Alberta Electric System Operator
System Co-ordination Plan
2013-12-23 to 2014-01-10
Approved Outages

Previous Version
Download CSV

From To Owner Type Element Scheduled Activity Date/Time Comments Interconnection
17-Jun-13 08:00 10-Jan-14 17:00 ENMAX Outage 9.62L (ENMAX 10 - ENMAX 9) 10 sub re-build to future 138kV 208 Days
Continuous
 
22-Sep-13 08:00 23-Dec-13 16:00 ENMAX Outage 32.82L (ENMAX 54 - ENMAX 32) re-conductor 93 Days
Continuous
 
27-Sep-13 14:00 31-Jul-14 18:00 ALTALINK IO Future 1109/985L (Open point LandN-C25s) ECTP: ENMAX to close Open Points(risers) on 1109/985L bays @ C25s 308 Days
Continuous
 
04-Nov-13 10:00 17-Jan-14 18:00 ALTALINK Outage 923L (324s Cassils - 356s Milo) re-conductor STR’s 87 - 104. 75 Days
Continuous
 
07-Nov-13 08:00 01-May-14 17:00 ALTALINK Outage 551BL1 (551BL) Advice CPR building new line. 176 Days
Continuous
 
21-Nov-13 08:00 31-Jan-14 16:00 ATCO Outage 732s 503R (732s Mitsue) Forced Outage 72 Days
Continuous
 
28-Nov-13 11:00 31-Mar-14 16:00 ALTALINK Outage 526L (515s Fed Pipe Judy Creek - 626L418) to allow new IPP at 659s Pegasus Lake to come online 124 Days
Continuous
 
03-Dec-13 07:00 31-Jan-14 18:00 ALTALINK IO 1034L (244s Bowmanton - 324s Cassils), 1035L (244s Bowmanton - 324s Cassils) replacement of defective bolts on towers 60 Days
Continuous
 
10-Dec-13 08:00 12-Jan-14 16:00 ENMAX TE ENMAX 14 14 sub 138 kV bus differential protection upgrade 34 Days
Continuous
 
11-Dec-13 08:00 17-Jan-14 17:00 ATCO TE 755s Cordel RTU/SCADA upgrade RTU 38 Days
Continuous
 
18-Dec-13 08:00 15-Jan-14 16:00 ALTALINK Outage 89s 1852 (89s Ellerslie) Heartland project 29 Days
Continuous
 
20-Dec-13 07:00 24-Dec-13 17:00 ALTALINK RB 920L (37s North Calder - 557s Castle Downs) working in the vicinity of 920L 5 Days
Daily
 
20-Dec-13 07:00 24-Dec-13 18:00 ALTALINK Outage 726L (37s North Calder - 71s Lamoureux) modify structures 17 to 22 5 Days
Continuous
 
20-Dec-13 07:00 23-Dec-13 18:00 ALTALINK RB 920L (37s North Calder - 557s Castle Downs) AltaLink transmission line work 4 Days
Continuous
 
23-Dec-13 08:00 27-Dec-13 16:00 Syncrude Outage Aurora T1, Aurora T-11 relay setting for tap changer 5 Days
Continuous
 
23-Dec-13 08:00 27-Dec-13 10:00 ATCO TE ATCO's system operations centre security patch install on SCADA workstations 5 Days
Continuous
 
23-Dec-13 10:00 23-Dec-13 12:00 ALTALINK Outage 77s 752 (77s Sagitawah) add SF6 2 Hours
Daily
 
23-Dec-13 10:00 23-Dec-13 12:00 ALTALINK Outage 258s 252 (258s Dow Hydrocarbons) add SF6 2 Hours
Continuous
 
23-Dec-13 12:00 23-Dec-13 14:00 ALTALINK Outage 77s 452 (77s Sagitawah) add Sf6 2 Hours
Daily
 
27-Dec-13 13:00 27-Dec-13 13:00 ALTALINK Trans Test/Comm 1206L/1212L energization energized at 240 kV 0 Mins
Daily
 
30-Dec-13 09:00 30-Dec-13 15:00 ALTALINK TE 906s Ross Creek RTU/SCADA RTU update 6 Hours
Continuous
 
30-Dec-13 09:30 31-Dec-13 16:00 ATCO Outage 6L05 (764s Heisler - 843s Bigknife Creek) maintenance 30.5 Hours
Continuous
 
02-Jan-14 10:00 02-Jan-14 12:00 ATCO TE ATCO's system operations centre replacing OSI COMM switch 2 Hours
Continuous
 
06-Jan-14 07:00 10-Jan-14 18:00 ATCO TE 700s Bonnyville RTU/SCADA RTU upgrade 5 Days
Continuous
 
06-Jan-14 07:30 06-Jan-14 17:00 ALTALINK Outage 928L (17s Benalto - 42s Sarcee) EPSC Working 36.111 9.5 Hours
Daily
AB-BC
06-Jan-14 07:30 06-Jan-14 17:00 ALTALINK Outage 928L (17s Benalto - 42s Sarcee) ENMAX crews working on distribution in area 9.5 Hours
Daily
 
06-Jan-14 08:00 13-Jan-14 16:00 ENMAX Outage 26.81L (ENMAX 54 - ENMAX 26) re-conductor 8 Days
Continuous
 
06-Jan-14 08:00 07-Jan-14 16:00 ENMAX Outage 1.84L (ENMAX 1 - ENMAX 5) top-up gas on A6-II GIS breaker 2 Days
Continuous
 
06-Jan-14 08:00 09-Jan-14 16:00 ATCO Outage 930s Syn Condenser (930s Arcenciel) bird mitigation and deficencies 4 Days
Continuous
 
07-Jan-14 05:00 07-Jan-14 11:30 EPCOR Outage 803s T1 (803s Lambton) prep work in preparation of transformer replacement 6.5 Hours
Continuous
 
07-Jan-14 07:00 07-Feb-14 18:00 ALTALINK Outage 797L (364s Whitecourt industrial - 268s Whitecourt), 364s Whitecourt Industrial 138 kV Bus 1 re-configure 797L at 364s 32 Days
Continuous
 
07-Jan-14 07:00 16-Jan-14 18:00 ATCO RB 7L85 (804s Wintering Hills - 803s Bullpound), 7L85 (803s Bullpound - 801s Anderson) string OPGW for new EATL line 10 Days
Continuous
 
07-Jan-14 08:00 13-Mar-14 19:00 ALTALINK Outage 164L (103s Goose Lake - 415s Drywood) rebuild 164L( 2nd stage) from Str #65 to Str #173. 66 Days
Continuous
 
07-Jan-14 10:00 07-Jan-14 12:00 ALTALINK IO 48S Pocaterra BCH request - RAS testing 2 Hours
Daily
 
07-Jan-14 10:00 07-Jan-14 14:00 ATCO Outage 822s Wolf Lake RTU/SCADA 822S 7L574 Relay Protection 4 Hours
Continuous
 
07-Jan-14 12:00 07-Jan-14 18:00 EPCOR Outage 803s T2 (803s Lambton) prep work in preparation of transformer replacement 6 Hours
Continuous
 
07-Jan-14 13:00 07-Jan-14 17:00 ALTALINK Outage 108s 352 (108s Amelia) correct deficiency on breaker 4 Hours
Daily
 
08-Jan-14 08:00 10-Jan-14 18:00 ALTALINK Outage 108s 152 (108s Amelia) add sync check 3 Days
Continuous
 
08-Jan-14 08:00 30-Apr-14 19:00 ALTALINK Outage 58L (245s Seebe - 32s Barrier), 90L (115s Mt. Allan - 32s Barrier) salvage 58L/90L and 32s re-build 113 Days
Continuous
 
08-Jan-14 10:00 08-Jan-14 12:00 ALTALINK Outage 80L (194s South Red Deer - 63s Red Deer) connect mobile to 80L 2 Hours
Daily
 
08-Jan-14 12:00 11-Jan-14 12:00 ALTALINK Outage 63s T1 (63s Red Deer), 63s T3 (63s Red Deer), 80L (194s South Red Deer - 63s Red Deer), 63s Red Deer 138 kV North Bus replace 138kV PT's, replace 138kV LAs on T3 3 Days
Continuous
 
09-Jan-14 01:30 09-Jan-14 04:00 ALTALINK Outage 780L (38s East Edmonton - 149s Nisku), 897L (38s East Edmonton - 45s Bretona) high load move 2.5 Hours
Daily
 
09-Jan-14 08:00 31-Jan-14 16:00 ENMAX Outage 1B138-8A0 (ENMAX 1) maintenance 23 Days
Continuous
 

Prepared On:   2013-12-23   9:50:18 AM

This document and the information contained herein are based upon information and data which by their nature contain a degree of uncertainty and are subject to change. In addition, this document may contain information and data from public sources and/or third parties, which have been assumed to be accurate and complete and have not been verified. Accordingly, the Independent System Operator, operating as the Alberta Electric System Operator (the "AESO") makes no warranty, representation or guarantee, express or implied, with respect to this document or the information contained herein, including, but not limited to, any warranty, representation or guarantee of accuracy, completeness, timeliness, reliability, availability, absence of computer virus, non- infringement, merchantability or suitability for any purpose. Under no circumstances will the AESO, its members, officers, employees, contractors or agents, or any of their respective affiliates, be liable for any errors or omissions in, or any losses, damages or claims whatsoever, whether in contract, tort or otherwise, arising from use of or reliance upon, this document or any information contained herein.