| Alberta Electric System Operator | |
| System Co-ordination Plan | |
| 2020-03-05 to 2020-03-13 | |
| Approved Outages |
| Previous Version | |
| Download CSV |
| From | To | Owner | Type | Element | Scheduled Activity | Date/Time Comments | Interconnection |
|---|---|---|---|---|---|---|---|
| 05-Oct-18 08:00 | 31-Dec-20 16:00 | EPCOR | IO | Rossdale C2 (Rossdale) | forced outage | 818.38 Days
Continuous |
|
| 24-Oct-18 01:13 | 31-Dec-20 16:00 | EPCOR | IO | Rossdale C1 (Rossdale) | forced outage | 799.66 Days
Continuous |
|
| 27-Aug-19 08:00 | 13-Apr-20 16:00 | ATCO | TE | 740S H.R.Milner | replace relays on 144 kV bus differential protection as part of 740S rebuild | 230.33 Days
Continuous |
|
| 19-Sep-19 08:00 | 19-Jun-20 16:00 | ATCO | Outage | 826s 504R (826s Marguerite Lake) | emergency: move reactor from 826s to 732s | 274.33 Days
Continuous |
|
| 28-Oct-19 08:00 | 01-May-20 17:00 | ATCO | TE | 740s H.R.Milner RTU/SCADA | part of the HRM rebuild project, download controller and test | 186.38 Days
Continuous |
|
| 24-Dec-19 12:00 | 09-Mar-20 17:00 | ATCO | Outage | 861S 602T (861S Eurekariver) | forced outage, low gas pressure | 76.17 Days
Continuous |
|
| 01-Jan-20 08:00 | 31-Dec-20 18:00 | SUNCOR | Outage | Unmodeled Transmission Facility (Suncor) | 29L3-167, 29L3-141 , 29PL3-63, 29PL3-183, 29PT-241 & 29PL7-4, 29PP-47 & 29PT-576, 29PP-46 & 29PT-575, 144KV NODE,29PT-246, 144KV NODE,29PT-238, 29PT-257 & 29PL7-4,29PT-260 & 29PL7-4, 29PT-250&29PL7-3,29PT-236 & 29PL7-3,29PL3-153/152/196, 29PT-128 & 29PL7-10 | 365.42 Days
Daily |
|
| 06-Jan-20 07:00 | 30-Apr-20 17:00 | EPCOR | TE | 330P Genesee | relay maintenance | 115.38 Days
Continuous |
|
| 06-Jan-20 07:00 | 31-Mar-20 17:00 | EPCOR | TE | Rossdale | relay maintenance | 85.38 Days
Daily |
|
| 20-Jan-20 07:00 | 10-Mar-20 17:00 | EPCOR | TE | 665S Dome | relay maintenance | 50.38 Days
Daily |
|
| 20-Jan-20 08:00 | 31-Mar-20 16:00 | ENMAX | TE | ENMAX 8 | installation of new switchgear | 71.29 Days
Continuous |
|
| 20-Jan-20 08:00 | 31-Mar-20 16:00 | ENMAX | TE | ENMAX 8 | installation of new switchgear | 71.29 Days
Continuous |
|
| 20-Jan-20 08:00 | 31-Mar-20 16:00 | ENMAX | Outage | ENMAX 8 138kV Bus, 8.1TR (ENMAX 8), 8.2TR (ENMAX 8) | installation of new switchgear and protection | 71.29 Days
Continuous |
|
| 20-Jan-20 08:00 | 31-Mar-20 16:00 | ENMAX | TE | ENMAX 8 138kV Bus | installation of new switchgear | 71.29 Days
Daily |
|
| 24-Jan-20 08:00 | 28-Mar-20 16:00 | ATCO | Outage | 2029s ACF13 (2029s Heathfield) | Forced outage repairs | 64.29 Days
Continuous |
|
| 28-Jan-20 07:00 | 31-Mar-20 17:00 | EPCOR | IO | EPCOR Network | firmware upgrades | 63.38 Days
Continuous |
|
| 30-Jan-20 07:00 | 09-Mar-20 18:00 | ALTALINK | IO | 551L (945s Sunshine Village - 953s Lake Louise) | energize/de-energize bypass line | 39.42 Days
Continuous |
|
| 08-Feb-20 11:03 | 31-Mar-20 18:00 | ALTALINK | Outage | 895s T2 (895s Suffield) | forced outage | 52.25 Days
Continuous |
|
| 10-Feb-20 07:00 | 31-May-20 17:00 | EPCOR | RB | 1139L (367s Harry Smith - EPCOR Riverview) | 1139L A/R block at both Harry Smith and Riverview S/S | 111.38 Days
Continuous |
|
| 10-Feb-20 07:00 | 31-May-20 17:00 | EPCOR | RB | 1164L (816s Petrolia - EPCOR Riverview) | 1164L A/R block at both Petrolia and Riverview S/S | 111.38 Days
Continuous |
|
| 15-Feb-20 07:00 | 30-Apr-20 17:00 | EPCOR | TE | 805S Jasper | 240/72 kV relay blocking for relay maintenance | 75.38 Days
Daily |
|
| 18-Feb-20 09:00 | 27-Mar-20 16:00 | ATCO | Outage | 9L100 (801s Anderson - 807s Sheerness), 807s 902 (807s Sheerness), 807s 902T (807s Sheerness) | maintenance & 9L100 protection upgrade | 38.25 Days
Continuous |
|
| 18-Feb-20 12:00 | 08-Mar-20 18:30 | ALTALINK | Outage | 310p T30 (310p Sundance) | corrosive sulphur mitigation | 19.23 Days
Continuous |
|
| 24-Feb-20 07:00 | 05-Mar-20 17:00 | ALTALINK | TE | 28S West Brooks | fault locating addition | 10.42 Days
Daily |
|
| 24-Feb-20 07:00 | 05-Mar-20 17:00 | ALTALINK | TE | 324S Cassils | adding line fault location | 10.42 Days
Daily |
|
| 24-Feb-20 07:00 | 05-Mar-20 17:00 | ALTALINK | TE | 324s Cassils RTU/SCADA | adding line fault location | 10.42 Days
Daily |
|
| 26-Feb-20 08:00 | 06-Mar-20 17:00 | ALTALINK | TE | 154s Black Spruce RTU/SCADA | RTU update to add fault location on 1118L, 1099L, 971L & 1115L | 9.38 Days
Daily |
|
| 26-Feb-20 08:00 | 06-Mar-20 17:00 | ALTALINK | TE | 154S Black Spruce | testing fault locating on the following relays: 1118L,1099L, 971L and 1115L | 9.38 Days
Daily |
|
| 26-Feb-20 08:00 | 06-Mar-20 17:00 | CENOVUS | TE | 539S Sunday Creek | isolate 1118L relays for fault locating addition at 154s Black Spruce | 9.38 Days
Daily |
|
| 26-Feb-20 08:00 | 06-Mar-20 17:00 | ALTALINK | TE | 698S Jackfish | isolate 1099L relays for fault locating addition at 154s Black Spruce | 9.38 Days
Daily |
|
| 26-Feb-20 08:00 | 06-Mar-20 17:00 | EXPPIPE1 | TE | 762S Conklin | isolate 971L relays for fault locating addition at 154s Black Spruce | 9.38 Days
Daily |
|
| 26-Feb-20 12:45 | 11-Mar-20 18:00 | EPCOR | Outage | RW 2401 (EPCOR Riverview) | forced outage | 14.18 Days
Continuous |
|
| 27-Feb-20 05:30 | 12-Mar-20 18:30 | ALTALINK | RB | 551L (123s Banff - 953s Lake Louise) | power line construction, excavation with track hoes, live line cutovers | 14.5 Days
Daily |
|
| 27-Feb-20 08:00 | 17-Mar-20 20:00 | Syncrude | Outage | Mildred T3 (Syncrude Mildred Lake) | de-energize temporary transformer to install new transformer T3 (P2039) | 19.46 Days
Continuous |
|
| 02-Mar-20 07:00 | 06-Mar-20 17:00 | ALTALINK, EPCOR | Outage | 930L (37s North Calder - Poundmaker) | maintenance | 4.42 Days
Continuous |
|
| 02-Mar-20 07:00 | 06-Mar-20 17:00 | ALTALINK | IO | 930L (37s - E Poundmaker) Epcor Info | required for Epcor relay maintenance and op- checks | 4.42 Days
Continuous |
|
| 02-Mar-20 08:00 | 05-Mar-20 16:00 | ENMAX | Outage | 32.2TR (ENMAX 32) | replace broken bushing insulator 32.17. 32 Sub 8kv 32.15 insulator broken, check reversing switch, oil sampling 32.2TR bushing | 3.33 Days
Continuous |
|
| 02-Mar-20 08:00 | 22-Mar-20 17:00 | ATCO | Outage | 7L64 (930s Arcenciel - 7L64D5) | replacing structures and crossarms | 20.33 Days
Continuous |
|
| 02-Mar-20 08:00 | 06-Mar-20 17:00 | ATCO | RB | 7L59 (786s High Level - 789s Keg River) | line inspection | 4.38 Days
Continuous |
|
| 02-Mar-20 08:00 | 28-Mar-20 16:00 | ATCO | Outage | 2029s ACF11 (2029s Heathfield) | Forced outage repairs | 26.29 Days
Continuous |
|
| 02-Mar-20 09:00 | 27-Mar-20 17:00 | ATCO | Outage | 7L63 (783s Cadotte River - 812s Norcen) | crossarm replacements | 25.29 Days
Continuous |
|
| 02-Mar-20 09:00 | 05-Mar-20 17:00 | ALTALINK | TE | 28s West Brooks RTU/SCADA | SCADA configurations update | 3.33 Days
Continuous |
|
| 02-Mar-20 09:30 | 05-Mar-20 17:30 | ALTALINK | RB | 763L (28s West Brooks - 158s Vauxhall) | components/structure replacements (763AL Str 92-96). 763AL Str 116 | 3.33 Days
Daily |
|
| 02-Mar-20 12:00 | 09-Mar-20 16:00 | ATCO | RB | 7L60 (780s Lubicon - 827s Cranberry Lake) | test and treat pole change | 7.13 Days
Continuous |
|
| 02-Mar-20 12:15 | 05-Mar-20 17:45 | ALTALINK | Outage | 794L (157s Lac La Biche - 819s Whitby Lake) | replace components str's range 9-258 | 3.23 Days
Continuous |
|
| 02-Mar-20 12:15 | 05-Mar-20 17:45 | ATCO | RB | 7L794 | Alatlink work on 794L | 3.23 Days
Continuous |
|
| 02-Mar-20 12:15 | 05-Mar-20 17:45 | ATCO | IO | 7L794 | AltaLink doing work on 794L | 3.23 Days
Continuous |
|
| 03-Mar-20 07:30 | 06-Mar-20 16:30 | ALTALINK | RB | 158L (65s High River - 392s Black Diamond) | OPGW testing and splicing on | 3.38 Days
Daily |
|
| 03-Mar-20 08:00 | 16-Mar-20 16:00 | ATCO | Outage | 740s 507C (740s H.R.Milner) | replace breaker | 13.29 Days
Continuous |
|
| 03-Mar-20 08:30 | 05-Mar-20 17:00 | ATCO | Outage | 7L171 (802s Michichi Creek - 804s Wintering Hills) | clearance Mitigation | 2.35 Days
Continuous |
|
| 03-Mar-20 08:45 | 05-Mar-20 15:30 | ALTALINK | TE | 163S Amoco Empress | standard relay maintenance | 2.28 Days
Daily |
|
| 03-Mar-20 09:00 | 06-Mar-20 18:00 | SUNCOR | TE | 30EDD-1 | relay setting modifications | 3.38 Days
Continuous |
|
| 03-Mar-20 09:00 | 07-Mar-20 15:00 | ATCO | Outage | 7L32 (813s Little Smoky - 862s South Bezanson) | line mitigation | 4.25 Days
Continuous |
|
| 04-Mar-20 07:00 | 05-Mar-20 18:00 | ALTALINK | Outage | 172EL (139s Hillridge - 172EL1) | urgent structure 15- 121 conductor and damper repair | 1.46 Days
Continuous |
|
| 04-Mar-20 08:00 | 05-Mar-20 18:00 | ENMAX | Outage | 14.83L (ENMAX 14 - ENMAX 36), 14.2TR (ENMAX 14), 14.4TR (ENMAX 14), 14.1C (ENMAX 14), 14.2C (ENMAX 14) | switch maintenance | 1.42 Days
Continuous |
|
| 04-Mar-20 08:30 | 05-Mar-20 16:30 | ALTALINK | TE | 377s 34 (377s Hardisty), 703L (213s Hughenden - 703BL tap) | relay maintenance | 1.33 Days
Daily |
|
| 04-Mar-20 09:30 | 17-Mar-20 17:45 | ALTALINK | Outage | 174L (197s Bardo - 289s Saunders Lake) | rebuild structures | 13.3 Days
Continuous |
|
| 04-Mar-20 15:00 | 05-Mar-20 15:00 | ALTALINK | TE | 341s Sand Hills Sub RTU/SCADA | commission new status points | 24 Hours
Daily |
|
| 05-Mar-20 07:00 | 05-Mar-20 17:30 | ATCO | TE | 2075s 905 (2075s Newell), 2075s 904 (2075s Newell) | relay firmware upgrade | 10.5 Hours
Continuous |
|
| 05-Mar-20 07:00 | 05-Mar-20 17:30 | ATCO | TE | 2075s 918 (2075s Newell) | relay firmware upgrade | 10.5 Hours
Continuous |
|
| 05-Mar-20 07:30 | 05-Mar-20 16:00 | ALTALINK | Outage | 364s 3052 (364s Whitecourt Industrial) | maintenance | 8.5 Hours
Daily |
|
| 05-Mar-20 07:30 | 05-Mar-20 16:00 | ATCO | IO | whitecourt Industrial (AL) | AltaLink maintenance on 364s3052 | 8.5 Hours
Continuous |
|
| 05-Mar-20 08:00 | 06-Mar-20 17:00 | ATCO | TE | 7L104 (856s Kinosis - 989s Quigley) | relay testing | 1.38 Days
Continuous |
|
| 05-Mar-20 08:00 | 05-Mar-20 17:00 | ALTALINK | RB | 971L (154s Black Spruce - 762s Conklin) | urgent fire mitigation | 9 Hours
Daily |
|
| 05-Mar-20 08:30 | 05-Mar-20 16:30 | ALTALINK | TE | 776L (308s Albchem Beaverhill Creek - 410s Josephburg) | TPR maintenance. | 8 Hours
Daily |
|
| 05-Mar-20 08:30 | 06-Mar-20 17:00 | ATCO | TE | 9L100 (801s Anderson - 807s Sheerness) | relay testing | 1.35 Days
Continuous |
|
| 05-Mar-20 08:30 | 05-Mar-20 16:30 | ALTALINK | TE | 1212L (12s Heartland - 89s Ellerslie) | firmware upgrades | 8 Hours
Daily |
|
| 05-Mar-20 08:30 | 05-Mar-20 17:00 | ALTALINK | TE | 89s Ellerslie RTU/SCADA | update RTU | 8.5 Hours
Daily |
|
| 05-Mar-20 09:00 | 05-Mar-20 15:00 | ALTALINK | TE | 74S Janet | troubleshoot and correct DNP polling issues | 6 Hours
Daily |
|
| 05-Mar-20 09:00 | 06-Mar-20 15:00 | ATCO | TE | 834s 901T (834s Wesley Creek), 834s 902T (834s Wesley Creek), 834s Wesley Creek RTU/SCADA | RTU Upgrades and Changes | 30 Hours
Continuous |
|
| 05-Mar-20 09:00 | 05-Mar-20 13:00 | ALTALINK | TE | 452s T1 (452s B.F. Goodrich Fort Saskatchewan) | relay settings changes | 4 Hours
Daily |
|
| 05-Mar-20 09:00 | 05-Mar-20 15:00 | ALTALINK | IO | 121s Info Only | site visit for 121s Brooks P&C major 2020 scope | 6 Hours
Daily |
|
| 05-Mar-20 09:00 | 05-Mar-20 16:00 | ALTALINK | TE | 74s 2752 (74s Janet) | standard relay maintenance | 7 Hours
Daily |
|
| 05-Mar-20 09:00 | 05-Mar-20 13:00 | ALTALINK | Outage | 409s T2 (409s Shell Scotford) | remove CTs from system | 4 Hours
Continuous |
|
| 05-Mar-20 09:30 | 05-Mar-20 16:30 | ALTALINK | TE | 396s T1 (396s Pincher Creek) | perform standard relay maintenance | 7 Hours
Daily |
|
| 05-Mar-20 13:30 | 05-Mar-20 17:00 | ALTALINK | TE | 127s Bruderheim RTU/SCADA | SCADA updates | 3.5 Hours
Daily |
|
| 06-Mar-20 07:00 | 15-Mar-20 17:00 | ATCO | IO | 9L948 (650s Hansman Lake - 863s Paintearth) | AltaLink 948L component replacements | 9.38 Days
Continuous |
|
| 06-Mar-20 07:00 | 15-Mar-20 17:30 | ALTALINK | Outage | 948L (650s Hansman Lake - 863s Paintearth) | component replacements | 9.4 Days
Continuous |
|
| 06-Mar-20 07:00 | 15-Mar-20 18:00 | ATCO | RB | 9L27 (755s Cordel - 863s Paintearth) | AltaLink doing work on 948L | 9.42 Days
Continuous |
|
| 06-Mar-20 07:30 | 10-Mar-20 17:30 | ALTALINK | TE | 331s Ponoka RTU/SCADA | RTU update | 4.38 Days
Daily |
|
| 06-Mar-20 08:00 | 14-Mar-20 17:00 | ALTALINK | RB | 730L (197s Bardo - 730L61), 730L (285s East Camrose - 730L62), 732L (299s Kingman - 730L tap) | safety clearance due to work on 174L | 8.33 Days
Daily |
|
| 06-Mar-20 08:00 | 06-Mar-20 17:00 | EPCOR | Outage | Rossdale RR729 (Rossdale) | substation training | 9 Hours
Continuous |
|
| 06-Mar-20 08:00 | 12-Mar-20 17:00 | ALTALINK | RB | 1047L (574s Nilrem - 650s Hansman Lake) | maintenance work on 948L | 6.33 Days
Daily |
|
| 06-Mar-20 08:00 | 06-Mar-20 16:00 | ENMAX | Outage | 37.1TR (ENMAX 37) | hotspot 37.1TR south phase | 8 Hours
Continuous |
|
| 06-Mar-20 08:00 | 06-Mar-20 17:00 | ATCO | TE | 856S Kinosis | 7l183 relay testing | 9 Hours
Continuous |
|
| 06-Mar-20 10:00 | 09-Mar-20 17:00 | ALTALINK | RB | 161L (255s Vulcan - 504s Queenstown) | prep for OPGW installation for the Claresholm project | 3.25 Days
Daily |
|
| 06-Mar-20 11:00 | 06-Mar-20 16:00 | ATCO | RB | 9L57 (939s Livock - 960s Birchwood Creek) | high load move | 5 Hours
Continuous |
|
| 06-Mar-20 14:00 | 10-Mar-20 17:00 | ALTALINK | Outage | 331s T1 (331s Ponoka) | maintenance | 4.08 Days
Continuous |
|
| 07-Mar-20 08:00 | 11-Mar-20 17:00 | ATCO | RB | 7L82 (788s Hotchkiss - 855s Hamburg), 7L82 (853s Ring Creek - 855s Hamburg) | hot line pole changes | 4.33 Days
Continuous |
|
| 09-Mar-20 03:00 | 23-Mar-20 09:00 | ATCO | Outage | 859s 701T (859s Primrose) | maintenance | 14.25 Days
Continuous |
|
| 09-Mar-20 06:30 | 10-Mar-20 18:30 | ALTALINK | Outage | 202L (58s Edson - 178s Cynthia) | replace str # 521 | 1.5 Days
Continuous |
|
| 09-Mar-20 07:00 | 17-Apr-20 17:00 | EPCOR | Outage | 72JW19 (805s Jasper - Woodcroft), 805s J724 (805s Jasper), Woodcroft W721 (Woodcroft) | termination rebuild | 39.42 Days
Continuous |
|
| 09-Mar-20 07:00 | 10-Mar-20 17:00 | EPCOR | Outage | 805s C1 (805s Jasper), 805s J2408 (805s Jasper) | relay maintenance op-checks | 1.42 Days
Continuous |
|
| 09-Mar-20 07:00 | 14-Mar-20 17:00 | EPCOR | Outage | Genesee S/S 12TC1 outage, 330p 1201 (330p Genesee), 330p 1204 (330p Genesee), 330p 1207 (330p Genesee) | relay repair/maintenance op-checks | 5.42 Days
Continuous |
|
| 09-Mar-20 07:00 | 09-Apr-20 18:00 | ALTALINK | Outage | 890L (58s Edson - 207s Pinedale) | rebuilding a portion of 890L between Strs 2 and 27 | 31.46 Days
Continuous |
|
| 09-Mar-20 07:00 | 20-Mar-20 17:30 | ALTALINK | TE | 102s Langdon RTU/SCADA | adding line fault location | 11.44 Days
Daily |
|
| 09-Mar-20 07:00 | 20-Mar-20 17:30 | ALTALINK | TE | 102S Langdon | adding line fault location | 11.44 Days
Daily |
|
| 09-Mar-20 07:00 | 20-Mar-20 17:30 | ALTALINK | TE | 520s Bennett RTU/SCADA | adding line fault location for 1201L | 11.44 Days
Daily |
|
| 09-Mar-20 07:00 | 20-Mar-20 17:30 | ALTALINK | TE | 520s Bennett | adding line fault location for 1201L | 11.44 Days
Daily |
|
| 09-Mar-20 07:00 | 09-Mar-20 17:00 | EPCOR | Outage | 72RV6 (Rossdale - 511s Victoria), Rossdale RV722 (Rossdale) | relay maintenance op-checks | 10 Hours
Continuous |
|
| 09-Mar-20 07:00 | 19-Mar-20 17:00 | ALTALINK | TE | 275s Jenner RTU/SCADA | adding line fault location for 945L, 601L, 951L, 1002L and 944L | 10.42 Days
Daily |
|
| 09-Mar-20 07:00 | 19-Mar-20 17:00 | ALTALINK | TE | 275S Jenner | adding line fault location | 10.42 Days
Daily |
|
| 09-Mar-20 07:00 | 09-Mar-20 17:30 | ATCO | TE | 2075S Newell | ACF1 relay firmware upgrade | 10.5 Hours
Continuous |
|
| 09-Mar-20 07:00 | 09-Mar-20 17:30 | ATCO | TE | 2075s 900BS2 240kV bus ( 2075s Newell) | relay firmware upgrades | 10.5 Hours
Continuous |
|
| 09-Mar-20 07:30 | 12-Mar-20 17:30 | ALTALINK | TE | 650S Hansman Lake | adding line fault location | 3.42 Days
Daily |
|
| 09-Mar-20 07:30 | 12-Mar-20 17:30 | ALTALINK | TE | 650s Hansman Lake RTU/SCADA | adding line fault location for 1047L, 948L, & 966L | 3.42 Days
Daily |
|
| 09-Mar-20 07:30 | 12-Mar-20 17:30 | ATCO | IO | Hansman Lake (AL) | ALtalink work on 650s- RTU and relay
|
3.42 Days
Continuous |
|
| 09-Mar-20 08:00 | 10-Mar-20 18:00 | ENMAX | Outage | 11.83L | HV SW maint SW90, SW91, MD-11.83 | 1.42 Days
Continuous |
|
| 09-Mar-20 08:00 | 17-Mar-20 20:00 | SUNCOR | Outage | 29PL6-4 (836s Steepbank - 29EDD-1) | maintenance | 8.5 Days
Continuous |
|
| 09-Mar-20 08:00 | 12-Mar-20 17:00 | ATCO | Outage | 7L139 (707s St.Paul - 819s Whitby Lake) | crossarm and insulator change | 3.38 Days
Continuous |
|
| 09-Mar-20 08:00 | 12-Mar-20 17:00 | ALTALINK | TE | 535s Joffre RTU/SCADA | RTU update to add fault location on 330L1A, 330L2A & 889L | 3.38 Days
Daily |
|
| 09-Mar-20 08:00 | 10-Mar-20 16:00 | ENMAX | Outage | 32.2TR (ENMAX 32) | T-60 upgrade phase 2, check reversing switch, oil sampling 32.2TR MT, TC, bushing | 1.33 Days
Continuous |
|
| 09-Mar-20 08:00 | 10-Mar-20 16:00 | ENMAX | Outage | 27.1TR (ENMAX 27) | T-60 upgrade phase 2, check reversing switch | 1.33 Days
Continuous |
|
| 09-Mar-20 08:00 | 12-Mar-20 17:00 | ALTALINK | TE | 535S Joffre | testing fault locating on 330L1A, 330L2A & 889L relays | 3.38 Days
Daily |
|
| 09-Mar-20 08:00 | 09-Mar-20 16:00 | ALTALINK | TE | 131s Moon Lake RTU/SCADA | upgrade MPLS node | 8 Hours
Daily |
|
| 09-Mar-20 08:00 | 13-Mar-20 16:00 | ENMAX | TE | ENMAX 47 | auto-switching protection relay testing | 4.33 Days
Continuous |
|
| 09-Mar-20 08:00 | 09-Mar-20 16:00 | ENMAX | TE | ENMAX 8 | installation of new switchgear and protection on 138 kV ring - 3.82L | 8 Hours
Continuous |
|
| 09-Mar-20 08:00 | 11-Mar-20 16:00 | ALTALINK | TE | 64s East Crossfield RTU/SCADA | upgrade MPLS node | 2.33 Days
Daily |
|
| 09-Mar-20 08:00 | 09-Mar-20 16:00 | ENMAX | Outage | 3.82L (ENMAX 3 - ENMAX 8) | remove scaffolding at 8 sub | 8 Hours
Continuous |
|
| 09-Mar-20 08:00 | 12-Mar-20 17:00 | ALTALINK | TE | AltaLink Radio Tower | 9516R Tomahawk - upgrade MPLS node | 3.38 Days
Daily |
|
| 09-Mar-20 08:15 | 12-Mar-20 15:50 | ALTALINK | Outage | 50L (44s Bearspaw Plant - ENMAX 21) | de-energized due to PT replacement at ENMAX 21 | 3.32 Days
Continuous |
|
| 09-Mar-20 08:15 | 12-Mar-20 15:50 | ENMAX | IO | Altalink outage. 50L | 138kV PT replacement | 3.32 Days
Continuous |
|
| 09-Mar-20 08:30 | 12-Mar-20 15:30 | ENMAX | IO | ENMAX 21 SW83 (ENMAX 21) | PT replacement | 3.29 Days
Continuous |
|
| 09-Mar-20 08:30 | 12-Mar-20 15:30 | ENMAX | Outage | ENMAX 21 SW83 (ENMAX 21) | PT replacement | 3.29 Days
Continuous |
|
| 09-Mar-20 09:00 | 19-Mar-20 16:00 | ALTALINK | TE | 74s Janet RTU/SCADA | install new configuration in RTUs to allow for changes associated to 901L upgrade | 10.29 Days
Daily |
|
| 09-Mar-20 09:00 | 19-Mar-20 16:00 | ALTALINK | TE | 64s East Crossfield RTU/SCADA | install new configuration in RTUs to allow for changes associated to 901L upgrade | 10.29 Days
Daily |
|
| 09-Mar-20 09:00 | 19-Mar-20 16:00 | ALTALINK | TE | 63s Red Deer RTU/SCADA | install new configuration in RTUs to allow for changes associated to 901L upgrade | 10.29 Days
Daily |
|
| 09-Mar-20 09:00 | 12-Mar-20 17:00 | ALTALINK | TE | 28s West Brooks RTU/SCADA | SCADA configurations update to cutover to new redundant SG4250’s | 3.33 Days
Continuous |
|
| 09-Mar-20 09:00 | 09-Mar-20 14:30 | EPCOR | Outage | Kennedale KAB1 (Kennedale), 72CK13 (987s Clover Bar - Kennedale) | repairs to disconnect switch | 5.5 Hours
Continuous |
|
| 09-Mar-20 09:00 | 12-Mar-20 18:00 | EPCOR | RB | 805S Jasper | 1045L RB - Altalink work adjacent to 909L | 3.38 Days
Continuous |
|
| 09-Mar-20 09:00 | 09-Mar-20 16:00 | ATCO | TE | 743S Sarah Lake | relay testing - 7L172 | 7 Hours
Continuous |
|
| 09-Mar-20 09:00 | 10-Mar-20 16:00 | ATCO | TE | 729S Otauwau | relay testing - 7L49 | 31 Hours
Continuous |
|
| 09-Mar-20 09:30 | 12-Mar-20 17:30 | ALTALINK | RB | 185L (379s Shell Canada Waterton - 415s Drywood), 185AL (415s Drywood - 995s Yarrow) | structure replacements 8-39 | 3.33 Days
Daily |
|
| 09-Mar-20 09:30 | 11-Mar-20 17:00 | ALTALINK, EPCOR | Outage | 909L (89s Ellerslie - 665s Dome), 665s TX1 (665s Dome) | relay maintenance | 2.31 Days
Continuous |
|
| 09-Mar-20 09:30 | 12-Mar-20 17:30 | ALTALINK, EPCOR | RB | 909L (310p Sundance - 665s Dome) | 909L - live line work for maintenance | 3.33 Days
Continuous |
|
| 09-Mar-20 09:30 | 12-Mar-20 17:30 | ALTALINK, EPCOR | RB | 909L (89s Ellerslie - 665s Dome) | components/structure replacements (Structures #59, 60, 61, 79, 80, 81, 151) | 3.33 Days
Daily |
|
| 09-Mar-20 09:30 | 11-Mar-20 17:00 | ALTALINK | IO | 909L (89s-E665)Advice for EPCOR | Epcor: Outage to TX#1 required for relay mtce op-checks and installation of new 240 KV breaker. | 2.31 Days
Continuous |
|
| 09-Mar-20 09:30 | 12-Mar-20 17:30 | ALTALINK, EPCOR | RB | 1044L (805s Jasper - 816s Petrolia) | crews working on parallel 909L | 3.33 Days
Daily |
|
| 09-Mar-20 09:30 | 12-Mar-20 17:30 | ALTALINK, EPCOR | RB | 1045L (310p Sundance - 320p Keephills - 805s Jasper) | crews working on parallel 909L | 3.33 Days
Daily |
|
| 09-Mar-20 11:30 | 09-Mar-20 16:30 | ALTALINK | TE | 74S Janet | standard relay maintenance | 5 Hours
Daily |
|
| 09-Mar-20 11:45 | 09-Mar-20 17:00 | ALTALINK | TE | 17S Benalto | standard relay maintenance | 5.25 Hours
Daily |
|
| 09-Mar-20 12:15 | 12-Mar-20 17:45 | ALTALINK | Outage | 728L (353s Plamondon - 405s Waupisoo) | components replacement | 3.23 Days
Continuous |
|
| 09-Mar-20 12:30 | 09-Mar-20 16:30 | ALTALINK | TE | 106s Paddle River RTU/SCADA | update RTU to replace HMI T1 metering | 4 Hours
Daily |
|
| 09-Mar-20 12:45 | 09-Mar-20 16:30 | ALTALINK | TE | 504S Queenstown | standard relay maintenance | 3.75 Hours
Daily |
|
| 09-Mar-20 14:00 | 10-Mar-20 16:00 | ALTALINK | TE | 650S Hansman Lake | relay maintenance | 26 Hours
Daily |
|
| 10-Mar-20 07:00 | 11-Mar-20 19:30 | ALTALINK | Outage | 535s T3 (535s Joffre) | replace 25kV feeder cables & switching cubicle on 297L1 | 1.52 Days
Continuous |
|
| 10-Mar-20 07:30 | 11-Mar-20 17:30 | ALTALINK | TE | 367s Harry Smith RTU/SCADA | update RTU configuration to add new battery monitoring alarm | 1.42 Days
Daily |
|
| 10-Mar-20 07:30 | 11-Mar-20 17:30 | ALTALINK | TE | 108s Amelia RTU/SCADA | update RTU configuration to add new battery monitoring alarm | 1.42 Days
Daily |
|
| 10-Mar-20 08:00 | 12-Mar-20 16:00 | ATCO | Outage | 7L46 | Raise Structures for Line mitigation, Associated with 7L45 HOP # 2-51167 | 2.33 Days
Continuous |
|
| 10-Mar-20 08:00 | 11-Mar-20 16:00 | CMH | Outage | MH-10L (MH69s2 North Industrial - MHS8 Burnside) | install a transformer that will be in proximity to the 10L line | 1.33 Days
Continuous |
|
| 10-Mar-20 08:00 | 10-Mar-20 16:00 | ENMAX | TE | ENMAX 8 | installation of new switchgear and protection on 138 kV ring | 8 Hours
Continuous |
|
| 10-Mar-20 08:00 | 12-Mar-20 16:00 | ATCO | RB | 7L45 (813s Little Smoky - 845s Big Mountain) | raise structures for mitigation, associated with 7L46 outage | 2.33 Days
Daily |
|
| 10-Mar-20 08:30 | 10-Mar-20 15:30 | ATCO | TE | 729S Otauwau | 144 kV breaker relays testing | 7 Hours
Continuous |
|
| 10-Mar-20 08:30 | 10-Mar-20 17:00 | SHELL | IO | 402S Shell Aosp1 | notice of Altalink working on site at 402s
|
8.5 Hours
Continuous |
|
| 10-Mar-20 08:30 | 10-Mar-20 12:30 | ALTALINK | TE | 906s Ross Creek RTU/SCADA | update RTU to remove T1 & T2 qualitrol trips | 4 Hours
Daily |
|
| 10-Mar-20 08:30 | 10-Mar-20 16:30 | ALTALINK | TE | 132S Ware Junction | relay firmware upgrades | 8 Hours
Daily |
|
| 10-Mar-20 08:30 | 10-Mar-20 16:30 | ALTALINK | TE | 370s North Lethbridge RTU/SCADA | SCADA updates for qualitrol & winding temp trips being removed | 8 Hours
Daily |
|
| 10-Mar-20 08:30 | 12-Mar-20 16:30 | ALTALINK | TE | 370S North Lethbridge | standard relay maintenance | 2.33 Days
Daily |
|
| 10-Mar-20 09:00 | 10-Mar-20 17:00 | ALTALINK | TE | 964s Pigeon Lake RTU/SCADA | RTU update | 8 Hours
Daily |
|
| 10-Mar-20 09:00 | 10-Mar-20 15:00 | ALTALINK | TE | 255S Vulcan | UR card replacement | 6 Hours
Daily |
|
| 10-Mar-20 09:00 | 10-Mar-20 16:30 | ALTALINK | TE | 500S Flatbush | relay maintenance | 7.5 Hours
Daily |
|
| 10-Mar-20 13:00 | 10-Mar-20 17:00 | ATCO | TE | ATCO Radio Tower | update firmware | 4 Hours
Continuous |
|
| 10-Mar-20 13:30 | 10-Mar-20 16:30 | ALTALINK | TE | 422s Westwood RTU/SCADA | update RTU to remove T1 qualitrol trips | 3 Hours
Daily |
|
| 11-Mar-20 07:00 | 11-Mar-20 11:00 | EPCOR | Outage | 805s J2403 (805s Jasper) | relay maintenance op-checks | 4 Hours
Continuous |
|
| 11-Mar-20 07:30 | 11-Mar-20 19:00 | ATCO | Outage | 756s 601T (756s Bigfoot), 6L08 (756s Bigfoot - 757s Battle River), 756S Bigfoot | 756S 601T salvage, 500SST1 install and relocate station service transformer | 11.5 Hours
Continuous |
|
| 11-Mar-20 07:30 | 11-Mar-20 18:00 | Syncrude | TE | Syncrude loss of visibility | SCADA update | 10.5 Hours
Daily |
|
| 11-Mar-20 07:30 | 11-Mar-20 17:30 | ALTALINK | TE | 42s Sarcee RTU/SCADA | RTU database update | 10 Hours
Daily |
|
| 11-Mar-20 07:30 | 11-Mar-20 17:30 | ALTALINK | TE | 39s Bickerdike RTU/SCADA | RTU database update | 10 Hours
Daily |
|
| 11-Mar-20 08:00 | 12-Mar-20 16:00 | ENMAX | Outage | 32.1TR (ENMAX 32) | T-60 upgrade phase 2 | 1.33 Days
Continuous |
|
| 11-Mar-20 08:00 | 12-Mar-20 16:00 | ENMAX | Outage | 27.2TR (ENMAX 27) | T-60 upgrade phase 2, check reversing switch | 1.33 Days
Continuous |
|
| 11-Mar-20 08:00 | 12-Mar-20 15:00 | ENMAX | Outage | 23.4TR (ENMAX 23) | hotspot, 23 sub Sw3 (South phase), EPSC installing SSTR23-1, which will be energized on return | 31 Hours
Continuous |
|
| 11-Mar-20 08:00 | 12-Mar-20 16:00 | ENMAX | Outage | 23.4TR (ENMAX 23) | tapchanger inspection check reversing switch oil sampling MT, TC. gas relay testing | 1.33 Days
Continuous |
|
| 11-Mar-20 08:00 | 12-Mar-20 17:00 | ATCO | TE | 856S Kinosis | relay testing - 7L15 | 1.38 Days
Continuous |
|
| 11-Mar-20 08:00 | 11-Mar-20 16:00 | ALTALINK | TE | AltaLink Radio Tower, 635s Rose Valley RTU/SCADA | 9653R - upgrade MPLS node | 8 Hours
Daily |
|
| 11-Mar-20 08:00 | 12-Mar-20 14:30 | ALTALINK | TE | 648S Metiskow | standard relay maintenance | 30.5 Hours
Daily |
|
| 11-Mar-20 08:30 | 11-Mar-20 15:30 | ATCO | TE | 743S Sarah Lake | relay testing - 7L67 | 7 Hours
Continuous |
|
| 11-Mar-20 08:30 | 12-Mar-20 16:00 | ATCO | TE | 729S Otauwau | relay testing - 7L162 | 31.5 Hours
Continuous |
|
| 11-Mar-20 08:30 | 11-Mar-20 16:30 | ALTALINK | TE | 405s Waupisoo RTU/SCADA | SCADA updates for qualitrol & winding temp trips being removed | 8 Hours
Daily |
|
| 11-Mar-20 08:30 | 11-Mar-20 16:30 | ALTALINK | TE | 28S West Brooks | standard relay maintenance | 8 Hours
Daily |
|
| 11-Mar-20 08:30 | 11-Mar-20 12:30 | ALTALINK | TE | 310P Sundance | standard relay maintenance | 4 Hours
Daily |
|
| 11-Mar-20 08:30 | 11-Mar-20 16:03 | ALTALINK | TE | 405S Waupisoo | add IRIG to the relays | 7.55 Hours
Daily |
|
| 11-Mar-20 08:30 | 11-Mar-20 17:00 | ALTALINK | TE | 17s Benalto RTU/SCADA | SCADA updates for qualitrol & winding temp trips being removed, relay update | 8.5 Hours
Daily |
|
| 11-Mar-20 10:30 | 11-Mar-20 16:30 | ALTALINK | TE | 409S Shell Scotford | standard relay maintenance | 6 Hours
Daily |
|
| 11-Mar-20 10:30 | 11-Mar-20 16:30 | ALTALINK | TE | 409s Shell Scotford RTU/SCADA | SCADA updates for qualitrol & winding temp trips being removed | 6 Hours
Daily |
|
| 11-Mar-20 12:00 | 11-Mar-20 17:00 | EPCOR | Outage | 805s J2404 (805s Jasper) | relay maintenance op-checks | 5 Hours
Continuous |
|
| 11-Mar-20 13:00 | 11-Mar-20 16:30 | ALTALINK | TE | 2739S Wabamun | standard relay maintenance | 3.5 Hours
Daily |
|
| 12-Mar-20 07:00 | 12-Mar-20 11:00 | EPCOR | Outage | 805s J2405 (805s Jasper) | relay maintenance op-checks | 4 Hours
Continuous |
|
| 12-Mar-20 07:30 | 12-Mar-20 17:30 | ALTALINK | TE | 522s Cooking Lake RTU/SCADA | update RTU configuration | 10 Hours
Daily |
|
| 12-Mar-20 08:00 | 13-Mar-20 17:00 | ATCO | TE | 856S Kinosis, 856s 901 (856s Kinosis), 856s 904 (856s Kinosis) | relay testing | 1.38 Days
Continuous |
|
| 12-Mar-20 08:00 | 12-Mar-20 16:00 | ALTALINK | TE | 325s Leduc RTU/SCADA | upgrade MPLS node | 8 Hours
Daily |
|
| 12-Mar-20 08:30 | 12-Mar-20 16:30 | ALTALINK | TE | 17S Benalto | standard relay maintenance | 8 Hours
Continuous |
|
| 12-Mar-20 08:30 | 12-Mar-20 16:00 | ALTALINK | TE | 159s T1 (159s Colinton) | protection outage | 7.5 Hours
Daily |
|
| 12-Mar-20 08:30 | 12-Mar-20 16:30 | ALTALINK | TE | 13S Deerland | add IRIG to L10 & L12 protections | 8 Hours
Daily |
|
| 12-Mar-20 08:30 | 12-Mar-20 16:30 | ALTALINK | TE | 13S Deerland | relay maintenance | 8 Hours
Daily |
|
| 12-Mar-20 08:30 | 12-Mar-20 16:00 | ALTALINK | TE | 159S Colinton | add IRIG | 7.5 Hours
Daily |
|
| 12-Mar-20 08:30 | 12-Mar-20 16:00 | ALTALINK | TE | 159s Colinton RTU/SCADA | investigate T1 metering inaccuracy | 7.5 Hours
Daily |
|
| 12-Mar-20 08:30 | 12-Mar-20 16:30 | ATCO | IO | Deerland (AL) | Altalink Job Scope: Protection outage required for techs to wire-in separate IRIG circuits for the relays listed below. :
L10 A Protection 9L961 A21/L10 7SA522 L12 A Protection 9L960 A21/L12 7SA522 |
8 Hours
Continuous |
|
| 13-Mar-20 05:30 | 31-Mar-20 18:30 | ALTALINK | RB | 551L (123s Banff - 953s Lake Louise) | power line construction, excavation with track hoes, live line cutovers | 18.54 Days
Daily |
|
| 13-Mar-20 07:00 | 13-Mar-20 11:00 | EPCOR | Outage | 805s J2406 (805s Jasper) | relay maintenance | 4 Hours
Continuous |
|
| 13-Mar-20 08:00 | 17-Mar-20 10:00 | ATCO | RB | 7L46 (813s Little Smoky - 845s Big Mountain) | raise structures for mitigation, associated with 7L45 outage | 4.08 Days
Continuous |
|
| 13-Mar-20 08:00 | 17-Mar-20 16:00 | ATCO | Outage | 7L45 (798s Bridge Creek - 813s Little Smoky) | maintnance | 4.33 Days
Continuous |
|
| 13-Mar-20 09:00 | 13-Mar-20 13:00 | ALTALINK | Outage | 409s T1 (409s Shell Scotford) | remove CTs from system | 4 Hours
Continuous |
|
| 13-Mar-20 10:00 | 14-Mar-20 16:00 | ATCO | Outage | 7L101 (790s Poplar Hill - 944s Lowe Lake) | test relays | 30 Hours
Continuous |
| This document and the information contained herein are based upon information and data which by their nature contain a degree of uncertainty and are subject to change. In addition, this document may contain information and data from public sources and/or third parties, which have been assumed to be accurate and complete and have not been verified. Accordingly, the Independent System Operator, operating as the Alberta Electric System Operator (the "AESO") makes no warranty, representation or guarantee, express or implied, with respect to this document or the information contained herein, including, but not limited to, any warranty, representation or guarantee of accuracy, completeness, timeliness, reliability, availability, absence of computer virus, non- infringement, merchantability or suitability for any purpose. Under no circumstances will the AESO, its members, officers, employees, contractors or agents, or any of their respective affiliates, be liable for any errors or omissions in, or any losses, damages or claims whatsoever, whether in contract, tort or otherwise, arising from use of or reliance upon, this document or any information contained herein. © 2009 Alberta Electric System Operator. All rights reserved |