Alberta Electric System Operator | |
System Co-ordination Plan | |
2020-08-13 to 2020-08-21 | |
Approved Outages |
Previous Version | |
Download CSV |
From | To | Owner | Type | Element | Scheduled Activity | Date/Time Comments | Interconnection |
---|---|---|---|---|---|---|---|
05-Oct-18 08:00 | 31-Dec-20 16:00 | EPCOR | IO | Rossdale C2 (Rossdale) | forced outage | Continuous |
818.38 Days
|
24-Oct-18 01:13 | 31-Dec-20 16:00 | EPCOR | IO | Rossdale C1 (Rossdale) | forced outage | 799.66 Days
Continuous |
|
19-Sep-19 08:00 | 31-Oct-20 16:00 | ATCO | Outage | 826s 504R (826s Marguerite Lake) | emergency: move reactor from 826s to 732s | 408.33 Days
Continuous |
|
01-Jan-20 08:00 | 31-Dec-20 18:00 | SUNCOR | Outage | Unmodeled Transmission Facility (Suncor) | 29L3-167, 29L3-141 , 29PL3-63, 29PL3-183, 29PT-241 & 29PL7-4, 29PP-47 & 29PT-576, 29PP-46 & 29PT-575, 144KV NODE,29PT-246, 144KV NODE,29PT-238, 29PT-257 & 29PL7-4,29PT-260 & 29PL7-4, 29PT-250&29PL7-3,29PT-236 & 29PL7-3,29PL3-153/152/196, 29PT-128 & 29PL7-10 | 365.42 Days
Daily |
|
24-Jan-20 08:00 | 11-Sep-20 16:00 | ATCO | Outage | 2029s ACF13 (2029s Heathfield) | Forced outage repairs | 231.29 Days
Continuous |
|
31-Mar-20 08:00 | 18-Aug-20 16:00 | ENMAX | IO | 2.84L (ENMAX 2 - ENMAX 8) | P1456 ISD Oct 04,2020 | 140.33 Days
Continuous |
|
15-May-20 07:00 | 23-Sep-20 17:00 | EPCOR | Outage | T2 (Namao) | transformer replacement | 131.42 Days
Continuous |
|
15-May-20 07:00 | 21-Oct-20 17:00 | EPCOR | Outage | T3 (Strathcona) | transformer replacement | 159.42 Days
Continuous |
|
26-May-20 07:00 | 15-Aug-20 17:00 | EPCOR | TE | Hardisty EPCOR | BF protection upgrade at Hardisty S/S | 81.42 Days
Continuous |
|
08-Jun-20 07:00 | 30-Sep-20 17:00 | EPCOR | TE | Woodcroft RTU/SCADA | station SA system being upgraded and tested to accommodate future upgrade to ADMS system | 114.42 Days
Continuous |
|
08-Jun-20 08:00 | 31-Aug-20 16:00 | ATCO | TE | 826s 144kV bus (826s Margueritelake) | protection upgrade | 84.33 Days
Continuous |
|
15-Jun-20 08:00 | 03-Nov-20 16:00 | ENMAX | TE | ENMAX 13 | line protection upgrade for autoswitching and 138 kV bus differential relays | 141.38 Days
Continuous |
|
22-Jun-20 18:30 | 29-Oct-20 15:00 | ALTALINK | IO | 285s T2 (285s East Camrose) | install new replacement T2 transformer & new switchgear building - info only | 128.85 Days
Continuous |
|
29-Jun-20 10:00 | 14-Aug-20 14:00 | ATCO | TE | 826s Marguerite Lake RTU/SCADA | support commissioning during project execution | 46.17 Days
Continuous |
|
06-Jul-20 07:00 | 31-Oct-20 17:00 | EPCOR | TE | Poundmaker RTU/SCADA, Poundmaker | station SA system being upgraded and tested to accommodate future upgrade to ADMS system | 117.42 Days
Continuous |
|
06-Jul-20 07:00 | 31-Oct-20 17:00 | EPCOR | TE | 987S Cloverbar, 987s Cloverbar RTU/SCADA | station SA system being upgraded and tested to accommodate future upgrade to ADMS system | 117.42 Days
Daily |
|
06-Jul-20 08:00 | 30-Aug-20 16:00 | ATCO | Outage | 826s 902T (826s Marguerite Lake) | breaker fail protection upgrade | 55.33 Days
Continuous |
|
20-Jul-20 08:00 | 04-Sep-20 16:00 | ATCO | TE | 2029s Heathfield | Valve cooling system | 46.33 Days
Continuous |
|
27-Jul-20 07:00 | 11-Sep-20 17:00 | EPCOR | Outage | 987s CH724 (987s Clover Bar), H725 (Hardisty Epcor), 72CH11 (987s Clover Bar - Hardisty) | degassing | 46.42 Days
Continuous |
|
28-Jul-20 08:00 | 21-Aug-20 16:00 | ENMAX | Outage | 13.3TR (ENMAX 13) | arc flash mitigation project | 24.33 Days
Continuous |
|
03-Aug-20 07:00 | 17-Aug-20 18:30 | ALTALINK | RB | 551L (123s Banff - 953s Lake Louise) | Salvage of road accesses to ROW, excavation with track hoes | 14.48 Days
Daily |
|
03-Aug-20 07:30 | 27-Aug-20 17:30 | ALTALINK | TE | 150s Clyde RTU/SCADA | update RTU configuration to migrate 138kV line (223L) SCADA control, status, metering and alarm points from the old D25 to new SMP RTU | 24.42 Days
Daily |
|
03-Aug-20 08:00 | 21-Aug-20 16:00 | ENMAX | Outage | 11B138-11.81 (ENMAX 11), 13B138-11.81 (ENMAX 13), 11.81L (ENMAX 11 - ENMAX 13) | arc flash mitigation project line protection upgrade | 18.33 Days
Continuous |
|
03-Aug-20 08:00 | 23-Aug-20 20:00 | Syncrude | Outage | Aurora T3 (Aurora) | maintenance | 20.5 Days
Continuous |
|
03-Aug-20 09:30 | 21-Aug-20 18:30 | ALTALINK | Outage | 150s 223N (150s Clyde), 159s 223 (159s Colinton), 223L (150s Clyde - 159s Colinton) | install new structures | 18.38 Days
Continuous |
|
04-Aug-20 08:00 | 04-Sep-20 16:00 | ALTALINK | IO | 24.83L Advice for ENMAX | gt68 transmission line relocate | 31.33 Days
Continuous |
|
04-Aug-20 08:00 | 21-Aug-20 16:00 | ATCO | TE | 770s Threehills RTU/SCADA | protection upgrade
|
17.33 Days
Continuous |
|
04-Aug-20 08:00 | 30-Aug-20 16:00 | ATCO | TE | 7L89 (721s La Corey - 826s Marguerite Lake), 9L36 (825s Whitefish Lake - 826s Marguerite Lake), 9L37 (825s Whitefish Lake - 826s Marguerite Lake), 7L587 (822s Wolf Lake - 826s Marguerite Lake) | commissioning to test trips from line protection, perform primary injection, and cut-in PT circuits to new devices | 26.33 Days
Continuous |
|
04-Aug-20 08:00 | 06-Sep-20 16:00 | ENMAX, ALTALINK | Outage | 24.83L (74s Janet - ENMAX 24) | transmission line relocate | 33.33 Days
Continuous |
|
04-Aug-20 09:00 | 28-Aug-20 17:00 | EPCOR | Outage | RR723 (Rossdale) | breaker replacement | 24.33 Days
Continuous |
|
04-Aug-20 09:00 | 14-Aug-20 18:00 | ALTALINK | Outage | 786L (799s Coleman - BCH Natal) | P5 786L urgent repair str's range 76-117 | 10.38 Days
Continuous |
AB-BC |
05-Aug-20 08:00 | 30-Sep-20 16:00 | ATCO | TE | 794S Valleyview | remove failed breaker 702 BF relay and install when it is returned from repair | 56.33 Days
Continuous |
|
06-Aug-20 13:00 | 14-Aug-20 18:00 | ALTALINK | Outage | 763L (158s Vauxhall - 763AL) | urgent line clearance | 8.21 Days
Continuous |
|
07-Aug-20 17:00 | 13-Aug-20 17:00 | SUNCOR | Outage | 635EDD-1000 635PK-1001 (635EDD-1000), 635EDD-1000 635-752-161 (635EDD-1000), 635EDD-1000 635-752-162 (635EDD-1000) | maintenance | 6 Days
Continuous |
|
09-Aug-20 07:00 | 14-Aug-20 18:00 | ALTALINK | Outage | 514L (513s Lundbreck - 514BL) | maintenance work on strs 201 - 447 | 5.46 Days
Continuous |
|
10-Aug-20 07:00 | 21-Aug-20 17:00 | EPCOR | Outage | 805s T3 (805s Jasper) | DGA monitor | 11.42 Days
Continuous |
|
10-Aug-20 07:00 | 14-Aug-20 17:00 | EPCOR | Outage | 803s T1 (803s Lambton) | doble / SFRA | 4.42 Days
Continuous |
|
10-Aug-20 07:00 | 14-Aug-20 17:30 | ALTALINK | TE | 296s Rosyth RTU/SCADA | SCADA upgrade project | 4.44 Days
Daily |
|
10-Aug-20 07:00 | 14-Aug-20 17:00 | ATCO | TE | 806s Oldman River RTU/SCADA | adding line fault location for 893BL | 4.42 Days
Daily |
|
10-Aug-20 07:00 | 14-Aug-20 17:30 | ALTALINK | TE | 525s Carseland RTU/SCADA | update config to add alarms | 4.44 Days
Daily |
|
10-Aug-20 07:30 | 13-Aug-20 18:30 | ALTALINK | Outage | 428s 733X (428s Namaka), 733L (179s Gleichen - 428s Namaka) | protection upgrades | 3.46 Days
Continuous |
|
10-Aug-20 08:00 | 13-Aug-20 17:00 | ATCO | Outage | 7L24 (846s Grand Centre - 7L24D3) | replacing cross-arms, poles and ground rod's | 3.38 Days
Continuous |
|
10-Aug-20 08:00 | 13-Aug-20 17:00 | ALTALINK | TE | 87S Gaetz | SCADA upgrade project | 3.38 Days
Daily |
|
10-Aug-20 08:00 | 13-Aug-20 16:00 | ALTALINK | TE | 428s Namaka RTU/SCADA | RTU database updates | 3.33 Days
Daily |
|
10-Aug-20 08:00 | 13-Aug-20 16:00 | ENMAX, ALTALINK | TE | 1003L (74s Janet - ENMAX 25) | upgrade the firmware for correct operation | 3.33 Days
Continuous |
|
10-Aug-20 08:00 | 13-Aug-20 17:00 | ALTALINK | TE | 428S Namaka | trip/function tests | 3.38 Days
Daily |
|
10-Aug-20 08:00 | 13-Aug-20 16:00 | ALTALINK | TE | 37S North Calder | test reclosers for new on site control, complete wiring for new auxiliary relay in breaker reclosing circuit | 3.33 Days
Daily |
|
10-Aug-20 08:00 | 14-Aug-20 18:30 | ENMAX | Outage | 5.9TR (ENMAX 5) | plastibeton tray replacement | 4.44 Days
Continuous |
|
10-Aug-20 08:00 | 13-Aug-20 16:00 | ENMAX | Outage | 37.2TR (ENMAX 37) | reinhausen tapchanger maintenance | 3.33 Days
Continuous |
|
10-Aug-20 08:00 | 13-Aug-20 17:00 | ALTALINK | TE | 428S Namaka | breaker fail outage | 3.38 Days
Daily |
|
10-Aug-20 08:00 | 23-Aug-20 20:00 | Syncrude | Outage | Aurora 11 (Aurora), Aurora 12 (Aurora), Aurora 13 (Aurora) | operate breaker and switch | 13.5 Days
Continuous |
|
10-Aug-20 08:00 | 13-Aug-20 17:00 | ALTALINK | TE | 276S Union Carbide Prentiss | cutover all points to new SCADA system- config file updates | 3.38 Days
Continuous |
|
10-Aug-20 08:00 | 14-Aug-20 17:00 | ALTALINK | TE | 103S Goose Lake | isolate 893L relays for fault locating addition | 4.38 Days
Daily |
|
10-Aug-20 08:00 | 14-Aug-20 17:00 | ALTALINK | TE | 312S Fidler | isolate 893L relays for fault locating addition | 4.38 Days
Daily |
|
10-Aug-20 08:00 | 14-Aug-20 17:00 | ATCO | TE | 806S Oldman River | testing fault locating on the following relays: 893BL | 4.38 Days
Daily |
|
10-Aug-20 08:00 | 14-Aug-20 17:00 | WINDYPWPL | TE | 112S Windy Point | isolate 893AL relays for fault locating addition | 4.38 Days
Daily |
|
10-Aug-20 08:00 | 21-Aug-20 16:00 | ENMAX | TE | ENMAX 9 | arc flash mitigation project | 11.33 Days
Continuous |
|
10-Aug-20 08:00 | 21-Aug-20 16:00 | ENMAX | TE | ENMAX 9 | arc flash mitigation project | 11.33 Days
Continuous |
|
10-Aug-20 08:00 | 14-Aug-20 18:00 | ATCO | TE | 733s Simonette RTU/SCADA | RTU update | 4.42 Days
Continuous |
|
10-Aug-20 08:00 | 14-Aug-20 18:00 | ATCO | TE | 810s Dome Cutbank RTU/SCADA | RTU update | 4.42 Days
Continuous |
|
10-Aug-20 08:30 | 13-Aug-20 16:00 | ATCO | Outage | 801s 906 (801s Anderson) | breaker min oil, HLR complete testing | 3.31 Days
Continuous |
|
10-Aug-20 08:30 | 13-Aug-20 16:00 | ENMAX, ALTALINK | TE | 1003L (74s Janet - ENMAX 25) | firmware upgrades to the following relay: 1003L A87/21/79/RAS/L9 SEL411L | 3.31 Days
Continuous |
|
10-Aug-20 09:00 | 20-Aug-20 18:00 | ALTALINK | Outage | 71s 1652 (71s Lamoureux) | replacing M/O breaker with a new SF6 Breaker | 10.38 Days
Continuous |
|
10-Aug-20 09:00 | 14-Aug-20 15:30 | ALTALINK | IO | 194s 15T2 City of Red Deer - Info | on load tap changer testing and overhaul | 4.27 Days
Continuous |
|
10-Aug-20 09:00 | 14-Aug-20 15:30 | REDDEER | Outage | 194s T2 (194s South Red Deer) | on load tap changer testing and overhaul | 4.27 Days
Continuous |
|
10-Aug-20 09:00 | 20-Aug-20 18:00 | EPCOR | RB | ALTALINK - 920LE - RECLOSER BLOCK @ CASTLEDOWNS | replacing M/O breaker with a new SF6 breaker | 10.38 Days
Continuous |
|
10-Aug-20 09:30 | 24-Aug-20 18:15 | ALTALINK | Outage | 174L (197s Bardo - 395s North Holden) | re-build from structure 486 to 539 | 14.36 Days
Continuous |
|
10-Aug-20 09:30 | 24-Aug-20 18:15 | ATCO | IO | Holden | 174L (197s-395s) – GOI
174L re-build from structure 486 to 539 AltaLink requested that ATCO be notified of this outage as their assistance may be required to maintain the voltages in Strome and Vegreville area |
14.36 Days
Continuous |
|
10-Aug-20 10:00 | 13-Aug-20 16:00 | ATCO | Outage | 879s 702T (879s Scotford Upgrader) | 35 kV “B” bus maintenance and
Basler relay testing |
3.25 Days
Continuous |
|
10-Aug-20 11:00 | 14-Aug-20 18:00 | ALTALINK | Outage | 262s T1 (262s Rocky Mountain House) | 138 kV & 25 kV bushings and 138 kV & 25 kV LAs (T1) & bird cover | 4.29 Days
Continuous |
|
10-Aug-20 12:00 | 14-Aug-20 18:00 | ALTALINK | Outage | 776L (308s Albchem Beaverhill Creek - 410s Josephburg), 773L (127s Bruderheim - 308s Albchem Beaverhill Creek), 308S Albchem Beaverhill Creek | replace the RTU | 4.25 Days
Continuous |
|
10-Aug-20 12:00 | 13-Aug-20 17:30 | ALTALINK | Outage | 391s T1 (391s Balzac) | perform 1st trip on 391s9 and PRC 5 tests on 391s30, replace T1 high side bushing, doble, SFRA & tapchanger maintenance | 3.23 Days
Continuous |
|
10-Aug-20 12:15 | 16-Aug-20 17:45 | ALTALINK | Outage | 157s T1 (157s Lac La Biche) | maintenance, oil reclaim (T1), leak repairs, & VR1 pad repair | 6.23 Days
Continuous |
|
10-Aug-20 12:30 | 16-Aug-20 17:30 | ALTALINK | Outage | 797L (268s Whitecourt - 364s Whitecourt industrial) | line clearance mitigation str's range 6-64 | 6.21 Days
Continuous |
|
10-Aug-20 12:30 | 16-Aug-20 17:30 | ALTALINK | RB | 798L (77s Sagitawah - 364s Whitecourt Industrial) | line clearance mitigation str's range 54-58 | 6.21 Days
Continuous |
|
10-Aug-20 12:30 | 16-Aug-20 17:30 | ATCO | IO | AltaLink NW AltaLink outage | ATCO’s assistance may be required to maintain the voltage in the Fox Creek and Whitecourt area during the outage and in the next contingency. | 6.21 Days
Continuous |
|
10-Aug-20 13:00 | 14-Aug-20 17:00 | ALTALINK | TE | 308S Albchem Beaverhill Creek | replace the RTU | 4.17 Days
Daily |
|
10-Aug-20 13:00 | 14-Aug-20 17:00 | ALTALINK | RB | 861L (71s Lamoureux - 258s Dow Hydro Carbons) | component replacements-insulators | 4.17 Days
Continuous |
|
11-Aug-20 08:00 | 13-Aug-20 17:00 | ALTALINK | TE | 322s Cowley Ridge RTU/SCADA | upgrade MPLS node | 2.38 Days
Daily |
|
11-Aug-20 08:00 | 14-Aug-20 17:00 | ALTALINK | TE | 83s Taber RTU/SCADA | supervisory outage to download new configurations | 3.38 Days
Daily |
|
11-Aug-20 08:00 | 14-Aug-20 17:00 | REDDEER | Outage | 217s T1 (217s North Red Deer) | forced outage | 3.38 Days
Continuous |
|
11-Aug-20 09:00 | 14-Aug-20 17:00 | ALTALINK | TE | 336s Fincastle RTU/SCADA | supervisory outage to download new configurations and commissioning of new controls | 3.33 Days
Continuous |
|
12-Aug-20 07:00 | 13-Aug-20 17:00 | ALTALINK | Outage | 521AL (867s Sundance Blow-Down - 521L), 521L (505L - 512L) | maintenance on structures 51, 53, 54, 55, 56, 57, 58, 60A, 61A, 62, 63, 65, and 66 | 1.42 Days
Continuous |
|
12-Aug-20 07:00 | 13-Aug-20 19:00 | ALTALINK | TE | 254s Coaldale RTU/SCADA | update configuration for new alarms | 1.5 Days
Daily |
|
12-Aug-20 08:00 | 28-Aug-20 16:00 | ENMAX | Outage | 9.3TR (ENMAX 9) | arc flash mitigation project protection outage and MV cable swap | 16.33 Days
Continuous |
|
12-Aug-20 08:00 | 13-Aug-20 15:30 | ALTALINK | TE | 511s Crossing | firmware upgrade for T11 'A' protection | 31.5 Hours
Daily |
|
12-Aug-20 08:00 | 15-Aug-20 16:00 | ENMAX | Outage | 3.3TR (ENMAX 3) | Reinhausen tapchanger maintenance, oil sampling MT, TC, check reversing switch | 3.33 Days
Continuous |
|
12-Aug-20 08:00 | 17-Aug-20 11:00 | ENMAX | Outage | ENMAX 8 | DCTRP. highpot test 2.84L | 5.13 Days
Continuous |
|
12-Aug-20 08:15 | 13-Aug-20 17:15 | ALTALINK | Outage | 102s SVC (102s Langdon) | spray and pull weeds in the SVC fenced area, glycol leak repairs | 1.38 Days
Continuous |
|
12-Aug-20 09:30 | 13-Aug-20 15:00 | ALTALINK | TE | 510S Sunnybrook | firmware upgrade for T11 A & B protection | 29.5 Hours
Daily |
|
12-Aug-20 13:00 | 17-Aug-20 15:00 | ALTALINK | TE | 263s Strachan RTU/SCADA | add door alarms | 5.08 Days
Daily |
|
12-Aug-20 20:00 | 13-Aug-20 04:00 | ATCO | IO | 7L81 (FNG Fort Nelson - 791s Rainbow Lake) | disconnect maintenance | 8 Hours
Continuous |
|
13-Aug-20 07:00 | 13-Aug-20 18:00 | ENMAX | Outage | 40.2TR (ENMAX 40) | roxtec installation | 11 Hours
Continuous |
|
13-Aug-20 07:00 | 13-Aug-20 18:00 | ALTALINK | Outage | 737L (38s East Edmonton - 95s Imperial Oil Edmonton) | line clearance mitigation | 11 Hours
Daily |
|
13-Aug-20 07:00 | 14-Aug-20 17:00 | ALTALINK | TE | 170s Pike RTU/SCADA | update configuration to add alarms | 1.42 Days
Daily |
|
13-Aug-20 07:30 | 13-Aug-20 17:30 | ALTALINK | TE | 321s Al Rothbauer RTU/SCADA | update configuration for new battery monitor alarms | 10 Hours
Daily |
|
13-Aug-20 08:00 | 16-Aug-20 08:00 | SHELL | Outage | 847s 901T (847s Muskeg River) | customer maintenance | 3 Days
Continuous |
|
13-Aug-20 08:00 | 13-Aug-20 16:00 | ENMAX | Outage | 162s 138-RB80 (162s Beddington) | breaker maintenance | 8 Hours
Continuous |
|
13-Aug-20 08:00 | 13-Aug-20 16:00 | ATCO | RB | 7L59 (786s High Level - 789s Keg River) | install new cleveland switch that will create a new J2 on the High Level side of Melito | 8 Hours
Continuous |
|
13-Aug-20 08:00 | 13-Aug-20 17:00 | ALTALINK | Outage | 37s 81 (37s North Calder) | complete wiring, commissioning and function testing for reclosing circuit | 9 Hours
Daily |
|
13-Aug-20 08:00 | 13-Aug-20 15:00 | ALTALINK | TE | 213s Hughenden RTU/SCADA | update transformer alarms | 7 Hours
Daily |
|
13-Aug-20 12:00 | 13-Aug-20 16:00 | ALTALINK | IO | ALC02L (409s-879s) open-end | relay maintenance at 879s - ATCO | 4 Hours
Daily |
|
14-Aug-20 07:00 | 14-Aug-20 19:00 | ALTALINK | TE | 199s East Airdrie RTU/SCADA | update configuration for new alarms | 12 Hours
Daily |
|
14-Aug-20 07:15 | 14-Aug-20 17:45 | ALTALINK | Outage | 922L (17s Benalto - 310p Sundance) | maintenance on str 461 | 10.5 Hours
Daily |
|
14-Aug-20 09:00 | 14-Aug-20 10:00 | BCH | TE | 5L94 (Cranbrook - 102s Langdon) | protection work | 60 Mins
Continuous |
|
15-Aug-20 07:00 | 15-Aug-20 13:00 | ALTALINK | Outage | 172s1 (T1 TX18092) Customer - Advice | Customer repairs to their 172s23 Breaker, Does not currently rack out | 6 Hours
Continuous |
|
15-Aug-20 07:15 | 17-Aug-20 17:45 | ALTALINK | Outage | 166L (256s Harmattan - 166AL) | scope of work including moving and replacing structures 109 and 110 and adding new str 109A | 2.44 Days
Continuous |
|
15-Aug-20 07:30 | 16-Aug-20 17:30 | ALTALINK | Outage | 523s T1 and 25kV Bus1 GOI | Repair AMI structure and replace 523s T1 LA’s. T1 doble, SFRA. AMI structure repairs, switch replacement (523s8) | 1.42 Days
Continuous |
|
15-Aug-20 07:30 | 21-Aug-20 17:30 | ALTALINK | TE | 271s RTU - Supervisory | Update RTU configuration to add new transformer monitoring alarms for T1. Loss of visibility for 10 minutes while RTU is update. | 6.42 Days
Daily |
|
15-Aug-20 08:00 | 15-Aug-20 12:00 | ENMAX | TE | 11s 11PT138-Z31 | Line Protection Upgrade. Cell rewiring | 4 Hours
Continuous |
|
15-Aug-20 09:00 | 15-Aug-20 13:00 | ENMAX | TE | 11s Z31 138kV Bus Differential Protection | Line Protection Upgrade. Cell rewiring. Bus Zone remains protected by Zone 2 distance protection from infeeding transmission lines. | 4 Hours
Continuous |
|
15-Aug-20 10:00 | 17-Aug-20 14:00 | ATCO | TE | 731S 25kV Breaker Relays | 731S Elmworth Bkr Replacement and Protection Upgrade project
Block Northstone Power DTT signal for the install of the new temporary signal that will remain in place for the duration of project. Notification to Northstone Power was made regarding the Temporary Protection Change |
2.17 Days
Continuous |
|
16-Aug-20 08:00 | 23-Aug-20 18:00 | SUNCOR | Outage | 29EDD-55 29Edd-55 | bus outage 29PP-37D, 29PT-165
|
7.42 Days
Continuous |
|
16-Aug-20 08:00 | 16-Aug-20 16:00 | ENMAX | Outage | 2.82L (ENMAX 2 - ENMAX 5) | power factor test HV breaker 5B138-2.82 | 8 Hours
Continuous |
|
16-Aug-20 11:00 | 16-Aug-20 12:00 | ALTALINK | TE | 74s Janet RTU/SCADA | update configuration | 60 Mins
Daily |
|
16-Aug-20 15:30 | 20-Aug-20 16:00 | ALTALINK | Outage | 523S Bullshead | 523s406W 25kV breaker replacement | 4.02 Days
Continuous |
|
17-Aug-20 07:00 | 21-Aug-20 17:00 | EPCOR | Outage | 803s T2 (803s Lambton), 803s L2402 (803s Lambton), 803s L2405 (803s Lambton) | Doble/ SFRA T2 | 4.42 Days
Continuous |
|
17-Aug-20 07:00 | 21-Aug-20 17:00 | EPCOR | Outage | 805s T3 (805s Jasper), 805s J2404 (805s Jasper), 805s J2405 (805s Jasper) | Doble T3 | 4.42 Days
Continuous |
|
17-Aug-20 07:00 | 28-Aug-20 17:00 | ATCO | Outage | 2029s ACF14 (2029s Heathfield) | trip coil testing | 11.42 Days
Continuous |
|
17-Aug-20 07:00 | 21-Aug-20 17:30 | ALTALINK | TE | 296s Rosyth RTU/SCADA | SCADA upgrade project | 4.44 Days
Daily |
|
17-Aug-20 07:00 | 20-Aug-20 17:00 | ALTALINK | TE | 288s Wolf Creek RTU/SCADA | add alarms | 3.42 Days
Daily |
|
17-Aug-20 07:00 | 23-Aug-20 17:00 | EPCOR | Outage | T2 (Rossdale) | outage for UGD | 6.42 Days
Continuous |
|
17-Aug-20 07:00 | 18-Aug-20 19:00 | ALTALINK | TE | 83s Taber RTU/SCADA | update configuration for new alarms | 1.5 Days
Daily |
|
17-Aug-20 07:00 | 21-Aug-20 17:00 | Saskpower | Outage | Sask Power PR901 | transformer & switch maintenance | 4.42 Days
Continuous |
AB-SK |
17-Aug-20 07:00 | 18-Aug-20 17:30 | ALTALINK | TE | 59s Peigan RTU/SCADA | update configuration to add alarms | 1.44 Days
Daily |
|
17-Aug-20 07:15 | 20-Aug-20 17:45 | ALTALINK | Outage | 914L (86s Bigstone - 87s Gaetz), 87s 1252 (87s Gaetz) | SCADA upgrade | 3.44 Days
Continuous |
|
17-Aug-20 07:15 | 26-Aug-20 17:00 | ALTALINK | Outage | 276s T2(TX 18471) GOI | CT upgrade | 9.41 Days
Continuous |
|
17-Aug-20 07:30 | 21-Aug-20 18:30 | ALTALINK | Outage | 428s T1 (428s Namaka) | Upgrade existing protections, LA replacement, bird cover install | 4.46 Days
Continuous |
|
17-Aug-20 07:30 | 24-Aug-20 14:30 | ALTALINK | Outage | 19s 69kV Bus (T8, 133L, 2739s & 352s Sta | Outage to replace 19s125 and install SAs for 19s123 & 19s124 | 7.29 Days
Continuous |
|
17-Aug-20 08:00 | 30-Aug-20 16:00 | ATCO | Outage | 7L61 (780s Lubicon - 796s Nipisi) | cross arm and insulator change out | 13.33 Days
Continuous |
|
17-Aug-20 08:00 | 20-Aug-20 17:00 | ATCO | Outage | 7L24 (846s Grand Centre - 7L24D3) | Replacing Cross-Arms, Poles and Ground Rod's | 3.38 Days
Continuous |
|
17-Aug-20 08:00 | 20-Aug-20 17:00 | ALTALINK | TE | 87s Gaetz RTU/SCADA | SCADA upgrade project. RTU updates to cutover SCADA points/controls to new SCADA system | 3.38 Days
Daily |
|
17-Aug-20 08:00 | 21-Aug-20 18:00 | ALTALINK | TE | 428s Namaka RTU/SCADA | RTU database updates | 4.42 Days
Daily |
|
17-Aug-20 08:00 | 17-Aug-20 18:00 | ENMAX, ALTALINK | Outage | 1080L (ENMAX 25 - ENMAX 65), 25B240-D138 (ENMAX 25), 25B240-D139 (ENMAX 25) | power factor test HV LA 25MD240-1080. | 10 Hours
Continuous |
|
17-Aug-20 08:00 | 21-Aug-20 17:00 | ATCO | Outage | 848s 903 (848s Ruth Lake) | replace CT | 4.38 Days
Continuous |
|
17-Aug-20 08:00 | 21-Aug-20 17:00 | ALTALINK | TE | 428S Namaka | trip/function tests; 428s19 | 4.38 Days
Daily |
|
17-Aug-20 08:00 | 04-Sep-20 16:00 | ENMAX | Outage | 23.4TR (ENMAX 23) | protection outage and MV cable swap | 18.33 Days
Continuous |
|
17-Aug-20 08:00 | 20-Aug-20 16:00 | ENMAX, ALTALINK | TE | 985L (74s Janet - ENMAX 25) | upgrade the firmware for correct operation | 3.33 Days
Continuous |
|
17-Aug-20 08:00 | 20-Aug-20 16:00 | ENMAX, ALTALINK | TE | 985L (74s Janet - ENMAX 25) | techs to perform CIP firmware upgrades | 3.33 Days
Continuous |
|
17-Aug-20 08:00 | 20-Aug-20 17:00 | ATCO | TE | ATCO Radio Tower | 9934R Touchwood MPLS - upgrade MPLS node | 3.38 Days
Daily |
|
17-Aug-20 08:00 | 21-Aug-20 17:00 | ALTALINK | TE | 428S Namaka | functional testing of the protection upgrade of 428s T1 | 4.38 Days
Daily |
|
17-Aug-20 08:00 | 31-Aug-20 20:00 | Syncrude | TE | T19 72/13.8KV Transformer & Capacitor Bank Outage (31-0-PC15-2) - Plant 31 Powerhouse Following Circuit Breaker will be operated: Breaker 1935, 19215 (Plant 31 Powerhouse) Following switch will be operated: 1934 (Plant 31 Powerhouse) | T19 72/13.8KV Transformer & Capacitor Bank Outage (31-0-PC15-2) - Plant 31 Powerhouse
Following Circuit Breaker will be operated: Breaker 1935, 19215 (Plant 31 Powerhouse) Following switch will be operated: 1934 (Plant 31 Powerhouse) |
14.5 Days
Continuous |
|
17-Aug-20 08:00 | 28-Aug-20 17:00 | ALTALINK | TE | 276s Union Carbide Prentiss RTU/SCADA | cutover all points to new SCADA system - configuration file updates - SCADA equipment installation and commissioning | 11.38 Days
Daily |
|
17-Aug-20 08:00 | 17-Aug-20 16:00 | ENMAX | Outage | 34B69-16.60 (ENMAX 34), 16.60L (ENMAX 16 - ENMAX 34) | power factor test HV breaker. 34B69-16.60 | 8 Hours
Continuous |
|
17-Aug-20 08:00 | 09-Sep-20 17:00 | ALTALINK | IO | A743s 701T OOS ATCO - Info | ATCO: ATCO will have the 144kv/72kv tie transformer @ 743S Sarah Lake out of service Aug 17-Sep 9,2020 for a Breaker replacement project. | 23.38 Days
Continuous |
|
17-Aug-20 08:00 | 17-Aug-20 17:00 | ATCO | Outage | 770S 704, 7L159 | 770S Protection Upgrade - 704 Test and Operate
Test and operate on breaker 704 to move alarm circuits to new SCADA system from old PLC system. Permit will be required to test trip coil for PRC-005. Line protection settings will be updated on A and B protection to change soft alarm descriptors. Each line protection relay (A and B) will only be isolated while the other is in service due to tele-protection being in place. 7L159 will be open at 770S Three Hills end. Line protection will be isolated, one relay at a time. |
9 Hours
Continuous |
|
17-Aug-20 08:00 | 17-Aug-20 16:00 | ALTALINK | IO | 1080L (ENMAX25SUB-ENMAX65SUB) - Info | Power factor test HV LA 25MD240-1080. | 8 Hours
Daily |
|
17-Aug-20 08:00 | 18-Aug-20 08:00 | ATCO | Outage | 743s 701T (743s Sarah Lake) | replace breaker | 24 Hours
Continuous |
|
17-Aug-20 08:15 | 17-Aug-20 10:30 | ATCO | Outage | 849s 901 (849s Joslyn Creek) | trip coil testing | 2.25 Hours
Continuous |
|
17-Aug-20 08:30 | 20-Aug-20 16:00 | ATCO | Outage | 801s 909 (801s Anderson) | breaker maintenance | 3.31 Days
Continuous |
|
17-Aug-20 09:00 | 21-Aug-20 18:00 | ALTALINK | Outage | 763L (158s Vauxhall - 763AL) | urgent line clearance: change structures range 322-406 | 4.38 Days
Continuous |
|
17-Aug-20 09:00 | 19-Aug-20 17:00 | ALTALINK | TE | 580s Sylvan Lake RTU/SCADA | configuration updates for new alarming | 2.33 Days
Daily |
|
17-Aug-20 09:00 | 20-Aug-20 18:00 | ALTALINK | Outage | 786L (799s Coleman - BCH Natal) | P5 urgent repair Str's range 76-117 | 3.38 Days
Continuous |
AB-BC |
17-Aug-20 10:00 | 24-Aug-20 15:00 | ATCO | Outage | 7L40 (733s Simonette - 813s Little Smoky) | x-arm change out | 7.21 Days
Continuous |
|
17-Aug-20 10:00 | 17-Aug-20 12:00 | ATCO | Outage | 7L172 (739s Edith Lake - 743s Sarah Lake), 743s 704 (743s Sarah Lake) | breaker trip coil maintenance | 2 Hours
Continuous |
|
17-Aug-20 10:45 | 17-Aug-20 13:30 | ATCO | Outage | 849s 902 (849s Joslyn Creek) | trip coil testing | 2.75 Hours
Continuous |
|
17-Aug-20 11:00 | 21-Aug-20 18:00 | ALTALINK | Outage | 262s T2 (262s Rocky Mountain House) | bushings, LAs and bird cover | 4.29 Days
Continuous |
|
17-Aug-20 11:30 | 17-Aug-20 17:30 | ALTALINK | TE | 89S Ellerslie | update card and firmware and replace battery on T2 protection | 6 Hours
Daily |
|
17-Aug-20 12:00 | 09-Sep-20 17:00 | ATCO | Outage | 743s 605 (743s Sarah Lake) | replacing breaker | 23.21 Days
Continuous |
|
17-Aug-20 12:30 | 20-Aug-20 17:30 | ALTALINK | Outage | 761L (38s East Edmonton - 71s Lamoureux) | component replacements including poles on Str's 1-195 | 3.21 Days
Continuous |
|
17-Aug-20 12:30 | 17-Aug-20 17:00 | FORTIS | TE | 140s Thompson RTU/SCADA | SCADA updates for qualitrol & winding temp trips being removed | 4.5 Hours
Daily |
|
17-Aug-20 12:30 | 18-Aug-20 17:30 | ALTALINK | TE | 575S Sundre | standard relay maintenance | 29 Hours
Daily |
|
17-Aug-20 13:00 | 17-Aug-20 17:30 | ALTALINK | TE | 385S Spring Coulee | standard relay maintenance | 4.5 Hours
Daily |
|
18-Aug-20 06:30 | 20-Aug-20 17:30 | ALTALINK | RB | 737L (38s East Edmonton - 95s Imperial Oil Edmonton) | crews working within close proximity on 761L | 2.46 Days
Daily |
|
18-Aug-20 06:30 | 20-Aug-20 17:30 | ALTALINK, EPCOR | RB | 921L (71s Lamoureux - 987s Clover Bar) | crews working within close proximity on 761L | 2.46 Days
Daily |
|
18-Aug-20 07:00 | 21-Aug-20 18:00 | ALTALINK | Outage | 514L (396s Pincher Creek - 514BL) | maintenance between Strs 2 & 195 | 3.46 Days
Daily |
|
18-Aug-20 07:00 | 01-Sep-20 18:30 | ALTALINK | RB | 551L (123s Banff - 953s Lake Louise) | salvage of road accesses to ROW, excavation with track hoes | 14.48 Days
Daily |
|
18-Aug-20 07:30 | 24-Aug-20 17:30 | ALTALINK | Outage | 271s T2 (271s Shell Jumping Pound) | replace existing PT4(271s13) and metering CTs, install new bus support insulators and PT support steel on center phase, replace JB3 and replace T2 revenue meter | 6.42 Days
Continuous |
|
18-Aug-20 08:00 | 18-Aug-20 16:00 | ALTALINK | Outage | 5s C3 (5s East Calgary), 5s C4 (5s East Calgary) | installing replacement surge arrestor on the cap bank CT neutral | 8 Hours
Daily |
|
18-Aug-20 08:00 | 18-Aug-20 16:00 | ATCO | Outage | 7L69 (731s Elmworth - 815s Goodfare) | pole relocate for customer | 8 Hours
Continuous |
|
18-Aug-20 08:00 | 20-Aug-20 16:00 | ENMAX | Outage | 25B240-D139 (ENMAX 25), 25 B240-D142 (ENMAX 25), ENMAX 25 240kV North Bus, 25B240-D133 (ENMAX 25), 25B240-D136 (ENMAX 25) | power factor test and replace switch mechs | 2.33 Days
Continuous |
|
18-Aug-20 08:00 | 19-Aug-20 12:00 | ATCO | Outage | 898s 901 (898s Heart Lake) | replace trip latch due to issue found during maintenance | 28 Hours
Continuous |
|
18-Aug-20 08:00 | 18-Aug-20 10:00 | ALTALINK | TE | 895s T3 (895s Suffield) | settings update for NGR install | 2 Hours
Daily |
|
18-Aug-20 08:00 | 18-Aug-20 17:00 | ALTALINK | TE | 580s T1 (580s Sylvan Lake) | separate out alarms | 9 Hours
Daily |
|
18-Aug-20 08:00 | 18-Aug-20 14:00 | ALTALINK | Outage | 396s T1 (396s Pincher Creek), 396s Pincher Creek 69kV Bus, 185L (379s Shell Canada Waterton - 396s Pincher Creek), 514L (396s Pincher Creek - 514BL) | replace 69kV switch and fill bushing on 396s30 | 6 Hours
Continuous |
|
18-Aug-20 08:00 | 25-Aug-20 17:00 | ATCO | Outage | 743s 702T (743s Sarah Lake) | replacing breaker 605, 605A & 605B | 7.38 Days
Continuous |
|
18-Aug-20 08:00 | 30-Oct-20 17:00 | ATCO | TE | 811s Clairmont Lake RTU/SCADA | RTU download and test | 73.38 Days
Continuous |
|
18-Aug-20 08:00 | 19-Aug-20 16:00 | ENMAX | Outage | 16.61L (ENMAX 16 - ENMAX 27), 27.1TR (ENMAX 27) | tapchanger inspection | 1.33 Days
Continuous |
|
18-Aug-20 08:00 | 18-Aug-20 16:00 | ENMAX | Outage | 47B138-771 (ENMAX 47) | power factor test HV PT | 8 Hours
Continuous |
|
18-Aug-20 08:00 | 18-Aug-20 17:00 | ALTALINK | TE | 157S Lac La Biche | UR card replacement (788L/L4 B) | 9 Hours
Daily |
|
18-Aug-20 08:00 | 18-Aug-20 17:00 | ALTALINK | Outage | 859L (20s Ghost - T793s Horse Creek), 793s 859W (793s Horse Creek) | implement/function sync check changes on M388/389 relay | 9 Hours
Daily |
|
18-Aug-20 08:00 | 19-Aug-20 13:00 | ALTALINK | Outage | 336s T2 (336s Fincastle) | replace temp SS2 Tx to permanent one, complete bird cover on SS2 TX and 25kV UG bus structure, repair 336s1452 | 29 Hours
Continuous |
|
18-Aug-20 08:00 | 18-Aug-20 16:00 | ALTALINK | Outage | 221s T3 (221s Sunken Lake) | customer installing wildlife cover-up | 8 Hours
Daily |
|
18-Aug-20 08:15 | 18-Aug-20 10:00 | ATCO | Outage | 849s 904 (849s Joslyn Creek) | PRC-005 trip coil testing | 105 Mins
Continuous |
|
18-Aug-20 08:30 | 18-Aug-20 16:30 | ALTALINK | TE | 283S Violet Grove | relay maintenance on 836L relays | 8 Hours
Daily |
|
18-Aug-20 08:30 | 19-Aug-20 16:30 | ALTALINK | TE | 74S Janet | standard relay maintenance | 1.33 Days
Daily |
|
18-Aug-20 09:00 | 20-Aug-20 15:30 | ALTALINK | IO | 247s 17T1 City of Red Deer - Info | power factor dissipation testing including bushings | 2.27 Days
Continuous |
|
18-Aug-20 09:00 | 20-Aug-20 15:30 | REDDEER | Outage | 247s T1 (247s Piper Creek) | power factor dissipation testing including bushings | 2.27 Days
Continuous |
|
18-Aug-20 09:15 | 18-Aug-20 15:45 | ALTALINK | Outage | 253s C1 (253s Blackie) | PRC5 maintenance and perform 1st trip | 6.5 Hours
Daily |
|
18-Aug-20 10:00 | 18-Aug-20 12:00 | ALTALINK | Outage | 895s T3 (895s Suffield) | tie in riser from new NGR to T3 | 2 Hours
Daily |
|
18-Aug-20 10:00 | 18-Aug-20 14:00 | ALTALINK | TE | AltaLink Radio Tower, 228s T.M.P.L.Niton RTU/SCADA | 9269R radio maintenance | 4 Hours
Daily |
|
18-Aug-20 10:30 | 18-Aug-20 13:00 | ATCO | Outage | 849s 905 (849s Joslyn Creek) | PRC-005 trip coil testing | 2.5 Hours
Continuous |
|
18-Aug-20 15:00 | 18-Aug-20 17:00 | ALTALINK | TE | 895s T3 (895s Suffield) | settings update for NGR install. | 2 Hours
Daily |
|
19-Aug-20 06:00 | 19-Aug-20 18:30 | ALTALINK | Outage | 747L (99s North St. Albert - 711L) | offload new control building onto new foundations | 12.5 Hours
Daily |
|
19-Aug-20 07:00 | 19-Aug-20 18:00 | ENMAX | Outage | 10.2TR (ENMAX 10) | roxtec installation | 11 Hours
Continuous |
|
19-Aug-20 07:00 | 20-Aug-20 17:00 | ALTALINK | TE | 331S Ponoka | relay settings change and testing | 1.42 Days
Daily |
|
19-Aug-20 07:00 | 20-Aug-20 17:30 | ALTALINK | TE | 799s Coleman RTU/SCADA | update configuration to add alarms | 1.44 Days
Daily |
|
19-Aug-20 08:00 | 19-Aug-20 17:00 | ALTALINK | TE | AltaLink Radio Tower | 9466R - 9028R - replace radio | 9 Hours
Daily |
|
19-Aug-20 08:00 | 19-Aug-20 16:00 | ENMAX | Outage | 47.1TR (ENMAX 47) | power factor test HV PT 47PT138-Z31 | 8 Hours
Continuous |
|
19-Aug-20 08:00 | 19-Aug-20 17:00 | ATCO | Outage | 770S Threehills | adding new station service transformers 500SST2 to be fed from 500BUS1 | 9 Hours
Continuous |
|
19-Aug-20 08:00 | 19-Aug-20 17:00 | ALTALINK | TE | 580S Sylvan Lake | T2 - removing 'A' & 'S' protections to separate out alarms | 9 Hours
Daily |
|
19-Aug-20 08:00 | 19-Aug-20 17:00 | ALTALINK | TE | 353S Plamondon | UR card replacement (728L/L3 A) | 9 Hours
Daily |
|
19-Aug-20 08:00 | 19-Aug-20 17:00 | ALTALINK | Outage | 433L (291s Cochrane - T793s Horse Creek), 793s 433 (793s Horse Creek) | implement/function sync check changes on M388/389 relay | 9 Hours
Daily |
|
19-Aug-20 08:00 | 19-Aug-20 17:00 | ALTALINK | TE | 437s Baymag RTU/SCADA | upgrade configuration and testing | 9 Hours
Daily |
|
19-Aug-20 08:30 | 19-Aug-20 16:30 | ALTALINK | TE | 281S Johnson | investigate/repair protection discrepancies | 8 Hours
Daily |
|
19-Aug-20 08:30 | 19-Aug-20 16:30 | ALTALINK | TE | 281s Johnson RTU/SCADA | RTU database update | 8 Hours
Daily |
|
19-Aug-20 09:00 | 21-Aug-20 17:00 | ATCO | Outage | 790s 702T (790s Poplar Hill), 790s 509C (790s Poplar Hill) | repair leaks | 2.33 Days
Continuous |
|
19-Aug-20 09:00 | 20-Aug-20 14:00 | ALTALINK | TE | 368S Burdett | standard relay maintenance | 29 Hours
Daily |
|
19-Aug-20 12:00 | 20-Aug-20 16:00 | ALTALINK | TE | 336s Fincastle RTU/SCADA | update configuration to add door alarm contacts | 28 Hours
Daily |
|
19-Aug-20 23:00 | 20-Aug-20 03:00 | ALTALINK | Outage | 62s 11 (62s Brazeau) | maintenance | 4 Hours
Daily |
|
20-Aug-20 03:00 | 20-Aug-20 07:00 | ALTALINK | Outage | 62s 12 (62s Brazeau) | maintenance | 4 Hours
Daily |
|
20-Aug-20 07:00 | 22-Aug-20 18:00 | ALTALINK | Outage | 707L (54s - 166s) - GOI | Fire mitigation to repair Structures #5 - 8, 16 - 19, 24, 35 & 36 | 2.46 Days
Continuous |
|
20-Aug-20 07:30 | 20-Aug-20 17:30 | ALTALINK | RB | 862L (166s Dow Chemical Fort Saskatchewan - 258s Dow Hydro Carbons) | Fire mitigation on Structures #1 & 2 | 10 Hours
Daily |
|
20-Aug-20 08:00 | 24-Aug-20 16:00 | ATCO | Outage | 7L22 (811s Clairmont Lake - 7L22D2) | protection upgrade | 4.33 Days
Continuous |
|
20-Aug-20 08:00 | 20-Aug-20 16:00 | ENMAX | Outage | 47.2TR (ENMAX 47), 47PT138-Z32. 47.2TR | power factor test | 8 Hours
Continuous |
|
20-Aug-20 08:00 | 20-Aug-20 11:00 | ALTALINK | TE | 150S Clyde | 138KV bus protection | 3 Hours
Daily |
|
20-Aug-20 08:00 | 20-Aug-20 14:00 | ALTALINK | TE | AltaLink Radio Tower | 9157R - 140s Radio - RTU | 6 Hours
Daily |
|
20-Aug-20 08:00 | 20-Aug-20 16:00 | ENMAX | IO | 38s STN SERVICE TRANSFORMER | Swap out station service transformer. Stations will run on a generator for the duration of the day except for approximately 1 hour while new transformer is terminated into switchgear. | 8 Hours
Continuous |
|
20-Aug-20 09:00 | 20-Aug-20 17:30 | ALTALINK | Outage | 56s C1 (56s Boyle) | Urgent repair to circuit switcher | 8.5 Hours
Daily |
|
20-Aug-20 10:00 | 25-Aug-20 17:00 | ALTALINK | TE | 55s Olds RTU/SCADA | RTU configuration uploads | 5.29 Days
Daily |
|
20-Aug-20 11:00 | 20-Aug-20 14:00 | ALTALINK | TE | 150s T1 (150s Clyde) | A protection maintenance | 3 Hours
Daily |
|
20-Aug-20 13:00 | 22-Aug-20 15:00 | ALTALINK | TE | 392s Black Diamond RTU/SCADA | update configuration | 2.08 Days
Daily |
|
20-Aug-20 14:00 | 20-Aug-20 17:00 | ALTALINK | TE | 150s T1 (150s Clyde) | B protection maintenance | 3 Hours
Daily |
|
21-Aug-20 08:00 | 27-Aug-20 18:00 | SUNCOR | Outage | Unmodeled Transmission Facility (Suncor) | 29PP-70C & 29PP-70F | 6.42 Days
Daily |
|
21-Aug-20 08:00 | 24-Aug-20 16:00 | ENMAX | Outage | 39.3TR (ENMAX 39) | Reinhausen tapchanger maintenance | 3.33 Days
Continuous |
|
21-Aug-20 08:00 | 21-Aug-20 14:00 | ALTALINK | Outage | 396s T1, 69kV Bus GOI | 396s31 replace 69kV switch and fill bushing on 396s30 | 6 Hours
Daily |
This document and the information contained herein are based upon information and data which by their nature contain a degree of uncertainty and are subject to change. In addition, this document may contain information and data from public sources and/or third parties, which have been assumed to be accurate and complete and have not been verified. Accordingly, the Independent System Operator, operating as the Alberta Electric System Operator (the "AESO") makes no warranty, representation or guarantee, express or implied, with respect to this document or the information contained herein, including, but not limited to, any warranty, representation or guarantee of accuracy, completeness, timeliness, reliability, availability, absence of computer virus, non- infringement, merchantability or suitability for any purpose. Under no circumstances will the AESO, its members, officers, employees, contractors or agents, or any of their respective affiliates, be liable for any errors or omissions in, or any losses, damages or claims whatsoever, whether in contract, tort or otherwise, arising from use of or reliance upon, this document or any information contained herein. © 2009 Alberta Electric System Operator. All rights reserved |