| Alberta Electric System Operator | |
| System Co-ordination Plan | |
| 2017-12-22 to 2018-01-05 | |
| Approved Outages |
| Previous Version | |
| Download CSV |
| From | To | Owner | Type | Element | Scheduled Activity | Date/Time Comments | Interconnection |
|---|---|---|---|---|---|---|---|
| 24-Jul-15 12:00 | 31-Dec-17 16:00 | ATCO | IO | 736s 601T (736s Valleyview P.R.O.P.L.),6L54 (736s Valleyviewp.R.O.P.L. - 734s Sturgeon) | customer request to permanently disconnect secondary from substation to their site | 891.21 Days
Continuous |
|
| 31-Jul-15 18:01 | 31-Aug-18 17:00 | EPCOR | Outage | Rossdale C1 | forced outage | 1,126.96 Days
Continuous |
|
| 28-Mar-17 12:00 | 31-Jan-18 12:00 | ATCO | TE | 801s Anderson RTU/SCADA | multiple SCADA cct cutovers from existing RTU to new RTU | 309.04 Days
Continuous |
|
| 22-Jul-17 07:00 | 03-Feb-18 17:30 | ATCO | TE | 822S Wolf Lake | partially disable 14.8.2 CNRL RAS A&B | 196.48 Days
Continuous |
|
| 09-Oct-17 17:00 | 30-Apr-18 16:00 | ATCO | Outage | 826s 502R (826s Marguerite Lake) | techs found scorch marks on the reactor (forced outage) | 202.96 Days
Continuous |
|
| 10-Oct-17 07:00 | 15-Feb-18 17:30 | ATCO | Outage | 734s 701T (734s Sturgeon),6L54 (736s Valleyviewp.R.O.P.L. - 734s Sturgeon),734s 704 (734s Sturgeon),734s 603 (734s Sturgeon),734s 601 (734s Sturgeon) | 6L54 and the 734S 72 KV bus will be salvaged | 128.48 Days
Continuous |
|
| 10-Oct-17 07:00 | 15-Feb-18 17:00 | EPCOR | TE | 665s Dome RTU/SCADA | 665S Dome S/S RTU | 128.46 Days
Daily |
|
| 10-Oct-17 07:00 | 15-Feb-18 17:00 | EPCOR | TE | 665S Dome | 665S Dome S/S relay blocking to 240 kV protection | 128.46 Days
Daily |
|
| 10-Oct-17 10:00 | 22-Dec-17 17:30 | ALTALINK | Trans Test | 325s 1552 (325s Leduc),325s C1 (325s Leduc) | install resister/filter bank on cap bank | 73.35 Days
Continuous |
|
| 15-Oct-17 07:00 | 29-Dec-17 16:00 | CMH, Medicine Hat | Outage | MH69s3 MH69_302 (MH69s3 South Ridge),MH69s6 MH69_611 (MH69s6 Riverview),20L (MH69S-6 Riverview - MH69S-3 South Ridge) | pole replacement work | 75.42 Days
Continuous |
|
| 30-Oct-17 08:00 | 15-Feb-18 16:00 | ATCO | TE | 7L57 (813s Little Smoky - 734s Sturgeon) | 734s Sturgeon 21-50BF/7L57 wiring changes | 108.38 Days
Continuous |
|
| 06-Nov-17 15:01 | 02-Jan-18 16:00 | ATCO | Outage | 863S Paintearth,9L948 (650s Hansman Lake - 863s Paintearth) | 240 kV switch replacement - changed to forced outage | 57.04 Days
Continuous |
|
| 27-Nov-17 08:00 | 31-Jan-18 16:00 | ENMAX | TE | ENMAX 31 | new 138kV bus differential instalation | 65.33 Days
Continuous |
|
| 02-Dec-17 06:00 | 22-Dec-17 19:00 | ATCO, ALTALINK | RB | 913L (69s North Barrhead - 732s Mitsue),9L913 (69s North Barrhead - 732s Mitsue) | new 500 kV line construction parallel to 9L913 | 20.54 Days
Daily |
|
| 11-Dec-17 08:00 | 22-Dec-17 16:00 | ENMAX | TE | ENMAX 31 RTU/SCADA | upgrade RTU | 11.33 Days
Daily |
|
| 14-Dec-17 10:00 | 05-Apr-18 17:00 | ATCO | IO | 706s 705A (706s Irish Creek) | 705C new construction | 112.25 Days
Continuous |
|
| 16-Dec-17 10:00 | 09-Jan-18 08:00 | ALTALINK | Outage | 42S Sarcee | 42s552 under outage until salvage | 23.92 Days
Continuous |
|
| 18-Dec-17 08:00 | 22-Dec-17 17:30 | ALTALINK | TE | 42s Sarcee RTU/SCADA | CSC 2017 maintenance to change default passwords | 4.4 Days
Continuous |
|
| 18-Dec-17 09:00 | 22-Dec-17 18:00 | ATCO | TE | 919s Hartley RTU/SCADA | download RTU & replace HMI | 4.38 Days
Continuous |
|
| 18-Dec-17 10:00 | 22-Dec-17 17:00 | ALBIAN | TE | 920s Jackpine RTU/SCADA | download RTU & replace HMI | 4.29 Days
Continuous |
|
| 20-Dec-17 07:00 | 22-Dec-17 17:00 | ATCO | TE | 2075S Newell | 2075s 9L1087 and 9L1035 protection relay - run 61850 network testing spot check | 2.42 Days
Continuous |
|
| 22-Dec-17 08:00 | 22-Dec-17 12:00 | ALTALINK | Outage | 838L (14s Devon - 325s Leduc),325s T2 (325s Leduc),325s Leduc 138kV Bus 2 | [SWEATD] install new name plate tags for VT6 | 4 Hours
Daily |
|
| 27-Dec-17 08:00 | 27-Dec-17 17:00 | MONTANA | TE | MATL (120s Picture Butte - Montana) | maintenance on protection equipment at Hay Lake, Marias and Great Falls | 9 Hours
Continuous |
|
| 02-Jan-18 06:30 | 31-Mar-18 18:30 | ALTALINK | RB | 551L (123s Banff - 953s Lake Louise) | line rebuild | 88.46 Days
Daily |
|
| 02-Jan-18 07:00 | 08-Jan-18 07:01 | ATCO | Outage | 801s Anderson 240kV BUS #2 | protection upgrade | 6 Days
Continuous |
|
| 02-Jan-18 07:00 | 25-Jan-18 17:00 | ALTALINK | IO | A801s 240kV Bus2 - ATCO Info | Atco maintenance | 23.42 Days
Continuous |
|
| 02-Jan-18 07:00 | 11-Jan-18 17:00 | ATCO | RB | 7L42 (751s Hill - 716s Lloydminster) | istall lightning spire | 9.42 Days
Daily |
|
| 02-Jan-18 08:00 | 04-Jan-18 16:00 | ATCO | Outage | 734s 702T (734s Sturgeon) | test new wiring to 702T and 702 breaker | 2.33 Days
Continuous |
|
| 02-Jan-18 08:00 | 02-Jan-18 12:00 | ATCO | TE | 2011s Dawes RTU/SCADA | download RTU config and check | 4 Hours
Continuous |
|
| 02-Jan-18 08:00 | 25-Jan-18 16:00 | ATCO | TE | 801S Anderson,9L59 (972s Tinchebray - 801s Anderson),9L950 (132s Ware Junction - 801s Anderson),9L933 (132s Ware Junction - 801s Anderson) | relay maintenance | 23.33 Days
Continuous |
|
| 02-Jan-18 12:00 | 02-Jan-18 16:00 | ATCO | TE | 2009s Willow Lake RTU/SCADA | download 2009S RTU config file and check | 4 Hours
Continuous |
|
| 03-Jan-18 06:30 | 04-Jan-18 20:00 | ATCO | Outage | 9L01 (888s Dover - 848s Ruth Lake),848s 9L01D1 (848s Ruth Lake),888s 9L01D2 (888s Dover) | install piles for new structures for Thickwood tap | 1.56 Days
Continuous |
|
| 03-Jan-18 08:00 | 03-Jan-18 18:00 | Syncrude | TE | Syncrude loss of visibility | ICCP server upgrade | 10 Hours
Continuous |
|
| 03-Jan-18 09:00 | 03-Jan-18 15:00 | ALTALINK, EPCOR | TE | 1043L (320p Keephills - 367s Harry Smith) | work on 1043L A protection module at 320p Keephills | 6 Hours
Continuous |
|
| 03-Jan-18 09:30 | 03-Jan-18 16:30 | ALTALINK | Outage | 633L (56s Boyle - 405s Waupisoo),405s 633 (405s Waupisoo) | breaker maintenance | 7 Hours
Daily |
|
| 03-Jan-18 10:00 | 03-Jan-18 14:00 | ATCO | TE | 885s McMillan RTU/SCADA | 885S Mcmillan RTU historian project | 4 Hours
Continuous |
|
| 04-Jan-18 06:00 | 20-Jan-18 19:00 | ALTALINK, ATCO | RB | 913L (69s North Barrhead - 732s Mitsue),9L913 (69s North Barrhead - 732s Mitsue) | new 500 kV line construction parallel to 9L913 | 16.54 Days
Daily |
|
| 04-Jan-18 07:30 | 04-Jan-18 12:30 | ALTALINK | IO | 833L / 12.2L Enmax - Info | Enmax RTU upgrade | 5 Hours
Daily |
|
| 04-Jan-18 07:30 | 04-Jan-18 14:30 | ALTALINK | Outage | 223L (159s Colinton - 150s Clyde),159s 223 (159s Colinton) | replace tank heater | 7 Hours
Daily |
|
| 04-Jan-18 08:00 | 04-Jan-18 12:00 | ENMAX, ALTALINK | Outage | 12.2TR (ENMAX 12),833L (ENMAX 2 - ENMAX 12),ENMAX 12 B138-833L (ENMAX 12) | install CAC/OAC relays and rewire device 43 for RTU upgrade | 4 Hours
Continuous |
|
| 04-Jan-18 08:30 | 04-Jan-18 09:00 | ALTALINK | Outage | 17s T2 (17s Benalto) | fix oil leaks | 30 Mins
Daily |
|
| 04-Jan-18 09:00 | 04-Jan-18 12:00 | ATCO | TE | 941s Bitumount RTU/SCADA | download RTU config and check | 3 Hours
Continuous |
|
| 04-Jan-18 09:00 | 04-Jan-18 17:00 | ALTALINK | TE | 1203L (320p Keephills - 510s Sunnybrook) | work on 1203L B prtoection at 320p Keephills and 510s Sunnybrook | 8 Hours
Continuous |
|
| 04-Jan-18 10:00 | 05-Jan-18 18:00 | ATCO | TE | 772s Youngstown RTU/SCADA | update RTU & HMI | 1.33 Days
Continuous |
|
| 04-Jan-18 10:00 | 05-Jan-18 18:00 | ATCO | TE | 768s Rowley RTU/SCADA | download RTU & update HMI program | 1.33 Days
Continuous |
|
| 04-Jan-18 12:00 | 04-Jan-18 16:00 | ATCO | TE | 2082s Dog Rib RTU/SCADA | download RTU configuration and check | 4 Hours
Continuous |
|
| 04-Jan-18 12:00 | 04-Jan-18 16:00 | ENMAX, ALTALINK | Outage | 12.1TR (ENMAX 12),832L (ENMAX 10 - ENMAX 12),ENMAX 12 B138-832L (ENMAX 12) | inInstall CAC/OAC relays and rewire device 43 for RTU upgrade | 4 Hours
Continuous |
|
| 04-Jan-18 12:30 | 04-Jan-18 16:30 | ALTALINK | IO | 832L / 12.1L Enmax - Info | Enmax RTU upgrade | 4 Hours
Continuous |
|
| 04-Jan-18 13:00 | 05-Jan-18 17:00 | ATCO | TE | 738s Virginia Hills RTU/SCADA | RTU and quickpanel configuration changes for 86T-1 indication | 28 Hours
Continuous |
|
| 05-Jan-18 06:30 | 15-Jan-18 19:00 | ALTALINK | RB | 763L (28s West Brooks - 158s Vauxhall) | safety requirement for 935L | 10.52 Days
Daily |
|
| 05-Jan-18 06:30 | 24-Jan-18 19:00 | ATCO, ALTALINK | RB | 923L (2075s Newell - 356s Milo) | safety requirement for 935L | 19.52 Days
Daily |
|
| 05-Jan-18 06:30 | 26-Jan-18 18:45 | ATCO | IO | 9L923 | AltaLink line maintenance | 21.51 Days
Daily |
|
| 05-Jan-18 07:15 | 24-Jan-18 18:45 | ALTALINK | Outage | 935L (324s Cassils - 356s Milo) | line maintenance | 19.48 Days
Continuous |
|
| 05-Jan-18 07:15 | 24-Jan-18 18:45 | ATCO | IO | 935L | AltaLink line maintenance | 19.48 Days
Continuous |
| This document and the information contained herein are based upon information and data which by their nature contain a degree of uncertainty and are subject to change. In addition, this document may contain information and data from public sources and/or third parties, which have been assumed to be accurate and complete and have not been verified. Accordingly, the Independent System Operator, operating as the Alberta Electric System Operator (the "AESO") makes no warranty, representation or guarantee, express or implied, with respect to this document or the information contained herein, including, but not limited to, any warranty, representation or guarantee of accuracy, completeness, timeliness, reliability, availability, absence of computer virus, non- infringement, merchantability or suitability for any purpose. Under no circumstances will the AESO, its members, officers, employees, contractors or agents, or any of their respective affiliates, be liable for any errors or omissions in, or any losses, damages or claims whatsoever, whether in contract, tort or otherwise, arising from use of or reliance upon, this document or any information contained herein. © 2009 Alberta Electric System Operator. All rights reserved |