Alberta Electric System Operator | |
Long Range Significant Transmission Outages for the period of 24 months starting 2017-03-11 | |
The table below contains the significant transmission outages submitted as tentative to the AESO. These Outages have not yet necessarily been approved, but are listed for awareness and coordination purposes. An Outage has been considered significant for this table if it meets any one (1) or more of the following criteria: |
|
|
|
Note: Where a transmission outage requires generation curtailments, the adjustments to generation will typically happen in the hours before the scheduled transmission outage and in the hour after the element is returned to service. | |
Previous Version | |
Download CSV | |
Owner | From | To | Duration | Element | Scheduled Activity | Affected Intertie |
---|---|---|---|---|---|---|
ATCO | 10-Jan-17 17:00 | 30-Apr-17 16:00 | 109.92 Days
Continuous |
732s 902T (732s Mitsue) | forced outage. transformer tap changer | |
ALTALINK | 26-Feb-17 14:00 | 03-Apr-17 17:00 | 36.08 Days
Continuous |
310p 6G (310p Sundance) | maintenance | |
ALTALINK | 27-Feb-17 05:30 | 21-Mar-17 17:30 | 22.46 Days
Continuous |
1053L (132s Ware Junction - 324s Cassils) | damper replacements, QA/QC checks | |
ALTALINK | 27-Feb-17 07:30 | 11-Mar-17 17:30 | 12.42 Days
Continuous |
966L (650s Hansman Lake - 932s Pemukan) | damper replacements, QA/QC checks | |
ALTALINK | 27-Feb-17 09:30 | 02-Apr-17 15:30 | 34.21 Days
Continuous |
310p 2452 (310p Sundance),310p 2352 (310p Sundance) | replacement of breaker control modules, maintenance | |
ALTALINK | 04-Mar-17 07:30 | 12-Apr-17 17:30 | 39.38 Days
Continuous |
1038L (138s Windy Flats - 237s Foothills) | damper replacement, QA/QC checks | |
ALTALINK | 06-Mar-17 09:00 | 16-Mar-17 17:00 | 10.29 Days
Continuous |
922L (310p Sundance - 17s Benalto),17S T3 (17s Benalto),17s Benalto 240 kV North Bus 1 | replace insulators on the 240kV north bus, replace 17s700 CVT, replace 17s922N & 17s35 switches | |
ATCO | 07-Mar-17 08:00 | 13-Mar-17 16:00 | 6.29 Days
Continuous |
7L64 | MITIGATION WORK | |
EPCOR | 09-Mar-17 07:00 | 17-Mar-17 17:00 | 8.38 Days
Continuous |
Tx1 outage and P2401/P2402 BF Protection Outages @ Petrolia S/S | Performing Breaker op-checks as part of relay maintenance and repairs to P2401 BF and P2402 BFrelay. | |
ENMAX | 11-Mar-17 08:00 | 11-Mar-17 12:00 | 4 Hours
Continuous |
28.80L. 28.2TR | Spring Substation Washing | |
ALTALINK | 13-Mar-17 07:00 | 13-Mar-17 07:15 | 15 Mins
Daily |
1059L (E803s-E52s-38s) EPCOR - De-energi | EPCOR requires 1059L de-energized to facilitate opening E52sEDS1 | |
ATCO | 13-Mar-17 07:00 | 17-Mar-17 17:00 | 4.42 Days
Continuous |
9L913 | Upgrade protection at both ends. | |
EPCOR | 13-Mar-17 07:00 | 17-Mar-17 17:00 | 4.42 Days
Continuous |
L2402 Breaker Outage and L2402 BF Protection Outage @ Lambton S/S | Performing Breaker op-checks as part of relay maintenance and repairs to L2402 BF relay. | |
EPCOR | 13-Mar-17 07:00 | 17-Mar-17 17:00 | 4.42 Days
Continuous |
Tx1 outage @ East Industrial S/S | Performing Relay Op-Checks. | |
ATCO | 13-Mar-17 08:00 | 15-Mar-17 16:00 | 2.33 Days
Continuous |
Kettle River_S-Telecom | 9L45 A & B TPR | |
ALTALINK | 13-Mar-17 11:00 | 16-Mar-17 17:00 | 3.25 Days
Continuous |
1209L (89s - 330p) - GOI | SCADA Equipment Upgrade | |
ATCO | 14-Mar-17 13:30 | 14-Mar-17 14:30 | 60 Mins
Continuous |
Hairy Hill_T-Telecom | 7L139 A & B TPR | |
ATCO | 14-Mar-17 16:00 | 14-Mar-17 17:00 | 60 Mins
Continuous |
Norberg_S-Telecom | Norberg_S SAR-7705 Requires a Firmware upgrade to Version 6, Norberg U/V RAS to be turned off for the duration of the work as per ATCO Risk Assessment Upgrade will take around 45 minutes to complete with only a 5 minute Service outage time. Circuits affected TPRFF131 - 7L139 A Protection TPRFF130 - 7L139 B Protection VPRN 5 - DNP/IP SCADA Norberg Sub |
|
ATCO | 15-Mar-17 08:00 | 15-Mar-17 16:00 | 8 Hours
Continuous |
Dawes_S-Telecom | 9L89A Dawes to McMillan TPR FF 135 9L89B Dawes to McMillan TPR FF 141 9L07A Dawes to Dover TPR FF 142 9L07B Dawes to Dover TPR FF 145 7L38A Algar to Horse River VIA Dawes TPR FF 146 7L38B Algar to Horse River VIA Dawes TPR FF 149 7L194A Dawes to Willow Lake TPR FF 150 7L194B Dawes to Willow Lake VPRN 5 DNP/IP SCADA |
|
ATCO | 15-Mar-17 08:30 | 15-Mar-17 09:30 | 60 Mins
Continuous |
StPaul_S-Telecom | St.Paul_S SAR-7705 Firmware upgrade to Version 6 Norberg U/V RAS to be turned off for the duration of the work as per ATCO Risk Assessment Upgrade will take around 45 minutes to complete with only a 5 minute Service outage time. TPRFF131 - 7L139 A Protection TPRFF130 - 7L139 B Protection VPRN 5 - DNP/IP SCADA St Paul Sub |
|
ALTALINK | 15-Mar-17 08:30 | 20-Mar-17 17:30 | 5.38 Days
Continuous |
310p696 Advice | Transformer maintenance | |
ATCO | 15-Mar-17 11:00 | 15-Mar-17 12:00 | 60 Mins
Continuous |
Whitby Lake_S-Telecom | Whitby Lake substation SAR-7705 requires a Firmware upgrade to Version 6 Upgrade will take around 45 minutes to complete with only a 5 minute Service outage time. Affected Circuits: TPRFF131 - 7L139 A Protection VPRN 5 - DNP/IP SCADA Whitby Lake Sub |
|
ATCO | 15-Mar-17 14:00 | 15-Mar-17 15:00 | 60 Mins
Continuous |
Bonnyville_S-Telecom | BONNYVILLE SUBSTATION - SAR-7705 UPGRADE TO FIRMWARE VERSION 6 Upgrade will take around 45 minutes to complete with only a 5 minute Service outage time. Circuits affected: TPRFF152 - 7L89 Protection (BFTT) VPRN 5 - DNP/IP SCADA Bonnyville Sub |
|
ATCO | 15-Mar-17 16:30 | 15-Mar-17 17:30 | 60 Mins
Continuous |
BearTrap_S-Telecom | WHITBY LAKE SUBSTATION - SAR-7705 UPGRADE TO FIRMWARE VERSION 6 Upgrade will take around 45 minutes to complete with only a 5 minute Service outage time. Circuits Affected: TPRFF126 - 7L24 Protection (BFTT) TPRFF127 - 7L24 Protection VPRN 5 - DNP/IP SCADA' Bear Trap Sub |
|
ATCO | 16-Mar-17 10:00 | 16-Mar-17 11:00 | 60 Mins
Continuous |
Marguerite Lake_S-Telecom | MARGUERITE LAKE SUBSTATION - SAR-7705 UPGRADE TO FIRMWARE VERSION 6 Upgrade will take around 45 minutes to complete with only a 5-minute Service outage time. The circuits will be affected: TPREE112 - 9L36 A Protection TPREE114 - 9L37 A Protection TPREE108 -7L91 A Protection TPREE109 -7L91 B Protection TPRFF151 - 7L89A Protection TPRFF152 - 7L89B Protection VPRN 5 - DNP/IP SCADA Lacorey Sub Bear Trap Sub |
|
ATCO | 16-Mar-17 12:00 | 16-Mar-17 13:00 | 60 Mins
Continuous |
LaCorey_S-Telecom | LA COREY SUBSTATION - SAR-7705 UPGRADE TO FIRMWARE VERSION 6 Upgrade will take around 45 minutes to complete with only a 5-minute Service outage time. The circuits will be affected: TPRFF151 - 7L89 Protection (BFTT) TPRFF152 - 7L89 Protection VPRN 5 - DNP/IP SCADA La corey Sub |
|
ATCO | 16-Mar-17 15:00 | 16-Mar-17 16:00 | 60 Mins
Continuous |
GrandeCentre_S-Telecom | GRAND CENTRE SUBSTATION - SAR-7705 UPGRADE TO FIRMWARE VERSION 6 Upgrade will take around 45 minutes to complete with only a 5-minute Service outage time. The circuits will be affected: TPRFF126 - 7L24 Protection SUPEE046 - Grande Centre Sub SCADA |
|
ALTALINK | 17-Mar-17 09:00 | 19-Mar-17 16:30 | 2.31 Days
Continuous |
520s T1 (520s Bennett),1201L (520s Bennett - BCH Cranbrook) | swap out transformers back to normal T1-4 to T1-3 | AB-BC |
MONTANA | 17-Mar-17 09:00 | 19-Mar-17 16:30 | 2.31 Days
Continuous |
MATL (120s Picture Butte - Montana) | align with 1201L outage | AB-MATL |
ALTALINK | 17-Mar-17 16:45 | 17-Mar-17 17:00 | 15 Mins
Daily |
1059L (E803s-E52s-38s) EPCOR - De-energi | EPCOR requires 1059L de-energized to facilitate closing E52sEDS1 | |
ENMAX | 18-Mar-17 08:00 | 18-Mar-17 10:30 | 2.5 Hours
Continuous |
162B240-RB134 | SF6 Gas RE - Sample | |
ENMAX | 18-Mar-17 10:30 | 18-Mar-17 13:30 | 3 Hours
Continuous |
162B240-RB135 | SF6 Gas Sample | |
ENMAX | 18-Mar-17 13:30 | 18-Mar-17 16:00 | 2.5 Hours
Continuous |
162B240-RB132 | SF6 Gas Sample | |
ALTALINK | 20-Mar-17 07:00 | 20-Mar-17 07:15 | 15 Mins
Daily |
908L (89s-E52s-38s) EPCOR - De-energize | EPCOR requires 908L de-energized to facilitate opening E52sEDS2 | |
EPCOR | 20-Mar-17 07:00 | 24-Mar-17 17:00 | 4.42 Days
Continuous |
L2403 Breaker Outage and L2403 BF Protection Outage @ Lambton S/S | Performing Breaker op-checks as part of relay maintenance and repairs to L2403 BF relay. | |
EPCOR | 20-Mar-17 07:00 | 25-Mar-17 17:00 | 5.42 Days
Continuous |
Tx3 outage @ JasperS/S | Performing Breaker op-checks as part of relay maintenance. | |
EPCOR | 20-Mar-17 07:00 | 25-Mar-17 17:00 | 5.42 Days
Continuous |
Tx2 outage @ East Industrial S/S | Performing Relay Op-Checks. Cutover of new ION meter. | |
ALTALINK | 20-Mar-17 08:00 | 23-Mar-17 17:00 | 3.38 Days
Continuous |
310p B Bus & 973L (310p-39s) GOI | Insulator replacement and switch maintenance | |
ENMAX | 20-Mar-17 08:00 | 31-Mar-17 16:00 | 11.33 Days
Continuous |
37.82L. 37s & Janet 138KV Bus Differential Protection | Line Protection Upgrade | |
BCH | 20-Mar-17 09:00 | 24-Mar-17 17:00 | 4.33 Days
Continuous |
5L96 (Selkirk - Vaseux Lake) | replace marker balls, shot insulators and damaged conductor | AB-BC |
ATCO | 20-Mar-17 10:15 | 20-Mar-17 11:15 | 60 Mins
Continuous |
Strome_T-Telecom | STROME TOWER - SAR-7705 UPGRADE TO FIRMWARE VERSION 6 Upgrade will take around 45 minutes to complete with only a 5-minute Service outage time. The circuits will be affected: SUPEE090 - Heisler SCADA TPRET071 - 7L702 B TPRET070 - 7L702 A TPRET035 - 7L224 A TPRET036 - 7L224 B |
|
ALTALINK | 20-Mar-17 11:00 | 23-Mar-17 17:00 | 3.25 Days
Continuous |
1212L (89s - 12s) - GOI | SCADA Equipment Upgrade | |
ATCO | 20-Mar-17 11:30 | 20-Mar-17 12:30 | 60 Mins
Continuous |
Heatburg_S-Telecom | HEATBURG SUBSTATION - SAR-7705 UPGRADE TO FIRMWARE VERSION 6 5-minute Service outage time to the following ccts; SUPEP064 - Heatburg SCADA TPRET031 - 7L159 A TPRET032 - 7L159 B TPRET072 - 7L159 A TPRET074 - 7L159 B |
|
ENMAX | 20-Mar-17 12:00 | 20-Mar-17 16:00 | 4 Hours
Continuous |
23.80L. 23.4TR | Spring Substation Washing | |
ATCO | 20-Mar-17 14:15 | 20-Mar-17 15:15 | 60 Mins
Continuous |
Elnora_T-Telecom | ELNORA TOWER - SAR-7705 UPGRADE TO FIRMWARE VERSION 6 5-minute Service outage time to the following ccts;. SUPEP042 - Ghostpine SCADA SUPEP058 - Three Hills SCADA SUPEP064 - Heatburg SCADA TPRET031 - 7L159 A TPRET032 - 7L159 B TPRET072 - 7L159 A TPRET074 - 7L159 B |
|
ATCO | 20-Mar-17 16:00 | 20-Mar-17 17:00 | 60 Mins
Continuous |
Chain Lakes_T-Telecom | CHAIN LAKES TOWER - SAR-7705 UPGRADE TO FIRMWARE VERSION 6 5-minute Service outage time to the following ccts;. RASEE012 - 9L20 RAS A Cordel/Newell, redundant CHB will remain in service RASEE013 - 9L20 RAS A Nevis/Newell, redundant CHB will remain in service RASEE014 - 9L912 RAS A Nevis/Newell, redundant CHB will remain in service TPREE094 - 9L59 A TPREE095 - 9L59 B |
|
ALTALINK | 21-Mar-17 07:30 | 21-Mar-17 17:30 | 10 Hours
Daily |
37s T6 (Tx18309) GOI | Replace Slack Span Insulators on Secondary Bus between T6 and 37s4 | |
ALTALINK | 21-Mar-17 07:30 | 09-Apr-17 18:30 | 19.46 Days
Continuous |
172L (370s - L181s) - GOI | Line Rebuild | |
ATCO | 21-Mar-17 08:00 | 21-Mar-17 16:00 | 8 Hours
Continuous |
Birchwood-S-Telecom | Birchwood Sub TOWER - SAR-7705 UPGRADE TO FIRMWARE VERSION 6 5-minute Service outage time to the following ccts;. TPRNF005 - 9L57 A TPRNF006 - 9L57 B TPRFF165 - 9L47 A TPRFF166 - 9L47 B "VPRN 5 - DNP/IP SCADA Yeo Sub Birchwood Creek Sub Birchwood Creek Sub IPP" "VPRN 2 - Telecom Yeo Sub Birchwood Creek Sub" "VPRN 4 - Electric/Metering Yeo Sub Birchwood Creek Sub" "VPLS 500 - Corporate Yeo Sub Birchwood Creek Sub" |
|
ATCO | 21-Mar-17 08:00 | 23-Mar-17 16:00 | 2.33 Days
Continuous |
7L27 | replace rotten crossarms | |
ALTALINK | 21-Mar-17 08:00 | 23-Mar-17 17:00 | 2.38 Days
Continuous |
17s34 (906L-42s) - GOI | Replace 17s34 Airbreak (Like for Like) | |
ATCO | 21-Mar-17 09:00 | 21-Mar-17 10:00 | 60 Mins
Continuous |
Anderson_T-Telecom | ANDERSON TOWER - SAR-7705 UPGRADE TO FIRMWARE VERSION 6 5-minute Service outage time to; RASEE012 - 9L20 RAS A Cordel/Newell RASEE013 - 9L20 RAS A Nevis/Newell RASEE014 - 9L912 RAS A Nevis/Newell TPREE094 - 9L59 A TPREE095 - 9L59 B TPREE096 - 7L128 A TPREE063 - 7L128 B TPREE105 - 7L85 Breaker Fail RASEE023 - Wintering Hills/Anderson RAS RASEE024 - Nevis/Wheatland RAS SUPEE049 - Michichi SCADA SUPEE051 - Bullpound PLC IPPEE005 - Wheatland IPP SCADA SUPEE085 - Wintering Hills SCADA VPRN 5 - DNP/IP SCADA Rowley |
|
ATCO | 21-Mar-17 10:30 | 21-Mar-17 11:30 | 60 Mins
Continuous |
Fleet _T-Telecom | FLEET TOWER - SAR-7705 UPGRADE TO FIRMWARE VERSION 6 5-minute Service outage time to; RASEE012 - 9L20 RAS A Cordel/Newell RASEE013 - 9L20 RAS A Nevis/Newell RASEE014 - 9L912 RAS A Nevis/Newell SUPEE047 - Ribstone SCADA TPREE094 - 9L59 A TPREE095 - 9L59 B |
|
ATCO | 21-Mar-17 13:30 | 21-Mar-17 14:30 | 60 Mins
Continuous |
Monitor_S_Telecom | MONITOR SUBSTATION- SAR-7705 UPGRADE TO FIRMWARE VERSION 6 5-minute Service outage time for; SUPEE048 - Monitor SCADA TPRET035 - 7L224 A TPRET036 - 7L224 B TPREE054 / 7L110 DTT CH C |
|
ATCO | 21-Mar-17 16:30 | 21-Mar-17 17:30 | 60 Mins
Continuous |
Oyen_S-Telecom | OYEN SUBSTATION- SAR-7705 UPGRADE TO FIRMWARE VERSION 6 5-minute Service outage time to; TPRET028 - 7L760 A Protection TPRET029 - 7L760 B Protection TPREE057 - 7L760 DTT CH C SUPEE003 - Oyen SCADA |
|
ATCO | 22-Mar-17 10:30 | 22-Mar-17 11:30 | 60 Mins
Continuous |
Empress_S_Telecom | EMPRESS SUBSTATION (ALTA LINK) - SAR-7705 UPGRADE TO FIRMWARE VERSION 6 Upgrade will take around 45 minutes to complete with only a 5-minute Service outage time. The circuits will be affected: SUPEE055 - McNEILL SCADA TPRET030 - 7L830 TPRET028 - 7L760 A Protection TPRET029 - 7L760 B Protection |
|
ATCO | 22-Mar-17 14:30 | 22-Mar-17 15:30 | 60 Mins
Continuous |
McNeill_S-Telecom | McNEILL SUBSTATION - SAR-7705 UPGRADE TO FIRMWARE VERSION 6 Upgrade will take around 45 minutes to complete with only a 5-minute Service outage time. The circuits will be affected: SUPEE055 - McNEILL SCADA TPRET030 - 7L830 |
|
ENMAX | 23-Mar-17 08:00 | 23-Mar-17 12:00 | 4 Hours
Continuous |
28.80L. 28.2TR | Spring Substation Washing | |
ATCO | 23-Mar-17 08:00 | 23-Mar-17 16:00 | 8 Hours
Continuous |
WillowLake_S-Telecom | SAR OS Upgrade. CCTS TPRFF138 - 7L36 A Protection TPRFF139 - 7L36 B Protection TPRFF149 - 7L194 A Protection TPRFF150 - 7L150 A Protection "VPRN 5 - DNP/IP SCADA Willow Lake Sub Willow Lake IPP" "VPRN 2 - Telecom Willow Lake Sub" "VPRN 4 - Electric/Metering Willow Lake Sub" "VPLS 500 - Corporate Willow Lake Sub" |
|
ATCO | 23-Mar-17 08:00 | 23-Mar-17 16:00 | 8 Hours
Continuous |
Algar_S-Telecom | SAR OS Upgrade. CCTS TPRFF145 - 7L38 A Protection TPRFF146 - 7L38 B Protection "VPRN 5 - DNP/IP SCADA Algar Sub" "VPRN 2 - Telecom Algar Sub" "VPRN 4 - Electric/Metering Algar Sub" "VPLS 500 - Corporate Algar Lake Sub" |
|
ALTALINK | 23-Mar-17 08:00 | 23-Mar-17 17:00 | 9 Hours
Daily |
244s T1 & T2 De-energized | Investigate paralleling issues for T1 and T2. Out of step relay operates when both transformers are on tap 1 and shouldn't. | |
ATCO | 24-Mar-17 08:00 | 26-Mar-17 17:00 | 2.38 Days
Continuous |
7L75 | LINE MITIGATION | |
ENMAX | 24-Mar-17 12:00 | 24-Mar-17 16:00 | 4 Hours
Continuous |
23.80L. 23.4TR | Spring Substation Washing | |
ALTALINK | 25-Mar-17 16:45 | 25-Mar-17 17:00 | 15 Mins
Daily |
908L (89s-E52s-38s) EPCOR - De-energize | EPCOR requires 908L de-energized to facilitate closing E52sEDS2 | |
EPCOR | 27-Mar-17 07:00 | 31-Mar-17 17:00 | 4.42 Days
Continuous |
Tx4 outage @ JasperS/S | Performing Breaker op-checks as part of relay maintenance. | |
EPCOR | 27-Mar-17 07:00 | 04-Apr-17 17:00 | 8.42 Days
Continuous |
Tx2 outage and P2404/P2405 BF Protection Outages @ Petrolia S/S | Performing Breaker op-checks as part of relay maintenance and repairs to P2404 BF and P2405 BFrelay. | |
ALTALINK | 27-Mar-17 08:00 | 07-Apr-17 17:30 | 11.4 Days
Continuous |
86s T1 GOI | Replace 240 kV and 138 kV bushings. Misc TX maintenance. | |
ALTALINK | 27-Mar-17 09:00 | 27-Mar-17 10:00 | 60 Mins
Daily |
310p2152 Advice | Trip test from 310p2452 breaker fail protection. | |
ALTALINK | 27-Mar-17 11:00 | 30-Mar-17 17:00 | 3.25 Days
Continuous |
1206L (89s - 12s) - GOI | SCADA Equipment Upgrade | |
ALTALINK | 28-Mar-17 07:30 | 31-Mar-17 17:30 | 3.42 Days
Continuous |
916L (42s - 5s) - GOI | Replace Steel Members | |
ALTALINK | 28-Mar-17 07:30 | 03-Apr-17 17:30 | 6.42 Days
Continuous |
1064L (74s - 102s) - GOI | Damper Replacements | |
ATCO | 28-Mar-17 08:00 | 28-Mar-17 16:00 | 8 Hours
Continuous |
Stoney Mtn_T-Telecom | SAR OS Upgrade & TPR cuicuits | |
ATCO | 28-Mar-17 08:30 | 30-Mar-17 16:00 | 2.31 Days
Continuous |
7L64 | replace 4 structures for line mitigation | |
EPCOR | 29-Mar-17 07:00 | 29-Mar-17 17:00 | 10 Hours
Continuous |
TX1 Bellamy | Repair | |
ATCO | 29-Mar-17 08:00 | 31-Mar-17 16:00 | 2.33 Days
Continuous |
Ruth Lake_S-Telecom | SAR OS Upgrade CCTS TPRFF169 - 9L58 A Protection TPRFF170 - 9L58 B Protection |
|
ENMAX | 01-Apr-17 08:00 | 01-Apr-17 16:00 | 8 Hours
Continuous |
932L | Doble PT 932L | |
ALTALINK | 01-Apr-17 08:00 | 02-Apr-17 17:30 | 1.4 Days
Continuous |
86s T1 & 240 kV Bus GOI | Breaker maintenance 86s1752, switch repair - 86s12A, switch maintenance. | |
ALTALINK | 02-Apr-17 17:01 | 15-Apr-17 17:00 | 13 Days
Continuous |
916L (42s-5s) GOI [SWCRR] | SWCRR: Foundation work for future U/G Riser structures | |
ALTALINK | 02-Apr-17 17:01 | 15-Apr-17 17:00 | 13 Days
Continuous |
693L (42s-C10s) GOI [SWCRR] | SWCRR Foundation work for future U/G Riser structures | |
ALTALINK | 03-Apr-17 07:00 | 06-Apr-17 17:00 | 3.42 Days
Continuous |
89s T1(TX18724,TX18725,TX18726) - GOI | SCADA Equipment Upgrade | |
EPCOR | 03-Apr-17 07:00 | 07-Apr-17 17:00 | 4.42 Days
Continuous |
Tx1 outage @ JasperS/S | Performing Breaker op-checks as part of relay maintenance. | |
EPCOR | 03-Apr-17 07:00 | 07-Apr-17 17:00 | 4.42 Days
Continuous |
L2404 Breaker Outage and L2404 BF Protection Outage @ Lambton S/S | Performing Breaker op-checks as part of relay maintenance and repairs to L2404 BF relay. | |
ATCO | 03-Apr-17 08:00 | 05-Apr-17 17:00 | 2.38 Days
Continuous |
7L89 | Pole change on 7L89/7L91 double cct line, 721s radial fed from 700s | |
ALTALINK | 03-Apr-17 10:30 | 04-Apr-17 17:30 | 31 Hours
Continuous |
905L (19s Wabamun - 37s North Calder),37s 76 (37s North Calder),37s 82 (37s North Calder) | 37s79 switch maintenance | |
ALTALINK | 04-Apr-17 07:00 | 04-Apr-17 18:00 | 11 Hours
Daily |
89s 240 kV West Bus GOI | Switch maintenance - 89s1 and 89s9 | |
ALTALINK | 04-Apr-17 07:30 | 08-Apr-17 17:30 | 4.42 Days
Continuous |
1065L (74s - 102s) - GOI | Damper Replacements | |
ATCO | 05-Apr-17 08:00 | 06-Apr-17 18:00 | 1.42 Days
Continuous |
789S 706C,789S 700 BUS 1,7L58,7L59,789S 701R | Tie new 144kV bus to old 144kV bus @ 789s for construction, 706C and 701R will be unavailable for dispatch, 7L58 and 7L59 will be open ended at 789s, 7L62 will be tied to 7L64 via bypass switch 7L62D2
AWAITING SLD SHOWING NEW BUS ISOLATION PTS. ADD PTS TO THIS PERMIT ONCE KNOWN (DRS) |
|
ALTALINK | 05-Apr-17 08:00 | 15-Apr-17 17:00 | 10.38 Days
Continuous |
1043L (320p Keephills - 816s Petrolia) | Install foundations for future line tap to new 289s | |
ALTALINK, ATCO | 05-Apr-17 08:30 | 05-Apr-17 17:30 | 9 Hours
Continuous |
72s 752 (72s Leismer),72s 852 (72s Leismer),9L990 (72s Leismer - 2049s Kettle River) | 72s19 switch maintenance | |
ALTALINK | 09-Apr-17 07:30 | 10-Apr-17 17:30 | 1.42 Days
Continuous |
985L (74s - C25s) - GOI | Damper Replacements | |
ALTALINK | 10-Apr-17 07:00 | 10-Apr-17 17:00 | 10 Hours
Daily |
42s T2 and 138kV South Bus - GOI | Installing pollution monitors | |
EPCOR | 10-Apr-17 07:00 | 14-Apr-17 17:00 | 4.42 Days
Continuous |
L2405 Breaker Outage and L2405 BF Protection Outage @ Lambton S/S | Performing Breaker op-checks as part of relay maintenance and repairs to L2405 BF relay. | |
ALTALINK | 10-Apr-17 08:00 | 11-Apr-17 18:00 | 1.42 Days
Continuous |
L674s725W (725L) Leth Open - Info | City Of Lethbridge L674s725W Breaker Maintenance | |
ALTALINK | 11-Apr-17 07:00 | 11-Apr-17 17:00 | 10 Hours
Daily |
42s T1 and 240kV North Bus - GOI | Installing pollution monitors | |
ALTALINK | 11-Apr-17 07:30 | 12-Apr-17 17:30 | 1.42 Days
Continuous |
1003L (74s - C25s) - GOI | Damper Replacements | |
NOVACORP | 11-Apr-17 09:00 | 13-Apr-17 17:00 | 2.33 Days
Continuous |
330s Nova Corp 138kV Bus 1B,330s BR_50 (330s Nova Corp) | maintenance on BR-50 | |
ALTALINK | 12-Apr-17 07:00 | 12-Apr-17 17:00 | 10 Hours
Daily |
42s T2 and 240kV South Bus - GOI | Installing pollution monitors | |
ALTALINK | 12-Apr-17 08:00 | 13-Apr-17 18:00 | 1.42 Days
Continuous |
L674s725E (725L) Leth Open - Info | City Of Lethbridge L674s725E Breaker Maintenance | |
EPCOR | 17-Apr-17 07:00 | 17-Apr-17 17:00 | 10 Hours
Continuous |
711L - Inland | Line Maintenance & Upgrades | |
ATCO | 17-Apr-17 13:00 | 20-Apr-17 17:00 | 3.17 Days
Continuous |
7L90 | replace poles for road crossing | |
EPCOR | 18-Apr-17 07:00 | 28-Apr-17 17:00 | 10.42 Days
Continuous |
P2406 BF Protection and a 1044L Line Outage @ Jasper S/S and Petrolia S/S | Performing Breaker op-checks as part of relay maintenance and repairs to P2406 BF relay. | |
ALTALINK | 18-Apr-17 12:30 | 29-Apr-17 17:30 | 11.21 Days
Continuous |
42s T1(Tx 18508) - GOI | Bushing replacements & doble testing | |
ATCO | 19-Apr-17 08:00 | 19-Apr-17 16:00 | 8 Hours
Continuous |
Irish Creek_S-Telecom,Bonnyville_S-Telecom | Teleprotection cct Bonnyville to Irish Creek, 7L53 CH A/B require to be moved to a new telecom multiplex one channel at a time. This will require a short 5-10 min outage to the teleprotection cct for cable connections and testing. | |
ATCO | 19-Apr-17 10:00 | 19-Apr-17 14:00 | 4 Hours
Continuous |
Bonnyville_S-Telecom,Lindbergh_S-Telecom | 7L53 TPR CHC (TPR-EE-060) and 7L53 IRAS (TPR-FF143) Bonnyville and Lindbergh ccts are to moved over to a new telecom multiplex. This will require short outages (<10 min each) to each teleprotection ccts for cable connections and testing. Anti-islanding IRAS Bville and Irish Ck channels have no redundancy and both are required in service to properly operate, thus IRAS will be OOS for approx 20 min total. Pengrowth DG at 969s will be separated from the grid or offline. | |
ATCO | 20-Apr-17 08:00 | 20-Apr-17 16:00 | 8 Hours
Continuous |
Bonnyville_S-Telecom,BearTrap_S-Telecom,700S 7L24 Protection Relay | Teleprotection cct Bonneville to Beartrap , TPR-EE-127 on line 7L24 to be moved over to new telecom multiplex. This will require a short outage (<10 minutes) to the teleprotection cct for cable connections and testing. | |
ATCO | 20-Apr-17 08:00 | 20-Apr-17 16:00 | 8 Hours
Continuous |
Bourque_S-Telecom,Bonnyville_S-Telecom | Teleprotection ccts 0n 7L146A and B from Bonnyville to Bourque lake require to be moved over to new telecom mux system. TPR-FF-101/102 one cct at a time. This will require short 5-10 min outages for cable moves and cct testing. | |
EPCOR | 22-Apr-17 07:00 | 23-Apr-17 17:00 | 1.42 Days
Continuous |
711L - Inland | Line Maintenance & Upgrades | |
EPCOR | 23-Apr-17 04:00 | 23-Apr-17 10:00 | 6 Hours
Continuous |
240kV Tx3 Outage @ Lambton S/S | Performing Relay Op-Checks as part of relay maintenance. | |
ALTALINK | 23-Apr-17 13:00 | 01-May-17 17:00 | 8.17 Days
Continuous |
38s T4,240kV Bus 2 & 138kV Bus 3 GOI | Replace T4, replace 38s1, replace insulators on 138kV bus 3 & 240kV bus 2 | |
ALTALINK | 24-Apr-17 07:00 | 24-Apr-17 07:15 | 15 Mins
Daily |
1059L (E803s-E52s-38s) EPCOR - De-energi | EPCOR requires 1059L de-energized to facilitate opening E52sEDS1 | |
ATCO | 24-Apr-17 07:00 | 24-Apr-17 12:00 | 5 Hours
Continuous |
7L73,730S 703 | 704 Breaker fail testing, Boucher Ck radial fed from 800s. | |
ALTALINK | 24-Apr-17 07:00 | 27-Apr-17 17:00 | 3.42 Days
Continuous |
89s T2(TX18727,TX18728,TX18733) - GOI | SCADA Equipment Upgrade | |
EPCOR | 24-Apr-17 07:00 | 28-Apr-17 17:00 | 4.42 Days
Continuous |
TX1 @ East industrial | Doble | |
ALTALINK | 24-Apr-17 09:30 | 27-Apr-17 17:30 | 3.33 Days
Continuous |
900L (17s - 63s) - GOI | Component Replacements | |
ATCO | 25-Apr-17 08:00 | 29-Apr-17 12:00 | 4.17 Days
Continuous |
930S Synchronous Condenser | Sync Condenser turnaround, unavailable for dispatch | |
ALTALINK | 26-Apr-17 07:30 | 26-Apr-17 17:30 | 10 Hours
Daily |
523s880 (880L) GOI | Wire & test trip relay for future station expansion project | |
ALTALINK | 28-Apr-17 08:00 | 11-May-17 17:00 | 13.38 Days
Continuous |
693L/916L GOI [SWCRR] - Placeholder | SWCRR: Foundation work for future U/G Riser structures | |
ALTALINK | 28-Apr-17 09:30 | 26-May-17 17:30 | 28.33 Days
Continuous |
777L (48s - 245s) - GOI | Relocate Structures | AB-BC |
ALTALINK | 28-Apr-17 16:45 | 28-Apr-17 17:00 | 15 Mins
Daily |
1059L (E803s-E52s-38s) EPCOR - De-energi | EPCOR requires 1059L de-energized to facilitate closing E52sEDS1 | |
EPCOR | 01-May-17 07:00 | 05-May-17 17:00 | 4.42 Days
Daily |
1045L Line Outage @ Jasper S/S and 310P Sundance S/S | Performing Breaker op-checks as part of relay maintenance and cutover over new line metering. | |
EPCOR | 01-May-17 07:00 | 05-May-17 17:00 | 4.42 Days
Continuous |
TX4 @ Jasper | CVT replacements | |
ALTALINK | 01-May-17 07:30 | 02-May-17 17:30 | 1.42 Days
Continuous |
1061L (12s - 681s) - GOI | Damper Replacements, QA/QC checks | |
ALTALINK | 01-May-17 07:30 | 04-May-17 17:30 | 3.42 Days
Continuous |
807AL/807L (410s - 233s - I_402s) - GOI | Damper Replacements | |
EPCOR | 02-May-17 07:00 | 02-May-17 17:00 | 10 Hours
Continuous |
Tx4 and Tx2 outages @ Cloverbar S/S | Performing Breaker op-checks as part of relay maintenance. | |
ENMAX | 02-May-17 08:00 | 05-May-17 16:00 | 3.33 Days
Continuous |
65.1TR. 65s 138KV South Bus | 54.81 line energization | |
ATCO | 02-May-17 11:00 | 19-May-17 13:00 | 17.08 Days
Continuous |
853S 702T | 853S 702T TRANSFORMER CLASS2 MAJOR TESTING
702T Oil reclaiming, 702T major testing; 502VR major testing Load will be carried by 701T and 501VR ON MAY 10 2017 (08:30 to 17:00) EXPAND THE 702T GOI TO INCLUDE 700D1; 7L113D2; 700PT2X1; 700PT2X2; 700PT2Y 7L113 open ended, all load still on 701T at the end of the day on May 10 the GOI will shrink back down to the original points |
|
ALTALINK | 03-May-17 07:30 | 04-May-17 17:30 | 1.42 Days
Continuous |
942L (71s - 681s) - GOI | Damper Replacements | |
EPCOR | 03-May-17 08:00 | 03-May-17 14:00 | 6 Hours
Continuous |
915L outage @ Cloverbar S/S and 38s S/S | Performing Breaker op-checks as part of relay maintenance. | |
ATCO | 05-May-17 07:00 | 09-May-17 17:00 | 4.42 Days
Continuous |
7L62 | Reroute line into new Keg River substation, modify 7L62D3 from DLO to LS/LD Work Sequence May 4 PM - transfer 5L457 to adjacent sub May 5 AM - Issue GOI 2-33607A (Isol. pts - 702A, 7L62D2, 7L62PTX @ 789s, 7L62D4, 701TD1 @ 797s) - line work, modify 7L62D3 - Plains Midstream outage reqd May 5 PM - Collapse GOI to 7L62D3 @ 797s - issue 2-33607B, then release 2-33607A - re-energize 797s May 6 AM - restore 5L457 external load transfer to normal May 5 PM - May 9 PM - continue 7L62 line reroute into 789s |
|
ALTALINK | 05-May-17 07:30 | 14-May-17 17:30 | 9.42 Days
Continuous |
1054L (12s - 13s) - GOI | Damper Replacements | |
ALTALINK | 07-May-17 13:00 | 18-May-17 17:00 | 11.17 Days
Continuous |
42s T2 GOI | Doble test and MR maintenance | |
ALTALINK | 08-May-17 07:00 | 08-May-17 07:15 | 15 Mins
Daily |
908L (89s-E52s-38s) EPCOR - De-energize | EPCOR requires 908L de-energized to facilitate opening E52sEDS2 | |
EPCOR | 08-May-17 07:00 | 12-May-17 17:00 | 4.42 Days
Daily |
1098L Line Outage @ Jasper S/S and Poundmaker S/S | Cutover over new line metering. | |
EPCOR | 08-May-17 07:00 | 12-May-17 17:00 | 4.42 Days
Continuous |
TX2 @ Poundmaker | Doble | |
EPCOR | 08-May-17 07:00 | 12-May-17 17:00 | 4.42 Days
Continuous |
915L @ Cloverbar -East Edmonton | CT replacements | |
EPCOR | 08-May-17 07:00 | 12-May-17 17:00 | 4.42 Days
Continuous |
TX2 @ East Industrial | Doble | |
EPCOR | 08-May-17 07:00 | 23-May-17 17:00 | 15.42 Days
Daily |
CV5 @ Castledowns to Victoria | Inspection and repair | |
ALTALINK | 08-May-17 11:00 | 11-May-17 17:00 | 3.25 Days
Continuous |
910L (89s - 288s) - GOI | SCADA Equipment Upgrade | |
ENMAX | 09-May-17 08:00 | 09-May-17 16:00 | 8 Hours
Continuous |
918L | Doble PT 918 | |
ATCO | 09-May-17 09:30 | 11-May-17 16:00 | 2.27 Days
Continuous |
749S 703,749S 704 | 749S 7L33 Sync Bypass Demo / Maint Sw Removal Remove Sync Circuit bypass switches and Maintenance Switch CG&E to be fed radially from 845S |
|
ENMAX | 11-May-17 08:00 | 11-May-17 16:00 | 8 Hours
Continuous |
832L. 10B138-832. 12B138-832 | SF6 Gas Sample 10B138-832, Doble 12B138-832 | |
EPCOR | 12-May-17 07:00 | 12-May-17 17:00 | 10 Hours
Continuous |
Bus 2 CVT @ Poundmaker | Doble | |
EPCOR | 12-May-17 07:00 | 12-May-17 17:00 | 10 Hours
Continuous |
908L East Industrial - Ellerslie | Doble | |
ALTALINK | 12-May-17 07:00 | 12-May-17 17:00 | 10 Hours
Daily |
908L (89s-E52s-38s) EPCOR - Advice | EPCOR to Doble 908L | |
ENMAX | 13-May-17 08:00 | 24-May-17 16:00 | 11.33 Days
Continuous |
28.80L. 28s & Sarcee 138KV Bus Differential Protection | Line Protection Upgrade | |
EPCOR | 15-May-17 07:00 | 19-May-17 17:00 | 4.42 Days
Continuous |
TX3 @ Poundmaker | Doble | |
ALTALINK | 15-May-17 11:00 | 18-May-17 17:00 | 3.25 Days
Continuous |
914L (89s - 86s) - GOI | SCADA Equipment Upgrade | |
ATCO | 16-May-17 08:00 | 18-May-17 15:00 | 2.29 Days
Continuous |
7L81,791S 702 | Install new 7L81 RASA & RASB | |
ENMAX | 17-May-17 08:00 | 18-May-17 16:00 | 1.33 Days
Continuous |
833L. 12B138-833 | HV Breaker Inspection, Doble 12B138-833. | |
EPCOR | 19-May-17 07:00 | 19-May-17 17:00 | 10 Hours
Continuous |
Bus 1 CVT @ Poundmaker | Doble | |
ALTALINK | 22-May-17 08:30 | 22-May-17 12:30 | 4 Hours
Daily |
648s29 (T3 & 954L) - Advice | Trip testing required for 648s749E protection replacement | |
EPCOR | 23-May-17 07:00 | 23-May-17 17:00 | 10 Hours
Continuous |
930L Poundmaker to North Calder | Doble | |
ALTALINK | 23-May-17 07:00 | 25-May-17 17:00 | 2.42 Days
Continuous |
89s1352,89s1452 - GOI | SCADA Equipment Upgrade | |
ENMAX | 23-May-17 08:00 | 04-Jun-17 16:00 | 12.33 Days
Continuous |
30.81L | (SWCRR)-Temporary tie in to 35 Sub. Energization of HV switchgear at 35 sub through 30.81 | |
ALTALINK | 23-May-17 09:30 | 25-May-17 17:30 | 2.33 Days
Continuous |
526AL (638s-526L367-526L220) - GOI | Line maintenance | |
EPCOR | 24-May-17 07:00 | 24-May-17 17:00 | 10 Hours
Continuous |
1098L Poundmaker to Jasper | Doble | |
ATCO | 24-May-17 09:00 | 25-May-17 17:00 | 1.33 Days
Continuous |
813S SVC | SVC maintenance, SVC not available for dispatch | |
EPCOR | 29-May-17 07:00 | 02-Jun-17 17:00 | 4.42 Days
Continuous |
TX1 @ Petrolia | Doble | |
ENMAX | 29-May-17 08:00 | 09-Jun-17 16:00 | 11.33 Days
Continuous |
24.83L. 24s & 74s 138KV Bus Differential Protection | Line Protection Upgrade on 24.83L | |
EPCOR | 02-Jun-17 07:00 | 02-Jun-17 17:00 | 10 Hours
Continuous |
TX1 CVT @ Petrolia | Doble | |
EPCOR | 05-Jun-17 07:00 | 06-Jun-17 17:00 | 1.42 Days
Continuous |
P2401 @ Petrolia | Doble | |
EPCOR | 07-Jun-17 07:00 | 08-Jun-17 17:00 | 1.42 Days
Continuous |
P2402 @ Petrolia | Doble | |
ENMAX | 08-Jun-17 08:00 | 08-Jun-17 16:00 | 8 Hours
Continuous |
24.83L. 24B138-24.83 | Doble breaker | |
EPCOR | 09-Jun-17 07:00 | 09-Jun-17 17:00 | 10 Hours
Continuous |
1043L CVT @ Petrolia - | Doble | |
EPCOR | 09-Jun-17 07:00 | 21-Jun-17 17:00 | 12.42 Days
Continuous |
1055L ( Argyll - Petrolia ) | Steel Pole Refurbishment | |
EPCOR | 12-Jun-17 07:00 | 13-Jun-17 17:00 | 1.42 Days
Continuous |
P2403 BKR @ Petrolia | Doble | |
EPCOR | 14-Jun-17 07:00 | 15-Jun-17 17:00 | 1.42 Days
Continuous |
P2406 BKR @ Petrolia | Doble | |
ATCO | 14-Jun-17 08:00 | 14-Jun-17 16:30 | 8.5 Hours
Continuous |
7L27 (834s Wesley Creek - A793s West Peace River),793S 705 | 793S 705 BREAKER SF6 HGF PARTIAL TESTING 7L27 Open ended for the duration of the work |
|
ALTALINK | 17-Jun-17 07:00 | 08-Jul-17 17:00 | 21.42 Days
Continuous |
928L (17s-42s) GOI [SWCRR] | SWCRR Line relocate: Set structures and string | |
ALTALINK | 17-Jun-17 07:00 | 08-Jul-17 17:00 | 21.42 Days
Continuous |
906L (17s-42s) GOI [SWCRR] | SWCRR String new alignment | |
EPCOR | 19-Jun-17 07:00 | 20-Jun-17 17:00 | 1.42 Days
Continuous |
P2405 BKR @ Petrolia | Doble | |
EPCOR | 21-Jun-17 07:00 | 23-Jun-17 17:00 | 2.42 Days
Continuous |
TX2 @ Petrolia | Maint | |
EPCOR | 22-Jun-17 07:00 | 06-Jul-17 17:00 | 14.42 Days
Continuous |
1056L ( Argyll - Bellamy ) | Steel Pole Refurbishment | |
EPCOR | 26-Jun-17 07:00 | 26-Jun-17 17:00 | 10 Hours
Continuous |
TX2 @ Cloverbar | Maint | |
EPCOR | 26-Jun-17 07:00 | 30-Jun-17 17:00 | 4.42 Days
Continuous |
P2404 BKR @ Petrolia | Maint | |
EPCOR | 27-Jun-17 07:00 | 27-Jun-17 17:00 | 10 Hours
Continuous |
TX3 @ Cloverbar | Maint | |
EPCOR | 28-Jun-17 07:00 | 28-Jun-17 17:00 | 10 Hours
Continuous |
TX4 @ Cloverbar | Maint | |
EPCOR | 03-Jul-17 07:00 | 07-Jul-17 17:00 | 4.42 Days
Continuous |
J2406 @ Jasper | Maint | |
ALTALINK | 04-Jul-17 08:00 | 04-Jul-17 12:00 | 4 Hours
Daily |
252s (704L/7L50) - GOI | Cut Open Point A into 704L-10. Open Point A needed to isolate 252s2 for breaker replacement later on. | |
EPCOR | 05-Jul-17 07:00 | 07-Jul-17 17:00 | 2.42 Days
Continuous |
TX3 @ Poundmaker | Tapchanger maint | |
EPCOR | 07-Jul-17 07:00 | 08-Jul-17 17:00 | 1.42 Days
Continuous |
TX1 @ Genesee | Tapchanger maint | |
EPCOR | 07-Jul-17 07:00 | 19-Jul-17 17:00 | 12.42 Days
Continuous |
1044L ( Jasper - Petrolia ) | Steel Pole Refurbishment | |
EPCOR | 09-Jul-17 07:00 | 09-Jul-17 17:00 | 10 Hours
Continuous |
TX2 @ Genesee | Tapchanger maint | |
EPCOR | 10-Jul-17 07:00 | 14-Jul-17 17:00 | 4.42 Days
Continuous |
J2405 @ Jasper | Maint | |
ALTALINK | 10-Jul-17 12:15 | 21-Jul-17 16:15 | 11.17 Days
Continuous |
163s T2 (Tx18482) GOI | Replace 163s T2 Bushings, T2 Maintenance | |
ALTALINK | 11-Jul-17 07:30 | 16-Jul-17 17:30 | 5.42 Days
Continuous |
39s T1(Tx 18107) - GOI | Replacing bushings | |
ALTALINK | 14-Jul-17 10:00 | 14-Jul-17 13:00 | 3 Hours
Daily |
252s (704L/7L50) - GOI | Close Open Point C To 704L-10. | |
EPCOR | 16-Jul-17 07:00 | 18-Jul-17 17:00 | 2.42 Days
Continuous |
TX1 @ Cloverbar | Tapchanger maint | |
EPCOR | 17-Jul-17 07:00 | 21-Jul-17 17:00 | 4.42 Days
Continuous |
J2401 @ Jasper | Maint | |
ALTALINK | 17-Jul-17 07:30 | 21-Jul-17 12:30 | 4.21 Days
Continuous |
39s T2(Tx 5778) - GOI | Replacing bushings | |
EPCOR | 24-Jul-17 07:00 | 28-Jul-17 17:00 | 4.42 Days
Continuous |
J2408 @ Jasper | Maint | |
ALTALINK | 26-Jul-17 09:00 | 26-Jul-17 13:00 | 4 Hours
Daily |
I_485s Telecom 1041/1036L De-energized | The MW radio between 120S Picture Butte and 554S Travers requires firmware upgrade to avoid unplanned outage. This outage requires 1041L and 1036L to be opened AT THE SAME TIME for three hours, up to four for contingencies. Upgrade required in order to avoid any unplanned breakdown or malfunction of the system. | |
SUNCOR | 02-Aug-17 08:00 | 08-Aug-17 20:00 | 6.5 Days
Continuous |
29PL9-13 (29EDD-34 - 29EDD-65) | maintenance from 29PS-216 to 29PS-201 | |
SUNCOR | 09-Aug-17 08:00 | 15-Aug-17 20:00 | 6.5 Days
Continuous |
29PL9-12 (29EDD-34 - 29EDD-65) | 5 YR maintenance - from 29PS220 to 29PS-63 SLD - SL30-P-141-106 & SL30-P141-109 | |
ATCO | 15-Aug-17 08:00 | 17-Aug-17 16:00 | 2.33 Days
Continuous |
826S 901T | Routine Maintenance on 901T, 902T will remain in service, 502R 20 MVAR reactor unavailable for dispatch | |
ENMAX | 21-Aug-17 08:00 | 21-Aug-17 16:00 | 8 Hours
Continuous |
30.81L | (SWCRR)-30.81 decomissioned | |
ATCO | 22-Aug-17 08:00 | 24-Aug-17 16:00 | 2.33 Days
Continuous |
826S 902T | Routine Maintenance on 902T, 901T will remain in service, 503R, 504R 20 MVAR reactors unavailable for dispatch, Stn service will be on 5L263 alternate source | |
ALTALINK | 24-Aug-17 07:00 | 01-Oct-17 17:00 | 38.42 Days
Continuous |
916L (42s-5s) GOI [SWCRR] | SWCRR Line construction | |
ALTALINK | 24-Aug-17 07:00 | 01-Oct-17 17:00 | 38.42 Days
Continuous |
693L (42s-C10s) GOI [SWCRR] | SWCRR Line construction | |
SUNCOR | 04-Sep-17 08:00 | 22-Sep-17 20:00 | 18.5 Days
Continuous |
29EDD-3 29PT-6 | oil leak repairs | |
ALTALINK | 10-Sep-17 07:30 | 30-Sep-17 17:30 | 20.42 Days
Continuous |
62s202 (202L) - GOI | Upgrading protections | |
ALTALINK | 11-Sep-17 11:00 | 22-Sep-17 15:00 | 11.17 Days
Continuous |
74s T2 GOI | Fix oil leaks on T2 Tx 18571 | |
ALTALINK | 01-Oct-17 07:30 | 22-Oct-17 17:30 | 21.42 Days
Continuous |
62s201 (801L) - GOI | Upgrading protections | |
ALTALINK | 05-Oct-17 08:00 | 03-Nov-17 17:00 | 29.38 Days
Continuous |
910L (89s-288s) GOI [SWEATD] | 910L reconfig @ 289s | |
ALTALINK | 05-Oct-17 08:00 | 03-Nov-17 17:00 | 29.38 Days
Continuous |
914L (89s-86s) GOI [SWEATD] | 914L reconfig @ 289s | |
ATCO | 16-Oct-17 07:00 | 29-Oct-17 18:00 | 13.46 Days
Continuous |
840S CONVERTER | McNeill 2017 Fall turn around. Site shut down for maint. work. | AB-SK |
ALTALINK | 13-Nov-17 10:00 | 16-Nov-17 17:00 | 3.29 Days
Continuous |
63s (912L - A732s) - GOI | Replace A and B Line Protection | |
ALTALINK | 14-Nov-17 08:00 | 25-Nov-17 17:00 | 11.38 Days
Continuous |
1043L (320p-E816s) GOI [SWEATD] | 1043L reconfig | |
ATCO | 27-Nov-17 07:00 | 30-Nov-17 17:30 | 3.44 Days
Continuous |
9L01 | 9L01 Install piles for new structures for Thickwood tap. | |
ATCO | 02-Feb-18 07:00 | 09-Feb-18 17:30 | 7.44 Days
Continuous |
9L07 | Install 9L07 cut in structures for new 951S Thickwood Hills substation. | |
ATCO | 09-Feb-18 07:00 | 11-Feb-18 17:30 | 2.44 Days
Continuous |
9L07(1) | String new portion 9L01/9L30 over 9L07 for new 951S Thickwood Hills substation. | |
ATCO | 15-Feb-18 07:00 | 24-Feb-18 17:30 | 9.44 Days
Daily |
9L01 | 9L01 Cut in for in and out addition of 951S Thickwood Hills substation. Install new structures. | |
ATCO | 27-Feb-18 07:00 | 04-Mar-18 18:00 | 5.46 Days
Continuous |
7L22 | Build junction for new in and out POD 2030S Hughes | |
ALTALINK | 06-Jun-18 07:00 | 09-Jul-18 17:00 | 33.42 Days
Continuous |
RATD 929L(74s-63s) GOI | Cut in 929L in and out from 287s (287s-63s) | |
ALTALINK | 06-Jun-18 08:00 | 09-Jul-18 17:00 | 33.38 Days
Continuous |
RATD 925L(74s-63s) GOI | install foundations for Hazelwood line in/out | |
ATCO | 10-Sep-18 09:00 | 14-Sep-18 17:00 | 4.33 Days
Continuous |
801S 901T | 801S Anderson 901T Re-test Sept 10, 2018 | |
ATCO | 18-Sep-18 07:00 | 20-Sep-18 17:30 | 2.44 Days
Continuous |
9L01 | 9L01 Cut in for in and out addition of 951S Thickwood Hills substation. Remove bypass at substation. | |
ATCO | 25-Sep-18 07:00 | 27-Sep-18 17:30 | 2.44 Days
Continuous |
9L07 | Cut in 951S Thickwood Hills substation. |
AB-BC, AB-SK & AB-MATL: refer to AESO web posting: | http://itc.aeso.ca/itc/public/reportIndex.do |
Also, | |
AB-BC, AB-SK & AB-MATL: refer to ISO Rule 203.6: | http://www.aeso.ca/rulesprocedures/18592.html |
Prepared On: | 2017-03-02 2:59:41 PM |
This document and the information contained herein are based upon information and data which by their nature contain a degree of uncertainty and are subject to change. In addition, this document may contain information and data from public sources and/or third parties, which have been assumed to be accurate and complete and have not been verified. Accordingly, the Independent System Operator, operating as the Alberta Electric System Operator (the "AESO") makes no warranty, representation or guarantee, express or implied, with respect to this document or the information contained herein, including, but not limited to, any warranty, representation or guarantee of accuracy, completeness, timeliness, reliability, availability, absence of computer virus, non- infringement, merchantability or suitability for any purpose. Under no circumstances will the AESO, its members, officers, employees, contractors or agents, or any of their respective affiliates, be liable for any errors or omissions in, or any losses, damages or claims whatsoever, whether in contract, tort or otherwise, arising from use of or reliance upon, this document or any information contained herein. © 2009 Alberta Electric System Operator. All rights reserved |