| Alberta Electric System Operator | |
| Long Range Significant Transmission Outages for the period of 24 months starting 2026-08-01 | |
|
The table below contains the significant transmission outages submitted as tentative to the AESO. These Outages have not yet necessarily been approved, but are listed for awareness and coordination purposes. An Outage has been considered significant for this table if it meets any one (1) or more of the following criteria: |
|
|
|
| Note: Where a transmission outage requires generation curtailments, the adjustments to generation will typically happen in the hours before the scheduled transmission outage and in the hour after the element is returned to service. | |
| Previous Version | |
| Download CSV | |
| Owner | From | To | Duration | Element | Scheduled Activity | Affected Intertie |
|---|---|---|---|---|---|---|
| ATCO | 25-Nov-25 17:46 | 18-Sep-26 18:00 | 7,127.23 Hours
Continuous |
876s 901T (876s Brintnell) | forced outage oil leaking | |
| SUNCOR | 04-Jan-26 08:00 | 02-Sep-26 16:00 | 5,791 Hours
Continuous |
29EDD-34 260kV Bus 29PP-45 (29EDD-34), 29EDD-34 29-952-113 (29EDD-34), 29EDD-34 29PS-216 (29EDD-34) | urgent repairs on 29PT-224 at 29EDD34 on 29PP-45 bus | |
| ATCO | 14-Jul-26 11:56 | 31-Aug-26 00:00 | 1,140.07 Hours
Continuous |
7L91 (715s Leming Lake - 826s Marguerite Lake) | forced outage | |
| ALTALINK | 15-Jul-26 14:01 | 05-Oct-26 09:00 | 1,962.98 Hours
Continuous |
417L (55s Olds - 281s Johnson), 55s T1 (55s Olds), 55s T2 (55s Olds), 55s 417 (55S Olds), 287s 552 (287s Hazelwood), 55s 2 (55s Olds) | mobile install at 55s for P_C major upgrade, repair/replace s80, s83, s84. salvage s51. | |
| EPCOR | 20-Jul-26 07:00 | 02-Aug-26 17:00 | 322 Hours
Continuous |
987s T1 (987s Clover Bar), 987s CCP7213 (987s Clover Bar), 987s CCP7214 (987s Clover Bar), 987s C2401 (987s Clover Bar), 987s C2403 (987s Clover Bar), 987s CDS25 (987s Cloverbar) | Cloverbar: breaker maintenance and CT doble and relay maintenance | |
| ALTALINK | 20-Jul-26 14:30 | 07-Aug-26 17:00 | 434.5 Hours
Continuous |
1083L (63s Red Deer - 288s Wolf Creek), 63s 452 (63s Red Deer), 63s 552 (63s Red Deer), 288s 352 (288s Wolf Creek), 288s 152 (288s Wolf Creek), 288s 1083 (288s Wolf Creek), 63s 1083 (63s Red Deer) | 63s452 breaker replacement | |
| Syncrude | 26-Jul-26 08:00 | 08-Aug-26 16:00 | 272 Hours
Continuous |
14 (Aurora), 213 (Aurora), 223 (Aurora), 24 (Aurora), 34 (Aurora), 260kV Bus 2 (Aurora), 72 kV Bus 2 (Aurora), T11 (Aurora), 89-216 (Aurora), 89-52 (Aurora) | zone 1 6 year PM at Aurora | |
| EPCOR | 27-Jul-26 07:00 | 04-Sep-26 17:00 | 946 Hours
Continuous |
EP 805s J2401 (EP 805s Jasper) | Jasper: J2401 replacement LCR | |
| SUNCOR | 31-Jul-26 08:00 | 06-Aug-26 16:00 | 156 Hours
Continuous |
29EDD-1 29EDD1s152 (29EDD-1 Millennium) | maintenance & trip test | |
| SUNCOR | 01-Aug-26 08:00 | 31-Aug-26 20:00 | 732 Hours
Continuous |
29EDD-60 29PT-702 (29EDD-60 Inglis Island) | 30PD-32 IPB PRESSURE LOW - Requires 29PT-702 to be 300691658 | |
| ALTALINK | 03-Aug-26 08:00 | 04-Aug-26 17:00 | 33 Hours
Continuous |
310p 1452 (310p Sundance) | Test 310p1452 CTs | |
| ENMAX, ALTALINK | 04-Aug-26 08:00 | 21-Aug-26 16:00 | 416 Hours
Continuous |
24.83L (74s Janet - SS-24) | Wood pole installation | |
| ALTALINK, ENMAX | 04-Aug-26 08:00 | 21-Aug-26 16:00 | 416 Hours
Continuous |
74s 24.83X (74s Janet), 24.83L (74s Janet - SS-24) | Enmax Wood pole installation | |
| ENMAX, ALTALINK | 04-Aug-26 09:00 | 04-Aug-26 17:00 | 8 Hours
Continuous |
5s T2 (5s East Calgary) | Altalink outage. Altalink will be removing 5s T2 from service for maintenance | |
| ALTALINK, TRANSALTA | 04-Aug-26 09:00 | 06-Aug-26 17:00 | 56 Hours
Continuous |
179s 733 (179s Gleichen), 428s 733X (428s Namaka), 733L (179s Gleichen - 428s Namaka) | 733Lstr. 161-211 Crossarm work. Maintenance/repairs. | |
| ENMAX, ALTALINK | 04-Aug-26 09:00 | 06-Aug-26 17:00 | 56 Hours
Continuous |
5s T2 (5s East Calgary) | 5sT2 PRC Doble , Major Maint. | |
| ATCO | 04-Aug-26 09:00 | 06-Aug-26 17:30 | 56.5 Hours
Continuous |
2029s 1301 (2029s Heathfield) | DC HIGH SPEED SWITCH MAINTENANCE - 1302 @ 2029S **EATL will need to run in P2 Return while 1302 is out of service |
|
| SUNCOR | 04-Aug-26 09:00 | 07-Aug-26 20:00 | 83 Hours
Continuous |
29EDD-1 29EDD1s952 (29EDD-1 Millennium) | 29EDD1s952 - Faulty SF6 Sensors / No visibility risk, No line outage - BPC-26-014 - 300677553 | |
| BCH | 04-Aug-26 09:00 | 23-Aug-26 13:00 | 460 Hours
Continuous |
5L91 (BCH Ashton Creek - BCH Selkirk) | maintenance | AB-BC |
| ALTALINK | 04-Aug-26 10:00 | 05-Aug-26 16:30 | 30.5 Hours
Continuous |
74s 104 (74s Janet), 74s 103 (74s Janet), 74s 102 (74s Janet), 74s C3 (74s Janet), 74s C4 (74s Janet) | 74s103 Major maint | |
| ATCO | 04-Aug-26 10:00 | 05-Aug-26 17:00 | 31 Hours
Continuous |
7L131 (834s Wesley Creek - 905s Meikle) | 708 Densimeters Replacement at 834s Wesley Creek Investigate Heater Fail - 708 at 834S Wesley Creek Investigate inoperable switch 708B |
|
| ALTALINK | 04-Aug-26 10:00 | 06-Aug-26 17:30 | 55.5 Hours
Continuous |
310p 2652 (310p Sundance), 310p 2752 (310p Sundance), 77s 29 (77s Sagitawah), 77s 26 (77s Sagitawah), 989L (77s Sagitawah - 310p Sundance) | 989L Line Maintenance. 77s26 Breaker maintenance | |
| ALTALINK | 05-Aug-26 07:00 | 06-Aug-26 16:00 | 33 Hours
Continuous |
310p 2852 (310p Sundance) | Test 310p2852 CTs | |
| ATCO | 05-Aug-26 08:00 | 06-Aug-26 13:00 | 29 Hours
Continuous |
7L85 (803s ATC Bullpound - 7LA85 tap) | Interphase spacer install, Deficiency repairs & insulator replacement between Badlands and Bullpound | |
| ATCO | 05-Aug-26 09:00 | 05-Aug-26 17:00 | 8 Hours
Continuous |
7L22 (790s Poplar Hill - 7L88 tap), 790s 702 (790s Poplar Hill) | ASEA IMBD CT Testing at 790S POPLAR HILL - CT702 - PRIORITY 2 | |
| ATCO | 06-Aug-26 09:00 | 06-Aug-26 17:00 | 8 Hours
Continuous |
7L07 (790s Poplar Hill - 815s Goodfare), 790s 703 (790s Poplar Hill) | ASEA IMBD CT Testing at 790S POPLAR HILL - CT703 - PRIORITY 2 | |
| SUNCOR | 06-Aug-26 14:01 | 06-Aug-26 20:00 | 5.98 Hours
Continuous |
29EDD-1 29EDD1s252 (29EDD-1 Millennium) | 29EDD1 29CVT-1/29PL9-2 SYS PVM 5Y 10Y PRC-005 Trip Test 29EDD1s252, We will trip and reclose the breaker | |
| SUNCOR | 07-Aug-26 10:00 | 07-Aug-26 12:59 | 2.98 Hours
Continuous |
29EDD-1 29EDD1s952 (29EDD-1 Millennium) | 29EDD1 / N260B2 NORTH BUS PRC-005 Relay Testing - Trip open 29EDD1S952 - - 450338056 In conjunction with Outage 1-00529372 |
|
| SUNCOR | 07-Aug-26 13:00 | 07-Aug-26 16:00 | 3 Hours
Continuous |
29EDD-1 29EDD1s752 (29EDD-1 Millennium) | 29EDD1 / N260B2 NORTH BUS PRC-005 Relay Testing - Trip open 29EDD1S752 - following outage: 1-00529374 - 450338056 In conjunction with Outage 1-00529372 |
|
| ENMAX, ALTALINK | 08-Aug-26 08:00 | 08-Aug-26 18:00 | 10 Hours
Continuous |
832L (SS-10 - SS-12), 12.1TR (SS-12) | Substation Structure Painting | |
| SUNCOR | 08-Aug-26 09:00 | 11-Aug-26 20:00 | 83 Hours
Continuous |
29EDD-1 29EDD1s852 (29EDD-1 Millennium) | 29EDD1S852 Replace Densimeter | |
| ENMAX, ALTALINK | 09-Aug-26 08:00 | 09-Aug-26 18:00 | 10 Hours
Continuous |
833L (SS-2 - SS-12), 12.2TR (SS-12) | Substation Structure Painting | |
| ATCO | 10-Aug-26 07:00 | 14-Aug-26 17:00 | 106 Hours
Continuous |
7L03 (749s Flyingshot Lake - 7L09 tap) | Tie in of a bypass for 7L03 to facilitate Alberta highways construction project. | |
| EPCOR | 10-Aug-26 07:00 | 16-Aug-26 17:00 | 154 Hours
Continuous |
665s T3 (665s Dome), 665s D721 (665s Dome), 665s D2404 (665s Dome), S721 (Strathcona) | DS26/Dome/Strathcona: Dome TX3 Doble and DAB3/DDS15/DDS16 Disconnect Maintenance and Strathcona DS26/CVT Doble and SDS3 Disconnect Maintenance | |
| ATCO | 10-Aug-26 09:00 | 13-Aug-26 16:00 | 79 Hours
Continuous |
969s 701T (969s Lindbergh), 969s Protection & Control (969s Lindbergh) | total station outage to replace failing HO/XO bushings on transformer, updates to anti-islanding RAS logic and alarming, replace NGR resistor and relay
coordinated with dates provided by Strathcona Resources, awaiting confirmation from IPL |
|
| ALTALINK, BCH | 10-Aug-26 09:00 | 20-Aug-26 17:00 | 248 Hours
Continuous |
1L274 (48s Pocaterra - 978s BCH Britt Creek) | maintenance | AB-BC |
| ALTALINK | 10-Aug-26 09:30 | 13-Aug-26 17:00 | 79.5 Hours
Continuous |
702L (137s Sedgewick - 757s Battle River) | Interphase spacers and pole replacements | |
| ATCO, ALTALINK | 10-Aug-26 10:00 | 13-Aug-26 16:30 | 78.5 Hours
Continuous |
7L702 (137s Sedgewick - 757s Battle River) | Interphase spacers and pole replacements | |
| ATCO | 10-Aug-26 10:00 | 14-Aug-26 17:30 | 103.5 Hours
Continuous |
959s SVC (959s Lanfine), 959s 921 (959s Lanfine) | DFR Upgrade / Replacement
SVC Transformer Maintenance Fire system inspection Install Blocking Switches Mechanical Maintenance & Capital BATTERY CHARGER COMPLETE TESTING @ LANFINE 959S SVC DC MOTOR |
|
| ALTALINK | 10-Aug-26 11:00 | 10-Aug-26 18:00 | 7 Hours
Daily |
77s 29 (77s Sagitawah) | trip test 77s29 | |
| ALTALINK | 10-Aug-26 11:00 | 13-Aug-26 16:30 | 77.5 Hours
Continuous |
71s 152 (71s Lamoureux), 71s 552 (71s Lamoureux), 71s 1052 (71s Lamoureux), 71s 952 (71s Lamoureux), 71s T1 (71s Lamoureux), 71s 138kV West Bus (71s Lamoureux) | Transformer maintenance, switch maintenance (71s13, 71s44, 71s45), breaker maintenance (71s1052) | |
| ALTALINK | 10-Aug-26 12:30 | 13-Aug-26 17:00 | 76.5 Hours
Continuous |
17s 85 (17s Benalto), 17s T2 (17s Benalto) | 17s85 CT replacement | |
| ATCO | 10-Aug-26 13:00 | 10-Aug-26 14:00 | 1 Hour
Continuous |
951s 1205 (951s Thickwood Hills) | PRC-005 Trip Coil testing, SOC ill open and close breaker (tests TC #1), Techs will isolate A protection tripping this breaker, TOC will open and close breaker (tests TC #2) | |
| ALTALINK | 10-Aug-26 14:00 | 18-Aug-26 17:00 | 195 Hours
Continuous |
275s T1 (275s Jenner) | Replace LV bushings, TC Maint, Cooper cutouts | |
| ATCO | 10-Aug-26 14:01 | 10-Aug-26 15:00 | 0.98 Hours
Continuous |
951s 1206 (951s Thickwood Hills) | PRC-005 Trip Coil testing, SOC ill open and close breaker (tests TC #1), Techs will isolate A protection tripping this breaker, TOC will open and close breaker (tests TC #2) | |
| ATCO | 10-Aug-26 15:00 | 10-Aug-26 16:00 | 1 Hour
Continuous |
951s 1213 (951s Thickwood Hills) | PRC-005 Trip Coil testing, SOC will open and close breaker (tests TC #1), Techs will isolate A protection tripping this breaker, TOC will open and close breaker (tests TC #2) | |
| ALTALINK | 11-Aug-26 06:30 | 11-Aug-26 12:30 | 6 Hours
Daily |
77s 40 (77s Sagitawah) | trip test 77s40 | |
| ALTALINK | 11-Aug-26 07:00 | 12-Aug-26 17:00 | 34 Hours
Continuous |
102s 552 (102s Langdon), 102s 252 (102s Langdon), 102s T4 (102s Langdon), 102s SVC (102s Langdon) | To install a config change on the MACH controls from the controls system upgrade. During testing it was found some settings required changing. This is to implement those changes. | |
| ALTALINK | 11-Aug-26 07:00 | 13-Aug-26 18:00 | 59 Hours
Continuous |
310p 1852 (310p Sundance) | Replace 310p1852 CT's | |
| ATCO | 11-Aug-26 09:00 | 14-Aug-26 17:00 | 80 Hours
Continuous |
834s 902T (834s Wesley Creek) | TRANSFORMER CLASS1 TAP CHANGER - 902T @ 834S
Investigate Heater Fail - 503 at 834S Wesley Creek |
|
| ATCO | 11-Aug-26 10:00 | 11-Aug-26 11:00 | 1 Hour
Continuous |
939s 1206 (939s Livock) | PRC-005 Trip Coil testing, | |
| ATCO | 11-Aug-26 11:00 | 11-Aug-26 12:00 | 1 Hour
Continuous |
939s 1207 (939s Livock) | PRC-005 Trip Coil testing, SOC will open and close breaker (tests TC #1), Techs will isolate A protection tripping this breaker, TOC will open and close breaker (tests TC #2) | |
| ATCO | 11-Aug-26 12:00 | 11-Aug-26 13:00 | 1 Hour
Continuous |
939s 1214 (939s Livock) | PRC-005 Trip Coil testing, SOC will open and close breaker (tests TC #1), Techs will isolate A protection tripping this breaker, TOC will open and close breaker (tests TC #2), | |
| ALTALINK | 11-Aug-26 12:31 | 11-Aug-26 18:00 | 5.48 Hours
Daily |
77s 57 (77s Sagitawah) | trip test 77s57 | |
| ATCO | 11-Aug-26 13:00 | 11-Aug-26 14:00 | 1 Hour
Continuous |
939s 1216 (939s Livock) | PRC-005 Trip Coil testing, SOC will open and close breaker (tests TC #1), Techs will isolate A protection tripping this breaker, TOC will open and close breaker (tests TC #2) | |
| SUNCOR | 12-Aug-26 09:00 | 15-Aug-26 20:00 | 83 Hours
Continuous |
29EDD-1 29EDD1s1052 (29EDD-1 Millennium) | 29EDD1S1052 Densimeter Replacement - No visibility outage, no line outage - BPC-26-017 - 300347749 | |
| EPCOR | 17-Aug-26 07:00 | 18-Aug-26 17:00 | 34 Hours
Continuous |
987s T3 (987s Clover Bar), 987s C2407 (987s Clover Bar) | Cloverbar: TX3, Relay Maintenance | |
| ENMAX, ALTALINK | 17-Aug-26 08:00 | 17-Aug-26 12:00 | 4 Hours
Continuous |
21.80L (42s Sarcee - SS-21), 21B138-21.80 (SS-21) | HV Breaker SF6 Gas Sample - 21B138-21.80 | |
| ALTALINK | 17-Aug-26 08:00 | 20-Aug-26 17:00 | 81 Hours
Continuous |
310p 1252 (310p Sundance), 310p 1152 (310p Sundance) | Replace 310p1152 BKR CT's and repair switch 310p11A. | |
| ALTALINK, EPCOR | 17-Aug-26 09:30 | 22-Aug-26 17:00 | 127.5 Hours
Continuous |
920L (71s Lamoureux - 557s Castle Downs), 557s CD2405 (557s Castle Downs), 557s CD2404 (557s Castle Downs) | 920LE/Castledowns: CT/CVT Doble and Surge Arrestor LCR | |
| ALTALINK, EPCOR | 17-Aug-26 09:30 | 22-Aug-26 17:00 | 127.5 Hours
Continuous |
920L (71s Lamoureux - 557s Castle Downs) | 920LE/Castledowns: CT/CVT Doble and Surge Arrestor LCR | |
| SUNCOR | 17-Aug-26 10:00 | 17-Aug-26 12:59 | 2.98 Hours
Continuous |
29EDD-1 29EDD1s1052 (29EDD-1 Millennium) | 29EDD1 / X260B2 SOUTH BUS PRC-005 / Relay Test -Trip open 29EDD1s1052 (29EDD-1 Millennium) - 450338057 In conjunction with Outage 1-00529388 |
|
| ATCO, ALTALINK | 17-Aug-26 10:00 | 20-Aug-26 16:30 | 78.5 Hours
Continuous |
7L702 (137s Sedgewick - 757s Battle River) | Interphase spacers and pole replacements | |
| ALTALINK | 17-Aug-26 10:00 | 20-Aug-26 16:30 | 78.5 Hours
Continuous |
702L (137s Sedgewick - 757s Battle River) | Interphase spacers and pole replacements | |
| ALTALINK | 17-Aug-26 11:00 | 20-Aug-26 16:45 | 77.75 Hours
Continuous |
71s 1752 (71s Lamoureux), 71s 1452 (71s Lamoureux), 71s 1352 (71s Lamoureux), 71s 32 (71s Lamoureux), 71s T2 (71s Lamoureux), 71s 240kV East Bus (71s Lamoureux) | Multiple switch repair/replacement and maintenance
71s36, 71s37, 71s46, 71s47 |
|
| ALTALINK | 17-Aug-26 12:00 | 20-Aug-26 17:00 | 77 Hours
Continuous |
777L (48s Pocaterra - 245s Seebe), 245s 777X (245s Seebe) | 245s777X 138kV CT replacement | AB-BC |
| ALTALINK | 17-Aug-26 12:30 | 20-Aug-26 17:00 | 76.5 Hours
Continuous |
320p 652 (320p Keephills) | Replace 320p652 external CT's | |
| SUNCOR | 17-Aug-26 13:00 | 17-Aug-26 17:00 | 4 Hours
Continuous |
29EDD-1 29EDD1s852 (29EDD-1 Millennium) | 29EDD1 / X260B2 SOUTH BUS PRC-005 / Relay Test -Trip open 29EDD1s852 (29EDD-1 Millennium) - 450338057 In conjunction with Outage 1-00529388, following outage 1-00529393 |
|
| ATCO | 17-Aug-26 13:00 | 20-Aug-26 13:00 | 72 Hours
Continuous |
9L10 (876s Brintnell - 939s Livock), 939s 903T (939s Livock), 939s 910A (939s Livock) | PRC-005 - SPR TESTING - TRANSFORMER 903T @ 939S Repair and adjust 910A @ 939S APL Repalce OLTC Filters, 903T @ 939S Livock |
|
| ATCO | 17-Aug-26 13:00 | 20-Aug-26 13:00 | 72 Hours
Continuous |
828s 702 (828s Sulphur Point), 7L93 (828s Sulphur Point - 930s Arcenciel) | BREAKER SF6 LTB145D1/B COMPLETE TESTING - 702 @ 828S
SLD notes that 7L93 relays should be on alt settings at 828S Sulphur Point |
|
| ALTALINK | 17-Aug-26 14:00 | 20-Aug-26 16:30 | 74.5 Hours
Continuous |
574s T1 (574s Nilrem) | Transformer maintenance | |
| ALTALINK | 18-Aug-26 07:00 | 18-Aug-26 18:00 | 10.5 Hours
Daily |
1112L (89s Ellerslie - 289s Saunders Lake) | transmission line maintenance | |
| ALTALINK, ATCO, FMGW | 18-Aug-26 08:00 | 19-Aug-26 17:00 | 33 Hours
Continuous |
964AL (1024s Granlea - 964L tap), 1024s PT-6001 (1024s Granlea), 1024s PT-6002 (1024s Granlea), 1024s 952-600001 (1024s Granlea), 1024s PS-6005 (1024s Granlea), 1024s PS-6006 (1024s Granlea), 1024s PS-6007 (1024s Granlea), 1024s PS-6008 (1024s Granlea), 1024s 489-600201 (1024s Granlea) | maintenance activities (testing and inspection) of electrical equipment | |
| SUNCOR | 21-Aug-26 10:00 | 21-Aug-26 11:59 | 1.98 Hours
Continuous |
29EDD-1 952-103 (29EDD-1 Millennium) | 29EDD1 / X260B1 SOUTH BUS PRC-005 / Relay Test - Trip Open 952-103 (29EDD-1 Millennium) - 450338059 In conjunction with outage 1-00529405 |
|
| SUNCOR | 21-Aug-26 12:00 | 21-Aug-26 13:59 | 1.98 Hours
Continuous |
29EDD-1 952-106 (29EDD-1 Millennium) | 29EDD1 / X260B1 SOUTH BUS PRC-005 / Relay Test - Trip Open 952-106 (29EDD-1 Millennium) - 450338059 In conjunction with outage 1-00529405, following outage 1-00529407 |
|
| SUNCOR | 21-Aug-26 14:00 | 21-Aug-26 16:00 | 2 Hours
Continuous |
29EDD-1 29EDD1s652 (29EDD-1 Millennium) | 29EDD1 / X260B1 SOUTH BUS PRC-005 / Relay Test - Trip Open 29EDD1s652 (29EDD-1 Millennium) - 450338059 In conjunction with outage 1-00529405, following outage 1-00529409 |
|
| ALTALINK | 23-Aug-26 11:30 | 23-Aug-26 17:30 | 6 Hours
Daily |
77s 29 (77s Sagitawah) | trip test 77s29 | |
| ALTALINK | 24-Aug-26 06:30 | 24-Aug-26 12:30 | 6 Hours
Daily |
77s 40 (77s Sagitawah) | trip test 77s40 | |
| EPCOR | 24-Aug-26 07:00 | 30-Aug-26 17:00 | 154 Hours
Continuous |
557s T2 (557s Castle Downs), 557s CD2403 (557s Castle Downs), 557s CD2404 (557s Castle Downs), 557s CDAB2 (557s Castle Downs) | Castledowns: TX2 tap changer and disconnect switch maintenance | |
| ALTALINK, BCH | 24-Aug-26 08:00 | 01-Sep-26 17:00 | 201 Hours
Continuous |
Path 1 (AIES Islanding), 1201L (520s Bennett - BCH Cranbrook), 5L94 (BCH Cranbrook - 520s Bennett) | South Crew will be doing Insulator and guy wire replacements | AB-BC |
| ALTALINK, BCH | 24-Aug-26 08:00 | 01-Sep-26 17:00 | 201 Hours
Continuous |
799s 786W (799s Coleman), 786L (799s Coleman - BCH Natal) | Opened because 1201L is out of service. | AB-BC |
| ALTALINK, BHE | 24-Aug-26 08:00 | 01-Sep-26 17:00 | 201 Hours
Continuous |
MATL (120s Picture Butte - Montana) | align with 1201L outage | AB-MATL |
| ALTALINK, EPCOR | 24-Aug-26 09:00 | 25-Aug-26 17:00 | 32 Hours
Continuous |
908AL (52S East Industrial - 908L tap), 52s T2 (52s East Industrial), 52s E2402 (52s East Industrial) | East Industrial/908LW: CVT JB Rewiring | |
| ALTALINK | 24-Aug-26 09:00 | 25-Aug-26 18:00 | 33 Hours
Continuous |
908L (38s East Edmonton - 908AL tap), 908L (89s Ellerslie - 908AL tap) | East Industrial/908LW: CVT JB Rewiring | |
| BCH | 24-Aug-26 09:00 | 01-Sep-26 17:00 | 200 Hours
Continuous |
5L92 (BCH Cranbrook - BCH Selkirk) | replace spacers, markerballs and insulators | AB-BC |
| ALTALINK | 24-Aug-26 11:30 | 27-Aug-26 17:00 | 77.5 Hours
Continuous |
71s 1452 (71s Lamoureux), 71s 1352 (71s Lamoureux), 71s 997E (71s Lamoureux) | switch replacement 71s997E, switch repair 71s46
|
|
| ALTALINK | 24-Aug-26 12:31 | 24-Aug-26 18:00 | 5.48 Hours
Daily |
77s 57 (77s Sagitawah) | trip test 77s57 | |
| ALTALINK | 24-Aug-26 13:00 | 28-Aug-26 17:00 | 100 Hours
Continuous |
28s R1 (28s West Brooks) | 28sR1 leak category 5, Doble R1
28s44 PRC5 (no first trip) |
|
| ATCO | 24-Aug-26 13:00 | 04-Sep-26 13:00 | 264 Hours
Continuous |
7L228 (845s Big Mountain - 7L20 tap), 7L20 (740s H.R. Milner - 810s Dome Cutbank) | 7L228D2 Line Switch Failure Replacement
Install BKR 703 |
|
| EPCOR | 26-Aug-26 07:00 | 30-Aug-26 17:00 | 106 Hours
Continuous |
52s T1 (52s East Industrial) | East Industrial: TX1 Doble | |
| ENMAX, ALTALINK | 26-Aug-26 08:00 | 27-Aug-26 16:00 | 32 Hours
Continuous |
833L (SS-2 - SS-12), 2B138-D87 (SS-2), 2B138-D88 (SS-2) | Install ITBs - 2RLY138-D87-D88 (BMR4). Relay maint. | |
| ENMAX | 28-Aug-26 08:00 | 28-Aug-26 18:00 | 10 Hours
Continuous |
162.2TR (SS-162), 138kV South Bus (SS-162), 240kV South Bus (SS-162) | Summer Substation Washing | |
| EPCOR, ALTALINK | 31-Aug-26 07:00 | 13-Sep-26 17:00 | 322 Hours
Continuous |
EP 803s T3 (EP 803s Lambton), EP 803s L2403 (EP 803s Lambton), EP 803s L2405 (EP 803s Lambton), EP 803s L721 (EP 803s Lambton), 72LS24 (EP 803s Lambton - Strathcona), 72LH8 (EP 803s Lambton - EP Hardisty), H726 (EP Hardisty), S724 (Strathcona) | Lambton: LDS14 LCR and L721 Breaker Maintenance (Min Oil) and TX3 Zone Doble and L2405 Breaker Maintenance (SF6) and LDS12 Drive Pipe Repair and TX3 Relay Maintenance | |
| ATCO | 31-Aug-26 09:30 | 04-Sep-26 17:30 | 104 Hours
Continuous |
801s 902 (801s Anderson) | BREAKER MIN OIL HLR COMPLETE TESTING | |
| ATCO | 31-Aug-26 10:00 | 03-Sep-26 15:00 | 77 Hours
Continuous |
813s 906 (813s Little Smoky) | BREAKER SF6 HGF COMPLETE TESTING - 906 @ 813S
Breaker 906 Counter Inoperable - Correct Counter Arm at 813s Little Smoky |
|
| ATCO | 31-Aug-26 10:00 | 03-Sep-26 16:00 | 78 Hours
Continuous |
826s 902T (826s Marguerite Lake) | transformer maintenance | |
| ALTALINK | 31-Aug-26 11:00 | 03-Sep-26 17:00 | 78 Hours
Continuous |
71s 1752 (71s Lamoureux), 71s 1652 (71s Lamoureux), 71s 942 (71s Lamoureux), 942L (71s Lamoureux - 681s Bannerman) | Switch replacement 71s942
Switch repair 71s49, 71s50 |
|
| ALTALINK | 01-Sep-26 08:00 | 02-Sep-26 11:30 | 27.5 Hours
Continuous |
650s 252 (650s Hansman Lake) | Adding a maintenance switch to 650s252 | |
| ALTALINK | 01-Sep-26 08:30 | 01-Sep-26 17:00 | 8.5 Hours
Daily |
17s 4 (17s Benalto) | PRC5 breaker maintenance & First Trip | |
| ATCO, ALTALINK | 01-Sep-26 09:00 | 03-Sep-26 17:30 | 56.5 Hours
Continuous |
9L961 (13s Deerland - 825s Whitefish Lake) | 9L961L structure 3 Replace synthetic insulators, pins & cotter keys | |
| BCH | 02-Sep-26 09:00 | 21-Sep-26 13:00 | 460 Hours
Continuous |
5L96 (BCH Selkirk - BCH Vaseux Lake) | maintenance. BC maintenance does not affect the Alberta ATC | AB-BC |
| ALTALINK | 02-Sep-26 12:30 | 03-Sep-26 14:00 | 25.5 Hours
Continuous |
650s 352 (650s Hansman Lake) | Adding a maintenance switch to 650s352 | |
| EPCOR | 03-Sep-26 07:00 | 03-Sep-26 17:00 | 10 Hours
Continuous |
987s C2405 (987s Clover Bar) | Cloverbar: C2405 Capacitor Nameplate Pictures | |
| SUNCOR | 06-Sep-26 08:00 | 01-Oct-26 20:00 | 612 Hours
Continuous |
29EDD-61 29PT-653 (29EDD-61 Stony Island) | 30PD-33 IPB PRESSURE LOW - Requires 29PT-653 to be isolated - 300691659 | |
| EPCOR | 07-Sep-26 07:00 | 11-Sep-26 17:00 | 106 Hours
Continuous |
987s GT2 (987s Clover Bar), 987s CGB2 (987s Clover Bar) | Cloverbar: | |
| EPCOR | 08-Sep-26 07:00 | 13-Sep-26 17:00 | 130 Hours
Continuous |
72PM25 (Poundmaker - Meadowlark), PM2402 (Poundmaker), PM2403 (Poundmaker), PM721 (Poundmaker), T4 (Poundmaker) | Poundmaker: TX4 Doble | |
| EPCOR | 08-Sep-26 07:00 | 23-Oct-26 17:00 | 1,090 Hours
Continuous |
805s T4 (805s Jasper), EP 805s J2405 (EP 805s Jasper), EP 805s J2406 (EP 805s Jasper) | Jasper: J2406/JDS10 Replacement LCR | |
| ENMAX, ALTALINK | 08-Sep-26 08:00 | 08-Sep-26 16:00 | 8 Hours
Continuous |
1065L (74s Janet - 102s Langdon) | Fall transmission pothead washing | |
| ENMAX, ALTALINK | 08-Sep-26 08:00 | 08-Sep-26 16:00 | 8 Hours
Continuous |
1064L (74s Janet - 102s Langdon) | Fall transmission pothead washing | |
| ATCO | 08-Sep-26 08:00 | 11-Sep-26 16:00 | 80 Hours
Continuous |
7L228 (845s Big Mountain - 7L20 tap), 2091s 7L228D3 (2091s Thornton) | ET 1138135 7L228D2 Line Switch Failure Replacement
- Remove 7L228D2 and jumper out permanently. - Rename 7L228D3 to D2. |
|
| CNRL, ATCO | 08-Sep-26 08:00 | 13-Sep-26 16:00 | 128 Hours
Continuous |
842s 75-1902 (842s Horizon Upgrading), 842s 75-1903 (842s Horizon Upgrading), 75-PLH-903 (838s Horizon Mining - 842s Horizon Upgrading), 838s 75-BC-1911 (838s Horizon Mining), 838s 75-BC-1918 (838s Horizon Mining) | 5YR PMs of Breakers, Disconnects, and Protective Relays | |
| ALTALINK | 08-Sep-26 09:00 | 09-Sep-26 17:30 | 32.5 Hours
Continuous |
1202L (89s Ellerslie - 320p Keephills) | Transmission line maintenance | |
| ATCO | 08-Sep-26 10:00 | 22-Sep-26 17:30 | 343.5 Hours
Continuous |
930s Syn Condenser (930s Arcenciel) | - Level 4 service / overhaul by ABB - DFR replacement |
|
| ATCO | 08-Sep-26 10:00 | 10-Dec-26 16:00 | 2,239 Hours
Continuous |
2015s 902 (2015s Yeo) | Remove circuit breaker for use at 2102S Armistead. New breaker to be installed at 2015S Yeo substation once received from manufacturer. | |
| ENMAX, ALTALINK | 08-Sep-26 12:00 | 08-Sep-26 18:00 | 6 Hours
Continuous |
28.80L (42s Sarcee - SS-28), 28.2TR (SS-28) | Fall Substation Washing. Reversing Switch Check - 28.2-TC | |
| ALTALINK | 08-Sep-26 12:30 | 11-Sep-26 17:00 | 76.5 Hours
Continuous |
370s 2152 (370s North Lethbridge), 370s T3 (370s North Lethbridge) | 370sT3 Leak repair, major TC maint. PRC5 | |
| ALTALINK | 08-Sep-26 23:00 | 09-Sep-26 07:00 | 8 Hours
Continuous |
250p 2 (250p Bighorn Plant) | maintenance | |
| ALTALINK | 09-Sep-26 07:00 | 10-Sep-26 07:00 | 24 Hours
Continuous |
250p 1 (250p Bighorn Plant) | maintenance | |
| ENMAX, ALTALINK | 09-Sep-26 08:00 | 09-Sep-26 16:00 | 8 Hours
Continuous |
1064L (74s Janet - 102s Langdon) | Fall transmission pothead washing | |
| ENMAX, ALTALINK | 09-Sep-26 08:00 | 09-Sep-26 16:00 | 8 Hours
Continuous |
1065L (74s Janet - 102s Langdon) | Fall transmission pothead washing | |
| ENMAX, ALTALINK | 09-Sep-26 08:00 | 09-Sep-26 16:00 | 8 Hours
Continuous |
20.82L (SS-20 - SS-21), 21.80L (42s Sarcee - SS-21), 21.1TR (SS-21), 21.4TR (SS-21) | Fall Substation Washing. Altalink required to remove AML VT4 60S100 fuses | |
| ENMAX, ALTALINK | 10-Sep-26 08:00 | 10-Sep-26 16:00 | 8 Hours
Continuous |
50L (44s Bearspaw Plant - SS-21), 21.1C (SS-21), 21.2TR (SS-21) | Fall Substation Washing | |
| ALTALINK, EPCOR | 10-Sep-26 08:00 | 10-Sep-26 17:30 | 9.5 Hours
Continuous |
1209L (89s Ellerslie - 330p Genesee) | 1209L Structure 45 and 145, Change saddles and pins. | |
| ALTALINK | 10-Sep-26 19:00 | 15-Sep-26 12:00 | 113 Hours
Continuous |
1141L (1172s Laramide - 237s Foothills) | End to end testing with Laramide 1172s | |
| ATCO, CNRL | 11-Sep-26 08:00 | 14-Sep-26 16:00 | 80 Hours
Continuous |
838s 75-SD-901 (838s Horizon Mining) | SEL-411L Firmware Update and Testing, and Breaker and Disconnect Testing | |
| ENMAX | 12-Sep-26 08:00 | 12-Sep-26 18:00 | 10 Hours
Continuous |
7.84L (SS-7 - SS-36), 36B138-36BT3 (SS-36), 36.1TR (SS-36), 36.3TR (SS-36), 36B138-36.81 (SS-36) | Fall Substation Washing | |
| CNRL | 12-Sep-26 08:00 | 20-Sep-26 16:00 | 200 Hours
Continuous |
842s 75-TR-4701 (842s Horizon Upgrading), 842s 75-1903 (842s Horizon Upgrading), 842s 75-1904 (842s Horizon Upgrading) | 5YR PMs of Transformer, Breakers, Disconnects, and Protective Relays | |
| EPCOR | 14-Sep-26 07:00 | 20-Sep-26 17:00 | 154 Hours
Continuous |
EP 803s L2402 (EP 803s Lambton) | Lambton: L2402 (Min Oil) Breaker Maintenance and CT Doble | |
| EPCOR | 14-Sep-26 07:00 | 21-Sep-26 17:00 | 178 Hours
Continuous |
987s GT3 (987s Clover Bar), 987s CGB3 (987s Clover Bar) | Cloverbar: | |
| ALTALINK, EPCOR | 14-Sep-26 09:30 | 17-Sep-26 17:00 | 79.5 Hours
Continuous |
920L (37s North Calder - 557s Castle Downs), 557s CD2401 (557s Castle Downs), 557s CD2403 (557s Castle Downs) | 920LW/Castledowns: Surge Arrestor LCR | |
| ALTALINK, EPCOR | 14-Sep-26 09:30 | 17-Sep-26 17:00 | 79.5 Hours
Continuous |
920L (37s North Calder - 557s Castle Downs) | 920LW/Castledowns: Surge Arrestor LCR | |
| ATCO | 14-Sep-26 10:00 | 28-Sep-26 17:30 | 343.5 Hours
Continuous |
840s 901T (840s McNeill Station), 840s 701 (840s McNeill Station), 840s 901 (840s McNeill Station), 840s 701T (840s McNeill Station) | Replace 901T bushings
901T Oil Leak Absorption Repairs At 840s McNeill TRANSFORMER CLASS1 MAJOR TESTING - 901T @ 840S TRANSFORMER CLASS1 TAP CHANGER - 901T @ 840S FIRE SUPPRESSION SYSTEM RE-CERTIFICATION @ MCNEILL 840S PRC testing DFR Replacement |
AB-SK |
| ALTALINK | 14-Sep-26 12:30 | 17-Sep-26 17:00 | 76.5 Hours
Continuous |
71s 452 (71s Lamoureux), 71s 852 (71s Lamoureux), 71s 708N (71s Lamoureux), 71s 31 (71s Lamoureux), 71s T2 (71s Lamoureux), 71s 138kV East Bus (71s Lamoureux) | 138kV switch repairs 71s8, 71s42, 71s708N | |
| ALTALINK | 15-Sep-26 07:00 | 16-Sep-26 18:00 | 35 Hours
Continuous |
691L (74s Janet - 419s Chestermere) | Foundation installation on structure 9 & 9A. | |
| ALTALINK | 15-Sep-26 07:30 | 15-Sep-26 12:00 | 4.5 Hours
Continuous |
927L (102s Langdon - 356s Milo), 102s 6652 (102s Langdon), 102s 6552 (102s Langdon), 356s 927 (356s Milo) | CT cutovers to new DLR protections LTO testing to RAS protections | |
| ATCO, CNRL | 15-Sep-26 08:00 | 19-Sep-26 16:00 | 104 Hours
Continuous |
838s 75-SD-902 (838s Horizon Mining) | SEL-411L Firmware Update and Testing, and Breaker and Disconnect Testing | |
| ALTALINK | 15-Sep-26 08:30 | 15-Sep-26 16:30 | 8 Hours
Continuous |
264s 352 (264s Elkwater) | CT testing | |
| ALTALINK, Lethbridge | 15-Sep-26 09:00 | 24-Sep-26 17:30 | 224.5 Hours
Continuous |
618s 725 (618s Riverbend), 725AL (618s Riverbend - 725L tap), 725L (111s Coalbanks - 725AL tap), 725L (674s Bowron - 725AL tap) | Outage required to replace 674s12-Disconnect Switch and 674sPT5-CVT | |
| ALTALINK | 15-Sep-26 12:30 | 15-Sep-26 15:30 | 3.98 Hours
Continuous |
924L (102s Langdon - 356s Milo), 102s 6952 (102s Langdon), 102s 6852 (102s Langdon), 356s 924 (356s Milo) | CT cutovers to new DLR protections LTO testing to RAS protections | |
| CNRL | 16-Sep-26 08:00 | 20-Sep-26 16:00 | 104 Hours
Continuous |
842s 75-1904 (842s Horizon Upgrading), 842s 75-1905 (842s Horizon Upgrading), 842s 75-TR-7701 (842s Horizon Upgrading) | 5YR PMs of Transformer, Breakers, Disconnects, and Protective Relays | |
| ALTALINK | 16-Sep-26 08:30 | 16-Sep-26 16:30 | 8 Hours
Continuous |
264s 452 (264s Elkwater) | CT testing | |
| ENMAX, ALTALINK | 16-Sep-26 12:00 | 16-Sep-26 18:00 | 6 Hours
Continuous |
23.80L (74s Janet - SS-23), 23.4TR (SS-23) | Fall Substation Washing | |
| ALTALINK | 16-Sep-26 23:30 | 17-Sep-26 02:30 | 3 Hours
Continuous |
62s 1 (62s Brazeau Plant) | maintenence | |
| ALTALINK | 17-Sep-26 03:30 | 17-Sep-26 06:30 | 3 Hours
Continuous |
62s 2 (62s Brazeau Plant) | maintenence | |
| ALTALINK | 17-Sep-26 08:00 | 17-Sep-26 12:30 | 4.5 Hours
Continuous |
33s 1 (33s Spray) | testing | |
| ALTALINK | 17-Sep-26 08:30 | 17-Sep-26 16:30 | 8 Hours
Continuous |
264s 252 (264s Elkwater) | CT testing | |
| BCH, BPA | 17-Sep-26 09:00 | 17-Sep-26 17:00 | 8 Hours
Continuous |
5L51 (BPA Custer - BCH Ingledow) | maintenance | AB-BC |
| ALTALINK | 17-Sep-26 13:00 | 17-Sep-26 17:00 | 4 Hours
Continuous |
33s 2 (33s Spray) | testing | |
| ENMAX, ALTALINK | 19-Sep-26 07:00 | 19-Sep-26 12:00 | 5 Hours
Continuous |
771L (SS-47 - SS-162), 162B138-RB82 (SS-162), 47.1TR (SS-47), 47B138-771/1 (SS-47), 47B138-771 (SS-47), 47.2TR (SS-47), 162B138-RB81 (SS-162) | Summer Substation Washing 162SUB, 138kV, 162MD138-771 | |
| ALTALINK | 21-Sep-26 07:00 | 28-Sep-26 18:00 | 179 Hours
Continuous |
691L (74s Janet - 419s Chestermere) | Line move for structures 4-12. | |
| CNRL | 21-Sep-26 08:00 | 28-Sep-26 16:00 | 176 Hours
Continuous |
842s 75-1901 (842s Horizon Upgrading), 842s 75-1905 (842s Horizon Upgrading), 842s 75-1906 (842s Horizon Upgrading), 842s 75-TR-5701 (842s Horizon Upgrading), 842s 75-TR-8701 (842s Horizon Upgrading) | 5YR PMs of Transformer, Breakers, Disconnects, and Protective Relays | |
| Syncrude | 21-Sep-26 08:00 | 06-Oct-26 16:00 | 368 Hours
Continuous |
34 (Aurora), 33B (Aurora), 34A (Aurora), 89-37 (Aurora), G21 (Aurora) | Zone 3 6yr PM | |
| ATCO | 21-Sep-26 10:00 | 22-Sep-26 16:00 | 30 Hours
Continuous |
815s 702 (815s Goodfare), 7L07 (790s Poplar Hill - 815s Goodfare) | BREAKER SF6 LTB145D1/B COMPLETE TESTING - 702 @ 815S | |
| ATCO | 21-Sep-26 10:00 | 24-Sep-26 16:00 | 78 Hours
Continuous |
888s 906 (888s Dover) | 21B/9L74 relay replacement. Cutover breaker and CT to new protection | |
| ALTALINK | 21-Sep-26 13:30 | 22-Sep-26 12:00 | 22.5 Hours
Continuous |
251s 1352 (251s Whitla) | 251s1352 HPL Major Maintenance. | |
| EPCOR | 22-Sep-26 07:00 | 25-Sep-26 17:00 | 82 Hours
Continuous |
987s GT1 (987s Clover Bar), 987s SST2 (987s Clover Bar), 987s CS2 (987s Clover Bar), 987s CGB1 (987s Clover Bar), 987s CCP7214 (987s Clover Bar), 987s CC24 (987s Clover Bar), 987s CH724 (987s Clover Bar), 987s CK726 (987s Clover Bar), 987s 72kV Bus 4 (987s Clover Bar) | Cloverbar: , SST2, BUS 4 Outage. CDS18 Disconnect Replacement | |
| ATCO, CNRL | 22-Sep-26 08:00 | 01-Oct-26 16:00 | 224 Hours
Continuous |
838s 75-BC-1917 (838s Horizon Mining), 838s 75-BC-1916 (838s Horizon Mining), 838s 75-TR-2801 (838s Horizon Mining) | Upgrade 75-RPX-2801B From SEL 387 to SEL 487, Transformer, Breaker and Disconnect testing | |
| ALTALINK | 22-Sep-26 11:00 | 23-Sep-26 13:00 | 26 Hours
Continuous |
251s 1452 (251s Whitla) | 251s1452 HPL Major Maintenance | |
| ALTALINK, WPLP | 23-Sep-26 09:00 | 23-Sep-26 17:00 | 8 Hours
Daily |
268s 268 (268s Whitecourt), 268s 503 (268s Whitecourt), 503L (268s Whitecourt - 323s Whitecourt Power) | 268s268 Breaker Maint. and heater replacement | |
| SUNCOR | 24-Sep-26 08:00 | 05-Oct-26 18:00 | 346 Hours
Continuous |
29EDD-63 29PT-179 (29EDD-63 Firebag Co-Gen), 29PL7-2 (29EDD-18 Firebag - 29EDD-63), 29EDD-63 30-252-11301 (29EDD-63), 29EDD-63 91-152-500201 (29EDD-63), 29EDD-18 29-752-105 (29EDD-18 Firebag), 29EDD-18 29-752-104 (29EDD-18 Firebag) | FIREBAG: Replace air bladder on 29PT-179, test 29PT-179, and execute 29PT-179 T60 replacement | |
| ATCO | 25-Sep-26 10:00 | 28-Sep-26 16:00 | 78 Hours
Continuous |
888s 905 (888s Dover) | 21B/9L74 relay replacement. Cutover breaker and CT to new protection | |
| ENMAX, ALTALINK | 27-Sep-26 08:30 | 09-Oct-26 14:00 | 293.5 Hours
Continuous |
37.2TR (SS-37), 37.82L (74s Janet - SS-37) | HV SW Replacement. 37SW85, 37SW86, 37SW89 | |
| ALTALINK | 28-Sep-26 07:00 | 08-Oct-26 17:00 | 250 Hours
Continuous |
510s 2652 (510s Sunnybrook), 510s 2752 (510s Sunnybrook), AML 511s 4852 (AML 511s Crossings), AML 511s 4952 (AML 511s Crossings), 1325L (510s Sunnybrook - AML 511s Crossings) | Annual Valve Hall Maintenance, PRC Tx Maintenance, Doble Testing of the Transformers, PRC Relay Maintenance, Annual Yard Inspections, TDC settings changes, VCS Maintenance | |
| ATCO | 28-Sep-26 08:00 | 05-Oct-26 16:00 | 176 Hours
Continuous |
7L44 (749s Flyingshot Lake - 845s Big Mountain) | Changing str 71,72,73 and 74 for high load move line raise | |
| ALTALINK, TRANSALTA, Lethbridge | 28-Sep-26 09:00 | 28-Sep-26 15:00 | 6 Hours
Continuous |
15s 725 (15s Fort Macleod), 725BL (240s McBride Lake - 725L tap), 725L (15s Fort MacLeod - 725BL tap), 725L (674s Bowron - 725BL tap) | Outage required to create open point 'A' on 725L to keep 240s online | |
| SUNCOR | 28-Sep-26 09:00 | 04-Oct-26 20:00 | 155 Hours
Continuous |
29EDD-34 260kV Bus 29PP-45 (29EDD-34) | 29EDD34 29PP45 A,C phase rebuild bus and supports that were removed as part of the 29PT-224 outage. |
|
| Lethbridge | 28-Sep-26 09:00 | 15-Oct-26 17:00 | 416 Hours
Continuous |
674s 1 (674s Bowron), 725LW (674s Bowron - 725BL tap) | Line outage required on 725LW at 674s to replace 674s1-Manual Airbreak Switch and replace 674s2 and 674s6 PT's | |
| ATCO | 28-Sep-26 10:00 | 02-Oct-26 17:30 | 103.5 Hours
Continuous |
2029s ACF22 (2029s Heathfield), 2029s 1223 (2029s Heathfield) | PRC-005 - TRIP COIL TESTING - BREAKER 1223 @ 2029S BREAKER SF6 3AP4FI MAINTENANCE - 1223 @ 2029S ACF22 Breaker low SF6 (breaker 1223) @2029S Heathfield FILTER BANK AC MAINTENANCE @ HEATHFIELD 2029S ACF22 |
|
| ALTALINK, Lethbridge | 28-Sep-26 14:05 | 15-Oct-26 18:05 | 412 Hours
Continuous |
725L (674s Bowron - 725BL tap) | Lethbridge outage required to replace 674s1-Disconnect Switch, 674sPT4-CVT, 674sPTB2-3phase CVT's, new screw piles and structure for 674sPTB2-CVT's | |
| ENMAX, ALTALINK | 29-Sep-26 08:00 | 29-Sep-26 17:30 | 9.5 Hours
Daily |
1109L (SS-25 - SS-65) | 1109L
Structure 15 Top Phase conductor Repair |
|
| ENMAX, ALTALINK | 29-Sep-26 08:00 | 29-Sep-26 17:30 | 9.5 Hours
Continuous |
1109L (SS-25 - SS-65) | Altalink outage. Remove 1109L from service to repair the top phase on Structure #15 | |
| ALTALINK | 29-Sep-26 08:30 | 29-Sep-26 15:30 | 7 Hours
Daily |
122s T1 (122s Alberta Newsprint) | Repair leaking PRD on T1 and clean leak mitigation materials | |
| ENMAX, ALTALINK | 29-Sep-26 08:30 | 29-Sep-26 17:30 | 9 Hours
Continuous |
1080L (SS-25 - SS-65) | Altalink outage. Crews will be working within close proximity on 1109L | |
| ALTALINK | 01-Oct-26 08:00 | 01-Oct-26 18:00 | 10 Hours
Daily |
1002L (163s Amoco Empress - 275s Jenner) | 1002L - Replace top phase spacer on STR67
|
|
| ALTALINK | 01-Oct-26 09:00 | 01-Oct-26 17:30 | 8.5 Hours
Continuous |
1043L (320p Keephills - 367s Harry Smith) | 1043L111 Conductor repair | |
| EPCOR | 05-Oct-26 07:00 | 18-Oct-26 17:00 | 322 Hours
Continuous |
CV5 (EP 511s Victoria - 557s Castle Downs) | CV5/TX5: Manhole Inspections and Maintenance and 72kV Breaker Fail Protection Upgrade Cutovers and Commissioning | |
| ALTALINK | 05-Oct-26 08:30 | 28-Nov-26 06:30 | 1,295 Hours
Continuous |
62s 2 (62s Brazeau Plant) | maintenence | |
| ATCO | 05-Oct-26 09:00 | 07-Oct-26 17:30 | 56.5 Hours
Continuous |
2029s 1301 (2029s Heathfield) | DC HIGH SPEED SWITCH MAINTENANCE - 1301 @ 2029S **EATL will need to run in P1 DMR Return while 1301 is out of service** AESO PLEASE ADD SWITCHED INTO DATABASE |
|
| ATCO | 05-Oct-26 10:00 | 08-Oct-26 16:00 | 78 Hours
Continuous |
9L74 (888s Dover - 960s Birchwood Creek) | 21B/9L74 relay three terminal line testing | |
| ATCO | 05-Oct-26 12:00 | 09-Oct-26 12:00 | 96 Hours
Continuous |
786s SVC (786s High Level) | ET 1136310 786S High Level SVC DFR Upgrade
SVC AIR COOLED MAINTENANCE @ HIGH LEVEL 786S |
|
| SUNCOR | 06-Oct-26 08:00 | 12-Oct-26 20:00 | 252 Hours
Continuous |
29EDD-2 29PT-3 (29EDD-2 Tar Island), 29PL6-22 (29EDD-1 Millennium - 29EDD-2 Tar Island) | 29EDD2;29PT-3, 29PL6-22 SYSTEM;PM 5y,10y |
|
| SUNCOR | 06-Oct-26 08:00 | 12-Oct-26 20:00 | 156 Hours
Continuous |
29EDD-2 29PT-3 (29EDD-2 Tar Island), 29PL6-22 (29EDD-1 Millennium - 29EDD-2 Tar Island) | 29EDD2; 29PP-2; 39PT-401 & 30PP-52 SYSTEM;PM 5y - 450504726; 29PT-3 Bushing Replacement; 29EDD2;39PT-401 & 30PP-52 SYSTEM;PM 5y |
|
| ATCO, ALTALINK | 07-Oct-26 08:00 | 07-Oct-26 17:00 | 9 Hours
Continuous |
760L (760AL tap - 7LA760 tap) | install interphase spacers | |
| ALTALINK | 07-Oct-26 08:00 | 07-Oct-26 17:00 | 9 Hours
Daily |
801L (62s Brazeau Plant - 294s Brazeau Plant Outlet Works) | 801L replace glass on STR 65 and 72 | |
| ALTALINK | 08-Oct-26 07:00 | 08-Oct-26 18:00 | 11 Hours
Continuous |
61s 202X (61s Lodgepole), 62s 202 (62s Brazeau Plant), 202L (61s Lodgepole - 62s Brazeau Plant) | Line Maintenance | |
| Syncrude | 10-Oct-26 08:00 | 28-Oct-26 16:00 | 440 Hours
Continuous |
1335 (Syncrude Mildred Lake), 134 (Syncrude Mildred Lake), 135 (Syncrude Mildred Lake), Mildred T1 (Syncrude Mildred Lake), Mildred T2 (Syncrude Mildred Lake), 2235 (Syncrude Mildred Lake), 234 (Syncrude Mildred Lake), 235 (Syncrude Mildred Lake), 3235 (Syncrude Mildred Lake), 335 (Syncrude Mildred Lake), 334 (Syncrude Mildred Lake), Mildred T3 (Syncrude Mildred Lake), Mildred T16 (Syncrude Mildred Lake), 1635 (Syncrude Mildred Lake), 1634 (Syncrude Mildred Lake), 1434 (Syncrude Mildred Lake), 1435 (Syncrude Mildred Lake), Mildred T14 (Syncrude Mildred Lake), Mildred T19 (Syncrude Mildred Lake), 1935 (Syncrude Mildred Lake), 1934 (Syncrude Mildred Lake), 814 (Syncrude Mildred Lake), 815 (Syncrude Mildred Lake), 816 (Syncrude Mildred Lake), Mildred Lake 72kV Bus B (Sycrude Mildred Lake), ML1 (D05 - Syncrude Mildred Lake), 914 (Syncrude Mildred Lake), 915 (Syncrude Mildred Lake), 916 (Syncrude Mildred Lake), 1224A (Syncrude Mildred Lake), 1224B (Syncrude Mildred Lake), 1225 (Syncrude Mildred Lake), D05 76 (D05), D05 76A (D05), D05 76B (D05) | SCL - Perform 72kV "B" Bus PM in Plant 31 at Mildred Lake. | |
| ATCO | 12-Oct-26 10:00 | 15-Oct-26 16:00 | 78 Hours
Continuous |
888s 906 (888s Dover) | 21A/9L74 relay replacement. Cutover breaker and CT to new protection | |
| ALTALINK | 12-Oct-26 12:00 | 16-Oct-26 13:00 | 97 Hours
Continuous |
602s T1 (602s Cold Creek) | Replace 25kv MOD switch 602s10 | |
| ATCO, ALTALINK | 13-Oct-26 09:00 | 17-Oct-26 17:30 | 104.5 Hours
Continuous |
986L (87s Gaetz - 972s Tinchebray) | 986L Interphase spacer work From Span 1 through 243 using HEC with a Helicopter | |
| ATCO, ALTALINK | 13-Oct-26 09:30 | 17-Oct-26 17:30 | 104 Hours
Continuous |
962L (87s Gaetz - 972s Tinchebray) | 962L Interphase spacer work From Span 1 through 243 Using HEC with a Helicopter | |
| ATCO, ALTALINK | 13-Oct-26 09:30 | 17-Oct-26 17:30 | 104 Hours
Continuous |
9L62 (87s Gaetz - 972s Tinchebray) | AltaLink Request: Interphase spacer work From Span 1 through 243 using HEC with a Helicopter. ATCO needs to enable the following RAS logics RAS 134 Logic 1b, RAS 134 Logic 2, RAS 211, RAS 215 , 973S RAS 134 , 615S RAS 134, 1045S RAS 134 |
|
| ATCO, ALTALINK | 13-Oct-26 09:30 | 17-Oct-26 17:30 | 104 Hours
Continuous |
9L86 (87s Gaetz - 972s Tinchebray) | AltaLink Request: Interphase spacer work From Span 1 through 243 using HEC with a Helicopter. ATCO needs to enable the following RAS logics RAS 134 Logic 1b, RAS 134 Logic 2, RAS 211, RAS 215 , 973S RAS 134 , 615S RAS 134, 1045S RAS 134 |
|
| ALTALINK | 15-Oct-26 08:00 | 15-Oct-26 18:00 | 10 Hours
Continuous |
158s 763N (158s Vauxhall), 28s 47 (28s West Brooks), 28s 31 (28s West Brooks), 447s 763A (447s Enchant), 447s 16 (447s Enchant), 763AL (447s Enchant - 763A1L tap), 763L (158s Vauxhall - 763AL tap), 763L (28s West Brooks - 763AL tap) | 447s27 Replace line VT. (Like for like replacement) | |
| ALTALINK, TRANSALTA, Lethbridge | 15-Oct-26 17:10 | 15-Oct-26 21:00 | 3.83 Hours
Continuous |
15s 725 (15s Fort Macleod), 725BL (240s McBride Lake - 725L tap), 725L (15s Fort MacLeod - 725BL tap), 725L (674s Bowron - 725BL tap) | to close 725L Open Point 'A' and restore 725L to normal | |
| ATCO | 16-Oct-26 10:00 | 19-Oct-26 16:00 | 78 Hours
Continuous |
888s 905 (888s Dover) | 21A/9L74 relay replacement. Cutover breaker and CT to new protection | |
| EPCOR | 19-Oct-26 07:00 | 11-Dec-26 17:00 | 1,283 Hours
Continuous |
814s T2 (814s Bellamy), BR722 (Rossdale), 814s B2402 (814s Bellamy), 814s B2406 (814s Bellamy) | Bellamy: TX2 Emergency Bushing Replacement | |
| ALTALINK, EPCOR | 19-Oct-26 09:30 | 25-Oct-26 17:00 | 151.5 Hours
Continuous |
908L (89s Ellerslie - 816s Petrolia) | Petrolia: 908LE Surge Arrestor and CVT LCR | |
| ALTALINK | 19-Oct-26 11:00 | 23-Oct-26 11:00 | 96 Hours
Continuous |
163s 1552 (163s Amoco Empress) | 1552 Breaker failure and control protection upgrade | |
| Syncrude | 23-Oct-26 08:00 | 06-Nov-26 16:00 | 345 Hours
Continuous |
11A (Aurora), 21A (Aurora), 31A (Aurora), 89-210 (Aurora), 89-51 (Aurora), T1 (Aurora), 211A (Aurora), 221A (Aurora), 260kV Bus 1 (Aurora), 72 kV Bus 1 (Aurora) | 6yr PM | |
| ALTALINK | 23-Oct-26 09:00 | 23-Oct-26 13:00 | 4 Hours
Continuous |
163s 1752 (163s Amoco Empress) | 11/1552 breaker fail trip testing | |
| ALTALINK, EPCOR | 26-Oct-26 07:00 | 30-Oct-26 17:00 | 106 Hours
Continuous |
909L (89s Ellerslie - 665s Dome), 665s D2401 (665s Dome), 665s D2404 (665s Dome), 72DS26 (665s Dome - Strathcona) | 909LE/Dome: Dome CVT LCR and 909LE Metering Upgrade | |
| EPCOR | 26-Oct-26 07:00 | 18-Dec-26 17:00 | 1,283 Hours
Continuous |
805s T3 (805s Jasper), EP 805s J2404 (EP 805s Jasper), EP 805s J2405 (EP 805s Jasper) | Jasper: J2404/JAB3/JDS9 Replacement LCR | |
| ENMAX, ALTALINK | 26-Oct-26 08:00 | 04-Nov-26 16:00 | 225 Hours
Continuous |
24.83L (74s Janet - SS-24) | Steel pole installation | |
| ENMAX, ALTALINK | 26-Oct-26 08:00 | 04-Nov-26 16:00 | 225 Hours
Continuous |
24.83L (74s Janet - SS-24), 74s 24.83X (74s Janet) | Enmax Steel pole installation | |
| ATCO | 26-Oct-26 08:00 | 13-Nov-26 17:00 | 442 Hours
Continuous |
806s 701T (806s Oldman River) | Telecommunications Upgrade, new UPS upgrades. | |
| ATCO | 26-Oct-26 09:00 | 26-Oct-26 17:30 | 32 Hours
Continuous |
757s 704 (757s Battle River) | BREAKER SF6 LTB145D1/B TESTING - 704 @ 757S PRC-005 - TRIP COIL TESTING - BREAKER 704 @ 757S |
|
| ALTALINK | 26-Oct-26 09:00 | 28-Oct-26 17:30 | 56.5 Hours
Continuous |
924L (102s Langdon - 356s Milo) | 924L192 Urgent repair Interphase spacer replacement | |
| ALTALINK, EPCOR | 26-Oct-26 09:00 | 30-Oct-26 17:30 | 104.5 Hours
Continuous |
89s 1052 (89s Ellerslie), 89s 1152 (89s Ellerslie), 909L (89s Ellerslie - 665s Dome) | 909LE/Dome: Dome CVT LCR and 909LE Metering Upgrade | |
| ATCO | 26-Oct-26 10:00 | 29-Oct-26 16:00 | 78 Hours
Continuous |
9L74 (888s Dover - 960s Birchwood Creek), 888s 905 (888s Dover), 888s 906 (888s Dover), 960s 901 (960s Birchwood Creek), 960s 902 (960s Birchwood Creek) | 21A/9L74 relay three terminal line testing | |
| ATCO, ALTALINK | 26-Oct-26 10:00 | 02-Nov-26 16:00 | 175 Hours
Continuous |
7L230 (69s North Barrhead - 888AL tap), 7L230 (743s Sarah Lake - 888AL tap) | Replace 7L230D1 disconnect switch | |
| ALTALINK | 26-Oct-26 11:00 | 30-Oct-26 11:00 | 96 Hours
Continuous |
163s 1252 (163s Amoco Empress) | 1252 Breaker failure & control protection upgrade | |
| ALTALINK | 27-Oct-26 07:00 | 27-Oct-26 17:00 | 10 Hours
Continuous |
AML 511s 5252 (AML 511s Crossings) | PRC Relay Maintenance on 5252 Siemens 6MD | |
| ALTALINK | 27-Oct-26 08:00 | 28-Oct-26 17:30 | 33.5 Hours
Continuous |
1037L (138s Windy Flats - 266s SC1), 1037L (237s Foothills - 266s SC1) | 1037L Install Vibration monitors and weather stations at Structure 285 and 334. | |
| ALTALINK | 27-Oct-26 08:30 | 30-Oct-26 16:30 | 80 Hours
Continuous |
836L (61s Lodgepole - 283s Violet Grove), 61s 836N (61s Lodgepole) | CT Replacement of CTs associated with 61s836N Breaker (CTL8) | |
| ALTALINK | 28-Oct-26 07:00 | 28-Oct-26 15:00 | 8 Hours
Continuous |
163s T1 (163s Amoco Empress) | Breaker Fail upgrade project: 11/1252 & 11/1552 breaker fail trip testing. Trip testing of 163s501, 163sXA, 163sXB | |
| ALTALINK | 28-Oct-26 07:00 | 28-Oct-26 15:00 | 8 Hours
Continuous |
AML 511s 5352 (AML 511s Crossings) | PRC Relay Maintenance on 5352 Siemens 6MD | |
| ALTALINK | 28-Oct-26 10:00 | 28-Oct-26 14:00 | 4 Hours
Continuous |
250p 1 (250p Bighorn Plant) | maintenance | |
| ALTALINK | 29-Oct-26 07:00 | 29-Oct-26 17:00 | 10 Hours
Continuous |
AML 511s 5052 (AML 511s Crossings) | PRC Mnt 0511DC ACF1 (s5052) 6MD66 CI | |
| ALTALINK | 29-Oct-26 08:00 | 31-Oct-26 18:00 | 58 Hours
Continuous |
927L (102s Langdon - 356s Milo) | 927L - (Urgent repair) Replace 2 Interphase spacers in span 188 | |
| ALTALINK | 29-Oct-26 10:00 | 29-Oct-26 14:00 | 4 Hours
Continuous |
250p 2 (250p Bighorn Plant) | maintenance | |
| ALTALINK | 30-Oct-26 09:00 | 30-Oct-26 13:00 | 4 Hours
Continuous |
163s 1552 (163s Amoco Empress) | 11/1252 Breaker Fail trip testing | |
| ALTALINK | 30-Oct-26 11:00 | 30-Oct-26 14:00 | 3 Hours
Continuous |
163s 1352 (163s Amoco Empress) | 11/1252 breaker fail trip testing | |
| ALTALINK, EPCOR | 02-Nov-26 07:00 | 13-Nov-26 17:00 | 274 Hours
Continuous |
909L (310p Sundance - 665s Dome), 665s D2403 (665s Dome) | Dome: 909LW/D2403, Metering Upgrade Cutovers and Commissioning | |
| ALTALINK | 03-Nov-26 07:00 | 03-Nov-26 17:00 | 10 Hours
Continuous |
510s 2552 (510s Sunnybrook) | PRC Relay Mnt 0510DC ACF1 (s2552) 6MD66 CI | |
| ALTALINK | 04-Nov-26 07:00 | 04-Nov-26 17:00 | 10 Hours
Continuous |
510s 1952 (510s Sunnybrook) | PRC Relay Mnt 0510DC ACF1 (s1952) 6MD66 CI | |
| ALTALINK | 05-Nov-26 03:30 | 05-Nov-26 06:30 | 3 Hours
Continuous |
62s 1 (62s Brazeau Plant) | maintenence | |
| ALTALINK | 05-Nov-26 07:00 | 05-Nov-26 17:00 | 10 Hours
Continuous |
510s 2052 (510s Sunnybrook) | PRC Relay Mnt 0510DC ACF2 (s2052) 6MD66 CI | |
| Syncrude | 07-Nov-26 08:00 | 17-Nov-26 16:00 | 248 Hours
Continuous |
223 (Aurora), 222B (Aurora), 89-225 (Aurora), 223A (Aurora) | Zone 4 6yr PM | |
| EPCOR | 09-Nov-26 07:00 | 11-Dec-26 17:00 | 778 Hours
Continuous |
PM2405 (Poundmaker) | Poundmaker: P2405 Breaker Replacement | |
| ATCO | 09-Nov-26 10:00 | 12-Nov-26 17:00 | 79 Hours
Continuous |
9L24 (946s Oakland - 959s Lanfine), 959s 906 (959s Lanfine), 959s 905 (959s Lanfine), 946s 902 (946s Oakland), 946s 903 (946s Oakland) | Cutover Bkr/MOD status, Commission new LTO/RAS 204 A/B - Lanfine/Oakland | |
| ATCO | 13-Nov-26 10:00 | 14-Nov-26 17:00 | 31 Hours
Continuous |
959s 901T (959s Lanfine), 959s 904 (959s Lanfine), 959s 919 (959s Lanfine), 959s 701 (959s Lanfine), 959s 706 (959s Lanfine), 959s 722 (959s Lanfine), 959S 722C (959S Lanfine) | Cutover MOD status, Commission inputs to RAS 204 A/B | |
| ALTALINK, EPCOR | 16-Nov-26 09:30 | 27-Nov-26 17:00 | 271.5 Hours
Continuous |
908L (89s Ellerslie - 816s Petrolia), 816s P2401 (816s Petrolia), 816s P2406 (816s Petrolia) | Petrolia: 908LE Surge Arrestor and CVT LCR | |
| ATCO | 16-Nov-26 12:00 | 19-Nov-26 12:00 | 72 Hours
Continuous |
740s 705 (740s H.R. Milner), 7L80 (740s H.R. Milner - 857s Kakwa Ridge) | PRC-005 - MICROPROCESSOR RELAY TESTING
TCM Program. RTXP Test Switch Mitigation and Replacement Both RAS-A and RAS-B 7L80 will also need be OOS for the RTXP work on 21A and 21B 7L80 |
|
| ATCO | 23-Nov-26 10:00 | 23-Nov-26 17:00 | 7 Hours
Continuous |
959s 904 (959s Lanfine) | Cutover and Commission Bkr 904 status to RAS 204 A/B | |
| ATCO | 23-Nov-26 10:00 | 24-Nov-26 15:00 | 29 Hours
Continuous |
813s 901 (813s Little Smoky) | 813S Little Smoky - 901 S/C Open/Close Control Mapping Issue | |
| ATCO | 23-Nov-26 13:00 | 30-Nov-26 13:00 | 168 Hours
Continuous |
930s SVC (930s Arcenciel) | ET 1137010 930S Arcenciel SVC DFR Upgrade
ET 1137018 930S Arcenciel SVC Protection Upgrade SVC AIR COOLED MAINTENANCE @ ARCENCIEL 930S |
|
| ATCO | 24-Nov-26 10:00 | 24-Nov-26 17:00 | 7 Hours
Continuous |
959s 919 (959s Lanfine) | Cutover and Commission Bkr 919 status to RAS 204 A/B | |
| ATCO | 25-Nov-26 10:00 | 25-Nov-26 17:00 | 7 Hours
Continuous |
959s 920 (959s Lanfine) | Cutover and Commission Bkr 920 status to RAS 204 A/B | |
| ATCO | 30-Nov-26 12:00 | 03-Dec-26 12:00 | 72 Hours
Continuous |
813s SVC (813s Little Smoky) | 813S Little Smoky SVC DFR Upgrade | |
| ALTALINK | 07-Dec-26 10:00 | 11-Dec-26 17:30 | 103.5 Hours
Continuous |
514L (396s Pincher Creek - 514BL tap) | 514L
Structure 48 - Replace cross arm Structure 99 - Replace structure Structure 102 - Replace structure Structure 158 - Replace Cross Arm |
|
| ALTALINK, EPCOR | 07-Dec-26 16:30 | 14-Dec-26 17:30 | 169 Hours
Continuous |
1056L (89s Ellerslie - 629s Argyll Transfer Station) | 1056L/240BA2: ADS3 LCR (1055L and BA3 will be jumpered out and energized bypassing ADS2 for the duration of this outage) | |
| ALTALINK | 16-Dec-26 10:00 | 16-Dec-26 14:00 | 4 Hours
Continuous |
250p 1 (250p Bighorn Plant) | maintenance | |
| ALTALINK | 17-Dec-26 10:00 | 17-Dec-26 14:00 | 4 Hours
Continuous |
250p 2 (250p Bighorn Plant) | maintenance | |
| ALTALINK | 23-Dec-26 23:30 | 24-Dec-26 02:30 | 3 Hours
Continuous |
62s 1 (62s Brazeau Plant) | maintenence | |
| ALTALINK | 24-Dec-26 03:30 | 24-Dec-26 06:30 | 3 Hours
Continuous |
62s 2 (62s Brazeau Plant) | maintenence | |
| EPCOR | 04-Jan-27 07:00 | 12-Feb-27 17:00 | 946 Hours
Continuous |
EP 805s J2405 (EP 805s Jasper) | Jasper: J2405 Replacement LCR | |
| EPCOR | 22-Jan-27 07:00 | 25-Jan-27 17:00 | 82 Hours
Continuous |
1055L (629s Argyll Transfer Station - 816s Petrolia), 240BA3 (629s Argyll Transfer Station - 814s Bellamy) | 1055L/240BA3: ADS3 LCR Preparation Outage, jumpering out ADS2 | |
| EPCOR, ALTALINK | 25-Jan-27 17:00 | 01-Feb-27 17:00 | 168 Hours
Continuous |
240BA2 (629s Argyll Transfer Station - 814s Bellamy), 1056L (89s Ellerslie - 629s Argyll Transfer Station) | 1056L/240BA2: ADS3 LCR (1055L and BA3 will be jumpered out and energized bypassing ADS2 for the duration of this outage) | |
| EPCOR | 01-Feb-27 17:00 | 05-Feb-27 17:00 | 96 Hours
Continuous |
1055L (629s Argyll Transfer Station - 816s Petrolia), 240BA3 (629s Argyll Transfer Station - 814s Bellamy) | 1055L/240BA3: ADS3 LCR Removing ADS2 jumper, restoring configuration | |
| EPCOR | 16-Feb-27 07:00 | 30-Mar-27 17:00 | 1,017 Hours
Continuous |
EP 805s J2407 (EP 805s Jasper) | Jasper: J2407 Replacement LCR | |
| ALTALINK, EPCOR | 19-Feb-27 07:00 | 05-Mar-27 17:00 | 346 Hours
Continuous |
1045L (EP 805s Jasper - 1045AL tap), EP 805s J2406 (EP 805s Jasper), EP 805s J2407 (EP 805s Jasper) | 1045L/Jasper: J2407 Replacement LCR | |
| ALTALINK | 19-Feb-27 07:00 | 05-Mar-27 18:00 | 347 Hours
Continuous |
1045AL (320p Keephills - 1045L tap), 1045L (310p Sundance - 1045AL tap) | 1045L/Jasper: J2407 Replacement LCR | |
| EPCOR | 22-Feb-27 07:00 | 05-Mar-27 17:00 | 274 Hours
Continuous |
814s T1 (814s Bellamy), BR721 (Rossdale), 814s B2401 (814s Bellamy), 814s B2407 (814s Bellamy) | Bellamy: TX1 Temp Monitor Install | |
| ATCO | 08-Mar-27 10:00 | 17-Mar-27 17:00 | 222 Hours
Continuous |
9L24 (946s Oakland - 959s Lanfine), 959s 906 (959s Lanfine), 959s 905 (959s Lanfine), 946s 902 (946s Oakland), 946s 903 (946s Oakland) | Replace A/B protection relays at 959S Lanfine and 946S Oakland Cut in and reroute 9L24 Connect new 9LA24 T-tap Commission Telecom and Protection to new 1072S Rose Lynn substation |
|
| EPCOR | 05-Apr-27 07:00 | 07-May-27 17:00 | 778 Hours
Continuous |
52s T2 (52s East Industrial), 52s E2402 (52s East Industrial) | East Industrial: TX2 Bushing Replacement | |
| SUNCOR | 05-Apr-27 09:00 | 11-Apr-27 20:00 | 155 Hours
Continuous |
29PL9-12 (29EDD-34 - 29EDD-65) | 29EDD34;29PL9-12 SYSTEM;PM 5y,10y |
|
| SUNCOR | 06-Apr-27 09:00 | 16-Apr-27 20:00 | 251 Hours
Continuous |
29EDD-34 29PT-112 (29EDD-34), 29EDD-34 29-752-121 (29EDD-34), 29EDD-34 29PS-68 (29EDD-34), 29EDD-34 29PS-67 (29EDD-34), 29EDD-34 29PS-66 (29EDD-34), 29EDD-34 29PS-65 (29EDD-34), 29EDD-34 29PS-225 (29EDD-34), 29EDD-34 29PS-230 (29EDD-34), 29EDD-34 29-952-141 (29EDD-34), 29EDD-34 29-952-131 (29EDD-34), 29EDD-34 29-952-111 (29EDD-34) | 29EDD34;29PT-112 & 29PP-24 SYSTEM;PM This will Place 29EDD-34 on one 260 kV bus and drop 29PL7-1 |
|
| ATCO | 12-Apr-27 10:00 | 19-Apr-27 17:00 | 175 Hours
Continuous |
7L22 (790s Poplar Hill - 7L88 tap) | Cut open 7L22, connect new line section to new 2061S Dobbs 7L22/21B relay upgrades at 790S Poplar Hill and 811S Clairmont Lake On completion energize new 2061S Dobbs substation |
|
| SUNCOR | 14-Apr-27 14:00 | 23-Apr-27 18:00 | 220 Hours
Continuous |
29EDD-65 29PT-0257 (29EDD-65), 29EDD-65 29-952-4812 (29EDD-65), 29EDD-65 29-952-4813 (29EDD-65), 29EDD-71 752-4624 (29EDD-71), 29EDD-71 752-4623 (29EDD-71), 29PL7-4 (29EDD-65 - 29EDD-71) | Firebag: 29EDD65;29PT-257 & 29PL7-4 SYSTEM, 29EDD65 ;29PT-260 & 29PL7-4 SYSTEM, 29EDD71 29PT-241 & 29PL7-4 | |
| ATCO | 03-May-27 09:00 | 17-May-27 17:30 | 344.5 Hours
Continuous |
2075s T11 (2075s Newell) | Annual EATL outage at 2075s & 2029s. | |
| ATCO | 03-May-27 09:00 | 17-May-27 17:30 | 344.5 Hours
Continuous |
2029s T11 (2029s Heathfield) | Annual EATL outage at 2075s & 2029s. | |
| ATCO | 03-May-27 09:00 | 17-May-27 17:30 | 344.5 Hours
Continuous |
13L50 (2029s Heathfield - 2075s Newell) | Annual EATL outage at 2075s & 2029s. **1218 IS NOT THE ISOALTION. ATCO SENT AESO OF REQUIRED ISOLATIONS BACK IN MAY 2024 TO UPDATE 2029S AND 2075S ISOLATIONS FOR 13L50 OUTAGES** |
|
| ATCO | 03-May-27 10:00 | 06-May-27 17:00 | 79 Hours
Continuous |
7L22 (811s Clairmont Lake - 7L88 tap) | 7L22/21B relay upgrade at 811S Clairmont Lake Upon completion new 2061S Dobbs substation ready to energize |
|
| SUNCOR | 04-May-27 09:00 | 14-May-27 20:00 | 251 Hours
Continuous |
29EDD-34 29PS-214 (29EDD-34), 29EDD-34 29-952-113 (29EDD-34), 29EDD-34 29PS-215 (29EDD-34), 29EDD-34 29PS-213 (29EDD-34) | 29EDD34;29PL9-13 SYSTEM;PM 5y,10y | |
| SUNCOR | 05-May-27 14:00 | 14-May-27 18:00 | 220 Hours
Continuous |
29EDD-65 29PT-0236 (29EDD-65), 29EDD-65 29-952-4823 (29EDD-65), 29EDD-65 29-952-4822 (29EDD-65), 29EDD-71 752-4634 (29EDD-71), 29EDD-71 752-4633 (29EDD-71), 29PL7-3 (29EDD-65 - 29EDD-71) | Firebag: 29EDD65;29PT-236 & 29PL7-3 SYSTEM, 29EDD65;29PT-250&29PL7-3 SYSTEM, 29PT-246 SYSTEM;29EDD71 | |
| ATCO | 10-May-27 10:00 | 11-May-27 17:00 | 31 Hours
Continuous |
7L03 (749s Flyingshot Lake - 7L09 tap) | Cutover and commission RAS analogs and LTO to 790S Poplar Hill RAS Hub | |
| ATCO | 12-May-27 10:00 | 13-May-27 17:00 | 31 Hours
Continuous |
7L03 (731s Elmworth - 7L09 tap) | Cutover and commission LTO to 790S Poplar Hill RAS Hub | |
| ATCO | 14-May-27 10:00 | 15-May-27 17:00 | 31 Hours
Continuous |
7L69 (731s Elmworth - 815s Goodfare) | Cutover and commission LTO to 790S Poplar Hill RAS Hub | |
| ATCO | 16-May-27 10:00 | 17-May-27 17:00 | 31 Hours
Continuous |
7L07 (790s Poplar Hill - 815s Goodfare) | Cutover and commission LTO to 790S Poplar Hill RAS Hub | |
| SUNCOR | 01-Jun-27 08:00 | 10-Jun-27 17:00 | 225 Hours
Continuous |
635EDD-1000 635-752-635PT-1000 (635EDD-1000), 635EDD-1000 635PT-1000 (635EDD-1000) | FH - Maintenance on Transformer, associated breakers, other equipment in isolation boundary and protection system testing. | |
| SUNCOR | 01-Jun-27 09:00 | 11-Jun-27 20:00 | 251 Hours
Continuous |
29EDD-94 407T (29EDD-94 Voyageur), 29EDD-94 29-952-9705 (29EDD-94 Voyageur), 29EDD-94 29PS-393 (29EDD-94 Voyageur), 29EDD-94 29PS-392 (29EDD-94 Voyageur), 29EDD-94 29-952-9704 (29EDD-94 Voyageur), 29EDD-94 29PS-400 (29EDD-94 Voyageur) | 29EDD94;29PT-407 SYSTEM;PM 5y,10y | |
| ATCO | 07-Jun-27 12:00 | 10-Jun-27 15:00 | 75 Hours
Continuous |
7L80 (733s Simonette - 857s Kakwa Ridge), 733s 701 (733s Simonette) | BREAKER SF6 HPL COMPLETE TESTING - 701 @ 733S | |
| SUNCOR | 11-Jun-27 08:00 | 20-Jun-27 17:00 | 225 Hours
Continuous |
635EDD-1000 635-752-635PT-1001 (635EDD-1000), 635EDD-1000 635PT-1001 (635EDD-1000) | FH - Maintenance on Transformer, associated breakers, other equipment in isolation boundary and protection system testing. | |
| SUNCOR | 15-Jun-27 09:00 | 25-Jun-27 20:00 | 251 Hours
Continuous |
29EDD-94 406T (29EDD-94 Voyageur), 29EDD-94 29-952-9702 (29EDD-94 Voyageur), 29EDD-94 29PS-388 (29EDD-94 Voyageur), 29EDD-94 29PS-389 (29EDD-94 Voyageur), 29EDD-94 29PS-399 (29EDD-94 Voyageur) | 29EDD94;29PT-406 SYSTEM;PM 5y,10y | |
| AESO, ATCO | 29-Jun-27 13:00 | 30-Jun-27 17:00 | 28 Hours
Continuous |
9LA93 (973s Lanes Lake - 9L93 tap) | Line to Ground Clearance Mitigation, Span 50-51. Repair deficiency on structure 57 | |
| ALTALINK, ATCO, FMGW | 17-Aug-27 08:00 | 18-Aug-27 17:00 | 33 Hours
Continuous |
964AL (1024s Granlea - 964L tap), 1024s PT-6001 (1024s Granlea), 1024s PT-6002 (1024s Granlea), 1024s 952-600001 (1024s Granlea), 1024s PS-6005 (1024s Granlea), 1024s PS-6006 (1024s Granlea), 1024s PS-6007 (1024s Granlea), 1024s PS-6008 (1024s Granlea), 1024s 489-600201 (1024s Granlea) | maintenance activities (testing and inspection) of electrical equipment | |
| ALTALINK, BCH | 23-Aug-27 07:00 | 03-Sep-27 17:00 | 274 Hours
Continuous |
1201L (520s Bennett - BCH Cranbrook), Path 1 (AIES Islanding) | annual maintenance | AB-BC |
| ALTALINK, BHE | 23-Aug-27 07:00 | 03-Sep-27 17:00 | 274 Hours
Continuous |
MATL (120s Picture Butte - Montana) | align with 1201L outage | AB-MATL |
| ALTALINK, BCH | 23-Aug-27 07:00 | 03-Sep-27 17:00 | 274 Hours
Continuous |
48s 887X (48s Pocaterra), 887L (48s Pocaterra - 978s BCH Britt Creek) | opened because 1201L is out of service . | AB-BC |
| ALTALINK, BCH | 23-Aug-27 07:00 | 03-Sep-27 17:00 | 274 Hours
Continuous |
799s 786W (799s Coleman), 786L (799s Coleman - BCH Natal) | opened because 1201L is out of service. | AB-BC |
| ATCO | 08-Nov-27 09:00 | 11-Nov-27 17:00 | 80 Hours
Continuous |
ALC02L (409s Shell Scotford - 879s Upgrader) | Install new Deadend corner structure on ALC02L | |
| ATCO | 08-Nov-27 09:00 | 11-Nov-27 17:00 | 80 Hours
Continuous |
ALC01L (408s Air Liquide Scotford - 409s Shell Scotford) | Install new Deadend corner structure on ALC02L. | |
| ATCO | 08-Feb-28 09:00 | 10-Feb-28 17:00 | 56 Hours
Continuous |
7L228 (845s Big Mountain - 7L20 tap) | AESO project P2716 - Install 7L228 bypass to facilitate the installation of new line switches for the new 7LA228 T-tap line connection to the new 2103S Pakenham substation Open 7L228, replace structures 551 and 551A, connect bypass. |
|
| ATCO | 06-Mar-28 10:00 | 22-Mar-28 16:00 | 389 Hours
Continuous |
826s 903 (826s Marguerite Lake), 826s 907 (826s Marguerite Lake), 826s 901T (826s Marguerite Lake) | Expand 240kV ring bus for new 9L42 line | |
| ATCO | 13-Mar-28 10:00 | 16-Mar-28 17:00 | 79 Hours
Continuous |
9L939 (77s Sagitawah - 809s Louise Creek) | Cut over 9L939 to temp bypass structures to allow for installation of new deadend corner towers. These are required to make the final connections to the new 2105S Jackson substation | |
| ATCO | 14-Mar-28 09:00 | 16-Mar-28 17:00 | 56 Hours
Continuous |
7L228 (845s Big Mountain - 7L20 tap) | AESO project P2716 - Disconnect bypass, connect new 7LA228D1 to 7LA228 Str #2, connect 7L228 to 7L228D2, connect 7L228 to 7L228D3. Renumber existing line switches 7L228D2 - D4, 7L228D3 - D5, 7L228D4 - D6 Commission DTT |
|
| ATCO | 17-Mar-28 10:00 | 17-Apr-28 17:00 | 751 Hours
Continuous |
9L938 (77s Sagitawah - 809s Louise Creek) | Install foundations (TBD assume concrete), assemble and erect new Q-towers 9L938/9L939-155A and 9L938/9L939-156A in existing ROW centreline. Daily outage until such a time as the new towers begin to encroach on 9L938. | |
| ATCO | 20-Mar-28 09:00 | 23-Mar-28 17:00 | 80 Hours
Continuous |
2091s 704 (2091s Thornton) | AESO project P2716 - cut over new SEL 2440 wiring at 2091S, relay programming, commission DTT and LTO | |
| ATCO | 24-Mar-28 09:00 | 27-Mar-28 17:00 | 80 Hours
Continuous |
740s 704 (740s H.R. Milner), 7L20 (740s H.R. Milner - 810s Dome Cutbank) | AESO project P2716 - cut over RAS #171 wiring at 740S, relay programming, commission LTO 7L20/7L228 | |
| SUNCOR | 04-Apr-28 08:00 | 07-Apr-28 19:00 | 83 Hours
Continuous |
29PL9-16 (29EDD-1 Millennium - 29EDD-94 Voyageur) | 29EDD1;29PT418/29PL9-16 SYSTEM;PM 5y,10y |
|
| ATCO | 18-Apr-28 10:00 | 25-Apr-28 17:00 | 175 Hours
Continuous |
9L938 (77s Sagitawah - 809s Louise Creek) | Open 9L938 conductors, complete assembly and connect to the new Q-Towers 9L938/9L939-155A and 9L938/9L939-156A, string to 2105S Jackson deadend and terminate. Relabel 9L938 segment from 809S Louise Creek to 2105S Jackson to 9L140. |
|
| ATCO | 01-May-28 10:00 | 04-May-28 17:00 | 79 Hours
Continuous |
9L939 (77s Sagitawah - 809s Louise Creek) | Disconnect 9L939 conductors from temp structure 9L939 -155A - 155E reconnect to existing structures 9L938/9L939-156 and 9L938/9L939-155, connect to the new Q-Towers 9L938/9L939-155A and 9L938/9L939-156A, string to 2105S Jackson deadend and terminate. Relabel 9L939 segment from 809S Louise Creek to 2 |
|
| ATCO | 08-May-28 09:00 | 10-Jul-28 17:00 | 1,520 Hours
Continuous |
959s 240kV Bus 900BS2 (959s Lanfine) | GOI on 9L141 until line terminated into 1162S Fair Acres and ready to energize | |
| ATCO | 08-May-28 09:00 | 10-Jul-28 17:00 | 1,520 Hours
Continuous |
959s 240kV Bus 900BS2 (959s Lanfine) | GOI on 902/903 until line terminated and 1162S Fair Acres ready to energize | |
| ATCO | 09-May-28 10:00 | 13-May-28 17:00 | 103 Hours
Continuous |
9L02 (809s Louise Creek - 813s Little Smoky) | Install concrete foundations for new structures 9L02/320A, 320H in preparation to cut into 9L02 and convert to a t-tap. | |
| ATCO | 15-May-28 09:00 | 17-May-28 17:00 | 56 Hours
Continuous |
959s 240kV Bus 900BS1 (959s Lanfine) | Connect new bus from new 902B to existing switch 901A to add new line 9L141, Cutover and commission 900PT1 ccts to new 9L141 relays |
|
| ATCO | 18-May-28 09:00 | 20-May-28 17:00 | 56 Hours
Continuous |
959s 240kV Bus 900BS2 (959s Lanfine) | Connect new bus from new Bkr 903 to existing switch 903B to add new line 9L141, Cutover and commission 900PT2 ccts to new 9L141 relays |
|
| ATCO | 29-May-28 09:00 | 08-Jun-28 17:00 | 248 Hours
Continuous |
9L24 (946s Oakland - 959s Lanfine) | Cutover and commission 905/906 CT's, 9L24PT ccts to new RAS 241 SEL 451A/B relays @ 959S Lanfine and update relay settings for RAS 241 and SCADA inputs @946S Oakland. | |
| ATCO | 19-Jun-28 10:00 | 30-Jun-28 16:00 | 270 Hours
Continuous |
9L20 (755s Cordel - 766s Nevis) | Install concrete foundations at 9L20 Structure 69 for new T-Tap connection |
|
| ATCO | 26-Jun-28 10:00 | 10-Jul-28 17:00 | 343 Hours
Continuous |
9L02 (809s Louise Creek - 813s Little Smoky) | Cut into 9L02 and connect new t-tap structures for 9LA02. 9L02-21A and 21B relay upgrades at 809S Louise Creek and 813S Little Smoky. Implement RAS Energize new line 9LA02 and 884S Magpie substation |
|
| ATCO | 31-Jul-28 10:00 | 15-Aug-28 16:00 | 366 Hours
Continuous |
766s 901 (766s Nevis), 9L20 (755s Cordel - 766s Nevis), 755s 906 (755s Cordel), 755s 901 (755s Cordel) | Cutover new 9L20 line section, terminate 9LA20 at customer substation. Install new line protection relays |
|
| ATCO | 01-Oct-28 08:00 | 21-Oct-28 16:00 | 488 Hours
Continuous |
972s 904 (972s Tinchebray) | CETO project
Install 904 and 904CT Commission 904 and 904CT Expand GOI to 900BS1 Isolation Points: 904A, 901A and 900SST1X Connect 907B to 900BS1 Shrink GOI to 907B |
|
| ATCO | 22-Oct-28 08:00 | 20-Nov-28 16:00 | 705 Hours
Continuous |
972s 906 (972s Tinchebray) | CETO project
Install 906 and 906CT Commission 906 and 906CT Expand GOI to 900BS2 OCT 22 2028 - NOV 20 2028 Isolation Points: 906A, 902B and 9L16D1@ CORDEL Connect 909A to 900BS2 Commission Logic and breaker fail Shrink GOI to 9L86D1 String 9L86 into substation |
| AB-BC, AB-SK & AB-MATL: refer to AESO web posting: | http://itc.aeso.ca/itc/public/atc |
| Also, | |
| AB-BC, AB-SK & AB-MATL: refer to ISO Rule 203.6: | http://www.aeso.ca/rulesprocedures/18592.html |
| Prepared On: | 2026-07-22 14:22:06 |
|
This document and the information contained herein are based upon information and data which by their nature contain a degree of uncertainty and are subject to change. In addition, this document may contain information and data from public sources and/or third parties, which have been assumed to be accurate and complete and have not been verified. Accordingly, the Independent System Operator, operating as the Alberta Electric System Operator (the "AESO") makes no warranty, representation or guarantee, express or implied, with respect to this document or the information contained herein, including, but not limited to, any warranty, representation or guarantee of accuracy, completeness, timeliness, reliability, availability, absence of computer virus, non- infringement, merchantability or suitability for any purpose. Under no circumstances will the AESO, its members, officers, employees, contractors or agents, or any of their respective affiliates, be liable for any errors or omissions in, or any losses, damages or claims whatsoever, whether in contract, tort or otherwise, arising from use of or reliance upon, this document or any information contained herein. © 2009 Alberta Electric System Operator. All rights reserved |