Alberta Electric System Operator | |
Long Range Significant Transmission Outages for the period of 24 months starting 2025-08-30 | |
The table below contains the significant transmission outages submitted as tentative to the AESO. These Outages have not yet necessarily been approved, but are listed for awareness and coordination purposes. An Outage has been considered significant for this table if it meets any one (1) or more of the following criteria: |
|
|
|
Note: Where a transmission outage requires generation curtailments, the adjustments to generation will typically happen in the hours before the scheduled transmission outage and in the hour after the element is returned to service. | |
Previous Version | |
Download CSV | |
Owner | From | To | Duration | Element | Scheduled Activity | Affected Intertie |
---|---|---|---|---|---|---|
EPCOR | 31-Mar-25 07:00 | 03-Oct-25 17:00 | Continuous |
186.42 Days
987s T1 (987s Clover Bar), 987s CCP7213 (987s Clover Bar), 987s CCP7214 (987s Clover Bar) | Cloverbar - TX1 LCR | |
NWE | 16-Jul-25 07:00 | 19-Sep-25 17:00 | 65.42 Days
Continuous |
2366 (NWE Marias) | install new equipment at Marias | AB-MATL |
ALTALINK | 17-Jul-25 08:30 | 31-Aug-25 16:30 | 45.33 Days
Daily |
74s C3 (74s Janet) | forced outage | |
ALTALINK, TRANSALTA | 29-Jul-25 08:00 | 25-Sep-25 17:00 | 58.38 Days
Continuous |
33s 2 (33s Spray), 33s T2 (33s Spray) | maintenance | |
ATCO | 02-Aug-25 23:30 | 12-Sep-25 18:00 | 40.77 Days
Continuous |
827s SVC (827s Cranberry Lake) | forced outage | |
ALTALINK | 14-Aug-25 14:00 | 25-Sep-25 17:00 | 42.13 Days
Continuous |
33s 3 (33s Spray) | condition assessment and T1 compliance testing | |
ATCO | 18-Aug-25 14:01 | 01-Sep-25 14:00 | 14 Days
Continuous |
732s 902T (732s Mitsue), 732s 503R (732s Mitsue), 732s 704 (732s Mitsue), 732s 705 (732s Mitsue), 732s 901 (732s Mitsue), 732s 906 (732s Mitsue), 732s 702TD (732s Mitsue), 732s 902TD (732s Mitsue), 732s 906A (732s MItsue), 732s 901A (732s MItsue) | protection upgrade | |
ALTALINK | 20-Aug-25 08:00 | 01-Sep-25 17:00 | 12.38 Days
Continuous |
799s 138kV Bus (799s Coleman), 170L (632s Russell - 799s Coleman), 799s T3 (799s Coleman), 799s 170E (799s Coleman) | remove s29 from foundation, repair foundation, install s29 and adjust, remove 25kV temp feed | AB-BC |
SUNCOR | 28-Aug-25 08:00 | 16-Sep-25 20:00 | 19.5 Days
Continuous |
29PL9-24 (29EDD-94 Voyageur - 29EDD-60 Inglis Island), 29EDD-60 29PT-702 (29EDD-60 Inglis Island), 29EDD-60 30-252-400001 (29EDD-60 Inglis Island) | 29pt-702 - repair / replace burned bonding conductor (9000807989) | |
ENMAX, ALTALINK | 30-Aug-25 08:00 | 30-Aug-25 12:00 | 4 Hours
Continuous |
28.80L (42s Sarcee - SS-28), 28.2TR (SS-28) | Substation - Insulator Washing (Fall) | |
ENMAX, ALTALINK | 30-Aug-25 08:00 | 30-Aug-25 12:00 | 4 Hours
Daily |
28.80L (42s Sarcee - SS-28) | Substation - Insulator Washing (Fall) | |
ATCO | 01-Sep-25 14:01 | 15-Sep-25 14:00 | 14 Days
Continuous |
732s 902T (732s Mitsue), 732s 503R (732s Mitsue) | Protection upgrade. Remove old protection, cut over to new protection and cut over equipment status, control and alarms to new station controller. | |
ATCO, ALTALINK | 02-Sep-25 07:00 | 10-Sep-25 18:00 | 8.46 Days
Continuous |
1036L (356s Milo - 554s Travers) | South Crew will be doing component replacement on 1036L (STR 5 - 101)See also 294976 1005L RB required due to proximity | |
EPCOR | 02-Sep-25 07:00 | 14-Sep-25 17:00 | 12.42 Days
Continuous |
EP 803s T2 (EP 803s Lambton), EP 803s L2402 (EP 803s Lambton), EP 803s L2405 (EP 803s Lambton) | Lambton: LAB2 LCR and TX2 Zone Doble and LDS4/LDS9 Disconnect and Tap Changer Maintenance | |
EPCOR | 02-Sep-25 07:00 | 26-Sep-25 17:00 | 24.42 Days
Continuous |
805s T1 (805s Jasper) | Jasper: TX1 Bushing Replacement (PCB) | |
EPCOR | 02-Sep-25 07:00 | 12-Oct-25 17:00 | 40.42 Days
Continuous |
557s T2 (557s Castle Downs) | Castle Downs S/S Tx2 Bay Outage | |
ALTALINK | 02-Sep-25 07:30 | 12-Sep-25 16:00 | 10.35 Days
Continuous |
1325L (510s Sunnybrook - AML 511s Crossings) | 510s DIW Piping Repair, Annual Link Outage for various maintenance. | |
BCH | 02-Sep-25 09:00 | 05-Sep-25 17:00 | 3.33 Days
Continuous |
5L91 (BCH Ashton Creek - BCH Selkirk) | replace marker balls | AB-BC |
BCH | 02-Sep-25 09:00 | 17-Sep-25 09:00 | 15 Days
Continuous |
T3 (BCH Natal), 12CB23 (BCH Natal) | natal substation replacement and ETM install | AB-BC |
ATCO | 02-Sep-25 10:00 | 12-Sep-25 17:00 | 10.29 Days
Daily |
9L16 (755s Cordel - 972s Tinchebray) | Install foundations for new 9L16 structures 73 and 74 in preparation of the future line bay re-termination into 972S Tinchebray expansion. Will return line to service in the evenings |
|
BCH | 02-Sep-25 10:00 | 01-Oct-25 15:00 | 29.21 Days
Continuous |
5L72 (BCH Mica G.S. - BCH Nicola) | MCA 500kV Switching Outage for Opening 5D5 for D12Y & Project work. | AB-BC |
BCH | 02-Sep-25 10:00 | 01-Oct-25 16:00 | 29.25 Days
Continuous |
5L72 (BCH Mica G.S. - BCH Nicola) | MCA F26 AOP Placeholder | |
BCH | 02-Sep-25 10:00 | 01-Oct-25 16:00 | 29.25 Days
Continuous |
5L72 (BCH Mica G.S. - BCH Nicola) | MCA 5CB9 Project GM-0463 | |
ALTALINK | 02-Sep-25 11:00 | 02-Sep-25 15:00 | 4 Hours
Daily |
801L (62s Brazeau Plant - 294s Brazeau Plant Outlet Works) | high side mobile disconnect | |
ALTALINK, GLPC | 02-Sep-25 12:00 | 02-Sep-25 17:00 | 5 Hours
Daily |
688L (199s East Airdrie - 688BL tap), 1055s T1 (1055s Sollair) | Replace PCB Lighting fixtures located within LOA at 199s | |
ALTALINK | 03-Sep-25 07:30 | 03-Sep-25 12:00 | 4.5 Hours
Daily |
71s 138kV East Bus (71s Lamoureux), 71s 240kV East Bus (71s Lamoureux), 71s T2 (71s Lamoureux), 71s 852 (71s Lamoureux), 71s 452 (71s Lamoureux), 71s 1752 (71s Lamoureux), 71s 1452 (71s Lamoureux) | Exercising all equipment within this GOI and documenting any potential issues prior to start of new DOW Project | |
ATCO | 03-Sep-25 08:00 | 03-Sep-25 16:00 | 8 Hours
Continuous |
7L58 (789s Keg River - 905s Meikle) | Emergency Pole replacement on 7L58 fire restoration This is rescheduled from the cancelled 1-00498577 due to inclemant weather |
|
ATCO | 03-Sep-25 09:00 | 11-Sep-25 08:00 | 7.96 Days
Continuous |
951S 907 (951s Thickwood Hills) | Installation of new POW relay/Protection | |
ATCO | 03-Sep-25 09:30 | 04-Sep-25 17:30 | 1.33 Days
Continuous |
802s 704 (802s Michichi Creek), 7L128 (802s Michichi Creek - 7LA128 tap) | BREAKER MIN OIL HLR PARTIAL TESTING - BREAKER 704 @ 802S | |
ALTALINK, EPCOR | 03-Sep-25 12:01 | 03-Sep-25 15:30 | 3.48 Hours
Daily |
71s 138kV West Bus (71s Lamoureux), 71s 240kV West Bus (71s Lamoureux), 71s T1 (71s Lamoureux), 921L (71s Lamoureux - 987s Clover Bar), 781L (71s Lamoureux - 172s Sherritt), 71s 252 (71s Lamoureux), 71s 152 (71s Lamoureux), 71s 1352 (71s Lamoureux), 71s 1252 (71s Lamoureux) | Exercising all equipment within this GOI and documenting any potential issues prior to start of new DOW Project | |
ALTALINK | 03-Sep-25 13:30 | 04-Sep-25 16:30 | 27 Hours
Continuous |
370s 2152 (370s North Lethbridge), 370s T3 (370s North Lethbridge) | First Trip, Breaker Maint. and investigate T3 oil leak. | |
ALTALINK, EPCOR | 03-Sep-25 15:31 | 03-Sep-25 17:30 | 119 Mins
Daily |
71s 1552 (71s Lamoureux), 71s 1652 (71s Lamoureux), 920L (71s Lamoureux - 557s Castle Downs) | Exercising all equipment within this GOI and documenting any potential issues prior to start of new DOW Project | |
ALTALINK | 06-Sep-25 12:01 | 06-Sep-25 16:30 | 4.48 Hours
Daily |
71s 1452 (71s Lamoureux), 71s 1352 (71s Lamoureux), 71s 997E (71s Lamoureux), 997L (71s Lamoureux - 430s Ursus) | Remove PCB ballast fixture on steel structure adjacent to 71s997E. Isolations required to allow for safe limits of approach for removal | |
ATCO | 07-Sep-25 09:00 | 10-Sep-25 17:00 | 3.33 Days
Continuous |
951s 1205 (951s Thickwood Hills) | 1205 Outage for POW relay addition project | |
EPCOR | 08-Sep-25 07:00 | 09-Sep-25 17:00 | 1.42 Days
Continuous |
52s T1 (52s East Industrial) | East Industrial: TX1 - MV Protection Upgrade Cutovers | |
ALTALINK, EPCOR | 08-Sep-25 07:00 | 12-Sep-25 17:00 | 4.42 Days
Continuous |
947L (89s Ellerslie - 987s Clover Bar), 987s C2402 (987s Clover Bar), 987s C2404 (987s Clover Bar) | Cloverbar: 947L Zone Doble and CDS27/CDS28/CDS29 Disconnect Maintenance | |
ALTALINK, EPCOR | 08-Sep-25 07:00 | 13-Sep-25 17:00 | 5.42 Days
Continuous |
657s SU2403 (657s Summerside), 657s SU2402 (657s Summerside), 657s T2 (657s Summerside) | Summerside: TX2 Zone Doble and Disconnect Maintenance | |
ATCO, ALBIAN | 08-Sep-25 08:00 | 09-Sep-25 16:00 | 1.33 Days
Continuous |
919s 908 (919s Hartley) | CNRL requested outage to breaker 908 at 919S to remove potential for Protection trips during function testing of new G60-A relay. | |
Lethbridge | 08-Sep-25 08:00 | 09-Sep-25 17:00 | 1.38 Days
Continuous |
241s 734L (241s Uplands) | Open end outage on 734L to Cutover SCADA points from SURVALENT Scout to SEL RTAC and test and commission protections | |
ATCO, ALBIAN | 08-Sep-25 08:00 | 14-Sep-25 16:00 | 6.33 Days
Continuous |
920s 902T (920s Jackpine) | request from CNRL carry out the repairs on 72kV cables connected to 902T |
|
BCH | 08-Sep-25 09:00 | 18-Sep-25 17:00 | 10.33 Days
Continuous |
5L92 (BCH Cranbrook - BCH Selkirk) | replace insulators & spacers | AB-BC |
BCH | 08-Sep-25 09:00 | 18-Sep-25 17:00 | 10.33 Days
Continuous |
5L92 (BCH Cranbrook - BCH Selkirk), T3 (BCH Cranbrook) | CBK Insulator Replacement project Step #5 | AB-BC |
ATCO | 08-Sep-25 09:30 | 09-Sep-25 17:30 | 1.33 Days
Continuous |
755s 902 (755s Cordel) | BREAKER SF6 GL315 COMPLETE TESTING - BREAKER 902 @ 755S TCM Program. RTXP Test Switch Mitigation and Replacement: 50BF/902 @ 755S |
|
ALTALINK, EPCOR | 08-Sep-25 09:30 | 12-Sep-25 17:00 | 4.31 Days
Continuous |
947L (89s Ellerslie - 987s Clover Bar) | Cloverbar: 947L Zone Doble and CDS27/CDS28/CDS29 Disconnect Maintenance | |
ALTALINK | 08-Sep-25 12:30 | 08-Sep-25 16:30 | 4 Hours
Daily |
17s 2 (17s Benalto) | Techs to take oil sample from CT252 associated with 17s2 240kV breaker. | |
ALTALINK | 09-Sep-25 07:30 | 09-Sep-25 12:30 | 5 Hours
Daily |
650s 252 (650s Hansman Lake) | Settings changes and breaker protection testing on 650s252 | |
ALTALINK | 09-Sep-25 07:30 | 09-Sep-25 17:30 | 10 Hours
Daily |
63s T2 (63s Red Deer) | Repair cracked/chipping 240kV Bushing heads | |
ATCO, ALTALINK | 09-Sep-25 09:00 | 10-Sep-25 18:00 | 1.38 Days
Continuous |
7L760D4 (7LA760 tap), 7L760D5 (7LA760 tap), 7L760 (7LA760 tap - 7LC760 tap), 760L (760AL tap - 7LA760 tap) | Building Temp Bypass to replace switches 7L760D4, 7L760D5 and 7LA760D1. Will Need COG from AltaLink at 760L41 |
|
ALTALINK | 09-Sep-25 12:30 | 09-Sep-25 17:30 | 5 Hours
Daily |
650s 352 (650s Hansman Lake) | Settings changes and breaker protection testing on 650s352 | |
ALTALINK, TRANSALTA | 09-Sep-25 23:00 | 11-Sep-25 07:00 | 1.33 Days
Continuous |
250p T2 (250p Bighorn Plant) | maintenance | |
ALTALINK, TRANSALTA | 10-Sep-25 07:00 | 11-Sep-25 07:00 | 24 Hours
Continuous |
250p T1 (250p Bighorn Plant) | maintenance | |
ALTALINK | 10-Sep-25 07:30 | 10-Sep-25 17:30 | 10 Hours
Daily |
63s 352 (63s Red Deer) | Top up low gas and repair nitrogen leaks | |
ALTALINK, Lethbridge | 10-Sep-25 08:00 | 11-Sep-25 17:00 | 1.38 Days
Continuous |
667L (146s MacDonald - 370s North Lethbridge) | Open End Outage on 667L to Cutover SCADA points from SURVALENT Scout to SEL RTAC. | |
SUNCOR | 10-Sep-25 08:00 | 19-Sep-25 20:00 | 9.5 Days
Continuous |
29EDD-34 29PT-341 (29EDD-34), 29EDD-34 29-952-142 (29EDD-34), 29EDD-34 29-952-143 (29EDD-34), 29EDD-34 29PS-0375 (29EDD-34), 29EDD-34 29-652-10200T (29EDD-34), 29EDD-34 29-652-10301 (29EDD-34), 29EDD-34 29-652-10302 (29EDD-34), 29EDD-34 29-652-10303 (29EDD-34), 29EDD-34 29PS-0380 (29EDD-34), 29EDD-34 29PS-0381 (29EDD-34), 29EDD-34 29PS-0382 (29EDD-34), 29EDD-34 29PS-609 (29EDD-34), 29EDD-34 29PS-610 (29EDD-34) | 10 year PM on 29EDD34;29PT-341 system and 5 year, 10 year PM on 29EDD34;29PP-103 system |
|
ALTALINK | 10-Sep-25 08:30 | 10-Sep-25 12:30 | 4 Hours
Daily |
338s 552 (338s Cherhill) | CT oil sample | |
ATCO | 10-Sep-25 09:00 | 10-Sep-25 09:15 | 15 Mins
Continuous |
7L01 (813s Little Smoky - 881s Sturgeon 2) | This will require 7L01 to be deenergized for 10-15mins while 881s 701TD is opened. | |
ATCO | 10-Sep-25 11:00 | 10-Sep-25 12:00 | 60 Mins
Continuous |
774s 701 (774s Monitor), 7L224 (650s Hansman Lake - 774s Monitor) | PRC-005 - TRIP COIL TESTING - BREAKER 701 @ 774S | |
ALTALINK | 10-Sep-25 12:00 | 10-Sep-25 15:00 | 3 Hours
Continuous |
199L (347s AML Fox Creek - 741s ATC Fox Creek) | Update 347s199W breaker maintenance switch and associated circuits. | |
ALTALINK | 10-Sep-25 15:00 | 10-Sep-25 17:30 | 2.5 Hours
Continuous |
199L (347s AML Fox Creek - 199AL tap), 347s 199E (347s AML Fox Creek) | update 347s199E breaker maintenance switch and associated circuits | |
ATCO | 11-Sep-25 08:01 | 11-Sep-25 13:00 | 4.98 Hours
Continuous |
951s 1201T (951s Thickwood Hills) | 900BS1 Outage for commissioning POW project | |
ATCO | 11-Sep-25 08:45 | 11-Sep-25 09:00 | 15 Mins
Continuous |
7L01 (813s Little Smoky - 881s Sturgeon 2) | This will require 7L01 to be deenergized for 10-15mins while 881s 701TD is closed. | |
ATCO | 11-Sep-25 09:00 | 11-Sep-25 13:00 | 4 Hours
Continuous |
12L44 (939s Livock - 951s Thickwood Hills) | 500KV Bus inspection | |
ATCO | 11-Sep-25 13:01 | 12-Sep-25 14:00 | 24.98 Hours
Continuous |
951s 1201T (951s Thickwood Hills) | Proof of concept commissioning. Energizing 1201T and the system through 907 & 1205 Breakers with new POW Relays Breakers will be Opened/Closed through out testing. |
|
BCH | 12-Sep-25 09:00 | 17-Sep-25 17:00 | 5.33 Days
Continuous |
2L113 (BCH Cranbrook - BCH Natal) | NTL station rebuild | AB-BC |
BCH | 12-Sep-25 13:00 | 26-Sep-25 17:00 | 14.17 Days
Continuous |
T4 (BCH Natal) | Natal substation replacement and ETM install | AB-BC |
ALTALINK | 13-Sep-25 08:00 | 13-Sep-25 13:00 | 5 Hours
Daily |
38s T1 (38s East Edmonton) | Extend 38sT1 CT wiring to DDR. Must be done to meet PRC002 compliance | |
ALTALINK | 13-Sep-25 13:30 | 13-Sep-25 18:00 | 4.5 Hours
Daily |
38s T4 (38s East Edmonton) | Extend 38sT1 CT wiring to DDR. Must be done to meet PRC002 compliance | |
ALTALINK | 14-Sep-25 08:30 | 14-Sep-25 18:30 | 10 Hours
Daily |
89s T2 (89s Ellerslie) | PRC005 testing of GDRs, gas detector replacement on 1 phase, testing of sudden pressure relief devices. | |
EPCOR | 15-Sep-25 07:00 | 16-Sep-25 17:00 | 1.42 Days
Continuous |
52s T2 (52s East Industrial) | East Industrial: TX2 - MV Protection Upgrade Cutovers | |
EPCOR | 15-Sep-25 07:00 | 20-Sep-25 17:00 | 5.42 Days
Continuous |
987s T1 (987s Clover Bar), 987s CCP7213 (987s Clover Bar), 987s CCP7214 (987s Clover Bar), 987s C2401 (987s Clover Bar), 987s C2403 (987s Clover Bar), 987s C2402 (987s Clover Bar), 987s T3 (987s Clover Bar) | Cloverbar: TX1 and TX3 Zone, Insulator Stand Install and CT Removal | |
ALTALINK | 15-Sep-25 09:30 | 18-Sep-25 12:30 | 3.13 Days
Continuous |
33s 1 (33s Spray) | Replacement 2 more CTs associated with 33s1 Breaker. | |
ALTALINK, EPCOR | 15-Sep-25 09:30 | 21-Sep-25 17:00 | 6.31 Days
Continuous |
909L (310p Sundance - 665s Dome), 665s D2402 (665s Dome), 665s D2403 (665s Dome), 665s T2 (665s Dome) | Dome: 909LE/TX2 Doble and DDS4/DDS5/DAB2 Disconnect Maintenance and Relay Maintenance | |
ALTALINK, EPCOR | 15-Sep-25 09:30 | 21-Sep-25 17:00 | 6.31 Days
Continuous |
909L (310p Sundance - 665s Dome) | Dome: 909LE/TX2 Doble and DDS4/DDS5/DAB2 Disconnect Maintenance and Relay Maintenance | |
ATCO | 15-Sep-25 10:00 | 03-Oct-25 17:30 | 18.31 Days
Continuous |
840s McNeill Station | CONVERTER INSPECTION @ MCNEILL 840S BREAKER SF6 HPL COMPLETE TESTING - |
AB-SK |
BCH | 15-Sep-25 13:00 | 15-Sep-25 14:00 | 60 Mins
Continuous |
2L112 (BPA Boundary - BCH Nelway) | EMERGENCY REPLACEMENT OF A BOUNDARY PCB AND IN ORDER TO MOVE IT INTO LOCATION WE NEED TO CLEAR PCB A-1220 WHICH WILL OPEN END THE BOUNDARY-NELWAY NO 1 230KV LINE. | AB-BC |
BCH | 15-Sep-25 13:00 | 15-Sep-25 14:00 | 60 Mins
Continuous |
2L112 (BPA Boundary - BCH Nelway) | PROXIMITY WORK REMOVING OLD BREAKER ON TRAILER UNDER MAIN BUS SIDE OF PCB A-1220 | AB-BC |
ALTALINK | 15-Sep-25 18:00 | 18-Sep-25 17:00 | 2.96 Days
Continuous |
421s T2 (421s Hays) | Urgent replacement of 421s14 due to bird contact and switch contact cleaning of 421s18 due to maintenance identified hotspot. | |
BCH | 16-Sep-25 00:00 | 16-Sep-25 00:00 | 0 Mins
Continuous |
5L72 (BCH Mica G.S. - BCH Nicola) | MCA 500kV Switching Outage for Opening 5D5 for D12Y & Project work. | AB-BC |
ALTALINK, TRANSALTA | 16-Sep-25 07:00 | 17-Sep-25 18:00 | 1.46 Days
Daily |
514L (396s Pincher Creek - 514BL tap), 514L (513s Lundbreck - 514BL tap), 322s T1 (322s Cowley Ridge) | Replacing structures 16 and 76 Replacing arms and insulators on structure 170 | |
ALTALINK | 16-Sep-25 08:00 | 18-Sep-25 17:30 | 2.4 Days
Continuous |
359s T2 (359s Esso West Pembina), 359s 202AX (359s Esso West Pembina) | Bushing replacement, Doble, maintenance, leaks, LTC maintenance | |
ALTALINK | 16-Sep-25 09:00 | 16-Sep-25 17:30 | 8.5 Hours
Daily |
68s T2 (68s Willesden Green) | First Trip & PRC Breaker Maintenance | |
BCH | 16-Sep-25 09:00 | 19-Sep-25 17:00 | 3.33 Days
Continuous |
5L72 (BCH Mica G.S. - BCH Nicola) | F26 AOP NERC CN PM on NIC 5CB3, 5CB13 and 5B43. CPC to enter PN's OOS OAT
|
|
SUNCOR | 17-Sep-25 08:00 | 24-Sep-25 18:00 | 7.42 Days
Continuous |
29PL7-4 (29EDD-65 - 29EDD-71), 29EDD-65 29PS-0284 (29EDD-65 Edd65Sub), 29EDD-71 29PS-243 (29EDD-71 Edd71Sub), 29EDD-65 29PT-0257 (29EDD-65) | FB-Maintenance, Repairs and Testing - PRC-5 Testing, 29PT-260, 29PL7-4, 29PT-241, 29PT-257, 29PS-243 (300415541, 31807283, 31773784, 300109525) | |
ALTALINK | 17-Sep-25 09:00 | 17-Sep-25 17:30 | 8.5 Hours
Daily |
62s 31 (62s Brazeau Plant), 62s T3 (62s Brazeau Plant) | 240kV breaker maintenance (N.O.) | |
CNRL | 18-Sep-25 08:00 | 22-Sep-25 16:00 | 4.33 Days
Continuous |
842s 75-1904 (842s Horizon Upgrading) | breaker tank heater repair | |
SUNCOR | 18-Sep-25 08:00 | 05-Oct-25 20:00 | 17.5 Days
Continuous |
29EDD-61 29PT-653 (29EDD-61 Stony Island) | 29PT-653 - Repair / Replace Burned Bonding Conductor (9000808061) | |
ALTALINK | 18-Sep-25 09:00 | 18-Sep-25 17:30 | 8.5 Hours
Daily |
62s T5 (62s Brazeau Plant) | Install Bushing monitoring devices | |
ALTALINK | 19-Sep-25 07:00 | 25-Sep-25 17:00 | 6.42 Days
Continuous |
520s T1 (520s Bennett), 520s R7 (520s Bennett) | South 520sT1 + R7 doble, maintenance and leaks | |
ALTALINK | 19-Sep-25 07:00 | 30-Sep-25 17:00 | 11.42 Days
Continuous |
1201L (520s Bennett - BCH Cranbrook) | South Crew will be completing component replacement from 1201L21 – 1201L435 | AB-BC |
ALTALINK | 19-Sep-25 07:00 | 30-Sep-25 17:00 | 11.42 Days
Continuous |
799s 786W (799s Coleman), 786L (799s Coleman - BCH Natal) | 786L required to be open due to 1201L as per AESO Rule | AB-BC |
BHE Canada | 19-Sep-25 07:00 | 30-Sep-25 17:00 | 11.42 Days
Continuous |
MATL (120s Picture Butte - Montana) | align with 1201L outage | AB-MATL |
AESO | 19-Sep-25 07:00 | 30-Sep-25 17:00 | 11.42 Days
Continuous |
Path 1 (AIES Islanding) | align with 1201L outage | AB-BC |
SUNCOR | 20-Sep-25 08:00 | 30-Sep-25 20:00 | 10.5 Days
Continuous |
29EDD-34 29PT-340 (29EDD-34) | 29EDD34;29PT-340 SYSTEM;PM 5y,10y; 29EDD34;29PP-102 SYSTEM;PM 5y,10y |
|
ENMAX, ALTALINK | 21-Sep-25 08:00 | 07-Oct-25 16:00 | 16.33 Days
Continuous |
50L (44s Bearspaw Plant - SS-21), 21.1C (SS-21), 21.2TR (SS-21) | 21.2TR Replacement. Decommission, remove existing 21.2TR and associated equipment | |
ENMAX, ALTALINK | 21-Sep-25 08:00 | 07-Oct-25 16:00 | 16.33 Days
Continuous |
50L (44s Bearspaw Plant - SS-21) | ENMAX - 21.2TR Replacement. Decommission, remove existing 21.2TR and associated equipment | |
ENMAX, ALTALINK | 21-Sep-25 08:00 | 07-Oct-25 16:00 | 16.33 Days
Continuous |
50L (44s Bearspaw Plant - SS-21) | 21.2TR Replacement. Decommission, remove existing 21.2TR and associated equipment. 21.80L & 20.82L will be open ended 50L FCT 27 cycles. 60s100 source will be moved to 21PT138-Z31 sec. fuses. | |
EPCOR | 22-Sep-25 07:00 | 03-Oct-25 17:00 | 11.42 Days
Continuous |
987s T1 (987s Clover Bar), 987s C2401 (987s Clover Bar), 987s C2403 (987s Clover Bar), 987s CCP7213 (987s Clover Bar), 987s CCP7214 (987s Clover Bar) | Cloverbar: TX1 LCR P&C Commissioning and Initial Energization | |
ALTALINK | 22-Sep-25 12:00 | 22-Sep-25 18:00 | 6 Hours
Daily |
74s 23.80W (74s Janet) | Substation - Insulator Washing (Fall). | |
ALTALINK | 22-Sep-25 12:30 | 25-Sep-25 16:30 | 3.17 Days
Continuous |
310p T30 (310p Sundance) | Bushing replacement, maintenance, and leak repair | |
ATCO | 22-Sep-25 13:00 | 25-Sep-25 16:00 | 3.13 Days
Continuous |
7L28 (717s Ethel Lake - 846s Grand Centre) | 7L28 Line to ground clearance mitigation | |
ALTALINK, EPCOR | 22-Sep-25 13:00 | 25-Sep-25 17:00 | 3.17 Days
Continuous |
1043L (320p Keephills - 367s Harry Smith), 320p 352 (320p Keephills), 320p 252 (320p Keephills) | Replace 320p289 | |
ATCO | 23-Sep-25 09:00 | 26-Sep-25 17:00 | 3.33 Days
Continuous |
9L99 (801s Anderson - 807s Sheerness) | 801S DFR requires 9L99 inputs to meet PRC-002 compliance | |
ALTALINK | 23-Sep-25 09:30 | 25-Sep-25 16:30 | 2.29 Days
Daily |
1071L (205s Castle Rock Ridge - 312s Fidler) | 205s352, 452 First Trip, CT testing, repair 205s7 seized switch | |
ENMAX | 23-Sep-25 12:00 | 23-Sep-25 18:00 | 6 Hours
Continuous |
23.80L (74s Janet - SS-23), 23.4TR (SS-23) | Substation - Insulator Washing (Fall) | |
ALTALINK | 25-Sep-25 06:15 | 27-Sep-25 17:45 | 2.48 Days
Continuous |
862L (166s Dow Chemical Fort Saskatchewan - 258s Dow Hydrocarbons) | Line Move to modify the existing alignment between structures 4-8 | |
ALTALINK, TRANSALTA | 26-Sep-25 09:00 | 26-Sep-25 12:00 | 3 Hours
Daily |
33s T1 (33s Spray) | testing | |
ALTALINK, TRANSALTA | 26-Sep-25 13:00 | 26-Sep-25 16:00 | 3 Hours
Daily |
33s T2 (33s Spray) | testing | |
ALTALINK | 27-Sep-25 07:00 | 12-Oct-25 18:00 | 15.46 Days
Continuous |
912L (63s Red Deer - 766s Nevis) | Arctic Arrow will be stringing overtop 912L STR 147-148 with the new CETO 962L/986L spans 165-166. | |
ALTALINK | 28-Sep-25 06:15 | 29-Sep-25 17:45 | 1.48 Days
Continuous |
707L (54s Fort Saskatchewan - 166s Dow Chemical Fort Saskatchewan) | Line Move to modify the existing alignment between structures 29-33 | |
ATCO | 28-Sep-25 09:00 | 05-Oct-25 15:00 | 7.25 Days
Continuous |
7L20 (740s H.R. Milner - 810s Dome Cutbank) | Outage on 7L20 for line maintenance program to change out following Structures. 69,66,65,64,62,60,59,54,53 |
|
EPCOR | 29-Sep-25 07:00 | 05-Oct-25 17:00 | 6.42 Days
Continuous |
816s P2404 (816s Petrolia), 816s P2405 (816s Petrolia), 816s T2 (816s Petrolia) | Petrolia: TX2 Zone Doble and Disconnect Maintenance | |
EPCOR | 29-Sep-25 07:00 | 12-Oct-25 17:00 | 13.42 Days
Continuous |
557s T2 (557s Castle Downs) | Castle Downs S/S Tx2 bay outage | |
Lethbridge | 29-Sep-25 08:00 | 30-Sep-25 17:00 | 1.38 Days
Continuous |
593s 824L (593s Lakeview) | Open End Outage on 824L to Cutover SCADA points from SURVALENT Scout to SEL RTAC and to test and commission. Require Protection outages on 824L "A" Protection relay (SEL 411L) , "B" Protection relay (GE L90), "152" Breaker Protection relay (GE C60) .Redundant Protection will be in place at all time | |
ALTALINK, Lethbridge | 29-Sep-25 08:00 | 30-Sep-25 17:00 | 1.38 Days
Continuous |
824L (593s Lakeview - 618s Riverbend) | Open End Outage on 824L to Cutover SCADA points from SURVALENT Scout to SEL RTAC and to test and commission | |
ATCO | 29-Sep-25 13:00 | 02-Oct-25 16:00 | 3.13 Days
Continuous |
7L28 (717s Ethel Lake - 846s Grand Centre) | 7L28 Line to ground clearance mitigation | |
ATCO | 29-Sep-25 14:01 | 13-Oct-25 14:00 | 14 Days
Continuous |
732s 701 (732s Mitsue), 732s 702 (732s Mitsue), 732s 901T (732s Mitsue), 732s 902 (732s Mitsue), 732s 903 (732s Mitsue) | Protection upgrade. Remove old protection, cut over to new protection and cut over equipment status, control and alarms to new station controller. | |
ALTALINK | 30-Sep-25 06:15 | 02-Oct-25 17:45 | 2.48 Days
Continuous |
787L (166s Dow Chemical Fort Saskatchewan - 787AL tap) | Line Move to modify the existing alignment between structures 35-39 | |
ALTALINK | 30-Sep-25 07:00 | 01-Oct-25 18:00 | 1.46 Days
Continuous |
180AL (604s Granum - 180L tap), 180L (928s East Stavely - 180AL tap), 180L (15s Fort Macleod - 180AL tap) | In this outage we will be updating our Protection Relay settings | |
ALTALINK | 30-Sep-25 07:00 | 09-Oct-25 18:00 | 9.46 Days
Continuous |
935L (324s Cassils - 356s Milo) | Performing mtce. between Structures #53 - 148 | |
ALTALINK, TRANSALTA | 30-Sep-25 16:00 | 25-Oct-25 18:00 | 25.08 Days
Continuous |
320p GT3 (320p Keephills) | maintenance | |
ALTALINK, EPCOR | 01-Oct-25 07:00 | 02-Oct-25 17:00 | 1.42 Days
Continuous |
1045L (310p Sundance - 1045AL tap), 1045L (EP 805s Jasper - 1045AL tap), 1045AL (320p Keephills - 1045L tap), EP 805s J2406 (EP 805s Jasper), EP 805s J2407 (EP 805s Jasper) | insulator repair | |
ALTALINK, EPCOR | 01-Oct-25 07:00 | 02-Oct-25 18:00 | 1.46 Days
Continuous |
1045AL (320p Keephills - 1045L tap), 1045L (310p Sundance - 1045AL tap), 1045L (EP 805s Jasper - 1045AL tap) | Aerial: Insulator Repair and Relay: Op Checks | |
ENMAX, ALTALINK | 01-Oct-25 08:00 | 01-Oct-25 16:00 | 8 Hours
Continuous |
1080L (SS-25 - SS-65) | Surge Arrestor Power Factor Test - 65MD240-1080 | |
ALTALINK | 01-Oct-25 08:00 | 11-Nov-25 17:00 | 41.42 Days
Continuous |
102s SVC (102s Langdon), 102s T4 (102s Langdon) | the controls change | AB-BC |
ALTALINK | 01-Oct-25 11:00 | 02-Oct-25 18:00 | 31 Hours
Continuous |
38s 7652 (38s East Edmonton) | 240kV breaker maintenance, rebuild dashpot | |
ALTALINK | 01-Oct-25 12:00 | 03-Oct-25 18:30 | 2.27 Days
Continuous |
89s T2 (89s Ellerslie) | 89s T2 Doble and maintenance. Replace gas detector relay. Update Qualitrol settings. Repair oil leaks. | |
ALTALINK | 02-Oct-25 07:00 | 02-Oct-25 12:00 | 5 Hours
Daily |
722L (107s Westfield - 368s Burdett) | Remove PCB Lighting fixture located within LOA at 107s | |
ENMAX, ALTALINK | 02-Oct-25 08:00 | 02-Oct-25 18:00 | 10 Hours
Continuous |
1080L (SS-25 - SS-65) | Surge Arrestor Power Factor Test - 25MD240-1080 | |
ALTALINK | 02-Oct-25 08:15 | 02-Oct-25 13:45 | 5.5 Hours
Daily |
853L (28s West Brooks - 853AL tap), 853L75 (853AL tap), 28s 25 (28s West Brooks), 28s 28 (28s West Brooks) | Insulator replacement | |
ALTALINK | 02-Oct-25 09:30 | 02-Oct-25 15:30 | 6 Hours
Daily |
632s 412 (632s Russell), 412L (396s Pincher Creek - 632s Russell) | Heater replacement | |
BCH, ALTALINK | 03-Oct-25 06:00 | 03-Oct-25 18:00 | 12 Hours
Continuous |
1L274 (48s Pocaterra - 978s BCH Britt Creek), 48s 887X (48s Pocaterra) | Placeholder to energize new equipment at FRO (Bauer Tower Equipment, BCH Metering Kit and Surge Arrestor, FRO FCD-H31 | AB-BC |
ALTALINK | 03-Oct-25 07:00 | 03-Oct-25 18:00 | 11 Hours
Continuous |
887L (48s Pocaterra - 978s BCH Britt Creek) | FRO project work. BCH to close their switch 1D23 de-energized | AB-BC |
ENMAX, ALTALINK | 03-Oct-25 08:00 | 03-Oct-25 12:00 | 4 Hours
Continuous |
28.80L (42s Sarcee - SS-28), 28B138-28.80 (SS-28) | HV Breaker SF6 Gas Sample - 28B138-28.80 | |
ALTALINK | 03-Oct-25 08:00 | 03-Oct-25 14:00 | 6 Hours
Daily |
1052L (28s West Brooks - 324s Cassils) | Replace 28s 1052L Strain Insulators, See also 294659 827L RB, & 1051L (28s-324s) - RB Required due to proximity. | |
ENMAX | 03-Oct-25 08:00 | 03-Oct-25 16:00 | 8 Hours
Continuous |
23.80L (74s Janet - SS-23) | Shield wire corrosion testing | |
ALTALINK | 03-Oct-25 08:00 | 03-Oct-25 16:00 | 8 Hours
Daily |
74s 30 (74s Janet) | Shield wire corrosion testing | |
EPCOR | 06-Oct-25 07:00 | 06-Oct-25 17:00 | 10 Hours
Continuous |
72DS26 (665s Dome - Strathcona), 665s D721 (665s Dome), S721 (Strathcona) | Dome/DS26: DDS17 Repair | |
ALTALINK | 06-Oct-25 08:00 | 06-Oct-25 17:30 | 9.5 Hours
Daily |
801L (62s Brazeau Plant - 294s Brazeau Plant Outlet Works) | allow wiring/testing/operation of 294s801N MOD | |
ATCO | 06-Oct-25 08:00 | 10-Oct-25 18:00 | 4.42 Days
Continuous |
7L228 (845s Big Mountain - 7L20 tap) | Outage on 7L228 for line maintenance program to change out following Structures. 652,651,648,647,608,611,578,574,534,533,529,528,526,500,499,495,470,471,479,457,456,453,447,441,437,435,433,428 |
|
ATCO | 06-Oct-25 09:00 | 09-Oct-25 16:00 | 3.29 Days
Continuous |
969s 701T (969s Lindbergh) | replace failing bushings on transformer | |
BCH | 06-Oct-25 09:00 | 10-Oct-25 17:00 | 4.33 Days
Continuous |
5L91 (BCH Ashton Creek - BCH Selkirk) | Replace markerballs & insulators | AB-BC |
BCH | 06-Oct-25 09:00 | 17-Oct-25 17:00 | 11.33 Days
Continuous |
2L112 (BPA Boundary - BCH Nelway), 2D24 (BCH Nelway), 2D2CB7 (BCH Nelway) | NLY 2SA2 2SA12 replacement, BC maintenance does not affect the Alberta ATC | AB-BC |
ATCO | 06-Oct-25 09:30 | 07-Oct-25 17:30 | 1.33 Days
Continuous |
845s 703 (845s Big Mountain), 845s 710 (845s Big Mountain), 7L228 (845s Big Mountain - 7L20 tap) | Replace Crank Mechanisms on 144 kV Switches at 845s Big Mountain - 703B Replace Crank Mechanisms on 144 kV Switches at 845s Big Mountain - 704B |
|
ATCO | 06-Oct-25 09:30 | 07-Oct-25 17:30 | 1.33 Days
Continuous |
755s 901 (755s Cordel) | BREAKER SF6 GL315 COMPLETE TESTING - BREAKER 901 @ 755S TCM Program. RTXP Test Switch Mitigation and Replacement: 50BF/901 @ 755S |
|
ALTALINK | 07-Oct-25 06:00 | 11-Oct-25 18:00 | 4.5 Days
Continuous |
1034L (244s Bowmanton - 324s Cassils) | Install new span of OPGW between 179-180, install splice boxes on structure 179 & 180, terminate the existing OPGW. | |
ATCO | 07-Oct-25 07:00 | 07-Oct-25 19:00 | 12 Hours
Continuous |
7L79 (771s Veteran - 892s Ribstone Creek), 7L696 (508s Lakesend - 892s Ribstone Creek) | Installing interspacers on 7L79 | |
ALTALINK | 07-Oct-25 08:00 | 08-Oct-25 17:00 | 1.38 Days
Daily |
725L (15s Fort MacLeod - 725BL tap), 725L (674s Bowron - 725BL tap) | Component replacement #221-227. | |
ALTALINK | 07-Oct-25 08:30 | 07-Oct-25 17:30 | 9 Hours
Daily |
320p PS2 (320p Keephills), 320p 2652 (320p Keephills) | 240kV breaker maintenance | |
ATCO | 07-Oct-25 09:30 | 07-Oct-25 17:30 | 8 Hours
Continuous |
801s 907 (801s Anderson) | breaker testing | |
ALTALINK | 08-Oct-25 07:00 | 08-Oct-25 18:00 | 11 Hours
Continuous |
931L (28s West Brooks - 132s Ware Junction) | South Crew will be repairing conductor at 931L66 | |
ALTALINK | 08-Oct-25 07:00 | 11-Oct-25 17:00 | 3.42 Days
Continuous |
914L (86s Bigstone - 87s Gaetz), 87s 240kV East Bus (87s Gaetz), 87s T2 (87s Gaetz) | East bus outage to install new screw piles for CETO project | |
ATCO | 08-Oct-25 09:30 | 09-Oct-25 17:30 | 1.33 Days
Continuous |
7L85 (801s Anderson - ATC 803s Bullpound), 801s 705 (801s Anderson) | BREAKER SF6 LTB145D1/B COMPLETE TESTING - 705 @ 801S | |
ALTALINK | 08-Oct-25 23:00 | 09-Oct-25 03:00 | 4 Hours
Continuous |
62s T1 (62s Brazeau Plant) | maintenance | |
ALTALINK | 09-Oct-25 03:00 | 09-Oct-25 07:00 | 4 Hours
Daily |
62s T2 (62s Brazeau Plant) | maintenance | |
ENMAX | 09-Oct-25 08:00 | 09-Oct-25 18:00 | 10 Hours
Continuous |
7.84L (SS-7 - SS-36), 36B138-36BT3 (SS-36), 36.1TR (SS-36), 36.3TR (SS-36), 36B138-36.81 (SS-36) | Substation - Insulator Washing (Fall) | |
ALTALINK | 12-Oct-25 07:00 | 15-Oct-25 17:00 | 3.42 Days
Continuous |
914L (63s Red Deer - 87s Gaetz), 87s 240kV West Bus (87s Gaetz), 87s T1 (87s Gaetz) | West bus outage to install new screw piles for CETO project | |
ATCO | 13-Oct-25 11:00 | 30-Oct-25 17:30 | 17.27 Days
Continuous |
840s McNeill Station | Replace failed control system parts | |
ATCO | 13-Oct-25 14:01 | 27-Oct-25 14:00 | 14 Days
Continuous |
732s 701 (732s Mitsue), 732s 702 (732s Mitsue), 732s 901T (732s Mitsue), 732s 501R (732s Mitsue) | Protection upgrade. Remove old protection, cut over to new protection and cut over equipment status, control and alarms to new station controller. | |
ALTALINK | 14-Oct-25 06:00 | 17-Oct-25 18:00 | 3.5 Days
Continuous |
100L (498s Tilley - 895s Suffield) | Install new tap structure for 100AL connections, and modify adjacent structures 242 & 243. | |
EPCOR | 14-Oct-25 07:00 | 14-Oct-25 17:00 | 10 Hours
Continuous |
805s T4 (805s Jasper) | Jasper: TX4 Conservator Inspection | |
ALTALINK, EPCOR | 14-Oct-25 07:00 | 18-Oct-25 17:00 | 4.42 Days
Continuous |
1058L (657s Summerside - EP 803s Lambton), EP 803s L2403 (EP 803s Lambton), EP 803s L2404 (EP 803s Lambton) | 1058L: Lambton CVT and Surge Arrestors LCR's | |
ALTALINK | 14-Oct-25 07:00 | 24-Oct-25 13:30 | 10.27 Days
Continuous |
924L (102s Langdon - 356s Milo), 102s 6952 (102s Langdon), 102s 6852 (102s Langdon), 356s 952 (356s Milo), 356s 852 (356s Milo) | Line protection replacements and RAS175 scheme upgrades | |
ATCO | 14-Oct-25 08:00 | 17-Oct-25 18:00 | 3.42 Days
Continuous |
7L228 (845s Big Mountain - 7L20 tap) | Outage on 7L228 for line maintenance program to change out following Structures. 652,651,648,647,608,611,578,574,534,533,529,528,526,500,499,495,470,471,479,457,456,453,447,441,437,435,433,428 |
|
ALTALINK, EPCOR | 14-Oct-25 09:00 | 17-Oct-25 17:30 | 3.35 Days
Continuous |
920L (71s Lamoureux - 557s Castle Downs) | EPCOR 920LE Zone Doble and disconnect maintenance. | |
ALTALINK, EPCOR | 14-Oct-25 09:30 | 17-Oct-25 17:00 | 3.31 Days
Continuous |
920L (71s Lamoureux - 557s Castle Downs), 557s CD2404 (557s Castle Downs), 557s CD2405 (557s Castle Downs) | Castledowns: 920LE Zone Doble and Disconnect Maintenance | |
ATCO | 14-Oct-25 10:00 | 14-Oct-25 17:30 | 7.5 Hours
Continuous |
801s 910 (801s Anderson) | BKR 910 Pole Low Oil at 801s Anderson | |
ATCO | 14-Oct-25 13:00 | 17-Oct-25 16:00 | 3.13 Days
Continuous |
7L28 (717s Ethel Lake - 846s Grand Centre) | 7L28 Line to ground clearance mitigation | |
ALTALINK | 14-Oct-25 13:00 | 18-Oct-25 16:00 | 4.13 Days
Continuous |
65s 753E (65s High River), 753L (65s High River - 253s Blackie) | Replace CTs and protection upgrade. | |
EPCOR | 15-Oct-25 07:00 | 17-Oct-25 17:00 | 2.42 Days
Continuous |
T4 (Poundmaker), 72PM25 (Poundmaker - Meadowlark), PM721 (Poundmaker) | Poundmaker: TX4 Tap Changer Sample Pipe Install | |
ALTALINK | 15-Oct-25 07:00 | 18-Oct-25 18:00 | 3.46 Days
Continuous |
935L (324s Cassils - 356s Milo) | Performing mtce. between Structures #53 - 148 | |
ATCO | 15-Oct-25 09:30 | 16-Oct-25 17:30 | 1.33 Days
Continuous |
801s 905 (801s Anderson) | breaker minimum oil HLR partial testing | |
ATCO, ALTALINK | 19-Oct-25 07:00 | 24-Oct-25 18:00 | 5.46 Days
Continuous |
923L (356s Milo - 2075s Newell) | Performing mtce. between Structures #74 - 162 | |
EPCOR | 20-Oct-25 07:00 | 24-Oct-25 17:00 | 4.42 Days
Continuous |
805s T3 (805s Jasper), EP 805s J2404 (EP 805s Jasper), EP 805s J2405 (EP 805s Jasper) | Jasper: TX3 Zone Relay Maintenance | |
ALTALINK | 20-Oct-25 07:00 | 25-Oct-25 18:00 | 5.46 Days
Continuous |
944L (132s Ware Junction - 275s Jenner) | Modifying existing structure 944L156 from a tangent assembly to a floating DE/phase raise configuration to tap onto a new adjacent substation. See also SAP: 294514 951L RB required due to proximity | |
EPCOR, ALTALINK | 20-Oct-25 07:00 | 26-Oct-25 17:00 | 6.42 Days
Continuous |
240BA2 (629s Argyll Transfer Station - 814s Bellamy), 1056L (89s Ellerslie - 629s Argyll Transfer Station), 814s B2402 (814s Bellamy), 814s B2401 (814s Bellamy) | 240BA2 Zone: ADS1 LCR, Bellamy Transducer and DFR Cutovers, Bellamy 240kV SF6 Gas Tests and Leak Checks | |
ALTALINK, EPCOR | 20-Oct-25 09:30 | 26-Oct-25 17:30 | 6.33 Days
Continuous |
1056L (89s Ellerslie - 629s Argyll Transfer Station) | 240BA2 Zone: ADS1 LCR, Bellamy Transducer and DFR Cutovers, Bellamy 240kV SF6 Gas Tests and Leak Checks | |
ATCO | 20-Oct-25 12:00 | 23-Oct-25 17:00 | 3.21 Days
Continuous |
951s SVC (951s Thickwood) | Semi Annual inspection & maintenance | |
ALTALINK | 20-Oct-25 14:00 | 23-Oct-25 16:00 | 3.08 Days
Continuous |
612L (336s Fincastle - 368s Burdett), 368s 612 (368s Burdett) | Maintenance. | |
ALTALINK | 21-Oct-25 07:00 | 24-Oct-25 18:00 | 3.46 Days
Continuous |
777L (48s Pocaterra - 245s Seebe) | Replacement of 48s CTs (CT#3) associated with the 777L .Cts located on the line side of 48s below note 12 | AB-BC |
ATCO, CNRL | 22-Oct-25 08:00 | 29-Oct-25 16:00 | 7.33 Days
Continuous |
838s 75-TR-1801 (838s Horizon Mining) | 260kV Transformer Relay Upgrade | |
ALTALINK | 23-Oct-25 08:00 | 23-Oct-25 18:00 | 10 Hours
Continuous |
678s 850 (678s Okotoks), 850L (525s Carseland - 678s Okotoks) | Major SCADA Upgrade Project. Cutting over supervisory controls to breaker and recloser to new RIO. | |
ALTALINK | 24-Oct-25 08:00 | 24-Oct-25 13:00 | 5 Hours
Daily |
44s T1 (44s Bearspaw Plant), 44s T2 (44s Bearspaw Plant) | Outage required to remove PCB Lighting fixture located within LOA. | |
EPCOR, ALTALINK | 27-Oct-25 07:00 | 02-Nov-25 16:00 | 6.42 Days
Continuous |
240BA3 (629s Argyll Transfer Station - 814s Bellamy), 814s B2406 (814s Bellamy), 814s B2407 (814s Bellamy), 1055L (629s Argyll Transfer Station - 816s Petrolia) | 240BA3 Zone: ADS2 LCR, Bellamy Transducer and DFR Cutovers, Bellamy 240kV SF6 Gas Tests and Leak Checks | |
ATCO, ALTALINK | 27-Oct-25 07:00 | 06-Nov-25 18:00 | 10.5 Days
Continuous |
1036L (356s Milo - 554s Travers) | Installing interphase spacers and repairing the inner of the conductor (STR 5-45) | |
ALTALINK | 27-Oct-25 12:00 | 30-Oct-25 16:00 | 3.17 Days
Continuous |
899s 749N (899s Edgerton), 749L (899s Edgerton - 7LB749 tap) | Replace 749LN A21/L8 LZ921 protection. | |
ALTALINK | 27-Oct-25 12:00 | 31-Oct-25 18:00 | 4.25 Days
Continuous |
749L (899s Edgerton - 7LB749 tap) | Component replacement from 749L338 - 749L463 | |
ALTALINK, TRANSALTA | 29-Oct-25 10:00 | 29-Oct-25 14:00 | 4 Hours
Daily |
250p T1 (250p Bighorn Plant) | maintenance | |
ALTALINK | 30-Oct-25 08:00 | 30-Oct-25 17:30 | 9.5 Hours
Daily |
17s 12 (17s Benalto) | 17s12 PRC005 brk maint + first trip | |
ALTALINK, TRANSALTA | 30-Oct-25 10:00 | 30-Oct-25 14:00 | 4 Hours
Daily |
250p T2 (250p Bighorn Plant) | maintenance | |
EPCOR | 03-Nov-25 07:00 | 09-Nov-25 17:00 | 6.42 Days
Continuous |
814s T1 (814s Bellamy), 814s B2401 (814s Bellamy), 814s B2407 (814s Bellamy), BR721 (Rossdale) | Bellamy: TX1 Bushing Replacement and 240kv SF6 Gas Tests and Leak Checks | |
ALTALINK, Lethbridge | 03-Nov-25 08:00 | 03-Nov-25 17:00 | 9 Hours
Continuous |
667L (146s MacDonald - 370s North Lethbridge), 146s 667 (146s Macdonald) | 146s667L Open End Outage required to add CT circuit into new SEL DDR. Test DDR Recording and commission . Require Protection outages on 667L "A" Protection relay (SEL 311L) , "B" Protection relay (GE L90), "352" Breaker Protection relays Redundant Protections will be in service at all times |
|
ALTALINK, Lethbridge | 03-Nov-25 08:00 | 03-Nov-25 17:00 | 9 Hours
Daily |
667L (146s MacDonald - 370s North Lethbridge) | 146s667L Open End Outage required to add CT circuit into new SEL DDR. Test DDR Recording and commission . . | |
Syncrude | 03-Nov-25 08:00 | 10-Nov-25 16:00 | 7.33 Days
Continuous |
222 (Aurora), 222A (Aurora), 222B (Aurora), 223 (Aurora), 223A (Aurora), 223B (Aurora), D05 514 (D05), D05 511 (D05), D05 511A (D05), D05 511B (D05), D05 512 (D05), D05 512A (D05), D05 512B (D05) | SCL - Complete D05 Substation, Zone 3 260kV PM | |
Syncrude | 03-Nov-25 08:00 | 13-Nov-25 16:00 | 10.33 Days
Continuous |
UE-1 (D05 - UE-1 Syncrude Plant 30-2), T1 (D05 Syncrude), D05 511 (D05), D05 519 (D05), D05 71 (D05), D05 71A (D05), D05 71B (D05), D05 80 (D05), D05 80B (D05), D05 79 (D05), D05 79B (D05), D05 73 (D05), D05 73A (D05), D05 73B (D05), D05 75 (D05), D05 75A (D05), LCF (D05), ML-4 (D05), UE-1 7206 (UE-1 Syncrude Plant 30-2), UE-1 72-16 (UE-1 Syncrude Plant 30-2) | complete 6-Year 72 kV A bus preventive maintenance in D05 substation | |
ATCO | 03-Nov-25 09:00 | 10-Nov-25 16:00 | 7.29 Days
Continuous |
7L45 (798s Bridge Creek - 813s Little Smoky) | Pole replacement line to ground issue ( Line raise ) | |
ALTALINK | 03-Nov-25 14:00 | 04-Nov-25 17:30 | 27.5 Hours
Continuous |
39s 26 (39s Bickerdike) | First trip & breaker maintenance on 39s26 | |
ENMAX, ALTALINK | 04-Nov-25 08:00 | 05-Nov-25 16:00 | 1.33 Days
Continuous |
7.82L (42s Sarcee - SS-7) | Replace connection point on shield wire weld tabs on structure | |
ENMAX, ALTALINK | 04-Nov-25 08:00 | 05-Nov-25 16:00 | 1.33 Days
Continuous |
7.82L (42s Sarcee - SS-7) | Replace connection point on shield wire weld tabs on structure | |
ATCO | 04-Nov-25 09:00 | 04-Nov-25 16:00 | 7 Hours
Continuous |
822s 701 (822s Wolf Lake), 7L587 (822s Wolf Lake - 826s Marguerite Lake) | Inspect CT wiring at RTXP test switch Replace RTXP Test switch if no issue found with wiring terminations Recommission affected test switch (Burden, logic testing) |
|
ALTALINK, CascadeP | 05-Nov-25 08:00 | 05-Nov-25 18:00 | 10 Hours
Daily |
39s 26 (39s Bickerdike), 39s 29 (39s Bickerdike), 1135L (39s Bickerdike - 1047s Whisky Jack) | First trip & breaker maintenance on 39s29. Repair 39s28. | |
ALTALINK | 05-Nov-25 17:00 | 06-Nov-25 18:00 | 25 Hours
Continuous |
39s 29 (39s Bickerdike) | Breaker maintenance on 39s29 | |
Syncrude | 11-Nov-25 08:00 | 18-Nov-25 16:00 | 7.33 Days
Continuous |
D05 512 (D05), D05 512A (D05), D05 512B (D05), D05 513 (D05), D05 513A (D05), D05 513B (D05), D05 515 (D05) | SCL - D05 Substation Zone 4 260kV PM with isolation of RL-2. | |
ALTALINK | 13-Nov-25 08:00 | 13-Nov-25 18:00 | 10 Hours
Daily |
1005AL (991s Little Bow - 1005L tap), 1005L (120s Picture Butte - 1005AL tap), 1005L (356s Milo - 1005AL tap) | Modifying 1005L85A and creating Open Point 'A' on the 356s Milo side of 1005L85A | |
ATCO | 13-Nov-25 09:00 | 13-Nov-25 17:00 | 8 Hours
Continuous |
834s 903 (834s Wesley Creek) | 903 B Phase Counter Replacement at 834s Wesley Creek | |
ALTALINK | 13-Nov-25 18:00 | 24-Nov-25 12:00 | 10.75 Days
Continuous |
1005L (356s Milo - 1005AL tap) | Repairing the inner between STR 3-75 on 1005L | |
EPCOR | 17-Nov-25 07:00 | 23-Nov-25 17:00 | 6.42 Days
Continuous |
814s B2402 (814s Bellamy), 814s B2406 (814s Bellamy), 814s T2 (814s Bellamy), BR722 (Rossdale) | Bellamy: TX2 Bushing Replacement and 240kv SF6 Gas Tests and Leak Checks | |
ENMAX | 17-Nov-25 08:00 | 17-Nov-25 18:00 | 10 Hours
Continuous |
162B240-RB131 (SS-162), 162B240-RB132 (SS-162), 1-GSU-XF-0001 (SS-162) | HV SW Maint. 162SW133, 162SW132. | |
ALTALINK | 17-Nov-25 08:30 | 20-Nov-25 16:30 | 3.33 Days
Continuous |
913L (69s North Barrhead - 732s Mitsue) | Protection upgrade. Remove old protection, cut over to new protection and cut over equipment status, control and alarms to new station controller. | |
ATCO | 17-Nov-25 09:00 | 20-Nov-25 16:00 | 3.29 Days
Continuous |
732s 903 (732s Mitsue), 732s 904 (732s Mitsue), 9L913 (69s North Barrhead - 732s Mitsue) | Protection upgrade. Remove old protection, cut over to new protection and cut over equipment status, control and alarms to new station controller. | |
ATCO | 17-Nov-25 10:00 | 24-Nov-25 16:00 | 7.25 Days
Continuous |
7L106 (834s Wesley Creek - 905s Meikle) | Soil around the tower footings has eroded ( Tower Replacement ) | |
ATCO | 17-Nov-25 10:00 | 24-Nov-25 16:00 | 7.25 Days
Continuous |
7L131 (834s Wesley Creek - 905s Meikle) | Soil around the tower footings has eroded ( Tower Replacement ) | |
ENMAX | 18-Nov-25 08:00 | 18-Nov-25 16:00 | 8 Hours
Continuous |
162B240-RB135 (SS-162), 162B240-RB134 (SS-162), 2-GSU-XF-0002 (SS-162) | HV SW Maint. 162SW143, 162SW142. Schedule with CEC outage spring 2026 | |
ATCO | 21-Nov-25 09:00 | 24-Nov-25 16:00 | 3.29 Days
Continuous |
732s 904 (732s Mitsue), 732s 906 (732s Mitsue), 9L56 (720s Wabasca - 732s Mitsue) | Protection upgrade. Remove old protection, cut over to new protection and cut over equipment status, control and alarms to new station controller. | |
ENMAX, ALTALINK | 21-Nov-25 18:00 | 23-Nov-25 08:00 | 1.58 Days
Continuous |
936L (5s East Calgary - 102s Langdon) | Crew working in vicinity of 937L | |
ENMAX, ALTALINK | 21-Nov-25 18:00 | 23-Nov-25 08:00 | 1.58 Days
Continuous |
937L (5s East Calgary - 102s Langdon) | Reconductor between str 15 to 18 on both Circuits for line Clearance Mitigation | |
ENMAX, ALTALINK | 21-Nov-25 18:00 | 23-Nov-25 08:00 | 1.58 Days
Continuous |
936L (5s East Calgary - 102s Langdon) | Crew working in vicinity of 937L | |
ENMAX, ALTALINK | 21-Nov-25 18:00 | 23-Nov-25 08:00 | 1.58 Days
Continuous |
936L (5s East Calgary - 102s Langdon) | Reconductor between str 15 to 18 on both Circuits for line Clearance Mitigation | |
ALTALINK, EPCOR | 24-Nov-25 07:00 | 28-Nov-25 17:00 | 4.42 Days
Continuous |
1044L (EP 805s Jasper - 816s Petrolia), 816s P2405 (816s Petrolia), 816s P2406 (816s Petrolia) | 1044L: Petrolia 1044L CT LCR | |
EPCOR | 24-Nov-25 07:00 | 30-Nov-25 17:00 | 6.42 Days
Continuous |
EP 803s T3 (EP 803s Lambton), EP 803s L721 (EP 803s Lambton), 72LH8 (EP 803s Lambton - EP Hardisty), 72LS24 (EP 803s Lambton - Strathcona) | Lambton/LH8/LS24: LDS11 and LDS12 LCR | |
ENMAX, ALTALINK | 24-Nov-25 07:00 | 02-Dec-25 12:00 | 8.21 Days
Continuous |
832L (SS-10 - SS-12), 10.1TR (SS-10), 10MD138-10.1TR (SS-10) | 10.1TR 'S' protection replacement. Trip test 10B138-832L. Protection operation 10MD138-10.1TR. | |
ALTALINK | 24-Nov-25 12:00 | 24-Nov-25 18:00 | 6 Hours
Daily |
1005AL (991s Little Bow - 1005L tap), 1005L (120s Picture Butte - 1005AL tap), 1005L (356s Milo - 1005AL tap) | Modifying 1005L85A and closing Open Point 'A' and creating Open Point 'B' on the 120s Picture Butte side of 1005L85A | |
ALTALINK | 24-Nov-25 18:00 | 04-Dec-25 08:30 | 9.6 Days
Continuous |
1005L (120s Picture Butte - 1005AL tap) | Completing maintenance on 1005L (STR 88-228) | |
ALTALINK | 26-Nov-25 23:00 | 27-Nov-25 03:00 | 4 Hours
Continuous |
62s T1 (62s Brazeau Plant) | maintenance | |
ALTALINK | 27-Nov-25 03:00 | 27-Nov-25 07:00 | 4 Hours
Daily |
62s T2 (62s Brazeau Plant) | maintenance | |
ENMAX, ALTALINK | 28-Nov-25 18:00 | 30-Nov-25 08:00 | 1.58 Days
Continuous |
936L (5s East Calgary - 102s Langdon) | Reconductor between str 15 to 18 on both Circuits for line Clearance Mitigation | |
ENMAX, ALTALINK | 28-Nov-25 18:00 | 30-Nov-25 08:00 | 1.58 Days
Continuous |
937L (5s East Calgary - 102s Langdon) | Crew working in vicinity of 936L | |
ENMAX, ALTALINK | 28-Nov-25 18:00 | 30-Nov-25 08:00 | 1.58 Days
Continuous |
937L (5s East Calgary - 102s Langdon) | Crew working in vicinity of 936L | |
ENMAX, ALTALINK | 28-Nov-25 18:00 | 30-Nov-25 08:00 | 1.58 Days
Continuous |
936L (5s East Calgary - 102s Langdon) | Reconductor between str 15 to 18 on both Circuits for line Clearance Mitigation | |
ATCO | 01-Dec-25 13:00 | 05-Dec-25 17:00 | 4.17 Days
Continuous |
732s 901 (732s Mitsue), 732s 902 (732s Mitsue), 9L40 (732s Mitsue - 809s Louise Creek) | 240kV Bus and 144kV Breaker Fail Protection upgrade + Scada Upgrade. Cutover 901, 902, and 9L40 to new Scada system, including end to ends with SOC. |
|
ENMAX, ALTALINK | 02-Dec-25 13:00 | 11-Dec-25 09:00 | 8.83 Days
Continuous |
693L (42s Sarcee - SS-10), 10.2TR (SS-10), 10MD138-10.2TR (SS-10) | 10.2TR 'S' protection replacement. Trip test 10B138-693L. Protection operation 10MD138-10.2TR. | |
ATCO | 04-Dec-25 08:00 | 05-Dec-25 16:00 | 1.33 Days
Continuous |
7L32 (811s Clairmont Lake - 862s South Bezanson) | TCM Pole replacement structure 1 | |
ALTALINK | 04-Dec-25 08:30 | 04-Dec-25 15:00 | 6.5 Hours
Daily |
1005AL (991s Little Bow - 1005L tap), 1005L (120s Picture Butte - 1005AL tap), 1005L (356s Milo - 1005AL tap) | Closing Open point 'B' | |
ATCO | 08-Dec-25 10:00 | 15-Dec-25 16:00 | 7.25 Days
Continuous |
9L40 (732s Mitsue - 809s Louise Creek) | Replace 4 damaged poles ( Need winter access) Structures 221, 286, 299 and 304 | |
ALTALINK | 09-Dec-25 07:00 | 12-Dec-25 17:30 | 3.44 Days
Continuous |
38s 7252 (38s East Edmonton) | Replace Koncar CTs associated with 38s7252 | |
ENMAX, ALTALINK | 11-Dec-25 09:00 | 11-Dec-25 15:00 | 6 Hours
Continuous |
832L (SS-10 - SS-12), 10.1TR (SS-10), Protection & Control (SS-10), 10MD138-10.1TR (SS-10) | Trip testing 10BA8-10.1TR, 10BB8-10.1TR, 10B138-832 | |
ALTALINK, TRANSALTA | 17-Dec-25 10:00 | 17-Dec-25 14:00 | 4 Hours
Daily |
250p T1 (250p Bighorn Plant) | maintenance | |
ALTALINK, TRANSALTA | 18-Dec-25 10:00 | 18-Dec-25 14:00 | 4 Hours
Daily |
250p T2 (250p Bighorn Plant) | maintenance | |
ATCO | 12-Jan-26 13:00 | 21-Jan-26 09:00 | 8.83 Days
Continuous |
9L57 (939s Livock - 960s Birchwood Creek) | 9L57 Line to Ground Clearance Mitigation | |
ATCO | 26-Jan-26 13:00 | 04-Feb-26 09:00 | 8.83 Days
Continuous |
9L57 (939s Livock - 960s Birchwood Creek) | 9L57 Line to Ground Clearance Mitigation | |
ATCO | 09-Feb-26 13:00 | 18-Feb-26 09:00 | 8.83 Days
Continuous |
9L57 (939s Livock - 960s Birchwood Creek) | 9L57 Line to Ground Clearance Mitigation | |
ATCO | 17-Feb-26 09:00 | 03-Mar-26 17:00 | 14.33 Days
Continuous |
972s 240kV Bus 900BS1 (972s Tinchebray) | Install Breaker 904 and 904CT On release leave Bkr 904, 904A/904B closed as feed through (disable bkr trips), Bkr 901 still protecting 9L93 |
|
ATCO | 23-Feb-26 13:00 | 04-Mar-26 09:00 | 8.83 Days
Continuous |
9L57 (939s Livock - 960s Birchwood Creek) | 9L57 Line to Ground Clearance Mitigation | |
SUNCOR | 02-Mar-26 08:00 | 08-Mar-26 20:00 | 6.46 Days
Continuous |
29PL9-16 (29EDD-1 Millennium - 29EDD-94 Voyageur) | 29EDD1;29PT418/29PL9-16 SYSTEM;PM 5y,10y |
|
ALTALINK | 03-Mar-26 07:00 | 09-Mar-26 17:00 | 6.38 Days
Continuous |
944L (132s Ware Junction - 275s Jenner) | Line outage to replace line protection relays at 132s Ware Junction, replace relay comm cards and update settings on line protections at 275s Jenner and implement third terminal 1080s Jurassic line protection relays. End to end testing between all three sites. | |
SUNCOR | 09-Mar-26 08:00 | 15-Mar-26 20:00 | 6.5 Days
Continuous |
29PL9-17 (29EDD-1 Millennium - 29EDD-94 Voyageur) | 29EDD1;29PT419/29PL9-17 SYSTEM;PM 5y,10y |
|
ATCO | 09-Mar-26 13:00 | 18-Mar-26 09:00 | 8.83 Days
Continuous |
9L57 (939s Livock - 960s Birchwood Creek) | 9L57 Line to Ground Clearance Mitigation | |
ATCO | 10-Mar-26 09:00 | 14-Apr-26 17:00 | 35.33 Days
Continuous |
972s 240kV Bus 900BS2 (972s Tinchebray) | Install Breakers 905/906, 905CT/906CT, switches 905A/906B On release leave Bkrs 905/906, 905A/905B, and 906A/906B closed as feed through (disable bkr trips), Bkr 903 still protecting 9L93, leave new 9L62D1 open for future line connection |
|
ATCO, SUNCOR | 16-Mar-26 08:00 | 22-Mar-26 20:00 | 6.5 Days
Continuous |
29PL9-1 (29EDD-1 Millennium - 848s Ruth Lake) | 29EDD1;29CVT-3 SYSTEM;PM 5y,10y |
|
ATCO, SUNCOR | 23-Mar-26 08:00 | 29-Mar-26 20:00 | 6.5 Days
Continuous |
29PL9-2 (29EDD-1 Millennium - 848s Ruth Lake) | 29EDD1;29CVT-1 SYSTEM;PM 5y,10y | |
ATCO, SUNCOR | 30-Mar-26 08:00 | 05-Apr-26 20:00 | 6.5 Days
Continuous |
6L32 (29EDD-1 Millennium - 737s ATC Horseshoe) | 29EDD1;29CVT-6 SYSTEM;5y,10y |
|
ENMAX, ALTALINK | 04-Apr-26 08:00 | 04-Apr-26 18:00 | 10 Hours
Continuous |
1003L (74s Janet - SS-25) | Surge Arrestor Power Factor Test - 25MD240-1003 | |
ENMAX, ALTALINK | 04-Apr-26 08:00 | 04-Apr-26 18:00 | 10 Hours
Continuous |
1003L (74s Janet - SS-25) | Surge Arrestor Power Factor Test - 25MD240-1003 | |
ENMAX, ALTALINK | 05-Apr-26 08:00 | 05-Apr-26 18:00 | 10 Hours
Continuous |
985L (74s Janet - SS-25) | Surge Arrestor Power Factor Test - 25MD240-985 | |
ENMAX, ALTALINK | 05-Apr-26 08:00 | 05-Apr-26 18:00 | 10 Hours
Continuous |
985L (74s Janet - SS-25) | Surge Arrestor Power Factor Test - 25MD240-985 | |
SUNCOR | 06-Apr-26 08:00 | 12-Apr-26 20:00 | 6.5 Days
Continuous |
29PL9-3 (29EDD-1 Millennium - 29EDD-3), 29EDD-3 29PT-6 (29EDD-3) | 29EDD1;29CVT-4 SYSTEM;PM 5y,10y; |
|
ENMAX | 06-Apr-26 08:00 | 14-Apr-26 16:00 | 8.33 Days
Continuous |
65.2TR (SS-65) | Tap Changer Inspection - 65.2-TC | |
SUNCOR | 13-Apr-26 08:00 | 19-Apr-26 20:00 | 6.5 Days
Continuous |
29EDD-1 T1 (29EDD-1 Millennium), 29EDD-1 260kV South Bus 1 (29EDD-1 Millennium), 29EDD-1 72kV South Bus (29EDD-1 Millennium) | 29EDD1;XFMR T1; X260B1; X72B1 SYSTEM;PM 5y | |
SUNCOR | 20-Apr-26 08:00 | 26-Apr-26 20:00 | 6.5 Days
Continuous |
29EDD-1 T2 (29EDD-1 Millennium), 29EDD-1 260kV North Bus 2 (29EDD-1 Millennium), 29EDD-1 72kV North Bus (29EDD-1 Millennium) | 29EDD1;XFMR T2; N260B2; N72B1 SYSTEM;PM 5y | |
ATCO | 21-Apr-26 09:00 | 26-Apr-26 17:00 | 5.33 Days
Continuous |
9LA93 (973s Lanes Lake - 9L93 tap) | Cutover and commission 9L93 protection ccts from Bkrs 901/903 to Bkrs 904/905 **AESO NEEDS TO ADD 9L93, 973S 9LA93D1** |
|
ATCO | 04-May-26 09:00 | 18-May-26 17:30 | 14.35 Days
Continuous |
13L50 (2029s Heathfield - 2075s Newell) | Kinbrook Addition to 2075s | |
ATCO | 04-May-26 09:00 | 18-May-26 17:30 | 14.35 Days
Continuous |
2029s T11 (2029s Heathfield) | Kinbrook Addition to 2075s Newell. | |
ATCO | 04-May-26 09:00 | 18-May-26 17:30 | 14.35 Days
Continuous |
2075s T11 (2075s Newell) | Kinbrook Addition to 2075s Newell. | |
ATCO | 05-May-26 09:00 | 06-May-26 17:00 | 1.33 Days
Continuous |
972s 240kV Bus 900BS1 (972s Tinchebray) | Connect new 907B to 900BS1 |
|
ATCO | 07-May-26 09:00 | 08-May-26 17:00 | 1.33 Days
Continuous |
972s 240kV Bus 900BS2 (972s Tinchebray) | Connect new 909A to 900BS2 | |
ATCO, ALTALINK | 11-May-26 07:00 | 14-May-26 18:00 | 3.46 Days
Continuous |
7LA114 (658s Chard - 7L114 tap), 7L114 (72s Leismer - 7LA114 tap), 7L114 (907s Waddell - 7LA114 tap), 907s Waddell | AltaLink outage on 72sT2 causing an outage to 7L114 at 907S | |
ALTALINK, ATCO | 11-May-26 07:00 | 14-May-26 18:00 | 3.46 Days
Continuous |
72s T2 (72s Leismer), 72s 144kV Bus (72s Leismer), 7L114 (72s Leismer - 7LA114 tap) | Transformer maintenance, doble, install Coresense & Qualitrol | |
ALTALINK, ATCO | 11-May-26 07:00 | 14-May-26 18:00 | 3.46 Days
Continuous |
72s 114 (72s Leismer), 7L114 (72s Leismer - 7LA114 tap) | Customer maintenance | |
SUNCOR | 18-May-26 08:00 | 24-May-26 20:00 | 6.5 Days
Continuous |
29PL9-12 (29EDD-34 - 29EDD-65) | 29EDD34;29PL9-12 SYSTEM;PM 5y,10y |
|
ATCO | 19-May-26 09:00 | 19-May-26 17:00 | 8 Hours
Continuous |
9L16 (755s Cordel - 972s Tinchebray), 755s 904 (755s Cordel), 755s 905 (755s Cordel), 972s 903 (972s Tinchebray) | Disconnect 9L16 from existing A-frame deadend and 9L16D2 (to be renamed 9L86D1) Restore bus leave renamed 9L86D1 open for future line connection. |
|
ATCO | 19-May-26 09:00 | 29-May-26 17:00 | 10.33 Days
Continuous |
9L16 (755s Cordel - 972s Tinchebray) | Disconnect 9L16 from existing A-frame deadend and 9L16D2 (to be renamed 9L86D1) Restore bus leave renamed 9L86D1 open for future line connection. |
|
ATCO | 02-Jun-26 09:00 | 13-Jun-26 17:00 | 11.33 Days
Continuous |
972s 905B (972s Tinchebray), 972s 906A (972s Tinchebray) | Connect new 9L62 to 972S and prepare to energize. String Conductors/OPGW 9L62 from Str #3 to substation A-frame deadends and connect to 9L62D1, coordinate with AML conductor jumpers and OPGW termination at the TFO boundary 9L86 Str 409 |
|
ATCO | 14-Jun-26 09:00 | 25-Jun-26 17:00 | 11.33 Days
Continuous |
9L62 (972s Tinchebray - 87s Gaetz) | Work on parallel line 9L86 | |
ATCO | 16-Jun-26 09:00 | 25-Jun-26 17:00 | 9.33 Days
Continuous |
972s 240kV Bus 900BS2 (972s Tinchebray) | Connect new 9L86 to 972S and prepare to energize. String Conductors/OPGW 9L86 from Str #3 to substation A-frame deadends and connect to 9L86D1, coordinate with AML conductor jumpers and OPGW termination at the TFO boundary 9L86 Str 409 Complete protection commissioning |
|
ATCO | 06-Jul-26 10:00 | 27-Nov-26 16:00 | 144.29 Days
Continuous |
2015s 902 (2015s Yeo) | Remove circuit breaker for use at 2102S Armistead. New breaker to be installed at 2015S Yeo substation once received from manufacturer. | |
ALTALINK | 10-Aug-26 09:30 | 13-Aug-26 17:00 | 3.31 Days
Continuous |
702L (137s Sedgewick - 757s Battle River) | Interphase spacers and pole replacements | |
ATCO | 10-Aug-26 10:00 | 13-Aug-26 16:30 | 3.27 Days
Continuous |
7L702 (137s Sedgewick - 757s Battle River) | Interphase spacers and pole replacements | |
ATCO | 17-Aug-26 10:00 | 20-Aug-26 16:30 | 3.27 Days
Continuous |
7L702 (137s Sedgewick - 757s Battle River) | Interphase spacers and pole replacements | |
ALTALINK | 17-Aug-26 10:00 | 20-Aug-26 16:30 | 3.27 Days
Continuous |
702L (137s Sedgewick - 757s Battle River) | Interphase spacers and pole replacements | |
ALTALINK, ATCO, FMGW | 18-Aug-26 08:00 | 19-Aug-26 17:00 | 1.38 Days
Continuous |
964AL (1024s Granlea - 964L tap), 1024s PT-6001 (1024s Granlea), 1024s PT-6002 (1024s Granlea), 1024s 952-600001 (1024s Granlea), 1024s PS-6005 (1024s Granlea), 1024s PS-6006 (1024s Granlea), 1024s PS-6007 (1024s Granlea), 1024s PS-6008 (1024s Granlea), 1024s 489-600201 (1024s Granlea) | maintenance activities (testing and inspection) of electrical equipment | |
ATCO | 21-Sep-26 10:00 | 24-Sep-26 16:00 | 3.25 Days
Continuous |
888s 906 (888s Dover) | 21B/9L74 relay replacement. Cutover breaker and CT to new protection | |
ATCO | 25-Sep-26 10:00 | 28-Sep-26 16:00 | 3.25 Days
Continuous |
888s 905 (888s Dover) | 21B/9L74 relay replacement. Cutover breaker and CT to new protection | |
ATCO | 05-Oct-26 10:00 | 08-Oct-26 16:00 | 3.25 Days
Continuous |
9L74 (888s Dover - 960s Birchwood Creek) | 21B/9L74 relay three terminal line testing | |
ATCO | 12-Oct-26 10:00 | 15-Oct-26 16:00 | 3.25 Days
Continuous |
888s 906 (888s Dover) | 21A/9L74 relay replacement. Cutover breaker and CT to new protection | |
ATCO | 16-Oct-26 10:00 | 19-Oct-26 16:00 | 3.25 Days
Continuous |
888s 905 (888s Dover) | 21B/9L74 relay replacement. Cutover breaker and CT to new protection | |
ATCO | 26-Oct-26 10:00 | 29-Oct-26 16:00 | 3.25 Days
Continuous |
9L74 (888s Dover - 960s Birchwood Creek) | 21B/9L74 relay three terminal line testing | |
ATCO | 09-Feb-27 09:00 | 11-Feb-27 17:00 | 2.33 Days
Continuous |
7L228 (845s Big Mountain - 7L20 tap) | AESO project P2716 - Install 7L228 bypass to facilitate the installation of new line switches for the new 7LA228 T-tap line connection to the new 2103S Pakenham substation Open 7L228, replace structures 551 and 551A, connect bypass. |
|
ATCO | 24-Feb-27 09:00 | 25-Feb-27 17:00 | 1.33 Days
Continuous |
959s 240kV Bus 900BS1 (959s Lanfine) | Connect new bus from new 902B to existing switch 901A to add new line 9L141, Cutover and commission 900PT1 ccts to new 9L141 relays |
|
ATCO | 26-Feb-27 09:00 | 27-Feb-27 17:00 | 1.33 Days
Continuous |
959s 240kV Bus 900BS2 (959s Lanfine) | Connect new bus from new Bkr 903 to existing switch 903B to add new line 9L141, Cutover and commission 900PT2 ccts to new 9L141 relays |
|
ATCO | 08-Mar-27 10:00 | 17-Mar-27 17:00 | 9.25 Days
Continuous |
9L24 (946s Oakland - 959s Lanfine), 959s 906 (959s Lanfine), 959s 905 (959s Lanfine), 946s 902 (946s Oakland), 946s 903 (946s Oakland) | Replace A/B protection relays at 959S Lanfine and 946S Oakland Cut in and reroute 9L24 Connect new 9LA24 T-tap Commission Telecom and Protection to new 1072S Rose Lynn substation |
|
ATCO | 16-Mar-27 09:00 | 18-Mar-27 17:00 | 2.33 Days
Continuous |
7L228 (845s Big Mountain - 7L20 tap) | AESO project P2716 - Disconnect bypass, connect new 7LA228D1 to 7LA228 Str #2, connect 7L228 to 7L228D2, connect 7L228 to 7L228D3. Renumber existing line switches 7L228D2 - D4, 7L228D3 - D5, 7L228D4 - D6 Commission DTT from Pakenham to Big Mountain |
|
ATCO | 26-Mar-27 09:00 | 29-Mar-27 17:00 | 3.33 Days
Continuous |
740s 704 (740s H.R. Milner), 7L20 (740s H.R. Milner - 810s Dome Cutbank) | AESO project P2716 - cut over RAS #171 wiring at 740S, relay programming, commission LTO 7L20/7L228 | |
ATCO | 12-Apr-27 10:00 | 19-Apr-27 17:00 | 7.29 Days
Continuous |
7L22 (790s Poplar Hill - 7L88 tap) | Cut open 7L22, connect new line section to new 2061S Dobbs 7L22/21B relay upgrades at 790S Poplar Hill and 811S Clairmont Lake On completion energize new 2061S Dobbs substation |
|
ATCO | 03-May-27 10:00 | 06-May-27 17:00 | 3.29 Days
Continuous |
7L22 (811s Clairmont Lake - 7L88 tap) | 7L22/21B relay upgrade at 811S Clairmont Lake Upon completion new 2061S Dobbs substation ready to energize |
|
ATCO | 10-May-27 10:00 | 11-May-27 17:00 | 31 Hours
Continuous |
7L03 (749s Flyingshot Lake - 7L09 tap) | Cutover and commission RAS analogs and LTO to 790S Poplar Hill RAS Hub | |
ATCO | 12-May-27 10:00 | 13-May-27 17:00 | 31 Hours
Continuous |
7L03 (731s Elmworth - 7L09 tap) | Cutover and commission LTO to 790S Poplar Hill RAS Hub | |
ATCO | 14-May-27 10:00 | 15-May-27 17:00 | 31 Hours
Continuous |
7L69 (731s Elmworth - 815s Goodfare) | Cutover and commission LTO to 790S Poplar Hill RAS Hub | |
ATCO | 16-May-27 10:00 | 17-May-27 17:00 | 31 Hours
Continuous |
7L07 (790s Poplar Hill - 815s Goodfare) | Cutover and commission LTO to 790S Poplar Hill RAS Hub | |
ATCO | 20-Jul-27 08:00 | 21-Jul-27 17:00 | 1.38 Days
Continuous |
7L53 (706s Irish Creek - 7LA53 tap), 7LA53 (969s Lindbergh - 7L53 tap), 7L53 (700s Bonnyville - 7LA53 tap) | Cold Lake Area Project to connect 1064s | |
ATCO | 22-Jul-27 08:00 | 25-Jul-27 17:00 | 3.38 Days
Continuous |
7L91 (715s Leming Lake - 826s Marguerite Lake) | Cold Lake Area Energy Centre Project |
|
ALTALINK, ATCO, FMGW | 17-Aug-27 08:00 | 18-Aug-27 17:00 | 1.38 Days
Continuous |
964AL (1024s Granlea - 964L tap), 1024s PT-6001 (1024s Granlea), 1024s PT-6002 (1024s Granlea), 1024s 952-600001 (1024s Granlea), 1024s PS-6005 (1024s Granlea), 1024s PS-6006 (1024s Granlea), 1024s PS-6007 (1024s Granlea), 1024s PS-6008 (1024s Granlea), 1024s 489-600201 (1024s Granlea) | maintenance activities (testing and inspection) of electrical equipment | |
ALTALINK | 08-Nov-27 08:30 | 11-Nov-27 17:30 | 3.38 Days
Continuous |
409s 110 (409s Shell Scotford) | Install new Deadend corner structure on ALC02L | |
ATCO | 08-Nov-27 09:00 | 11-Nov-27 17:00 | 3.33 Days
Continuous |
ALC02L (409s Shell Scotford - 879s Upgrader) | Install new Deadend corner structure on ALC02L | |
ATCO | 08-Nov-27 09:00 | 11-Nov-27 17:00 | 3.33 Days
Continuous |
ALC01L (408s Air Liquide Scotford - 409s Shell Scotford) | Install new Deadend corner structure on ALC02L. |
AB-BC, AB-SK & AB-MATL: refer to AESO web posting: | http://itc.aeso.ca/itc/public/atc |
Also, | |
AB-BC, AB-SK & AB-MATL: refer to ISO Rule 203.6: | http://www.aeso.ca/rulesprocedures/18592.html |
Prepared On: | 2025-08-20 16:35:32 |
This document and the information contained herein are based upon information and data which by their nature contain a degree of uncertainty and are subject to change. In addition, this document may contain information and data from public sources and/or third parties, which have been assumed to be accurate and complete and have not been verified. Accordingly, the Independent System Operator, operating as the Alberta Electric System Operator (the "AESO") makes no warranty, representation or guarantee, express or implied, with respect to this document or the information contained herein, including, but not limited to, any warranty, representation or guarantee of accuracy, completeness, timeliness, reliability, availability, absence of computer virus, non- infringement, merchantability or suitability for any purpose. Under no circumstances will the AESO, its members, officers, employees, contractors or agents, or any of their respective affiliates, be liable for any errors or omissions in, or any losses, damages or claims whatsoever, whether in contract, tort or otherwise, arising from use of or reliance upon, this document or any information contained herein. © 2009 Alberta Electric System Operator. All rights reserved |