Alberta Electric System Operator
Long Range Significant Transmission Outages for the period of 24 months starting 2026-01-24

The table below contains the significant transmission outages submitted as tentative to the AESO.
These Outages have not yet necessarily been approved, but are listed for awareness and coordination purposes.
An Outage has been considered significant for this table if it meets any one (1) or more of the following criteria:
  1. it affects a transmission facility operating at two hundred and forty (240) kV or greater;
  2. it affects an intertie;
  3. it affects an element connecting facilities owned by two (2) or more different legal owners of transmission facilities;
  4. it affects an element that connects a generating unit or an aggregated generating facility to the interconnected electric system;
  5. it requires the ISO to issue a dispatch or directive for generation in order to facilitate the planned outage;
  6. it affects a cutplane limit;
  7. it limits or reduces the operability of a synchronous condenser, static VAr compensator, static compensator or other similar dynamic device; or
  8. it affects high voltage direct current facilities.
Note: Where a transmission outage requires generation curtailments, the adjustments to generation will typically happen in the hours before the scheduled transmission outage and in the hour after the element is returned to service.

Previous Version
Download CSV

Owner From To Duration Element Scheduled Activity Affected Intertie
EPCOR 25-Jul-25 17:01 17-Apr-26 17:00 266 Days
Continuous
T2 (EP Riverview) bushing test failure (found during OE110184)  
ALTALINK 01-Nov-25 12:00 01-Feb-26 18:00 92.29 Days
Continuous
AML 511s ACF12 (AML 511s Crossings) forced outage  
ATCO 25-Nov-25 17:46 30-Jan-26 18:00 66.01 Days
Continuous
876s 901T (876s Brintnell) forced outage oil leaking  
SUNCOR 04-Jan-26 08:00 31-Mar-26 16:00 86.29 Days
Continuous
29EDD-34 260kV Bus 29PP-45 (29EDD-34), 29EDD-34 29-952-113 (29EDD-34) urgent repairs on 29PT-224 at 29EDD34 on 29PP-45 bus  
ALTALINK, EPCOR 26-Jan-26 07:00 30-Jan-26 17:00 4.42 Days
Continuous
920L (37s North Calder - 557s Castle Downs), 557s CD2405 (557s Castle Downs), 557s CD2406 (557s Castle Downs) 920LW/Castledowns: Relay Maintenance and Op Checks  
ATCO 26-Jan-26 09:00 04-Feb-26 15:00 9.25 Days
Continuous
9L57 (939s Livock - 960s Birchwood Creek) 9L57 Line to Ground Clearance Mitigation  
ATCO 28-Jan-26 09:00 28-Jan-26 11:00 2 Hours
Continuous
9L59 (801s Anderson - 9LA59 tap) accommodate outage 1-00508220  
ALTALINK 02-Feb-26 07:00 02-Feb-26 18:30 11.5 Hours
Daily
922L (17s Benalto - 310p Sundance) Clipping in 922L OHSW between strs 922L1 and 922L7, after raising 922/926L4. See also SAP: 401749 926L RB required due to proximity  
ALTALINK, EPCOR 02-Feb-26 07:00 06-Feb-26 17:00 4.42 Days
Continuous
920L (71s Lamoureux - 557s Castle Downs), 557s CD2405 (557s Castle Downs), 557s CD2404 (557s Castle Downs) 920LE/Castledowns: Relay Maintenance and Op Checks  
ALTALINK 02-Feb-26 19:00 03-Feb-26 18:30 23.5 Hours
Continuous
926L (17s Benalto - 310p Sundance) Clipping in 926L OHSW between strs 926L1 and 926L7, after raising str 922/926L4 See also SAP: 401745 922L RB required due to proximity  
ATCO 05-Feb-26 07:00 08-Feb-26 16:00 3.38 Days
Continuous
9L913 (69s North Barrhead - 732s Mitsue) Changing white tag poles from Test & Treat ( Str 16,69 and 503 )  
ALTALINK 05-Feb-26 07:00 08-Feb-26 16:30 3.4 Days
Continuous
913L (69s North Barrhead - 732s Mitsue) Changing white tag poles from Test & Treat ( Str 16,69 and 503 )  
Syncrude 09-Feb-26 08:00 20-Feb-26 16:00 11.33 Days
Continuous
Mildred T6 (Syncrude Mildred Lake), 6335 (Syncrude Mildred Lake), 634 (Syncrude Mildred Lake), 635 (Syncrude Mildred Lake) SCL - Repair Tap Changer in T6 Transformer.  
ATCO 09-Feb-26 09:00 18-Feb-26 13:00 9.17 Days
Continuous
9L57 (939s Livock - 960s Birchwood Creek) 9L57 Line to Ground Clearance Mitigation  
ENMAX, ALTALINK 17-Feb-26 08:00 18-Feb-26 16:00 1.33 Days
Continuous
832L (SS-10 - SS-12), 12.1TR (SS-12) HV SW Maintenance SW84, SW85, SW86, MD-12.1TR. Reversing Switch Check - 12.1-TC  
BCH 17-Feb-26 08:00 24-Feb-26 16:00 7.33 Days
Continuous
T3 (BCH Natal) ETM install AB-BC
ATCO 17-Feb-26 09:00 03-Mar-26 17:00 14.33 Days
Continuous
972s 240kV Bus 900BS1 (972s Tinchebray) Install Breaker 904 and 904CT
On release leave Bkr 904, 904A/904B closed as feed through (disable bkr trips), Bkr 901 still protecting 9L93
 
ALTALINK 18-Feb-26 07:00 18-Feb-26 18:00 11 Hours
Daily
254s T2 (254s Coaldale) Add T2 tap position sensor and tap position visibility. The tap changer will be run through the various positions to ensure visibility in all positions.  
ALTALINK 19-Feb-26 07:00 19-Feb-26 18:00 11 Hours
Daily
135s T1 (135s Conrad), 135s 138kV Bus (135s Conrad), 607L (135s Conrad - 607AL tap) Add T1 tap position sensor and tap position visibility. The tap changer will be run through the various positions to ensure visibility in all positions.  
ENMAX, ALTALINK 19-Feb-26 08:00 20-Feb-26 16:00 1.33 Days
Continuous
833L (SS-2 - SS-12), 12.2TR (SS-12) HV SW Maintenance SW81, SW82, SW83, MD-12.2TR. Reversing Switch Check - 12.2-TC  
ATCO 19-Feb-26 08:00 22-Feb-26 16:00 3.33 Days
Continuous
9L40 (732s Mitsue - 809s Louise Creek) Changing rotten poles from our inspection.  
ALTALINK 19-Feb-26 09:00 19-Feb-26 18:00 9 Hours
Daily
862L (166s Dow Chemical Fort Saskatchewan - 258s Dow Hydrocarbons) Arctic arrow requires a GOI on 862L for a planned high load move between structures 26-27. See also 402077 706L GOI  
EPCOR 23-Feb-26 07:00 20-Mar-26 17:00 25.38 Days
Continuous
805s T3 (805s Jasper) Jasper TX3: Bushing Change (PCB)  
ATCO 23-Feb-26 08:30 24-Feb-26 14:00 29.5 Hours
Continuous
7L91 (715s Leming Lake - 826s Marguerite Lake) Install aerial nest platform pole and transfer osprey nest from 7L91-158  
ATCO 23-Feb-26 09:00 04-Mar-26 13:00 9.17 Days
Continuous
9L57 (939s Livock - 960s Birchwood Creek) 9L57 Line to Ground Clearance Mitigation  
EPCOR 24-Feb-26 07:00 24-Feb-26 17:00 10 Hours
Continuous
330p 1209 (330p Genesee) Genesee: 1209 Breaker Status Indicator Investigation  
ALTALINK 26-Feb-26 09:00 26-Feb-26 18:00 9 Hours
Daily
862L (166s Dow Chemical Fort Saskatchewan - 258s Dow Hydrocarbons) Arctic arrow requires a GOI on 862L for a planned high load move between structures 26-27. Goes with 402078 706L GOI  
SUNCOR 01-Mar-26 08:00 05-Mar-26 20:00 4.5 Days
Continuous
29EDD-1 Millennium, 29EDD-1 T2 (29EDD-1 Millennium) 29EDD-1S - Correct leaning structure for 29CVT-13 (T2 Outage) - 300551776  
ALTALINK, EPCOR 02-Mar-26 07:00 03-Mar-26 17:00 1.42 Days
Continuous
1044L (EP 805s Jasper - 816s Petrolia), EP 805s J2403 (EP 805s Jasper), EP 805s J2404 (EP 805s Jasper), 816s P2405 (816s Petrolia), 816s P2406 (816s Petrolia) Petrolia: 1044L Relay Maintenance and PDS14 Repair  
EPCOR 02-Mar-26 07:00 06-Mar-26 17:00 4.42 Days
Continuous
557s T2 (557s Castle Downs) Castle Downs: TX2 Surge Arrestor LCR  
EPCOR 02-Mar-26 07:00 06-Mar-26 17:00 4.42 Days
Continuous
EP 803s T1 (EP 803s Lambton), EP 803s L2401 (EP 803s Lambton), EP 803s L2402 (EP 803s Lambton) Lambton: TX1 Relay Maintenance  
SUNCOR 02-Mar-26 08:00 08-Mar-26 20:00 6.46 Days
Continuous
29PL9-16 (29EDD-1 Millennium - 29EDD-94 Voyageur) 29EDD1;29PT418/29PL9-16 SYSTEM;PM 5y,10y
 
ALTALINK 02-Mar-26 12:30 05-Mar-26 17:30 3.21 Days
Continuous
749L (899s Edgerton - 7LB749 tap) Replace 749LN A21/L8. Update settings on B21/L8.  
ALTALINK 03-Mar-26 07:00 09-Mar-26 17:00 6.38 Days
Continuous
944L (132s Ware Junction - 275s Jenner) Replace line relays at 132s Ware Junction, replace relay comm cards and update settings on protections at 275s Jenner, implement third 944AL terminal. New 1080s Raptor line protection relays. End to end testing new 1080s Raptor and 944ALtap addition.  
BCH 03-Mar-26 08:00 05-Mar-26 16:00 2.33 Days
Continuous
T7 (BCH Natal) ETM install AB-BC
EPCOR 04-Mar-26 07:00 06-Mar-26 17:00 2.42 Days
Continuous
816s T1 (816s Petrolia), 816s P2402 (816s Petrolia), 816s P2401 (816s Petrolia) Petrolia: TX1 Relay Maintenance  
ALTALINK 04-Mar-26 23:00 05-Mar-26 03:00 4 Hours
Continuous
62s T1 (62s Brazeau Plant) maintenance  
ALTALINK 05-Mar-26 03:00 05-Mar-26 07:00 4 Hours
Daily
62s T2 (62s Brazeau Plant) maintenance  
ALTALINK 05-Mar-26 07:00 05-Mar-26 18:00 11 Hours
Daily
1037L (138s Windy Flats - 266s SC1), 1037L (237s Foothills - 266s SC1) South Crew will be doing component replacement on 1037L (STR 280-342)See also SAP: 401547 1038L RB Required due to proximity.  
ATCO 05-Mar-26 08:00 08-Mar-26 16:00 3.29 Days
Continuous
9L40 (732s Mitsue - 809s Louise Creek) Changing rotten poles from our inspection.  
ALTALINK, EPCOR 09-Mar-26 07:00 10-Mar-26 17:00 1.42 Days
Continuous
908L (89s Ellerslie - 816s Petrolia), 816s P2401 (816s Petrolia), 816s P2406 (816s Petrolia) Petrolia: 908L Relay Maintenance  
ALTALINK, EPCOR 09-Mar-26 07:00 13-Mar-26 17:00 4.42 Days
Continuous
1059L (EP 803s Lambton - 1059AL tap), EP 803s L2401 (EP 803s Lambton), EP 803s L2404 (EP 803s Lambton) 1059L/Lambton: Relay Maintenance  
SUNCOR 09-Mar-26 08:00 15-Mar-26 20:00 6.5 Days
Continuous
29PL9-17 (29EDD-1 Millennium - 29EDD-94 Voyageur) 29EDD1;29PT419/29PL9-17 SYSTEM;PM 5y,10y
 
ATCO 09-Mar-26 13:00 18-Mar-26 09:00 8.83 Days
Continuous
9L57 (939s Livock - 960s Birchwood Creek) 9L57 Line to Ground Clearance Mitigation  
ALTALINK 10-Mar-26 07:00 10-Mar-26 18:00 11 Hours
Daily
1072L (103s Goose Lake - 205s Castle Rock Ridge) South Crew will be doing component replacement on 1072L15  
ALTALINK 10-Mar-26 07:00 13-Mar-26 18:00 3.46 Days
Continuous
1325L (510s Sunnybrook - AML 511s Crossings) South Crew will be doing component replacement on 1325L (STR 501-542)  
ATCO 10-Mar-26 09:00 14-Apr-26 17:00 35.33 Days
Continuous
972s 240kV Bus 900BS2 (972s Tinchebray) Install Breakers 905/906, 905CT/906CT, switches 905A/906B
On release leave Bkrs 905/906, 905A/905B, and 906A/906B closed as feed through (disable bkr trips), Bkr 903 still protecting 9L93, leave new 9L62D1 open for future line connection
 
ENMAX, ALTALINK 10-Mar-26 10:00 10-Mar-26 12:00 2 Hours
Continuous
28.80L (42s Sarcee - SS-28) 1 sub Transmission line cut over.  
ENMAX, ALTALINK 10-Mar-26 10:00 10-Mar-26 12:00 2 Hours
Daily
28.80L (42s Sarcee - SS-28) 1 sub Transmission line cut over..  
EPCOR 11-Mar-26 07:00 11-Mar-26 17:00 10 Hours
Continuous
557s CD2401 (557s Castle Downs) Castledowns: CD2401 NAIT Student Substation Tour  
EPCOR 11-Mar-26 07:00 13-Mar-26 17:00 2.42 Days
Continuous
816s T2 (816s Petrolia), 816s P2404 (816s Petrolia), 816s P2405 (816s Petrolia) Petrolia: TX2 Relay Maintenance  
ALTALINK 13-Mar-26 07:15 13-Mar-26 17:45 10.5 Hours
Daily
199L (268s Whitecourt - 199AL tap) Replace keeper keys at structure 375  
EPCOR 16-Mar-26 07:00 16-Mar-26 17:00 10 Hours
Continuous
816s P2403 (816s Petrolia) Petrolia: P2403 Relay Maintenance  
ALTALINK, EPCOR 16-Mar-26 07:00 19-Mar-26 17:00 3.42 Days
Continuous
1058L (657s Summerside - EP 803s Lambton), EP 803s L2403 (EP 803s Lambton), EP 803s L2404 (EP 803s Lambton), 657s SU2403 (657s Summerside), 657s SU2404 (657s Summerside) 1058L: Lambton Surge Counter Install and Summerside SUDS10 Ice Shield Repair  
EPCOR 16-Mar-26 07:00 20-Mar-26 17:00 4.42 Days
Continuous
805s T3 (805s Jasper), EP 805s J2405 (EP 805s Jasper), EP 805s J2404 (EP 805s Jasper) Jasper: TX3 Relay Maintenance  
EPCOR 16-Mar-26 07:00 20-Mar-26 17:00 4.42 Days
Continuous
T2 (Poundmaker) Poundmaker: TX2 Bladder and Sample Pipe Repair  
ALTALINK 16-Mar-26 07:00 25-Mar-26 18:00 9.46 Days
Continuous
87s 240kV West Bus (87s Gaetz), 87s T1 (87s Gaetz) Installing new 87s1752 & 87s1952. Closing Open Points 'F', 'G', 'H'.  
ALTALINK 16-Mar-26 07:15 19-Mar-26 17:45 3.44 Days
Continuous
788L (898s Heart Lake - 788AL tap), 788L107A (788AL tap), 602L1 (602L tap) component replacement on 788L (STR 157 - 218)  
ATCO, SUNCOR 16-Mar-26 08:00 22-Mar-26 20:00 6.5 Days
Continuous
29PL9-1 (29EDD-1 Millennium - 848s Ruth Lake) 29EDD1;29CVT-3 SYSTEM;PM 5y,10y
 
ATCO 16-Mar-26 10:00 16-Mar-26 16:00 6 Hours
Continuous
715s 701 (715s Leming Lake), 7L583 (715s Leming Lake - 970s Bourque) PRC-005 Trip Coil Testing, 701CT Inspection/ Testing  
BCH 17-Mar-26 08:00 20-Mar-26 16:00 3.33 Days
Continuous
5L92 (BCH Cranbrook - BCH Selkirk) replace end of life spacers. AB-BC
ATCO 17-Mar-26 10:00 17-Mar-26 16:00 6 Hours
Continuous
715s 702 (715s Leming Lake), 7L91 (715s Leming Lake - 826s Marguerite Lake) PRC-005 Trip Coil Testing, 702CT Inspection/ Testing  
ALTALINK 18-Mar-26 07:00 19-Mar-26 18:00 1.46 Days
Continuous
1002L (163s Amoco Empress - 275s Jenner) South Crew will be doing component replacement on 1002L (STR 67-99)  
ATCO 18-Mar-26 10:00 18-Mar-26 16:00 6 Hours
Continuous
715s 703 (715s Leming Lake), 7L66 (715s Leming Lake - 717s Ethel Lake) PRC-005 Trip Coil Testing, 703CT Inspection/ Testing  
EPCOR 20-Mar-26 07:00 20-Mar-26 17:00 10 Hours
Continuous
52s T2 (52s East Industrial), 908AL (52S East Industrial - 908L tap) 908LW/East Industrial: EDS2 Repair/Adjustment  
EPCOR 23-Mar-26 07:00 23-Mar-26 17:00 10 Hours
Continuous
RW2401 (EP Riverview) Riverview: RW2401 (SF6) Breaker Maintenance  
ALTALINK 23-Mar-26 07:00 26-Mar-26 16:30 3.4 Days
Continuous
AML 511s T30 (AML 511s Crossings), AML 511s SVC Plus (AML 511s Crossings) Firmware upgrades on protections that are OOS, VCS Maintenance, Annual SVC+ maintenance  
EPCOR, ALTALINK 23-Mar-26 07:00 27-Mar-26 17:00 4.42 Days
Continuous
EP 805s J2406 (EP 805s Jasper), EP 805s J2407 (EP 805s Jasper), 1045L (EP 805s Jasper - 1045AL tap), 1098L (EP 805s Jasper - Poundmaker) 1098L/1045L/Jasper: Relay Maintenance  
ATCO, SUNCOR 23-Mar-26 08:00 29-Mar-26 20:00 6.5 Days
Continuous
29PL9-2 (29EDD-1 Millennium - 848s Ruth Lake) 29EDD1;29CVT-1 SYSTEM;PM 5y,10y  
EPCOR 24-Mar-26 07:00 24-Mar-26 17:00 10 Hours
Continuous
RW2402 (EP Riverview) Riverview: RW2402 (SF6) Breaker Maintenance  
ALTALINK 26-Mar-26 07:00 26-Mar-26 18:00 11 Hours
Daily
237s T2 (237s Foothills), 237s 240kV Bus 2 (237s Foothills) Install bus support piles for new 240kV Bay.  
ALTALINK 27-Mar-26 07:00 27-Mar-26 18:00 11 Hours
Daily
237s T1 (237s Foothills), 237s 240kV Bus 1 (237s Foothills) Install bus support piles for new 240kV Bay.  
EPCOR 30-Mar-26 07:00 02-Apr-26 17:00 3.42 Days
Continuous
987s T3 (987s Clover Bar), 987s C2407 (987s Clover Bar) Cloverbar: C2407 (SF6) Breaker Maintenance and TX3 Relay Maintenance  
EPCOR 30-Mar-26 07:00 02-Apr-26 17:00 3.42 Days
Continuous
805s T1 (805s Jasper), 805s C1 (805s Jasper), EP 805s J2401 (EP 805s Jasper), EP 805s J2403 (EP 805s Jasper), EP 805s J2408 (EP 805s Jasper), EP 805s J724 (EP 805s Jasper), EP 805s J722 (EP 805s Jasper) Jasper: TX1, CAP BANK Relay Maintenance  
ALTALINK 30-Mar-26 07:00 08-Apr-26 18:00 9.46 Days
Continuous
87s 240kV East Bus (87s Gaetz), 87s T2 (87s Gaetz), 914L (86s Bigstone - 87s Gaetz) Installing new 87s1352 & 87s1552. Closing Open points 'E', 'J', 'K' & 'L'. Creating permanent bus cut between 87s27 & 87s 240kV East Bus.  
ATCO, SUNCOR 30-Mar-26 08:00 05-Apr-26 20:00 6.5 Days
Continuous
6L32 (29EDD-1 Millennium - 737s ATC Horseshoe) 29EDD1;29CVT-6 SYSTEM;5y,10y
 
SUNCOR 01-Apr-26 08:00 10-Apr-26 20:00 9.5 Days
Continuous
29EDD-34 29PT-341 (29EDD-34), 29EDD-34 29-952-142 (29EDD-34), 29EDD-34 29-952-143 (29EDD-34), 29EDD-34 29-652-10200T (29EDD-34), 29EDD-34 29-652-10301 (29EDD-34), 29EDD-34 29-652-10302 (29EDD-34), 29EDD-34 29-652-10303 (29EDD-34), 29EDD-34 29PS-0375 (29EDD-34), 29EDD-34 29PS-0380 (29EDD-34), 29EDD-34 29PS-0381 (29EDD-34), 29EDD-34 29PS-0383 (29EDD-34), 29EDD-34 29PS-609 (29EDD-34) 10 year PM on 29EDD34;29PT-341 system and 5 year, 10 year PM on 29EDD34;29PP-103 system
 
SUNCOR 01-Apr-26 08:00 11-Apr-26 20:00 10.5 Days
Continuous
29EDD-34 29PT-340 (29EDD-34) 29EDD34;29PT-340 SYSTEM;PM 5y,10y; 29EDD34;29PP-102 SYSTEM;PM 5y,10y
 
ENMAX, ALTALINK 04-Apr-26 08:00 04-Apr-26 18:00 10 Hours
Continuous
1003L (74s Janet - SS-25) Surge Arrestor Power Factor Test - 25MD240-1003  
ENMAX, ALTALINK 04-Apr-26 08:00 04-Apr-26 18:00 10 Hours
Continuous
1003L (74s Janet - SS-25) Surge Arrestor Power Factor Test - 25MD240-1003  
ENMAX, ALTALINK 05-Apr-26 08:00 05-Apr-26 18:00 10 Hours
Continuous
985L (74s Janet - SS-25) Surge Arrestor Power Factor Test - 25MD240-985  
ENMAX, ALTALINK 05-Apr-26 08:00 05-Apr-26 18:00 10 Hours
Continuous
985L (74s Janet - SS-25) Surge Arrestor Power Factor Test - 25MD240-985  
SUNCOR 06-Apr-26 08:00 12-Apr-26 20:00 6.5 Days
Continuous
29PL9-3 (29EDD-1 Millennium - 29EDD-3), 29EDD-3 29PT-6 (29EDD-3) 29EDD1;29CVT-4 SYSTEM;PM 5y,10y;
 
ENMAX 06-Apr-26 08:00 14-Apr-26 16:00 8.33 Days
Continuous
65.2TR (SS-65) Tap Changer Inspection - 65.2-TC  
EPCOR 13-Apr-26 07:00 13-Apr-26 17:00 10 Hours
Continuous
72JW19 (EP 805s Jasper - Woodcroft), 805s T1 (805s Jasper), EP 805s J722 (EP 805s Jasper), EP 805s J724 (EP 805s Jasper) Jasper: JDS21 Repair  
ALTALINK, EPCOR 13-Apr-26 07:00 17-Apr-26 17:00 4.42 Days
Continuous
947L (89s Ellerslie - 987s Clover Bar), 987s C2402 (987s Clover Bar), 987s C2404 (987s Clover Bar) Cloverbar: 947L Relay Maintenance  
ALTALINK 13-Apr-26 07:00 20-Apr-26 18:00 7.46 Days
Continuous
87s 240kV West Bus (87s Gaetz), 87s T1 (87s Gaetz), 914L (86s Bigstone - 87s Gaetz) Closing Open point 'I' and creating second permanent bus cut between 87s26 & 87s 240kV West Bus.  
EPCOR 13-Apr-26 07:00 08-May-26 17:00 25.42 Days
Continuous
805s T4 (805s Jasper) Jasper TX4: Bushing Change (PCB) and Fan Failure Repair and Conservator Tank Inspection  
SUNCOR 13-Apr-26 08:00 19-Apr-26 20:00 6.5 Days
Continuous
29EDD-1 T1 (29EDD-1 Millennium), 29EDD-1 260kV South Bus 1 (29EDD-1 Millennium), 29EDD-1 72kV South Bus (29EDD-1 Millennium) 29EDD1;XFMR T1; X260B1; X72B1 SYSTEM;PM 5y  
ALTALINK, TRANSALTA 13-Apr-26 10:00 17-Apr-26 16:00 4.25 Days
Continuous
179s T1 (179s Gleichen) 179s Oil reclaim, 25kV insulator replacements throughout 179s25,179s9,179s26 line sides & 25kV Bus / VR1 and bus side of 179s6, T1 maintenance,& VR1 maintenance.  
SUNCOR 20-Apr-26 08:00 26-Apr-26 20:00 6.5 Days
Continuous
29EDD-1 T2 (29EDD-1 Millennium), 29EDD-1 260kV North Bus 2 (29EDD-1 Millennium), 29EDD-1 72kV North Bus (29EDD-1 Millennium) 29EDD1;XFMR T2; N260B2; N72B1 SYSTEM;PM 5y  
ATCO 20-Apr-26 13:00 20-Apr-26 17:30 4.5 Hours
Continuous
755s 901 (755s Cordel) PRC-005 - TRIP & CLOSE COIL TESTING.  
ATCO 21-Apr-26 09:00 26-Apr-26 17:00 5.33 Days
Continuous
9LA93 (973s Lanes Lake - 9L93 tap) Cutover and commission 9L93 protection ccts from Bkrs 901/903 to Bkrs 904/905

 
ATCO 21-Apr-26 09:30 21-Apr-26 12:00 2.5 Hours
Continuous
755s 902 (755s Cordel) PRC-005 - TRIP & CLOSE COIL TESTING.  
ATCO 21-Apr-26 13:00 21-Apr-26 17:30 4.5 Hours
Continuous
755s 904 (755s Cordel) PRC-005 - TRIP & CLOSE COIL TESTING.  
ATCO 22-Apr-26 09:30 24-Apr-26 17:30 2.33 Days
Continuous
755s 903 (755s Cordel) PRC-005 - TRIP & CLOSE COIL TESTING.  
ALTALINK 22-Apr-26 23:00 23-Apr-26 03:00 4 Hours
Continuous
62s T1 (62s Brazeau Plant) maintenance  
ALTALINK 23-Apr-26 03:00 23-Apr-26 07:00 4 Hours
Daily
62s T2 (62s Brazeau Plant) maintenance  
ALTALINK 27-Apr-26 09:00 01-May-26 18:00 4.38 Days
Continuous
953L (574s Nilrem - 755s Cordel) Switch and breaker maintenance  
ALTALINK, EPCOR 27-Apr-26 09:30 27-Apr-26 17:00 7.5 Hours
Continuous
1057L (89s Ellerslie - 657s Summerside), 657s SU2401 (657s Summerside), 657s SU2402 (657s Summerside) 1057L/Summerside: CVT/Arrestor Doble, SUDS1/SUDS3/SUDS9 Disconnect Maintenance  
ATCO 27-Apr-26 09:30 01-May-26 17:30 4.33 Days
Continuous
755s 905 (755s Cordel), 755s 906 (755s Cordel), 9L953 (574s Nilrem - 755s Cordel) PRC-005 - TRIP COIL TESTING - BREAKER 905 @ 755S
PRC-005 - TRIP & CLOSE COIL TESTING - BREAKER 906 @ 755S
Adjust 905B Switch at 755s Cordel
Adjust 906A Switch at 755s Cordel
Repair 9L953D1 at 755s Cordel
RTXP Test Switch Mitigation and Replacement
 
ALTALINK 29-Apr-26 08:00 07-May-26 18:00 8.42 Days
Continuous
275s T2 (275s Jenner) 275sT2 Oil Reclaim  
EPCOR 04-May-26 07:00 08-May-26 17:00 4.42 Days
Continuous
805s T4 (805s Jasper), EP 805s J2406 (EP 805s Jasper), EP 805s J2405 (EP 805s Jasper) Jasper: TX4 Relay Maintenance  
EPCOR 04-May-26 07:00 10-May-26 17:00 6.42 Days
Continuous
BR721 (Rossdale), 814s T1 (814s Bellamy), 814s B2401 (814s Bellamy), 814s B2407 (814s Bellamy) Bellamy: TX1 Zone Doble and BR721 Breaker Maintenance/Doble, and BDS15 Disconnect Maintenance  
EPCOR 04-May-26 07:00 10-May-26 17:00 6.42 Days
Continuous
557s T2 (557s Castle Downs), 557s CD2403 (557s Castle Downs), 557s CD2404 (557s Castle Downs) Castledowns: TX2 Doble, Tap Changer Maintenance, and CDAB2CDDS6/CDDS7 Disconnect Maintenance  
ATCO 04-May-26 09:00 18-May-26 17:30 14.35 Days
Continuous
13L50 (2029s Heathfield - 2075s Newell) Kinbrook Addition to 2075s  
ATCO 04-May-26 09:00 18-May-26 17:30 14.35 Days
Continuous
2029s T11 (2029s Heathfield) Kinbrook Addition to 2075s Newell.  
ATCO 04-May-26 09:00 18-May-26 17:30 14.35 Days
Continuous
2075s T11 (2075s Newell) Kinbrook Addition to 2075s Newell.  
ATCO 05-May-26 09:00 07-May-26 17:00 2.33 Days
Continuous
9L59 (801s Anderson - 9LA59 tap), 9L59 (972s Tinchebray - 9LA59 tap) Connect new 907B to 900BS1
 
ATCO 07-May-26 09:00 19-May-26 17:00 12.33 Days
Continuous
9L16 (755s Cordel - 972s Tinchebray) GOI is required on 907B to isolate 908/909 bay and new 9L16.  
ATCO 08-May-26 09:00 09-May-26 17:00 1.33 Days
Continuous
972s 240kV Bus 900BS2 (972s Tinchebray) Connect new 909A to 900BS2  
EPCOR 11-May-26 07:00 13-May-26 17:00 2.42 Days
Continuous
557s T1 (557s Castle Downs) Castledowns: TX1 Tap Changer Maintenance and Conservator Pipe Leak Repair  
ATCO, ALTALINK 11-May-26 07:00 14-May-26 18:00 3.46 Days
Continuous
7LA114 (658s Chard - 7L114 tap), 7L114 (72s Leismer - 7LA114 tap), 7L114 (907s Waddell - 7LA114 tap), 907s Waddell AltaLink outage on 72sT2 causing an outage to 7L114 at 907S  
ALTALINK, ATCO 11-May-26 07:00 14-May-26 18:00 3.46 Days
Continuous
72s T2 (72s Leismer), 72s 144kV Bus (72s Leismer), 7L114 (72s Leismer - 7LA114 tap) Transformer maintenance, doble, install Coresense & Qualitrol  
ALTALINK, ATCO 11-May-26 07:00 14-May-26 18:00 3.46 Days
Continuous
72s 114 (72s Leismer), 7L114 (72s Leismer - 7LA114 tap) maintenance  
EPCOR 11-May-26 07:00 17-May-26 17:00 6.42 Days
Continuous
814s T2 (814s Bellamy), BR722 (Rossdale), 814s B2402 (814s Bellamy), 814s B2406 (814s Bellamy) Bellamy: TX2 Zone Doble and BR722 Breaker Maintenance/Doble, and BDS17 Disconnect Maintenance  
EPCOR 11-May-26 07:00 22-May-26 17:00 11.42 Days
Continuous
52s T1 (52s East Industrial) East Industrial: TX1 DGA Monitor Replacement  
EPCOR 18-May-26 07:00 29-May-26 17:00 11.42 Days
Continuous
CV5 (EP 511s Victoria - 557s Castle Downs) CV5: Manhole Inspections and Maintenance  
SUNCOR 18-May-26 08:00 24-May-26 20:00 6.5 Days
Continuous
29PL9-12 (29EDD-34 - 29EDD-65) 29EDD34;29PL9-12 SYSTEM;PM 5y,10y
 
ALTALINK, EPCOR 19-May-26 07:00 22-May-26 17:00 3.42 Days
Continuous
1055L (629s Argyll Transfer Station - 816s Petrolia), 816s P2402 (816s Petrolia), 816s P2403 (816s Petrolia) 1055L/Petrolia: SA/CT/CVT Doble and PDS4/PDS5 Disconnect Maintenance and Aerial Washing Program  
EPCOR 19-May-26 07:00 24-Jul-26 17:00 66.42 Days
Continuous
805s T3 (805s Jasper), EP 805s J2404 (EP 805s Jasper), EP 805s J2405 (EP 805s Jasper) Jasper: J2402/JAB3/JDS9 Replacement LCR  
ATCO 19-May-26 09:00 19-May-26 17:00 8 Hours
Continuous
9L16 (755s Cordel - 972s Tinchebray), 755s 904 (755s Cordel), 755s 905 (755s Cordel), 972s 903 (972s Tinchebray) Disconnect 9L16 from existing A-frame deadend and 9L16D2 (to be renamed 9L86D1)
Restore bus leave renamed 9L86D1 open for future line connection.
 
ATCO 19-May-26 09:00 29-May-26 17:00 10.33 Days
Continuous
9L16 (755s Cordel - 972s Tinchebray) Disconnect 9L16 from existing A-frame deadend and 9L16D2 (to be renamed 9L86D1)
Restore bus leave renamed 9L86D1 open for future line connection.
 
ALTALINK 20-May-26 08:00 28-May-26 16:00 8.33 Days
Continuous
275s T1 (275s Jenner) 275sT1 Oil Reclaim  
ALTALINK, EPCOR 23-May-26 07:00 25-May-26 17:00 2.42 Days
Continuous
1056L (89s Ellerslie - 629s Argyll Transfer Station) 1056L: Structure Refurbishment  
EPCOR 25-May-26 07:00 27-May-26 17:00 2.42 Days
Continuous
816s P2401 (816s Petrolia) Petrolia: P2401 CT Doble  
EPCOR 25-May-26 07:00 05-Jun-26 17:00 11.42 Days
Continuous
987s T4 (987s Clover Bar), 987s C2408 (987s Clover Bar) Cloverbar: TX4 DGA Monitor Replacement and Relay Maintenance  
EPCOR 28-May-26 07:00 30-May-26 17:00 2.42 Days
Continuous
816s P2405 (816s Petrolia) Petrolia: P2405 CT Doble  
EPCOR 01-Jun-26 07:00 03-Jun-26 17:00 2.42 Days
Continuous
816s P2406 (816s Petrolia) Petrolia: P2406 CT Doble  
EPCOR 01-Jun-26 07:00 07-Jun-26 17:00 6.42 Days
Continuous
T4 (Poundmaker), PM721 (Poundmaker), PM2402 (Poundmaker), PM2403 (Poundmaker) Poundmaker: TX4 Doble and PMAB4/PMDS4/PMDS5 Disconnect Maintenance  
ATCO 02-Jun-26 09:00 13-Jun-26 17:00 11.33 Days
Continuous
972s 905B (972s Tinchebray), 972s 906A (972s Tinchebray) Connect new 9L62 to 972S and prepare to energize.
String Conductors/OPGW 9L62 from Str #3 to substation A-frame deadends and connect to 9L62D1, coordinate with AML conductor jumpers and OPGW termination at the TFO boundary 9L86 Str 409
 
EPCOR, ALTALINK 08-Jun-26 07:00 14-Jun-26 17:00 6.42 Days
Continuous
657s T3 (657s Summerside), 657s SU2405 (657s Summerside), 657s SU2401 (657s Summerside) Summerside: TX3 Doble and SUAB3/SUDS2/SUDS12 Disconnect Maintenance  
EPCOR 08-Jun-26 07:00 19-Jun-26 17:00 11.42 Days
Continuous
T1 (Rossdale), R721 (Rossdale), RR723 (Rossdale), BR722 (Rossdale), 814s T2 (814s Bellamy) Rossdale: TX1 LCR Demo  
ALTALINK 10-Jun-26 23:00 11-Jun-26 03:00 4 Hours
Continuous
62s T1 (62s Brazeau Plant) maintenance  
ALTALINK 11-Jun-26 03:00 11-Jun-26 07:00 4 Hours
Daily
62s T2 (62s Brazeau Plant) maintenance  
ATCO 14-Jun-26 09:00 25-Jun-26 17:00 11.33 Days
Continuous
9L62 (972s Tinchebray - 87s Gaetz) Work on parallel line 9L86  
ATCO, CNRL 15-Jun-26 05:00 29-Jun-26 10:00 14.21 Days
Continuous
859s 701TD (859s Primrose), 859s 701 (859s Primrose), 859s 704 (859s Primrose), 859s Protection & Control (859s Primrose), 859s RTU/SCADA (859s Primrose), 859s 52G (859s Primrose), 859s 701T (859s Primrose) maintenance  
ALTALINK, EPCOR 15-Jun-26 09:30 15-Jun-26 17:00 7.5 Hours
Continuous
915L (38s East Edmonton - 987s Clover Bar), 987s C2403 (987s Clover Bar), 987s C2405 (987s Clover Bar) 915L/Cloverbar: CT/CVT/SA Doble and CDS35/CDS36/CDS7 Disconnect Maintenance and Relay Maintenance  
ALTALINK, EPCOR 15-Jun-26 09:30 15-Jun-26 17:00 7.5 Hours
Continuous
1139L (367s Harry Smith - EP Riverview), RW2405 (EP Riverview), RW2403 (EP Riverview) Riverview: 1139L Zone Doble and RWDS6/RWDS9/RWSA12 Disconnect Maintenance and RW2403/RW2405 (SF6) Breaker Maintenance  
ATCO 16-Jun-26 09:00 25-Jun-26 17:00 9.33 Days
Continuous
972s 240kV Bus 900BS2 (972s Tinchebray) Connect new 9L86 to 972S and prepare to energize.
String Conductors/OPGW 9L86 from Str #3 to substation A-frame deadends and connect to 9L86D1, coordinate with AML conductor jumpers and OPGW termination at the TFO boundary 9L86 Str 409
Complete protection commissioning
 
EPCOR 22-Jun-26 07:00 28-Jun-26 17:00 6.42 Days
Continuous
52s T1 (52s East Industrial) East Industrial: TX1 Doble  
ALTALINK, EPCOR 22-Jun-26 09:30 22-Jun-26 17:00 7.5 Hours
Continuous
921L (71s Lamoureux - 987s Clover Bar), 987s C2404 (987s Clover Bar), 987s C2406 (987s Clover Bar) 921L/Cloverbar: CT/CVT/SA Doble and CDS9/CDS14/CDS17 Disconnect Maintenance and C2404 (Min Oil) Breaker Maintenance and C2401 Relay Maintenance  
ATCO 29-Jun-26 13:00 30-Jun-26 17:00 28 Hours
Continuous
9LA93 (973s Lanes Lake - 9L93 tap) Line to Ground Clearance Mitigation, Span 50-51. Repair deficiency on structure 57  
EPCOR 02-Jul-26 07:00 18-Sep-26 17:00 78.42 Days
Continuous
805s T4 (805s Jasper), EP 805s J2405 (EP 805s Jasper), EP 805s J2406 (EP 805s Jasper) Jasper: J2406/JDS10 Replacement LCR  
EPCOR 06-Jul-26 07:00 12-Jul-26 17:00 6.42 Days
Continuous
987s T2 (987s Clover Bar), 987s CC721 (987s Clover Bar), 987s C2406 (987s Clover Bar), 987s C2410 (987s Clover Bar) Cloverbar: TX2 Doble and CDS1/CDS31/CDS33/CDS43 Disconnect Maintenance and Measurements w/Engineering  
EPCOR 13-Jul-26 07:00 19-Jul-26 17:00 6.42 Days
Continuous
EP 803s L2401 (EP 803s Lambton) Lambton: L2401 (Min Oil) Breaker Maintenance and CT Doble  
SUNCOR 15-Jul-26 08:00 25-Jul-26 20:00 10.5 Days
Continuous
29EDD-2 29PT-3 (29EDD-2 Tar Island), 29PL6-22 (29EDD-1 Millennium - 29EDD-2 Tar Island) 29EDD2;29PT-3, 29PL6-22 SYSTEM;PM 5y,10y
 
EPCOR 20-Jul-26 07:00 26-Jul-26 17:00 6.42 Days
Continuous
EP 803s L2402 (EP 803s Lambton) Lambton: L2402 (Min Oil) Breaker Maintenance and CT Doble  
ALTALINK 20-Jul-26 09:00 20-Jul-26 15:00 6 Hours
Daily
603L (138s Windy Flats - 243s Soderglen) maintenance  
ALTALINK 20-Jul-26 13:30 23-Jul-26 17:30 3.17 Days
Continuous
777L (48s Pocaterra - 245s Seebe), 245s 777X (245s Seebe) 245s777X Koncar CT replacement  
ATCO 21-Jul-26 08:00 22-Jul-26 17:00 1.38 Days
Continuous
7L65 (709s Vegreville - 7LA65 tap), 7L65 (710s Vermilion - 7LA65 tap), 7LA65 (708s Grizzly Bear - 7L65 tap) Switch Repairs, 7LA65D1  
ALTALINK, EPCOR 27-Jul-26 09:30 27-Jul-26 17:00 7.5 Hours
Continuous
909L (310p Sundance - 665s Dome), 665s D2403 (665s Dome) 909LW/Dome: CVT/SA Doble and DDS6/DDS7/DDS14 Disconnect Maintenance and 909LW Relay Maintenance  
ALTALINK 29-Jul-26 23:00 30-Jul-26 03:00 4 Hours
Continuous
62s T1 (62s Brazeau Plant) maintenance  
ALTALINK 30-Jul-26 03:00 30-Jul-26 07:00 4 Hours
Daily
62s T2 (62s Brazeau Plant) maintenance  
EPCOR 10-Aug-26 07:00 16-Aug-26 17:00 6.42 Days
Continuous
665s T3 (665s Dome), 665s D721 (665s Dome), 665s D2404 (665s Dome), S721 (Strathcona) DS26/Dome/Strathcona: Dome TX3 Doble and DAB3/DDS15/DDS16 Disconnect Maintenance and Strathcona DS26/CVT Doble and SDS3 Disconnect Maintenance  
ALTALINK 10-Aug-26 09:30 13-Aug-26 17:00 3.31 Days
Continuous
702L (137s Sedgewick - 757s Battle River) Interphase spacers and pole replacements  
ATCO 10-Aug-26 10:00 13-Aug-26 16:30 3.27 Days
Continuous
7L702 (137s Sedgewick - 757s Battle River) Interphase spacers and pole replacements  
ALTALINK, EPCOR 17-Aug-26 09:30 22-Aug-26 17:00 5.31 Days
Continuous
920L (71s Lamoureux - 557s Castle Downs), 557s CD2405 (557s Castle Downs), 557s CD2404 (557s Castle Downs) 920LE/Castledowns: CT/CVT Doble and Surge Arrestor LCR  
ATCO 17-Aug-26 10:00 20-Aug-26 16:30 3.27 Days
Continuous
7L702 (137s Sedgewick - 757s Battle River) Interphase spacers and pole replacements  
ALTALINK 17-Aug-26 10:00 20-Aug-26 16:30 3.27 Days
Continuous
702L (137s Sedgewick - 757s Battle River) Interphase spacers and pole replacements  
ALTALINK, ATCO, FMGW 18-Aug-26 08:00 19-Aug-26 17:00 1.38 Days
Continuous
964AL (1024s Granlea - 964L tap), 1024s PT-6001 (1024s Granlea), 1024s PT-6002 (1024s Granlea), 1024s 952-600001 (1024s Granlea), 1024s PS-6005 (1024s Granlea), 1024s PS-6006 (1024s Granlea), 1024s PS-6007 (1024s Granlea), 1024s PS-6008 (1024s Granlea), 1024s 489-600201 (1024s Granlea) maintenance activities (testing and inspection) of electrical equipment  
EPCOR, ALTALINK 31-Aug-26 07:00 13-Sep-26 17:00 13.42 Days
Continuous
EP 803s T3 (EP 803s Lambton), EP 803s L2403 (EP 803s Lambton), EP 803s L2405 (EP 803s Lambton), EP 803s L721 (EP 803s Lambton), 72LS24 (EP 803s Lambton - Strathcona), 72LH8 (EP 803s Lambton - EP Hardisty), H726 (EP Hardisty), S724 (Strathcona) Lambton: LDS14 LCR and L721 Breaker Maintenance (Min Oil) and TX3 Zone Doble and L2405 Breaker Maintenance (SF6) and LDS12 Drive Pipe Repair and TX3 Relay Maintenance  
ALTALINK 07-Sep-26 07:00 08-Sep-26 18:00 1.46 Days
Continuous
237s T2 (237s Foothills), 237s 240kV Bus 2 (237s Foothills) Closing Open Point 'C'  
ATCO 08-Sep-26 10:00 10-Dec-26 16:00 93.29 Days
Continuous
2015s 902 (2015s Yeo) Remove circuit breaker for use at 2102S Armistead. New breaker to be installed at 2015S Yeo substation once received from manufacturer.  
ALTALINK 09-Sep-26 07:00 10-Sep-26 18:00 1.46 Days
Continuous
237s T1 (237s Foothills), 237s 240kV Bus 1 (237s Foothills) Closing Open Points 'A' & 'B'  
ALTALINK 10-Sep-26 18:00 15-Sep-26 13:00 4.79 Days
Continuous
1141L (1172s Laramide - 237s Foothills) End to end testing with Laramide 1172s  
ALTALINK, EPCOR 14-Sep-26 09:30 17-Sep-26 17:00 3.31 Days
Continuous
920L (37s North Calder - 557s Castle Downs), 557s CD2401 (557s Castle Downs), 557s CD2403 (557s Castle Downs) 920LW/Castledowns: Surge Arrestor LCR  
ALTALINK 16-Sep-26 23:00 17-Sep-26 03:00 4 Hours
Continuous
62s T1 (62s Brazeau Plant) maintenance  
ALTALINK 17-Sep-26 03:00 17-Sep-26 07:00 4 Hours
Daily
62s T2 (62s Brazeau Plant) maintenance  
EPCOR 21-Sep-26 07:00 03-Oct-26 17:00 12.42 Days
Continuous
987s CCP7213 (987s Clover Bar), 987s CCP7214 (987s Clover Bar), 987s C2401 (987s Clover Bar), 987s C2403 (987s Clover Bar), 987s T1 (987s Clover Bar) Cloverbar: C2401/C2403 Breaker Maintenance and CT Doble and CDS19 LCR and C2401 Relay Maintenance  
EPCOR 21-Sep-26 07:00 30-Oct-26 17:00 39.42 Days
Continuous
EP 805s J2405 (EP 805s Jasper) Jasper: J2405 Replacement LCR  
ATCO 21-Sep-26 10:00 24-Sep-26 16:00 3.25 Days
Continuous
888s 906 (888s Dover) 21B/9L74 relay replacement. Cutover breaker and CT to new protection  
ALTALINK 22-Sep-26 07:00 22-Sep-26 19:00 12 Hours
Daily
608AL (528s Blue Trail Wind Farm - 608L tap) Removing D608BL conductors from existing str 608AL32 for salvage. Adding new 608AL32A.  
ALTALINK 24-Sep-26 07:00 24-Sep-26 19:00 12 Hours
Daily
603L (138s Windy Flats - 243s Soderglen) Removing D603AL conductors from existing str 603L97 for salvage. Replacing 603L98.  
ATCO 25-Sep-26 10:00 28-Sep-26 16:00 3.25 Days
Continuous
888s 905 (888s Dover) 21B/9L74 relay replacement. Cutover breaker and CT to new protection  
EPCOR 05-Oct-26 07:00 20-Nov-26 17:00 46.46 Days
Continuous
814s T1 (814s Bellamy), BR721 (Rossdale), 814s B2401 (814s Bellamy), 814s B2407 (814s Bellamy) Bellamy: TX1 Oil Reclamation and LTC Monitor Install  
ALTALINK 05-Oct-26 08:00 28-Nov-26 19:00 54.5 Days
Continuous
62s T2 (62s Brazeau Plant) maintenance  
ATCO 05-Oct-26 10:00 08-Oct-26 16:00 3.25 Days
Continuous
9L74 (888s Dover - 960s Birchwood Creek) 21B/9L74 relay three terminal line testing  
ATCO 12-Oct-26 10:00 15-Oct-26 16:00 3.25 Days
Continuous
888s 906 (888s Dover) 21A/9L74 relay replacement. Cutover breaker and CT to new protection  
ATCO 16-Oct-26 10:00 19-Oct-26 16:00 3.25 Days
Continuous
888s 905 (888s Dover) 21B/9L74 relay replacement. Cutover breaker and CT to new protection  
ALTALINK, EPCOR 19-Oct-26 09:30 19-Oct-26 17:00 7.5 Hours
Continuous
908L (89s Ellerslie - 816s Petrolia), 816s P2401 (816s Petrolia), 816s P2406 (816s Petrolia) Petrolia: 908LE Surge Arrestor and CVT LCR  
ATCO 26-Oct-26 10:00 29-Oct-26 16:00 3.25 Days
Continuous
9L74 (888s Dover - 960s Birchwood Creek) 21B/9L74 relay three terminal line testing  
EPCOR 02-Nov-26 07:00 06-Nov-26 17:00 4.42 Days
Continuous
EP 805s J2407 (EP 805s Jasper) Jasper: J2407 Replacement LCR  
Syncrude 03-Nov-26 08:00 18-Nov-26 16:00 15.33 Days
Continuous
UE-1 (D05 - UE-1 Syncrude Plant 30-2), T1 (D05 Syncrude), D05 511 (D05), D05 519 (D05), D05 71 (D05), D05 71A (D05), D05 71B (D05), D05 80 (D05), D05 80B (D05), D05 79 (D05), D05 79B (D05), D05 73 (D05), D05 73A (D05), D05 73B (D05), D05 75 (D05), D05 75A (D05), LCF (D05), ML-4 (D05), UE-1 7206 (UE-1 Syncrude Plant 30-2), UE-1 72-16 (UE-1 Syncrude Plant 30-2), D05 511A (D05), D05 519A (D05), D05 519B (D05), D05 80A (D05), D05 79A (D05), D05 75B (D05) complete 6-Year 72 kV A bus preventive maintenance in D05 substation  
ALTALINK 05-Nov-26 03:00 05-Nov-26 07:00 4 Hours
Daily
62s T1 (62s Brazeau Plant) maintenance  
ALTALINK, EPCOR 06-Nov-26 07:00 27-Nov-26 17:00 21.42 Days
Continuous
1045L (EP 805s Jasper - 1045AL tap), EP 805s J2407 (EP 805s Jasper), EP 805s J2406 (EP 805s Jasper), EP 805s J2401 (EP 805s Jasper), 1098L (EP 805s Jasper - Poundmaker) 1045L/1098L/Jasper: J2407 Replacement LCR  
EPCOR 09-Nov-26 07:00 11-Dec-26 17:00 32.42 Days
Continuous
52s T2 (52s East Industrial), 52s E2402 (52s East Industrial) East Industrial: TX2 Bushing Replacement  
EPCOR 09-Nov-26 07:00 11-Dec-26 17:00 32.42 Days
Continuous
PM2405 (Poundmaker) Poundmaker: P2405 Breaker Replacement  
EPCOR 23-Nov-26 07:00 04-Dec-26 17:00 11.42 Days
Continuous
814s T2 (814s Bellamy), BR722 (Rossdale), 814s B2402 (814s Bellamy), 814s B2406 (814s Bellamy) Bellamy: TX2 LTC Monitor Install  
EPCOR 27-Nov-26 07:00 18-Dec-26 17:00 21.42 Days
Continuous
EP 805s J2407 (EP 805s Jasper) Jasper: J2407 Replacement LCR  
ALTALINK 23-Dec-26 23:00 24-Dec-26 03:00 4 Hours
Continuous
62s T1 (62s Brazeau Plant) maintenance  
ALTALINK 24-Dec-26 03:00 24-Dec-26 07:00 4 Hours
Daily
62s T2 (62s Brazeau Plant) maintenance  
EPCOR 04-Jan-27 07:00 12-Mar-27 17:00 67.42 Days
Continuous
EP 805s J2401 (EP 805s Jasper) Jasper: J2401 Replacement LCR  
ATCO 09-Feb-27 09:00 11-Feb-27 17:00 2.33 Days
Continuous
7L228 (845s Big Mountain - 7L20 tap) AESO project P2716 - Install 7L228 bypass to facilitate the installation of new line switches for the new 7LA228 T-tap line connection to the new 2103S Pakenham substation
Open 7L228, replace structures 551 and 551A, connect bypass.
 
EPCOR 15-Feb-27 07:00 19-Feb-27 17:00 4.42 Days
Continuous
EP 805s J2403 (EP 805s Jasper) Jasper: J2403 Replacement LCR  
EPCOR, ALTALINK 19-Feb-27 07:00 05-Mar-27 17:00 14.42 Days
Continuous
EP 805s J2404 (EP 805s Jasper), EP 805s J2403 (EP 805s Jasper), EP 805s J2408 (EP 805s Jasper), 805s C1 (805s Jasper), 1044L (EP 805s Jasper - 816s Petrolia) 1044L/Jasper: J2403 Replacement LCR  
EPCOR 05-Mar-27 07:00 26-Mar-27 17:00 21.38 Days
Continuous
EP 805s J2403 (EP 805s Jasper) Jasper: J2403 Replacement LCR  
ATCO 08-Mar-27 10:00 17-Mar-27 17:00 9.25 Days
Continuous
9L24 (946s Oakland - 959s Lanfine), 959s 906 (959s Lanfine), 959s 905 (959s Lanfine), 946s 902 (946s Oakland), 946s 903 (946s Oakland) Replace A/B protection relays at 959S Lanfine and 946S Oakland
Cut in and reroute 9L24
Connect new 9LA24 T-tap
Commission Telecom and Protection to new 1072S Rose Lynn substation
 
ATCO 16-Mar-27 09:00 18-Mar-27 17:00 2.33 Days
Continuous
7L228 (845s Big Mountain - 7L20 tap) AESO project P2716 - Disconnect bypass, connect new 7LA228D1 to 7LA228 Str #2, connect 7L228 to 7L228D2, connect 7L228 to 7L228D3. Renumber existing line switches 7L228D2 - D4, 7L228D3 - D5, 7L228D4 - D6
Commission DTT from Pakenham to Big Mountain
 
ATCO 22-Mar-27 09:00 25-Mar-27 17:00 3.33 Days
Continuous
2091s 704 (2091s Thornton) AESO project P2716 - cut over new SEL 2440 wiring at 2091S, relay programming, commission DTT and LTO from 2103S Pakenham  
ATCO 26-Mar-27 09:00 29-Mar-27 17:00 3.33 Days
Continuous
740s 704 (740s H.R. Milner), 7L20 (740s H.R. Milner - 810s Dome Cutbank) AESO project P2716 - cut over RAS #171 wiring at 740S, relay programming, commission LTO 7L20/7L228  
SUNCOR 06-Apr-27 09:00 16-Apr-27 20:00 10.46 Days
Continuous
29EDD-34 29PT-112 (29EDD-34), 29EDD-34 29-752-121 (29EDD-34), 29EDD-34 29PS-68 (29EDD-34), 29EDD-34 29PS-67 (29EDD-34), 29EDD-34 29PS-66 (29EDD-34), 29EDD-34 29PS-65 (29EDD-34), 29EDD-34 29PS-225 (29EDD-34), 29EDD-34 29PS-230 (29EDD-34), 29EDD-34 29-952-141 (29EDD-34), 29EDD-34 29-952-131 (29EDD-34), 29EDD-34 29-952-111 (29EDD-34) 29EDD34;29PT-112 & 29PP-24 SYSTEM;PM
This will Place 29EDD-34 on one 260 kV bus and drop 29PL7-1
 
ATCO 12-Apr-27 10:00 19-Apr-27 17:00 7.29 Days
Continuous
7L22 (790s Poplar Hill - 7L88 tap) Cut open 7L22, connect new line section to new 2061S Dobbs
7L22/21B relay upgrades at 790S Poplar Hill and 811S Clairmont Lake
On completion energize new 2061S Dobbs substation
 
SUNCOR 14-Apr-27 14:00 23-Apr-27 18:00 9.17 Days
Continuous
29EDD-65 29PT-0257 (29EDD-65), 29EDD-65 29-952-4812 (29EDD-65), 29EDD-65 29-952-4813 (29EDD-65), 29EDD-71 752-4624 (29EDD-71), 29EDD-71 752-4623 (29EDD-71), 29PL7-4 (29EDD-65 - 29EDD-71) Firebag: 29EDD65;29PT-257 & 29PL7-4 SYSTEM, 29EDD65 ;29PT-260 & 29PL7-4 SYSTEM, 29EDD71 29PT-241 & 29PL7-4  
ATCO 03-May-27 09:00 17-May-27 17:30 14.35 Days
Continuous
2075s T11 (2075s Newell) Annual EATL outage at 2075s & 2029s.  
ATCO 03-May-27 09:00 17-May-27 17:30 14.35 Days
Continuous
2029s T11 (2029s Heathfield) Annual EATL outage at 2075s & 2029s.  
ATCO 03-May-27 09:00 17-May-27 17:30 14.35 Days
Continuous
13L50 (2029s Heathfield - 2075s Newell) Annual EATL outage at 2075s & 2029s.
**1218 IS NOT THE ISOALTION. ATCO SENT AESO OF REQUIRED ISOLATIONS BACK IN MAY 2024 TO UPDATE 2029S AND 2075S ISOLATIONS FOR 13L50 OUTAGES**
 
ATCO 03-May-27 10:00 06-May-27 17:00 3.29 Days
Continuous
7L22 (811s Clairmont Lake - 7L88 tap) 7L22/21B relay upgrade at 811S Clairmont Lake
Upon completion new 2061S Dobbs substation ready to energize
 
SUNCOR 04-May-27 09:00 14-May-27 20:00 10.46 Days
Continuous
29EDD-34 29PS-214 (29EDD-34), 29EDD-34 29-952-113 (29EDD-34), 29EDD-34 29PS-215 (29EDD-34), 29EDD-34 29PS-213 (29EDD-34) 29EDD34;29PL9-13 SYSTEM;PM 5y,10y  
SUNCOR 05-May-27 14:00 14-May-27 18:00 9.17 Days
Continuous
29EDD-65 29PT-0236 (29EDD-65), 29EDD-65 29-952-4823 (29EDD-65), 29EDD-65 29-952-4822 (29EDD-65), 29EDD-71 752-4634 (29EDD-71), 29EDD-71 752-4633 (29EDD-71), 29PL7-3 (29EDD-65 - 29EDD-71) Firebag: 29EDD65;29PT-236 & 29PL7-3 SYSTEM, 29EDD65;29PT-250&29PL7-3 SYSTEM, 29PT-246 SYSTEM;29EDD71  
ATCO 10-May-27 10:00 11-May-27 17:00 31 Hours
Continuous
7L03 (749s Flyingshot Lake - 7L09 tap) Cutover and commission RAS analogs and LTO to 790S Poplar Hill RAS Hub  
ATCO 12-May-27 10:00 13-May-27 17:00 31 Hours
Continuous
7L03 (731s Elmworth - 7L09 tap) Cutover and commission LTO to 790S Poplar Hill RAS Hub  
ATCO 14-May-27 10:00 15-May-27 17:00 31 Hours
Continuous
7L69 (731s Elmworth - 815s Goodfare) Cutover and commission LTO to 790S Poplar Hill RAS Hub  
ATCO 16-May-27 10:00 17-May-27 17:00 31 Hours
Continuous
7L07 (790s Poplar Hill - 815s Goodfare) Cutover and commission LTO to 790S Poplar Hill RAS Hub  
SUNCOR 01-Jun-27 08:00 10-Jun-27 17:00 9.38 Days
Continuous
635EDD-1000 635-752-635PT-1000 (635EDD-1000), 635EDD-1000 635PT-1000 (635EDD-1000) FH - Maintenance on Transformer, associated breakers, other equipment in isolation boundary and protection system testing.  
SUNCOR 01-Jun-27 09:00 11-Jun-27 20:00 10.46 Days
Continuous
29EDD-94 407T (29EDD-94 Voyageur), 29EDD-94 29-952-9705 (29EDD-94 Voyageur), 29EDD-94 29PS-393 (29EDD-94 Voyageur), 29EDD-94 29PS-392 (29EDD-94 Voyageur), 29EDD-94 29-952-9704 (29EDD-94 Voyageur), 29EDD-94 29PS-400 (29EDD-94 Voyageur) 29EDD94;29PT-407 SYSTEM;PM 5y,10y  
SUNCOR 11-Jun-27 08:00 20-Jun-27 17:00 9.38 Days
Continuous
635EDD-1000 635-752-635PT-1001 (635EDD-1000), 635EDD-1000 635PT-1001 (635EDD-1000) FH - Maintenance on Transformer, associated breakers, other equipment in isolation boundary and protection system testing.  
SUNCOR 15-Jun-27 09:00 25-Jun-27 20:00 10.46 Days
Continuous
29EDD-94 406T (29EDD-94 Voyageur), 29EDD-94 29-952-9702 (29EDD-94 Voyageur), 29EDD-94 29PS-388 (29EDD-94 Voyageur), 29EDD-94 29PS-389 (29EDD-94 Voyageur), 29EDD-94 29PS-399 (29EDD-94 Voyageur) 29EDD94;29PT-406 SYSTEM;PM 5y,10y  
ATCO 20-Jul-27 08:00 21-Jul-27 17:00 1.38 Days
Continuous
7L53 (706s Irish Creek - 7LA53 tap), 7LA53 (969s Lindbergh - 7L53 tap), 7L53 (700s Bonnyville - 7LA53 tap) Cold Lake Area Project to connect 1064s  
ATCO 22-Jul-27 08:00 25-Jul-27 17:00 3.38 Days
Continuous
7L91 (715s Leming Lake - 826s Marguerite Lake) Cold Lake Area Energy Centre Project
 
ALTALINK, ATCO, FMGW 17-Aug-27 08:00 18-Aug-27 17:00 1.38 Days
Continuous
964AL (1024s Granlea - 964L tap), 1024s PT-6001 (1024s Granlea), 1024s PT-6002 (1024s Granlea), 1024s 952-600001 (1024s Granlea), 1024s PS-6005 (1024s Granlea), 1024s PS-6006 (1024s Granlea), 1024s PS-6007 (1024s Granlea), 1024s PS-6008 (1024s Granlea), 1024s 489-600201 (1024s Granlea) maintenance activities (testing and inspection) of electrical equipment  
ALTALINK 08-Nov-27 08:30 11-Nov-27 17:30 3.38 Days
Continuous
409s 110 (409s Shell Scotford) Install new Deadend corner structure on ALC02L  
ALTALINK 08-Nov-27 08:30 11-Nov-27 17:30 3.38 Days
Continuous
409s 107 (409s Shell Scotford) Install new Deadend corner structure on ALC02L.  
ATCO 08-Nov-27 09:00 11-Nov-27 17:00 3.33 Days
Continuous
ALC02L (409s Shell Scotford - 879s Upgrader) Install new Deadend corner structure on ALC02L  
ATCO 08-Nov-27 09:00 11-Nov-27 17:00 3.33 Days
Continuous
ALC01L (408s Air Liquide Scotford - 409s Shell Scotford) Install new Deadend corner structure on ALC02L.  
ATCO 06-Mar-28 10:00 22-Mar-28 16:00 16.21 Days
Continuous
826s 903 (826s Marguerite Lake), 826s 907 (826s Marguerite Lake), 826s 901T (826s Marguerite Lake) Expand 240kV ring bus for new 9L42 line  
ALTALINK 13-Mar-28 09:30 16-Mar-28 17:30 3.33 Days
Continuous
939L (77s Sagitawah - 809s Louise Creek) Cut over 9L939 to temp bypass structures to allow for installation of new deadend corner towers. These are required to make the final connections to the new 2105S Jackson substation.  
ATCO 13-Mar-28 10:00 16-Mar-28 17:00 3.29 Days
Continuous
9L939 (77s Sagitawah - 809s Louise Creek) Cut over 9L939 to temp bypass structures to allow for installation of new deadend corner towers. These are required to make the final connections to the new 2105S Jackson substation  
ALTALINK 17-Mar-28 09:30 17-Apr-28 17:30 31.33 Days
Continuous
939L (77s Sagitawah - 809s Louise Creek) Install foundations (TBD assume concrete), assemble and erect new Q-towers 9L938/9L939-155A and 9L938/9L939-156A in existing ROW centreline. Daily outage until such a time as the new towers begin to encroach on 9L938.  
ATCO 17-Mar-28 10:00 17-Apr-28 17:00 31.29 Days
Continuous
9L938 (77s Sagitawah - 809s Louise Creek) Install foundations (TBD assume concrete), assemble and erect new Q-towers 9L938/9L939-155A and 9L938/9L939-156A in existing ROW centreline. Daily outage until such a time as the new towers begin to encroach on 9L938.  
ALTALINK 18-Apr-28 09:30 25-Apr-28 17:30 7.33 Days
Continuous
938L (77s Sagitawah - 809s Louise Creek) Open 9L938 conductors, complete assembly and connect to the new Q-Towers 9L938/9L939-155A and 9L938/9L939-156A, string to 2105S Jackson deadend and terminate. Re-label 9L938 segment from 809S Louise Creek to 2105S Jackson to 9L140.  
ATCO 18-Apr-28 10:00 25-Apr-28 17:00 7.29 Days
Continuous
9L938 (77s Sagitawah - 809s Louise Creek) Open 9L938 conductors, complete assembly and connect to the new Q-Towers 9L938/9L939-155A and 9L938/9L939-156A, string to 2105S Jackson deadend and terminate.
Relabel 9L938 segment from 809S Louise Creek to 2105S Jackson to 9L140.
 
ALTALINK 01-May-28 09:30 04-May-28 17:30 3.33 Days
Continuous
939L (77s Sagitawah - 809s Louise Creek) Disconnect 9L939 conductors from temp structure  
ATCO 01-May-28 10:00 04-May-28 17:00 3.29 Days
Continuous
9L939 (77s Sagitawah - 809s Louise Creek) Disconnect 9L939 conductors from temp structure 9L939 -155A - 155E reconnect to existing structures 9L938/9L939-156 and 9L938/9L939-155, connect to the new Q-Towers 9L938/9L939-155A and 9L938/9L939-156A, string to 2105S Jackson deadend and terminate.
Relabel 9L939 segment from 809S Louise Creek to 2
 
ATCO 08-May-28 09:00 10-Jul-28 17:00 63.33 Days
Continuous
959s 240kV Bus 900BS2 (959s Lanfine) GOI on 9L141 until line terminated into 1162S Fair Acres and ready to energize  
ATCO 08-May-28 09:00 10-Jul-28 17:00 63.33 Days
Continuous
959s 240kV Bus 900BS2 (959s Lanfine) GOI on 902/903 until line terminated and 1162S Fair Acres ready to energize  
ATCO 09-May-28 10:00 13-May-28 17:00 4.29 Days
Continuous
9L02 (809s Louise Creek - 813s Little Smoky) Install concrete foundations for new structures 9L02/320A, 320H in preparation to cut into 9L02 and convert to a t-tap.  
ATCO 15-May-28 09:00 17-May-28 17:00 2.33 Days
Continuous
959s 240kV Bus 900BS1 (959s Lanfine) Connect new bus from new 902B to existing switch 901A to add new line 9L141,
Cutover and commission 900PT1 ccts to new 9L141 relays
 
ATCO 18-May-28 09:00 20-May-28 17:00 2.33 Days
Continuous
959s 240kV Bus 900BS2 (959s Lanfine) Connect new bus from new Bkr 903 to existing switch 903B to add new line 9L141,
Cutover and commission 900PT2 ccts to new 9L141 relays
 
ATCO 29-May-28 09:00 08-Jun-28 17:00 10.33 Days
Continuous
9L24 (946s Oakland - 959s Lanfine) Cutover and commission 905/906 CT's, 9L24PT ccts to new RAS 241 SEL 451A/B relays @ 959S Lanfine and update relay settings for RAS 241 and SCADA inputs @946S Oakland.  
ATCO 19-Jun-28 10:00 30-Jun-28 16:00 11.25 Days
Continuous
9L20 (755s Cordel - 766s Nevis) Red Willow Solar
Install concrete foundations at 9L20 Structure 69 for new T-Tap connection
 
ATCO 26-Jun-28 10:00 10-Jul-28 17:00 14.29 Days
Continuous
9L02 (809s Louise Creek - 813s Little Smoky) Cut into 9L02 and connect new t-tap structures for 9LA02.
9L02-21A and 21B relay upgrades at 809S Louise Creek and 813S Little Smoky. Implement RAS
Energize new line 9LA02 and 884S Magpie substation (UK Solar LS1)
 

AB-BC, AB-SK & AB-MATL: refer to AESO web posting: http://itc.aeso.ca/itc/public/atc
Also,
AB-BC, AB-SK & AB-MATL: refer to ISO Rule 203.6: http://www.aeso.ca/rulesprocedures/18592.html

Prepared On: 2026-01-14   15:32:37


This document and the information contained herein are based upon information and data which by their nature contain a degree of uncertainty and are subject to change. In addition, this document may contain information and data from public sources and/or third parties, which have been assumed to be accurate and complete and have not been verified. Accordingly, the Independent System Operator, operating as the Alberta Electric System Operator (the "AESO") makes no warranty, representation or guarantee, express or implied, with respect to this document or the information contained herein, including, but not limited to, any warranty, representation or guarantee of accuracy, completeness, timeliness, reliability, availability, absence of computer virus, non- infringement, merchantability or suitability for any purpose. Under no circumstances will the AESO, its members, officers, employees, contractors or agents, or any of their respective affiliates, be liable for any errors or omissions in, or any losses, damages or claims whatsoever, whether in contract, tort or otherwise, arising from use of or reliance upon, this document or any information contained herein.

© 2009 Alberta Electric System Operator. All rights reserved