| Alberta Electric System Operator | |
| System Co-ordination Plan | |
| 2019-01-12 to 2019-01-18 | |
| Approved Outages |
| Previous Version | |
| Download CSV |
| From | To | Owner | Type | Element | Scheduled Activity | Date/Time Comments | Interconnection |
|---|---|---|---|---|---|---|---|
| 27-Aug-18 07:00 | 15-Jan-19 17:00 | EPCOR | TE | Woodcroft | substation automation upgrade | 141.46 Days
Daily |
|
| 18-Sep-18 08:00 | 31-Mar-19 17:00 | ALTALINK, EPCOR | TE | 920L (71s Lamoureux - 557s Castle Downs) | performing settings updates | 194.38 Days
Daily |
|
| 18-Sep-18 18:00 | 31-Mar-19 18:00 | ALTALINK | Outage | 221s T3 (221s Sunken Lake) | transformer removal | 194 Days
Continuous |
|
| 24-Sep-18 08:00 | 28-Feb-19 15:00 | ATCO | TE | 709s Vegreville RTU/SCADA | new RTU download and test | 157.33 Days
Continuous |
|
| 25-Sep-18 08:00 | 15-Jan-19 17:00 | EPCOR | TE | 511s Victoria T1 (511s Victoria),511s Victoria T2 (511s Victoria) | update relay settings | 112.42 Days
Continuous |
|
| 04-Oct-18 09:00 | 31-Mar-19 20:00 | Syncrude | Outage | Mildred T3 (Syncrude Mildred Lake) | damaged transformer repairs | 178.46 Days
Continuous |
|
| 05-Oct-18 08:00 | 30-Jun-19 16:00 | EPCOR | Outage | Rossdale C2 (Rossdale) | forced outage | 268.33 Days
Continuous |
|
| 24-Oct-18 01:13 | 30-Jun-19 16:00 | EPCOR | Outage | Rossdale C1 (Rossdale) | forced outage | 249.62 Days
Continuous |
|
| 03-Nov-18 07:00 | 01-Mar-19 17:00 | EPCOR | Outage | 72CN10 (987s Clover Bar - Namao) | termination rebuild | 118.46 Days
Continuous |
|
| 06-Nov-18 08:00 | 28-Feb-19 16:00 | ALTALINK | Outage | 267s C3 (267s Killarney Lake) | forced out of service | 114.33 Days
Continuous |
|
| 07-Nov-18 08:00 | 31-Jan-19 17:00 | ATCO | IO | 951S Thickwood Hills | construction work on 951S 900BS2 and allow energization of 951S 900BS1 | 85.38 Days
Continuous |
|
| 17-Nov-18 08:00 | 11-Feb-19 16:00 | ENMAX | Outage | ENMAX 22 | partial 138 kV bus outage for construction of new 138kV PT at 22sub | 86.33 Days
Continuous |
|
| 21-Nov-18 08:00 | 15-Feb-19 18:00 | ENMAX | Outage | 36.5TR (ENMAX 36),16.63L (ENMAX 16 - ENMAX 36) | replace 36.5TR | 86.42 Days
Continuous |
|
| 21-Nov-18 12:00 | 15-Jan-19 17:00 | ATCO | IO | 951S 900BS2 | construction COG to continue work on 951S SVC and allow energization of 951S 900BS2 | 55.21 Days
Continuous |
|
| 27-Nov-18 07:00 | 30-May-19 17:00 | EPCOR | TE | 72CN10 (987s Clover Bar - Namao) | protection upgrade | 184.38 Days
Continuous |
|
| 08-Dec-18 08:00 | 20-Jan-19 16:00 | ENMAX | TE | ENMAX 37 | decommission old U/F relays, UF protection will be resorted as each feeder relay comes on line | 43.33 Days
Continuous |
|
| 11-Dec-18 09:00 | 19-Jan-19 16:30 | ATCO | TE | 828S Sulphur Point | 87B/700BS1 relocate CT grounding, 87B/700BS1 relay OOS | 39.31 Days
Continuous |
|
| 11-Dec-18 10:00 | 19-Jan-19 16:30 | ATCO | TE | 828s 701T (828s Sulphur Point) | relay replacement | 39.27 Days
Continuous |
|
| 13-Dec-18 09:30 | 19-Jan-19 17:30 | ATCO | TE | 828s Sulphur Point RTU/SCADA | update RTU | 37.33 Days
Continuous |
|
| 16-Dec-18 08:00 | 20-Jan-19 13:00 | ATCO | TE | 6L126 (515L tap - 743s Sarah Lake) | place 6L126 in normal/alternate settings for Altalink work on 6L126/526L | 35.21 Days
Continuous |
|
| 18-Dec-18 07:00 | 19-Jan-19 08:00 | ALTALINK | Outage | 526L(526L190 - 526L208) | creating temporary Open Point 'E' between structures #215 & 216 | 32.04 Days
Daily |
|
| 18-Dec-18 08:00 | 19-Jan-19 17:00 | ATCO | IO | 6L126 (515L tap - 743s Sarah Lake) | AltaLink requires and advice on 6L126 | 32.38 Days
Continuous |
|
| 02-Jan-19 05:30 | 31-Mar-19 18:00 | ALTALINK | RB | 551L (123s Banff - 953s Lake Louise) | line rebuild | 88.48 Days
Daily |
|
| 03-Jan-19 08:00 | 24-Feb-19 18:00 | ENMAX | Outage | 7.2TR (ENMAX 7) | remove old 7.2TR and install new 7.2TR | 52.42 Days
Continuous |
|
| 05-Jan-19 07:00 | 18-Jan-19 18:00 | ATCO | RB | 9L10 (876s Brintnell - 939s Livock) | new 500 kv line construction parallel to 9L10 | 13.46 Days
Continuous |
|
| 07-Jan-19 07:00 | 14-Jan-19 13:00 | ALTALINK | Outage | 1046L (310p Sundance - 338s Cherhill),902L (19s Wabamun - 310p Sundance),310p 1052 (310p Sundance),310p 1152 (310p Sundance),310p 752 (310p Sundance),310p 852 (310p Sundance) | re-route 1046L temporarily onto 902L by creating Open Point 'B' & 'C' and jumper 1046L to 902L to accommodate structure repairs | 7.25 Days
Continuous |
|
| 07-Jan-19 07:30 | 13-Jan-19 17:00 | EPCOR | Outage | 805s C1 (805s Jasper),805s T1 (805s Jasper),72JM18 (805s Jasper - Meadowlark),72JW19 (805s Jasper - Woodcroft) | metering cutover | 6.4 Days
Continuous |
|
| 07-Jan-19 07:30 | 28-Feb-19 17:00 | EPCOR | TE | 330P Genesee RTU/SCADA | maintenance | 52.4 Days
Daily |
|
| 07-Jan-19 07:30 | 28-Feb-19 17:00 | EPCOR | TE | 330P Genesee | relay maintenance | 52.4 Days
Daily |
|
| 07-Jan-19 07:30 | 28-Feb-19 17:00 | EPCOR | TE | 657S Summerside | relay maintenance | 52.4 Days
Daily |
|
| 07-Jan-19 07:30 | 28-Feb-19 17:00 | EPCOR | TE | 665S Dome | relay maintenance | 52.4 Days
Daily |
|
| 07-Jan-19 07:30 | 28-Feb-19 17:00 | EPCOR | TE | 814S Bellamy | relay maintenance | 52.4 Days
Daily |
|
| 07-Jan-19 08:00 | 18-Jan-19 16:00 | ATCO | TE | 754s Ksituan River RTU/SCADA | PLC replacement & pre-commissioning | 11.33 Days
Continuous |
|
| 08-Jan-19 07:00 | 15-Jan-19 17:00 | ATCO | Outage | 7L73 (829s Boucher Creek - 800s Friedenstal),800s 702 (800s Friedenstal) | upgrade 7L73 protection and install TPR and new RAS | 7.42 Days
Continuous |
|
| 08-Jan-19 07:00 | 18-Jan-19 17:00 | ATCO | RB | 9L57 (939s Livock - 960s Birchwood Creek) | 500kv line construction in close proximity of 9L57 | 10.42 Days
Daily |
|
| 08-Jan-19 08:00 | 22-Jan-19 17:00 | ALTALINK | RB | 1034L (244s Bowmanton - 324s Cassils) | working within close proximity on adjacent line | 14.38 Days
Daily |
|
| 08-Jan-19 08:00 | 14-Jan-19 16:00 | ALTALINK | IO | 38.83L Enmax - Info | insulator and conductor replacement | 6.33 Days
Continuous |
|
| 10-Jan-19 07:00 | 22-Jan-19 18:00 | ATCO, ALTALINK | Outage | 1035L (2075s Newell - 244s Bowmanton) | component replacements | 12.46 Days
Continuous |
|
| 10-Jan-19 08:00 | 14-Jan-19 16:00 | ENMAX | Outage | 38.83L (ENMAX 39 - ENMAX 38) | insulator and conductor replacement | 4.33 Days
Continuous |
|
| 10-Jan-19 08:00 | 26-Feb-19 16:00 | ATCO | TE | 800S Friedenstal | implement new bus lockout relay | 47.33 Days
Continuous |
|
| 11-Jan-19 09:00 | 14-Jan-19 17:00 | ALTALINK | RB | 887L (48s Pocaterra - BCH Britt Creek) | BCH work | 3.33 Days
Daily |
|
| 12-Jan-19 08:00 | 13-Jan-19 16:00 | ENMAX | Outage | 39.1TR (ENMAX 39),39.3TR (ENMAX 39) | 38.83L insulator & conductor replacement | 1.33 Days
Continuous |
|
| 12-Jan-19 08:00 | 31-Jan-19 17:00 | ATCO | TE | 800s Friedenstal RTU/SCADA | update & download PLC | 19.38 Days
Continuous |
|
| 14-Jan-19 06:00 | 14-Jan-19 18:00 | ALTALINK, FORTIS | Outage | 1020s Exshaw Extension,985s 811QC04 (985s Exshaw) | maintenance | 12 Hours
Continuous |
|
| 14-Jan-19 07:00 | 31-Mar-19 18:00 | ALTALINK | Outage | 13L/158L (65s High River - 392s Black Diamond) | phase 2 & 3 rebuilding 13L line from Structures #1 - 16 and rebuilding 158L line from Structures #4 - 53 | 76.42 Days
Continuous |
|
| 14-Jan-19 07:30 | 18-Jan-19 18:30 | ALTALINK | IO | 9L59 (A972s - A801s) ATCO Info | 9L59- GOI permit for Clearance Mitigation | 4.46 Days
Continuous |
|
| 14-Jan-19 08:00 | 18-Jan-19 18:00 | ATCO, GREENGATEP | Outage | 9L59 (972s Tinchebray - 801s Anderson),9L59D1 (801s Anderson),9L59D2 (972s Tinchebray) | 9L59 - GOI permit for clearance mitigation | 4.42 Days
Continuous |
|
| 14-Jan-19 08:00 | 20-Jan-19 16:00 | ENMAX | Outage | 37.2TR (ENMAX 37) | 37s RTU replacement | 6.33 Days
Continuous |
|
| 14-Jan-19 08:00 | 16-Jan-19 16:00 | ENMAX | Outage | 3.3TR (ENMAX 3) | T-60 relay CPU upgrade. test HV CTs | 2.33 Days
Continuous |
|
| 14-Jan-19 08:00 | 15-Jan-19 18:00 | ENMAX | Outage | 6.4TR (ENMAX 6),6.80L (ENMAX 35 - ENMAX 6) | switch maintenance and check reversing switch | 1.42 Days
Continuous |
|
| 14-Jan-19 08:00 | 18-Jan-19 16:00 | ENMAX | TE | ENMAX 11 RTU/SCADA | upgrade RTU | 4.33 Days
Daily |
|
| 14-Jan-19 08:00 | 14-Jan-19 18:00 | ENMAX | Outage | 11.4TR (ENMAX 11) | RTU upgrade | 10 Hours
Continuous |
|
| 14-Jan-19 08:00 | 14-Jan-19 12:00 | ATCO | TE | 769s Stettler RTU/SCADA | replace RTU power supply | 4 Hours
Continuous |
|
| 14-Jan-19 08:00 | 15-Jan-19 19:00 | ALTALINK | TE | 252s Jarrow RTU/SCADA | RTU upgrade | 1.46 Days
Daily |
|
| 14-Jan-19 08:00 | 08-Feb-19 14:00 | ALTALINK | Outage | 551L (945s Sunshine Village - 953s Lake Louise) | place 551JL tap loads on temp genset to string bypass | 25.25 Days
Continuous |
|
| 14-Jan-19 09:00 | 18-Jan-19 16:00 | ALTALINK | TE | 310P Sundance RTU/SCADA | update RTU configuration | 4.29 Days
Daily |
|
| 14-Jan-19 09:30 | 17-Jan-19 17:00 | ALTALINK | Outage | 254s 2162X (254s Coaldale) | disconnect old cables and connect new cables | 3.31 Days
Continuous |
|
| 14-Jan-19 12:00 | 28-Feb-19 13:00 | ALTALINK | Outage | 902L (310p - Open Point 'A') - GOI | CANA has requested that his portion of 902L remain under a separate GOI zone to prevent mis-coordination | 45.04 Days
Continuous |
|
| 14-Jan-19 12:00 | 21-Jan-19 12:00 | ATCO | Outage | 7L61 (780s Lubicon - 796s Nipisi) | replace/repair transmission poles | 7 Days
Continuous |
|
| 14-Jan-19 13:00 | 28-Feb-19 14:00 | ALTALINK | Outage | 1046L (Open Point 'B' - Open Point 'C') | Replacing Structures #11 & 12 | 45.04 Days
Continuous |
|
| 14-Jan-19 13:00 | 17-Jan-19 16:30 | ALTALINK | TE | 1046L (310p Sundance - 338s Cherhill) | CANA will remove the A21 from service to upgrade firmware and install permanent settings | 3.15 Days
Daily |
|
| 15-Jan-19 07:30 | 18-Jan-19 17:30 | ALTALINK | RB | 825L (484s Millar Western - 77s Sagitawah) | component replacements (str's range 1A-75) | 3.42 Days
Continuous |
|
| 15-Jan-19 08:00 | 17-Jan-19 16:00 | ATCO | Outage | 827s SVC (827s Cranberry Lake) | UPS replacement @ 827S Cranberry SVC outage to replace 5KVA DC/AC inverter |
2.33 Days
Continuous |
|
| 15-Jan-19 08:00 | 18-Jan-19 16:00 | ENMAX | TE | ENMAX 14 RTU/SCADA | upgrade RTU | 3.33 Days
Daily |
|
| 15-Jan-19 08:00 | 15-Jan-19 16:00 | ENMAX | Outage | 14.1C (ENMAX 14),14.2C (ENMAX 14) | RTU upgrade | 8 Hours
Continuous |
|
| 15-Jan-19 08:00 | 15-Jan-19 16:00 | ENMAX | TE | ENMAX 14 138kV Bus 1,ENMAX 14 138kV Bus 2 | RTU upgrade | 8 Hours
Continuous |
|
| 15-Jan-19 08:00 | 15-Jan-19 18:00 | ENMAX | Outage | 11.3TR (ENMAX 11) | RTU upgrade | 10 Hours
Continuous |
|
| 15-Jan-19 08:00 | 15-Jan-19 12:00 | ENMAX | Outage | 22.1TR (ENMAX 22) | construction for 138kV BT at 22sub | 4 Hours
Continuous |
|
| 15-Jan-19 08:00 | 15-Jan-19 16:00 | ATCO | TE | ATCO Radio Tower | moving T1 DSX jackfields to new location | 8 Hours
Continuous |
|
| 15-Jan-19 08:00 | 16-Jan-19 17:00 | ALTALINK | TE | 149s Nisku RTU/SCADA | RTU outage for new point addition | 1.38 Days
Daily |
|
| 15-Jan-19 08:30 | 15-Jan-19 16:00 | ALTALINK | TE | 20S Ghost | standard relay maintenance | 7.5 Hours
Daily |
|
| 15-Jan-19 08:30 | 17-Jan-19 16:30 | ALTALINK | TE | 198S Blackfalds | perform standard relay maintenance | 2.33 Days
Daily |
|
| 15-Jan-19 09:00 | 15-Jan-19 15:00 | ATCO | TE | ATCO's system operations centre | cutover the SCADA servers and telecom circuits to the new ECC and operate off of the new ECC equipment from the SOC for a couple of hours | 6 Hours
Continuous |
|
| 15-Jan-19 10:00 | 15-Jan-19 11:00 | SUNCOR | TE | SUNCOR ICCP Outage | firewall replacement | 60 Mins
Continuous |
|
| 15-Jan-19 10:30 | 15-Jan-19 16:30 | ALTALINK | TE | 353S Plamondon | standard relay maintenance | 6 Hours
Daily |
|
| 15-Jan-19 10:30 | 16-Jan-19 16:30 | ALTALINK | TE | 39S Bickerdike | perform settings changes (PRC-0023) | 30 Hours
Daily |
|
| 15-Jan-19 10:30 | 15-Jan-19 16:30 | ALTALINK | TE | 353s Plamondon RTU/SCADA | set up web page access on HMI | 6 Hours
Daily |
|
| 15-Jan-19 12:00 | 18-Jan-19 16:30 | ATCO | TE | 827s Cranberry Lake RTU/SCADA | RTU-PLC-HMI update | 3.19 Days
Continuous |
|
| 15-Jan-19 12:00 | 15-Jan-19 16:00 | ENMAX | Outage | 22.2TR (ENMAX 22) | Construction for 138kV BT at 22sub | 4 Hours
Continuous |
|
| 15-Jan-19 13:00 | 25-Jan-19 17:00 | ATCO | TE | 951s Thickwood Hills RTU/SCADA | redundancy upgrades on RTU | 10.17 Days
Continuous |
|
| 15-Jan-19 13:00 | 25-Jan-19 17:00 | ATCO | TE | 951s Thickwood Hills RTU/SCADA | redundancy upgrades on SVC RTU | 10.17 Days
Continuous |
|
| 16-Jan-19 07:00 | 19-Jan-19 15:00 | CMH, Medicine Hat | Outage | 20L (MH69S-6 Riverview - MH69S-3 South Ridge),MH69s6 MH69-T63 (MH69s6 Riverview),MH69s3 T34 (MH69s3 South Ridge) | line work on underbuild distribution circuits | 3.33 Days
Continuous |
|
| 16-Jan-19 08:00 | 16-Jan-19 17:00 | ALTALINK | Outage | 13s 1352 (13s Deerland) | correct a wiring error on the 13s1352 breaker control interface | 9 Hours
Daily |
|
| 16-Jan-19 08:00 | 16-Jan-19 17:00 | ATCO, ALTALINK | RB | 9L961 (13s Deerland - 825s Whitefish Lake) | AltaLink requires the reclosing to be blocked at 825S for 13s1352 breaker control interface @ 13S | 9 Hours
Continuous |
|
| 16-Jan-19 08:00 | 25-Jan-19 16:00 | ALTALINK | IO | 2.80L Enmax Info | Green Line LRT Project | 9.33 Days
Continuous |
|
| 16-Jan-19 08:00 | 17-Jan-19 18:00 | ENMAX | Outage | 6.1TR (ENMAX 6),6.82L (ENMAX 6 - ENMAX 41) | switch maintenance and check reversing switch 6.1TR | 1.42 Days
Continuous |
|
| 16-Jan-19 08:00 | 16-Jan-19 18:00 | ENMAX | Outage | 14.83L (ENMAX 14 - ENMAX 36),ENMAX 36.2TR (ENMAX 36) | crane in new 36.5TR to pad | 10 Hours
Continuous |
|
| 16-Jan-19 08:00 | 16-Jan-19 10:00 | ENMAX | Outage | 14.3TR (ENMAX 14) | 14 sub RTU upgrade | 2 Hours
Continuous |
|
| 16-Jan-19 08:00 | 16-Jan-19 12:00 | ENMAX | Outage | 11.2TR (ENMAX 11) | 11 sub RTU upgrade | 4 Hours
Continuous |
|
| 16-Jan-19 08:00 | 25-Jan-19 16:00 | ENMAX | Outage | 2.80L (ENMAX 2 - ENMAX 23) | Green Line LRT Project | 9.33 Days
Continuous |
|
| 16-Jan-19 08:00 | 17-Jan-19 17:00 | ALTALINK | TE | 638s Esso Judy Creek RTU/SCADA | RTU outage for new point addition | 1.38 Days
Daily |
|
| 16-Jan-19 08:30 | 16-Jan-19 16:30 | ALTALINK | TE | 13S Deerland | correct a wiring error on the 13s1352 breaker control interface | 8 Hours
Daily |
|
| 16-Jan-19 08:30 | 17-Jan-19 16:00 | ALTALINK | TE | 77S Sagitawah | standard relay maintenance | 31.5 Hours
Daily |
|
| 16-Jan-19 10:00 | 16-Jan-19 12:00 | ENMAX | Outage | 14.4TR (ENMAX 14) | RTU upgrade | 2 Hours
Continuous |
|
| 16-Jan-19 10:00 | 16-Jan-19 15:00 | ALTALINK | Outage | 765L (151s Strathmore - 419s Chestermere) | high load move between Structures #198 & 199 | 5 Hours
Daily |
|
| 16-Jan-19 11:00 | 18-Jan-19 16:00 | ATCO | TE | 721s La Corey RTU/SCADA | telecom outage | 2.21 Days
Continuous |
|
| 16-Jan-19 11:00 | 18-Jan-19 14:00 | ATCO | TE | ATCO Radio Tower | cutover to new antennas at the Marguerite Lake_S-Telecom | 2.13 Days
Continuous |
|
| 16-Jan-19 11:00 | 16-Jan-19 15:00 | ALTALINK | Outage | 250p11 (250p Bighorn Plant) | maintenance | 4 Hours
Daily |
|
| 16-Jan-19 12:00 | 16-Jan-19 16:00 | ENMAX | Outage | 11.1TR (ENMAX 11) | RTU upgrade | 4 Hours
Continuous |
|
| 17-Jan-19 08:00 | 17-Jan-19 16:00 | ENMAX | Outage | 32.1TR (ENMAX 32) | take measurements for HV and MV bushings | 8 Hours
Continuous |
|
| 17-Jan-19 08:30 | 17-Jan-19 16:00 | ALTALINK | TE | 20S Ghost | relay maintenance | 7.5 Hours
Daily |
|
| 17-Jan-19 08:30 | 17-Jan-19 16:30 | ALTALINK | TE | 103S Goose Lake | relay maintenance | 8 Hours
Daily |
|
| 17-Jan-19 09:00 | 17-Jan-19 16:00 | ENMAX | Outage | 28.1TR (ENMAX 28) | reverse PT secondary wiring in control cabinet | 7 Hours
Continuous |
|
| 17-Jan-19 09:00 | 17-Jan-19 16:30 | ALTALINK | TE | 426S Coalspur | relay maintenance | 7.5 Hours
Daily |
|
| 17-Jan-19 09:00 | 17-Jan-19 13:00 | ALTALINK | Outage | 250p22 (250p Bighorn Plant) | maintenance | 4 Hours
Daily |
|
| 17-Jan-19 09:00 | 01-Feb-19 16:00 | ALTALINK | Outage | 225L (229s Glenwood - 385s Spring Coulee) | line re-build | 15.29 Days
Continuous |
|
| 17-Jan-19 12:00 | 05-Feb-19 14:00 | ALTALINK | Outage | 551L (945s Sunshine Village - 953s Lake Louise) | rebuild of 551L (Sections 14B/C) | 19.08 Days
Continuous |
|
| 18-Jan-19 08:00 | 18-Jan-19 12:00 | ENMAX | Outage | 1.5TR (ENMAX 1) | add heat shrink to NGR riser | 4 Hours
Continuous |
|
| 18-Jan-19 09:00 | 18-Jan-19 17:00 | ALTALINK | RB | 753L (65s High River - 253s Blackie) | urgent repair to structure #753L243 | 8 Hours
Daily |
|
| 18-Jan-19 12:00 | 18-Jan-19 18:00 | ENMAX | Outage | 1.6TR (ENMAX 1) | add heat shrink to NGR riser | 6 Hours
Continuous |
|
| 18-Jan-19 22:00 | 21-Jan-19 06:00 | ENMAX, ALTALINK | Outage | 7.2TR (ENMAX 7),7.82L (42s Sarcee - ENMAX 7) | transformer upgrade, rewiring PTs | 2.33 Days
Continuous |
| This document and the information contained herein are based upon information and data which by their nature contain a degree of uncertainty and are subject to change. In addition, this document may contain information and data from public sources and/or third parties, which have been assumed to be accurate and complete and have not been verified. Accordingly, the Independent System Operator, operating as the Alberta Electric System Operator (the "AESO") makes no warranty, representation or guarantee, express or implied, with respect to this document or the information contained herein, including, but not limited to, any warranty, representation or guarantee of accuracy, completeness, timeliness, reliability, availability, absence of computer virus, non- infringement, merchantability or suitability for any purpose. Under no circumstances will the AESO, its members, officers, employees, contractors or agents, or any of their respective affiliates, be liable for any errors or omissions in, or any losses, damages or claims whatsoever, whether in contract, tort or otherwise, arising from use of or reliance upon, this document or any information contained herein. © 2009 Alberta Electric System Operator. All rights reserved |