The table below contains the critical transmission maintenance outages submitted as tentative to the AESO. These Outages have not yet necessarily been approved, but are listed for awareness and coordination purposes. An Outage has been considered critical for this table if it affects: | |
| |
Note: Where a transmission outage requires generation curtailments, the adjustments to generation will typically happen in the hours before the scheduled transmission outage and in the hour after the element is returned to service. | |
Previous Version | |
Download CSV | |
Owner | From | To | Duration | Element | Scheduled Activity | Affected Intertie |
---|---|---|---|---|---|---|
ATCO | 21-Nov-13 08:00 | 30-Jun-14 16:00 | 222 Days Continuous | 732s 503R (732s Mitsue) | Forced Outage | |
ALTALINK | 18-Dec-13 08:00 | 31-May-14 16:00 | 165 Days Continuous | 89s 1852 (89s Ellerslie) | Heartland project | |
ALTALINK | 01-Feb-14 08:00 | 28-Apr-14 08:00 | 86 Days Continuous | 102s R7 (102s Langdon) | move reactors from 102s to 520s - affects 1201L reclosing - WATL | |
ALTALINK | 03-Feb-14 10:30 | 25-Mar-14 17:30 | 51 Days Continuous | 935L (324s Cassils - 356s Milo) | re conductor STR’s #87 to #104 | |
ALTALINK | 24-Feb-14 09:00 | 20-Mar-14 17:00 | 25 Days Continuous | 310p 1952 (310p Sundance) | replace breaker, CTs, breaker fail relay | |
ENMAX | 01-Mar-14 08:00 | 31-Mar-14 16:00 | 31 Days Continuous | 38.1C (ENMAX 38) | low SF6 (forced outage) | AB-BC |
ENMAX | 01-Mar-14 08:00 | 31-Mar-14 16:00 | 31 Days Continuous | 14.1C (ENMAX 14), 14.2C (ENMAX 14) | forced outage | AB-BC |
ALTALINK | 05-Mar-14 07:00 | 15-Apr-14 17:00 | 42 Days Continuous | 1003L (74s Janet - ENMAX 25) | L to J: 1003L rebuild L9 diameter - new switchs, CT, CVT - P&C, SCADA & Telecom. | |
ALTALINK | 05-Mar-14 07:30 | 15-May-14 17:00 | 72 Days Continuous | 1071L (103s Goose Lake - 205s Castle Rock Ridge) | string new 1071L & 994L to 312s Fidler. | |
ALTALINK | 06-Mar-14 07:30 | 17-Mar-14 19:00 | 12 Days Continuous | 903L (17s Benalto - 320p Keephills) | string 1325L over 903L & 190L - WATL | AB-BC |
ALTALINK | 12-Mar-14 08:00 | 28-Mar-14 12:00 | 17 Days Continuous | 1036L (370s North Lethbridge - 356s Milo) | Re-terminate at 554s Travers - BSR | |
ALTALINK | 15-Mar-14 06:30 | 15-Mar-14 15:00 | 8.5 Hours Daily | 74s C3 (74s Janet), 74s C4 (74s Janet), 74s T2 (74s Janet) | L to J project. De- energize: Create open point for bus construction expansion and re-energize T2. | AB-BC |
ENMAX | 17-Mar-14 08:00 | 19-Mar-14 16:00 | 3 Days Continuous | 25s Bus | SW/MD Mtce (151, 150, 149, 145, 137, 131) | |
ALTALINK | 17-Mar-14 13:00 | 18-Mar-14 14:00 | 25 Hours Continuous | 89s1552 - GOI | 240kV Breaker Maintenance | |
ALTALINK | 19-Mar-14 08:00 | 19-Mar-14 12:00 | 4 Hours Daily | 250p11 (250s Bighorn) | maintenance | |
ALTALINK | 19-Mar-14 08:00 | 19-Mar-14 17:00 | 9 Hours Daily | 74s2252 - GOI | oil leak on grading caps | |
ALTALINK | 19-Mar-14 12:00 | 19-Mar-14 16:00 | 4 Hours Daily | 250p22 (250p Bighorn) | maintenance | |
ALTALINK | 20-Mar-14 08:30 | 20-Mar-14 09:00 | 30 Mins Daily | 310p2552 Advice | Trip test from 310p1952 new breaker fail relay | |
ALTALINK | 20-Mar-14 10:00 | 20-Mar-14 10:30 | 30 Mins Daily | 310p2252 Advice | Trip test from 310p1952 new breaker fail relay | |
ALTALINK | 20-Mar-14 11:00 | 20-Mar-14 11:30 | 30 Mins Daily | 310p1652 Advice | Trip test from 310p1952 new breaker fail relay | |
ALTALINK | 20-Mar-14 12:00 | 20-Mar-14 12:30 | 30 Mins Daily | 310p1352 Advice | Trip test from 310p1952 new breaker fail relay | |
ALTALINK | 20-Mar-14 13:00 | 20-Mar-14 13:30 | 30 Mins Daily | 310p1052 Advice | Trip test from 310p1952 new breaker fail relay | |
ALTALINK | 20-Mar-14 14:00 | 20-Mar-14 14:30 | 30 Mins Daily | 310p752 Advice | Trip test from 310p1952 new breaker fail relay | |
ALTALINK | 20-Mar-14 15:00 | 20-Mar-14 15:30 | 30 Mins Daily | 310p452 Advice | Trip test from 310p1952 new breaker fail relay | |
ALTALINK | 20-Mar-14 16:00 | 20-Mar-14 16:30 | 30 Mins Daily | 310p152 Advice | Trip test from 310p1952 new breaker fail relay | |
ALTALINK | 20-Mar-14 17:00 | 20-Mar-14 17:30 | 30 Mins Daily | 310p2852 Advice | Trip test from 310p1952 new breaker fail relay | |
ALTALINK | 20-Mar-14 17:30 | 20-Mar-14 19:00 | 90 Mins Daily | 922L (310p Sundance - 17s Benalto) | Trip test to 310p2052, energize new 310p1952 & CTs | AB-BC |
EPCOR | 24-Mar-14 08:00 | 28-Mar-14 16:00 | 5 Days Continuous | 805S Trans #3 | CVT Replacement | |
ALTALINK | 24-Mar-14 10:00 | 27-Mar-14 15:00 | 4 Days Continuous | 905L (19s - 37s) GOI | Conductor Repair | |
ALTALINK | 25-Mar-14 08:00 | 27-Mar-14 17:00 | 3 Days Continuous | 17s6 - GOI | 240kV breaker maintenance | |
ALTALINK | 27-Mar-14 08:00 | 27-Mar-14 14:00 | 6 Hours Daily | 283s31 (C1) - GOI | 138kV Breaker Maintenance | |
ALTALINK | 27-Mar-14 08:00 | 27-Mar-14 17:00 | 9 Hours Daily | 77s T2 TX18521 - GOI | T2 Maintenance | |
ALTALINK | 30-Mar-14 08:00 | 31-Mar-14 16:00 | 2 Days Continuous | 1005L (120s - 356s) GOI | Remove temporary bypass - BSR | |
ALTALINK | 31-Mar-14 08:00 | 11-Apr-14 16:00 | 12 Days Continuous | 83s T1 & 25kV Bus 1 GOI | Replace various switches, LAs, insualtors | |
ENMAX | 01-Apr-14 08:00 | 02-Apr-14 16:00 | 2 Days Continuous | 162B240-RB136 | Dashpot maint on 162B240-RB136 | |
ALTALINK | 01-Apr-14 09:00 | 01-Apr-14 17:00 | 8 Hours Daily | 650s70 & T3 - GOI | 650s70 Replace Latch | |
ATCO | 02-Apr-14 08:00 | 06-Apr-14 18:00 | 5 Days Continuous | 9L57 | CONNECT LINES9L57 TOBIRCHWOOD (LINES WILL NOT BE CONNECTED INTO BIRCHWOOD A BYPASS WILLBE INSTALLED) | |
ENMAX | 03-Apr-14 08:00 | 03-Apr-14 16:00 | 8 Hours Continuous | 1080L | Maint 65MD240-1080, SW 133, SW134 | |
ENMAX | 05-Apr-14 08:00 | 07-Apr-14 16:00 | 3 Days Continuous | 917L | Activity | |
ALTALINK | 07-Apr-14 08:00 | 08-Apr-14 17:00 | 2 Days Continuous | 305s 138kV West Bus (712L, C1) & 739L GO | Replace 305s1, create open point 'A', repair 305s24 hotspot | |
ALTALINK | 07-Apr-14 14:00 | 07-Apr-14 17:00 | 3 Hours Daily | 72s852 - GOI | 240kV Breaker Maintenance | |
ALTALINK | 08-Apr-14 08:00 | 10-Apr-14 17:00 | 3 Days Continuous | 28s41 - GOI | 240kV breaker maintenance | |
ALTALINK | 08-Apr-14 08:00 | 10-Apr-14 17:00 | 3 Days Continuous | 17s9 - GOI | 240kV breaker maintenance | |
ALTALINK | 09-Apr-14 08:00 | 14-Apr-14 17:00 | 6 Days Continuous | 305s 138kV East Bus & 739L (C1) GOI | Replace 305s3 & 305s4, repair 305s23 hotspot | |
ALTALINK | 09-Apr-14 09:00 | 09-Apr-14 17:00 | 8 Hours Daily | 818s17 (C1) - GOI | Investigate C2 Alarm | |
ALTALINK | 10-Apr-14 08:00 | 10-Apr-14 12:00 | 4 Hours Daily | 405s17 (C1)- GOI | Cap Bank Blown Fuse | |
ALTALINK | 10-Apr-14 09:00 | 10-Apr-14 17:00 | 8 Hours Daily | 149s 858L & T1 - GOI | T1 Bushing Check & 149s1 Mech Repairs | |
ALTALINK | 12-Apr-14 08:00 | 13-Apr-14 17:00 | 2 Days Continuous | 38sT4 (Tx18247) GOI | Replace breaker control module on 38s18 | |
ALTALINK | 15-Apr-14 08:00 | 15-Apr-14 17:00 | 9 Hours Daily | 59s952 - GOI | 240kV breaker maintenance | |
ALTALINK | 15-Apr-14 08:00 | 15-Apr-14 17:00 | 9 Hours Daily | 305s 138kV West Bus (712L, 739L, C1) GOI | Close open point 'A' | |
ALTALINK | 15-Apr-14 08:01 | 15-Apr-14 17:00 | 9 Hours Daily | 74s C3 (74s Janet), 74s C4 (74s Janet), 74s T2 (74s Janet) | L to J project. De-enrgize T2: Close open point for B2 bus construction expansion and re-energize | AB-BC |
ALTALINK | 16-Apr-14 08:00 | 16-Apr-14 13:00 | 5 Hours Daily | 151s C1 (151s Strathmore) | 151s44: Migrate breaker control, status, alarms to new SCADA RTU system | |
ALTALINK | 17-Apr-14 07:30 | 02-May-14 09:00 | 16 Days Continuous | 937L (102s Langdon - 74s Janet) | Move line from old 102s 240 kV Bus to new 102s 240 kV Bus - WATL | AB-BC |
ALTALINK | 22-Apr-14 10:00 | 24-Apr-14 17:00 | 3 Days Continuous | 89s452 - GOI | 240kV Breaker Maintenance | |
ALTALINK | 23-Apr-14 07:30 | 24-Apr-14 18:00 | 2 Days Continuous | 1201L (102s Langdon - BCH), 1113L & 102s SVC (affects 1201L) GOI | affects 1201L; connect new 102s 240 kV bus to 1113AL - WATL | AB-BC |
ALTALINK | 26-Apr-14 08:00 | 27-Apr-14 17:00 | 2 Days Continuous | 38s 240kV Bus 1, 138kV Bus 1& T1 GOI | Replace 38s31, repair 38s98, maintain T1 | |
ALTALINK | 26-Apr-14 08:00 | 27-Apr-14 17:00 | 2 Days Continuous | 648s Partial 138kV Bus & 954L - GOI | Breaker and Switch Maintenance | |
ALTALINK | 28-Apr-14 07:30 | 01-May-14 18:00 | 4 Days Continuous | 1201L (102s Langdon - BCH) | Re-terminate 1201L at 520s (permanent) - WATL | AB-BC |
ALTALINK | 28-Apr-14 08:00 | 30-Apr-14 17:00 | 3 Days Continuous | 37s T6 (Tx18309) GOI | Replace 138 & 240kV Tx bushings | |
ALTALINK | 28-Apr-14 12:00 | 01-May-14 17:00 | 4 Days Continuous | 89s852 - GOI | 240kV Breaker Maintenance | |
ALTALINK | 01-May-14 08:00 | 01-May-14 14:00 | 6 Hours Daily | 69s45 & 913L - GOI | 69s45 Hot Spot | |
ALTALINK | 01-May-14 09:00 | 01-May-14 17:00 | 8 Hours Continuous | 217s 138kV 1/2 Bus (80L, 768L, C1, T7) - | TX and cap bank maintenance | |
ALTALINK | 02-May-14 08:00 | 09-May-14 18:00 | 8 Days Continuous | 924L (102s - 356s) GOI | Move line from old 102s 240 kV Bus to new 102s 240 kV Bus - WATL | |
ALTALINK | 05-May-14 07:30 | 05-May-14 13:00 | 5.5 Hours Daily | 914L (86s Bigstone - 89s Ellerslie) | SCADA Equipment Upgrade | AB-BC |
ALTALINK | 05-May-14 07:30 | 16-May-14 18:00 | 12 Days Continuous | 1209L (89s Ellerslie - 330p Genesee) | Epcor Sunnybrook Project; ***outage duration is under review with the TFO’s and may be shortened as we get closer to the date*** | AB-BC |
ALTALINK | 06-May-14 07:30 | 06-May-14 13:00 | 5.5 Hours Daily | 914L (86s Bigstone - 89s Ellerslie) | SCADA Equipment Upgrade | AB-BC |
ALTALINK | 10-May-14 08:00 | 16-May-14 18:00 | 7 Days Continuous | 927L (102s - 356s) GOI | Move line from old 102s 240 kV Bus to new 102s 240 kV Bus - WATL | |
ALTALINK | 13-May-14 08:00 | 13-May-14 14:00 | 6 Hours Daily | 86s T1(TX18491) - GOI | SCADA Equipment Upgrade | |
ALTALINK | 17-May-14 08:00 | 04-Jun-14 18:00 | 19 Days Daily | 1212L(89s-12s) G.O.I. | EATL Interface: Line move. | |
ALTALINK | 20-May-14 07:30 | 27-May-14 18:00 | 8 Days Continuous | 936L (102s Langdon - 74s Janet) | Move line from old 102s 240 kV Bus to new 102s 240 kV Bus - WATL | AB-BC |
ALTALINK | 26-May-14 13:00 | 29-May-14 17:00 | 4 Days Continuous | 902L (19s-310P) - GOI | 138kV Breaker Maintenance & Hot Spots | |
ALTALINK | 29-May-14 07:00 | 29-May-14 19:00 | 12 Hours Daily | 1053L (132s Ware Junction - 324s Cassils) | EATL interface: ATCO installing 13L50 Str # 1327. | |
ALTALINK | 31-May-14 07:00 | 15-Jun-14 18:00 | 16 Days Daily | 1206L(89s-12s) G.O.I. | EATL Interface: | |
ATCO | 01-Jun-14 07:00 | 02-Jun-14 18:00 | 2 Days Continuous | 9L27 | 9L27 GOI TO SET RIDER POLES FOR EATL XING AT NW 8 40 14 W4 | |
ATCO | 09-Jun-14 07:00 | 10-Jun-14 18:00 | 2 Days Continuous | 9L27 | 9L27 GOI TO REMOVE RIDER POLES FOR EATL XING AT NW 8 40 14 W4W4 | |
ALTALINK | 10-Jun-14 08:00 | 10-Jun-14 14:00 | 6 Hours Daily | 650s T1(TX18691) - GOI | SCADA Equipment Upgrade | |
ALTALINK | 14-Jun-14 07:00 | 19-Jul-14 18:00 | 36 Days Continuous | 1034L(324s-244s)GOI | EATL Interface: Line cut in and out. | |
ALTALINK | 14-Jun-14 07:00 | 25-Jul-14 18:00 | 42 Days Continuous | 1088L(OLD 1035L)(324s-Newell)GOI | EATL Interface: Line cut into Newell and commission. | |
ALTALINK | 14-Jun-14 07:00 | 07-Aug-14 18:00 | 55 Days Continuous | 1035L(324s-244s)GOI | EATL Interface: Line cut in and out. | |
ALTALINK | 15-Jun-14 07:00 | 20-Jun-14 18:00 | 6 Days Continuous | 925L (63s Red Deer - 74s Janet) | L to J : Replace 74s21N, PTs, CTs and footings. | AB-BC |
ALTALINK | 21-Jun-14 07:00 | 26-Jun-14 18:00 | 6 Days Continuous | 901L (63s Red Deer - 74s Janet) | L to J : Replace 74s24N, PTs, CTs and footings. | AB-BC |
ENMAX | 26-Jun-14 08:00 | 30-Jun-14 16:00 | 5 Days Continuous | 5sT2 | Tie into 138KV GIS @ 2s | |
ALTALINK | 14-Jul-14 08:00 | 14-Jul-14 13:00 | 5 Hours Daily | 77s14 - GOI | SCADA Equipment Upgrade | |
ALTALINK | 15-Jul-14 08:00 | 15-Jul-14 13:00 | 5 Hours Daily | 275s1752 - GOI | SCADA Equipment Upgrade | |
ALTALINK | 15-Jul-14 08:00 | 15-Jul-14 13:00 | 5 Hours Daily | 77s48 - GOI | SCADA Equipment Upgrade | |
ALTALINK | 15-Jul-14 13:00 | 15-Jul-14 14:00 | 60 Mins Daily | 919L (77s-310p) - Advice | SCADA Equipment Upgrade | |
ALTALINK | 16-Jul-14 08:00 | 16-Jul-14 13:00 | 5 Hours Daily | 77s40 - GOI | SCADA Equipment Upgrade | |
ALTALINK | 16-Jul-14 08:00 | 16-Jul-14 13:00 | 5 Hours Daily | 275s1852 - GOI | SCADA Equipment Upgrade | |
ALTALINK | 16-Jul-14 13:00 | 16-Jul-14 14:00 | 60 Mins Daily | 938L (77s-A809s) - Advice | SCADA Equipment Upgrade | |
ALTALINK | 16-Jul-14 13:30 | 16-Jul-14 14:30 | 60 Mins Daily | 951L (275s-132s) - Advice | SCADA Equipment Upgrade | |
ALTALINK | 19-Jul-14 07:00 | 22-Jul-14 18:00 | 4 Days Continuous | 935L(356s-324s)GOI | EATL Interface: Relocate to original tower. | |
ALTALINK | 21-Jul-14 08:00 | 21-Jul-14 13:00 | 5 Hours Daily | 77s29 - GOI | SCADA Equipment Upgrade | |
ALTALINK | 22-Jul-14 08:00 | 22-Jul-14 13:00 | 5 Hours Daily | 77s26 - GOI | SCADA Equipment Upgrade | |
ALTALINK | 22-Jul-14 08:00 | 22-Jul-14 13:00 | 5 Hours Daily | 275s1952 - GOI | SCADA Equipment Upgrade | |
ALTALINK | 22-Jul-14 13:00 | 22-Jul-14 14:00 | 60 Mins Daily | 989L (77s-310p) - Advice | SCADA Equipment Upgrade | |
ALTALINK | 22-Jul-14 13:30 | 22-Jul-14 14:30 | 60 Mins Daily | 1002L (275s-163s) - Advice | SCADA Equipment Upgrade | |
ALTALINK | 23-Jul-14 07:00 | 28-Jul-14 18:00 | 6 Days Continuous | 923L(356s-324s)GOI | EATL Interface: Line cut in. | |
ALTALINK | 23-Jul-14 07:00 | 31-Jul-14 18:00 | 9 Days Continuous | 1087L(OLD 923L)(324s-Newell)GOI | EATL Interface: Line cut in and commission. | |
ALTALINK | 23-Jul-14 08:00 | 23-Jul-14 13:00 | 5 Hours Daily | 77s51 - GOI | SCADA Equipment Upgrade | |
ALTALINK | 23-Jul-14 08:00 | 23-Jul-14 13:00 | 5 Hours Daily | 275s2 - GOI | SCADA Equipment Upgrade | |
ALTALINK | 28-Jul-14 08:00 | 28-Jul-14 13:00 | 5 Hours Daily | 77s54 - GOI | SCADA Equipment Upgrade | |
ALTALINK | 29-Jul-14 08:00 | 29-Jul-14 13:00 | 5 Hours Daily | 275s5 - GOI | SCADA Equipment Upgrade | |
ALTALINK | 29-Jul-14 08:00 | 29-Jul-14 13:00 | 5 Hours Daily | 77s57 - GOI | SCADA Equipment Upgrade | |
ALTALINK | 29-Jul-14 13:00 | 29-Jul-14 14:00 | 60 Mins Daily | 907L (77s-122s) - Advice | SCADA Equipment Upgrade | |
ALTALINK | 29-Jul-14 13:30 | 29-Jul-14 14:30 | 60 Mins Daily | 944L (275s-132s) - Advice | SCADA Equipment Upgrade | |
ALTALINK | 29-Jul-14 14:00 | 29-Jul-14 15:00 | 60 Mins Daily | 939L (77s-A809s) - Advice | SCADA Equipment Upgrade | |
ALTALINK | 30-Jul-14 08:00 | 30-Jul-14 13:00 | 5 Hours Daily | 275s8 - GOI | SCADA Equipment Upgrade | |
ALTALINK | 30-Jul-14 13:30 | 30-Jul-14 14:30 | 60 Mins Daily | 945L (275s-562s) - Advice | SCADA Equipment Upgrade | |
ALTALINK | 03-Aug-14 07:00 | 10-Aug-14 18:00 | 8 Days Continuous | 942L (71s Lamoureux - 13s Deerland) | EATL interface: ATCO deadline crossing for 13L50 | |
ALTALINK | 03-Aug-14 07:00 | 10-Aug-14 18:00 | 8 Days Continuous | 943L (13s Deerland - 108s Amelia) | EATL interface: ATCO deadline crossing for 13L50 | |
ALTALINK | 06-Aug-14 08:00 | 06-Aug-14 15:00 | 7 Hours Daily | 275s T1(TX18457) - GOI | SCADA Equipment Upgrade | |
ALTALINK | 12-Aug-14 08:00 | 12-Aug-14 13:00 | 5 Hours Daily | 77s552 - GOI | SCADA Equipment Upgrade | |
ALTALINK | 12-Aug-14 08:00 | 12-Aug-14 15:00 | 7 Hours Daily | 275s T2(TX18458) - GOI | SCADA Equipment Upgrade | |
ENMAX | 14-Aug-14 08:00 | 27-Aug-14 16:00 | 14 Days Continuous | 917L | 23s flyover with 2-240 ccts. | |
ALTALINK | 19-Aug-14 08:00 | 19-Aug-14 14:00 | 6 Hours Daily | 77s T1(TX18372) - GOI | SCADA Equipment Upgrade | |
ALTALINK | 20-Aug-14 08:00 | 20-Aug-14 14:00 | 6 Hours Daily | 77s T2(TX18521) - GOI | SCADA Equipment Upgrade | |
ATCO | 25-Aug-14 08:30 | 29-Aug-14 15:30 | 5 Days Continuous | 840S McNeill Station | McNeill 2014 FALL Turn Around. | AB-SK |
ENMAX | 01-Sep-14 08:00 | 01-Feb-15 16:00 | 154 Days Continuous | 65.1TR | FATD, Check reversing sw, Doble, Oil sample LTC | |
ALTALINK | 05-Sep-14 08:00 | 02-Oct-14 16:00 | 28 Days Continuous | 5s C1 (5s East Calgary), 5s C2 (5s East Calgary) | ECTP 2s, Swap AIS to GIS | AB-BC |
ALTALINK | 16-Sep-14 07:30 | 30-Sep-14 18:00 | 15 Days Continuous | 74s C3 (74s Janet), 74s C4 (74s Janet), 74s T2 (74s Janet) | Janet to Langdon project. Tie in South Bus Extension. | AB-BC |
ALTALINK | 17-Sep-14 08:00 | 17-Sep-14 14:00 | 6 Hours Daily | 473c102 (C1) - GOI | SCADA Equipment Upgrade | |
ALTALINK | 28-Sep-14 07:30 | 09-Oct-14 18:00 | 12 Days Continuous | 1203L (320p Keephills - 330p Genesee) | Cut in/out of 510s - WATL. ***outage duration is under review with the TFO’s and may be shortened as we get closer to the date*** | AB-BC |
ALTALINK | 29-Sep-14 08:00 | 05-Jan-15 18:00 | 99 Days Continuous | 5s T1 and 240KV Bus GOI | East Calgary 5S – Replace existing TXMER with new. | |
ALTALINK | 01-Oct-14 08:00 | 15-Oct-14 18:00 | 15 Days Continuous | 74s T1 and 240 kV Bus 1 GOI | Janet to Langdon project. Tie in North Bus Extension. |
AB-BC, AB-SK & AB-MATL: refer to AESO web posting: | http://itc.aeso.ca/itc/public/atcQueryInit.do |
Also, | |
AB-BC, AB-SK & AB-MATL: refer to ISO Rule 203.6: | http://www.aeso.ca/rulesprocedures/18592.html |
Prepared On: | 2014-03-05 4:51:00 PM |
This document and the information contained herein are based upon information and data which by their nature contain a degree of uncertainty and are subject to change. In addition, this document may contain information and data from public sources and/or third parties, which have been assumed to be accurate and complete and have not been verified. Accordingly, the Independent System Operator, operating as the Alberta Electric System Operator (the "AESO") makes no warranty, representation or guarantee, express or implied, with respect to this document or the information contained herein, including, but not limited to, any warranty, representation or guarantee of accuracy, completeness, timeliness, reliability, availability, absence of computer virus, non- infringement, merchantability or suitability for any purpose. Under no circumstances will the AESO, its members, officers, employees, contractors or agents, or any of their respective affiliates, be liable for any errors or omissions in, or any losses, damages or claims whatsoever, whether in contract, tort or otherwise, arising from use of or reliance upon, this document or any information contained herein. © 2009 Alberta Electric System Operator. All rights reserved |