Alberta Electric System Operator | |
Long Range Significant Transmission Outages for the period of 24 months starting 2018-03-24 | |
The table below contains the significant transmission outages submitted as tentative to the AESO. These Outages have not yet necessarily been approved, but are listed for awareness and coordination purposes. An Outage has been considered significant for this table if it meets any one (1) or more of the following criteria: |
|
|
|
Note: Where a transmission outage requires generation curtailments, the adjustments to generation will typically happen in the hours before the scheduled transmission outage and in the hour after the element is returned to service. | |
Previous Version | |
Download CSV | |
Owner | From | To | Duration | Element | Scheduled Activity | Affected Intertie |
---|---|---|---|---|---|---|
ALTALINK | 06-Feb-18 10:00 | 30-Mar-18 15:30 | 52.19 Days
Continuous |
526L (268s Whitecourt - 526DL185) | work between structures 1 - 151 | |
ALTALINK | 04-Mar-18 20:00 | 06-Apr-18 17:00 | 32.83 Days
Daily |
289s 1552 (289s Saunders Lake) | PT emergency repair - forced outage | |
ALTALINK | 25-Mar-18 08:00 | 28-Mar-18 14:30 | 3.27 Days
Continuous |
69s T4 (69s North Barrhead),69s 713 (69s North Barrhead) | Replace 69s713 breaker fail protection. | |
ATCO | 26-Mar-18 08:00 | 28-Mar-18 17:00 | 2.38 Days
Daily |
7L32 (811s Clairmont Lake - 862s South Bezanson) | replace rotten crossarms from inspection | |
ALTALINK | 26-Mar-18 08:00 | 30-Mar-18 17:00 | 4.38 Days
Continuous |
510s ACF14 (510s Sunnybrook) | ACF 14 Shunt Reactor Inspection and leak repair. | |
Syncrude | 26-Mar-18 08:00 | 01-Apr-18 18:00 | 6.42 Days
Continuous |
AL-1 (D05 Syncrude - Aurora) | line maintenance | |
SUNCOR | 26-Mar-18 09:00 | 30-Mar-18 18:00 | 4.38 Days
Continuous |
29EDD1S452 (29EDD-1 Millennium) | SF6 top up on breaker 29EDD1S452 | |
ENMAX, ALTALINK | 26-Mar-18 09:15 | 28-Mar-18 17:45 | 2.35 Days
Continuous |
918L (281s Johnson - 162s Beddington) | Component Replacement | |
ENMAX, ALTALINK | 26-Mar-18 12:00 | 26-Mar-18 18:00 | 6 Hours
Continuous |
23.80L (74s Janet - ENMAX 23),23.4TR (ENMAX 23) | Spring Substation Washing | |
ALTALINK | 27-Mar-18 08:00 | 27-Mar-18 17:00 | 9 Hours
Daily |
5s7E Advice for AltaLink | Maintain 5s71 circuit switcher and airbreak | |
ALTALINK | 27-Mar-18 09:00 | 27-Mar-18 18:00 | 9 Hours
Daily |
931L (132s Ware Junction - 28s West Brooks) | Salvaging old Underpower RAS Scheme and associated equipment @ 132s; This RAS is no longer in use and is being removed permanently. Crews will not be hanging grounds and just require the equipment de- energized | |
ATCO | 27-Mar-18 10:00 | 28-Mar-18 12:00 | 26 Hours
Continuous |
939s 911 (939s Livock) | 939S 911 Pole 1 Repair SF6 Leak Repair Leaking Breaker Pole The Phase Shifting Transformer will be out of service |
|
ALTALINK | 27-Mar-18 23:00 | 28-Mar-18 03:00 | 4 Hours
Continuous |
62s11 (62s Brazeau) | maintenance | |
ALTALINK | 28-Mar-18 03:01 | 28-Mar-18 07:00 | 3.98 Hours
Daily |
62s12 (62s Brazeau) | maintenance | |
ATCO | 28-Mar-18 12:30 | 29-Mar-18 15:00 | 26.5 Hours
Continuous |
939s 904 (939s Livock) | Repair Breaker 904 @ 939S Livock Repair and Top up Breaker 904. this Breaker has a long history of a slow leak. The Breaker is currently low and will need a top up for safe operation. We will be attempting a permanent repair during this outage which is why it cannot be done in one day. 240 KV Bus Open for duration of repair |
|
ALTALINK | 28-Mar-18 15:30 | 28-Mar-18 17:30 | 2 Hours
Daily |
913L (69s North Barrhead - 732s Mitsue),69s 913N (69s North Barrhead) | Trip test from new 69s713 breaker fail protection | |
ENMAX, ALTALINK | 31-Mar-18 08:00 | 01-Apr-18 18:00 | 1.42 Days
Continuous |
36.81L (44s Bearspaw - ENMAX 36),7.84L (ENMAX 36 - ENMAX 7),36.1TR (ENMAX 36),36.3TR (ENMAX 36),36B138-36BT3 (ENMAX 36) | HV SW/MD Maintenance 36.1MD, SW88, SW89, SW90, SW83. doble 36PT138-Z31-C? Spring Substation Washing | |
ALTALINK, ATCO | 02-Apr-18 08:00 | 06-Apr-18 13:00 | 4.21 Days
Continuous |
69s 723E (69s North Barrhead),69s 230W (69s North Barrhead),7L230 (69s North Barrhead - 7L230 tap),723L (69s North Barrhead - 723L133),69s T5 (69s North Barrhead) | Replace 69s13 & 69s15. Replace 69s723W breaker fail protection. | |
Syncrude | 02-Apr-18 08:00 | 12-Apr-18 18:00 | 10.42 Days
Continuous |
D05 T1 (D05 Syncrude) | will be isolated
from Primary and Secondary for 5 Yr PM. |
|
ENMAX | 02-Apr-18 08:00 | 13-Apr-18 16:00 | 11.33 Days
Continuous |
35.81L (42s Sarcee - ENMAX 35) | Request from road contractor to install girders on a bridge south of 42s | |
ENMAX | 02-Apr-18 09:00 | 11-Apr-18 09:00 | 9 Days
Continuous |
ENMAX 25 B240-D131 (ENMAX 25),ENMAX 25 B240-D132 (ENMAX 25) | switch repair | |
ENMAX | 02-Apr-18 10:00 | 11-Apr-18 10:00 | 9 Days
Continuous |
ENMAX 25 B240-D141 (ENMAX 25),ENMAX 25 B240-D140 (ENMAX 25),ENMAX 25 MD240-3GSU (ENMAX 25) | testing | |
EPCOR | 03-Apr-18 07:00 | 20-Apr-18 17:00 | 17.42 Days
Continuous |
805s T1 (805s Jasper) | Manhole resurfacing | |
ATCO | 03-Apr-18 08:00 | 05-Apr-18 17:00 | 2.38 Days
Daily |
7L32 (862s South Bezanson - 813s Little Smoky) | replace rotten crossarms from inspection | |
ALTALINK | 04-Apr-18 07:00 | 04-Apr-18 18:00 | 11 Hours
Continuous |
730L (285s East Camrose - 730L62) | Installing bird diverters | |
ALTALINK | 04-Apr-18 08:00 | 11-Apr-18 16:00 | 7.33 Days
Continuous |
936L (102s Langdon - 5s East Calgary) | Green Line LRT Project | |
ENMAX, ALTALINK | 04-Apr-18 08:00 | 11-Apr-18 16:00 | 7.33 Days
Continuous |
937L (102s Langdon - 5s East Calgary) | Green Line LRT Project | |
SUNCOR | 05-Apr-18 16:00 | 11-Apr-18 18:00 | 6.08 Days
Continuous |
30EDD-1-623 (30EDD-1),30EDD-1-624 (30EDD-1),30EDD-1-625 (30EDD-1),30EDD-1-626 (30EDD-1) | line maintenance and protection | |
ALTALINK | 07-Apr-18 09:00 | 07-Apr-18 11:00 | 2 Hours
Daily |
69s T4 (69s North Barrhead),69s 713 (69s North Barrhead) | Trip test from new 69s723E breaker fail protection | |
ALTALINK | 08-Apr-18 08:00 | 19-Apr-18 18:00 | 11.42 Days
Continuous |
38s East Edmonton 240 kV Bus 1,38s T1 (38s East Edmonton) | Replacement of T1, Replacement of 38s50 switch including new structure and foundations | |
EPCOR | 09-Apr-18 07:00 | 13-Apr-18 17:00 | 4.42 Days
Continuous |
987s T3 (987s Clover Bar) | Doble | |
BCH | 09-Apr-18 09:00 | 20-Apr-18 17:00 | 11.33 Days
Continuous |
2L294 (Cranbrook - Nelway) | Fortis annual plan (AAL CB3-1 Switch Replacement) | AB-BC |
ALTALINK | 09-Apr-18 09:30 | 07-May-18 18:00 | 28.35 Days
Continuous |
320p 1352 (320p Keephills) | [KATR]-Installing new line protection for 3-terminal scheme and functional testing; repairing 320p212 | |
ALTALINK | 09-Apr-18 10:00 | 12-Apr-18 15:00 | 3.21 Days
Continuous |
190L (17s Benalto - 320p Keephills),17s Benalto 240 kV North Bus 1 | 17s190N Switch Replacement - Bus needed due to Proximity / Approach | |
ALTALINK | 09-Apr-18 12:00 | 12-Apr-18 18:00 | 3.25 Days
Continuous |
938L (77s Sagitawah - 809s Louise Creek),77s 40 (77s Sagitawah) | 240kV CT replacement & 77s40 mtce. | |
ENMAX | 11-Apr-18 11:00 | 18-Apr-18 09:00 | 6.92 Days
Continuous |
ENMAX 25 MD240-2GSU (ENMAX 25),ENMAX 25 B240-D135 (ENMAX 25),ENMAX 25 B240-D134 (ENMAX 25) | testing | |
SUNCOR | 12-Apr-18 08:00 | 17-Apr-18 17:00 | 5.38 Days
Continuous |
30EDD-1-621 (30EDD-1),30EDD-1-622 (30EDD-1),30EDD-1-623 (30EDD-1),29PL6-4 (836s Steepbank - 29EDD-1) | line maintenance and protection | |
ALTALINK | 12-Apr-18 15:00 | 16-Apr-18 16:00 | 4.04 Days
Continuous |
17s Benalto 240 kV North Bus 1,903L (17s Benalto - 320p Keephills) | 17s903N Switch Replacement - Bus needed due to Proximity / Approach | |
Syncrude | 13-Apr-18 08:00 | 20-Apr-18 18:00 | 7.42 Days
Continuous |
AL-2 (D05 Syncrude - Aurora) | line maintenance | |
EPCOR | 16-Apr-18 07:00 | 20-Apr-18 17:00 | 4.42 Days
Continuous |
557s T2 (557s Castle Downs) | Calisto Install | |
EPCOR | 16-Apr-18 07:00 | 20-Apr-18 17:00 | 4.42 Days
Continuous |
987s T4 (987s Clover Bar) | Doble | |
ATCO | 16-Apr-18 07:00 | 07-Jun-18 17:00 | 52.42 Days
Continuous |
7L23 (732s Mitsue - 858s Narrows Creek),732s 703 (732s Mitsue),732s 701 (732s Mitsue),732s 702 (732s Mitsue),732s 901T (732s Mitsue),7L49 (732s Mitsue - 729s Otauwau) | Replace breaker 702 and CT's and Breaker 703 and CT's
April 16-24 GOI 2-43738A Outage on 702, 703, 7L49 open ended Isolation points:702A, 703A, 7L49D1 @732S Mitsue April 24-May 3 GOI 2-43738B Expand Outage to include 7L49, 7L23, 901T Isolation points:901TD, 500D1, 701A, 707B, 7L49D1, 7L23D4 May 3-Jun 1 GOI 2-43738C Reduce Isolation zone to include Breaker 702, 703, 7L49 open ended Isolation points:702A, 703A, 7L49D1 |
|
ALTALINK | 16-Apr-18 07:30 | 18-Apr-18 17:30 | 2.42 Days
Continuous |
367s T1 (367s Harry Smith) | [SWEATD] Tap changer gas piping modification | |
ALBIAN, ATCO | 18-Apr-18 07:00 | 02-May-18 17:00 | 14.42 Days
Continuous |
919s 908 (919s Hartley),847s 902T (847s Muskeg River) | Transformer protection upgrade during planned generator turnaround. | |
ALTALINK | 19-Apr-18 07:30 | 21-Apr-18 17:30 | 2.42 Days
Continuous |
367s T2 (367S Harry Smith) | [SWEATD] Tap changer gas piping modification | |
EPCOR | 20-Apr-18 07:00 | 20-Apr-18 17:00 | 10 Hours
Continuous |
987S Clover Bar 240 kV Bus 2 | Doble | |
EPCOR | 23-Apr-18 07:00 | 24-Apr-18 17:00 | 1.42 Days
Continuous |
803s T1 (803s Lambton) | Cutover of new relay protection | |
EPCOR | 23-Apr-18 07:00 | 27-Apr-18 17:00 | 4.42 Days
Continuous |
814s T1 (814s Bellamy) | Doble | |
EPCOR | 23-Apr-18 07:00 | 27-Apr-18 17:00 | 4.42 Days
Daily |
987s C2406 (987s Clover Bar) | Maint | |
ALTALINK | 23-Apr-18 07:00 | 03-May-18 18:00 | 10.46 Days
Continuous |
166s 862N (166s Dow Chem Fort Saskatchewan),166s 899N (166s Dow Chem Fort Saskatchewan),166s T1 (166s Dow Chemical Fort Saskatchewan) | Replace CT4 and replace 166s8, maintenance on T1 | |
ALTALINK | 23-Apr-18 07:30 | 25-Apr-18 17:30 | 2.42 Days
Continuous |
289s T2 (289s Saunders Lake) | [SWEATD] Tap changer gas piping modification | |
BCH | 23-Apr-18 09:00 | 27-Apr-18 17:00 | 4.33 Days
Continuous |
5L51 (Ingledow - Custer) | ING 5D23 cutting over controls and replace failed glass on 9 structures | AB-BC |
ALTALINK | 23-Apr-18 10:00 | 30-Apr-18 12:00 | 7.08 Days
Continuous |
916L (42s Sarcee - 5s East Calgary) | [SWCRR] Enter settings and commissioning of point on wave controller for 42s916E breaker | |
SUNCOR | 24-Apr-18 08:00 | 01-May-18 18:00 | 7.42 Days
Continuous |
30EDD-1-627 (30EDD-1),30EDD-1-628 (30EDD-1),30EDD-1-629 (30EDD-1),30EDD-1-626 (30EDD-1) | line maintenance and protection | |
ALTALINK | 24-Apr-18 10:30 | 26-Apr-18 14:00 | 2.15 Days
Continuous |
28s T2 (28s West Brooks) | Maintain, doble and SFRA T2 | |
ALTALINK, EPCOR | 25-Apr-18 07:00 | 27-Apr-18 18:00 | 2.46 Days
Continuous |
809L (320p Keephills - 510s Sunnybrook) | [KATR]-Moving a portion of 1043L in preparation for 1045L to terminate at 320P | |
ALTALINK, EPCOR | 25-Apr-18 07:00 | 01-May-18 18:00 | 6.46 Days
Continuous |
1043L (320p Keephills - 367s Harry Smith) | [KATR]-Re-configure part of 1043L into 320p1352 bay | |
ENMAX, ALTALINK | 25-Apr-18 08:00 | 25-Apr-18 16:00 | 8 Hours
Continuous |
37.82L (74s Janet - ENMAX 37) | HV breaker maintenance 7B138-7.82, SF6 gas sample 7B138-7.82 | |
ATCO | 25-Apr-18 08:30 | 25-Apr-18 15:30 | 7 Hours
Continuous |
930s SVC (930s Arcenciel) | Complete SVC Air Cooling Inspection and Adjustment And Complete Breaker 401 Partial PM, SVC Offline for the Duration of the Work | |
ALTALINK | 25-Apr-18 08:30 | 25-Apr-18 17:00 | 8.5 Hours
Daily |
17s T1 (17s Benalto) | Maintain, doble and SFRA T1 | |
ALTALINK | 25-Apr-18 10:00 | 25-Apr-18 14:00 | 4 Hours
Daily |
42s C2 (42s Sarcee),42s C3 (42s Sarcee) | [SWCRR] C2 and C3 Cap banks are required as part of the commissioning of the the new 42s 916L POW controller | |
EPCOR | 26-Apr-18 07:00 | 27-Apr-18 17:00 | 1.42 Days
Continuous |
803s T2 (803s Lambton) | Cutover of new relay protection | |
ALTALINK | 26-Apr-18 07:30 | 28-Apr-18 17:30 | 2.42 Days
Continuous |
289s T1 (289s Saunders Lake) | [SWEATD] Tap changer gas piping modification | |
ALTALINK | 26-Apr-18 08:30 | 26-Apr-18 17:00 | 8.5 Hours
Daily |
900L (63s Red Deer - 17s Benalto) | 17s900E Unable to open and needs to be adjusted | |
ATCO | 29-Apr-18 07:00 | 29-Apr-18 17:00 | 10 Hours
Continuous |
7L69 (815s Goodfare - 731s Elmworth),815s 704 (815s Goodfare) | protection upgrade | |
EPCOR | 30-Apr-18 07:00 | 04-May-18 17:00 | 4.42 Days
Continuous |
814s T2 (814s Bellamy) | Doble | |
ATCO | 30-Apr-18 07:00 | 11-May-18 18:00 | 11.46 Days
Continuous |
2029S BUILDING VALVE HALL | Valve Hall outage is required to conduct Preventative Maintenance on all equipment within the zone of isolation i.e. Valve Cooling DIW Strainers, Valve Module inspections, Switch operations, etc. Power transmission on the DC link (13L50) will not be possible during the outage. . |
|
ATCO | 30-Apr-18 07:00 | 11-May-18 18:00 | 11.46 Days
Continuous |
2075S BUILDING VALVE HALL | Valve Hall outage is required to conduct Preventative Maintenance on all equipment within the zone of isolation. i.e. Valve Cooling DIW Strainers, Valve Module inspections, Switch operations, etc. Power transmission on the DC link (13L50) will not be possible during the outage. | |
ATCO | 30-Apr-18 07:00 | 11-May-18 18:00 | 11.46 Days
Continuous |
13L50 (2029s Heathfield - 2075s Newell) | 13L50 will be out of service during this time as the connecting stations, Heathfield and Newell, are isolating their respective Valve Halls. | |
ENMAX, ALTALINK | 30-Apr-18 08:00 | 01-May-18 16:00 | 1.33 Days
Continuous |
832L (ENMAX 10 - ENMAX 12) | HV breaker maintenance 12B138-832L | |
ALTALINK | 30-Apr-18 11:30 | 03-May-18 16:30 | 3.21 Days
Continuous |
63s 452 (63s Red Deer) | Maintain minimum oil breaker 240kV ABB HLRE. | |
ALTALINK | 30-Apr-18 12:30 | 02-May-18 17:30 | 2.21 Days
Continuous |
320p 1352 (320p Keephills) | 320p1352 A,B,C (CB1246) SF6 240kV HGF ADD: 320P212 Needs Adjustment | |
EPCOR | 02-May-18 07:00 | 02-May-18 17:00 | 10 Hours
Continuous |
52sE2402 (52s East Industrial) | Maint | |
ALTALINK | 02-May-18 07:00 | 07-May-18 18:00 | 5.46 Days
Continuous |
1045L (320p-310p-E805s) - GOI [KATR] | [KATR]-Terminating 1045L into 320p1352 | |
ALTALINK | 02-May-18 08:30 | 02-May-18 16:00 | 7.5 Hours
Daily |
199s 688 (199s East Airdrie),688L (199s East Airdrie - 688DL23) | Maintain 138kV SF6 breaker | |
EPCOR | 03-May-18 07:00 | 05-May-18 18:00 | 2.46 Days
Continuous |
ALTALINK - REQUIRES ISOLATION @ JASPER - JDS27,JDS12 | Terminating 1045L into 320p1352 | |
ALTALINK | 05-May-18 07:00 | 19-May-18 18:00 | 14.46 Days
Continuous |
510s 2852 (510s Sunnybrook) | Installing foundation for the new 510s2952 and associated equipment | |
ALTALINK | 05-May-18 15:01 | 05-May-18 17:00 | 119 Mins
Daily |
38s72 (38s73 brkr) Advice | Trip test from 38s62 breaker fail | |
EPCOR | 07-May-18 07:00 | 11-May-18 17:00 | 4.42 Days
Continuous |
805s T3 (805s Jasper) | Doble | |
BCH | 07-May-18 09:00 | 11-May-18 17:00 | 4.33 Days
Continuous |
2L112 (Nelway - Boundary) | annual plan request F19 | AB-BC |
ALTALINK | 08-May-18 07:00 | 08-May-18 12:00 | 5 Hours
Daily |
199L (347s - 259s - 199L187B) - GOI | Creating Open Point 'A' @ Structure 187A | |
ALTALINK | 08-May-18 07:00 | 24-May-18 12:00 | 16.21 Days
Continuous |
199L (347s - Open Point 'A') - GOI | Installing a new airbrake switch 199L187A | |
ATCO | 08-May-18 09:00 | 09-May-18 16:00 | 31 Hours
Continuous |
800s 701 (800s Friedenstal),7L75 (A793s West Peace River - 800s Friedenstal) | BREAKER MIN OIL HLR PARTIAL TESTING @ FRIEDENSTAL 800S 701
Complete Partial PM on Breaker 701 7L75 open ended for the duration of the work |
|
ATCO | 10-May-18 09:00 | 11-May-18 16:00 | 31 Hours
Continuous |
7L73 (829s Boucher Creek - 800s Friedenstal),800s 702 (800s Friedenstal) | BREAKER MIN OIL HLR PARTIAL TESTING @ FRIEDENSTAL 800S 702
Complete Partial PM on Breaker 702 7L73 open ended for the duration of the work |
|
ATCO | 14-May-18 10:00 | 18-May-18 14:00 | 4.17 Days
Continuous |
959S SVC (959s Lanfine) | SVC warranty repair work- GE Repairs/Modifications, SVC will not be available for duration of outage | |
ALTALINK | 14-May-18 12:30 | 16-May-18 13:30 | 2.04 Days
Continuous |
338s 252 (338s Cherhill) | 338s252 maint | |
ATCO | 15-May-18 08:30 | 15-May-18 16:30 | 8 Hours
Continuous |
786s SVC (786s High Level) | Complete Inspection and Adjustment of SVC Air Cooling, SVC Off LIne for the Duration of the Work | |
ALTALINK | 16-May-18 07:30 | 16-May-18 18:00 | 10.5 Hours
Daily |
37s71 (37s North Calder),905L (19s Wabamun - 37s North Calder) | 60 deg hot spot. | |
ENMAX, ALTALINK | 17-May-18 08:00 | 17-May-18 16:00 | 8 Hours
Continuous |
21.80L (42s Sarcee - ENMAX 21) | SF6 gas sample 21B138-21.80 | |
ALTALINK | 17-May-18 08:30 | 17-May-18 16:30 | 8 Hours
Daily |
71s 1652 (71s Lamoureux) | Hotspot All Phases (60deg)-71s35 | |
EPCOR | 22-May-18 07:00 | 08-Jun-18 17:00 | 17.42 Days
Continuous |
511s Victoria T5 (511s Victoria),CV5 (557s Castle Downs - 511s Victoria) | Doble / Cable, manhole inspection. | |
ALTALINK | 22-May-18 08:45 | 25-May-18 17:45 | 3.38 Days
Continuous |
28s 138kV Bus 1 & T1 – GOI,28s T1 (28s West Brooks) | CT Wiring of T1, 28s22, 28s31 & Trip Tests for B Protection Addition | |
BCH | 22-May-18 09:00 | 15-Jun-18 17:00 | 24.33 Days
Continuous |
5L72 (Mica Creek - Nicola) | Annual Plan Request F19 - PLACEHOLDER for Conductor Spacer Replacement | AB-BC |
AESO | 22-May-18 09:30 | 25-May-18 16:30 | 3.29 Days
Continuous |
787L (166s Dow Chemical Fort Saskatchewan - 71s Lamoureux) | Replace PT's | |
ALTALINK | 23-May-18 07:30 | 24-May-18 17:30 | 1.42 Days
Continuous |
973L (39s Bickerdike - 310p Sundance) | Replace 1 PT @ 310p. | |
ALTALINK | 23-May-18 09:00 | 24-May-18 16:30 | 31.5 Hours
Continuous |
250P 1 (250P Bighorn Plant) | Maintain 138kV minimum oil breaker | |
ALTALINK | 24-May-18 07:00 | 24-May-18 12:00 | 5 Hours
Daily |
199L (347s - 259s - 199L187B) - GOI | Closing Open Point 'A' @ Structure 187A | |
EPCOR | 24-May-18 07:00 | 29-May-18 17:00 | 5.42 Days
Continuous |
987s GDS3 (987s Cloverbar) | maintenance | |
ALTALINK | 25-May-18 11:00 | 25-May-18 13:30 | 2.5 Hours
Daily |
28s R1 (28s West Brooks),28s 44 (28s West Brooks) | Trip Test Required for Bus Protection Addition | |
ALTALINK | 25-May-18 12:30 | 25-May-18 14:30 | 2 Hours
Daily |
28s 41 (28s West Brooks) | Trip Test Required for Bus Protection Addition | |
ALTALINK | 25-May-18 14:30 | 25-May-18 16:30 | 2 Hours
Daily |
28s 8 (28s West Brooks) | Trip Test Required for Bus Protection Addition | |
EPCOR | 28-May-18 07:00 | 28-May-18 17:00 | 10 Hours
Continuous |
240BA3 (814s Bellamy - 629s Argyll Transfer Station),1055L (816s Petrolia - 629s Argyll Transfer Station) | Doble | |
ALTALINK | 28-May-18 08:45 | 31-May-18 17:45 | 3.38 Days
Continuous |
28s T2 (28s West Brooks),28s 138kV Bus 2 & T2 – GOI | CT Wiring of T2, 28s55, 28s81 & Trip Tests For B Protection Addition | |
ALTALINK, EPCOR | 28-May-18 09:30 | 31-May-18 16:30 | 3.29 Days
Continuous |
921L (71s Lamoureux - 987s Clover Bar) | Replace PT's | |
ALTALINK, EPCOR | 29-May-18 07:00 | 29-May-18 17:00 | 10 Hours
Continuous |
920L (37s North Calder - 557s Castle Downs) | Doble | |
ATCO | 29-May-18 07:00 | 31-May-18 17:00 | 2.42 Days
Continuous |
757s 702 (757s Battle River),7L702 (137s Sedgewick - 757s Battle River) | install and test protection | |
ALTALINK | 29-May-18 07:00 | 31-May-18 18:30 | 2.48 Days
Continuous |
828L (178s Cynthia - 489s Petro Canada Brazeau River),489s T1 (489s Petro Canada Brazeau River) | 489s maint Tx18558 LTC FPE/ASEA 138/4.16 ADD: 489s16 west phase adjustment, 489s T1 Moisture in liquid temp gauge, 489s T1 LTC sweating, 489sT1 Hydran Sensor Failed, 489sT1 MT Conservator Moisture in Gauge, 489s T1 TC door gasket | |
ATCO | 30-May-18 07:00 | 01-Jun-18 17:30 | 2.44 Days
Continuous |
9L46 (932s Pemukan - 959s Lanfine) | attach new line connection | |
SUNCOR | 31-May-18 09:00 | 21-Jun-18 18:00 | 21.38 Days
Continuous |
29PL6-7 (836s Steepbank - 29EDD-5 29Edd-5) | 5 year maintenance | |
ALTALINK | 31-May-18 12:30 | 31-May-18 15:00 | 2.5 Hours
Daily |
28s 52 (28s West Brooks) | Trip Test Required for Bus Protection Addition | |
ALTALINK | 31-May-18 15:00 | 31-May-18 16:30 | 90 Mins
Daily |
28s 2 (28s West Brooks) | Trip Test Required for Bus Protection Addition | |
ATCO | 02-Jun-18 08:00 | 04-Jun-18 17:00 | 2.38 Days
Continuous |
791S 702,7L81 | Install new 7L81 RASA & RASB | |
EPCOR | 04-Jun-18 07:00 | 05-Jun-18 17:00 | 1.42 Days
Continuous |
805s C1 (805s Jasper) | Doble | |
ALTALINK | 04-Jun-18 09:30 | 07-Jun-18 17:00 | 3.31 Days
Continuous |
77s T1 (77s Sagitawah),77s Sagitawah 138 kV West Bus,77s Sagitawah 240 kV West Bus | Protection upgrade | |
ALTALINK | 04-Jun-18 12:00 | 07-Jun-18 16:30 | 3.19 Days
Continuous |
841L (477s Amoco West Pembina - 489s Amoco Canada Brazeau River),489s T2 (489s Petro Canada Brazeau River) | 489sT2 doble TX 18559 LTC FPE/ASEA 138/4, ADD: 489sT2 maint TX 18559 LTC FPE/ASEA 138/4, 489s T2 Moisture in temp gauge 2, 489sT2 LTC 1" Conservator Valve Leak 90241462, 489s T2 MT 2" Bleed Leaking, 489sT2 MT Conservator Moisture in Gauge, 489s17 requires adjustment, motor/man sw, 489s photo cell not working | |
ALTALINK | 04-Jun-18 13:00 | 07-Jun-18 17:00 | 3.17 Days
Continuous |
1053L (324s - 132s) GOI | SCADA system upgrade | |
BCH | 05-Jun-18 09:00 | 15-Jun-18 17:00 | 10.33 Days
Continuous |
2L294 (Nelway - A.A. Lambert) | replacement of defective insulators | AB-BC |
EPCOR | 06-Jun-18 07:00 | 07-Jun-18 17:00 | 1.42 Days
Continuous |
816s P2404 (816s Petrolia) | Doble | |
CENOVUS | 06-Jun-18 07:00 | 13-Jun-18 18:00 | 7.46 Days
Continuous |
539s PCB_9202 (539s Sunday Creek) | insulator testing | |
CENOVUS | 06-Jun-18 07:00 | 13-Jun-18 18:00 | 7.46 Days
Continuous |
539s PCB_9203 (539s Sunday Creek) | insulator testing | |
CENOVUS | 06-Jun-18 07:00 | 13-Jun-18 18:00 | 7.46 Days
Continuous |
539s 9201T (539s Sunday Creek) | insulator testing | |
ENMAX, ALTALINK | 06-Jun-18 08:00 | 06-Jun-18 16:00 | 8 Hours
Continuous |
28.80L (42s Sarcee - ENMAX 28) | HV breaker maintenance 28B138-28.80, SF6 gas sample 28B138-28.80 | |
BCH | 06-Jun-18 09:00 | 07-Jun-18 17:00 | 1.33 Days
Continuous |
1L274 (Elkford - EFT1D22),1L274 (EFT 1D22 - 1D3L274) | Annual Plan Request | AB-BC |
ALTALINK, EPCOR | 08-Jun-18 07:00 | 08-Jun-18 17:00 | 10 Hours
Continuous |
1044L (805s Jasper - 816s Petrolia) | Doble | |
ALTALINK | 09-Jun-18 07:00 | 09-Jun-18 17:00 | 10 Hours
Continuous |
908L (89s Ellerslie - 816s Petrolia) | Doble | |
ALTALINK | 11-Jun-18 08:00 | 17-Jun-18 17:00 | 6.38 Days
Continuous |
Valve Hall and T11 GOI,510s DC yard | Annual Inspection and Maintenance, Link will be out of service | |
ALTALINK | 11-Jun-18 08:00 | 17-Jun-18 17:00 | 6.38 Days
Continuous |
511s DC yard,Valve Hall and T11 GOI,1325L (510s Sunnybrook - 511s Crossings) | Annual Inspection and Maintenance, Link will be out of service | |
ALTALINK | 11-Jun-18 09:30 | 14-Jun-18 17:00 | 3.31 Days
Continuous |
77s Sagitawah 138 kV East Bus,77s T2 (77s Sagitawah),77s Sagitawah 240 kV West Bus | Protection upgrade | |
ALTALINK | 11-Jun-18 13:00 | 14-Jun-18 17:00 | 3.17 Days
Continuous |
935L (324s - 356s) GOI | SCADA system upgrade | |
ALTALINK | 17-Jun-18 15:01 | 17-Jun-18 17:00 | 119 Mins
Daily |
38s17 (38s18 brkr) Advice | Trip test from 3552 breaker fail | |
EPCOR | 18-Jun-18 07:00 | 18-Jun-18 17:00 | 10 Hours
Continuous |
Poundmaker 2401 (Poundmaker) | Maint | |
EPCOR | 18-Jun-18 07:00 | 22-Sep-18 17:00 | 96.42 Days
Continuous |
TX1 @ Jasper | Doble | |
BCH | 18-Jun-18 09:00 | 06-Jul-18 17:00 | 18.33 Days
Continuous |
5L71 (Mica Creek - Nicola) | Annual Plan Request F19 | AB-BC |
ALTALINK | 18-Jun-18 13:00 | 21-Jun-18 17:00 | 3.17 Days
Continuous |
1052L (324s - 28s) GOI | SCADA system upgrade | |
EPCOR | 19-Jun-18 07:00 | 19-Jun-18 17:00 | 10 Hours
Continuous |
Poundmaker 2402 (Poundmaker) | Maint | |
BCH | 19-Jun-18 09:00 | 21-Jun-18 17:00 | 2.33 Days
Continuous |
2L293 (Selkirk - Nelway) | Placeholder for Annual Plan Request F19 | AB-BC |
EPCOR | 20-Jun-18 07:00 | 20-Jun-18 17:00 | 10 Hours
Continuous |
Poundmaker 2403 (Poundmaker) | Maint | |
EPCOR | 21-Jun-18 07:00 | 21-Jun-18 17:00 | 10 Hours
Continuous |
Poundmaker 2404 (Poundmaker) | Maint | |
ALTALINK | 25-Jun-18 13:00 | 28-Jun-18 17:00 | 3.17 Days
Continuous |
1034L (324s - 244s) GOI | SCADA system upgrade | |
ALTALINK | 04-Jul-18 11:00 | 05-Jul-18 15:00 | 28 Hours
Continuous |
748L(277s-267s) and 267s T1 (Tx18304) GO | 138kV HGF SF6 gas breaker maintenance @ both ends of 748L | |
ATCO | 09-Jul-18 08:00 | 12-Jul-18 17:00 | 3.38 Days
Continuous |
7L702 (137s Sedgewick - 757s Battle River) | Change Arms and Insulators on 7L702 | |
ALTALINK | 09-Jul-18 09:15 | 19-Jul-18 17:45 | 10.35 Days
Continuous |
754L (245s - 754L65A) GOI | Structure Replacements | |
ALTALINK | 09-Jul-18 13:00 | 12-Jul-18 17:00 | 3.17 Days
Continuous |
1087L (324s - A2075s) GOI | SCADA system upgrade | |
ATCO | 16-Jul-18 08:00 | 19-Jul-18 17:00 | 3.38 Days
Continuous |
7L702 (137s Sedgewick - 757s Battle River) | Change Arms and Insulators on 7L702 | |
ALTALINK | 16-Jul-18 11:00 | 26-Jul-18 16:00 | 10.21 Days
Continuous |
1112L (89s-289s) - Advice | 89s1452 Breaker Replacement, 89s81 PT Replacement | |
ALTALINK | 16-Jul-18 13:00 | 19-Jul-18 17:00 | 3.17 Days
Continuous |
1088L (324s - A2075s) GOI | SCADA system upgrade | |
BCH | 17-Jul-18 09:00 | 19-Jul-18 17:00 | 2.33 Days
Continuous |
2L113 (B1s Natal - B2s Cranbrook) | Placeholder for Annual Plan Request F19 | AB-BC |
ATCO | 23-Jul-18 08:00 | 26-Jul-18 17:00 | 3.38 Days
Continuous |
7L702 (137s Sedgewick - 757s Battle River) | Change Arms and Insulators on 7L702 | |
ALTALINK | 23-Jul-18 09:15 | 02-Aug-18 17:45 | 10.35 Days
Continuous |
754L (437s - 754L75) GOI | Structure Replacements | |
ALTALINK | 23-Jul-18 13:00 | 26-Jul-18 17:00 | 3.17 Days
Continuous |
1051L (324s - 28s) GOI | SCADA system upgrade | |
SUNCOR | 30-Jul-18 09:00 | 17-Aug-18 18:00 | 18.38 Days
Continuous |
29PL9-14 (29EDD-56 - 29EDD-34) | 5 year maintenance on breakers, bus CT and switches | |
BCH | 03-Aug-18 09:00 | 12-Sep-18 17:00 | 40.33 Days
Continuous |
5L71 (Mica Creek - Nicola) | Placeholder for MCA Switchgear Roof Replacement | AB-BC |
ENMAX | 06-Aug-18 08:00 | 17-Aug-18 16:00 | 11.33 Days
Continuous |
162.1TR (ENMAX 162 Beddington) | Tapchanger Inspection. Doble Test Transformer | |
BCH | 06-Aug-18 09:00 | 10-Aug-18 17:00 | 4.33 Days
Continuous |
2L294 (Nelway - A.A. Lambert) | Placeholder for Annual Plan Request F19 | AB-BC |
ALTALINK | 13-Aug-18 07:30 | 14-Aug-18 17:30 | 1.42 Days
Continuous |
805L) - GOI *pl,86s T1 & 138kV Bus (804 | Replace failed PT | |
ATCO | 13-Aug-18 09:00 | 26-Aug-18 18:00 | 13.38 Days
Continuous |
840S McNeill Station | 2018 McNeill Fall T/A. Arrestor install and Bird Proofing | AB-SK |
ALTALINK | 13-Aug-18 11:00 | 23-Aug-18 16:00 | 10.21 Days
Continuous |
1057L (89s-E657s) - Advice | 89s452 Breaker Replacement, 89s73 PT Replacement | |
BCH | 14-Aug-18 09:00 | 17-Aug-18 17:00 | 3.33 Days
Continuous |
5L96 (Selkirk - Vaseux Lake) | annual plan request F19 | AB-BC |
EPCOR | 20-Aug-18 07:00 | 21-Aug-18 17:00 | 1.42 Days
Continuous |
330p 1201 (330p Genesee) | BKR Maint | |
ENMAX | 20-Aug-18 08:00 | 31-Aug-18 16:00 | 11.33 Days
Continuous |
162.2TR (ENMAX 162 Beddington) | Tapchanger Inspection. Doble Test Transformer | |
BCH | 20-Aug-18 09:00 | 24-Aug-18 17:00 | 4.33 Days
Continuous |
5L91 (Selkirk - Ashton Creek) | annual plan request F19 | AB-BC |
BCH | 20-Aug-18 09:00 | 31-Aug-18 17:00 | 11.33 Days
Continuous |
1L274 (EFT - 1D2L274) | Annual Plan Request F19 | AB-BC |
SUNCOR | 20-Aug-18 09:00 | 07-Sep-18 18:00 | 18.38 Days
Continuous |
29PL9-15 (29EDD-56 - 29EDD-34) | 5 year maintenance on breakers, bus CT and switches | |
ALTALINK, EPCOR | 22-Aug-18 07:00 | 22-Aug-18 17:00 | 10 Hours
Continuous |
1238L (510s Sunnybrook - 330p Genesee),Sunnybrook | BKR Maint | |
EPCOR | 23-Aug-18 07:00 | 24-Aug-18 17:00 | 1.42 Days
Continuous |
330p 1203 (330p Genesee) | BKR Maint | |
BCH | 27-Aug-18 09:00 | 31-Aug-18 17:00 | 4.33 Days
Continuous |
5L92 (Cranbrook - Selkirk) | annual plan request F19 | AB-BC |
ATCO, SUNCOR | 01-Sep-18 09:00 | 04-Sep-18 18:00 | 3.38 Days
Continuous |
29PL9-1 (29EDD-1 Millennium - 848s Ruth Lake),29PL9-3 (29EDD-1 Millennium - 29EDD-3) | maintenance - replacement of 29CT-5 | |
BCH | 03-Sep-18 09:00 | 14-Sep-18 17:00 | 11.33 Days
Continuous |
5L98 (BCH Nicola - Vaseux Lake) | annual plan request F19 | AB-BC |
ATCO | 04-Sep-18 07:00 | 25-Nov-18 17:00 | 82.46 Days
Continuous |
972S 905B | 972s 905B | |
SHELL, ALBIAN | 10-Sep-18 07:00 | 10-Sep-18 17:00 | 10 Hours
Continuous |
847s 901T (847s Muskeg River),919s 906 (919s Hartley) | Transformer protection upgrade during planned generator turnaround. | |
ALTALINK | 10-Sep-18 08:00 | 27-Sep-18 17:00 | 17.38 Days
Continuous |
62s T5 GOI | Protection upgrade | |
ALTALINK | 10-Sep-18 08:00 | 27-Sep-18 17:00 | 17.38 Days
Continuous |
995L (17s Benalto - 995AL tap) | Replacement of strain insulators for 995L and post insulators for 17s76, 17s77,CVT(17s78) replacement | |
ATCO | 10-Sep-18 09:00 | 14-Sep-18 17:00 | 4.33 Days
Continuous |
801s 901T (801s Anderson) | 801S Anderson 901T Re-test Sept 10, 2018 | |
BCH | 10-Sep-18 09:00 | 14-Sep-18 17:00 | 4.33 Days
Continuous |
1L274 (B1s BCH Natal - 1D1L274) | 2018 annual plan work | AB-BC |
SUNCOR | 10-Sep-18 09:00 | 21-Sep-18 18:00 | 11.38 Days
Continuous |
260kV bus 29PP-45 (29EDD-34) | 5 year maintenance on 29PP-45 bus | |
ALTALINK, EPCOR | 17-Sep-18 07:00 | 29-Sep-18 18:00 | 12.46 Days
Continuous |
510s2852 and 510s3052 (1238L) - GOI,510s 2852 (510s Sunnybrook),1238L (510s Sunnybrook - 330p Genesee) | Installing new 510s2952, CT's, 510s46, 510s48 and protection/breaker fail mods | |
MONTANA | 17-Sep-18 08:00 | 20-Sep-18 18:00 | 3.42 Days
Continuous |
MATL (120s Picture Butte - Montana) | align with 1201L outage | AB-MATL |
ALTALINK | 17-Sep-18 09:00 | 20-Sep-18 18:00 | 3.38 Days
Continuous |
1201L (520s Bennett - BCH Cranbrook) | Maintenance Components | AB-BC |
MONTANA | 24-Sep-18 08:00 | 27-Sep-18 18:00 | 3.42 Days
Continuous |
MATL (120s Picture Butte - Montana) | align with 1201L outage | AB-MATL |
ALTALINK | 24-Sep-18 09:00 | 27-Sep-18 18:00 | 3.38 Days
Continuous |
1201L (520s Bennett - BCH Cranbrook) | Maintenance Components | AB-BC |
SUNCOR | 24-Sep-18 09:00 | 05-Oct-18 18:00 | 11.38 Days
Continuous |
29PL9-14 (29EDD-56 - 29EDD-34),29PL9-15 (29EDD-56 - 29EDD-34) | maintenance on bus 29PP-41F | |
BCH | 27-Sep-18 09:00 | 02-Nov-18 17:00 | 36.33 Days
Continuous |
5L72 (Mica Creek - Nicola) | Placeholder for MCA Switchgear Roof Replacement. | AB-BC |
ALTALINK | 01-Oct-18 08:00 | 05-Oct-18 18:00 | 4.42 Days
Continuous |
62s 138 KV Bus Advice | Protection upgrade | |
MONTANA | 01-Oct-18 11:00 | 04-Oct-18 18:00 | 3.29 Days
Continuous |
MATL (120s Picture Butte - Montana) | align with 1201L outage | AB-MATL |
ALTALINK | 01-Oct-18 12:00 | 04-Oct-18 18:00 | 3.25 Days
Continuous |
1201L (520s Bennett - BCH Cranbrook) | Maintenance Components | AB-BC |
SUNCOR | 02-Oct-18 09:00 | 12-Oct-18 18:00 | 10.38 Days
Continuous |
29PL9-2 (29EDD-1 Millennium - 848s Ruth Lake) | maintenance on 29CTT-1 in 29EDD-1 | |
BCH | 19-Oct-18 15:00 | 19-Oct-18 17:00 | 2 Hours
Continuous |
5L52 (Ingledow - Custer) | ING 5D25 cutting over controls to new station control equipment | AB-BC |
ALTALINK | 26-Nov-18 07:00 | 04-Dec-18 18:00 | 8.46 Days
Continuous |
510s 2852 (510s Sunnybrook),510s2852 and 510s2952 - GOI | Closing Open Point 'C' and energizing new VT13 and new reactor bank R3 (72 hour soak test) | |
ATCO | 08-Jan-19 07:00 | 11-Jan-19 17:30 | 3.44 Days
Continuous |
9L01 | 9L01 Cut in for in and out addition of 951S Thickwood Hills substation. Remove bypass at substation. | |
ATCO | 15-Jan-19 07:00 | 18-Jan-19 17:30 | 3.44 Days
Continuous |
9L07 | Cut in 951S Thickwood Hills substation. | |
ATCO | 02-May-19 07:00 | 02-May-19 17:00 | 10 Hours
Continuous |
6L57 | Install temp bypass for construction of new Kinuso substation | |
ATCO | 03-Jun-19 09:00 | 29-Jul-19 17:00 | 56.33 Days
Continuous |
840S McNeill Station | 2019 McNeill Fall T/A. Arrestor install and Bird Proofing | AB-SK |
AB-BC, AB-SK & AB-MATL: refer to AESO web posting: | http://itc.aeso.ca/itc/public/reportIndex.do |
Also, | |
AB-BC, AB-SK & AB-MATL: refer to ISO Rule 203.6: | http://www.aeso.ca/rulesprocedures/18592.html |
Prepared On: | 2018-03-14 3:51:13 PM |
This document and the information contained herein are based upon information and data which by their nature contain a degree of uncertainty and are subject to change. In addition, this document may contain information and data from public sources and/or third parties, which have been assumed to be accurate and complete and have not been verified. Accordingly, the Independent System Operator, operating as the Alberta Electric System Operator (the "AESO") makes no warranty, representation or guarantee, express or implied, with respect to this document or the information contained herein, including, but not limited to, any warranty, representation or guarantee of accuracy, completeness, timeliness, reliability, availability, absence of computer virus, non- infringement, merchantability or suitability for any purpose. Under no circumstances will the AESO, its members, officers, employees, contractors or agents, or any of their respective affiliates, be liable for any errors or omissions in, or any losses, damages or claims whatsoever, whether in contract, tort or otherwise, arising from use of or reliance upon, this document or any information contained herein. © 2009 Alberta Electric System Operator. All rights reserved |