| Alberta Electric System Operator | |
| Long Range Significant Transmission Outages for the period of 24 months starting 2026-05-02 | |
|
The table below contains the significant transmission outages submitted as tentative to the AESO. These Outages have not yet necessarily been approved, but are listed for awareness and coordination purposes. An Outage has been considered significant for this table if it meets any one (1) or more of the following criteria: |
|
|
|
| Note: Where a transmission outage requires generation curtailments, the adjustments to generation will typically happen in the hours before the scheduled transmission outage and in the hour after the element is returned to service. | |
| Previous Version | |
| Download CSV | |
| Owner | From | To | Duration | Element | Scheduled Activity | Affected Intertie |
|---|---|---|---|---|---|---|
| ATCO | 25-Nov-25 17:46 | 18-Sep-26 18:00 | 296.97 Days
Continuous |
876s 901T (876s Brintnell) | forced outage oil leaking | |
| SUNCOR | 04-Jan-26 08:00 | 02-Sep-26 16:00 | 241.29 Days
Continuous |
29EDD-34 260kV Bus 29PP-45 (29EDD-34), 29EDD-34 29-952-113 (29EDD-34), 29EDD-34 29PS-216 (29EDD-34) | urgent repairs on 29PT-224 at 29EDD34 on 29PP-45 bus | |
| BHE Canada | 22-Mar-26 13:00 | 30-Jun-26 17:00 | 100.17 Days
Continuous |
120s C1 (120s Picture Butte), 120s C2 (120s Picture Butte) | forced outage | |
| ALTALINK | 30-Mar-26 08:30 | 04-May-26 16:30 | 35.33 Days
Continuous |
62s T1 (62s Brazeau Plant), 62s 1 (62s Brazeau Plant) | maintenance | |
| EPCOR | 13-Apr-26 07:00 | 29-May-26 17:00 | 46.42 Days
Continuous |
805s T4 (805s Jasper) | bushing replacement and fan repair | |
| BCH | 20-Apr-26 09:00 | 08-May-26 17:00 | 18.33 Days
Continuous |
5L98 (BCH Nicola - BCH Vaseux Lake) | replace spacer damper and insulator, BC maintenance does not affect the Alberta ATC | AB-BC |
| ALTALINK, ATCO | 27-Apr-26 08:00 | 11-May-26 18:00 | 14.42 Days
Continuous |
87s T2 (87s Gaetz), 87s 240kV East Bus (87s Gaetz), 87s 1552 (87s Gaetz), 87s 1652 (87s Gaetz), 87s 1952 (87s Gaetz), 87s 1252 (87s Gaetz), 962L (87s Gaetz - 972s Tinchebray), 986L (87s Gaetz - 972s Tinchebray) | Closing Open points 'A' & 'C' and commissioning 87s962 & 87s986 MODs | |
| ATCO | 27-Apr-26 12:00 | 04-May-26 12:00 | 7 Days
Continuous |
730s STATCOM (730s Rycroft), 730s 705 (730s Rycroft), 730s 702T (730s Rycroft) | svc fire system and annual inspection @ Rycroft 730s | |
| ALTALINK | 29-Apr-26 08:00 | 07-May-26 18:00 | 8.42 Days
Continuous |
275s T1 (275s Jenner) | 275sT1 Oil Reclaim, Maintenance, Plugged Radiator, Replace switch 275s37 and 275s39. Replace 25kV post insulators.275s2269, 275s2036N, & 275s81 | |
| ALTALINK | 29-Apr-26 17:00 | 19-May-26 07:00 | 19.58 Days
Continuous |
320p 2089 (320p Keephills) | Urgent customer work on G3 | |
| ALTALINK | 01-May-26 14:00 | 07-May-26 16:00 | 6.08 Days
Continuous |
37s Protection & Control (37s North Calder), 37s T6 (37s North Calder) | P&C upgrades (37s4, 37s88, 37s81, T6, PT20) | |
| ENMAX | 02-May-26 08:00 | 02-May-26 18:00 | 10 Hours
Continuous |
162.1TR (SS-162), 240kV North Bus (SS-162), 138kV North Bus (SS-162) | Summer Substation Washing | |
| ENMAX | 03-May-26 08:00 | 03-May-26 18:00 | 10 Hours
Continuous |
162.2TR (SS-162), 138kV South Bus (SS-162), 240kV South Bus (SS-162) | Summer Substation Washing | |
| EPCOR | 04-May-26 07:00 | 08-May-26 17:00 | 4.42 Days
Continuous |
805s T4 (805s Jasper), EP 805s J2406 (EP 805s Jasper), EP 805s J2405 (EP 805s Jasper) | Jasper: TX4 Relay Maintenance | |
| EPCOR | 04-May-26 07:00 | 10-May-26 17:00 | 6.42 Days
Continuous |
BR721 (Rossdale), 814s T1 (814s Bellamy), 814s B2401 (814s Bellamy), 814s B2407 (814s Bellamy) | Bellamy: TX1 Zone Doble and BR721 Breaker Maintenance/Doble, and BDS15 Disconnect Maintenance | |
| EPCOR | 04-May-26 07:00 | 10-May-26 17:00 | 6.42 Days
Continuous |
557s T2 (557s Castle Downs), 557s CD2403 (557s Castle Downs), 557s CD2404 (557s Castle Downs) | Castledowns: TX2 Doble, Tap Changer Maintenance, and CDAB2CDDS6/CDDS7 Disconnect Maintenance | |
| BCH, BPA | 04-May-26 08:00 | 15-May-26 17:00 | 11.38 Days
Continuous |
2L112 (BPA Boundary - BCH Nelway) | emergency replacement of a boundary PCB | AB-BC |
| Syncrude | 04-May-26 08:00 | 24-May-26 16:00 | 20.33 Days
Continuous |
Mildred T6 (Syncrude Mildred Lake), 635 (Syncrude Mildred Lake) | SCL - repair tap changer in T6 transformer | |
| ATCO | 04-May-26 09:00 | 18-May-26 17:30 | 14.35 Days
Continuous |
13L50 (2029s Heathfield - 2075s Newell) | Kinbrook Addition to 2075s | |
| ATCO | 04-May-26 09:00 | 18-May-26 17:30 | 14.35 Days
Continuous |
2029s T11 (2029s Heathfield) | Kinbrook Addition to 2075s Newell. | |
| ATCO | 04-May-26 09:00 | 18-May-26 17:30 | 14.35 Days
Continuous |
2075s T11 (2075s Newell) | Kinbrook Addition to 2075s Newell. | |
| ALTALINK | 04-May-26 10:00 | 04-May-26 15:00 | 5 Hours
Continuous |
254s 35 (254s Coaldale), 254s T2 (254s Coaldale) | Repair/Complete lightning arrestor grounding on T2 (TX18710) | |
| ATCO | 04-May-26 10:00 | 07-May-26 10:00 | 3 Days
Continuous |
9L19 (937s AMR02 - 960s Birchwood Creek), 937s 06-TR-8001A (937s Amr02), 937s 06-DS-89T1 (937s Amr02), 937s 9L19 (937s Amr02) | transformer and disconnect maintenance | |
| ATCO, CNRL | 04-May-26 10:00 | 08-May-26 16:00 | 4.25 Days
Continuous |
838s RTU/SCADA (838s Horizon Mining), 842s RTU/SCADA (842s Horizon Upgrading) | Brief SCADA Outages(15-30min) while RTU updates are completed. | |
| ATCO, ALTALINK | 04-May-26 11:00 | 05-May-26 17:00 | 30 Hours
Continuous |
953L (574s Nilrem - 755s Cordel) | Transmission line maintenance | |
| BCH | 05-May-26 09:00 | 06-May-26 17:00 | 1.33 Days
Continuous |
5L98 (BCH Nicola - BCH Vaseux Lake) | NIC 5CB51 rebuild | AB-BC |
| ATCO | 05-May-26 09:00 | 07-May-26 17:00 | 2.33 Days
Continuous |
972s 901 (972s Tinchebray) | Connect 900BS1 to new 907B Cutover 900SST1 Non Elec trips to new 900BS1 protection Cutover 901CT and 901 trips to new 900BS1 protection |
|
| ATCO | 05-May-26 12:00 | 08-May-26 12:00 | 3 Days
Continuous |
786s SVC (786s High Level) | SVC AIR COOLED MAINTENANCE @ HIGH LEVEL 786S | |
| ALTALINK | 06-May-26 08:00 | 06-May-26 16:00 | 8 Hours
Continuous |
132s 37 (132s Ware Junction), 132s 40 (132s Ware Junction), 275s 1852 (275s Jenner), 275s 1752 (275s Jenner), 951L (132s Ware Junction - 275s Jenner) | Center phase socket clevis that holds yolk plate has a keeper key backed out str 164 | |
| ALTALINK, Lethbridge | 06-May-26 08:00 | 06-May-26 16:00 | 8 Hours
Continuous |
734L (241s Uplands - 370s North Lethbridge) | 734L Open End Outage at 241S to Cutover CT Circuits for NEW DDR Installation & Test. |
|
| ENMAX | 06-May-26 08:00 | 07-May-26 16:00 | 1.33 Days
Continuous |
12B138-832L (SS-12), 832L (SS-10 - SS-12) | HV Breaker Maintenance | |
| ATCO, ALTALINK | 06-May-26 08:00 | 07-May-26 17:00 | 1.38 Days
Continuous |
948L (650s Hansman Lake - 863s Paintearth) | Transmission line maintenance | |
| ATCO, GREENGATEP | 07-May-26 09:00 | 19-May-26 17:00 | 12.33 Days
Continuous |
9L16 (755s Cordel - 972s Tinchebray) | GOI is required on 907B to isolate 908/909 bay and new 9L16. **THERE IS NO OUTAGE TO 9L16 UNTIL MAY 19, 2026 |
|
| ATCO | 07-May-26 10:01 | 10-May-26 17:30 | 3.31 Days
Continuous |
9L28 (937s AMR02 - 960s Birchwood Creek), 937s 06-TR-8001B (937s Amr02), 937s 9L28 (937s Amr02), 937s 06-DS-89T2 (937s Amr02) | transformer and disconnect maintenance | |
| ALTALINK, EPCOR | 07-May-26 14:00 | 14-May-26 17:00 | 7.13 Days
Continuous |
37s Protection & Control (37s North Calder), 37s 88 (37s North Calder), 37s 82 (37s North Calder), 920L (37s North Calder - 557s Castle Downs) | P&C upgrades (37s88, 37s82, PT21) | |
| ATCO | 08-May-26 09:00 | 09-May-26 17:00 | 1.33 Days
Continuous |
972s 240kV Bus 900BS2 (972s Tinchebray) | Connect new 909A to 900BS2 | |
| ENMAX | 09-May-26 07:00 | 09-May-26 12:00 | 5 Hours
Continuous |
771L (SS-47 - SS-162), 162B138-RB82 (SS-162), 47.1TR (SS-47), 47B138-771/1 (SS-47), 47B138-771 (SS-47), 47.2TR (SS-47), 162B138-RB81 (SS-162) | Summer Substation Washing | |
| ALTALINK | 09-May-26 07:00 | 13-May-26 18:00 | 4.46 Days
Continuous |
336s 612 (336s Fincastle), 368s 612 (368s Burdett), 612L (336s Fincastle - 368s Burdett) | Replacing cross arms and insulators on structures 174, 196, 197, 198, 203, 205, 206, 207, 208, 209, 210, 211, and 212 | |
| ENMAX, ALTALINK | 09-May-26 12:00 | 09-May-26 18:00 | 6 Hours
Continuous |
162B138-RB80 (SS-162), 162B138-RB81 (SS-162), 162.81L (391s Balzac - SS-162) | Summer Substation Washing | |
| ALTALINK, ENMAX | 09-May-26 12:00 | 09-May-26 18:00 | 6 Hours
Continuous |
391s 162.81 (391s Balzac), 162.81L (391s Balzac - SS-162) | Summer Substation Washing | |
| ENMAX, ALTALINK | 10-May-26 08:00 | 10-May-26 12:00 | 4 Hours
Continuous |
162B240-RB133 (SS-162), 918L (281s Johnson - SS-162), 162B240-RB132 (SS-162) | Summer Substation Washing | |
| ENMAX, ALTALINK | 10-May-26 08:30 | 10-May-26 12:00 | 3.5 Hours
Continuous |
918L (281s Johnson - SS-162) | Enmax Summer Substation Washing | |
| ENMAX, ALTALINK | 10-May-26 12:00 | 10-May-26 18:00 | 6 Hours
Continuous |
932L (74s Janet - SS-162), 162B240-RB136 (SS-162), 162B240-RB135 (SS-162) | Summer Substation Washing | |
| ENMAX, ALTALINK | 10-May-26 12:30 | 10-May-26 18:00 | 5.5 Hours
Continuous |
932L (74s Janet - SS-162) | Enmax Summer Substation Washing | |
| EPCOR | 11-May-26 07:00 | 11-May-26 13:00 | 6 Hours
Continuous |
987s GT3 (987s Clover Bar) | Cloverbar: G3 Outage, CPC Request | |
| ATCO, ALTALINK | 11-May-26 07:00 | 14-May-26 18:00 | 3.46 Days
Continuous |
7LA114 (658s Chard - 7L114 tap), 7L114 (72s Leismer - 7LA114 tap), 7L114 (907s Waddell - 7LA114 tap), 907s Waddell | AltaLink outage on 72sT2 causing an outage to 7L114 at 907S | |
| ALTALINK | 11-May-26 07:00 | 14-May-26 18:00 | 3.46 Days
Continuous |
72s T2 (72s Leismer), 72s 1052 (72s Leismer) | Transformer maintenance, doble, install Coresense & Qualitrol. 1st trips and breaker maintenance on 72s1052. | |
| EPCOR | 11-May-26 07:00 | 17-May-26 17:00 | 6.42 Days
Continuous |
814s T2 (814s Bellamy), BR722 (Rossdale), 814s B2402 (814s Bellamy), 814s B2406 (814s Bellamy) | Bellamy: TX2 Zone Doble and BR722 Breaker Maintenance/Doble, and BDS17 Disconnect Maintenance | |
| EPCOR | 11-May-26 07:00 | 22-May-26 17:00 | 11.42 Days
Continuous |
52s T1 (52s East Industrial) | East Industrial: TX1 DGA Monitor Replacement | |
| ENMAX | 11-May-26 08:00 | 12-May-26 16:00 | 1.33 Days
Continuous |
12B138-833L (SS-12), 833L (SS-2 - SS-12) | HV Breaker Maintenance | |
| ALTALINK, ATCO | 11-May-26 08:00 | 14-May-26 16:00 | 3.33 Days
Continuous |
72s 1052 (72s Leismer), 7L114 (72s Leismer - 7LA114 tap) | Customer maintenance | |
| ATCO, ALBIAN | 11-May-26 09:00 | 12-May-26 15:00 | 30 Hours
Continuous |
920s 901T (920s Jackpine) | Isolation of 901T for CNRL to troubleshoot problems on their system | |
| ATCO | 11-May-26 13:00 | 14-May-26 13:00 | 3 Days
Continuous |
827s SVC (827s Cranberry Lake) | SVC AIR COOLED MAINTENANCE SVC AUX TRIP RELAY TESTING SVC MICROPROCESSOR RELAY TESTING SPR TESTING - TRANSFORMER 703T TRIP COIL TESTING 401, 703 |
|
| ATCO, ALTALINK, ENBRIDGE | 11-May-26 13:00 | 14-May-26 13:00 | 3 Days
Continuous |
7L114 (72s Leismer - 7LA114 tap), 7LA114 (658s Chard - 7L114 tap), 7L114 (907s Waddell - 7LA114 tap) | Planned inspection on 7L114/7LA114 to take place during the AltaLink outage to their T2 transformer at 72S | |
| ALTALINK | 11-May-26 13:30 | 14-May-26 17:00 | 3.15 Days
Continuous |
38s 7452 (38s East Edmonton) | 240kV breaker maintenance | |
| ATCO, ALTALINK | 11-May-26 18:00 | 06-Jun-26 16:30 | 25.94 Days
Continuous |
962L (87s Gaetz - 972s Tinchebray) | Switch needs to remain open until ATCO is ready @ 972s for energization | |
| ATCO, ALTALINK | 11-May-26 18:00 | 06-Jun-26 16:30 | 25.94 Days
Continuous |
986L (87s Gaetz - 972s Tinchebray) | Switch needs to remain open until ATCO is ready @ 972s for energization | |
| ALTALINK | 12-May-26 07:15 | 12-May-26 17:45 | 10.5 Hours
Continuous |
1206L (12s Heartland - 89s Ellerslie) | Transmission line maintenance | |
| ALTALINK | 12-May-26 08:00 | 12-May-26 17:00 | 9 Hours
Continuous |
77s 26 (77s Sagitawah) | 240kV breaker maintenance | |
| ALTALINK, ICPCL | 12-May-26 08:00 | 13-May-26 17:00 | 1.38 Days
Continuous |
225s 225E (225s Magrath), 67s 225 (67s Stirling), 225AL (313s Raymond Reservoir - 225L tap), 225L (225s Magrath - 225AL tap), 225L (67s Stirling - 225AL tap) | 93, 149 replace arms and insulators | |
| Syncrude | 12-May-26 08:00 | 23-May-26 16:00 | 11.33 Days
Continuous |
211 (Aurora), 213 (Aurora), 212B (Aurora), 213A (Aurora), 89-215 (Aurora) | Zone 5 6yr PM | |
| ALTALINK | 13-May-26 08:00 | 13-May-26 17:00 | 9 Hours
Continuous |
77s 40 (77s Sagitawah) | 240kV breaker maintenance | |
| ATCO, ALBIAN | 13-May-26 09:00 | 14-May-26 15:00 | 30 Hours
Continuous |
920s 902T (920s Jackpine) | Isolation of 902T for CNRL to troubleshoot problems on their system | |
| ALTALINK | 14-May-26 08:00 | 14-May-26 17:00 | 9 Hours
Continuous |
321s 880 (321s Al Rothbauer), 523s 880 (523s Bullshead), 880L (321s Al Rothbauer - 523s Bullshead) | Re-installing damper on structure 4
Re-tying OHSW's on structure 8 |
|
| ATCO, ALBIAN, CNRL | 14-May-26 08:00 | 29-May-26 16:00 | 15.33 Days
Continuous |
919s 908 (919s Hartley), 847s 902T (847s Muskeg River) | CNRL Request COG to open 908 breaker and 902TD in the Hartley 919S substation at CNRL Albian Sands. |
|
| SUNCOR | 18-May-26 08:00 | 24-May-26 20:00 | 6.5 Days
Continuous |
29PL9-12 (29EDD-34 - 29EDD-65) | 29EDD34;29PL9-12 SYSTEM;PM 5y,10y |
|
| EPCOR | 19-May-26 07:00 | 19-May-26 17:00 | 10 Hours
Continuous |
T2 (Poundmaker), PM2405 (Poundmaker), PM2401 (Poundmaker) | Poundmaker: TX2 Zone, PMAB2 Repair | |
| EPCOR | 19-May-26 07:00 | 22-May-26 17:00 | 3.42 Days
Continuous |
557s T1 (557s Castle Downs) | Castledowns: TX1 Tapchanger Maintenance/Testing and Conservator Pipe Leak Repair | |
| EPCOR | 19-May-26 07:00 | 01-Jun-26 07:00 | 13 Days
Continuous |
T1 (Rossdale), R721 (Rossdale), RR723 (Rossdale), BR722 (Rossdale), 814s T2 (814s Bellamy) | Rossdale: TX1 LCR Demo | |
| ALTALINK | 19-May-26 08:00 | 22-May-26 10:05 | 3.09 Days
Continuous |
254s 172E (254s Coaldale), 83s 172W (83s Taber), 172L (254s Coaldale - 172EL tap), 172L (83s Taber - 172EL tap) | 172L outage to facilitate the opening of 172EL1 which is required to be opened de-energized. | |
| ALTALINK, ACCIONA | 19-May-26 08:30 | 22-May-26 17:00 | 3.35 Days
Continuous |
172EL (139s Hillridge - 172L tap) | Site coming offline to perform minor preventative maintenance. This includes SAB-1 and all downstream components (52-T1, 52-F1, 52-F2, 52-F3) | |
| ATCO | 19-May-26 09:00 | 19-May-26 17:00 | 8 Hours
Continuous |
9L16 (755s Cordel - 972s Tinchebray), 755s 904 (755s Cordel), 755s 905 (755s Cordel), 972s 903 (972s Tinchebray) | Disconnect 9L16 from existing A-frame deadend and 9L16D2 (to be renamed 9L86D1) Restore bus leave renamed 9L86D1 open for future line connection. |
|
| BCH, BPA | 19-May-26 09:00 | 20-May-26 17:00 | 1.33 Days
Continuous |
5L52 (BPA Custer - BCH Ingledow) | Glass replacement | AB-BC |
| BCH, BPA | 19-May-26 09:00 | 23-May-26 17:00 | 4.33 Days
Continuous |
5L52 (BPA Custer - BCH Ingledow) | doble and inspection 5CB5 | AB-BC |
| ATCO | 19-May-26 09:00 | 29-May-26 17:00 | 10.33 Days
Continuous |
9L16 (755s Cordel - 972s Tinchebray) | Disconnect 9L16 from existing A-frame deadend and 9L16D2 (to be renamed 9L86D1) Restore bus leave renamed 9L86D1 open for future line connection. |
|
| ALTALINK | 19-May-26 13:00 | 21-May-26 16:00 | 2.13 Days
Continuous |
525s 851X (525s Carseland), 851L (253s Blackie - 525s Carseland) | 525s851X PRC5 Breaker maintenance. | |
| ALTALINK | 19-May-26 23:00 | 21-May-26 07:00 | 1.33 Days
Continuous |
250p 1 (250p Bighorn Plant) | maintenance | |
| ALTALINK | 20-May-26 07:00 | 21-May-26 07:00 | 24 Hours
Continuous |
250p 2 (250p Bighorn Plant) | maintenance | |
| BCH | 20-May-26 08:00 | 21-May-26 16:00 | 1.33 Days
Continuous |
T3 (BCH Natal) | inspection/doble | AB-BC |
| BCH | 20-May-26 08:00 | 21-May-26 16:00 | 1.33 Days
Continuous |
2L113 (BCH Cranbrook - BCH Natal) | install marker balls | AB-BC |
| ALTALINK, ALPAC | 20-May-26 08:30 | 20-May-26 18:00 | 9.5 Hours
Continuous |
796L (282s Grassland - 796AL tap) | Customer maintenance @ 282s | |
| ALTALINK | 20-May-26 09:00 | 28-May-26 17:00 | 8.33 Days
Continuous |
275s T2 (275s Jenner) | 275sT2 Oil Reclaim and Maint. Replace switches 275s45, 275s49, 275s47. Replace 25kV Post Insulators. 275s2323, 275s167W | |
| ATCO, CNRL | 22-May-26 11:01 | 22-May-26 12:59 | 118 Mins
Continuous |
9L32 (941s Bitumount - 2005s Secord), 9L32 (838s Horizon Mining - 941s Bitumount) | MUST TAKE 9L32 OOS for telecom worl 1-00509997 and 1-00510463 |
|
| ALTALINK, ACCIONA | 22-May-26 16:05 | 22-May-26 17:35 | 90 Mins
Continuous |
254s 172E (254s Coaldale), 83s 172W (83s Taber), 172EL (139s Hillridge - 172L tap), 172L (254s Coaldale - 172EL tap), 172L (83s Taber - 172EL tap) | 172L out of service to close 172EL1 | |
| ENMAX, ALTALINK | 23-May-26 08:00 | 23-May-26 11:00 | 3 Hours
Continuous |
5s T1 (5s East Calgary) | Summer Substation Washing | |
| ENMAX, ALTALINK | 23-May-26 08:00 | 23-May-26 12:00 | 4 Hours
Continuous |
5s T1 (5s East Calgary) | Summer Substation Washing | |
| ALTALINK, Lethbridge | 23-May-26 08:00 | 24-May-26 17:00 | 1.38 Days
Continuous |
207L (111s Coalbanks - 370s North Lethbridge) | 207L Hardware tightening on structure 8 and 11 | |
| ATCO | 23-May-26 10:00 | 26-May-26 10:00 | 3 Days
Continuous |
9L19 (937s AMR02 - 960s Birchwood Creek) | Customer request - Disconnect Switch Maintenance | |
| ENMAX, ALTALINK | 23-May-26 11:00 | 23-May-26 13:00 | 2 Hours
Continuous |
5s T2 (5s East Calgary) | Summer Substation Washing | |
| ENMAX, ALTALINK | 23-May-26 11:00 | 23-May-26 14:00 | 3 Hours
Continuous |
5s T2 (5s East Calgary) | Summer Substation Washing | |
| Syncrude | 24-May-26 08:00 | 07-Jun-26 16:00 | 14.33 Days
Continuous |
334 (Syncrude Mildred Lake), 335 (Syncrude Mildred Lake), 3235 (Syncrude Mildred Lake), Mildred T3 (Syncrude Mildred Lake), 234 (Syncrude Mildred Lake), 235 (Syncrude Mildred Lake), 2235 (Syncrude Mildred Lake), Mildred T2 (Syncrude Mildred Lake), Mildred T1 (Syncrude Mildred Lake), 135 (Syncrude Mildred Lake), 134 (Syncrude Mildred Lake), 1335 (Syncrude Mildred Lake), Mildred T16 (Syncrude Mildred Lake), 1635 (Syncrude Mildred Lake), 1634 (Syncrude Mildred Lake), 1434 (Syncrude Mildred Lake), 1435 (Syncrude Mildred Lake), Mildred T14 (Syncrude Mildred Lake), 1934 (Syncrude Mildred Lake), 1935 (Syncrude Mildred Lake), Mildred T19 (Syncrude Mildred Lake), ML1 (D05 - Syncrude Mildred Lake), 914 (Syncrude Mildred Lake), 915 (Syncrude Mildred Lake), 916 (Syncrude Mildred Lake), 814 (Syncrude Mildred Lake), 815 (Syncrude Mildred Lake), 816 (Syncrude Mildred Lake), 1224A (Syncrude Mildred Lake), 1224B (Syncrude Mildred Lake), 1225 (Syncrude Mildred Lake), 19215 (Syncrude Mildred Lake), D05 76 (D05), D05 75B (D05), D05 76A (D05) | SCL - Plant 31 6-Year 72kV "B" Bus PM During the 72kV "B" Bus PM at Mildred Lake Plant 31, |
|
| ALTALINK, DOW | 25-May-26 07:00 | 26-May-26 18:00 | 1.46 Days
Continuous |
166s 787W (166s Dow Chemical Fort Saskatchewan), 71s 452 (71s Lamoureux), 71s 352 (71s Lamoureux), 906s 787AE (906s Ross Creek), 787AL (906s Ross Creek - 787L tap), 787L (166s Dow Chemical Fort Saskatchewan - 787AL tap), 787L (71s Lamoureux - 787AL tap) | Replace Structure 787L30, 31,32 and D78269 with new configuration where proposed self-supporting 787L31 will be located in proximity to salvaged D782L69 and will support the OPGW | |
| EPCOR | 25-May-26 07:00 | 27-May-26 17:00 | 2.42 Days
Continuous |
816s P2401 (816s Petrolia) | Petrolia: P2401 CT Doble | |
| EPCOR | 25-May-26 07:00 | 05-Jun-26 17:00 | 11.42 Days
Continuous |
987s T4 (987s Clover Bar), 987s C2408 (987s Clover Bar) | Cloverbar: TX4 DGA Monitor Replacement and Relay Maintenance | |
| ATCO | 25-May-26 09:00 | 27-May-26 17:30 | 2.35 Days
Continuous |
2075s 911 (2075s Newell) | BREAKER SF6 3AP4FI MAINTENANCE | |
| Lethbridge | 25-May-26 10:00 | 25-May-26 14:00 | 4 Hours
Continuous |
181s 172L (181s Chinook) | 181s 172L Open End Outage to Cutover CT Circuits for NEW DDR Installation & Test "Initiate" Output circuit. | |
| ATCO | 25-May-26 10:00 | 25-May-26 16:00 | 6 Hours
Continuous |
898s 904 (898s Heart Lake) | PRC-005 TRIP COIL TESTING, B PHASE MOTOR CCT DC FAIL TROUBLESHOOTING/ REPAIR |
|
| ATCO | 25-May-26 10:00 | 26-May-26 16:00 | 30 Hours
Continuous |
715s 701 (715s Leming Lake), 7L583 (715s Leming Lake - 970s Bourque) | PRC-005 Trip Coil Testing, 701CT Inspection/ Testing | |
| ALTALINK | 25-May-26 13:30 | 28-May-26 17:00 | 3.15 Days
Continuous |
77s T1 (77s Sagitawah) | PRC5 Transformer Maintenance, Doble, Leak repair & IDD replacement | |
| ALTALINK | 25-May-26 14:00 | 06-Jun-26 17:00 | 12.13 Days
Continuous |
63s 352 (63s Red Deer), 925L (63s Red Deer - 74s Janet) | 63s352 Breaker Replacement to SF6 breaker. | |
| ATCO | 26-May-26 08:00 | 26-May-26 09:59 | 119 Mins
Continuous |
898s 901 (898s Heart Lake) | PRC-005 TRIP COIL TESTING |
|
| Lethbridge | 26-May-26 09:00 | 26-May-26 13:00 | 4 Hours
Continuous |
181s 463L (181s Chinook) | 181s 463L Open End Outage to Cutover CT Circuits for NEW DDR Installation & to Test "Initiate" Output circuits from required relays to DDR. | |
| ATCO | 26-May-26 10:00 | 26-May-26 11:59 | 119 Mins
Continuous |
898s 902 (898s Heart Lake) | PRC-005 TRIP COIL TESTING |
|
| ATCO | 26-May-26 12:00 | 26-May-26 13:59 | 119 Mins
Continuous |
898s 903 (898s Heart Lake) | PRC-005 TRIP COIL TESTING |
|
| ATCO | 26-May-26 13:00 | 29-May-26 13:00 | 3 Days
Continuous |
9L28 (937s AMR02 - 960s Birchwood Creek) | Customer request - Disconnect Switch Maintenance | |
| ATCO | 26-May-26 14:00 | 26-May-26 15:59 | 119 Mins
Continuous |
898s 905 (898s Heart Lake) | PRC-005 TRIP COIL TESTING |
|
| ATCO | 27-May-26 08:00 | 27-May-26 09:59 | 119 Mins
Continuous |
898s 906 (898s Heart Lake) | PRC-005 TRIP COIL TESTING |
|
| ENMAX, ALTALINK | 27-May-26 08:00 | 28-May-26 16:00 | 1.33 Days
Continuous |
24.83L (74s Janet - SS-24) | HV Breaker Maintenance. 24B138-24.83 Breaker Racking Support Install | |
| Syncrude | 27-May-26 08:00 | 13-Jun-26 16:00 | 17.33 Days
Continuous |
11A (Aurora), 21A (Aurora), 31A (Aurora), 89-210 (Aurora), 89-51 (Aurora), T1 (Aurora), 211A (Aurora), 221A (Aurora), 260kV Bus 1 (Aurora), 72 kV Bus 1 (Aurora) | 6yr PM | |
| SUNCOR | 27-May-26 09:00 | 01-Jun-26 20:00 | 5.46 Days
Continuous |
29EDD-1 29EDD1S11 (29EDD-1 Millennium), 29EDD-1 29EDD1s552 (29EDD-1 Millennium), 29EDD-1 29EDD1s652 (29EDD-1 Millennium), 29EDD-3 29PT-6 (29EDD-3) | 29EDD-1 29EDD1S11 Repair Broken Switch 29EDD1;29CVT-4 SYSTEM Protection testing, Breaker trip testing | |
| ATCO | 27-May-26 10:00 | 27-May-26 11:59 | 119 Mins
Continuous |
898s 908 (898s Heart Lake) | PRC-005 TRIP COIL TESTING |
|
| ATCO | 27-May-26 10:00 | 28-May-26 16:00 | 30 Hours
Continuous |
715s 702 (715s Leming Lake), 7L91 (715s Leming Lake - 826s Marguerite Lake) | PRC-005 Trip Coil Testing, 702CT Inspection/ Testing | |
| ATCO | 27-May-26 11:00 | 29-May-26 11:00 | 2 Days
Continuous |
740s 705 (740s H.R. Milner), 7L80 (740s H.R. Milner - 857s Kakwa Ridge) | PRC-005 - MICROPROCESSOR RELAY TESTING TCM Program. RTXP Test Switch Mitigation and Replacement Both RAS-A and RAS-B 7L80 will also need be OOS for the RTXP work on 21A and 21B 7L80 |
|
| ATCO | 27-May-26 12:00 | 27-May-26 13:59 | 119 Mins
Continuous |
898s 909 (898s Heart Lake) | PRC-005 TRIP COIL TESTING |
|
| EPCOR | 28-May-26 07:00 | 30-May-26 17:00 | 2.42 Days
Continuous |
816s P2405 (816s Petrolia) | Petrolia: P2405 CT Doble | |
| ATCO, ALTALINK | 28-May-26 11:01 | 28-May-26 13:00 | 119 Mins
Continuous |
898s 708 (898s Heart Lake), 788L (898s Heart Lake - 788AL tap) | PRC-005 TRIP COIL TESTING | |
| ATCO | 30-May-26 09:00 | 13-Jun-26 17:00 | 14.33 Days
Continuous |
972s 905B (972s Tinchebray), 972s 906A (972s Tinchebray) | Connect new 9L62 to 972S and prepare to energize. String Conductors/OPGW 9L62 from Str #3 to substation A-frame deadends and connect to 9L62D1, coordinate with AML conductor jumpers and OPGW termination at the TFO boundary 9L86 Str 409 |
|
| EPCOR | 01-Jun-26 07:00 | 02-Jun-26 17:00 | 1.42 Days
Continuous |
T1 (EP Riverview) | Riverview: TX1 Secondary Cabinet Venting Install | |
| EPCOR | 01-Jun-26 07:00 | 03-Jun-26 17:00 | 2.42 Days
Continuous |
816s P2406 (816s Petrolia) | Petrolia: P2406 CT Doble | |
| EPCOR | 01-Jun-26 07:00 | 07-Jun-26 17:00 | 6.42 Days
Continuous |
T4 (Poundmaker), PM721 (Poundmaker), PM2402 (Poundmaker), PM2403 (Poundmaker) | Poundmaker: TX4 Doble and PMAB4/PMDS4/PMDS5 Disconnect Maintenance | |
| EPCOR | 01-Jun-26 07:00 | 10-Jul-26 17:00 | 39.42 Days
Continuous |
EP 805s J2403 (EP 805s Jasper) | Jasper: J2403 Replacement LCR | |
| SUNCOR | 01-Jun-26 08:00 | 05-Jun-26 20:00 | 4.5 Days
Continuous |
29EDD-94 29PP-97 260kV Bus (29EDD-94 Voyageur) | 29EDD94, 29PT-412B Oil Leak (29PP-97 260KV outage) - Leak repair and top up (9001051293) TDEC | |
| ALTALINK | 01-Jun-26 08:00 | 11-Jun-26 15:00 | 10.29 Days
Continuous |
19s 905 (19s Wabamun), 37s Protection & Control (37s North Calder), 37s 82 (37s North Calder), 37s 76 (37s North Calder), 905L (19s Wabamun - 37s North Calder) | Protection upgrade | |
| ATCO | 01-Jun-26 10:00 | 02-Jun-26 16:00 | 30 Hours
Continuous |
715s 703 (715s Leming Lake), 7L66 (715s Leming Lake - 717s Ethel Lake) | PRC-005 Trip Coil Testing, 703CT Inspection/ Testing | |
| ALTALINK | 01-Jun-26 10:30 | 04-Jun-26 17:00 | 3.27 Days
Continuous |
320p 91 (320p Keephills), 320p 1352 (320p Keephills), 320p 752 (320p Keephills), 320p 352 (320p Keephills), 320p 2152 (320p Keephills), 320p T1 (320p Keephills), 320p 240kV Bus B (320p Keephills), 1045AL (320p Keephills - 1045L tap) | 320p91 Breaker Maintenance and 320p213 Switch repair | |
| ALTALINK | 02-Jun-26 07:00 | 03-Jun-26 17:00 | 1.42 Days
Continuous |
944L (132s Ware Junction - 275s Jenner) | Telecom SIA specifies that a 944L and 944AL outage is required for dish realignment. Both A and B protections will be out of service. 1080s Will be offline.
|
|
| ALTALINK, RESC | 02-Jun-26 08:00 | 04-Jun-26 18:00 | 2.42 Days
Continuous |
1012L (326s Murray Lake - 516s Forty Mile) | Programmed maintenance.
|
|
| ALTALINK | 03-Jun-26 09:00 | 04-Jun-26 16:30 | 31.5 Hours
Continuous |
852s T1 (852s Round Hill) | TX Maintenance, Doble and IDD troubleshooting | |
| ENMAX, ALTALINK | 05-Jun-26 08:00 | 05-Jun-26 18:00 | 10 Hours
Continuous |
693L (42s Sarcee - SS-10), 10.2TR (SS-10), 10B138-693 (SS-10) | Power Factor Test - 10PT138-693, 10PT138-Z31. Breaker Trip Circuit Test - 10B138-693 | |
| EPCOR | 05-Jun-26 17:00 | 19-Jun-26 17:00 | 14 Days
Continuous |
EP 805s J2404 (EP 805s Jasper), EP 805s J2403 (EP 805s Jasper), EP 805s J2408 (EP 805s Jasper), 805s C1 (805s Jasper), 1044L (EP 805s Jasper - 816s Petrolia) | 1044L/Jasper: J2403 Replacement LCR | |
| SUNCOR | 06-Jun-26 08:00 | 09-Jun-26 20:00 | 3.5 Days
Continuous |
29EDD-1 29EDD1s952 (29EDD-1 Millennium) | 29EDD1s952 - Faulty SF6 Sensors - 300677553 | |
| ALTALINK, BCH | 07-Jun-26 08:00 | 07-Jun-26 17:00 | 9 Hours
Continuous |
786L (799s Coleman - BCH Natal) | Repairing woodpecker damage on structures 94, 112 and 118
Replacing damaged insulator on structure 121 |
AB-BC |
| EPCOR, ALTALINK | 08-Jun-26 07:00 | 14-Jun-26 17:00 | 6.42 Days
Continuous |
657s T3 (657s Summerside), 657s SU2405 (657s Summerside), 657s SU2401 (657s Summerside) | Summerside: TX3 Doble and SUAB3/SUDS2/SUDS12 Disconnect Maintenance | |
| ENMAX | 08-Jun-26 08:00 | 08-Jun-26 12:00 | 4 Hours
Continuous |
162B240-RB132 (SS-162) | HV Breaker SF6 Gas Sample | |
| ATCO | 08-Jun-26 09:30 | 10-Jun-26 17:30 | 2.33 Days
Continuous |
801s 909 (801s Anderson) | BREAKER MIN OIL HLR COMPLETE TESTING | |
| ATCO | 08-Jun-26 10:00 | 09-Jun-26 16:00 | 30 Hours
Continuous |
849s 901 (849s Joslyn Creek) | breaker maintenance, PRC-005 trip coil testing | |
| ENMAX | 08-Jun-26 12:00 | 08-Jun-26 16:00 | 4 Hours
Continuous |
162B240-RB135 (SS-162) | HV Breaker SF6 Gas Sample | |
| ALTALINK | 08-Jun-26 14:00 | 11-Jun-26 16:00 | 3.08 Days
Continuous |
17s 85 (17s Benalto), 17s T2 (17s Benalto) | 17s85 CT Replacement | |
| ALTALINK, ATCO | 08-Jun-26 16:30 | 29-Jun-26 18:30 | 21.08 Days
Continuous |
87s 1252 (87s Gaetz), 87s 1652 (87s Gaetz), 87s T2 (87s Gaetz), 87s 240kV East Bus (87s Gaetz), 87s 1552 (87s Gaetz), 87s 1952 (87s Gaetz), 962L (87s Gaetz - 972s Tinchebray), 986L (87s Gaetz - 972s Tinchebray) | Completing all telecom work & protection testing with ATCO | |
| ENMAX | 09-Jun-26 08:00 | 09-Jun-26 12:00 | 4 Hours
Continuous |
162B240-RB136 (SS-162) | HV Breaker SF6 Gas Sample | |
| ALTALINK | 09-Jun-26 09:15 | 09-Jun-26 12:30 | 3.25 Hours
Continuous |
852s 152 (852s Round Hill) | Breaker maintenance and first trip | |
| ALTALINK | 09-Jun-26 13:15 | 09-Jun-26 16:30 | 3.25 Hours
Continuous |
852s 252 (852s Round Hill) | Breaker maintenance, heater replacement & first trip | |
| SUNCOR | 10-Jun-26 08:00 | 13-Jun-26 20:00 | 3.5 Days
Continuous |
29EDD-1 29EDD1s852 (29EDD-1 Millennium) | 29EDD1S852 Replace Densimeter | |
| ALTALINK | 10-Jun-26 09:00 | 10-Jun-26 16:00 | 7 Hours
Continuous |
32s 22 (32s Barrier) | 32s22 LTB PRC5 minor maintenance. | |
| BCH | 10-Jun-26 09:00 | 19-Jun-26 17:00 | 9.33 Days
Continuous |
2L294 (BCH A. A. Lambert - BCH Cranbrook), T3 (BCH Cranbrook), T7 (BCH Cranbrook) | insulator replacement | AB-BC |
| ATCO | 10-Jun-26 10:00 | 11-Jun-26 16:00 | 30 Hours
Continuous |
849s 904 (849s Joslyn Creek) | breaker maintenance, PRC-005 trip coil testing | |
| ALTALINK | 10-Jun-26 23:30 | 11-Jun-26 02:30 | 3 Hours
Continuous |
62s 1 (62s Brazeau Plant) | maintenence | |
| ALTALINK | 11-Jun-26 03:30 | 11-Jun-26 06:30 | 3 Hours
Continuous |
62s 2 (62s Brazeau Plant) | maintenence | |
| ALTALINK | 11-Jun-26 10:00 | 11-Jun-26 12:00 | 2 Hours
Continuous |
37s 88 (37s North Calder) | Breaker fail trip testing | |
| ALTALINK | 11-Jun-26 10:00 | 12-Jun-26 07:00 | 21 Hours
Continuous |
534s 138kV Bus 1 (534s Eckville), 757L (17s Benalto - 758L tap), 757L (297s Rimbey - 758L tap), 297s 757 (297s Rimbey), 297s T1 (297s Rimbey), 297s T2 (297s Rimbey), 534s 758 (534s Eckville), 534s T1 (534s Eckville), 297s 138kV Bus 1 (297s Rimbey), 17s 757N (17s Benalto), 297s 138kV Bus 2 (297s Rimbey) | 757L199 Replace crossarm and insulators.
17s Dead end insulator replacement. Rising Edge Jeremy Lesoway. |
|
| ALTALINK | 11-Jun-26 13:00 | 11-Jun-26 15:00 | 2 Hours
Continuous |
37s 81 (37s North Calder) | Breaker fail trip testing | |
| SUNCOR | 14-Jun-26 08:00 | 17-Jun-26 20:00 | 3.5 Days
Continuous |
29EDD-1 29EDD1s1052 (29EDD-1 Millennium) | 29EDD1S1052 Densimeter Replacement - 300347749 | |
| ATCO | 14-Jun-26 09:00 | 25-Jun-26 17:00 | 11.33 Days
Continuous |
9L62 (87s Gaetz - 972s Tinchebray) | Work on parallel line 9L86 | |
| EPCOR | 15-Jun-26 07:00 | 19-Jun-26 17:00 | 4.42 Days
Continuous |
987s GT2 (987s Clover Bar) | Cloverbar: | |
| EPCOR, ALTALINK | 15-Jun-26 07:00 | 19-Jun-26 17:00 | 4.42 Days
Continuous |
1058L (657s Summerside - EP 803s Lambton), EP 803s L2404 (EP 803s Lambton), EP 803s L2403 (EP 803s Lambton) | 1058L: Aerial Washing Program | |
| ALTALINK | 15-Jun-26 07:30 | 18-Jun-26 18:00 | 3.44 Days
Continuous |
510s 2652 (510s Sunnybrook), 510s 2752 (510s Sunnybrook), AML 511s 4852 (AML 511s Crossings), AML 511s 4952 (AML 511s Crossings), 1325L (510s Sunnybrook - AML 511s Crossings) | South Lines Crew will be doing component replacement on 1325L (STR 501-542) HVDC Maint. | |
| ALTALINK | 15-Jun-26 08:00 | 19-Jun-26 16:00 | 4.33 Days
Continuous |
266s 252 (266s SC1) | 2665sFSC2 Unbalance Alarm, Series cap door bolts, annual maintenance. | |
| ALTALINK, EPCOR | 15-Jun-26 09:00 | 15-Jun-26 16:00 | 7 Hours
Continuous |
930L (37s North Calder - Poundmaker), 37s 76 (37s North Calder), 37s 81 (37s North Calder), 37s 72 (37s North Calder) | 930L MOD (37s72) supervisory cutovers and function testing | |
| ATCO | 15-Jun-26 09:00 | 18-Jun-26 16:00 | 3.29 Days
Continuous |
7L03 (731s Elmworth - 7L09 tap) | TCM pole changes from Test and treat. | |
| ATCO, CNRL | 15-Jun-26 09:00 | 29-Jun-26 10:00 | 14.04 Days
Continuous |
859s 701TD (859s Primrose), 859s 701 (859s Primrose), 859s 704 (859s Primrose), 859s 701T (859s Primrose) | maintenance | |
| ALTALINK, EPCOR | 15-Jun-26 09:30 | 19-Jun-26 17:00 | 4.31 Days
Continuous |
915L (38s East Edmonton - 987s Clover Bar), 987s C2403 (987s Clover Bar), 987s C2405 (987s Clover Bar) | 915L/Cloverbar: CT/CVT/SA Doble and CDS35/CDS36/CDS7 Disconnect Maintenance and Relay Maintenance | |
| ALTALINK, EPCOR | 15-Jun-26 09:30 | 19-Jun-26 17:00 | 4.31 Days
Continuous |
915L (38s East Edmonton - 987s Clover Bar) | 915L/Cloverbar: CT/CVT/SA Doble and CDS35/CDS36/CDS7 Disconnect Maintenance and Relay Maintenance | |
| ALTALINK, EPCOR | 15-Jun-26 09:30 | 20-Jun-26 17:00 | 5.31 Days
Continuous |
1139L (367s Harry Smith - EP Riverview), RW2405 (EP Riverview), RW2403 (EP Riverview) | Riverview: 1139L Zone Doble and RWDS6/RWDS9/RWSA12 Disconnect Maintenance and RW2403/RW2405 (SF6) Breaker Maintenance | |
| ALTALINK, EPCOR | 15-Jun-26 09:30 | 20-Jun-26 17:00 | 5.31 Days
Continuous |
1139L (367s Harry Smith - EP Riverview) | Riverview: 1139L Zone Doble and RWDS6/RWDS9/RWSA12 Disconnect Maintenance and RW2403/RW2405 (SF6) Breaker Maintenance | |
| ATCO | 15-Jun-26 10:00 | 15-Jun-26 11:59 | 119 Mins
Continuous |
849s 902 (849s Joslyn Creek) | PRC-005 trip coil testing | |
| ATCO | 15-Jun-26 10:00 | 17-Jun-26 12:00 | 2.08 Days
Continuous |
2029s ACF12 (2029s Heathfield), 2029s 1219 (2029s Heathfield) | FILTER BANK AC MAINTENANCE @ HEATHFIELD 2029S ACF12 PRC-005 - TRIP COIL TESTING - BREAKER 1219 @ 2029S |
|
| ALTALINK | 15-Jun-26 11:30 | 19-Jun-26 16:30 | 4.21 Days
Continuous |
163s 1752 (163s Amoco Empress), 163s Protection & Control (163s Amoco Empress), 163s 1552 (163s Amoco Empress), 1002L (163s Amoco Empress - 275s Jenner) | Replace 163s1752 Breaker CT at 163s Amoco | |
| ATCO | 15-Jun-26 12:00 | 15-Jun-26 13:59 | 119 Mins
Continuous |
849s 903 (849s Joslyn Creek) | PRC-005 trip coil testing | |
| ATCO | 15-Jun-26 14:00 | 15-Jun-26 15:59 | 119 Mins
Continuous |
849s 905 (849s Joslyn Creek) | PRC-005 trip coil testing | |
| ATCO | 16-Jun-26 09:00 | 25-Jun-26 17:00 | 9.33 Days
Continuous |
972s 240kV Bus 900BS2 (972s Tinchebray) | Connect new 9L86 to 972S and prepare to energize. String Conductors/OPGW 9L86 from Str #3 to substation A-frame deadends and connect to 9L86D1, coordinate with AML conductor jumpers and OPGW termination at the TFO boundary 9L86 Str 409 Complete protection commissioning |
|
| ATCO | 16-Jun-26 10:00 | 16-Jun-26 11:59 | 119 Mins
Continuous |
849s 906 (849s Joslyn Creek) | PRC-005 trip coil testing | |
| ATCO | 16-Jun-26 12:00 | 16-Jun-26 13:59 | 119 Mins
Continuous |
849s 907 (849s Joslyn Creek) | PRC-005 trip coil testing | |
| EPCOR | 17-Jun-26 07:00 | 24-Jun-26 17:00 | 7.42 Days
Continuous |
987s GT3 (987s Clover Bar) | maintenance | |
| ATCO | 17-Jun-26 13:00 | 19-Jun-26 17:30 | 2.19 Days
Continuous |
2029s ACF14 (2029s Heathfield), 2029s 1221 (2029s Heathfield) | FILTER BANK AC MAINTENANCE @ HEATHFIELD 2029S ACF12 PRC-005 - TRIP COIL TESTING - BREAKER 1219 @ 2029S |
|
| ENMAX, ALTALINK | 19-Jun-26 08:00 | 19-Jun-26 16:00 | 8 Hours
Continuous |
693L (42s Sarcee - SS-10), 10B138-693 (SS-10) | HV Breaker SF6 Gas Sample - 10B138-693 | |
| EPCOR | 22-Jun-26 07:00 | 25-Jun-26 17:00 | 3.42 Days
Continuous |
987s GT1 (987s Clover Bar) | maintenance | |
| SUNCOR | 22-Jun-26 08:00 | 28-Jun-26 20:00 | 6.5 Days
Continuous |
29PL9-17 (29EDD-1 Millennium - 29EDD-94 Voyageur) | 29EDD1;29PT419 / 29PL9-17 SYSTEM;PM 5y,10y; 29PL9-17 Powerline & OHSW repairs |
|
| EPCOR, ALTALINK | 22-Jun-26 09:00 | 28-Jun-26 17:00 | 6.33 Days
Continuous |
52s T1 (52s East Industrial), 1059AL (52s East Industrial - 1059L tap), 1059L (EP 803s Lambton - 1059AL tap), EP 803s L2401 (EP 803s Lambton), EP 803s L2404 (EP 803s Lambton) | East Industrial: Apparatus- TX1 Doble, and Aerial- Jumper Conductor Repair and Insulator Washing | |
| ALTALINK, EPCOR | 22-Jun-26 09:30 | 27-Jun-26 17:00 | 5.31 Days
Continuous |
921L (71s Lamoureux - 987s Clover Bar), 987s C2404 (987s Clover Bar), 987s C2406 (987s Clover Bar) | 921L/Cloverbar: CT/CVT/SA Doble and CDS9/CDS14/CDS17 Disconnect Maintenance and C2404 (Min Oil) Breaker Maintenance and C2401 Relay Maintenance | |
| ALTALINK, EPCOR | 22-Jun-26 09:30 | 27-Jun-26 17:00 | 5.31 Days
Continuous |
921L (71s Lamoureux - 987s Clover Bar) | 921L/Cloverbar: CT/CVT/SA Doble and CDS9/CDS14/CDS17 Disconnect Maintenance and C2404 (Min Oil) Breaker Maintenance and C2401 Relay Maintenance | |
| ALTALINK, EPCOR | 22-Jun-26 09:30 | 28-Jun-26 17:00 | 6.31 Days
Continuous |
1059L (38s East Edmonton - 1059AL tap), 1059L (EP 803s Lambton - 1059AL tap) | East Industrial: Apparatus- TX1 Doble, and Aerial- Jumper Conductor Repair and Insulator Washing | |
| ATCO | 22-Jun-26 10:00 | 24-Jun-26 12:00 | 2.08 Days
Continuous |
2029s ACF11 (2029s Heathfield), 2029s 1218 (2029s Heathfield) | FILTER BANK AC MAINTENANCE @ HEATHFIELD 2029S ACF11 PRC-005 - TRIP COIL TESTING - BREAKER 1218 @ 2029S |
|
| ATCO | 24-Jun-26 13:00 | 26-Jun-26 17:30 | 2.19 Days
Continuous |
2029s ACF21 (2029s Heathfield), 2029s 1222 (2029s Heathfield) | FILTER BANK AC MAINTENANCE @ HEATHFIELD 2029S ACF21 PRC-005 - TRIP COIL TESTING - BREAKER 1222 @ 2029S |
|
| SUNCOR | 29-Jun-26 08:00 | 02-Jul-26 19:00 | 3.46 Days
Continuous |
29PL9-16 (29EDD-1 Millennium - 29EDD-94 Voyageur) | 29EDD1;29PT418/29PL9-16 SYSTEM;PM 5y,10y |
|
| ATCO | 29-Jun-26 09:00 | 29-Jun-26 17:30 | 8.5 Hours
Continuous |
2075s ACF24 (2075s Newell), 2075S 933 (2075s Newell) | PRC-005 - TRIP COIL TESTING - BREAKER 933 @ 2075S FILTER BANK AC MAINTENANCE @ NEWELL 2075S ACF24 |
|
| ATCO | 29-Jun-26 10:00 | 30-Jun-26 17:30 | 31.5 Hours
Continuous |
2029s ACF13 (2029s Heathfield), 2029s 1220 (2029s Heathfield) | FILTER BANK AC MAINTENANCE @ HEATHFIELD 2029S ACF13 PRC-005 - TRIP COIL TESTING - BREAKER 1220 @ 2029S |
|
| ALTALINK | 29-Jun-26 13:00 | 30-Jun-26 17:00 | 28 Hours
Continuous |
132s 55 (132s Ware Junction) | 132s55 Minor Maint. First Trip. | |
| ATCO | 30-Jun-26 09:00 | 30-Jun-26 17:30 | 8.5 Hours
Continuous |
2075s ACF23 (2075s Newell), 2075S 932 (2075s Newell) | PRC-005 - TRIP COIL TESTING - BREAKER 932 @ 2075S FILTER BANK AC MAINTENANCE @ NEWELL 2075S ACF23 |
|
| ALTALINK | 30-Jun-26 10:00 | 30-Jun-26 16:00 | 6 Hours
Continuous |
63s T2 (63s Red Deer), 63s 25 (63s Red Deer) | PRC5 maintenance and first trip | |
| ATCO | 30-Jun-26 10:00 | 30-Jun-26 16:00 | 6 Hours
Continuous |
856s 902T (856s Kinosis), 856s 505R (856s Kinosis) | PRC-005 sudden pressure relay trip testing | |
| ATCO | 02-Jul-26 09:00 | 03-Jul-26 17:30 | 1.35 Days
Continuous |
2075s ACF22 (2075s Newell), 2075S 931 (2075s Newell) | PRC-005 - TRIP COIL TESTING - BREAKER 931 @ 2075S FILTER BANK AC MAINTENANCE @ NEWELL 2075S ACF22 |
|
| ATCO | 02-Jul-26 10:00 | 03-Jul-26 17:30 | 31.5 Hours
Continuous |
2029s ACF23 (2029s Heathfield), 2029s 1224 (2029s Heathfield) | FILTER BANK AC MAINTENANCE @ HEATHFIELD 2029S ACF23 PRC-005 - TRIP COIL TESTING - BREAKER 1224 @ 2029S |
|
| ATCO, SUNCOR | 03-Jul-26 08:00 | 09-Jul-26 20:00 | 6.5 Days
Continuous |
29PL9-1 (29EDD-1 Millennium - 848s Ruth Lake), 29EDD-1 29EDD1s452 (29EDD-1 Millennium) | 29EDD1;29CVT-3 SYSTEM;PM 5y,10y; 29EDD1;29EDD1S452 MAINT&TEST;PM 10y; 29EDD1;29CVT-3 SYSTEM;PM 5y,10y; 29PL9-1 Str#5 vibration damper |
|
| EPCOR | 06-Jul-26 07:00 | 12-Jul-26 17:00 | 6.42 Days
Continuous |
987s T2 (987s Clover Bar), 987s CC721 (987s Clover Bar), 987s C2406 (987s Clover Bar), 987s C2410 (987s Clover Bar) | Cloverbar: TX2 Doble and CDS1/CDS31/CDS33/CDS43 Disconnect Maintenance and Measurements w/Engineering | |
| ATCO, GREENGATEP | 06-Jul-26 09:00 | 09-Jul-26 17:00 | 3.33 Days
Continuous |
9L59 (801s Anderson - 9LA59 tap), 9L59 (972s Tinchebray - 9LA59 tap) | Connect new 907B to 900BS1 |
|
| ATCO | 06-Jul-26 09:00 | 10-Jul-26 17:30 | 4.35 Days
Continuous |
2075s ACF21 (2075s Newell), 2075S 930 (2075s Newell) | SVC NEWELL MAINTENANCE - SVC2 @ 2075S SEMI-ANNUAL SVC VALVE COOLING MAINTENANCE @ NEWELL 2075S SVC2 PRC-005 - TRIP COIL TESTING - BREAKER 930 @ 2075S SVC2 Blocking Switch Installs SVC2 VESDA Replacement SVC2 Annual Fire System Inspection |
|
| ATCO | 06-Jul-26 09:30 | 09-Jul-26 13:00 | 3.15 Days
Continuous |
856s 903T (856s Kinosis) | transformer maintenance PRC-005 trip coil testing on 903 and 906 during this switching |
|
| ATCO | 06-Jul-26 10:00 | 07-Jul-26 16:00 | 30 Hours
Continuous |
825s 901 (825s Whitefish Lake) | BREAKER MAINTENANCE | |
| ATCO | 06-Jul-26 10:00 | 10-Jul-26 17:30 | 4.31 Days
Continuous |
2029s ACF22 (2029s Heathfield), 2029s 1223 (2029s Heathfield) | PRC-005 - TRIP COIL TESTING - BREAKER 1223 @ 2029S BREAKER SF6 3AP4FI MAINTENANCE - 1223 @ 2029S ACF22 Breaker low SF6 (breaker 1223) @2029S Heathfield FILTER BANK AC MAINTENANCE @ HEATHFIELD 2029S ACF22 |
|
| ATCO, ALTALINK | 08-Jul-26 07:00 | 08-Jul-26 18:00 | 11 Hours
Continuous |
9L912 (63s Red Deer - 766s Nevis), 766s 902 (766s Nevis) | AltaLink Scope: Replacing insulators on structure 36 Switching line out of service for AltaLink to perform maintenance |
|
| ALTALINK, ATCO | 08-Jul-26 08:00 | 08-Jul-26 17:00 | 9 Hours
Continuous |
63s 852 (63s Red Deer), 63s 952 (63s Red Deer), 912L (63s Red Deer - 766s Nevis) | Replacing insulators on structure 36 | |
| ATCO | 08-Jul-26 10:00 | 09-Jul-26 16:00 | 30 Hours
Continuous |
825s 902 (825s Whitefish Lake) | BREAKER MAINTENANCE | |
| ATCO | 09-Jul-26 13:01 | 09-Jul-26 15:00 | 119 Mins
Continuous |
856s 901 (856s Kinosis) | PRC-005 trip coil testing | |
| ENMAX, ALTALINK | 10-Jul-26 08:00 | 10-Jul-26 16:00 | 8 Hours
Continuous |
37.82L (74s Janet - SS-37) | Shield Wire Replacement. | |
| ALTALINK, ENMAX | 10-Jul-26 08:00 | 10-Jul-26 17:00 | 9 Hours
Continuous |
74s 37.82W (74s Janet), 37.82L (74s Janet - SS-37) | Enmax Shield Wire Replacement. | |
| ATCO, SUNCOR | 10-Jul-26 08:00 | 16-Jul-26 20:00 | 6.5 Days
Continuous |
29PL9-2 (29EDD-1 Millennium - 848s Ruth Lake), 29EDD-1 29EDD1s152 (29EDD-1 Millennium) | 29EDD1;29CVT-1 SYSTEM;PM 5y,10y | |
| EPCOR | 13-Jul-26 07:00 | 19-Jul-26 17:00 | 6.42 Days
Continuous |
EP 803s L2401 (EP 803s Lambton) | Lambton: L2401 (Min Oil) Breaker Maintenance and CT Doble | |
| EPCOR | 13-Jul-26 07:00 | 21-Aug-26 17:00 | 39.42 Days
Continuous |
EP 805s J2401 (EP 805s Jasper) | Jasper: J2401 Replacement LCR | |
| ATCO | 13-Jul-26 09:00 | 24-Jul-26 17:30 | 11.35 Days
Continuous |
2075S 927 (2075s Newell), 2075S 928 (2075s Newell), 2075S 929 (2075s Newell), 2075S 934 (2075s Newell), 2075s ACF11 (2075s Newell), 2075s ACF12 (2075s Newell), 2075s ACF13 (2075s Newell), 2075s ACF14 (2075s Newell) | SVC NEWELL MAINTENANCE - SVC1 @ 2075S SEMI-ANNUAL SVC VALVE COOLING MAINTENANCE @ NEWELL 2075S SVC1 **PLEASE ADD IN 2075S ACF1** |
|
| ATCO | 13-Jul-26 10:00 | 14-Jul-26 16:00 | 30 Hours
Continuous |
825s 903 (825s Whitefish Lake) | BREAKER MAINTENANCE | |
| ATCO | 13-Jul-26 10:00 | 14-Jul-26 16:00 | 30 Hours
Continuous |
856s 902 (856s Kinosis) | PRC-005 trip coil testing, BREAKER MAINTENANCE | |
| ALTALINK | 14-Jul-26 09:30 | 23-Jul-26 11:00 | 9.06 Days
Continuous |
163s T5 (163s Amoco Empress) | 163sT5 maintenance and oil leaks. | |
| ENMAX, ALTALINK | 15-Jul-26 08:00 | 15-Jul-26 16:00 | 8 Hours
Continuous |
1064L (74s Janet - 102s Langdon) | Shield Wire Replacement. | |
| ENMAX, ALTALINK | 15-Jul-26 08:00 | 15-Jul-26 16:00 | 8 Hours
Continuous |
1065L (74s Janet - 102s Langdon) | Shield Wire Replacement. | |
| SUNCOR | 15-Jul-26 08:00 | 25-Jul-26 20:00 | 10.5 Days
Continuous |
29EDD-2 29PT-3 (29EDD-2 Tar Island), 29PL6-22 (29EDD-1 Millennium - 29EDD-2 Tar Island) | 29EDD2;29PT-3, 29PL6-22 SYSTEM;PM 5y,10y |
|
| ALTALINK | 15-Jul-26 10:00 | 15-Jul-26 14:00 | 4 Hours
Continuous |
250p 1 (250p Bighorn Plant) | maintenance | |
| ATCO | 15-Jul-26 10:00 | 16-Jul-26 16:00 | 30 Hours
Continuous |
825s 904 (825s Whitefish Lake) | BREAKER MAINTENANCE | |
| ATCO | 15-Jul-26 10:00 | 16-Jul-26 16:00 | 30 Hours
Continuous |
856s 904 (856s Kinosis) | PRC-005 trip coil testing, BREAKER MAINTENANCE | |
| ALTALINK | 16-Jul-26 10:00 | 16-Jul-26 14:00 | 4 Hours
Continuous |
250p 2 (250p Bighorn Plant) | maintenance | |
| ATCO, SUNCOR | 17-Jul-26 08:00 | 23-Jul-26 20:00 | 6.5 Days
Continuous |
6L32 (29EDD-1 Millennium - 737s ATC Horseshoe), 29EDD-1 29EDD1S28 (29EDD-1 Millennium), 29EDD-1 29PS-197 (29EDD-1 Millennium) | 29EDD1;29CVT-6 SYSTEM;5y,10y; 29EDD1s28 Alignment Issues; 29PS-197 Paddle Rotation |
|
| EPCOR | 20-Jul-26 07:00 | 26-Jul-26 17:00 | 6.42 Days
Continuous |
EP 803s L2402 (EP 803s Lambton) | Lambton: L2402 (Min Oil) Breaker Maintenance and CT Doble | |
| EPCOR | 20-Jul-26 07:00 | 02-Aug-26 17:00 | 13.42 Days
Continuous |
987s CCP7213 (987s Clover Bar), 987s CCP7214 (987s Clover Bar), 987s C2401 (987s Clover Bar), 987s C2403 (987s Clover Bar), 987s T1 (987s Clover Bar) | Cloverbar: C2401/C2403 Breaker Maintenance and CT Doble and CDS19 LCR and C2401 Relay Maintenance | |
| ALTALINK, TRANSALTA | 20-Jul-26 08:00 | 23-Jul-26 17:00 | 3.38 Days
Continuous |
179s 733 (179s Gleichen), 428s 733X (428s Namaka), 733L (179s Gleichen - 428s Namaka) | Interphase spacers str: 181, 193, 195, 196
Repair conductor with sleeve or preform splice: 181,193, 195, 196 Str change: 211 (foundation in concrete) arm/insulator change str: 161, 163, 165 " |
|
| ALTALINK | 20-Jul-26 09:30 | 20-Jul-26 15:00 | 5.5 Hours
Continuous |
138s 2552 (138s Windy Flats), 603L (138s Windy Flats - 243s Soderglen) | Job Scope: We need to complete maintenance on 243s138DS1 | |
| ATCO | 20-Jul-26 10:00 | 21-Jul-26 16:00 | 30 Hours
Continuous |
825s 905 (825s Whitefish Lake) | BREAKER MAINTENANCE | |
| ATCO | 20-Jul-26 10:00 | 22-Jul-26 12:00 | 2.08 Days
Continuous |
804s 702 (804s Wintering Hills), 7L85 (804s Wintering Hills - 7LA85 tap) | BREAKER SF6 GL312 TESTING - 702 @ 804S | |
| ATCO | 20-Jul-26 10:00 | 24-Jul-26 16:00 | 4.25 Days
Continuous |
977s 901T (977s Salt Creek), 7L135 (820s Hangingstone - 977s Salt Creek) | TRANSFORMER AND TAP CHANGER MAINTENANCE | |
| ALTALINK | 20-Jul-26 14:00 | 31-Jul-26 17:00 | 11.13 Days
Continuous |
63s 452 (63s Red Deer), 1083L (63s Red Deer - 288s Wolf Creek) | 63s452 Breaker Replacement to SF6 breaker. | |
| ATCO | 21-Jul-26 08:00 | 21-Jul-26 16:00 | 8 Hours
Continuous |
7L85 (804s Wintering Hills - 7LA85 tap) | Interphase spacer install, Deficiency repairs & insulator replacement between Wintering Hills and Badlands | |
| ATCO | 21-Jul-26 08:00 | 22-Jul-26 17:00 | 1.38 Days
Continuous |
7L65 (709s Vegreville - 7LA65 tap), 7L65 (710s Vermilion - 7LA65 tap), 7LA65 (708s Grizzly Bear - 7L65 tap) | Switch Repairs, 7LA65D1 | |
| ATCO, OWF2 | 22-Jul-26 12:00 | 24-Jul-26 17:30 | 2.23 Days
Continuous |
804s 703 (804s Wintering Hills), 7L153 (609s Wheatland - 804s Wintering Hills) | BREAKER SF6 GL312 TESTING - 703 @ 804S | |
| ATCO | 23-Jul-26 08:00 | 23-Jul-26 15:00 | 7 Hours
Continuous |
7L85 (803s ATC Bullpound - 7LA85 tap) | Interphase spacer install, Deficiency repairs & insulator replacement between Badlands and Bullpound | |
| SUNCOR | 24-Jul-26 08:00 | 06-Aug-26 20:00 | 13.5 Days
Continuous |
29EDD-34 29PT-341 (29EDD-34), 29EDD-34 29-952-142 (29EDD-34), 29EDD-34 29-952-143 (29EDD-34), 29EDD-34 29-652-10200T (29EDD-34), 29EDD-34 29-652-10301 (29EDD-34), 29EDD-34 29-652-10302 (29EDD-34), 29EDD-34 29-652-10303 (29EDD-34), 29EDD-34 29PS-0375 (29EDD-34), 29EDD-34 29PS-0380 (29EDD-34), 29EDD-34 29PS-0381 (29EDD-34), 29EDD-34 29PS-0383 (29EDD-34), 29EDD-34 29PS-609 (29EDD-34) | 10 year PM on 29EDD34;29PT-341 system and 5 year, 10 year PM on 29EDD34;29PP-103 system |
|
| SUNCOR | 25-Jul-26 08:00 | 31-Jul-26 20:00 | 6.5 Days
Continuous |
29PL9-3 (29EDD-1 Millennium - 29EDD-3), 29EDD-3 29PT-6 (29EDD-3) | 29EDD1;29CVT-4 SYSTEM;PM 5y,10y; |
|
| ALTALINK, TRANSALTA | 27-Jul-26 08:00 | 30-Jul-26 17:00 | 3.38 Days
Continuous |
179s 733 (179s Gleichen), 428s 733X (428s Namaka), 733L (179s Gleichen - 428s Namaka) | Interphase spacers str: 181, 193, 195, 196
Repair conductor with sleeve or preform splice: 181,193, 195, 196 Str change: 211 (foundation in concrete) arm/insulator change str: 161, 163, 165 " |
|
| ALTALINK, EPCOR | 27-Jul-26 08:30 | 31-Jul-26 18:00 | 4.4 Days
Continuous |
310p 1352 (310p Sundance), 310p 1452 (310p Sundance), 909L (310p Sundance - 665s Dome) | 909LW/Dome: CVT/SA Doble and DDS6/DDS7/DDS14 Disconnect Maintenance and 909LW Relay Maintenance | |
| ALTALINK, EPCOR | 27-Jul-26 09:30 | 31-Jul-26 17:00 | 4.31 Days
Continuous |
909L (310p Sundance - 665s Dome), 665s D2403 (665s Dome) | 909LW/Dome: CVT/SA Doble and DDS6/DDS7/DDS14 Disconnect Maintenance and 909LW Relay Maintenance | |
| ATCO | 27-Jul-26 10:00 | 29-Jul-26 16:00 | 2.25 Days
Continuous |
848s 905 (848s Ruth Lake) | BREAKER MAINTENANCE | |
| ATCO | 27-Jul-26 10:00 | 31-Jul-26 17:30 | 4.31 Days
Continuous |
801s 901T (801s Anderson), 801s 704 (801s Anderson), 7L85 (801s Anderson - ATC 803s Bullpound) | PRC-005 - SPR TESTING - TRANSFORMER 901T @ 801S Replace X3 Bushing on 901T at 801s Anderson TRANSFORMER CLASS1 MAJOR TESTING - 901T @ 801S TRANSFORMER CLASS1 TAP CHANGER - 901T @ 801S BREAKER MIN OIL HLR PARTIAL TESTING - 704 @ 801S |
|
| ATCO | 28-Jul-26 08:00 | 29-Jul-26 16:00 | 1.33 Days
Continuous |
7L85 (801s Anderson - ATC 803s Bullpound) | Interphase spacer install, Deficiency repairs & cross arm replacement between Bullpound and Anderson | |
| ATCO | 28-Jul-26 10:00 | 29-Jul-26 17:00 | 31 Hours
Continuous |
789s 701 (789s Keg River), 7L64 (779s Chinchaga River - 789s Keg River) | PRC Trip Coil Testing. 789s 7L62D2 will be closed for the outage duration. | |
| ALTALINK | 29-Jul-26 23:30 | 30-Jul-26 02:30 | 3 Hours
Continuous |
62s 1 (62s Brazeau Plant) | maintenence | |
| ALTALINK | 30-Jul-26 03:30 | 30-Jul-26 06:30 | 3 Hours
Continuous |
62s 2 (62s Brazeau Plant) | maintenence | |
| ATCO | 30-Jul-26 10:00 | 31-Jul-26 17:00 | 31 Hours
Continuous |
789s 703 (789s Keg River), 7L59 (789s Keg River - 7L59 tap) | PRC Trip Coil Testing | |
| ENMAX, ALTALINK | 04-Aug-26 08:00 | 21-Aug-26 16:00 | 17.33 Days
Continuous |
24.83L (74s Janet - SS-24) | Wood pole installation | |
| ALTALINK, ENMAX | 04-Aug-26 08:00 | 21-Aug-26 16:00 | 17.33 Days
Continuous |
74s 24.83X (74s Janet), 24.83L (74s Janet - SS-24) | Enmax Wood pole installation | |
| ALTALINK, TRANSALTA | 04-Aug-26 09:00 | 06-Aug-26 17:00 | 2.33 Days
Continuous |
179s 733 (179s Gleichen), 428s 733X (428s Namaka), 733L (179s Gleichen - 428s Namaka) | 733Lstr. 161-211 Crossarm work. Maintenance/repairs. | |
| ATCO | 04-Aug-26 10:00 | 06-Aug-26 16:00 | 2.25 Days
Continuous |
848s 906 (848s Ruth Lake) | BREAKER MAINTENANCE | |
| ALTALINK | 06-Aug-26 07:00 | 06-Aug-26 18:00 | 11 Hours
Daily |
237s 2352 (237s Foothills), 237s 2652 (237s Foothills), 237s T2 (237s Foothills), 237s 240kV Bus 2 (237s Foothills) | Install bus support piles for new 240kV Bay. | |
| ALTALINK | 07-Aug-26 07:00 | 07-Aug-26 18:00 | 11 Hours
Daily |
237s 2152 (237s Foothills), 237s 2452 (237s Foothills), 237s T1 (237s Foothills), 237s 240kV Bus 1 (237s Foothills) | Install bus support piles for new 240kV Bay. | |
| SUNCOR | 07-Aug-26 08:00 | 20-Aug-26 20:00 | 13.5 Days
Continuous |
29EDD-34 29PT-340 (29EDD-34) | 29EDD34;29PT-340 SYSTEM;PM 5y,10y; 29EDD34;29PP-102 SYSTEM;PM 5y,10y |
|
| EPCOR | 10-Aug-26 07:00 | 16-Aug-26 17:00 | 6.42 Days
Continuous |
665s T3 (665s Dome), 665s D721 (665s Dome), 665s D2404 (665s Dome), S721 (Strathcona) | DS26/Dome/Strathcona: Dome TX3 Doble and DAB3/DDS15/DDS16 Disconnect Maintenance and Strathcona DS26/CVT Doble and SDS3 Disconnect Maintenance | |
| ATCO | 10-Aug-26 09:00 | 13-Aug-26 16:00 | 3.29 Days
Continuous |
969s 701T (969s Lindbergh) | total station outage to replace failing HO/XO bushings on transformer, updates to anti-islanding RAS logic and alarming, replace NGR resistor and relay |
|
| ATCO, ALTALINK | 10-Aug-26 09:30 | 11-Aug-26 17:30 | 1.33 Days
Continuous |
757s 708 (757s Battle River), 7L702 (137s Sedgewick - 757s Battle River) | BREAKER SF6 LTB145D1/B TESTING - 708 @ 757S PRC-005 - TRIP COIL TESTING - BREAKER 708 @ 757S |
|
| ALTALINK | 10-Aug-26 09:30 | 13-Aug-26 17:00 | 3.31 Days
Continuous |
702L (137s Sedgewick - 757s Battle River) | Interphase spacers and pole replacements | |
| ATCO | 10-Aug-26 10:00 | 13-Aug-26 16:30 | 3.27 Days
Continuous |
7L702 (137s Sedgewick - 757s Battle River) | Interphase spacers and pole replacements | |
| ATCO | 10-Aug-26 10:00 | 14-Aug-26 17:30 | 4.31 Days
Continuous |
959s SVC (959s Lanfine) | DFR Upgrade / Replacement SVC Transformer Maintenance Fire system inspection Install Blocking Switches Mechanical Maintenance & Capital BATTERY CHARGER COMPLETE TESTING @ LANFINE 959S SVC DC MOTOR |
|
| ATCO | 10-Aug-26 13:00 | 10-Aug-26 14:00 | 60 Mins
Continuous |
951s 1205 (951s Thickwood Hills) | PRC-005 Trip Coil testing, SOC ill open and close breaker (tests TC #1), Techs will isolate A protection tripping this breaker, TOC will open and close breaker (tests TC #2) | |
| ALTALINK | 10-Aug-26 13:00 | 13-Aug-26 16:00 | 3.13 Days
Continuous |
368s 612 (368s Burdett), 612L (336s Fincastle - 368s Burdett) | 368s612 138kv CT Replacement | |
| ATCO | 10-Aug-26 14:01 | 10-Aug-26 15:00 | 59 Mins
Continuous |
951s 1206 (951s Thickwood Hills) | PRC-005 Trip Coil testing, SOC ill open and close breaker (tests TC #1), Techs will isolate A protection tripping this breaker, TOC will open and close breaker (tests TC #2) | |
| ATCO | 10-Aug-26 15:00 | 10-Aug-26 16:00 | 60 Mins
Continuous |
951s 1213 (951s Thickwood Hills) | PRC-005 Trip Coil testing, SOC will open and close breaker (tests TC #1), Techs will isolate A protection tripping this breaker, TOC will open and close breaker (tests TC #2) | |
| ATCO | 11-Aug-26 10:00 | 11-Aug-26 11:00 | 60 Mins
Continuous |
939s 1206 (939s Livock) | PRC-005 Trip Coil testing, | |
| ATCO | 11-Aug-26 11:00 | 11-Aug-26 12:00 | 60 Mins
Continuous |
939s 1207 (939s Livock) | PRC-005 Trip Coil testing, SOC will open and close breaker (tests TC #1), Techs will isolate A protection tripping this breaker, TOC will open and close breaker (tests TC #2) | |
| ATCO | 11-Aug-26 13:00 | 11-Aug-26 14:00 | 60 Mins
Continuous |
939s 1216 (939s Livock) | PRC-005 Trip Coil testing, SOC will open and close breaker (tests TC #1), Techs will isolate A protection tripping this breaker, TOC will open and close breaker (tests TC #2) | |
| ATCO | 12-Aug-26 09:30 | 13-Aug-26 17:30 | 1.33 Days
Continuous |
757s 704 (757s Battle River), 757s 704T (757s Battle River) | BREAKER SF6 LTB145D1/B TESTING - 704 @ 757S PRC-005 - TRIP COIL TESTING - BREAKER 704 @ 757S |
|
| ATCO | 12-Aug-26 10:00 | 14-Aug-26 16:00 | 2.25 Days
Continuous |
848s 907 (848s Ruth Lake) | BREAKER MAINTENANCE | |
| ALTALINK, EPCOR | 17-Aug-26 09:30 | 22-Aug-26 17:00 | 5.31 Days
Continuous |
920L (71s Lamoureux - 557s Castle Downs), 557s CD2405 (557s Castle Downs), 557s CD2404 (557s Castle Downs) | 920LE/Castledowns: CT/CVT Doble and Surge Arrestor LCR | |
| ALTALINK, EPCOR | 17-Aug-26 09:30 | 22-Aug-26 17:00 | 5.31 Days
Continuous |
920L (71s Lamoureux - 557s Castle Downs) | 920LE/Castledowns: CT/CVT Doble and Surge Arrestor LCR | |
| ATCO | 17-Aug-26 10:00 | 20-Aug-26 16:30 | 3.27 Days
Continuous |
7L702 (137s Sedgewick - 757s Battle River) | Interphase spacers and pole replacements | |
| ALTALINK | 17-Aug-26 10:00 | 20-Aug-26 16:30 | 3.27 Days
Continuous |
702L (137s Sedgewick - 757s Battle River) | Interphase spacers and pole replacements | |
| ALTALINK | 17-Aug-26 12:00 | 20-Aug-26 17:00 | 3.21 Days
Continuous |
245s 777X (245s Seebe), 777L (48s Pocaterra - 245s Seebe) | 245s777X 138kV CT testing | AB-BC |
| ALTALINK, ATCO, FMGW | 18-Aug-26 08:00 | 19-Aug-26 17:00 | 1.38 Days
Continuous |
964AL (1024s Granlea - 964L tap), 1024s PT-6001 (1024s Granlea), 1024s PT-6002 (1024s Granlea), 1024s 952-600001 (1024s Granlea), 1024s PS-6005 (1024s Granlea), 1024s PS-6006 (1024s Granlea), 1024s PS-6007 (1024s Granlea), 1024s PS-6008 (1024s Granlea), 1024s 489-600201 (1024s Granlea) | maintenance activities (testing and inspection) of electrical equipment | |
| EPCOR | 24-Aug-26 07:00 | 09-Oct-26 17:00 | 46.42 Days
Continuous |
805s T4 (805s Jasper), EP 805s J2405 (EP 805s Jasper), EP 805s J2406 (EP 805s Jasper) | Jasper: J2406/JDS10 Replacement LCR | |
| ALTALINK, BCH | 24-Aug-26 08:00 | 01-Sep-26 17:00 | 8.38 Days
Continuous |
Path 1 (AIES Islanding), 1201L (520s Bennett - BCH Cranbrook), 5L94 (BCH Cranbrook - 520s Bennett) | South Crew will be doing Insulator and guy wire replacements | AB-BC |
| ALTALINK, BCH | 24-Aug-26 08:00 | 01-Sep-26 17:00 | 8.38 Days
Continuous |
48s 887X (48s Pocaterra), 887L (48s Pocaterra - 978s BCH Britt Creek) | Opened because 1201L is out of service . | AB-BC |
| ALTALINK, BCH | 24-Aug-26 08:00 | 01-Sep-26 17:00 | 8.38 Days
Continuous |
799s 786W (799s Coleman), 786L (799s Coleman - BCH Natal) | Opened because 1201L is out of service. | AB-BC |
| BHE Canada | 24-Aug-26 08:00 | 01-Sep-26 17:00 | 8.38 Days
Continuous |
MATL (120s Picture Butte - Montana) | align with 1201L outage | AB-MATL |
| ALTALINK | 24-Aug-26 13:00 | 28-Aug-26 17:00 | 4.17 Days
Continuous |
28s R1 (28s West Brooks) | 28sR1 leak category 5, Doble R1
28s44 PRC5 (no first trip) |
|
| Syncrude | 28-Aug-26 08:00 | 11-Sep-26 16:00 | 14.33 Days
Continuous |
223B (Aurora), 213B (Aurora), 89-216 (Aurora), 89-52 (Aurora), 34B (Aurora), 24B (Aurora), 14B (Aurora), T11 (Aurora), 72 kV Bus 2 (Aurora), 260kV Bus 2 (Aurora) | Zone 1 6yr PM | |
| EPCOR, ALTALINK | 31-Aug-26 07:00 | 13-Sep-26 17:00 | 13.42 Days
Continuous |
EP 803s T3 (EP 803s Lambton), EP 803s L2403 (EP 803s Lambton), EP 803s L2405 (EP 803s Lambton), EP 803s L721 (EP 803s Lambton), 72LS24 (EP 803s Lambton - Strathcona), 72LH8 (EP 803s Lambton - EP Hardisty), H726 (EP Hardisty), S724 (Strathcona) | Lambton: LDS14 LCR and L721 Breaker Maintenance (Min Oil) and TX3 Zone Doble and L2405 Breaker Maintenance (SF6) and LDS12 Drive Pipe Repair and TX3 Relay Maintenance | |
| ATCO | 31-Aug-26 09:30 | 04-Sep-26 17:30 | 4.33 Days
Continuous |
801s 902 (801s Anderson) | BREAKER MIN OIL HLR COMPLETE TESTING | |
| ATCO | 31-Aug-26 10:00 | 03-Sep-26 16:00 | 3.25 Days
Continuous |
826s 902T (826s Marguerite Lake) | transformer maintenance | |
| EPCOR | 07-Sep-26 07:00 | 11-Sep-26 17:00 | 4.42 Days
Continuous |
987s GT2 (987s Clover Bar) | Cloverbar: | |
| ATCO | 08-Sep-26 10:00 | 10-Dec-26 16:00 | 93.29 Days
Continuous |
2015s 902 (2015s Yeo) | Remove circuit breaker for use at 2102S Armistead. New breaker to be installed at 2015S Yeo substation once received from manufacturer. | |
| ALTALINK | 08-Sep-26 13:00 | 17-Sep-26 16:00 | 9.13 Days
Continuous |
370s 2152 (370s North Lethbridge), 370s T3 (370s North Lethbridge) | 370sT3 Leak repair, major TC maint. PRC5 | |
| ALTALINK | 08-Sep-26 23:00 | 09-Sep-26 07:00 | 8 Hours
Continuous |
250p 2 (250p Bighorn Plant) | maintenance | |
| ALTALINK | 09-Sep-26 07:00 | 10-Sep-26 07:00 | 24 Hours
Continuous |
250p 1 (250p Bighorn Plant) | maintenance | |
| ALTALINK | 10-Sep-26 19:00 | 15-Sep-26 12:00 | 4.71 Days
Continuous |
1141L (1172s Laramide - 237s Foothills) | End to end testing with Laramide 1172s | |
| EPCOR | 14-Sep-26 07:00 | 21-Sep-26 17:00 | 7.42 Days
Continuous |
987s GT3 (987s Clover Bar) | Cloverbar: | |
| ALTALINK, EPCOR | 14-Sep-26 09:30 | 17-Sep-26 17:00 | 3.31 Days
Continuous |
920L (37s North Calder - 557s Castle Downs), 557s CD2401 (557s Castle Downs), 557s CD2403 (557s Castle Downs) | 920LW/Castledowns: Surge Arrestor LCR | |
| ALTALINK, EPCOR | 14-Sep-26 09:30 | 17-Sep-26 17:00 | 3.31 Days
Continuous |
920L (37s North Calder - 557s Castle Downs) | 920LW/Castledowns: Surge Arrestor LCR | |
| ATCO, ALTALINK | 14-Sep-26 10:00 | 28-Sep-26 17:30 | 14.31 Days
Continuous |
840s 901T (840s McNeill Station), 830L (562s Cypress - 840s McNeill Station), 840s 701 (840s McNeill Station), 840s 901 (840s McNeill Station) | Replace 901T bushings 901T Oil Leak Absorption Repairs At 840s McNeill |
AB-SK |
| ALTALINK, Lethbridge | 15-Sep-26 09:00 | 24-Sep-26 17:30 | 9.35 Days
Continuous |
618s 725 (618s Riverbend), 725AL (618s Riverbend - 725L tap), 725L (111s Coalbanks - 725AL tap), 725L (674s Bowron - 725AL tap) | Outage required to replace 674s12-Disconnect Switch and 674sPT5-CVT | |
| ALTALINK | 16-Sep-26 23:30 | 17-Sep-26 02:30 | 3 Hours
Continuous |
62s 1 (62s Brazeau Plant) | maintenence | |
| ALTALINK | 17-Sep-26 03:30 | 17-Sep-26 06:30 | 3 Hours
Continuous |
62s 2 (62s Brazeau Plant) | maintenence | |
| ATCO | 21-Sep-26 10:00 | 24-Sep-26 16:00 | 3.25 Days
Continuous |
888s 906 (888s Dover) | 21B/9L74 relay replacement. Cutover breaker and CT to new protection | |
| EPCOR | 22-Sep-26 07:00 | 25-Sep-26 17:00 | 3.42 Days
Continuous |
987s GT1 (987s Clover Bar), 987s SST2 (987s Clover Bar), 987s CS2 (987s Clover Bar), 987s CGB1 (987s Clover Bar), 987s CCP7214 (987s Clover Bar), 987s CC24 (987s Clover Bar), 987s CH724 (987s Clover Bar), 987s CK726 (987s Clover Bar), 987s 72kV Bus 4 (987s Clover Bar) | Cloverbar: , SST2, BUS 4 Outage. CDS18 Disconnect Replacement | |
| ATCO | 25-Sep-26 10:00 | 28-Sep-26 16:00 | 3.25 Days
Continuous |
888s 905 (888s Dover) | 21B/9L74 relay replacement. Cutover breaker and CT to new protection | |
| ALTALINK, TRANSALTA, Lethbridge | 28-Sep-26 09:00 | 28-Sep-26 15:00 | 6 Hours
Continuous |
15s 725 (15s Fort Macleod), 725BL (240s McBride Lake - 725L tap), 725L (15s Fort MacLeod - 725BL tap), 725L (674s Bowron - 725BL tap) | Outage required to create open point 'A' on 725L to keep 240s online | |
| Lethbridge | 28-Sep-26 09:00 | 15-Oct-26 17:00 | 17.33 Days
Continuous |
674s 1 (674s Bowron), 725LW (674s Bowron - 725BL tap) | Line outage required on 725LW at 674s to replace 674s1-Manual Airbreak Switch and replace 674s2 and 674s6 PT's | |
| ALTALINK, Lethbridge | 28-Sep-26 14:05 | 15-Oct-26 18:05 | 17.17 Days
Continuous |
725L (674s Bowron - 725BL tap) | Lethbridge outage required to replace 674s1-Disconnect Switch, 674sPT4-CVT, 674sPTB2-3phase CVT's, new screw piles and structure for 674sPTB2-CVT's | |
| EPCOR | 05-Oct-26 07:00 | 18-Oct-26 17:00 | 13.42 Days
Continuous |
CV5 (EP 511s Victoria - 557s Castle Downs) | CV5: Manhole Inspections and Maintenance | |
| ALTALINK | 05-Oct-26 08:30 | 28-Nov-26 06:30 | 53.96 Days
Continuous |
62s 2 (62s Brazeau Plant) | maintenence | |
| ATCO | 05-Oct-26 10:00 | 08-Oct-26 16:00 | 3.25 Days
Continuous |
9L74 (888s Dover - 960s Birchwood Creek) | 21B/9L74 relay three terminal line testing | |
| ATCO, ALTALINK | 07-Oct-26 08:00 | 07-Oct-26 17:00 | 9 Hours
Continuous |
760L (760AL tap - 7LA760 tap) | install interphase spacers | |
| ATCO | 12-Oct-26 10:00 | 15-Oct-26 16:00 | 3.25 Days
Continuous |
888s 906 (888s Dover) | 21A/9L74 relay replacement. Cutover breaker and CT to new protection | |
| EPCOR | 13-Oct-26 07:00 | 04-Dec-26 17:00 | 52.46 Days
Continuous |
805s T3 (805s Jasper), EP 805s J2404 (EP 805s Jasper), EP 805s J2405 (EP 805s Jasper) | Jasper: J2404/JAB3/JDS9 Replacement LCR | |
| ALTALINK | 15-Oct-26 08:00 | 15-Oct-26 18:00 | 10 Hours
Continuous |
158s 763N (158s Vauxhall), 28s 47 (28s West Brooks), 28s 31 (28s West Brooks), 447s 763A (447s Enchant), 447s 16 (447s Enchant), 763AL (447s Enchant - 763A1L tap), 763L (158s Vauxhall - 763AL tap), 763L (28s West Brooks - 763AL tap) | 447s27 Replace line VT. (Like for like replacement) | |
| ALTALINK, TRANSALTA, Lethbridge | 15-Oct-26 17:10 | 15-Oct-26 21:00 | 3.83 Hours
Continuous |
15s 725 (15s Fort Macleod), 725BL (240s McBride Lake - 725L tap), 725L (15s Fort MacLeod - 725BL tap), 725L (674s Bowron - 725BL tap) | to close 725L Open Point 'A' and restore 725L to normal | |
| ATCO | 16-Oct-26 10:00 | 19-Oct-26 16:00 | 3.25 Days
Continuous |
888s 905 (888s Dover) | 21B/9L74 relay replacement. Cutover breaker and CT to new protection | |
| ALTALINK | 19-Oct-26 07:00 | 20-Oct-26 18:00 | 1.46 Days
Continuous |
237s 2352 (237s Foothills), 237s 2652 (237s Foothills), 237s T2 (237s Foothills), 237s 240kV Bus 2 (237s Foothills) | Closing Open Point 'C' | |
| EPCOR | 19-Oct-26 07:00 | 30-Oct-26 17:00 | 11.42 Days
Continuous |
814s T1 (814s Bellamy), BR721 (Rossdale), 814s B2401 (814s Bellamy), 814s B2407 (814s Bellamy) | Bellamy: TX1 LTC Monitor Install | |
| ALTALINK, EPCOR | 19-Oct-26 09:30 | 25-Oct-26 17:00 | 6.31 Days
Continuous |
908L (89s Ellerslie - 816s Petrolia), 816s P2401 (816s Petrolia), 816s P2406 (816s Petrolia) | Petrolia: 908LE Surge Arrestor and CVT LCR | |
| ALTALINK, EPCOR | 19-Oct-26 09:30 | 25-Oct-26 17:00 | 6.31 Days
Continuous |
908L (89s Ellerslie - 816s Petrolia) | Petrolia: 908LE Surge Arrestor and CVT LCR | |
| ALTALINK | 21-Oct-26 08:00 | 22-Oct-26 17:00 | 1.38 Days
Continuous |
237s 2152 (237s Foothills), 237s 2452 (237s Foothills), 237s T1 (237s Foothills), 237s 240kV Bus 1 (237s Foothills), 1141L (1172s Laramide - 237s Foothills) | Closing Open Points 'A' & 'B' | |
| ALTALINK, EPCOR | 26-Oct-26 07:00 | 30-Oct-26 17:00 | 4.42 Days
Continuous |
909L (89s Ellerslie - 665s Dome), 665s D2401 (665s Dome), 665s D2404 (665s Dome), 72DS26 (665s Dome - Strathcona) | 909LE/Dome: Dome CVT LCR and 909LE Metering Upgrade | |
| ALTALINK, EPCOR | 26-Oct-26 07:30 | 30-Oct-26 17:00 | 4.4 Days
Continuous |
89s 1052 (89s Ellerslie), 89s 1152 (89s Ellerslie), 909L (89s Ellerslie - 665s Dome) | 909LE/Dome: Dome CVT LCR and 909LE Metering Upgrade | |
| ENMAX, ALTALINK | 26-Oct-26 08:00 | 04-Nov-26 16:00 | 9.38 Days
Continuous |
24.83L (74s Janet - SS-24) | Steel pole installation | |
| ENMAX, ALTALINK | 26-Oct-26 08:00 | 04-Nov-26 16:00 | 9.38 Days
Continuous |
24.83L (74s Janet - SS-24), 74s 24.83X (74s Janet) | Enmax Steel pole installation | |
| ATCO | 26-Oct-26 10:00 | 29-Oct-26 16:00 | 3.25 Days
Continuous |
9L74 (888s Dover - 960s Birchwood Creek) | 21B/9L74 relay three terminal line testing | |
| ATCO, ALTALINK | 26-Oct-26 10:00 | 02-Nov-26 16:00 | 7.29 Days
Continuous |
7L230 (69s North Barrhead - 888AL tap), 7L230 (743s Sarah Lake - 888AL tap) | Replace 7L230D1 disconnect switch | |
| ALTALINK | 28-Oct-26 10:00 | 28-Oct-26 14:00 | 4 Hours
Continuous |
250p 1 (250p Bighorn Plant) | maintenance | |
| ALTALINK | 29-Oct-26 10:00 | 29-Oct-26 14:00 | 4 Hours
Continuous |
250p 2 (250p Bighorn Plant) | maintenance | |
| ATCO | 30-Oct-26 10:00 | 02-Nov-26 17:00 | 3.33 Days
Continuous |
7L238 (959s Lanfine - 601s Bufallo Bird), 959s 708 (959s Lanfine), 959s 707 (959s Lanfine) | Cutover CT/PT ccts, Commission new RAS A-B/7L238, end-to-end testing with 601S Buffalo Bird | |
| EPCOR | 02-Nov-26 07:00 | 13-Nov-26 17:00 | 11.42 Days
Continuous |
814s T2 (814s Bellamy), BR722 (Rossdale), 814s B2402 (814s Bellamy), 814s B2406 (814s Bellamy) | Bellamy: TX2 LTC Monitor Install | |
| ALTALINK | 05-Nov-26 03:30 | 05-Nov-26 06:30 | 3 Hours
Continuous |
62s 1 (62s Brazeau Plant) | maintenence | |
| EPCOR | 09-Nov-26 07:00 | 11-Dec-26 17:00 | 32.42 Days
Continuous |
52s T2 (52s East Industrial), 52s E2402 (52s East Industrial) | East Industrial: TX2 Bushing Replacement | |
| EPCOR | 09-Nov-26 07:00 | 11-Dec-26 17:00 | 32.42 Days
Continuous |
PM2405 (Poundmaker) | Poundmaker: P2405 Breaker Replacement | |
| ATCO | 09-Nov-26 10:00 | 12-Nov-26 17:00 | 3.29 Days
Continuous |
9L24 (946s Oakland - 959s Lanfine), 959s 906 (959s Lanfine), 959s 905 (959s Lanfine), 946s 902 (946s Oakland), 946s 903 (946s Oakland) | Cutover Bkr/MOD status, Commission new LTO/RAS 204 A/B - Lanfine/Oakland | |
| ATCO | 13-Nov-26 10:00 | 14-Nov-26 17:00 | 31 Hours
Continuous |
959s 901T (959s Lanfine), 959s 904 (959s Lanfine), 959s 919 (959s Lanfine), 959s 701 (959s Lanfine), 959s 706 (959s Lanfine) | Cutover MOD status, Commission inputs to RAS 204 A/B | |
| ATCO | 23-Nov-26 10:00 | 23-Nov-26 17:00 | 7 Hours
Continuous |
959s 904 (959s Lanfine) | Cutover and Commission Bkr 904 status to RAS 204 A/B | |
| ATCO | 24-Nov-26 10:00 | 24-Nov-26 17:00 | 7 Hours
Continuous |
959s 919 (959s Lanfine) | Cutover and Commission Bkr 919 status to RAS 204 A/B | |
| ATCO | 25-Nov-26 10:00 | 25-Nov-26 17:00 | 7 Hours
Continuous |
959s 920 (959s Lanfine) | Cutover and Commission Bkr 919 status to RAS 204 A/B | |
| ALTALINK | 16-Dec-26 10:00 | 16-Dec-26 14:00 | 4 Hours
Continuous |
250p 1 (250p Bighorn Plant) | maintenance | |
| ALTALINK | 17-Dec-26 10:00 | 17-Dec-26 14:00 | 4 Hours
Continuous |
250p 2 (250p Bighorn Plant) | maintenance | |
| ALTALINK | 23-Dec-26 23:30 | 24-Dec-26 02:30 | 3 Hours
Continuous |
62s 1 (62s Brazeau Plant) | maintenence | |
| ALTALINK | 24-Dec-26 03:30 | 24-Dec-26 06:30 | 3 Hours
Continuous |
62s 2 (62s Brazeau Plant) | maintenence | |
| EPCOR | 04-Jan-27 07:00 | 12-Feb-27 17:00 | 39.42 Days
Continuous |
EP 805s J2405 (EP 805s Jasper) | Jasper: J2405 Replacement LCR | |
| EPCOR | 16-Feb-27 07:00 | 30-Mar-27 17:00 | 42.38 Days
Continuous |
EP 805s J2407 (EP 805s Jasper) | Jasper: J2407 Replacement LCR | |
| ALTALINK, EPCOR | 19-Feb-27 07:00 | 05-Mar-27 17:00 | 14.42 Days
Continuous |
1045L (EP 805s Jasper - 1045AL tap), EP 805s J2406 (EP 805s Jasper), EP 805s J2407 (EP 805s Jasper) | 1045L/Jasper: J2407 Replacement LCR | |
| ATCO | 08-Mar-27 10:00 | 17-Mar-27 17:00 | 9.25 Days
Continuous |
9L24 (946s Oakland - 959s Lanfine), 959s 906 (959s Lanfine), 959s 905 (959s Lanfine), 946s 902 (946s Oakland), 946s 903 (946s Oakland) | Replace A/B protection relays at 959S Lanfine and 946S Oakland Cut in and reroute 9L24 Connect new 9LA24 T-tap Commission Telecom and Protection to new 1072S Rose Lynn substation |
|
| SUNCOR | 06-Apr-27 09:00 | 16-Apr-27 20:00 | 10.46 Days
Continuous |
29EDD-34 29PT-112 (29EDD-34), 29EDD-34 29-752-121 (29EDD-34), 29EDD-34 29PS-68 (29EDD-34), 29EDD-34 29PS-67 (29EDD-34), 29EDD-34 29PS-66 (29EDD-34), 29EDD-34 29PS-65 (29EDD-34), 29EDD-34 29PS-225 (29EDD-34), 29EDD-34 29PS-230 (29EDD-34), 29EDD-34 29-952-141 (29EDD-34), 29EDD-34 29-952-131 (29EDD-34), 29EDD-34 29-952-111 (29EDD-34) | 29EDD34;29PT-112 & 29PP-24 SYSTEM;PM This will Place 29EDD-34 on one 260 kV bus and drop 29PL7-1 |
|
| ATCO | 12-Apr-27 10:00 | 19-Apr-27 17:00 | 7.29 Days
Continuous |
7L22 (790s Poplar Hill - 7L88 tap) | Cut open 7L22, connect new line section to new 2061S Dobbs 7L22/21B relay upgrades at 790S Poplar Hill and 811S Clairmont Lake On completion energize new 2061S Dobbs substation |
|
| SUNCOR | 14-Apr-27 14:00 | 23-Apr-27 18:00 | 9.17 Days
Continuous |
29EDD-65 29PT-0257 (29EDD-65), 29EDD-65 29-952-4812 (29EDD-65), 29EDD-65 29-952-4813 (29EDD-65), 29EDD-71 752-4624 (29EDD-71), 29EDD-71 752-4623 (29EDD-71), 29PL7-4 (29EDD-65 - 29EDD-71) | Firebag: 29EDD65;29PT-257 & 29PL7-4 SYSTEM, 29EDD65 ;29PT-260 & 29PL7-4 SYSTEM, 29EDD71 29PT-241 & 29PL7-4 | |
| ATCO | 03-May-27 09:00 | 17-May-27 17:30 | 14.35 Days
Continuous |
2075s T11 (2075s Newell) | Annual EATL outage at 2075s & 2029s. | |
| ATCO | 03-May-27 09:00 | 17-May-27 17:30 | 14.35 Days
Continuous |
2029s T11 (2029s Heathfield) | Annual EATL outage at 2075s & 2029s. | |
| ATCO | 03-May-27 09:00 | 17-May-27 17:30 | 14.35 Days
Continuous |
13L50 (2029s Heathfield - 2075s Newell) | Annual EATL outage at 2075s & 2029s. **1218 IS NOT THE ISOALTION. ATCO SENT AESO OF REQUIRED ISOLATIONS BACK IN MAY 2024 TO UPDATE 2029S AND 2075S ISOLATIONS FOR 13L50 OUTAGES** |
|
| ATCO | 03-May-27 10:00 | 06-May-27 17:00 | 3.29 Days
Continuous |
7L22 (811s Clairmont Lake - 7L88 tap) | 7L22/21B relay upgrade at 811S Clairmont Lake Upon completion new 2061S Dobbs substation ready to energize |
|
| SUNCOR | 04-May-27 09:00 | 14-May-27 20:00 | 10.46 Days
Continuous |
29EDD-34 29PS-214 (29EDD-34), 29EDD-34 29-952-113 (29EDD-34), 29EDD-34 29PS-215 (29EDD-34), 29EDD-34 29PS-213 (29EDD-34) | 29EDD34;29PL9-13 SYSTEM;PM 5y,10y | |
| SUNCOR | 05-May-27 14:00 | 14-May-27 18:00 | 9.17 Days
Continuous |
29EDD-65 29PT-0236 (29EDD-65), 29EDD-65 29-952-4823 (29EDD-65), 29EDD-65 29-952-4822 (29EDD-65), 29EDD-71 752-4634 (29EDD-71), 29EDD-71 752-4633 (29EDD-71), 29PL7-3 (29EDD-65 - 29EDD-71) | Firebag: 29EDD65;29PT-236 & 29PL7-3 SYSTEM, 29EDD65;29PT-250&29PL7-3 SYSTEM, 29PT-246 SYSTEM;29EDD71 | |
| ATCO | 10-May-27 10:00 | 11-May-27 17:00 | 31 Hours
Continuous |
7L03 (749s Flyingshot Lake - 7L09 tap) | Cutover and commission RAS analogs and LTO to 790S Poplar Hill RAS Hub | |
| ATCO | 12-May-27 10:00 | 13-May-27 17:00 | 31 Hours
Continuous |
7L03 (731s Elmworth - 7L09 tap) | Cutover and commission LTO to 790S Poplar Hill RAS Hub | |
| ATCO | 14-May-27 10:00 | 15-May-27 17:00 | 31 Hours
Continuous |
7L69 (731s Elmworth - 815s Goodfare) | Cutover and commission LTO to 790S Poplar Hill RAS Hub | |
| ATCO | 16-May-27 10:00 | 17-May-27 17:00 | 31 Hours
Continuous |
7L07 (790s Poplar Hill - 815s Goodfare) | Cutover and commission LTO to 790S Poplar Hill RAS Hub | |
| SUNCOR | 01-Jun-27 08:00 | 10-Jun-27 17:00 | 9.38 Days
Continuous |
635EDD-1000 635-752-635PT-1000 (635EDD-1000), 635EDD-1000 635PT-1000 (635EDD-1000) | FH - Maintenance on Transformer, associated breakers, other equipment in isolation boundary and protection system testing. | |
| SUNCOR | 01-Jun-27 09:00 | 11-Jun-27 20:00 | 10.46 Days
Continuous |
29EDD-94 407T (29EDD-94 Voyageur), 29EDD-94 29-952-9705 (29EDD-94 Voyageur), 29EDD-94 29PS-393 (29EDD-94 Voyageur), 29EDD-94 29PS-392 (29EDD-94 Voyageur), 29EDD-94 29-952-9704 (29EDD-94 Voyageur), 29EDD-94 29PS-400 (29EDD-94 Voyageur) | 29EDD94;29PT-407 SYSTEM;PM 5y,10y | |
| SUNCOR | 11-Jun-27 08:00 | 20-Jun-27 17:00 | 9.38 Days
Continuous |
635EDD-1000 635-752-635PT-1001 (635EDD-1000), 635EDD-1000 635PT-1001 (635EDD-1000) | FH - Maintenance on Transformer, associated breakers, other equipment in isolation boundary and protection system testing. | |
| SUNCOR | 15-Jun-27 09:00 | 25-Jun-27 20:00 | 10.46 Days
Continuous |
29EDD-94 406T (29EDD-94 Voyageur), 29EDD-94 29-952-9702 (29EDD-94 Voyageur), 29EDD-94 29PS-388 (29EDD-94 Voyageur), 29EDD-94 29PS-389 (29EDD-94 Voyageur), 29EDD-94 29PS-399 (29EDD-94 Voyageur) | 29EDD94;29PT-406 SYSTEM;PM 5y,10y | |
| AESO, ATCO | 29-Jun-27 13:00 | 30-Jun-27 17:00 | 28 Hours
Continuous |
9LA93 (973s Lanes Lake - 9L93 tap) | Line to Ground Clearance Mitigation, Span 50-51. Repair deficiency on structure 57 | |
| ALTALINK, ATCO, FMGW | 17-Aug-27 08:00 | 18-Aug-27 17:00 | 1.38 Days
Continuous |
964AL (1024s Granlea - 964L tap), 1024s PT-6001 (1024s Granlea), 1024s PT-6002 (1024s Granlea), 1024s 952-600001 (1024s Granlea), 1024s PS-6005 (1024s Granlea), 1024s PS-6006 (1024s Granlea), 1024s PS-6007 (1024s Granlea), 1024s PS-6008 (1024s Granlea), 1024s 489-600201 (1024s Granlea) | maintenance activities (testing and inspection) of electrical equipment | |
| ATCO | 08-Nov-27 09:00 | 11-Nov-27 17:00 | 3.33 Days
Continuous |
ALC02L (409s Shell Scotford - 879s Upgrader) | Install new Deadend corner structure on ALC02L | |
| ATCO | 08-Nov-27 09:00 | 11-Nov-27 17:00 | 3.33 Days
Continuous |
ALC01L (408s Air Liquide Scotford - 409s Shell Scotford) | Install new Deadend corner structure on ALC02L. | |
| ATCO | 08-Feb-28 09:00 | 10-Feb-28 17:00 | 2.33 Days
Continuous |
7L228 (845s Big Mountain - 7L20 tap) | AESO project P2716 - Install 7L228 bypass to facilitate the installation of new line switches for the new 7LA228 T-tap line connection to the new 2103S Pakenham substation Open 7L228, replace structures 551 and 551A, connect bypass. |
|
| ATCO | 06-Mar-28 10:00 | 22-Mar-28 16:00 | 16.21 Days
Continuous |
826s 903 (826s Marguerite Lake), 826s 907 (826s Marguerite Lake), 826s 901T (826s Marguerite Lake) | Expand 240kV ring bus for new 9L42 line | |
| ATCO | 13-Mar-28 10:00 | 16-Mar-28 17:00 | 3.29 Days
Continuous |
9L939 (77s Sagitawah - 809s Louise Creek) | Cut over 9L939 to temp bypass structures to allow for installation of new deadend corner towers. These are required to make the final connections to the new 2105S Jackson substation | |
| ATCO | 14-Mar-28 09:00 | 16-Mar-28 17:00 | 2.33 Days
Continuous |
7L228 (845s Big Mountain - 7L20 tap) | AESO project P2716 - Disconnect bypass, connect new 7LA228D1 to 7LA228 Str #2, connect 7L228 to 7L228D2, connect 7L228 to 7L228D3. Renumber existing line switches 7L228D2 - D4, 7L228D3 - D5, 7L228D4 - D6 Commission DTT |
|
| ATCO | 17-Mar-28 10:00 | 17-Apr-28 17:00 | 31.29 Days
Continuous |
9L938 (77s Sagitawah - 809s Louise Creek) | Install foundations (TBD assume concrete), assemble and erect new Q-towers 9L938/9L939-155A and 9L938/9L939-156A in existing ROW centreline. Daily outage until such a time as the new towers begin to encroach on 9L938. | |
| ATCO | 20-Mar-28 09:00 | 23-Mar-28 17:00 | 3.33 Days
Continuous |
2091s 704 (2091s Thornton) | AESO project P2716 - cut over new SEL 2440 wiring at 2091S, relay programming, commission DTT and LTO | |
| ATCO | 24-Mar-28 09:00 | 27-Mar-28 17:00 | 3.33 Days
Continuous |
740s 704 (740s H.R. Milner), 7L20 (740s H.R. Milner - 810s Dome Cutbank) | AESO project P2716 - cut over RAS #171 wiring at 740S, relay programming, commission LTO 7L20/7L228 | |
| ATCO | 18-Apr-28 10:00 | 25-Apr-28 17:00 | 7.29 Days
Continuous |
9L938 (77s Sagitawah - 809s Louise Creek) | Open 9L938 conductors, complete assembly and connect to the new Q-Towers 9L938/9L939-155A and 9L938/9L939-156A, string to 2105S Jackson deadend and terminate. Relabel 9L938 segment from 809S Louise Creek to 2105S Jackson to 9L140. |
|
| ATCO | 01-May-28 10:00 | 04-May-28 17:00 | 3.29 Days
Continuous |
9L939 (77s Sagitawah - 809s Louise Creek) | Disconnect 9L939 conductors from temp structure 9L939 -155A - 155E reconnect to existing structures 9L938/9L939-156 and 9L938/9L939-155, connect to the new Q-Towers 9L938/9L939-155A and 9L938/9L939-156A, string to 2105S Jackson deadend and terminate. Relabel 9L939 segment from 809S Louise Creek to 2 |
|
| ATCO | 08-May-28 09:00 | 10-Jul-28 17:00 | 63.33 Days
Continuous |
959s 240kV Bus 900BS2 (959s Lanfine) | GOI on 9L141 until line terminated into 1162S Fair Acres and ready to energize | |
| ATCO | 08-May-28 09:00 | 10-Jul-28 17:00 | 63.33 Days
Continuous |
959s 240kV Bus 900BS2 (959s Lanfine) | GOI on 902/903 until line terminated and 1162S Fair Acres ready to energize | |
| ATCO | 09-May-28 10:00 | 13-May-28 17:00 | 4.29 Days
Continuous |
9L02 (809s Louise Creek - 813s Little Smoky) | Install concrete foundations for new structures 9L02/320A, 320H in preparation to cut into 9L02 and convert to a t-tap. | |
| ATCO | 15-May-28 09:00 | 17-May-28 17:00 | 2.33 Days
Continuous |
959s 240kV Bus 900BS1 (959s Lanfine) | Connect new bus from new 902B to existing switch 901A to add new line 9L141, Cutover and commission 900PT1 ccts to new 9L141 relays |
|
| ATCO | 18-May-28 09:00 | 20-May-28 17:00 | 2.33 Days
Continuous |
959s 240kV Bus 900BS2 (959s Lanfine) | Connect new bus from new Bkr 903 to existing switch 903B to add new line 9L141, Cutover and commission 900PT2 ccts to new 9L141 relays |
|
| ATCO | 29-May-28 09:00 | 08-Jun-28 17:00 | 10.33 Days
Continuous |
9L24 (946s Oakland - 959s Lanfine) | Cutover and commission 905/906 CT's, 9L24PT ccts to new RAS 241 SEL 451A/B relays @ 959S Lanfine and update relay settings for RAS 241 and SCADA inputs @946S Oakland. | |
| ATCO | 19-Jun-28 10:00 | 30-Jun-28 16:00 | 11.25 Days
Continuous |
9L20 (755s Cordel - 766s Nevis) | Install concrete foundations at 9L20 Structure 69 for new T-Tap connection |
|
| ATCO | 26-Jun-28 10:00 | 10-Jul-28 17:00 | 14.29 Days
Continuous |
9L02 (809s Louise Creek - 813s Little Smoky) | Cut into 9L02 and connect new t-tap structures for 9LA02. 9L02-21A and 21B relay upgrades at 809S Louise Creek and 813S Little Smoky. Implement RAS Energize new line 9LA02 and 884S Magpie substation |
|
| ATCO | 31-Jul-28 10:00 | 15-Aug-28 16:00 | 15.25 Days
Continuous |
766s 901 (766s Nevis), 9L20 (755s Cordel - 766s Nevis), 755s 906 (755s Cordel), 755s 901 (755s Cordel) | Cutover new 9L20 line section, terminate 9LA20 at customer substation. Install new line protection relays |
|
| ATCO, GREENGATEP | 01-Oct-28 08:00 | 21-Oct-28 16:00 | 20.33 Days
Continuous |
972S 904, 972s 904 (972s Tinchebray) | CETO project
Install 904 and 904CT Commission 904 and 904CT Expand GOI to 900BS1 Isolation Points: 904A, 901A and 900SST1X Connect 907B to 900BS1 Shrink GOI to 907B |
| AB-BC, AB-SK & AB-MATL: refer to AESO web posting: | http://itc.aeso.ca/itc/public/atc |
| Also, | |
| AB-BC, AB-SK & AB-MATL: refer to ISO Rule 203.6: | http://www.aeso.ca/rulesprocedures/18592.html |
| Prepared On: | 2026-04-22 14:00:47 |
|
This document and the information contained herein are based upon information and data which by their nature contain a degree of uncertainty and are subject to change. In addition, this document may contain information and data from public sources and/or third parties, which have been assumed to be accurate and complete and have not been verified. Accordingly, the Independent System Operator, operating as the Alberta Electric System Operator (the "AESO") makes no warranty, representation or guarantee, express or implied, with respect to this document or the information contained herein, including, but not limited to, any warranty, representation or guarantee of accuracy, completeness, timeliness, reliability, availability, absence of computer virus, non- infringement, merchantability or suitability for any purpose. Under no circumstances will the AESO, its members, officers, employees, contractors or agents, or any of their respective affiliates, be liable for any errors or omissions in, or any losses, damages or claims whatsoever, whether in contract, tort or otherwise, arising from use of or reliance upon, this document or any information contained herein. © 2009 Alberta Electric System Operator. All rights reserved |