Alberta Electric System Operator | |
Long Range Significant Transmission Outages for the period of 24 months starting 2024-10-12 | |
The table below contains the significant transmission outages submitted as tentative to the AESO. These Outages have not yet necessarily been approved, but are listed for awareness and coordination purposes. An Outage has been considered significant for this table if it meets any one (1) or more of the following criteria: |
|
|
|
Note: Where a transmission outage requires generation curtailments, the adjustments to generation will typically happen in the hours before the scheduled transmission outage and in the hour after the element is returned to service. | |
Previous Version | |
Download CSV | |
Owner | From | To | Duration | Element | Scheduled Activity | Affected Intertie |
---|---|---|---|---|---|---|
ALTALINK | 11-Jul-24 00:00 | 31-Oct-24 17:00 | 112.71 Days
Continuous |
74s C4 (74s Janet) | forced outage | |
ALTALINK | 19-Aug-24 07:00 | 28-Oct-24 08:00 | 70.04 Days
Continuous |
19s 240kV Bus A (19S Wabamun), 19s 240kV Transfer Bus (19S Wabamun) | issue salvage clearance on 19s 240kV ‘A’ & Transfer Busses. | |
EPCOR | 29-Aug-24 11:16 | 31-Oct-24 00:00 | 62.53 Days
Continuous |
EP 805s J2408 (EP 805s Jasper), 805s C1 (805s Jasper) | Forced outage. | |
EPCOR | 16-Sep-24 07:00 | 15-Nov-24 17:00 | 60.46 Days
Continuous |
557s T1 (557s Castle Downs) | S/S Tx1 outage for secondary duct bank modification | |
ATCO | 23-Sep-24 10:00 | 20-Oct-24 17:00 | 27.29 Days
Continuous |
806s 701T (806s Oldman River), 806s 152 (806s Oldman River) | maintenance | |
SUNCOR | 01-Oct-24 00:00 | 31-Oct-24 00:00 | 30 Days
Continuous |
29EDD-71 29PT-336 (29EDD-71), 29EDD-71 752-4652 (29EDD-71), 29EDD-71 752-4651 (29EDD-71), 29EDD-71 29PS-430 (29EDD-71 Edd71Sub) | FB-29PT-336, 30PP-125 6Y, 29PT-517 5Y (450236820, 300184327, 450260042, 450241892) | |
Syncrude | 03-Oct-24 08:00 | 18-Oct-24 16:00 | 15.33 Days
Continuous |
Mildred T1 (Syncrude Mildred Lake), 134 (Syncrude Mildred Lake), 135 (Syncrude Mildred Lake), 1335 (Syncrude Mildred Lake) | PM and maintenance. | |
ALTALINK | 04-Oct-24 14:00 | 18-Oct-24 18:00 | 14.17 Days
Continuous |
523s 138kV Bus 2 (523s Bullshead), 523s T2 (523s Bullshead), 676L (244s Bowmanton - 523s Bullshead), 523s 552 (523s Bullshead), 523s 289 (523s Bullshead) | connecting new 498L and closing Open Points 'A' & 'B'. Fiber splicing on 498L OPGW & end to end testing | |
ALTALINK | 07-Oct-24 07:00 | 16-Oct-24 17:00 | 9.42 Days
Continuous |
1325L (510s Sunnybrook - AML 511s Crossings), AML 511s T11 (AML 511s Crossings), 510s T11 (510s Sunnybrook), AML 511s 4852 (AML 511s Crossings), AML 511s 4952 (AML 511s Crossings), 510s 2652 (510s Sunnybrook), 510s 2752 (510s Sunnybrook), AML 511s 1489 (AML 511s Crossings), AML 511s 74 (AML 511s Crossings), AML 511s 76 (AML 511s Crossings), 510s 41 (510s Sunnybrook), 510s 43 (510s Sunnybrook), 510s 4289 (510s Sunnybrook) | WATL annual outage, DC yard maintenance, valve hall grading electrode inspections, VCS work, ground switch repairs | |
ATCO | 07-Oct-24 09:00 | 16-Oct-24 18:00 | 9.38 Days
Continuous |
7L20 (740s H.R. Milner - 810s Dome Cutbank) | changing structures between 740s and 810s | |
BCH | 07-Oct-24 09:00 | 01-Nov-24 17:00 | 25.33 Days
Continuous |
2L293 (BCH Nelway - BCH Selkirk) | 2L293 replace structure & crossarms BC maintenance does not affect the Alberta ATC | AB-BC |
ATCO | 07-Oct-24 10:00 | 07-Nov-24 17:00 | 31.33 Days
Continuous |
9L100 (801s Anderson - 807s Sheerness), 807s 902 (807s Sheerness), 801s 910 (801s Anderson), 801s 911 (801s Anderson) | replace Breaker 902 at 807s | |
ALTALINK | 07-Oct-24 10:00 | 29-Nov-24 10:00 | 53.04 Days
Continuous |
62s 11 (62s Brazeau Plant) | maintenance | |
BCH | 09-Oct-24 09:00 | 13-Oct-24 16:00 | 4.29 Days
Continuous |
5L51 (BPA Custer - BCH Ingledow) | ING 5CB3 insp, | AB-BC |
SUNCOR | 10-Oct-24 08:00 | 26-Oct-24 16:00 | 16.33 Days
Continuous |
29EDD-1 T1 (29EDD-1 Millennium), 29EDD-1 29EDD1s952 (29EDD-1 Millennium), 29EDD-1 29EDD1s1052 (29EDD-1 Millennium), 29EDD-1 29EDD1s852 (29EDD-1 Millennium), 29EDD-1 29EDD1S23 (29EDD-1 Millennium), 29EDD-1 29EDD1S24 (29EDD-1 Millennium), 29EDD-1 29EDD1S1452 (29EDD-1 Millennium), 29EDD-1 29EDD1s1852 (29EDD-1 Millennium) | T1 Bushings and 72kv arresters replacement | |
ENMAX | 12-Oct-24 07:00 | 15-Oct-24 10:00 | 3.13 Days
Continuous |
2-GSU-XF-0002 (SS-162), 162B240-RB135 (SS-162), 162B240-RB134 (SS-162) | maintenance | |
Lethbridge, ALTALINK | 12-Oct-24 07:30 | 12-Oct-24 17:00 | 9.5 Hours
Continuous |
146s 667 (146s Macdonald), 667L (146s MacDonald - 370s North Lethbridge) | Require open end outage on 667L breaker to replace faulty tank heaters. | |
ENMAX, ALTALINK | 12-Oct-24 08:00 | 12-Oct-24 16:00 | 8 Hours
Continuous |
50L (44s Bearspaw Plant - SS-21), 21.1C (SS-21), 21.2TR (SS-21) | Fall Substation Washing | |
ENMAX, ALTALINK | 12-Oct-24 08:00 | 12-Oct-24 16:00 | 8 Hours
Continuous |
50L (44s Bearspaw Plant - SS-21) | Fall Substation Washing | |
ENMAX, ALTALINK | 12-Oct-24 08:00 | 13-Oct-24 16:00 | 1.33 Days
Continuous |
24.81L (SS-24 - SS-31), 24.83L (74s Janet - SS-24), 24.1TR (SS-24), 24B138-24BT3 (SS-24) | Power Factor Test - 24B138-24.83-CT, 24PT138-Z31. HV Breaker Maintenance - 24B138-24.81. | |
ENMAX, ALTALINK | 14-Oct-24 08:00 | 17-Oct-24 16:00 | 3.33 Days
Continuous |
50L (44s Bearspaw Plant - SS-21) | 21 Substation -Surge Arrester Addition | |
ALTALINK, ATCO | 14-Oct-24 12:00 | 14-Oct-24 17:30 | 5.5 Hours
Daily |
244s 152 (244s Bowmanton), 244s 252 (244s Bowmanton), 1035L (244s Bowmanton - 2075s Newell) | Cut over CTs to new PMU. | |
ENMAX, ALTALINK | 15-Oct-24 06:00 | 15-Oct-24 18:00 | 12 Hours
Continuous |
833L (SS-2 - SS-12) | 12 Sub Building Upgrade | |
ALTALINK | 15-Oct-24 07:00 | 15-Oct-24 12:00 | 5 Hours
Daily |
965L (326s Murray lake - 244s Bowmanton), 244s 252 (244s Bowmanton), 244s 352 (244s Bowmanton) | Cut over CTs to new PMU. | |
EPCOR | 15-Oct-24 07:00 | 16-Oct-24 17:00 | 1.42 Days
Continuous |
EP 805s J2407 (EP 805s Jasper), 1098L (EP 805s Jasper - Poundmaker) | Jasper/1098L: DFR Cutovers and Commissioning | |
ALTALINK | 15-Oct-24 07:00 | 16-Oct-24 18:30 | 1.48 Days
Continuous |
275s 240kV Bus 2 (275s Jenner), 275s T2 (275s Jenner) | Replace 275s22 CVT8, replace JB and wire, like for like replacement | |
ALTALINK | 15-Oct-24 07:15 | 24-Oct-24 16:45 | 9.4 Days
Continuous |
37s 76 (37s North Calder), 37s 82 (37s North Calder), 905L (19s Wabamun - 37s North Calder) | Remove old breaker (37s76) and CTs. New foundation screw piles, install new breaker, wire and install risers, install new string insulators on 905L | |
ATCO | 15-Oct-24 08:30 | 16-Oct-24 16:00 | 31.5 Hours
Continuous |
7L28 (717s Ethel Lake - 846s Grand Centre), 717s 701 (717s Ethel Lake) | breaker maintenance | |
ATCO | 15-Oct-24 10:00 | 18-Oct-24 12:00 | 3.08 Days
Continuous |
735s 601T (735s Swan River) | Transformer maintenance, mobile sub will be installed between 699TD and 599TD | |
ATCO | 15-Oct-24 10:00 | 18-Oct-24 16:00 | 3.25 Days
Continuous |
732s 901T (732s Mitsue), 732s 501R (732s Mitsue), 732s Protection & Control (732s Mitsue) | PRC-005 - SPR TESTING - TRANSFORMER 901T @ 732S, PRC-005 - TRIP COIL TESTING - BREAKER 501 @ 732S TCM Program. RTXP Test Switch Mitigation and Replacement: 87T-A/901T, 87T-B/901T, 50-51TV-59/901T |
|
ATCO | 15-Oct-24 11:00 | 08-Nov-24 17:30 | 24.31 Days
Continuous |
840s McNeill Station, 840s 701T (840s McNeill Station), 840s 901T (840s McNeill Station), 840s 901 (840s McNeill Station), 840s 701 (840s McNeill Station), 840s 702C (840s McNeill Station), 840s 703C (840s McNeill Station) | Transformer 701T and 901T Bushing replacements and post replacement testing HMI Server 1 replacement and commissioning. Annual maintenance | AB-SK |
ALTALINK | 15-Oct-24 12:00 | 15-Oct-24 17:30 | 5.5 Hours
Daily |
244s 552 (244s Bowmanton), 244s 652 (244s Bowmanton), 1074L (244s Bowmanton - 1074AL Tap) | Cut over CTs to new PMU. | |
ALTALINK | 15-Oct-24 13:00 | 17-Oct-24 17:30 | 2.19 Days
Continuous |
89s 352 (89s Ellerslie) | Breaker maint. + First Trip, replace leaking grading capacitor | |
ENMAX | 15-Oct-24 16:00 | 24-Oct-24 16:30 | 9.02 Days
Continuous |
1-GSU-XF-0001 (SS-162), 162B240-RB132 (SS-162), 162B240-RB131 (SS-162) | maintenance | |
ALTALINK | 16-Oct-24 07:30 | 16-Oct-24 12:00 | 4.5 Hours
Daily |
1034L (244s Bowmanton - 324s Cassils), 244s 452 (244s Bowmanton), 244s 552 (244s Bowmanton) | Cut over CTs to new PMU. | |
ATCO | 16-Oct-24 08:00 | 17-Oct-24 16:30 | 1.35 Days
Continuous |
848s 902 (848s Ruth Lake), 848s 907 (848s Ruth Lake) | DFR Upgrade at Ruth Lake. 902CT, 907CT and 902PT inputs will be cutover to new DFR and commissioned. |
|
ALTALINK | 16-Oct-24 08:30 | 16-Oct-24 13:30 | 5 Hours
Daily |
264s 252 (264s Elkwater) | Replace gas density monitors on Breaker 264s252 | |
ATCO | 16-Oct-24 09:00 | 28-Oct-24 17:00 | 12.33 Days
Continuous |
7L81 (791s Rainbow Lake - BCH Harvest Energy FNC Tap), 791s 702 (791s Rainbow Lake) | 7L81 upgrade @ 791S. Scada system upgrade @ 791S |
|
ALTALINK | 16-Oct-24 10:00 | 16-Oct-24 14:00 | 4 Hours
Daily |
250p 11 (250p Bighorn Plant) | maintenance | |
ALTALINK | 16-Oct-24 12:00 | 16-Oct-24 17:30 | 5.5 Hours
Daily |
244s 2152 (244s Bowmanton), 244s 2252 (244s Bowmanton), 676L (244s Bowmanton - 523s Bullshead) | Cut over CTs to new PMU. | |
ALTALINK | 17-Oct-24 07:00 | 18-Oct-24 18:00 | 1.46 Days
Continuous |
765L (151s Strathmore - 419s Chestermere) | Perform maintenance work on structures 63, 64, 65, 290, 292 and 293. | |
ALTALINK | 17-Oct-24 09:00 | 17-Oct-24 15:00 | 6 Hours
Daily |
1202L (89s Ellerslie - 320p Keephills), 320p 3152 (320p Keephills), 320p 3052 (320p Keephills) | connect Summated 1202L CT from 320p3152 & 320p3052 to new PMU | |
ALTALINK | 17-Oct-24 10:00 | 17-Oct-24 14:00 | 4 Hours
Daily |
250p 22 (250p Bighorn Plant) | maintenance | |
ALTALINK | 17-Oct-24 12:00 | 17-Oct-24 17:30 | 5.5 Hours
Daily |
244s 2952 (244s Bowmanton), 244s 3052 (244S Bowmanton), 892L (244s Bowmanton - 895s Suffield) | Cut over CTs to new PMU for 244s voltage control project. Commission new LTO to ras relays. Addition of new breaker maint switch 43M/2952 for breaker 244s2952 - 1054s Holsom (Winifred MPC wind) project . | |
ALTALINK | 18-Oct-24 07:30 | 18-Oct-24 12:00 | 4.5 Hours
Daily |
244s 3052 (244S Bowmanton), 244s 3152 (244s Bowmanton), 674L (244s Bowmanton - 649s Chappice Lake) | Cut over CTs to new PMU. | |
ATCO | 18-Oct-24 08:00 | 19-Oct-24 16:30 | 1.35 Days
Continuous |
9L58 (848s Ruth Lake - 888s Dover), 848s 907 (848s Ruth Lake), 848s 908 (848s Ruth Lake) | DFR Upgrade at Ruth Lake. Cutover 907CT, 908CT, and 908PT inputs will be cutover to new DFR and commissioned. |
|
ALTALINK, EPCOR | 18-Oct-24 09:00 | 18-Oct-24 15:00 | 6 Hours
Daily |
1203L (320p Keephills - 510s Sunnybrook), 320p 3452 (320p Keephills), 320p 2952 (320p Keephills) | connect Summated 1203L CT from 320p3452 & 320p2952 to new PMU | |
ATCO | 18-Oct-24 10:00 | 18-Oct-24 16:00 | 6 Hours
Continuous |
951s 908 (951s Thickwood Hills) | PRC-005 Trip Coil Testing | |
ALTALINK | 19-Oct-24 07:00 | 19-Oct-24 18:00 | 11 Hours
Daily |
786L (799s Coleman - BCH Natal) | Repair woodpecker damage on structures 97 & 109. Hardware tighten structure 108. | AB-BC |
ALTALINK | 19-Oct-24 07:00 | 19-Oct-24 18:00 | 11 Hours
Daily |
940L (120s Picture Butte - 370s North Lethbridge) | URGENT Arctic arrow crew will require a GOI to fix 940L42 Urgent repair. Crew will be replacing the cold end shackles on all 3 phases. See also 291764 172L (354s-370s) RB, that goes with this due to proximity | |
ALTALINK | 19-Oct-24 07:30 | 19-Oct-24 12:00 | 4.5 Hours
Daily |
675L (244s Bowmanton - 321s Al Rothbauer), 244s 2552 (244s Bowmanton), 244s 2652 (244s Bowmanton) | Cut over CTs to new PMU. | |
ALTALINK | 20-Oct-24 07:30 | 20-Oct-24 13:30 | 6 Hours
Daily |
38s 240kV Bus 1 (38s East Edmonton), 38s T1 (38s East Edmonton) | Cutover new alarms, controls, and statuses to new SCADA system. | |
ATCO | 20-Oct-24 08:00 | 21-Oct-24 16:30 | 1.35 Days
Continuous |
9L23 (848s Ruth Lake - 977s Salt Creek), 848s 905 (848s Ruth Lake), 848s 906 (848s Ruth Lake) | DFR Upgrade at Ruth Lake. 905CT, 906CT and 905PT inputs will be cutover to new DFR and commissioned. |
|
ALTALINK | 21-Oct-24 07:00 | 21-Oct-24 13:00 | 6 Hours
Daily |
616L (59s Peigan - 616AL tap), 616L (103s Goose Lake - 616AL tap), 616AL (383s Kettles Hill Windfarm - 616L tap) | Creating Open Point 'C' @ Structure #39 | |
EPCOR | 21-Oct-24 07:00 | 21-Oct-24 17:00 | 10 Hours
Continuous |
PM2405 (Poundmaker) | Poundmaker: PM2405 NAIT Student Substation Tour | |
EPCOR | 21-Oct-24 07:00 | 26-Oct-24 17:00 | 5.42 Days
Continuous |
52s E2402 (52s East Industrial), 52s T2 (52s East Industrial) | East Industrial: TX2 Doble and E2402 (SF6) Breaker Maintenance | |
ALTALINK | 21-Oct-24 07:00 | 30-Oct-24 18:00 | 9.46 Days
Continuous |
820AL (315s Chin Chute - 820L tap), 820BL (967s Redcoat - 820L tap), 820L (254s Coaldale - 820AL tap), 820L (67s Stirling - 820BL tap), 820L (820AL tap - 820BL tap), 67s T2 (67s Stirling) | LCM & WFM on several structures between Structures #172 - 325 | |
ALTALINK | 21-Oct-24 07:30 | 22-Oct-24 16:30 | 1.38 Days
Continuous |
880L (321s Al Rothbauer - 523s Bullshead) | Updating and testing line protections. Commission new LTO and RAS Circuits. | |
ATCO | 21-Oct-24 08:30 | 23-Oct-24 16:00 | 2.31 Days
Continuous |
7L583 (715s Leming Lake - 970s Bourque), 715s 701 (715s Leming Lake) | breaker maintenance | |
ATCO | 21-Oct-24 10:00 | 24-Oct-24 16:00 | 3.25 Days
Continuous |
732s 902T (732s Mitsue), 732s 503R (732s Mitsue), 732s Protection & Control (732s Mitsue) | PRC-005 - SPR TESTING - TRANSFORMER 902T @ 732S, PRC-005 - TRIP COIL TESTING - BREAKER 503 @ 732S TCM Program. RTXP Test Switch Mitigation and Replacement: 87T-A/902T, 87T-B/902T, 50-51TV-59/902T |
|
ATCO | 21-Oct-24 10:00 | 24-Oct-24 16:30 | 3.27 Days
Continuous |
7L50 (757s Battle River - 491L tap) | Structure, cross arm and insulator replacement on 7L50 between battle river and Jarrow. | |
ALTALINK | 21-Oct-24 13:00 | 31-Oct-24 17:30 | 10.19 Days
Continuous |
63s T1 (63s Red Deer) | 25kV bushing(H0X0) replacement, doble, maintenance, leak repairs | |
ALTALINK | 21-Oct-24 13:30 | 24-Oct-24 17:30 | 3.17 Days
Continuous |
320p 3152 (320p Keephills) | 500kV breaker maintenance | |
ENMAX, ALTALINK | 22-Oct-24 06:00 | 22-Oct-24 18:00 | 12 Hours
Continuous |
832L (SS-10 - SS-12) | 12 Sub Building Upgrade | |
ALTALINK, EPCOR | 22-Oct-24 09:00 | 22-Oct-24 15:00 | 6 Hours
Daily |
1043L (320p Keephills - 367s Harry Smith), 320p 252 (320p Keephills), 320p 352 (320p Keephills) | Connect Summated 1043L CT from 320p252 & 320p352 to new PMU | |
ENMAX, ALTALINK | 23-Oct-24 07:00 | 27-Oct-24 18:00 | 4.46 Days
Continuous |
50L (44s Bearspaw Plant - SS-21) | Repair woodpecker damage at structures 119 & 122. Replace structures 116 & 117. | |
ENMAX, ALTALINK | 23-Oct-24 07:00 | 27-Oct-24 18:00 | 4.46 Days
Continuous |
50L (44s Bearspaw Plant - SS-21) | Altalink outage. 50L will be removed from service to repair woodpecker damage on Structures #119 & 122. Also, crews will be replacing Structures #116 & 117. Reclose block required on 50L. | |
ALTALINK | 23-Oct-24 07:00 | 31-Oct-24 18:00 | 8.46 Days
Continuous |
925L (63s Red Deer - 74s Janet) | South Crew will be repairing conductor core at 925L188 | |
ALTALINK | 23-Oct-24 07:30 | 24-Oct-24 16:30 | 1.38 Days
Continuous |
676L (244s Bowmanton - 523s Bullshead) | Updating and testing line protections. Commission new LTO and RAS Circuits to I-1054s. | |
ALTALINK | 23-Oct-24 09:00 | 23-Oct-24 15:00 | 6 Hours
Daily |
190L (17s Benalto - 320p Keephills), 320p 652 (320p Keephills), 320p 552 (320p Keephills) | Connect Summated 190L CT from 320p552 & 320p652 to new PMU | |
ALTALINK, EPCOR | 24-Oct-24 09:00 | 24-Oct-24 15:00 | 6 Hours
Daily |
930L (37s North Calder - Poundmaker), 320p 2052 (320p Keephills), 320p 2152 (320p Keephills) | Connect Summated 903L CT from 320p2052 & 320p2152 to new PMU | |
ALTALINK | 25-Oct-24 09:00 | 25-Oct-24 15:00 | 6 Hours
Daily |
1045AL (320p Keephills - 1045L tap), 320p 1352 (320p Keephills) | Connect 1045AL CT from 320p1352 to new PMU | |
ALTALINK | 26-Oct-24 09:00 | 26-Oct-24 15:00 | 6 Hours
Continuous |
320p 3052 (320p Keephills), 320p 2952 (320p Keephills) | Connect Summated KH3 CT from 320p3052, 320p2952 to new PMU | |
ALTALINK | 28-Oct-24 07:00 | 31-Oct-24 18:00 | 3.46 Days
Continuous |
19s T10 (19s Wabamun), 19s 240kV Bus A (19S Wabamun), 905L (19s Wabamun - 37s North Calder), 902L (19s Wabamun - 310p Sundance) | Proximity outage to complete the salvage of 19s 240kV ‘A’ Bus & 240kV Transfer Bus. Replace 19s905 CTs. RSLD 3 to be implemented at the start of the outage. | |
EPCOR | 28-Oct-24 07:00 | 01-Nov-24 17:00 | 4.42 Days
Continuous |
EP 803s T3 (EP 803s Lambton), EP 803s L721 (EP 803s Lambton) | Lambton: L721 Bay PT LCR | |
EPCOR | 28-Oct-24 07:00 | 02-Nov-24 17:00 | 5.42 Days
Continuous |
1164L (816s Petrolia - EP Riverview), RW2401 (EP Riverview), RW2402 (EP Riverview), 816s P2403 (816s Petrolia), 816s P2404 (816s Petrolia) | 1164L: P2404 Breaker LCR Commissioning (PDS12 Op Checks), Apparatus-RWDS2/RWDS3/RWDS11 Disconnect Maintenance, Aerial- 1164L Insulator replacement | |
ATCO | 28-Oct-24 10:00 | 31-Oct-24 16:30 | 3.27 Days
Continuous |
7L50 (757s Battle River - 491L tap) | Structure, cross arm and insulator replacement on 7L50 between battle river and Jarrow. | |
ENMAX, ALTALINK | 28-Oct-24 12:30 | 31-Oct-24 17:30 | 3.21 Days
Continuous |
24.83L (74s Janet - SS-24) | Altalink outage. 74s24.83X first trip and maintenance. Enmax to block reclosers on 24.83L. | |
ENMAX, ALTALINK | 28-Oct-24 12:30 | 31-Oct-24 17:30 | 3.21 Days
Continuous |
24.83L (74s Janet - SS-24) | 74s24.83X first trip and maintenance. | |
ALTALINK | 28-Oct-24 13:30 | 31-Oct-24 17:30 | 3.17 Days
Continuous |
89s 1752 (89s Ellerslie) | 500kV breaker maintenance | |
ALTALINK | 29-Oct-24 08:00 | 30-Oct-24 16:00 | 1.33 Days
Continuous |
763A1L (1039s Wheatcrest - 763A1L tap), 763AL (447s Enchant - 763A1L tap), 447s T1 (447s Enchant), 447s T2 (447s Enchant) | maintenance | |
ATCO, SUNCOR | 29-Oct-24 08:00 | 30-Oct-24 16:30 | 1.35 Days
Continuous |
29PL9-1 (29EDD-1 Millennium - 848s Ruth Lake), 848s 903 (848s Ruth Lake), 848s 906 (848s Ruth Lake) | DFR Upgrade at Ruth Lake. 903 breaker statuses, 903CT, 906CT and 903PT inputs will be cutover to new DFR and commissioned. |
|
ATCO, FMGW, ALTALINK | 29-Oct-24 08:00 | 31-Oct-24 17:30 | 2.4 Days
Continuous |
1024s PT-6001 (1024s Granlea), 1024s PT-6002 (1024s Granlea), 1024s RTU/SCADA (1024s Granlea) | SGRE uprate work, relay work for hybrid contact swap, Firewall and network changes – remote/on-site, AE will perform point-to-point check, GE MPT 1 leak repairs. | |
ATCO | 29-Oct-24 09:00 | 05-Nov-24 17:00 | 7.38 Days
Continuous |
7L171 (802s Michichi Creek - 804s Wintering Hills) | 7L171 critical crossing, Line to Ground and Line to Line Mitigation. Cross arm and insulator replacement on 7L171, 30 Structures |
|
ATCO | 29-Oct-24 10:00 | 29-Oct-24 16:00 | 6 Hours
Continuous |
939s 1216R (939s Livock) | update ITM settings on 1216R, relay settings changes to REQ670 bay controller, alarm changes/ updates to station controller and HMI. | |
ALTALINK | 30-Oct-24 07:15 | 02-Nov-24 17:45 | 3.44 Days
Continuous |
1206L (12s Heartland - 89s Ellerslie) | WMP: Replace insulator at structure 43. Replace jumper at structure 32. Repair downlead and install ground rod at structure 59. Replace broken insulators at structures 100, 103 | |
ALTALINK, TRANSALTA | 30-Oct-24 09:00 | 30-Oct-24 15:00 | 6 Hours
Daily |
320p 852 (320p Keephills) | Connect KH2 CT from 320p852 to new PMU | |
ALTALINK | 30-Oct-24 23:00 | 31-Oct-24 03:00 | 4 Hours
Daily |
62s 11 (62s Brazeau Plant) | maintenance | |
ALTALINK | 31-Oct-24 03:00 | 31-Oct-24 07:00 | 4 Hours
Daily |
62s 12 (62s Brazeau Plant) | maintenance | |
ALTALINK | 31-Oct-24 09:00 | 31-Oct-24 12:00 | 3 Hours
Daily |
103s 352 (103s Goose Lake) | Urgent Gas Top off | |
ALTALINK | 31-Oct-24 12:30 | 31-Oct-24 16:00 | 3.5 Hours
Daily |
103s 652 (103s Goose Lake) | Urgent Gas Top off | |
ENMAX | 01-Nov-24 08:00 | 01-Nov-24 12:00 | 4 Hours
Continuous |
162B240-RB134 (SS-162) | CT Terminal Block Replacement | |
ALTALINK | 03-Nov-24 07:15 | 04-Nov-24 17:45 | 1.44 Days
Continuous |
1212L (12s Heartland - 89s Ellerslie) | WMP: Replace insulator at structure 46, 48. Replace jumper at structure 32 | |
ALTALINK, EPCOR | 04-Nov-24 07:00 | 05-Nov-24 17:00 | 1.42 Days
Continuous |
1044L (EP 805s Jasper - 816s Petrolia), 816s P2405 (816s Petrolia), 816s P2406 (816s Petrolia), EP 805s J2403 (EP 805s Jasper), EP 805s J2404 (EP 805s Jasper) | Petrolia and Jasper/1044L: P2405 Breaker LCR Commissioning (PDS14 Op Checks) and Jasper DFR Cutover and Commissioning | |
ALTALINK | 04-Nov-24 07:30 | 07-Nov-24 14:30 | 3.29 Days
Continuous |
37s T5 (37s North Calder), 37s T6 (37s North Calder), 37s 138kV Bus (37s North Calder), 37s 4 (37s North Calder) | Switch replacement (37s3) | |
ALTALINK | 04-Nov-24 08:00 | 04-Nov-24 17:00 | 9 Hours
Daily |
1097L (356s Milo – 611s Amber) | Customer outage to straighten a leaning structure on 1097L | |
ALTALINK | 04-Nov-24 08:00 | 09-Nov-24 17:00 | 5.38 Days
Continuous |
760L (760AL tap - 7LA760 tap) | Replace cross arms and insulators on 7L760, 242 structures | |
ALTALINK, EPCOR | 04-Nov-24 09:30 | 15-Nov-24 17:00 | 11.31 Days
Continuous |
915L (38s East Edmonton - 987s Clover Bar), 987s C2403 (987s Clover Bar), 987s C2405 (987s Clover Bar) | 915L: Cloverbar Teleprotection Upgrade w/AltaLink | |
ALTALINK, EPCOR | 04-Nov-24 09:30 | 15-Nov-24 17:00 | 11.31 Days
Continuous |
915L (38s East Edmonton - 987s Clover Bar), 38s 7152 (38s East Edmonton), 38s 7252 (38s East Edmonton) | 915L Cloverbar Teleprotection Upgrade w/AltaLink | |
ATCO | 04-Nov-24 10:00 | 07-Nov-24 16:30 | 3.27 Days
Continuous |
7L50 (757s Battle River - 491L tap) | Structure, cross arm and insulator replacement on 7L50 between battle river and Jarrow. | |
ATCO | 04-Nov-24 10:00 | 08-Nov-24 16:00 | 4.25 Days
Continuous |
951s 901T (951s Thickwood Hills), 951s 902T (951s Thickwood Hills), 951s SVC (951s Thickwood) | SVC fall inspections and maintenance, IPCOMM (SVC Data Concentrator) relay replacement/ commissioning/ RTU Config updates | |
ALTALINK | 04-Nov-24 12:01 | 18-Nov-24 15:00 | 14.12 Days
Continuous |
199L (347s AML Fox Creek - 741s ATC Fox Creek) | A741s work by ATCO | |
ALTALINK | 04-Nov-24 12:30 | 07-Nov-24 17:00 | 3.19 Days
Continuous |
266s 1037L FSC1 (266s SC1) | FSC1 maintenance, CT repair/replacement | |
ENMAX, ALTALINK | 05-Nov-24 06:00 | 05-Nov-24 18:00 | 12 Hours
Continuous |
833L (SS-2 - SS-12) | 12 Sub Building Upgrade | |
ATCO | 05-Nov-24 08:00 | 08-Nov-24 16:00 | 3.33 Days
Continuous |
930s Syn Condenser (930s Arcenciel) | maintenance on Synchronous Condenser | |
BCH | 05-Nov-24 09:00 | 08-Nov-24 17:00 | 3.33 Days
Continuous |
5L91 (BCH Ashton Creek - BCH Selkirk) | Outage required to replaced badly damaged portion of steel tower 39-2, discovered during September 2024 line maintenance BC maintenance does not affect the Alberta ATC | AB-BC |
ALTALINK | 07-Nov-24 09:00 | 07-Nov-24 14:00 | 5 Hours
Daily |
925L (63s Red Deer - 74s Janet) | 925L Dead end Hardware on the A frame at 74s | |
ENMAX | 08-Nov-24 08:00 | 08-Nov-24 12:00 | 4 Hours
Continuous |
162B240-RB131 (SS-162) | CT Terminal Block Replacement | |
ENMAX, ALTALINK | 08-Nov-24 08:00 | 12-Nov-24 16:00 | 4.33 Days
Continuous |
936L (5s East Calgary - 102s Langdon) | Tower climbing inspections. Install dampers | |
ENMAX, ALTALINK | 08-Nov-24 08:00 | 12-Nov-24 16:00 | 4.33 Days
Continuous |
937L (5s East Calgary - 102s Langdon) | Tower climbing inspections. Install dampers | |
ENMAX, ALTALINK | 08-Nov-24 08:00 | 12-Nov-24 16:00 | 4.33 Days
Continuous |
936L (5s East Calgary - 102s Langdon) | Tower climbing inspections. Install dampers. | |
ENMAX, ALTALINK | 08-Nov-24 08:00 | 12-Nov-24 16:00 | 4.33 Days
Continuous |
937L (5s East Calgary - 102s Langdon) | Tower climbing inspections. Install dampers. | |
ENMAX | 08-Nov-24 12:00 | 08-Nov-24 16:00 | 4 Hours
Continuous |
162B240-RB132 (SS-162) | CT Terminal Block Replacement | |
ALTALINK | 11-Nov-24 07:00 | 11-Nov-24 11:00 | 4 Hours
Daily |
879L (244s Bowmanton - 879AL tap), 879L (368s Burdett - 879L tap) | Open East side jumpers at 457A. Install and Commission new CT circuits to new RAS protections | |
EPCOR | 11-Nov-24 07:00 | 15-Nov-24 17:00 | 4.42 Days
Continuous |
330p 1207 (330p Genesee), 330p 1204 (330p Genesee), 330p 1201 (330p Genesee), 330P 12TC1 (330p Genesee), 330p 1210 (330p Genesee), 330p 1214 (330p Genesee), 330p 805 (330p Genesee) | Genesee: 500kV BUS 1 - RTU Upgrade Project Cutovers/Commissioning | |
ALTALINK | 11-Nov-24 09:00 | 22-Nov-24 12:00 | 11.13 Days
Continuous |
15s 138kV Bus1 (15s Fort Macleod), 15s T1 (15s Fort Macleod), 180L (15s Fort Macleod - 180AL tap), 463L (15s Fort Macleod - 463AL tap) | Install and commission new T1 protections, 15s22 control, VT1 distribution, 138kV bus differential protection upgrades, 138V/25kV trip testing pertaining to the 15s Stage 3 building upgrade project. | |
ALTALINK | 11-Nov-24 11:00 | 21-Nov-24 14:00 | 10.13 Days
Continuous |
879L (244s Bowmanton - 879AL tap) | Replace cross-arms, pole replacement and bird diverter installation between str 303-450 - VATD. Install new line protection and RAS. | |
ALTALINK | 12-Nov-24 07:00 | 14-Nov-24 18:00 | 2.46 Days
Continuous |
1041L (370s North Lethbridge - 554s Travers) | *P5* South will be replacing dampers on 1041L195,196, 221, 223, 267, 269 See also 291617 1005L (356s-I_991s_120s) RB, that goes with this due to proximity | |
EPCOR | 12-Nov-24 07:00 | 13-Dec-24 17:00 | 31.42 Days
Continuous |
816s P2402 (816s Petrolia) | Petrolia: P2402 Breaker LCR | |
ALTALINK, EPCOR | 12-Nov-24 08:00 | 15-Nov-24 17:00 | 3.38 Days
Continuous |
1043L (320p Keephills - 367s Harry Smith) | Replace CVT1 and 1043L strain insulators. | |
BCH | 12-Nov-24 09:00 | 22-Nov-24 17:00 | 10.33 Days
Continuous |
T3 (BCH Natal) | NTL station rebuild. T3 OOS for PN replacement | AB-BC |
EPCOR | 13-Nov-24 07:00 | 15-Nov-24 17:00 | 2.42 Days
Continuous |
805s T1 (805s Jasper), 72JM18 (EP 805s Jasper - Meadowlark), 72JW19 (EP 805s Jasper - Woodcroft), EP 805s J722 (EP 805s Jasper), EP 805s J724 (EP 805s Jasper) | Jasper: TX1 DFR Cutovers and Commissioning | |
EPCOR | 13-Nov-24 07:00 | 15-Nov-24 17:00 | 2.42 Days
Continuous |
52s T1 (52s East Industrial), 52s E2401 (52s East Industrial) | East Industrial: TX1 MV BUS OC Upgrade Cutovers and Commissioning | |
SUNCOR | 13-Nov-24 08:00 | 20-Nov-24 18:00 | 7.42 Days
Continuous |
29EDD-71 29PT-234 (29EDD-71) | Firebag: 6 year PM 30EDD240 30PP-121 system | |
ATCO | 13-Nov-24 09:00 | 13-Nov-24 11:00 | 2 Hours
Continuous |
7L68 (730s Rycroft - 811s Clairmont Lake) | HIGH LOAD UNDER LINE AT 7L68-416 | |
ATCO | 13-Nov-24 09:00 | 14-Nov-24 16:00 | 31 Hours
Continuous |
9L59 (801s Anderson - 9LA59 tap), 801s 902 (801s Anderson), 801s 903 (801s Anderson) | DFR Upgrade at Anderson. Cutover and commission the following inputs to the new DFR: CT902-X, CT903-Y, 902PTY2, 902 status, and 903 status. Demo inputs from existing DSM: CT902-X, CT903-Y, and 902PTY1. Cutover 903A from existing RTU I/O to new SEL DPAC I/O and verify status and control to local HM |
|
ATCO | 13-Nov-24 09:00 | 18-Nov-24 17:00 | 5.33 Days
Continuous |
7L171 (802s Michichi Creek - 804s Wintering Hills) | 7L171 critical crossing, Line to Ground and Line to Line Mitigation. Cross arm and insulator replacement on 7L171, 30 Structures |
|
ALTALINK | 13-Nov-24 12:00 | 13-Nov-24 17:30 | 5.5 Hours
Daily |
244s 3152 (244s Bowmanton), 244s 3252 (244s Bowmanton), 879L (244s Bowmanton - 879AL tap) | Cutover CTs to new PMU for 244s voltage control project. | |
ATCO | 14-Nov-24 08:30 | 14-Nov-24 16:30 | 8 Hours
Continuous |
7L65 tap, 7L65 (709s Vegreville - 7LA65 tap), 7L65 (710s Vermilion - 7LA65 tap), 7LA65 (708s Grizzly Bear - 7L65 tap) | Replace Damaged 7LA65D1 switch vacuum bottles. Full Line Outage on 7L65 required. Inspect and make adjustments to 7LA65D1, 7L65D2, 7L65D3 |
|
ATCO | 15-Nov-24 09:00 | 16-Nov-24 16:00 | 31 Hours
Continuous |
801s 903 (801s Anderson), 801s 904 (801s Anderson), 9L70 (801s Anderson - 946s Oakland) | Cutover and commission the following inputs to the new DFR: CT903-X, CT904-Y, and 904 status. | |
ATCO | 17-Nov-24 09:00 | 18-Nov-24 16:00 | 31 Hours
Continuous |
9L950 (132s Ware Junction - 801s Anderson), 801s 911 (801s Anderson), 801s 912 (801s Anderson) | DFR Upgrade at Anderson. Cutover and commission the following inputs to the new DFR: CT911-X & CT912-X, 911PTY2, and 912 status. Demo inputs from existing DSM: CT911-X & CT912-X, 911PTY1 PRC-005 - TRIP & CLOSE COIL TESTING - BREAKER 912 |
|
ALTALINK, DOW | 18-Nov-24 07:00 | 19-Nov-24 17:00 | 1.42 Days
Continuous |
166s T1 (166s Dow Chemical Fort Saskatchewan) | maintenance | |
ALTALINK, EPCOR | 18-Nov-24 07:00 | 22-Nov-24 17:00 | 4.42 Days
Continuous |
1238L (330p Genesee - 510s Sunnybrook), 330p 1201 (330p Genesee), 330p 1202 (330p Genesee) | Genesee:1238L - RTU Upgrade Project Cutovers/Commissioning | |
EPCOR | 18-Nov-24 07:00 | 23-Nov-24 17:00 | 5.42 Days
Continuous |
EP 803s T2 (EP 803s Lambton), EP 803s L2402 (EP 803s Lambton), EP 803s L2405 (EP 803s Lambton) | Lambton: LDS9 LCR and TX2 Leak Repair and L2402 P&C Maintenance | |
ALTALINK, TRANSALTA | 18-Nov-24 07:30 | 19-Nov-24 16:30 | 1.38 Days
Continuous |
733L (179s Gleichen - 428s Namaka), 179s 733 (179s Gleichen) | Add A27/DER and B27/DER Protections (new secondary CT circuits) | |
ATCO | 18-Nov-24 08:30 | 21-Nov-24 17:30 | 3.38 Days
Continuous |
9L36 (825s Whitefish Lake - 826s Marguerite Lake), 825s 902 (825s Whitefish Lake), 825s 906 (825s Whitefish Lake) | 902 PRC Trip Coil Testing 9L36 PRC Aux. relay testing 9L36 RTXP replacement |
|
ATCO | 18-Nov-24 09:30 | 21-Nov-24 17:30 | 3.33 Days
Continuous |
7L44 (749s Flyingshot Lake - 845s Big Mountain), 845s 709 (845s Big Mountain), 845s 710 (845s Big Mountain) | Replace CT710 Replace Crank Mechanisms on 144 kV Switches at 845s Big Mountain - 710B Replace Crank Mechanisms on 144 kV Switches at 845s Big Mountain - 709B |
|
ALTALINK | 18-Nov-24 09:30 | 28-Nov-24 17:30 | 10.33 Days
Continuous |
74s 2452 (74s Janet) | Replace 74s2452 Breaker to new SF6 Type | |
ALTALINK, EPCOR | 18-Nov-24 09:30 | 29-Nov-24 17:00 | 11.31 Days
Continuous |
921L (71s Lamoureux - 987s Clover Bar), 987s C2404 (987s Clover Bar), 987s C2406 (987s Clover Bar) | 921L: Cloverbar Teleprotection Upgrade w/AltaLink | |
ALTALINK, EPCOR | 18-Nov-24 09:30 | 29-Nov-24 17:00 | 11.31 Days
Continuous |
921L (71s Lamoureux - 987s Clover Bar), 71s 1252 (71s Lamoureux), 71s 1352 (71s Lamoureux) | 921L Cloverbar Teleprotection Upgrade w/AltaLink | |
ALTALINK | 18-Nov-24 11:30 | 18-Nov-24 17:00 | 5.5 Hours
Daily |
901L (74s Janet - 901AL tap), 901L (63s Red Deer - 901AL tap), 901AL (64s East Crossfield - 901L tap) | First trip and breaker maintenance 74s2552 and replace hardware on the A frame. | |
ALTALINK | 18-Nov-24 13:00 | 19-Nov-24 16:30 | 27.5 Hours
Continuous |
205s 452 (205s Castle Rock Ridge), 205s 352 (205s Castle Rock Ridge), 1071L (205s Castle Rock Ridge - 312s Fidler) | 205s452 Breaker maintenance and first trip. Exercise/ repair 205s7. | |
ALTALINK | 18-Nov-24 13:00 | 22-Nov-24 17:00 | 4.17 Days
Continuous |
702L (137s Sedgewick - 377s AML Hardisty) | 702L Component Replacement (STR 269 - 455) | |
ATCO | 18-Nov-24 13:00 | 25-Nov-24 08:00 | 6.79 Days
Continuous |
7L40 (733s Simonette - 813s Little Smoky) | 7l40 Line to ground mitigation | |
ALTALINK | 18-Nov-24 17:00 | 22-Nov-24 17:00 | 4 Days
Continuous |
74s 2552 (74s Janet) | First trip and breaker maintenance. | |
ALTALINK | 19-Nov-24 07:00 | 22-Nov-24 17:30 | 3.44 Days
Continuous |
74s 23.80W (74s Janet) | Replace 74s23.80 (1352) Breaker CT | |
ATCO | 19-Nov-24 09:00 | 21-Nov-24 16:00 | 2.29 Days
Continuous |
13L50 (2029s Heathfield - 2075s Newell) | Bird Mitigation on 2075S DC FILTER DCF11. | |
ATCO | 19-Nov-24 09:00 | 24-Nov-24 17:00 | 5.33 Days
Continuous |
7L701 (757s Battle River - 7LA701 tap) | Replace overhead shield wire with OPGW cable on 7L701 from Structure 1 to 11. | |
ALTALINK, DOW | 20-Nov-24 07:00 | 21-Nov-24 17:00 | 1.42 Days
Continuous |
166s T2 (166s Dow Chemical Fort Saskatchewan) | maintenance | |
ALTALINK | 20-Nov-24 10:00 | 21-Nov-24 16:00 | 30 Hours
Continuous |
1048L (59s Peigan - 138s Windy Flats) | 59s952 First Trip and Maint. replace densimeter. 59s23 switch repair. | |
ALTALINK, EPCOR | 21-Nov-24 09:00 | 21-Nov-24 17:00 | 8 Hours
Daily |
510s 3052 (510s Sunnybrook), 510s 2952 (510s Sunnybrook), 1238L (330p Genesee - 510s Sunnybrook) | Replace damaged corona ring on bus expansion joint. | |
ALTALINK | 21-Nov-24 14:00 | 21-Nov-24 18:00 | 4 Hours
Daily |
879L (244s Bowmanton - 879AL tap), 879L (368s Burdett - 879L tap) | Close East side jumpers at 457A. | |
ALTALINK | 23-Nov-24 07:00 | 25-Nov-24 17:00 | 2.42 Days
Continuous |
725L (674s Bowron - 725AL tap) | Replace protections and install new risers on 674s4 | |
Lethbridge, ALTALINK | 23-Nov-24 07:30 | 25-Nov-24 17:00 | 2.4 Days
Continuous |
674s 725W (674s Bowron), 725L (674s Bowron - 725AL tap) | Install new A & B protections and perform local commissioning at 674s. | |
ALTALINK, EPCOR | 25-Nov-24 07:00 | 29-Nov-24 17:00 | 4.42 Days
Continuous |
1239L (330p Genesee - 510s Sunnybrook), 330p 1205 (330p Genesee), 330p 1206 (330p Genesee) | Genesee:1239L - RTU Upgrade Project Cutovers/Commissioning | |
ALTALINK, EPCOR | 25-Nov-24 07:00 | 29-Nov-24 17:00 | 4.42 Days
Continuous |
1239L (330p Genesee - 510s Sunnybrook) | Genesee: 1239L - RTU Upgrade Project Cutovers/Commissioning | |
ENMAX, ALTALINK | 25-Nov-24 08:00 | 28-Nov-24 16:00 | 3.33 Days
Continuous |
918L (281s Johnson - SS-162) | 162 Substation -Surge Arrester Addition | |
ENMAX, ALTALINK | 25-Nov-24 08:00 | 28-Nov-24 16:00 | 3.33 Days
Continuous |
918L (281s Johnson - SS-162) | 162 Substation -Surge Arrester Addition | |
ALTALINK | 25-Nov-24 09:30 | 29-Nov-24 17:30 | 4.33 Days
Continuous |
74s 37.82W (74s Janet) | Replace 74s37.82 (1252) Breaker CT | |
ATCO | 25-Nov-24 13:00 | 29-Nov-24 17:00 | 4.17 Days
Continuous |
7L702 (137s Sedgewick - 757s Battle River) | AltaLink Request for COG from ATCO for 702L Component Replacement (STR 26 - 167). | |
ALTALINK | 25-Nov-24 13:00 | 29-Nov-24 17:00 | 4.17 Days
Continuous |
702L (137s Sedgewick - 757s Battle River) | 702L Component Replacement (STR 26 - 167) | |
ALTALINK | 26-Nov-24 07:00 | 26-Nov-24 17:00 | 10 Hours
Daily |
498s T1 (498s Tilley) | Modify A87/50/51/T1 CT contribuition. Test 67/67N/79/81/96/L7 Breaker fail trip to 498s29 and 498s257E.Modify B87/50/51/51NN/T1 | |
ENMAX, ALTALINK | 26-Nov-24 07:00 | 26-Nov-24 18:00 | 11 Hours
Continuous |
1107L (237s Foothills - SS-65) | Altalink outage. Replace insulators at structure 33. Block reclosers on 1107L. | |
ATCO | 26-Nov-24 09:00 | 27-Nov-24 16:00 | 31 Hours
Continuous |
9L97 (801s Anderson - 946s Oakland), 801s 905 (801s Anderson), 801s 906 (801s Anderson) | DFR Upgrade at Anderson. Cutover and commission the following inputs to the new DFR: CT905-X, CT906-X, and 905 status. Demo inputs from existing DSM: CT905-X, CT906-X Cutover 905a / 905b / 906a from existing RTU I/O to new SEL DPAC I/O and verify status and control to local HMI and SOC. PRC-005 - T |
|
ATCO | 26-Nov-24 09:00 | 03-Dec-24 17:00 | 7.33 Days
Continuous |
7L171 (802s Michichi Creek - 804s Wintering Hills) | 7L171 critical crossing, Line to Ground and Line to Line Mitigation. Cross arm and insulator replacement on 7L171, 30 Structures |
|
ALTALINK | 26-Nov-24 10:30 | 26-Nov-24 17:00 | 6.5 Hours
Daily |
100L (498s Tilley - 895s Suffield) | 895s100 – PRC5 First Trip / breaker maintenance / PRC5 | |
ALTALINK | 28-Nov-24 07:00 | 28-Nov-24 18:00 | 11 Hours
Continuous |
612L (336s Fincastle - 368s Burdett) | Replacing arms and insulators on structure 85 . | |
ALTALINK | 28-Nov-24 07:30 | 29-Nov-24 17:00 | 1.4 Days
Continuous |
725L (15s Fort MacLeod - 725BL tap), 725L (674s Bowron - 725BL tap), 725BL (240s McBride Lake - 725L tap) | Line outage to perform end to end and functional testing requiring trips at 674s and 15s | |
Lethbridge | 28-Nov-24 07:30 | 29-Nov-24 17:00 | 1.4 Days
Continuous |
674s 725W (674s Bowron) | 725LW Line outage to perform end-to-end and functional testing at 15s and 674s | |
ATCO | 28-Nov-24 09:00 | 29-Nov-24 16:00 | 31 Hours
Continuous |
9L933 (132s Ware Junction - 801s Anderson), 801s 907 (801s Anderson), 801s 908 (801s Anderson) | DFR Upgrade at Anderson. Cutover and commission the following inputs to the new DFR: CT907-X & CT908-Y, and 908 status. Demo inputs from existing DSM: None Cutover 907a / 908b / 908a / 9l933d1 / 908 alarms from existing RTU I/O to new SEL DPAC I/O and verify status and control to local HMI and SOC. |
|
ATCO | 30-Nov-24 09:00 | 01-Dec-24 16:00 | 31 Hours
Continuous |
9L934 (132s Ware Junction - 801s Anderson), 801s 909 (801s Anderson), 801s 910 (801s Anderson) | DFR Upgrade at Anderson. Cutover and commission the following inputs to the new DFR: CT909-X, CT910-X, 909PTY2, and 909 status. Demo inputs from existing DSM: CT909, CT910, and 909pty1. |
|
ALTALINK | 02-Dec-24 07:00 | 02-Dec-24 12:30 | 5.5 Hours
Daily |
616L (59s Peigan - 616AL tap), 616L (103s Goose Lake - 616AL tap), 616AL (383s Kettles Hill Windfarm - 616L tap) | Closing Open Point 'C' @ Structure #39 | |
ALTALINK, EPCOR | 02-Dec-24 07:00 | 06-Dec-24 17:00 | 4.42 Days
Continuous |
1209L (89s Ellerslie - 330p Genesee) | Genesee: 1209L - RTU Upgrade Project Cutovers/Commissioning | |
ATCO | 02-Dec-24 10:00 | 09-Dec-24 08:00 | 6.92 Days
Continuous |
7L40 (733s Simonette - 813s Little Smoky) | 7l40 Line to ground mitigation | |
ATCO | 02-Dec-24 13:00 | 06-Dec-24 17:00 | 4.17 Days
Continuous |
7L702 (137s Sedgewick - 757s Battle River) | AltaLink Request for COG from ATCO for 702L Component Replacement (STR 26 - 167). | |
ALTALINK | 02-Dec-24 13:00 | 06-Dec-24 17:00 | 4.17 Days
Continuous |
702L (137s Sedgewick - 757s Battle River) | 702L Component Replacement (STR 26 - 167) | |
ALTALINK | 03-Dec-24 07:00 | 13-Dec-24 17:30 | 10.44 Days
Continuous |
74s C3 (74s Janet), 74s C4 (74s Janet) | Upgrade A&B C3/C4 Protections,Implement Visimax POW for C3/C4 Breakers, Replace Optical CTs on C3/C4 with CTs and VT | |
ALTALINK | 04-Dec-24 07:00 | 08-Dec-24 18:00 | 4.46 Days
Continuous |
100L (498s Tilley - 895s Suffield) | Upgrade 100L for 1061s Alderson Park Interconnection Project - str 242-297. | |
ALTALINK | 04-Dec-24 10:00 | 04-Dec-24 14:00 | 4 Hours
Daily |
250p 11 (250p Bighorn Plant) | maintenance | |
ALTALINK, EPCOR | 05-Dec-24 07:00 | 06-Dec-24 17:00 | 1.42 Days
Continuous |
1055L (629s Argyll Transfer Station - 816s Petrolia), 816s P2402 (816s Petrolia), 816s P2403 (816s Petrolia) | Petrolia: P2402 Breaker LCR Commissioning (PDS11 Op Checks) | |
ALTALINK | 05-Dec-24 10:00 | 05-Dec-24 14:00 | 4 Hours
Daily |
250p 22 (250p Bighorn Plant) | maintenance | |
EPCOR | 09-Dec-24 07:00 | 10-Dec-24 17:00 | 1.42 Days
Continuous |
816s P2402 (816s Petrolia), 816s P2401 (816s Petrolia), 816s T1 (816s Petrolia) | Petrolia: P2402 Breaker LCR Commissioning (PAB1 Op Checks) | |
EPCOR | 09-Dec-24 07:00 | 13-Dec-24 17:00 | 4.42 Days
Continuous |
330p 1209 (330p Genesee), 330p 1203 (330p Genesee), 330p 12TC2 (330p Genesee), 330p 809 (330p Genesee), 330p 1211 (330p Genesee), 330p 1215 (330p Genesee) | Genesee:500kV BUS 2 - RTU Upgrade Project Cutovers/Commissioning | |
BCH | 09-Dec-24 09:00 | 20-Dec-24 17:00 | 11.33 Days
Continuous |
T4 (BCH Natal) | NTL station rebuild, T4 out of service for PN replacement | AB-BC |
ALTALINK | 09-Dec-24 12:00 | 12-Dec-24 17:30 | 3.23 Days
Continuous |
244s 240kV Bus 1 (244s Bowmanton), 244s 138kV Bus 1 (244s Bowmanton), 244s T1 (244s Bowmanton), 244s 152 (244s Bowmanton), 244s 452 (244s Bowmanton), 244s 2189 (244s Bowmanton), 244s 2152 (244s Bowmanton), 244s 2552 (244s Bowmanton), 244s 3752 (244s Bowmanton) | Connect risers to new C1 and C2. Trip test breakers and connect CTs. | |
ATCO | 09-Dec-24 13:00 | 13-Dec-24 17:00 | 4.17 Days
Continuous |
7L702 (137s Sedgewick - 757s Battle River) | AltaLink Request for COG from ATCO for 702L Component Replacement (STR 26 - 167). | |
ALTALINK | 09-Dec-24 13:00 | 13-Dec-24 17:00 | 4.17 Days
Continuous |
702L (137s Sedgewick - 757s Battle River) | 702L Component Replacement (STR 26 - 167) | |
ALTALINK | 10-Dec-24 07:15 | 11-Dec-24 17:45 | 1.44 Days
Continuous |
926L (17s Benalto - 310p Sundance) | LCM; install phase raisers on bottom phase (str24) | |
ATCO | 10-Dec-24 09:00 | 17-Dec-24 17:00 | 7.33 Days
Continuous |
7L171 (802s Michichi Creek - 804s Wintering Hills) | 7L171 critical crossing, Line to Ground and Line to Line Mitigation. Cross arm and insulator replacement on 7L171, 30 Structures |
|
ENMAX, ALTALINK | 11-Dec-24 08:00 | 16-Dec-24 16:00 | 5.33 Days
Continuous |
21.80L (42s Sarcee - SS-21) | 21 Substation -Surge Arrester Addition | |
ENMAX, ALTALINK | 11-Dec-24 08:00 | 16-Dec-24 16:00 | 5.33 Days
Continuous |
932L (74s Janet - SS-162) | 162 Substation -Surge Arrester Addition | |
ENMAX, ALTALINK | 11-Dec-24 08:00 | 16-Dec-24 16:00 | 5.33 Days
Continuous |
21.80L (42s Sarcee - SS-21) | 21 Substation -Surge Arrester Addition | |
ENMAX, ALTALINK | 11-Dec-24 08:00 | 16-Dec-24 16:00 | 5.33 Days
Continuous |
932L (74s Janet - SS-162) | 21 Substation -Surge Arrester Addition | |
ALTALINK | 12-Dec-24 07:15 | 13-Dec-24 18:45 | 1.48 Days
Continuous |
922L (17s Benalto - 310p Sundance) | LCM; install phase raisers on bottom phase (str24) | |
ALTALINK, TRANSALTA | 12-Dec-24 13:00 | 16-Dec-24 17:00 | 4.17 Days
Continuous |
59s T1 (59s Peigan), 616L (59s Peigan - 616AL tap) | Demo/Remove 59s11 and 59s8 and convert into bus support structures. | |
ALTALINK | 13-Dec-24 07:30 | 16-Dec-24 12:00 | 3.19 Days
Continuous |
244s 138kV Bus 2 (244s Bowmanton), 244s T2 (244s Bowmanton), 244s 240kV Bus 2 (244s Bowmanton), 244s 352 (244s Bowmanton), 244s 652 (244s Bowmanton), 244s 2389 (244s Bowmanton), 244s 2252 (244s Bowmanton), 244s 2652 (244s Bowmanton), 244s 2489 (244s Bowmanton) | Connect risers to new C3. Trip test breakers and connect CTs. | |
ALTALINK | 15-Dec-24 07:00 | 19-Dec-24 18:00 | 4.46 Days
Continuous |
929L (74S Janet - 287s Hazelwood) | Arctic Arrow requires a GOI on 929L to complete installation on interphase spacers in spans 117-120, 363, & 388-399. See also 290369 925L RB and 290370 932L RB that goes with this due to proximity | |
ATCO | 16-Dec-24 10:00 | 23-Dec-24 16:00 | 7.25 Days
Continuous |
7L40 (733s Simonette - 813s Little Smoky) | Changing Poles and Cross Arms | |
ALTALINK | 16-Dec-24 12:30 | 17-Dec-24 17:00 | 28.5 Hours
Continuous |
763L (158s Vauxhall - 257s Hull) | 158s763N – PRC5 First Trip / breaker maintenance / PRC5 | |
ALTALINK | 18-Dec-24 23:00 | 19-Dec-24 03:00 | 4 Hours
Daily |
62s 11 (62s Brazeau Plant) | maintenance | |
ALTALINK | 19-Dec-24 03:00 | 19-Dec-24 07:00 | 4 Hours
Daily |
62s 12 (62s Brazeau Plant) | maintenance | |
ATCO | 06-Jan-25 08:00 | 13-Jan-25 16:00 | 7.33 Days
Continuous |
7L68 (730s Rycroft - 811s Clairmont Lake) | Line to line and line to ground mitigation | |
ATCO | 06-Jan-25 10:00 | 13-Jan-25 16:00 | 7.25 Days
Continuous |
7L40 (733s Simonette - 813s Little Smoky) | Changing rotten X Arms and rotten poles from Test and Treat | |
ATCO | 07-Jan-25 09:00 | 10-Jan-25 16:00 | 3.29 Days
Continuous |
801s 901T (801s Anderson), 801s 902 (801s Anderson), 801s 704 (801s Anderson) | DFR Upgrade at Anderson. Cutover and commission the following inputs to the new DFR: CT901-X, CT902-Y, and 704 status. Relay settings updates: 87tb/901t and 51tv-59n-51n/901t and associated wiring modifications. Scada configuration changes, including verification of alarms to local HMI and SOC. |
|
ATCO | 11-Jan-25 09:00 | 12-Jan-25 17:00 | 1.33 Days
Continuous |
801s 705 (801s Anderson), 7L85 (801s Anderson - ATC 803s Bullpound) | DFR Upgrade at Anderson. Demo inputs from existing DSM: 705CT, 21A/7L85 and 21B/7L85 DSM trigger, 94-700BS1 trigger (requires blocking of 87BA/700BS1 during wire removal), and 700PT1Y1 input (requires blocking during wire removal). 7L85 relay setting updates. |
|
EPCOR | 13-Jan-25 07:00 | 17-Jan-25 17:00 | 4.42 Days
Continuous |
987s T2 (987s Clover Bar), 987s C2410 (987s Clover Bar), 987s C2406 (987s Clover Bar), 987s CC721 (987s Clover Bar) | Cloverbar: TX2 VRR Cut Overs | |
ATCO | 14-Jan-25 10:00 | 14-Jan-25 17:00 | 7 Hours
Continuous |
801s 902 (801s Anderson) | Final connection of Bkr 902/52a single pole status inputs to DFR, Commission | |
ATCO | 15-Jan-25 10:00 | 15-Jan-25 17:00 | 7 Hours
Continuous |
801S 903, 801s 903 (801s Anderson) | Final connection of Bkr 903 52a single pole status inputs to DFR, Commission | |
ATCO | 16-Jan-25 10:00 | 16-Jan-25 17:00 | 7 Hours
Continuous |
801S 904, 801s 904 (801s Anderson) | Final connection of Bkr 904 52a single pole status inputs to DFR, Commission | |
ATCO | 17-Jan-25 10:00 | 17-Jan-25 17:00 | 7 Hours
Continuous |
801s 905 (801s Anderson) | Final connection of Bkr 905 52a single pole status inputs to DFR, Commission | |
ATCO | 18-Jan-25 10:00 | 18-Jan-25 17:00 | 7 Hours
Continuous |
801s 906 (801s Anderson) | Final connection of Bkr 906 52a single pole status inputs to DFR, Commission | |
ATCO | 19-Jan-25 10:00 | 19-Jan-25 17:00 | 7 Hours
Continuous |
801s 907 (801s Anderson) | Final connection of Bkr 907 52a single pole status inputs to DFR, Commission | |
ATCO | 20-Jan-25 08:00 | 27-Jan-25 16:00 | 7.33 Days
Continuous |
7L68 (730s Rycroft - 811s Clairmont Lake) | Line to line and line to ground mitigation | |
ATCO, ALTALINK | 20-Jan-25 10:00 | 23-Jan-25 16:30 | 3.27 Days
Continuous |
7L129 (526s Buffalo Creek - 7LA129 tap) | Replace structures, cross arms and insulators on 7L129 | |
ALTALINK | 20-Jan-25 10:00 | 23-Jan-25 16:30 | 3.27 Days
Continuous |
526s 20 (526s Buffalo Creek) | Replace structures, cross arms and insulators on 7L129 | |
ATCO | 20-Jan-25 10:00 | 24-Jan-25 12:00 | 4.08 Days
Continuous |
741s 701T (741s Fox Creek), 741s 701 (741s ATC Fox Creek), 741s 702 (741s ATC Fox Creek), 741s 702T (741s Fox Creek), 741s 703 (741s ATC Fox Creek), 741s 704 (741s ATC Fox Creek), 741s 705C (741s Fox Creek), 741s 705 (741s ATC Fox Creek), 7L90 (741s ATC Fox Creek - 7LA90 tap), 7L199 (347s AML Fox Creek - 741s ATC Fox Creek) | Install new 144kV PT to 144kV bus in a new location. | |
ATCO, ALTALINK | 27-Jan-25 10:00 | 30-Jan-25 16:30 | 3.27 Days
Continuous |
7L129 (526s Buffalo Creek - 7LA129 tap) | Replace structures, cross arms and insulators on 7L129 | |
ALTALINK | 27-Jan-25 10:00 | 30-Jan-25 16:30 | 3.27 Days
Continuous |
526s 20 (526s Buffalo Creek) | Replace structures, cross arms and insulators on 7L129 | |
ATCO | 28-Jan-25 10:00 | 28-Jan-25 17:00 | 7 Hours
Continuous |
801s 908 (801s Anderson) | Final connection of Bkr 908 52a single pole status inputs to DFR, Commission | |
ATCO | 29-Jan-25 10:00 | 29-Jan-25 17:00 | 7 Hours
Continuous |
801s 909 (801s Anderson) | Final connection of Bkr 909 52a single pole status inputs to DFR, Commission | |
ATCO | 30-Jan-25 10:00 | 30-Jan-25 17:00 | 7 Hours
Continuous |
801s 910 (801s Anderson) | Final connection of Bkr 910 52a single pole status inputs to DFR, Commission | |
ATCO | 31-Jan-25 10:00 | 31-Jan-25 17:00 | 7 Hours
Continuous |
801s 911 (801s Anderson) | Final connection of Bkr 911 52a single pole status inputs to DFR, Commission | |
ATCO | 01-Feb-25 10:00 | 01-Feb-25 17:00 | 7 Hours
Continuous |
801s 912 (801s Anderson) | Final connection of Bkr 912 52a single pole status inputs to DFR, Commission | |
ATCO | 03-Feb-25 08:00 | 10-Feb-25 16:00 | 7.33 Days
Continuous |
7L68 (730s Rycroft - 811s Clairmont Lake) | Line to line and line to ground mitigation | |
ATCO | 03-Feb-25 09:00 | 10-Feb-25 16:00 | 7.29 Days
Continuous |
9L10 (876s Brintnell - 939s Livock) | Line to Ground Mitigation | |
ATCO | 10-Feb-25 08:00 | 13-Feb-25 17:00 | 3.38 Days
Continuous |
7L85 (803s ATC Bullpound - 7LA85 tap) | Install interphase spacers | |
ATCO | 10-Feb-25 12:30 | 13-Feb-25 15:00 | 3.1 Days
Continuous |
7L85 (804s Wintering Hills - 7LA85 tap) | Cross arm and insulator replacement on 7L85 insulator replacement on 7L85 |
|
ATCO | 14-Feb-25 08:00 | 17-Feb-25 17:00 | 3.38 Days
Continuous |
7L85 (804s Wintering Hills - 7LA85 tap) | Install interphase spacers | |
ATCO | 17-Feb-25 09:00 | 24-Feb-25 16:00 | 7.29 Days
Continuous |
9L10 (876s Brintnell - 939s Livock) | Line to Ground Mitigation | |
ATCO | 17-Feb-25 12:01 | 03-Mar-25 12:00 | 14 Days
Continuous |
7L199 (347s AML Fox Creek - 741s ATC Fox Creek), 741s 702 (741s ATC Fox Creek) | Fox Creek Substation Upgrade project. Demo old cables, install and terminate new cables, cut over to new protection. |
|
ATCO | 24-Feb-25 07:00 | 17-Mar-25 17:00 | 21.38 Days
Continuous |
730s 701T (730s Rycroft) | install new relays, new 2z panel, end to end testing. | |
ATCO | 24-Feb-25 08:00 | 03-Mar-25 17:00 | 7.38 Days
Continuous |
7L85 (801s Anderson - ATC 803s Bullpound) | Crossarm Replacements, install interphase spacers, clearance mitigation | |
ENMAX, ALTALINK | 24-Feb-25 08:00 | 14-Mar-25 16:00 | 18.29 Days
Continuous |
20.82L (SS-20 - SS-21), 21.80L (42s Sarcee - SS-21), 21.1TR (SS-21) | HV SW Replacement 21SW81, 21SW82, 21SW83, 21MD138-21.1TR, 21.4TR (SS-21) | |
ENMAX, ALTALINK | 24-Feb-25 08:00 | 14-Mar-25 16:00 | 18.29 Days
Continuous |
21.80L (42s Sarcee - SS-21) | HV SW Replacement 21SW81, 21SW82, 21SW83, 21MD138-21.1TR, 21.4TR (SS-21) | |
ATCO | 03-Mar-25 09:00 | 10-Mar-25 16:00 | 7.25 Days
Continuous |
9L10 (876s Brintnell - 939s Livock) | Line to Ground Mitigation | |
ATCO | 10-Mar-25 08:00 | 13-Mar-25 17:00 | 3.38 Days
Continuous |
7L28 (717s Ethel Lake - 846s Grand Centre) | 7L28 Line to ground clearance mitigation | |
ATCO | 10-Mar-25 08:00 | 17-Mar-25 17:00 | 7.38 Days
Continuous |
7L85 (801s Anderson - ATC 803s Bullpound) | Crossarm Replacements, install interphase spacers, clearance mitigation | |
ENMAX, ALTALINK | 17-Mar-25 08:00 | 27-Mar-25 16:00 | 10.33 Days
Continuous |
50L (44s Bearspaw Plant - SS-21) | HV SW Replacement 21SW87, 21SW88, 21SW89, 21MD138-21.2TR | |
ENMAX, ALTALINK | 17-Mar-25 08:00 | 27-Mar-25 16:00 | 10.33 Days
Continuous |
50L (44s Bearspaw Plant - SS-21), 21.1C (SS-21), 21.2TR (SS-21) | HV SW Replacement 21SW87, 21SW88, 21SW89, 21MD138-21.2TR | |
ALTALINK | 18-Mar-25 07:00 | 31-Mar-25 18:00 | 13.46 Days
Continuous |
610L (83s Taber - 336s Fincastle) | VATD - Rebuild 610L. | |
ATCO | 18-Mar-25 08:00 | 19-Mar-25 17:00 | 1.38 Days
Continuous |
7L53 (706s Irish Creek - 7LA53 tap), 7LA53 (969s Lindbergh - 7L53 tap), 7L53 (700s Bonnyville - 7LA53 tap) | Cold Lake Area Project to connect 1064s | |
ATCO | 24-Mar-25 07:00 | 27-Mar-25 17:00 | 3.42 Days
Continuous |
730s 703 (730s Rycroft), 7L73 (730s Rycroft - 829s Boucher Creek) | Disconnect and remove 703/7L73 cabling from panel 1Z and 2M, complete cut in and termination of new yard cabling to 703, cutover SCADA ccts to station controller. Commission new integrated protection relays for 703/7L73 inputs, SCADA end-to-end testing. | |
ATCO | 24-Mar-25 08:00 | 27-Mar-25 17:00 | 3.38 Days
Continuous |
7L91 (715s Leming Lake - 826s Marguerite Lake) | Cold Lake Area Energy Centre Project Cutover CT/PT/P&C ccts for new Thermal RAS relays Complete commissioning 49A/49B/7L91 relays End-to-end testing to 1064S |
|
ATCO | 24-Mar-25 08:00 | 31-Mar-25 17:00 | 7.38 Days
Continuous |
7L85 (801s Anderson - ATC 803s Bullpound) | Crossarm Replacements, install interphase spacers, clearance mitigation | |
ATCO, ALTALINK | 24-Mar-25 10:00 | 27-Mar-25 16:30 | 3.27 Days
Continuous |
7L129 (526s Buffalo Creek - 7LA129 tap) | Replace structures, cross arms and insulators on 7L129 | |
ATCO | 21-Apr-25 08:00 | 24-Apr-25 17:00 | 3.38 Days
Continuous |
7L86 (822s Wolf Lake - 1200s Foster Creek) | Cenovus is expanding their 1200S substation 26m to the south, toward structure 449. We will be relocating the conductor north of structure 449 to the new A-Frame structure that Cenovus is installing inside their substation. |
|
ENMAX, ALTALINK | 25-Apr-25 08:00 | 28-Apr-25 16:00 | 3.33 Days
Continuous |
20.82L (SS-20 - SS-21), 21.80L (42s Sarcee - SS-21), 21.1TR (SS-21), 50L (44s Bearspaw Plant - SS-21), 21.1C (SS-21), 21.2TR (SS-21) | HV SW Replacement 21SW86. Full substation outage | |
ALTALINK, ENMAX | 25-Apr-25 08:00 | 28-Apr-25 16:00 | 3.33 Days
Continuous |
42s 22 (42s Sarcee), 21.80L (42s Sarcee - SS-21) | HV SW Replacement 21SW86. Full substation outage | |
ENMAX, ALTALINK | 25-Apr-25 08:00 | 28-Apr-25 16:00 | 3.33 Days
Continuous |
50L (44s Bearspaw Plant - SS-21) | HV SW Replacement 21SW86. Full substation outage | |
SUNCOR | 03-May-25 09:00 | 15-May-25 16:00 | 12.29 Days
Continuous |
29EDD-1 T2 (29EDD-1 Millennium) | BP-29EDD-1 - TA - T2 OLTC Maintenance and Testing; 29EDD-1 T2 72LV Arrester replacement (CG) 300199837, 300203566 |
|
ATCO | 05-May-25 09:00 | 06-May-25 15:00 | 30 Hours
Continuous |
755s 901 (755s Cordel) | BREAKER 901 SF6 GL315 COMPLETE TESTING @ 755S Cordel | |
ATCO | 07-May-25 09:00 | 08-May-25 15:00 | 30 Hours
Continuous |
755s 902 (755s Cordel) | BREAKER 902 SF6 GL315 COMPLETE TESTING @ 755S Cordel | |
ATCO | 20-May-25 08:00 | 27-May-25 17:00 | 7.38 Days
Continuous |
7L224 (650s Hansman Lake - 774s Monitor) | Install interphase spacers on 7L224 | |
SUNCOR | 06-Jun-25 00:00 | 22-Jun-25 00:00 | 16 Days
Continuous |
29PL7-4 (29EDD-65 - 29EDD-71), 29EDD-65 29PS-0284 (29EDD-65 Edd65Sub), 29EDD-71 29PS-243 (29EDD-71 Edd71Sub), 29EDD-65 29PT-0257 (29EDD-65) | FB-Maintenance and Testing - 29PT-260, 29PL7-4, 29PT-241, 29PT-257, 29PS-243 (450236799, 450233735, 31773784, 450237159) | |
ATCO | 09-Jun-25 09:00 | 23-Jun-25 17:30 | 14.35 Days
Continuous |
2029S BUILDING VALVE HALL, 2029s 1205 (2029s Heathfield), 2029s 1206 (2029s Heathfield) | Annual EATL outage at 2075s & 2029s.
2029s & 2075s AC & DC O&M. USE 2-70215 FOR 13L50 GOI USE 2-70216 FOR 2029s GOI USE 2-70217 FOR 2075s GOI |
|
ATCO | 09-Jun-25 09:00 | 23-Jun-25 17:30 | 14.35 Days
Continuous |
2075S BUILDING VALVE HALL, 2075s 916 (2075s Newell), 2075s 917 (2075s Newell) | Annual EATL outage at 2075s & 2029s.
2029s & 2075s AC & DC O&M. USE 2-70215 FOR 13L50 GOI USE 2-70216 FOR 2029s GOI USE 2-70217 FOR 2075s GOI |
|
ATCO | 09-Jun-25 09:00 | 23-Jun-25 17:30 | 14.35 Days
Continuous |
13L50 (DC LINK), 13L50 (2029s Heathfield - 2075s Newell) | Annual EATL outage at 2075s & 2029s.
2029s & 2075s AC & DC O&M. USE 2-70215 FOR 13L50 GOI USE 2-70216 FOR 2029s GOI USE 2-70217 FOR 2075s GOI |
|
ENMAX, ALTALINK | 16-Jun-25 08:00 | 19-Jun-25 16:00 | 3.33 Days
Continuous |
28.80L (42s Sarcee - SS-28) | HV SW Replacement. 28SW80 | |
ENMAX, ALTALINK | 16-Jun-25 08:00 | 19-Jun-25 16:00 | 3.33 Days
Continuous |
28.80L (42s Sarcee - SS-28) | HV SW Replacement 28SW80 | |
ENMAX, ALTALINK | 27-Jun-25 08:00 | 03-Jul-25 16:00 | 6.33 Days
Continuous |
37.2TR (SS-37), 37.82L (74s Janet - SS-37) | HV SW Replacement. 37SW84, 37SW85, 37SW86 | |
ENMAX, ALTALINK | 27-Jun-25 08:00 | 03-Jul-25 16:00 | 6.33 Days
Continuous |
50L (44s Bearspaw Plant - SS-21) | HV SW Replacement. 37SW84, 37SW85, 37SW86 | |
SUNCOR | 01-Jul-25 00:00 | 18-Jul-25 00:00 | 17 Days
Continuous |
29PL7-3 (29EDD-65 - 29EDD-71), 29EDD-65 29PT-0236 (29EDD-65) | FB-Maintenance and Testing - 29PT-250, 29PL7-3, 29PT-246, 29PT-236 (450237140, 450237180, 450237158) | |
ATCO | 03-Jul-25 08:00 | 05-Jul-25 17:00 | 2.38 Days
Continuous |
7L701 (757s Battle River - 7LA701 tap) | Install interphase spacers | |
ATCO, ALTALINK | 06-Jul-25 08:00 | 08-Jul-25 17:00 | 2.38 Days
Continuous |
7L701D1 (7LA701 tap), 701L (223s Strome - 7LA701 tap) | Install interphase spacers | |
ATCO | 05-Aug-25 08:00 | 07-Aug-25 16:30 | 2.35 Days
Continuous |
7L702 (137s Sedgewick - 757s Battle River) | Interphase spacers and pole replacements | |
ATCO | 11-Aug-25 10:00 | 14-Aug-25 16:30 | 3.27 Days
Continuous |
7L702 (137s Sedgewick - 757s Battle River) | Interphase spacers and pole replacements | |
ATCO | 18-Aug-25 10:00 | 21-Aug-25 16:30 | 3.27 Days
Continuous |
7L702 (137s Sedgewick - 757s Battle River) | Interphase spacers and pole replacements | |
ATCO, ALTALINK | 18-Aug-25 10:00 | 27-Aug-25 17:00 | 9.29 Days
Continuous |
7L129 (526s Buffalo Creek - 7LA129 tap), 710s 704 (710s Vermilion) | 7L129 - A and B line protection upgrade. | |
ATCO, ALTALINK | 29-Sep-25 09:00 | 03-Oct-25 17:00 | 4.33 Days
Continuous |
7L77 (395s North Holden - 709s Vegreville) | Install interphase spacers | |
ALTALINK | 01-Oct-25 08:00 | 11-Nov-25 17:00 | 41.42 Days
Continuous |
102s SVC (102s Langdon), 102s T4 (102s Langdon) | the controls change | AB-BC |
ATCO | 14-Oct-25 08:00 | 21-Oct-25 17:00 | 7.38 Days
Continuous |
7L171 (802s Michichi Creek - 804s Wintering Hills) | Install interphase spacers | |
ATCO | 03-Nov-25 12:00 | 09-Dec-25 17:00 | 36.21 Days
Continuous |
9L99 (801s Anderson - 807s Sheerness) | Replace Breaker 901 @ 807S Sheerness, complete line 21A, 21B/9L99 protection upgrade and Commissioning | |
ATCO | 08-Dec-25 13:00 | 11-Dec-25 15:00 | 3.08 Days
Continuous |
7L89 (721s La Corey - 826s Marguerite Lake) | Line to ground clearance mitigation spans 202-203; 209-210; 216-217-218; 217-218; 221-222-223-224; 255-256; 313-314-315 | |
ATCO | 15-Dec-25 13:00 | 18-Dec-25 15:00 | 3.08 Days
Continuous |
7L89 (721s La Corey - 826s Marguerite Lake) | Line to ground clearance mitigation spans 202-203; 209-210; 216-217-218; 217-218; 221-222-223-224; 255-256; 313-314-315 | |
ATCO | 13-Apr-26 10:00 | 18-Apr-26 17:00 | 5.29 Days
Continuous |
7L22 (790s Poplar Hill - 7L88 tap) | Cut open 7L22, connect new line section to new 2061S Dobbs 7L22/21B relay upgrades at 790S Poplar Hill and 811S Clairmont Lake On completion energize new 2061S Dobbs substation |
|
ATCO | 03-May-26 10:00 | 04-May-26 17:00 | 31 Hours
Continuous |
7L22 (811s Clairmont Lake - 7L88 tap) | 7L22/21B relay upgrade at 811S Clairmont Lake Upon completion new 2061S Dobbs substation ready to energize |
|
ATCO | 08-Mar-27 10:00 | 17-Mar-27 17:00 | 9.25 Days
Continuous |
9L24 (946s Oakland - 959s Lanfine), 959s 906 (959s Lanfine), 959s 905 (959s Lanfine), 946s 902 (946s Oakland), 946s 903 (946s Oakland) | Replace A/B protection relays at 959S Lanfine and 946S Oakland Cut in and reroute 9L24 Connect new 9LA24 T-tap Commission Telecom and Protection to new 1072S Rose Lynn substation |
AB-BC, AB-SK & AB-MATL: refer to AESO web posting: | http://itc.aeso.ca/itc/public/atc |
Also, | |
AB-BC, AB-SK & AB-MATL: refer to ISO Rule 203.6: | http://www.aeso.ca/rulesprocedures/18592.html |
Prepared On: | 2024-10-02 16:13:34 |
This document and the information contained herein are based upon information and data which by their nature contain a degree of uncertainty and are subject to change. In addition, this document may contain information and data from public sources and/or third parties, which have been assumed to be accurate and complete and have not been verified. Accordingly, the Independent System Operator, operating as the Alberta Electric System Operator (the "AESO") makes no warranty, representation or guarantee, express or implied, with respect to this document or the information contained herein, including, but not limited to, any warranty, representation or guarantee of accuracy, completeness, timeliness, reliability, availability, absence of computer virus, non- infringement, merchantability or suitability for any purpose. Under no circumstances will the AESO, its members, officers, employees, contractors or agents, or any of their respective affiliates, be liable for any errors or omissions in, or any losses, damages or claims whatsoever, whether in contract, tort or otherwise, arising from use of or reliance upon, this document or any information contained herein. © 2009 Alberta Electric System Operator. All rights reserved |