Alberta Electric System Operator
System Co-ordination Plan
2013-11-02 to 2013-11-08
Approved Outages

Previous Version
Download CSV

From To Owner Type Element Scheduled Activity Date/Time Comments Interconnection
17-Jun-13 08:00 31-Dec-13 17:00 ENMAX Outage 9.62L (ENMAX 10 - ENMAX 9) 10 sub re-build to future 138kV 198 Days
Continuous
 
09-Jul-13 17:00 15-Nov-13 18:00 ALTALINK Outage 324s 1152 (324s Cassils) construct new 324s1052 breaker , VT7 & 1053L termination point 130 Days
Continuous
 
12-Aug-13 11:00 31-Dec-13 17:00 ATCO Outage 813s 501R (813s Little Smoky) 501R has failed. Needs replaced 142 Days
Continuous
 
22-Sep-13 08:00 30-Nov-13 16:00 ENMAX Outage 32.82L (ENMAX 54 - ENMAX 32) re-conductor 70 Days
Continuous
 
25-Sep-13 09:00 29-Nov-13 17:00 ATCO Outage 757s 707 (757s Battle River) breaker replacement 66 Days
Continuous
 
07-Oct-13 08:00 08-Nov-13 18:00 EPCOR Outage 809L (320p Keephills - 330p Genesee) preparation work for the HVDC Project. outage to provide proper limits of approach 33 Days
Continuous
 
15-Oct-13 08:00 07-Nov-13 16:30 ATCO TE 755S Cordel wiring for protection replacement 24 Days
Continuous
 
16-Oct-13 08:00 08-Nov-13 17:00 ALTALINK Outage 310p 1752 (310p Sundance) replace breaker & CTs 24 Days
Continuous
 
21-Oct-13 07:00 04-Nov-13 19:00 ALTALINK RB 853L (28s West Brooks - 504s Queenstown) install rider poles and stringing of 1053L - HATD CWJ 15 Days
Daily
 
21-Oct-13 07:00 04-Nov-13 19:00 ALTALINK RB 763L (28s West Brooks - 763L257A), 763L (158s Vauxhall - 763L259) install rider poles and stringing of 1053L - HATD CWJ 15 Days
Daily
 
21-Oct-13 08:00 22-Nov-13 16:00 ALTALINK Outage 33s 4 (33s Spray) replace T2 33 Days
Continuous
 
21-Oct-13 09:00 07-Nov-13 16:00 ATCO Outage 757s 912T (757s Battle River), 9L80 (757s Battle River - 755s Cordel) maintenance on breaker and transformer 18 Days
Continuous
 
21-Oct-13 09:00 07-Nov-13 16:00 ATCO Outage 9L80 (757s Battle River - 755s Cordel) ATCO maintenance 18 Days
Continuous
 
23-Oct-13 08:00 06-Dec-13 17:00 ALTALINK Outage 734L (241s Lethbridge Uplands - 370s North Lethbridge) outage required for approach to install new sewer/water lines 45 Days
Continuous
 
23-Oct-13 09:00 15-Nov-13 16:00 ALTALINK Outage 76L (115s Mt. Allan - 33s Spray) STR replacements 24 Days
Continuous
 
26-Oct-13 08:00 05-Nov-13 19:00 ALTALINK RB 874L (522s Cooking Lake - 45s Bretona) string 1206L & 1212L - Heartland 11 Days
Continuous
 
27-Oct-13 08:00 02-Nov-13 19:00 ALTALINK, EPCOR RB 731L (38s East Edmonton - 420s Broadmoor), 731L (420s Broadmoor - 7746DL8), 746AL (524s Fiberglass - 746L tap), 746BL (337s Canada Liquidair - 746DL17), 746BL (337s Canada Liquidair - 746DL8) insulator washing 7 Days
Daily
 
28-Oct-13 07:00 08-Nov-13 19:00 ALTALINK RB 943L (13s Deerland - 108s Amelia) restring OHSW as OPGW on 942L - Heartland 12 Days
Continuous
 
28-Oct-13 08:00 08-Nov-13 17:00 ALTALINK Outage 942L (71s Lamoureux - 13s Deerland) re-string OHSW as OPGW & terminate 942L @ 12s - Heartland 12 Days
Continuous
 
28-Oct-13 08:00 22-Nov-13 16:00 EPCOR IO 72RV2 Rossdale to 511S Victoria Replace RV728 Breaker 26 Days
Continuous
 
28-Oct-13 10:00 03-Nov-13 17:00 ALTALINK Outage 80L (152s Didsbury - 80L194A) replacing structures 7 Days
Continuous
 
28-Oct-13 12:00 04-Nov-13 15:00 ATCO Outage 718s 702T (718s Parsons Creek) replace the foundation 8 Days
Continuous
 
29-Oct-13 07:00 17-Nov-13 18:00 ALTALINK Outage 851L (525s Carseland - 253s Blackie) rebuild line from structure 97 to structure 115 20 Days
Continuous
 
29-Oct-13 07:00 12-Nov-13 01:00 ALTALINK RB 1005L (120s Picture Butte - 356s Milo) install footings for 554s addition 14 Days
Daily
 
29-Oct-13 07:00 15-Nov-13 19:00 ALTALINK RB 600L (523s Bullshead - 404s Peace Butte) install rider poles, string lines, remove rider poles - SATR BW 18 Days
Daily
 
29-Oct-13 08:00 12-Nov-13 18:00 ALTALINK Outage 1036L (370s North Lethbridge - 356s Milo) install footings to allow construction of 554s tap point 15 Days
Continuous
 
29-Oct-13 08:00 08-Nov-13 16:00 ALTALINK IO 39.82L ENMAX Outage - Info ENMAX Switch and bushing work @ C39s 11 Days
Continuous
 
30-Oct-13 07:00 13-Nov-13 19:00 ALTALINK RB 901AL (64s East Crossfield - 901L tap), 901L (63s Red Deer - 901AL tap), 901L (74s Janet - 901AL tap) line flattening on 925L in vicinity, required for safety - WATL 15 Days
Daily
 
30-Oct-13 07:00 13-Nov-13 19:00 ALTALINK RB 929L (63s Red Deer - 74s Janet) liine flattening on 925L in vicinity, required for safety - WATL 15 Days
Daily
 
30-Oct-13 07:30 13-Nov-13 17:00 ALTALINK Outage 925L (63s Red Deer - 74s Janet) WATL - reconfigure line at crossing point 15 Days
Continuous
AB-BC
31-Oct-13 08:00 06-Nov-13 15:00 ALTALINK Outage 37s T5 (37s North Calder) replace T5 protections 7 Days
Continuous
 
31-Oct-13 08:00 08-Nov-13 19:00 ENMAX Outage 39.2TR (ENMAX 39), 39.4TR (ENMAX 39), 22.81L (ENMAX 22 - ENMAX 39), 39.82L (ENMAX 162 Beddington - ENMAX 39) replace switches & bushings & doble 39.2TR 9 Days
Continuous
 
31-Oct-13 14:30 04-Nov-13 23:30 ATCO TE 9L69 (934s Black Fly - 957s McClelland) protection relay testing 5 Days
Continuous
 
01-Nov-13 07:00 02-Nov-13 19:00 ALTALINK RB 808L (13s Deerland - 171s Redwater) replace OHSW with OPGW 2 Days
Daily
 
01-Nov-13 09:00 04-Nov-13 16:00 ATCO IO 709S Vegreville AltaLink work 4 Days
Continuous
 
01-Nov-13 09:00 04-Nov-13 16:00 ATCO IO 7L77 (395s North Holden - 709s Vegreville) AltaLink work 4 Days
Continuous
 
01-Nov-13 12:00 04-Nov-13 16:00 ALTALINK, ATCO Outage 395s T1 (395s North Holden), 174L (197s Bardo - 395s North Holden), 7L77 (395s North Holden - 709s Vegreville), 701L (395s North Holden - 223s Strome), 395s North Holden 138 kV Bus replace 395s1, replace 138kV PTs, replace 138kV insulators 4 Days
Continuous
 
02-Nov-13 08:00 22-Nov-13 16:00 ENMAX Outage Enmax 8 B138-3A0 (ENMAX 8) breaker maintenance 21 Days
Continuous
 
02-Nov-13 08:00 02-Nov-13 11:00 ALTALINK Outage 603L (243s Soderglen Wind Farm - 59s Peigan) urgent repairs: jumper replacement at STR 97 3 Hours
Daily
 
02-Nov-13 09:00 02-Nov-13 19:00 ATCO Outage 7L97 (820s Hangingstone - 933s Tower Road) repair 7L97D2 & bird proof 2014s Halfway 10 Hours
Continuous
 
02-Nov-13 09:00 02-Nov-13 19:00 ATCO Outage 2014s 701T (2014s Halfway), 2014s 702T (2014s Halfway) bird proofing 10 Hours
Continuous
 
03-Nov-13 08:00 03-Nov-13 18:00 ALTALINK Outage 1201L (102s Langdon - BCH) trouble corrective: tower steel repairs at STR;436, 445, and defective insulators at STR 213 10 Hours
Daily
AB-BC
03-Nov-13 08:00 14-Nov-13 19:00 ALTALINK RB 780L (38s East Edmonton - 149s Nisku) string 1206L & 1212L - Heartland 12 Days
Daily
 
03-Nov-13 08:00 14-Nov-13 19:00 ALTALINK RB 946L (89s Ellerslie - 38s East Edmonton) string 1206L & 1212L - Heartland 12 Days
Daily
 
03-Nov-13 08:00 09-Nov-13 18:00 EPCOR Outage 805s C1 (805s Jasper), 805s T1 (805s Jasper), 72JM18 (805s Jasper - Meadowlark), 72JW19 (805s Jasper - Woodcroft) protection upgrade 7 Days
Continuous
 
04-Nov-13 07:00 09-Nov-13 19:00 ALTALINK RB 795L (121s Brooks - 421s Hays) install aerial markers - SATR CB 6 Days
Daily
 
04-Nov-13 07:00 09-Nov-13 19:00 ALTALINK RB 892L (895s Suffield - 41s Medicine Hat) install aerial markers - SATR CB 6 Days
Daily
 
04-Nov-13 07:00 09-Nov-13 19:00 ALTALINK RB 100L (895s Suffield - 498s Tilley) install aerial markers - SATR CB 6 Days
Daily
 
04-Nov-13 07:00 04-Nov-13 17:00 ALTALINK Outage 17s Benalto 240 kV North Bus 1, 17S T3 (17s Benalto) insulators replacement 10 Hours
Continuous
 
04-Nov-13 07:30 08-Nov-13 18:00 EPCOR Outage 557s T1 (557s Castle Downs) tapchanger maintenance/bushing monitors 5 Days
Continuous
 
04-Nov-13 08:00 10-Nov-13 19:00 ALTALINK Outage 132s Ware Junction 240kV South Bus replace switch 132s11 & add switch 132s34. String 1053L into 132s 7 Days
Continuous
 
04-Nov-13 08:00 29-Nov-13 18:00 ALTALINK RB 935L (324s Cassils - 356s Milo) re conductor 923L, which is on the same double circuit towers as 935L. 26 Days
Daily
 
04-Nov-13 08:00 04-Nov-13 17:00 ATCO TE 757S Battle River 144kV bus breaker fail output to 710 will be tested to confirm proper tripping operation for breakers 9 Hours
Continuous
 
04-Nov-13 08:00 04-Nov-13 16:00 ALTALINK IO 1080L (ENMAX 65 - 74s Janet) (240 kV) A protection change comm card (B Prot intact) 8 Hours
Daily
 
04-Nov-13 08:00 08-Nov-13 16:00 ENMAX RB 1.80L (ENMAX 28 - ENMAX 1) tree trimming 5 Days
Daily
 
04-Nov-13 08:00 08-Nov-13 16:00 ENMAX RB 20.82L (ENMAX 21 - ENMAX 20) tree trimming 5 Days
Daily
 
04-Nov-13 08:00 07-Nov-13 17:00 ALTALINK Outage 80L (55s Olds - 152s Didsbury) replacing structures 4 Days
Continuous
 
04-Nov-13 08:00 08-Nov-13 16:00 EPCOR Outage Garneau T3 (Garneau) LTC monitor 5 Days
Continuous
 
04-Nov-13 08:30 08-Nov-13 16:00 ATCO Outage 7L45 (798s Bridge Creek - 813s Little Smoky) inspection and install conductor damper between 7L45D2and 813S Little Smokey 5 Days
Continuous
 
04-Nov-13 08:30 07-Nov-13 18:00 ALTALINK Outage 324s 1752 (324s Cassils), 324s 1852 (324s Cassils), 324s 2052 (324s Cassils), 324s 2152 (324s Cassils) end – end testing of 1034L & 1035L 4 Days
Continuous
 
04-Nov-13 09:00 04-Nov-13 10:00 ALTALINK TE MPLS 102s supervisory 60 Mins
Daily
 
04-Nov-13 09:30 05-Nov-13 14:00 ALTALINK Outage 672L (235s Entwistle - 131s Moon Lake) disonnecting Mobile (474s) 28.5 Hours
Continuous
 
04-Nov-13 10:00 29-Nov-13 18:00 ALTALINK Outage 923L (324s Cassils - 356s Milo) re-conductor STR’s 87 - 104. 26 Days
Continuous
 
04-Nov-13 10:00 04-Nov-13 11:00 ALTALINK TE MPLS 194s supervisory 60 Mins
Daily
 
04-Nov-13 10:00 15-Nov-13 16:00 ALTALINK Outage 83s C1 (83s Taber), 83s C2 (83s Taber), 83s 61 (83s Taber), 83s 67 (83s Taber) replace 83s61 & protections 12 Days
Continuous
 
04-Nov-13 10:00 04-Nov-13 13:30 ALTALINK TE MUX Radio 9195R circuit move to new antenna 3.5 Hours
Daily
 
04-Nov-13 10:00 04-Nov-13 17:00 ALTALINK TE 103S Goose Lake relay testing 7 Hours
Daily
 
04-Nov-13 10:00 05-Nov-13 17:00 TRANSALTA TE 59S Peigan relay testing 31 Hours
Continuous
 
04-Nov-13 12:00 05-Nov-13 17:00 ALTALINK TE 37s North Calder RTU/SCADA RTU config update to add alarms and controls 29 Hours
Daily
 
04-Nov-13 13:00 04-Nov-13 14:00 ALTALINK TE MPLS 217s supervisory 60 Mins
Daily
 
04-Nov-13 14:00 04-Nov-13 14:30 ALTALINK TE MUX Radio 9195R circuit move to new antenna 30 Mins
Daily
 
04-Nov-13 14:00 04-Nov-13 15:00 ALTALINK TE MPLS 67s supervisory 60 Mins
Daily
 
04-Nov-13 16:01 12-Nov-13 12:00 ALTALINK Outage 701L (395s North Holden - 223s Strome) replace 395s12, install bird coverup, replace LAs, replace 25kV bushings on T1, replace 395s8 PTs 8 Days
Continuous
 
04-Nov-13 17:00 04-Nov-13 22:00 ATCO TE 7L74 (7L35D1 - 822s Wolf Lake) 822s 25kV breaker relay 5 Hours
Continuous
 
04-Nov-13 17:00 07-Nov-13 17:00 ALTALINK Outage 922L (310p Sundance - 17s Benalto) insulators replacement 3 Days
Continuous
 
04-Nov-13 19:00 04-Nov-13 23:00 ATCO TE 7L583 (970s Bourque - 715s Leming Lake), 7L574 (970s Bourque - 7L574 tap) 970s 144kV breaker relays, add settings to 21B 4 Hours
Continuous
 
05-Nov-13 08:00 06-Nov-13 17:00 ALTALINK Outage 38s T3 (38s East Edmonton), 761L (71s Lamoureux - 39s East Edmonton), 865L (216s Knightsbridge - 38s East Edmonton) replace 38s34 2 Days
Continuous
 
05-Nov-13 08:00 05-Nov-13 17:30 ALTALINK Outage 285s T2 (285s East Camrose) winding resistance test, gas detection test, hot spots 9.5 Hours
Daily
 
05-Nov-13 08:00 05-Nov-13 15:00 ATCO Outage 6L56 (763s Hanna - 802s Michichi Creek) replace structure / maintenance 7 Hours
Continuous
 
05-Nov-13 08:00 05-Nov-13 16:00 ENMAX IO ENMAX 11 bus differential relay maintenance 8 Hours
Daily
 
05-Nov-13 08:00 05-Nov-13 16:00 ENMAX Outage 20.82L (ENMAX 21 - ENMAX 20) crane work install 8 kV gear 8 Hours
Daily
 
05-Nov-13 08:00 08-Nov-13 18:00 ALTALINK Outage 832L (42s Sarcee - ENMAX 12) erect new steel monopoles 4 Days
Continuous
 
05-Nov-13 08:00 05-Nov-13 17:00 ALTALINK TE 158S Vauxhall relay test 9 Hours
Daily
 
05-Nov-13 08:00 06-Nov-13 16:00 ALTALINK TE 165S T.M.P.L.Gainford advice to customer 2 Days
Continuous
 
05-Nov-13 08:00 08-Nov-13 18:00 ALTALINK RB 917L (74s Janet - 5s East Calgary) in conjunction with 832L GOI. 4 Days
Daily
 
05-Nov-13 08:00 05-Nov-13 16:00 EPCOR Outage NamaoT1 (Namao) internal inspection 8 Hours
Daily
 
05-Nov-13 08:00 07-Nov-13 18:00 ALTALINK Outage 324S Cassils relay 3 Days
Continuous
 
05-Nov-13 09:00 05-Nov-13 10:00 ALTALINK TE MPLS 9285s cutover of supervisory communications to MPLS telecom system. 60 Mins
Daily
 
05-Nov-13 09:00 05-Nov-13 10:00 MONTANA TE 120S Picture Butte circuit move to MPLS 60 Mins
Daily
 
05-Nov-13 09:00 05-Nov-13 09:30 ALTALINK TE MUX Radio 9195R circuit move to new antenna 30 Mins
Daily
 
05-Nov-13 10:00 05-Nov-13 11:00 ALTALINK TE 299S Kingman cutover of supervisory communications to MPLS telecom system 60 Mins
Daily
 
05-Nov-13 13:00 05-Nov-13 14:00 ALTALINK TE 285S East Camrose cutover of supervisory communications to MPLS telecom system 60 Mins
Daily
 
05-Nov-13 14:00 05-Nov-13 15:00 ALTALINK TE 356S Milo circuit move to MPLS 60 Mins
Daily
 
06-Nov-13 05:00 06-Nov-13 06:00 ALTALINK Outage 747L (37s North Calder - 711L tap), 37s 747W (37s North Calder), 37s41 (37s North Calder) perform test trip for new T5 protection 60 Mins
Daily
 
06-Nov-13 06:00 06-Nov-13 06:30 DAISHOWA Outage 147s Daishowa Plant RTU/SCADA DMI network upgrade 30 Mins
Continuous
 
06-Nov-13 06:01 06-Nov-13 07:00 ALTALINK Outage 898L (37s North Calder - 92s Viscount), 37s 898 (37s North Calder), 37s41 (37s North Calder) perform breaker test trip for new T5 protection 59 Mins
Daily
 
06-Nov-13 07:01 06-Nov-13 08:00 ALTALINK Outage 726L (37s North Calder - 71s Lamoureux), 37s 726E (37s North Calder), 37s 5 (37s North Calder) perform test trip for new T5 protection 59 Mins
Daily
 
06-Nov-13 08:00 06-Nov-13 16:00 ENMAX TE ENMAX 33 RTU/SCADA maintenance 8 Hours
Daily
 
06-Nov-13 08:00 27-Nov-13 16:00 ENMAX TE ENMAX 5 commissioning of new protection (Z32 & Z33) 22 Days
Continuous
 
06-Nov-13 08:00 06-Nov-13 16:00 ENMAX RB 2.83L (ENMAX 5 - 2.83L tap), 2.83L (ENMAX 2 - 2.83L tap), 2.83L (ENMAX 13 - 2.83L tap) tree trimming 8 Hours
Daily
 
06-Nov-13 08:00 08-Nov-13 16:00 ENMAX RB 30.81L (42s Sarcee - ENMAX 30) tree trimming 3 Days
Daily
 
06-Nov-13 08:00 07-Nov-13 19:00 ALTALINK TE 332s Ellis RTU/SCADA new RTU config 2 Days
Continuous
 
06-Nov-13 08:00 06-Nov-13 15:00 ALTALINK Outage 500S Flatbush new SCADA system 7 Hours
Daily
 
06-Nov-13 08:01 06-Nov-13 09:00 ALTALINK Outage 37s T6 (37s North Calder), 37s 4 (37s North Calder), 37s 3 (37s North Calder) perform test trip for new T5 protection 59 Mins
Daily
 
06-Nov-13 09:00 06-Nov-13 10:00 ALTALINK Outage 822L (38s East Edmonton - 822L tap), 38s 822X (38s East Edmonton), 38s173 (38s East Edmonton) trip breaker to test 38sT2 protection upgrade 60 Mins
Daily
 
06-Nov-13 09:00 06-Nov-13 09:30 ALTALINK TE 87s Gaetz RTU/SCADA circuit move to new antenna 30 Mins
Daily
 
06-Nov-13 09:00 06-Nov-13 17:00 ALTALINK TE 275S Jenner 240 kV bus 2 protection fail investigation 8 Hours
Continuous
 
06-Nov-13 10:00 06-Nov-13 11:00 ALTALINK TE MPLS 9035R - supervisory, circuit move to MPLS 60 Mins
Daily
 
06-Nov-13 10:00 06-Nov-13 11:00 ALTALINK TE MUX Radio 9910R cutover of supervisory communications to MPLS telecom system 60 Mins
Daily
 
06-Nov-13 10:01 06-Nov-13 11:00 ALTALINK Outage 38s 738W (38s East Edmonton), 38s 220 (38s East Edmonton) trip breaker to test 38sT2 protection upgrade 59 Mins
Daily
 
06-Nov-13 11:00 06-Nov-13 14:00 ATCO Outage 827s SVC (827s Cranberry Lake) replace a blown thyristor 3 Hours
Continuous
 
06-Nov-13 12:00 06-Nov-13 13:00 ALTALINK TE MPLS 51s Wainwright - cutover of supervisory communications to MPLS Telecom System 60 Mins
Daily
 
06-Nov-13 13:00 06-Nov-13 14:00 ALTALINK TE MPLS 137s Sedgewick - cutover of supervisory communications to MPLS telecom system 60 Mins
Daily
 
06-Nov-13 23:00 07-Nov-13 04:00 ALTALINK Outage 62s11 (62s Brazeau) maintenance 5 Hours
Continuous
 
07-Nov-13 04:00 07-Nov-13 07:00 ALTALINK Outage 62s12 (62s Brazeau) maintenance 3 Hours
Daily
 
07-Nov-13 08:00 07-Nov-13 10:00 ALTALINK Outage 37s T3 (37s North Calder), 37s12 (37s North Calder) perform breaker test trip for new T5 protection 2 Hours
Daily
 
07-Nov-13 09:00 08-Nov-13 15:00 ALTALINK Outage 575s T2 (575s Sundre) bird proof east bus 25 kV feeders 30 Hours
Continuous
 
07-Nov-13 10:00 07-Nov-13 11:00 ALTALINK TE 118S Canmore circuit move to MPLS 60 Mins
Daily
 
07-Nov-13 10:00 07-Nov-13 11:00 ALTALINK TE 899s Edgerton RTU/SCADA cutover of supervisory communications to MPLS telecom system 60 Mins
Daily
 
07-Nov-13 11:00 07-Nov-13 12:00 ALTALINK TE 213s Hughenden RTU/SCADA cutover of supervisory communications to MPLS telecom system 60 Mins
Daily
 
07-Nov-13 12:30 07-Nov-13 17:00 ATCO Outage 766s Nevis RTU/SCADA terminate wires for new security card readers 4.5 Hours
Continuous
 
07-Nov-13 13:00 07-Nov-13 14:00 ALTALINK TE MUX Radio 9029R circuit move to MPLS 60 Mins
Daily
 
08-Nov-13 08:00 10-Dec-13 20:59 SUNCOR Outage Suncor (Millennium) Islanding RAS (IRAS) RAS upgrade 33 Days
Continuous
 
08-Nov-13 08:00 08-Nov-13 16:00 ENMAX RB 16.63L (ENMAX 16 - ENMAX 36) tree trimming 8 Hours
Continuous
 
08-Nov-13 15:00 08-Nov-13 17:00 ALTALINK Outage 575s T1 (575s Sundre) re-issue trip settings and trip test feeders 2 Hours
Daily
 

Prepared On:   2013-11-01   5:22:39 PM

This document and the information contained herein are based upon information and data which by their nature contain a degree of uncertainty and are subject to change. In addition, this document may contain information and data from public sources and/or third parties, which have been assumed to be accurate and complete and have not been verified. Accordingly, the Independent System Operator, operating as the Alberta Electric System Operator (the "AESO") makes no warranty, representation or guarantee, express or implied, with respect to this document or the information contained herein, including, but not limited to, any warranty, representation or guarantee of accuracy, completeness, timeliness, reliability, availability, absence of computer virus, non- infringement, merchantability or suitability for any purpose. Under no circumstances will the AESO, its members, officers, employees, contractors or agents, or any of their respective affiliates, be liable for any errors or omissions in, or any losses, damages or claims whatsoever, whether in contract, tort or otherwise, arising from use of or reliance upon, this document or any information contained herein.

© 2009 Alberta Electric System Operator. All rights reserved