Alberta Electric System Operator | |
Long Range Significant Transmission Outages for the period of 24 months starting 2014-10-11 | |
The table below contains the significant transmission outages submitted as tentative to the AESO. These Outages have not yet necessarily been approved, but are listed for awareness and coordination purposes. An Outage has been considered significant for this table if it meets any one (1) or more of the following criteria: |
|
|
|
Note: Where a transmission outage requires generation curtailments, the adjustments to generation will typically happen in the hours before the scheduled transmission outage and in the hour after the element is returned to service. | |
Previous Version | |
Download CSV | |
Owner | From | To | Duration | Element | Scheduled Activity | Affected Intertie |
---|---|---|---|---|---|---|
ATCO | 30-May-14 08:00 | 31-Oct-14 16:00 | 154.33 Days
Continuous |
840S McNeill Station,840s 901T (840s MCNEILLSTATION),840s 701T (840s MCNEILLSTATION) | upgrade McNeill HVDC controls | AB-SK |
ALTALINK | 14-Jun-14 07:00 | 31-Oct-14 18:00 | 139.46 Days
Continuous |
1034L (244s Bowmanton - 324s Cassils),1035L (244s Bowmanton - 324s Cassils),1088L (324s Cassils - 2075s Newell) | EATL Interface: Line cut in and out | |
EPCOR | 25-Jun-14 07:00 | 15-Nov-14 18:00 | 143.5 Days
Continuous |
1055L (629s Argyll Transfer - 816s Petrolia),240BA2 (814s Bellamy - 629s Argyll Transfer Station) | reterminate and rebuild as required on the 240 Kv oil filled cable at 629s | |
ALTALINK | 21-Aug-14 13:00 | 01-Mar-15 17:00 | 192.21 Days
Continuous |
33s3 (33s Spray) | maintenance | |
ALTALINK | 15-Sep-14 07:30 | 22-Oct-14 18:00 | 37.44 Days
Continuous |
911L (59s Peigan - ENMAX 65) | FATD - SFTP: BYPASS #3 # 4 & CROSSING 6.Relocate a portion of 911L off of existing ROW to allow for new 1037/1038L. | AB-BC |
AESO | 15-Sep-14 08:00 | 31-Oct-14 17:00 | 46.38 Days
Continuous |
983L (251S Whitla - 244S Bowmanton),964L (251s Whitla - 244s Bowmanton) | step bolt replacement - deficiency from construction - SATR BW | |
ALTALINK | 15-Sep-14 08:30 | 17-Oct-14 17:00 | 32.35 Days
Continuous |
310p 1352 (310p Sundance),310p 1452 (310p Sundance) | replace 310p1352, replace 310p1352 CTs, replace 310p1452 CTs, replace 310p1352 breaker fail protection, replace PTs | |
ATCO, IMPERIALOIL | 01-Oct-14 08:00 | 29-Oct-14 16:00 | 28.33 Days
Continuous |
7L105 (837s Mahihkan - 909s Mahno) | maintenance | |
CapitalPower | 05-Oct-14 08:00 | 25-Nov-14 08:00 | 51.04 Days
Continuous |
615S Halkirk | DSTATCOM trasnfomer | |
ALTALINK | 06-Oct-14 00:00 | 11-Oct-14 08:00 | 5.33 Days
Continuous |
320p3452 GOI | Replace breaker control module | |
ALTALINK | 06-Oct-14 07:30 | 16-Oct-14 17:00 | 10.4 Days
Continuous |
901L (63s Red Deer - 901AL tap),901L (74s Janet - 901AL tap) | replace structures 307 and 309 with Steel H Frames. | |
ALTALINK | 06-Oct-14 08:00 | 11-Oct-14 08:00 | 5 Days
Continuous |
320p3452 GOI | Replace breaker control module | |
ATCO, SUNCOR | 09-Oct-14 08:00 | 15-Oct-14 19:00 | 6.46 Days
Continuous |
29PL9-1 (29EDD-1 Millennium - 848s Ruth Lake) | Regular mtce on relay, CVT, Arrestor and cleaning. | |
ENMAX | 11-Oct-14 06:30 | 11-Oct-14 19:00 | 12.5 Hours
Continuous |
906L | ENMAX:OH crews working on Distribution on feeder 25-36.112 | |
ALTALINK | 11-Oct-14 07:00 | 13-Oct-14 17:00 | 2.42 Days
Continuous |
956L (103s-59s) GOI | Trouble corrective: Replace step bolts | |
ALTALINK | 11-Oct-14 07:30 | 22-Oct-14 18:00 | 11.44 Days
Continuous |
1203L (320p Keephills - 330p Genesee) | Cut 1203L in/out of 510s. Energize 500 kV equipment at end of outage - WATL | AB-BC/MATL |
EPCOR | 11-Oct-14 08:00 | 22-Oct-14 16:00 | 11.33 Days
Continuous |
1203 Line 320P Keephills to 330P Genesee | Sunnybrook Project HVDC/WATL Project & the commisioning of the 12038/1239 transmission lines | |
EPCOR | 11-Oct-14 08:00 | 05-Nov-14 18:00 | 25.46 Days
Continuous |
1238L (From Old 1203L Bay) @ Genesee | Cutovers of new protection panel, perform Final End to End Test for New 1238L and energize 1238L | |
EPCOR | 13-Oct-14 07:00 | 18-Oct-14 18:00 | 5.46 Days
Continuous |
557s Castledowns CD2406 | Retrofit of the Alstom Breaker | |
ENMAX | 13-Oct-14 08:00 | 15-Oct-14 16:00 | 2.33 Days
Continuous |
25B240-D139 | Doble, SF6 Sample & Install new position indicator (Day 1). First year check/Maintenance (Days 2&3) | |
BCH | 13-Oct-14 08:00 | 16-Oct-14 16:00 | 3.33 Days
Continuous |
2L294 (Cranbrook - A.A. Lambert) | replacing insulators at CBK/AAL/NLY - BC maintenance does not affect AB ATC | AB-BC |
ALTALINK, ENMAX | 14-Oct-14 08:00 | 16-Oct-14 16:00 | 2.33 Days
Continuous |
(Energize new: 693L,10PT138-693),832L,832L (ENMAX 10 - ENMAX 12),10.2TR | Remove T-Tap & terminate new 693L & 832L. Forward energize 10.2TR VIA 693L & 832L at return | |
ALTALINK | 14-Oct-14 08:00 | 17-Oct-14 17:00 | 3.38 Days
Continuous |
310p2852 GOI | Replace CTs, 767L will be closed to carry the 310p load. Require redundant protections to come out of service to facilitate the replacement of the CTs. | |
ALTALINK | 14-Oct-14 11:00 | 14-Oct-14 17:00 | 6 Hours
Daily |
17s922N (922L) - GOI,922L (310p Sundance - 17s Benalto) | Hot Switch Repair | AB-BC |
ALTALINK | 15-Oct-14 07:00 | 15-Oct-14 19:00 | 12 Hours
Continuous |
223s Station (701L) GOI | Close open points, Energize new 223s T3 & test protections | |
ALTALINK | 15-Oct-14 07:00 | 16-Oct-14 17:00 | 1.42 Days
Continuous |
T2,69s24 (partial 138kV Bus,T4) - GOI | 138kV Switch Replacement (69s24) | |
ALTALINK | 15-Oct-14 08:00 | 15-Oct-14 17:00 | 9 Hours
Daily |
13s 138kV North Bus & T2 - GOI | Bus dampers coming out of bus | |
ENMAX | 15-Oct-14 08:00 | 17-Oct-14 16:00 | 2.33 Days
Continuous |
25B240-D138 | Doble, SF6 Sample & Install new position indicator (Day 1). First year check/Maintenance (Days 2&3) | |
ALTALINK | 15-Oct-14 09:00 | 15-Oct-14 13:00 | 4 Hours
Daily |
154s VT3 (971L)Advice | adjust tension on control cables no outage to 971L | |
ALTALINK | 15-Oct-14 19:01 | 16-Oct-14 17:00 | 21.98 Hours
Continuous |
223s Partial 138kV Bus (701L) GOI | Install new bus protections and trip test breakers | |
ATCO | 16-Oct-14 07:30 | 17-Oct-14 17:00 | 1.4 Days
Continuous |
9L20 (766s Nevis - 755s Cordel) | 9L20 O/S FOR DRAGLINE WALK | AB-BC/MATL |
ALTALINK | 16-Oct-14 07:30 | 17-Oct-14 17:00 | 1.4 Days
Continuous |
9L912(63s - A766s) GOI for ATCO (info o | 9L20 O/S FOR DRAGLINE WALK | |
ALTALINK | 16-Oct-14 08:00 | 17-Oct-14 17:00 | 1.38 Days
Continuous |
9L20 (A755s - A766s) GOI for ATCO (info) | ATCO Work | |
ALTALINK | 16-Oct-14 08:00 | 17-Oct-14 17:00 | 1.38 Days
Continuous |
9L20 ATCO Outage - Info | 9L20 O/S FOR DRAGLINE WALK | |
AESO | 16-Oct-14 08:00 | 22-Oct-14 19:00 | 6.46 Days
Continuous |
29PL9-2 (29EDD-1 Millennium - 848s Ruth Lake) | Regular mtce on relay, CVT, Arrestor and cleaning. | |
ALTALINK | 16-Oct-14 08:30 | 16-Oct-14 09:00 | 30 Mins
Daily |
310p152 Advice | Complete trip test from 310p1352 breaker fail | |
ALTALINK | 16-Oct-14 09:15 | 16-Oct-14 09:45 | 30 Mins
Daily |
310p452 Advice | Complete trip test from 310p1352 breaker fail | |
ALTALINK | 16-Oct-14 10:00 | 16-Oct-14 10:30 | 30 Mins
Daily |
310p752 Advice | Complete trip test from 310p1352 breaker fail | |
ATCO | 16-Oct-14 10:00 | 17-Oct-14 17:00 | 31 Hours
Continuous |
766S 901T | 766S NEVIS 901T WILL BE REMOVED FROM SERVICE FOR MTCE ON BKR 701 SEE SCADA AND SLD NOTES. |
|
ALTALINK | 16-Oct-14 10:45 | 16-Oct-14 11:15 | 30 Mins
Daily |
310p1052 Advice | Complete trip test from 310p1352 breaker fail | |
ALTALINK | 16-Oct-14 11:30 | 16-Oct-14 12:00 | 30 Mins
Daily |
310p1652 Advice | Complete trip test from 310p1352 breaker fail | |
ALTALINK | 16-Oct-14 12:45 | 16-Oct-14 13:15 | 30 Mins
Daily |
310p1952 Advice | Complete trip test from 310p1352 breaker fail | |
ALTALINK | 16-Oct-14 13:30 | 16-Oct-14 14:00 | 30 Mins
Daily |
310p2252 Advice | Complete trip test from 310p1352 breaker fail | |
ALTALINK | 16-Oct-14 14:15 | 16-Oct-14 14:45 | 30 Mins
Daily |
310p2552 Advice | Complete trip test from 310p1352 breaker fail | |
ENMAX | 17-Oct-14 07:00 | 18-Oct-14 19:00 | 1.5 Days
Continuous |
240KV Ring @ 162s,SW 143 & 142,PT Z42 | maintenance | |
ALTALINK | 18-Oct-14 07:30 | 18-Oct-14 15:00 | 7.5 Hours
Daily |
914L (86s Bigstone - 89s Ellerslie),86s 1252 (86s Bigstone) | 240kV Breaker Maintenance | AB-BC |
ALTALINK | 18-Oct-14 07:30 | 19-Oct-14 17:00 | 1.4 Days
Daily |
86s1252 (914L) - GOI | 240kV Breaker Maintenance | |
ALTALINK | 18-Oct-14 08:00 | 19-Oct-14 16:00 | 1.33 Days
Daily |
618s725N (725AL) - GOI | RTU Replacement Project | |
ALTALINK | 18-Oct-14 08:00 | 19-Oct-14 16:00 | 1.33 Days
Continuous |
207L (370s-L111s) - Advice | CoL to repair bus connections and structures (L111s) | |
EPCOR | 18-Oct-14 08:00 | 22-Oct-14 18:00 | 4.42 Days
Continuous |
1239L (From Old 1209L Bay) @ Genesee | To perform Final End to End Test for New 1239L protection to Sunnybrook | |
BCH | 18-Oct-14 09:00 | 18-Oct-14 19:00 | 10 Hours
Continuous |
5L96 (Selkirk - Vaseux Lake) | test disconnect - BC maintenance does not affect AB ATC | AB-BC |
ALTALINK | 19-Oct-14 15:00 | 19-Oct-14 17:00 | 2 Hours
Daily |
86s 1752 (86s Bigstone) | Breaker Low Oil | |
EPCOR | 20-Oct-14 07:00 | 25-Oct-14 18:00 | 5.46 Days
Continuous |
987s Cloverbar C2407 | Retrofit of the Alstom Breaker | |
ALTALINK | 20-Oct-14 07:30 | 23-Oct-14 17:00 | 3.4 Days
Daily |
912L (63s Red Deer - 766s Nevis) | Replace 63s58 PT & Switch Work | AB-BC |
ENMAX | 20-Oct-14 08:00 | 20-Oct-14 16:00 | 8 Hours
Continuous |
25B240-D134 (ENMAX 25) | First year check/Maintenance | |
ALTALINK | 20-Oct-14 08:00 | 23-Oct-14 17:00 | 3.38 Days
Continuous |
32s22 GOI | Install new CTs at 32s22 | |
ALTALINK | 20-Oct-14 08:00 | 23-Oct-14 18:00 | 3.42 Days
Continuous |
275s2 GOI | Replace CT’s at 275s2 | |
ALTALINK | 20-Oct-14 08:30 | 23-Oct-14 16:30 | 3.33 Days
Continuous |
310p1252 GOI | Replace 310p1252 CTs. Please note that some redundant protections will have out of service 1 at a time to facilitate the replacement of the CTs. | |
EPCOR | 21-Oct-14 07:00 | 22-Oct-14 18:00 | 1.46 Days
Daily |
Lambton Tx2 | Replace PT | |
ENMAX | 21-Oct-14 08:00 | 21-Oct-14 16:00 | 8 Hours
Continuous |
25B240-D142 | First year check/Maintenance | |
ALTALINK | 21-Oct-14 08:00 | 21-Oct-14 17:00 | 9 Hours
Daily |
122s T2 TX18553 - GOI | Replace oil gauge, Doble, hot spot and o-ring replacement | |
ALTALINK | 21-Oct-14 08:00 | 21-Oct-14 17:00 | 9 Hours
Daily |
39s T1 & 240kV Bus 1 - GOI | 39s34 Switch Repairs | |
ATCO | 21-Oct-14 13:00 | 21-Oct-14 17:00 | 4 Hours
Continuous |
9L948 (650s Hansman Lake - 863s Paintearth) | 9L948 IS REQUIRED TO BE OPEN ENDED @ 650S HANSMAN LAKE TO ACCOMMODATE TESTING OF THE NEW SVC @ 959S LANFINE
ALTA LINK WILL ONLY ALLOW 5 MINUTE OUTAGE ON 9L948 ALTALINK WILL ONLY ALLOW 9L24 & 948L TO BE REMOVED FROM SERVICE AT THE SAME TIME FOR APPROX 5 MIN PLEASE REFER TO THE ATTACHED RISK ASSESSMENTS THIS WORK IS IN CONJUNCTION WITH CROW #2-28022 |
|
ENMAX | 22-Oct-14 08:00 | 22-Oct-14 16:00 | 8 Hours
Continuous |
162B240-RB136 | Maintenance, SF6 Sample | |
ALTALINK | 22-Oct-14 08:00 | 22-Oct-14 17:00 | 9 Hours
Daily |
132s15 - GOI | 240kV Breaker Maintenance | |
ALTALINK | 22-Oct-14 08:00 | 23-Oct-14 17:00 | 1.38 Days
Continuous |
268s 503L (268s-323s) - Advice | Install Grounds For 323sCustomer | |
EPCOR | 22-Oct-14 08:00 | 05-Nov-14 18:00 | 14.46 Days
Continuous |
1238 Line 330P to 510S | Isolate the 1238 line Node formally the 1209 line Node | |
ENMAX, ALTALINK | 22-Oct-14 11:30 | 22-Oct-14 16:00 | 4.5 Hours
Continuous |
918L (17s Benalto - 162s Beddington),162s 240KV Bus | Substation Washing, SCADA Function Checks | AB-BC |
ALTALINK | 23-Oct-14 07:00 | 28-Oct-14 18:00 | 5.46 Days
Continuous |
985L (74s-C25s) GOI(Commission) | L to J: Complete L 10 Bay work and test energize new bay and Line to C25s. Close open points on 985L | |
ALTALINK | 23-Oct-14 08:00 | 23-Oct-14 17:00 | 9 Hours
Daily |
74s56 (C1) - GOI | 138kV Breaker Maintenance | AB-BC |
AESO | 23-Oct-14 08:00 | 30-Oct-14 19:00 | 7.46 Days
Continuous |
29PL9-5 (29EDD-1 Millennium - 29EDD-34) | Regular mtce on relay, CVT, Arrestor and cleaning. | |
ALTALINK | 23-Oct-14 09:30 | 23-Oct-14 17:00 | 7.5 Hours
Daily |
48s887X (887L) - GOI | 138kV Breaker Maintenance | AB-BC |
ENMAX | 23-Oct-14 11:30 | 23-Oct-14 16:00 | 4.5 Hours
Continuous |
21.80L (42s Sarcee - ENMAX 21),21.1C (ENMAX 21),21.4TR (ENMAX 21),20.82L (ENMAX 21 - ENMAX 20),21.1TR,21s 138KV Bus | Substation Washing | AB-BC |
ALTALINK | 25-Oct-14 07:00 | 25-Oct-14 18:00 | 11 Hours
Daily |
74s T2 (74s Janet) | ECTP and L to J: Install new double curlew slack span bay going into new 985L(old 937L) bay. | |
ENMAX | 25-Oct-14 08:00 | 25-Oct-14 10:00 | 2 Hours
Continuous |
RB131,162s 240KV Bus | SCADA Function Checks | |
ALTALINK | 25-Oct-14 08:00 | 26-Oct-14 17:00 | 1.38 Days
Continuous |
86s T1 & 138kV Bus - GOI | Oil Gauge, Switch Hot Spots | |
ENMAX | 25-Oct-14 10:00 | 25-Oct-14 12:00 | 2 Hours
Continuous |
162s 240KV Bus,RB134 | SCADA Function Checks | |
ALTALINK | 27-Oct-14 07:00 | 31-Oct-14 18:00 | 4.46 Days
Continuous |
1077L (74s-5s) GOI | ECTP: Install 1077L conductors fromm SS thru QQ and to 6 pole U/G riser on 936L bypass. Line de-energized | |
EPCOR | 27-Oct-14 07:00 | 01-Nov-14 18:00 | 5.46 Days
Continuous |
557s Cloverbar C2408 | Retrofit of the Alstom Breaker | |
ALTALINK | 27-Oct-14 08:00 | 31-Oct-14 17:00 | 4.38 Days
Continuous |
929L (63s - 74s) GOI | Complete line reconfiguration for 1325L crossing | AB-BC |
ALTALINK | 27-Oct-14 08:30 | 14-Nov-14 16:30 | 18.38 Days
Continuous |
310p1152 GOI | Replace 310p1152 CTs, replace 310p1152 breaker, replace 310p1152 breaker fail protection. Please note that some redundant protections will have out of service 1 at a time to facilitate the replacement of the CTs. | |
ALTALINK | 27-Oct-14 12:00 | 06-Nov-14 17:00 | 10.25 Days
Continuous |
63s T1 TX18310 - GOI | Bushing Replacement & Oil Leaks | |
ALTALINK | 27-Oct-14 13:00 | 28-Oct-14 16:00 | 27 Hours
Daily |
618s863X (863L/891L) - GOI | RTU Replacement Project | |
ALTALINK | 28-Oct-14 08:00 | 26-Nov-14 08:00 | 29.04 Days
Continuous |
244s 240/138KV buss & TXFs GOI | Close In Open points A & B | |
ALTALINK | 29-Oct-14 07:00 | 31-Oct-14 18:00 | 2.46 Days
Continuous |
1003L (74s-C25s) GOI | ECTP: Upgrade CT ratio, Update laminated pole, Install inter- phase spacers and P & C work | |
AESO | 30-Oct-14 08:00 | 05-Nov-14 19:00 | 6.5 Days
Continuous |
29PL9-6 (29EDD-1 Millennium - 29EDD-34) | Regular mtce on relay, CVT, Arrestor and cleaning. | |
ALTALINK | 30-Oct-14 08:30 | 30-Oct-14 17:00 | 8.5 Hours
Daily |
17s16 (C1) - GOI | Cap Bank Testing | AB-BC |
ALTALINK | 31-Oct-14 07:00 | 31-Oct-14 17:00 | 10 Hours
Daily |
927L & 356s bkrs GOI | Replace VT 4 | |
ALTALINK | 01-Nov-14 06:30 | 03-Nov-14 18:00 | 2.52 Days
Continuous |
936L (74s-5s-102s) GOI(Bypass energizati | L to J: 936L bay swap from L17 to new 936L 240kv U/G bypass. | AB-BC |
EPCOR | 03-Nov-14 07:00 | 05-Nov-14 18:00 | 2.46 Days
Continuous |
Poundmaker P2401 | Retrofit of the Alstom Breaker | |
ALTALINK | 03-Nov-14 08:00 | 04-Nov-14 16:00 | 1.33 Days
Continuous |
310p B Bus GOI | Replace strain insulators | |
ENMAX | 03-Nov-14 08:00 | 04-Nov-14 16:00 | 1.33 Days
Continuous |
24.83L (74s Janet - ENMAX 24) | Point trotter phase 2 ptB salvage | |
ALTALINK | 03-Nov-14 08:00 | 07-Nov-14 17:00 | 4.38 Days
Continuous |
154s 240kv bus 2 Advice | Add SS VT and connect to 240kv bus 2 | |
ALTALINK | 04-Nov-14 06:30 | 06-Nov-14 18:00 | 2.48 Days
Continuous |
937L (102s-74s) GOI | L to J: 937L bay swap from L12 to L17. In preparetion to go to U/G bypass | AB-BC |
ALTALINK | 04-Nov-14 07:00 | 05-Nov-14 17:00 | 1.42 Days
Continuous |
693L (42s - C10s)GOI | Remove CT's ans replace with insulators | |
ALTALINK | 05-Nov-14 08:00 | 06-Nov-14 16:00 | 1.33 Days
Daily |
618s824 (824L) - GOI | RTU Replacement Project and 824L CT ratio change upgrade project | |
EPCOR | 05-Nov-14 19:00 | 08-Nov-14 19:00 | 3 Days
Continuous |
Poundmaker P2404 | Retrofit of the Alstom Breaker | |
ATCO | 07-Nov-14 07:00 | 10-Nov-14 18:00 | 3.46 Days
Continuous |
9L59 | String new 13L50 line over 9L59 Between Towers 882 & 883 @ NW 18-34-13-4.
Work cannot be done using live line techniques due to clearance limitations AESO Derates may apply @ Sheerness depending on system and wind conditions |
|
ALTALINK | 07-Nov-14 15:00 | 07-Nov-14 17:00 | 2 Hours
Daily |
154s Station service advice | close open point for new SS2 | |
ALTALINK | 08-Nov-14 08:00 | 24-Nov-14 18:00 | 16.42 Days
Continuous |
74s T1 and 240 kV Bus 1 GOI | L to J project. Tie in North Bus Extension. | |
EPCOR | 10-Nov-14 07:00 | 12-Nov-14 18:00 | 2.46 Days
Continuous |
Poundmaker PM2402 | Retrofit of the Alstom Breaker | |
EPCOR | 12-Nov-14 19:00 | 15-Nov-14 18:00 | 2.96 Days
Continuous |
Poundmaker PM2403 | Retrofit of the Alstom Breaker | |
ALTALINK | 15-Nov-14 08:00 | 16-Nov-14 17:00 | 1.38 Days
Continuous |
83s 138kV West Bus (610L,172L,C2) - Ad | Replace west bus 138kV PT’s [ 83s3 ] | |
ENMAX | 17-Nov-14 08:00 | 18-Nov-14 16:00 | 1.33 Days
Continuous |
162.1TR (ENMAX 162 Beddington),162s 138KV Bus | North bus extension | |
EPCOR | 17-Nov-14 08:00 | 21-Nov-14 18:00 | 4.42 Days
Continuous |
B2401,B2402,BDS3,at 814s Bellamy | Hydraulic maintenance by manufacturer & repairs to SF6 compartment | |
EPCOR | 17-Nov-14 08:00 | 21-Nov-14 18:00 | 4.42 Days
Continuous |
240BA2 814s Bellamy | Repairs to a SF6 compartment on 240BA2 Node | |
ENMAX | 19-Nov-14 08:00 | 20-Nov-14 16:00 | 1.33 Days
Continuous |
162s 138KV Bus,162.2TR | South bus extension | |
EPCOR | 22-Nov-14 07:00 | 05-Dec-14 18:00 | 13.46 Days
Continuous |
240CV5 Cable 557s Castledowns to 511s Victoria | Manhole Inspections | |
EPCOR | 24-Nov-14 07:00 | 28-Nov-14 18:00 | 4.46 Days
Continuous |
511s Victoria V2401 | Retrofit of the Alstom Breaker | |
EPCOR | 24-Nov-14 07:00 | 28-Nov-14 18:00 | 4.46 Days
Continuous |
511s Victoria TX5 | Retrofit of the Alstom Breaker | |
EPCOR | 24-Nov-14 08:00 | 26-Nov-14 12:00 | 2.17 Days
Continuous |
814s Bellamy B2406 | Hydraulic maintenance by manufacturer | |
ALTALINK | 24-Nov-14 08:30 | 12-Dec-14 16:30 | 18.33 Days
Continuous |
310p152 GOI | Replace 310p152 CTs, replace 310p152 breaker, replace 310p152 breaker fail protection. Please note that some redundant protections will have out of service 1 at a time to facilitate the replacement of the CTs. | |
SUNCOR | 25-Nov-14 09:00 | 26-Nov-14 19:00 | 1.42 Days
Continuous |
29EDD-34 952_141 (29EDD-34) | Gauge Replacement. | |
EPCOR | 26-Nov-14 13:00 | 28-Nov-14 18:00 | 2.21 Days
Continuous |
814s Bellamy B2407 | Hydraulic maintenance by manufacturer | |
SUNCOR | 01-Dec-14 08:00 | 06-Dec-14 20:00 | 5.5 Days
Continuous |
29PL9-2 (29EDD-1 Millennium - 848s Ruth Lake) | Disconnect Switch Maintenance | |
SUNCOR | 01-Dec-14 08:00 | 07-Dec-14 19:00 | 6.46 Days
Continuous |
29PL9-2 (29EDD-1 Millennium - 848s Ruth Lake) | Regular mtce on relay, CVT, Arrestor and cleaning. | |
ENMAX | 06-Dec-14 08:00 | 06-Dec-14 16:00 | 8 Hours
Continuous |
23.80L,23.4TR,8KV Bus (23.4TR) | Substation Washing. Wet wash if weather permits | |
ATCO | 08-Dec-14 07:00 | 15-Dec-14 18:00 | 7.46 Days
Continuous |
9L32 (941s Bitumount -957s McClelland) | LINE MOVE FOR FORT HILLS PROJECT (55578) | |
AESO | 08-Dec-14 08:00 | 14-Dec-14 19:00 | 6.46 Days
Continuous |
29PL9-5 (29EDD-1 Millennium - 29EDD-34) | Regular mtce on relay, CVT, Arrestor and cleaning. | |
AESO | 15-Dec-14 08:00 | 21-Dec-14 19:00 | 6.46 Days
Continuous |
29PL9-6 (29EDD-1 Millennium - 29EDD-34) | Regular mtce on relay, CVT, Arrestor and cleaning. | |
ALTALINK | 25-Dec-14 08:00 | 31-Dec-14 16:30 | 6.35 Days
Continuous |
1045L (310p - 805s) ADVICE | Replace VTs & 310p132 Junction box | |
ALTALINK | 15-Jan-15 08:00 | 15-Mar-15 18:00 | 59.38 Days
Continuous |
5s T1 and 240KV Bus 1 GOI | ECTP – Replace existing TXMER with new. Commission new TXI and north bus. | |
ENMAX | 01-Feb-15 08:00 | 01-Feb-15 16:00 | 8 Hours
Continuous |
65.1TR,South 240KV Bus | FATD, Check reversing sw, Doble, Oil sample LTC | |
ALTALINK | 03-Feb-15 08:00 | 05-Feb-15 16:00 | 2.33 Days
Continuous |
919L (77s-310p) - GOI | SCADA Equipment Upgrade Project | |
ALTALINK | 10-Feb-15 08:00 | 12-Feb-15 16:00 | 2.33 Days
Continuous |
989L (77s-310p) - GOI | SCADA Equipment Upgrade Project | |
ALTALINK | 17-Feb-15 08:00 | 19-Feb-15 16:00 | 2.33 Days
Continuous |
938L (77s-A809s) - GOI | SCADA Equipment Upgrade Project | |
ALTALINK | 24-Feb-15 08:00 | 26-Feb-15 16:00 | 2.33 Days
Continuous |
939L (77s-A809s) - GOI | SCADA Equipment Upgrade Project | |
ALTALINK | 03-Mar-15 08:00 | 05-Mar-15 16:00 | 2.33 Days
Continuous |
907L (77s-122s) - GOI | SCADA Equipment Upgrade Project | |
ALTALINK | 24-Mar-15 08:00 | 26-Mar-15 16:00 | 2.33 Days
Continuous |
77s T1(TX18372) - GOI | SCADA Equipment Upgrade Project | |
ALTALINK | 31-Mar-15 08:00 | 02-Apr-15 16:00 | 2.33 Days
Continuous |
77s T2(TX18521) - GOI | SCADA Equipment Upgrade Project | |
ENMAX | 19-May-15 07:30 | 19-Jun-15 16:00 | 31.35 Days
Continuous |
5s Cap Bank | ECTP 2s, Swap AIS to GIS | AB-BC |
ENMAX | 01-Jun-15 07:30 | 14-Jun-15 16:00 | 13.35 Days
Continuous |
33.83L,6.82L,41.1C (ENMAX 41),41.2TR | SW's 81, 82, 83, 87, 88 & 89 @ 41s Replacement, 41.2TR MD Replacement | AB-BC |
ENMAX | 02-Jun-15 08:00 | 12-Jun-15 16:00 | 10.33 Days
Continuous |
833L | ECTP 2s, Swap AIS to GIS | |
ENMAX | 22-Jun-15 08:00 | 05-Jul-15 16:00 | 13.33 Days
Continuous |
833L,12.2TR | SW's 81, 82 & 83 @ 12s Replacement, 12.2TR MD Replacement | |
ATCO | 01-Jul-15 08:00 | 31-Aug-15 16:00 | 61.33 Days
Continuous |
9L32 (941s Bitumount -957s McClelland) | CONNECT 2005S SECORD TO 9L32 (IN / OUT CONFIGURATION)N | |
ENMAX | 14-Sep-15 08:00 | 25-Sep-15 16:00 | 11.33 Days
Continuous |
36.81L | Line Differential |
AB-BC, AB-SK & AB-MATL: refer to AESO web posting: | http://itc.aeso.ca/itc/public/atcQueryInit.do |
Also, | |
AB-BC, AB-SK & AB-MATL: refer to ISO Rule 203.6: | http://www.aeso.ca/rulesprocedures/18592.html |
Prepared On: | 2014-10-01 5:00:22 PM |
This document and the information contained herein are based upon information and data which by their nature contain a degree of uncertainty and are subject to change. In addition, this document may contain information and data from public sources and/or third parties, which have been assumed to be accurate and complete and have not been verified. Accordingly, the Independent System Operator, operating as the Alberta Electric System Operator (the "AESO") makes no warranty, representation or guarantee, express or implied, with respect to this document or the information contained herein, including, but not limited to, any warranty, representation or guarantee of accuracy, completeness, timeliness, reliability, availability, absence of computer virus, non- infringement, merchantability or suitability for any purpose. Under no circumstances will the AESO, its members, officers, employees, contractors or agents, or any of their respective affiliates, be liable for any errors or omissions in, or any losses, damages or claims whatsoever, whether in contract, tort or otherwise, arising from use of or reliance upon, this document or any information contained herein. © 2009 Alberta Electric System Operator. All rights reserved |