| Alberta Electric System Operator | |
| Long Range Significant Transmission Outages for the period of 24 months starting 2026-01-24 | |
|
The table below contains the significant transmission outages submitted as tentative to the AESO. These Outages have not yet necessarily been approved, but are listed for awareness and coordination purposes. An Outage has been considered significant for this table if it meets any one (1) or more of the following criteria: |
|
|
|
| Note: Where a transmission outage requires generation curtailments, the adjustments to generation will typically happen in the hours before the scheduled transmission outage and in the hour after the element is returned to service. | |
| Previous Version | |
| Download CSV | |
| Owner | From | To | Duration | Element | Scheduled Activity | Affected Intertie |
|---|---|---|---|---|---|---|
| EPCOR | 25-Jul-25 17:01 | 17-Apr-26 17:00 | 266 Days
Continuous |
T2 (EP Riverview) | bushing test failure (found during OE110184) | |
| ALTALINK | 01-Nov-25 12:00 | 01-Feb-26 18:00 | 92.29 Days
Continuous |
AML 511s ACF12 (AML 511s Crossings) | forced outage | |
| ATCO | 25-Nov-25 17:46 | 30-Jan-26 18:00 | 66.01 Days
Continuous |
876s 901T (876s Brintnell) | forced outage oil leaking | |
| SUNCOR | 04-Jan-26 08:00 | 31-Mar-26 16:00 | 86.29 Days
Continuous |
29EDD-34 260kV Bus 29PP-45 (29EDD-34), 29EDD-34 29-952-113 (29EDD-34) | urgent repairs on 29PT-224 at 29EDD34 on 29PP-45 bus | |
| ALTALINK, EPCOR | 26-Jan-26 07:00 | 30-Jan-26 17:00 | 4.42 Days
Continuous |
920L (37s North Calder - 557s Castle Downs), 557s CD2405 (557s Castle Downs), 557s CD2406 (557s Castle Downs) | 920LW/Castledowns: Relay Maintenance and Op Checks | |
| ATCO | 26-Jan-26 09:00 | 04-Feb-26 15:00 | 9.25 Days
Continuous |
9L57 (939s Livock - 960s Birchwood Creek) | 9L57 Line to Ground Clearance Mitigation | |
| ATCO | 28-Jan-26 09:00 | 28-Jan-26 11:00 | 2 Hours
Continuous |
9L59 (801s Anderson - 9LA59 tap) | accommodate outage 1-00508220 | |
| ALTALINK | 02-Feb-26 07:00 | 02-Feb-26 18:30 | 11.5 Hours
Daily |
922L (17s Benalto - 310p Sundance) | Clipping in 922L OHSW between strs 922L1 and 922L7, after raising 922/926L4. See also SAP: 401749 926L RB required due to proximity | |
| ALTALINK, EPCOR | 02-Feb-26 07:00 | 06-Feb-26 17:00 | 4.42 Days
Continuous |
920L (71s Lamoureux - 557s Castle Downs), 557s CD2405 (557s Castle Downs), 557s CD2404 (557s Castle Downs) | 920LE/Castledowns: Relay Maintenance and Op Checks | |
| ALTALINK | 02-Feb-26 19:00 | 03-Feb-26 18:30 | 23.5 Hours
Continuous |
926L (17s Benalto - 310p Sundance) | Clipping in 926L OHSW between strs 926L1 and 926L7, after raising str 922/926L4 See also SAP: 401745 922L RB required due to proximity | |
| ATCO | 05-Feb-26 07:00 | 08-Feb-26 16:00 | 3.38 Days
Continuous |
9L913 (69s North Barrhead - 732s Mitsue) | Changing white tag poles from Test & Treat ( Str 16,69 and 503 ) | |
| ALTALINK | 05-Feb-26 07:00 | 08-Feb-26 16:30 | 3.4 Days
Continuous |
913L (69s North Barrhead - 732s Mitsue) | Changing white tag poles from Test & Treat ( Str 16,69 and 503 ) | |
| Syncrude | 09-Feb-26 08:00 | 20-Feb-26 16:00 | 11.33 Days
Continuous |
Mildred T6 (Syncrude Mildred Lake), 6335 (Syncrude Mildred Lake), 634 (Syncrude Mildred Lake), 635 (Syncrude Mildred Lake) | SCL - Repair Tap Changer in T6 Transformer. | |
| ATCO | 09-Feb-26 09:00 | 18-Feb-26 13:00 | 9.17 Days
Continuous |
9L57 (939s Livock - 960s Birchwood Creek) | 9L57 Line to Ground Clearance Mitigation | |
| ENMAX, ALTALINK | 17-Feb-26 08:00 | 18-Feb-26 16:00 | 1.33 Days
Continuous |
832L (SS-10 - SS-12), 12.1TR (SS-12) | HV SW Maintenance SW84, SW85, SW86, MD-12.1TR. Reversing Switch Check - 12.1-TC | |
| BCH | 17-Feb-26 08:00 | 24-Feb-26 16:00 | 7.33 Days
Continuous |
T3 (BCH Natal) | ETM install | AB-BC |
| ATCO | 17-Feb-26 09:00 | 03-Mar-26 17:00 | 14.33 Days
Continuous |
972s 240kV Bus 900BS1 (972s Tinchebray) | Install Breaker 904 and 904CT On release leave Bkr 904, 904A/904B closed as feed through (disable bkr trips), Bkr 901 still protecting 9L93 |
|
| ALTALINK | 18-Feb-26 07:00 | 18-Feb-26 18:00 | 11 Hours
Daily |
254s T2 (254s Coaldale) | Add T2 tap position sensor and tap position visibility. The tap changer will be run through the various positions to ensure visibility in all positions. | |
| ALTALINK | 19-Feb-26 07:00 | 19-Feb-26 18:00 | 11 Hours
Daily |
135s T1 (135s Conrad), 135s 138kV Bus (135s Conrad), 607L (135s Conrad - 607AL tap) | Add T1 tap position sensor and tap position visibility. The tap changer will be run through the various positions to ensure visibility in all positions. | |
| ENMAX, ALTALINK | 19-Feb-26 08:00 | 20-Feb-26 16:00 | 1.33 Days
Continuous |
833L (SS-2 - SS-12), 12.2TR (SS-12) | HV SW Maintenance SW81, SW82, SW83, MD-12.2TR. Reversing Switch Check - 12.2-TC | |
| ATCO | 19-Feb-26 08:00 | 22-Feb-26 16:00 | 3.33 Days
Continuous |
9L40 (732s Mitsue - 809s Louise Creek) | Changing rotten poles from our inspection. | |
| ALTALINK | 19-Feb-26 09:00 | 19-Feb-26 18:00 | 9 Hours
Daily |
862L (166s Dow Chemical Fort Saskatchewan - 258s Dow Hydrocarbons) | Arctic arrow requires a GOI on 862L for a planned high load move between structures 26-27. See also 402077 706L GOI | |
| EPCOR | 23-Feb-26 07:00 | 20-Mar-26 17:00 | 25.38 Days
Continuous |
805s T3 (805s Jasper) | Jasper TX3: Bushing Change (PCB) | |
| ATCO | 23-Feb-26 08:30 | 24-Feb-26 14:00 | 29.5 Hours
Continuous |
7L91 (715s Leming Lake - 826s Marguerite Lake) | Install aerial nest platform pole and transfer osprey nest from 7L91-158 | |
| ATCO | 23-Feb-26 09:00 | 04-Mar-26 13:00 | 9.17 Days
Continuous |
9L57 (939s Livock - 960s Birchwood Creek) | 9L57 Line to Ground Clearance Mitigation | |
| EPCOR | 24-Feb-26 07:00 | 24-Feb-26 17:00 | 10 Hours
Continuous |
330p 1209 (330p Genesee) | Genesee: 1209 Breaker Status Indicator Investigation | |
| ALTALINK | 26-Feb-26 09:00 | 26-Feb-26 18:00 | 9 Hours
Daily |
862L (166s Dow Chemical Fort Saskatchewan - 258s Dow Hydrocarbons) | Arctic arrow requires a GOI on 862L for a planned high load move between structures 26-27. Goes with 402078 706L GOI | |
| SUNCOR | 01-Mar-26 08:00 | 05-Mar-26 20:00 | 4.5 Days
Continuous |
29EDD-1 Millennium, 29EDD-1 T2 (29EDD-1 Millennium) | 29EDD-1S - Correct leaning structure for 29CVT-13 (T2 Outage) - 300551776 | |
| ALTALINK, EPCOR | 02-Mar-26 07:00 | 03-Mar-26 17:00 | 1.42 Days
Continuous |
1044L (EP 805s Jasper - 816s Petrolia), EP 805s J2403 (EP 805s Jasper), EP 805s J2404 (EP 805s Jasper), 816s P2405 (816s Petrolia), 816s P2406 (816s Petrolia) | Petrolia: 1044L Relay Maintenance and PDS14 Repair | |
| EPCOR | 02-Mar-26 07:00 | 06-Mar-26 17:00 | 4.42 Days
Continuous |
557s T2 (557s Castle Downs) | Castle Downs: TX2 Surge Arrestor LCR | |
| EPCOR | 02-Mar-26 07:00 | 06-Mar-26 17:00 | 4.42 Days
Continuous |
EP 803s T1 (EP 803s Lambton), EP 803s L2401 (EP 803s Lambton), EP 803s L2402 (EP 803s Lambton) | Lambton: TX1 Relay Maintenance | |
| SUNCOR | 02-Mar-26 08:00 | 08-Mar-26 20:00 | 6.46 Days
Continuous |
29PL9-16 (29EDD-1 Millennium - 29EDD-94 Voyageur) | 29EDD1;29PT418/29PL9-16 SYSTEM;PM 5y,10y |
|
| ALTALINK | 02-Mar-26 12:30 | 05-Mar-26 17:30 | 3.21 Days
Continuous |
749L (899s Edgerton - 7LB749 tap) | Replace 749LN A21/L8. Update settings on B21/L8. | |
| ALTALINK | 03-Mar-26 07:00 | 09-Mar-26 17:00 | 6.38 Days
Continuous |
944L (132s Ware Junction - 275s Jenner) | Replace line relays at 132s Ware Junction, replace relay comm cards and update settings on protections at 275s Jenner, implement third 944AL terminal. New 1080s Raptor line protection relays. End to end testing new 1080s Raptor and 944ALtap addition. | |
| BCH | 03-Mar-26 08:00 | 05-Mar-26 16:00 | 2.33 Days
Continuous |
T7 (BCH Natal) | ETM install | AB-BC |
| EPCOR | 04-Mar-26 07:00 | 06-Mar-26 17:00 | 2.42 Days
Continuous |
816s T1 (816s Petrolia), 816s P2402 (816s Petrolia), 816s P2401 (816s Petrolia) | Petrolia: TX1 Relay Maintenance | |
| ALTALINK | 04-Mar-26 23:00 | 05-Mar-26 03:00 | 4 Hours
Continuous |
62s T1 (62s Brazeau Plant) | maintenance | |
| ALTALINK | 05-Mar-26 03:00 | 05-Mar-26 07:00 | 4 Hours
Daily |
62s T2 (62s Brazeau Plant) | maintenance | |
| ALTALINK | 05-Mar-26 07:00 | 05-Mar-26 18:00 | 11 Hours
Daily |
1037L (138s Windy Flats - 266s SC1), 1037L (237s Foothills - 266s SC1) | South Crew will be doing component replacement on 1037L (STR 280-342)See also SAP: 401547 1038L RB Required due to proximity. | |
| ATCO | 05-Mar-26 08:00 | 08-Mar-26 16:00 | 3.29 Days
Continuous |
9L40 (732s Mitsue - 809s Louise Creek) | Changing rotten poles from our inspection. | |
| ALTALINK, EPCOR | 09-Mar-26 07:00 | 10-Mar-26 17:00 | 1.42 Days
Continuous |
908L (89s Ellerslie - 816s Petrolia), 816s P2401 (816s Petrolia), 816s P2406 (816s Petrolia) | Petrolia: 908L Relay Maintenance | |
| ALTALINK, EPCOR | 09-Mar-26 07:00 | 13-Mar-26 17:00 | 4.42 Days
Continuous |
1059L (EP 803s Lambton - 1059AL tap), EP 803s L2401 (EP 803s Lambton), EP 803s L2404 (EP 803s Lambton) | 1059L/Lambton: Relay Maintenance | |
| SUNCOR | 09-Mar-26 08:00 | 15-Mar-26 20:00 | 6.5 Days
Continuous |
29PL9-17 (29EDD-1 Millennium - 29EDD-94 Voyageur) | 29EDD1;29PT419/29PL9-17 SYSTEM;PM 5y,10y |
|
| ATCO | 09-Mar-26 13:00 | 18-Mar-26 09:00 | 8.83 Days
Continuous |
9L57 (939s Livock - 960s Birchwood Creek) | 9L57 Line to Ground Clearance Mitigation | |
| ALTALINK | 10-Mar-26 07:00 | 10-Mar-26 18:00 | 11 Hours
Daily |
1072L (103s Goose Lake - 205s Castle Rock Ridge) | South Crew will be doing component replacement on 1072L15 | |
| ALTALINK | 10-Mar-26 07:00 | 13-Mar-26 18:00 | 3.46 Days
Continuous |
1325L (510s Sunnybrook - AML 511s Crossings) | South Crew will be doing component replacement on 1325L (STR 501-542) | |
| ATCO | 10-Mar-26 09:00 | 14-Apr-26 17:00 | 35.33 Days
Continuous |
972s 240kV Bus 900BS2 (972s Tinchebray) | Install Breakers 905/906, 905CT/906CT, switches 905A/906B On release leave Bkrs 905/906, 905A/905B, and 906A/906B closed as feed through (disable bkr trips), Bkr 903 still protecting 9L93, leave new 9L62D1 open for future line connection |
|
| ENMAX, ALTALINK | 10-Mar-26 10:00 | 10-Mar-26 12:00 | 2 Hours
Continuous |
28.80L (42s Sarcee - SS-28) | 1 sub Transmission line cut over. | |
| ENMAX, ALTALINK | 10-Mar-26 10:00 | 10-Mar-26 12:00 | 2 Hours
Daily |
28.80L (42s Sarcee - SS-28) | 1 sub Transmission line cut over.. | |
| EPCOR | 11-Mar-26 07:00 | 11-Mar-26 17:00 | 10 Hours
Continuous |
557s CD2401 (557s Castle Downs) | Castledowns: CD2401 NAIT Student Substation Tour | |
| EPCOR | 11-Mar-26 07:00 | 13-Mar-26 17:00 | 2.42 Days
Continuous |
816s T2 (816s Petrolia), 816s P2404 (816s Petrolia), 816s P2405 (816s Petrolia) | Petrolia: TX2 Relay Maintenance | |
| ALTALINK | 13-Mar-26 07:15 | 13-Mar-26 17:45 | 10.5 Hours
Daily |
199L (268s Whitecourt - 199AL tap) | Replace keeper keys at structure 375 | |
| EPCOR | 16-Mar-26 07:00 | 16-Mar-26 17:00 | 10 Hours
Continuous |
816s P2403 (816s Petrolia) | Petrolia: P2403 Relay Maintenance | |
| ALTALINK, EPCOR | 16-Mar-26 07:00 | 19-Mar-26 17:00 | 3.42 Days
Continuous |
1058L (657s Summerside - EP 803s Lambton), EP 803s L2403 (EP 803s Lambton), EP 803s L2404 (EP 803s Lambton), 657s SU2403 (657s Summerside), 657s SU2404 (657s Summerside) | 1058L: Lambton Surge Counter Install and Summerside SUDS10 Ice Shield Repair | |
| EPCOR | 16-Mar-26 07:00 | 20-Mar-26 17:00 | 4.42 Days
Continuous |
805s T3 (805s Jasper), EP 805s J2405 (EP 805s Jasper), EP 805s J2404 (EP 805s Jasper) | Jasper: TX3 Relay Maintenance | |
| EPCOR | 16-Mar-26 07:00 | 20-Mar-26 17:00 | 4.42 Days
Continuous |
T2 (Poundmaker) | Poundmaker: TX2 Bladder and Sample Pipe Repair | |
| ALTALINK | 16-Mar-26 07:00 | 25-Mar-26 18:00 | 9.46 Days
Continuous |
87s 240kV West Bus (87s Gaetz), 87s T1 (87s Gaetz) | Installing new 87s1752 & 87s1952. Closing Open Points 'F', 'G', 'H'. | |
| ALTALINK | 16-Mar-26 07:15 | 19-Mar-26 17:45 | 3.44 Days
Continuous |
788L (898s Heart Lake - 788AL tap), 788L107A (788AL tap), 602L1 (602L tap) | component replacement on 788L (STR 157 - 218) | |
| ATCO, SUNCOR | 16-Mar-26 08:00 | 22-Mar-26 20:00 | 6.5 Days
Continuous |
29PL9-1 (29EDD-1 Millennium - 848s Ruth Lake) | 29EDD1;29CVT-3 SYSTEM;PM 5y,10y |
|
| ATCO | 16-Mar-26 10:00 | 16-Mar-26 16:00 | 6 Hours
Continuous |
715s 701 (715s Leming Lake), 7L583 (715s Leming Lake - 970s Bourque) | PRC-005 Trip Coil Testing, 701CT Inspection/ Testing | |
| BCH | 17-Mar-26 08:00 | 20-Mar-26 16:00 | 3.33 Days
Continuous |
5L92 (BCH Cranbrook - BCH Selkirk) | replace end of life spacers. | AB-BC |
| ATCO | 17-Mar-26 10:00 | 17-Mar-26 16:00 | 6 Hours
Continuous |
715s 702 (715s Leming Lake), 7L91 (715s Leming Lake - 826s Marguerite Lake) | PRC-005 Trip Coil Testing, 702CT Inspection/ Testing | |
| ALTALINK | 18-Mar-26 07:00 | 19-Mar-26 18:00 | 1.46 Days
Continuous |
1002L (163s Amoco Empress - 275s Jenner) | South Crew will be doing component replacement on 1002L (STR 67-99) | |
| ATCO | 18-Mar-26 10:00 | 18-Mar-26 16:00 | 6 Hours
Continuous |
715s 703 (715s Leming Lake), 7L66 (715s Leming Lake - 717s Ethel Lake) | PRC-005 Trip Coil Testing, 703CT Inspection/ Testing | |
| EPCOR | 20-Mar-26 07:00 | 20-Mar-26 17:00 | 10 Hours
Continuous |
52s T2 (52s East Industrial), 908AL (52S East Industrial - 908L tap) | 908LW/East Industrial: EDS2 Repair/Adjustment | |
| EPCOR | 23-Mar-26 07:00 | 23-Mar-26 17:00 | 10 Hours
Continuous |
RW2401 (EP Riverview) | Riverview: RW2401 (SF6) Breaker Maintenance | |
| ALTALINK | 23-Mar-26 07:00 | 26-Mar-26 16:30 | 3.4 Days
Continuous |
AML 511s T30 (AML 511s Crossings), AML 511s SVC Plus (AML 511s Crossings) | Firmware upgrades on protections that are OOS, VCS Maintenance, Annual SVC+ maintenance | |
| EPCOR, ALTALINK | 23-Mar-26 07:00 | 27-Mar-26 17:00 | 4.42 Days
Continuous |
EP 805s J2406 (EP 805s Jasper), EP 805s J2407 (EP 805s Jasper), 1045L (EP 805s Jasper - 1045AL tap), 1098L (EP 805s Jasper - Poundmaker) | 1098L/1045L/Jasper: Relay Maintenance | |
| ATCO, SUNCOR | 23-Mar-26 08:00 | 29-Mar-26 20:00 | 6.5 Days
Continuous |
29PL9-2 (29EDD-1 Millennium - 848s Ruth Lake) | 29EDD1;29CVT-1 SYSTEM;PM 5y,10y | |
| EPCOR | 24-Mar-26 07:00 | 24-Mar-26 17:00 | 10 Hours
Continuous |
RW2402 (EP Riverview) | Riverview: RW2402 (SF6) Breaker Maintenance | |
| ALTALINK | 26-Mar-26 07:00 | 26-Mar-26 18:00 | 11 Hours
Daily |
237s T2 (237s Foothills), 237s 240kV Bus 2 (237s Foothills) | Install bus support piles for new 240kV Bay. | |
| ALTALINK | 27-Mar-26 07:00 | 27-Mar-26 18:00 | 11 Hours
Daily |
237s T1 (237s Foothills), 237s 240kV Bus 1 (237s Foothills) | Install bus support piles for new 240kV Bay. | |
| EPCOR | 30-Mar-26 07:00 | 02-Apr-26 17:00 | 3.42 Days
Continuous |
987s T3 (987s Clover Bar), 987s C2407 (987s Clover Bar) | Cloverbar: C2407 (SF6) Breaker Maintenance and TX3 Relay Maintenance | |
| EPCOR | 30-Mar-26 07:00 | 02-Apr-26 17:00 | 3.42 Days
Continuous |
805s T1 (805s Jasper), 805s C1 (805s Jasper), EP 805s J2401 (EP 805s Jasper), EP 805s J2403 (EP 805s Jasper), EP 805s J2408 (EP 805s Jasper), EP 805s J724 (EP 805s Jasper), EP 805s J722 (EP 805s Jasper) | Jasper: TX1, CAP BANK Relay Maintenance | |
| ALTALINK | 30-Mar-26 07:00 | 08-Apr-26 18:00 | 9.46 Days
Continuous |
87s 240kV East Bus (87s Gaetz), 87s T2 (87s Gaetz), 914L (86s Bigstone - 87s Gaetz) | Installing new 87s1352 & 87s1552. Closing Open points 'E', 'J', 'K' & 'L'. Creating permanent bus cut between 87s27 & 87s 240kV East Bus. | |
| ATCO, SUNCOR | 30-Mar-26 08:00 | 05-Apr-26 20:00 | 6.5 Days
Continuous |
6L32 (29EDD-1 Millennium - 737s ATC Horseshoe) | 29EDD1;29CVT-6 SYSTEM;5y,10y |
|
| SUNCOR | 01-Apr-26 08:00 | 10-Apr-26 20:00 | 9.5 Days
Continuous |
29EDD-34 29PT-341 (29EDD-34), 29EDD-34 29-952-142 (29EDD-34), 29EDD-34 29-952-143 (29EDD-34), 29EDD-34 29-652-10200T (29EDD-34), 29EDD-34 29-652-10301 (29EDD-34), 29EDD-34 29-652-10302 (29EDD-34), 29EDD-34 29-652-10303 (29EDD-34), 29EDD-34 29PS-0375 (29EDD-34), 29EDD-34 29PS-0380 (29EDD-34), 29EDD-34 29PS-0381 (29EDD-34), 29EDD-34 29PS-0383 (29EDD-34), 29EDD-34 29PS-609 (29EDD-34) | 10 year PM on 29EDD34;29PT-341 system and 5 year, 10 year PM on 29EDD34;29PP-103 system |
|
| SUNCOR | 01-Apr-26 08:00 | 11-Apr-26 20:00 | 10.5 Days
Continuous |
29EDD-34 29PT-340 (29EDD-34) | 29EDD34;29PT-340 SYSTEM;PM 5y,10y; 29EDD34;29PP-102 SYSTEM;PM 5y,10y |
|
| ENMAX, ALTALINK | 04-Apr-26 08:00 | 04-Apr-26 18:00 | 10 Hours
Continuous |
1003L (74s Janet - SS-25) | Surge Arrestor Power Factor Test - 25MD240-1003 | |
| ENMAX, ALTALINK | 04-Apr-26 08:00 | 04-Apr-26 18:00 | 10 Hours
Continuous |
1003L (74s Janet - SS-25) | Surge Arrestor Power Factor Test - 25MD240-1003 | |
| ENMAX, ALTALINK | 05-Apr-26 08:00 | 05-Apr-26 18:00 | 10 Hours
Continuous |
985L (74s Janet - SS-25) | Surge Arrestor Power Factor Test - 25MD240-985 | |
| ENMAX, ALTALINK | 05-Apr-26 08:00 | 05-Apr-26 18:00 | 10 Hours
Continuous |
985L (74s Janet - SS-25) | Surge Arrestor Power Factor Test - 25MD240-985 | |
| SUNCOR | 06-Apr-26 08:00 | 12-Apr-26 20:00 | 6.5 Days
Continuous |
29PL9-3 (29EDD-1 Millennium - 29EDD-3), 29EDD-3 29PT-6 (29EDD-3) | 29EDD1;29CVT-4 SYSTEM;PM 5y,10y; |
|
| ENMAX | 06-Apr-26 08:00 | 14-Apr-26 16:00 | 8.33 Days
Continuous |
65.2TR (SS-65) | Tap Changer Inspection - 65.2-TC | |
| EPCOR | 13-Apr-26 07:00 | 13-Apr-26 17:00 | 10 Hours
Continuous |
72JW19 (EP 805s Jasper - Woodcroft), 805s T1 (805s Jasper), EP 805s J722 (EP 805s Jasper), EP 805s J724 (EP 805s Jasper) | Jasper: JDS21 Repair | |
| ALTALINK, EPCOR | 13-Apr-26 07:00 | 17-Apr-26 17:00 | 4.42 Days
Continuous |
947L (89s Ellerslie - 987s Clover Bar), 987s C2402 (987s Clover Bar), 987s C2404 (987s Clover Bar) | Cloverbar: 947L Relay Maintenance | |
| ALTALINK | 13-Apr-26 07:00 | 20-Apr-26 18:00 | 7.46 Days
Continuous |
87s 240kV West Bus (87s Gaetz), 87s T1 (87s Gaetz), 914L (86s Bigstone - 87s Gaetz) | Closing Open point 'I' and creating second permanent bus cut between 87s26 & 87s 240kV West Bus. | |
| EPCOR | 13-Apr-26 07:00 | 08-May-26 17:00 | 25.42 Days
Continuous |
805s T4 (805s Jasper) | Jasper TX4: Bushing Change (PCB) and Fan Failure Repair and Conservator Tank Inspection | |
| SUNCOR | 13-Apr-26 08:00 | 19-Apr-26 20:00 | 6.5 Days
Continuous |
29EDD-1 T1 (29EDD-1 Millennium), 29EDD-1 260kV South Bus 1 (29EDD-1 Millennium), 29EDD-1 72kV South Bus (29EDD-1 Millennium) | 29EDD1;XFMR T1; X260B1; X72B1 SYSTEM;PM 5y | |
| ALTALINK, TRANSALTA | 13-Apr-26 10:00 | 17-Apr-26 16:00 | 4.25 Days
Continuous |
179s T1 (179s Gleichen) | 179s Oil reclaim, 25kV insulator replacements throughout 179s25,179s9,179s26 line sides & 25kV Bus / VR1 and bus side of 179s6, T1 maintenance,& VR1 maintenance. | |
| SUNCOR | 20-Apr-26 08:00 | 26-Apr-26 20:00 | 6.5 Days
Continuous |
29EDD-1 T2 (29EDD-1 Millennium), 29EDD-1 260kV North Bus 2 (29EDD-1 Millennium), 29EDD-1 72kV North Bus (29EDD-1 Millennium) | 29EDD1;XFMR T2; N260B2; N72B1 SYSTEM;PM 5y | |
| ATCO | 20-Apr-26 13:00 | 20-Apr-26 17:30 | 4.5 Hours
Continuous |
755s 901 (755s Cordel) | PRC-005 - TRIP & CLOSE COIL TESTING. | |
| ATCO | 21-Apr-26 09:00 | 26-Apr-26 17:00 | 5.33 Days
Continuous |
9LA93 (973s Lanes Lake - 9L93 tap) | Cutover and commission 9L93 protection ccts from Bkrs 901/903 to Bkrs 904/905 |
|
| ATCO | 21-Apr-26 09:30 | 21-Apr-26 12:00 | 2.5 Hours
Continuous |
755s 902 (755s Cordel) | PRC-005 - TRIP & CLOSE COIL TESTING. | |
| ATCO | 21-Apr-26 13:00 | 21-Apr-26 17:30 | 4.5 Hours
Continuous |
755s 904 (755s Cordel) | PRC-005 - TRIP & CLOSE COIL TESTING. | |
| ATCO | 22-Apr-26 09:30 | 24-Apr-26 17:30 | 2.33 Days
Continuous |
755s 903 (755s Cordel) | PRC-005 - TRIP & CLOSE COIL TESTING. | |
| ALTALINK | 22-Apr-26 23:00 | 23-Apr-26 03:00 | 4 Hours
Continuous |
62s T1 (62s Brazeau Plant) | maintenance | |
| ALTALINK | 23-Apr-26 03:00 | 23-Apr-26 07:00 | 4 Hours
Daily |
62s T2 (62s Brazeau Plant) | maintenance | |
| ALTALINK | 27-Apr-26 09:00 | 01-May-26 18:00 | 4.38 Days
Continuous |
953L (574s Nilrem - 755s Cordel) | Switch and breaker maintenance | |
| ALTALINK, EPCOR | 27-Apr-26 09:30 | 27-Apr-26 17:00 | 7.5 Hours
Continuous |
1057L (89s Ellerslie - 657s Summerside), 657s SU2401 (657s Summerside), 657s SU2402 (657s Summerside) | 1057L/Summerside: CVT/Arrestor Doble, SUDS1/SUDS3/SUDS9 Disconnect Maintenance | |
| ATCO | 27-Apr-26 09:30 | 01-May-26 17:30 | 4.33 Days
Continuous |
755s 905 (755s Cordel), 755s 906 (755s Cordel), 9L953 (574s Nilrem - 755s Cordel) | PRC-005 - TRIP COIL TESTING - BREAKER 905 @ 755S PRC-005 - TRIP & CLOSE COIL TESTING - BREAKER 906 @ 755S Adjust 905B Switch at 755s Cordel Adjust 906A Switch at 755s Cordel Repair 9L953D1 at 755s Cordel RTXP Test Switch Mitigation and Replacement |
|
| ALTALINK | 29-Apr-26 08:00 | 07-May-26 18:00 | 8.42 Days
Continuous |
275s T2 (275s Jenner) | 275sT2 Oil Reclaim | |
| EPCOR | 04-May-26 07:00 | 08-May-26 17:00 | 4.42 Days
Continuous |
805s T4 (805s Jasper), EP 805s J2406 (EP 805s Jasper), EP 805s J2405 (EP 805s Jasper) | Jasper: TX4 Relay Maintenance | |
| EPCOR | 04-May-26 07:00 | 10-May-26 17:00 | 6.42 Days
Continuous |
BR721 (Rossdale), 814s T1 (814s Bellamy), 814s B2401 (814s Bellamy), 814s B2407 (814s Bellamy) | Bellamy: TX1 Zone Doble and BR721 Breaker Maintenance/Doble, and BDS15 Disconnect Maintenance | |
| EPCOR | 04-May-26 07:00 | 10-May-26 17:00 | 6.42 Days
Continuous |
557s T2 (557s Castle Downs), 557s CD2403 (557s Castle Downs), 557s CD2404 (557s Castle Downs) | Castledowns: TX2 Doble, Tap Changer Maintenance, and CDAB2CDDS6/CDDS7 Disconnect Maintenance | |
| ATCO | 04-May-26 09:00 | 18-May-26 17:30 | 14.35 Days
Continuous |
13L50 (2029s Heathfield - 2075s Newell) | Kinbrook Addition to 2075s | |
| ATCO | 04-May-26 09:00 | 18-May-26 17:30 | 14.35 Days
Continuous |
2029s T11 (2029s Heathfield) | Kinbrook Addition to 2075s Newell. | |
| ATCO | 04-May-26 09:00 | 18-May-26 17:30 | 14.35 Days
Continuous |
2075s T11 (2075s Newell) | Kinbrook Addition to 2075s Newell. | |
| ATCO | 05-May-26 09:00 | 07-May-26 17:00 | 2.33 Days
Continuous |
9L59 (801s Anderson - 9LA59 tap), 9L59 (972s Tinchebray - 9LA59 tap) | Connect new 907B to 900BS1 |
|
| ATCO | 07-May-26 09:00 | 19-May-26 17:00 | 12.33 Days
Continuous |
9L16 (755s Cordel - 972s Tinchebray) | GOI is required on 907B to isolate 908/909 bay and new 9L16. | |
| ATCO | 08-May-26 09:00 | 09-May-26 17:00 | 1.33 Days
Continuous |
972s 240kV Bus 900BS2 (972s Tinchebray) | Connect new 909A to 900BS2 | |
| EPCOR | 11-May-26 07:00 | 13-May-26 17:00 | 2.42 Days
Continuous |
557s T1 (557s Castle Downs) | Castledowns: TX1 Tap Changer Maintenance and Conservator Pipe Leak Repair | |
| ATCO, ALTALINK | 11-May-26 07:00 | 14-May-26 18:00 | 3.46 Days
Continuous |
7LA114 (658s Chard - 7L114 tap), 7L114 (72s Leismer - 7LA114 tap), 7L114 (907s Waddell - 7LA114 tap), 907s Waddell | AltaLink outage on 72sT2 causing an outage to 7L114 at 907S | |
| ALTALINK, ATCO | 11-May-26 07:00 | 14-May-26 18:00 | 3.46 Days
Continuous |
72s T2 (72s Leismer), 72s 144kV Bus (72s Leismer), 7L114 (72s Leismer - 7LA114 tap) | Transformer maintenance, doble, install Coresense & Qualitrol | |
| ALTALINK, ATCO | 11-May-26 07:00 | 14-May-26 18:00 | 3.46 Days
Continuous |
72s 114 (72s Leismer), 7L114 (72s Leismer - 7LA114 tap) | maintenance | |
| EPCOR | 11-May-26 07:00 | 17-May-26 17:00 | 6.42 Days
Continuous |
814s T2 (814s Bellamy), BR722 (Rossdale), 814s B2402 (814s Bellamy), 814s B2406 (814s Bellamy) | Bellamy: TX2 Zone Doble and BR722 Breaker Maintenance/Doble, and BDS17 Disconnect Maintenance | |
| EPCOR | 11-May-26 07:00 | 22-May-26 17:00 | 11.42 Days
Continuous |
52s T1 (52s East Industrial) | East Industrial: TX1 DGA Monitor Replacement | |
| EPCOR | 18-May-26 07:00 | 29-May-26 17:00 | 11.42 Days
Continuous |
CV5 (EP 511s Victoria - 557s Castle Downs) | CV5: Manhole Inspections and Maintenance | |
| SUNCOR | 18-May-26 08:00 | 24-May-26 20:00 | 6.5 Days
Continuous |
29PL9-12 (29EDD-34 - 29EDD-65) | 29EDD34;29PL9-12 SYSTEM;PM 5y,10y |
|
| ALTALINK, EPCOR | 19-May-26 07:00 | 22-May-26 17:00 | 3.42 Days
Continuous |
1055L (629s Argyll Transfer Station - 816s Petrolia), 816s P2402 (816s Petrolia), 816s P2403 (816s Petrolia) | 1055L/Petrolia: SA/CT/CVT Doble and PDS4/PDS5 Disconnect Maintenance and Aerial Washing Program | |
| EPCOR | 19-May-26 07:00 | 24-Jul-26 17:00 | 66.42 Days
Continuous |
805s T3 (805s Jasper), EP 805s J2404 (EP 805s Jasper), EP 805s J2405 (EP 805s Jasper) | Jasper: J2402/JAB3/JDS9 Replacement LCR | |
| ATCO | 19-May-26 09:00 | 19-May-26 17:00 | 8 Hours
Continuous |
9L16 (755s Cordel - 972s Tinchebray), 755s 904 (755s Cordel), 755s 905 (755s Cordel), 972s 903 (972s Tinchebray) | Disconnect 9L16 from existing A-frame deadend and 9L16D2 (to be renamed 9L86D1) Restore bus leave renamed 9L86D1 open for future line connection. |
|
| ATCO | 19-May-26 09:00 | 29-May-26 17:00 | 10.33 Days
Continuous |
9L16 (755s Cordel - 972s Tinchebray) | Disconnect 9L16 from existing A-frame deadend and 9L16D2 (to be renamed 9L86D1) Restore bus leave renamed 9L86D1 open for future line connection. |
|
| ALTALINK | 20-May-26 08:00 | 28-May-26 16:00 | 8.33 Days
Continuous |
275s T1 (275s Jenner) | 275sT1 Oil Reclaim | |
| ALTALINK, EPCOR | 23-May-26 07:00 | 25-May-26 17:00 | 2.42 Days
Continuous |
1056L (89s Ellerslie - 629s Argyll Transfer Station) | 1056L: Structure Refurbishment | |
| EPCOR | 25-May-26 07:00 | 27-May-26 17:00 | 2.42 Days
Continuous |
816s P2401 (816s Petrolia) | Petrolia: P2401 CT Doble | |
| EPCOR | 25-May-26 07:00 | 05-Jun-26 17:00 | 11.42 Days
Continuous |
987s T4 (987s Clover Bar), 987s C2408 (987s Clover Bar) | Cloverbar: TX4 DGA Monitor Replacement and Relay Maintenance | |
| EPCOR | 28-May-26 07:00 | 30-May-26 17:00 | 2.42 Days
Continuous |
816s P2405 (816s Petrolia) | Petrolia: P2405 CT Doble | |
| EPCOR | 01-Jun-26 07:00 | 03-Jun-26 17:00 | 2.42 Days
Continuous |
816s P2406 (816s Petrolia) | Petrolia: P2406 CT Doble | |
| EPCOR | 01-Jun-26 07:00 | 07-Jun-26 17:00 | 6.42 Days
Continuous |
T4 (Poundmaker), PM721 (Poundmaker), PM2402 (Poundmaker), PM2403 (Poundmaker) | Poundmaker: TX4 Doble and PMAB4/PMDS4/PMDS5 Disconnect Maintenance | |
| ATCO | 02-Jun-26 09:00 | 13-Jun-26 17:00 | 11.33 Days
Continuous |
972s 905B (972s Tinchebray), 972s 906A (972s Tinchebray) | Connect new 9L62 to 972S and prepare to energize. String Conductors/OPGW 9L62 from Str #3 to substation A-frame deadends and connect to 9L62D1, coordinate with AML conductor jumpers and OPGW termination at the TFO boundary 9L86 Str 409 |
|
| EPCOR, ALTALINK | 08-Jun-26 07:00 | 14-Jun-26 17:00 | 6.42 Days
Continuous |
657s T3 (657s Summerside), 657s SU2405 (657s Summerside), 657s SU2401 (657s Summerside) | Summerside: TX3 Doble and SUAB3/SUDS2/SUDS12 Disconnect Maintenance | |
| EPCOR | 08-Jun-26 07:00 | 19-Jun-26 17:00 | 11.42 Days
Continuous |
T1 (Rossdale), R721 (Rossdale), RR723 (Rossdale), BR722 (Rossdale), 814s T2 (814s Bellamy) | Rossdale: TX1 LCR Demo | |
| ALTALINK | 10-Jun-26 23:00 | 11-Jun-26 03:00 | 4 Hours
Continuous |
62s T1 (62s Brazeau Plant) | maintenance | |
| ALTALINK | 11-Jun-26 03:00 | 11-Jun-26 07:00 | 4 Hours
Daily |
62s T2 (62s Brazeau Plant) | maintenance | |
| ATCO | 14-Jun-26 09:00 | 25-Jun-26 17:00 | 11.33 Days
Continuous |
9L62 (972s Tinchebray - 87s Gaetz) | Work on parallel line 9L86 | |
| ATCO, CNRL | 15-Jun-26 05:00 | 29-Jun-26 10:00 | 14.21 Days
Continuous |
859s 701TD (859s Primrose), 859s 701 (859s Primrose), 859s 704 (859s Primrose), 859s Protection & Control (859s Primrose), 859s RTU/SCADA (859s Primrose), 859s 52G (859s Primrose), 859s 701T (859s Primrose) | maintenance | |
| ALTALINK, EPCOR | 15-Jun-26 09:30 | 15-Jun-26 17:00 | 7.5 Hours
Continuous |
915L (38s East Edmonton - 987s Clover Bar), 987s C2403 (987s Clover Bar), 987s C2405 (987s Clover Bar) | 915L/Cloverbar: CT/CVT/SA Doble and CDS35/CDS36/CDS7 Disconnect Maintenance and Relay Maintenance | |
| ALTALINK, EPCOR | 15-Jun-26 09:30 | 15-Jun-26 17:00 | 7.5 Hours
Continuous |
1139L (367s Harry Smith - EP Riverview), RW2405 (EP Riverview), RW2403 (EP Riverview) | Riverview: 1139L Zone Doble and RWDS6/RWDS9/RWSA12 Disconnect Maintenance and RW2403/RW2405 (SF6) Breaker Maintenance | |
| ATCO | 16-Jun-26 09:00 | 25-Jun-26 17:00 | 9.33 Days
Continuous |
972s 240kV Bus 900BS2 (972s Tinchebray) | Connect new 9L86 to 972S and prepare to energize. String Conductors/OPGW 9L86 from Str #3 to substation A-frame deadends and connect to 9L86D1, coordinate with AML conductor jumpers and OPGW termination at the TFO boundary 9L86 Str 409 Complete protection commissioning |
|
| EPCOR | 22-Jun-26 07:00 | 28-Jun-26 17:00 | 6.42 Days
Continuous |
52s T1 (52s East Industrial) | East Industrial: TX1 Doble | |
| ALTALINK, EPCOR | 22-Jun-26 09:30 | 22-Jun-26 17:00 | 7.5 Hours
Continuous |
921L (71s Lamoureux - 987s Clover Bar), 987s C2404 (987s Clover Bar), 987s C2406 (987s Clover Bar) | 921L/Cloverbar: CT/CVT/SA Doble and CDS9/CDS14/CDS17 Disconnect Maintenance and C2404 (Min Oil) Breaker Maintenance and C2401 Relay Maintenance | |
| ATCO | 29-Jun-26 13:00 | 30-Jun-26 17:00 | 28 Hours
Continuous |
9LA93 (973s Lanes Lake - 9L93 tap) | Line to Ground Clearance Mitigation, Span 50-51. Repair deficiency on structure 57 | |
| EPCOR | 02-Jul-26 07:00 | 18-Sep-26 17:00 | 78.42 Days
Continuous |
805s T4 (805s Jasper), EP 805s J2405 (EP 805s Jasper), EP 805s J2406 (EP 805s Jasper) | Jasper: J2406/JDS10 Replacement LCR | |
| EPCOR | 06-Jul-26 07:00 | 12-Jul-26 17:00 | 6.42 Days
Continuous |
987s T2 (987s Clover Bar), 987s CC721 (987s Clover Bar), 987s C2406 (987s Clover Bar), 987s C2410 (987s Clover Bar) | Cloverbar: TX2 Doble and CDS1/CDS31/CDS33/CDS43 Disconnect Maintenance and Measurements w/Engineering | |
| EPCOR | 13-Jul-26 07:00 | 19-Jul-26 17:00 | 6.42 Days
Continuous |
EP 803s L2401 (EP 803s Lambton) | Lambton: L2401 (Min Oil) Breaker Maintenance and CT Doble | |
| SUNCOR | 15-Jul-26 08:00 | 25-Jul-26 20:00 | 10.5 Days
Continuous |
29EDD-2 29PT-3 (29EDD-2 Tar Island), 29PL6-22 (29EDD-1 Millennium - 29EDD-2 Tar Island) | 29EDD2;29PT-3, 29PL6-22 SYSTEM;PM 5y,10y |
|
| EPCOR | 20-Jul-26 07:00 | 26-Jul-26 17:00 | 6.42 Days
Continuous |
EP 803s L2402 (EP 803s Lambton) | Lambton: L2402 (Min Oil) Breaker Maintenance and CT Doble | |
| ALTALINK | 20-Jul-26 09:00 | 20-Jul-26 15:00 | 6 Hours
Daily |
603L (138s Windy Flats - 243s Soderglen) | maintenance | |
| ALTALINK | 20-Jul-26 13:30 | 23-Jul-26 17:30 | 3.17 Days
Continuous |
777L (48s Pocaterra - 245s Seebe), 245s 777X (245s Seebe) | 245s777X Koncar CT replacement | |
| ATCO | 21-Jul-26 08:00 | 22-Jul-26 17:00 | 1.38 Days
Continuous |
7L65 (709s Vegreville - 7LA65 tap), 7L65 (710s Vermilion - 7LA65 tap), 7LA65 (708s Grizzly Bear - 7L65 tap) | Switch Repairs, 7LA65D1 | |
| ALTALINK, EPCOR | 27-Jul-26 09:30 | 27-Jul-26 17:00 | 7.5 Hours
Continuous |
909L (310p Sundance - 665s Dome), 665s D2403 (665s Dome) | 909LW/Dome: CVT/SA Doble and DDS6/DDS7/DDS14 Disconnect Maintenance and 909LW Relay Maintenance | |
| ALTALINK | 29-Jul-26 23:00 | 30-Jul-26 03:00 | 4 Hours
Continuous |
62s T1 (62s Brazeau Plant) | maintenance | |
| ALTALINK | 30-Jul-26 03:00 | 30-Jul-26 07:00 | 4 Hours
Daily |
62s T2 (62s Brazeau Plant) | maintenance | |
| EPCOR | 10-Aug-26 07:00 | 16-Aug-26 17:00 | 6.42 Days
Continuous |
665s T3 (665s Dome), 665s D721 (665s Dome), 665s D2404 (665s Dome), S721 (Strathcona) | DS26/Dome/Strathcona: Dome TX3 Doble and DAB3/DDS15/DDS16 Disconnect Maintenance and Strathcona DS26/CVT Doble and SDS3 Disconnect Maintenance | |
| ALTALINK | 10-Aug-26 09:30 | 13-Aug-26 17:00 | 3.31 Days
Continuous |
702L (137s Sedgewick - 757s Battle River) | Interphase spacers and pole replacements | |
| ATCO | 10-Aug-26 10:00 | 13-Aug-26 16:30 | 3.27 Days
Continuous |
7L702 (137s Sedgewick - 757s Battle River) | Interphase spacers and pole replacements | |
| ALTALINK, EPCOR | 17-Aug-26 09:30 | 22-Aug-26 17:00 | 5.31 Days
Continuous |
920L (71s Lamoureux - 557s Castle Downs), 557s CD2405 (557s Castle Downs), 557s CD2404 (557s Castle Downs) | 920LE/Castledowns: CT/CVT Doble and Surge Arrestor LCR | |
| ATCO | 17-Aug-26 10:00 | 20-Aug-26 16:30 | 3.27 Days
Continuous |
7L702 (137s Sedgewick - 757s Battle River) | Interphase spacers and pole replacements | |
| ALTALINK | 17-Aug-26 10:00 | 20-Aug-26 16:30 | 3.27 Days
Continuous |
702L (137s Sedgewick - 757s Battle River) | Interphase spacers and pole replacements | |
| ALTALINK, ATCO, FMGW | 18-Aug-26 08:00 | 19-Aug-26 17:00 | 1.38 Days
Continuous |
964AL (1024s Granlea - 964L tap), 1024s PT-6001 (1024s Granlea), 1024s PT-6002 (1024s Granlea), 1024s 952-600001 (1024s Granlea), 1024s PS-6005 (1024s Granlea), 1024s PS-6006 (1024s Granlea), 1024s PS-6007 (1024s Granlea), 1024s PS-6008 (1024s Granlea), 1024s 489-600201 (1024s Granlea) | maintenance activities (testing and inspection) of electrical equipment | |
| EPCOR, ALTALINK | 31-Aug-26 07:00 | 13-Sep-26 17:00 | 13.42 Days
Continuous |
EP 803s T3 (EP 803s Lambton), EP 803s L2403 (EP 803s Lambton), EP 803s L2405 (EP 803s Lambton), EP 803s L721 (EP 803s Lambton), 72LS24 (EP 803s Lambton - Strathcona), 72LH8 (EP 803s Lambton - EP Hardisty), H726 (EP Hardisty), S724 (Strathcona) | Lambton: LDS14 LCR and L721 Breaker Maintenance (Min Oil) and TX3 Zone Doble and L2405 Breaker Maintenance (SF6) and LDS12 Drive Pipe Repair and TX3 Relay Maintenance | |
| ALTALINK | 07-Sep-26 07:00 | 08-Sep-26 18:00 | 1.46 Days
Continuous |
237s T2 (237s Foothills), 237s 240kV Bus 2 (237s Foothills) | Closing Open Point 'C' | |
| ATCO | 08-Sep-26 10:00 | 10-Dec-26 16:00 | 93.29 Days
Continuous |
2015s 902 (2015s Yeo) | Remove circuit breaker for use at 2102S Armistead. New breaker to be installed at 2015S Yeo substation once received from manufacturer. | |
| ALTALINK | 09-Sep-26 07:00 | 10-Sep-26 18:00 | 1.46 Days
Continuous |
237s T1 (237s Foothills), 237s 240kV Bus 1 (237s Foothills) | Closing Open Points 'A' & 'B' | |
| ALTALINK | 10-Sep-26 18:00 | 15-Sep-26 13:00 | 4.79 Days
Continuous |
1141L (1172s Laramide - 237s Foothills) | End to end testing with Laramide 1172s | |
| ALTALINK, EPCOR | 14-Sep-26 09:30 | 17-Sep-26 17:00 | 3.31 Days
Continuous |
920L (37s North Calder - 557s Castle Downs), 557s CD2401 (557s Castle Downs), 557s CD2403 (557s Castle Downs) | 920LW/Castledowns: Surge Arrestor LCR | |
| ALTALINK | 16-Sep-26 23:00 | 17-Sep-26 03:00 | 4 Hours
Continuous |
62s T1 (62s Brazeau Plant) | maintenance | |
| ALTALINK | 17-Sep-26 03:00 | 17-Sep-26 07:00 | 4 Hours
Daily |
62s T2 (62s Brazeau Plant) | maintenance | |
| EPCOR | 21-Sep-26 07:00 | 03-Oct-26 17:00 | 12.42 Days
Continuous |
987s CCP7213 (987s Clover Bar), 987s CCP7214 (987s Clover Bar), 987s C2401 (987s Clover Bar), 987s C2403 (987s Clover Bar), 987s T1 (987s Clover Bar) | Cloverbar: C2401/C2403 Breaker Maintenance and CT Doble and CDS19 LCR and C2401 Relay Maintenance | |
| EPCOR | 21-Sep-26 07:00 | 30-Oct-26 17:00 | 39.42 Days
Continuous |
EP 805s J2405 (EP 805s Jasper) | Jasper: J2405 Replacement LCR | |
| ATCO | 21-Sep-26 10:00 | 24-Sep-26 16:00 | 3.25 Days
Continuous |
888s 906 (888s Dover) | 21B/9L74 relay replacement. Cutover breaker and CT to new protection | |
| ALTALINK | 22-Sep-26 07:00 | 22-Sep-26 19:00 | 12 Hours
Daily |
608AL (528s Blue Trail Wind Farm - 608L tap) | Removing D608BL conductors from existing str 608AL32 for salvage. Adding new 608AL32A. | |
| ALTALINK | 24-Sep-26 07:00 | 24-Sep-26 19:00 | 12 Hours
Daily |
603L (138s Windy Flats - 243s Soderglen) | Removing D603AL conductors from existing str 603L97 for salvage. Replacing 603L98. | |
| ATCO | 25-Sep-26 10:00 | 28-Sep-26 16:00 | 3.25 Days
Continuous |
888s 905 (888s Dover) | 21B/9L74 relay replacement. Cutover breaker and CT to new protection | |
| EPCOR | 05-Oct-26 07:00 | 20-Nov-26 17:00 | 46.46 Days
Continuous |
814s T1 (814s Bellamy), BR721 (Rossdale), 814s B2401 (814s Bellamy), 814s B2407 (814s Bellamy) | Bellamy: TX1 Oil Reclamation and LTC Monitor Install | |
| ALTALINK | 05-Oct-26 08:00 | 28-Nov-26 19:00 | 54.5 Days
Continuous |
62s T2 (62s Brazeau Plant) | maintenance | |
| ATCO | 05-Oct-26 10:00 | 08-Oct-26 16:00 | 3.25 Days
Continuous |
9L74 (888s Dover - 960s Birchwood Creek) | 21B/9L74 relay three terminal line testing | |
| ATCO | 12-Oct-26 10:00 | 15-Oct-26 16:00 | 3.25 Days
Continuous |
888s 906 (888s Dover) | 21A/9L74 relay replacement. Cutover breaker and CT to new protection | |
| ATCO | 16-Oct-26 10:00 | 19-Oct-26 16:00 | 3.25 Days
Continuous |
888s 905 (888s Dover) | 21B/9L74 relay replacement. Cutover breaker and CT to new protection | |
| ALTALINK, EPCOR | 19-Oct-26 09:30 | 19-Oct-26 17:00 | 7.5 Hours
Continuous |
908L (89s Ellerslie - 816s Petrolia), 816s P2401 (816s Petrolia), 816s P2406 (816s Petrolia) | Petrolia: 908LE Surge Arrestor and CVT LCR | |
| ATCO | 26-Oct-26 10:00 | 29-Oct-26 16:00 | 3.25 Days
Continuous |
9L74 (888s Dover - 960s Birchwood Creek) | 21B/9L74 relay three terminal line testing | |
| EPCOR | 02-Nov-26 07:00 | 06-Nov-26 17:00 | 4.42 Days
Continuous |
EP 805s J2407 (EP 805s Jasper) | Jasper: J2407 Replacement LCR | |
| Syncrude | 03-Nov-26 08:00 | 18-Nov-26 16:00 | 15.33 Days
Continuous |
UE-1 (D05 - UE-1 Syncrude Plant 30-2), T1 (D05 Syncrude), D05 511 (D05), D05 519 (D05), D05 71 (D05), D05 71A (D05), D05 71B (D05), D05 80 (D05), D05 80B (D05), D05 79 (D05), D05 79B (D05), D05 73 (D05), D05 73A (D05), D05 73B (D05), D05 75 (D05), D05 75A (D05), LCF (D05), ML-4 (D05), UE-1 7206 (UE-1 Syncrude Plant 30-2), UE-1 72-16 (UE-1 Syncrude Plant 30-2), D05 511A (D05), D05 519A (D05), D05 519B (D05), D05 80A (D05), D05 79A (D05), D05 75B (D05) | complete 6-Year 72 kV A bus preventive maintenance in D05 substation | |
| ALTALINK | 05-Nov-26 03:00 | 05-Nov-26 07:00 | 4 Hours
Daily |
62s T1 (62s Brazeau Plant) | maintenance | |
| ALTALINK, EPCOR | 06-Nov-26 07:00 | 27-Nov-26 17:00 | 21.42 Days
Continuous |
1045L (EP 805s Jasper - 1045AL tap), EP 805s J2407 (EP 805s Jasper), EP 805s J2406 (EP 805s Jasper), EP 805s J2401 (EP 805s Jasper), 1098L (EP 805s Jasper - Poundmaker) | 1045L/1098L/Jasper: J2407 Replacement LCR | |
| EPCOR | 09-Nov-26 07:00 | 11-Dec-26 17:00 | 32.42 Days
Continuous |
52s T2 (52s East Industrial), 52s E2402 (52s East Industrial) | East Industrial: TX2 Bushing Replacement | |
| EPCOR | 09-Nov-26 07:00 | 11-Dec-26 17:00 | 32.42 Days
Continuous |
PM2405 (Poundmaker) | Poundmaker: P2405 Breaker Replacement | |
| EPCOR | 23-Nov-26 07:00 | 04-Dec-26 17:00 | 11.42 Days
Continuous |
814s T2 (814s Bellamy), BR722 (Rossdale), 814s B2402 (814s Bellamy), 814s B2406 (814s Bellamy) | Bellamy: TX2 LTC Monitor Install | |
| EPCOR | 27-Nov-26 07:00 | 18-Dec-26 17:00 | 21.42 Days
Continuous |
EP 805s J2407 (EP 805s Jasper) | Jasper: J2407 Replacement LCR | |
| ALTALINK | 23-Dec-26 23:00 | 24-Dec-26 03:00 | 4 Hours
Continuous |
62s T1 (62s Brazeau Plant) | maintenance | |
| ALTALINK | 24-Dec-26 03:00 | 24-Dec-26 07:00 | 4 Hours
Daily |
62s T2 (62s Brazeau Plant) | maintenance | |
| EPCOR | 04-Jan-27 07:00 | 12-Mar-27 17:00 | 67.42 Days
Continuous |
EP 805s J2401 (EP 805s Jasper) | Jasper: J2401 Replacement LCR | |
| ATCO | 09-Feb-27 09:00 | 11-Feb-27 17:00 | 2.33 Days
Continuous |
7L228 (845s Big Mountain - 7L20 tap) | AESO project P2716 - Install 7L228 bypass to facilitate the installation of new line switches for the new 7LA228 T-tap line connection to the new 2103S Pakenham substation Open 7L228, replace structures 551 and 551A, connect bypass. |
|
| EPCOR | 15-Feb-27 07:00 | 19-Feb-27 17:00 | 4.42 Days
Continuous |
EP 805s J2403 (EP 805s Jasper) | Jasper: J2403 Replacement LCR | |
| EPCOR, ALTALINK | 19-Feb-27 07:00 | 05-Mar-27 17:00 | 14.42 Days
Continuous |
EP 805s J2404 (EP 805s Jasper), EP 805s J2403 (EP 805s Jasper), EP 805s J2408 (EP 805s Jasper), 805s C1 (805s Jasper), 1044L (EP 805s Jasper - 816s Petrolia) | 1044L/Jasper: J2403 Replacement LCR | |
| EPCOR | 05-Mar-27 07:00 | 26-Mar-27 17:00 | 21.38 Days
Continuous |
EP 805s J2403 (EP 805s Jasper) | Jasper: J2403 Replacement LCR | |
| ATCO | 08-Mar-27 10:00 | 17-Mar-27 17:00 | 9.25 Days
Continuous |
9L24 (946s Oakland - 959s Lanfine), 959s 906 (959s Lanfine), 959s 905 (959s Lanfine), 946s 902 (946s Oakland), 946s 903 (946s Oakland) | Replace A/B protection relays at 959S Lanfine and 946S Oakland Cut in and reroute 9L24 Connect new 9LA24 T-tap Commission Telecom and Protection to new 1072S Rose Lynn substation |
|
| ATCO | 16-Mar-27 09:00 | 18-Mar-27 17:00 | 2.33 Days
Continuous |
7L228 (845s Big Mountain - 7L20 tap) | AESO project P2716 - Disconnect bypass, connect new 7LA228D1 to 7LA228 Str #2, connect 7L228 to 7L228D2, connect 7L228 to 7L228D3. Renumber existing line switches 7L228D2 - D4, 7L228D3 - D5, 7L228D4 - D6 Commission DTT from Pakenham to Big Mountain |
|
| ATCO | 22-Mar-27 09:00 | 25-Mar-27 17:00 | 3.33 Days
Continuous |
2091s 704 (2091s Thornton) | AESO project P2716 - cut over new SEL 2440 wiring at 2091S, relay programming, commission DTT and LTO from 2103S Pakenham | |
| ATCO | 26-Mar-27 09:00 | 29-Mar-27 17:00 | 3.33 Days
Continuous |
740s 704 (740s H.R. Milner), 7L20 (740s H.R. Milner - 810s Dome Cutbank) | AESO project P2716 - cut over RAS #171 wiring at 740S, relay programming, commission LTO 7L20/7L228 | |
| SUNCOR | 06-Apr-27 09:00 | 16-Apr-27 20:00 | 10.46 Days
Continuous |
29EDD-34 29PT-112 (29EDD-34), 29EDD-34 29-752-121 (29EDD-34), 29EDD-34 29PS-68 (29EDD-34), 29EDD-34 29PS-67 (29EDD-34), 29EDD-34 29PS-66 (29EDD-34), 29EDD-34 29PS-65 (29EDD-34), 29EDD-34 29PS-225 (29EDD-34), 29EDD-34 29PS-230 (29EDD-34), 29EDD-34 29-952-141 (29EDD-34), 29EDD-34 29-952-131 (29EDD-34), 29EDD-34 29-952-111 (29EDD-34) | 29EDD34;29PT-112 & 29PP-24 SYSTEM;PM This will Place 29EDD-34 on one 260 kV bus and drop 29PL7-1 |
|
| ATCO | 12-Apr-27 10:00 | 19-Apr-27 17:00 | 7.29 Days
Continuous |
7L22 (790s Poplar Hill - 7L88 tap) | Cut open 7L22, connect new line section to new 2061S Dobbs 7L22/21B relay upgrades at 790S Poplar Hill and 811S Clairmont Lake On completion energize new 2061S Dobbs substation |
|
| SUNCOR | 14-Apr-27 14:00 | 23-Apr-27 18:00 | 9.17 Days
Continuous |
29EDD-65 29PT-0257 (29EDD-65), 29EDD-65 29-952-4812 (29EDD-65), 29EDD-65 29-952-4813 (29EDD-65), 29EDD-71 752-4624 (29EDD-71), 29EDD-71 752-4623 (29EDD-71), 29PL7-4 (29EDD-65 - 29EDD-71) | Firebag: 29EDD65;29PT-257 & 29PL7-4 SYSTEM, 29EDD65 ;29PT-260 & 29PL7-4 SYSTEM, 29EDD71 29PT-241 & 29PL7-4 | |
| ATCO | 03-May-27 09:00 | 17-May-27 17:30 | 14.35 Days
Continuous |
2075s T11 (2075s Newell) | Annual EATL outage at 2075s & 2029s. | |
| ATCO | 03-May-27 09:00 | 17-May-27 17:30 | 14.35 Days
Continuous |
2029s T11 (2029s Heathfield) | Annual EATL outage at 2075s & 2029s. | |
| ATCO | 03-May-27 09:00 | 17-May-27 17:30 | 14.35 Days
Continuous |
13L50 (2029s Heathfield - 2075s Newell) | Annual EATL outage at 2075s & 2029s. **1218 IS NOT THE ISOALTION. ATCO SENT AESO OF REQUIRED ISOLATIONS BACK IN MAY 2024 TO UPDATE 2029S AND 2075S ISOLATIONS FOR 13L50 OUTAGES** |
|
| ATCO | 03-May-27 10:00 | 06-May-27 17:00 | 3.29 Days
Continuous |
7L22 (811s Clairmont Lake - 7L88 tap) | 7L22/21B relay upgrade at 811S Clairmont Lake Upon completion new 2061S Dobbs substation ready to energize |
|
| SUNCOR | 04-May-27 09:00 | 14-May-27 20:00 | 10.46 Days
Continuous |
29EDD-34 29PS-214 (29EDD-34), 29EDD-34 29-952-113 (29EDD-34), 29EDD-34 29PS-215 (29EDD-34), 29EDD-34 29PS-213 (29EDD-34) | 29EDD34;29PL9-13 SYSTEM;PM 5y,10y | |
| SUNCOR | 05-May-27 14:00 | 14-May-27 18:00 | 9.17 Days
Continuous |
29EDD-65 29PT-0236 (29EDD-65), 29EDD-65 29-952-4823 (29EDD-65), 29EDD-65 29-952-4822 (29EDD-65), 29EDD-71 752-4634 (29EDD-71), 29EDD-71 752-4633 (29EDD-71), 29PL7-3 (29EDD-65 - 29EDD-71) | Firebag: 29EDD65;29PT-236 & 29PL7-3 SYSTEM, 29EDD65;29PT-250&29PL7-3 SYSTEM, 29PT-246 SYSTEM;29EDD71 | |
| ATCO | 10-May-27 10:00 | 11-May-27 17:00 | 31 Hours
Continuous |
7L03 (749s Flyingshot Lake - 7L09 tap) | Cutover and commission RAS analogs and LTO to 790S Poplar Hill RAS Hub | |
| ATCO | 12-May-27 10:00 | 13-May-27 17:00 | 31 Hours
Continuous |
7L03 (731s Elmworth - 7L09 tap) | Cutover and commission LTO to 790S Poplar Hill RAS Hub | |
| ATCO | 14-May-27 10:00 | 15-May-27 17:00 | 31 Hours
Continuous |
7L69 (731s Elmworth - 815s Goodfare) | Cutover and commission LTO to 790S Poplar Hill RAS Hub | |
| ATCO | 16-May-27 10:00 | 17-May-27 17:00 | 31 Hours
Continuous |
7L07 (790s Poplar Hill - 815s Goodfare) | Cutover and commission LTO to 790S Poplar Hill RAS Hub | |
| SUNCOR | 01-Jun-27 08:00 | 10-Jun-27 17:00 | 9.38 Days
Continuous |
635EDD-1000 635-752-635PT-1000 (635EDD-1000), 635EDD-1000 635PT-1000 (635EDD-1000) | FH - Maintenance on Transformer, associated breakers, other equipment in isolation boundary and protection system testing. | |
| SUNCOR | 01-Jun-27 09:00 | 11-Jun-27 20:00 | 10.46 Days
Continuous |
29EDD-94 407T (29EDD-94 Voyageur), 29EDD-94 29-952-9705 (29EDD-94 Voyageur), 29EDD-94 29PS-393 (29EDD-94 Voyageur), 29EDD-94 29PS-392 (29EDD-94 Voyageur), 29EDD-94 29-952-9704 (29EDD-94 Voyageur), 29EDD-94 29PS-400 (29EDD-94 Voyageur) | 29EDD94;29PT-407 SYSTEM;PM 5y,10y | |
| SUNCOR | 11-Jun-27 08:00 | 20-Jun-27 17:00 | 9.38 Days
Continuous |
635EDD-1000 635-752-635PT-1001 (635EDD-1000), 635EDD-1000 635PT-1001 (635EDD-1000) | FH - Maintenance on Transformer, associated breakers, other equipment in isolation boundary and protection system testing. | |
| SUNCOR | 15-Jun-27 09:00 | 25-Jun-27 20:00 | 10.46 Days
Continuous |
29EDD-94 406T (29EDD-94 Voyageur), 29EDD-94 29-952-9702 (29EDD-94 Voyageur), 29EDD-94 29PS-388 (29EDD-94 Voyageur), 29EDD-94 29PS-389 (29EDD-94 Voyageur), 29EDD-94 29PS-399 (29EDD-94 Voyageur) | 29EDD94;29PT-406 SYSTEM;PM 5y,10y | |
| ATCO | 20-Jul-27 08:00 | 21-Jul-27 17:00 | 1.38 Days
Continuous |
7L53 (706s Irish Creek - 7LA53 tap), 7LA53 (969s Lindbergh - 7L53 tap), 7L53 (700s Bonnyville - 7LA53 tap) | Cold Lake Area Project to connect 1064s | |
| ATCO | 22-Jul-27 08:00 | 25-Jul-27 17:00 | 3.38 Days
Continuous |
7L91 (715s Leming Lake - 826s Marguerite Lake) | Cold Lake Area Energy Centre Project |
|
| ALTALINK, ATCO, FMGW | 17-Aug-27 08:00 | 18-Aug-27 17:00 | 1.38 Days
Continuous |
964AL (1024s Granlea - 964L tap), 1024s PT-6001 (1024s Granlea), 1024s PT-6002 (1024s Granlea), 1024s 952-600001 (1024s Granlea), 1024s PS-6005 (1024s Granlea), 1024s PS-6006 (1024s Granlea), 1024s PS-6007 (1024s Granlea), 1024s PS-6008 (1024s Granlea), 1024s 489-600201 (1024s Granlea) | maintenance activities (testing and inspection) of electrical equipment | |
| ALTALINK | 08-Nov-27 08:30 | 11-Nov-27 17:30 | 3.38 Days
Continuous |
409s 110 (409s Shell Scotford) | Install new Deadend corner structure on ALC02L | |
| ALTALINK | 08-Nov-27 08:30 | 11-Nov-27 17:30 | 3.38 Days
Continuous |
409s 107 (409s Shell Scotford) | Install new Deadend corner structure on ALC02L. | |
| ATCO | 08-Nov-27 09:00 | 11-Nov-27 17:00 | 3.33 Days
Continuous |
ALC02L (409s Shell Scotford - 879s Upgrader) | Install new Deadend corner structure on ALC02L | |
| ATCO | 08-Nov-27 09:00 | 11-Nov-27 17:00 | 3.33 Days
Continuous |
ALC01L (408s Air Liquide Scotford - 409s Shell Scotford) | Install new Deadend corner structure on ALC02L. | |
| ATCO | 06-Mar-28 10:00 | 22-Mar-28 16:00 | 16.21 Days
Continuous |
826s 903 (826s Marguerite Lake), 826s 907 (826s Marguerite Lake), 826s 901T (826s Marguerite Lake) | Expand 240kV ring bus for new 9L42 line | |
| ALTALINK | 13-Mar-28 09:30 | 16-Mar-28 17:30 | 3.33 Days
Continuous |
939L (77s Sagitawah - 809s Louise Creek) | Cut over 9L939 to temp bypass structures to allow for installation of new deadend corner towers. These are required to make the final connections to the new 2105S Jackson substation. | |
| ATCO | 13-Mar-28 10:00 | 16-Mar-28 17:00 | 3.29 Days
Continuous |
9L939 (77s Sagitawah - 809s Louise Creek) | Cut over 9L939 to temp bypass structures to allow for installation of new deadend corner towers. These are required to make the final connections to the new 2105S Jackson substation | |
| ALTALINK | 17-Mar-28 09:30 | 17-Apr-28 17:30 | 31.33 Days
Continuous |
939L (77s Sagitawah - 809s Louise Creek) | Install foundations (TBD assume concrete), assemble and erect new Q-towers 9L938/9L939-155A and 9L938/9L939-156A in existing ROW centreline. Daily outage until such a time as the new towers begin to encroach on 9L938. | |
| ATCO | 17-Mar-28 10:00 | 17-Apr-28 17:00 | 31.29 Days
Continuous |
9L938 (77s Sagitawah - 809s Louise Creek) | Install foundations (TBD assume concrete), assemble and erect new Q-towers 9L938/9L939-155A and 9L938/9L939-156A in existing ROW centreline. Daily outage until such a time as the new towers begin to encroach on 9L938. | |
| ALTALINK | 18-Apr-28 09:30 | 25-Apr-28 17:30 | 7.33 Days
Continuous |
938L (77s Sagitawah - 809s Louise Creek) | Open 9L938 conductors, complete assembly and connect to the new Q-Towers 9L938/9L939-155A and 9L938/9L939-156A, string to 2105S Jackson deadend and terminate. Re-label 9L938 segment from 809S Louise Creek to 2105S Jackson to 9L140. | |
| ATCO | 18-Apr-28 10:00 | 25-Apr-28 17:00 | 7.29 Days
Continuous |
9L938 (77s Sagitawah - 809s Louise Creek) | Open 9L938 conductors, complete assembly and connect to the new Q-Towers 9L938/9L939-155A and 9L938/9L939-156A, string to 2105S Jackson deadend and terminate. Relabel 9L938 segment from 809S Louise Creek to 2105S Jackson to 9L140. |
|
| ALTALINK | 01-May-28 09:30 | 04-May-28 17:30 | 3.33 Days
Continuous |
939L (77s Sagitawah - 809s Louise Creek) | Disconnect 9L939 conductors from temp structure | |
| ATCO | 01-May-28 10:00 | 04-May-28 17:00 | 3.29 Days
Continuous |
9L939 (77s Sagitawah - 809s Louise Creek) | Disconnect 9L939 conductors from temp structure 9L939 -155A - 155E reconnect to existing structures 9L938/9L939-156 and 9L938/9L939-155, connect to the new Q-Towers 9L938/9L939-155A and 9L938/9L939-156A, string to 2105S Jackson deadend and terminate. Relabel 9L939 segment from 809S Louise Creek to 2 |
|
| ATCO | 08-May-28 09:00 | 10-Jul-28 17:00 | 63.33 Days
Continuous |
959s 240kV Bus 900BS2 (959s Lanfine) | GOI on 9L141 until line terminated into 1162S Fair Acres and ready to energize | |
| ATCO | 08-May-28 09:00 | 10-Jul-28 17:00 | 63.33 Days
Continuous |
959s 240kV Bus 900BS2 (959s Lanfine) | GOI on 902/903 until line terminated and 1162S Fair Acres ready to energize | |
| ATCO | 09-May-28 10:00 | 13-May-28 17:00 | 4.29 Days
Continuous |
9L02 (809s Louise Creek - 813s Little Smoky) | Install concrete foundations for new structures 9L02/320A, 320H in preparation to cut into 9L02 and convert to a t-tap. | |
| ATCO | 15-May-28 09:00 | 17-May-28 17:00 | 2.33 Days
Continuous |
959s 240kV Bus 900BS1 (959s Lanfine) | Connect new bus from new 902B to existing switch 901A to add new line 9L141, Cutover and commission 900PT1 ccts to new 9L141 relays |
|
| ATCO | 18-May-28 09:00 | 20-May-28 17:00 | 2.33 Days
Continuous |
959s 240kV Bus 900BS2 (959s Lanfine) | Connect new bus from new Bkr 903 to existing switch 903B to add new line 9L141, Cutover and commission 900PT2 ccts to new 9L141 relays |
|
| ATCO | 29-May-28 09:00 | 08-Jun-28 17:00 | 10.33 Days
Continuous |
9L24 (946s Oakland - 959s Lanfine) | Cutover and commission 905/906 CT's, 9L24PT ccts to new RAS 241 SEL 451A/B relays @ 959S Lanfine and update relay settings for RAS 241 and SCADA inputs @946S Oakland. | |
| ATCO | 19-Jun-28 10:00 | 30-Jun-28 16:00 | 11.25 Days
Continuous |
9L20 (755s Cordel - 766s Nevis) | Red Willow Solar Install concrete foundations at 9L20 Structure 69 for new T-Tap connection |
|
| ATCO | 26-Jun-28 10:00 | 10-Jul-28 17:00 | 14.29 Days
Continuous |
9L02 (809s Louise Creek - 813s Little Smoky) | Cut into 9L02 and connect new t-tap structures for 9LA02. 9L02-21A and 21B relay upgrades at 809S Louise Creek and 813S Little Smoky. Implement RAS Energize new line 9LA02 and 884S Magpie substation (UK Solar LS1) |
| AB-BC, AB-SK & AB-MATL: refer to AESO web posting: | http://itc.aeso.ca/itc/public/atc |
| Also, | |
| AB-BC, AB-SK & AB-MATL: refer to ISO Rule 203.6: | http://www.aeso.ca/rulesprocedures/18592.html |
| Prepared On: | 2026-01-14 15:32:37 |
|
This document and the information contained herein are based upon information and data which by their nature contain a degree of uncertainty and are subject to change. In addition, this document may contain information and data from public sources and/or third parties, which have been assumed to be accurate and complete and have not been verified. Accordingly, the Independent System Operator, operating as the Alberta Electric System Operator (the "AESO") makes no warranty, representation or guarantee, express or implied, with respect to this document or the information contained herein, including, but not limited to, any warranty, representation or guarantee of accuracy, completeness, timeliness, reliability, availability, absence of computer virus, non- infringement, merchantability or suitability for any purpose. Under no circumstances will the AESO, its members, officers, employees, contractors or agents, or any of their respective affiliates, be liable for any errors or omissions in, or any losses, damages or claims whatsoever, whether in contract, tort or otherwise, arising from use of or reliance upon, this document or any information contained herein. © 2009 Alberta Electric System Operator. All rights reserved |