Alberta Electric System Operator
System Co-ordination Plan
2013-11-30 to 2013-12-06
Approved Outages

Previous Version
Download CSV

From To Owner Type Element Scheduled Activity Date/Time Comments Interconnection
17-Jun-13 08:00 31-Dec-13 17:00 ENMAX Outage 9.62L (ENMAX 10 - ENMAX 9) 10 sub re-build to future 138kV 198 Days
Continuous
 
22-Sep-13 08:00 12-Dec-13 16:00 ENMAX Outage 32.82L (ENMAX 54 - ENMAX 32) re-conductor 82 Days
Continuous
 
27-Sep-13 14:00 31-Jul-14 18:00 ALTALINK IO Future 1109/985L (Open point LandN-C25s) ECTP: ENMAX to close Open Points(risers) on 1109/985L bays @ C25s 308 Days
Continuous
 
23-Oct-13 08:00 21-Dec-13 17:00 ALTALINK Outage 734L (241s Lethbridge Uplands - 370s North Lethbridge) outage required for approach to install new sewer/water lines 60 Days
Continuous
 
04-Nov-13 08:00 06-Dec-13 18:00 ALTALINK RB 935L (324s Cassils - 356s Milo) re conductor 923L, which is on the same double circuit towers as 935L. 33 Days
Daily
 
07-Nov-13 08:00 01-May-14 17:00 ALTALINK Outage 551BL1 (551BL) Advice CPR building new line. 176 Days
Continuous
 
12-Nov-13 08:00 20-Dec-13 18:00 ALTALINK IO 12s Heartland 240 kV Bus 1 modify bus to connect 1206L energized at 240 kV - Heartland 39 Days
Continuous
 
15-Nov-13 08:00 02-Dec-13 14:00 ATCO Outage 7L59 (786s High Level - 789s Keg River) replace crossarms 18 Days
Continuous
 
16-Nov-13 08:00 06-Dec-13 16:00 ENMAX Outage Enmax 1 B138-7A0 (ENMAX 1) breaker maintenance 21 Days
Continuous
 
17-Nov-13 08:00 20-Dec-13 16:00 ATCO Outage 757s 702 (757s Battle River) replacement 34 Days
Continuous
 
17-Nov-13 08:00 12-Dec-13 16:00 ALTALINK RB 1058L (657s Summerside - 803s Lambton), 908L (38s East Edmonton - 908AL tap), 946L (89s Ellerslie - 38s East Edmonton), 947L (89s Ellerslie - 987s Clover Bar) installing sock line, pulling conductor in vicinity for new heartland project 1212L and 1206L 26 Days
Continuous
 
17-Nov-13 08:00 12-Dec-13 19:00 ALTALINK RB 780L (38s East Edmonton - 149s Nisku) 1206L & 1212L stringing 26 Days
Continuous
 
19-Nov-13 08:00 10-Dec-13 20:59 SUNCOR Outage Suncor (Millennium) Islanding RAS (IRAS) RAS upgrade 22 Days
Continuous
 
21-Nov-13 08:00 31-Jan-14 16:00 ATCO Outage 732s 503R (732s Mitsue) Forced Outage 72 Days
Continuous
 
22-Nov-13 11:01 11-Dec-13 18:00 ALTALINK Outage 38s 62 (38s East Edmonton), 38s34 (38s East Edmonton) test trip of 38s62 for 38sT3 protections 20 Days
Daily
 
23-Nov-13 07:30 20-Dec-13 16:00 EPCOR Outage NamaoT2 (Namao) new switchgear installation 28 Days
Continuous
 
25-Nov-13 08:00 30-Nov-13 17:00 ALTALINK Outage 38s T3 (38s East Edmonton) protection replacement on T3, 38s87 & 38s45 6 Days
Continuous
 
25-Nov-13 08:00 06-Dec-13 15:00 ALTALINK IO 807L (233s Beamer - 807L tap), 807L (410s Josephburg - 807L tap) COG for AltalInk work on 807L 12 Days
Continuous
 
25-Nov-13 08:00 06-Dec-13 15:00 ALTALINK Outage 807L (233s Beamer - 807L tap), 807L (410s Josephburg - 807L tap) 233s807X breaker replacement 12 Days
Continuous
 
26-Nov-13 08:00 01-Dec-13 17:00 ATCO Outage 7L92 (777s Vilna - 709s Vegreville) to complete the inline switches and install the tap from the line 6 Days
Continuous
 
26-Nov-13 08:00 05-Dec-13 18:00 ALTALINK Outage 753L (65s High River - 253s Blackie) replace insulators, structures and arms 10 Days
Continuous
 
26-Nov-13 08:00 06-Dec-13 15:00 ALTALINK RB 715L (545s Provost - 650s Hansman Lake) replacing structures 11 Days
Daily
 
27-Nov-13 10:00 09-Dec-13 10:00 ALTALINK Outage 632L (325s Leduc - 538s Buford), 837L (964s Pigeon Lake - 538s Burford) replace control building, upgrade P&C and SCADA schemes 12 Days
Continuous
 
28-Nov-13 07:00 01-Dec-13 13:00 ALTALINK Outage 150L (42s Sarcee - 150L47) high load move under 150L 4 Days
Continuous
 
28-Nov-13 07:30 30-Nov-13 16:00 ALTALINK RB 1044L (805s Jasper - 816s Petrolia) maintenance 3 Days
Continuous
 
28-Nov-13 08:00 18-Dec-13 18:00 ALTALINK Outage 162L (415s Drywood - 229s Glenwood) line rebuild 21 Days
Continuous
 
28-Nov-13 08:00 01-Dec-13 18:00 EPCOR RB 1055L (629s Argyll Transfer Station - Petrolia) AltaLink transmission line work 4 Days
Continuous
 
28-Nov-13 08:00 02-Dec-13 18:00 ATCO TE 701T 50/51 Tie in and commission 50-51/701T wiring 5 Days
Continuous
 
28-Nov-13 08:00 02-Dec-13 18:00 ATCO TE 7L56 86T3 RELAY Rewiring block trip/close from 86T3 to 144KV line MOD's 5 Days
Continuous
 
28-Nov-13 10:00 01-Dec-13 17:00 ALTALINK, EPCOR Outage 908L (89s Ellerslie - 816s Petrolia), 909L (320p Keephills - 665s Dome) installing a monopole mid span 4 Days
Continuous
 
28-Nov-13 10:00 01-Dec-13 17:00 EPCOR RB 1055L (629s Argyll Transfer Station - Petrolia) installing a monopole mid span on 909L & 908L (Working in the vicinity) 4 Days
Continuous
 
28-Nov-13 11:00 31-Mar-14 16:00 ALTALINK Outage 526L (515s Fed Pipe Judy Creek - 626L418) to allow new IPP at 659s Pegasus Lake to come online 124 Days
Continuous
 
29-Nov-13 08:00 02-Dec-13 18:00 ATCO TE 701T 87 RELAY Tie in tripping relays to non-electrical and differnetial relay circuits.
-Commission BKR 701 tripping circuits wihtout physically tripping breaker
Tie in and commission tripping relays
4 Days
Continuous
 
29-Nov-13 08:00 02-Dec-13 18:00 ATCO TE 701T 86 RELAY Remove 86T-2in prep. to install 94-TEMP 4 Days
Continuous
 
30-Nov-13 08:00 01-Dec-13 17:00 ALTALINK Outage 253s C1 (253s Blackie), 161L (255s Vulcan - 253s Blackie), 851L (525s Carseland - 253s Blackie), 852L (253s Blackie - 504s Queenstown), 253S Blackie 138 kV bus bus protection relay change-out, bus protection relay change-out. 2 Days
Continuous
 
30-Nov-13 08:00 30-Nov-13 16:00 ENMAX Outage 23.80L (74s Janet - ENMAX 23) isolate to split trip coils on
23B138-23.80
8 Hours
Daily
 
30-Nov-13 08:00 30-Dec-13 16:00 ENMAX IO 162s Beddington re-route fiber 31 Days
Continuous
 
30-Nov-13 08:00 30-Nov-13 16:00 ENMAX Outage 23.80L (74s Janet - ENMAX 23) ENMAX trip coils on 23B138-23.80 8 Hours
Daily
 
30-Nov-13 08:00 01-Dec-13 17:30 ALTALINK Outage 56L (245s Seebe - 20s Ghost) replacing dead end insulators on multiple structures. 2 Days
Continuous
 
30-Nov-13 09:00 01-Dec-13 15:00 ATCO RB 9L32 (941s Bitumount -957s McClelland) tie in 957s McClelland 30 Hours
Continuous
 
01-Dec-13 08:00 01-Dec-13 19:00 ENMAX Outage 23.3TR (ENMAX 23), 2.80L (ENMAX 2 - ENMAX 23) separating trip contacts 11 Hours
Continuous
 
01-Dec-13 08:00 02-Dec-13 18:00 ATCO TE 738S Virginia Hills to tie in and commission 701 2 Days
Continuous
 
01-Dec-13 09:00 01-Dec-13 17:30 ALTALINK Outage 253s 182 (253s Blackie) 138kV C/S maintenance 8.5 Hours
Daily
 
01-Dec-13 10:00 01-Dec-13 14:00 ALTALINK TE 253s Blackie RTU/SCADA alarm addition and SCADA verification for bus prot
replacement
4 Hours
Continuous
 
02-Dec-13 08:00 03-Dec-13 17:00 ATCO Outage 9L32 (849s Joslyn Creek - 941s Bitumount) install a permanent structure on 9L32 outside of McClelland SUB. 2 Days
Continuous
 
02-Dec-13 08:00 13-Dec-13 16:00 EPCOR Outage 72RW3 (Rossdale - Woodcroft) replace BD1W Switch 12 Days
Daily
 
02-Dec-13 08:00 13-Dec-13 16:00 EPCOR Outage 72RG7 (Rossdale - Garneau) replace BD1W Switch 12 Days
Daily
 
02-Dec-13 08:00 03-Dec-13 16:00 ENMAX RB 14.83L (ENMAX 14 - ENMAX 36) Tree trimming 2 Days
Daily
 
02-Dec-13 08:00 03-Dec-13 16:00 EPCOR Outage 557s T1 (557s Castle Downs) tapchanger maintenance 2 Days
Continuous
 
02-Dec-13 08:30 04-Dec-13 17:00 ATCO Outage 7L45 (798s Bridge Creek - 813s Little Smoky) inspection and install conductor damper between 7L45D2 and 813s 3 Days
Daily
 
02-Dec-13 09:00 02-Dec-13 17:00 ALTALINK TE 415s Drywood RTU/SCADA update RTU configuration 8 Hours
Daily
 
02-Dec-13 09:30 05-Dec-13 14:00 ATCO TE 989s Quigley RTU/SCADA download RTU update HMI program. commissioning activities 4 Days
Continuous
 
02-Dec-13 10:00 05-Dec-13 16:00 ATCO Outage 7L162 (732s Mitsue - 729s Otauwau) 729s Ottauwau bkr 704 o/s to replace the 21b relay 4 Days
Continuous
 
02-Dec-13 11:00 02-Dec-13 12:00 ALTALINK TE 966L (650s Hansman Lake - 932s Pemukan) replace fibre optic cable splice - affects 966L 'B' protection only 60 Mins
Daily
 
02-Dec-13 12:00 02-Dec-13 16:00 ALTALINK TE 415s Drywood RTU/SCADA, 379s Shell Canada Waterton RTU/SCADA, 385s Spring Coulee RTU/SCADA resolve power supply alarm 4 Hours
Daily
 
02-Dec-13 15:00 05-Dec-13 23:00 ATCO TE 732S Mitsue 732S Station General Equipment OOS 4 Days
Continuous
 
03-Dec-13 07:00 21-Dec-13 18:00 ALTALINK IO 1034L (244s Bowmanton - 324s Cassils), 1035L (244s Bowmanton - 324s Cassils) replacement of defective bolts on towers 19 Days
Continuous
 
03-Dec-13 08:00 03-Dec-13 17:00 ALTALINK Outage 61L (252s Jarrow - 61DL386), 252s 61 (252s Jarrow) tank heater replacement 9 Hours
Daily
 
03-Dec-13 08:00 06-Dec-13 17:30 ALTALINK Outage 777L (245s Seebe - 48s Pocaterra) replacing badly damaged insulators 4 Days
Daily
AB-BC
03-Dec-13 08:00 04-Dec-13 16:00 ENMAX RB 7.84L (ENMAX 36 - ENMAX 7) tree trimming 2 Days
Daily
 
03-Dec-13 08:00 04-Dec-13 16:00 ENMAX RB 11.82L (ENMAX 14 - ENMAX 11) tree trimming 2 Days
Daily
 
03-Dec-13 08:00 03-Dec-13 16:00 ATCO TE 716S Lloydminster relay test 8 Hours
Continuous
 
03-Dec-13 08:00 04-Dec-13 16:30 ATCO TE 849s Joslyn Creek RTU/SCADA download RTU update HMI program 2 Days
Continuous
 
03-Dec-13 08:00 03-Dec-13 10:00 ALTALINK Outage 799s T3 (799s Coleman) perform a noise measurement 2 Hours
Daily
 
03-Dec-13 08:00 03-Dec-13 12:00 ALTALINK IO 9282R - Info troubleshooting RX optical power alarm on MPLS 4 Hours
Daily
 
03-Dec-13 12:00 03-Dec-13 17:00 ALTALINK TE 356s Milo RTU/SCADA investigate power supply warning 5 Hours
Daily
 
03-Dec-13 14:00 03-Dec-13 17:00 ALTALINK RB 995AL (68s Willesden Green - 995L tap), 995L (17s Benalto - 995AL tap) high load move 3 Hours
Daily
 
03-Dec-13 15:00 04-Dec-13 23:00 ATCO TE 989s Quigley RTU/SCADA commissioning: scada end to end for 7L167 2 Days
Continuous
 
04-Dec-13 07:00 04-Dec-13 17:00 ALTALINK TE 364s Whitecourt Industrial RTU/SCADA supervisory: download of new configuration to D20 RTU, Verification off new alarm points to ACC and local HMI 10 Hours
Daily
 
04-Dec-13 07:00 04-Dec-13 19:00 ATCO RB 7L25 (768s Rowley - 802s Michichi Creek) work within proximity on 7L137 12 Hours
Continuous
 
04-Dec-13 08:00 04-Dec-13 15:00 ALTALINK TE 500S Flatbush new SCADA system 7 Hours
Daily
 
04-Dec-13 08:00 04-Dec-13 09:00 ALTALINK Outage 822L (38s East Edmonton - 822AL tap), 822L (133s Stelco Edmonton - 822L tap), 38s 822X (38s East Edmonton) test trip of 38s822X related 38sT2 protection upgrade 60 Mins
Daily
 
04-Dec-13 08:00 13-Dec-13 16:00 ENMAX Outage 20.82L (ENMAX 21 - ENMAX 20) line diff / corna ring install on St 19 10 Days
Continuous
 
04-Dec-13 08:00 04-Dec-13 16:00 ATCO TE 751S Hill change setting and test relay and isolate 8 Hours
Continuous
 
04-Dec-13 08:00 06-Dec-13 16:00 EPCOR Outage 557s T2 (557s Castle Downs) Tapchanger Maintenance 3 Days
Continuous
 
04-Dec-13 08:00 04-Dec-13 12:00 ALTALINK Outage 717L (17s Benalto - 262s Rocky Mountain House) moving high load move under 717L. 4 Hours
Daily
 
04-Dec-13 08:00 04-Dec-13 12:00 Lethbridge IO 823L (146s Lethbridge MacDonald - 593s Lethbridge Lakeview) Lethbridge line work 4 Hours
Daily
 
04-Dec-13 08:00 04-Dec-13 17:00 ALTALINK IO 410S Josephburg analogs at 410s are suspect 9 Hours
Daily
 
04-Dec-13 08:00 04-Dec-13 12:00 Lethbridge Outage 823L (146s Lethbridge MacDonald - 593s Lethbridge Lakeview) install SWAGE connections 4 Hours
Daily
 
04-Dec-13 08:00 04-Dec-13 17:00 ALTALINK IO 77s T1 (77s Sagitawah), 77s Sagitawah 138 kV West Bus function check 77s352 from A87/ 138’W’, B87 / 138’W’ A87/T1 & B87/T1
9 Hours
Continuous
 
04-Dec-13 08:00 05-Dec-13 17:00 ALTALINK Outage 310p 2552 (310p Sundance) replace leaky CT 2 Days
Continuous
 
04-Dec-13 09:00 04-Dec-13 14:00 ALTALINK Outage 807L (233s Beamer - 807L tap), 233s Beamer 138 kV Bus 1 233s 807L bus side riser replacement 5 Hours
Daily
 
04-Dec-13 09:00 04-Dec-13 16:00 ATCO Outage 840S McNeill Station replace fire sensor Valve Hall. 7 Hours
Continuous
AB-SK
04-Dec-13 09:00 05-Dec-13 16:00 ATCO Outage 840S 502 replace breaker mech and Vac bottles 31 Hours
Continuous
 
04-Dec-13 09:00 04-Dec-13 16:00 ATCO Outage 840S McNeill Station ATCO replace fire sensor valve hall. 7 Hours
Daily
 
04-Dec-13 09:01 04-Dec-13 10:00 ALTALINK Outage 738L (38s East Edmonton - 95s Imperial Oil Edmonton), 38s 220 (38s East Edmonton) test trip of 38s738W related to 38sT2 protection upgrade 59 Mins
Daily
 
04-Dec-13 10:00 04-Dec-13 11:00 ALTALINK TE 38s East Edmonton RTU/SCADA supervisory: update RTU configuration and test alarms, status, and controls 60 Mins
Daily
 
04-Dec-13 10:00 17-Dec-13 17:00 ALTALINK Outage 83s T1 (83s Taber), 83s T3 (83s Taber), AltaLink 25kV Bus 1&2 replace 83s12, s13, s14, s16, s17, s18, s19, s21, s22, s23,s24, s40, s53, install bird coverup 14 Days
Continuous
 
04-Dec-13 12:00 04-Dec-13 15:30 ATCO TE 784s 701T (784s Donnelly) 50/51 mechanical overcurrent relay testing 3.5 Hours
Continuous
 
05-Dec-13 07:00 10-Dec-13 19:00 ATCO Outage 7L143 (766s Nevis - 769s Stettler) install dampners 6 Days
Continuous
 
05-Dec-13 08:30 06-Dec-13 17:00 ATCO Outage 7L45 (845s Big Mountain - 798s Bridge Creek), 7L45 (798s Bridge Creek - 813s Little Smoky) inspection & install conductor damper 2 Days
Daily
 
05-Dec-13 12:00 05-Dec-13 13:00 ALTALINK Outage 763L (83s Taber - 158s Vauxhall), 83s38 (83s Taber) test trip of 83s763N for 38s61 breaker fail 60 Mins
Daily
 
05-Dec-13 13:01 05-Dec-13 14:00 ALTALINK Outage 610L (336s Fincastle Sub - 83s Taber), 83s2 (83s Taber) test trip of 83s610 for 38s61 breaker fail 59 Mins
Daily
 
05-Dec-13 14:01 05-Dec-13 15:00 ALTALINK Outage 172L (83s Taber - 172L 944A), 83s36 (83s Taber) test trip of 83s172W for 38s61 breaker fail 59 Mins
Daily
 
06-Dec-13 08:00 06-Dec-13 17:00 ALTALINK Outage 223s 39 (223s Strome), 701L (395s North Holden - 223s Strome) low/leaking gas on breaker 9 Hours
Daily
 
06-Dec-13 08:00 06-Dec-13 17:00 ENMAX Outage 9.83L (ENMAX 43 - ENMAX 9) Sheath Test 9 Hours
Daily
 
06-Dec-13 08:30 06-Dec-13 17:30 ALTALINK Outage 74s 2252 (74s Janet) Slow breaker operation 9 Hours
Daily
 

Prepared On:   2013-11-28   4:51:15 PM

This document and the information contained herein are based upon information and data which by their nature contain a degree of uncertainty and are subject to change. In addition, this document may contain information and data from public sources and/or third parties, which have been assumed to be accurate and complete and have not been verified. Accordingly, the Independent System Operator, operating as the Alberta Electric System Operator (the "AESO") makes no warranty, representation or guarantee, express or implied, with respect to this document or the information contained herein, including, but not limited to, any warranty, representation or guarantee of accuracy, completeness, timeliness, reliability, availability, absence of computer virus, non- infringement, merchantability or suitability for any purpose. Under no circumstances will the AESO, its members, officers, employees, contractors or agents, or any of their respective affiliates, be liable for any errors or omissions in, or any losses, damages or claims whatsoever, whether in contract, tort or otherwise, arising from use of or reliance upon, this document or any information contained herein.