L. 60S100. 21.1TR. 21.4TR, 21.80L (42s Sarcee - ENMAX 21), 20.82L (ENMAX 20 - ENMAX 21) | Fall Substation Washing. | |
ENMAX | 14-Nov-21 08:00 | 14-Nov-21 16:00 | 8 Hours
Continuous |
25B240-D131, 25B240-D131 (ENMAX 25) | HV Breaker maintenance 25B240-D131 | |
EPCOR | 15-Nov-21 07:00 | 19-Nov-21 17:00 | 4.42 Days
Continuous |
1058L and LDS6 @ Lambton E806S and Summerside E657S, 1058L (657s Summerside - EP 803s Lambton) | 1058L Line Maintenance and Lambton LDS6 LCR | |
EPCOR | 15-Nov-21 07:00 | 19-Nov-21 17:00 | 4.42 Days
Continuous |
12TC2 and 12BU2 @ Genesee 330P, 330P 12TC2 (330p Genesee) | Spire #3 repair | |
ENMAX, ALTALINK | 15-Nov-21 08:00 | 16-Nov-21 16:00 | 1.33 Days
Continuous |
1080L., 1080L (ENMAX 25 - ENMAX 65) | 25MD240-1080 Replacement | |
ENMAX, ALTALINK | 15-Nov-21 08:00 | 21-Nov-21 16:00 | 6.33 Days
Continuous |
28.80L., 28.80L (42s Sarcee - ENMAX 28) | HPL breaker refurbishments on 28B138-28.80 | |
BCH | 15-Nov-21 09:00 | 19-Nov-21 17:00 | 4.33 Days
Continuous |
5L52 (Custer - Ingledow) | insulator replacement, BC maintenance does not affect the Alberta ATC | AB-BC |
ALTALINK | 15-Nov-21 11:15 | 25-Nov-21 15:45 | 10.19 Days
Continuous |
370s47 GOI, 370s 1252 (370s North Lethbridge), 370s 47 (370s North Lethbridge), 968L (138s Windy Flats - 370s North Lethbridge) | 370s N.Lethbridge 240kV Breaker (370s47) replacement | |
ALTALINK | 15-Nov-21 12:00 | 18-Nov-21 18:00 | 3.25 Days
Continuous |
905L (37s - 19s) - GOI, 905L (19s Wabamun - 37s North Calder) | Component replacements and fire mitigation(Str's Range 905L( 2-180) | |
ATCO | 15-Nov-21 12:00 | 29-Nov-21 17:00 | 14.21 Days
Continuous |
7L59, 7L59 (789s Keg River - 7L59 tap) | Replace crossarms and replace poles | |
ALTALINK | 16-Nov-21 09:00 | 16-Nov-21 17:00 | 8 Hours
Daily |
723s252, T2, & 25kV Bus 2 – GOI, 723s 252 (723s Christina Lake), 723s T2 (723s Christina Lake) | Replace fuse holder for 723s31. SF6 top up & maintenance on 723s252. Sub checks | |
EPCOR | 17-Nov-21 07:00 | 20-Dec-21 17:00 | 33.42 Days
Continuous |
Poundmaker S/S Tx2 Bay Outage, 1098L bay outage and PM2405 bay outage, 1098L (805s Jasper - Poundmaker), T2 (Poundmaker) | Continuation of 240 kV ring re-configuration for WETUP project.
HV bus re-configuration to tie Tx2 in between PM2401 and newly installed PM2405. Outage will provide isolation for HV bus re work and PMDS12 installation. |
|
ALTALINK | 17-Nov-21 07:15 | 13-Dec-21 17:45 | 26.44 Days
Continuous |
225L(225s-313s-67s) GOI, 225AL (313s Raymond Reservoir - 225L tap), 225L (67s Stirling - 225s Magrath) | Scope of work includes rebuilding a portion of 225L from structure 241 to structure 281 | |
ATCO | 17-Nov-21 11:00 | 28-Nov-21 18:00 | 11.29 Days
Continuous |
930S Synchronous Condenser | ABB Rep Repair Investigation | |
ENMAX | 22-Nov-21 08:00 | 22-Nov-21 16:00 | 8 Hours
Continuous |
162.1TR, 162.1TR (162s Beddington), 240kV North Bus (ENMAX 162), 138kV North Bus (ENMAX 162) | Relays - Fault Pressure Testing - 240-162.1TR. Lock out relay testing 86-Z43A, 86-T1A, 86-T1B, 86-Z43B, 86-Z31A, 86-Z31B | |
EPCOR, ALTALINK | 22-Nov-21 09:30 | 26-Nov-21 17:00 | 4.31 Days
Continuous |
1059L, 1059L (38s East Edmonton - EP 803s Lambton) | Line Maintenance | |
EPCOR, ALTALINK | 22-Nov-21 09:30 | 26-Nov-21 17:00 | 4.31 Days
Continuous |
1238L and 12TC2 @ Genesee 330P, 1238L (330p Genesee - 510s Sunnybrook) | Spire #2 Repair | |
ALTALINK | 22-Nov-21 12:00 | 25-Nov-21 18:00 | 3.25 Days
Continuous |
905L (37s - 19s) - GOI, 905L (19s Wabamun - 37s North Calder) | Component replacements and fire mitigation(Str's Range 905L( 2-180) | |
ALTALINK | 22-Nov-21 12:30 | 26-Nov-21 17:30 | 4.21 Days
Continuous |
74s103 and 74s102 (affect C3 and C4) GOI, 74s C3 (74s Janet), 74s C4 (74s Janet) | 74s C4 relay replacement | |
EPCOR | 23-Nov-21 07:00 | 24-Nov-21 17:00 | 1.42 Days
Continuous |
Summerside S/S Tx1 bay outage, 657s T1 (657s Summerside) | Removal of 240 kV bus work for SU2405 bay installation for South East Expansion Project.
Tx1 to be energized from SU2404 breaker during the restoration of this outage with 240 kV bus removed from SUDS2 to SUAB1 for the duration on SU2405 bay installation. Physical bus separation from SUDS2 to SUAB1 to remain upon Tx1 restoration. |
|
ALTALINK | 23-Nov-21 07:15 | 25-Nov-21 15:45 | 2.35 Days
Continuous |
275s T1(Tx18457) GOI, 275s T1 (275s Jenner) | Isolation of T1 Tx 18457 to install new Bird mitigation for the secondary side of T1 bus work and new reactor portion. | |
ENMAX | 23-Nov-21 08:00 | 23-Nov-21 16:00 | 8 Hours
Continuous |
162.2TR (162s Beddington) | Resolve online monitoring project punch list items. Relays - Fault Pressure Testing - 240-162.2TR, Lock out relay testing 86-Z44A, 86-Z44B, 86-Z32A, 86-Z32B, 86-T2A, 86-T2B | |
ATCO | 24-Nov-21 08:00 | 26-Nov-21 17:00 | 2.38 Days
Continuous |
740S 701T, 740S 702T, 740S 703T, 740s 701T (740s H.R.Milner), 740s 702T (740s H.R.Milner), 740s 703T (740s H.R.Milner) | HR Milner Upgrade project
|
|
ALTALINK | 24-Nov-21 09:00 | 24-Nov-21 15:30 | 6.5 Hours
Daily |
42s906N (906L) GOI, 906L (17s Benalto - 42s Sarcee) | replace heater | |
EPCOR | 25-Nov-21 07:00 | 26-Nov-21 17:00 | 1.42 Days
Continuous |
Summerside S/S Tx2 Bay Outage and SU2401 bay outage, 657s T2 (657s Summerside), 657s SU2401 (657s Summerside) | Continuation of 240 kV ring re-configuration for South East Expansion Project. 240 kV bus to be removed from SUDS2 and SUAB1 in order to make room for SU2405 breaker bay and CVT installation.
Tx1 to be energized from through SU2404 breaker during this outage. |
|
ATCO | 25-Nov-21 08:00 | 27-Nov-21 17:00 | 2.38 Days
Continuous |
7L03, 7L03 (731s Elmworth - 749s Flying Shot) | Northstone DG at 731S Elmworth Project | |
ALTALINK | 25-Nov-21 09:00 | 25-Nov-21 15:30 | 6.5 Hours
Daily |
102s7452 GOI | replace heater | |
ENMAX, ALTALINK | 26-Nov-21 12:00 | 26-Nov-21 16:00 | 4 Hours
Continuous |
23.80L, 23.80L (74s Janet - ENMAX 23) | 23 Sub 138kV DFR Equipment Upgrade | |
ATCO | 28-Nov-21 18:00 | 01-Dec-21 18:00 | 3 Days
Continuous |
930S Synchronous Condenser, 930S 407 | ABB Rep Repair Investigation.
Sync Condenser will be offline from November 17 - December 1 (except when in service during T&O). Test and Operate on sync condenser after GOI 2-59836. Breaker 407 will be operated during test and operate. |
|
EPCOR | 29-Nov-21 07:00 | 03-Dec-21 17:00 | 4.42 Days
Continuous |
1205 @ Genesee 330P, 330p 1205 (330p Genesee) | Spire #8 Repair | |
EPCOR | 29-Nov-21 07:00 | 11-Feb-22 17:00 | 74.42 Days
Continuous |
Summerside S/S Tx1 bay outage, 657s T1 (657s Summerside) | Continuation of 240 kV ring re-configuration for South East Expansion Project.
Tx1 bay to be isolated for 240 kV bus re-configuration and installation of SU2405, SUDS11 and CVT's. Upon restoration Tx1 to be energized from SU2404 and a new isolation point of SUDS11 disconnect to remain open. |
|
ALTALINK | 29-Nov-21 10:00 | 29-Nov-21 12:00 | 2 Hours
Daily |
17s43 (17s1652) - Advice, 17s 43 (17s Benalto), 17s 1652 (17s Benalto) | Trip test from 17s85 BF Replacement | |
ALTALINK | 29-Nov-21 12:00 | 02-Dec-21 18:00 | 3.25 Days
Continuous |
905L (37s - 19s) - GOI, 905L (19s Wabamun - 37s North Calder) | Component replacements and fire mitigation(Str's Range 905L( 2-180) | |
ALTALINK | 29-Nov-21 12:30 | 29-Nov-21 14:30 | 2 Hours
Daily |
17s23 (17s3) - Advice, 17s 23 (17s Benalto), 17s 3 (17s Benalto) | Trip test from 17s85 BF replacement | |
ALTALINK | 29-Nov-21 15:00 | 29-Nov-21 17:00 | 2 Hours
Daily |
17s39 (17s9) - Advice, 17s 39 (17s Benalto), 17s 9 (17s Benalto) | Trip test from 17s85 BF Replacement | |
ALTALINK | 30-Nov-21 09:30 | 30-Nov-21 15:30 | 6 Hours
Daily |
324s2152 GOI | heater replacement | |
ALTALINK | 30-Nov-21 10:00 | 30-Nov-21 12:00 | 2 Hours
Daily |
17s34 (17s4) - Advice, 17s 34 (17s Benalto), 17s 4 (17s Benalto) | Trip test from 17s85 BF Replacement | |
ALTALINK | 30-Nov-21 12:30 | 30-Nov-21 14:30 | 2 Hours
Daily |
17s59 (17s13) - Advice, 17s 13 (17s Benalto), 17s 59 (17s Benalto) | Trip test from s85 BF | |
ALTALINK | 30-Nov-21 15:00 | 30-Nov-21 17:00 | 2 Hours
Daily |
17s79 (C1) - Advice, 17s C1 (17s Benalto) | Trip test from s85 BF | |
ALTALINK, Lethbridge | 01-Dec-21 07:15 | 01-Dec-21 17:45 | 10.5 Hours
Daily |
370s175 (172L) GOI, 172L (181s Chinook - 370s North Lethbridge) | Isolate breaker to complete P&C Cutovers, Remove and Add Trips, Modify Block Close | |
ALTALINK, Lethbridge | 02-Dec-21 07:15 | 02-Dec-21 17:45 | 10.5 Hours
Daily |
370s207X GOI, 207L (111s Coalbanks - 370s North Lethbridge) | Isolate breaker to complete P&C Cutovers, Remove and Add Trips, Modify Block Close | |
ATCO | 06-Dec-21 08:00 | 13-Dec-21 16:00 | 7.33 Days
Continuous |
9L74, 888S 905, 888S 906, 9L74 (888s Dover - 960s Birchwood Creek), 888s 905 (888s Dover), 888s 906 (888s Dover) | Cut in new CT and PT circuit extension to the new RAS relays, complete SCADA terminations. | |
ALTALINK | 06-Dec-21 12:00 | 09-Dec-21 18:00 | 3.25 Days
Continuous |
905L (37s - 19s) - GOI, 905L (19s Wabamun - 37s North Calder) | Component replacements and fire mitigation(Str's Range 905L( 2-180) | |
ATCO | 06-Dec-21 12:00 | 20-Dec-21 17:00 | 14.21 Days
Continuous |
7L59, 7L59 (789s Keg River - 7L59 tap) | Replace crossarms and replace poles. | |
BCH | 07-Dec-21 08:00 | 23-Dec-21 18:00 | 16.42 Days
Continuous |
1L274 (48s Pocaterra - Britt Creek) | transmission refurbishment | AB-BC |
ALTALINK | 08-Dec-21 08:00 | 08-Dec-21 11:00 | 3 Hours
Daily |
17s46 (17s2852- 17s T3) - Advice, 17s 2852 (17s Benalto), 17s T3 (17s Benalto) | Trip test from new s92 breaker fail and s757N breaker fail | |
EPCOR | 13-Dec-21 07:00 | 17-Dec-21 17:00 | 4.42 Days
Continuous |
LDS5 @ Lambton E803S and Hardisty and Strathcona, EP 803s L2403 (EP 803s Lambton), EP 803s L2405 (EP 803s Lambton), EP 803s T3 (EP 803s Lambton), 72LH8 (EP 803s Lambton - EPCOR Hardisty), 72LS24 (EP 803s Lambton - Strathcona) | Lambton LDS5 LCR
(Isolates 72LH8 and 72LS24 from Lambton) |
|
ATCO | 13-Dec-21 08:00 | 16-Dec-21 12:00 | 3.17 Days
Continuous |
7L199, 741s 7L199D1 (741s Fox Creek), 7L199 (347s Fox Creek - 741s Fox Creek) | Changing X Arms | |
ATCO | 13-Dec-21 08:00 | 16-Dec-21 16:00 | 3.33 Days
Continuous |
7L54, 7L54 (794s Valleyview - 813s Little Smoky) | Changing X Arms | |
ALTALINK | 13-Dec-21 09:00 | 14-Dec-21 18:00 | 1.38 Days
Continuous |
789L (A898s - 602L1 - 789L192A) - GOI, 789L (898s Heart Lake - 789BL tap) | Maintenance on Structures #77 & 78. | |
ALTALINK | 14-Dec-21 06:00 | 15-Dec-21 18:00 | 1.5 Days
Continuous |
39s T1 & 240B1 & New 240KV - GOI, 39s T1 (39s Bickerdike) | GOI on 240B2 to close open point J to new sub expansion equipment | |
ATCO | 20-Dec-21 08:00 | 22-Dec-21 16:00 | 2.33 Days
Continuous |
7L54, 7L54 (794s Valleyview - 813s Little Smoky) | Changing X Arms | |
ATCO | 03-Jan-22 08:00 | 05-Jan-22 17:00 | 2.38 Days
Continuous |
7L69, 7L69 (731s Elmworth - 815s Goodfare) | Test and Operate 815S 704 | |
EPCOR | 10-Jan-22 07:00 | 28-Jan-22 17:00 | 18.42 Days
Continuous |
Poundmaker S/S Tx4 bay outage | Continuation of 240 kV ring re-configuration for WETUP project.
Outage will provide isolation for tie in of new Tx4. (P1649) |
|
ATCO | 10-Jan-22 08:00 | 13-Jan-22 17:00 | 3.38 Days
Continuous |
7L07 | Project (P2394) | |
ATCO | 10-Jan-22 09:00 | 30-Jan-22 17:00 | 20.33 Days
Continuous |
9L939, 9L939 (77s Sagitawah - 809s Louise Creek) | Louise Creek Rebuild project
Wiring for 905/906BF relays. CT ratio changes. Relay programming. Commission control, alarms and status. Blocking procedures for BF and Bus protections. |
|
ATCO | 17-Jan-22 08:00 | 19-Jan-22 17:00 | 2.38 Days
Continuous |
7L22 | Elmworth Project | |
ALTALINK | 20-Jan-22 08:00 | 22-Jan-22 17:00 | 2.38 Days
Continuous |
973L (39s-310p) - GOI, 973L (39s Bickerdike - 310p Sundance) | Install new 973L Str 2 in the existing line. Install new 1135L3 in the existing 973L line. Install conductor between new Str 2 and 1C to connect 973L in the new alignment. Remove conductor between new 973L2 and 1135L3. | |
ALTALINK | 23-Jan-22 08:00 | 25-Jan-22 17:00 | 2.38 Days
Continuous |
974L (39s-310p) - GOI, 974L (39s Bickerdike - 310p Sundance) | Install new 974L Str 2 in the existing line. Install new 1084L Str 3 in the existing 974L line. Install conductor between new 974L Str 2 and 1C to connect 974L in the new alignment. Remove conductor between new 974L2 and 1084L3. | |
ATCO, ALTALINK | 24-Jan-22 08:00 | 27-Jan-22 17:00 | 3.38 Days
Continuous |
7L129, 7L129 (526s Buffalo Creek - 7LA129 tap) | GOI 7L129D3 to 526S Buffalo Creek Reroute Transmission Line around water | |
ALTALINK, EPCOR | 25-Jan-22 07:00 | 25-Jan-22 18:00 | 11 Hours
Daily |
920L (71s - E557s) - GOI, 920L (71s Lamoureux - 557s Castle Downs) | Maintenance on structure 48 | |
ATCO, CNRL | 27-Jan-22 08:00 | 07-Feb-22 17:00 | 11.38 Days
Continuous |
75-PLH-902, 75-PLH-902 (838s Horizon Mining - 849s Joslyn) | ATCO 9L32-9L66 CNRL- Horizon Project
Disconnect existing 75-PLH-902 from Horizon substation 75 Connect new bus Horizon substation 75 (former 75-PLH-902 bay)to new 838S-900BS1 Reroute and connect 9L137 (former 75-PLH-902) to new 838S and energize Commission 87L/900BS1 protection, end-to-end testing Upgrade 21B/9L137 line protection @ 849S Joslyn Commission line protection, SCADA and end-to-end testing, BF/DTT to 838S |
|
ALTALINK | 02-Feb-22 07:00 | 06-Feb-22 18:00 | 4.46 Days
Continuous |
39s 240kV Bus 2 (39s Bickerdike), 39s 240kV Bus 2 - GOI | Install new 973L, 974L and 1168L into A-frames at 39S as part of Cascade Project. New spans to 973L, 974L and 1168L A-frames to cross over 39S 240 kV bus 2. | |
ATCO, CNRL | 08-Feb-22 08:00 | 19-Feb-22 17:00 | 11.38 Days
Continuous |
75-PLH-901, 75-PLH-901 (838s Horizon Mining - 849s Joslyn) | ATCO 9L32-9L66 CNRL- Horizon Project
Disconnect existing 75-PLH-901 from Horizon substation 75 Connect new bus Horizon substation 75 (former 75-PLH-901 bay) to new 838S-900BS2 Reroute and connect 9L155 (former 75-PLH-901) to new 838S and energize Commission 87L/900BS1 protection, end-to-end testing Upgrade 21B/9L155 line protection @ 849S Joslyn Commission line protection, SCADA and end-to-end testing, BF/DTT to 838S |
|
EPCOR | 14-Feb-22 07:00 | 18-Feb-22 17:00 | 4.42 Days
Continuous |
TX3 @ Jasper Terminal E805S | 15kV BUS PT Replacement | |
EPCOR | 14-Feb-22 07:00 | 11-Mar-22 17:00 | 25.42 Days
Continuous |
Summerside S/S Tx2 bay outage, 1057L bay outage and SU2405 bay outage, 657s T2 (657s Summerside) | Continuation of 240 kV ring re-configuration for South East Expansion Project.
Outage will provide isolation for HV bus re work and SUDS12 installation. |
|
ATCO, ALTALINK | 14-Feb-22 08:00 | 14-Feb-22 18:00 | 10 Hours
Continuous |
7L65, 7L77, 7L77 (395s North Holden - 709s Vegreville), 7L65 (709s Vegreville - 710s Vermilion) | String over 7L65 and 7L77 | |
ALTALINK | 14-Feb-22 08:00 | 23-Feb-22 18:30 | 9.44 Days
Continuous |
39s 138kV B2, T2, 240B2, & 973L - GOI, 39s T2 (39s Bickerdike), 973L (39s Bickerdike - 310p Sundance) | Complete relocation of 973L, Complete connection of 1135L Close open point ‘K’,Complete breaker fail, T2 trip testing from/to 39s452, 39s852, 39s1152, 39s29, 39s1752 | |
ATCO | 20-Feb-22 08:00 | 23-Feb-22 17:00 | 3.38 Days
Continuous |
9L66, 9L66 (847s Muskeg River - 849s Joslyn Creek) | ATCO 9L32-9L66 CNRL- Horizon Project
Disconnect existing line 9L66 at tap point and connect new line segment to 838S Horizon Expansion Disconnect existing 9L66 from Joslyn 849S Commissioning upgrade - relay settings @ 847S |
|
ATCO | 21-Feb-22 08:00 | 21-Feb-22 16:00 | 8 Hours
Continuous |
766S 901T, 766s 901T (766s Nevis) | TransAlta GARDEN PLAIN PROJECT
Complete the structural and electrical work related to protection panel, Automation & SCADA panel and telecom panels. Complete the line work associated with Line 9LA59 which will be connected to 1045S Garden Plain substation. |
|
ALTALINK | 23-Feb-22 17:30 | 30-Mar-22 15:30 | 34.88 Days
Continuous |
1084L (39s-1047s) - GOI, 1084L (59s Peigan - 278s Kaiyatree) | Complete 1084L Line relay testing between 39s and 1047s | |
ALTALINK | 24-Feb-22 07:00 | 24-Feb-22 18:00 | 11 Hours
Continuous |
310p 240kV B Bus - GOI, 310p 240kV Bus B (310p Sundance) | Scope of work includes replacing insulators on structures 310P and 1 on 1046L, we require a GOI on the B bus in order to safely handle the conductor running over the bus work as well as safely set up the equipment inside the 310p Sundance Substation. Required due to proximity for 1046L GOI See also SAP: 277114 | |
ALTALINK | 24-Feb-22 07:00 | 27-Feb-22 18:00 | 3.46 Days
Continuous |
1046L (310p-338s) - GOI, 1046L (310p Sundance - 338s Cherhill) | Scope of work includes maintenance on structures 310p, 1 ,21, 22, 23, 24, 25, 26, 55, 57, 74, 75, 80, 89, 90, 91, 102, 110, 111, 120 and 121. See also 310p 240kV Bus SAP: 277113 Required due to proximity to 1046L and also SAP: 277115 902L R/B required due to proximity to 1046L | |
ALTALINK | 24-Feb-22 07:00 | 05-Mar-22 18:00 | 9.46 Days
Continuous |
974L (39s-310p) - GOI, 974L (39s Bickerdike - 310p Sundance) | Install new 974L Str 2 in the existing line. Install new 1084L Str 3 in the existing 974L line. Install conductor between new 974L Str 2 and 1C to connect 974L in the new alignment. Remove conductor between new 974L2 and 1084L3. | |
ATCO | 24-Feb-22 08:00 | 27-Feb-22 17:00 | 3.38 Days
Continuous |
9L32, 9L32 (849s Joslyn Creek - 2005s Secord) | ATCO 9L32-9L66 CNRL- Horizon Project
Disconnect existing line 9L32 at tap point and connect new line segment to 838S Horizon Expansion Disconnect existing 9L32 from Joslyn 849S Commissioning upgrade - relay settings @ 2005S |
|
EPCOR | 28-Feb-22 07:00 | 04-Mar-22 17:00 | 4.42 Days
Continuous |
TX1 @ Jasper Terminal E805S | Surge Arrestor Replacement | |
ALTALINK | 01-Mar-22 07:00 | 08-Mar-22 16:00 | 7.38 Days
Continuous |
39s T1, 138kV B1, 240B1, 974L, 1084L, 1168L -, 974L (39s Bickerdike - 310p Sundance), 39s T1 (39s Bickerdike) | Complete relocation of 974L (close open point ‘L’) Terminate 1084L, Terminate 1168L (close open point ‘M’) Complete breaker fail, T1 trip testing from/to 39s1552, 39s26, 39s33, 39s38, 39s152, 39s1052 | |
ALTALINK | 05-Mar-22 15:30 | 30-Mar-22 15:30 | 24.96 Days
Continuous |
1168L (39s-1047s) - GOI | Complete 1168L relay testing between 39s and 1047s | |
ALTALINK | 05-Mar-22 16:00 | 30-Mar-22 15:30 | 24.94 Days
Continuous |
1135L (39s-1047s) - GOI | Complete 1135L relay testing between 39s and 1047s | |
ATCO | 14-Mar-22 08:00 | 15-Mar-22 17:00 | 1.38 Days
Continuous |
766S 901T, 766s 901T (766s Nevis) | Sharp Hills Project
Installation of new RAS panel at 766S Nevis |
|
ATCO | 14-Mar-22 08:00 | 01-Apr-22 16:00 | 18.33 Days
Continuous |
951S 900BS2, 951S 908, 951S 903, 951S 906, 951S 907 | 951S construction for 9L162 & 9L193 addition
AESO should be notified of any changes to below workplan: Isolation pts: 908B,909A Impact: BKR 908 OOS Scope of work: Demo bus & install 909A & 909B March 31, 2022 – April 01, 2022 Expand to isolation pts:903B, 906B,908B Impact: BKR 903,BKR 906, 900BS2 OOS Scope of work: Make connections to 909A & 912A |
|
ALTALINK | 14-Mar-22 12:00 | 17-Mar-22 18:00 | 3.25 Days
Continuous |
1206L (89s - 12s) - GOI, 1206L (12s Heartland - 89s Ellerslie) | Component Replacements on 1206L ( Structure Range 2-193) | |
ALTALINK | 21-Mar-22 12:00 | 24-Mar-22 18:00 | 3.25 Days
Continuous |
1206L (89s - 12s) - GOI, 1206L (12s Heartland - 89s Ellerslie) | Component Replacements on 1206L ( Structure Range 2-193) | |
ATCO, ALTALINK | 22-Mar-22 07:00 | 22-Mar-22 17:00 | 10 Hours
Continuous |
7L77, 7L77 (395s North Holden - 709s Vegreville) | 7L65 Rebuild Project | |
ALTALINK | 28-Mar-22 12:00 | 31-Mar-22 18:00 | 3.25 Days
Continuous |
1212L (89s - 12s) - GOI, 1212L (12s Heartland - 89s Ellerslie) | Component Replacements on 1212L ( Structure Range 20-194) | |
EPCOR | 04-Apr-22 07:00 | 08-Apr-22 17:00 | 4.42 Days
Continuous |
1098L @ Jasper Terminal E805S and Poundmaker | Jasper 1098L VT LCR
1007295 WO: 037069 |
|
SUNCOR | 04-Apr-22 08:00 | 07-Apr-22 18:00 | 3.42 Days
Continuous |
29EDD-65 Edd65Sub | 29EDD65 ;29PT-259 SYSTEM;PM 5y line 29PL9-12 | |
ALTALINK | 04-Apr-22 12:00 | 07-Apr-22 18:00 | 3.25 Days
Continuous |
1212L (89s - 12s) - GOI, 1212L (12s Heartland - 89s Ellerslie) | Component Replacements on 1212L ( Structure Range 20-194) | |
ATCO | 09-Apr-22 08:00 | 15-Apr-22 17:00 | 6.38 Days
Continuous |
9L46, 9L46 (932s Pemukan - 959s Lanfine) | Sharp Hills Project
Outage for Line termination to 363S Sedalia on 9L46 |
|
EPCOR | 11-Apr-22 07:00 | 06-May-22 17:00 | 25.42 Days
Continuous |
P2401 @ Petrolia E816S, 816s P2401 (816s Petrolia) | Petrolia P2401 LCR
1007155 WO: 036932 |
|
ATCO | 11-Apr-22 08:00 | 12-Apr-22 16:00 | 1.33 Days
Continuous |
951S 900BS1, 951s 240kV 900BS1 (951s Thickwood Hills), 951s 1201T (951s Thickwood Hills) | 951S construction for 240kv expansion - 9L162 & 9L193 addition
Connect 910A to 900BS1 Impact: 900BS1 OOS, BKR 901 OOS, BKR 904 OOS, BKR 907 OOS, 920C OOS |
|
ATCO | 12-Apr-22 08:00 | 15-Apr-22 17:00 | 3.38 Days
Continuous |
801S 901T, 801s 901T (801s Anderson) | WHEATLAND PROJECT
801S Anderson Sub Protection Upgrade |
|
ATCO | 24-Apr-22 08:00 | 27-Apr-22 17:00 | 3.38 Days
Continuous |
766S 901T, 766s 901T (766s Nevis) | WHEATLAND PROJECT
766S Nevis Sub Protection Upgrade |
|
ATCO | 02-May-22 08:00 | 15-May-22 00:17 | 12.68 Days
Continuous |
7L01, 7L01 (813s Little Smoky - 881s Sturgeon) | 813S Little Smoky Rebuild
BKR 711 and 712 P&C wiring, remove old panel 8G, set up new panel 7P2, prep work Relay programming and functionality Commission control, alarms and status |
|
EPCOR | 09-May-22 07:00 | 03-Jun-22 17:00 | 25.42 Days
Continuous |
P2406 @ Petrolia E816S, 816s P2406 (816s Petrolia) | Petrolia P2406 LCR
1007155 WO: 038105 |
|
ATCO | 16-May-22 08:00 | 29-May-22 17:00 | 13.38 Days
Continuous |
7L46, 7L46 (813s Little Smoky - 845s Big Mountain) | 813S Little Smoky Rebuild
Replace 705CT and 706CT junction boxes 705, 706 P&C wiring, prep work Relay programming and functionality Commission control, alarms and status |
|
ATCO | 30-May-22 08:00 | 12-Jun-22 17:00 | 13.38 Days
Continuous |
7L45, 7L45 (813s Little Smoky - 845s Big Mountain) | 813S Little Smoky Rebuild813S Little Smoky Rebuild
BKR 703 and 704 P&C wiring, remove old panel 7G, set up new panel 7P4, prep work Relay programming and functionality Commission control, alarms and status |
|
EPCOR | 06-Jun-22 07:00 | 30-Jun-22 17:00 | 24.42 Days
Continuous |
P2404 @ Petrolia E816S, EP 803s L2404 (EP 803s Lambton) | Petrolia P2404 LCR
1007156 WO: 037002 |
|
ATCO | 13-Jun-22 08:00 | 26-Jun-22 17:00 | 13.38 Days
Continuous |
7L54, 7L54 (794s Valleyview - 813s Little Smoky) | 813S Little Smoky Rebuild813S Little Smoky Rebuild
BKR 703 and 704 P&C wiring, remove old panel 7G, set up new panel 7P4, prep work Relay programming and functionality Commission control, alarms and status |
|
ATCO | 15-Jun-22 07:00 | 28-Jul-22 17:00 | 43.42 Days
Continuous |
972S 900BS2, 9L16, 9L16 (755s Cordel - 972s Tinchebray), 972s 240kV Bus 900BS2 (972s Tinchebray) | Outage on 907B and 908A for the installation and commissioning of 907 and 907CT | |
ATCO | 29-Jun-22 07:00 | 01-Jul-22 17:00 | 2.42 Days
Continuous |
766S 701, 766S 901T, 766s 901T (766s Nevis), 766s 701 (766s Nevis) | RAS modifications for the Pattern Lanfine WAGF project | |
ATCO | 12-Jul-22 07:00 | 16-Jul-22 17:00 | 4.42 Days
Continuous |
7L224, 774S 701, 7L224 (650s Hansman Lake - 774s Monitor), 774s 701 (774s Monitor) | RAS modifications for the Pattern Lanfine WAGF project | |
ATCO | 25-Jul-22 08:00 | 07-Aug-22 17:00 | 13.38 Days
Continuous |
7L40, 7L40 (733s Simonette - 813s Little Smoky) | 813S Little Smoky Rebuild
BKR 709 and 710 P&C wiring, remove old panels 3G and 4G, set up new panel 7P1, prep work Relay programming and functionality Commission control, alarms and status |
|
ATCO | 27-Jul-22 06:00 | 28-Jul-22 17:00 | 1.46 Days
Continuous |
972S 900BS2, 9L16, 9L16 (755s Cordel - 972s Tinchebray), 972s 240kV Bus 900BS2 (972s Tinchebray) | Outage on 9L16 to cut the line over to the new bay | |
ATCO | 27-Jul-22 07:00 | 31-Jul-22 17:00 | 4.42 Days
Continuous |
7L760, 767S 702, 7L760 (767s Oyen - 7L760D2), 767s 702 (767s Oyen) | RAS modifications for the Pattern Lanfine WAGF project | |
ATCO | 29-Jul-22 07:00 | 03-Aug-22 17:00 | 5.42 Days
Continuous |
9L177, 9L177 (620s Goldeye - 972s Tinchebray) | Installing new 240Kv Bay (connect 907B to BUS 1) for 620S Goldeye substation connection | |
ATCO | 08-Aug-22 08:00 | 11-Aug-22 17:00 | 3.38 Days
Continuous |
9L29, 9L29 (946s Oakland - 963s Coyote Lake) | BER Hand Hills Project
P & C circuit cutovers Commission LTO 908 & 909 52b open status and line MOD 9L29D2 89b open status @ 946S and LTO 901 open status and line MOD, 9L29D1 open status @ 963S, end-to-end testing |
|
ATCO | 08-Aug-22 08:00 | 21-Aug-22 17:00 | 13.38 Days
Continuous |
7L32, 7L32 (813s Little Smoky - 862s South Bezanson) | 813S Little Smoky Rebuild
BKR 701 and 702 P&C wiring, prep work Relay programming and functionality Commission control, alarms and status |
|
ATCO | 22-Aug-22 08:00 | 29-Aug-22 16:00 | 7.33 Days
Continuous |
766S 901T, 766s 901T (766s Nevis) | Joss Jenner 2 Power Project Connection
Complete CT, PT, P&C cutover, commission relays and DTT to 770S Three Hills (option 1) or 1-114S Ghost Pine (option 2) |
|
ATCO | 05-Sep-22 08:00 | 24-Sep-22 17:00 | 19.38 Days
Continuous |
813S 901T, 813s 901T (813s Little Smoky) | 813S Little Smoky Rebuild
Remove panels 3K,4K - install new panel 9T1 - BKR 901, 701, 705, 718 P&C wiring, prep work Replace 500PT disconnect assembly Relay programming and functionality Commission control, alarms and status |
|
ATCO | 05-Sep-22 08:00 | 30-Sep-22 16:00 | 25.33 Days
Continuous |
972S 900BS2, 972s 240kV Bus 900BS2 (972s Tinchebray) | CETO project | |
ATCO | 26-Sep-22 08:00 | 19-Oct-22 17:00 | 23.38 Days
Continuous |
813S 902T, 813s 902T (813s Little Smoky) | 813S Little Smoky Rebuild
Remove panels 1K,2K - install new panel 9T2 - BKR 904, 710, 711, 713, 717 P&C wiring, prep work Replace cap bank protection relays Replace 501PT disconnect assembly Relay settings update for capacitor banks 714C, 715C, 716C Relay programming and functionality Commission control, alarms and status |
|
ATCO | 22-Oct-22 07:00 | 02-Nov-22 17:00 | 11.42 Days
Continuous |
7L129, 7L129 (710s Vermilion - 918s Bauer) | Re stringing conductor | |
ATCO | 24-Oct-22 08:00 | 06-Nov-22 17:00 | 13.42 Days
Continuous |
9L11, 9L11 (813s Little Smoky - 834s Wesley Creek) | 813S Little Smoky Rebuild
Remove panels 5H,6H - install new panel 9P3 - BKR 905 and 906 P&C wiring, prep work Relay programming and functionality Commission control, alarms and status |
|
EPCOR | 31-Oct-22 07:00 | 04-Nov-22 17:00 | 4.42 Days
Continuous |
1164L @ Petrolia E816S and Riverview, 1164L (816s Petrolia - EPCOR Riverview), 816s P2404 (816s Petrolia), 816s P2403 (816s Petrolia) | Petrolia 1164L VT LCR
1007295 WO: 037070 |
|
ATCO | 07-Nov-22 08:00 | 20-Nov-22 17:00 | 13.38 Days
Continuous |
9L05, 9L05 (809s Louise Creek - 813s Little Smoky) | 813S Little Smoky Rebuild
Remove panels 5H,6H - install new panel 9P3 - BKR 905 and 906 P&C wiring, prep work Relay programming and functionality Commission control, alarms and status |
|
ATCO | 08-Nov-22 08:00 | 08-Nov-22 17:00 | 9 Hours
Continuous |
7L32 (813s Little Smoky - 862s South Bezanson) | 862S S. Bezanson Substation Rebuild Project, Disconnect and remove 7L32PT2 | |
ATCO | 08-Nov-22 08:00 | 08-Nov-22 17:00 | 9 Hours
Continuous |
7L32 (811s Clairmont Lake - 862s South Bezanson) | 862S S. Bezanson Substation Rebuild Project, Disconnect and remove 7L32PT3 | |
ATCO | 21-Nov-22 08:00 | 04-Dec-22 17:00 | 13.38 Days
Continuous |
9L02, 9L02 (809s Louise Creek - 813s Little Smoky) | "Louise Creek Rebuild project - On Oct 24 - Breaker 903 will remain open overnight as this breaker will be part of the following GOI on 9L40 2-50614. Reason: Protection on this breaker is only partially upgraded at this point.
Wiring for 903/910BF relays. CT ratio changes. Relay programming and functionality. Commission control, alarms and status. Blocking procedures for BF protections." |
|
ATCO | 05-Dec-22 08:00 | 18-Dec-22 17:00 | 13.38 Days
Continuous |
813S SVC, 813s SVC (813s Little Smoky) | 813S Little Smoky Rebuild
Cutover new filter bank relays, P&C wiring Relay programming and functionality Commission control, alarms and status |
|
ATCO | 15-Dec-22 07:00 | 23-Dec-22 17:00 | 8.42 Days
Continuous |
730S 702, 730S 704, 730s 702 (730s Rycroft), 7L73 (730s Rycroft - 829s Boucher Creek), 730s 704 (730s Rycroft) | SVC addition and 144 kv bus rebuild. | |
ATCO | 21-Mar-23 08:00 | 22-Mar-23 17:00 | 1.38 Days
Continuous |
7L53, 7LA53, 7L53 (700s Bonnyville - 706s Irish Creek) | Cold Lake Area Energy Centre Project
7LA53 (New Line T-Tap) 1064S Garnier Lake Sub (Customer) Build 6km 7LA53 144kV from T-Tap to 1064S Garnier Lake Substation. Remote end protection upgrades |
|
ATCO | 27-Mar-23 08:00 | 30-Mar-23 17:00 | 3.38 Days
Continuous |
7L91, 7L91 (715s Leming Lake - 826s Marguerite Lake) | Cold Lake Area Energy Centre Project
Cutover CT/PT/P&C ccts for new Thermal RAS relays Complete commissioning 49A/49B/7L91 relays End-to-end testing to 1064S |
AB-BC, AB-SK & AB-MATL: refer to AESO web posting: | http://itc.aeso.ca/itc/public/atc |
Also, | |
AB-BC, AB-SK & AB-MATL: refer to ISO Rule 203.6: | http://www.aeso.ca/rulesprocedures/18592.html |
Prepared On: | 2021-10-06 14:45:54 |
This document and the information contained herein are based upon information and data which by their nature contain a degree of uncertainty and are subject to change. In addition, this document may contain information and data from public sources and/or third parties, which have been assumed to be accurate and complete and have not been verified. Accordingly, the Independent System Operator, operating as the Alberta Electric System Operator (the "AESO") makes no warranty, representation or guarantee, express or implied, with respect to this document or the information contained herein, including, but not limited to, any warranty, representation or guarantee of accuracy, completeness, timeliness, reliability, availability, absence of computer virus, non- infringement, merchantability or suitability for any purpose. Under no circumstances will the AESO, its members, officers, employees, contractors or agents, or any of their respective affiliates, be liable for any errors or omissions in, or any losses, damages or claims whatsoever, whether in contract, tort or otherwise, arising from use of or reliance upon, this document or any information contained herein. © 2009 Alberta Electric System Operator. All rights reserved |