Alberta Electric System Operator
Long Range Significant Transmission Outages for the period of 24 months starting 2023-12-09

The table below contains the significant transmission outages submitted as tentative to the AESO.
These Outages have not yet necessarily been approved, but are listed for awareness and coordination purposes.
An Outage has been considered significant for this table if it meets any one (1) or more of the following criteria:
  1. it affects a transmission facility operating at two hundred and forty (240) kV or greater;
  2. it affects an intertie;
  3. it affects an element connecting facilities owned by two (2) or more different legal owners of transmission facilities;
  4. it affects an element that connects a generating unit or an aggregated generating facility to the interconnected electric system;
  5. it requires the ISO to issue a dispatch or directive for generation in order to facilitate the planned outage;
  6. it affects a cutplane limit;
  7. it limits or reduces the operability of a synchronous condenser, static VAr compensator, static compensator or other similar dynamic device; or
  8. it affects high voltage direct current facilities.
Note: Where a transmission outage requires generation curtailments, the adjustments to generation will typically happen in the hours before the scheduled transmission outage and in the hour after the element is returned to service.

Previous Version
Download CSV

Owner From To Duration Element Scheduled Activity Affected Intertie
ATCO 29-May-23 08:20 12-Jan-24 23:00 228.65 Days
Continuous
840s McNeill Station filter bank forced outage AB-SK
EPCOR 05-Jun-23 07:00 22-Dec-23 17:00 200.46 Days
Continuous
805s C1 (805s Jasper), EP 805s J2408 (EP 805s Jasper) Jasper: Emergency Investigation of J2408 Cap Bank Breaker  
ATCO 12-Jun-23 00:00 31-Mar-24 00:00 293 Days
Continuous
7L64 (747s Bassett - 930s Arcenciel) forced outage due to fire  
ATCO 01-Sep-23 20:00 31-Mar-24 17:00 211.88 Days
Continuous
7L113 (853s Ring Creek - 930s Arcenciel) forced outage  
ATCO, SUNCOR 08-Sep-23 09:30 14-Dec-23 17:30 97.38 Days
Continuous
29PL9-1 (29EDD-1 Millennium - 848s Ruth Lake), 848s 903 (848s Ruth Lake), 848s 906 (848s Ruth Lake) reconductor 29PL9-1 (Suncor Capacity Increase project)  
EPCOR 18-Oct-23 07:00 01-Feb-24 17:00 106.46 Days
Continuous
987s CDS33 (987s Cloverbar) continued re-configuration of 240 kV ring for new 1191L bay construction will leave the ring open from newly energized CDS41 and CDS44 disconnects.  
ATCO, SUNCOR 14-Nov-23 18:01 19-Dec-23 18:00 35 Days
Continuous
29PL9-1 (29EDD-1 Millennium - 848s Ruth Lake), 29PL9-2 (29EDD-1 Millennium - 848s Ruth Lake) reconductoring for 29PL9-2 and 29PL9-1, protection retrofit and associated pre-commissioning and commissioning
 
ALTALINK, EPCOR 22-Nov-23 07:00 20-Dec-23 17:00 28.42 Days
Continuous
921L (71s Lamoureux - 987s Clover Bar), 987s T2 (987s Clover Bar), 987s T4 (987s Clover Bar), 987s CC721 (987s Clover Bar), 987s CDS31 (987s Clover Bar), 987s C2404 (987s Clover Bar), 987s C2405 (987s Clover Bar), 987s C2406 (987s Clover Bar), 987s C2408 (987s Clover Bar), 987s CDS39 (987s Cloverbar) Cloverbar S/S 240 kV re-configuration as part of the air products project  
EPCOR 24-Nov-23 07:00 22-Dec-23 17:00 28.42 Days
Continuous
330P 12TC1 (330p Genesee), 330p 805 (330p Genesee) Genesee S/S 12TC1 decommissioning  
ENMAX, ALTALINK 27-Nov-23 09:30 10-Dec-23 19:00 13.4 Days
Continuous
918L (281s Johnson - SS-162) completion of replacement of bent steel, re-tie/replace OHSW dampers, installation on aerial number boards, and damper replacement between structures 606-840  
ATCO, ALTALINK 27-Nov-23 12:01 11-Dec-23 13:00 14.04 Days
Continuous
9L55 (AML 852s Round Hill - 885s McMillan), 885s 902T (885s McMillan), 885s 260kV Bus 900BS2 (885s McMillan), 885s 902 (885s McMillan), 885s 903 (885s McMillan), 885S 902TD (885s McMillan), 885S 702TD (885s McMillan), 885s 704 (885s McMillan), 885s 501R (885s McMillan) 885s McMillan sub protection upgrade  
ALTALINK 02-Dec-23 07:00 19-Dec-23 17:00 17.42 Days
Continuous
929L (74S Janet - 287s Hazelwood) component replacements between structures #929L72 - 929L404  
EPCOR 04-Dec-23 07:00 15-Dec-23 17:00 11.42 Days
Continuous
CV5 (EP 511s Victoria - 557s Castle Downs), EP 511s Victoria T5 (EP 511s Victoria), EP 511s V2401 (EP 511s Victoria) CV5: annual manhole inspections and maintenance  
ALTALINK, ATCO 04-Dec-23 10:00 09-Dec-23 14:00 5.17 Days
Continuous
852s 152 (852s Round Hill), 852s 252 (852s Round Hill), 1085L (852s Round Hill - 885s McMillan) updates to L1 protections to accommodate ATCO remote end updates  
ALTALINK 04-Dec-23 17:01 15-Dec-23 12:30 10.81 Days
Continuous
658L (562s Cypress - 658AL tap) 658L comp replacement (298-331)  
ALTALINK 05-Dec-23 07:00 13-Dec-23 18:00 8.46 Days
Continuous
1047L (574s Nilrem - 650s Hansman Lake) Replace dampers on 1047L structures 1-64  
ALTALINK 07-Dec-23 07:00 12-Dec-23 17:00 5.42 Days
Continuous
927L (102s Langdon - 356s Milo) Line inspection , Multiple locations between 102s and 356s, See also SAP: 287331 924L RB required due to proximity.  
ALTALINK 08-Dec-23 07:00 10-Dec-23 17:00 2.42 Days
Continuous
964L (244s Bowmanton - 964L tap), 964L (251s Whitla - 964L tap), 244s 252 (244s Bowmanton), 244s 352 (244s Bowmanton), 251s 252 (251s Whitla), 251s 352 (251s Whitla), 964AL (1024s Granlea - 964L tap) tying in the new 326s Murray Lake Substation  
ATCO, FMGW 08-Dec-23 07:00 10-Dec-23 17:00 2.42 Days
Continuous
1024s PT-6001 (1024s Granlea), 1024s PT-6002 (1024s Granlea), 1024s PS-6005 (1024s Granlea), 1024s PS-6006 (1024s Granlea) maintenance  
ALTALINK 09-Dec-23 08:00 09-Dec-23 16:00 8 Hours
Daily
33s 2 (33s Spray) maintenance  
ALTALINK 09-Dec-23 08:00 09-Dec-23 17:00 9 Hours
Daily
33s 2 (33s Spray) PRC5 breaker maintenance Scheduled Shannon Bouchard Issue To: Anton Karentnikov Contact #: 403.669.1466  
ALTALINK 10-Dec-23 08:00 19-Dec-23 17:00 9.38 Days
Continuous
765L (151s Strathmore - 419s Chestermere) perform maintenance work on structures  
ALTALINK 10-Dec-23 17:00 17-Dec-23 17:00 7 Days
Continuous
964L (244s Bowmanton - 964L tap), 244s 252 (244s Bowmanton), 244s 352 (244s Bowmanton) Tying in the new 326s Murray Lake Substation @ Structures #283 - 285  
EPCOR 11-Dec-23 07:00 15-Dec-23 17:00 4.42 Days
Continuous
T1 (EP Riverview) Riverview: TX1 Repair w/Hitachi  
ATCO 11-Dec-23 09:00 14-Dec-23 16:00 3.29 Days
Continuous
7L03 (731s Elmworth - 7L09 tap) Replacing red tag poles  
ALTALINK 11-Dec-23 09:30 21-Dec-23 18:00 10.35 Days
Continuous
901AL (64s East Crossfield - 901L tap), 901L (63s Red Deer - 901AL tap), 901L (74s Janet - 901AL tap) Crews will be completing CR work (Insulator Replacements)See also 287199 912L required due to proximity to 901L  
ATCO 11-Dec-23 14:00 14-Dec-23 16:00 3.08 Days
Continuous
876S 240kV Breaker Relays, 876S 9L10 Protection Relay, 9L10, 876S 901, 876S 903, 9L10 (876s Brintnell - 939s Livock), 876s 901 (876s Brintnell), 876s 903 (876s Brintnell) 21A&B/ 9L10, 50BF/901&903 RTXP Test Switch Replacement, PRC-005 Relay Testing 21A&B / 9L10 an 50BF/ Bkr 901&903, PRC-005 Trip Coil Testing Breaker 901 & 903  
ENMAX, ALTALINK 12-Dec-23 08:00 15-Dec-23 16:00 3.33 Days
Continuous
24B138-24.81 (SS-24), 24B138-24.83 (SS-24), 24B138-24BT3 (SS-24), 24.1TR (SS-24), 24.81L (SS-24 - SS-31), 24.83L (74s Janet - SS-24) Surge Arrestor Replacement 24B138-24.83, 24B138-24.81. Check reversing switch 24.1TR. 24MD138-24.1TR require adjustment. 24B138-24.83 CT Terminal Block Replacement, 24B138-24BT3 CT Terminal Block Replacement  
ENMAX, ALTALINK 12-Dec-23 08:00 15-Dec-23 16:00 3.33 Days
Continuous
24.83L (74s Janet - SS-24) Surge Arrestor Replacement 24B138-24.83, 24B138-24.81  
ALTALINK 12-Dec-23 17:30 17-Dec-23 18:00 5.02 Days
Continuous
924L (102s Langdon - 356s Milo) Line inspection , Multiple locations between 102s and 356s, See also SAP: 287333 927L RB required due to proximity. Note 927L RB starts the next day on Dec 13  
ALTALINK 15-Dec-23 12:30 15-Dec-23 16:30 4 Hours
Daily
658AL (662s Hilda - 658AL tap), 658L (562s Cypress - 658AL tap), 658L (649s Chappice Lake - 658AL tap) Close South jumpers at structure 286A.  
ALTALINK 17-Dec-23 17:00 18-Dec-23 18:00 25 Hours
Continuous
964AL (1024s Granlea - 964L tap), 964L (244s Bowmanton - 964L tap), 964L (251s Whitla - 964L tap), 244s 252 (244s Bowmanton), 244s 352 (244s Bowmanton), 251s 252 (251s Whitla), 251s 352 (251s Whitla) Outage to close the open point ‘D’ at 964L287 and energize the newly split 965L and 964L and 326s substation  
ATCO, FMGW 18-Dec-23 08:00 18-Dec-23 18:00 10 Hours
Continuous
1024s PT-6001 (1024s Granlea), 1024s PT-6002 (1024s Granlea), 1024s PS-6001 (1024s Granlea), 1024s PS-6005 (1024s Granlea), 1024s PS-6006 (1024s Granlea) maintenance  
ATCO 18-Dec-23 09:00 21-Dec-23 16:00 3.29 Days
Continuous
7L03 (731s Elmworth - 7L09 tap) Pole Change from Test and Treat  
ALTALINK 19-Dec-23 07:30 19-Dec-23 16:30 9 Hours
Daily
103s T1 (103s Goose Lake) Replace high side LA grounding as part of grounding mitigation project  
ATCO 02-Jan-24 09:00 08-Jan-24 12:00 6.13 Days
Continuous
7L32 (811s Clairmont Lake - 862s South Bezanson) Line to Ground Mitigation  
ATCO 02-Jan-24 09:00 08-Jan-24 16:00 6.29 Days
Continuous
7L40 (733s Simonette - 813s Little Smoky) Pole Replacement from Test and Treat  
ENMAX, ALTALINK 03-Jan-24 08:00 03-Jan-24 17:00 9 Hours
Daily
937L (5s East Calgary - 102s Langdon) Replace insulators at structures 101, 102, 107, 114, 117, 119, 122, 127 & 128. Re-tie OHSW at structures 114 & 122.  
ALTALINK 03-Jan-24 08:00 05-Jan-24 17:00 2.38 Days
Continuous
733L (179s Gleichen - 428s Namaka) Replace crossarms and insulators at structures 250, 251 & 252. Measure catch arm & adjust if requires at structure 239 & 260. Bond OHSW at structure 272. Add insulators at structure 264 & 265.  
ALTALINK 03-Jan-24 08:00 05-Jan-24 17:00 2.38 Days
Continuous
994L (103s Goose Lake - 312s Fidler) Replace dead-end insulators at structure 10 and 38. Replace insulators at structure 13. Repair OPGW bond at structure 31.  
EPCOR 04-Jan-24 07:00 08-Jan-24 17:00 4.42 Days
Continuous
330p 1210 (330p Genesee), 330p 1211 (330p Genesee) 330P Genesee S/S tie and energization  
ALTALINK 05-Jan-24 08:00 10-Jan-24 17:00 5.38 Days
Continuous
906L (17s Benalto - 42s Sarcee) Replace insulator attachment hardware at structure 20.  
EPCOR 08-Jan-24 07:00 18-Jan-24 17:00 10.42 Days
Continuous
Cloverbar S/S Tx4 bay and 1191L bay, 987s CDS35 (987s Cloverbar) Continued re-configuration 240 kV ring for new 1191L bay  
ALTALINK 08-Jan-24 09:30 12-Jan-24 18:00 4.35 Days
Continuous
180L (255s Vulcan - 928s East Stavely) 180L/161L OPGW work 180L - STR 35-37 (Between 255s-928s) See also SAP: 286778 161L (504s-255s) - R/B-LL - Common Tower with 161L  
ATCO 08-Jan-24 10:00 22-Jan-24 12:00 14.08 Days
Continuous
9L155 (838s Horizon Mining - 849s Joslyn Creek), 849s 907 (849s Joslyn Creek) 849s Joslyn Protection Upgrade

- Move 9L155 into 901/902 Bay (former 9L66) - J3
- Demo 907 protection
- Protection ends to ends with 838s for 9L155 new line diff
 
ATCO 08-Jan-24 10:00 22-Jan-24 12:00 14.08 Days
Continuous
849s 901 (849s Joslyn Creek), 849s 902 (849s Joslyn Creek) 849s Joslyn Protection Upgrade

- Move 9L155 into 901/902 Bay (former 9L66)
- Protection ends to ends with 838s for 9L155 new line diff
 
Lethbridge, ALTALINK 15-Jan-24 08:00 29-Jan-24 17:00 14.38 Days
Continuous
593s 824L (593s Lakeview), 824L (593s Lakeview - 618s Riverbend) Replacing 593s824L HV BReaker  
ALTALINK, Lethbridge 15-Jan-24 08:00 29-Jan-24 17:00 14.38 Days
Continuous
824L (593s Lakeview - 618s Riverbend) Replace 593s824L HV Breaker  
ATCO 15-Jan-24 09:00 22-Jan-24 16:00 7.29 Days
Continuous
7L40 (733s Simonette - 813s Little Smoky) Pole Replacement from Test and Treat  
ATCO 15-Jan-24 09:00 22-Jan-24 16:00 7.29 Days
Continuous
7L32 (813s Little Smoky - 862s South Bezanson) Pole Change from test treat and X Arm change  
EPCOR 22-Jan-24 07:00 01-Feb-24 17:00 10.42 Days
Continuous
Cloverbar S/S Tx2 bay and 1191L bay, 987s CDS32 (987s Cloverbar) Continued re-configuration 240 kV ring for new 1191L bay. 1191L to be energize post outage with new isolation point of CDS45 to remain until 1191L is ready to energize.  
ATCO 22-Jan-24 12:01 05-Feb-24 17:30 14.23 Days
Continuous
9L137 (838s Horizon Mining - 849s Joslyn Creek), 9L08 (849s Joslyn Creek - 888s Dover), 849s 903 (849s Joslyn Creek), 849s 904 (849s Joslyn Creek), 849s 905 (849s Joslyn Creek), 849s 906 (849s Joslyn Creek) 849s Joslyn Protection Upgrade
- Move 9L137 into 904/905 Bay (former 9L32)
- Install new 900BS2 protection
- End to end testing for new 9L137 protection

Feb 1-5 - contract GOI to 849S 904A,838S 905B, 849S 904A,849S 905B
 
ALTALINK 22-Jan-24 14:00 05-Feb-24 14:00 14 Days
Continuous
948L (650s Hansman Lake - 863s Paintearth) Protection upgrade @ 863s - ATCO  
ATCO 23-Jan-24 09:00 25-Jan-24 16:00 2.29 Days
Continuous
730s STATCOM (730s Rycroft), 730s 705 (730s Rycroft) SVS Deficiency repairs by Hitachi  
ENMAX, ALTALINK 29-Jan-24 08:00 30-Jan-24 16:00 1.33 Days
Continuous
28.80L (42s Sarcee - SS-28), 28B138-28.80 (SS-28), 28.2TR (SS-28) HV SW Maint. MD-28.2TR, SW86, SW82, SW81, SW80  
ENMAX, ALTALINK 29-Jan-24 08:00 30-Jan-24 16:00 1.33 Days
Continuous
28.80L (42s Sarcee - SS-28) 28.80L (42s Sarcee - SS-28), 28B138-28.80 (SS-28), 28.2TR (SS-28).  
ATCO 29-Jan-24 09:00 05-Feb-24 12:00 7.13 Days
Continuous
9L40 (732s Mitsue - 809s Louise Creek) Pole changes  
ATCO 29-Jan-24 09:00 05-Feb-24 16:00 7.29 Days
Continuous
7L32 (813s Little Smoky - 862s South Bezanson) Pole change from test and treat / X Arm change  
ATCO 29-Jan-24 09:00 05-Feb-24 16:00 7.29 Days
Continuous
7L40 (733s Simonette - 813s Little Smoky) 7l40 Line to ground mitigation  
ATCO 29-Jan-24 11:00 02-Feb-24 17:30 4.27 Days
Continuous
840s McNeill Station Transformer 701T has an active leak between the main tank and LTC tank requiring oil to be drained monthly in order to prevent surpassing safe operating maximum levels. Hitachi is coming to site to remove the diverter and replace O rings and gaskets in efforts to stop the leak. In addition, they wil  
ATCO 01-Feb-24 08:00 05-Feb-24 17:30 4.4 Days
Continuous
9L137 (838s Horizon Mining - 849s Joslyn Creek), 849s 904 (849s Joslyn Creek), 849s 905 (849s Joslyn Creek) This outage request is just to show the contraction of the Isolations that are referenced in 1-00425862  
BCH 05-Feb-24 09:00 09-Feb-24 17:00 4.33 Days
Continuous
2L294 (BCH A. A. Lambert - BCH Nelway) replace structures and lacing AB-BC
ENMAX, ALTALINK 05-Feb-24 09:15 08-Feb-24 16:45 3.31 Days
Continuous
937L (5s East Calgary - 102s Langdon), 5s 1552 (5s East Calgary), 5s 1652 (5s East Calgary), 5s 937 (5s East Calgary) SCADA upgrade  
ATCO, ALTALINK 12-Feb-24 09:00 15-Feb-24 16:30 3.31 Days
Continuous
7L50 (526s Buffalo Creek - 491L tap), 7L50 (757s Battle River - 491L tap) 7L50 Pole and arm replacement  
ATCO 12-Feb-24 09:00 18-Feb-24 16:00 6.29 Days
Continuous
7L32 (813s Little Smoky - 862s South Bezanson) Pole change from test and treat / X Arm change  
ALTALINK 12-Feb-24 09:30 15-Feb-24 16:45 3.3 Days
Continuous
916L (5s East Calgary - 42s Sarcee) SCADA Upgrade  
ATCO 12-Feb-24 11:00 06-May-24 14:00 84.08 Days
Continuous
813s 901 (813s Little Smoky) Take 901 OOS to open bus up and add a new 902PT, and 902 breaker bay for the new 9L201 line to MPC Gas.  
ATCO 13-Feb-24 09:00 17-Feb-24 17:00 4.33 Days
Continuous
7L85 (801s Anderson - ATC 803s Bullpound) 7L85 Line Mitigation. Replace/modify structures 19, 72, 86, 96, 138, 204, 206, 208, 238, 245, 249, 250.  
ATCO 18-Feb-24 09:00 22-Feb-24 17:00 4.33 Days
Continuous
7L85 (801s Anderson - ATC 803s Bullpound) 7L85 Line Mitigation. Replace/modify/install new structures, 335, 382, 383, 392, 397A, 409, 417, 447  
ATCO 19-Feb-24 14:30 04-Mar-24 14:00 13.98 Days
Continuous
863S 901, 9L27, 9L27 (755s Cordel - 863s Paintearth) 863S Paintearth Protection Upgrade
Demo old wiring, and old Line protection panel, install and terminate new wiring, and new Line protection panel. Commission new wiring/Line protection, and new Line protection panel.

Once GOI is released 901A will need to be commissioned.
 
ATCO, ALTALINK 20-Feb-24 09:00 22-Feb-24 16:30 2.31 Days
Continuous
7L50 (526s Buffalo Creek - 491L tap), 7L50 (757s Battle River - 491L tap) 7L50 Pole and arm replacement  
ENMAX, ALTALINK 20-Feb-24 09:15 22-Feb-24 16:45 2.31 Days
Continuous
936L (5s East Calgary - 102s Langdon) SCADA Upgrade  
ATCO 20-Feb-24 15:00 05-Mar-24 13:00 13.92 Days
Continuous
9L89, 885S 900 BUS 1, 885S 900PT1, 885S 900PT3, 885S 901, 885S 902, 9L89 (885s McMillan - 2011s Dawes), 885s 260kV Bus 900BS1 (885s McMillan) 885S McMillan sub Protection Upgrade: Complete protection cut over and Commissioning of new protection on 901,902,900PT1,9L89PT,9L89 Line Protection,900PT3.  
ATCO 26-Feb-24 09:00 04-Mar-24 16:00 7.29 Days
Continuous
7L32 (813s Little Smoky - 862s South Bezanson) Pole change from test and treat / X Arm change  
ENMAX, ALTALINK 26-Feb-24 09:30 01-Mar-24 12:30 4.13 Days
Continuous
5s T1 (5s East Calgary) SCADA Upgrade  
ENMAX, ALTALINK 26-Feb-24 09:30 01-Mar-24 12:30 4.13 Days
Continuous
5s T1 (5s East Calgary) Altalink Outage. SCADA Upgrade  
ALTALINK 26-Feb-24 13:00 08-Mar-24 12:00 10.96 Days
Continuous
676L (244s Bowmanton - 523s Bullshead), 244s 2152 (244s Bowmanton), 244s 2252 (244s Bowmanton), 523s 676 (523s Bullshead) Install and commission new circuits and protections pertaining to the Dunmore Project  
ENMAX, ALTALINK 04-Mar-24 09:30 08-Mar-24 12:30 4.13 Days
Continuous
5s T2 (5s East Calgary) SCADA Upgrade  
ENMAX, ALTALINK 04-Mar-24 09:30 08-Mar-24 12:30 4.13 Days
Continuous
5s T2 (5s East Calgary) Altalink Outage. SCADA Upgrade  
ATCO 04-Mar-24 14:30 18-Mar-24 15:00 13.98 Days
Continuous
9L948 (650s Hansman Lake - 863s Paintearth), 863s 902 (863s Paintearth) 863S Paintearth Protection Upgrade
Demo old wiring, and old Line protection panel, install and terminate new wiring, and new Line protection panel. Commission new wiring/Line protection, and new Line protection panel.

Once GOI is released 902A will need to be commissioned.
 
ATCO 11-Mar-24 09:00 18-Mar-24 16:00 7.29 Days
Continuous
7L32 (813s Little Smoky - 862s South Bezanson) Pole change from test and treat / X Arm change  
ALTALINK 11-Mar-24 12:15 15-Mar-24 17:45 4.23 Days
Continuous
702L (137s Sedgewick - 757s Battle River) FRM; Component Replacement (Str 11-197)  
ALTALINK 12-Mar-24 07:00 12-Mar-24 18:00 11 Hours
Daily
880L (321s Al Rothbauer - 523s Bullshead), 321s 880 (321s Al Rothbauer), 523s 880 (523s Bullshead) install and commission new circuits and protections pertaining to the Dunmore Project  
ATCO, ALTALINK 18-Mar-24 10:30 21-Mar-24 16:30 3.25 Days
Continuous
7L50 (526s Buffalo Creek - 491L tap), 7L50 (757s Battle River - 491L tap) 7L50 Pole and arm replacement  
ALTALINK 18-Mar-24 12:15 27-Mar-24 17:45 9.23 Days
Continuous
702L (137s Sedgewick - 757s Battle River) FRM; Component Replacement (Str 11-197)  
ATCO 18-Mar-24 14:30 29-Apr-24 14:00 41.98 Days
Continuous
863s 902T (863s Paintearth) protection upgrade, Commission new wiring/Transformer protection, and new Transformer protection panel  
ALTALINK 22-Mar-24 07:30 22-Mar-24 12:30 5 Hours
Daily
244s 152 (244s Bowmanton) Install and commission new circuits and protections pertaining to the Dunmore Project  
ALTALINK 25-Mar-24 07:00 27-Mar-24 18:00 2.46 Days
Continuous
925L (63s Red Deer - 74s Janet) Component Replacement between Structures #1 - 369  
ALTALINK 25-Mar-24 12:00 25-Mar-24 17:00 5 Hours
Daily
244s 452 (244s Bowmanton) Install and commission new circuits and protections pertaining to the Dunmore Project  
ALTALINK 26-Mar-24 12:30 26-Mar-24 17:30 5 Hours
Daily
244s 352 (244s Bowmanton) install and commission new circuits and protections pertaining to the Dunmore Project  
ALTALINK 27-Mar-24 07:30 27-Mar-24 12:30 5 Hours
Daily
244s 652 (244s Bowmanton) install and commission new circuits and protections pertaining to the Dunmore Project  
ENMAX 30-Mar-24 08:00 01-Apr-24 18:00 2.42 Days
Continuous
65.2TR (SS-65) HV SW Maint. SW141, SW135, SW86, SW93, SW87, MD138-65.2TR, MD240-65.2TR. 65.2TR Oil Sampling MT, TC. Check reversing switch. Gas Monitor Maintenance. Transformer Monitor Maintenance.  
ALTALINK 02-Apr-24 07:00 02-Apr-24 18:00 11 Hours
Daily
244s T1 (244s Bowmanton) install and commission new circuits and protections pertaining to the Dunmore Project  
ALTALINK 02-Apr-24 07:00 12-Apr-24 18:00 10.46 Days
Continuous
925L (63s Red Deer - 74s Janet) Component Replacement between Structures #1 - 369  
ENMAX 02-Apr-24 08:00 04-Apr-24 18:00 2.42 Days
Continuous
65.1TR (SS-65) HV SW Maint. SW130, SW136, SW88, SW80, SW81, SW83, MD138-65.1TR, MD240-65.1TR. 65.1TR Oil Sampling MT, TC. Check reversing switch. Gas Monitor Maintenance. Transformer Monitor Maintenance. Bus washing.  
ATCO 02-Apr-24 09:00 08-Apr-24 16:00 6.29 Days
Continuous
9L56 (720s Wabasca - 732s Mitsue) Line Mitigation ( Critical Crossing )  
ATCO 02-Apr-24 09:00 08-Apr-24 16:00 6.29 Days
Continuous
7L32 (813s Little Smoky - 862s South Bezanson) Pole replacement from Test and Treat  
ATCO 02-Apr-24 10:00 21-Apr-24 17:00 19.29 Days
Continuous
728s 701T (728s Mercer Hill) Replace Bkr 503 and 503B
Once 503/503B and all 501A, 502A, 503A solid blade switches are replaced and commissioned, restore 25kV bus, GOI can be shrunk to isolation points 7LA39D2 and 501TD
Continue with 701T protection upgrade, relocate 144 alarms, status, control to new station controller
 
ALTALINK 02-Apr-24 12:15 05-Apr-24 17:45 3.23 Days
Continuous
702L (137s Sedgewick - 757s Battle River) FRM; Component Replacement (Str 11-197)  
ALTALINK 02-Apr-24 12:30 11-Apr-24 16:00 9.15 Days
Continuous
158s T2 (158s Vauxhall) 158sT2 Oil Reclaim/Tx leak repair  
ALTALINK 03-Apr-24 07:00 03-Apr-24 18:00 11 Hours
Daily
244s T2 (244s Bowmanton) install and commission new circuits and protections pertaining to the Dunmore Project  
ALTALINK 03-Apr-24 08:30 03-Apr-24 17:30 9 Hours
Daily
613L (103s Goose Lake - 396s Pincher Creek) Clean/Grease 103s21 & 103s1352,103s1452 First Trips on return switching.  
ENMAX, ALTALINK 05-Apr-24 08:00 06-Apr-24 16:00 1.33 Days
Continuous
1109L (SS-25 - SS-65), 25B240-D141 (SS-25), 25B240-D142 (SS-25) HV SW Maint. MD-1109, SW152, SW153. Power Factor Test - 25PT240-985  
ENMAX, ALTALINK 07-Apr-24 08:00 08-Apr-24 16:00 1.33 Days
Continuous
1080L (SS-25 - SS-65), 25B240-D139 (SS-25), 25B240-D138 (SS-25) HV SW Maint. MD-1080, SW147, SW146. Power Factor Test - 25PT240-1080  
ENMAX, ALTALINK 09-Apr-24 08:00 10-Apr-24 16:00 1.33 Days
Continuous
985L (74s Janet - SS-25) HV SW Maint. MD-985, SW135, SW134. Summer Substation Washing. D133, D132, MD-985  
ENMAX 09-Apr-24 08:00 12-Apr-24 18:00 3.42 Days
Continuous
240kV West Bus (SS-25), 25B240-D142 (SS-25), 25B240-D139 (SS-25), 25B240-D136 (SS-25), 25B240-D133 (SS-25) Summer Substation Washing. Outage required for washing stand off insulators near transmission lines.  
ENMAX, ALTALINK 11-Apr-24 08:00 12-Apr-24 16:00 1.33 Days
Continuous
1003L (74s Janet - SS-25), 25B240-D136 (SS-25), 25B240-D135 (SS-25) HV SW Maint. MD-1003, SW141, SW140. Power Factor Test - 25PT240-1003. Summer Substation Washing. D136, D135, MD-1003  
ALTALINK 15-Apr-24 07:00 19-Apr-24 18:00 4.46 Days
Continuous
925L (63s Red Deer - 74s Janet) Component Replacement between Structures #1 - 369  
EPCOR 15-Apr-24 07:00 22-Apr-24 07:00 7 Days
Continuous
816s P2402 (816s Petrolia), 816s P2401 (816s Petrolia), 816s T1 (816s Petrolia) Petrolia: P2401 Breaker LCR  
ATCO 15-Apr-24 09:00 22-Apr-24 16:00 7.29 Days
Continuous
7L32 (813s Little Smoky - 862s South Bezanson) Pole replacement from Test and Treat  
ALTALINK 15-Apr-24 13:30 19-Apr-24 17:00 4.15 Days
Continuous
28s T2 (28s West Brooks) 28sT2 PRC5, Leak repair, Maintenance.  
ENMAX 16-Apr-24 08:00 16-Apr-24 13:00 5 Hours
Continuous
2GSU-XF-001 (SS-25) Summer Substation Washing  
ENMAX 17-Apr-24 08:00 17-Apr-24 18:00 10 Hours
Continuous
1GSU-XF-001 (SS-25) Summer Substation Washing  
ENMAX, ALTALINK 18-Apr-24 13:00 18-Apr-24 18:00 5 Hours
Daily
1003L (74s Janet - SS-25) Summer Substation Washing. D136, D135, MD-1003.  
ALTALINK 22-Apr-24 07:00 25-Apr-24 18:00 3.46 Days
Continuous
925L (63s Red Deer - 74s Janet) Component Replacement between Structures #1 - 369  
EPCOR 22-Apr-24 07:00 10-May-24 17:00 18.42 Days
Continuous
816s P2401 (816s Petrolia) Petrolia: P2401 Breaker LCR  
ALTALINK 23-Apr-24 08:30 23-Apr-24 13:30 5 Hours
Daily
15s 463 (15s Fort Macleod), 463L (15s Fort Macleod - 463AL tap) 15s463 PRC 5 First Trip and maint.  
ALTALINK 23-Apr-24 09:00 30-Apr-24 18:00 7.38 Days
Continuous
492s T1 (492s Monarch) Doble, SFRA, maintenance, oil leaks and P5 breaker maintenance. s455X U/G cable repair. 492s6 inoperable repairs.  
ATCO 29-Apr-24 14:30 10-Jun-24 14:00 41.98 Days
Continuous
863S 504, 863S 901T, 863S Station Service, 863S 500PT2X, 863S 500PT2Y, 863s 901T (863s Paintearth) 863S Paintearth Protection Upgrade  
ATCO 06-May-24 09:00 19-May-24 17:30 13.35 Days
Continuous
2029S BUILDING VALVE HALL, 2029s 1205 (2029s Heathfield), 2029s 1206 (2029s Heathfield) Annual EATL outage at 2075s & 2029s.

2029s & 2075s AC & DC O&M.

USE 2-70212 FOR 13L50 GOI
USE 2-70213 FOR 2029s GOI
USE 2-70214 FOR 2075s GOI
 
ATCO 06-May-24 09:00 19-May-24 17:30 13.35 Days
Continuous
2075S BUILDING VALVE HALL, 2075s 916 (2075s Newell), 2075s 917 (2075s Newell) Annual EATL outage at 2075s & 2029s.

2029s & 2075s AC & DC O&M.

USE 2-70212 FOR 13L50 GOI
USE 2-70213 FOR 2029s GOI
USE 2-70214 FOR 2075s GOI
 
ATCO 06-May-24 09:00 19-May-24 17:30 13.35 Days
Continuous
13L50 (DC LINK), 13L50 (2029s Heathfield - 2075s Newell) Annual EATL outage at 2075s & 2029s.

2029s & 2075s AC & DC O&M.

USE 2-70212 FOR 13L50 GOI
USE 2-70213 FOR 2029s GOI
USE 2-70214 FOR 2075s GOI
 
ATCO 06-May-24 14:00 20-May-24 14:00 14 Days
Continuous
813s 901 (813s Little Smoky), 9L05 (809s Louise Creek - 813s Little Smoky), 813s 904 (813s Little Smoky) 903PT, 904, and 9L05 OOS to cut over 904 trips to new protection.  
ATCO 13-May-24 10:00 22-May-24 10:00 9 Days
Continuous
9L16, 9L16 (755s Cordel - 972s Tinchebray) Upgrade 9L16 21A and 21B relays at both 755S Cordel and 972S Tinchebray.
Connect new 9LA16 to new 620S Goldeye substation
 
EPCOR 21-May-24 07:00 14-Jun-24 17:00 24.42 Days
Continuous
816s P2402 (816s Petrolia) Petrolia: P2402 Breaker LCR  
SUNCOR 29-May-24 08:00 14-Jun-24 18:00 16.42 Days
Continuous
29PT-232 29PT-240, 29EDD-71 29PT-232 (29EDD-71), 29PL7-4 (29EDD-65 - 29EDD-71), 29EDD-71 29PS-243 (29EDD-71 Edd71Sub), 29EDD-71 29PS-242 (29EDD-71 Edd71Sub), 29EDD-71 752-4623 (29EDD-71) FB - 29EDD-71,29PS-0242 REPLACE / REPAIR, 29PL7-4 ;29PS-243 REPLACE SWITCH, 29EDD71;29PT-232 SYSTEM;PM 5Y (46756865)
29EDD-71;144KV NODE,29PT-240 (46699353), 29EDD71;29-752-4623 MAINT & TEST;PM 10y

 
ATCO 03-Jun-24 08:00 14-Jun-24 17:30 11.4 Days
Continuous
12L41 (510s Sunnybrook - 939s Livock), 12L44 (939s Livock - 951s Thickwood Hills) APL O&M outage

Use 2-70262 for 12L44 GOI
Use 2-70263 for 939s-APL GOI
Use 2-70264 for 951s-APL GOI
APL O&M outage

Use 2-70262 for 12L44 GOI
Use 2-70263 for 939s-APL GOI
Use 2-70264 for 951s-APL GOI
 
SUNCOR 04-Jun-24 08:00 18-Jun-24 18:00 14.42 Days
Continuous
29PL6-22 (29EDD-1 Millennium - 29EDD-2 Tar Island), 29EDD-2 29PT-3 (29EDD-2 Tar Island) isolation and PM and corrective on 29PP-1/2 buses. for this isolation there will be momentary loss during switching once for PL6-32 once the ring bus is closed this will come back online.  
ALTALINK 10-Jun-24 08:00 11-Jun-24 17:00 1.38 Days
Continuous
676L (244s Bowmanton - 523s Bullshead) OPGW will be cut and spliced into to bring the fiber down for the new 1011s Dunmore Substation  
CNRL, ATCO 10-Jun-24 08:00 17-Jun-24 07:00 6.96 Days
Continuous
859s 52G (859s Primrose), 859s 701T (859s Primrose), 859s Protection & Control (859s Primrose)
701T will be isolated to start work on 25kV switchgear project - 501TD will be left open after the outage.
70T1 XFMR Diff relay and 144kV overcurrent relay will have settings changes for PRC-025 compliance.
 
EPCOR 24-Jun-24 07:00 19-Jul-24 17:00 25.42 Days
Continuous
816s P2403 (816s Petrolia) Petrolia: P2403 Breaker LCR  
ALTALINK 02-Jul-24 12:30 11-Jul-24 15:30 9.13 Days
Continuous
370s T5 (370s North Lethbridge) 370sT5 Maintenance 370s2252 Maint.  
ATCO 03-Jul-24 09:00 08-Sep-24 11:00 67.08 Days
Continuous
848S 601, 848S 602, 848S 607, 848S 608, 848S 900BS1, 848S 901T, 848s 240kV Bus 900BS1 (848s Ruth Lake), 848s 901T (848s Ruth Lake) 848S Ruth Lake Substation Rebuild: Upgrading protection to IEC 61850, Replace breaker 401. Cut over to new protection, Install oil containment for 901T. Pull all new outdoor cable, modify cable tray, install new cable tray.  
ATCO 09-Jul-24 10:00 01-Aug-24 17:00 23.29 Days
Continuous
9L24 (946s Oakland - 959s Lanfine), 959s 906 (959s Lanfine), 959s 905 (959s Lanfine), 946s 902 (946s Oakland), 946s 903 (946s Oakland) Replace A/B protection relays at 959S Lanfine and 946S Oakland
Cut in and reroute 9L24
Connect new 9LA24 T-tap
Commission Telecom and Protection to new 1072S Rose Lynn substation
 
ENMAXEC 15-Jul-24 08:00 19-Jul-24 18:00 4.42 Days
Continuous
383s T1 (383s Kettles Hill Windfarm), 383s T2 (383s Kettles Hill Windfarm) substation maintenance  
ALTALINK 16-Jul-24 07:00 18-Jul-24 19:30 2.52 Days
Continuous
1148L (251s Whitla - 1018s Shamrock) Annual Substation Maintenance Outage  
EPCOR 29-Jul-24 07:00 23-Aug-24 17:00 25.42 Days
Continuous
816s P2404 (816s Petrolia) Petrolia: P2404 Breaker LCR  
ATCO 04-Aug-24 10:00 04-Aug-24 17:00 7 Hours
Continuous
801S 902, 801s 902 (801s Anderson) Final connection of Bkr 902/52a single pole status inputs to DFR, Commission  
ATCO 06-Aug-24 10:00 01-Sep-24 15:00 26.21 Days
Continuous
741s 702T (741s Fox Creek), 7L199 (347s AML Fox Creek - 741s ATC Fox Creek), 741s 702 (741s ATC Fox Creek), 741s 705C (741s Fox Creek) Demo 144kV bus and structures up to J1, install new foundations, steel structures up to J1, Demo old PT, Replace gang switches 7L199D1 & 702A, string new overhead bus and connect equipment.
Complete protection upgrade & Commissioning activities to accommodate 7L199 upgrade and 7LA199 T-Tap.
 
ATCO 07-Aug-24 08:00 19-Aug-24 10:01 12.08 Days
Continuous
788S 701T, 788s 701T (788s Hotchkiss) Remove 701TCS, add NEW 707 breaker and switch 707A. Add NEW 701T  
ATCO 13-Aug-24 10:00 13-Aug-24 17:00 7 Hours
Continuous
801S 903, 801s 903 (801s Anderson) Final connection of Bkr 903 52a single pole status inputs to DFR, Commission  
ATCO 14-Aug-24 10:00 14-Aug-24 17:00 7 Hours
Continuous
801S 904, 801s 904 (801s Anderson) Final connection of Bkr 904 52a single pole status inputs to DFR, Commission  
ATCO 15-Aug-24 10:00 15-Aug-24 17:00 7 Hours
Continuous
801s 905 (801s Anderson) Final connection of Bkr 905 52a single pole status inputs to DFR, Commission  
ATCO 16-Aug-24 10:00 16-Aug-24 17:00 7 Hours
Continuous
801s 906 (801s Anderson) Final connection of Bkr 906 52a single pole status inputs to DFR, Commission  
ATCO 17-Aug-24 10:00 17-Aug-24 17:00 7 Hours
Continuous
801s 907 (801s Anderson) Final connection of Bkr 907 52a single pole status inputs to DFR, Commission  
ATCO 18-Aug-24 10:00 18-Aug-24 17:00 7 Hours
Continuous
801s 908 (801s Anderson) Final connection of Bkr 908 52a single pole status inputs to DFR, Commission  
ATCO 27-Aug-24 10:00 27-Aug-24 17:00 7 Hours
Continuous
801s 909 (801s Anderson) Final connection of Bkr 909 52a single pole status inputs to DFR, Commission  
ATCO 28-Aug-24 10:00 28-Aug-24 17:00 7 Hours
Continuous
801s 910 (801s Anderson) Final connection of Bkr 910 52a single pole status inputs to DFR, Commission  
ATCO 29-Aug-24 10:00 29-Aug-24 17:00 7 Hours
Continuous
801s 911 (801s Anderson) Final connection of Bkr 911 52a single pole status inputs to DFR, Commission  
ATCO 30-Aug-24 10:00 30-Aug-24 17:00 7 Hours
Continuous
801s 912 (801s Anderson) Final connection of Bkr 912 52a single pole status inputs to DFR, Commission  
ALTALINK 02-Sep-24 07:30 02-Sep-24 12:00 4.5 Hours
Daily
1202L (89s Ellerslie - 320p Keephills), 320p 3152 (320p Keephills), 320p 3052 (320p Keephills) Connect Summated 1202L CT from 320p3152 & 320p3052 to new PMU  
ALTALINK, EPCOR 02-Sep-24 12:00 02-Sep-24 16:30 4.5 Hours
Daily
1203L (320p Keephills - 510s Sunnybrook), 320p 3452 (320p Keephills), 320p 2952 (320p Keephills) Connect Summated 1203L CT from 320p3452 & 320p2952 to new PMU  
EPCOR 03-Sep-24 07:00 10-Sep-24 07:00 7 Days
Continuous
816s T1 (816s Petrolia), 816s P2404 (816s Petrolia), 816s P2405 (816s Petrolia) Petrolia: P2405 Breaker LCR  
ALTALINK 03-Sep-24 07:30 03-Sep-24 12:00 4.5 Hours
Daily
1045AL (320p Keephills - 1045L tap), 320p 1352 (320p Keephills) Connect 1045AL CT from 320p1352 to new PMU  
ALTALINK, EPCOR 03-Sep-24 12:00 03-Sep-24 16:30 4.5 Hours
Daily
1043L (320p Keephills - 367s Harry Smith), 320p 252 (320p Keephills), 320p 352 (320p Keephills) Connect Summated 1043L CT from 320p252 & 320p352 to new PMU  
ALTALINK 04-Sep-24 07:30 04-Sep-24 12:00 4.5 Hours
Daily
190L (17s Benalto - 320p Keephills), 320p 652 (320p Keephills), 320p 552 (320p Keephills) Connect Summated 190L CT from 320p552 & 320p652 to new PMU  
ALTALINK, EPCOR 04-Sep-24 12:00 04-Sep-24 16:30 4.5 Hours
Daily
930L (37s North Calder - Poundmaker), 320p 2052 (320p Keephills), 320p 2152 (320p Keephills) Connect Summated 903L CT from 320p2052 & 320p2152 to new PMU  
EPCOR 10-Sep-24 07:00 27-Sep-24 17:00 17.42 Days
Continuous
816s P2405 (816s Petrolia) Petrolia: P2405 Breaker LCR  
ATCO 10-Sep-24 09:00 02-Dec-24 11:00 83.13 Days
Continuous
848S 603, 848S 604, 848S 605T, 848S 606, 848S 848-501, 848S 848-504, 848S 848S 500BS2 25kv Protection System, 848S 900BS2, 848S 902T, 848s 240kV Bus 900BS2 (848s Ruth Lake), 848s 902T (848s Ruth Lake) 848S Ruth Lake Substation Rebuild: upgrading protection to IEC 61850, Replace breakers 603 & 604. Cut over to new protection: Install oil containment for 902T. Pull all new outdoor cable, modify cable tray, install new cable tray.  
ATCO 16-Sep-24 08:00 29-Sep-24 17:00 13.38 Days
Continuous
788s 703 (788s Hotchkiss), 7L63 (788s Hotchkiss - 7LA63 tap) 703 breaker replacement  
ALTALINK 23-Sep-24 08:00 04-Oct-24 18:00 11.42 Days
Continuous
1201L (520s Bennett - BCH Cranbrook) Maintenance tasks str range 18-513.  
ALTALINK, EPCOR 07-Oct-24 00:00 18-Oct-24 00:00 11 Days
Continuous
908L (89s Ellerslie - 816s Petrolia), 1044L (EP 805s Jasper - 816s Petrolia) Petrolia: P2406 Breaker LCR  
ALTALINK, EPCOR 07-Oct-24 09:30 18-Oct-24 17:00 11.31 Days
Continuous
1044L (EP 805s Jasper - 816s Petrolia), 908L (89s Ellerslie - 816s Petrolia), 816s P2401 (816s Petrolia), 816s P2405 (816s Petrolia), 816s P2406 (816s Petrolia) Petrolia: P2406 Breaker LCR  
EPCOR 18-Oct-24 17:00 01-Nov-24 17:00 14 Days
Continuous
816s P2406 (816s Petrolia) Petrolia: P2406 Breaker LCR  
ATCO 11-Nov-24 10:00 25-Nov-24 17:00 14.29 Days
Continuous
9L100 (801s Anderson - 807s Sheerness) Replace Breaker 902 @ 807S Sheerness, complete line 21A, 21B/9L100 protection upgrade and Commissioning  
ATCO 17-Feb-25 08:00 20-Feb-25 17:00 3.38 Days
Continuous
7L128 (802s Michichi Creek - 7LA128 tap) Installation of dynamic line rating sensors.  
ATCO 24-Mar-25 08:00 27-Mar-25 17:00 3.38 Days
Continuous
7L91 (715s Leming Lake - 826s Marguerite Lake) Cold Lake Area Energy Centre Project
Cutover CT/PT/P&C ccts for new Thermal RAS relays
Complete commissioning 49A/49B/7L91 relays
End-to-end testing to 1064S
 
ATCO 29-Apr-25 10:00 20-May-25 17:00 21.29 Days
Continuous
9L99 (801s Anderson - 807s Sheerness) Replace Breaker 901 @ 807S Sheerness, complete line 21A, 21B/9L99 protection upgrade and Commissioning  
ATCO 05-May-25 09:00 30-May-25 17:30 25.35 Days
Continuous
2029S BUILDING VALVE HALL, 2029s 1205 (2029s Heathfield), 2029s 1206 (2029s Heathfield) Annual EATL outage at 2075s & 2029s.

2029s & 2075s AC & DC O&M.

USE 2-70215 FOR 13L50 GOI
USE 2-70216 FOR 2029s GOI
USE 2-70217 FOR 2075s GOI
 
ATCO 05-May-25 09:00 30-May-25 17:30 25.35 Days
Continuous
2075S BUILDING VALVE HALL, 2075s 916 (2075s Newell), 2075s 917 (2075s Newell) Annual EATL outage at 2075s & 2029s.

2029s & 2075s AC & DC O&M.

USE 2-70215 FOR 13L50 GOI
USE 2-70216 FOR 2029s GOI
USE 2-70217 FOR 2075s GOI
 
ATCO 05-May-25 09:00 30-May-25 17:30 25.35 Days
Continuous
13L50 (DC LINK), 13L50 (2029s Heathfield - 2075s Newell) Annual EATL outage at 2075s & 2029s.

2029s & 2075s AC & DC O&M.

USE 2-70215 FOR 13L50 GOI
USE 2-70216 FOR 2029s GOI
USE 2-70217 FOR 2075s GOI
 
ATCO, Syncrude 20-May-25 09:00 12-Jun-25 10:00 23.04 Days
Continuous
848S 910, 848S 911, 848S RL1 SYNCRUDE ISLANDING RAS (IRAS), RL1 (848s Ruth Lake - D05) 848S Ruth Lake Sub rebuild/upgrade protection to IEC 61850 - Cut over to new protection: 910CT,910,910B,910PT,RL-1D1,911B,911,911CT.  
ATCO 12-Jun-25 11:00 04-Jul-25 09:00 21.92 Days
Continuous
848S 911, 848S 913, 9L01 (848s Ruth Lake - 951s Thickwood Hills), 848s 911 (848s Ruth Lake), 848s 913 (848s Ruth Lake) 848S Ruth Lake Sub rebuild/upgrade protection to IEC 61850 - Cut over to new protection: 911,911CT,912B,9L01D1,913PT,913B,913,913CT  
ATCO 04-Jul-25 11:00 24-Jul-25 09:00 19.92 Days
Continuous
848S 905, 848S 906, 9L23 (848s Ruth Lake - 977s Salt Creek), 848s 905 (848s Ruth Lake), 848s 906 (848s Ruth Lake) 848S Ruth Lake Sub rebuild/upgrade protection to IEC 61850 - Cut over to new protection: 905CT,905,905B,905PT,9L23D1,906B,906,906CT,906A.  
ATCO, SUNCOR 24-Jul-25 11:00 14-Aug-25 09:00 20.92 Days
Continuous
848S 906, 848S 903, 848S 29PL9-1 SUNCOR ISLANDING RAS (IRAS), 29PL9-1 (29EDD-1 Millennium - 848s Ruth Lake), 848s 903 (848s Ruth Lake), 848s 906 (848s Ruth Lake) 848S Ruth Lake Sub rebuild/upgrade protection to IEC 61850 - Cut over to new protection: 906,906CT,904B,29PL9-1D1,903PT,903B,903,903CT.  
ATCO, SUNCOR 14-Aug-25 11:00 04-Sep-25 09:00 20.92 Days
Continuous
848S 901, 848S 902, 848S 29PL9-2 SUNCOR ISLANDING RAS (IRAS), 29PL9-2 (29EDD-1 Millennium - 848s Ruth Lake), 848s 901 (848s Ruth Lake), 848s 902 (848s Ruth Lake) 848S Ruth Lake Sub rebuild/upgrade protection to IEC 61850 - Cut over to new protection: 901CT,901,901B,901PT,29PL9-2D1,902B,902,902CT.  
ATCO, Syncrude 04-Sep-25 11:00 25-Sep-25 09:00 20.92 Days
Continuous
848S 902, 848S 907, 848s 902 (848s Ruth Lake), 848s 907 (848s Ruth Lake), RL2 (848s Ruth Lake - D05) 848S Ruth Lake Sub rebuild/upgrade protection to IEC 61850 - Cut over to new protection: 902,902CT,902A,902PT,RL-2D1,907A,907CT,907.  
ATCO 25-Sep-25 11:00 17-Oct-25 14:00 22.13 Days
Continuous
848S 907, 848S 908, 9L58 (848s Ruth Lake - 888s Dover), 848s 907 (848s Ruth Lake), 848s 908 (848s Ruth Lake) 848S Ruth Lake Sub rebuild/upgrade protection to IEC 61850 - Cut over to new protection: 907CT,907,907B,9L58D2,908PT,908B,908,908CT.  

AB-BC, AB-SK & AB-MATL: refer to AESO web posting: http://itc.aeso.ca/itc/public/atc
Also,
AB-BC, AB-SK & AB-MATL: refer to ISO Rule 203.6: http://www.aeso.ca/rulesprocedures/18592.html

Prepared On: 2023-11-29   15:12:41


This document and the information contained herein are based upon information and data which by their nature contain a degree of uncertainty and are subject to change. In addition, this document may contain information and data from public sources and/or third parties, which have been assumed to be accurate and complete and have not been verified. Accordingly, the Independent System Operator, operating as the Alberta Electric System Operator (the "AESO") makes no warranty, representation or guarantee, express or implied, with respect to this document or the information contained herein, including, but not limited to, any warranty, representation or guarantee of accuracy, completeness, timeliness, reliability, availability, absence of computer virus, non- infringement, merchantability or suitability for any purpose. Under no circumstances will the AESO, its members, officers, employees, contractors or agents, or any of their respective affiliates, be liable for any errors or omissions in, or any losses, damages or claims whatsoever, whether in contract, tort or otherwise, arising from use of or reliance upon, this document or any information contained herein.