The table below contains the significant transmission outages submitted as tentative to the AESO. These Outages have not yet necessarily been approved, but are listed for awareness and coordination purposes. An Outage has been considered significant for this table if it meets any one (1) or more of the following criteria: |
|
|
|
Note: Where a transmission outage requires generation curtailments, the adjustments to generation will typically happen in the hours before the scheduled transmission outage and in the hour after the element is returned to service. | |
Previous Version | |
Download CSV | |
Owner | From | To | Duration | Element | Scheduled Activity | Affected Intertie |
---|---|---|---|---|---|---|
ATCO | 17-Jun-21 13:00 | 12-Jul-21 09:00 | Continuous |
24.83 Days
730s 701T (730s Rycroft) | transformer class 2 major testing | |
ALTALINK | 20-Jun-21 11:00 | 14-Jul-21 18:00 | 24.29 Days
Continuous |
74s T2 (74s Janet) | maintenance | |
ATCO | 05-Jul-21 08:00 | 30-Jul-21 15:30 | 25.31 Days
Continuous |
2075s 917 (2075s Newell), 2075s 918 (2075s Newell), 2075s ACF14 (2075s Newell), 2075s ACF13 (2075s Newell), 2075s ACF12 (2075s Newell), 2075s SVC1 (2075s Newell) | cooling system maintenance | |
ATCO | 05-Jul-21 10:00 | 13-Jul-21 17:00 | 8.29 Days
Continuous |
809s 901T (809s Louise Creek), 809s 503R (809s Louise Creek), 809s 504R (809s Louise Creek) | modifications to 901T - Louise Creek rebuild project- | |
ATCO | 05-Jul-21 12:00 | 12-Jul-21 12:00 | 7 Days
Continuous |
7L80 (733s Simonette - 740s H.R.Milner) | climbing and walk up inspection with insulator repairs | |
ALTALINK | 08-Jul-21 07:00 | 13-Jul-21 18:00 | 5.46 Days
Continuous |
847L (602s Cold Creek - 847AL tap) | replace 847L Str 291 and 297 for line clearance mitigation | |
ALTALINK | 08-Jul-21 07:15 | 11-Jul-21 17:45 | 3.44 Days
Continuous |
719L (256s Harmattan - 719CL tap) | maintenance work (Strs 4 ~ 72) | |
ENMAX | 10-Jul-21 12:00 | 10-Jul-21 18:00 | 6 Hours
Continuous |
24.81L. 24.83L. 24.1TR. 24PT138-Z31 | Substation Summer Washing. Check Reversing Switch . Original Outage June 17th. | |
EPCOR | 12-Jul-21 07:00 | 16-Jul-21 17:00 | 4.42 Days
Continuous |
East Industrial S/S TX2 Bay, 52s T2 (52s East Industrial) | Isolate TX2 bay to relocate metering and transformer controls. | |
ALTALINK | 12-Jul-21 07:30 | 13-Jul-21 17:00 | 1.4 Days
Continuous |
205s13 Advice for customer | Customer maintenance | |
ATCO | 12-Jul-21 07:30 | 16-Jul-21 15:00 | 4.31 Days
Continuous |
2029S ACF21, 2029S ACF22, 2029S ACF23, 2029s ACF21 (2029s Heathfield), 2029s ACF22 (2029s Heathfield), 2029s ACF23 (2029s Heathfield) | PRC testing AC Filter Bank 2
No Filter redundancy during work |
|
ENMAX | 12-Jul-21 08:00 | 12-Jul-21 11:00 | 3 Hours
Continuous |
162B240-RB133, 162B240-RB133 (ENMAX 162) | SF6 Sample. Dashpot Checks 162B240-RB133 | |
EPCOR | 12-Jul-21 08:00 | 16-Jul-21 12:00 | 4.17 Days
Continuous |
Lambton S/S Tx1 bay outage, EP 803s T1 (EP 803s Lambton) | Tower Removal | |
ALTALINK | 12-Jul-21 08:00 | 16-Jul-21 16:00 | 4.33 Days
Continuous |
510s AC Filter 11 - GOI, 510s ACF11 (510s Sunnybrook) | Annual Filter Bank outage and inspection | |
BCH | 12-Jul-21 09:00 | 16-Jul-21 17:00 | 4.33 Days
Continuous |
2L294 (A.A. Lambert - Nelway) | insulator replacement | AB-BC |
ALTALINK | 12-Jul-21 09:30 | 14-Jul-21 16:30 | 2.29 Days
Continuous |
42s906N Advice, 906L (17s Benalto - 42s Sarcee) | Migrate and commission all 42s906N & L4-906L at 42s Sarcee associated line protections, recloser, synch check, breakers, breaker fail alarms, status, controls, metering and remote access to new RTU and LAN. . | |
ATCO | 12-Jul-21 09:30 | 15-Jul-21 16:00 | 3.27 Days
Continuous |
885S 901, 885S 902, 9L89, 9L89 (885s McMillan - 2011s Dawes) | 901 Breaker Maintenance & 9L89 RTXP switch replacements - The GOI zone can be reduced to 901A, 901B for 885S 901 breaker Maintenance after the RTXP switches have been replaced. | |
ATCO | 12-Jul-21 10:00 | 15-Jul-21 16:30 | 3.27 Days
Continuous |
876S 901T, 876s 901T (876s Brintnell) | 901T Leak mitigation, and 901T transformer Maintenance | |
ATCO | 12-Jul-21 10:00 | 19-Jul-21 15:00 | 7.21 Days
Continuous |
7L32, 7L32 (813s Little Smoky - 862s South Bezanson) | Crossarm changing | |
ENMAX | 12-Jul-21 11:00 | 12-Jul-21 13:00 | 2 Hours
Continuous |
162B240-RB134, 162B240-RB134 (ENMAX 162) | SF6 Sample. Dashpot Checks 162B240-RB134 | |
ALTALINK, EPCOR | 12-Jul-21 11:00 | 15-Jul-21 18:00 | 3.29 Days
Continuous |
908L (89s-E816s) - GOI, 89s 652 (89s Ellerslie), 89s 752 (89s Ellerslie), 908L (89s Ellerslie - 816s Petrolia) | Replace 240kV PTs 89s75. 89s652 maintenance including 1st trips. Replace 12 grading capacitors. | |
ENMAX | 12-Jul-21 13:00 | 12-Jul-21 16:00 | 3 Hours
Continuous |
162B240-RB131, 162B240-RB131 (ENMAX 162) | SF6 Gas Sample, Dashpot Checks 162B240-RB131 | |
ENMAX | 13-Jul-21 08:00 | 13-Jul-21 16:00 | 8 Hours
Continuous |
25B240-D132, 25B240-D132 (ENMAX 25) | HV Breaker maintenance 25B240-D132 | |
BCH | 13-Jul-21 08:00 | 13-Jul-21 16:00 | 8 Hours
Continuous |
1L274 (B1s BCH Natal - 1D1L274) | structure refurbishment | AB-BC |
BCH | 13-Jul-21 08:00 | 13-Jul-21 18:00 | 10 Hours
Continuous |
1L274 (48s Pocaterra - Britt Creek), 1L275 (799s Coleman - Natal) | NTL station work | AB-BC |
ALTALINK | 13-Jul-21 08:00 | 14-Jul-21 16:00 | 1.33 Days
Continuous |
510s AC Filter 12 - GOI, 510s ACF12 (510s Sunnybrook) | Annual Filter Bank outage and inspections | |
ATCO | 13-Jul-21 17:01 | 22-Aug-21 17:00 | 40 Days
Continuous |
809S 901T, 9L938, 9L938 (77s Sagitawah - 809s Louise Creek) | Louise Creek Rebuild project- Replace 912, 900PT1, CT modifications to 906CT, 912CT, and 901T
July 5-13 – Isolation Points: 809S 901TD, 809S 701B, 809S 201TD, 809S 500D1 – 809S 901T OOS July 13-August 22 – Expand GOI – Isolation points: 809S 911A, 809S 906A, 809S 701A, 809S 500D1, 809S 201TD1 & 77S938N (COG From AltaLink) - 809S 901T OOS & 9L938 OOS 809S 911 Breaker will be in-operable at the end of this outage and will be included on the following GOI for 809S 902T on August 23 2-50617. |
|
ALTALINK | 14-Jul-21 07:30 | 15-Jul-21 17:00 | 1.4 Days
Continuous |
205s14 Advice for customer | Customer maintenance | |
ENMAX | 14-Jul-21 08:00 | 14-Jul-21 16:00 | 8 Hours
Continuous |
25B240-D142 | HV Breaker maintenance 25B240-D142. Original outage date July 15. | |
ALTALINK | 14-Jul-21 09:15 | 19-Jul-21 14:45 | 5.23 Days
Continuous |
968L (138s - 370s) GOI, 968L (138s Windy Flats - 370s North Lethbridge) | Outage required on 240kv bus to install future breaker piles | |
ALTALINK | 15-Jul-21 07:00 | 15-Jul-21 18:00 | 11 Hours
Daily |
729L (542s - 729L13A) - GOI | Fire mitigation on Structures #15 & 123 | |
ALTALINK, Lethbridge | 15-Jul-21 08:00 | 15-Jul-21 13:00 | 5 Hours
Continuous |
725L (15s Fort MacLeod - 674s Lethbridge Bowron) | air break function test and maintance
|
|
ALTALINK | 15-Jul-21 09:00 | 15-Jul-21 10:30 | 90 Mins
Daily |
283s836 (836L) - GOI, 836L (61s Lodgepole - 283s Violet Grove) | Transformer protection upgrade, trip testing to breaker | |
EPCOR | 17-Jul-21 07:00 | 17-Jul-21 17:00 | 10 Hours
Continuous |
C2403 @ Cloverbar E987S, 987s C2403 (987s Clover Bar) | C2403 Dashpot Repair | |
ENMAX, ALTALINK | 18-Jul-21 08:00 | 18-Jul-21 18:00 | 10 Hours
Continuous |
24.83L. 24.81L. 24.1TR, 24.83L (74s Janet - ENMAX 24), 24.81L (ENMAX 24 - ENMAX 31) | HV Breaker maintenance 24B138-24.83. SF6 Gas sample 24B138-24BT3. Check reversing switch 24.1TR | |
EPCOR | 19-Jul-21 07:00 | 20-Jul-21 17:00 | 1.42 Days
Continuous |
Summerside S/S SU2401 Bay, 657s SU2401 (657s Summerside) | Isolate SU2401 to cutover new controls, status, alarms to new RTU. | |
ALTALINK, EPCOR | 19-Jul-21 07:00 | 23-Jul-21 15:00 | 4.33 Days
Continuous |
1055L (E816s-E814s) Epcor - Info, 1055L (629s Argyll Transfer Station - 816s Petrolia) | Epcor Substation Life Cycle Replacement of HV VTs - Petrolia- 1055L CVT and 1055L Line Maintenance | |
EPCOR | 19-Jul-21 07:00 | 23-Jul-21 17:00 | 4.42 Days
Continuous |
Petrolia- 1055L CVT, 1055L (629s Argyll Transfer Station - 816s Petrolia) | Substation Life Cycle Replacement of HV VTs - Petrolia- 1055L CVT | |
ENMAX | 19-Jul-21 08:00 | 19-Jul-21 16:00 | 8 Hours
Continuous |
25B240-D138, 25B240-D138 (ENMAX 25) | HV Breaker maintenance 25B240-D138 | |
ALTALINK, ENMAX | 19-Jul-21 09:00 | 22-Jul-21 17:00 | 3.33 Days
Continuous |
21.80L(42s - Enmax sub #21) GOI, 21.80L (42s Sarcee - ENMAX 21) | Migrate and commission all 42s21 (752) & L7-21.80L at 42s Sarcee associated line protections, recloser, synch check, breakers, breaker fail alarms, status, controls, metering and remote access to new RTU and LAN. Install and commission new SCADA meter. | |
BCH | 19-Jul-21 09:00 | 23-Jul-21 17:00 | 4.33 Days
Continuous |
5L91 (Ashton Creek - Selkirk) | structure replacement, BC Maintenance does not affect the Alberta ATC | AB-BC |
ATCO, ALTALINK | 19-Jul-21 09:30 | 22-Jul-21 16:00 | 3.27 Days
Continuous |
885S 902, 885S 903, 9L55, 9L55 (852s Round Hill - 885s McMillan) | 9L55 RTXP replacements
903 Breaker Maintenance The GOI zone can be reduced to only include 903 breaker after the RTXP switches have been replaced. 903A, 903B |
|
ATCO | 19-Jul-21 10:00 | 21-Jul-21 17:00 | 2.29 Days
Continuous |
813S SVC, 813s SVC (813s Little Smoky) | Work on glycol system. Pump replacements and in line filter installation. | |
ALTALINK, EPCOR | 19-Jul-21 11:00 | 22-Jul-21 18:00 | 3.29 Days
Continuous |
908L (89s-E52s-38s) - GOI, 89s 752 (89s Ellerslie), 89s 852 (89s Ellerslie), 908L (89s Ellerslie - 908AL tap), 908AL (52S East Industrial - 908L tap), 908L (38s East Edmonton - 908AL tap) | Replace 240kV PTs 89s76. 89s15 maintenance. | |
ALTALINK | 19-Jul-21 12:30 | 22-Jul-21 16:30 | 3.17 Days
Continuous |
562s T1(TX18773) GOI, 562s T1 (562s Cypress) | Doble, Maintenance, leak repairs | |
ALTALINK | 19-Jul-21 13:00 | 22-Jul-21 17:00 | 3.17 Days
Continuous |
410s T1 TX18134, 410s T1 (410s Josephburg) | 138 kV and 25 kV bushings replacement on Transformer T1. T1 Maintenance, doble, standoffs and oil leaks | |
ALTALINK | 20-Jul-21 07:00 | 20-Jul-21 18:00 | 11 Hours
Daily |
71s1252 - GOI | Isolate breaker for ABB representative to complete commissioning | |
ALTALINK | 20-Jul-21 07:15 | 21-Jul-21 17:45 | 1.44 Days
Continuous |
891L (891L1 - 226s) GOI, 891L (226s Garden City - 863L tap) | Scope of work includes maintenance on structures 7, 9, 15, 17, 18, 20, 24, 28, 29, 30, 35 and 37 | |
ENMAX | 20-Jul-21 08:00 | 20-Jul-21 16:00 | 8 Hours
Continuous |
25B240-D139, 25B240-D139 (ENMAX 25) | HV Breaker maintenance 25B240-D139 | |
ATCO | 20-Jul-21 08:00 | 20-Jul-21 17:00 | 9 Hours
Continuous |
7L760, 7L760 (767s Oyen - 7LA760 tap), 7LA760 (914s Bindloss - 7LA760 tap) | Planned High load to cross under 7L760 in Two locations | |
EPCOR | 21-Jul-21 07:00 | 21-Jul-21 17:00 | 10 Hours
Continuous |
Summerside S/S SU2402 Bay, 657s SU2402 (657s Summerside) | Isolate SU2402 to cutover controls, status, alarms to new RTU. | |
ALTALINK | 21-Jul-21 07:00 | 21-Jul-21 18:00 | 11 Hours
Daily |
71s1352 - GOI | Isolate breaker for ABB representative to complete commissioning | |
ALTALINK | 21-Jul-21 08:15 | 21-Jul-21 17:15 | 9 Hours
Daily |
63s552 GOI, 63s 552 (63s Red Deer) | 1st trip PRC5 maintenance | |
EPCOR | 22-Jul-21 07:00 | 22-Jul-21 17:00 | 10 Hours
Continuous |
Summerside S/S SU2403 Bay, 657s SU2403 (657s Summerside) | Isolate SU2403 to cutover new controls, status, alarms to new RTU. | |
ALTALINK | 22-Jul-21 09:00 | 22-Jul-21 17:30 | 8.5 Hours
Daily |
17s2 GOI, 17s 2 (17s Benalto) | 240kV breaker maintenance | |
EPCOR | 23-Jul-21 07:00 | 23-Jul-21 17:00 | 10 Hours
Continuous |
Summerside S/S SU2404 Bay, 657s SU2404 (657s Summerside) | Isolate SU2404 to cutover new controls, status, alarms to new RTU. | |
ENMAX, ALTALINK | 23-Jul-21 08:00 | 10-Aug-21 16:00 | 18.33 Days
Continuous |
7.82L, 7.82L (42s Sarcee - ENMAX 7) | Line relocation at Bow Trail. Phasing required. | |
EPCOR, ALTALINK | 23-Jul-21 15:00 | 23-Jul-21 17:00 | 2 Hours
Continuous |
1055L Extended Zone @ Petrolia E816S and Argyll Transfer Station E629S, 816s P2402 (816s Petrolia), 816s P2403 (816s Petrolia), 1055L (629s Argyll Transfer Station - 816s Petrolia) | Extended zone to energize new Petrolia CVT's with breaker. | |
ALTALINK | 24-Jul-21 07:15 | 25-Jul-21 12:45 | 29.5 Hours
Continuous |
419s691 (691) GOI, 691L (74s Janet - 419s Chestermere) | Install and commission relays for RAS on 691L, remove RAS from line protection relay. | |
ALTALINK | 24-Jul-21 08:00 | 24-Jul-21 17:30 | 9.5 Hours
Continuous |
74s691 (affect 691L) GOI | Replace Breaker 74s691 Grading Capacitors | |
EPCOR | 26-Jul-21 07:00 | 29-Jul-21 17:00 | 3.42 Days
Continuous |
987s GDS1 (987s Cloverbar) | Line Maintenance | |
EPCOR, ALTALINK | 26-Jul-21 07:00 | 30-Jul-21 17:00 | 4.42 Days
Continuous |
Dome 909L CVT Replacement, 909L (310p Sundance - 665s Dome) | Dome 909LW CVT Replacement | |
ENMAX | 26-Jul-21 08:00 | 27-Jul-21 16:00 | 1.33 Days
Continuous |
833L | HV Breaker maintenance 12B138-833L. Original outage June 28-29 | |
Syncrude | 26-Jul-21 08:00 | 30-Jul-21 20:00 | 4.5 Days
Continuous |
Significant Outage: T1 Transformer (260/72KV) in D05 Substation Following Circuit Breakers will be operated to isolate T1: 519, 511, 71 Following MOD's will be operated to isolate T1: 519A, 519B, 511A, 511B, 510, 71A, 71B, D05 T1 (D05 Syncrude) | Significant Outage:
T1 Transformer (260/72KV) in D05 Substation Following Circuit Breakers will be operated to isolate T1: 519, 511, 71 Following MOD's will be operated to isolate T1: 519A, 519B, 511A, 511B, 510, 71A, 71B |
|
ALTALINK | 26-Jul-21 09:00 | 29-Jul-21 17:00 | 3.33 Days
Continuous |
916L(42s - 5s) GOI, 916L (5s East Calgary - 42s Sarcee) | Migrate and commission all 42s916E (1352) & L13-916L at 42s Sarcee associated line protections, recloser, POW, synch check, breakers, breaker fail alarms, status, controls, metering and remote access to new RTU and LAN. Project PM: Golaleh Rahimi Issue to: Jesse Soonias Contact #: 403-606-8152 | |
BCH | 26-Jul-21 09:00 | 06-Aug-21 17:00 | 11.33 Days
Continuous |
5L96 (Selkirk - Vaseux Lake) | marker ball installation, BC Maintenance does not affect the Alberta ATC | AB-BC |
ATCO | 26-Jul-21 10:00 | 29-Jul-21 15:00 | 3.21 Days
Continuous |
7L40, 7L40 (733s Simonette - 813s Little Smoky) | crossarm changes | |
ATCO | 26-Jul-21 10:00 | 09-Aug-21 15:00 | 14.21 Days
Continuous |
7L32 | Crossarm changing | |
ALTALINK | 26-Jul-21 10:30 | 26-Jul-21 15:30 | 5 Hours
Daily |
287s552 GOI | 240kV breker maintenance | |
ALTALINK | 26-Jul-21 11:00 | 26-Jul-21 16:30 | 5.5 Hours
Daily |
71s1452 - GOI | Maintenance on breaker including 1st trip maintenance. | |
ATCO | 27-Jul-21 08:00 | 27-Jul-21 11:30 | 3.5 Hours
Continuous |
2005s 905 | Test and Operate. PRC005 Trip coil on Breaker 905 | |
ATCO | 27-Jul-21 09:00 | 27-Jul-21 15:00 | 6 Hours
Continuous |
7L89, 7L89 (700s Bonnyville - 721s La Corey) | Removing 7L89PT2, as Auto sectionalizing scheme is no longer in required | |
ATCO | 27-Jul-21 11:45 | 27-Jul-21 16:30 | 4.75 Hours
Continuous |
2005s 906 | Test and Operate. PRC005 Trip coil on Breaker 906 | |
ENMAX | 28-Jul-21 08:00 | 28-Jul-21 16:00 | 8 Hours
Continuous |
36.81L | HV Breaker maintenance 36B138-36.81. Original outage date June 30th | |
ATCO | 28-Jul-21 09:00 | 28-Jul-21 15:00 | 6 Hours
Continuous |
7L89 (721s La Corey - 826s Marguerite Lake), 7L89 | Removing 7L89PT1, as Auto sectionalizing scheme is no longer in required | |
EPCOR | 29-Jul-21 07:00 | 29-Jul-21 17:00 | 10 Hours
Continuous |
TX3 and 15kV Bus @ Jasper Terminal E805S, 805s T3 (805s Jasper) | 15kV Bus PT Inspection with ABB 1007365-039715 | |
ALTALINK | 29-Jul-21 09:00 | 29-Jul-21 10:30 | 90 Mins
Daily |
283s836 (836L) - GOI, 836L (61s Lodgepole - 283s Violet Grove) | Transformer protection upgrade, trip testing to breaker | |
ALTALINK | 29-Jul-21 09:30 | 29-Jul-21 14:30 | 5 Hours
Daily |
89s252 - GOI | Maintenance on breaker including 1st trip maintenance | |
EPCOR | 30-Jul-21 07:00 | 05-Aug-21 17:00 | 6.42 Days
Continuous |
987s GDS3 (987s Cloverbar) | Line Maintenance | |
ENMAX, ALTALINK | 30-Jul-21 08:00 | 30-Jul-21 16:00 | 8 Hours
Continuous |
693L. 10.2TR. 10PT138-Z31, 693L (42s Sarcee - ENMAX 10), 10.2TR (ENMAX 10) | Power factor test 10PT138-693, 10PT138-Z31 | |
ALTALINK | 03-Aug-21 07:00 | 06-Aug-21 18:00 | 3.46 Days
Continuous |
707L (54s-166s), 166s T2 & part. 138kV B | 166s maintenance on T2, 166s707X (including 1st trip), & 138kV switches. 54s maintenance on 54s707N (including 1st trip) & 138kV switch. 707L line maintenance. | |
ATCO | 03-Aug-21 08:00 | 05-Aug-21 11:30 | 2.15 Days
Continuous |
848S 907, 848s 907 (848s Ruth Lake) | 907 BKR Maintenance | |
ATCO | 03-Aug-21 08:00 | 05-Aug-21 17:00 | 2.38 Days
Continuous |
863S 902, 9L948, 9L948 (650s Hansman Lake - 863s Paintearth) | 902 Maintenance | |
Syncrude | 03-Aug-21 08:00 | 05-Aug-21 20:00 | 2.5 Days
Continuous |
Significant Outage: T2 Transfromer (260/72kV) @ D05 Substation Following Breakers will be operated: 78 @ D05 Substation 513 @ D05 Substation 516 @ D05 Substation Following MOD's will be operated: 78A @ D05 Substation 509 @ D05 Substation 513A @ D05 Substa, D05 T2 (D05 Syncrude) | Significant Outage:
T2 Transfromer (260/72kV) @ D05 Substation Following Breakers will be operated: 78 @ D05 Substation 513 @ D05 Substation 516 @ D05 Substation Following MOD's will be operated: 78A @ D05 Substation 509 @ D05 Substation 513A @ D05 Substation 516A @ D05 Substation |
|
ALTALINK | 03-Aug-21 09:15 | 03-Aug-21 15:45 | 6.5 Hours
Daily |
514L (513s - 322s - 396s) GOI, 514L (513s Range. Pipe Lundbreck - 514BL tap), 514L (396s Pincher Creek - 514BL tap) | 514L2 Replace Insulation | |
ALTALINK | 03-Aug-21 09:30 | 05-Aug-21 16:30 | 2.29 Days
Continuous |
42s Cap bank C2 GOI, 42s C2 (42s Sarcee) | Migrate and commission all Cap bank C2 & 42S74 (2152) associated protections, breakers, breaker fail, POW alarms, status, controls, metering and remote access to new RTU and LAN. | |
ATCO | 03-Aug-21 10:00 | 09-Aug-21 15:00 | 6.21 Days
Continuous |
7L40, 7L40 (733s Simonette - 813s Little Smoky) | crossarm changes | |
ALTALINK | 03-Aug-21 11:00 | 05-Aug-21 17:00 | 2.25 Days
Daily |
74s552 GOI, 74s 552 (74s Janet) | 1st Trip. Crew will get ACC to perform a couple of open and closes as needed when they are ready. Crew may or may not need a GOI depending on the test results of the first trip. | |
ALTALINK | 03-Aug-21 11:00 | 12-Aug-21 17:30 | 9.27 Days
Continuous |
905L (37s - 19s) - GOI, 905L (19s Wabamun - 37s North Calder) | Replace 37s77 & 37s79 Switches. Maintenance on 37s76 including first trip testing. Replace grading caps on 37s76. | |
ALTALINK | 04-Aug-21 08:00 | 04-Aug-21 17:30 | 9.5 Hours
Daily |
12s952 - GOI, 12s 952 (12s Heartland) | Gas top up and take care of breaker trouble alarm | |
ENMAX | 04-Aug-21 08:00 | 05-Aug-21 16:00 | 1.33 Days
Continuous |
1080L. | 25MD240-1080 Replacement | |
SUNCOR | 04-Aug-21 08:00 | 10-Aug-21 18:00 | 6.42 Days
Continuous |
29PL7-2 (29EDD-18 - 29EDD-63) | Maintenance and testing of 29PT-179 and 30PT-219, 144 kV breakers/switches, GCB and PRC-005 testing during GTG7 outage | |
ALTALINK | 05-Aug-21 07:00 | 05-Aug-21 18:00 | 11 Hours
Daily |
788L (788L107A - A898s - 602L1) - GOI, 788L (898s Heart Lake - 788AL tap) | replacing Structure #285 and maintenance on Structure #284 | |
ALTALINK | 05-Aug-21 07:00 | 15-Aug-21 18:00 | 10.46 Days
Continuous |
908L (38s-E52s-89s) - GOI | Repair sub bundle, broken inner core between 908L234 and 242. Replace all damaged dead end insulation and jumper strings 908L234. Repair Mid-span OHSW Tie 908L249. Replace all Dead-end insulation to 25 KIP NGK. | |
ATCO | 05-Aug-21 08:00 | 06-Aug-21 17:00 | 1.38 Days
Continuous |
863S 902T, 863s 902T (863s Paintearth) | 902T Leak mitigation | |
ALTALINK | 06-Aug-21 07:15 | 11-Aug-21 17:45 | 5.44 Days
Continuous |
444L (217s - 198s) GOI, 444L (198s Blackfalds - 217s North Red Deer) | Scope of work includes replacing structures 7, 8, 10 and 12 and maintenance on Structures 1, 2, 6 and 25 | |
BCH | 08-Aug-21 08:00 | 08-Aug-21 18:00 | 10 Hours
Continuous |
1L274 (Elkford - EFT1D21), 1L274 (Elkford - EFT1D22) | Transformer energization | AB-BC |
ALTALINK | 09-Aug-21 06:00 | 20-Aug-21 18:00 | 11.5 Days
Continuous |
121s 138kV North Bus & T5(18407) GOI | Cutover of the following protections during outage: 121s831N BF and Control, 831L A&B Prot, 121s814W BF and Control, 814L A&B Prot, 138NB87A, 138NB87B, CVT5 Distribution, T5_A87, T5_B87, 121s37(389) Cont, 121s38(589) Cont. | |
EPCOR | 09-Aug-21 07:00 | 11-Aug-21 17:00 | 2.42 Days
Continuous |
1044L Zone @ Japser Terminal E805S and Petrolia E816S | 1044L at Jasper Arrestor Doble, JDS25/JDS6/JDS7 Switch Maintenance | |
EPCOR | 09-Aug-21 07:00 | 13-Aug-21 17:00 | 4.42 Days
Continuous |
805 Bay @ Genesee 330P, 330p 805 (330p Genesee), 330P 12TC1 (330p Genesee) | 805 Maintenance and CT Doble | |
ATCO | 09-Aug-21 08:00 | 11-Aug-21 17:00 | 2.38 Days
Continuous |
732S 901 | 732S 901 Breaker Maintenance | |
ATCO | 09-Aug-21 08:00 | 17-Aug-21 17:00 | 8.38 Days
Continuous |
7L84, 7L84 (722s Crystal Lake - 749s Flyingshot Lake) | 7L84 line mitigation project
Modifications to Structures 14,59,128, & 129 Replace switch 702A & 7L84D1 |
|
ATCO | 09-Aug-21 08:00 | 20-Aug-21 17:30 | 11.4 Days
Continuous |
2075S 900SST1, 2075s 900SST1 (2075s Newell) | - Install Breaker Thermal Windows in LV1 Room at 2075S Newell
- 900SST1 Gasket Repalcements |
|
ATCO | 09-Aug-21 08:30 | 11-Aug-21 16:30 | 2.33 Days
Continuous |
848S 902, 848s 902 (848s Ruth Lake) | 902 BKR Maintenance | |
ATCO | 09-Aug-21 09:00 | 13-Aug-21 16:00 | 4.29 Days
Continuous |
766S 901, 9L20 | Repair breaker 901 - grading capacitors | |
BCH | 09-Aug-21 09:00 | 13-Aug-21 17:00 | 4.33 Days
Continuous |
5L98 (BCH Nicola - Vaseux Lake) | insulator replacement, BC Maintenance does not affect the Alberta ATC | AB-BC |
ALTALINK | 09-Aug-21 09:30 | 12-Aug-21 16:30 | 3.29 Days
Continuous |
42s T2 (Tx18507) GOI, 42s T2 (42s Sarcee) | Migrate and commission all T1 TX18507, 42S63 (289), 42S60 (1152) associated transformer protections, tap changer, breaker, breaker fail alarms, status, controls, metering and remote access to new RTU and LAN. . | |
ATCO | 09-Aug-21 12:00 | 16-Aug-21 15:50 | 7.16 Days
Continuous |
7L84 | Mitigation Work | |
ALTALINK | 10-Aug-21 07:00 | 10-Aug-21 18:00 | 11 Hours
Daily |
787L (71s - 787L29) - GOI, 787L (71s Lamoureux - 787AL tap) | Fire mitigation on Structure #8 | |
ALTALINK | 10-Aug-21 07:00 | 13-Aug-21 18:00 | 3.46 Days
Continuous |
900L (17s - 63s) - GOI | GOI required for Phase Raiser installation on 900L2 | |
ALTALINK | 11-Aug-21 07:30 | 11-Aug-21 17:00 | 9.5 Hours
Daily |
166s787W (787L) - GOI, 166s 787W (166s Dow Chem Fort Saskatchewan), 787L (166s Dow Chemical Fort Saskatchewan - 787AL tap) | 1st trip and PRC5 maintenance and fix broken shroud | |
EPCOR | 12-Aug-21 05:00 | 13-Aug-21 17:00 | 1.5 Days
Continuous |
1045L @ Jasper Terminal E805S, Keephills 320P, Sundance 310P | 1045L at Jasper CVT/Arrestor Doble, JDS27/JDS12 Switch Maintenance | |
ATCO | 12-Aug-21 08:00 | 16-Aug-21 17:00 | 4.38 Days
Continuous |
732S 903 | 903 Breaker Maintenance | |
ALTALINK | 12-Aug-21 08:30 | 12-Aug-21 17:30 | 9 Hours
Daily |
19s905 (905L) - GOI | Replace grading capacitor on 19s905 240kV breaker. | |
ENMAX, ALTALINK | 13-Aug-21 08:00 | 13-Aug-21 16:00 | 8 Hours
Continuous |
1109L., 1109L (ENMAX 25 - ENMAX 65) | Power factor test 25MD240-1109 LA. 25 Sub SW152, SW153 Replace Switch Mech | |
ATCO | 13-Aug-21 08:00 | 14-Aug-21 17:00 | 1.38 Days
Continuous |
7L33 | Replace Structure 14 on 7L33 | |
ATCO | 13-Aug-21 08:00 | 20-Aug-21 16:00 | 7.33 Days
Continuous |
846S 701T, 846S 701TCS, 846S 702T, 846S 702TCS, 7L24, 7L24 (846s Grand Centre - 7LA24 tap), 846s 701T (846s Grand Centre), 846s 702T (846s Grand Centre) | Maintenance on 846S
Install mobile sub to by pass 701TCS, 702TCS. |
|
ATCO | 15-Aug-21 08:00 | 16-Aug-21 17:00 | 1.38 Days
Continuous |
7L33 | Replace Structure 59 on 7L33 | |
EPCOR | 16-Aug-21 07:00 | 16-Aug-21 17:00 | 10 Hours
Continuous |
240BA2 @ Argyll Transfer Station E629S and Bellamy E814S, 240BA2 (629s Argyll Transfer Station - 814s Bellamy) | Doble CT/Arrestors | |
ATCO | 16-Aug-21 08:30 | 18-Aug-21 16:30 | 2.33 Days
Continuous |
848S 908, 848s 908 (848s Ruth Lake) | 908 BKR Maintenance | |
ALTALINK | 16-Aug-21 09:30 | 19-Aug-21 14:30 | 3.21 Days
Continuous |
17s717W (717L-262s) - GOI, 717L (17s Benalto - 262s Rocky Mountain House) | A/B Line prot replacement. Tie in new 138B3 'B' CT cont | |
ALTALINK | 16-Aug-21 10:30 | 17-Aug-21 17:30 | 31 Hours
Continuous |
74s102 (Affecting C3 and C4) Advice | PRC5 1st Trip & Maintenance (SF6) | |
ALTALINK | 16-Aug-21 11:30 | 19-Aug-21 17:30 | 3.25 Days
Continuous |
83s T1 GOI, 83s T1 (83s Taber) | Replace 138 kV LA’s, TC filter, 25 kV bushings, and 138 kV bushings on T1 | |
ALTALINK | 16-Aug-21 12:00 | 20-Aug-21 18:00 | 4.25 Days
Continuous |
946L (89s - 38s) - GOI, 946L (38s East Edmonton - 89s Ellerslie) | Component Replacements 946L (Str's Range 30-71) | |
ATCO | 16-Aug-21 13:00 | 22-Aug-21 15:30 | 6.1 Days
Continuous |
930S SVC, 930s SVC (930s Arcenciel) | Svc air cooled maintenance, various PRC relay testing | |
ALTALINK | 17-Aug-21 07:15 | 19-Aug-21 17:45 | 2.44 Days
Continuous |
608L (138s - 418s - 528s) GOI and Advice, 608L (138s Windy Flats - 418s Ardenville - 528s Blue Trail Wind Farm) | Salvage 608AL31 Airbrake and install at training yard. | |
ATCO | 17-Aug-21 08:00 | 19-Aug-21 17:00 | 2.38 Days
Continuous |
732S 904, 732s 904 (732s Mitsue) | 904 Breaker Maintenance | |
ALTALINK | 17-Aug-21 14:00 | 17-Aug-21 17:00 | 3 Hours
Daily |
121s23N Advice, 121s 23N (121s Brooks) | 152BF, 452BF, T5 A/B, 138NB A/B protection trip test | |
ALTALINK | 19-Aug-21 07:00 | 19-Aug-21 17:30 | 10.5 Hours
Daily |
166s T1, T2, 707L, 862L & 899L - GOI | 1st trip PRC5 maintenance on 166s862N, fix CT shroud and capacitor mount; T1: replace conservator gauge, fix Hydran monitor warning. 166s1 clean and adjust | |
ATCO | 22-Aug-21 08:00 | 22-Aug-21 16:00 | 8 Hours
Continuous |
766S 901T, 766s 901T (766s Nevis) | TransAlta GARDEN PLAIN PROJECT
Complete the structural and electrical work related to protection panel, Automation & SCADA panel and telecom panels. Complete the line work associated with Line 9LA59 which will be connected to 1045S Garden Plain substation. |
|
BCH | 22-Aug-21 09:00 | 24-Aug-21 11:00 | 2.08 Days
Continuous |
1L275 (799s Coleman - Natal) | structure replacement, BC Maintenance does not affect the Alberta ATC | AB-BC |
ALTALINK | 22-Aug-21 10:00 | 26-Aug-21 17:30 | 4.31 Days
Continuous |
244s T1(TX18841) GOI, 244s T1 (244s Bowmanton) | maintenance, doble, leak repair | |
EPCOR | 23-Aug-21 07:00 | 24-Aug-21 17:00 | 1.42 Days
Continuous |
Summerside/Ellerslie S/S 1057L Outage | Isolate 1057L to cut over controls, status, alarms to new RTU at Summerside | |
ALTALINK | 23-Aug-21 07:00 | 24-Aug-21 18:00 | 1.46 Days
Continuous |
862L (166s - 258s) - GOI | Replacing 166s4 and also replacing strain insulators on 862L @ 258s | |
ATCO | 23-Aug-21 08:00 | 03-Sep-21 17:30 | 11.4 Days
Continuous |
2075S 900SST2, 2075s 900SST2 (2075s Newell) | - Install Breaker Thermal Windows in LV2 Room at 2075S Newell
- 900SST2 Gasket Replacements |
|
ATCO | 23-Aug-21 08:30 | 27-Aug-21 17:00 | 4.35 Days
Continuous |
9L939, 9L939 (77s Sagitawah - 809s Louise Creek) | Louise Creek Rebuild project- Replace 911.
9L939 needs to be out of service as it runs over the top of 911 breaker inside the substation |
|
ATCO | 23-Aug-21 08:30 | 03-Oct-21 17:00 | 41.35 Days
Continuous |
809S 902T, 809s 902T (809s Louise Creek) | Louise Creek Rebuild project Upgrade 902T protection.
August 23-26, 2021 Replace 911 BKR, Isolation points: 809S 911A, 809S 911B associated with 2-56595 9L939 Outage Aug 27-Oct.3, 2021 Expand GOI to include all of 902T isolation points 809S 500D1,809S 702A, 809S 910B, & 809S 911B |
|
ALTALINK | 23-Aug-21 09:30 | 26-Aug-21 16:30 | 3.29 Days
Continuous |
42s T1 (Tx18508) GOI, 42s T1 (42s Sarcee) | Migrate and commission all T1 TX18508, 42S44 (189), 42S40 (252) associated transformer protections, tap changer, breaker, breaker fail alarms, status, controls, metering and remote access to new RTU and LAN. . | |
ALTALINK | 23-Aug-21 10:00 | 26-Aug-21 18:00 | 3.33 Days
Continuous |
258s T1, 138kV Bus 1 & 862L - GOI, 258s T1 (258s Dow Hydro Carbons), 862L (166s Dow Chemical Fort Saskatchewan - 258s Dow Hydro Carbons) | T2: maintain, doble, fix leaks, 258s5 adjust, 258s152 PRC maintain | |
ATCO | 23-Aug-21 10:00 | 30-Aug-21 15:00 | 7.21 Days
Continuous |
7L32, 7L32 (813s Little Smoky - 862s South Bezanson) | Crossarm changing | |
ALTALINK | 23-Aug-21 12:00 | 27-Aug-21 18:00 | 4.25 Days
Continuous |
946L (89s - 38s) - GOI, 946L (38s East Edmonton - 89s Ellerslie) | Component Replacements 946L (Str's Range 30-71) | |
ATCO | 24-Aug-21 08:00 | 25-Aug-21 16:00 | 1.33 Days
Continuous |
793S 704, ATC 793s 704 (ATC 793s West Peace River), 7L04 (ATC 793s West Peace River - 839s Daishowa) | Complete 704 Maintenance PM, | |
BCH | 24-Aug-21 08:00 | 25-Aug-21 18:00 | 1.42 Days
Continuous |
1L274 (EFT - 1D2L274) | EFD T1 station work. Outage scheduled Aug 24 2300 to Aug 25 0300. AESO/AML supplies GRH and FRO | AB-BC |
SUNCOR | 24-Aug-21 08:00 | 06-Sep-21 17:00 | 13.38 Days
Continuous |
635PL9-1000 and 635PT-1000 | 260kV line structure change for line lift; maintenance of 260kV line, transformer, associated equipment and protection | |
ATCO | 24-Aug-21 08:30 | 26-Aug-21 16:30 | 2.33 Days
Continuous |
848S 905 | 905 BKR Maintenance | |
ATCO | 24-Aug-21 10:00 | 26-Aug-21 14:00 | 2.17 Days
Continuous |
7L27 | Changing a structure and xarms | |
ALTALINK | 25-Aug-21 07:00 | 25-Aug-21 19:00 | 12 Hours
Daily |
13s T2 & 138kV Portion of 13s – GOI | Replace 13s JBDC3 with new junction box. DC from the JB supplies 13s101, 13s452, 13s152, 13s552, 13s808N and 13s815W. | |
ALTALINK | 25-Aug-21 07:00 | 26-Aug-21 07:00 | 24 Hours
Continuous |
263s 138kV bus 1, T1, 718L, 870L GOI, 870L (262s Rocky Mountain House - 263s Strachan), 718L (250p Bighorn Plant - 263s Strachan), 263s T1 (263s Strachan) | 24hour outage to replace 263s1,138kv motor operated disconnect switch, qty 24 string glass insulators to be changed out. | |
BCH | 25-Aug-21 08:00 | 25-Aug-21 16:00 | 8 Hours
Continuous |
1L274 (B1s BCH Natal - 1D1L274) | structure refurbishment | AB-BC |
ATCO | 26-Aug-21 08:00 | 26-Aug-21 17:00 | 9 Hours
Continuous |
9L59, 9L59 (801s Anderson - 972s Tinchebray) | Change Angle Pole | |
ATCO | 26-Aug-21 08:00 | 03-Sep-21 17:00 | 8.38 Days
Continuous |
740S 700BS2, 740s 144kV Floating Bus (740s H.R.Milner) | 740S 770BS2 outage | |
BCH | 26-Aug-21 09:00 | 27-Aug-21 17:00 | 1.33 Days
Continuous |
2L113 (B1s Natal - B2s Cranbrook) | conductor repair | AB-BC |
EPCOR | 28-Aug-21 07:00 | 29-Aug-21 19:00 | 1.5 Days
Continuous |
TX1 @ Bellamy E814S | Bellamy TX1 Oil Clean up and inspection, Doble Bellamy TX1 PT | |
EPCOR | 30-Aug-21 07:00 | 30-Aug-21 17:00 | 10 Hours
Continuous |
LDS4 @ Lambton E803S, 803S EPCOR Lambton, EP 803s L2402 (EP 803s Lambton), EP 803s L2405 (EP 803s Lambton) | LDS4 Disconnect Maintenance | |
EPCOR | 30-Aug-21 07:00 | 03-Sep-21 17:00 | 4.42 Days
Continuous |
Dome TX2 Bushing Replacement, 665s T2 (665s Dome) | Replace 240kV Bushings (1007378) | |
ATCO | 30-Aug-21 08:00 | 02-Sep-21 17:00 | 3.38 Days
Continuous |
7L91, 7L91 (715s Leming Lake - 826s Marguerite Lake) | Clearance Mitigation GOI on 7L91 HOP on 7L66 | |
ALTALINK, ENMAX | 30-Aug-21 09:00 | 01-Sep-21 17:00 | 2.33 Days
Continuous |
28.80L(42s - Enmax sub #28) GOI, 28.80L (42s Sarcee - ENMAX 28) | Migrate and commission all 42s28 (652) & L6-28.80L at 42s Sarcee associated line protections, recloser, synch check, breakers, breaker fail alarms, status, controls, metering and remote access to new RTU and LAN. . | |
ATCO | 30-Aug-21 09:00 | 02-Sep-21 16:00 | 3.29 Days
Continuous |
7L113, 7L113 (853s Ring Creek - 930s Arcenciel) | Time Domain Line Protection Project for circuit modifications required to install new relays at Ring Creek 853S & Arcenceil 930S Substations. | |
ALTALINK | 30-Aug-21 09:15 | 03-Sep-21 17:45 | 4.35 Days
Continuous |
170L (632s - 799s) GOI, 170L (632s Russell - 799s Coleman) | Fire Mitigation; Structure Replacements Strs 48-54 | AB-BC |
ATCO | 30-Aug-21 11:00 | 10-Sep-21 16:00 | 11.21 Days
Continuous |
840S CONVERTER | 6 x 25 kV breaker maintenance, replace station controller, leak repair 901T | |
ALTALINK, EPCOR | 30-Aug-21 12:00 | 03-Sep-21 18:00 | 4.25 Days
Continuous |
947L (89s - E987s) - GOI, 947L (89s Ellerslie - 987s Clover Bar) | Component Replacements 947L (Str's Range 2-88) | |
ALTALINK | 31-Aug-21 08:30 | 01-Sep-21 16:30 | 1.33 Days
Daily |
370s T3 (TX18307) GOI | Clean up oil spill and repair leak. | |
EPCOR | 01-Sep-21 07:00 | 02-Sep-21 17:00 | 1.42 Days
Continuous |
Summerside S/S TX1 Bay, 657s T1 (657s Summerside) | Isolate Summerside TX1 Bay to cut over control, alarms, status to new RTU | |
ALTALINK | 01-Sep-21 12:30 | 01-Sep-21 16:30 | 4 Hours
Daily |
17s49 (17s717W-262s) - Advice, 717L (17s Benalto - 262s Rocky Mountain House) | Trip test | |
ALTALINK | 02-Sep-21 08:45 | 02-Sep-21 16:15 | 7.5 Hours
Daily |
908L (89s) - OOS | Breaker open on 908L for TPR work. | |
ALTALINK | 03-Sep-21 07:00 | 03-Sep-21 18:00 | 11 Hours
Daily |
861L (258s - 71s) - GOI | Replacing strain insulators on 861L @ 258s | |
EPCOR | 06-Sep-21 07:00 | 07-Sep-21 17:00 | 1.42 Days
Continuous |
Summerside S/S TX2 Bay, 657s T2 (657s Summerside) | Isolate Summerside TX2 Bay to cut over controls, alarms, status to new RTU | |
BCH | 06-Sep-21 09:00 | 06-Sep-21 19:00 | 10 Hours
Continuous |
1L274 (48s Pocaterra - Britt Creek) | Station equipnment inspection | AB-BC |
ATCO | 06-Sep-21 10:00 | 13-Sep-21 15:00 | 7.21 Days
Continuous |
7L32, 7L32 (811s Clairmont Lake - 862s South Bezanson) | Crossarm changing | |
ALTALINK | 07-Sep-21 07:45 | 08-Sep-21 16:45 | 1.38 Days
Continuous |
1083L (288s - 63s) GOI | Fix 63s1083 MOD | |
ENMAX, ALTALINK | 07-Sep-21 08:00 | 07-Sep-21 18:00 | 10 Hours
Continuous |
7.84L. 36.81L. 36.1TR. 36.3TR. 36PT138-Z31., 7.84L (ENMAX 7 - ENMAX 36), 36.81L (44s Bearspaw - ENMAX 36), 36.1TR (ENMAX 36), 36.3TR (ENMAX 36) | Fall Substation Washing | |
ATCO | 07-Sep-21 08:30 | 09-Sep-21 16:50 | 2.35 Days
Continuous |
925S 902T, 925s 902T (925s Green Stocking) | 902T maintenance | |
ATCO | 07-Sep-21 08:30 | 26-Sep-21 17:30 | 19.38 Days
Continuous |
2029S BUILDING VALVE HALL, 2075S BUILDING VALVE HALL, 13L50 (DC LINK), 13L50 (2029s Heathfield - 2075s Newell) | Valve Hall Inspections
- Valve Hall Camera Repairs - LOP work |
|
ALTALINK, ENMAX | 07-Sep-21 09:00 | 09-Sep-21 17:00 | 2.33 Days
Continuous |
693L (42s - Enmax sub # 10) GOI, 693L (42s Sarcee - ENMAX 10) | Migrate and commission all 42s693 (1452) & L5-693L at 42s Sarcee associated line protections, recloser, POW, synch check, breakers, breaker fail alarms, status, controls, metering and remote access to new RTU and LAN. | |
ALTALINK, EPCOR | 07-Sep-21 09:00 | 10-Sep-21 18:00 | 3.38 Days
Continuous |
947L (89s - E987s) - GOI, 947L (89s Ellerslie - 987s Clover Bar) | Component Replacements 947L (Str's Range 2-88) | |
ALTALINK | 07-Sep-21 09:15 | 10-Sep-21 17:45 | 3.35 Days
Continuous |
170L (632s - 799s) GOI, 170L (632s Russell - 799s Coleman) | Fire Mitigation; Structure Replacements Strs 48-54 | AB-BC |
ALTALINK | 07-Sep-21 09:30 | 09-Sep-21 17:00 | 2.31 Days
Continuous |
17s T3 TX18814 - GOI | SCADA alarm/control upgrade for T3, s389, s2852, Tie in new 138B3 'B' CT cont | |
ALTALINK | 08-Sep-21 07:00 | 14-Sep-21 18:00 | 6.46 Days
Continuous |
801L (62s-294s) - GOI, 801L (62s Brazeau - 294s Brazeau Outlet Works) | Replace 801L Str 4, 15, 94 and 97 for urgent line clearance mitigation. | |
CMH | 08-Sep-21 08:00 | 16-Sep-21 17:00 | 8.38 Days
Continuous |
T15 (MH69s-1 Power Plant Switchyard) | rung T15 north T15 segment upgrade phase 4C | |
ALTALINK | 08-Sep-21 10:00 | 08-Sep-21 13:00 | 3 Hours
Daily |
893L (312s-I112s-I806s-103s) OOS | Open 893L for 312s MPLS upgrade. | |
ENMAX, ALTALINK | 10-Sep-21 08:00 | 10-Sep-21 16:00 | 8 Hours
Continuous |
50L. 21.2TR. 138KV PT @ Bearspaw. 21 CAP. 21PT138-Z31, 50L (44s Bearspaw Plant - ENMAX 21), 21.2TR (ENMAX 21) | Fall Substation Washing | |
ALTALINK | 13-Sep-21 07:00 | 17-Sep-21 17:00 | 4.42 Days
Continuous |
511s T30 & SVC Plus - GOI, AML 511s T30 (AML 511s Crossings), AML 511s SVC Plus (AML 511s Crossings) | Doble T30, SVC Plus maintenance, MSR re-wiring. | |
ALTALINK | 13-Sep-21 07:30 | 17-Sep-21 13:00 | 4.23 Days
Continuous |
63s 138kV North Bus & T3 GOI, 63s T1 (63s Red Deer), 63s 24 (63s Red Deer), 63s 26 (63s Red Deer), 63s T3 (63s Red Deer), 63s 51 (63s Red Deer), 426L (63s Red Deer - 194s South Red Deer) | Wire CT contributions for new 138kV bus protections and complete trip testing | |
ENMAX | 13-Sep-21 08:00 | 13-Sep-21 16:00 | 8 Hours
Continuous |
25B240-D131 | HV Breaker maintenance 25B240-D131 | |
ALTALINK | 13-Sep-21 08:00 | 15-Sep-21 16:00 | 2.33 Days
Continuous |
510s AC Filter 14 - GOI, 510s ACF14 (510s Sunnybrook) | Annual Filter Bank outage and inspections | |
ATCO | 13-Sep-21 08:00 | 20-Sep-21 16:00 | 7.33 Days
Continuous |
9L07, 951S 905, 951S 906, 9L07 (951s Thickwood - 2011s Dawes), 951s 905 (951s Thickwood Hills), 951s 906 (951s Thickwood Hills) | Cut in CT/'PT/SCADA circuits to the new RAS relays | |
ATCO, ALTALINK | 13-Sep-21 08:00 | 20-Sep-21 17:00 | 7.38 Days
Continuous |
7L77, 7L77 (395s North Holden - 709s Vegreville) | GOI on 7L77 from 7L77D1 to 395S Holdon change arms insulators | |
ATCO, ALBIAN, SHELL | 13-Sep-21 08:30 | 13-Sep-21 12:00 | 3.5 Hours
Continuous |
919S 906, 847S 901T, 919s 906 (919s Hartley), 847s 901T (847s Muskeg River) | PRC005 Trip coil testing, Test and operate 906, 901T @ 847S OOS
|
|
ATCO | 13-Sep-21 08:30 | 15-Sep-21 16:50 | 2.35 Days
Continuous |
925S 901T | 901T maintenance | |
ALTALINK, ENMAX | 13-Sep-21 09:00 | 15-Sep-21 17:00 | 2.33 Days
Continuous |
35.81L (42s - Enmax sub # 35) GOI, 35.81L (42s Sarcee - ENMAX 35) | Migrate and commission all 42s35 (352) & L3-35.81L at 42s Sarcee associated line protections, recloser, POW, synch check, breakers, breaker fail alarms, status, controls, metering and remote access to new RTU and LAN. . | |
BCH | 13-Sep-21 09:00 | 17-Sep-21 17:00 | 4.33 Days
Continuous |
2L294 (A.A. Lambert - Cranbrook) | disconnect switch inspections | AB-BC |
ATCO, ALBIAN | 13-Sep-21 12:00 | 13-Sep-21 16:00 | 4 Hours
Continuous |
919S 908, 847S 902T, 919s 908 (919s Hartley), 847s 902T (847s Muskeg River) | PRC005 Trip coil testing. Test and operate 908 847S 902T OOS, | |
ALTALINK, EPCOR | 13-Sep-21 12:00 | 14-Sep-21 18:00 | 30 Hours
Continuous |
921L (71s-E987s) & 71s 240kV West Bus -, 921L (71s Lamoureux - 987s Clover Bar) | Component Replacements on dead end glass on 921L, and Str's 41 & 72 | |
ALTALINK | 13-Sep-21 12:00 | 16-Sep-21 18:00 | 3.25 Days
Continuous |
861L (258s - 71s) - GOI | Components insulator replacements (Str's Range 3-15) | |
ALTALINK | 13-Sep-21 12:00 | 26-Sep-21 18:00 | 13.25 Days
Continuous |
37s T6 (Tx 18309) - GOI, 37s T6 (37s North Calder) | Maintenance, doble and leak repairs. PRC5 work. | |
SUNCOR | 14-Sep-21 08:00 | 27-Sep-21 17:00 | 13.38 Days
Continuous |
635PL9-1001 and 635PT-1001 | 260kV line structure change for line lift; maintenance of 260kV line, transformer, associated equipment and protection | |
ATCO | 14-Sep-21 13:30 | 14-Sep-21 16:30 | 3 Hours
Continuous |
828S 703, 7L133, 7L133 (786s High Level - 828s Sulphur Point) | PRC-005 - TRIP COIL TESTING - BREAKER 703 @ 828S
703 OOS for duration of work under T&O for trip coil testing. |
|
ALTALINK, EPCOR | 15-Sep-21 07:00 | 16-Sep-21 18:00 | 1.46 Days
Continuous |
920L (71s - E557s) - GOI, 920L (71s Lamoureux - 557s Castle Downs) | Component Replacements on 920L Str's Range ( 52D-100 ) | |
ENMAX, ALTALINK | 15-Sep-21 12:00 | 15-Sep-21 18:00 | 6 Hours
Continuous |
21.80L. 20.82L. 60S100. 21.1TR. 21.4TR, 21.80L (42s Sarcee - ENMAX 21), 20.82L (ENMAX 20 - ENMAX 21), 21.1TR (ENMAX 21), 21.4TR (ENMAX 21) | Fall Substation Washing | |
ALTALINK, ENMAX | 16-Sep-21 09:15 | 17-Sep-21 17:15 | 1.33 Days
Daily |
42s7 (7.82L) GOI, 7.82L (42s Sarcee - ENMAX 7) | PRC 1st Trip & Maintenance | |
ALTALINK | 17-Sep-21 13:00 | 20-Sep-21 17:00 | 3.17 Days
Continuous |
63s 240kV North Bus & T1 GOI, 63s T1 (63s Red Deer), 63s 24 (63s Red Deer), 63s 152 (63s Red Deer), 63s 452 (63s Red Deer), 63s 752 (63s Red Deer), 63s 2652 (63s Red Deer) | Wire CT contributions for new 138kV bus protections and complete trip testing | |
BCH | 18-Sep-21 09:00 | 25-Sep-21 17:00 | 7.33 Days
Continuous |
5L92 (Cranbrook - Selkirk) | insulator replacement | AB-BC |
ATCO | 19-Sep-21 08:30 | 23-Sep-21 15:00 | 4.27 Days
Continuous |
790S 703T, 790s 703T (790s Poplar Hill) | 703T main
704 top up low pole with SF6 |
|
ATCO | 19-Sep-21 09:00 | 23-Sep-21 17:00 | 4.33 Days
Continuous |
790S 704, 790S 703T | Replace 1 phase on 790S 704, 790S 703T maintenance | |
ATCO | 20-Sep-21 08:00 | 23-Sep-21 16:00 | 3.33 Days
Continuous |
951S 900BS2, 951S 908, 951S 903, 951S 906, 951s 903 (951s Thickwood Hills), 951s 906 (951s Thickwood Hills), 951s 908 (951s Thickwood Hills) | 951S construction for 9L162 & 9L193 addition
AESO should be notified of any changes to below workplan: Jan 20, 2021 – Feb 20, 2021 Isolation pts: 908B,909A Impact: BKR 908 OOS Scope of work: Demo bus & install 909A & 909B Feb 21, 2021 – Feb 23, 2021 Expand to isolation pts:903B, 906B,908B Impact: BKR 903,BKR 906, 900BS2 OOS Scope of work: Make connections to 909A & 912A |
|
ATCO | 20-Sep-21 08:00 | 28-Sep-21 16:00 | 8.33 Days
Continuous |
12L44 | Suncor Capacity increase project
Cut in new CT and PT circuit extension to the new RAS relays, T&O Line Terminal Open (LTO) on 1206, 1207, and 12L44D1 @ 939S APL Livock and 1244D1, 1205, 1206, 1201TA, and 901TA @ 951S APL Thickwood. Complete commissioning of RAS relays, end-to-end tests including output to Thickwood RAS |
|
ALTALINK, ATCO | 20-Sep-21 12:30 | 23-Sep-21 17:30 | 3.21 Days
Continuous |
650s T3 & SVC - GOI, 650s T3 (650s Hansman Lake), 650S SVC (650s Hansman Lake) | Maintenance on SVC. T3 maintenance, doble Schedued By: Tyler Schiltroth Requested By: MAPS North Contact #: Issue to: Jory Schell Contact #:403-318-4758 | |
ATCO | 21-Sep-21 08:30 | 22-Sep-21 16:30 | 1.33 Days
Continuous |
848S 906 | 906 BKR Maintenance | |
ENMAX, ALTALINK | 21-Sep-21 12:00 | 21-Sep-21 16:00 | 4 Hours
Continuous |
23.80L. 23.4TR, 23.80L (74s Janet - ENMAX 23), 23.4TR (ENMAX 23) | Fall Substation Washing | |
ATCO | 22-Sep-21 09:00 | 23-Sep-21 17:00 | 1.33 Days
Continuous |
790S 702, 7L22 | 790S 702 maintenance, 7L22 open ended | |
ATCO | 24-Sep-21 08:00 | 26-Sep-21 16:00 | 2.33 Days
Continuous |
951S 900BS1, 951s 1201T (951s Thickwood Hills), 951s 920C (951s Thickwood) | 951S construction for 240kv expansion - 9L162 & 9L193 addition
Connect 910A to 900BS1 Impact: 900BS1 OOS, BKR 901 OOS, BKR 904 OOS, BKR 907 OOS, 920C OOS |
|
ALTALINK | 25-Sep-21 06:15 | 29-Sep-21 17:45 | 4.48 Days
Continuous |
121s23N GOI, 121s 23N (121s Brooks) | 121s23N Protection and control replacement. | |
EPCOR | 27-Sep-21 07:00 | 01-Oct-21 17:00 | 4.42 Days
Continuous |
SDS2L @ Cloverbar E987S, 987s T2 (987s Clover Bar) | Substation Manual Disconnect Switches LCR - Clover Bar SDS2L
- SST2 Outage |
|
EPCOR | 27-Sep-21 07:00 | 12-Nov-21 17:00 | 46.46 Days
Continuous |
Victoria TX5, EP 511s Victoria T5 (EP 511s Victoria) | Victoria TX5 regasketing | |
ALTALINK | 27-Sep-21 07:30 | 01-Oct-21 14:00 | 4.27 Days
Continuous |
63s 138kV South Bus & T4 GOI, 63s T4 (63s Red Deer), 63s T2 (63s Red Deer), 63s 25 (63s Red Deer), 63s 51 (63s Red Deer), 63s 427 (63s Red Deer), 63s 648 (63s Red Deer), 427L (63s Red Deer - 247s Piper Creek), 648L (63s Red Deer - 580s Sylvan Lake) | Wire CT contributions for new 138kV bus protections and complete trip testing | |
BCH | 27-Sep-21 08:00 | 27-Sep-21 18:00 | 10 Hours
Continuous |
1L274 (48s Pocaterra - Britt Creek) | BCK station work | AB-BC |
ENMAX, ALTALINK | 27-Sep-21 08:00 | 17-Oct-21 16:00 | 20.33 Days
Continuous |
7.82L, 7.82L (42s Sarcee - ENMAX 7) | HW 8 relocation. Line relocation at 101 street.. Phasing required. | |
BCH | 27-Sep-21 09:00 | 08-Oct-21 17:00 | 11.33 Days
Continuous |
2L293 (Nelway - Selkirk) | structure replacement, BC Maintenance does not affect the Alberta ATC | AB-BC |
ALTALINK | 27-Sep-21 12:00 | 17-Oct-21 18:00 | 20.25 Days
Continuous |
320P T6 – GOI, 320p T6 (320p Keephills) | T6 Maintenance, leaks, CT replacement, Model 11 Relay replacements. | |
ATCO | 27-Sep-21 14:00 | 04-Oct-21 12:00 | 6.92 Days
Continuous |
850S 701T, 850s 701T (850s Rainbow Cogen) | Perform maintenance testing on the following equipment:
850S 701T 850S 701T Protective Relays 850S RB4 Switchgear breakers 791S BKR 459 |
|
ALTALINK | 28-Sep-21 08:00 | 03-Oct-21 18:00 | 5.42 Days
Continuous |
62s T5 (Tx 18580) - GOI | 62sT5 PRC5 doble, maintenance, buck indicator, gas monitor failure, Connect IDD, LA base insulators, leak from H1, LTC push buttons replace for MR | |
ATCO | 29-Sep-21 08:00 | 01-Oct-21 16:00 | 2.33 Days
Continuous |
9L59, 9L59 (801s Anderson - 972s Tinchebray) | TransAlta GARDEN PLAIN PROJECT
Line 9LA59 tie-in to Garden Plain Sub |
|
ATCO | 29-Sep-21 08:00 | 01-Oct-21 16:00 | 2.33 Days
Continuous |
801S 903, 801S 902, 9L59, 9L59 (801s Anderson - 972s Tinchebray) | TransAlta GARDEN PLAIN PROJECT
Relay Settings changes |
|
ATCO | 29-Sep-21 08:00 | 01-Oct-21 16:00 | 2.33 Days
Continuous |
972S 901, 972S 902, 9L59, 9L59 (801s Anderson - 972s Tinchebray) | TransAlta GARDEN PLAIN PROJECT
Relay Settings Changes |
|
CMH | 01-Oct-21 08:00 | 03-Oct-21 16:00 | 2.33 Days
Continuous |
MHS9 T11 (MHS9 Power Plant) | install new PT | |
ATCO | 01-Oct-21 08:00 | 05-Oct-21 16:00 | 4.33 Days
Continuous |
757S 911, 9L79, 757s 9L79D1 (757s Battle River) | Replace Breaker operating mech's on 911 | |
ATCO | 01-Oct-21 09:00 | 05-Oct-21 16:30 | 4.31 Days
Continuous |
9L79, 755S 902, 755S 9L79 CHANNEL A TP FAIL, 755S 9L79 CHANNEL B TP FAIL, 755S 9L79 Protection Relay, 757s 9L79D1 (757s Battle River) | Protection upgrade to 9L79 relays, testing of MODs @755s. PRC005 at the 757s Battle River end on Breaker 911 | |
ALTALINK | 01-Oct-21 14:00 | 04-Oct-21 17:00 | 3.13 Days
Continuous |
63s 240kV South BUS & T2 GOI, 63s T2 (63s Red Deer), 63s 352 (63s Red Deer), 63s 652 (63s Red Deer), 63s 952 (63s Red Deer), 63s 2752 (63s Red Deer) | Wire CT contributions for new 138kV bus protections and complete trip testing | |
EPCOR | 04-Oct-21 07:00 | 06-Oct-21 17:00 | 2.42 Days
Continuous |
1201 Bay @ Genesee 330P, 330p 1201 (330p Genesee) | 1201 Maintenance and CT Doble | |
EPCOR | 04-Oct-21 07:00 | 15-Oct-21 17:00 | 11.42 Days
Continuous |
240CV5 @ Victoria E511S and CastleDowns E557S, CV5 (EP 511s Victoria - 557s Castle Downs) | CV5 Manhole Inspections | |
ALTALINK | 04-Oct-21 07:00 | 15-Oct-21 17:00 | 11.42 Days
Continuous |
CV5 (E511s-E557s) EPCOR - Info | Epcor CV5 Manhole Inspections | |
ATCO | 04-Oct-21 08:00 | 08-Oct-21 16:00 | 4.33 Days
Continuous |
720S 902T | 902T leak mitigation and transformer maintenance | |
ATCO, ALTALINK | 04-Oct-21 08:00 | 08-Oct-21 17:00 | 4.38 Days
Continuous |
7L77, 7L77 (395s North Holden - 709s Vegreville) | GOI on 7L77 from 7L77D1 to 395S Holdon change arms insulators | |
ATCO | 04-Oct-21 08:00 | 18-Oct-21 17:00 | 14.38 Days
Continuous |
9L939, 9L939 (77s Sagitawah - 809s Louise Creek) | Louise Creek Rebuild project
Wiring for 905/906BF relays. CT ratio changes. Relay programming. Commission control, alarms and status. Blocking procedures for BF and Bus protections. |
|
ALTALINK | 04-Oct-21 09:00 | 07-Oct-21 14:00 | 3.21 Days
Continuous |
39s T1 & 240kV Bus 1 - GOI | Replace 240kV CTs associated with 39s26. Repair 39s25. | |
ALTALINK | 04-Oct-21 09:30 | 06-Oct-21 16:30 | 2.29 Days
Continuous |
42s Cap Bank 3 (C3) GOI, 42s 76 (42s Sarcee), 42s C3 (42s Sarcee) | Migrate and commission all Cap bank C3 & 42S76 (2252) associated protections, breakers, breaker fail, POW alarms, status, controls, metering and remote access to new RTU and LAN. | |
ALTALINK | 04-Oct-21 11:00 | 08-Oct-21 13:00 | 4.08 Days
Continuous |
61s 138kV Bus 1 (T1, 202L, 836L) - GOI | Replacing 61s13 and strain insulators on 836L | |
ALTALINK | 04-Oct-21 12:15 | 08-Oct-21 17:45 | 4.23 Days
Continuous |
48s887X (887L) GOI, 887L (48s Pocaterra - BCH Britt Creek) | Install breaker failure protection for breaker 252 | AB-BC |
ALTALINK | 07-Oct-21 07:30 | 07-Oct-21 18:00 | 10.5 Hours
Daily |
48s Station & 777L (48s - 245s) GOI, 777L (48s Pocaterra - 245s Seebe) | Install breaker failure protection for breaker 252 | |
ATCO | 11-Oct-21 08:00 | 18-Oct-21 16:00 | 7.33 Days
Continuous |
9L23, 848S 905, 848S 906, 9L23 (848s Ruth Lake - 977s Salt Creek), 848s 906 (848s Ruth Lake), 848s 905 (848s Ruth Lake) | Cut in new CT and PT circuit extension to the new RAS relays, complete SCADA terminations | |
BCH | 11-Oct-21 09:00 | 05-Nov-21 17:00 | 25.33 Days
Continuous |
2L112 (Boundary - Nelway) | oil containment install, BC Maintenance does not affect the Alberta ATC | AB-BC |
ALTALINK | 11-Oct-21 09:30 | 13-Oct-21 18:00 | 2.35 Days
Continuous |
1206L (89s-12s) - GOI | Scope of work includes maintenance on structures 2, 7, 16, 31, 48, 50, 51, 52, 55, 77 and 78. | |
EPCOR | 12-Oct-21 07:00 | 12-Oct-21 17:00 | 10 Hours
Continuous |
DDS4 and TX2 @ Dome E665S, 665s DDS4 (665s Dome), 665s T2 (665s Dome) | DDS4 maintenance | |
EPCOR | 12-Oct-21 07:00 | 14-Oct-21 17:00 | 2.42 Days
Continuous |
330p 1204 (330p Genesee), 330p 1205 (330p Genesee) | 1204 Bay Doble, G2 Arrestor Doble, G2 Zone Relay Maintenance | |
ALTALINK, ENMAX | 12-Oct-21 09:00 | 14-Oct-21 17:00 | 2.33 Days
Continuous |
42s7.82 (42s - Enmax Sub #7) Advice, 7.82L (42s Sarcee - ENMAX 7) | Migrate and commission all 42s7 (1552) & L15-7.82L at 42s Sarcee associated line protections, recloser, synch check, breakers, breaker fail alarms, status, controls, metering and remote access to new RTU and LAN. Install and commission new SCADA meter. | |
ALTALINK | 13-Oct-21 07:00 | 13-Oct-21 18:00 | 11 Hours
Daily |
903L (17s-320p) - GOI, 903L (17s Benalto - 320p Keephills) | Asset Management request for crew to hold GOI and escort Acuren to inspect welds on 903L66 | |
ALTALINK | 14-Oct-21 07:00 | 16-Oct-21 18:00 | 2.46 Days
Continuous |
1212L (89s-12s) - GOI | Scope of work includes maintenance on structures 31, 42, 46, 71 and 76 | |
ALTALINK | 14-Oct-21 08:15 | 15-Oct-21 15:45 | 31.5 Hours
Continuous |
368s 138kV Bus1 (T1, C1, C2, 879L) GOI, 879L (244s Bowmanton - 368s Burdett), 368s C1 (368s Burdett), 368s C2 (368s Burdett), 368s T1 (368s Burdett) | install/commission new protections (rattlesnake ridge) | |
ALTALINK | 15-Oct-21 07:15 | 18-Oct-21 17:45 | 3.44 Days
Continuous |
820L (254s - 315s - 67s) GOI, 820L (254s Coaldale - 820AL tap), 820L (67s Stirling - 820AL tap) | Scope of work includes maintenance on structures 160, 161, 168, 175, 176, 177, 179, 187, 190, 197 and 198 | |
EPCOR | 15-Oct-21 17:00 | 16-Oct-21 17:00 | 24 Hours
Continuous |
72kV Bus 1 and 2 @ Cloverbar E987s and Namao, 987s Cloverbar 72kV Bus 1, 987s Cloverbar 72kV Bus 2 | Arrestor Support Replacement, CDS4 repair, Bus 1/2 doble, CN10 Line Arrestor doble | |
ALTALINK | 16-Oct-21 08:15 | 17-Oct-21 15:45 | 31.5 Hours
Continuous |
368s 138kV Bus2 (T2, C1, C2, 612L, 722L), 722L (107s Westfield - 368s Burdett), 612L (336s Fincastle - 368s Burdett), 368s C1 (368s Burdett), 368s C2 (368s Burdett), 368s T2 (368s Burdett) | install/commission new protections (rattlesnake ridge) | |
ALTALINK | 17-Oct-21 07:00 | 18-Oct-21 18:00 | 1.46 Days
Continuous |
1209L (89s-E330p) - GOI | Scope of work includes maintenance on structures 57, 59, 62, 67 and 68 | |
ENMAX | 18-Oct-21 08:00 | 21-Oct-21 16:00 | 3.33 Days
Continuous |
833L | 12B138-833L CT Replacement | |
ATCO | 18-Oct-21 08:00 | 26-Oct-21 16:00 | 8.33 Days
Continuous |
12L41 | Suncor Capacity increase Project
Cut in new CT and PT circuit extension to the new RAS relays, T&O Line Terminal Open (LTO) on 1206, 1207, and 12L41D1 @ 939S APL Livock and @ 510S Sunnybrook (Altalink). Complete commissioning of RAS relays, end-to-end tests including output to Thickwood RAS |
|
BCH | 18-Oct-21 09:00 | 21-Oct-21 17:00 | 3.33 Days
Continuous |
5L94 (Cranbrook - 102s Langdon) | NERC PM | AB-BC |
ALTALINK | 18-Oct-21 09:00 | 29-Oct-21 18:00 | 11.38 Days
Continuous |
1201L (520s - B2s) GOI, 1201L (520s Bennett - BCH Cranbrook) | components-structure range 383-464 | AB-BC |
MONTANA | 18-Oct-21 09:00 | 29-Oct-21 18:00 | 11.38 Days
Continuous |
MATL (120s Picture Butte - Montana) | align with 1201L outage | AB-MATL |
ALTALINK | 18-Oct-21 09:30 | 19-Oct-21 16:30 | 31 Hours
Continuous |
42s70 GOI, 42s 70 (42s Sarcee) | Migrate and commission all 42s70 (1052) at 42s Sarcee associated protections, synch check, breakers, breaker fail alarms, status, controls, metering and remote access to new RTU and LAN. Project PM: Golaleh Rahimi Issue to: Jesse Soonias Contact #: 403-606-8152 | |
ALTALINK | 18-Oct-21 10:05 | 25-Oct-21 17:30 | 7.31 Days
Continuous |
520s552 GOI | 520s552 Replace "A Phase" pole, & Corona Ring Bent Replacement | |
ALTALINK | 18-Oct-21 11:00 | 21-Oct-21 18:00 | 3.29 Days
Continuous |
89s T1 & 240kV West Bus 1 - GOI | Replace 240kV PTs 89s80 & 89s90 | |
ALTALINK, Lethbridge | 19-Oct-21 08:00 | 19-Oct-21 13:00 | 5 Hours
Continuous |
667L (146s Lethbridge MacDonald - 370s North Lethbridge), 146s 667 (146s Lethbridge McDonald) | test trip and breaker fail trip | |
ATCO | 19-Oct-21 08:00 | 01-Nov-21 17:00 | 13.38 Days
Continuous |
9L05, 9L05 (809s Louise Creek - 813s Little Smoky) | Louise Creek Rebuild project
Wiring for 904/905BF relays. CT ratio changes. Relay programming and functionality. Commission control, alarms and status. Blocking procedures for BF and Bus protections. |
|
EPCOR | 20-Oct-21 07:00 | 22-Oct-21 17:00 | 2.42 Days
Continuous |
C2404 and C2406 @ Cloverbar E987S, 987s C2404 (987s Clover Bar), 987s C2406 (987s Clover Bar) | 240CVT 85/86/87 and C2404 Bay CT's Doble | |
ATCO | 20-Oct-21 09:00 | 20-Oct-21 17:00 | 8 Hours
Continuous |
811S 709, 7L39 | 811S 709 partial maintenance | |
ALTALINK | 21-Oct-21 07:00 | 21-Oct-21 18:00 | 11 Hours
Daily |
913L (338s - 69s) - GOI, 913L (69s North Barrhead - 338s Cherhill) | Crews performing mtce. on Structure #913L124 | |
EPCOR | 25-Oct-21 07:00 | 29-Oct-21 17:00 | 4.42 Days
Continuous |
LSD2 @ Lambton E803S | Lambton LDS2 LCR | |
ENMAX | 25-Oct-21 08:00 | 28-Oct-21 16:00 | 3.33 Days
Continuous |
832L | 12B138-832L CT Replacement | |
ATCO | 25-Oct-21 08:00 | 01-Nov-21 16:00 | 7.33 Days
Continuous |
848S 901T, 848s 901T (848s Ruth Lake) | Complete cut in CT/'PT/SCADAcircuits to the new RAS relays | |
BCH | 25-Oct-21 09:00 | 29-Oct-21 17:00 | 4.33 Days
Continuous |
5L51 (Custer - Ingledow) | insulator replacement, BC Maintenance does not affect the Alberta ATC | AB-BC |
ATCO | 25-Oct-21 09:00 | 11-Nov-21 15:30 | 17.31 Days
Continuous |
757S 704, 757S 704B, 757S 704PT, 757s 704 (757s Battle River) |
PRC005 work on 704 Breaker, 704T Maintenance PRC005 work on 704 Breaker |
|
ALTALINK | 25-Oct-21 11:00 | 28-Oct-21 18:00 | 3.29 Days
Continuous |
89s T2 & 240kV East Bus 2 - GOI | Replace 240kV PTs 89s91. Maintainance on 89s8, 89s16, 89s32. | |
ALTALINK, EPCOR | 25-Oct-21 12:00 | 28-Oct-21 18:00 | 3.25 Days
Continuous |
908L (89s-E816s) - GOI, 908L (89s Ellerslie - 816s Petrolia) | Component replacements and fire mitigation on 908L Str's Range 200-232 | |
EPCOR | 25-Oct-21 12:00 | 28-Oct-21 18:00 | 3.25 Days
Continuous |
ALTALINK - 908L - DE-ENERGIZE LINE | Component replacements and fire mitigation on 908L Str's Range 200-232 | |
EPCOR, ALTALINK | 26-Oct-21 07:00 | 29-Oct-21 17:00 | 3.42 Days
Continuous |
TX1 and 1059L @ East Industrial E52S and East Edmonton 38S and Lambton E803S, 1059L (38s East Edmonton - EP 803s Lambton), 52s T1 (52s East Industrial) | TX1 Tap Changer Maintenance, 1059L CT and Arrestor Doble, EDS1 Maintenance | |
ALTALINK, Lethbridge | 27-Oct-21 08:00 | 27-Oct-21 13:00 | 5 Hours
Daily |
667L (146s Lethbridge MacDonald - 370s North Lethbridge), 813L (146s Lethbridge MacDonald - 241s Lethbridge Uplands) | energize new distribution transformer | |
BCH | 27-Oct-21 08:00 | 27-Oct-21 18:00 | 10 Hours
Continuous |
1L274 (48s Pocaterra - Britt Creek) | BCK station work | AB-BC |
ALTALINK | 01-Nov-21 07:00 | 04-Nov-21 18:00 | 3.46 Days
Continuous |
121s 25kV BUS 1 GOI, 121s T5 (121s Brooks) | Replace 121s38 Switch Glass. Migrate 25kV Bus 1 PT distribution to new building. | |
EPCOR | 01-Nov-21 07:00 | 05-Nov-21 17:00 | 4.42 Days
Continuous |
LDS5 @ Lambton E803S | Lambton LDS5 LCR | |
ATCO | 01-Nov-21 08:00 | 03-Nov-21 17:00 | 2.38 Days
Continuous |
740S 701T, 740S 702T, 740S 703T, 740s 701T (740s H.R.Milner), 740s 702T (740s H.R.Milner), 740s 703T (740s H.R.Milner) | maintenance | |
Lethbridge | 01-Nov-21 08:00 | 04-Nov-21 16:00 | 3.33 Days
Continuous |
667L ( 146S) | Air break and switch function test and maintance | |
BCH | 01-Nov-21 09:00 | 05-Nov-21 17:00 | 4.33 Days
Continuous |
5L52 (Custer - Ingledow) | insulator replacement, BC Maintenance does not affect the Alberta ATC | AB-BC |
ALTALINK | 01-Nov-21 09:30 | 20-Nov-21 17:00 | 19.35 Days
Continuous |
17s 138kV Bus 4 & T2 TX18477 - GOI | Replace 138kv Bus 4 bus prots, Replace breaker fails on s92, s85, s848X Replace s85 sync check, Replace line protections on 848L, Tie in new 138B3 'B' CT cont, and Tie in new 138B3 'B' CT cont | |
ALTALINK | 01-Nov-21 12:00 | 04-Nov-21 18:00 | 3.25 Days
Continuous |
908L (38s-E52s-89s) - GOI, 908L (38s East Edmonton - 89s Ellerslie) | Component replacements and fire mitigation on Str's Range 233-298 | |
EPCOR | 01-Nov-21 12:00 | 04-Nov-21 18:00 | 3.25 Days
Continuous |
ALTALINK - 908L(89s-E52s-38s) - DE-ENERGIZE LINE | Component replacements and fire mitigation on Str's Range 233-298 | |
ATCO | 08-Nov-21 08:00 | 15-Nov-21 16:00 | 7.33 Days
Continuous |
848S 902T, 848s 902T (848s Ruth Lake) | Cut in new CT and PT circuit extension to the new RAS relays, complete SCADA terminations. | |
EPCOR, ALTALINK | 08-Nov-21 09:30 | 10-Nov-21 16:00 | 2.27 Days
Continuous |
930L, 930L (37s North Calder - Poundmaker) | Line Maintenance | |
ALTALINK | 08-Nov-21 12:00 | 10-Nov-21 18:00 | 2.25 Days
Continuous |
908L (38s-E52s-89s) - GOI | Component replacements and fire mitigation on Str's Range 233-298 | |
ALTALINK | 08-Nov-21 12:00 | 10-Nov-21 18:00 | 2.25 Days
Continuous |
1059L (38s-E52s-E803s) - RB | RB for component replacements and fire mitigation on 908L Str's Range 233-298 | |
ATCO, ALTALINK | 12-Nov-21 08:00 | 14-Nov-21 17:00 | 2.38 Days
Continuous |
7L129, 7L129 (526s Buffalo Creek - 7LA129 tap) | GOI 7L129D3 to 526S Buffalo Creek Reroute Transmission Line around water | |
ATCO | 13-Nov-21 08:00 | 14-Nov-21 17:00 | 1.38 Days
Continuous |
740S 701T, 740S 702T, 740S 703T, 740s 701T (740s H.R.Milner), 740s 702T (740s H.R.Milner), 740s 703T (740s H.R.Milner) | maintenance | |
ATCO | 14-Nov-21 08:00 | 29-Nov-21 17:00 | 15.38 Days
Continuous |
9L40, 9L40 (732s Mitsue - 809s Louise Creek) | Louise Creek Rebuild project
Wiring for 903/904BF relays. CT ratio changes. Relay programming and functionality. Commission control, alarms and status. Blocking procedures for BF protections. |
|
EPCOR | 15-Nov-21 07:00 | 19-Nov-21 17:00 | 4.42 Days
Continuous |
1058L and LDS6 @ Lambton E806S and Summerside E657S | 1058L Line Maintenance and Lambton LDS6 LCR | |
ALTALINK | 15-Nov-21 11:15 | 25-Nov-21 15:45 | 10.19 Days
Continuous |
370s47 GOI, 370s 1252 (370s North Lethbridge), 370s 47 (370s North Lethbridge), 968L (138s Windy Flats - 370s North Lethbridge) | 370s N.Lethbridge 240kV Breaker (370s47) replacement | |
ALTALINK | 15-Nov-21 12:00 | 18-Nov-21 18:00 | 3.25 Days
Continuous |
905L (37s - 19s) - GOI, 905L (19s Wabamun - 37s North Calder) | Component replacements and fire mitigation(Str's Range 905L( 2-180) | |
EPCOR, ALTALINK | 22-Nov-21 09:30 | 26-Nov-21 17:00 | 4.31 Days
Continuous |
1059L, 1059L (38s East Edmonton - EP 803s Lambton) | Line Maintenance | |
ALTALINK | 22-Nov-21 12:00 | 25-Nov-21 18:00 | 3.25 Days
Continuous |
905L (37s - 19s) - GOI, 905L (19s Wabamun - 37s North Calder) | Component replacements and fire mitigation(Str's Range 905L( 2-180) | |
ALTALINK | 22-Nov-21 12:30 | 26-Nov-21 17:30 | 4.21 Days
Continuous |
74s103 and 74s102 (affect C3 and C4) GOI, 74s C3 (74s Janet), 74s C4 (74s Janet) | 74s C4 relay replacement | |
EPCOR, ALTALINK | 29-Nov-21 09:30 | 01-Dec-21 16:00 | 2.27 Days
Continuous |
930L, 930L (37s North Calder - Poundmaker) | Line Maintenance | |
ALTALINK | 29-Nov-21 10:00 | 29-Nov-21 12:00 | 2 Hours
Daily |
17s43 (17s1652) - Advice | Trip test from 17s85 BF Replacement | |
ALTALINK | 29-Nov-21 12:00 | 02-Dec-21 18:00 | 3.25 Days
Continuous |
905L (37s - 19s) - GOI, 905L (19s Wabamun - 37s North Calder) | Component replacements and fire mitigation(Str's Range 905L( 2-180) | |
ALTALINK | 29-Nov-21 12:30 | 29-Nov-21 14:30 | 2 Hours
Daily |
17s23 (17s3) - Advice | Trip test from 17s85 BF replacement | |
ALTALINK | 29-Nov-21 15:00 | 29-Nov-21 17:00 | 2 Hours
Daily |
17s39 (17s9) - Advice | Trip test from 17s85 BF Replacement | |
ATCO | 30-Nov-21 08:00 | 14-Dec-21 17:00 | 14.38 Days
Continuous |
9L02, 9L02 (809s Louise Creek - 813s Little Smoky) | Louise Creek Rebuild project
Wiring for 903/910BF relays. CT ratio changes. Relay programming and functionality. Commission control, alarms and status. Blocking procedures for BF protections. |
|
ALTALINK | 30-Nov-21 10:00 | 30-Nov-21 12:00 | 2 Hours
Daily |
17s34 (17s4) - Advice | Trip test from 17s85 BF Replacement | |
ALTALINK | 30-Nov-21 12:30 | 30-Nov-21 14:30 | 2 Hours
Daily |
17s59 (17s13) - Advice | Trip test from s85 BF | |
ALTALINK | 30-Nov-21 15:00 | 30-Nov-21 17:00 | 2 Hours
Daily |
17s79 (C1) - Advice | Trip test from s85 BF | |
ATCO | 06-Dec-21 08:00 | 13-Dec-21 16:00 | 7.33 Days
Continuous |
9L74, 888S 905, 888S 906, 9L74 (888s Dover - 960s Birchwood Creek), 888s 905 (888s Dover), 888s 906 (888s Dover) | Cut in new CT and PT circuit extension to the new RAS relays, complete SCADA terminations. | |
ALTALINK | 06-Dec-21 12:00 | 09-Dec-21 18:00 | 3.25 Days
Continuous |
905L (37s - 19s) - GOI, 905L (19s Wabamun - 37s North Calder) | Component replacements and fire mitigation(Str's Range 905L( 2-180) | |
ALTALINK | 07-Dec-21 07:15 | 23-Dec-21 18:45 | 16.48 Days
Continuous |
887L/1L274 (48s) - BCH Advice | transmission refurbishment. Advice needed by BC Hydro on 48s38. | AB-BC |
BCH | 07-Dec-21 08:00 | 23-Dec-21 18:00 | 16.42 Days
Continuous |
1L274 (48s Pocaterra - Britt Creek) | transmission refurbishment | AB-BC |
ALTALINK | 07-Dec-21 15:00 | 07-Dec-21 18:00 | 3 Hours
Daily |
17s49 (17s717W-262s) - Advice, 717L (17s Benalto - 262s Rocky Mountain House) | Trip test | |
ALTALINK | 08-Dec-21 08:00 | 08-Dec-21 11:00 | 3 Hours
Daily |
17s46 (17s2852- 17s T3) - Advice | Trip test from new s92 breaker fail and s757N breaker fail | |
ALTALINK | 13-Dec-21 09:00 | 14-Dec-21 18:00 | 1.38 Days
Continuous |
789L (A898s - 602L1 - 789L192A) - GOI | Maintenance on Structures #77 & 78. | |
ATCO | 17-Jan-22 08:00 | 24-Jan-22 16:00 | 7.33 Days
Continuous |
9L84, 934S 905, 934S 906, 9L84 (934s Black Fly - 977s Salt Creek), 934s 905 (934s Blackfly), 934s 906 (934s Blackfly) | Cut in new CT and PT circuit extension to the new RAS relays, complete SCADA terminations. | |
ATCO, CNRL | 27-Jan-22 08:00 | 07-Feb-22 17:00 | 11.38 Days
Continuous |
75-PLH-902, 75-PLH-902 (838s Horizon Mining - 849s Joslyn) | ATCO 9L32-9L66 CNRL- Horizon Project
Disconnect existing 75-PLH-902 from Horizon substation 75 Connect new bus Horizon substation 75 (former 75-PLH-902 bay)to new 838S-900BS1 Reroute and connect 9L137 (former 75-PLH-902) to new 838S and energize Commission 87L/900BS1 protection, end-to-end testing Upgrade 21B/9L137 line protection @ 849S Joslyn Commission line protection, SCADA and end-to-end testing, BF/DTT to 838S |
|
ATCO, CNRL | 08-Feb-22 08:00 | 19-Feb-22 17:00 | 11.38 Days
Continuous |
75-PLH-901, 75-PLH-901 (838s Horizon Mining - 849s Joslyn) | ATCO 9L32-9L66 CNRL- Horizon Project
Disconnect existing 75-PLH-901 from Horizon substation 75 Connect new bus Horizon substation 75 (former 75-PLH-901 bay) to new 838S-900BS2 Reroute and connect 9L155 (former 75-PLH-901) to new 838S and energize Commission 87L/900BS1 protection, end-to-end testing Upgrade 21B/9L155 line protection @ 849S Joslyn Commission line protection, SCADA and end-to-end testing, BF/DTT to 838S |
|
ATCO, ALTALINK | 14-Feb-22 08:00 | 14-Feb-22 18:00 | 10 Hours
Continuous |
7L65, 7L77, 7L77 (395s North Holden - 709s Vegreville), 7L65 (709s Vegreville - 710s Vermilion) | String over 7L65 and 7L77 | |
ATCO | 20-Feb-22 08:00 | 23-Feb-22 17:00 | 3.38 Days
Continuous |
9L66, 9L66 (847s Muskeg River - 849s Joslyn Creek) | ATCO 9L32-9L66 CNRL- Horizon Project
Disconnect existing line 9L66 at tap point and connect new line segment to 838S Horizon Expansion Disconnect existing 9L66 from Joslyn 849S Commissioning upgrade - relay settings @ 847S |
|
ATCO | 24-Feb-22 08:00 | 27-Feb-22 17:00 | 3.38 Days
Continuous |
9L32, 9L32 (849s Joslyn Creek - 2005s Secord) | ATCO 9L32-9L66 CNRL- Horizon Project
Disconnect existing line 9L32 at tap point and connect new line segment to 838S Horizon Expansion Disconnect existing 9L32 from Joslyn 849S Commissioning upgrade - relay settings @ 2005S |
|
ATCO | 01-Mar-22 08:00 | 03-Mar-22 17:00 | 2.38 Days
Continuous |
9L46, 9L46 (932s Pemukan - 959s Lanfine) | Sharp Hills Wind Farm Project
Outage for structure foundations work directly under 9L46 |
|
ATCO | 14-Mar-22 08:00 | 15-Mar-22 17:00 | 1.38 Days
Continuous |
766S 901T, 766s 901T (766s Nevis) | Sharp Hills Wind Farm Project
Installation of new RAS panel at 766S Nevis |
|
ATCO, ALTALINK | 22-Mar-22 07:00 | 22-Mar-22 17:00 | 10 Hours
Continuous |
7L77, 7L77 (395s North Holden - 709s Vegreville) | 7L65 Rebuild Project | |
EPCOR | 28-Mar-22 07:00 | 01-Apr-22 17:00 | 4.42 Days
Continuous |
1098L @ Jasper Terminal E805S and Poundmaker | Jasper 1098L VT LCR
1007295 WO: 037069 |
|
ATCO | 09-Apr-22 08:00 | 15-Apr-22 17:00 | 6.38 Days
Continuous |
9L46, 9L46 (932s Pemukan - 959s Lanfine) | Sharp Hills Wind Farm Project
Outage for Line termination to 363S Sedalia on 9L46 |
|
EPCOR | 11-Apr-22 07:00 | 06-May-22 17:00 | 25.42 Days
Continuous |
P2401 @ Petrolia E816S | Petrolia P2401 LCR
1007155 WO: 036932 |
|
ATCO | 02-May-22 08:00 | 15-May-22 00:17 | 12.68 Days
Continuous |
7L01, 7L01 (813s Little Smoky - 881s Sturgeon) | 813S Little Smoky Rebuild
BKR 711 and 712 P&C wiring, remove old panel 8G, set up new panel 7P2, prep work Relay programming and functionality Commission control, alarms and status |
|
EPCOR | 09-May-22 07:00 | 03-Jun-22 17:00 | 25.42 Days
Continuous |
P2406 @ Petrolia E816S | Petrolia P2406 LCR
1007155 WO: 038105 |
|
ATCO | 16-May-22 08:00 | 29-May-22 17:00 | 13.38 Days
Continuous |
7L46, 7L46 (813s Little Smoky - 845s Big Mountain) | 813S Little Smoky Rebuild
Replace 705CT and 706CT junction boxes 705, 706 P&C wiring, prep work Relay programming and functionality Commission control, alarms and status |
|
ATCO | 30-May-22 08:00 | 12-Jun-22 17:00 | 13.38 Days
Continuous |
7L45, 7L45 (813s Little Smoky - 845s Big Mountain) | 813S Little Smoky Rebuild813S Little Smoky Rebuild
BKR 703 and 704 P&C wiring, remove old panel 7G, set up new panel 7P4, prep work Relay programming and functionality Commission control, alarms and status |
|
EPCOR | 06-Jun-22 07:00 | 30-Jun-22 17:00 | 24.42 Days
Continuous |
P2404 @ Petrolia E816S | Petrolia P2404 LCR
1007156 WO: 037002 |
|
ATCO | 13-Jun-22 08:00 | 26-Jun-22 17:00 | 13.38 Days
Continuous |
7L54, 7L54 (794s Valleyview - 813s Little Smoky) | 813S Little Smoky Rebuild813S Little Smoky Rebuild
BKR 703 and 704 P&C wiring, remove old panel 7G, set up new panel 7P4, prep work Relay programming and functionality Commission control, alarms and status |
|
ATCO | 15-Jun-22 07:00 | 28-Jul-22 17:00 | 43.42 Days
Continuous |
972S 900BS2, 9L16, 9L16 (755s Cordel - 972s Tinchebray), 972s 240kV Bus 900BS2 (972s Tinchebray) | Outage on 9L16 to cut the line over to the new bay | |
ATCO | 29-Jun-22 07:00 | 01-Jul-22 17:00 | 2.42 Days
Continuous |
766S 701, 766S 901T, 766s 901T (766s Nevis), 766s 701 (766s Nevis) | RAS modifications for the Pattern Lanfine WAGF project | |
ATCO | 12-Jul-22 07:00 | 16-Jul-22 17:00 | 4.42 Days
Continuous |
7L224, 774S 701, 7L224 (650s Hansman Lake - 774s Monitor), 774s 701 (774s Monitor) | RAS modifications for the Pattern Lanfine WAGF project | |
ATCO | 25-Jul-22 08:00 | 07-Aug-22 17:00 | 13.38 Days
Continuous |
7L40, 7L40 (733s Simonette - 813s Little Smoky) | 813S Little Smoky Rebuild
BKR 709 and 710 P&C wiring, remove old panels 3G and 4G, set up new panel 7P1, prep work Relay programming and functionality Commission control, alarms and status |
|
ATCO | 27-Jul-22 06:00 | 28-Jul-22 17:00 | 1.46 Days
Continuous |
972S 900BS2, 9L16, 9L16 (755s Cordel - 972s Tinchebray), 972s 240kV Bus 900BS2 (972s Tinchebray) | Outage on 9L16 to cut the line over to the new bay | |
ATCO | 27-Jul-22 07:00 | 31-Jul-22 17:00 | 4.42 Days
Continuous |
7L760, 767S 702, 7L760 (767s Oyen - 7L760D2), 767s 702 (767s Oyen) | RAS modifications for the Pattern Lanfine WAGF project | |
ATCO | 29-Jul-22 07:00 | 03-Aug-22 17:00 | 5.42 Days
Continuous |
9L177, 9L177 (620s Goldeye - 972s Tinchebray) | Installing new 240Kv Bay (connect 907B to BUS 1) for 620S Goldeye substation connection | |
ATCO | 08-Aug-22 08:00 | 21-Aug-22 17:00 | 13.38 Days
Continuous |
7L32, 7L32 (813s Little Smoky - 862s South Bezanson) | 813S Little Smoky Rebuild
BKR 701 and 702 P&C wiring, prep work Relay programming and functionality Commission control, alarms and status |
|
ATCO | 22-Aug-22 08:00 | 29-Aug-22 16:00 | 7.33 Days
Continuous |
766S 901T, 766s 901T (766s Nevis) | Joss Jenner 2 Power Project Connection
Complete CT, PT, P&C cutover, commission relays and DTT to 770S Three Hills (option 1) or 1-114S Ghost Pine (option 2) |
|
ATCO | 05-Sep-22 08:00 | 24-Sep-22 17:00 | 19.38 Days
Continuous |
813S 901T, 813s 901T (813s Little Smoky) | 813S Little Smoky Rebuild
Remove panels 3K,4K - install new panel 9T1 - BKR 901, 701, 705, 718 P&C wiring, prep work Replace 500PT disconnect assembly Relay programming and functionality Commission control, alarms and status |
|
ATCO | 05-Sep-22 08:00 | 30-Sep-22 16:00 | 25.33 Days
Continuous |
972S 900BS2, 972s 240kV Bus 900BS2 (972s Tinchebray) | CETO project | |
ATCO | 26-Sep-22 08:00 | 19-Oct-22 17:00 | 23.38 Days
Continuous |
813S 902T, 813s 902T (813s Little Smoky) | 813S Little Smoky Rebuild
Remove panels 1K,2K - install new panel 9T2 - BKR 904, 710, 711, 713, 717 P&C wiring, prep work Replace cap bank protection relays Replace 501PT disconnect assembly Relay settings update for capacitor banks 714C, 715C, 716C Relay programming and functionality Commission control, alarms and status |
|
ATCO | 22-Oct-22 07:00 | 02-Nov-22 17:00 | 11.42 Days
Continuous |
7L129, 7L129 (710s Vermilion - 918s Bauer) | Re stringing conductor | |
ATCO | 24-Oct-22 08:00 | 06-Nov-22 17:00 | 13.42 Days
Continuous |
9L11, 9L11 (813s Little Smoky - 834s Wesley Creek) | 813S Little Smoky Rebuild
Remove panels 5H,6H - install new panel 9P3 - BKR 905 and 906 P&C wiring, prep work Relay programming and functionality Commission control, alarms and status |
|
EPCOR | 31-Oct-22 07:00 | 04-Nov-22 17:00 | 4.42 Days
Continuous |
1164L @ Petrolia E816S and Riverview | Petrolia 1164L VT LCR
1007295 WO: 037070 |
|
ATCO | 07-Nov-22 08:00 | 20-Nov-22 17:00 | 13.38 Days
Continuous |
9L05, 9L05 (809s Louise Creek - 813s Little Smoky) | 813S Little Smoky Rebuild
Remove panels 5H,6H - install new panel 9P3 - BKR 905 and 906 P&C wiring, prep work Relay programming and functionality Commission control, alarms and status |
|
ATCO | 21-Nov-22 08:00 | 04-Dec-22 17:00 | 13.38 Days
Continuous |
9L02, 9L02 (809s Louise Creek - 813s Little Smoky) | 813S Little Smoky Rebuild
Remove panels 5H,6H - install new panel 9P3 - BKR 905 and 906 P&C wiring, prep work Relay programming and functionality Commission control, alarms and status |
|
ATCO | 05-Dec-22 08:00 | 18-Dec-22 17:00 | 13.38 Days
Continuous |
813S SVC, 813s SVC (813s Little Smoky) | 813S Little Smoky Rebuild
Cutover new filter bank relays, P&C wiring Relay programming and functionality Commission control, alarms and status |
|
ATCO | 15-Dec-22 07:00 | 23-Dec-22 17:00 | 8.42 Days
Continuous |
730S 702, 730S 704, 730s 702 (730s Rycroft), 7L73 (730s Rycroft - 829s Boucher Creek), 730s 704 (730s Rycroft) | SVC addition and 144 kv bus rebuild. | |
ATCO | 21-Mar-23 08:00 | 22-Mar-23 17:00 | 1.38 Days
Continuous |
7L53, 7LA53, 7L53 (700s Bonnyville - 706s Irish Creek) | Cold Lake Area Energy Centre Project
7LA53 (New Line T-Tap) 1064S Garnier Lake Sub (Customer) Build 6km 7LA53 144kV from T-Tap to 1064S Garnier Lake Substation. Remote end protection upgrades |
|
ATCO | 27-Mar-23 08:00 | 30-Mar-23 17:00 | 3.38 Days
Continuous |
7L91, 7L91 (715s Leming Lake - 826s Marguerite Lake) | Cold Lake Area Energy Centre Project
Cutover CT/PT/P&C ccts for new Thermal RAS relays Complete commissioning 49A/49B/7L91 relays End-to-end testing to 1064S |
AB-BC, AB-SK & AB-MATL: refer to AESO web posting: | http://itc.aeso.ca/itc/public/atc |
Also, | |
AB-BC, AB-SK & AB-MATL: refer to ISO Rule 203.6: | http://www.aeso.ca/rulesprocedures/18592.html |
Prepared On: | 2021-07-05 9:49:07 AM |
This document and the information contained herein are based upon information and data which by their nature contain a degree of uncertainty and are subject to change. In addition, this document may contain information and data from public sources and/or third parties, which have been assumed to be accurate and complete and have not been verified. Accordingly, the Independent System Operator, operating as the Alberta Electric System Operator (the "AESO") makes no warranty, representation or guarantee, express or implied, with respect to this document or the information contained herein, including, but not limited to, any warranty, representation or guarantee of accuracy, completeness, timeliness, reliability, availability, absence of computer virus, non- infringement, merchantability or suitability for any purpose. Under no circumstances will the AESO, its members, officers, employees, contractors or agents, or any of their respective affiliates, be liable for any errors or omissions in, or any losses, damages or claims whatsoever, whether in contract, tort or otherwise, arising from use of or reliance upon, this document or any information contained herein. © 2009 Alberta Electric System Operator. All rights reserved |